Best Practices on Construction Projects. January 29, 2008

Size: px
Start display at page:

Download "Best Practices on Construction Projects. January 29, 2008"

Transcription

1 Best Practices on Construction Projects Project Management Procedures Request for Information January 29, 2008 Presented by the Claims Avoidance & Resolution Committee 1

2 PROJECT MANAGEMENT PROCEDURES Request for Information (RFIs) 2

3 RFI Best Practices Panel Subcommittee for Project Management Procedures Stephen A. Hess, PE Lawrence M. Lenahan, PE William Scott, PE John Ciccarelli, PE, CCE, PSP 3

4 RFI Background RFI is a communication tool to facilitate resolution of or to clarify design document issues Typically contractor submits and designer responds Clarify a legitimate question concerning the design documents Keep the project moving forward and build the job Can lead to Change Orders Process will vary from project to project Effectively coordinate and manage RFIs Assist documenting the history of the project 4

5 RFI Background (continued) Design / Engineering firms becoming more involved with construction claims (with both Owners and Contractors) Reason - design documents are allegedly: Faulty Ambiguous Inadequate Incomplete Conflicting, etc Claim submitted for acts or omissions of the Design Professional based on RFIs Perceived as providing a methodology to document deficiencies in the contract documents and establish a basis for additional costs and time 5

6 RFI When Used as Basis for Claims (Abuses and Pitfalls) Submitted for a clearly identifiable item that should have been addressed pre-bid Submitted significant number to establish support for claim Design was incomplete / faulty look at the number of RFIs submitted! Submitted numerous and excessive RFIs (at the same time) and overwhelm the designer or Designer / Owner hinders the process and does not provide a decision or respond Delays caused by non-responsive or late replies to RFIs Insufficient response frustrates the Contractor and does not progress the work Provide as specified or It s on the drawings Use RFI to propose alternative construction methods or substitute items (or-equal) 6

7 Claims Based on RFIs Response to RFI will be the basis for the claim Extreme position that the first RFI indicates incomplete design Contractor claims for: Work performed based on response to RFI as a Change Order Additional construction costs Delay damage and off-setting of liquidated damages Owner claims for: Cost for delayed project completion Increased interest and expenses 7

8 Best Practices Develop an RFI protocol/procedure to address: The items that will and will not be accepted as an RFI Information which is on the contract documents will not be addressed in a response Define the documentation and supporting data required Time frame for response Qualify that the response is not a Change Order Does not address construction means and methods or site safety Will not review requests for substitute items as an RFI Discuss the procedure at pre-construction meeting or include as part of the bid documents Discuss RFI issues prior to formal submittal Confirming RFI to confirm previous agreement 8

9 Best Practices (continued) Proactively develop RFIs prior to construction or work in an area Develop an RFI form and require project participants to use it. Form should require: Concise statement of the issue (limit to one issue) Identify the specific plans or specification in question Develop internal procedure for receiving, handling and responding to RFI in a timely manner Single source responsibility Procedure to forward to specialty consultants Communicate when the RFI will be completed Maintain log and track status (monitored by individual in company, but not involved with the project) 9

10 Best Practices (continued) Define the response time Designer will have at least 3 days "The Contracting Officer, acting on behalf of the Owner, will be the initial interpreter of the requirements of the Contract Documents, and in such capacity, will render determinations on the acceptability of the Work. Notices, proposals or other matters relating to the acceptability of the Work or the interpretation of the Contract Documents shall be referred to the Contracting Officer in writing, within twenty (20) days after the Program Manager first recognizes the issue, but in no event more than six (6) months after the occurrence giving rise to the issue, requesting a formal, written determination, which the Contracting Officer will render on behalf of the Owner within a reasonable time." 10

11 Best Practices (continued) During construction must reply timely and appropriately Inform the Owner if an RFI results in a design change, additional costs or delay and document the reason Dislodge complex issues from the RFI process Use subcommittee approach for more complex issues Dislodge resolved RFIs from the process RFI response then moves to Change Order or other Contractual process Prioritize RFIs Need response in: days, weeks, or months 11

12 Claim Scenario Legitimate RFI? RFI submitted for a clearly identifiable item that should have been addressed pre-bid or is on the existing contract documents Are the RFI s legitimate? Check other bidder s bid documents to demonstrate the contractor missed something that others included Should issue be removed from the RFI process and addressed in another forum? 12

13 Claim Scenario Design Incomplete or Faulted Submitted significant number to establish support for a claim that the design was incomplete / faulted Look at the number of RFIs we have submitted! RFI count may or may not indicate an incomplete or late-evolving design Significant increase in RFI submissions late in the project often precedes an oncoming design claim Are the RFIs valid or should be addressed in another forum? Compare RFI with other bidder s bid documents to demonstrate the contractor missed something that others included When were the RFIs submitted relative to work execution? Or relative to the commencement of delay Know the impacts of releasing design documents during construction. 13

14 Sample RFI Distribution Chart Monthly Detail Drawings Issued to Contractor by Designer - The designer issued drawings containing new scope and some changed scope through the life of the project - The RFI's, which were usually sub-contractor items, grew steadilly during the project - the rate actually increased at the end of the prime work period D J F M A M J J A S O N D J F M A M J J A S O N D J F Monthly Detail Drawings Total RFIs 14

15 Claim Scenario Delayed Response Submitted numerous and excessive RFIs (often at the same time) to overwhelm the designer and establish a delay claim caused by late or nonresponsiveness to RFIs Do the RFIs impact critical path activities? Were delays cited contemporaneously? Is there a review time or process specified in the contract? EJCDC Standard General Conditions of the Construction Contract AIA General Conditions Are the RFI s legitimate? 15

16 Example Claim Presentation of RFI Response Time RFI RESPONSE TIME 3-7 Days 15% 8-14 Days 7% More than 14 Days 15% 0-2 Days 18% No Response 45% 16

