QUALITATIVE DEVELOPMENT OF DEBT/EQUITY MODEL FOR BOT INFRASTRUCTURE PROJECTS
|
|
|
- Alan Watson
- 9 years ago
- Views:
Transcription
1 QUALITATIVE DEVELOPMENT OF DEBT/EQUITY MODEL FOR BOT INFRASTRUCTURE PROJECTS B. S. Koh Land Transport Authority, Singapore S. Q. Wang School of Building and Real Estate, National University of Singapore R. L. K. Tiong School of CSE, Nanyang Technological University, Singapore Abstract This paper is concerned with determinants of equity investment in build, operate and transfer (BOT) infrastructure project. The determinants such as revenue risks, availability of guarantees or security, loan tenor, location of project and novelty of proposal had being identified in Woodward et al (1996). The results from surveys on the factors are studied in conjunction with actual BOT projects. Finally, a qualitative model which provides a systematic approach in the determination of optimum equity level is presented in this paper. Keywords: Build-Operate-Transfer (BOT), Equity Investment, Financing, Infrastructure Beng Soon Koh is a Project Engineer with the Land Transport Authority (LTA), Singapore. Currently, he is in the planning team at LTA for the North-East Line of the mass rapid transit project. Shou Qing Wang is a Fellow in Construction Management at National University of Singapore. He specializes in the risk management of China's BOT project, productivity of concrete placing and IT application in construction engineering and management. Robert L. K. Tiong is an Associate Professor at Nanyang Technological University and the Coordinator of the MSc Program in Int'l Constr. Mgmt. He specializes in project financing, structuring of BOT projects, construction risks and project management. 1
2 INTRODUCTION Equity finance of BOT infrastructure projects represents the injection of risk capital by the project promoter and investors into the concession company. Given the uncertain nature of the revenue stream associated with BOT infrastructure projects, investors risk can be high. Since the servicing of debt has priority over dividend payment, dividends can only be paid after the debt claims have been met. However, equity investment is inevitable in certain BOT projects especially those in the developing countries. It is necessary for the promoters to raise the non-recourse financing or even to win the concession. How much then is the optimum equity? All parties have to negotiate for the best allocation of risks and the returns on their investments. Woodward, et al (1996) have identified ten factors which constitute the main elements that determine the debt-equity ratio for most BOT projects. The common factors are identified from analysis of several major infrastructure projects developed using BOT principles. They have also recommended further investigations into the optimum level of debt/equity for BOT projects. These factors are Long Concession Period, High Commercial/Revenue Risks, Availability of Guarantees, Location of Project, Dispersion of Ownership, Size of Project, Real Interest Rate, Speculative Vs Invited Bid, Novelty of Proposal and Consolidation. The objectives of this paper are to further analyze the key determinants so as to establish those factors that would encourage high equity participation. It will propose a qualitative model that will incorporate those factors and provide a systematic approach in determining the optimum level of equity investment in infrastructure projects. RESEARCH METHODOLOGIES The methodologies of this research study are literature review, interviews and survey questionnaire with the findings supported by data of BOT projects from Loh et al (1992), Mohd (1991), Tiong et al (1996), Tiong (1995), Woodward et al (1993) and Yeoh (1995). Two sets of mail questionnaires were sent out and the targeted respondents were the major BOT project promoters in Malaysia and the BOT financial advisors and lenders in Singapore. Structured interviews were also conducted in depth with the respondents of the first survey. The first set of questionnaire was sent to the respondents by hand during the interviews which were conducted in Malaysia in December The authors interviewed senior executives of 5 BOT project promoters. For the first survey, three project promoters and one financial advisor, responded out of a total of 6 questionnaires submitted. In the second survey, sent in February 1997 to financial advisors in Singapore, a total of 8 bankers responded out of a total of 16 questionnaires submitted. In addition, 2 promoters replied to the second survey also. There are ten factors listed in the questionnaire for the respondents to evaluate their importance. Table 1 shows the summary of the results. ANALYSIS OF DETERMINANTS OF EQUITY INVESTMENT F1 - Revenue Risks and Sectors Risks such as construction risks, technological risks, environmental risks, feedstock risks and political risks can cause uncertainty in future revenues of projects and lead to high equity requirement. Projects with a high degree of certainty in revenue generation may also have a relatively high proportion of equity. The reason for this is the attractiveness of the project to the investor looking for a high equity return. The lenders 2
3 on their part will find it easier to get credit committee approval and to syndicate a deal of this nature if the certainty of revenue is high. Table 1. Ranking of Key Determinants from Survey Factors Rank Average Score F1 Revenue Risk and Sectors F2 Availability of Guarantees F3 Loan Repayment Period F4 Real Interest Rate F5 Location of Project F6 Concession Period F7 Novelty of Proposal F8 Size of Project F9 Speculative Vs Invited Bid F10 Dispersion of Ownership a Score: 5 = most important, 4 = very important, 3 = important, 2 = fairly important and 1 = not important. b Average score = (frequency x score) / (frequency). c Rank = 1 as the most important and so on The lenders are willing to lend if the project has attractive economic fundamentals, attractive internal rate of return (IRR), positive net present value (NPV), consistent Debt Service Cover Ratio (DSCR) and Loan Life Cover Ratio (LLCR). The above must be maintained even in a worst case scenario. From the interviews and the surveys, the DSCR of the project must be more than the minimum range of 1.10 to 1.25 in order for the project to be bankable. The satisfactory or comfortable range of DSCR is 1.30 to 1.50 and any DSCR above this range is preferable. Table 2 shows the ranges of equity that were used in BOT projects in the infrastructure sectors, with toll roads exhibiting the lowest average equity participation of 15% as compared to 26% for the water supply project. Table 2. Revenue Risks and Sectors F1: Revenue Risk And Sectors Tolls Power Water Others No. of Projects - developed country developing country Range of Equity (%) Mean Equity (%) F2 - Availability of Guarantees and Securities a) Guarantees by host government 3
