Walter Andreeff, BSc. Applied and Environmental Geology

Size: px
Start display at page:

Download "Walter Andreeff, BSc. Applied and Environmental Geology"

Transcription

1 The Peace River Environmental Society Apri1 4, 2013 Ms. Linda Jones, Panel Manager Review Panels Canadian Environmental Assessment Agency 22 nd. Floor, 160 Elgin Street Ottawa, Ontario K1A 0H3 Mr. Brian Murphy, Executive Project Director BC Environmental Assessment Office PO Box 9426 Stn Prov Govt Victoria, BC V8W 9V1 Dear Ms. Jones and Mr. Murphy: The Peace River Environmental Society has reviewed the subject matter of the EIS and have noted the following concerns: Walter Andreeff, BSc. Applied and Environmental Geology Volume 1: Introduction, Project Planning, and Description Dam Safety Operations, Maintenance and Surveillance Manuals are required to follow the CDA Dam Safety Guidelines (CDA 2007). In the CDA 2007 guide under data requirements for Operations (3.4.2) it is noted that the Dam operator should consider obtaining data for certain aspects of Dam surveillance such as headwater, tail water elevations, flow data, etc. and install the means to gauge flow volumes. It is noted in (Volume 5) that the flows for 1986 were excluded from the Flood frequency analysis of the site C catchment area because of missing records. This suggests that the maintenance and/or surveillance documentation system may not have been fully functional at that time. As noted in of the CDA 2007, the dam owner should establish a procedure to document findings.that require follow-up action.

2 How does the project proponent ensure that Peace River Dam safety systems and required operating, maintenance and surveillance procedures for each dam are audited and inspected? What is the frequency of dam safety audits and are they undertaken by an external third party arms-length organization? What is the historical record of safety evaluations and audits undertaken at all the Dams upstream of the proposed Site C dam project and what does it imply for start-up and normal operations of the proposed dam? References: Canadian Dam Association (CDA), 2007a. Surveillance of Dam Facilities. Volume 2: Assessment Methodology and Environmental Effects Assessment Regional Bedrock Geology and Dam Site Geology CDA 2007 states that the Geotechnical assessment review many types of available information including air photos and other maps along with site reconnaissance. In this instance the EIS need to consider additional work on the underlying geology of the project area. Both sections of the EIS omit a prominent geological feature known as the Peace River Arch that underlies the bedrock units in the technical study area and location of the Site C dam states that tectonic activity has had little effect on the rocks of the proposed Reservoir area but in fact Peace River Arch (PRA) Geological features have been mapped and interpreted as influencing the path of river courses such as the Moberly River and the Peace River near the proposed Site C dam location. In a February 2009 article in the Canadian Society of Petroleum Geologists (CSPG) Reservoir, the writers suggest that several structural elements are easily identified in interpreting High Resolution Aeromagnetic (HRAM) surveys of the PRA area. They further interpret that many structural geological features such as normal, strike-slip faults, pull-apart basins and detached thrust faults can also be observed through HRAM survey. This suggests there is more complex geological story involving tectonic elements that requires further scientific investigation to determine potential tectonic feature impacts to the Site C Dam. I note that in EIS Figures and there is little definition of the number, length or orientation of the PRA faults.

3 Figure 1: Figure 5 from the 2009 CSPG Reservoir. A geological and geophysical data interpretation of the Monias area. This data includes: a seismic line across the Monias field (5A). An HRAM image showing the magnetic expressions of near-surface faults and their relationships to known producing fields (5B). Surface structure map of the Wilder field, which was interpreted from stereo photography (5C) and Landsat imagery showing the surface expression of Wilder Field (5D). Unfortunately, geological structural data such as strike and dip readings nor other typical geological information is available in the EIS for technical review and analysis although it is evident that information has been collected at several site locations. The cross section of Figure does not provide a map to provide the location of the cross section on any map nor the linear orientation of the cross section. Also, The Little Ricky Shear noted on the cross section figure should be described and dip, strike details of the shear be made available. There are also several cross sections denoted as A-A, B-B, D-D and MR-1L that are not in Vol. 2, Appendix B, Geology and Terrain, Part 2 Preliminary Reservoir Impact Lines in the required section of Drawing 13. References: Berger, Zeev, M. Boast, and M. Mushayandebvu, February, 2009, Reservoir Issue 2. The monthly magazine of Canadian Society of Petroleum Geologists, Pp Canadian Dam Association (CDA), 2007b. Geotechnical Considerations for Dam Safety. Landslide inventory The landslide inventory should include an assessment of slides from the Alberta Region. The Eureka River Slide of June 1990 at 50 Million cubic meters of landslide material is one of the seven largest translational landslides to have occurred in the Peace River area within the last 65 years. According to the authors, the texture and Atterberg limits of the sample of preglacial

4 lacustrine sediment collected at the Eureka River landslide are within the range of values found at the Attachie landslide.. This would suggest that these features, although a distance from the proposed Dam location site, should be included in the EIS to better understand the Peace River regional features of the surficial Geology and gain a greater understanding of landslide effects to the Site C project. References: B.G.N. Miller., D.M. Cruden. 2002, The Eureka River landslide and dam, Peace River Lowlands, Alberta, Pp Accessed at the NRC Research Press Web site. Regional Seismicity In this section (line s 39-40) it is noted that no faults in the Peace River Embayment are reported to extend into the Middle or upper Cenozoic. I point out that the Shaftesbury and Dunvegan formations were deposited during the Mesozoic era and faults have been mapped in the late cretaceous rocks of the Dawson Creek Graben. Therefore there may be evidence of faulting due to the tectonic activity within the area of the PRA on formations deposited during the Mesozoic and Paleozoic era that are underneath the base of the proposed Dam location Seismic Hazard Assessment Lines 9-40 lists the experience and proficiency of professionals who were involved in undertaking the Hazard assessment. However, the proceedings of those meeting s and related documented interactions with the project proponent are not available for public review. Nor are there adequate resources and review time supplied by the project proponent to stakeholder professional s or other representatives to properly assess the work of the Hazard Assessment team(s). Without the openness of peer review and public disclosure of the data and information to the private, public sector or academia the public cannot be assured the work was completed in the public interest. Petroleum Industry-Related Activities that may affect Seismicity Information stated in this section on hydraulic fracking suggests that there is little risk to the public from activities yet it was made clear by a 2012 BC Oil and Gas commission report that 38 earthquakes were induced by movements on pre-existing faults due to fluid injection during fracking activities. It is important to note that the area where these earthquakes occurred were remote unpopulated areas of north east BC therefore the public was unlikely at risk. However, within 100 km s of the Site C Dam there are several Oil and Gas development area s that use hydraulic fracking. Given that the research, experience with horizontal well drilling and fracking is relatively young (2005) within the BC Oil and Gas industry and the effects or impacts are not fully understood it may be prudent to limit fracking

5 activities near the dam location during and after the filling of the Site C Dam reservoir for a period of time. Real time Monitoring of potential ground movement s on or near the Moberly River and Tea Creek landslide area s during fracking activities would be prudent when water saturation values in the subsurface are higher than normal due to abnormal precipitation occurrence s. A report and several maps produced in October 2012 on the Montney formation in north east BC by the BC OGC noted several gas pools and new 2012 subsurface land sales near the area of the proposed dam and reservoir. Reservoir development of the Montney depends on fracking and horizontal drilling technology therefore it needs good oversight by the BC Oil and Gas Commission as the Montney play is developed in this area. Figure 2 Montney unconventional play trend 2012 (grey slant lines) Montney horizontal wells are darker grey

6 Figure 3 Montney pools denoted as red circles Figure Montney land sales in red Note subsurface land sales near the Site C dam location References: BC Oil and Gas Commission, August 2012, Investigation of the Observed Seismicity in the Horn river Basin. BC Oil and Gas Commission, October 2012, Montney Formation Play Atlas NEBC.

