State Data Centre Disaster Recovery Handbook Version 1.0

Size: px
Start display at page:

Download "State Data Centre Disaster Recovery Handbook Version 1.0"

Transcription

1 State Data Centre Disaster Recovery Handbook Version Page

2 Table of Contents Chapter 1: Introduction Overview Disaster Recovery Exclusion List Important References 4 Chapter 2: Business Impact Analysis & Risk Assessment Objective BIA Summary of Applications for DR Risk Assessment 6 Chapter 3: Disaster Recovery Planning (DRP) Task Force & Event Handling Procedures Team Composition Disaster Recovery Planning Coordinator Crisis Management Team Damage Assessment Team (DAT) Operations Recovery Team (ORT) Help Desk Disaster Recovery Process Flowchart <team coordinator> Criteria for Disaster Declaration and the Recovery Strategies Procedures for Emergency Response, Recovery & Restoration Time bound Disaster Recovery Directives Application level Classification for Disaster Recovery 17 Chapter 4: Disaster Recovery Plan Testing & Updation Plan Maintenance Test Plan Drill Plan 18 Annexure I : Damage Assessment Report Annexure II: Team Details Annexure - III: DR Site Activation Checklist Page

3 Chapter 1: Introduction As per the National egovernance Plan (NeGP), State Data Centres (SDC) have been coming up in all States / UTs of India to support various State Departments in running their applications catering to G2G (Government to Government), G2C (Government to Citizen), and G2B (Government to Business) services. With the maturity of SDCs and criticality realization of States applications and data, it has become imperative to provision a mechanism to secure the critical data of States. The Disaster Recovery (DR) Handbook, is a step in this regard. DR Handbook is a template DR Plan that the State is expected to populate with relevant entries, including extracts from the DR Strategy Document, as desired. It has been identified that the 4 NDCs of NIC located at Delhi, Pune, Hyderabad, and Bhubaneswar shall act as DR sites for the SDCs. This Handbook has been formulated keeping in mind the overall common State Data Centre Applications, Operations and Infrastructure. Individual Application level disasters to be handled by the User Dept. The SDC will support the User Departments in this activity. 1.1 Overview Every SDC, to protect itself from potential disruptions due to be caused by the occurrence of a disaster, needs to be in a certain DR readiness State so as to be in the best position to perform critical operational recovery activities in the a time efficient manner in the event of an actual disaster. An effective SDC DR Plan, thus, requires thorough coverage of all aspects in the event of a Disaster for the SDC, in order to ensure a smooth recovery of operations from the DR Site. Following are the aspects that are essential to be covered in this regard: What - Actions to be taken How - Procedures to be followed Who - Stakeholders expected to perform specific tasks When - Timelines to be adhered to, before, during, and after a disaster has been declared. A number of activities need to be performed to reach a state of DR readiness. These activities have been mentioned briefly as follows: i. Selection of Critical Applications to be considered for Disaster Recovery After due analysis to be conducted by the Composite Team along with the individual User Departments, critical applications shall be taken for Disaster Recovery. A Business Impact Analysis (BIA) needs to be conducted for the selection of critical applications. The same has been discussed in detail in Chapter 2. ii. Identification of Risks Various threats, however regular or event triggered, may pose a risk to the SDC Infrastructure to make it more vulnerable to external / internal disruptions. A Risk Assessment needs to be carried out at the SDC to identify which threat has the potential to cause more damage to the SDC and accordingly adopt Prevention Strategies to mitigate them. iii. Identification of DR Procedures, mapped with appropriate Timelines iv. Forming Action Teams for the Disaster Recovery Lifecycle and identifying their Roles and Responsibilities v. Regular DR Testing, Drills and DR Plan updations 3 Page

4 The succeeding chapter describes in detail all the above mentioned points. 1.2 Disaster Recovery Exclusion List While the complete DR Plan discusses in detail the various Disaster causing threats, there are certain scenarios, that may cause disruptions to the SDC operations, but are not valid scenarios for the declaration of a Disaster, as follows: Known Data Center equipment malfunctioning, where procedures and guidelines are already known to SDC on the recovery of the same. Network spikes caused owing to momentary high traffic flows and not due to any SDC common networking equipment / Software issues. Resignation / Unplanned extended Leave of any Data Center employee, however critical he / she may be to the daily Data Center operations. Virus / Spamming attacks on a single Server causing an isolated application outage. Any non-critical application shutting down, irrespective of the down time duration Planned Individual critical DR application shut down for a period less than the Defined DR RTO. Natural Calamity in the neighboring areas not bound to affect Data Center premises / operations. 1.3 Important References While all activities required for formulating an efficient SDC DR Plan are required to be done independently, there are specific parameters of some activities that overlap with other activities expected to be undertaken at the SDC as part of specific functions at the SDC. Following is a list of reference documents that may assist the State in specific DR Strategy planning activities: Document Name Original Purpose of Document SDC DR Strategy Document Disaster Recovery Strategy Planning SDC Information Security ISMS set up at the SDC for ISO Information System (ISMS) Risk Certification Assessment Report Reference for DR Strategy Overall SDC DR Planning Risk Assessment and Threat identification for DR Planning 4 Page

5 Chapter 2: Business Impact Analysis & Risk Assessment 2.1 Objective The objective of BIA is to understand the impact that could be caused to the organization if the business processes under consideration are disrupted and the concerned departments are unable to continue with their core processes. It has been carried out to develop an understanding of processes, resources required to carry out the processes, and recovery time frames for the same. The analysis includes gathered information regarding User Department processes and prioritizing them based on the following impacts: Financial Services Target Citizen base Legal and Regulatory Note: The State may append its own parameters with the ones mentioned above, as per its own individual priorities. A Draft Template for BIA is placed in the Annexure. Composite Team shall undertake the task of conducting BIA of User Department Applications along with the User Departments The approach adopted to achieve the objective of the BIA exercise shall be as follows: Identify business critical applications through interactions with representatives of the User Departments: Understand Applications and their relevance as per the above mentioned impacts Understand operational and functional interdependence between applications Conduct Business Impact Analysis sessions through personal interactions with a BIA Questionnaire Identify time-sensitive criticality ratings for critical applications Compile Recovery Objectives after thorough analysis of all of the above Prioritize recovery schedules of critical applications A detailed BIA result of all User Department applications shall be documented in the SDC BIA Report. As and when new Departments come on board, the BIA Report shall reflect the amended Applications analysis data. The BIA Report shall include the following Application specific data: 1. Recovery Point Objective (RPO): The point beyond which data loss is not permissible. It will act as the basis for the development of appropriate backup strategies. 2. Recovery Time Objective (RTO): The time within which the Systems/ Applications/ Functions must be recovered after an outage. It will act as a basis for the development of suitable recovery strategies. 3. Criticality Ranking of Applications The objectives above are set keeping in mind the threats and impact on the operations, coupled with the minimum recovery time required for the restoration of services. RTO planned shall take 5 Page

6 into consideration all the threats, including natural calamities. However, acceptable RTO and RPO for individual applications have been distinctly defined as per the Business Impact Analysis (BIA) findings. 2.2 BIA Summary of Applications for DR Following is the Table describing individual Recovery objectives for Applications and Data. The same shall be a compiled summary of the detailed BIA Report:- S No Applications RTO RPO Risk Assessment The objective of a Risk Assessment is to set priorities for the inherent threats to SDC and highlight exposures in the SDC environment. For the purpose of assessment of the potential risks, a relevant mix of IT related and generic threats are chosen, which may compromise the resources available at SDC. The approach towards risk assessment shall be taken to ascertain certain parameter ratings for each threat. These parameters are: Vulnerability - Indicating exposure of SDC to threats. This is a function of the specific weaknesses existing in spite of the mitigation, which exposes SDC to the respective threats. Probability - Indicating the probability of a threat occurring. This is a function of the inherent vulnerabilities in the environment and the existing mitigation for the threats. Impact - Indicating impact of a threat on SDC. This is a function of the technology enablers or facilities resources that may be affected due to occurrence of the threats. The assessment shall be conducted by the Composite Team, and shall be based on:- i. Discussions with SIA, DCO, and Application owners ii. Physical visits and observations at the Data Center site iii. Past history of disasters iv. Known relevant intelligence available in reliable public domain like Government websites. 6 Page