17 Claim Avoidance - Mitigation Delays caused by incomplete or faulty design Know the Project schedule Manage the RFI process; do not just accept each as valid and necessary RFIs must conform with the intent to clarify contracts and design documents/specifications. Track the receipt and return of RFI submittals take notice immediately of dramatic increases in RFI count and/or response time 17

18 Claim Avoidance - Mitigation Delays caused by late or lack of response Establish procedures, including the RFI submission format, within the Contract or prior to construction Track receipt and return of all RFIs during the project and act to detect trends Know the schedule and prioritize Designer understand the importance of response Contractor pre-planning work and identify conflicts early Do not sit on RFIs - accept and address or reject promptly Ensure that RFIs are complete and do not accept RFIs that fail to conform to submission requirements Clarification of Contract or design documents only 18

19 Litigation / Legal Considerations United States v. Spearin, 248 U.S. at (1918) United States Supreme Court: "if the contractor is bound to build according to plans and specifications prepared by the owner, the contractor will not be responsible for the consequences of defects in the plans and specifications." Implied warranty Cumulative effect of changes recognized that inefficiency claim based on disruptive effect of individual compensable changes: Jackson Constr. Co., Inc. v. United States, 62 Fed. CI. 84, (2004) (citing J.A. Jones Constr. Co., ENGBCA Nos. 6348, , B.C.A. (CCH) P31,000, at 153, 107, 2000 WL (2000); McMillin Bros. Constr., Inc., EBCA No ,91-1 BCA P 23,351, at 117,102-05, 1990 WL (1990), aff'd, 949 F.2d 403 (Fed. Cir. 1991); Bechtel Nat'l, Inc., NASA BCA No , 90-1 BCA P 22,549, at 113,177-78, 1989 WL (1989) 19

20 Litigation / Legal Considerations Duty The government has a duty not to act in a way that will hinder or delay the contractor's performance ( refrain from willfully or negligently interfering with a contractor's performance. ). Malone v. United States, 849 F.2d 1441, 1445 (Fed. Cir. 1988), modified, 857 F.2d 787 (1988); SMS Data Prods. Group, Inc. v. United States, 17 Cl. Ct. 1, 6 (1989). For the government to be found liable for delay a plaintiff must demonstrate that the government caused the plaintiff a compensable injury. The government, therefore, is not liable for breach of contract, or causes of action that rely upon "severe defects" in contract drawings, or government hindrance of performance, unless SCBI proves that the alleged defects, changes, or hindrances negatively impacted costs and performance of the contract. Servidone Constr. Corp. v. United States, 931 F.2d 860, 861 (1991); Boyajian v. United States, 191 Ct. Cl. 233, , 423 F.2d 1231, 1235 (1970). 20

21 Litigation / Legal Considerations SOUTHERN COMFORT BUILDERS, INC., Plaintiff, v. UNITED STATES, Defendant. No C; UNITED STATES COURT OF FEDERAL CLAIMS 67 Fed. Cl. 124; 2005 U.S. Claims LEXIS 225; July 29, 2005 SCBI alleges that many of the disruptions caused by the government resulted from NASA's failure to respond to plaintiff's RFIs in a timely manner, which addressed interferences or obstructions encountered by SCBI. In the documents provided to the court, SCBI submitted an RFI log indicating the times within which NASA responded to SCBI's RFIs. Of the RFIs submitted by SCBI, many were answered in about a week's time. Others were responded to more slowly by NASA, including those which resulted in contract change orders. Ruled in favor of the Defendant (two contract modifications had to be paid by defendant, all other claims dismissed. Defendant awarded counter claim). 21

22 Litigation / Legal Considerations CADDELL CONSTRUCTION CO., INC., Plaintiff, v. THE UNITED STATES, Defendant. No C; UNITED STATES COURT OF FEDERAL CLAIMS; 78 Fed. Cl. 406; 2007 U.S; Claims LEXIS 285; September 7, 2007 Defective design resulted in plaintiff issuing large number of RFIs and government failed to promptly and fully answer and as a result plaintiff missed steel fabrication window. Defendant contended RFI process was obstructed as Defendant held onto RFIs from subcontractors and submitted in large batches and that Plaintiff did not demonstrate delay caused by allegedly slow response Ruled in favor of the Defendant based on contractor s duty to coordinate and that the Defendant answered more than one third of the RFIs in less than 30 days and more than 90% in less than 45 days Third party beneficiary status of contractors, Privity, Economic Loss Doctrine, Accepted Work Doctrine 22

23 Recommended Project Management Procedure - RFIs Clearly define and use the RFI process with the designer to seek clarification or interpretation of conflicts, errors, discrepancies or ambiguities in the Contract Documents limit to clarification only Define and document the response time at the project (kick-off) pre-construction meeting. Sample Contract language: 23

24 Recommended Project Management Procedure - RFIs Define the number of copies required (no oral or incomplete RFIs accepted) Review and response to RFIs shall not constitute approval, direction, or procedures for means and methods. Limit each RFI to a single issue Information discernable from the existing documents, or addressing construction means and methods or site safety will not be addressed Designer should designate a specific representative to manage the process 24

25 Recommended Project Management Procedure - RFIs RFI Form should include Chronological number for the RFI (Tracking Mechanism) Date issued Name of person and contractor requesting information Applicable Specification section and page number Applicable drawing number and title Clear statement of the request Remark for any increase in cost or time Designer should review RFI for compliance with protocol and return any non-complying RFIs 25

26 Sample RFI Form 26

27 Sample RFI Form (from Timberline Software) Company Address Company Address

28 Sample RFI Form 28

29 Sample RFI From ConstructWare Software 29

30 Recommended Project Management Procedure - RFIs Upon receipt of RFI, responsible party should Calculate response due date Notify Contractor of date received and when response should be expected Review for compliance with protocol and return any non-complying RFIs Enter RFI into log 30

31 Recommended Project Management Procedure - RFIs RFI log manual or electronic, should include: RFI Number Name of requester and contractor Date of receipt Original response due date Name of RFI reviewer Date forwarded for review Date returned to Contractor Any extension information (date, etc) Summary of response Does response necessitate a change, extra or time extension Other (trade or discipline involved, ) 31