4 Guarantees provided by the host government will encourage participation of the lenders and equity investors. The credit standing of the government agency, its track record and the strength of the off-take contract by the government agency are also crucial. The incentives and guarantees that have been given include: 1) Guaranteed Minimum Income; 2) Government Support Loan; 3) Transfer of Existing Infrastructure for Operation; 4) No Second Similar Infrastructure to be Built; 5) Tax Incentives; 6) Longer Concession Period. b) Security package Taking security over the project assets and contracts gives the lenders the ability to control the project s cash flows and even step in and operate in adverse situations. The most common securities are mortgage charge over the physical assets, assignments of project contracts, contract undertakings, shareholder undertakings, insurances and bonds. Table 3 shows the comparison of mean equity level between projects which were granted with guarantees and those without guarantees or security. It shows that those projects without guarantee would require a high equity level by the project promoters. Table 3. Availability of Guarantees and Securities F2: Availability Of Guarantees & Securities None Yes No. of Projects - developed country developing country 13 5 Range of Equity (%) Mean Equity (%) F3 - Loan Repayment Period/ Loan Tenor It is the natural preference for lenders to see that their debt is repaid as quickly as possible so that their loans are exposed in the shortest period of time to the project risks. However, project promoters typically want longer tenors to ease their cash flow. But if the loan tenor is stretched to a longer period, the total interest charges payable will be higher. Loan repayment periods of 1 to 5 years are considered short but lenders would be reluctant to consider a period exceeding 15 years. Lenders would question whether the project is able to service the debt as the DSCR may fall below the comfort zone. F4 - Real Interest Rate Economic theory suggests that the nominal cost of borrowing is largely irrelevant, since the inflation in revenues will automatically compensate for it (Woodward, et al, 1996). The higher the interest charged, the higher could be the debt level provided by lenders provided that lenders are satisfied with the risk security structure. In certain conditions, this may not be true because the debt servicing will increase due to the heavy interest charges. The DSCR of higher interest rate is of course lower compared to the lower interest rate when all other factors are equal. Therefore, high interest rate will not compensate for poorly structured project. Furthermore, it is the interest margin that determines lenders appetite, not the absolute level of interest. This margin will reflect a combination of many risk determinants in loan tenor, industry demand, sponsor quality, country risk, quality of off takers and fuel supplier, project economics and other factors like security structures. F5 - Location Of Project 4
5 Favorable location of the project is viewed as important. Factors that should be considered include political and economical stability, and depth of local financial market and even geological parameters. The current financial turmoil in some Asian countries has caused a flight of capital and suspension of many mega infrastructure projects. Due to the crisis, lenders will only be comfortable if there is a higher equity investment for projects in developing countries. Up to this point of time, there is no BOT project financing in developing countries which has a 100% debt financing as shown in Table 4. Table 4. Location of Project F5 : Location of Project Developed Countries Developing Countries Number of Projects Range of equity (%) Mean Equity (%) The scenario is different in developed countries where the equity requirement for BOT project could be low and 100% debt financing had been attained in UK. The range of equity level in developed countries is 0% to 28% which is comparable to the developing countries' 'pre-crisis' equity of 3% to 30%. F6 - Concession Period A project with a short-term equity pay back is more attractive than one with a longer term pay back. If the economics of the concession are such that a long concession is needed to recoup the investment, then a high equity ratio will be necessary to allow repayment of debt within normal market tenors. Lenders have maximum tenors for various industries and countries. Concession period has to be longer than the loan tenor. After that, the equity will be the main consideration. This means that DSCR is only important for the loan tenor period and not relevant to lender beyond the specified period of repayment. Figure 1 shows the correlation between equity and concession period based on the data from BOT projects. The hypothetical equation for developed countries is E = 1.64 x n 1.17 and for developing countries is E = 0.05 x n 2.5 where E equal to calculated equity and n is the concession period of the projects. 400 Equity, US $m Developing Countries E = 0.05 n 2.5 R 2 = Developed Countries E = 1.64n 1.17 R 2 = n, years Developed Countries Developing Countries Figure 1. Equity Vs Concession Period 5
