1 First Addendum RFP for Solar Photovoltaic Generating System RFP Depot Bid Number Section 18, Addenda and Interpretation, of the RFP is deleted in its entirety and replaced with the following: 18. ADDENDA AND INTERPRETATION 18.1 The City shall not be responsible for nor be bound by any oral instructions, interpretations or explanations issued by the City or its representatives. Should discrepancies or omissions be found in this RFP or should there be a need to clarify the RFP, requests for clarification may be sent via or fax to the attention of the contact named in Section 6 or through RFPDepot.com Answers to questions submitted through RFP Depot shall be considered addenda to the solicitation documents. All addenda and notices related to this procurement will be posted by CITY on RFP Depot. In the event this solicitation is obtained through any means other than RFP Depot, CITY will not be responsible for the completeness, accuracy, or timeliness of the final solicitation document. 2. Q. Per Section of the CSI Handbook, solar equipment must serve an onsite electrical load. Because highway 101 is a public access road, the fuel farm ground area is considered a separate site from the Terminal A site (location of the interconnection). As such, the City, nor a PPA Investor, cannot receive CSI rebates for a system located at the fuel farm site with a tie-in located at Terminal A. Please confirm whether or not the City has obtained a variance on this issue. If not, please notify bidders if we should assume the fuel farm site is no longer in scope. A. The City has not received a variance from PG&E for the fuel farm site location. However, based on the current version of the CSI Handbook, we believe that the question was intended to quote CSI Handbook Section 2.2.4, Equipment Must Serve On-Site Electrical Load. The intent of this section appears to primarily address that the actual size of the system cannot exceed the required usage of the service that is being tied in to. The CSI application submitted by the City described the work and identified all potential sites. The application was approved by the CSI Program Administrator (PG&E). Notwithstanding any statements or representations made by the City in this RFP, the City does not represent or warrant that any of the proposed four sites at the Airport or any PV System proposed will qualify for the PG&E CSI Program. Therefore, proposers should make their own determination as to whether their Page 1 of 9
2 proposals, including but not limited to their proposed installation site(s) at the Airport, will qualify for the PG&E CSI Program. This question has been submitted to PG&E for clarification, and this City will issue an addendum in the event that the City receives additional information from PG&E regarding this question before the proposal deadline. 3. Q. We'd like to request a one-week extension to the period to provide feedback on the Solar Energy Purchase Agreement (Attachment G). It would be greatly helpful if we can provide comments by Tuesday 5/13, 6pm. A. After considering your request to extend the deadline for questions, the Airport has determined that the resulting impact on the project schedule would be detrimental and therefore will not extend the date from the current May 6, 2008 date posted. 4. Q. What is the basis of Design Capacity of Solar Power for SJ International Airport? A. As stated in section 4.1 of the RFP, a 1 megawatt solar system will generate approximately 1/4 of the current annual consumption for Terminal A. 5. Q. Is it Minimum 1 MW and Multiples of 1 MW additional capacity for future expansion? A. As stated in Section 4.1 of the RFP, proposers must provide a minimum of 1 MW ac of PV. Proposers may exceed 1 MW if they deem that to be the most cost effective approach. There is no preference on sizing increments beyond 1 MW. 6. Q. Is there a provision for future expansion? A. Not required by RFP 7. Q. Fresno airport has capacity of 2 MW. So If SJ International Airport is double the size of Fresno airport/we need at least 5 MW solar power. A. This RFP is for a minimum 1 MW ac solar PV. 8. Q. In deciding solar power/renewable power is Fuel Cell Power a good option/ may be based load for Fuel cell Power of 5 MW/or 3 MW and 1 or 2 MW Solar Power Project? A. This RFP is for a minimum 1 MW ac solar PV. 9. Q. The SJ Airport expansion is in several phases /what are the power needs projections for first year/first five years & ten years projection on expansion & potential for local Airports /Aircrafts Maintenance & Business Technology Park similar to Rolls Royce Engine Repairs project near Oakland airport? Page 2 of 9
3 A. Potential future Airport RFP's may address additional solar opportunities. This RFP is for a minimum 1 MW ac solar PV. 10. Q If possible, please provide 12 months of electricity bill from PG&E (preferably all of 2007). Currently attachment D of the RFP provides only one month. A. The utility bills requested for this site are not available within the timeframe of this addendum; however, power usage for this meter is very constant throughout the year. The one month provided is a good representation of standard power usage. 11. Q. Which roofing company has the warranty for the FIS building? A. S. J. Amoroso Construction Company, the Contractor that constructed the FIS facility, provided the warranty for the roof. 12. Q. At the site visit it was mentioned the Terminal A roof was 18-years old. Will this be re-roofed prior to the PV system being installed? Proposer suggests doing this to help improve project economics. A. Section 4.1, Solar Site #2: Terminal A Roof, states this roof to be approximately 15 years old and does not anticipate that a replacement of the roof will occur prior to the application of the solar array. Proposers are to assume that this roof will be re-roofed during the term of the solar PPA agreement. 13. Q. What are the security requirements for personnel working on this project? A. Systems located on the FIS or the Terminal A sites are in the secure area. Contractor employees accessing this area will have to attend a 2-3 hour training and badging process. 14. Q. Are there any recent updates on the installation schedule for the new 12kV tie-in from the new fuel farm? A. The 12kV tie-in will not occur within the timeframe of the installation of this solar project. The 12kV substation is not programmed at this time. 15. Q. With reference to Fuel farm site layout plans on the CD, we can only see 2.5 acre's available at the east corner of the fuel farm field. We were told in the presentations that there was 4 acre's available for a 1Mw system. Can you confirm that the 4 acre's are available and on which part of the field. (Can we use the phase 2 area dedicated to the fuel farm also shown on the site layout plans.). A. The area available for the solar is southeast of the Fuel Tank Farm area and not within the boundaries of the Fuel Tank Farm. See Exhibit C of the RFP for site clarification. There are approximately 3 1/2 to 4 acres available. Page 3 of 9