7 Volume 2: Appendix B Geology, Terrain and Soil, Part 2 Preliminary Reservoir Impact Lines: Bedrock Geology The report section references that past tectonic activity has had little effect on the rocks of the proposed reservoir area. (Pp. 10) However, I believe further field investigation, documentation research and Geological modeling is required. A 2008 report wrote on the reactivation of subsurface faults during the upper cretaceous time period located in the Dawson Creek Graben complex near the Site C location. The study focused mainly on North West Alberta in the subsurface area of the Peace River Arch (PRA). It is well known the PRA is present in North East BC and North West Alberta suggesting that faults in Alberta in the PRA may also be present in the Cretaceous rock of the bedrock underlying the Site C dam location. Figure 4 Note the lineament trending north south above the 7 and the photo 3 displayed below located near the Montagnuese River. Some brief field investigations in the areas of the Montagnuese River and the Peace River valley South West and North West of Fairview Alberta were undertaken in August 2012.

8 The Peace River valley is about 200 meters deep at this location and access to the area is west of secondary road 729. Several photos were taken of the west side of the Peace River of a linear feature at the surface that can be observed on satellite images and on maps. The feature is over 2.5 kilometers long and appears from an observation distance of 4 km s as if a block of material separated from the west valley wall of the Peace River and moved downwards towards the river. The location of the feature is N and W. Also, the direction orientation of the feature appears to strike parallel to the direction of the Montagnuese River. Further site investigation should assist to classify the type of landslide. Photo 1 Observing downstream to the South West Photo 2 Observing to the West

9 Photo 3 Looking to the North West A report published by TUL Petroleum Ltd. stated that the Montagnuese river is underlain by an deep basement fault. A paper from the CSPG (O Connell et al., Vol 38A, Pp. 76) noted the same fault on a structural contour map of the Precambrian surface. If the fault in the river valley is the same fault that may have enabled the landslide mentioned previously it suggests this may be evidence of the surface expression of a deep fault currently impacting the Peace River valley. Combined with studies mentioned earlier on small faulting in Cretaceous rocks it suggests that the Peace River Arch needs to be further defined and researched beneath the Site C Dam location. References: Stapleton, Murray J., 1997, Lamprophyres of the Peace River District, TUL Petroleums Ltd., Peace Diamond Project Assessment Work Report No A. Mei, Shilong. 2007, Updates on Faults and Structural Framework of the Peace River Arch Region, Northwest Alberta, Obtained using a New Approach, 2007 CSPG CSEG Convention, Pp Eaton, D., Hope, J., and Ross, G The rise and fall of a cratonic arch: A regional seismic perspective on the Peace River Arch, Alberta Bulletin of Canadian Petroleum Geology, VOL. 47, NO. 4 (DECEMBER, 1999), P Background on Landslides in the Peace River Valley 4.1 As written, landslides investigations have taken place between Hudson s Hope and the BC/Alberta Border. There is mention of some landslide investigations in Alberta but the locations are not listed. Why are the landslide investigations in Alberta not part of the report and included in the EIS? What is required to disclose this information in the Site C Dam EIS. Seismicity Table 9-3 pseudo-static seismic analyses assumes firm ground conditions at each cross section location. PGA values are based on firm ground conditions when we know ground conditions can vary at each cross section location. Why are firm ground condition s assumed for the application of the 2010 NBCC seismic calculator and why is

10 a conservative approached used when there might be uncertainties in the input of the scenario calculations? Table 9-2 lists shear strength parameters that have different values for a diverse set of surface materials and Table 9-1 lists a summary of 13 scenarios of stability analysis. It s not clear to me how Table 9-1 that are determined by different software packages such as Slide and Seep/W are used as input into Table 9-3. Are there any uncertainty ranges in this methodology and are the uncertainties taken into account in calculating the Table 9-3 results? Also, I note that Table 9-3 uses the Median hazard value when the 2007 Dam Safety Guidelines recommend the use of Mean value. What were the rationale in using the Median value? References: Canadian Dam Association (CDA), 2007c. Seismic Hazard Considerations for Dam Safety. Volume 5: Requirements for the Federal Environmental Assessment: Seismic Data This section refers the EIS reviewer to the Project Proponents (BC Hydro) science and engineering review reports in the EIS rather than conducting a separate science based research and review of the project as the responsible federal crown agency. Given the interprovincial aspect of the water flow from BC to Alberta, the continuation of subsurface geological features, the impacts to the local economies, and indirect and direct effects including cumulative impacts across interprovincial boundaries, the crown has not applied the due diligence required in managing the assessment of this project for the people of Canada nor the people of Alberta downstream from the Site C dam. Seismic Activity No comments are supplied in the EIS. Accordingly, the crown has not conducted a separate science based research and review of the project as the responsible federal crown agency. Given the interprovincial aspect of the water flow from BC to Alberta, the continuation of subsurface geological features, the impacts to the local economies, and indirect and direct effects including cumulative impacts across interprovincial boundaries, the crown has not applied the due diligence required in managing the assessment of this project for the people of Canada nor the people of Alberta downstream from the Site C dam. Earthfill Dams This was a great job. Very impressive interesting reading.

11 Teunis H. op ten Noort, Ir (MSc.) Engineer Dam Breaching Scenarios I have updated my comments, mainly because I fail to understand some result of the dam breach analyses, notably Vol 5 Tables (pp37-56/57/58). How can a Sunny Day situation yield to higher peak flood flows at Site C than the inflowing Probable Maximum Flood (PMF), which is much higher by definition? Unless the breach parameters are completely different. But BC Hydro does not mention them in detail). I only considered Site C, but of course this also holds for the situation further downstream. When W.A.C Bennett Dam (WACBD) and probably Peace Canyon Dam (PCN) as well were designed, similar dam breach investigations may have been modelled. But I would recommend strongly that this exercise for WACBD be repeated since the downstream situation is going to change considerably with the construction of Site C. The effect of WACBD breaching and consequently the other dams in the cascade, PCN and Site C, could have dire consequences for the communities downstream, much more than what has been modelled in Vol 5 Sec I would recommend they use the Sunny Day and PMF situations at WACBD. It is possible that the PMF for WACDB must be updated (Probable Maximum Precipitation, UBC Watershed, etc.), and of course severe inflow from the local catchment between WACDB and Site C must also be included in the analysis. The modelling of this series of events would not be difficult as they have already have the model and the data. EPP (Emergency Preparedness Plan) I had a look at the BC Dam Safety Regulations of 2000, including amendments up to 30 Nov 2011, which are, fortunately, directly available from the internet. There it is specified under EPP that: 3.1 (1) A dam owner of a dam that has a classification of significant, high, very high or extreme must, in the form and manner and within the time period specified by the comptroller or regional water manager, (a) prepare a plan that describes the actions to be taken by the dam owner in the event of an emergency at the dam, and (b) submit the plan to a dam safety officer for acceptance by the dam safety officer. (2) Subsection (1) applies whether or not there is a term or condition in an approval granted or licence issued that requires the preparation of such a plan for the dam. (3) A dam owner of a dam that has a classification of significant, high, very high or extreme must (a) review, and revise if necessary, the emergency preparedness plan for the dam no less frequently than is specified for the classification of the dam in items 5 and 6 in the Schedule 2 table, and (b) submit any revisions to a dam safety officer for acceptance by the dam safety officer. [en. B.C. Reg. 108/2011, App. 1, s. 4.]

