1 STATEMENT OF WORK LOS ANGELES COUNTY DEPARTMENT OF REGISTRAR-RECORDER/COUNTY CLERK System Center Configuration Manager Statement of Work June 19, 2015
2 1.0 INTRODUCTION The purpose of this document is to define the requirements, deliverables, tasks, and scope of the work to be delivered by the CONTRACTOR to the Los Angeles County Department of Registrar- Recorder/County Clerk (RRCC). CONTRACTOR shall provide the services necessary to fully manage all tasks and subtasks in this Statement of Work (SOW) to successfully install, configure, test, and implement the Microsoft System Center Configuration Manager (SCCM). Services include the configuration of hardware, software, setup and Professional Services, including, but not limited to, all associated software and/or firmware, patches/fixes, and interfaces, post implementation support, technical and end-user transfer of knowledge. CONTRACTOR is responsible for all acts, and services required to provide RRCC with a fully operational system, in accordance with Microsoft Best Practices and Standards for the implementation of SCCM. Whether or not the acts or services required to do so are specifically identified as a task, subtask, or deliverable in this Statement of Work, and unless otherwise expressly stated, all work described in this Statement of Work shall be performed by CONTRACTOR. Formatted: Justified, Line spacing: Multiple 1.15 li 2.0 EXECUTIVE SUMMARY The Los Angeles County Registrar-Recorder/County Clerk (RRCC) Department supports an estimated 1,400 computing devices consisting of: desktops, laptops, tablets. Device management, which includes software and hardware updates, inventory management, security and software versioning are important functions in maintaining critical business services for department employees and customers. To support the department s critical business: Elections, Document Recording, and Vital Record Management, RRCC uses several different systems to secure and update devices, the goal of the department is to utilize a centrally managed system based on Microsoft System Center Configuration Manager (SCCM). RRCC is requesting implementation and project management services to deploy the Microsoft System Center Configuration Manager 2012 R2 System, for centralized device management. RRCC currently has a single forest Active Directory deployed with multiple domain controllers in various offsite locations throughout Los Angeles County. RRCC shall require a Microsoft Gold Certified System Center Configuration consultant and team to oversee the installation, configuration, deployment and implementation of SCCM on up to 1,400 computing devices, including the offsite locations throughout Los Angeles County. The fully configured system shall provide a complete inventory of software and hardware of all computing devices, inclusive of dashboards for Help Desk, Network Services, and Management to review the immediate status of customer devices and to remotely control, configure and manage devices, provide software and patch management distribution tools in a post implementation environment. The deployment shall include various types of output reports to be available for audit and inventory control; reporting shall also be used for the planning of software updates and upgrades and shall incorporate Microsoft SCCM System, Best Practices and Standards as part of the completed implementation. 3.0 PROJECT SCOPE RRCC is requesting the CONTRACTOR to include project: scoping, planning, setup, installation, testing, implementation and professional services as part of this statement of work (SOW), describes 2 Formatted: Justified, Line spacing: Multiple 1.15 li
3 the effort required to implement the Microsoft System Center Configuration Management System (SCCM). The implementation team must be able to assess the existing, current, server and computing device infrastructure and to guide the deployment of SCCM to an estimated 1,400 devices, while maintaining the security and stability of the infrastructure. Service deployment shall be required within a VMware virtualized infrastructure and the consultant/vendor must have demonstrated deployment expertise with SCCM within a vsphere v5.5, vcenter v5.5 system. The recommendations and deployment methodologies used by the consultant/vendor should incorporate existing RRCC systems such as McAfee Encryption and Anti-Virus, and system compatibility with a proposed system deployment of. The SCCM implementation shall also require integration with a proposed deployment of the Cherwell Service Management System (Cherwell SMS); SCCM implementation should be designed for the system integration with the Cherwell SMS. All previously mentioned systems must be integrated and must work concurrently, in a cohesive manner and without disruption to any installed or pending system implementations. Upon completion, the SCCM System must be demonstrated to RRCC IT Managers and IT Staff to work per Microsoft s stated specifications. Appropriate reporting and documentation to be recommended by the consultant/vendor with the final output reporting to be determined by RRCC IT Management. The SCCM implementation shall include a transfer of knowledge in using and managing the service. CONTRACTOR shall, deliver and/or transfer any and all documentation and licenses for software, firmware, utility programs, and any and all other software provided by the manufacturer as well as warranties. CONTRACTOR consultant shall lead the project as the Project Manager over a team that may include RRCC supervisors/staff. The CONTRACTOR shall oversee the installation, configuration, deployment and implementation of SCCM on up to 1,400 computing devices, including the offsite locations throughout Los Angeles County. The fully configured system shall provide a complete inventory of software and hardware of all computing devices, inclusive of dashboards for Help Desk, Network Services, and Management to review the immediate status of customer devices and to remotely control, configure and manage devices, provide software and patch management distribution tools in a post implementation environment. The deployment shall include various types of output reports to be available for audit and inventory control; reporting shall also be used for the planning of software updates and upgrades and shall incorporate Microsoft SCCM System, Best Practices and Standards as part of the completed implementation within the existing RRCC infrastructure 3.1 Vendor Certifications All scoping, planning, setup, installation, testing, implementation and professional services, listed in EXHIBIT A must be completed by CONTRACTOR with the following minimum qualification credentials: CONTRACTOR must be an authorized VMware Premier Solutions Provider and must hold a VMware Certified Professional Certification ( VCP ). CONTRACTOR and/or Consultant must be a Cisco Gold Partner. CONTRACTOR must hold Specializations in Advanced Data Center Architecture and Advanced Data Center Networking Infrastructure certifications with a Cisco Certified Internetworking Engineer ( CCIE ) certification. CONTRACTOR must be an authorized Hewlett Packard Partner Specialist Designation in Enterprise Storage Solutions, NetApp Star Partner, NetApp 3