4 16. Q. Are there any height restrictions on panels in the field? A. Yes, there are airspace restrictions, but these should not affect expected ground mount installation. 17. Q. What type of security fence will be installed at the fuel farm (Question is a reflection on panel shading)? A. Unknown at this time, however Fuel Farm fencing will only be on the northwest side of the solar site. 18. Q. How close can we install panels to the fuel farm? A. Up to the south east boundary of the Fuel Farm security fencing. 19. SECTION 2.3: TERM Q. It is a condition precedent to the effectiveness of the PPA that moneys required for payments under the PPA are appropriated from the City Council. Proposer proposes that alternative remedies, including a termination payment, be considered in the event that San Jose terminates the PPA as a result of an appropriation. How does San Jose presently appropriate power? A. The City will not agree to an early termination payment, and Section 2.3 therefore remains unchanged. The City currently includes appropriations for power at the Airport in its annual budget. 20. SECTION 4.3: STANDARDS OF OPERATION Q. If the Lessee is to be bound by the covenants in Section 4.3 relating to a the prohibition on causing a conflict with, cancellation of, or increased premium relating to San Jose s insurance policies, the Lessee must be provided with the content of such insurance policies for its review. A. The City's insurance policies are public records and are available for review by proposers and will be available for review by the Lessee. 21. SECTION 8: RENT, FEES AND CHARGES Q. Rather than a Lease and Rental Fee Structure as presented in Section 8 of the PPA, Proposer would suggest the provision of easements or a less administratively taxing leasing structure. A. It is standard practice at the Airport to charge a lease rate which is established through a City Council Resolution for Airport Premises under the exclusive control of a Lessee. Setting aside the proposed solar locations has an opportunity cost to the Airport as those locations cannot be used for other purposes. Page 4 of 9
5 22. Q. Note that the unilateral right to adjust the Security Deposit without a stated ceiling to such amount is unacceptable to Proposer (Section 8.3). A. The provisions in Section 8.3 are consistent with provisions in the City s standard leases at the Airport, and Section 8.3 therefore remains unchanged. 23. Q. Section 8 further states that the Rent, Fees and Charges may be unilaterally amended by Resolution of the City Council. What does such Rent, Fees and Charges include? Is it intended to cover any compensation of the contractor for the Generating System? A. Section 8 refers to lease rates, security badging fees, and other costs of doing business at the Airport. It is not intended as compensation for the Generating System. 24. SECTION 9.2: TITLE TO ATTRIBUTES Q. San Jose is entitled to benefit from title to Environmental Attributes. We understand that certain of the incentives included within the present definition of Environmental Attributes would be allocable to a financing party, including the CSI incentive. Proposer would be pleased to propose an alternative definition for Environmental Attributes A. Section 1, Summary of Terms, definition of Environmental Attributes, of the PPA is deleted in its entirety and replaced with the following: "Environmental Attributes" shall mean that attribute of energy which qualifies for any type of credit or incentive for generating energy through a means which does not rely on the continual consumption of fossil fuels, but specifically excluding any tax credits, investment credits, product tax credits, rebates, or other similar tax benefits that may be associated with owning, operating or generating electricity through means which do not rely on the continual consumption of fossil fuels. Environmental Attributes include carbon trading credits, renewable energy credits or certificates, emission reduction credits, emissions allowances, green tags, tradeable renewable credits, Green-e products, and all similar credits. Environmental Attributes includes those credits available upon the Effective Date and all of those which may become available during the Term. This definition excludes the PG&E furnished California Solar Initiative program credits and rebates described in Exhibit E. 25. SECTIONS 10 and 11: MAINTENANCE OF PREMISES AND IMPROVEMENTS Q. Provisions relating to operation and maintenance of the Premises, including Improvements, standards of performance and the compensation, should be further discussed. If San Jose has specific and particular requirements relating to the operation and maintenance of the Generating System, such particulars and the operator s compensation, must separately negotiated and contained within an operation and maintenance agreement (Section 10). Page 5 of 9
6 A. The City does not intend to enter into a separate operation and maintenance agreement with the Lessee. Sections 10 and 11 remain unchanged. 26. SECTION 13.2: TITLE TO IMPROVEMENTS, ALTERATION AND REPAIR Q. A financing party is likely to have certain constraints, and further comments relating to, San Jose s early right to purchase the Generating System. A. Section 13.2 remains unchanged. As provided in Section 22.1 of the RFP, by submitting a proposal, each Proposer agrees to execute the City's PPA in substantially the form attached to the RFP, as revised to incorporate the pertinent criteria contained in the selected Proposer's submittal. The City will not agree to any substantive changes to the PPA after award, regardless of any changes requested by either the selected Proposer or its financing party. Exhibit F to the PPA, Buyout Schedule, should include impacts associated with early buyout 27. SECTON 14.1: PAYMENT BOND Q. San Jose to explain bonding requirements relating to the Unemployment Insurance Code. A. Section 14.1 is amended and restated in its entirety as follows: "The payment bond must provide that if Lessee's contractor or its subcontractor(s) fails to pay any of the persons named in Section 3181 of the California Civil Code, or amounts due under the Unemployment Insurance Code with respect to the work or labor contracted to be done and performed by any claimant, then the surety will pay for same, in an amount not exceeding the amount of the payment bond. The payment bond shall protect City from any liens, liability, losses or damages arising therefrom, and shall name Lessee's contractor or contractors as principals, and City as obligee. 28. SECTION 17: SECURITY MEASURES Q. As Lessee is expected to abide by its provisions, please provide a copy of the Airport Masters Security Plan (Section 17.1). A. The Airport Master Security Plan is designated as Sensitive Security Information (SSI) under applicable Federal law and is therefore confidential. Airport staff will notify the successful proposer of all provisions of the Airport Master Security Plan that will be applicable to the Lessee. 29. Q. The PPA allocates responsibility for preventing vandalism and damage to the Generating System to the Lessee (Section 17.2). Proposer believes that the security infrastructure at the San Jose Airport is better suited to perform these obligations, as it has an effective security system currently in place. Page 6 of 9
