Performance Contracting. Len Hoey, PEM. State Energy Office. Department of Commerce
|
|
|
- Isaac Andrews
- 9 years ago
- Views:
Transcription
1 Performance Contracting Len Hoey, PEM State Energy Office Department of Commerce
2 Terms and Acronyms Performance Contract Guaranteed Energy Savings Agreement Energy Savings Performance Contract ESCO Energy Service Company RFP Request for Proposal IGA Investment Grade Audit M&V Monitoring and Verification ESA Energy Services Agreement ECM Energy Conservation Measure LGC - Local Government Commission
3 What is Performance Contracting An ESCO designs and proposes a package of energy cost reduction measures, installs or implements those cost reduction measures, and guarantees the savings of the cost reductions. The issuer pays for the package over time using the stream of revenue provided by the energy reduction measures Third party monitoring and verification
4 Why not do it yourself? Often opportunities to reduce energy costs are well known but owners are unable to take advantage of them Capital Expertise Manpower Can you guarantee the savings?
5 Performance Contracting Advantages A Design-Build process with a single point of responsibility Provides capital Provides engineering and project management expertise No reduction in utility funding over project life Guaranteed performance/savings
6 Performance Contracting Intangibles Improved lighting quality HVAC Improved indoor air quality Improved occupant comfort Potentially provide educational / teaching opportunities Dashboards Energy Star Building labeling
7 Performance Contracting Pitfalls Failure of owner to perform due diligence Failure to understand contract Overly optimistic expectations / promises RFP IGA M&V Time must be allocated to see process through
8 Identify a Project Building energy costs greater than $1.50/sq ft Annual utility costs greater than $300, ,000 sq ft or greater Building use and occupancy stable No significant renovations or additions planned In NC contracts have ranged from $400,000 to $60,000,000
9 Steps to a Successful Project The State Energy Office will provide assistance during each step of the process All documents and steps must conform to General Statues and North Carolina Administrative Code
10 Steps to a Successful Project Assemble stakeholders Create data packet for project (Application) Issue RFP Evaluate responses (select ESCO) Negotiate and Perform IGA Negotiate contracts ESCO contract Financial contract Local Government Commission approval or Council of State approval
11 Assemble Stakeholders Convene a project team consisting of: Engineering Finance Maintenance & operations Administration Purchasing & Legal Building occupants The State Energy Office will provide assistance to the team
12 Project Data Packet Create project scope 3 year billing history for project building(s) Occupancy, use and schedule Indoor air requirements Temperature and humidity requirements Lighting level requirements Prior audit or survey reports Schematics/prints and equipment lists This packet will serve as the application to SEO
13 The Request For Proposals SEO has a template available for use Specify any special circumstances (security, building schedule - work schedule conflicts etc.) Mandatory onsite meeting Schedule building walk through (site visit) Data packet available to all ESCOs Specify evaluation method and criteria Deadline for responses (give adequate time) All questions should be handled in writing with both questions and answers available to all responders.