32 Sample RFI Log Transit Project Transit Project 32

33 Sample RFI Log

34 Sample RFI Log From ConstructWare Software 34

35 Recommended Project Management Procedure - RFIs Forward response to Contractor and copy appropriate parties (Owner, CM, Resident Engineer) Contractor can disagree with response and initiate meeting and resolution in another forum RFI is closed 35

36 Recommended Best Practices Designer understand your Contract and the Contractor s Contract provisions with the Owner Use RFIs with owner during design phase Required response time for RFIs and communicate expected response time to contractor Know Contract roles and responsibilities Understand the Project Schedule Does the Contractor s schedule need to or include shop drawing review and other A/E related activities? Monitor and manage RFIs and utilize an RFI log Be prompt with response and/or document why not Don t let paperwork languish! 36

37 Additional References Defending Claims by Owners & Contractors for Damages Arising from RFIs and Approved and Unapproved Change Orders, Seamen, Drew F. and Waggoner, Thomas F., at The 40 th Annual Meeting of Invited Attorneys, EJCDC Standard General Conditions AIA A201 General Conditions American Institute of Steel Construction Code of Standard Practice, Articles and

38 Benefits of Implementing Procedures Facilitates communication Streamlines the RFI process Maintains progress on the project Documents project history Helps mitigate and avoids claims 38

39 Questions? 39

STANDARD SUBCONTRACT AGREEMENT FOR BUILDING CONSTRUCTION

STANDARD SUBCONTRACT AGREEMENT FOR BUILDING CONSTRUCTION STANDARD SUBCONTRACT AGREEMENT FOR BUILDING CONSTRUCTION THIS AGREEMENT made at Columbus, Ohio on by and between Lincoln Construction, Inc., hereinafter referred to as the Contractor, and, hereinafter

More information

Assistant Project Management - Training Program A 3-year Program Beginning strategy places the new employee into a three-year program that provides

Assistant Project Management - Training Program A 3-year Program Beginning strategy places the new employee into a three-year program that provides Assistant Project Management - Training Program A 3-year Program Beginning strategy places the new employee into a three-year program that provides for experience in the Construction Company's three areas

More information

Construction Schedules

Construction Schedules CONSTRUCTION CLAIMS EDITION EDITION NO. 15 September 2013 Construction Schedules Recovery Schedules And Constructive Acceleration Protect Yourself From Pitfalls By Christopher M. Burke Partner, Watt, Tieder,

More information

Checklist 26: How Owners Can Avoid Litigation on Construction Projects

Checklist 26: How Owners Can Avoid Litigation on Construction Projects Checklist 26: How Owners Can Avoid Litigation on Construction Projects While it is impossible to completely avoid litigation on construction projects, certain steps can be taken to minimize the potential

More information

Bond Form Commentary and Comparison

Bond Form Commentary and Comparison Bond Form Commentary and Comparison AIA Document A310 2010, Bid Bond, and AIA Document A312 2010, Performance Bond and Payment Bond INTRODUCTION Since the first publication of The Standard Form of Bond

More information

City of Vallejo REQUEST FOR PROPOSAL WORKERS COMPENSATION CLAIMS AUDIT

City of Vallejo REQUEST FOR PROPOSAL WORKERS COMPENSATION CLAIMS AUDIT City of Vallejo REQUEST FOR PROPOSAL WORKERS COMPENSATION CLAIMS AUDIT Date original issued: September 28, 2015 Qualifications Statements due: The City of Vallejo will consider Proposals submitted in response

More information

Construction Bonds. Vanessa S. Werden 604.408.2033 [email protected]

Construction Bonds. Vanessa S. Werden 604.408.2033 vsw@shk.ca Construction Bonds Vanessa S. Werden 604.408.2033 [email protected] What is a bond? A bond is a special form of contract whereby one party guarantees the performance by another party of certain obligations. A

More information

LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980

LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Richard J. Long, P.E. Table of Contents 1. INTRODUCTION...

More information

Manage Deliverables - Construction Step 6. July 12, 2012

Manage Deliverables - Construction Step 6. July 12, 2012 Manage Deliverables - Construction Step 6 July 12, 2012 Project Management Concept Step 1: Needs Development Step 2: Scope Development Step 3: Procurement of Design Team Step 4: Design Step 5: Bid/Procurement

More information

a. Proposals shall be submitted in a sealed envelope and addressed as follows:

a. Proposals shall be submitted in a sealed envelope and addressed as follows: 1 CITY OF ATCHISON REQUEST FOR QUALIFICATIONS & PROPOSAL PLUMBING SERVICES JANUARY 1, 2014 THROUGH DECEMBER 31, 2014 DUE: DECEMBER 10, 2013 10:00 A.M. The City of Atchison (City) invites interested and

More information

City of Moreno Valley Date Council Approved March 13, 2007 Date Effective April 6, 2007 CLASS SPECIFICATION Senior Electrical Engineer, P.E.

City of Moreno Valley Date Council Approved March 13, 2007 Date Effective April 6, 2007 CLASS SPECIFICATION Senior Electrical Engineer, P.E. City of Moreno Valley Date Council Approved March 13, 2007 Date Effective April 6, 2007 CLASS SPECIFICATION Senior Electrical Engineer, P.E. GENERAL PURPOSE Under direction, manages, oversees, evaluates,

More information

Canterbury Park Pool Chamber Replacement

Canterbury Park Pool Chamber Replacement Requirement Request For Quotation To provide services, equipment and materials to replace the Concrete Pool Service & Drainage vault at the Canterbury Park Pool located at 2185 Arch Street, Ottawa, ON

More information

ITEM 639.30030002 DOCUMENT CONTROL MANAGEMENT DESCRIPTION:

ITEM 639.30030002 DOCUMENT CONTROL MANAGEMENT DESCRIPTION: DESCRIPTION: Under this item the Contractor shall provide an individual(s), designated the Document Control Specialist. The Document Control Specialist shall use a software to prepare, status, electronically