7 The Risk Assessment sheet prepared for the Information Security Management System implementation for SDC at the State may be referred for the above activity. Following is an indicative classification of the threats identified:- Physical and Environmental Threats - Fire - Earthquake - Cyclones - Power Outage - Physical Location Insecurities - Physical Security IT Services Threats - Weak Data Back-up - Inefficient Storage Management - - Weak Server Management - Vulnerable Operation Systems / Software The SDC DR Strategy Document may be referred for clarity on the SDC Threats mentioned above. 7 Page

8 Chapter 3: Disaster Recovery Planning (DRP) Task Force & Event Handling Procedures In order to facilitate the efficient recovery and restoration of critical business functions, key SDC staff members have been assigned to different teams. Any DRP event would be handled by four teams: Crisis Management Team (CMT), Damage Assessment Team (DAT), Operations Recovery Team (ORT), and Help Desk This section covers the composition, and indicative roles & responsibilities and the actionable steps to be followed by each of these teams. The functions of the above teams would vary with the extent and impact of the different disasters that could hinder SDC operations. The above mentioned teams shall be lead by the Disaster Recovery Planning Coordinator who shall be the responsible authority for timely recovery in the event of a disaster. 3.1 Team Composition Each team must have a designated Team Leader (Team coordinator) to drive the planning process as well as the team s response in the event of disaster. The first person listed on the team list is the Team Coordinator. Each coordinator is responsible for ensuring that the tasks and procedures detailed in the plan accurately reflect actions that will be taken during an actual disaster. Team listings must contain the names, phone number(s), and addresses of all team members. Because of the uncertainty of staff availability, team leaders are equipped to assign individual roles to team members at the time of Plan activation. 3.2 Disaster Recovery Planning Coordinator The key to success in developing and maintaining an effective and efficient Disaster Recovery capability is the leadership provided by the Disaster Recovery Planning Coordinator, who works closely with SDC stakeholders in ensuring absolute readiness in the wake of a disaster. Following are the key responsibilities of the DRP coordinator:- Provide overall guidance during the emergency response and recovery efforts Review damage assessment reports Initiate recall procedures Keep senior management and the concerned Department officials advised of recovery status, and Provide overall coordination support and assistance Note: In the absence of a DRP Coordinator, the Crisis Management Team Coordinator shall act as the DRP Coordinator. 3.3 Crisis Management Team The Crisis Management Team (CMT) comprises of senior staff, which commands the resources needed to recover SDC s operations in the event of a Disaster. The CMT members shall be listed in Annexure II. Members of CMT as well as other teams have been annexed so that various DR 8 Page

9 Stakeholders may keep isolated teams information without having to keep the entire SDC DR Strategy document. The Crisis Management Team, headed by the CMT Coordinator can operate from any location, provided they are available for communication. Note: The SDC Project Co-coordinator from the State Implementing Agency shall be the Crisis Management Team Coordinator in the absence of the nominated CMT Coordinator Roles & Responsibilities of Crisis Management Team Coordinator The CMT Coordinator shall have the overall responsibility for all response and recovery actions taken. However, he may delegate the team management and co-ordination responsibilities to other members of the Team. This will entail the complete delegation of decision-making power and authority for taking quick decisions as and when necessary. The CMT coordinator has a number of other responsibilities such as liaisoning with other departments in the SDC Group, for any recovery support. He/She would also be responsible for coordinating with all critical vendors for relevant support during the resumption of services. Responsibilities include: Disaster Declaration Overall responsibility for response & recovery actions Assisting in decision making, and data processing on impacts Authorizing crucial action steps Making arrangements for immediate relief to next of kin of any deceased staff Briefing staff of overall situation & giving overall guidance Vetting sensitive communications Assisting in crucial negotiations (financial & legal) Keeping the SIA informed of the status of the situation 9 Page

10 Crisis Management Team Members The CMT s responsibility is to manage and co-ordinate the response to, and recovery from, a crisis. This role will continue throughout the restoration until the situation returns to normal. That is, until SDC can cope with the situation without additional senior management supervision. The CMT carries out project management and decision-making, overseeing a senior State Data Centre management team that has the experience and expertise to provide necessary support in driving the recovery. Crisis Management Team does not perform any recovery tasks, focusing rather on the co-ordination and management roles It involves gathering relevant information and options from the various Operations Recovery and Damage Assessment teams to enable accurate decision-making, and to delegate and follow up tasks to ensure ground level implementations The individual recovery teams need to focus on their specific roles and responsibilities. However, it is important for them to understand the overall recovery strategy and appreciate the functions of other teams. The Crisis Management Team is responsible for communicating this information on a regular basis in order to prevent information isolation. The role requires absolute control over all aspects of recovery. The only way to achieve this is for all decisions to funnel through the Crisis Management Team. This will help reduce problems caused by individuals taking initiatives that upset the overall recovery progress. In short, the recovery teams must do what they are instructed to do, and all decisions must be referred to the Crisis Management Team. Responsibilities include Formalizing operational requirements Damage Assessment Coordinating and managing recovery of Facility, Operations and IT infrastructure Coordinating recovery of critical processes in different departments Deciding on teams to be invoked as deemed necessary for DR Liasioning with vendors for emergency / recovery support Monitoring Staff Welfare Proposing legal action, if required Crisis Management Team Recovery Actions Based on the initial information about the disaster, CMT would identify whether enablers / facilities have been affected or whether there is a risk of damage to premises or danger to employees. They would authorize the relevant parts of the CMT recovery actions as per the type and intensity of the disaster. The recovery actions of the Crisis Management Team can be classified into the following different categories: I. Emergency Actions II. Situation Assessment III. Plan Activation IV. Status Monitoring V. Recovery Support I. Emergency Actions 10 Page

11 1. Notify critical emergency contacts (internal and external) 2. Decide on location where the CMT will operate from, including exploring realistic possibilities of prolonged video conferencing support 3. Inform all CMT members of the selected location and time of the initial CMT meeting 4. Contact the DAT Coordinator to verify: Evacuation of employees undertaken, if deemed necessary Emergency security at the primary site Resumption of entry to premises 5. Receive Initial Assessments from the Damage Assessment Team Coordinator including list of missing persons / casualties, if any. 6. Decide Operations Recovery Team Coordinators to be mobilized and provide immediate instructions to the same 7. Establish the readiness of the DR Site through coordination with the NIC members at the mapped NDC, before the initial CMT meeting. II. Situation Assessment 1. Hold the initial CMT meeting 2. Complete an interim impact assessment. Consider the following:- Loss of life/ casualties, if any Extent of damage to premises Loss of IT Hardware Loss of applications Loss of communication links Loss of critical data Loss of other assets 3. Refine the Recovery Strategy according to the situation. Decide which DR Strategy to be invoked and brought into action. The SDC DR Strategy Document may be referred to in this regard. 4. Contact the personnel at the designated DR Site to:- Verify the level of resources and materials required. Facilitate the same. Plan occupation of alternate sites by Operations Recovery Teams Verify retrieval of emergency resources from off-site storage Verify timeframes for the availability of critical servers Verify voice line redirection, message content and call routing / handling to DR site 5. Establish timelines for the facilities and equipment available at the DR site to be operational, keeping individual RPOs and RTOs in concurrence. 6. Contact Damage Assessment Team (DAT) and establish whether access has been allowed to the damaged premises, and if so: What has been salvaged and its condition What has been irretrievably lost or destroyed What is intact, but inaccessible Infrastructure damage and access availability Expected rebuild timeframes (including possibilities of alternate Data Center site development) 7. Hold the Operations Recovery Team Coordinators briefing, which will include: Internal press release, résumé of events and status Damage and impact assessment Salvage status Recovery strategy and critical milestones Roles and responsibilities 11 Page