7 A. The Lessee will have possession of the leased premises during the term of the agreement and therefore should be responsible to prevent vandalism and damage to the Generating System. Section 17.2 remains unchanged. 30. Q. San Jose to explain the intent of Section In particular, please confirm what such reference to the reduction of rent or fee payments includes. A. Section 17.3 is not applicable to the Solar PV System and is therefore deleted in its entirety. 31. SECTION 19: ASSIGNMENT OR TRANSFER Q. Section 19 states that a transfer or assignment of the PPA would require the prior consent of San Jose. Note that a potential transaction and financing structure would require assigning the PPA from the contractor to such financing party. If such structure is elected, the consent of San Jose would be expected in advance within the body of the PPA, and without any suggested processing fee. A. Any assignment or transfer of the PPA required as part of Lessee financing will require City's consent as provided in Section 19, and the City will not agree to waive its approval rights for assignments or transfers in connection with Lessee financing. The City shall waive its right to assess a processing fee and therefore, Section 19.4 of the PPA is deleted in its entirety and replaced with the following: Lessee's failure to provide City with full, complete and necessary information shall be sufficient cause for City to deny consent to, or to refuse to review, the proposed transfer. 32. SECTION 20.1: EVENTS OF DEFAULT Q. Events of Default to include any customary cure periods, and be adjusted appropriately to reflect any change in the transactional structure, as the case may be. San Jose should be subject to reciprocal Events of Default. The remedies and damages described in Section 20.2 are not, in the experience of Proposer typical for an Event of Default relating to similar transactions. Each party should be entitled to terminate the PPA following an uncured Event of Default and seek damages suffered, as determined in accordance with a legal proceeding. A. The provisions in Section 20.1 are consistent with provisions in the City's standard leases at the Airport, and Section 20.1 therefore remains unchanged. Page 7 of 9
8 33. SECTION 22: INDEMNITY AND WAIVER OF CLAIM Q. San Jose should provide a reciprocal indemnity in favor of the Lessee. In the experience of Proposer, the indemnity provision provided in Section 22.1 is unusually onerous. Neither party should be entitled to full indemnification in the face of joint, several or concurrent liability. Why is Lessee being asked to waive all claims for action against San Jose in Section 22.3? A. The provisions in Section 22 are consistent with provisions in the City's standard leases at the Airport, and Section 22 therefore remains unchanged. 34. SECTION 23: INSURANCE Q. Insurance Requirements, as set out in Exhibit B and Section 23, are subject to the internal approval of Proposer. A. The City's minimum insurance requirements as set out in Section 23 remain unchanged. 35. SECTION 26.3: TAXES; ABSENCE OF LIENS Q. Why is the Lessee obligated to post a bond, in an amount acceptable to San Jose, in the event that Lessee contests the failure to impose a lien? A. Section 26.3 is consistent with provisions in the City's standard leases at the Airport, and Section 26.3 therefore remains unchanged. 36. SECTION 28.2: DAMAGE OR DESTRUCTION Q. Termination rights of San Jose, in all cases, and in the case of damage or destruction, are likely to be subject to further comments of a financing party. A. The City will not agree to any changes to Section 28.2 after award. 37. SECTION 39: RELOCATION, EXPANSION OR CONTRACTION Q. Why is the Lessee responsible for costs of relocation, expansion or contraction? A. Section 39, Relocation, Expansion or Contraction of Premises, is deleted in its entirety and replaced with the following: In the event that implementation of the City's requirements for the Airport, changes in airlines or flight schedules, or other changes in business conditions necessitate the relocation, expansion or contraction of the Premises, or any part thereof, Lessee shall relocate all or part of its operations on the Premises, or any part thereof, or contract or expand the size of the Premises in an expeditious manner only as may be permitted, Page 8 of 9
9 directed or required by the Director. In such event, City shall pay Lessee s reasonable relocation costs. Amendments to this Agreement which change or modify the description of the Premises set forth in Section Error! Reference source not found. above to specify in writing increases, decreases, or relocation of the Premises, and which include only such rental rates on a per square foot basis as are specified or authorized in accordance with Section Error! Reference source not found. above, may be executed on behalf of the City by the Director. 38. SECTION 40.5: MISCELLANIOUS Q. In our experience, the Force Majeure provision is extremely limited, and should be expanded to align with market provisions. A. No specific changes to Section 40.5 are proposed in this question. Section 40.5 is consistent with provisions in the City's standard leases at the Airport, and Section 40.5 therefore remains unchanged 39. EXHIBIT C: HAZARDOUS MATERIAL Q. San Jose to explain reasoning behind Lessee assumption of risk relating to Hazardous Material released during the course of the Agreement. This risk is unacceptable to Proposer. A. Exhibit C is consistent with provisions in the City's standard leases at the Airport, and Exhibit C therefore remains unchanged. 40. A proposer has submitted some objections to the RFP and Power Purchasing Agreement (PPA). The City s response is attached as Attachment 1 to this Addendum. Page 9 of 9
10 Attachment 1
11 Attachment 1
How To Co-Location
Cellular Antenna Leases: A Checklist for Landlords A cellular carrier s lease form or the form of an independent cell site developer (both are referred to as a carrier ) is prepared by and strongly biased
More informationPROJECT NO. 2733, RFP NO. 14-15/02. Peralta Community College District. 333 East 8th Street, Oakland, CA 94606. Questions
PROJECT NO. 2733, RFP NO. 14-15/02 Peralta Community College District 333 East 8th Street, Oakland, CA 94606 August 7, 2014 ADDENDUM No. 1 This addendum supersedes items of the original contract documents
More information388 Blohm Ave. PO Box 388 Aromas CA 95004-0388 (831)726-3155 FAX (831)726-3951 email aromaswd@aol.com ADDENDUM NO. 1
388 Blohm Ave. PO Box 388 Aromas CA 95004-0388 (831)726-3155 FAX (831)726-3951 email aromaswd@aol.com May 6, 2015 To: All Plan Holders From: Vicki Morris General Manager Subject: Water Serviceline Installation
More informationREQUEST FOR PROPOSALS
ROWAN COUNTY 130 West Innes Street Salisbury, NC 28144 Tel: (704) 216-8174 Email: david.sifford@rowancountync.gov REQUEST FOR PROPOSALS FOR REPLACEMENT OF COMMERCIAL ROOFTOP AIR CONDITIONING UNIT Issued
More informationAIA Document A310 TM 2010
AIA Document A310 TM 2010 Bid Bond CONTRACTOR: OWNER: «Lane County» «125 East Eighth Avenue BOND AMOUNT: $ PROJECT: (Name, location or address, and Project number, if any) «Lane County Adult Corrections
More informationLEX HELIUS: THE LAW OF SOLAR ENERGY Solar Energy System Design, Engineering, Construction, and Installation Agreements
LEX HELIUS: THE LAW OF SOLAR ENERGY Solar Energy System Design, Engineering, Construction, and Installation Agreements Alan R. Merkle Stoel Rives LLP 600 University Street, Suite 3600 Seattle, WA 98101-4109
More informationREQUEST FOR PROPOSALS SOLAR POWER PURCHASE AGREEMENT (PPA)
ISSUE DATE: July 24, 2015 REQUEST FOR PROPOSALS SOLAR POWER PURCHASE AGREEMENT (PPA) Proposals will be received until 2:00 P.M. Monday, August 24, 2015 for furnishing the services described herein. Email
More informationSolicitation 2013-9. Emergency Disaster Cleanup Services. Bid designation: Public. Lehi City
Solicitation 2013-9 Emergency Disaster Cleanup Services Bid designation: Public Lehi City 11/4/2013 4:51 PM p. 1 Bid Number 2013-9 Bid Title Emergency Disaster Cleanup Services Emergency Disaster Cleanup
More informationRequest for Proposals to Design, Build, Finance, Operate and Maintain North Commuter Parkway and Traffic Bridge Project City of Saskatoon
Request for Proposals to Design, Build, Finance, Operate and Maintain North Commuter Parkway and Traffic Bridge Project City of Saskatoon () Request for Proposals TABLE OF CONTENTS SECTION 1 INTRODUCTION...