More information

Document B101 TM. Standard Form of Agreement Between Owner and Architect

Document B101 TM. Standard Form of Agreement Between Owner and Architect Document B101 TM 2007 Standard Form of Agreement Between Owner and Architect AGREEMENT made as of the th day of in the year 2014 (In words, indicate day, month and year.) BETWEEN the Architect s client

More information

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF DELAWARE

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF DELAWARE IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF DELAWARE ROGER HAUTH, Plaintiff, v. Civil Action No. 00-166-JJF ROBERT P. LOBUE, ESQUIRE, Defendant. Kevin William Gibson, Esquire of Gibson & Perkins,

More information

CONTRACT FOR PROJECT MANAGEMENT SERVICES (Green Repair Program)

CONTRACT FOR PROJECT MANAGEMENT SERVICES (Green Repair Program) CONTRACT FOR PROJECT MANAGEMENT SERVICES () This Contract is made this day of in the year between (day) (month) (year) the, (Owner), Massachusetts (City) (State), (Zip Code) hereinafter called "the Owner"

More information

8:11-mn-02000-JMC Date Filed 04/22/15 Entry Number 150 Page 1 of 8

8:11-mn-02000-JMC Date Filed 04/22/15 Entry Number 150 Page 1 of 8 8:11-mn-02000-JMC Date Filed 04/22/15 Entry Number 150 Page 1 of 8 IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF SOUTH CAROLINA GREENWOOD DIVISION In re: Building Materials Corporation of America

More information

OCIPs and Professional Responsibility

OCIPs and Professional Responsibility OCIPs and Professional Responsibility Rosary A. Hernandez Wood Smith Henning & Berman LLP 2525 E. Camelback Road, Suite 450 Phoenix, AZ 85016-4210 (602) 441-1305 [email protected] Rosary A. Hernandez,

More information

ResearcH JournaL 2012 / VOL 04.01. www.perkinswill.com

ResearcH JournaL 2012 / VOL 04.01. www.perkinswill.com ResearcH JournaL 2012 / VOL 04.01 www.perkinswill.com Architectural Services During Construction 01. ARCHITECTURAL SERVICES DURING CONSTRUCTION: Duties and Liability Helena O Connor, CAU-RJ, LEED AP BD+C,

More information

AIA Document A312 - Electronic Format. Performance Bond

AIA Document A312 - Electronic Format. Performance Bond AIA Document A312 - Electronic Format Performance Bond THIS DOCUMENT HAS IMPORTANT LEGAL CONSEQUENCES: CONSULTATION WITH AN ATTORNEY IS ENCOURAGED WITH RESPECT TO ITS COMPLETION OR MODIFICATION. AUTHENTICATION

More information

VIRGINIA: IN THE CIRCUIT COURT OF SOUTHWESTERN COUNTY 1

VIRGINIA: IN THE CIRCUIT COURT OF SOUTHWESTERN COUNTY 1 VIRGINIA: IN THE CIRCUIT COURT OF SOUTHWESTERN COUNTY 1 SMOOTH RIDE, INC., Plaintiff, v. Case No.: 1234-567 IRONMEN CORP. d/b/a TUFF STUFF, INC. and STEEL-ON-WHEELS, LTD., Defendants. PLAINTIFF SMOOTH

More information

Construction Management Services Delmar School District RFP No. DSD16001-CONSTR_MAN

Construction Management Services Delmar School District RFP No. DSD16001-CONSTR_MAN Construction Management Services Delmar School District RFP No. DSD16001-CONSTR_MAN The Delmar School District (DSD) is seeking the professional services of a Construction Management (CM) firm for the

More information

Attachment 5 Electrical Engineering

Attachment 5 Electrical Engineering A. Phase 1, Preliminary Design: The CONSULTANT shall: Attachment 5 Electrical Engineering 1. Ascertain the requirements for each project through a meeting with the Capital Projects Division Manager or

More information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services

More information

By: Pat Derdenger, Partner Steptoe & Johnson LLP 201 East Washington Street, 16 th Floor Phoenix, Arizona 85004-2382. Sub

By: Pat Derdenger, Partner Steptoe & Johnson LLP 201 East Washington Street, 16 th Floor Phoenix, Arizona 85004-2382. Sub ARIZONA TAX: CONSTRUCTION MANAGEMENT AND THE ORMOND CASE; THE COURT OF APPEALS FINALLY ANSWERS THE QUESTION OF WHETHER A CONSTRUCTION MANAGER IS A PRIME CONTRACTOR SUBJECT TO THE ARIZONA TRANSACTION PRIVILEGE

More information

a. Proposals shall be submitted in a sealed envelope and addressed as follows:

a. Proposals shall be submitted in a sealed envelope and addressed as follows: 1 CITY OF ATCHISON REQUEST FOR QUALIFICATIONS & PROPOSAL HVAC SERVICES JANUARY 1, 2014 THROUGH DECEMBER 31, 2014 DUE: DECEMBER 10, 2013 10:00 A.M. The City of Atchison (City) invites interested and qualified

More information

LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980

LONG INTERNATIONAL. Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 LONG INTERNATIONAL Long International, Inc. 10029 Whistling Elk Drive Littleton, CO 80127-6109 (303) 972-2443 Fax: (303) 972-6980 www.long-intl.com Richard J. Long, P.E. and Rod C. Carter, CCP, PSP Table

More information

STANDARD FORM OF AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR (Where Contractor and Subcontractor Share Risk of Owner Payment)

STANDARD FORM OF AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR (Where Contractor and Subcontractor Share Risk of Owner Payment) State License #CGC048773 STANDARD FORM OF AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR (Where Contractor and Subcontractor Share Risk of Owner Payment) This Agreement is made this day of, 200, by and

More information

PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT

PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT PROJECT AND CONSTRUCTION MANAGEMENT SERVICES FOR KUWAIT PORT AUTHORITY FOR PROJECTS AT SHUAIBA PORT - INTRODUCTION 1.1. General. Kuwait Ports Authority (KPA) through the Ministry Of Finance (MOF) wishes

More information

IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF ILLINOIS EASTERN DIVISION

IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF ILLINOIS EASTERN DIVISION Case 1:09-cv-06119 Document 45 Filed 05/17/10 Page 1 of 17 IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF ILLINOIS EASTERN DIVISION LYON FINANCIAL SERVICES, INC., ) ) Plaintiff, ) ) v.