6 F7 - Novelty of Proposal When the construction technique is complicated, the lenders will consider the project inherently more risky. Thus, higher equity level is required. There is evidence that lenders are more comfortable with those proposals that are similar to ones they have previously financed and in areas of activity in which they are familiar (Woodward, et al, 1996). New and unproven technology is unlikely to be financed in the absence of a guarantee from a strong and credible promoter. Table 5 provides the suggested equity level for three different levels of construction novelty from the second survey. Table 5. Novelty of Construction and Equity Level Novelty Level of Construction Range of Recommended Equity Level (%) Level 1: Proven Conventional Method (e.g. road construction) Level 2: Difficult Construction & Operation (e.g. tunnels and dams) Level 3: Radical Construction Techniques (technology not proven) * exclude the technology of operational equipment The recommended equity level ranges from 20 to 30% for the proven conventional construction method (novelty level 1). For example in road construction, the equity investment is lower as compared to other. For BOT projects such as tunnels and dams where construction and operations are difficult, the equity commitment will be higher (30% to 60%). The above guidelines should be used with discretion. Each project needs to be carefully studied and to be categorized into correct level of novelty. F8 - Size of Project Availability of equity investment is possibly constrained by the risk capital available in the economy at any one time (Woodward, et al, 1996). Therefore, the equity investment by BOT developers will also be affected by the size of project. Generally, the lenders are not attracted by small project size, say below US$10 million, though in an emerging market, lenders may be interested to deal on a full recourse basis for small projects. A relationship between the project size and the amount of equity in absolute dollar for the BOT cases is as shown in Figure 2: the bigger the project size, the bigger amount of equity is required. Due to the wide range of project sizes which are covered (US$38m to US$9200m of size and US$9m to US$1720m of equity), the log graph is plotted to illustrate the relationship of the two parameters. Logarithms are suitable for improving resolution where data go through many powers of 10. The equation is Equity = x Size , Equity and Size are in terms of absolute amount (US$ millions). The relationship between the debt-equity ratio and the project size is shown in Figure 3 also. The relationship can be represented by the equation Debt-Equity ratio = (Size ) x 10-4, where size of project is in terms of absolute amount (US$ million). From this equation, for a project size is of US$500m, debt-equity ratio can be estimated as 3.24 [from ( ) x 10-4 ], or 76.4% of debt and 23.6% of equity. 6
7 1,000 Log (Equity) ,000 10,000 Equity = x Size Log (Size) R 2 = Figure 2. Log (Equity) Vs Log (Size) 10 Debt-Equity ratio ,000 10,000 Log(Size) Debt-Equity ratio = (Size )X10-4 Figure 3. Debt-Equity ratio Vs Log(Size) R 2 = F9 - Speculative Vs Invited Bid An unsolicited proposal or speculative bid is a proposal which is prepared and submitted solely at the initiative of a private promoter and is not in response to an official Request For Proposal (RFP). BOT projects need government support and political will. A speculative proposal is therefore assumed inherently more risky to invest since it is difficult to determine its validity and the commitment of the host government. The associated risks also depend on the off-take contracts and other forms of guarantees. Therefore high equity may be required by the lenders. If the bid is not accepted, there will be no risks taken by the lenders. If the speculative bid is accepted and all normal agreements are in place, then it does not differ from other projects approved based on RFP route. This factor is important to be considered only at the conceptual development stage of the BOT project. This is shown in Table 6 which shows the distribution of speculative and invited bids in developed countries and developing countries. The mean equity is about 17% for both cases. Table 6. Speculative Vs Invited Bid F9: Speculative vs Invited Bid Speculative Invited No. of Projects - developed country 2 13 No. of Projects - developing country 7 11 Range of Equity (%) Mean Equity (%)
8 F10 - Dispersion of Ownership The issue of wide dispersion of the ownership (equity) of a project will not affect the equity participation. The control over the project is left to the major shareholder and the voting right of the rest of the shareholders. The greater the equity, the greater the likelihood of an increase in the number of the owners of the project because one single project promoter may not be able to raise the equity. For many large projects (US$1000m above) several promoters are required and funds may have to be raised through public share issues or bonds. DEVELOPING THE EQUITY MODEL The qualitative modeling of determinants of the optimum debt-equity ratio is developed from the above factors: those factors that will affect the debt-equity ratio are listed in accordance to the phases in a BOT project which are conceptual development stage, project development and implementation stage and transfer. The factors or determinants of equity investment in BOT projects are modeled in groups of sub-factors As shown in Figure 4, there are five columns in the model with the sixth column providing the estimation of equity level for each small group such as E 1, E 2, E 3 and so on. The final optimum level of equity is E 0. CONCEPTUAL DEVELOPMENT STAGE The commercial viability of the proposal is determined to confirm the level of equity investment at the early stage of conceptual development. This stage involves the application of different strategies in BOT tender. Factors F5 (Location of Project), F7 (Novelty of Proposal), F8 (Size of Project), F9 (Speculative or Invited Bid) and F10 (Dispersion of Ownership) are identified as important factors. PROJECT DEVELOPMENT AND IMPLEMENTATION Project Development - Financing The important factors at this stage are F1 (Revenue Risks and Sectors), F2 (Availability of Guarantees and Securities), F3 (Loan Repayment Period/Loan Tenor), F4 (Real Interest Rate), F6 (Concession Period) and F8 (Size of Project). The challenge of structuring the project finance is to establish a mixture of debt, equity and mezzanine financing that optimizes the use of financial sources. The sources of equity and the availability of debt would play a part in deciding the debt-equity ratio. The financial indicators need to be calculated with a high certainty to prove their validity in this application. Figure 5 is extracted from Figure 4 to illustrate the financing stage in Column 4 and Column 5. The range of DSCR and attractiveness of the investment return are determined in Column 4 and then the desirable equity levels, E 7 and E 8, are determined in the subsequent steps. Project Implementation - Build The factors associated with project implementation that would differences the debt/equity ratio are F2 (Availability of Guarantees and Securities), F5 (Location of Project), F7 (Novelty of Proposal) and F8 (Size of Project): 8
