The 2011 MDB Harmonized Major Works (Construction) Contract Conference. Session 3 Employer s and Contractor s Issues
|
|
|
- Arthur Burke
- 9 years ago
- Views:
Transcription
1 The 2011 MDB Harmonized Major Works (Construction) Contract Conference Renaissance Brussels Hotel, Brussels, Belgium; January 2011 Session 3 Employer s and Contractor s Issues Pieter G.A. de Bruijn Ballast Nedam : Contracts and Legal Department Head of Contracts EIC: Working Group Africa ; member
2 Introduction Purpose Identify and try to create awaraness of a set of Contractor s Issues that arise in day to day practice of the administration of a FIDIC (MDB) Contract based on experience with a number of financed FIDIC and EDF contracts Address the common interest between MDB s, Employers, Engineers and Contractors to resolve the issue Propose improvements and positive response by the MDB s 2
3 Recurring Contractor s issues Based on the inevitability of scope creep which seems to happen often but especially if the Contract is entered into too early. Contractor s Issues are presented by way of a brief discussion between a Contractor who is a bit of a cynic and a FIDIC Expert who is very knowledgeable. 3
4 Issue 1 The dependance on the determinations role of the Engineer The Contractor-cynic notes that it is a contractual fact of life that Clauses crucial for Contractor are based on the principle that the Engineer..makes fair determinations.. (Clause 3.5) (note 3.5 already greatly improved in the MDB form)..fairly determines.. (Clause 14.6 / 14.13) etc has a critical role in measurement (Cl 12), payment (Cl 14), taking over (Cl10) which leads to Contractor s Issue 1 Contractor is too much dependant on the fairness of the Engineer. Positie voor foto s, etc. 4
5 Issue 1 The dependance on the determinations role of the Engineer The FIDIC experts counter question is: Why is that a Contractor s Issue? He can negotiate with a professional Engineer who is fair and reasonable can t he? (refer eg to Mr Robert Gaitskell s presentation FIDIC User s Conference December 1-2, 2010) 5
6 Issue 2 Employer s procurement of the services of such Engineer The Contractor cynic s reply is... well no., in the world outside the reality is as follows: Engineer s fairness is subjective. Judgement whether such fairness was used is not by Contractor neither by Employer but ultimately by a legal institution. Meanwhile, during ongoing discusisons, Contractor has to continue to comply with his obligations while he waits for his money. which leads to Contractor s Issue 2 Contractor is too dependant on the quality of the services by the Engineer and therefore Employer s procurement of the services of such Engineer 6
7 Impression of procurement of services of an Engineer 7
8 Issue 2 Employer s procurement of the services of such Engineer The FIDIC experts counter question is: Are you not exagerating? and in case the Engineer is unreasonable or not fair in his determinations, surely can Contractor not invoke Clause 16.1 Suspension (or termination) by Contractor? 8
9 Issue 3: Contractor s remedy in case of unfair / unreasonable determinations The Contractor replies... well no., in the world outside it is as follows:..as long as.. - the Engineer issues an Interim Payment Certificate in time (regardless of the fairness of the content) - the Employer pays that amount in time (regardless the fairness of the amount), Clause 16.1 cannot be invoked and is of no practical use as instrument which is Contractor s Issue 3: 9
10 Issue 3: Contractor s remedy in case of unfair / unreasonable determinations The FIDIC expert asks: Well that s still not a Contractor s problem is it? Once a dispute has arisen under a MDB Contract, the Contractor can seek interim relief and refer the issue to the Dispute Board as per Clause 20.4 can t he? 10
11 Issue 4 The DB as instrument for interim relief The Contractor s reply is. well no., in the world outside the reality is as follows: reality 1 reality 2 reality 3 DB boards are frequently written out of the Contract or amended by the Employer and.if that hasn t been done.. The way the DB clause are drafted and recent legal cases lead to conclusion that DB decisions may very well not be enforceable and if they would be.. it takes a very long time to enforce them. (refer eg to Christofer Seppälä s presentation FIDIC User s Conference December 1-2, 2010) which leads to Contractor s Issue 4 11
12 Issue 4 Which interim relief options does Contractor have in case of a dispute? Contractor s Issue 4 Contractor can often not rely on a DB decision as interim relief and is left with 2 options: 1. Enter into an arbitration as per Clause 20.6 which implies waiting for financial relief during probably long lasting litigation period OR 2. Accept financial settlement earlier but at less favourable terms to Contractor which is why Contractor may inflate his claim as he knows it will ultimately be settled at less. 12