14 RFP Evaluation & ESCO Selection Cost benefit analysis performed for each option Substantial conformity with RFP Guaranteed savings and contract period Project cost and time to complete Product quality manufacturers warranties Check references
15 RFP Evaluation & ESCO Selection Create short list of responders for oral interview Allow each ESCO a set amount of time to describe their company ESCO may only clarify response not improve it
16 Investment Grade Audit SEO has a sample contract Audit within 10% of RFP calculations Yes issuer at risk for cost if project terminated No ESCO at risk for cost if project terminated M&V methodology must be stated and conform to: The International Performance Measurement and Verification Protocol Certification by registered engineer that M&V protocol presented is capable of measuring actual savings May wish to engage same group that will do independent third party M&V for year end validation & reconciliation of savings
17 Energy Service Agreement ECMs and their installation Specify conditions required: lighting levels, temperature & humidity, water temperature, indoor air quality etc. Specify equipment capacity, operating range maintenance requirements etc. ESCO provides many of the equipment details but owner must be satisfied that all of the items specified are acceptable
18 Energy Service Agreement Maintenance contract Owner may contract with third party for maintenance service The ESCO may provide the maintenance service The owner may provide maintenance Cost of the maintenance contract is to be included in the total project cost
19 The Guarantees Construction bond The construction bond ensures the equipment is delivered as specified, properly installed and properly commissioned The construction bond will cover the cost of the project completion if for any reason the contractor is unable to complete the project
20 The Guarantees Guaranteed savings bond This bond is a standing guarantee that all of the guaranteed savings specified in the contract can be paid The ESCO shall provide security to the governmental unit in the form acceptable to the Office of the State Treasurer and in an amount equal to 100% of the total cost of the guaranteed savings contract
21 Measurement & Verification Actual savings measured are compared to guaranteed savings by third party If actual savings less than guaranteed savings, ESCO pays the difference to the governmental unit The cost of the required third party M&V is to be included in the contract
22 Assistance Available From SEO List of pre-qualified ESCOs Application assistance (project identification) Standard RFP available Standard Investment Grade Audit Contract available Standard Energy Services Agreement available Proposal and IGA Evaluation available List of qualified engineering service / M&V providers
23 Legislative Basis General Statute Article 3B through L General Statute Article through North Carolina Administrative Code 01 NCAC 41B.0101 through 41B.0901 LGC Application for Approval of Guaranteed Energy Savings Contracts
24 Len Hoey USI Contacts Renee Hutcheson Lyn Martin Reid Conway
25 Thank You for Attending
ESPC Life of Contract (LOC) Plan:
ESPC Life of Contract (LOC) Plan: Documents Management and Checklist for Savings Performance Contracts (ESPC) (Contract Number), (Date Amended), (Contributors) (SITE) ENERGY SAVINGS PERFORMANCE CONTRACT
ESCO BASE CONTRACT FOR AS-NEEDED ENERGY PERFORMANCE CONTRACTING SERVICES
ATTACHMENT A ESCO BASE CONTRACT FOR AS-NEEDED ENERGY PERFORMANCE CONTRACTING SERVICES The Energy Services Coalition offers a collection of model procurement and contracting documents that represent Best
REQUEST FOR PROPOSAL GUARANTEED ENERGY SAVINGS CONTRACT. Dallas School District 2000 Conyngham Avenue Dallas, PA 18612. Addendum 2
REQUEST FOR PROPOSAL GUARANTEED ENERGY SAVINGS CONTRACT Dallas School District 2000 Conyngham Avenue Dallas, PA 18612 Addendum 2 Introduction The Dallas School District is requesting Proposals for Energy
STATE OF NORTH CAROLINA DEPARTMENT OF STATE TREASURER
STATE OF NORTH CAROLINA DEPARTMENT OF STATE TREASURER STATE AND LOCAL GOVERNMENT FINANCE DIVISION AND THE LOCAL GOVERNMENT COMMISSION Mailing Address: 325 North Salisbury Street Raleigh, North Carolina