9 Column 1 Column 2 F5 Developing Country? A1 A: CONCEPTUAL DEVELOPMENT STAGE F7 F8 Proven Technology? Any Past Experiences? E0 = x Size DER = (Size ) x 10-4 A2 A3 F9 Private Initiation? RFP? A4 F10 Equity from Government? Local Partner Important? A5 1B : FINANCING F1, F2 F3, F4 F6, F8 PROJECT CASH FLOW CORPORATE CASH FLOW 1B1 1B2 F2 Contractual Undertakings 2B1 B: PROJECT DEVELOPMENT & IMPLEMENTATION 2B : BUILD F5 F7 Labour/ Material Costs Construction/ Installation Risks 2B2 2B3 F8 Construction Costs 2B4 F1 Demand Study 3B1 F2 O & M Contract 3B2 3B : OPERATION F5 Political Stability 3B3 F6 E = 1.64 x n 1.17 E = 0.05 x n 2.5 3B4 C: TRANSFER PROCEDURE F7 OPERATING RISKS 3B5 Note: denotes key factor/determinant; & denote connector to column 3 in next page Figure 4. Flow Chart for Equity Model (Continued Next Page) 9
10 Column 3 Column 4 A1 A2 A3 Country Commercial Risks Political Risks Country Legal Risks Level of Novelty Adjustment Range ± 5% Adjustment of D-E-ratio General Economics Financial Strength Inflation Rate Tax Rate E h R Change in Regulation/Law Level 3 Level 2 Level A4 Finance Uncertain? Competition Keen? Bidding Risks YES NO HIGH Equity Need not be high 5 A5 1B1 1B2 2B1 2B2 2B3 2B4 3B1 3B2 3B3 3B4 3B5 YES NO DSCR, LLCR, LOAN TENOR PAY BACK, IRR, ROE, ROI Certainty of Assumptions/ Projection ( C1, C2, C3, C4 ) Construction Contract Supply Contract Insurance Contract Land Acquisition Costs Range of DSCR IRR ROE etc Attractive Unattractive Contract Based Market/ Contract Mixed 10 Market Based Adjustment Range 12 Proven Equipment Technology Note: & denote connector to column 5 in next page Figure 4. Flow Chart for Equity Model (Continued Next Page) 10
11 Column High Equity Medium Equity Low Equity E 1 E 2 E 3 4 E High Equity Medium Equity Low Equity E 5 E High Equity Medium Equity Low Equity E 7 E 8 Optimum Equity 9 High Equity Medium Equity Low Equity E 9 E High Equity Medium Equity 12 Low Equity 13 Note: High Equity = 25 % to 40 % Medium Equity = 15 % to 25 % Low Equity = 10 % to 15 % E 11 E 12 E 13 Figure 4. Flow Chart for Equity Model Project Implementation - Operation The factors that need to be considered at this stage are F1 (Revenue Risks and Sectors), F2 (Availability of Guarantees and Securities), F5 (Location of Project), F6 (Concession Period) and F7 (Novelty of Proposal): TRANSFER PROCEDURE The possibility of early or timely transfer, the extension of concession period, new O&M contract and the transfer of technology are the main factors identified. 11
12 Column 4 Column 5 7&8 Range of DSCR IRR, ROE etc Attractive Unattractive High Equity Medium Equity Low Equity E 7 E 8 Figure 5. Columns 4 and 5 of Financing in Equity Model CONCLUSIONS The qualitative equity model is developed to determine the optimum equity level from the view point of a project promoter. The 10 key determinants of equity are classified into three broad categories depending on the stage of BOT development. The ability to identify the determinants in each particular infrastructure project is the first step to obtain the optimum equity level. There must exist the ability to measure or evaluate all these identified determinants and subsequently control them. From the survey analysis, F1 (Revenue Risks and Sectors) and F2 (Availability of Guarantees and Securities) seemed to be the main concerns of most project promoters. The importance of government support and guarantees must not be neglected especially for the developing countries. Typically equity of more than 30% is considered as high equity participation. Basically the equity level can be classified into low, medium and high risks and the respective equity level is being recommended at the range of 10-15, and 25-40%. REFERENCES Koh, B. S. (1997). "Determinants of Debt/Equity Ratio for BOT Projects", Nanyang Technological University, Singapore Loh N., Lim, W. K. (1992). Risk Management Of Large Infrastructure Projects, Nanyang Technological University, Singapore. Mohd Tajuddin, Md. G. (1991). Malaysia s Experience in BOT Method of Project Development, Proceedings of the International Seminar on BOT For Project Implementation & Financing, pp. 74. Tiong, L. K. and He, Z. (1996). Development of Financial Risk Assessment Model For Overseas Project Investment, Nanyang Technological University, Singapore Tiong, L. K. (1995). Competitive Advantage of Equity in BOT Tender, Journal of Construction Engineering and Management, ASCE, Vol. 121, No.3, pp Woodward, D. G. and Chan, S. L. F. (1993). Equity Finance. Conf. On Build-Own- Operate-Transfer (BOOT) Projects, UMIST, Budapest, Hungary. Woodward, D. G., Tiong, L. K. and Munro, J. W. (1996). An investigation into the determinants of BOT project financing, Proceeding of IPMA 96 World Congress On Project Management & 12th AFITEP Annual Meeting, France, Vol. 2, pp Yeoh, K. S. (1995). A Study Of BOT and Concession-Based Contracts, Nanyang Technological University, Singapore. 12
Financing PPPs: Project Finance June 2006
Financing PPPs: Project Finance June 2006 Index Section I. Section II. Section III. Project Finance Spanish Market Advantages Risk Matrix P. 2 Section I Project Finance Project Finance Definition Definition:
Understanding a Firm s Different Financing Options. A Closer Look at Equity vs. Debt
Understanding a Firm s Different Financing Options A Closer Look at Equity vs. Debt Financing Options: A Closer Look at Equity vs. Debt Business owners who seek financing face a fundamental choice: should
Community and Renewable Energy Scheme Project Development Toolkit
Community and Renewable Energy Scheme Project Development Toolkit Balance Sheet Equity Investment Community Bond Issues Community Vehicle Crowd Funding Debentures a form of bond Debt Debt Service Cover
Borrowing Money for Your Business
Borrowing Money for Your Business After you have developed a cash flow analysis and determined when your business will make profit, you may decide you need additional funding. Borrowing money is one of
PROCUREMENT GUIDE: CHP FINANCING
PROCUREMENT GUIDE: CHP FINANCING 1. Overview The decision of whether and how to finance a CHP system is a critical step in the development of a CHP project. CHP systems require an initial investment to
Chapter Seven STOCK SELECTION
Chapter Seven STOCK SELECTION 1. Introduction The purpose of Part Two is to examine the patterns of each of the main Dow Jones sectors and establish relationships between the relative strength line of
BUSINESS PLANS. . The best part of this is that it is free!