13 Summary The cynic concludes that the Contractor s Issues mentioned above will inevitably lead to: Inflated claims by Contractor, Value leakage for all parties and a strained relationship between the Parties and the Engineer. Are there ways to improve things? 13
14 Proposed improvements early MDB involvement. Two proposals, both related to early MDB involvement. Proposal 1 - Recognize the importance of real fairness under e.g. Clause 3.5 and MDB involvement in re-thinking / imposing the way of procurement services of the FIDIC Engineer by the Employer e.g. by introducing key performance criteria FIDIC Engineer based on track record, capabilities, behaviors, etc. - MDB involvement in auditing the governance process during construction. 14
15 Proposed improvements early MDB involvement. Proposal 2 Ensure access for the Parties to a DB procedure with brief decision periods which provides interim relief pending any arbitration on the merits. Obligatory inclusion of DB board procedure with ensured enforceability of DB s decision irrespective of the jurisdiction (imposed by the MDB in the Financing Conditions applicable to the Loan Agreement). 15
16 CONCLUSION For proper working of construction project under a MDB Contract an equal playing field / a certain balance (of instruments) is preferable and it is in the interest of Contractor but also of MDB and Employer that parties can rely on (i) a governance process which enables negotiation in an equal and disciplined form (ii) access to Dispute Board with brief decision periods and decisions which are enforceable (iii) (appointment of) an Engineer with appropriate measurable level of professionalism 16
17 CONCLUSION The MDB environment provides a chance for improvement. The merits of the two proposals will have a positive effect for both Contractor and Employer. Note: Even being a cynic, the Contractor is of the opinion that the MDB Harmonised Edition 2010 is as good as it gets and expresses the hope that other funding agents (e.g. the EC) will consider to adopt this form as their standard form of contract as well. 17
18 CONCLUSION Thank you for the opportunity to present this 18
Developments and Challenges of DAB Procedures Enforcement of a DAB s Decision
Developments and Challenges of DAB Procedures Enforcement of a DAB s Decision By Dr. ImadAl Jamal 1. The decision of a Dispute Adjudication Board ( DAB ) becomes a contract obligation by virtue of Sub-Clause
MEDIATION PROCEDURES FOR RESOLVING BUSINESS-TO-BUSINESS DISPUTES
6465 Wayzata Blvd., Suite 470 Minneapolis, MN 55426 Phone: 800-474-2371 Fax: 952-345-1160 www.adrforum.com MEDIATION PROCEDURES FOR RESOLVING BUSINESS-TO-BUSINESS DISPUTES July 11, 2014 1 FORUM Request
Customer Responsiveness Strategy
Customer Responsiveness Strategy Dated 23 June 2006. Telstra Corporation Limited (ABN 33 051 775 556) ( Telstra ) Disclaimer This Customer Responsiveness Strategy is being published in furtherance of Telstra
Risks in International Consultancy Appointments: The FIDIC White Book
Risks in International Consultancy Appointments: The FIDIC White Book An increasing number of UK based consultants are involved in international projects. Given the forecasted growth in global construction
19:13-2.1 Who may file
CHAPTER 13 SCOPE OF NEGOTIATIONS PROCEEDINGS Authority N.J.S.A. 34:13A-5.4d, 34:13A-11 and 34:13A-27. SOURCE AND EFFECTIVE DATE R.2011 d.238, effective August 11, 2011. See: 43 N.J.R. 1189(a), 43 N.J.R.
Managing Payment Risks on International Construction Projects
Managing Payment Risks on International Construction Projects January 23, 2006 (The following outline was used in a presentation to the Overseas Construction Association of Japan, Inc. (OCAJI) on July
15-213. Procurement practices of school districts and charter schools; definitions
ARIZONA AUTHORITY 15-213. Procurement practices of school districts and charter schools; definitions A. The state board of education shall adopt rules prescribing procurement practices for all school districts
The FIDIC Suite of Contracts
Less well know FIDIC contracts are also available such as the Turquoise Book for Dredging and Reclamation Works published in January 2006 and the White Book model services agreement published in October
APPENDIX A that is not acceptable. Arbitration settled by arbitration arbitration shall be held in New Jersey substantive law of New Jersey
APPENDIX A The attorneys in the Office of University Counsel at the University of Colorado Denver Anschutz Medical Campus review many different types of contracts on behalf of the University. Legal review
FUNDING AGREEMENT GENERAL TERMS
1. Appointment FUNDING AGREEMENT GENERAL TERMS 1.1. In consideration of the Foundation agreeing to make the Grant to the Recipient, the Recipient: 2. Term a) appoints the Foundation as [a/the] [major/exclusive]
Section 1. Objective and Scope
TEXTUAL PROPOSAL DISPUTE SETTLEMENT General Notes: 1. Articles are numbered from 1 for ease of reading, especially when an Article cross-refers to another provision of the Dispute Settlement chapter. The
Dispute Resolution. White Paper. This document on Dispute Resolution outlines the four main approaches to resolving contractual disputes.