More informationSTATE OF WEST VIRGINIA BOARD OF RISK AND INSURANCE MANAGEMENT REQUEST FOR PROPOSAL RFP# 05122010
STATE OF WEST VIRGINIA BOARD OF RISK AND INSURANCE MANAGEMENT REQUEST FOR PROPOSAL RFP# 05122010 Fiscal Year 2011 1 TABLE OF CONTENTS Part 1 - Informational...3 Part 2 - Operating Environment...8 Part
More informationCalifornia Solar Initiative (CSI) Program 2007 Reservation Request Form and Program Contract [follows the second page Reservation Request form]
California Solar Initiative (CSI) Program 2007 Reservation Request Form and Program Contract [follows the second page Reservation Request form] CSI CONTRACT TERMS AND CONDITIONS This California Solar Initiative
More informationCSA CONSTRUCTION, INC. 2314 McAllister Road Houston, Texas 77092 SUBCONTRACTOR AGREEMENT
CSA CONSTRUCTION, INC. 2314 McAllister Road Houston, Texas 77092 SUBCONTRACTOR AGREEMENT THIS AGREEMENT made this day of Month, Year, by and between CSA CONSTRUCTION, INC., a Texas corporation whose principal
More informationCITY OF BONITA SPRINGS, FLORIDA RFP # 14-019
CITY OF BONITA SPRINGS, FLORIDA RFP # 14-019 Pursuant to Florida Statutes, Chapter 287, The City of Bonita Springs hereinafter referred to as the City, will accept sealed Responses for Qualifications and
More informationOKLAHOMA GAS AND ELECTRIC COMPANY REQUEST FOR INFORMATION. Solar Energy Purchase Power Agreement Information
OKLAHOMA GAS AND ELECTRIC COMPANY REQUEST FOR INFORMATION Solar Energy Purchase Power Agreement Information RFI Issue Date May 18, 2015 Responses Due June 15, 2015 1. RFI Purpose and Scope 1.1 Purpose
More informationASBESTOS/LEAD SURVEY AND CONSULTING AGREEMENT BY AND BETWEEN NEW YORK UNIVERSITY / NYU HOSPITALS CENTER - OWNER - AND - CONSULTANT - --------- PROJECT
APPENDIX A ASBESTOS/LEAD SURVEY AND CONSULTING AGREEMENT BY AND BETWEEN NEW YORK UNIVERSITY / NYU HOSPITALS CENTER - OWNER - AND - CONSULTANT - --------- PROJECT DATED AS OF ASBESTOS/LEAD SURVEY AND CONSULTING
More informationTHE UNIVERSITY OF UTAH INDEPENDENT CONTRACTOR SERVICES AGREEMENT INSTRUCTIONS
THE UNIVERSITY OF UTAH INDEPENDENT CONTRACTOR SERVICES AGREEMENT INSTRUCTIONS Contracting for Independent Contractor services with the University of Utah may require completion of the following: Employee/Independent
More informationMODEL LAW ON MOTOR VEHICLE INSPECTION BY INDEPENDENT CONTRACTORS AND SELF INSPECTORS
MODEL LAW ON MOTOR VEHICLE INSPECTION BY INDEPENDENT CONTRACTORS AND SELF INSPECTORS Section 1. Definitions.-- As used in this act, the term: (1) "Contractor" means any person, corporation, or partnership
More informationPURCHASE AGREEMENT THIS IS A LEGALLY BINDING CONTRACT BETWEEN PURCHASER AND SELLER. IF YOU DO NOT UNDERSTAND IT, SEEK LEGAL ADVICE.
PURCHASE AGREEMENT THIS IS A LEGALLY BINDING CONTRACT BETWEEN PURCHASER AND SELLER. IF YOU DO NOT UNDERSTAND IT, SEEK LEGAL ADVICE. 1. PARTIES TO CONTRACT - PROPERTY. Purchaser and Seller acknowledge that
More informationFIRST AND FINAL ADDENDUM RFP FOR ROOFING SERVICES FOR DISASTER RECOVERY ASSISTANCE
THE SCHOOL DISTRICT SHARON SWAN ARTHUR C. JOHNSON, Ph.D. OF PALM BEACH COUNTY, FLORIDA DIRECTOR SUPERINTENDENT CONSTRUCTION PURCHASING DEPARTMENT 3661 INTERSTATE PARK ROAD NORTH, SUITE 200 RIVIERA BEACH,
More informationUNIVERSITY OF CALIFORNIA, REQUEST FOR PROPOSAL # UCM1019DG
UNIVERSITY OF CALIFORNIA BERKELEY DAVIS IRVINE LOS ANGELES MERCED RIVERSIDE SAN DIEGO SAN FRANCISCO SANTA BARBARA SANTA CRUZ UNIVERSITY OF CALIFORNIA, MERCED 5200 LAKE ROAD MERCED, CALIFORNIA 95343 (209)
More informationBond Form Commentary and Comparison
Bond Form Commentary and Comparison AIA Document A310 2010, Bid Bond, and AIA Document A312 2010, Performance Bond and Payment Bond INTRODUCTION Since the first publication of The Standard Form of Bond
More informationCITY OF LANCASTER RFP NO. 621-15 LANCASTER PERFORMING ARTS CENTER TICKETING SOFTWARE SUBMISSION DEADLINE. July 24, 2015 BY 11:00 A.M.