12 Operation recovery targets Staff transport arrangements to the alternate site(s) Timeframes for critical resource recovery (Systems etc) Funding and emergency purchase limits Team reporting and problem escalation guidelines Voice and fax communications availability and usage Progress reporting 8. The message to Team Coordinators must: Provide the minimum data to initiate the response and explain the current situation Verify the Team s individual Emergency Response Tasks Identify any business-critical activity demanding priority Confirm CMT and Team Coordinator s immediate contact details Give notice of the CMT and Team Coordinator s briefing time and place III. Plan Activation 1. Determine if assistance from third parties is required. 2. Confirm with the Operations Recovery Team coordinator at DR Site on the following: The recovery status of critical applications affected by the disaster event and being recovered at the DR sites. Obtain status of the following: Redirection of data communications Retrieval of back-up media Access to critical servers Establishing of IT Help Desk Intimation of IT Emergency procedures 3. Intimate User Departments for critical issues needing their involvement for data gathering & analysis IV. Status Monitoring 1. Contact Operations Recovery Team coordinator at DR Site for:- Progress against Critical Timeframes Assessment of availability and performance of systems and IT equipment Identification of current and anticipated resource needs. Assessment of current and anticipated problem areas in terms of technology and resource availability. Establishment of overall recovery progress. Review and adjustments in the Recovery Strategy. 2. Determine the extent of backlogs and their impact on recovery timeframes. 3. Continue contact with the Damage Assessment Team to review status of damage at the affected premises. 4. If the affected premises cannot be recovered or it will not become habitable within an acceptable timeline, make arrangements for a long-term recovery operation. Otherwise, initiate request to State for reconstruction and refit of affected premises. 5. Liaise with the Operations Recovery Team coordinator to begin to develop a long-term recovery plan. Convene a Crisis Management Team meeting to confirm and communicate updates to the recovery objectives and strategies. 6. Consolidate the detailed damage assessment and salvage report from the DAT. 7. Assess recovery expenditure outlay to date. 12 Page

13 8. Finalize Recovery action. 9. Update the DRP document for lessons learnt with respect to the DR process, if any. 10. Update internal operating and emergency procedures. V. Recovery Support: 1. Maintain contact with other Teams coordinators: Respond promptly to requests for information Inform of notable occurrences, which may affect priorities 2. Perform the following activities at each milestone: Receive Recovery Team reports of recovery progress against target time scales Review and update operational requirements Update the timeframe schedule Prepare updates for all Team coordinators Assess well-being of staff and identify need for Administration support Determine the need for third party assistance, and communicate the same Provide approved statements for use by the Recovery Team 3. Control all expenditure decisions and maintain regular contact with Finance Department 3.4 Damage Assessment Team (DAT) Perhaps the most important issue to be resolved immediately following a disaster is the status of affected SDC's resources, such as:- Information Technology Telecommunications equipments People The primary responsibility of the Damage Assessment Team is to assess the damage caused by the disaster and obtain key information concerning the level of serviceability of the facility and its resources. A Damage Assessment Team coordinator heads the Team, which includes members who are knowledgeable in the following areas: IT security, IT Infrastructure, and primary vendors Physical security for the damaged site Strong abilities to recover and salvage computer equipments and data/voice communications networks Knowhow of all relevant vendors and suppliers to determine equipment recovery requirements. Clarity of vision to drive the coordination channel between the various teams. The Damage Assessment Team makes an initial estimate in the mean time necessary to repair and/or replace infrastructure necessary for the resumption of operations. A Damage Assessment Report is prepared and reported to the Crisis Management Team. The damage assessment report shall follow the template as given in Annexure I. 3.5 Operations Recovery Team (ORT) 13 Page

14 The Operations Recovery Team would comprise of the head of the primary Data Center facility or a senior official nominated by him/her leading the team as a the Team coordinator, assisted by key personnel from the designated DR site. The objective of this team is to ensure that the IT Infrastructure is properly handled during the recovery process and the required resources are available on time. The focus of this Team is to recover the IT enablers supporting SDC s critical business processes, to be up and running in concurrence with the identified Recovery objectives (RTO and RPO). The Team must be aware of the Disaster Recovery Planning document. The other Teams must be able to assist the Operations Recovery Team, lead by the coordinator with the implementation of the plan. A detailed recovery checklist is given in Annexure-III. Detailed list of Operations Recovery Team composition and their contact numbers are given in Annexure-II. 3.6 Help Desk The Information Help Desk would play a crucial role in providing information proactively to various SDC Stakeholders. The information help desk should be manned by employees with good communication skills. The Help Desk shall assist the DR teams in communication setups like TeleConference, Video Conferencing, etc. Travel arrangements shall also be done by the Help Desk members. The Help Desk team details are available in Annexure. All employees should be advised to call the INFORMATION HELP DESK rather than operational staff or various Disaster Teams members for information. This will enable the operational staff members to focus on recovery procedures, rather than just providing information. The State shall consider the Roles & Responsibilities of all above mentioned teams and compile a Run Book of the events to take place post Declaration of Disaster, for DR and running of operations from the DR Site. The existing Help Desk at the SDC shall perform the emergency Help Desk operations described in detail in the SDC DR Handbook Document. Relevant training and drills shall be conducted for the Help Desk for coordination among various DR teams so as to assist in seamless recovery of operations from the DR Site in event of a Disaster. 14 Page

15 3.7 Disaster Recovery Process Flowchart <team coordinator> First Contact If any employee suspects a disruption of services falling under the potential Disaster Recovery criterion, the concerned employee should immediately inform his team lead. The lead should then communicate to the network / application owners in SDC for operational status / initial failure analysis. In case of a physical security incident, Help Desk shall inform Fire Brigade, Police and other Emergency Services, as the case may be. Crisis Management Team (CMT) coordinator should be contacted depending on the initial assessment carried out by Security / IT Department / Administrator or Facility in-charge DR Execution Verification Damage Assessment Team coordinator shall inform the Crisis Management Team Coordinator. The steps to be taken are: 1. Reporting a possible Disaster with a copy of the Initial Damage Assessment checklist. 2. Meeting the individual who gave the first alert and with personnel of the civic emergency services (fire station, police etc.) to assess extent of damage to the business. 3. Enter premises only with the consent of civic service personnel and evaluate extent of damage Declaration of Disaster 15 Page

16 Based on the intensity of an event, the initial assessment of the Damage Assessment Team (DAT), and the expected time to recover normal operations, the CMT shall suggest a DR event to the CMT Coordinator, who in turn will declare a Disaster. In the absence of the CMT Coordinator, the SDC Project Manager shall declare the disaster. 3.8 Criteria for Disaster Declaration and the Recovery Strategies The Disaster Recovery (DR) site for the Data Center has been established at < Designated DR Site> Decision for shifting to Disaster Recovery Site Approval for shifting operations to the DR site shall be obtained from the DRP coordinator. The procedure for transmission of data from the primary site to the DR Site, for restoration of database at the DR Site, as well as for switching over the system (with network changes) to DR Site shall be clearly documented. The SDC DR Strategy Document describes the various DR Strategies that may be adopted for different Disaster scenarios. The service recovery has to be initiated from the DR Site only after Disaster Declaration. 3.9 Procedures for Emergency Response, Recovery & Restoration Key administrators at the Data Center are identified in the following areas:- System Network & Security Database Storage & Backup Infrastructure Logistics / Administration All of the above are required to first assess the disruption in their respective identified DR services, and subsequently follow the problem resolution steps and appropriate recovery procedures for various threats. The Crisis Management Team should be notified in case the disruption is of a major level such that the restoration of services isn t possible for at least the minimum RTO time. 16 Page

17 3.10 Time bound Disaster Recovery Directives There needs to be clearly defined timelines for the steps to be taken from the Outage identification to Disaster Declaration. The State shall come up with a timeline as below to map the activities to their concluding periods. Timeline Activities to be performed Ownership Monitoring Problem / outage noticed Members 0-2 (minutes) 2-10 (minutes) (minutes) (minutes) (minutes) Respective employee informs lead and / or physical security head Lead performs initial analysis and communicates to administrators / administration In-charge / physical security head Initial analysis mail sent to all DAT and CMT members. Sample DAT meeting for damage analysis, control, and recovery timelines Communications to third party and vendors for recovery assistance Status mail sent from to all DAT and CMT members, copying DRP coordinator. CMT plans to meet, coordinating members' presence for call DAT continues analysis, sends initial report to CMT CMT meeting with DAT coordinator, with DRP coordinator as passive participant CMT discusses with DRP coordinator whether to proceed for Disaster declaration Disaster Declared. Communication through mail / notice board announcement / verbal announcement sent to all SDC employees Employee Team Lead Team Team Lead Damage Assessment Team coordinator Damage Assessment Team coordinator Damage Assessment Team coordinator Crisis Management Team first contact Damage Assessment Team coordinator Crisis Management Team Crisis Management Team Crisis Management Team Coordinator 3.11 Application level Classification for Disaster Recovery Criticality of all Applications shall be categorized into 3 classes, Class I - Highly Critical Class II - Critical Class III Not Critical All User Department applications covered under Class I and II shall be undertaken for Disaster Recovery, or as per individual decisions of the State. Also, all applications needn t necessarily be in the same recovery timeline bracket, i.e., some applications can be recovered earlier than the others. Thus, all applications have been classified under 3 priority scales. These scales represent the time brackets to be considered while recovering the critical applications at the respective DR sites. 17 Page