More information

MASTER AGREEMENT FOR PROJECT THE DEKALB COUNTY BOARD OF EDUCATION. Dated:

MASTER AGREEMENT FOR PROJECT THE DEKALB COUNTY BOARD OF EDUCATION. Dated: MASTER AGREEMENT FOR PROJECT MANAGEMENT SERVICES BETWEEN THE DEKALB COUNTY BOARD OF EDUCATION AND Dated: T A B L E O F C O N T E N T S ARTICLE 1 DEFINITIONS... 1 ARTICLE 2 REPRESENTATIONS... 4 2.1 Specific

More information

Construction Practice Group

Construction Practice Group Advising and counseling our clients through every phase of even the most complex construction matters is what differentiates the lawyers in Gould & Ratner s construction practice. As a group, they possess

More information

PRIME CONSULTANT SERVICES

PRIME CONSULTANT SERVICES GUIDELINES FOR Professional Engineers providing PRIME CONSULTANT SERVICES 1.0 INTRODUCTION 1.1 PURPOSE OF GUIDELINES The "Guidelines for Professional Engineers providing Prime Consultant Services" have

More information

How To Write A Short Form Prime Prime Prime Contract Between A Contractor And Owner

How To Write A Short Form Prime Prime Prime Contract Between A Contractor And Owner SHORT FORM PRIME CONTRACT BETWEEN OWNER & CONTRACTOR This Agreement ( Contract ) is made this day of, 20, between ( Contractor ) and ( Owner ) at The work described in Section 1 below shall be performed

More information

Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive

Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive Jacobs Contract performance Tracking spreadsheet = Excellent 2 = Meets performance standards 1 = Improvement needed 0= Unsatisfactory Report for the time period: Annual report 210 Total average score 2.86

More information

An Oracle White Paper April 2009. Change Management Best Practices for the Engineering and Construction Industry

An Oracle White Paper April 2009. Change Management Best Practices for the Engineering and Construction Industry An Oracle White Paper April 2009 Change Management Best Practices for the Engineering and Construction Industry Introduction... 1 Understanding Project Changes... 2 Directed Changes... 2 Constructive Changes...

More information

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF PENNSYLVANIA. Memorandum and Order

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF PENNSYLVANIA. Memorandum and Order IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF PENNSYLVANIA CAROSELLA & FERRY, P.C., Plaintiff, v. TIG INSURANCE COMPANY, Defendant. CIVIL ACTION NO. 00-2344 Memorandum and Order YOHN,

More information

A. For the consideration agreed below to be paid to Contractor by City, Contractor shall provide

A. For the consideration agreed below to be paid to Contractor by City, Contractor shall provide STATE OF TEXAS CONTRACT FOR SERVICES COUNTY OF DALLAS THIS CONTRACT is made and entered into by and between the CITY OF DALLAS, a Texas municipal corporation, located in Dallas County, Texas (hereinafter

More information

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E.

Memorandum. Jeff Jasper, P.E. Director, Division of Design. Technical Support TEBM, Division of Construction. From: Jeremiah Littleton, P.E. Memorandum To: Thru: Jeff Jasper, P.E. Director, Division of Design Rachel Mills, P.E. Technical Support TEBM, Division of Construction From: Jeremiah Littleton, P.E. Division of Construction Date: June

More information

Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho

Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho REQUEST FOR QUALIFICATIONS Independent School District No. 1, Lewiston, Idaho ( District ) is seeking responses from individuals

More information

IN THE COURT OF COMMON PLEAS OF PHILADELPHIA COUNTY FIRST JUDICIAL DISTRICT OF PENNSYLVANIA CIVIL TRIAL DIVISION

IN THE COURT OF COMMON PLEAS OF PHILADELPHIA COUNTY FIRST JUDICIAL DISTRICT OF PENNSYLVANIA CIVIL TRIAL DIVISION IN THE COURT OF COMMON PLEAS OF PHILADELPHIA COUNTY FIRST JUDICIAL DISTRICT OF PENNSYLVANIA CIVIL TRIAL DIVISION EASTERN DENTIST INSURANCE : April Term 2004 COMPANY, : Plaintiff, : No. 2398 v. : LIONEL

More information

1.1 The contract shall be deemed to have been entered into upon receipt of supplier s written acknowledgement stating its acceptance of the order.

1.1 The contract shall be deemed to have been entered into upon receipt of supplier s written acknowledgement stating its acceptance of the order. Kendrion (Switzerland) AG Albisstrasse 26 CH-8915 Hausen am Albis of Contract (Rev. 1, valid from 01.01.2013) 1 General 1.1 The contract shall be deemed to have been entered into upon receipt of supplier

More information

CALIFORNIA CONSTRUCTION CONTRACTS, DEFECTS, AND LITIGATION (1st Edition) November 2015 TABLE OF CONTENTS

CALIFORNIA CONSTRUCTION CONTRACTS, DEFECTS, AND LITIGATION (1st Edition) November 2015 TABLE OF CONTENTS CALIFORNIA CONSTRUCTION CONTRACTS, DEFECTS, AND LITIGATION (1st Edition) November 2015 TABLE OF CONTENTS File Name Book Section Title CH01 Chapter 1 Contractor Licensing; Remedies for Unlicensed Work 01-022

More information

REQUEST FOR PROPOSALS DESIGN OF COMMUNTIY SKATE PARK FREDERICK, COLORADO

REQUEST FOR PROPOSALS DESIGN OF COMMUNTIY SKATE PARK FREDERICK, COLORADO REQUEST FOR PROPOSALS DESIGN OF COMMUNTIY SKATE PARK FREDERICK, COLORADO 1. INTRUDUCTION The Town of Frederick is seeking proposals in response to this Request for Proposals (RFP) from a qualified skateboard