Energy Savings Performance Contracting ( ESPC )
Energy Savings Performance Contracting ( ESPC ) The Good, the Bad and the Ugly Richard G. Lubinski CEM, CEA, CDSM, CSDP, BEP, CEMSC Think Energy Management LLC 1 ONLY 50 MINUTES to cover 50 hours of ESPC
Optimising building HVAC services through control
Optimising building HVAC services through control AIRAH Divisional Meeting September 2014 Chris Flanagan AIRAH Committee President What s keeping you up at night? Owner-occupied Occupant complaints and
Placing UESC Task Orders Under a GSA Areawide Contract
FEMP Federal First Energy Thursday Management Seminars Program Placing UESC Task Orders Under a GSA Areawide Contract Instructor: FEMP Expert: Julia Kelley, Oak Ridge National Laboratory David McAndrew,
REQUEST FOR PROPOSALS (RFP) FOR FINANCIAL ADVISORY SERVICES
REQUEST FOR PROPOSALS (RFP) FOR FINANCIAL ADVISORY SERVICES Appointment to the NJ Tobacco Settlement Financing Corporation Credit Enhancement Transaction Winter 2014 Issued by the State of New Jersey Treasurer
STATE HUMAN RESOURCES COMMISSION MEETING LEARNING AND DEVELOPMENT CENTER, COMMISSION CONFERENCE ROOM 101 WEST PEACE STREET - RALEIGH, NORTH CAROLINA
STATE HUMAN RESOURCES COMMISSION MEETING LEARNING AND DEVELOPMENT CENTER, COMMISSION CONFERENCE ROOM 101 WEST PEACE STREET - RALEIGH, NORTH CAROLINA MEETING MINUTES JUNE 4, 2015 Members Present Members
REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT AT-RISK FOR LOGANVILLE ELEMENTARY SCHOOL (REPLACEMENT) FOR THE WALTON COUNTY SCHOOL DISTRICT
ADVERTISEMENT: REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT AT-RISK FOR LOGANVILLE ELEMENTARY SCHOOL (REPLACEMENT) FOR THE WALTON COUNTY SCHOOL DISTRICT The WALTON COUNTY SCHOOL DISTRICT will receive
A guide to Energy Services Companies (ESCOs) on how to participate in the Dubai Buildings Retrofit Program
A guide to Energy Services Companies (ESCOs) on how to participate in the Dubai Buildings Retrofit Program Version 1.0 Produced by Etihad Energy Services Co. May 2014 Contents Introduction... 3 The Dubai
REQUEST FOR PROPOSALS FOR FINANCIAL ADVISORY SERVICES
REQUEST FOR PROPOSALS FOR FINANCIAL ADVISORY SERVICES Appointment to the New Jersey Building Authority Capital Budget Modeling and Advisory Services State Fiscal Years 2016, 2017 and 2018 Issued by the
NATIONAL INSTITUTE FOR CERTIFICATION IN ENGINEERING TECHNOLOGIES www.nicet.org 888-476-4238. Fire Alarm Systems
Fire Alarm Systems Level IV Content Outline Standard Model/CBT The skills and knowledge listed under each task are suggestive of those involved in that task, but are not intended to constitute an exhaustive
METHODOLOGY TO IDENTIFY AND EVALUATE ENERGY SERVICES COMPANIES (ESCOS)
METHODOLOGY TO IDENTIFY AND EVALUATE ENERGY SERVICES COMPANIES (ESCOS) Translated from original Metodología para identificar y evaluar empresas de servicios energéticos (ESCOS), 2007 Proyecto Desarrollo
GUIDELINES FOR THE ENGAGEMENT OF EXTERNAL CONSULTANTS/PROFESSIONAL SERVICES AT MEMORIAL UNIVERSITY
GUIDELINES FOR THE ENGAGEMENT OF EXTERNAL CONSULTANTS/PROFESSIONAL SERVICES AT MEMORIAL UNIVERSITY INTENT: 1. To ensure due diligence and consistency is followed in the solicitation, selection, contract
REQUEST FOR PROPOSALS ENERGY PERFORMANCE CONTRACT
REQUEST FOR PROPOSALS ENERGY PERFORMANCE CONTRACT Luzerne County Community College (LCCC) is soliciting proposals from qualified Energy Service Companies (ESCOs) to provide an energy performance audit
WHITE PAPER DEVELOPING A SUCCESSFUL WEBSITE RFP. Find the Right Web Development Partner through an Engaging and Informative RFP.
WHITE PAPER DEVELOPING A SUCCESSFUL WEBSITE RFP Find the Right Web Development Partner through an Engaging and Informative RFP By Devin Gauthier INTRODUCTION So you ve decided to undertake a new website
ACG Commissioning Guideline
ACG Commissioning Guideline Appendix A Sample Commissioning Specification NOTES TO APPENDIX A This appendix contains a sample Request for Proposal (RFP) for Commissioning Services as would be issued by
City of Moreno Valley Date Council Approved March 13, 2007 Date Effective April 6, 2007 CLASS SPECIFICATION Senior Electrical Engineer, P.E.