18 Chapter 4: Disaster Recovery Plan Testing & Updation An effective DRP is an evolving documentation, accommodating all changes within SDC in terms of people, process, and technology. To keep Disaster Recovery free from real-time operational obstacles, regular or need-based revisions need to be undertaken by concerned stakeholders. The ownership of DRP revisions shall lie with the Disaster Recovery Planning coordinator Plan updates will be the result of monitoring and testing of DR related activities. It is the responsibility of the DRP coordinator to revise the Disaster Recovery Plan appropriately once changes have been identified. Changes to the plan need to be discussed with the relevant personnel. 4.1 Plan Maintenance Plan maintenance includes time driven activities aimed for periodic revisions of the Disaster Recovery Plan to keep it up to date with the ever so changing dynamics of the organization. The frequency and type of reviews that need to be performed to maintain a Disaster Recovery Plan can be decided by the State as it finds feasible. 4.2 Test Plan Assumptions The test plan shall be formulated, based on the DR strategy selected by SDC and on the following assumptions: Adequate steps are taken so as to not affect the production environment All components of DR selected as part of DR strategy are implemented Dedicated resources are available during the DR testing Required test environment and tools are available Tests are being carried out in a low customer traffic time frame 4.3 Drill Plan Initially, SDC shall have a Bi-annual cycle of Disaster Mock drills between the production and DR sites. Over a period of time, with process maturity after conducting multiple drills, the same can be an annual activity. At least one participant from each team Identified for Disaster recovery activity should be available for the Disaster recovery. Drill Team members may be identified and informed prior to the Drill activity. For any drill, there shall be two nominated positions, being a DR planner and a Recorder. It is the Disaster Recovery Planning coordinator s responsibility to nominate himself / others as a DR Planner, and a Crisis Management Team member as a Recorder. 18 Page

19 Annexure I : Damage Assessment Report Damage Assessment Report Event Date Damage Assessment Team Member Event Reported by SDC Area Affected Initial Description of Event as given by the user Event Impact Description Damaged Area Loss of life/ casualties, if any Extent of damage to premises Loss of IT Hardware Damage Description Loss of applications Loss of communication links Loss of critical data Loss of other assets Root cause of the event as per Initial Assessment Expected Recovery Time Recommendation of DAT Team DAT Team Member Name: Signature: Date: 19 Page

20 Annexure II: Team Details An indicative list of Team members have been mentioned in the SDC DR Strategy Document, for the State s reference. However, the State may choose to nominate members as per its own convenience. A. Crisis Management Team (CMT) Coordinator Team Member Contact Details Name Designation Office Mobile B. Damage Assessment Team (DAT) Team Coordinator Team Member Contact Details Name Designation Office Mobile C. Operations Recovery Team (ORT) Team Coordinator Team Member Contact Details Name Designation Office Mobile D. Information Help Desk 20 Page

21 Team Coordinator Team Member Contact Details Name Designation Office Mobile 21 Page

22 Annexure - III: DR Site Activation Checklist All DR Teams must be aware of the Disaster Recovery Planning document. Other Teams must be able to assist the Operations Recovery Team, lead by the coordinator with the implementation of the plan Activity Responsibility Activity Status Meeting with CMT Coordinator, Operations Recovery Team Summarization of Root cause analysis as given by DAT Team Refer to Recovery steps to adopt Perform Necessary configuration changes for Recovery Coordinator, Operations Recovery Team Coordinator, Operations Recovery Team Operations Recovery Team Update CMT representative and Handover Recovery testing Update CMT representative Notify users about Service resumption Operations Recovery Team Operations Recovery Team Coordinator, Operations Recovery Team Crisis Management Team 22 Page

23 Annexure IV: Business Impact Analysis Business Impact Analysis (BIA) Template Application User Department Critical Processes Supported ApplicationDeveloper Hosting Model (Co- Located / Shared) X <State> SDC Address Head of Application Maintenance activity Interfaces with other applications Server Name OS Details Database Server and details Brief on X's functionality Business Impact on non - availability of business application system Type of Impact Description of impact Financial 23 Page

24 Services Citizen base Legal and regulatory Others Impact Financial Services Please indicate the rating of losses in term of Low, Medium or High Upt o 1 hou r 1-3 hou rs 3-8 hou rs 8-24 hou rs 1-3 da ys 3 da ys - 1 we ek 1-3 wee ks Mo re tha n 3 wee ks Citizen base Legal & regulatory Maximum Acceptable Downtime for the business application ( RTO ) : Maximum Acceptable Timeframe for data loss (RPO ) : Overall Criticality Rating : 24 Page

State Data Centre Disaster Recovery Strategy Document Version 1.0

State Data Centre Disaster Recovery Strategy Document Version 1.0 State Data Centre Disaster Recovery Strategy Document Version 1.0 Table of Contents SDC DR Strategy Document: Version 1.0 Chapter 1: Introduction... 4 1.1 Objective... 4 1.2 DR Site... 4 1.3 Assumptions...

More information

NEEDS BASED PLANNING FOR IT DISASTER RECOVERY

NEEDS BASED PLANNING FOR IT DISASTER RECOVERY The Define/Align/Approve Reference Series NEEDS BASED PLANNING FOR IT DISASTER RECOVERY Disaster recovery planning is essential it s also expensive. That s why every step taken and dollar spent must be

More information

Business Continuity Planning and Disaster Recovery Planning

Business Continuity Planning and Disaster Recovery Planning 4 Business Continuity Planning and Disaster Recovery Planning Basic Concepts 1. Business Continuity Management: Business Continuity means maintaining the uninterrupted availability of all key business

More information

Company Management System. Business Continuity in SIA

Company Management System. Business Continuity in SIA Company Management System Business Continuity in SIA Document code: Classification: Company Project/Service Year Document No. Version Public INDEX 1. INTRODUCTION... 3 2. SIA S BUSINESS CONTINUITY MANAGEMENT

More information

Guidelines for Infrastructure & Application Hosting in SDC

Guidelines for Infrastructure & Application Hosting in SDC Guidelines for Infrastructure & Application Hosting in SDC V 1.0 Department of Electronics & Information Technology, Ministry of Communications and Information Technology, Government of India Abstract

More information

How To Manage A Disruption Event

How To Manage A Disruption Event BUSINESS CONTINUITY FRAMEWORK DOCUMENT INFORMATION DOCUMENT TYPE: DOCUMENT STATUS: POLICY OWNER POSITION: INTERNAL COMMITTEE ENDORSEMENT: APPROVED BY: Strategic document Approved Manager Organisational

More information

CISM Certified Information Security Manager

CISM Certified Information Security Manager CISM Certified Information Security Manager Firebrand Custom Designed Courseware Chapter 4 Information Security Incident Management Exam Relevance Ensure that the CISM candidate Establish an effective

More information

Joint Universities Computer Centre Limited ( JUCC ) Information Security Awareness Training- Session Four

Joint Universities Computer Centre Limited ( JUCC ) Information Security Awareness Training- Session Four Joint Universities Computer Centre Limited ( JUCC ) Information Security Awareness Training- Session Four Data Handling in University Business Impact Analysis ( BIA ) Agenda Overview Terminologies Performing

More information

Institute for Business Continuity Training 1623 Military Road, # 377 Niagara Falls, NY 14304-1745