4 Authorized Professional Services Partner, Engineers with Hewlett Packard s Master Accredited Systems Engineer Storage Solutions, NetApp Certified Data Management Administrator ( NCDA ). Other certifications may not be substituted. In the event that technical support or other services are required during or after the SCCM project deployment, due to problems resulting from this project, one of CONTRACTOR s Cisco Gold Partner with Cisco Master Specialization Cloud Builder, Advanced Data Center Architecture, Advanced Data Center Networking Infrastructure certification, Cisco Certified Internetworking Engineer ( CCIE ) certification must be able to respond onsite within four hours for diagnosis and problem resolution or escalation. If the event requires assistance due to the connectivity between SCCM and the EVA or NetApp Storage, then, CONTRACTOR must provide a Consultant that has expertise and hold a Hewlett Packard s Master Accredited Systems Engineer Storage Solutions, NetApp Certified Design Architect; Technical Engineer or Consultant must also be able to respond onsite for diagnosis and problem resolution or escalation and problem resolution. 3.2 Project Scoping and Planning CONTRACTOR shall meet with the RRCC Network Team, at the RRCC Headquarters Office, located at Imperial Hwy, Norwalk, CA 90650, to identify customer and vendor resources and contacts. CONTRACTOR shall perform site readiness assessment ensuring hardware and software environments are ready for project commencement, perform requirement gathering and final design sessions in preparation for writing transfer of knowledge documentation. Further, CONTRACTOR shall perform a site readiness assessment ensuring hardware environment is ready for project initiation. CONTRACTOR and RRCC must also agree upon versions of software and/or firmware, if required. CONTRACTOR must also review, agree upon and document any questions with respect to VMware, vcenter or RRCC VLAN configurations that are required before commencement of the project. The CONTRACOR shall meet with the RRCC IT Managers and Network Team to provide an overview of project and scope. CONTRACTOR shall provide a presentation to RRCC Management that provides the overview of the deployment plan, in addition, shall provide related documentation that fully describes the deployment plan with proposed milestone dates. CONTRACTOR shall prepare a Project Plan, Gantt Chart with defined tasks, and Project Milestone list with applicable critical milestone dates. CONTRACTOR shall identify Customer and CONTRACTOR Action Items and shall confirm, in writing, the roles and responsibilities of the CONTRACTOR. 4
5 3.3 Professional Services Formatted: Justified, Space After: 0 pt PHASE I 1.1 SERVICES The Services that vendor and/or subcontractor shall provide shall include: Phase 1: SCCM Design & Planning Tasks Conduct a project kick-off meeting Discovery o Prepare a detailed inventory of all physical servers, virtual machines, operating systems and applications to be monitored o Determine the use of best practices with the current environment o Research current processes and connectivity Personnel Requirements Gathering o Interview administrative personnel and subset of end users o Interview Business Stake holders for requirements, planning, strategy Infrastructure o Review best practices with Customer o Review proposed SCCM infrastructure design o Assess SCCM and Reporting SQL architecture and planning considerations Server configuration Database settings Disk I/O configuration Sizing and planning o Design and document SCCM and Reporting SQL hardware and topological configurations o Design and document the SQL requirements for all required highly available SQL database environments o Assess Active Directory services, Domain, Sites as it pertains to SCCM implementation Users (meta-data) Computers Printers o Document required service accounts to be used SCCM Solution Features o Management Point Servers, Distributions Points Shares, in terms of health, performance and load readiness. o Assess configuration of individual features: Agent Configuration Software Distribution 5
6 Hardware & Software Inventory Software Updates Operating System Deployment o Demonstrate Cherwell System integration readiness Provide a detailed project plan for all remaining phases of the project Troubleshooting of Active Directory may be needed to necessitate the installation and configuration of SCCM. Active Directory configuration and data population to be reviewed and adapted to provide a thorough and accurate installation of SCCM. PHASE I - Completion Criteria Detailed Design Documents completed and delivered to and approved by the RRCC Department Detailed Project Plan completed and delivered to and approved by the RRCC Department A Milestone and Timeline Document to be prepared in advance and approved by the RRCC Department in preparation for the SCCM implementation. PHASE II Phase 2: SCCM Installation & Point-of-Concept Validation Prerequisites All prior phases are complete Appropriate Microsoft Licenses, Media, and License keys have been procured Servers and storage provisioned according to the documented prerequisites SQL Server installed Tasks Configure SQL for the SCCM environment Infrastructure o Install and configure System Center Configuration Manager 2012 R2 on the primary site server as per design and deploy SCCM at RRCC Branch Offices. o Implement the following Site System Roles for Point-of-Concept: Primary Site Server (1) Management Point Site Server (1) Fallback Site Server (1) Distribution Points (up to 1) o Implement the following Hierarchy Configurations: Active Directory System Discovery Active Directory User Discovery Site Boundaries and Boundary Groups o Implement Agent deployment for Point-of-Concept Group Client push installation settings for installation of SCCM 2012 agents Deploy agent to Workstations (up to 1,400) 6