City of Moreno Valley Date Council Approved March 13, 2007 Date Effective April 6, 2007 CLASS SPECIFICATION Senior Electrical Engineer, P.E. GENERAL PURPOSE Under direction, manages, oversees, evaluates,
ATTACHMENT A. Ozarks Technical Community College Pre-Established Criteria for Construction Management and Design Build Construction Projects
Ozarks Technical Community College Pre-Established Criteria for Construction Management and Design Build Construction Projects Pursuant to Revised Statute of Missouri Section 8.250(3), Ozarks Technical
MANTON CONSOLIDATED SCHOOLS. REQUEST for PROPOSALS ENERGY SAVING CAPITAL IMPROVEMENT PROJECTS. On a PERFORMANCE CONTRACTING BASIS
MANTON CONSOLIDATED SCHOOLS REQUEST for PROPOSALS ENERGY SAVING CAPITAL IMPROVEMENT PROJECTS On a PERFORMANCE CONTRACTING BASIS July 16, 2010 1 NOTICE IS HEREBY GIVEN THAT THE BOARD OF EDUCATION OF MANTON
ILLINOIS DEPARTMENT OF CENTRAL MANAGEMENT SERVICES CLASS SPECIFICATION ENERGY AND NATURAL RESOURCES SPECIALIST SERIES
ILLINOIS DEPARTMENT OF CENTRAL MANAGEMENT SERVICES CLASS SPECIFICATION ENERGY AND NATURAL RESOURCES SPECIALIST SERIES CLASS TITLE POSITION CODE ENERGY AND NATURAL RESOURCES SPECIALIST TRAINEE 13715 ENERGY
Energy Savings Performance Contracting. Guidelines for State Agencies. Part 2
Energy Savings Performance Contracting For The Owner (Agency) Contract Structure, Essential Elements, and Certifications Page 1 of 20 Table of Contents Table of Contents... 2 Texas Government Code Contract
SCHOOL BOARD AGENDA ITEM RATIONALE
2014-2015 SCHOOL BOARD AGENDA ITEM RATIONALE DATE OF BOARD ACTION: DISTRICT DEPARTMENT: January 13, 2015 Operations and Planning DIRECTOR/SUPERVISOR S SIGNATURE: Digitally signed by Patrick Lefere Date:
Retaining Wall Replacement at the Currituck County Veterans Memorial Park
CONTRACT DOCUMENTS FOR Retaining Wall Replacement at the Currituck County Veterans Memorial Park Coinjock, NC May 24, 2016 NOTICE TO BIDDERS Bids will be received until 4:00 pm on June 17, 2016 at the
Energy Savings Performance Contract (ESPC) Lesson Learned Panel. Federal Environmental Symposium- West
Energy Savings Performance Contract (ESPC) Lesson Learned Panel Federal Environmental Symposium- West June 17, 2008 Karin King, LEED AP Sr. Environmental Engineer DOE/NNSA The Drivers EO 13423- Strengthening
CITY OF STARKE. Project # 2016-02
CITY OF STARKE Project # 2016-02 Request for Proposals For Enterprise Content Management System 209 N. Thompson Street Post Office Drawer C Starke, Florida 32091 00 Contents CITY OF STARKE REQUEST FOR
On behalf of Governor Pat Quinn and CDB s Executive Director, Jim Underwood Welcome!
On behalf of Governor Pat Quinn and CDB s Executive Director, Jim Underwood Welcome! 1 WHAT CDB IS DOING FOR THE STATE OF ILLINOIS 2 Capital Development Board Created in 1972 Illinois General Assembly
Talent Management and OD Specialist
Position Employee category level Department Reporting to Line reports Purpose of the role Key Responsibilities Talent Management and OD Specialist Professionally qualified HR professional and experienced
Auditor General Procurement Processes Review - Bid Bonds/Performance Bonds
STAFF REPORT June 22, 2005 To: From: Subject: Administration Committee Deputy City Manager and Chief Financial Officer Auditor General Procurement Processes Review - Bid Bonds/Performance Bonds Purpose:
ESCO Financing. State of Israel Ministry of National Infrastructure. Pierre Baillargeon. March 2007 ECONOLER INTERNATIONAL
ESCO Financing State of Israel Ministry of National Infrastructure Pierre Baillargeon March 2007 Agenda Evaluation of the EE market Introduction to the ESCO concept Introduction to performance contracts
RRC STAFF OPINION PERIODIC REVIEW AND EXPIRATION OF EXISTING RULES REPORT
RRC STAFF OPINION PERIODIC REVIEW AND EXPIRATION OF EXISTING RULES REPORT PLEASE NOTE: THIS COMMUNICATION IS EITHER 1) ONLY THE RECOMMENDATION OF AN RRC STAFF ATTORNEY AS TO ACTION THAT THE ATTORNEY BELIEVES
RFP ADDENDUM. North Carolina Department of Health and Human Services Division of Medical Assistance
RFP ADDENDUM North Carolina Department of Health and Human Services Division of Medical Assistance Bidders: Your failure to sign this addendum and return it to the agency at the address specified in the
AUDITOR GUIDELINES. Responsibilities Supporting Inputs. Receive AAA, Sign and return to IMS with audit report. Document Review required?