12 The specific Emergency Preparedness Process (EPP) for Site C has not yet been presented in the EIS but we expect it will be prescriptive and thorough as described in the 2007 Dam Safety Guidelines sections 1.3, 4.0, and General Throughout the report(s) is mentioned... Maintenance policies and procedures would be implemented to ensure that structures and equipment are maintained in a safe operating condition." (Vol 1 page4-66 line7) I stress the... would be... This is just an example. The question is: who will implement it and when, and who is to check it? What happens if it is not done? Who is to monitor this? Drainage areas mentioned, notably at the key points Bennett Dam, PCN and Site C are not univocal. E.g. In Vol 1 Appendix E Sec 6.1 (page 25) The contributing drainage are at PCN is sq km, in the Water Use Plan (page 4) it is sq km and in Vol2 App I page 6 it is sq km. I did not locate any references made to the future decommissioning when the Site C Dam is at the end of service. As mankind is progressing to find new alternate forms of energy use, decommissioning is a serious option which should be estimated and included in the economic analyses. GHG (Green House Gases) Vol1 Appendix D Pp. 3 upper right corner. Another point is that the EIS states that there are no Green House Gas (GHG) emission s for new projects! Apart from emissions during construction, including fabrication of equipment which would happen with any energy generating project there are numerous GHGs emissions. Only after 30 years or later, are the GHGs more or less equal to the emssion s of a natural lake. In the same context I don't understand why a Canada Boreal Hydroelectric plant would produce more GHGs than the Site C Dam would. Isn't Site C also considered a boreal area (the colder climate the less GHG), see Vol 1 p7-21 Table 7.14 first 2 lines? Also compare Vol 2 p15-16 Table 15.8 last line with the first line in Table The figures in Table 15.8 are much higher than those in What is the reason for this? ENVIRONMENTAL IMPACT STATEMENT (EIS) COMMENT TABLE Name of Party Providing the Comment(s): Teunis H. op ten Noort for the Peace River Environmental Society EIS Volume # and # Page # Line # Comment # Comment Volume 1, Where are the Emergency EIS Guidelines (where relevant)

13 EIS Volume # and # Page # Line # Comment # Comment Preparedness Plans? Volume 1, Figures Fig The cross-sections do not show the following levels: top of radial gates, bottom of radial gates and Volume 2, Appendix I Volume 2, Appendix I and further crest level of auxiliary spillway 54 N/A 3 2) Runoff from onshore construction activities around the dam site These sediment inputs have not been explicitly estimated at this time. These inputs would need to be kept below the effluent criteria to be set out in the Environmental Management Plan. This has to be checked and monitored 55 N/A 4 The estimated total fine sediment input from in stream construction activities during the eight-year construction phase ranges from approximately 18,000 tonnes to 30,000 tonnes. For comparison, the mean annual suspended sediment load in the Peace River is 1.36 million tonnes/yr (at Site C).), It will drop considerably during filling of the reservoir and the period thereafter. This gives rise to degradation the first km d/s of the dam Who will ensure that these plans are made and adhered to? Where is Chapter 9.1.4? , Is there a case where the wave generated by 1000-yr wind is smaller than the one generated by a 100km/h wind? 8 Reference is made to the wrong 9 Reference is made to the wrong , All references made to xxxxx are wrong and should be rectified. (as in comments 7 and 8) The peak PMF inflow is given as 19,300 m 3 /s. However, in Vol1, Appendix E, 6.2, p 25 the EIS Guidelines (where relevant)

14 EIS Volume # and # and further in general Page # Line # Comment # Comment PMF inflow (peak) is given as 20,810 m 3 /s (+7.8%). Which one is correct, and used in the calculations? All references made to xxxxx are wrong and should be rectified Reference is made to the wrong 37-56/47/58 14 Table 37.18: Needs an explanation why the Peak Flood Flow at Site C = m 3 /s compared to m 3 /s and m 3 /s in Table and respectively. Apart from the very high figure in Table which could be the result of an instant breach (please explain), explain why there is little difference in the w/ and w/o project situation. Table 37.21: If all outlet systems including turbines fail and the earth dam gets overtopped, please explain why the peak flood flow is higher than the PMF (even if the retarding effect of Site C reservoir is neglected) Reference is made to the wrong Figure Reference is made to the wrong 17 Consequences of PMF and Dam breaches are calculated but nowhere is indicated what mitigating measures are going to be taken, neither in BC nor in Alberta. Is this (going to be) part of the Emergency Preparedness Plans? In my opinion the population deserves to be informed of what they could expect in some future disastrous situation before the construction of Site C EIS Guidelines (where relevant)

Site C Clean Energy Project Topic Specific Sessions: Presentation by Natural Resources Canada

Site C Clean Energy Project Topic Specific Sessions: Presentation by Natural Resources Canada Site C Clean Energy Project Topic Specific Sessions: Presentation by Natural Resources Canada Fort St. John, British Columbia January 13, 2014 Outline 1. Context for NRCan s Participation in the Joint

More information

The correct answers are given below. Some talking points have been added for the teachers use.

The correct answers are given below. Some talking points have been added for the teachers use. Natural Resources Canada 2011: Lesson Plan Grades 11 and 12 Landslide activity 5b: Landslides in Canada quiz Description: This is an independent study activity for grades 11 and 12. Students will read

More information

Management of flooding downstream of dams

Management of flooding downstream of dams Management of flooding downstream of dams Attachment to Victoria State Flood Emergency Plan Version 1.0 (6 February 2013) This plan is produced by the Victoria State Emergency Service and Department of

More information

CHAPTER 9 CONCLUSIONS AND RECOMMENDED MITIGATION

CHAPTER 9 CONCLUSIONS AND RECOMMENDED MITIGATION CHAPTER 9 CONCLUSIONS AND RECOMMENDED MITIGATION 9.1 Conclusions Based on the stability cross-sections down the SE flank of Snodgrass Mountain, most landslides on low- to moderate-gradient slopes have

More information

Small Dam Hazard Assessment Inventory

Small Dam Hazard Assessment Inventory Small Dam Hazard Assessment Inventory What would happen if your dam were to fail? This is a question that most dam owners hope they will never have to answer. However it is a question you, as a responsible

More information

FERC Engineering Guidelines Risk-Informed Decision Making

FERC Engineering Guidelines Risk-Informed Decision Making FERC Engineering Guidelines Risk-Informed Decision Making Chapter R1 Introduction to Risk-Informed Decision Making Chapter R1, Risk-Informed Decision Making Table of Contents Chapter R1 Introduction to

More information

Flood mitigation program for Gatun lake. Programa de mitigación de inundaciones del lago Gatún

Flood mitigation program for Gatun lake. Programa de mitigación de inundaciones del lago Gatún Flood mitigation program for Gatun lake Programa de mitigación de inundaciones del lago Gatún Moffatt & Nichol Engineers 10 de febrero de 2005 Contrato No. 126161 Introducción y Recomendaciones 1 INTRODUCTION

More information

ICOLD POSITION PAPER ON DAM SAFETY AND EARTHQUAKES

ICOLD POSITION PAPER ON DAM SAFETY AND EARTHQUAKES ICOLD POSITION PAPER ON DAM SAFETY AND EARTHQUAKES August 2012 Dam Safety and Earthquakes Position Paper of International Commission on Large Dams (ICOLD) Prepared by ICOLD Committee on Seismic Aspects

More information

Safety of Small/Rural Dams and Barrier Lake Management

Safety of Small/Rural Dams and Barrier Lake Management Safety of Small/Rural Dams and Barrier Lake Management A. Introduction 1. Lessons learnt and recommendations are provided for artificial dams and barrier lakes. In the case of artificial dams, emphasis

More information

WILLOCHRA BASIN GROUNDWATER STATUS REPORT 2009-10

WILLOCHRA BASIN GROUNDWATER STATUS REPORT 2009-10 WILLOCHRA BASIN GROUNDWATER STATUS REPORT 2009-10 SUMMARY 2009-10 The Willochra Basin is situated in the southern Flinders Ranges in the Mid-North of South Australia, approximately 50 km east of Port Augusta

More information

Interim Technical Guidelines for the Development of Environmental Management Plans for Underground Infrastructure Revised - July 2013.