White Paper Dispute Resolution This document on Dispute Resolution outlines the four main approaches to resolving contractual disputes. CIPS members can record one CPD hour for reading a CIPS Knowledge
Dispute Board Manual
Dispute Board Manual March 2012 Japan International Cooperation Agency version 1.0 DISPUTE BOARD MANUAL Table of Contents Acknowledgement Preface 1. Introduction... 1 2. Brief explanation of Dispute Board
Sample Arbitration Clauses with Comments
Sample Arbitration Clauses with Comments BRIEF DESCRIPTION Arbitrations are creatures of contract. Thus, the parties can shape an arbitration proceeding to a great extent in their arbitration agreements.
Measured development Construction and Engineering Training Supplement Guide
Construction and Engineering Training Supplement Guide Welcome Eversheds is the law firm behind some of the world s most ambitious construction and engineering projects. We have one of the biggest teams
Banking & Finance Terms of Reference
Banking & Finance Terms of Reference These Terms of Reference apply to those members of the Financial Ombudsman Service Limited who have been designated as having the Banking & Finance Terms of Reference
LEGAL SCHEME REGULATIONS
LEGAL SCHEME REGULATIONS These Regulations came into force on 1 July 2014. 1 Introduction 1.1 These Regulations govern the Union s legal Scheme. The Rules of the Union set out your other rights and entitlements.
Ukraine. Taras Dumych. Wolf Theiss Kiev. [email protected] Law firm bio. Olena Kravtsova. Wolf Theiss Kiev
Ukraine Taras Dumych Wolf Theiss Kiev [email protected] Law firm bio Olena Kravtsova Wolf Theiss Kiev [email protected] Law firm bio 1. What are the current challenges to enforcement
DEBT RECOVERY IN BELGIUM Law Firm Van Dievoet, Jegers, Van der Mosen & Partners
Error!Marcador no definido.introduction The implementation of Directive 2000/35/EC of the European Parliament and of the Council of June 29, 2000 into Belgian law The European directive had to be implemented
Guidelines for Parenting Coordination FOREWORD
BC PARENTING COORDINATORS ROSTER SOCIETY Guidelines for Parenting Coordination FOREWORD These Guidelines for Parenting Coordination in British Columbia ( Guidelines") have been developed from the Guidelines
Draft Model Social Infrastructure PPP Bill
Draft Model Social Infrastructure PPP Bill RELATING TO PUBLIC-PRIVATE AGREEMENTS FOR PUBLIC BUILDINGS BE IT ENACTED BY THE LEGISLATURE OF THE STATE OF [add state name]: SECTION. The Legislature makes the
ISTANBUL ARBITRATION CENTRE ARBITRATION RULES
ISTANBUL ARBITRATION CENTRE ARBITRATION RULES Section I INTRODUCTORY PROVISIONS ARTICLE 1 The Istanbul Arbitration Centre and the Board of Arbitration 1. The Istanbul Arbitration Centre is an independent
Conditional Fee Agreement (CFA)
Conditional Fee Agreement (CFA) This agreement is a binding legal contract between you and your solicitor/s. Before you sign, please read everything carefully. This agreement must be read in conjunction
IBA Guide on Shareholders Agreements
IBA Guide on Shareholders Agreements South Africa Edward Nathan Sonnenbergs Inc 1. Are shareholders agreements frequent in South Africa? Shareholders agreements are widely used in South Africa. The use
RULE 63 DIVORCE AND FAMILY LAW
RULE 63 DIVORCE AND FAMILY LAW Definitions (1) In this rule, Application claim for relief includes a child support order, a spousal support order, a custody order, a property order, and corollary relief
TEMPLE LITIGATION ADVANTAGE INSURANCE FOR DISBURSEMENTS AND OPPONENT S COSTS Certificate of Insurance
TEMPLE LITIGATION ADVANTAGE INSURANCE FOR DISBURSEMENTS AND OPPONENT S COSTS Certificate of Insurance In return for the payment of the Premium specified in the Schedule and based on any Information that
CONTRACT FOR CONSULTING SERVICES SMALL ASSIGNMENTS LUMP-SUM PAYMENTS (INTER-AMERICAN DEVELOPMENT BANK/ANY FUND ADMINISTERED BY THE BANK FINANCED)