CITY OF LANCASTER RFP NO. 621-15 LANCASTER PERFORMING ARTS CENTER TICKETING SOFTWARE SUBMISSION DEADLINE July 24, 2015 BY 11:00 A.M. SUBMIT TO: Office of the City Clerk Lancaster City Hall 44933 Fern Avenue
More informationKentucky Department of Education Version of Document A312 2010
Kentucky Department of Education Version of Document A312 2010 Performance Bond CONTRACTOR: (Name, legal status and address) SURETY: (Name, legal status and principal place of business) OWNER: (Name, legal
More informationBID BOND CITY OF EAST POINT, GEORGIA
BID BOND CITY OF EAST POINT, GEORGIA BIDDER (Name and Address): SURETY (Name and Address of Principal Place of Business): OWNER (hereinafter referred to as the City (Name and Address): City of East Point
More informationMemorandum Potentially Affected AIA Contract Documents AIA Document A105 2007 AIA Document B105 2007 Important Information
Memorandum Important information related to requirements of state or local laws to include additional provisions in residential construction contracts Potentially Affected AIA Contract Documents AIA Document
More informationAGREEMENT BETWEEN THE CITY OF BEVERLY HILLS AND VENDOR TBD FOR PURCHASE AND INSTALLATION OF AUTOMATED LICENSE PLATE RECOGNITION SYSTEMS
AGREEMENT BETWEEN THE CITY OF BEVERLY HILLS AND VENDOR TBD FOR PURCHASE AND INSTALLATION OF AUTOMATED LICENSE PLATE RECOGNITION SYSTEMS NAME OF CONTRACTOR: RESPONSIBLE PRINCIPAL OF CONTRACTOR:, Vendor
More informationCustomer: Address: Support Contact:
MaxxVault MaxxDocs Software Subscription and Support Agreement 3340 Veterans Memorial Highway Suite 400 Bohemia, NY 11716 631-446-4800 www.maxxvault.com Customer: Address: Support Contact: Effective Date:
More informationPERFORMANCE BOND INSTRUCTIONS (FEB 2015)
PERFORMANCE BOND INSTRUCTIONS (FEB 2015) 1. Introduction a. Procurement Services Division has posted two distinct performance bond forms. One is an indemnity bond. The other is a completion bond. The nature
More informationDocument Comparison. AIA Documents A134 2009 and A131CMc 2003
Document Comparison AIA Documents A134 2009 and A131CMc 2003 AIA Document A134 2009 is in the right-hand column. Corresponding sections of AIA Document A131 CMc 2003 are in the left-hand column. Sections
More informationCITY OF POMONA. Request for Qualifications and Proposals. For
CITY OF POMONA Request for Qualifications and Proposals For One-Time Assignment of Rights to Wireless Telecommunication Facilities, and Related Access Easements (Cell Tower Leases) Purchasing Specification
More informationAGREEMENT FOR INTERCONNECTION AND PARALLEL OPERATION OF DISTRIBUTED GENERATION
AGREEMENT FOR INTERCONNECTION AND PARALLEL OPERATION OF DISTRIBUTED GENERATION This Interconnection Agreement ( Agreement ) is made and entered into this day of,, by Sharyland Utilities, L.P. McAllen (
More informationPROVO CITY UTILITIES NET METERING LICENSE AGREEMENT
PROVO CITY UTILITIES NET METERING LICENSE AGREEMENT Customer-Owned Electric Generating Systems of 25kW or Less This NET METERING LICENSE AGREEMENT ( Agreement ) is between ( Customer ) and Provo City -
More informationConstruction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures.
Construction Management Contract This agreement is made by (Contractor) and (Owner) on the date written beside our signatures. Contractor City, Zip Work Phone Number: Cell Phone Number: Fax Number: Email
More informationREQUEST FOR PROPOSALS BOND COUNSEL SERVICES FOR AFFORDABLE HOUSING RFP # 16-018. Santa Ana Housing Authority
REQUEST FOR PROPOSALS BOND COUNSEL SERVICES FOR AFFORDABLE HOUSING RFP # 16-018 20 Civic Center Plaza Santa Ana, CA 92701 Judson Brown Housing Division Manager (714) 667-2241 Office JBrown@santa-ana.org
More informationAIA Document A312 - Electronic Format. Performance Bond
AIA Document A312 - Electronic Format Performance Bond THIS DOCUMENT HAS IMPORTANT LEGAL CONSEQUENCES: CONSULTATION WITH AN ATTORNEY IS ENCOURAGED WITH RESPECT TO ITS COMPLETION OR MODIFICATION. AUTHENTICATION
More informationCONSULTING SERVICES AGREEMENT
CONSULTING SERVICES AGREEMENT THIS AGREEMENT ("Agreement") is entered into on / /, between SCWOA ("Consultant"), a CA corporation with its principal place of business located at PO Box 1195, Pacifica,
More informationPURCHASE AGREEMENT. 1.0 - SELLER(S): Marital Status: Current Address: Home Phone: Work Phone: Cell Phone: Alternate Phone:
PURCHASE AGREEMENT 1.0 - SELLER(S): Marital Status: Current Address: Home Phone: Work Phone: Cell Phone: Alternate Phone: 1.1 - BUYER(S): Marital Status: Current Address: Home Phone: Work Phone: Cell Phone:
More informationFMC/City of San Jose Terms Sheet for Coleman Avenue Purchase. 1. Seller. FMC Corporation, a Delaware corporation
FMC/City of San Jose Terms Sheet for Coleman Avenue Purchase 1. Seller. FMC Corporation, a Delaware corporation 2. Buyer. City of San Jose, a municipal corporation 3. Property. The property consists of
More informationARIEL AIRPORT OWNERS AND OPERATORS LIABILITY INSURANCE
ARIEL AIRPORT OWNERS AND OPERATORS LIABILITY INSURANCE The Insurers hereby agree to the extent and in the manner hereinafter provided, to pay on behalf of the Insured all sums which the Insured shall become
More informationCOMPUTER AND INFORMATION TECHNOLOGY MANAGED SERVICES AGREEMENT
COMPUTER AND INFORMATION TECHNOLOGY MANAGED SERVICES AGREEMENT This Computer and Information Technology Services Agreement is made as of the day of, between Crown Networking Consultants, Inc. (CNC Inc.),
More informationBelow is an overview of the Molex lease process as it applies to Molex Application Tooling equipment.
Dear Valued Customer, Below is an overview of the Molex lease process as it applies to Molex Application Tooling equipment. Lease process: Molex does not offer leases for all of the equipment that we promote.