Institute for Business Continuity Training 1623 Military Road, # 377 Niagara Falls, NY 14304-1745 ECP - 601: Effective Business Continuity Management: ISO 22301 This 3-day course provides an intensive, hands-on workshop covering all major aspects for the design of an effective Business Continuity Plan

More information

SCHEDULE 25. Business Continuity

SCHEDULE 25. Business Continuity SCHEDULE 25 Business Continuity 1. Scope 1.1 This schedule covers TfL s requirements in respect of: any circumstance or event which renders, or which TfL considers likely to render, it necessary or desirable

More information

85-01-55 Overview of Business Continuity Planning Sally Meglathery Payoff

85-01-55 Overview of Business Continuity Planning Sally Meglathery Payoff 85-01-55 Overview of Business Continuity Planning Sally Meglathery Payoff Because a business continuity plan affects all functional units within the organization, each functional unit must participate

More information

Supervisory Policy Manual

Supervisory Policy Manual This module should be read in conjunction with the Introduction and with the Glossary, which contains an explanation of abbreviations and other terms used in this Manual. If reading on-line, click on blue

More information

Ohio Supercomputer Center

Ohio Supercomputer Center Ohio Supercomputer Center IT Business Continuity Planning No: Effective: OSC-13 06/02/2009 Issued By: Kevin Wohlever Director of Supercomputer Operations Published By: Ohio Supercomputer Center Original

More information

Data Center Assistance Group, Inc. DCAG Contact: Tom Bronack Phone: (718) 591-5553 Email: bronackt@dcag.com Fax: (718) 380-7322

Data Center Assistance Group, Inc. DCAG Contact: Tom Bronack Phone: (718) 591-5553 Email: bronackt@dcag.com Fax: (718) 380-7322 Business Continuity and Disaster Recovery Job Descriptions Table of Contents Business Continuity Services Organization Chart... 2 Director Business Continuity Services Group... 3 Manager of Business Recovery

More information

Disaster Recovery and Business Continuity Plan

Disaster Recovery and Business Continuity Plan Disaster Recovery and Business Continuity Plan Table of Contents 1. Introduction... 3 2. Objectives... 3 3. Risks... 3 4. Steps of Disaster Recovery Plan formulation... 3 5. Audit Procedure.... 5 Appendix

More information

Overview of how to test a. Business Continuity Plan

Overview of how to test a. Business Continuity Plan Overview of how to test a Business Continuity Plan Prepared by: Thomas Bronack Phone: (718) 591-5553 Email: bronackt@dcag.com BRP/DRP Test Plan Creation and Exercise Page: 1 Table of Contents BCP/DRP Test

More information

PAPER-6 PART-3 OF 5 CA A.RAFEQ, FCA

PAPER-6 PART-3 OF 5 CA A.RAFEQ, FCA Chapter-4: Business Continuity Planning and Disaster Recovery Planning PAPER-6 PART-3 OF 5 CA A.RAFEQ, FCA Learning Objectives 2 To understand the concept of Business Continuity Management To understand

More information

Business Continuity (Policy & Procedure)

Business Continuity (Policy & Procedure) Business Continuity (Policy & Procedure) Publication Scheme Y/N Can be published on Force Website Department of Origin Force Operations Policy Holder Ch Supt Head of Force Ops Author Business Continuity

More information

IT Disaster Recovery and Business Resumption Planning Standards

IT Disaster Recovery and Business Resumption Planning Standards Information Technology Disaster Recovery and Business IT Disaster Recovery and Business Adopted by the Information Services Board (ISB) on May 28, 1992 Policy No: Also see: 500-P1, 502-G1 Supersedes No:

More information

CITY UNIVERSITY OF HONG KONG Business Continuity Management Standard

CITY UNIVERSITY OF HONG KONG Business Continuity Management Standard PUBLIC Version: 1.0 CITY UNIVERSITY OF HONG KONG Business Continuity Management Standard (Approved by the Information Strategy and Governance Committee in December 2013; revision 1.1 approved by Chief

More information

Business Continuity and Disaster Recovery Policy

Business Continuity and Disaster Recovery Policy Maine State Government Dept. of Administrative & Financial Services Office of Information Technology (OIT) Business Continuity and Disaster Recovery Policy I. Statement The Office of Information Technology

More information

Guidelines For Technical and Financial Support For Establishment of State Data Centre (SDC)

Guidelines For Technical and Financial Support For Establishment of State Data Centre (SDC) Guidelines For Technical and Financial Support For Establishment of State Data Centre (SDC) Department of Information Technology, Govt. of India, Electronics Niketan, New Delhi 110 003. 1.0 Preamble 1.1

More information

The Weill Cornell Medical College and Graduate School of Medical Sciences. Responsible Department: Information Technologies and Services (ITS)

The Weill Cornell Medical College and Graduate School of Medical Sciences. Responsible Department: Information Technologies and Services (ITS) Information Technology Disaster Recovery Policy Policy Statement This policy defines acceptable methods for disaster recovery planning, preparedness, management and mitigation of IT systems and services

More information

Federal Financial Institutions Examination Council FFIEC. Business Continuity Planning BCP MARCH 2003 MARCH 2008 IT EXAMINATION

Federal Financial Institutions Examination Council FFIEC. Business Continuity Planning BCP MARCH 2003 MARCH 2008 IT EXAMINATION Federal Financial Institutions Examination Council FFIEC Business Continuity Planning MARCH 2003 MARCH 2008 BCP IT EXAMINATION H ANDBOOK TABLE OF CONTENTS INTRODUCTION... 1 BOARD AND SENIOR MANAGEMENT

More information

IT Disaster Recovery Plan Template

IT Disaster Recovery Plan Template HOPONE INTERNET CORP IT Disaster Recovery Plan Template Compliments of: Tim Sexton 1/1/2015 An information technology (IT) disaster recovery (DR) plan provides a structured approach for responding to unplanned

More information

Business Continuity Business Impact Analysis arrangements

Business Continuity Business Impact Analysis arrangements Aberdeen City Council Internal Audit Report 2012/2013 for Aberdeen City Council May 2013 Business Continuity Business Impact Analysis arrangements Final Report Contents Section Page 1. Executive Summary

More information

THORNBURG INVESTMENT MANAGEMENT THORNBURG INVESTMENT TRUST. Business Continuity Plan

THORNBURG INVESTMENT MANAGEMENT THORNBURG INVESTMENT TRUST. Business Continuity Plan THORNBURG INVESTMENT MANAGEMENT THORNBURG INVESTMENT TRUST Business Continuity Plan June 2012 Purpose The purpose of this Business Continuity Plan ( BCP ) is to define the strategies and the plans which

More information

<Client Name> IT Disaster Recovery Plan Template. By Paul Kirvan, CISA, CISSP, FBCI, CBCP

<Client Name> IT Disaster Recovery Plan Template. By Paul Kirvan, CISA, CISSP, FBCI, CBCP IT Disaster Recovery Plan Template By Paul Kirvan, CISA, CISSP, FBCI, CBCP Revision History REVISION DATE NAME DESCRIPTION Original 1.0 2 Table of Contents Information Technology Statement

More information

GUIDANCE NOTE FOR DEPOSIT-TAKERS. Operational Risk Management. March 2012

GUIDANCE NOTE FOR DEPOSIT-TAKERS. Operational Risk Management. March 2012 GUIDANCE NOTE FOR DEPOSIT-TAKERS Operational Risk Management March 2012 Version 1.0 Contents Page No 1 Introduction 2 2 Overview 3 Operational risk - fundamental principles and governance 3 Fundamental

More information

SAMPLE IT CONTINGENCY PLAN FORMAT

SAMPLE IT CONTINGENCY PLAN FORMAT SAMPLE IT CONTINGENCY PLAN FORMAT This sample format provides a template for preparing an information technology (IT) contingency plan. The template is intended to be used as a guide, and the Contingency

More information

Disaster Recovery Plan

Disaster Recovery Plan Disaster Recovery Plan Date: February 2, 2009 Revision: 9.0 EXTERNAL BUSINESS CONTINUITY PLAN PAGE 1 of 13 Federal regulation states, and internal corporate policies require, that Penson Financial Services,

More information

Federal Financial Institutions Examination Council FFIEC BCP. Business Continuity Planning FEBRUARY 2015 IT EXAMINATION H ANDBOOK

Federal Financial Institutions Examination Council FFIEC BCP. Business Continuity Planning FEBRUARY 2015 IT EXAMINATION H ANDBOOK Federal Financial Institutions Examination Council FFIEC Business Continuity Planning BCP FEBRUARY 2015 IT EXAMINATION H ANDBOOK Table of Contents Introduction 1 Board and Senior Management Responsibilities

More information

EMERGENCY PREPAREDNESS PLAN Business Continuity Plan

EMERGENCY PREPAREDNESS PLAN Business Continuity Plan EMERGENCY PREPAREDNESS PLAN Business Continuity Plan GIS Bankers Insurance Group Powered by DISASTER PREPAREDNESS Implementation Small Business Guide to Business Continuity Planning Surviving a Catastrophic

More information

Why Should Companies Take a Closer Look at Business Continuity Planning?