1 CONTRACT FOR CONSULTING SERVICES SMALL ASSIGNMENTS LUMP-SUM PAYMENTS (INTER-AMERICAN DEVELOPMENT BANK/ANY FUND ADMINISTERED BY THE BANK FINANCED) CONTRACT THIS CONTRACT ( Contract ) is entered into this
IN FIDIC 99 RED BOOK COULD IT BE SUPERVISION CONSTRUCTION. Dr. Munther M. Saket. The Role of the Engineer
THE ROLE OF THE ENGINEER IN FIDIC 99 RED BOOK COULD IT BE PERFORMED BY A SUPERVISION CONSULTANT & A CONSTRUCTION MANAGER? Dr. Munther M. Saket December 2010 The Role of the Engineer 1 The ENGINEER S ROLE
Anglo American Procurement Solutions Site
Anglo American Procurement Solutions Site Event Terms and Conditions Anglo American Procurement Solutions Site Event Terms and Conditions Event Terms and Conditions 3 1. Defined terms 3 2. Interpretation
Appendix 18 NEC3 Options
Appendix 18 NEC3 Options December 2007 Page 449 Appendix 18 NEC3 Options NEC3 Main Options There are six main options as set out below. The Contractor carries the greatest risk under options A and B, and
OCTOBER 7, 2015 SMALL BUSINESS ADVISORY REVIEW PANEL FOR POTENTIAL RULEMAKING ON ARBITRATION AGREEMENTS
OCTOBER 7, 2015 SMALL BUSINESS ADVISORY REVIEW PANEL FOR POTENTIAL RULEMAKING ON ARBITRATION AGREEMENTS DISCUSSION ISSUES FOR SMALL ENTITY REPRESENTATIVES To help frame discussion of issues and cost of
CIVIL LITIGATION ASSISTANCE SCHEME CONDITIONS OF ASSISTANCE
APPLICATION CIVIL LITIGATION ASSISTANCE SCHEME CONDITIONS OF ASSISTANCE 1. Applications for funding under the Civil Litigation Assistance Scheme can only be submitted through a private legal practitioner
Briefing document: Understanding the Royal Institute of British Architects (RIBA) Building Contracts. 5 November 2014
Briefing document: Understanding the Royal Institute of British Architects (RIBA) Building Contracts 5 vember 2014 Table of Contents Part 1 Introduction Part 2 Why new contracts? The reason for the publication
CONTRACTING HINTS AND TIPS
CONTRACTING HINTS AND TIPS Contents 1. Contract formation 2. Entire agreement clauses 3. Warranties and indemnities 4. Time of the essence 5. Contract variation 6. Exclusion and limitation clauses 7. Exercising
THE FOLLOWING ARE INSTRUCTIONS FROM THE FRONT SIDE OF SEAGATE PURCHASE ORDERS:
THE FOLLOWING ARE INSTRUCTIONS FROM THE FRONT SIDE OF SEAGATE PURCHASE ORDERS: INSTRUCTIONS: Read this entire order form, including the incorporated terms and conditions located at http://www.seagate.com/about/legal-privacy/purchasing-and-pricing/purchase-orders-legal-overview/
AE RISK REVIEW A PUBLICATION FOR DESIGN PROFESSIONALS YOUR RISK MANAGEMENT CONNECTION. Prevailing Opinions on Prevailing Party Contract Clauses
AE RISK REVIEW A PUBLICATION FOR DESIGN PROFESSIONALS YOUR RISK MANAGEMENT CONNECTION This material is provided for informational purposes only. Before taking any action that could have legal or other
PERMANENT COURT OF ARBITRATION OPTIONAL RULES FOR ARBITRATING DISPUTES BETWEEN TWO STATES
PERMANENT COURT OF ARBITRATION OPTIONAL RULES FOR ARBITRATING DISPUTES BETWEEN TWO STATES 39 OPTIONAL ARBITRATION RULES TWO STATES CONTENTS Introduction 43 Section I. Introductory Rules 45 Scope of Application
Payment Processing Agreement
Payment Processing Agreement Dated 2015 Cabcharge Australia Ltd. ( Cabcharge ( Payment Processor Payment Processing Agreement Details 3 General terms 4 1 Access to and use of the System 4 1.1 Access to
DRAFT Version 1.2 Revision Date: 16/7/10
LOCAL AUTHORITY SEARCH REPORT INSURANCE POLICY 1. Policy Issuer: Stanley Davis Group Limited trading as York Place Policy Number: SDGLA0001 Definitions In this policy unless the context otherwise requires:
PROPERTY MANAGEMENT AGREEMENT
PROPERTY MANAGEMENT AGREEMENT OWNER: AGENT: PROPERTY: APN: Owner and Property Manager, as hereinafter identified, agree as follows: 1. APPOINTMENT OF AGENT: Owner hereby appoints and grants Property Manager
Jurisdiction. Egypt.