BUSINESS PLANS A business plan is absolutely essential to the creation of a new business entity as well as the continued profitable operation of an established business. The conduct of a business in the
Fundamentals Level Skills Module, Paper F9
Answers Fundamentals Level Skills Module, Paper F9 Financial Management June 2008 Answers 1 (a) Calculation of weighted average cost of capital (WACC) Cost of equity Cost of equity using capital asset
Agreements, bonds and guarantees
Agreements, bonds and guarantees SPV Formation The Special Project Vehicle (SPV) may take a variety of forms, including a corporation, limited liability company, general partnership, limited partnership,
Module 1: Corporate Finance and the Role of Venture Capital Financing TABLE OF CONTENTS
1.0 FINANCING PRINCIPLES Module 1: Corporate Finance and the Role of Venture Capital Financing Financing Principles 1.01 Introduction to Financing Principles 1.02 Capitalization of a Business 1.03 Capital
Choice of Discount Rate
Choice of Discount Rate Discussion Plan Basic Theory and Practice A common practical approach: WACC = Weighted Average Cost of Capital Look ahead: CAPM = Capital Asset Pricing Model Massachusetts Institute
MBA Financial Management and Markets Exam 1 Spring 2009
MBA Financial Management and Markets Exam 1 Spring 2009 The following questions are designed to test your knowledge of the fundamental concepts of financial management structure [chapter 1], financial
The relationship of accounting ratios in balance sheets
The relationship of accounting ratios in balance sheets Accounting Ratios are the ratios show the relationship between accounting data in a balance sheet, profit and loss account in a particular organization.
1 (a) NPV calculation Year 1 2 3 4 5 $000 $000 $000 $000 $000 Sales revenue 5,614 7,214 9,015 7,034. Contribution 2,583 3,283 3,880 2,860
Answers Fundamentals Level Skills Module, Paper F9 Financial Management December 2012 Answers 1 (a) NPV calculation Year 1 2 3 4 5 $000 $000 $000 $000 $000 Sales revenue 5,614 7,214 9,015 7,034 Variable
Conceptual Framework for Financial Reporting
Conceptual Framework for Financial Reporting Chapter 1: The Objective of Financial Reporting INTRODUCTION OB1. The first chapter of the conceptual framework establishes the objective of general purpose
Management Accounting and Decision-Making
Management Accounting 15 Management Accounting and Decision-Making Management accounting writers tend to present management accounting as a loosely connected set of decision making tools. Although the
B U I L D I N G P A R T N E R S H I P S F O R E N E R G Y S E C U R I T Y www.inogate.org
"INOGATE Technical Secretariat & Integrated Programme in support of the Baku Initiative and the Eastern Partnership energy objectives" Project B U I L D I N G P A R T N E R S H I P S F O R E N E R G Y
PPP GLOSSARY. Availability. Base Case. Bidder BOOT BOT. Business Case. Commercial Operations Date (COD) Concession
PPP GLOSSARY Availability Base Case Bidder Bond BOOT BOT Term Business Case Capex Commercial Operations Date (COD) Concession Meaning The period when the facility (or the relevant part thereof) is able
CONCEPT AND BACKGROUND TO PUBLIC PRIVATE PARTNERSHIP (PPP) / PRIVATE FINANCE INITIATIVE (PFI) UK EXPERIENCE
CONCEPT AND BACKGROUND TO PUBLIC PRIVATE PARTNERSHIP (PPP) / PRIVATE FINANCE INITIATIVE (PFI) UK EXPERIENCE Professor Mustafa Alshawi 11/20/2009 Chairman Iraq Institute for Economic Reforms (IIER) Baghdad,
CALCULATING "ADDITIONAL FUNDS NEEDED" (A.F.N.)
CALCULATING "ADDITIONAL FUNDS NEEDED" (A.F.N.) Economic volatility in the agribusiness industry over the past decade has, in my opinion, comprised a mixed-bag of hardships and blessings. Organizational
Consolidated Financial Statements
STATUTORY BOARD FINANCIAL REPORTING STANDARD SB-FRS 110 Consolidated Financial Statements This standard applies for annual periods beginning on or after 1 January 2013. Earlier application is permitted
1 (a) Calculation of net present value (NPV) Year 1 2 3 4 5 6 $000 $000 $000 $000 $000 $000 Sales revenue 1,600 1,600 1,600 1,600 1,600
Answers Fundamentals Level Skills Module, Paper F9 Financial Management December 2011 Answers 1 (a) Calculation of net present value (NPV) Year 1 2 3 4 5 6 $000 $000 $000 $000 $000 $000 Sales revenue 1,600
Higher National Unit specification: general information
Higher National Unit specification: general information Unit code: H0C0 35 Superclass: AL Publication date: May 2012 Source: Scottish Qualifications Authority Version: 01 Unit purpose This Unit is designed
PROJECT FINANCE UNCDF October 2014 Dar Es Salaam
Project Finance PROJECT FINANCE UNCDF October 2014 Dar Es Salaam AGENDA History and Definition Structure of Project Finance Transactions Key Players Milestones Role of Debt in PF transactions Risk Management
E2-2: Identifying Financing, Investing and Operating Transactions?