More information

CALIFORNIA DEPARTMENT OF TRANSPORTATION CONTRACTOR LIABILITY INSURANCE

CALIFORNIA DEPARTMENT OF TRANSPORTATION CONTRACTOR LIABILITY INSURANCE CALIFORNIA DEPARTMENT OF TRANSPORTATION CONTRACTOR LIABILITY INSURANCE The following are excerpts from Caltrans 2010Standard Specifications. Specifications are subject to change so refer to the project

More information

NORTH COLONIE CENTRAL SCHOOL DISTRICT 91 FIDDLERS LANE LATHAM, NEW YORK 12110-5349 INVITATION FOR CONSTRUCTION MANAGEMENT PROPOSALS

NORTH COLONIE CENTRAL SCHOOL DISTRICT 91 FIDDLERS LANE LATHAM, NEW YORK 12110-5349 INVITATION FOR CONSTRUCTION MANAGEMENT PROPOSALS NORTH COLONIE CENTRAL SCHOOL DISTRICT 91 FIDDLERS LANE LATHAM, NEW YORK 12110-5349 INVITATION FOR CONSTRUCTION MANAGEMENT PROPOSALS The North Colonie Central School District invites your firm to submit

More information

1 OF 7. there will be few "surprises" as the work progresses.

1 OF 7. there will be few surprises as the work progresses. 1 OF 7 FP-G1.94 GUIDELINES FOR SUCCESSFUL SUPERVISION OF SCHOOL DISTRICT CAPITAL CONSTRUCTION PROJECTS There is no doubt that the successful completion of any capital construction project is the result

More information

Document Comparison. AIA Documents A134 2009 and A131CMc 2003

Document Comparison. AIA Documents A134 2009 and A131CMc 2003 Document Comparison AIA Documents A134 2009 and A131CMc 2003 AIA Document A134 2009 is in the right-hand column. Corresponding sections of AIA Document A131 CMc 2003 are in the left-hand column. Sections

More information

Case 2:10-cv-02263-JAR Document 98 Filed 05/04/11 Page 1 of 8 IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF KANSAS

Case 2:10-cv-02263-JAR Document 98 Filed 05/04/11 Page 1 of 8 IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF KANSAS Case 2:10-cv-02263-JAR Document 98 Filed 05/04/11 Page 1 of 8 IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF KANSAS SANDRA H. DEYA and EDWIN DEYA, individually and as next friends and natural

More information

7.4.1 Be required to make exhaustive or continuous on-site reviews;

7.4.1 Be required to make exhaustive or continuous on-site reviews; SUPPLEMENTARY CONDITIONS TO THE CANADIAN STANDARD FORM OF CONTRACT FOR ARCHITECTURAL SERVICES DOCUMENT SIX 2006 EDITION RAIC 6 2006 FRASER HEALTH PROJECTS The following Supplementary Conditions are specific

More information

WEB SITE DEVELOPMENT AGREEMENT. This WEB SITE DEVELOPMENT AGREEMENT ("Agreement") is an agreement between 3WDirect

WEB SITE DEVELOPMENT AGREEMENT. This WEB SITE DEVELOPMENT AGREEMENT (Agreement) is an agreement between 3WDirect WEB SITE DEVELOPMENT AGREEMENT This WEB SITE DEVELOPMENT AGREEMENT ("Agreement") is an agreement between 3WDirect ("Company") and the party set forth in the related order form ("Customer" or "you") incorporated

More information

IN THE UNITED STATES DISTRICT COURT FOR THE SOUTHERN DISTRICT OF TEXAS HOUSTON DIVISION

IN THE UNITED STATES DISTRICT COURT FOR THE SOUTHERN DISTRICT OF TEXAS HOUSTON DIVISION Goodridge v. Hewlett Packard Company Doc. 13 IN THE UNITED STATES DISTRICT COURT FOR THE SOUTHERN DISTRICT OF TEXAS HOUSTON DIVISION CHARLES GOODRIDGE, Plaintiff, v. CIVIL ACTION H-07-4162 HEWLETT-PACKARD

More information

GREENBURGH CENTRAL SCHOOL DISTRICT No. 7 REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES

GREENBURGH CENTRAL SCHOOL DISTRICT No. 7 REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES GREENBURGH CENTRAL SCHOOL DISTRICT No. 7 REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES Greenburgh Central School District No. 7 ( The District ) invites proposals to perform construction management

More information

REQUEST FOR PROPOSALS FOR DISASTER RECOVERY ADMINISTRATIVE SERVICES

REQUEST FOR PROPOSALS FOR DISASTER RECOVERY ADMINISTRATIVE SERVICES REQUEST FOR PROPOSALS FOR DISASTER RECOVERY ADMINISTRATIVE SERVICES Notice is hereby given that the Santa Rosa County Board of County Commissioners is calling for and requesting proposals from qualified

More information

CHAPTER 23. Contract Management and Administration

CHAPTER 23. Contract Management and Administration Date Issued: June 12, 2009 Date Last Revised: September 28, 2015 CHAPTER 23. Contract Management and Administration Table of Contents CHAPTER 23. Contract Management and Administration... 23-1 23.1 Policy...