Interim Technical Guidelines for the Development of Environmental Management Plans for Underground Infrastructure Revised - July 2013. Interim Technical Guidelines for the Development of Environmental Management Plans for Underground Infrastructure Revised - July 2013 Rationale Underground infrastructure may be at risk from valley, streambank

More information

Avison Management Services Ltd. COMPANY PROFILE

Avison Management Services Ltd. COMPANY PROFILE Avison Management Services Ltd. COMPANY PROFILE Providing resource management through environmental leadership. Mission Statement: We are committed to providing high quality, timely, and cost effective

More information

Watershed Rehabilitation Program in Texas

Watershed Rehabilitation Program in Texas Watershed Rehabilitation Program in Texas 1 Dams Constructed by Year (nationwide) 700 600 500 PL-566 Pilot/RC&D PL-534 400 300 200 100 0 48 51 54 57 60 63 66 69 72 75 78 81 84 87 90 93 96 99 Year 2 Number

More information

EcoInformatics International Inc.

EcoInformatics International Inc. 1 von 10 03.08.2010 14:25 EcoInformatics International Inc. Home Services - solutions Projects Concepts Tools Links Contact EXPLORING BEAVER HABITAT AND DISTRIBUTION WITH GOOGLE EARTH: THE LONGEST BEAVER

More information

Strategy and Procedures for Compliance and Enforcement

Strategy and Procedures for Compliance and Enforcement Strategy and Procedures for Compliance and Enforcement Dam Safety Program Ministry of Forests, Lands and Natural Resource Operations Last Update: November 2014 A Dam Safety Compliance & Enforcement Policy

More information

Dip is the vertical angle perpendicular to strike between the imaginary horizontal plane and the inclined planar geological feature.

Dip is the vertical angle perpendicular to strike between the imaginary horizontal plane and the inclined planar geological feature. Geological Visualization Tools and Structural Geology Geologists use several visualization tools to understand rock outcrop relationships, regional patterns and subsurface geology in 3D and 4D. Geological

More information

Information Request 14

Information Request 14 Information Request 14 Information Request 14 14-1 Responses to Information Request 14 Response to Information Request 14a Response to Information Request 14b Response to Information Request 14c Response

More information

APPENDIX F. Baker County. Mason Dam Hydroelectric Project FERC No. P-12686. Turbidity Monitoring Plan

APPENDIX F. Baker County. Mason Dam Hydroelectric Project FERC No. P-12686. Turbidity Monitoring Plan APPENDIX F Baker County Mason Dam Hydroelectric Project FERC No. P-12686 Turbidity Monitoring Plan April 2011 857 Table of Contents 1.0 Introduction 1 2.0 Purpose and Scope 2 3.0 Turbidity Monitoring and

More information

Appendix B. Introduction to Landslide Evaluation Tools Mapping, Remote Sensing, and Monitoring of Landslides

Appendix B. Introduction to Landslide Evaluation Tools Mapping, Remote Sensing, and Monitoring of Landslides Appendix B. Introduction to Landslide Evaluation Tools Mapping, Remote Sensing, and Monitoring of Landslides 66 The Landslide Handbook A Guide to Understanding Landslides Part 1. Mapping Maps are a useful

More information

AMEC 6007: Linear Velocity and Acceleration Learning Outcome. CHEM 6012: Oil and Gas Compositions and Sales Specifications Learning Outcome

AMEC 6007: Linear Velocity and Acceleration Learning Outcome. CHEM 6012: Oil and Gas Compositions and Sales Specifications Learning Outcome s/objectives Level F ADMN 6044: Post Job Management It is important to know the proper procedures for closing out a job so that rigging and equipment is maintained for future use and personnel are adequately

More information

6.0 Results of Risk Analyses

6.0 Results of Risk Analyses 6. Results of Risk Analyses A risk analysis of the optimized embankment designs for the Salton Sea restoration project was conducted jointly by Kleinfelder and representatives from Reclamation. A risk

More information

Fort Dodge Stormwater Master Planning. Prepared By: Ralph C. Stark, Jr., P.E., C.F.M. Joel N. Krause, P.E., C.F.M.

Fort Dodge Stormwater Master Planning. Prepared By: Ralph C. Stark, Jr., P.E., C.F.M. Joel N. Krause, P.E., C.F.M. Fort Dodge Stormwater Master Planning Prepared By: Ralph C. Stark, Jr., P.E., C.F.M. Joel N. Krause, P.E., C.F.M. Project Location Project Background Flooding History Localized flooding and storm sewer

More information

Guidelines. Legislated Landslide Assessments. Proposed Residential Developments. in BC. for. for. Revised May 2010 APEGBC

Guidelines. Legislated Landslide Assessments. Proposed Residential Developments. in BC. for. for. Revised May 2010 APEGBC Guidelines for Legislated Landslide Assessments for Proposed Residential Developments in BC Association of Professional Engineers and Geoscientists of British Columbia Revised May 2010 APEGBC TABLE OF

More information

WETLAND RESTORATION PROGRAM WATER ACT APPROVAL ADMINISTRATIVE GUIDE

WETLAND RESTORATION PROGRAM WATER ACT APPROVAL ADMINISTRATIVE GUIDE WETLAND RESTORATION PROGRAM WATER ACT APPROVAL ADMINISTRATIVE GUIDE May 24, 2005 Table of Contents Introduction...3 Definitions...3 Types of Wetland Restorations...4 Re-Contouring...4 Engineered...4 Water

More information

USACE Dam Safety Program Current Approach & Methodology

USACE Dam Safety Program Current Approach & Methodology USACE Dam Safety Program Current Approach & Methodology Siamac Vaghar, PE, MASCE Chief, Geotechnical Engineering Section Dam Safety Program Manager US Army Corps of Engineers New England District Corps

More information

INTERPRETATION ADDENDUM CANADIAN MINING COMPANY INC. SUITE 2300-1066 WEST HASTINGS STREET VANCOUVER, BC V6E 3X2 3D INDUCED POLARIZATION

INTERPRETATION ADDENDUM CANADIAN MINING COMPANY INC. SUITE 2300-1066 WEST HASTINGS STREET VANCOUVER, BC V6E 3X2 3D INDUCED POLARIZATION INTERPRETATION ADDENDUM FOR CANADIAN MINING COMPANY INC. SUITE 2300-1066 WEST HASTINGS STREET VANCOUVER, BC V6E 3X2 3D INDUCED POLARIZATION ON THE SAN BERNARDO PROJECT EL GOCHICO GRID Approximate Location:

More information

Emergency Spillways (Sediment basins)

Emergency Spillways (Sediment basins) Emergency Spillways (Sediment basins) DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short-Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]