E2-2: Identifying Financing, Investing and Operating Transactions? Listed below are eight transactions. In each case, identify whether the transaction is an example of financing, investing or operating
PORT REFORM TOOLKIT WORLD BANK
WORLD BANK FINANCIAL MODEL MANUAL Concession Project in the port sector 1/ PRELIMINARY ADVICE Required Software : Excel 2000 for PC Data & parameters of modelling : It appears in blue colour and exclusively
Success in Renewables. Glossary of Terms Investment and Renewables
Success in Renewables Glossary of Terms Investment and Renewables If you re new to renewable energy or investment, then it can be a minefield of new language and terminology. What seems totally normal
How to Assess Your Financial Planning and Loan Proposals By BizMove Management Training Institute
How to Assess Your Financial Planning and Loan Proposals By BizMove Management Training Institute Other free books by BizMove that may interest you: Free starting a business books Free management skills
SMALL BUSINESS DEVELOPMENT CENTER RM. 032
SMALL BUSINESS DEVELOPMENT CENTER RM. 032 FINANCING THROUGH COMMERCIAL BANKS Revised January, 2013 Adapted from: National Federation of Independent Business report Steps to Small Business Financing Jeffrey
Characteristics of the Participants
3 Financial Analysis for Replacement of Construction Equipment in Saudi Arabia Ali A. Shash (Center for Engineering Research, Research Institute, King Fahd University of Petroleum & Minerals, Saudi Arabia)
Mezzanine Finance. by Corry Silbernagel Davis Vaitkunas Bond Capital. With a supplement by Ian Giddy
Mezzanine Finance by Corry Silbernagel Davis Vaitkunas Bond Capital With a supplement by Ian Giddy Mezzanine Debt--Another Level To Consider Mezzanine debt is used by companies that are cash flow positive
Study on Financing Growth Capital for SMEs
Study on Financing Growth Capital for SMEs Remarks by Marion G. Wrobel Vice-President, Policy and Operations Canadian Bankers Association for The Standing Senate Committee on Banking Trade and Commerce
Understanding Leverage in Closed-End Funds
Closed-End Funds Understanding Leverage in Closed-End Funds The concept of leverage seems simple: borrowing money at a low cost and using it to seek higher returns on an investment. Leverage as it applies
The refinancing of the Fazakerley PFI prison contract
Report by the Comptroller and Auditor General The Prison Service The refinancing of the Fazakerley PFI prison contract Ordered by the House of Commons to be printed 26 June 2000 LONDON: The Stationery
Funding wind power: the view from a financial institution
Funding wind power: the view from a financial institution TPWind Nicolas Gourvitch - 24 September 2013 GGEB - A specialist advisory boutique focused on renewable energy At the heart of the energy transition
Topic 7: Financial Performance
Topic 7: Financial Performance One of the most important tasks in transition planning is analyzing the financial performance of the farm operation. Too many farms move ahead making decisions regarding
Land Acquisition and Development Finance Part IV
Land Acquisition and Development Finance Part IV In last month s Learn article, we discussed tying up the land and a more in depth formal due diligence process. This article will discuss Development financing.
Specialized Financing in the Oil & Gas Industry
Specialized Financing in the Oil & Gas Industry How to proceed? What are our needs when starting a project? What are our objectives when we approach financings? Why we can rely on banking financings? 1
Information Paper 10. Debt Management
Information Paper 10 Debt Management February 2007 Introduction Local Government financial statements, like those of other spheres of government and the corporate sector, include a good many items of considerable
Enterprise Valuation of Private Investments Policy
Enterprise Valuation of Private Investments Policy Policy Sponsor: CFO Summary: This accounting policy applies to all private investments, represented by directly held real estate assets (i.e., revenue
Renewable Energy Finance Fundamentals
Renewable Energy Finance Fundamentals The US Partnership for Renewable Energy Finance (US PREF) has prepared the following brief summary of the basics of renewable energy project finance. An appreciation
Uses and Limitations of Ratio Analysis
Uses and Limitations of Ratio Analysis Balkrishna Parab ACS, AICWA [email protected] F inancial statement analysis involves comparing the firm s performance with that of other firms in the same
TAKING THE MYSTERY OUT OF FINANCE
TAKING THE MYSTERY OUT OF FINANCE Presented By: Eva Brown, Director of Access to Capital 312 853 3477 x 560 OBJECTIVES Determine how much money you need to start/expand your business. Determine your ability
Urban Community Energy Fund Getting your project investment ready
Urban Community Energy Fund Getting your project investment ready What is investment readiness, and why does it matter? Investment readiness is when your project is at the right stage to secure a bank
An Alternative Way to Diversify an Income Strategy
Senior Secured Loans An Alternative Way to Diversify an Income Strategy Alternative Thinking Series There is no shortage of uncertainty and risk facing today s investor. From high unemployment and depressed
Investment Options and Risk
Investment Options and Risk Issued 1 July 2013 The information in this document forms part of the Product Disclosure Statement for the Military Superannuation and Benefits Scheme (MilitarySuper), third
Why Invest in a Non-Traded Business Development Company?