More informationIOWA LOTTERY AUTHORITY BID 16-03 Security Assessment Services
IOWA LOTTERY AUTHORITY BID 16-03 Security Assessment Services SECTION 1. OVERVIEW AND BID PROCEDURES. 1.0 Introduction and Background. The purpose of this Request for Bid is to solicit proposals from qualified
More informationHow To Manage A Power Station
CARESERV TECHNOLOGIES, LLC SERVICE AGREEMENT COLOCATION SERVICES SCHEDULE Version 2014.1 (01.01.2014) This Schedule, together with any Order referencing this Schedule or pursuant to which the services
More informationCONSULTANT AGREEMENT
Douglas County School District Re.1 Castle Rock, Colorado CONSULTANT AGREEMENT This agreement, dated effective as of is made and entered into by and between the Douglas County School District Re.1, Douglas
More informationCity of Bellevue Request for Proposal RFP #15091 Locate Ticket Management Software
City of Bellevue Request for Proposal RFP #15091 Locate Ticket Management Software RFP GENERAL INFORMATION RFP Notification: Notice is hereby given that proposals will be received by the City of Bellevue,
More informationGOODS AND SERVICES AGREEMENT BETWEEN SOUTHERN CALIFORNIA PUBLIC POWER AUTHORITY AND COMPANY/CONTRACTOR NAME
GOODS AND SERVICES AGREEMENT BETWEEN SOUTHERN CALIFORNIA PUBLIC POWER AUTHORITY AND COMPANY/CONTRACTOR NAME This GOODS AND SERVICES AGREEMENT ("Agreement") is entered into and effective [DATE], by and
More informationREQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS Security Guard Services Provider Listing for Public and/or Private Special Events at Brentwood Senior Activity Center and Brentwood Community Center Brentwood, CA February 2016 City
More informationREQUEST FOR EXPRESSIONS OF INTEREST 4887 EOI NETWORK BACKUP/EMAIL ARCHIVING
4887 EOI REQUEST FOR EXPRESSIONS OF INTEREST 4887 EOI NETWORK BACKUP/EMAIL ARCHIVING Expressions of Interest will be received at the Information Counter, Main Floor, Richmond City Hall, addressed to the
More informationNEW REQUESTS FOR PROPOSALS for INTERNET SERVICE PROVIDER SERVICES at CHARLOTTE DOUGLAS INTERNATIONAL AIRPORT for the CITY OF CHARLOTTE, NORTH CAROLINA
NEW REQUESTS FOR PROPOSALS for INTERNET SERVICE PROVIDER SERVICES at CHARLOTTE DOUGLAS INTERNATIONAL AIRPORT for the CITY OF CHARLOTTE, NORTH CAROLINA ACTIVITY (All times are EST) Dated September 20, 2013
More informationSURETY. and Title: (Any additional signatures appear on the last page of this Performance Bond.)
Performance Bond Document A312 2010 CONTRACTOR: (Name, legal status and address) SURETY: (Name, legal status and principal place of business) OWNER: (Name, legal status and address) CONSTRUCTION CONTRACT
More informationREQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS 1.0 GENERAL INFORMATION 1.1 Introduction. a. The Pennsylvania Convention Center Authority ( PCCA or the Authority ) is the entity responsible for the construction and operation of
More informationAGENT / AGENCY AGREEMENT
AGENT / AGENCY AGREEMENT This Agreement entered into this day of, 20, by and between Guardian Legal Services, Inc. (GUARDIAN), and General Agent, hereinafter called GA. GUARDIAN has organized a Legal Insurance
More informationHow To Get Construction Procurement Services
Construction Procurement William C. Charvat, AIA, CSI Excerpt from The Architect s Handbook of Professional Practice, 13th edition 2000 The procurement of construction services brings together the team
More informationThis page left blank intentionally
ATTACHMENT 13 PERFORMANCE AND PAYMENT BONDS This page left blank intentionally RFP #0606-14 Attachment 13: Payment & Performance Bonds Page 1 of 8 PAYMENT BOND (CALIFORNIA PUBLIC WORK) KNOW ALL MEN BY
More informationChase Lincoln Realty & Property Management Company 7045 Summer Place Charlotte, NC 28213 Phone: 704-921-1912, Fax: 704-921-1914
Chase Lincoln Realty & Property Management Company 7045 Summer Place Charlotte, NC 28213 Phone: 7049211912, Fax: 7049211914 EXCLUSIVE PROPERTY MANAGEMENT AGREEMENT Longterm Rental Property This Exclusive
More informationWASHINGTON SUBURBAN SANITARY COMMISSION
APPENDI B WASHINGTON SUBURBAN SANITARY COMMISSION PROCUREMENT OFFICE INSURANCE AND BONDING CONTRACT NO. 1. INSURANCE REQUIREMENTS A. INSURANCE: The Contractor shall be required to maintain insurance for
More informationTop 10 Mistakes School Districts Make When Pursuing Solar Power Projects
Top 10 Mistakes School Districts Make When Pursuing Solar Power Projects Presented by: David A. Soldani, Esq. Cerritos Fresno Irvine Pleasanton Riverside Sacramento San Diego Solar Power Transactions Here
More informationDated Tuesday, 24 March 2015
Dated Tuesday, 24 March 2015 «PROJECT_NAME» Landlord(s (1 GREEN ENERGY COMMERCIAL LTD Tenant LEASE relating to premises known as «LOCATION» and the airspace thereabove PARTICULARS PART 1 : LAND REGISTRY
More informationRequest for Proposal. Uintah High School Yearbook Publishing & Printing Services. Uintah School District 635 West 200 South Vernal Utah, 84078
Request for Proposal Uintah High School Yearbook Publishing & Printing Services Uintah School District 635 West 200 South Vernal Utah, 84078 Deadline for Submittal June 18, 2014 2:00 p.m. Uintah School
More informationCITY OF DALLAS. Request for Competitive Sealed Proposal (RFCSP) BUZ1524. For. SCADA Repair, Parts and Support
CITY OF DALLAS Request for Competitive Sealed Proposal (RFCSP) BUZ1524 For SCADA Repair, Parts and Support Purpose The purpose of this specification is to establish a thirty-six (36) month service agreement
More information28. Time is of the essence in this Lease and in each and all of its provisions.
COMMERCIAL VEHICLE/EQUIPMENT LEASE AGREEMENT Please print and fax to: 281-842-9345 Stutes Enterprise Systems, Inc. ("Lessor"), located at 1426 Sens Rd #5, LaPorte, Texas 77571, leases to, ("Lessee"), located
More informationGENERAL TERMS. 1.1 Hardware refers to the computer equipment, including components, options and spare parts.