Jurisdiction Egypt. Arbitration legislation Egypt conceded to the Convention on the Recognition and Enforcement of Foreign Arbitral Awards ( New York Convention ) on 2nd of February 1959, ratified it on
Christopher Noble, Negotiating Owner-Architect Agreements: Theory and Practice (revised February 2011)
Christopher Noble, Negotiating Owner-Architect Agreements: Theory and Practice (revised February 2011) Construction projects are usually complex undertakings with numerous participants, linked by a web
SPECIAL CONDITIONS PART A SPECIFIC CONDITIONS OF CONTRACT
Ministry of Education Page 1 of 5 SPECIAL CONDITIONS PART A SPECIFIC CONDITIONS OF CONTRACT Clause references below refer to clauses in the General Conditions of Contract for Consultancy Services August
SCHEDULE 13 DISPUTE RESOLUTION PROCEDURE. In this Schedule, in addition to the definitions set out in Section 1.1 of the Agreement:
SCHEDULE 13 DISPUTE RESOLUTION PROCEDURE 1. INTERPRETATION 1.1 Definitions In this Schedule, in addition to the definitions set out in Section 1.1 of the Agreement: "Dispute" means any disagreement, failure
CHAPTER 11 APPEALS AND DISPUTES
CHAPTER 11 APPEALS AND DISPUTES In this Chapter look for... 11. General 11.1 Deleted 11.2 Administrative Appeals 11.3 Disputes 11.4 Alternative Dispute Resolution (ADR) 11. General. The Virginia Public
Alternative Dispute Resolution (ADR) Procedures
Alternative Dispute Resolution (ADR) Procedures The background Traditional dispute resolution procedures Private Negotiation 1. A lost skill, negotiation is a process of the parties themselves or via skilled
Appendix A8.1: Service Level Agreement Contents
Appendix A8.1: Service Level Agreement Contents 11/03/2010 This section provides a practical guide to the preparation and use of Service Level Agreements (SLAs) in the context of shared services. It will
California Solar Initiative (CSI) Program 2007 Reservation Request Form and Program Contract [follows the second page Reservation Request form]
California Solar Initiative (CSI) Program 2007 Reservation Request Form and Program Contract [follows the second page Reservation Request form] CSI CONTRACT TERMS AND CONDITIONS This California Solar Initiative
TEXTURA AUSTRALASIA PTY LTD ACN 160 777 088 ( Textura ) CONSTRUCTION PAYMENT MANAGEMENT SYSTEM TERMS AND CONDITIONS OF USE
TEXTURA AUSTRALASIA PTY LTD ACN 160 777 088 ( Textura ) CONSTRUCTION PAYMENT MANAGEMENT SYSTEM TERMS AND CONDITIONS OF USE Welcome to the Textura Construction Payment Management ( CPM ) System. By clicking
inform practice note SUBCONTRACTING ARRANGEMENTS Content Synopsis: Practice Note # 7 May 2007 (Version 1 - May 2007) construction industry development
construction industry development inform practice note Issued by the Construction Industry Development Board Development through partnership construction procurement and delivery SUBCONTRACTING ARRANGEMENTS
Indemnification Clauses, Part 1* Discussion from a/e ProNet's Risk Management and Contract Guide. J. Kent Holland, Jr., Esq.