7 Deploy agent to Servers (up to 10) Solution Feature Deployment o Prepare Client Settings o Prepare Server Settings Conduct Point-of-Concept Validation of SCCM functionality with up to 1,400 workstations and 10 servers. A sampling of workstations in different physical locations should be included in the Point-of-Concept. Point-of-Concept activities include: o Validate hardware / software inventory features and reporting o Test / validate Distribution Point o Test / validate Fallback Point o Test / validate backup of SCCM Demonstrate SCCM 2012 features to RRCC IT Managers, IT Supervisors and Network Team staff. Provide training on System Center Configuration Manager features deployed. This shall include working with the RRCC Department assigned staff during the engagement. Completion Criteria Successful installation of Systems Center Configuration Manager Successful Point-of-Concept of the SCCM functions listed above Provide a Design and Implementation Project Report PHASE III Phase 3: SCCM Point-of-Concept to Production Validation Prerequisites Access to operational SCCM 2012 environment RRCC Department is prepared and ready to begin the Production SCCM Client deployment Validate the Point-of-Concept Site is ready to migrate to Production Assist the RRCC Department in formulating and documenting a rollout plan Assist in moving servers from Point-of-Concept zone to Production Assist in the deployment of SCCM distribution points to all remaining offices or locations where an SCCM Distribution Point is required Assist in the deployment of SCCM agents to all remaining client workstations (up to 1,400) Assist in the deployment of SCCM agents to all remaining servers (up to 100) Refine and deliver the Validation Specification Document complete with acceptance testing Provide support as issues arise for up to two weeks after the full agent push to all workstations and servers 7
8 Completion Criteria A rollout plan and support services have been provided to the RRCC Department for deploying the SCCM Client to all workstations and servers in the organization PHASE IV Phase 4: Documentation & Training Prerequisites All prior phases are complete Tasks Collect final configuration information Document the deployed SCCM environment as the final end-state configuration Provide detailed Visio diagrams for RRCC Department Review documentation and final configuration with RRCC Department Document suggestions for future improvement and optimization as appropriate Completion Criteria Documentation has been delivered and reviewed with the RRCC Department and approved by RRCC Department Project to be completed, no later than August 31, DELIVERABLES 1.2 DELIVERABLES Deliverables shall include all services described in the above sections. Notwithstanding anything to the contrary set forth herein: (i) RRCC shall have the right to retain a copy of any work product of its personnel for its records; (ii) as part of RRCC provision of the Services hereunder, RRCC may utilize proprietary works of authorship, pre-existing or otherwise, that have not been created specifically for RRCC Department, including without limitation computer programs, methodologies, templates flowcharts, architecture designs, tools, specifications, drawings, sketches, models, samples, records and documentation, as well as copyrights, trademarks, service marks, ideas, concepts, know-how, techniques, knowledge or data, and any derivatives thereof, which have been originated, developed or purchased by RRCC, a parent or affiliated company of RRCC, or by third parties under contract to RRCC or to a parent or affiliated company of RRCC (all of the foregoing, collectively, RRCC Information ); and (iii) RRCC Information and RRCC administrative communications, records, files and working papers relating to the Services shall remain the sole and exclusive property of RRCC. Notwithstanding anything contained herein to the contrary, RRCC shall retain rights in such proprietary products, materials and methodologies of RRCC or any third parties. 8
9 1.3 PROJECT LOCATION Unless otherwise specified elsewhere in this SOW, all on-site Services shall be performed at RRCC Department s facilities located at the following location(s) ( RRCC Department Site ): Imperial Highway Norwalk, CA PROJECT MANAGER The RRCC Project Coordinator, with work with the CONTRACTOR Project Manager (PM) to: Serve as primary point of contact on project issues, scheduling, and RRCC Department satisfaction concerns Complete Change Request documentation as required Schedule and coordinate the necessary resources to support the project Identify, escalate, and document project issues as necessary Schedule and conduct team update/status meetings Prepare and deliver completion documentation for acceptance TESTING PHASE Following the installation of the SCCM System, connectivity to the service, server, workstations and Disaster Recovery or Failover solution(s) shall be tested to confirm that the deployed system operates in the prescribed manner and at a minimum, based on Microsoft SCCM Best Practices and industrywide standards. The VENDOR shall provide a Project wrap-up meeting at the conclusion of this Project, in-person. Following RRCC Department s acceptance of all deliverables under this SOW, RRCC shall provide the vendor an executed Milestone and Services Completion Letter. Hours of installation: Monday-Friday, 9:00am to 4:00pm or alternate schedule by mutual agreement between the RRCC and the SCCM Consultant/Vendor. Site preparation: Work may be completed between 8:00a.m. to 5:00p.m., Monday through Friday with pre-approval of scheduling from RRCC staff or Management. Any disruptive work that affects access to the Data Center and/or Storage Area Network (SAN) or attached production servers shall be scheduled for after business hours or weekend hours at the discretion of RRCC staff or Management and to be planned and/or scheduled in advance. 9
10 Exhibit A Software, Service & Warranty Software Microsoft System Center Configuration Manager 2012 R2 software to be provided by the RRCC Department including all upgrades, patches, licensing for servers and computers. Symantec IT Management Suite 7.6 (Altiris ) to be provided by the RRCC Department including all upgrades, patches, licensing for servers and computers. Cherwell Service Management System integration requirements to be provided by the RRCC and Internal Service Department(s) (ISD) including access to system documentation and information as it relates to the integration of SCCM with the ISD Cherwell SMS. Services A list to be provided to the CONTRACTOR of all servers, workstations, desktop, laptop and tablet computers to be included in the system deployment by RRCC staff. RRCC staff will work with the CONTRACTOR at the required RRCC Branch office locations, as designated by IT Management. Warranty CONTRACTOR warrants that the Microsoft System Center Configuration Manager shall work as scoped, designed and implemented; additional availability of the vendor, onsite or by phone to address any latent issues for a period of one month following the implementation. 10
ediscovery Implementation Services Statement of Work To be Executed under State Blanket Contract ITS53 Cat2B
ediscovery Implementation Services Statement of Work To be Executed under State Blanket Contract ITS53 Cat2B Overview: The Massachusetts Water Resources Authority is looking for a vendor to provide business
More informationVMware Cloud Automation Design and Deploy IaaS Service
DATASHEET VMware Cloud Automation AT A GLANCE The VMware Cloud Automation Design and Deploy IaaS Service expands the power of virtualization and moves IT services away from existing infrastructure delivery
More informationStatement of Work. Systems Center Configuration Manager. Prepared for School Board of Sarasota County Thursday, 12 June 2008 Version 1.3.