More information

NPSA GENERAL PROVISIONS

NPSA GENERAL PROVISIONS NPSA GENERAL PROVISIONS 1. Independent Contractor. A. It is understood and agreed that CONTRACTOR (including CONTRACTOR s employees) is an independent contractor and that no relationship of employer-employee

More information

CONTRACT FOR DESIGN SERVICES. Appendix 2 Contract Documents Design Services. PS-0748-A Page 1 5/4/2016 Appendix 2

CONTRACT FOR DESIGN SERVICES. Appendix 2 Contract Documents Design Services. PS-0748-A Page 1 5/4/2016 Appendix 2 CONTRACT FOR DESIGN SERVICES Contract Documents Design Services PS-0748-A Page 1 5/4/2016 Table of Contents Design Services Contract Contract references Attachments described below that will be provided

More information

In the United States Court of Federal Claims

In the United States Court of Federal Claims In the United States Court of Federal Claims No. 03-1345 C Filed September 24, 2004 TO BE PUBLISHED ) FREDERICK J. SONNENFELD, ) ) RCFC 12(b)(1), RCFC 12(b)(6), Plaintiff, ) Tucker Act, 28 U.S.C. 1491,

More information

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT SERVICES

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT SERVICES REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGEMENT SERVICES ISSUED BY: INGLEWOOD UNIFIED SCHOOL DISTRICT Issued: November 20, 2015 Due: December 18, 2015 SCHEDULE OF EVENTS INGLEWOOD UNIFIED SCHOOL

More information

AIA Document A312 TM 1984

AIA Document A312 TM 1984 Performance Bond AIA Document A312 TM 1984 CONTRACTOR (Name and Address): H. B. Barnard, General Corporation 53 West Jackson Boulevard Suite 235 OWNER (Name and Address): The Chicago Society of Alpha Delta

More information

Construction Contract Clause Digest

Construction Contract Clause Digest Construction Contract Clause Digest A Service of The Harmonie Group Construction Law Committee The Harmonie Group provides INTERNATIONAL ACCESS TO EXCELLENCE. The defense firms in our network handle complex

More information

Case 1:07-cv-01949-LTB Document 17 Filed 01/23/2008 Page 1 of 6

Case 1:07-cv-01949-LTB Document 17 Filed 01/23/2008 Page 1 of 6 Case 1:07-cv-01949-LTB Document 17 Filed 01/23/2008 Page 1 of 6 Civil Case No. 07-cv-01949-LTB IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLORADO LEWIS T. BABCOCK, JUDGE UNITED STATES OF

More information

CITY OF LANCASTER RFP NO. 621-15 LANCASTER PERFORMING ARTS CENTER TICKETING SOFTWARE SUBMISSION DEADLINE. July 24, 2015 BY 11:00 A.M.

CITY OF LANCASTER RFP NO. 621-15 LANCASTER PERFORMING ARTS CENTER TICKETING SOFTWARE SUBMISSION DEADLINE. July 24, 2015 BY 11:00 A.M. CITY OF LANCASTER RFP NO. 621-15 LANCASTER PERFORMING ARTS CENTER TICKETING SOFTWARE SUBMISSION DEADLINE July 24, 2015 BY 11:00 A.M. SUBMIT TO: Office of the City Clerk Lancaster City Hall 44933 Fern Avenue

More information

388 Blohm Ave. PO Box 388 Aromas CA 95004-0388 (831)726-3155 FAX (831)726-3951 email [email protected] ADDENDUM NO. 1

388 Blohm Ave. PO Box 388 Aromas CA 95004-0388 (831)726-3155 FAX (831)726-3951 email aromaswd@aol.com ADDENDUM NO. 1 388 Blohm Ave. PO Box 388 Aromas CA 95004-0388 (831)726-3155 FAX (831)726-3951 email [email protected] May 6, 2015 To: All Plan Holders From: Vicki Morris General Manager Subject: Water Serviceline Installation

More information

Invitation to Bid and Instructions to Bidders (This is Phase I of the project please note on any Bid that it Applies to Phase I only) May 1, 2015

Invitation to Bid and Instructions to Bidders (This is Phase I of the project please note on any Bid that it Applies to Phase I only) May 1, 2015 Invitation to Bid and Instructions to Bidders (This is Phase I of the project please note on any Bid that it Applies to Phase I only) May 1, 2015 For PROJECT : Renovation and Repair of Atlanta Jewish Academy

More information

SUMMARY OF CHANGES COMMERCIAL ARBITRATION RULES

SUMMARY OF CHANGES COMMERCIAL ARBITRATION RULES SUMMARY OF CHANGES COMMERCIAL ARBITRATION RULES Amended and Effective October 1, 2013 SIGNIFICANT CHANGES: 1. Mediation R-9. Mediation: Mediation is increasingly relied upon and is an accepted part of

More information

Case: 2:04-cv-01110-JLG-NMK Doc #: 33 Filed: 06/13/05 Page: 1 of 7 PAGEID #: <pageid>

Case: 2:04-cv-01110-JLG-NMK Doc #: 33 Filed: 06/13/05 Page: 1 of 7 PAGEID #: <pageid> Case: 2:04-cv-01110-JLG-NMK Doc #: 33 Filed: 06/13/05 Page: 1 of 7 PAGEID #: IN THE UNITED STATES DISTRICT COURT FOR THE SOUTHERN DISTRICT OF OHIO EASTERN DIVISION ALVIN E. WISEMAN, Plaintiff,

More information

Memorandum Potentially Affected AIA Contract Documents AIA Document A105 2007 AIA Document B105 2007 Important Information

Memorandum Potentially Affected AIA Contract Documents AIA Document A105 2007 AIA Document B105 2007 Important Information Memorandum Important information related to requirements of state or local laws to include additional provisions in residential construction contracts Potentially Affected AIA Contract Documents AIA Document

More information

Payment and Performance Surety Bonds in Construction Projects: Perspectives of Owners, Contractors and Sureties

Payment and Performance Surety Bonds in Construction Projects: Perspectives of Owners, Contractors and Sureties Presenting a live 90-minute webinar with interactive Q&A Payment and Performance Surety Bonds in Construction Projects: Perspectives of Owners, Contractors and Sureties Asserting and Defending Surety Bond

More information

The New Standard Construction Contracts: NZS3910, 3916 and 3917

The New Standard Construction Contracts: NZS3910, 3916 and 3917 The New Standard Construction Contracts: NZS3910, 3916 and 3917 Brian Clayton, Partner FEBRUARY 2014 3258689.3 Chapman Tripp Introduction Standards New Zealand has recently completed the first review of

More information

City of Portsmouth, Portsmouth, NH School Department Plumbing Repair Services INVITATION TO BID

City of Portsmouth, Portsmouth, NH School Department Plumbing Repair Services INVITATION TO BID INVITATION TO BID Sealed bid proposals, plainly marked "Plumbing Repair Services Contract" will be accepted at the office of the Business Administrator, Portsmouth School Department, 1 Junkins Avenue,

More information

Columbia University Service Provider Agreement

Columbia University Service Provider Agreement Columbia University Agreement Agreement ( Agreement ) dated as of, 20 (the Effective Date ) between The Trustees of Columbia University in the City of New York ( Columbia ) and ( Service Provider ). 1.