Why Should Companies Take a Closer Look at Business Continuity Planning? whitepaper Why Should Companies Take a Closer Look at Business Continuity Planning? How Datalink s business continuity and disaster recovery solutions can help organizations lessen the impact of disasters

More information

Temple university. Auditing a business continuity management BCM. November, 2015

Temple university. Auditing a business continuity management BCM. November, 2015 Temple university Auditing a business continuity management BCM November, 2015 Auditing BCM Agenda 1. Introduction 2. Definitions 3. Standards 4. BCM key elements IT Governance class - IT audit program

More information

CENTRAL BANK OF KENYA (CBK) PRUDENTIAL GUIDELINE ON BUSINESS CONTINUITY MANAGEMENT (BCM) FOR INSTITUTIONS LICENSED UNDER THE BANKING ACT

CENTRAL BANK OF KENYA (CBK) PRUDENTIAL GUIDELINE ON BUSINESS CONTINUITY MANAGEMENT (BCM) FOR INSTITUTIONS LICENSED UNDER THE BANKING ACT CENTRAL BANK OF KENYA (CBK) PRUDENTIAL GUIDELINE ON BUSINESS CONTINUITY MANAGEMENT (BCM) FOR INSTITUTIONS LICENSED UNDER THE BANKING ACT JANUARY 2008 GUIDELINE ON BUSINESS CONTINUITY GUIDELINE CBK/PG/14

More information

Emergency Response Plan

Emergency Response Plan Emergency Response Plan Public Version Contents INTRODUCTION... 4 SCOPE... 5 DEFINITION OF AN EMERGENCY... 5 AUTHORITY... 6 ACTION PRIOR TO DECLARATION... 6 FREEDOM OF INFORMATION & PRIVACY PROTECTION...

More information

Unit Guide to Business Continuity/Resumption Planning

Unit Guide to Business Continuity/Resumption Planning Unit Guide to Business Continuity/Resumption Planning (February 2009) Revised June 2011 Executive Summary... 3 Purpose and Scope for a Unit Business Continuity Plan(BCP)... 3 Resumption Planning... 4 Assumptions

More information

BUSINESS CONTINUITY MANAGEMENT PLAN

BUSINESS CONTINUITY MANAGEMENT PLAN BUSINESS CONTINUITY MANAGEMENT PLAN For Thistley Hough Academy Detailing arrangements for Recovery and Resumption of Normal Academy Activity Table of Contents Section Content 1.0 About this Plan 1.1 Document

More information

Disaster Recovery Plan

Disaster Recovery Plan Disaster Recovery Plan Date: Revision: 8.0 EXTERNAL BCP PLAN PAGE 1 OF 12 Federal regulation states, and internal corporate policies require, that Penson Financial Services, Inc. (Penson) develop Business

More information

Building a Disaster Recovery Program By: Stieven Weidner, Senior Manager

Building a Disaster Recovery Program By: Stieven Weidner, Senior Manager Building a Disaster Recovery Program By: Stieven Weidner, Senior Manager Part two of a two-part series. If you read my first article in this series, Building a Business Continuity Program, you know that

More information

Business Continuity Planning 101. +1 610 768-4120 (800) 634-2016 www.strohlsystems.com info@strohlsystems.com

Business Continuity Planning 101. +1 610 768-4120 (800) 634-2016 www.strohlsystems.com info@strohlsystems.com Business Continuity Planning 101 Presentation Overview What is business continuity planning Plan Development Plan Testing Plan Maintenance Future advancements in BCP Question & Answer What is a Disaster?

More information

INSIDE. Preventing Data Loss. > Disaster Recovery Types and Categories. > Disaster Recovery Site Types. > Disaster Recovery Procedure Lists

INSIDE. Preventing Data Loss. > Disaster Recovery Types and Categories. > Disaster Recovery Site Types. > Disaster Recovery Procedure Lists Preventing Data Loss INSIDE > Disaster Recovery Types and Categories > Disaster Recovery Site Types > Disaster Recovery Procedure Lists > Business Continuity Plan 1 Preventing Data Loss White Paper Overview

More information

Disaster Recovery Policy

Disaster Recovery Policy Disaster Recovery Policy INTRODUCTION This policy provides a framework for the ongoing process of planning, developing and implementing disaster recovery management for IT Services at UCD. A disaster is

More information

FINAL Version 1.0 November 6, 2014

FINAL Version 1.0 November 6, 2014 CENTERS for MEDICARE & MEDICAID SERVICES Enterprise Information Security Group 7500 Security Boulevard Baltimore, Maryland 21244-1850 Risk Management Handbook Volume II Procedure 4.5 FINAL Version 1.0

More information

Business Continuity Plan

Business Continuity Plan Business Continuity Plan October 2007 Agenda Business continuity plan definition Evolution of the business continuity plan Business continuity plan life cycle FFIEC & Business continuity plan Questions

More information

Creating a Business Continuity Plan. What We ll Cover... What is a BCP? Micky Hogue, CRM

Creating a Business Continuity Plan. What We ll Cover... What is a BCP? Micky Hogue, CRM Creating a Business Continuity Plan Micky Hogue, CRM Sandia National Laboratories Albuquerque, NM 505-844-6640 Mlhogue@sandia.gov What We ll Cover... What is a Business Continuity Plan Why create a BCP?

More information

The University of Iowa. Enterprise Information Technology Disaster Plan. Version 3.1

The University of Iowa. Enterprise Information Technology Disaster Plan. Version 3.1 Version 3.1 November 22, 2004 TABLE OF CONTENTS PART 1: DISASTER RECOVERY EXPECTATIONS... 3 OVERVIEW...3 EXPECTATIONS PRIOR TO AN INCIDENT OCCURRENCE...3 EXPECTATIONS PRIOR TO A DISASTER OCCURRENCE...4

More information

Enterprise UNIX Services - Systems Support - Extended

Enterprise UNIX Services - Systems Support - Extended 1 General Overview This is a Service Level Agreement ( SLA ) between and Enterprise UNIX Services to document: The technology services Enterprise UNIX Services provides to the customer. The targets for

More information

Business Continuity. Port environment

Business Continuity. Port environment Business Continuity Port environment DEFINE BUSINESS CONTINUITY WHAT IT IS NOT RECOVERY FOCUS: PEOPLE PROCESSES TECHNOLOGY DELIVERABLES INFRAGARD DEFINITION MANAGEMENT PROCESS DEVELOPING ADVANCE PROCEDURES

More information

Offsite Disaster Recovery Plan

Offsite Disaster Recovery Plan 1 Offsite Disaster Recovery Plan Offsite Disaster Recovery Plan Presented By: Natan Verkhovsky President Disty Portal Inc. 2 Offsite Disaster Recovery Plan Introduction This document is a comprehensive

More information

Business Continuity and Disaster Recovery Planning

Business Continuity and Disaster Recovery Planning Business Continuity and Disaster Recovery Planning Jennifer Brandt, CISA A p r i l 16, 2015 HISTORY OF STINNETT & ASSOCIATES Stinnett & Associates (Stinnett) is a professional advisory firm offering services

More information

Business Continuity Position Description

Business Continuity Position Description Position Description February 9, 2015 Position Description February 9, 2015 Page i Table of Contents General Characteristics... 2 Career Path... 3 Explanation of Proficiency Level Definitions... 8 Summary