YOU AGREE THAT BY PLACING AN ORDER THROUGH AN ORDERING DOCUMENT THAT INCORPORATES THESE GENERAL TERMS (THE ORDERING DOCUMENT ) YOU AGREE TO FOLLOW AND BE BOUND BY THE TERMS AND CONDITIONS OF THE ORDERING
More informationInvitation to Bid and Instructions to Bidders (This is Phase I of the project please note on any Bid that it Applies to Phase I only) May 1, 2015
Invitation to Bid and Instructions to Bidders (This is Phase I of the project please note on any Bid that it Applies to Phase I only) May 1, 2015 For PROJECT : Renovation and Repair of Atlanta Jewish Academy
More informationSMALL SOLAR. 2014 Nebraska Wind and Solar Conference and Exhibition. Guy C. Smith October 29, 2014
SMALL SOLAR 2014 Nebraska Wind and Solar Conference and Exhibition Guy C. Smith October 29, 2014 TYPES OF SOLAR PROJECTS Concentrated Solar Projects (CSP) Systems generate solar power using mirrors or
More informationRequest for Proposals for Upgraded or Replacement Phone System
City of Bandon Request for Proposals for Upgraded or Replacement Phone System 7/17/2015 Phone System Request for Proposal Page 1 NOTICE The City of Bandon is accepting Proposals for an upgraded or replacement
More informationColocation Master Services Vol.1.0
Colocation Master Services Vol.1.0 THIS COLOCATION MASTER SERVICE AGREEMENT ( Colo MSA or Colocation MSA ) shall apply to Service Orders or Agreements ( agreement(s), service order(s), or contract(s) )
More informationCity of Vallejo REQUEST FOR PROPOSAL WORKERS COMPENSATION CLAIMS AUDIT
City of Vallejo REQUEST FOR PROPOSAL WORKERS COMPENSATION CLAIMS AUDIT Date original issued: September 28, 2015 Qualifications Statements due: The City of Vallejo will consider Proposals submitted in response
More informationREQUEST FOR PROPOSAL
REQUEST FOR PROPOSAL General Insurance Brokerage Services Date of Issue: December 6, 2012 Closing Location:Prince Rupert, B.C. Mail or courier: Dan Rodin Chief Financial Officer City of Prince Rupert 424-3
More informationREQUEST FOR PROPOSALS
PLYMOUTH-CANTON COMMUNITY SCHOOLS REQUEST FOR PROPOSALS Assignment of Rights to Wireless Telecommunication Lease, Tower and/or Tower Management Agreement Plymouth-Canton Community Schools E.J. McClendon
More informationARTICLE 11. INSURANCE AND BONDS
Provide submittals to Architect / Engineer that are required by any governing body or other authorities. Upon receipt of the Contractor s list, the Architect will make an inspection to determine whether
More informationCENTRAL OFFICE COLOCATION SERVICES SCHEDULE
CENTRAL OFFICE COLOCATION SERVICES SCHEDULE In addition to the general terms and conditions contained in the Service Agreement between PAETEC and Customer (the Agreement ), of which this Colocation Schedule
More informationFour Seasons Property Management Inc 2334 The Plaza Charlotte, NC 28205
Four Seasons Property Management Inc 2334 The Plaza Charlotte, NC 28205 EXCLUSIVE PROPERTY MANAGEMENT AGREEMENT Long-term Rental Property This Exclusive Property Management Agreement is entered into by
More informationPROPERTY MANAGEMENT AGREEMENT
PROPERTY MANAGEMENT AGREEMENT OWNER: AGENT: PROPERTY: APN: Owner and Property Manager, as hereinafter identified, agree as follows: 1. APPOINTMENT OF AGENT: Owner hereby appoints and grants Property Manager
More informationEXPERIENTIAL EDUCATION AGREEMENT BETWEEN THE ADMINISTRATORS OF THE TULANE EDUCATIONAL FUND, THROUGH ITS COMMUNITY FOR PUBLIC SERVICE AND
EXPERIENTIAL EDUCATION AGREEMENT BETWEEN THE ADMINISTRATORS OF THE TULANE EDUCATIONAL FUND, THROUGH ITS COMMUNITY FOR PUBLIC SERVICE AND THIS EXPERIENTIAL EDUCATION AGREEMENT ( Agreement ) is made by and
More informationNew York's Real Estate Law - Requirements For the District
DATE: NOVEMBER 13, 2012 REQUEST FOR PROPOSAL RFP NUMBER: RDP12-024 RFP NAME: PROPOSALS WILL BE RECEIVED UNTIL 11:00 A.M. NOVEMBER 30, 2012 Proposal documents can be downloaded from the Long Island Bid
More informationPlanning Request for Proposal. Digitize Records for Import to Electronic Document Management System Project Number 15-079-5200
Planning Request for Proposal Digitize Records for Import to Electronic Document Management System Project Number 15-079-5200 Let Date: November 6, 2015 Bid Deadline: November 19, 2015 02:00 PM Deliver
More informationPURCHASE ORDER TERMS AND CONDITIONS
PURCHASE ORDER TERMS AND CONDITIONS 1. DEFINITIONS: In these Terms and Conditions and all documents related to the Purchase Order: Purchaser means the entity issuing the Purchase Order as identified on
More informationREQUEST FOR STATEMENT OF INTEREST AND QUALIFICATIONS (SOIQ) FOR ARCHITECTURAL SERVICES Provo City School District
Introduction: REQUEST FOR STATEMENT OF INTEREST AND QUALIFICATIONS (SOIQ) FOR ARCHITECTURAL SERVICES Provo City School District Pursuant to Utah Code Ann. 63G-6-701, it is the policy of the Provo City
More informationAgreement for Net Metering and Interconnection Services (Level 1, 2 and 3 Interconnection)
Agreement for Net Metering and Interconnection Services (Level 1, 2 and 3 Interconnection) This Agreement for Net Metering and Interconnection Services ( Agreement ) is made and entered into this day of
More informationRequest for Proposals for Enhanced Call Center Services for the San Diego Association of Governments 511 Traveler Information System
Request for Proposals for Enhanced Call Center Services for the San Diego Association of Governments 511 Traveler Information System Issued by ICx Transportation Group, Inc. on behalf of Telvent Farradyne
More informationOAKLAND USD RFP /09) ATTOR RNEY ENSATION WORKERS' COMP