Statement of Work Systems Center Configuration Manager Prepared for School Board of Sarasota County Thursday, 12 June 2008 Version 1.3.1 Released Prepared by Dom Vila Program Manager dom.vila@microsoft.com
More informationREQUEST FOR PROPOSALS INFORMATION TECHNOLOGY SUPPORT SERVICES. Bid Packets are Due:
REQUEST FOR PROPOSALS INFORMATION TECHNOLOGY SUPPORT SERVICES Issue Date: Friday, March 15 th, 2013 Closing Date: Monday, April 15 th, 2013 University City District is requesting proposals from qualified,
More informationLEARNING SOLUTIONS website milner.com/learning email training@milner.com phone 800 875 5042
Course 6451B: Planning, Deploying and Managing Microsoft System Center Configuration Manager 2007 Length: 3 Days Published: June 29, 2012 Language(s): English Audience(s): IT Professionals Level: 300 Technology:
More informationManaged IT Services. Maintain, manage and report
Managed IT Services Maintain, manage and report 1 2 Comunet was established in 1995 to provide professional Information Technology services to Australian businesses and organisations. Its vision now, as
More informationCourse Syllabus. Course 6451A: Planning, Deploying and Managing Microsoft Systems Center Configuration Manager 2007. Key Data.
Key Data Product #: 3384 Course #: 6451A Number of Days: 5 Format: Instructor-Led Certification Exams: This course helps you prepare for the following Microsoft Certified Professional exams: 70-401 TS:
More informationRequest for Information RFI #15/16-300 for Enterprise Password Management Software
Company Name: This RFI response has been submitted by: Address: (Street, Su. # City, State, Zip) Request for Information RFI #15/16-300 for Enterprise Password Management Software Contact Name: Telephone
More informationData Sheet: Backup & Recovery Symantec Backup Exec 12.5 for Windows Servers The gold standard in Windows data protection
The gold standard in Windows data protection Overview Symantec Backup Exec 12.5 delivers market-leading backup and recovery protection from server to desktop, providing complete data protection for the
More informationRequest for Proposal Managed IT Services 7 December 2009
Request for Proposal Managed IT Services 7 December 2009 BuzzBack, LLC 25 West 45 th Street Suite 202 New York, NY 10036 Table of Contents 1 Summary... 1 2 Proposal Guidelines and Requirements... 1 2.1
More informationREQUEST FOR PROPOSAL-INFORMATION TECHNOLOGY SUPPORT SERVICES
Isothermal Planning & Development Commission (IPDC) REQUEST FOR PROPOSAL-INFORMATION TECHNOLOGY SUPPORT SERVICES Proposals will be received by the IPDC for Information Technology Support Services. Interested
More informationRFP-00118 ADDENDUM NO. 1
INTERNAL SERVICES DEPARTMENT PROCUREMENT MANAGEMENT SERVICES 111 NW 1 ST Street Suite 1300 Miami, Florida 33128-1974 Telephone: 305-375-4725 Fax: (305) 375-5688 RFP-00118 ADDENDUM NO. 1 DATE: March 26,
More informationService Description. vstart Solution Assistance & Consulting Service
Service SKUs SKU # SKU Description Provider 936-9749 Infrastructure Consulting Services, Custom, vstart Solution assistance and Consulting, 1week GICS Resource for 1 unit of service Duration (hours) Virtualization
More informationPrepared by: OIC OF SOUTH FLORIDA. May 2013
OIC OF SOUTH FLORIDA REQUEST FOR PROPOSAL INFORMATION TECHNOLOGY SUPPORT SERVICES Proposals will be received by OIC of South Florida for Information Technology Support Services. Interested vendors should
More information211 LA County. Technology Infrastructure Assessment. Request for Proposals. August 2012 Request for Proposals- 211 LA County 1
211 LA County Technology Infrastructure Assessment Request for Proposals August 2012 Request for Proposals- 211 LA County 1 1. General conditions and proposers directions 1.1. Overview 1.1.1. 211 LA County
More informationAGREEMENT- LEXMARK ENTERPRISE SOFTWARE, LLC
TULSA COUNTY PURCHASING DEPARTMENT MEM DATE: SEPTEMBER 30, 2015 FROM: PURCHASING DIRECTO ~ TO: SUBJECT: BOARD OF COUNTY COMMISSIONERS AGREEMENT- LEXMARK ENTERPRISE SOFTWARE, LLC SUBMITTED FOR YOUR APPROVAL
More informationSENIOR SYSTEMS ANALYST
CITY OF MONTEBELLO 109 DEFINITION Under general administrative direction of the City Administrator, provides advanced professional support to departments with very complex computer systems, programs and
More informationCarahsoft End-User Computing Solutions Services
Carahsoft End-User Computing Solutions Services Service Description Horizon View Managed Services Bronze Package Managed Services Package Options # of Desktops to be Managed Desktop Type Duration of Services
More informationOracle Technical Cloud Consulting Services Descriptions. July 23, 2015
Oracle Technical Cloud Consulting Services Descriptions July 23, 2015 Oracle Database Cloud Service Rapid Start Service Part # B83896 (For use in the US only) Description of Services Oracle will provide
More informationSubject: Request for Proposals: Enterprise Systems Backup Solution, # FIT-2013-005 Due: May 14, 2013 at 2:00 PM EST
NOTICE OF ADDENDUM ADDENDUM #4 May 7, 2013 Subject: Request for Proposals: Enterprise Systems Backup Solution, # FIT-2013-005 Due: May 14, 2013 at 2:00 PM EST Dear Sir or Madam: The Columbus Regional Airport
More informationManaged Services Agreement. Hilliard Office Solutions, Ltd. PO Box 52510 Phone: 432-617-4677 Midland, Texas 79710 Fax: 432-617-3043