More information

IUCN Guidelines to Avoid Impacts of Water Resources Projects on Dams and Other Water Infrastructure

IUCN Guidelines to Avoid Impacts of Water Resources Projects on Dams and Other Water Infrastructure IUCN Guidelines to Avoid Impacts of Water Resources Projects on Dams and Other Water Infrastructure (December 2013) IUCN does not engage in projects which involve the design, construction or rehabilitation

More information

Frequently Asked Questions (FAQs) on Hydropower

Frequently Asked Questions (FAQs) on Hydropower Frequently Asked Questions (FAQs) on Hydropower What are the advantages of Hydropower? A renewable source of energy - saves scarce fuel reserves. Non-polluting and hence environment friendly. Long life

More information

Ministry of Natural Gas Development. Guide to Oil and Gas Land Plats and Tenure Areas

Ministry of Natural Gas Development. Guide to Oil and Gas Land Plats and Tenure Areas Ministry of Natural Gas Development Guide to Oil and Gas Land Plats and Tenure Areas Approved by: Inés Piccinino Assistant Deputy Minister Upstream Development Division October 2015 Summary of Revisions

More information

PRELIMINARY REPORT ON THE NORTHSTAR #1 CLASS II INJECTION WELL AND THE SEISMIC EVENTS IN THE YOUNGSTOWN, OHIO AREA

PRELIMINARY REPORT ON THE NORTHSTAR #1 CLASS II INJECTION WELL AND THE SEISMIC EVENTS IN THE YOUNGSTOWN, OHIO AREA PRELIMINARY REPORT ON THE NORTHSTAR #1 CLASS II INJECTION WELL AND THE SEISMIC EVENTS IN THE YOUNGSTOWN, OHIO AREA Tom Tomastik, Geologist, ODNR, Division of Oil and Gas Resources Management PURPOSE AND

More information

From: Jean Hicks [ ] Sent: May 4, 2012 10:55 AM To: SiteC Review / Examen SiteC [CEAA] Subject: Public Submission

From: Jean Hicks [ ] Sent: May 4, 2012 10:55 AM To: SiteC Review / Examen SiteC [CEAA] Subject: Public Submission From: Jean Hicks [ ] Sent: May 4, 2012 10:55 AM To: SiteC Review / Examen SiteC [CEAA] Subject: Public Submission Canadian Environmental Assessment Agency: Please find comments as attached. The second

More information

Queensland Dam Safety Management Guidelines. February 2002

Queensland Dam Safety Management Guidelines. February 2002 Queensland Dam Safety Management Guidelines February 2002 QNRM02013 ISBN 0 7345 2633 4 The State of Queensland (Department of Natural Resources and Mines) 2002 Copyright protects this publication. Except

More information

Integrated Water and Sediment Management of Yellow River

Integrated Water and Sediment Management of Yellow River Keeping Health Life of Yellow River: Integrated Water and Sediment Management of Yellow River Shang Hongqi Yellow River Conservancy Commission 18 March 2009 Istanbul, Turkey Outline: I. Yellow River Characteristic

More information

HUDSON RIVER-BLACK RIVER REGULATING DISTRICT BOARD MEETING JUNE 10, 2014

HUDSON RIVER-BLACK RIVER REGULATING DISTRICT BOARD MEETING JUNE 10, 2014 HUDSON RIVER-BLACK RIVER REGULATING DISTRICT BOARD MEETING JUNE 10, 2014 PRESENTATION TOPICS Analysis Objectives Analysis Dam Removal Plan Dam Remediation Plan Effects Analysis Permit Requirements Decision

More information

Burnt River Black River and Gull River Flood Contingency Plan

Burnt River Black River and Gull River Flood Contingency Plan Burnt River Black River and Gull River Flood Contingency Plan Objective: The objective of this plan is to preplan and prepare for flooding events in the Burnt River, Black River and Gull River area of

More information

How To Fix A Creek In Sandon

How To Fix A Creek In Sandon Valhalla Wilderness Society Box 329, New Denver, British Columbia, Canada V0G 1S0 Phone: (250) 358-2333, Fax: (250) 358-7950, E-mail: vws@vws.org, Web: http://www.vws.org Robyn Roome Regional Director,

More information

Jackson Gulch Outlet Canal Rehabilitation Project

Jackson Gulch Outlet Canal Rehabilitation Project Jackson Gulch Outlet Canal Rehabilitation Project Preliminary Budgetary Estimate for Rehabilitation February 2004 Prepared for the Mancos Water Conservancy District Jackson Gulch Reservoir 42888 County

More information

Engineering Geological Asset Management for Large Dams. Yasuhito SASAKI (1)

Engineering Geological Asset Management for Large Dams. Yasuhito SASAKI (1) Engineering Geological Asset Management for Large Dams Yasuhito SASAKI (1) (1) Geology Research Team, Public Works Research Institute, Japan E-mail:ya-sasa@pwri.go.jp Abstract Comprehensive inspection

More information

Woodfibre Liquefied Natural Gas (LNG) Project. Review of Related Upstream Greenhouse Gas (GHG) Emissions Estimates

Woodfibre Liquefied Natural Gas (LNG) Project. Review of Related Upstream Greenhouse Gas (GHG) Emissions Estimates 1 February 2016 Woodfibre Liquefied Natural Gas (LNG) Project Review of Related Upstream Greenhouse Gas (GHG) Emissions Estimates Summary The Canadian Environmental Assessment Agency (the Agency) sought

More information

NAPA COUNTY WATERSHED SYMPOSIUM

NAPA COUNTY WATERSHED SYMPOSIUM Planning, Building, and Environmental Services NAPA VALLEY GROWTH NAPA COUNTY WATERSHED SYMPOSIUM Plunging Forward May 15, 2015 1 YOU CAN T CROSS THE SEA MERELY BY STANDING AND STARING AT THE WATER. Rabindranath

More information

Plate Tectonics: Ridges, Transform Faults and Subduction Zones

Plate Tectonics: Ridges, Transform Faults and Subduction Zones Plate Tectonics: Ridges, Transform Faults and Subduction Zones Goals of this exercise: 1. review the major physiographic features of the ocean basins 2. investigate the creation of oceanic crust at mid-ocean

More information

Proposal for a RECOMMENDATION OF THE EUROPEAN COMMISSION

Proposal for a RECOMMENDATION OF THE EUROPEAN COMMISSION EUROPEAN COMMISSION Brussels, XXX [ ] (2013) XXX draft Proposal for a RECOMMENDATION OF THE EUROPEAN COMMISSION Providing minimum principles for the exploration and production of hydrocarbons (especially

More information

Re: File Number S7-29-07 Concept Release on Possible revisions to the Disclosure Requirements relating to Oil and Gas Reserves

Re: File Number S7-29-07 Concept Release on Possible revisions to the Disclosure Requirements relating to Oil and Gas Reserves Hugh L. Hooker Chief Compliance Officer, Corporate Secretary, Associate General Counsel Petro-Canada 37 th Floor, 150 6 th Avenue S.W. P.O. Box2844 Calgary, Alberta T2P 3E3 Telephone (403) 296-7778 Facsimile

More information

The AIR Inland Flood Model for the United States In Spring 2011, heavy rainfall and snowmelt produced massive flooding along the Mississippi River,

The AIR Inland Flood Model for the United States In Spring 2011, heavy rainfall and snowmelt produced massive flooding along the Mississippi River, The AIR Inland Flood Model for the United States In Spring 2011, heavy rainfall and snowmelt produced massive flooding along the Mississippi River, inundating huge swaths of land across seven states. As

More information

BLACK/HARMONY/FAREWELL CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT

BLACK/HARMONY/FAREWELL CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT Harmony Creek subwatershed Harmony Creek subwatershed BLACK/HARMONY/FAREWELL CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT April 2011 TABLE OF CONTENTS 1.0 INTRODUCTION...