Indemnification Clauses, Part 1* Discussion from a/e ProNet's Risk Management and Contract Guide J. Kent Holland, Jr., Esq. Issue: Indemnification provisions in contracts may require the design professional
Common traps people fall into when renting commercial property ( and how to avoid them)
Common traps people fall into when renting commercial property ( and how to avoid them) For most businesses, the renting of a commercial property represents a major financial decision. Whether you are
TEXAS ASSOCIATION OF REALTORS INDEPENDENT CONTRACTOR AGREEMENT FOR SALES ASSOCIATE. Robyn Jones Homes, LLC
1 TEXAS ASSOCIATION OF REALTORS INDEPENDENT CONTRACTOR AGREEMENT FOR SALES ASSOCIATE USE OF THIS FORM BY PERSONS WHO ARE NOT MEMBERS OF THE TEXAS ASSOCIATION OF REALTORS IS NOT AUTHORIZED Texas Association
SUBMISSIONS TO THE PORTFOLIO COMMITTEE ON TRADE & INDUSTRY ON THE PROMOTION AND PROTECTION OF INVESTMENT BILL, 2015
SUBMISSIONS TO THE PORTFOLIO COMMITTEE ON TRADE & INDUSTRY ON THE PROMOTION AND PROTECTION OF INVESTMENT BILL, 2015 ANGLO AMERICAN SOUTH AFRICA LIMITED 15 September 2015 ABOUT ANGLO AMERICAN SOUTH AFRICA
Transfers of undertakings an introduction
Transfers of undertakings an introduction January 2014 The law relating to transfers of undertakings is notoriously complex and is constantly developing. Inevitably, this account can only be an introduction,
COALITION PROVISIONAL AUTHORITY ORDER NUMBER 87 PUBLIC CONTRACTS
COALITION PROVISIONAL AUTHORITY ORDER NUMBER 87 PUBLIC CONTRACTS Pursuant to my authority as Administrator of the Coalition Provisional Authority (CPA), and under the laws and usages of war, and consistent
Checklist: Cloud Computing Agreement
Checklist: Cloud Computing Agreement crosslaw s checklists Date : 21 November 2015 Version 1.4 Tags : ICT Law Johan Vandendriessche Johan is partner and heads the ICT/IP/Data Protection practice. He combines
NATIONAL INSURANCE BROKERS ASSOCIATION OF AUSTRALIA (NIBA) Submission to WorkCover Western Australia. Legislative Review 2013
NATIONAL INSURANCE BROKERS ASSOCIATION OF AUSTRALIA (NIBA) ABOUT NIBA Submission to WorkCover Western Australia Legislative Review 2013 February 2014 NIBA is the peak body of the insurance broking profession
Construction Claims in
Construction Claims in the Gulf ICES CPD Event 12/2012 ADMC Auditorium 19 December 2012 DISPUTES & INVESTIGATIONS ECONOMICS FINANCIAL ADVISORY MANAGEMENT CONSULTING Context» Aftermath of 2008 / 2009 financial
Best Practice Guide Effective dispute resolution
Best Practice Guide Effective dispute resolution 01 Work & family 02 Consultation & cooperation in the workplace 03 Use of individual flexibility arrangements 04 A guide for young workers 05 An employer
CLIENT / PROJECT MANAGER AGREEMENT
Authorship of this work is claimed by The Association of Construction Project Managers and any unauthorised reproduction constitutes an infringement in terms of the Copyright Act No 98 of 1978. CLIENT
CONTRACT MANAGEMENT FRAMEWORK
CONTRACT MANAGEMENT FRAMEWORK August 2010 Page 1 of 20 Table of contents 1 Introduction to the CMF... 3 1.1 Purpose and scope of the CMF... 3 1.2 Importance of contract management... 4 1.3 Managing contracts...
Resolving IP and Technology Disputes Through WIPO ADR. Getting back to business
Resolving IP and Technology Disputes Through WIPO ADR Getting back to business Intellectual property (IP) is a central component of today s knowledge economy, and its efficient exploitation is of growing
4. A tribunal constituted under this Section may not decide claims that fall outside of the scope of this Article.
Section 6: Investor-State Dispute Settlement Article X.17: Scope of a Claim to Arbitration 1. Without prejudice to the rights and obligations of the Parties under Chapter [XY](Dispute Settlement), an investor
Venezuela. Carlos Dominguez Hernandez and Yulena Sanchez-Hoet. Hoet Pelaez Castillo & Duque. Litigation 1 Court system
Carlos Dominguez Hernandez and Yulena Sanchez-Hoet Hoet Pelaez Castillo & Duque Litigation 1 Court system What is the structure of the civil court system? The general structure of s judicial system and
60 Day Expert Determination Structured to Meet the Commercial Expectations of Business Management
60 Day Expert Determination Structured to Meet the Commercial Expectations of Business Management By Charles O Neil FCIArb and Dr. Michael Hammes Published in Arbitration Journal April 2011 (Chartered
Outlines matters to be discussed when entering a shareholders agreement.
This information leaflet gives you introductory guidance to shareholders agreements. It does not however give you legal advice. If you need legal advice please contact Kay Waddington in our Corporate department
MEMORANDUM ON OFFERS TO SETTLE. 1. What is an Offer to Settle? 2. Why Make an Offer to Settle? 3. How Can it Help to Make an Offer to Settle?