More information

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF PENNSYLVANIA

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF PENNSYLVANIA IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF PENNSYLVANIA HASSAN DRIDI : CIVIL ACTION : v. : : WHOLE FOODS MARKET GROUP, INC. : NO. 07-2512 O NEILL, J. JANUARY 2, 2008 MEMORANDUM On

More information

Case: 1:04-cv-01865-JMM Doc #: 47 Filed: 08/23/05 1 of 8. PageID #: 276

Case: 1:04-cv-01865-JMM Doc #: 47 Filed: 08/23/05 1 of 8. PageID #: 276 Case: 1:04-cv-01865-JMM Doc #: 47 Filed: 08/23/05 1 of 8. PageID #: 276 IN THE UNITED STATES DISTRICT COURT FOR THE NORTHERN DISTRICT OF OHIO EASTERN DIVISION AVERY DENNISON CORP., ) CASE NO. 1:04CV1865

More information

CONSTRUCTION & DESIGN AGREEMENTS FOR OWNERS. Presented by ALEXANDER F. FERRINI, III

CONSTRUCTION & DESIGN AGREEMENTS FOR OWNERS. Presented by ALEXANDER F. FERRINI, III CONSTRUCTION & DESIGN AGREEMENTS FOR OWNERS Basics for Projects of All Sizes Presented by ALEXANDER F. FERRINI, III Why do I need an agreement? Why do I need an agreement? Why do I need an agreement? Design

More information

REPUBLIC OF SOUTH AFRICA

REPUBLIC OF SOUTH AFRICA REPUBLIC OF SOUTH AFRICA IN THE HIGH COURT OF SOUTH AFRICA GAUTENG LOCAL DIVISION, JOHANNESBURG CASE NO: 13/33469 (1) REPORTABLE: YES / NO (2) OF INTEREST TO OTHER JUDGES: YES/NO (3) REVISED... DATE...

More information

Who pays the Money for the Time?

Who pays the Money for the Time? Construction Delays & Best Practices Gene Wortham Idaho Transportation Department Time is Money Who pays the Money for the Time? Effects of Construction Acceleration Delays Schedule Change - Inefficiency

More information

REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT AT-RISK FOR LOGANVILLE ELEMENTARY SCHOOL (REPLACEMENT) FOR THE WALTON COUNTY SCHOOL DISTRICT

REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT AT-RISK FOR LOGANVILLE ELEMENTARY SCHOOL (REPLACEMENT) FOR THE WALTON COUNTY SCHOOL DISTRICT ADVERTISEMENT: REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT AT-RISK FOR LOGANVILLE ELEMENTARY SCHOOL (REPLACEMENT) FOR THE WALTON COUNTY SCHOOL DISTRICT The WALTON COUNTY SCHOOL DISTRICT will receive

More information

PROJECT MANAGEMENT BASICS

PROJECT MANAGEMENT BASICS PROJECT MANAGEMENT BASICS Rick Panos AIA, CCM Director of Construction Management Totum Consulting Gary Cardamone, P.E., FCMAA Principal, G J Cardamone Consulting, LLC Program Management Is.... In the

More information

Terms of Service. 1. Acceptance Of Terms. 2. Use Of Customer Information And Privacy Policy. 3. Ownership Of Site Content

Terms of Service. 1. Acceptance Of Terms. 2. Use Of Customer Information And Privacy Policy. 3. Ownership Of Site Content Terms of Service 1. Acceptance Of Terms IT4Professionals is an Internet-based Web site that offers webdesign, domain name registration, hosting, dynamic DNS, email and sms marketing, PC services and software

More information

INVITATION TO BID. Web and Application Development Services. Monday, February 23, 2015 at 10:00 AM

INVITATION TO BID. Web and Application Development Services. Monday, February 23, 2015 at 10:00 AM 200 GRAND RIVER, SUITE 203 Pg 1 of 11 BID: RFP-IT-0215-292 INVITATION TO BID ITEM: PreBid Conference: DEADLINE: BID OPENING: Web and Application Development Services Monday, February 9, 2015 at 11:00 AM

More information

Document B101 TM. Standard Form of Agreement Between Owner and Architect

Document B101 TM. Standard Form of Agreement Between Owner and Architect Document B101 TM 2007 Standard Form of Agreement Between Owner and Architect AGREEMENT made as of the day of in the year 2014 (In words, indicate day, month and year.) BETWEEN the Architect s client identified

More information

Employees have the right to appeal against any disciplinary warnings and dismissal.

Employees have the right to appeal against any disciplinary warnings and dismissal. ST JUST IN PENWITH TOWN COUNCIL DISCIPLINARY PROCEDURES Introduction This procedure is designed to help and encourage all employees to achieve and maintain acceptable standards of conduct and job performance.

More information

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF KANSAS

IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF KANSAS Case 5:13-cv-04137-JWL-JPO Document 16 Filed 02/04/14 Page 1 of 5 IN THE UNITED STATES DISTRICT COURT FOR THE DISTRICT OF KANSAS UNITED STATES OF AMERICA, for the use and benefit of LAWRENCE KEVIN WRIGHT,

More information

A Guide to Renovation and Repair Contract Warranties

A Guide to Renovation and Repair Contract Warranties A Guide to Renovation and Repair Contract Warranties By Gerald A. Dalrymple, PE A fter being retained to review the merits of several major disputes involving the scope of warranties in renovation and

More information