More information

(1) Discuss the determination of the need for public visitation. Visitor center density within 100 miles.

(1) Discuss the determination of the need for public visitation. Visitor center density within 100 miles. Chapter 4 Specifications Designs 3. Visitors Centers 3. Visitors Centers. The Introduction (Chapter 1) for these design data collection guidelines contains additional information concerning: preparing

More information

Methods for Determination of Safe Yield and Compensation Water from Storage Reservoirs

Methods for Determination of Safe Yield and Compensation Water from Storage Reservoirs US Army Corps of Engineers Hydrologic Engineering Center Methods for Determination of Safe Yield and Compensation Water from Storage Reservoirs October 1966 Approved for Public Release. Distribution Unlimited.

More information

Hydrologic Engineering Techniques for Regional Water Resources Planning

Hydrologic Engineering Techniques for Regional Water Resources Planning US Army Corps of Engineers Hydrologic Engineering Center Hydrologic Engineering Techniques for Regional Water Resources Planning October 1969 Approved for Public Release. Distribution Unlimited. TP-17

More information

Appendix C - Risk Assessment: Technical Details. Appendix C - Risk Assessment: Technical Details

Appendix C - Risk Assessment: Technical Details. Appendix C - Risk Assessment: Technical Details Appendix C - Risk Assessment: Technical Details Page C1 C1 Surface Water Modelling 1. Introduction 1.1 BACKGROUND URS Scott Wilson has constructed 13 TUFLOW hydraulic models across the London Boroughs

More information

Risk and vulnerability assessment of the build environment in a dynamic changing society

Risk and vulnerability assessment of the build environment in a dynamic changing society Risk and vulnerability assessment of the build environment in a dynamic changing society Limnei Nie SINTEF Building and infrastructure, P.O.Box 124 Blindern, NO-0314 Oslo, Norway. linmei.nie@sintef.no

More information

DISASTER RISK DETECTION AND MANAGEMENT COURSES SETUP SCENARIO AT MAKERERE UNIVERSITY. Makerere University

DISASTER RISK DETECTION AND MANAGEMENT COURSES SETUP SCENARIO AT MAKERERE UNIVERSITY. Makerere University DISASTER RISK DETECTION AND MANAGEMENT COURSES SETUP SCENARIO AT MAKERERE UNIVERSITY CASE OF THE DEPARTMENT OF GEOGRAPHY Derek Muhwezi 2 MISSION OF THE DEPARTMENT To provide and promote quality education,

More information

Plan Plus Volume 1 No 1 2002 (117-123)

Plan Plus Volume 1 No 1 2002 (117-123) Plan Plus Volume 1 No 1 2002 (117-123) APPLICATION OF GIS (GEOGRAPHIC INFORMATION SYSTEM) FOR LANDSLIDE HAZARD ZONATION AND MAPPING DISASTER PRONE AREA: A STUDY OF KULEKHANI WATERSHED, NEPAL Purna Chandra

More information

REPORT TO REGIONAL WATER SUPPLY COMMISSION MEETING OF WEDNESDAY, SEPTEMBER 4, 2013 LEECH WATER SUPPLY AREA RESTORATION UPDATE

REPORT TO REGIONAL WATER SUPPLY COMMISSION MEETING OF WEDNESDAY, SEPTEMBER 4, 2013 LEECH WATER SUPPLY AREA RESTORATION UPDATE Making a difference... together Agenda Item #9 REPORT #RWSC 2013-17 REPORT TO REGIONAL WATER SUPPLY COMMISSION MEETING OF WEDNESDAY, SEPTEMBER 4, 2013 SUBJECT LEECH WATER SUPPLY AREA RESTORATION UPDATE

More information

The Geothermal Information System for Germany

The Geothermal Information System for Germany The Geothermal Information System for Germany www.geotis.de Britta Ganz T. Agemar, J. A. Alten, J. Kuder, K. Kühne, S. Schumacher & R. Schulz CGER Meeting 21 May 2012, Oslo Project Funding Partners Support

More information

LYNDE CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT

LYNDE CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT Whitby CLOCA Whitby CLOCA LYNDE CREEK WATERSHED EXISTING CONDITIONS REPORT CHAPTER 12 - STORMWATER MANAGEMENT June 2008 TABLE OF CONTENTS 1.0 INTRODUCTION... 3 2.0 STUDY AREA AND SCOPE... 4 3.0 METHODOLOGY...

More information

GEOTECHNICAL ISSUES OF LANDSLIDES CHARACTERISTICS MECHANISMS PREPARDNESS: BEFORE, DURING AND AFTER A LANDSLIDE QUESTIONS FOR DISCUSSIONS

GEOTECHNICAL ISSUES OF LANDSLIDES CHARACTERISTICS MECHANISMS PREPARDNESS: BEFORE, DURING AND AFTER A LANDSLIDE QUESTIONS FOR DISCUSSIONS GEOTECHNICAL ISSUES OF LANDSLIDES CHARACTERISTICS MECHANISMS PREPARDNESS: BEFORE, DURING AND AFTER A LANDSLIDE QUESTIONS FOR DISCUSSIONS Huge landslide Leyte, Phillipines, 1998 2000 casulties Small debris

More information

DYNAMIC CRUST: Unit 4 Exam Plate Tectonics and Earthquakes

DYNAMIC CRUST: Unit 4 Exam Plate Tectonics and Earthquakes DYNAMIC CRUST: Unit 4 Exam Plate Tectonics and Earthquakes NAME: BLOCK: DATE: 1. Base your answer to the following question on The block diagram below shows the boundary between two tectonic plates. Which

More information

Stream Rehabilitation Concepts, Guidelines and Examples. Objectives. Pierre Y. Julien. Three Laws of Stream Restoration

Stream Rehabilitation Concepts, Guidelines and Examples. Objectives. Pierre Y. Julien. Three Laws of Stream Restoration Stream Rehabilitation Concepts, Guidelines and Examples Pierre Y. Julien Wuhan 2005 Objectives Part I - Stream restoration and rehabilitation: 1. Present and discuss important concepts, laws, criteria

More information

Landslides & Mudflows

Landslides & Mudflows 1 2 - What is a Landslide? - Geologic hazard Common to almost all 50 states Annual global Billions in losses Thousands of deaths and injuries 3 1 - What is a Landslide? - Gravity is driving force Some

More information

Water Pricing under Bill 18 - BC Water Sustainability Act

Water Pricing under Bill 18 - BC Water Sustainability Act April 8, 2014 Ms. Lynn Kriwoken Director, Water Protection & Sustainability BC Ministry of Environment PO Box 9362 Stn Prov Govt Victoria British Columbia V8W 9M1 Dear Ms. Kriwoken: Re: Water Pricing under

More information

MANITOBA FLOOD PROTECTION PROJECTS Project Justification and Benefits. Science Imagination Collaboration

MANITOBA FLOOD PROTECTION PROJECTS Project Justification and Benefits. Science Imagination Collaboration MANITOBA FLOOD PROTECTION PROJECTS Project Justification and Benefits Science Imagination Collaboration Presentation Outline Extreme events on Red and Assiniboine Manitoba Flood Protection Works KGS Group

More information

SITE C CLEAN ENERGY PROJECT: BUSINESS CASE SUMMARY

SITE C CLEAN ENERGY PROJECT: BUSINESS CASE SUMMARY SITE C CLEAN ENERGY PROJECT: BUSINESS CASE SUMMARY UPDATED MAY 2014 A HERITAGE BUILT FOR GENERATIONS Clean, abundant electricity has been key to British Columbia s economic prosperity and quality of life

More information

Adaptive Management Measures under the Canadian Environmental Assessment Act

Adaptive Management Measures under the Canadian Environmental Assessment Act Operational Policy Statement Adaptive Management Measures under the Canadian Environmental Assessment Act Purpose This operational policy statement (OPS) provides best practice guidance on the use of adaptive

More information

./01&2/M./T34 1MP36T ST3T.M./T. 1a$t3l$4 536e-al4 13$7363 83%3te9. Sol9ara 1 Pro;ect. !"l$%e ( Mai$ &e(ort. Te-t. )e*te%,e- 2//0 :; <//0=>=?