1 Overview of Audit Process The flow chart below shows the overall process for auditors carrying out audits for IMS International. Stages within this process are detailed further in this document. Scheme
ROCKINGHAM COUNTY GOVERNMENTAL CENTER Purchasing Office
ROCKINGHAM COUNTY GOVERNMENTAL CENTER Purchasing Office Rockingham County Government REQUEST FOR PROPOSALS INSURANCE BROKERS / CONSULTANTS RFP #15-07 Rockingham County Government is seeking bidders from
ASTM Building Energy Performance Assessment (BEPA) Standard E 2797
EBA MEETING FORT MYERS, FL JANUARY 17, 2011 ASTM Building Energy Performance Assessment (BEPA) Standard E 2797 Presented by: Anthony J. Buonicore, PE, QEP, BCEE CEO, The Buonicore Group ASTM BEPA Task
IT Vendor Due Diligence. Jennifer McGill CIA, CISA, CGEIT IT Audit Director Carolinas HealthCare System December 9, 2014
IT Vendor Due Diligence Jennifer McGill CIA, CISA, CGEIT IT Audit Director Carolinas HealthCare System December 9, 2014 Carolinas HealthCare System (CHS) Second largest not-for-profit healthcare system
Qualified Energy Conservation Bonds and Green Community Programs. VRA Infrastructure Financing Conference
Qualified Energy Conservation Bonds and Green Community Programs VRA Infrastructure Financing Conference WHO WE ARE Energy Management Technology Abundant Power is an energy management services company
Basic Steps to Establish ISO/IEC 17025 Compliant Testing Laboratories
Workshop for Caribbean countries to promote the development and implementation of Conformity Assessment programmes St. Augustine (Trinidad and Tobago) 2-4 December Basic Steps to Establish ISO/IEC 17025
Doniphan-Trumbull Public School BP 902.05 Page 1 of 6 CONSTRUCTION MANAGEMENT AT RISK SCHOOL CONSTRUCTION ALTERNATIVE
Page 1 of 6 CONSTRUCTION MANAGEMENT AT RISK SCHOOL CONSTRUCTION ALTERNATIVE The school district adopts this policy in the event it resolves to use the construction management at risk (CM at risk) construction
Energy Efficiency Building Retrofit Case Study: City of Houston Retrofit Program, Tranche 2 Results
Energy Efficiency Building Retrofit Case Study: City of Houston Retrofit Program, Tranche 2 Results OVERVIEW With the support of the C40 and Clinton Climate Initiative (CCI), the Houston mayor s office
GENERAL CONTRACTOR PRE-QUALIFICATION 2014 - FOR PERIOD ENDING DEC 2017
APPLICATION for PRE QUALIFICATION GENERAL CONSTRUCTION CONTRACTORS Construction Projects up to $3,000,000 Prequalified General Contractors will be invited to submit bids for various Renovation and Construction
CALIFORNIA SECURE CHOICE RETIREMENT SAVINGS INVESTMENT BOARD
SEPTEMBER 29, 2014 AGENDA ITEM 05 ACTION ITEM CALIFORNIA SECURE CHOICE RETIREMENT SAVINGS INVESTMENT BOARD Market Analysis and Feasibility Study Request for Proposals Discussion of Timeline and Process
Job Classification Manual Page 1 of 42 Vol. II
Job Classification Manual Page 1 of 42 TIER II STANDARD FOR JURISTS INTRODUCTION 1. This grade level standard illustrates the application of the ICSC Master Standard (Tier I) to a specific field of work
Sullivan County RFP for HVAC Maintenance Page 2 of 5 April 14, 2016
SULLIVAN COUNTY, NH REQUEST FOR PROPOSALS FOR HVAC MAINTENANCE AND MECHANICAL SERVICES PROPOSALS ARE DUE NO LATER THAN 12:00 NOON ON MONDAY, MAY 16, 2016 AND SHALL BE SEALED AND ADDRESSED TO: John Cressy
Website and Integrated Database Management System REQUEST FOR PROPOSAL