Managed Services Agreement Hilliard Office Solutions, Ltd. PO Box 52510 Phone: 432-617-4677 Midland, Texas 79710 Fax: 432-617-3043 SERVICE DESCRIPTIONS By purchasing these Services from Hilliard Office
More informationVMware Performance and Capacity Management Accelerator Service
AT A GLANCE The VMware Performance and Capacity Management Accelerator Service rapidly deploys a performance management, capacity optimization, and log management solution focused on a limited predefined
More informationLHRIC Network Support - Additional Service Features
LHRIC Network Support - Additional Service Features It is important to note that costs associated with LHRIC Network Support service not only cover an on-site support engineer but also include a number
More informationIII. Services Required The following details the services to be provided to the Town of North Haven in the area of information services:
TOWN OF NORTH HAVEN REQUEST FOR PROPOSALS INFORMATION TECHNOLOGY NETWORK SUPPORT SERVICES Issue Date: March 7, 2016 Due Date: 10:00 AM, Monday, March 28, 2016 I. Introduction The Town of North Haven is
More informationBENCHMARK EVALUATION. Highways and Public Works Information and Communications Technology
Identification Section BENCHMARK EVALUATION Position Title: Supervisor s Title: Department: Branch/Unit: Network Solutions Specialist Network Solutions Architect Highways and Public Works Information and
More informationHosted SharePoint: Questions every provider should answer
Hosted SharePoint: Questions every provider should answer Deciding to host your SharePoint environment in the Cloud is a game-changer for your company. The potential savings surrounding your time and money
More informationSTATEMENT OF WORK (SOW) Data Governance Tool
1.0 Introduction Colorado Springs Utilities (UTILITIES) is a municipality owned four-service utility company, an enterprise of the City of Colorado Springs, located in Colorado Springs, Colorado. UTILITIES
More informationAgilisys G-Cloud Service V
Agilisys G-Cloud Service V Service Definition Endpoint Management Lot 1 Infrastructure as a Service (IaaS) April 2014 At Agilisys we deliver success through innovation working with our clients to transform
More informationInForm On Demand Single Trial Services Description
InForm On Demand Single Trial Services Description Version 7.0 Effective Date: 0 25-Sep-2014 This is the Services Description for Oracle InForm On Demand Single Trial ( Schedule ) to Your Study Order for
More informationStatement of Work RFP-DF-96217 Virtual Desktop Infrastructure
Statement of Work RFP-DF-96217 Virtual Desktop Infrastructure 1.0 Introduction Colorado Springs Utilities (UTILITIES) desires to contract with a reputable firm for the purchase and implementation of a
More informationInformation Technology Services
Information Technology Services 2011 Services Guide 77 Accord Park Drive, Suite A10 Norwell, MA 02061 (781) 871-3662 A proactive, preventative approach to IT management. System downtime, viruses, spyware,
More informationREQUEST FOR PROPOSALS. Business Continuity Planning Consultant Services APPENDIX C RFP STATEMENT OF WORK EXHIBITS 1-3
REQUEST FOR PROPOSALS Business Continuity Planning Consultant Services APPENDIX C RFP STATEMENT OF WORK EXHIBITS 1-3 EXHIBITS EXHIBIT 1 EXHIBIT 2 EXHIBIT 3 Glossary of Terms and Acronyms Contract Discrepancy
More informationKASEYA CLOUD SOLUTION CATALOG 2016 Q1. UPDATED & EFFECTIVE AS OF: February 1, 2016. Kaseya Catalog - 1 - Kaseya Copyright 2016. All rights reserved.
KASEYA CLOUD SOLUTION CATALOG 2016 Q1 UPDATED & EFFECTIVE AS OF: February 1, 2016 Kaseya Catalog - 1 - Overview of the Kaseya Cloud Subscription Solutions The Kaseya Cloud solutions are designed to meet
More informationCisco and VMware Virtualization Planning and Design Service
Cisco and VMware Virtualization Planning and Design Service Create an End-to-End Virtualization Strategy with Combined Services from Cisco and VMware Service Overview A Collaborative Approach to Virtualization
More informationAdministration A. Superintendent. Technology Services Proposal. Board of Education Dr. Bruce Law Superintendent of Schools DATE: July 30 2015
Dr. Bruce Law Pamela Bylsma Tammy Prentiss Domenico Maniscalco Bill Eagan Superintendent Assistant Superintendent Assistant Superintendent Chief Human Chief Financial of Schools for Academics for Student
More informationRemote Infrastructure Support Services & Managed IT Services
Remote Infrastructure Support Services & Managed IT Services Remote Desktop Services are designed to optimize the customers IT resource utilization and provide a standardized end-user environment. The
More informationData Sheet: Endpoint Management Altiris Client Management Suite 7.0 Deploy, manage, secure, and troubleshoot
Deploy, manage, secure, and troubleshoot Overview The cost of a PC is only a small part of its total cost. Nearly 80 percent of the total cost of owning a client system goes toward the support and maintenance
More informationRequest for Proposal Outsourced IT & Managed Services
Request for Proposal Outsourced IT & Managed Services Issue Date: January 2, 2015 Submission Deadline: January 30, 2015 at 5:00 p.m. CST RFP Coordinator: Katie Kosseff, Operations Manager kkosseff@womenventure.org
More informationAPPENDIX 5 TO SCHEDULE 3.3
EHIBIT K to Amendment No. 60 - APPENDI 5 TO SCHEDULE 3.3 TO THE COMPREHENSIVE INFRASTRUCTURE AGREEMENT APPENDI 5 TO SCHEDULE 3.3 TO THE COMPREHENSIVE INFRASTRUCTURE AGREEMENT EHIBIT K to Amendment No.