./01&2/M./T34 1MP36T ST3T.M./T. 1a$t3l$4 536e-al4 13$7363 83%3te9. Sol9ara 1 Pro;ect. !l$%e ( Mai$ &e(ort. Te-t. )e*te%,e- 2//0 :; <//0=>=? ./01&2/M./T34 1MP36T ST3T.M./T 1a$t3l$4 536e-al4 13$7363 83%3te9 Sol9ara 1 Pro;ect!"l$%e ( Mai$ &e(ort Te-t )e*te%,e- 2//0 :; =?@ ENVIRONMENTAL IMPACT STATEMENT VOLUME A: MAIN REPORT TEXT CR 7008_09_v4

More information

3.3.9. Construction Phase Activities 3.3.9. Construction Phase Activities

3.3.9. Construction Phase Activities 3.3.9. Construction Phase Activities Site C Clean Energy Project to Advisory Working Group Comments on Draft Environmental Impact Statement Guidelines, Version 1 March 30, 2012 to Advisory Working Group Comments on Draft Environmental Impact

More information

Data Mining and Exploratory Statistics to Visualize Fractures and Migration Paths in the WCBS*

Data Mining and Exploratory Statistics to Visualize Fractures and Migration Paths in the WCBS* Data Mining and Exploratory Statistics to Visualize Fractures and Migration Paths in the WCBS* Jean-Yves Chatellier 1 and Michael Chatellier 2 Search and Discovery Article #41582 (2015) Posted February

More information

4. Environmental Impacts Assessment and Remediation Targets

4. Environmental Impacts Assessment and Remediation Targets 4. Environmental Impacts Assessment and Remediation Targets 4.1 Environmental Impacts Significant additional development in the Alder Creek watershed is not anticipated at this time; however, there are

More information

Sample DEQ Plan Submitter s Checklist for Stormwater Management Plans

Sample DEQ Plan Submitter s Checklist for Stormwater Management Plans APPENDIX IV Version: February 2, 2015 Sample DEQ Plan Submitter s Checklist for Stormwater Management Plans Please fill in all blanks and please reference the plan sheets/pages where the information may

More information

A Green Sector Overview

A Green Sector Overview A Green Sector Overview Micro Hydro Electric Power Ontario's Waterpower Resources: Past and Present The first hydroelectric generator in Canada was installed near Ottawa, which was the first city in North

More information

Environmental guidelines for preparation of an Environment Management Plan

Environmental guidelines for preparation of an Environment Management Plan Environmental guidelines for preparation of an Environment Management Plan Environment Protection Authority MAY 2013 Australian Capital Territory, Canberra 2013 This work is copyright. Apart from any use

More information

Black Mountain Reservoir Land Rezoning

Black Mountain Reservoir Land Rezoning Black Mountain Reservoir Rezoning Information Meeting Black Mountain Reservoir Rezoning 1.0 Black Mountain Reservoir What the reservoir provides The Black Mountain Reservoir will be a low-elevation raw

More information

The successful integration of 3D seismic into the mining process: Practical examples from Bowen Basin underground coal mines

The successful integration of 3D seismic into the mining process: Practical examples from Bowen Basin underground coal mines Geophysics 165 Troy Peters The successful integration of 3D seismic into the mining process: Practical examples from Bowen Basin underground coal mines This paper discusses how mine staff from a number

More information

US Army Corps of Engineers BUILDING STRONG

US Army Corps of Engineers BUILDING STRONG Fort Worth District Public Meeting 20 August 2013 US Army Corps of Engineers Lewisville Dam - Authorization Authorized by the River and Harbor Act, approved 2 March 1945 (Public Law 14, 79th Congress,

More information

Basement Flood Risk Reduction City of Winnipeg. Charles Boulet

Basement Flood Risk Reduction City of Winnipeg. Charles Boulet Basement Flood Risk Reduction City of Winnipeg Charles Boulet Outline Background Winnipeg Floodway Rain Events Winnipeg Sewer System Basement Flooding Flood Reduction Measures ICLR - BFRR Strategy 2 Where

More information

Guideline: Works that interfere with water in a watercourse watercourse diversions. September 2014

Guideline: Works that interfere with water in a watercourse watercourse diversions. September 2014 Guideline: Works that interfere with water in a watercourse watercourse diversions September 2014 This publication has been compiled by the Department of Natural Resources and Mines. State of Queensland,

More information

Abaya-Chamo Lakes Physical and Water Resources Characteristics, including Scenarios and Impacts

Abaya-Chamo Lakes Physical and Water Resources Characteristics, including Scenarios and Impacts LARS 2007 Catchment and Lake Research Abaya-Chamo Lakes Physical and Water Resources Characteristics, including Scenarios and Impacts Seleshi Bekele Awulachew International Water Management Institute Introduction

More information

HOMEOWNER S GUIDE. to LANDSLIDES. and MITIGATION RECOGNITION, PREVENTION, CONTROL, Compiled by Dr. Scott F. Burns Tessa M. Harden Carin J.

HOMEOWNER S GUIDE. to LANDSLIDES. and MITIGATION RECOGNITION, PREVENTION, CONTROL, Compiled by Dr. Scott F. Burns Tessa M. Harden Carin J. HOMEOWNER S GUIDE to LANDSLIDES RECOGNITION, PREVENTION, CONTROL, and MITIGATION Compiled by Dr. Scott F. Burns Tessa M. Harden Carin J. Andrew Federal Emergency Management Agency Region 10 If you are

More information

Water Security Agency. Plan for 2015-16. saskatchewan.ca

Water Security Agency. Plan for 2015-16. saskatchewan.ca Water Security Agency Plan for 2015-16 saskatchewan.ca Statement from the Minister I am pleased to present the Water Security Agency s Plan for 2015-16. The Honourable Scott Moe Minister Responsible for

More information

Development of an Impervious-Surface Database for the Little Blackwater River Watershed, Dorchester County, Maryland

Development of an Impervious-Surface Database for the Little Blackwater River Watershed, Dorchester County, Maryland Development of an Impervious-Surface Database for the Little Blackwater River Watershed, Dorchester County, Maryland By Lesley E. Milheim, John W. Jones, and Roger A. Barlow Open-File Report 2007 1308

More information

Federal Guidelines for Dam Safety

Federal Guidelines for Dam Safety Federal Guidelines for Dam Safety Selecting and Accomodating Inflow Design Floods for Dams April 2004 FEDERAL GUIDELINES FOR DAM SAFETY: SELECTING AND ACCOMMODATING INFLOW DESIGN FLOODS FOR DAMS prepared