Why Invest in a Non-Traded Business Development Company? This literature must be read in conjunction with the prospectus in order to fully understand all of the implications and risks of the offering of
How To Calculate Financial Leverage Ratio
What Do Short-Term Liquidity Ratios Measure? What Is Working Capital? HOCK international - 2004 1 HOCK international - 2004 2 How Is the Current Ratio Calculated? How Is the Quick Ratio Calculated? HOCK
BENEFIT-COST ANALYSIS Financial and Economic Appraisal using Spreadsheets
BENEFIT-COST ANALYSIS Financial and Economic Appraisal using Spreadsheets Ch. 4: Project and Private Benefit-Cost Analysis Private Benefit-Cost Analysis Deriving Project and Private cash flows: Project
Robert and Mary Sample
Comprehensive Financial Plan Sample Plan Robert and Mary Sample Prepared by : John Poels, ChFC, AAMS Senior Financial Advisor February 11, 2009 Table Of Contents IMPORTANT DISCLOSURE INFORMATION 1-7 Presentation
Debt Financing for Healthcare Companies: The Current State of the Market
Debt Financing for Healthcare Companies: The Current State of the Market Note: For the purposes of this paper, we will define healthcare as life sciences/biotech, medical devices, diagnostics and health
Financing a New Venture
Financing a New Venture A Canadian Innovation Centre How-To Guide 1 Financing a new venture New ventures require financing to fund growth Forms of financing include equity (personal, family & friends,
Financial Evolution and Stability The Case of Hedge Funds
Financial Evolution and Stability The Case of Hedge Funds KENT JANÉR MD of Nektar Asset Management, a market-neutral hedge fund that works with a large element of macroeconomic assessment. Hedge funds
how to prepare a cash flow statement
business builder 4 how to prepare a cash flow statement zions business resource center zions business resource center 2 how to prepare a cash flow statement A cash flow statement is important to your business
PEI: New Strategies for Risk Management in Private Equity
PEI: New Strategies for Risk Management in Private Equity Risk in non-traditional secondary strategies By Augustin Duhamel and Vidar Bergum, 17Capital Introduction As the private equity industry has matured,
Ethiopian Institute of Financial Studies (EIFS) PROJECT FINANCE
PROJECT FINANCE With the growth in the economy and the revival in the industrial sector coupled with the increasing role of private players in the field of infrastructure, more and more Ethiopian banks
Financing DESCOs A framework
Financing DESCOs A framework A framework discussion about financing working capital for distributed energy services companies Chris Aidun and Dirk Muench March 2015 This paper looks at the growing need
FIIG ESSENTIALS GUIDE. Residential Mortgage Backed Securities
FIIG ESSENTIALS GUIDE Residential Mortgage Backed Securities Introduction Residential Mortgage Backed Securities (RMBS) are debt securities that are secured by a pool of home loans. RMBS are a subset
Gebze Izmir Motorway & Izmit Bay Crossing Project
Gebze Izmir Motorway & Izmit Bay Crossing Project F.Mehmet Coşan CFO Haluk BÜYÜKBAŞ Secretary General, TCA Gebze Orhangazi Izmir Project is the landmark transaction for the infrastructure sector in Turkey
Dealing With Your Banker &
Dealing With Your Banker & Other Lenders Your financing The success or failure of your business will depend on whether or not you have enough capital to: buy the equipment and inventory you need; pay overhead
SHUAA Capital PSC INTERIM CONDENSED CONSOLIDATED FINANCIAL STATEMENTS
INTERIM CONDENSED CONSOLIDATED FINANCIAL STATEMENTS 30 SEPTEMBER INTERIM CONSOLIDATED STATEMENT OF INCOME Notes 1 July to (3 Months) 1 January to 1 July to (3 Months) 1 January to Interest income 31,906
AN INTRODUCTION TO REAL ESTATE INVESTMENT ANALYSIS: A TOOL KIT REFERENCE FOR PRIVATE INVESTORS
AN INTRODUCTION TO REAL ESTATE INVESTMENT ANALYSIS: A TOOL KIT REFERENCE FOR PRIVATE INVESTORS Phil Thompson Business Lawyer, Corporate Counsel www.thompsonlaw.ca Rules of thumb and financial analysis
Existing Procedure and Guidelines for approval of Foreign Private Loan.
Existing Procedure and Guidelines for approval of Foreign Private Loan. With a view to promote foreign investment in the private sector through easier long term financing of industrial project at lower
Financial System Inquiry SocietyOne Submission
Financial System Inquiry SocietyOne Submission SocietyOne is pleased to make the following submission to the Financial System Inquiry. SocietyOne is Australia s first fully compliant Peer-to-Peer (P2P)
Ipx!up!hfu!uif Dsfeju!zpv!Eftfswf
Ipx!up!hfu!uif Dsfeju!zpv!Eftfswf Credit is the lifeblood of South Louisiana business, especially for the smaller firm. It helps the small business owner get started, obtain equipment, build inventory,
Meet challenges head on
Meet challenges head on Deal Advisory / Global We can help you master Financial Restructuring. Enhancing value through financial restructuring. / 1 Your vision. Our proven capabilities. Despite its challenges,
Sources of finance (Or where can we get money from?)