More informationAltiris Client Management Suite
Altiris Client Management Suite Agenda 1 What DO YOU Need Help With 2 What does Altiris have to Assist 3 What s New with CMS 7 4 Beyond Client Management Altiris Client Management Suite Leads the Way Symantec
More informationHP Technical Services
HP Technical Services Microsoft Windows Infrastructure Migration Statement of work for City of Costa Mesa Date: 08/24/2004 Prepared by: Brian Vagg Project ID: SWA2336 Version: 1.0 Proprietary Notice Restriction
More informationFully Managed IT Support. Proactive Maintenance. Disaster Recovery. Remote Support. Service Desk. Call Centre. Fully Managed Services Guide July 2007
Fully Managed IT Support Proactive Maintenance Disaster Recovery Remote Support Service Desk Call Centre London Office ITVET Limited 2 nd Floor 145 157 St John Street London EC1V 4PY t: +44(0)8704 232
More informationCENG Information Technology Services University of North Texas
CENG Information Technology Services University of North Texas for the Information Technology Services as applied To the University of North Texas College of Engineering 1.0 Agreement 1.1 Purpose CENGITS
More informationData Sheet: Archiving Altiris Client Management Suite 7.0 from Symantec Deploy, manage, secure, and troubleshoot
Deploy, manage, secure, and troubleshoot Overview The cost of a PC is only a small part of its total cost. Nearly 80 percent of the total cost of owning a client system goes toward the support and maintenance
More informationSERVICE SCHEDULE INFRASTRUCTURE AND PLATFORM SERVICES
SERVICE SCHEDULE INFRASTRUCTURE AND PLATFORM SERVICES This Product Schedule Terms & Conditions is incorporated into a Services Agreement also comprising the General Terms and Conditions which the Customer
More informationManaged Service Plans
Managed Service Plans www.linkedtech.com 989.837.3060 989.832.2802 fax Managed Information Technology Services System downtime, viruses, spy ware, losses of productivity Are the computer systems you rely
More informationUnlimited Server 24/7/365 Support
Unlimited Server 24/7/365 Support Unlimited Server Support from System Architects covers your Windows servers, Linux servers and virtual machines. Your servers are monitored and managed 24 hours a day,
More informationDevice Management Module (North America)
Device Management Module (North America) Part Number: MSFSEU-10 Motorola's device management module is designed to be utilized alongside an existing Motorola Service Center Support Bronze, Service Center
More informationIT Strategic Plan INFRASTRUCTURE PROPERTIES AND PLANNING
IT Strategic Plan INFRASTRUCTURE PROPERTIES AND PLANNING 2016-2019 Purpose The purpose of this document is to provide the general scope and direction for information technology (IT) in Infrastructure Properties
More informationCITY OF WICHITA FALLS
CITY OF WICHITA FALLS RFP #09-09 LASERFICHE DOCUMENTS MANAGEMENT SOLUTION PROPOSAL DUE DATE DECEMBER 17, 2009 2:00PM REQUEST FOR ADDITIONAL INFORMATION NOVEMBER 24, 2009 2:00PM ADDENDUM ISSUED DECEMBER
More informationIBM Implementation Services for Power Systems IBM Systems Director
Sample Statement of Work for Services This an example and your Statement of Work may vary given your specific requirements and the related IBM engagement. IBM Implementation Services for Power Systems
More information1.Cisco Network Architect
1.Cisco Network Architect Analyze business requirements to develop technical network solutions and their framework. Design, test, and inspect data communications systems. Perform network modeling, analysis,
More informationMicrosoft Premier Deployment. Office 365 Service Description
Microsoft Premier Deployment Office 365 Service The information contained in this document represents the current view of Microsoft Corporation on the issues discussed as of the date of publication and
More informationSTATEMENT OF WORK (SOW) for Web Content Management System Professional Services
1.0 Introduction With electronic and social media becoming a more important part of our overall communications strategy, the Colorado Springs Utilities (UTILITIES) Internet site has become an even greater
More informationGet what s right for your business. Contact @lliance Technologies.
Provisioning Looking for new technology? You need systems in line with your business goals. You also need those systems to interact seamlessly. We can help you get the right technology to the right place
More informationManaged Services Overview Servers, Exchange, Help Desk, and Citrix Infrastructures
Overview Servers, Exchange, Help Desk, and Citrix Infrastructures Prepared By: Envision Information Technologies Last Modified: Thursday, August 28, 2014 Table of Contents Table of Contents... 2 EIT Contacts...
More informationCloud & Datacenter Monitoring with System Center Operations Manager
Page 1 of 5 Overview This course equips students with the skills they require to deploy and configure System Center 2012 R2 Operations. Using hands-on labs, students learn the following: How to architect
More informationAppendix A1 AUTOMATED EMPLOYEE SCHEDULING SYSTEM (AESS) PHASE I PILOT INSTALLATION. Statement of Work
Appendix A1 AUTOMATED EMPLOYEE SCHEDULING SYSTEM (AESS) PHASE I PILOT INSTALLATION Statement of Work These requirements are intended to provide general information only and are subject to revision. The
More informationIT Assessment Report. Prepared by: Date: BRI Works www.bri.works 321 East Main Street, Suite 200 Charlottesville VA 22902 434.951.