More information

USSD Workshop on Dam Break Analysis Applied to Tailings Dams

USSD Workshop on Dam Break Analysis Applied to Tailings Dams USSD Workshop on Dam Break Analysis Applied to Tailings Dams Antecedents Newtonian / non-newtonian flows Available models that allow the simulation of non- Newtonian flows (tailings) Other models used

More information

WHAT YOU NEED TO KNOW ABOUT LIVING NEAR INDIANA COAL MINES

WHAT YOU NEED TO KNOW ABOUT LIVING NEAR INDIANA COAL MINES WHAT YOU NEED TO KNOW ABOUT LIVING NEAR INDIANA COAL MINES Who Should Read This Guide? Home Buyers/Owners Lending Institutions Landowners Developers Local Officials Construction Design Realtors Companies

More information

Basements and Deep Building Construction Policy 2014

Basements and Deep Building Construction Policy 2014 Basements and Deep Building Construction Policy 2014 APPROVAL Council / CEO 27 October 2014 VERSION NO: Version 1.0 TRIM REF: 14/67838 REVIEW 30/10/2019 RESPONSIBLE EXECUTIVE General Manager City Assets

More information

April 24, 2015. Dear Mr. Fraser: Ontario Energy Board Energy East consultations

April 24, 2015. Dear Mr. Fraser: Ontario Energy Board Energy East consultations Mr. Peter Fraser Vice-President Industry Operations and Performance PO Box 2319-2300 Yonge Street Toronto, Ontario M4P 1E4 Dear Mr. Fraser: RE: Energy East consultations The Canadian Association of Petroleum

More information

Oil Sands Environmental Coalition

Oil Sands Environmental Coalition Oil Sands Environmental Coalition 2 December 2013 Canadian Environmental Assessment Agency Attention: David Haddon Panel Manager 160 Elgin Street, 22nd Floor Ottawa ON K1A 0H3 Frontier.Review@ceaa-acee.gc.ca

More information

Multisensor Data Integration in O&G Business Lutz Petrat Hélène Lemonnier Michael Hall

Multisensor Data Integration in O&G Business Lutz Petrat Hélène Lemonnier Michael Hall Multisensor Data in O&G Business Lutz Petrat Hélène Lemonnier Michael Hall ESA Oil and Gas Workshop 15/09/2010, Frascati, Italy Satellite Products and Services during a typical O&G project Project Life

More information

Growth Faulting, Associated Geologic Hazards, Economic & Regulatory Impact, and Methods of Investigation for the Houston, Texas Area

Growth Faulting, Associated Geologic Hazards, Economic & Regulatory Impact, and Methods of Investigation for the Houston, Texas Area Growth Faulting, Associated Geologic Hazards, Economic & Regulatory Impact, and Methods of Investigation for the Houston, Texas Area GSA / AEG-Tx Growth Fault Symposium Texas A&M University, College Station,

More information

Rapid Changes in Earth s Surface

Rapid Changes in Earth s Surface TEKS investigate rapid changes in Earth s surface such as volcanic eruptions, earthquakes, and landslides Rapid Changes in Earth s Surface Constant Changes Earth s surface is constantly changing. Wind,

More information

Flash Flood Science. Chapter 2. What Is in This Chapter? Flash Flood Processes

Flash Flood Science. Chapter 2. What Is in This Chapter? Flash Flood Processes Chapter 2 Flash Flood Science A flash flood is generally defined as a rapid onset flood of short duration with a relatively high peak discharge (World Meteorological Organization). The American Meteorological

More information

A disaster occurs at the point of contact between social activities and a natural phenomenon of unusual scale.

A disaster occurs at the point of contact between social activities and a natural phenomenon of unusual scale. Hazard Mapping and Vulnerability Assessment Mr. Toshiaki Udono Senior Project Manager, Kansai Division, PASCO Corporation, Japan Mr. Awadh Kishor Sah Project Manager, Project Implementation Department,

More information

NEWS RELEASE. Government takes action on Chief Inspector of Mines recommendations

NEWS RELEASE. Government takes action on Chief Inspector of Mines recommendations For Immediate Release 2015MEM0030-002119 Dec. 17, 2015 NEWS RELEASE Government takes action on Chief Inspector of Mines recommendations VICTORIA In response to the findings and recommendations of the Chief

More information

Impact of water harvesting dam on the Wadi s morphology using digital elevation model Study case: Wadi Al-kanger, Sudan

Impact of water harvesting dam on the Wadi s morphology using digital elevation model Study case: Wadi Al-kanger, Sudan Impact of water harvesting dam on the Wadi s morphology using digital elevation model Study case: Wadi Al-kanger, Sudan H. S. M. Hilmi 1, M.Y. Mohamed 2, E. S. Ganawa 3 1 Faculty of agriculture, Alzaiem

More information

Re: Teck Frontier Oil Sands Mine Project: Responses to Supplemental Information Requests (SIRs)

Re: Teck Frontier Oil Sands Mine Project: Responses to Supplemental Information Requests (SIRs) Teck Resources Limited January 16, 2014 Métis Local 125 (Fort Chipewyan Métis) Attention: Fred Fraser (President) Re: Teck Frontier Oil Sands Mine Project: Responses to Supplemental Information Requests

More information

Utah State General Records Retention Schedule SCHEDULE 1 GEOSPATIAL DATA SETS

Utah State General Records Retention Schedule SCHEDULE 1 GEOSPATIAL DATA SETS Utah State General Records Retention Schedule SCHEDULE 1 BIOTA RECORDS (Item 1-26) These are geospatial records that depict wildlife use areas in the state of Utah as determined by wildlife biologists

More information

Lisgar District Basement Water Infiltration Investigation Answers to Residents Written Questions Received by Councillors Ward 10 Office

Lisgar District Basement Water Infiltration Investigation Answers to Residents Written Questions Received by Councillors Ward 10 Office Lisgar District Basement Water Infiltration Investigation Part A Answers to Technical Questions 1. There has been a tremendous amount of work done everywhere along the creek. If there was nothing wrong

More information

* 765 million tons of recoverable reserves as of 1970; W.E. Edmonds, Pennsylvania Geologic Survey

* 765 million tons of recoverable reserves as of 1970; W.E. Edmonds, Pennsylvania Geologic Survey IV. PROPOSED PLAN FOR AMD ABATEMENT GOALS AND OBJECTIVES Although the major natural resource in the Wyoming Valley is anthracite coal*, its importance to the present and future economy of the area is limited

More information

Final. Contact person: Colin Whittemore Aurecon Centre 1 Century City Drive Waterford Precinct, Century City Cape Town, South Africa

Final. Contact person: Colin Whittemore Aurecon Centre 1 Century City Drive Waterford Precinct, Century City Cape Town, South Africa Review Report and Recommendations for the Remediation of Flood Damage at the Berg River Causeway and the Dam Bypass Channel on Portion of Farms 1646 and 1014, Franschhoek Contact person: Colin Whittemore

More information

Light Oil Exploration Williston Basin Saskatchewan, Canada. Corporate Presentation Q1 2015

Light Oil Exploration Williston Basin Saskatchewan, Canada. Corporate Presentation Q1 2015 Light Oil Exploration Williston Basin Saskatchewan, Canada Corporate Presentation Q1 2015 Forward Looking Statements This presentation includes forward-looking statements as well as historical information.

More information

Environmental Case Study Decatur, Georgia, DeKalb County A Suburban Creek Resists Channelization

Environmental Case Study Decatur, Georgia, DeKalb County A Suburban Creek Resists Channelization Introduction A visual examination of Doolittle Creek in a highly developed suburban county in Georgia yielded telltale signs of a creek whose original streambed had been altered. Examination of official

More information