Website and Integrated Database Management System REQUEST FOR PROPOSAL February 10, 2016 RFP Issue Date: Feb. 10, 2016 RFP Questions & Enquires Closing Date: Feb. 26, 2016 RFP CLOSING DATE & TIME: 4:00pm
ENTERPRISE PROJECT MANAGEMENT OFFICE
ENTERPRISE PROJECT MANAGEMENT OFFICE QUALITY MANAGEMENT SYSTEM ISO 9001:2008 STATE CHIEF INFORMATION OFFICER CHRIS ESTES DEPUTY STATE CHIEF INFORMATION OFFICER AARON WIENSHIENK DEPARTMENT MANAGER JAMES
CCM Energy Efficiency Program
CCM Energy Efficiency Program Town of Willington Andy Merola, BEP CCM Energy & Program Development Manager Jerry Drummond, CEM, CEP Sales Team Leader Energy Solutions, Siemens Why now? You re spending
Personal Service Contract Review Board March 2016
for Personal and Professional Services Procurement Personal Service Contract Review Board How to use this Guide This is an informational guide to be used as a resource for agencies in implementing the
Investment Opportunities in the Global Energy Management Systems Industry
Investment Opportunities in the Global Energy Management Systems Industry Integration of Technology Providers with Service Companies and Development of Smart Applications to Disrupt the Market April 2015
ENERGY AUDITS FOR EXISTING BUILDINGS: It s like (nearly) free money! FSi consulting engineers
ENERGY AUDITS FOR EXISTING BUILDINGS: It s like (nearly) free money! Who is FSi?, established 1985 We are a single discipline mechanical engineering firm based out of Seattle and Baltimore. FSi places
Gasparilla Island Bridge Authority REQUEST FOR PROPOSALS LANDSCAPE SERVICES
Gasparilla Island Bridge Authority REQUEST FOR PROPOSALS LANDSCAPE SERVICES RFP #2016-03 P.O. Box 1918 Boca Grande, Florida 33921 www.giba.us Kathy Banson-Verrico, Executive Director INTRODUCTION The State
Computer Network Infrastructure CAT6 Wiring Request for Proposal
Distributed by: Ecorse Public Schools 27225 West Outer Drive Ecorse, MI 48229 Section 1 - Introduction The purpose of this (RFP) is to obtain pricing of Computer Network Infrastructure within the Ecorse
Pre-qualification for Construction Services Using a Qualifying System in Publicly Bid Projects
Pre-qualification for Construction Services Using a Qualifying System in Publicly Bid Projects Introduction: Pre-qualification provides a formal, comprehensive method of identifying companies that meet
Construction Management At-Risk
Oconee County Schools P.O. Box 146, 34 School Street Watkinsville, GA 30677 706-769-5130 706-769-3513 REQUEST FOR PROPOSALS ISSUE DATE: March 10, 2016 RFP REF: Construction Management At-Risk Construction
Construction Delivery Methods for Texas school districts
Construction Delivery Methods for Texas school districts Pfluger Associates Architects, P.L.L.C. ARCHITECTS / PLANNING CONSULTANTS History Prior to 1995, public school districts were required to utilize
Energy Audits and Retro-commissioning Background Report
Energy Audits and Retro-commissioning Background Report An energy audit is a comprehensive assessment of a building s physical and operational characteristics, along with its energy profile, that also
September 2014 Report No. 15-003
John Keel, CPA State Auditor An Audit Report on The Texas Enterprise Fund at the Office of the Governor Report No. 15-003 An Audit Report on The Texas Enterprise Fund at the Office of the Governor Overall
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services
Tool 3 What makes a job satisfying for you?