IT Assessment Report Prepared by: Date: BRI Works www.bri.works 321 East Main Street, Suite 200 Charlottesville VA 22902 434.951.7979 Table of Contents Executive Summary 3 IT Summary 3 Assessment Goal
More informationVDI Best Practices with Citrix XenDesktop. www.gtcsystems.com
VDI Best Practices with Citrix XenDesktop Mission Statement: No More IT Infrastructure Headaches Because we provide the: People Process Technology To Help our clients PLAN BUILD MANAGE The IT Infrastructure
More informationSymmetry Networks. Corporate Managed Services Schedule
Symmetry Networks Corporate Managed Services Schedule A Managed Services Solution version 1.0 January 2015 This Service Schedule forms part of the Agreement between Us (Symmetry Networks Pty Ltd) and You
More informationMicrosoft Active Directory Project
Microsoft Active Directory Project Simcoe County District School Board Project Kick-off Meeting Rami Wehbe (Solution Architect) January 18, 2012 Agenda Introductions Project objectives and drivers Approach
More informationMSN Upgrade and Refresh with Remote Support Services
MSN Upgrade and Refresh with Remote Support Services Service Summary Mountain States Networking ( MSN ) shall provide the following Upgrade and Refresh Services to Customer for up to one (1) chassis limited
More informationSymantec Backup Exec.cloud
Automatic, continuous, and secure protection that backs up data to the cloud, or via a hybrid approach combining on-premise and cloud-based backup. Data Sheet: Symantec.cloud Only 21 percent of SMBs are
More informationSymantec Backup Exec 2010
Reliable Backup and Recovery Designed for Your Growing Business Overview delivers market leading backup and recovery protection from server to desktop. Easily protect more data while you reduce storage
More informationSCHOOL DISTRICT OF MARION COUNTY JOB CLASSIFICATION DESCRIPTION LEVEL/POSITION: COMPUTER NETWORK SPECIALIST 4.78
SCHOOL DISTRICT OF MARION COUNTY JOB CLASSIFICATION DESCRIPTION LEVEL/POSITION: COMPUTER NETWORK SPECIALIST 4.78 AREA(S): DATA CENTER OPERATIONS POSITION SUMMARY: The Network Specialist s role is to install,
More informationService Level Agreement
This document outlines the Service Level Agreement (SLA) between University Technology Services (UTS) and our Customers for the delivery of. The purpose of this agreement is threefold: 1. To clearly represent
More informationCA Support Policy and Terms
1. Overview CA Support for CA software consists of operational assistance and technical support provided by CA, in its reasonable judgment, during the term of CA Support procured by you. CA will supply
More informationCounselorMax and ORS Managed Hosting RFP 15-NW-0016
CounselorMax and ORS Managed Hosting RFP 15-NW-0016 Posting Date 4/22/2015 Proposal submission deadline 5/15/2015, 5:00 PM ET Purpose of the RFP NeighborWorks America has a requirement for managed hosting
More informationHP Data Replication Solution Service for 3PAR Virtual Copy
HP Data Replication Solution Service for 3PAR Virtual Copy HP Care Pack Services Technical data HP Data Replication Solution Service for 3PAR Virtual Copy provides implementation of the HP 3PAR Storage
More informationMore enhanced features.
More enhanced features. Saves time and lowers cost. Upgrade today for complete data and system protection across your virtual and physical server environments. Symantec Backup Exec 12.5 NEW agents for
More informationHP Hardware Technical Support
HP Hardware Technical Support HP Technology Services - Contractual Services Technical data HP Hardware Technical Support service provides a remote hardware telephone support service on selected HP and
More informationACME Enterprises IT Infrastructure Assessment
Prepared for ACME Enterprises March 25, 2014 Table of Contents Executive Summary...2 Introduction...2 Background...2 Scope of IT Assessment...2 Findings...2 Detailed Findings for Key Areas Reviewed...3
More informationYour IT Helpdesk and On-Site and Remote Support Terms and Conditions. Document Revision 1 Sept 09
Your IT Helpdesk and On-Site and Remote Support Terms and Conditions These terms and conditions are in addition to our standard Terms of Business (available at http://www.tripod-it.co.uk) Our company details
More informationTIBCO Nimbus Cloud Service
TIBCO Nimbus Cloud Service TIBCO Nimbus TIBCO Software Inc. (NASDAQ: TIBX) is a provider of infrastructure software for companies to use onpremise or as part of cloud computing environments. Whether it's
More information1 OPPORTUNITY SUMMARY
REQUEST FOR PROPOSALS: MANAGED SERVICES FOR INFRASTRUCTURE AND IT SUPPORT SERVICES Posting Date: Thursday, January 7, 2016 Due Date: Friday, February 5, 2016 1 OPPORTUNITY SUMMARY The Massachusetts Clean
More informationSelect IT Consulting Services RFP 11-01 Technical and Network Support Specialist Services (Lot Group C)
Computer/Application Support Specialist Computer/Application Support Specialist 1 Typical Functions: Preferred This function requires business work experience with Windows XP, IT experience, work experience
More informationHP Virtualized Network Protection Service
HP Virtualized Network Protection Service HP Networking Consulting Technology Consulting Service overview With the proliferation of Virtual Datacenters (vdcs) and cloud computing environments, secure virtual
More informationHP 3PAR Software Installation and Startup Service
Technical data HP 3PAR Software Installation and Startup Service HP Care Pack Services For smooth startup, HP 3PAR Software Installation and Startup Service provides deployment of your HP 3PAR software,
More informationPreliminary Course Syllabus
Preliminary Course Syllabus Designing a Windows Active Directory Infrastructure and Services Elements of this syllabus are subject to change. Key Data Product #: 3741 Course #: 6436A Number of Days: 5
More informationVMware ESX 3.5, VSphere, VMware Workstation. Project Management: Microsoft Office 2013/365, Microsoft Project, Microsoft Visio, Juriba Dashworks.