MEMORANDUM ON OFFERS TO SETTLE 1. What is an Offer to Settle? 2. Why Make an Offer to Settle? 3. How Can it Help to Make an Offer to Settle? The purpose of this memorandum is to assist you in understanding
AND REDUNDANCY. Summary of the law on
Summary of the law on UNFAIR DISMISSAL AND REDUNDANCY Workers are protected under the Employment Rights Act 1996 from being sacked or chosen unfairly for redundancy. This booklet provides a basic outline
IMF (Australia) Ltd. Combined Financial Services Guide and Product Disclosure Statement
IMF (Australia) Ltd Combined Financial Services Guide and Product Disclosure Statement Dated the 18th day of January 2010 FINANCIAL SERVICES GUIDE & PRODUCT DISCLOSURE STATEMENT PAGE 2 1. Introduction
BEPS ACTION 14: MAKE DISPUTE RESOLUTION MECHANISMS MORE EFFECTIVE
Public Discussion Draft BEPS ACTION 14: MAKE DISPUTE RESOLUTION MECHANISMS MORE EFFECTIVE 18 December 2014 16 January 2015 PROPOSED DISCUSSION DRAFT ON ACTION 14: MAKE DISPUTE RESOLUTION MECHANISMS MORE
Asset Protection Agreement Templates - Customer Explanatory Notes. Explanatory Notes on Asset Protection Agreement
Asset Protection Agreement Templates - Customer Explanatory Notes Explanatory Notes on Asset Protection Agreement Clause Heading Background The Asset Protection Agreement is intended for use where the
(1) risks should be allocated to the party that is in the position to control them and
Risk allocation in the FIDIC Conditions of Contract (1999) for Construction (Red Book) and the FIDIC Conditions of Contract (1999) for EPC/Turnkey Projects (Silver Book) from the perspective of a German
PENNSYLVANIA BUILDERS ASSOCIATION INSTRUCTIONS TO HOME IMPROVEMENT MODEL CONTRACT STANDARD FORM Introduction
PENNSYLVANIA BUILDERS ASSOCIATION INSTRUCTIONS TO HOME IMPROVEMENT MODEL CONTRACT STANDARD FORM Introduction Below are instructions for use with the Home Improvement Model Contract Standard Form, which
September 2008. Claims Guideline
September 2008 Claims Guideline CLAIMS GUIDELINE Table of Contents 1 INTRODUCTION... 1 2 PURPOSE OF THE GUIDELINE... 1 3 DEFINITIONS... 2 MARKET CONDUCT 4 GENERAL REQUIREMENTS... 3 5 CLAIMS NOTIFICATION...
CONTRACTUAL CHANGES CONTROL VALUE AND MANAGE RISKS
1 (1) CONTRACTUAL CHANGES CONTROL VALUE AND MANAGE RISKS ANETTE KAVALEFF [OY KAVALEFF CONSULTING AB] KATJA KOSKELAINEN MARJAANA KOUSA [RASTOR OY] 1. ABSTRACT Changes during a project are more of a rule
An organization which employs, or is about to employ, any of the above, has a financial or other interest in the firm selected for award.
85.36 Procurement (a) States. When procuring property and services under a grant, a State will follow the same policies and procedures it uses for procurements from its non-federal funds. The State will
HERALD INVESTMENT MANAGEMENT LIMITED
HERALD INVESTMENT MANAGEMENT LIMITED Registered Office: 10/11 CHARTERHOUSE SQUARE LONDON EC1M 6EE Tel: 020 7553 6300 Fax: 020 7490 8026 E-mail: [email protected] Website:www.heralduk.com IRREVOCABLE UNDERTAKING
THE POLICY. 2003-2013 MYNIC BERHAD. All rights reserved.
MYNIC'S (.my) DOMAIN NAME DISPUTE RESOLUTION POLICY THE POLICY 2003-2013 MYNIC BERHAD. All rights reserved. MYNIC's (.my) Domain Name Dispute Resolution Policy THE POLICY 1. Purpose 1.1 MYNIC's (.my) Domain
Loan regulations (Adopted by the Administrative Council by Resolution 1562, on 14 November 2013)
Loan regulations (Adopted by the Administrative Council by Resolution 1562, on 14 November 2013) Edition updated in November 2014 CHAPTER 1 Object of the Loan Regulations ARTICLE 1.1 Object of the Loan
CONTRACT MANAGEMENT POLICY POLICY ADOPTED BY COUNCIL ON???? AT ITEM C.????