OAKLAND UNIFIED SCHOOL DISTRICTT REQUEST FOR PROPOSALSS ( NO. 15-16/ /09) ATTOR RNEY SERVICES WORKERS' COMP ENSATION DEFENSEE 1 OAKLAND USD RFP (NO. 15 16/ /09) ATTORNEY SERVICES, WORKERS COMPENSATION
More informationCorona Department of Water & Power (DWP) Solar Partnership Program Guidelines and Application
Corona Department of Water & Power (DWP) Solar Partnership Program Guidelines and Application DWP s new Solar Partnership Program is available to help offset your investment in a PV system and get you
More informationREQUEST FOR QUALIFICATIONS/PROPOSALS (RFQ/P) FOR COMMERCIAL PROPERTY MANGEMENT SERVICES FOR 3737 MAIN STREET GROUND FLOOR COMMERCIAL
REQUEST FOR QUALIFICATIONS/PROPOSALS (RFQ/P) FOR COMMERCIAL PROPERTY MANGEMENT SERVICES FOR 3737 MAIN STREET GROUND FLOOR COMMERCIAL ISSUED: JUNE 21, 2016 PROPOSALS DUE: AUGUST 22, 2016 CITY OF RIVERSIDE
More informationCOUNTY OF TANEY, MISSOURI
COUNTY OF TANEY, MISSOURI REQUEST FOR BID For WORKERS COMPENSATION INSURANCE Taney County, Missouri RFB# 201202-168 Workers Compensation Insurance Release Date: February 25, 2012 Submittal Deadline: March
More informationDuring the performance of this contract, the contractor, for itself, its assignees and successors in interest agrees as follows:
CONTRACT FORM CONTRACT # This Contract, made and entered into this day of, 20, by and between the State of Nevada Department of Transportation, hereinafter called the Department, and (Contractor Name and
More informationAGREEMENT FOR FINANCIAL AND ACCOUNTING CONSULTATION SERVICES
AGREEMENT FOR FINANCIAL AND ACCOUNTING CONSULTATION SERVICES THIS AGREEMENT is made as of December 1, 2003, by and between the San Francisquito Creek Joint Powers Authority, a body corporate and politic
More informationAT: 1. Norridge Village Hall - 4000 N. Olcott Ave. and 2. Norridge Police Department - 4020 N. Olcott Ave.
Date: 03/07/2014 RFP # 2014-6 Request for Proposal for: Paper Shredding / Document Destruction Services AT: 1. Norridge Village Hall - 4000 N. Olcott Ave. and 2. Norridge Police Department - 4020 N. Olcott
More informationSAMPLE SERVICES CONTRACT
SAMPLE SERVICES CONTRACT The parties to this contract are the SAN DIEGO COUNTY WATER AUTHORITY, a county water authority, (the Water Authority) and, [a / an], having its principal place of business at
More informationTHE CORPORATION OF THE CITY OF BURLINGTON D1 - AGREEMENT
Agreement 2006 Page 1 THE CORPORATION OF THE CITY OF BURLINGTON D1 - AGREEMENT THIS AGREEMENT made in triplicate this day of 20 THE CORPORATION OF THE CITY OF BURLINGTON (hereinafter called "the City")
More informationExpedited Dispute Resolution Bond (P3 Form)
Expedited Dispute Resolution Bond (P3 Form) Bond No. KNOW ALL WHO SHALL SEE THESE PRESENTS: THAT WHEREAS, (the "Owner") has awarded to (the "Obligee"), a Public-Private Agreement (the PPA ) for a project
More informationNet Energy Metering Southern California Edison
NET ENERGY METERING To encourage small electrical customers to install environmentally friendly sources of electrical power, the State of California has passed laws to make the process of interconnecting
More informationAIA Document A312 TM 1984
Performance Bond AIA Document A312 TM 1984 CONTRACTOR (Name and Address): H. B. Barnard, General Corporation 53 West Jackson Boulevard Suite 235 OWNER (Name and Address): The Chicago Society of Alpha Delta
More informationAmendment and Consent No. 2 (Morris County Renewable Energy Program, Series 2011)
Execution Version Amendment and Consent No. 2 (Morris County Renewable Energy Program, Series 2011) by and among MORRIS COUNTY IMPROVEMENT AUTHORITY, COUNTY OF MORRIS, NEW JERSEY, U.S. BANK NATIONAL ASSOCIATION
More informationPerformance Bond. Business):
Performance Bond CONTRACTOR (Name and Address): (Name and Address of Principal Place of Business): OWNER (Name and Address): City of Cedar Rapids City Clerk, 101 First Street SE Cedar Rapids, IA 52401
More informationUTAH COUNTY REQUEST FOR PROPOSALS FOR HEALTH AND LIFE INSURANCE BROKER
UTAH COUNTY REQUEST FOR PROPOSALS FOR HEALTH AND LIFE INSURANCE BROKER SECTION 1 ADMINISTRATIVE OVERVIEW 1.1 PURPOSE Utah County is soliciting proposals from insurance brokers/consultants qualified to
More informationAgent Agreement WITNESSETH
PATRIOT NATIONAL UNDERWRITERS, INC. Agent Agreement THIS AGENT AGREEMENT (the Agreement ) is made and entered into by and between Patriot National Underwriters, Inc., a Texas corporation ( Patriot ), and
More informationPROFESSIONAL/CONSULTING SERVICES AGREEMENT
This SERVICES AGREEMENT ( Agreement ) is entered into by and between the undersigned, ( Contractor ), (Social Security Number or Federal I.D. No.), located at and Texas Southern University ( TSU ), an
More informationREQUEST FOR PROPOSAL ENERGY MANAGEMENT SERVICES REQUEST FOR PROPOSAL FOR RENEWABLE ENERGY SYSTEM IN THE TOWN OF NORWELL
REQUEST FOR PROPOSAL ENERGY MANAGEMENT SERVICES REQUEST FOR PROPOSAL FOR RENEWABLE ENERGY SYSTEM IN THE TOWN OF NORWELL Awarding Authority: TOWN OF NORWELL Address: 345 MAIN STREET, P.O. BOX 295, NORWELL,
More informationSTANDARD FORM OF AGREEMENT BETWEEN OWNER AND DESIGN- BUILDER - LUMP SUM
DC STANDARD FORM OF AGREEMENT BETWEEN OWNER AND DESIGN- BUILDER - LUMP SUM Document No. 525 Second Edition, 2010 Design-Build Institute of America Washington, Design-Build Institute of America - Contract
More informationDepartment of Purchasing & Contract Compliance
Department of Purchasing & Contract Compliance Felicia Strong-Whitaker, Purchasing Director REQUEST FOR E-QUOTE NUMBER: 15RD99627B PROJECT TITLE: Barracuda Web App Firewall 460Vx Support and Licenses Information
More information