More information

Building and Maintaining a Business Continuity Program

Building and Maintaining a Business Continuity Program Building and Maintaining a Business Continuity Program Successful strategies for financial institutions for effective preparation and recovery Table of Contents Introduction...3 This white paper was written

More information

Statement of Guidance

Statement of Guidance Statement of Guidance Business Continuity Management All Licensees 1. Statement of Objectives 1.1. To enhance the resilience of the financial sector and to minimise the potential impact of a major operational

More information

Disaster Recovery Plan The Business Imperatives

Disaster Recovery Plan The Business Imperatives Disaster Recovery Plan The Business Imperatives Table of Contents Disaster Recovery Plan The Business Imperatives... 3 Introduction... 3 A Disaster Recovery Program The Need of the Hour... 3 Approach to

More information

Systems Support - Standard

Systems Support - Standard 1 General Overview This is a Service Level Agreement ( SLA ) between document: and Enterprise Windows Services to The technology services Enterprise Windows Services provides to the customer The targets

More information

Documentation. Disclaimer

Documentation. Disclaimer HOME UTORprotect DOCUMENTATION AMS/ROSI SERVICES CONTACT Documentation Disaster Recovery Planning Disaster Recovery Planning Disclaimer The following project outline is provided solely as a guide. It is

More information

www.pwc.com Business Resiliency Business Continuity Management - January 14, 2014

www.pwc.com Business Resiliency Business Continuity Management - January 14, 2014 www.pwc.com Business Resiliency Business Continuity Management - January 14, 2014 Agenda Key Definitions Risks Business Continuity Management Program BCM Capability Assessment Process BCM Value Proposition

More information

BUSINESS CONTINUITY MANAGEMENT GUIDELINES FOR BANKS AND FINANCIAL INSTITUTIONS

BUSINESS CONTINUITY MANAGEMENT GUIDELINES FOR BANKS AND FINANCIAL INSTITUTIONS BUSINESS CONTINUITY MANAGEMENT GUIDELINES FOR BANKS AND FINANCIAL INSTITUTIONS DIRECTORATE OF BANKING SUPERVISION AUGUST 2009 TABLE OF CONTENTS PAGE 1.0 INTRODUCTION..3 1.1 Background...3 1.2 Citation...3

More information

Q uick Guide to Disaster Recovery Planning An ITtoolkit.com White Paper

Q uick Guide to Disaster Recovery Planning An ITtoolkit.com White Paper This quick reference guide provides an introductory overview of the key principles and issues involved in IT related disaster recovery planning, including needs evaluation, goals, objectives and related

More information

Cisco Unified Communications and Collaboration technology is changing the way we go about the business of the University.

Cisco Unified Communications and Collaboration technology is changing the way we go about the business of the University. Data Sheet Cisco Optimization s Optimize Your Solution using Cisco Expertise and Leading Practices Optimizing Your Business Architecture Today, enabling business innovation and agility is about being able

More information

NIST SP 800-34, Revision 1 Contingency Planning Guide for Federal Information Systems

NIST SP 800-34, Revision 1 Contingency Planning Guide for Federal Information Systems NIST SP 800-34, Revision 1 Contingency Planning Guide for Federal Information Systems Marianne Swanson NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY 1 Table Of Contents Introduction to NIST SP 800-34

More information

Flinders University IT Disaster Recovery Framework

Flinders University IT Disaster Recovery Framework Flinders University IT Disaster Recovery Framework Establishment: Flinders University, 1 August 2013 Last Amended: Manager, ITS Security Services, 4 October 2013 Nature of Amendment: Initial release Date

More information

Clinic Business Continuity Plan Guidelines

Clinic Business Continuity Plan Guidelines Clinic Business Continuity Plan Guidelines Published: January 2015 Table of Contents Emergency Notification Contacts Primary... 2 Emergency Notification Contacts Backups (in case primary is unavailable)...

More information

Business Continuity Planning Instructions

Business Continuity Planning Instructions Business Continuity Planning Instructions Business continuity planning is a proactive planning process that ensures critical services or products are delivered during a disruption. In creating the plan,

More information

DISASTER RECOVERY PLANNING GUIDE

DISASTER RECOVERY PLANNING GUIDE DISASTER RECOVERY PLANNING GUIDE AN INTRODUCTION TO BUSINESS CONTINUITY PLANNING FOR JD EDWARDS SOFTWARE CUSTOMERS www.wts.com WTS Disaster Recovery Planning Guide Page 1 Introduction This guide will provide

More information

COMCARE BUSINESS CONTINUITY MANAGEMENT

COMCARE BUSINESS CONTINUITY MANAGEMENT COMCARE BUSINESS CONTINUITY MANAGEMENT Title Business Continuity Management Version 2.1 Authorised by Executive Committee Effective date Authorisation date 10/7/2012 10/7/2012 COMCARE BUSINESS CONTINUITY

More information

1.0 Policy Statement / Intentions (FOIA - Open)

1.0 Policy Statement / Intentions (FOIA - Open) Force Policy & Procedure Reference Number Business Continuity Management D269 Policy Version Date 23 July 2015 Review Date 23 July 2016 Policy Ownership Portfolio Holder Links or overlaps with other policies

More information

PAPER-6 PART-1 OF 5 CA A.RAFEQ, FCA

PAPER-6 PART-1 OF 5 CA A.RAFEQ, FCA 1 Chapter-4: Business Continuity Planning and Disaster Recovery Planning PAPER-6 PART-1 OF 5 CA A.RAFEQ, FCA Learning Objectives 2 To understand the concept of Business Continuity Management To understand

More information

ICT & Communications Services Disaster & Recovery Plan

ICT & Communications Services Disaster & Recovery Plan ICT & Communications Services Disaster & Recovery Plan Advanced IT Services with George Spencer Academy www.aitn.co.uk Advanced IT Services - Arthur Mee Road, Stapleford, Nottingham. NG9 7EW Email: info@advanceditservices.co.uk

More information

Ohio Conference for Payroll Professionals Disaster Recovery

Ohio Conference for Payroll Professionals Disaster Recovery Ohio Conference for Payroll Professionals Disaster Recovery Speaker Bruce E. Phipps CPP 2011 APA Payroll Man of the Year Principal Product Manager US Legislative Analyst ORACLE Corporation bruce.phipps@oracle.com

More information

Business Continuity Planning (BCP) / Disaster Recovery (DR)

Business Continuity Planning (BCP) / Disaster Recovery (DR) Business Continuity Planning (BCP) / Disaster Recovery (DR) Introduction Interruptions to business functions can result from major natural disasters such as earthquakes, floods, and fires, or from man-made

More information

Disaster Recovery Plan Documentation for Agencies Instructions

Disaster Recovery Plan Documentation for Agencies Instructions California Office of Information Security Disaster Recovery Plan Documentation for Agencies Instructions () November 2009 SCOPE AND PURPOSE The requirements included in this document are applicable to

More information

Virginia Commonwealth University School of Medicine Information Security Standard

Virginia Commonwealth University School of Medicine Information Security Standard Virginia Commonwealth University School of Medicine Information Security Standard Title: Scope: Business Continuity Management Standard for IT Systems This standard is applicable to all VCU School of Medicine

More information

Threat Management: Incident Handling. Incident Response Plan

Threat Management: Incident Handling. Incident Response Plan In order to meet the requirements of VCCS Security Standards 13.1 Reporting Information Security Events, and 13.2 Management of Information Security Incidents, SVCC drafted an (IRP). Incident handling

More information

Smart Meters Programme Schedule 8.6. (Business Continuity and Disaster Recovery Plan) (CSP North version)

Smart Meters Programme Schedule 8.6. (Business Continuity and Disaster Recovery Plan) (CSP North version) Smart Meters Programme Schedule 8.6 (Business Continuity and Disaster Recovery Plan) (CSP North version) Schedule 8.6 (Business Continuity and Disaster Recovery Plan) (CSP North version) Amendment History

More information

ICT Contingency Plan Top Level Plan

ICT Contingency Plan Top Level Plan ICT Contingency Plan Top Level Plan - 1 - Document Control Information Title: ICT Contingency Plan: Top Level Plan Date: June 2013 Version: 3.0 Authors: John Redeyoff (NCC) Contents by Neil Dudleston /

More information

BUSINESS CONTINUITY PLAN

BUSINESS CONTINUITY PLAN Business Logo or Name here BUSINESS CONTINUITY PLAN FOR PERSONAL CARE PROVIDERS TEMPLATE PREPARED BY DEVON COUNTY COUNCIL EMERGENCY PLANNING SERVICE BUSINESS CONTINUITY PLAN LIST OF CONTENTS 1. DISCLAIMER...