CONTRACT MANAGEMENT POLICY POLICY ADOPTED BY COUNCIL ON???? AT ITEM C.???? 1 1. PRE-AMBLE All transactions undertaken by the Cape Winelands District Municipality involves a contract whether explicitly
PCA - Contract Interpretation Manual (Nurses Bargaining Association) Revised 2006
- Grievances Related Articles: 6.04, 6.05, 6.08, 6.09, 8.05, 10, 15.04, 16.02 (C), 32.06 Interpretation Guidelines:.01 - Discussion of Differences This clause sets out the work now, grieve later rule.
BUSINESS OCR LEVEL 3 CAMBRIDGE TECHNICAL. Cambridge TECHNICALS ASPECTS OF CONTRACT AND BUSINESS LAW CERTIFICATE/DIPLOMA IN F/502/5452 LEVEL 3 UNIT 16
Cambridge TECHNICALS OCR LEVEL 3 CAMBRIDGE TECHNICAL CERTIFICATE/DIPLOMA IN BUSINESS ASPECTS OF CONTRACT AND BUSINESS LAW F/502/5452 LEVEL 3 UNIT 16 GUIDED LEARNING HOURS: 60 UNIT CREDIT VALUE: 10 ASPECTS
Data Breach Response Basic Principles Under U.S. State and Federal Law. ABA Litigation Section Core Knowledge January 2015 1
Data Breach Response Basic Principles Under U.S. State and Federal Law ABA Litigation Section Core Knowledge January 2015 1 I. Introduction Data breaches have become an unfortunate reality for many of
Accounting and Related Services Arbitration Rules and Mediation Procedures
Accounting and Related Services Arbitration Rules and Mediation Procedures Rules Amended and Effective February 1, 2015 Available online at adr.org/accounting Table of Contents Introduction.... 6 Standard
INTERNATIONAL CENTRE FOR SETTLEMENT OF INVESTMENT DISPUTES (ICSID Case No. ARB(AF)/12/1) (1) APOTEX HOLDINGS INC. (2) APOTEX INC.
INTERNATIONAL CENTRE FOR SETTLEMENT OF INVESTMENT DISPUTES (ICSID Case No. ARB(AF)/12/1) (1) APOTEX HOLDINGS INC. (2) APOTEX INC. v. Claimants THE UNITED STATES OF AMERICA Respondent PROCEDURAL ORDER ON
Cloud Computing. Patrick Van Eecke. Partner, DLA Piper Brussels Professor Universiteit Antwerpen
Cloud Computing Legal issues Patrick Van Eecke Partner, DLA Piper Brussels Professor Universiteit Antwerpen Cloud computing & the law Infrastructure as a Service Data storage e.g. Amazon S3 Platform as
Taking Action. Dispute resolution, legal action and claims for negligence
Taking Action Dispute resolution, legal action and claims for negligence Taking Action Part 3: Dispute Resolution, taking legal action and claims for negligence Introduction If you believe an architect
Code of Conduct for Marketing Retail Energy in Victoria
Code of Conduct for Marketing Retail Energy in Victoria January 2009 TABLE OF CONTENTS Page INTRODUCTION...1 1. MARKETING REPRESENTATIVES - TRAINING...3 2. CONTACT WITH CONSUMERS...4 2.1 Personal contact...4
Risk in Construction
Risk in Construction Market Research prepared for June 2014 In association with the Chartered Institution of Civil Engineering Surveyors, The Institution of Civil Engineers and the UK s leading Design
GENERAL TERMS AND CONDITIONS
GENERAL TERMS AND CONDITIONS Contents A. SCOPE...3 B. CONFIDENTIALITY, NAME, INTELLECTUAL PROPERTY AND TAX EXEMPT STATUS OF THE WTO...3 B.1. Confidentiality...3 B.2. Use of the name, logo or official seal
ROADMAP TO A SUCCESSFUL TERMINATION FOR DEFAULT
ROADMAP TO A SUCCESSFUL TERMINATION FOR DEFAULT By: Frank E. Riggs, Jr. [email protected] 404.885.3353 One of the most difficult, and potentially costly, decisions facing a project owner
Standard conditions of purchase
Standard conditions of purchase 1 OFFER AND ACCEPTANCE 2 PROPERTY, RISK & DELIVERY 3 PRICES & RATES The Supplier shall provide all Goods and Services in accordance with the terms and conditions set out
CO-MARKETING AGREEMENT
CO-MARKETING AGREEMENT This CO-MARKETING AGREEMENT ( Agreement ) between [full legal name], a [entity type and state] ( Company1 ) and [full legal name], a Delaware corporation ( Company2 ) is effective