KAMAL GOYAL +91-9740222166, 8197010066 iamkamalgoyal@gmail.com, mailme@kamalgoyal.com M-409, Ittina Mahaveer, Neeladri Road, Electronic City Phase 1, Bangalore 560100 PROFESSIONAL SUMMARY Over 10 years
More informationCOMPLIANCEDESKTOP TECHNOLOGY PLATFORM SUPPORT AND MAINTENANCE SERVICES
COMPLIANCEDESKTOP TECHNOLOGY PLATFORM SUPPORT AND MAINTENANCE SERVICES TERMS AND CONDITIONS The Red Flag Group ( RFG ) shall provide Support and Maintenance Services for the ComplianceDesktop Technology
More informationHP IT Professional Help Desk for SMB Service HP Care Pack Services
HP IT Professional Help Desk for SMB Service HP Care Pack Services Technical data HP IT Professional Help Desk for SMB Service gives Small to Medium Business customers a single source of 2nd and 3rd Level
More informationHP Windows 7 Onsite Upgrade Service
HP Windows 7 Onsite Upgrade Service HP Care Pack Services Technical data The Windows 7 Onsite Upgrade Service provides your company with onsite installation, setup, and training for the Microsoft Windows
More informationSERVICE SCHEDULE HOSTED DESKTOP SERVICES
SERVICE SCHEDULE HOSTED DESKTOP SERVICES This Product Schedule Terms & Conditions is incorporated into a Services Agreement also comprising the General Terms and Conditions which the Partner has previously
More informationDesigning, Optimizing and Maintaining a Database Administrative Solution for Microsoft SQL Server 2008
Course 50400A: Designing, Optimizing and Maintaining a Database Administrative Solution for Microsoft SQL Server 2008 Length: 5 Days Language(s): English Audience(s): IT Professionals Level: 300 Technology:
More informationThe Service Provider will monitor the VM for the Customer and provide notifications on an opt in basis, which is strongly recommended.
Virtual Machine Service Level Agreement 1. Agreement This agreement is to define Virtual Server Collocation services provided to a Customer. Typically, services definitions include hours, availability,
More informationDesigning and Deploying Messaging Solutions with Microsoft Exchange Server 2010
Course 10233A: Designing and Deploying Messaging Solutions with Microsoft Exchange Server 2010 OVERVIEW About this Course This five-day, instructor-led course provides you with the knowledge and skills
More informationHP Hardware Support Onsite 6-Hour Call-to-Repair Service HP Customer Support Contractual Service Package
HP Hardware Support Onsite 6-Hour Call-to-Repair Service HP Customer Support Contractual Service Package Technical data HP Hardware Support Onsite 6-Hour Call-to-Repair Service provides an IT manager with
More informationQHR Accuro EMR IT Hardware Requirements
QHR Accuro EMR IT Hardware Requirements Hardware Requirements for Accuro EMR Table of Contents Local Install Platform:... 3 Server Requirements:... 3 Workstation Requirements:... 4 Peripheral Requirements:...
More informationG-Cloud 6 Service Definition DCG Cloud Disaster Recovery Service
G-Cloud 6 Service Definition DCG Cloud Disaster Recovery Service 1 of 19 CONTACT INFORMATION Guy Silver T: 07733 008799 E: guy.silver@dcggroup.com W: www.dcggroup.com Data Continuity Group Limited, Bridge
More informationTown of West New York Hudson County, NJ Notice for R.F.P. (Request for Proposal)
Town of West New York Hudson County, NJ Notice for R.F.P. (Request for Proposal) Request for Proposals will be received by the Town Clerk of the Town of West New York, in the County of Hudson, New Jersey,
More informationInfrastructure Technical Support Services. Request for Proposal
Infrastructure Technical Support Services Request for Proposal 15 May 2015 ISAAC reserves the right to reject any and all proposals, with or without cause, and accept proposals that it considers most favourable
More informationService Description. Remote Consulting Service. Introduction to your service agreement. The scope of your service agreement
Service Description Remote Consulting Service Introduction to your service agreement Remote Consulting Services ( RCS ) provide for remote assistance with certain IT infrastructure tasks ( Service or Services
More informationEnterprise Management Service
Enterprise Management Service To assist you through the management of PowerSchool, the Pearson Technical Solutions Group ( TSG ) offers an Enterprise Management Service (EMS) agreement. The Enterprise
More informationCourse 2788A: Designing High Availability Database Solutions Using Microsoft SQL Server 2005
Course Syllabus Course 2788A: Designing High Availability Database Solutions Using Microsoft SQL Server 2005 About this Course Elements of this syllabus are subject to change. This three-day instructor-led
More informationSTATE OF NEVADA Department of Administration Division of Human Resource Management CLASS SPECIFICATION
STATE OF NEVADA Department of Administration Division of Human Resource Management LASS SPEIFIATION TITLE GRADE EEO-4 ODE IT TEHNIIAN SUPERVISOR 37 7.927 SERIES ONEPT Information Technology (IT) Technicians
More informationperforms a variety of complicated tasks, may lead and direct the work of others, may report directly to a project
State of Iowa-IT Services-Position Descriptions Levels of Experience The following levels of experience apply to all job categories unless a job category details other requirements (example Data Entry).
More information