Sources of finance (Or where can we get money from?) Why do we need finance? 1. Setting up a business 2. Need to finance our day-to-day activities 3. Expansion 4. Research into new products 5. Special
A 10-year Investment Performance Review of. the MPF System. (1 December 2000 31 December 2010)
A 10-year Investment Performance Review of the MPF System (1 December 2000 31 December 2010) Acknowledgement The methodology and analysis of this report have been reviewed by Prof Kalok Chan, Synergis-Geoffrey
Buying and Selling an ESOP Company
Buying and Selling an ESOP Company 2015 ACG Charlotte Deal Crawl Affinity Seminar September 22, 2015 Alberto Toribio del Pilar ButcherJoseph & Co. 101 S. Hanley Rd., Suite 1450 St. Louis, MO 63105 P: (314)
Loans and Security Training
Jonathan Lawrence, Finance Partner, London Loans and Security Training November 2014 Copyright 2014 by K&L Gates LLP. All rights reserved. LOANS AND SECURITY TRAINING A. Entering into a loan facility B.
Professional Level Skills Module, Paper P4
Answers Professional Level Skills Module, Paper P4 Advanced Financial Management December 2011 Answers 1 Up to 4 professional marks are available for the presentation of the answer, which should be in
SMALL BUSINESS OWNER S HANDBOOK
SMALL BUSINESS OWNER S HANDBOOK PART II: FINANCIAL PLANNING FOR SMALL BUSINESSES Introduction Financial Planning Methods of Financing Your Business Other Types of Funds & Financing How to Approach Lenders
A B C D E F G H I J K L M N O P Q R S T U V W X Y Z
Jargon Buster Contents listed alphabetically: A B C D E F G H I J K L M N O P Q R S T U V W X Y Z A Additional Voluntary Contribution (AVC) Extra payments you can make in additional to your main occupational
PUBLIC-PRIVATE PARTNERSHIP (PPP)
PUBLIC-PRIVATE PARTNERSHIP (PPP) Virginia Tan, Allen & Overy Type: Published: Last Updated: Keywords: Legal guide June 2012 June 2012 PPP, infrastructure assets, public and private sectors This document
Investment options and risk
ADF Super Australian Defence Force Superannuation Investment options and Issued 2 June 2016 The information in this document forms part of the Product Disclosure Statement for the Australian Defence Force
Contribution 787 1,368 1,813 983. Taxable cash flow 682 1,253 1,688 858 Tax liabilities (205) (376) (506) (257)
Answers Fundamentals Level Skills Module, Paper F9 Financial Management June 2012 Answers 1 (a) Calculation of net present value (NPV) As nominal after-tax cash flows are to be discounted, the nominal
11.437 Financing Community Economic Development Class 6: Fixed Asset Financing
11.437 Financing Community Economic Development Class 6: Fixed Asset Financing I. Purpose of asset financing Fixed asset financing refers to the financing for real estate and equipment needs of a business.
Athens University of Economics and Business
Athens University of Economics and Business MSc in International Shipping, Finance and Management Corporate Finance George Leledakis An Overview of Corporate Financing Topics Covered Corporate Structure
Construction Economics & Finance. Module 6. Lecture-1
Construction Economics & Finance Module 6 Lecture-1 Financial management: Financial management involves planning, allocation and control of financial resources of a company. Financial management is essential
Financial Ratios and Quality Indicators
Financial Ratios and Quality Indicators From U.S. Small Business Administration Online Women's Business Center If you monitor the ratios on a regular basis you'll gain insight into how effectively you
Introduction to Australian Real Estate Debt Securities
1 Introduction Introduction to Australian Real Estate Debt Securities Superannuation fund investors and managers have for a long time invested in real estate as part of their asset allocation in the belief
APRIL 2015. Economic Impact of AIM
APRIL 2015 Economic Impact of AIM Foreword AIM, which is 20 years old this year, has weathered several economic storms over the past two decades, but has remained true to its core purpose of providing
CONTRACTS FOR DIFFERENCE
CONTRACTS FOR DIFFERENCE Contracts for Difference (CFD s) were originally developed in the early 1990s in London by UBS WARBURG. Based on equity swaps, they had the benefit of being traded on margin. They
Shares Mutual funds Structured bonds Bonds Cash money, deposits
FINANCIAL INSTRUMENTS AND RELATED RISKS This description of investment risks is intended for you. The professionals of AB bank Finasta have strived to understandably introduce you the main financial instruments
UK Export Finance Main Features of the Export Refinancing Facility:
UK Export Finance Main Features of the Export Refinancing Facility: Main Features of the Export Refinancing Facility (ERF) Summary UK Export Finance s Export Refinancing Facility (ERF) will help overseas
1 (a) Net present value of investment in new machinery Year 1 2 3 4 5 $000 $000 $000 $000 $000 Sales income 6,084 6,327 6,580 6,844
Answers Fundamentals Level Skills Module, Paper F9 Financial Management June 2013 Answers 1 (a) Net present value of investment in new machinery Year 1 2 3 4 5 $000 $000 $000 $000 $000 Sales income 6,084
A QUICK GUIDE TO PREPARING A FINANCING PROPOSAL
A QUICK GUIDE TO PREPARING A FINANCING PROPOSAL FOR PRINCE EDWARD ISLAND SMALL BUSINESS Page1of5 Bankers are just like other entrepreneurs; they seek new clients and would not stay in business if they
Commonwealth Caribbean Regional Conference. Investing in Youth Exploring Strategies for Sustainable Employment. Financing and Financial Mechanisms
Commonwealth Caribbean Regional Conference Investing in Youth Exploring Strategies for Sustainable Employment Financing and Financial Mechanisms Presented by Ian Chinapoo May 25 th, 2011 Outline: Background