More information

Proposal for Business Continuity Plan and Management Review 6 August 2008

Proposal for Business Continuity Plan and Management Review 6 August 2008 Proposal for Business Continuity Plan and Management Review 6 August 2008 2008/8/6 Contents About Newton IT / Quality of our services. BCM & BS25999 Overview 2. BCM Development in line with BS25999 3.

More information

BUSINESS CONTINUITY PLANNING GUIDELINES

BUSINESS CONTINUITY PLANNING GUIDELINES BUSINESS CONTINUITY PLANNING GUIDELINES Washington University in St. Louis The purpose of this guide is to serve as a tool to all departments, divisions, and labs across the University in building a Business

More information

BUSINESS CONTINUITY PLAN

BUSINESS CONTINUITY PLAN Business Logo Here BUSINESS CONTINUITY PLAN FOR SMALL TO MEDIUM SIZED BUSINESSES DATE :??? VERSION:?? PRODUCED BY DURHAM CIVIL CONTINGENCIES UNIT BUSINESS CONTINUITY PLAN LIST OF CONTENTS 1. DISCLAIMER...4

More information

Domain 1 The Process of Auditing Information Systems

Domain 1 The Process of Auditing Information Systems Certified Information Systems Auditor (CISA ) Certification Course Description Our 5-day ISACA Certified Information Systems Auditor (CISA) training course equips information professionals with the knowledge

More information

How to write a DISASTER RECOVERY PLAN. To print to A4, print at 75%.

How to write a DISASTER RECOVERY PLAN. To print to A4, print at 75%. How to write a DISASTER RECOVERY PLAN To print to A4, print at 75%. TABLE OF CONTENTS SUMMARY SUMMARY WHAT IS A DRP AND HOW CAN IT HELP MY COMPANY? CHAPTER PREPARING TO WRITE YOUR DISASTER RECOVERY PLAN

More information

Joint Universities Computer Centre Limited ( JUCC ) Information Security Awareness Training- Session Three

Joint Universities Computer Centre Limited ( JUCC ) Information Security Awareness Training- Session Three Joint Universities Computer Centre Limited ( JUCC ) Information Security Awareness Training- Session Three Information Security- Perspective for Management Business Impact Analysis ( BIA ) and Business

More information

BUSINESS CONTINUITY PLAN OVERVIEW

BUSINESS CONTINUITY PLAN OVERVIEW BUSINESS CONTINUITY PLAN OVERVIEW INTRODUCTION The purpose of this document is to provide Loomis customers with an overview of the company s Business Continuity Plan (BCP). Because of the specific and

More information

ITSM Tools Operation Continuity Plan Example

ITSM Tools Operation Continuity Plan Example ITSM Tools Operation Continuity Plan Example 1 Table of Contents 2 Introduction... 2 3 Invocation... 2 4 Scope... 2 5 Data Dependencies and Considerations... 3 6 Security and Access Considerations... 3

More information

Information Security Management: Business Continuity Planning. Presentation by Stanislav Nurilov March 9th, 2005 CS 996: Info. Sec. Mgmt.

Information Security Management: Business Continuity Planning. Presentation by Stanislav Nurilov March 9th, 2005 CS 996: Info. Sec. Mgmt. Information Security Management: Business Continuity Planning Presentation by Stanislav Nurilov March 9th, 2005 CS 996: Info. Sec. Mgmt. Overview BCP: Definition BCP: Need for (Why?) BCP: When BCP: Who

More information

Business Continuity Management

Business Continuity Management Business Continuity Management cliftonlarsonallen.com Introductions Brian Pye CliftonLarsonAllen Senior Manager Business Risk Services group 15 years of experience with Business Continuity Megan Moore

More information

Technology Recovery Plan Instructions

Technology Recovery Plan Instructions State of California California Information Security Office Technology Recovery Plan Instructions SIMM 5325-A (Formerly SIMM 65A) September 2013 REVISION HISTORY REVISION DATE OF RELEASE OWNER SUMMARY OF

More information

Processing Sites for Commonwealth Agencies

Processing Sites for Commonwealth Agencies Information Technology Supporting Documentation Commonwealth of Pennsylvania Governor's Office of Administration/Office for Information Technology Document Number: OPD-SYM004A Document Title: Guidelines

More information

SCHEDULE 25. Business Continuity

SCHEDULE 25. Business Continuity SCHEDULE 25 Business Continuity 1. Scope 1.1 This schedule covers TfL s requirements in respect of: any circumstance or event which renders, or is likely (in TfL s absolute discretion (subject to paragraph

More information

Information Technology Services (ITS)

Information Technology Services (ITS) Information Technology Services (ITS) Disaster Recovery Plan Version 2.11 DOCUMENT VERSION CONTROL Version Date Description/Notes Author/s V2.00 02/06/2014 New plan based on updated Standby plan. V2.10

More information

Head of Information & Communications Technology Responsible work team: ICT Security. Key point summary... 2

Head of Information & Communications Technology Responsible work team: ICT Security. Key point summary... 2 Policy Procedure Information security policy Policy number: 442 Old instruction number: MAN:F005:a1 Issue date: 24 August 2006 Reviewed as current: 11 July 2014 Owner: Head of Information & Communications

More information

UMHLABUYALINGANA MUNICIPALITY

UMHLABUYALINGANA MUNICIPALITY UMHLABUYALINGANA MUNICIPALITY DISASTER RECOVERY PLAN TEMPLATE DRAFT TO BE COMPLETED BY THE MUNICIPALITY TABLE OF CONTENTS 1. INTRODUCTION... 4 2. SCOPE OF THIS PLAN... 4 3. DISASTER SCENARIOS... 4 4. CURRENT

More information

Code Subsidiary Document No. 0007: Business Continuity Management. September 2015

Code Subsidiary Document No. 0007: Business Continuity Management. September 2015 Code Subsidiary Document No. 0007: September 2015 Change History Version Number Date of Issue Reason For Change Change Control Reference Sections Affected 20150511 11 May 2015 For industry consultation

More information

INFORMATION TECHNOLOGY ENGINEER V

INFORMATION TECHNOLOGY ENGINEER V 1464 INFORMATION TECHNOLOGY ENGINEER V NATURE AND VARIETY OF WORK This is senior level lead administrative, professional and technical engineering work creating, implementing, and maintaining the County

More information

OCCUPATIONAL GROUP: Information Technology. CLASS FAMILY: Security CLASS FAMILY DESCRIPTION:

OCCUPATIONAL GROUP: Information Technology. CLASS FAMILY: Security CLASS FAMILY DESCRIPTION: OCCUPATIONAL GROUP: Information Technology CLASS FAMILY: Security CLASS FAMILY DESCRIPTION: This family of positions provides security and monitoring for the transmission of information in voice, data,

More information

PPSADOPTED: OCT. 2012 BACKGROUND POLICY STATEMENT PHYSICAL FACILITIES. PROFESSIONAL PRACTICE STATEMENT Developing a Business Continuity Plan

PPSADOPTED: OCT. 2012 BACKGROUND POLICY STATEMENT PHYSICAL FACILITIES. PROFESSIONAL PRACTICE STATEMENT Developing a Business Continuity Plan PROFESSIONAL PRACTICE STATEMENT Developing a Business Continuity Plan OCT. 2012 PPSADOPTED: What is a professional practice statement? Professional Practice developed by the Association Forum of Chicagoland

More information

Disaster Recovery Planning

Disaster Recovery Planning Disaster Recovery Planning NOW or NEVER Disaster Recovery Team Aura Advanced Technologies Aura Advanced Technologies Inc 1301-1121 Sixth Avenue SW Calgary, Alberta T2P 5J4 Phone: 403-269-6123 Fax: 403-269-6169

More information