Tool 3 What makes a job satisfying for you? Instructions This tool will help you select factors that make a job satisfying for you. Read each listed factor and select your top 10 items. You can prioritise
REQUEST FOR PROPOSALS FOR FINANCIAL ADVISORY SERVICES
REQUEST FOR PROPOSALS FOR FINANCIAL ADVISORY SERVICES Appointment to the State of New Jersey Rating Agency Presentation Review/Analysis Summer 2016 Issued by the State of New Jersey Treasurer s Office
Overview 1) Grantee s procurement requirements must be in conformance with the appropriate applicable Federal, State, and local laws.
The award of Federal funds does not exempt the Grantee organization from compliance with State, and local requirements. When similar requirements exist at all levels, the rule of thumb is that the most
Grow and Expand Your Business Into Home Energy Performance Contracting With Dr. Energy Saver
Grow and Expand Your Business Into Home Energy Performance Contracting With Dr. Energy Saver Providing Home Energy Performance and Related Contractors the Marketing Programs, Sales Systems, Business and
Alaska Commercial Energy Audit Program 2013 Program Guidelines
Alaska Commercial Energy Audit Program 2013 Program Guidelines November 1, 2013 Application Deadline: December 20, 2013 (4:30 pm) Introduction The Alaska Energy Authority initiated a commercial energy
New WMHS Construction Management Firm
New WMHS Construction Management Firm RFQ Schedule November 5, 2013 Board Meeting Approval to Advertise and use revised RFQ Week December 9, 2013 Ad runs in local papers (Thursday Dec. 12 th ) Week December
Comments of PU Europe on the Energy Efficiency Plan 2011 Commission Communication COM(2011) 109 final
Comments of PU Europe on the Energy Efficiency Plan 2011 Commission Communication COM(2011) 109 final PU Europe is the European association representing the polyurethane insulation industry (PUR/PIR).
REQUEST FOR INFORMATION (RFI) FOR ENERGY EFFICIENCY AND ALTERNATIVE ENERGY SOLUTIONS (RFI ENERGY)
REQUEST FOR INFORMATION (RFI) FOR ENERGY EFFICIENCY AND ALTERNATIVE ENERGY SOLUTIONS (RFI ENERGY) Responses to the ENERGY EFFICIENCY AND ALTERNATIVE ENERGY SOLUTIONS, RFI ENERGY, will be received by the
BOARD POLICY DJA: PROFESSIONAL/TECHNICAL SERVICE CONTRACTS
CARROLL COUNTY PUBLIC SCHOOLS ADMINISTRATIVE REGULATIONS BOARD POLICY DJA: PROFESSIONAL/TECHNICAL SERVICE CONTRACTS Administrative Procedures For Appointment of Architectural, Engineering and Construction
Contract Management Principles and Practices
2 Contract Management Principles and Practices SUMMARY Minnesota statutes and Department of Administration guidelines provide a framework for professional/technical contracting that reflects effective
Using ISO 15489 as an Audit Tool
Using ISO 15489 as an Audit Tool ISO 15489, the first international standard devoted to records management, provides a comprehensive and practical basis for auditing full and partial records management
LEED for Homes Rating System
LEED for Homes Rating System market rate affordable multi-family TARGET MARKET REGULATIONS typical building practices 70% The top 25% of new homes based on performance and environmental responsibility
Sustainable Buildings and the Surety BY BRYAN M. SEIFERT, ESQ.
FOCUS ON GREEN BUILDING Sustainable Buildings and the Surety BY BRYAN M. SEIFERT, ESQ. ONE OF THE MORE VITAL, THOUGH OFTEN HIDDEN, types of risk transfer mechanisms on many construction projects is the