Contract Administration
|
|
|
- Stephanie Higgins
- 10 years ago
- Views:
Transcription
1 Contract Administration Patrick Mays, AIA Excerpt from The Architect s Handbook of Professional Practice, 13th edition 2000 As construction administrators, architects interpret construction contract documents, track the progress of the work, and reconcile the sometimes conflicting interests of owners and builders. The architect serving as a construction administrator observes construction for conformity to construction drawings and specifications. These documents are part of the legal contract between the owner and general contractor. When interpreting these legal documents, the architect s role shifts. The architect serves not as the owner s direct agent but in a quasi-judicial capacity, showing partiality to neither owner nor contractor. At other times during the construction phase the architect acts as the owner s representative and agent In the 1970s and early 1980s, in an effort to save money and fast-track construction, many developers started using nonarchitect construction managers for construction administration services. This placed architects in an awkward position, as they retained risk for the completed structure while not being compensated for their site observation services and other duties. Architects have strong incentives to serve as construction administrators. Through construction administration, the architect can support the continuity, quality, and intent of the design. The architect serving as a construction administrator can better manage and limit project risks by facilitating project communications and maintaining clear project records. Serving as construction administrator also enables t he architect to identify and correct problems in time to eliminate or minimize negative impact on construction costs. Summary CONTRACT ADMINISTRATION SERVICES Why a Client May Need These Services To ensure construction conforms to construction documents To support the design intent To lessen project risks To identify and resolve construction problems early To supplement the client s construction knowledge Knowledge and Skills Required Substantial design and construction experience Understanding of construction techniques and methods Ability to understand and interpret the design intent Understanding of building codes and standards Ability to communicate, negotiate, and resolve disputes Keen observational skills Ability to document observations and decisions Ability to organize and manage project records Representative Process Tasks Establish lines of communication CLIENT NEEDS Establish record-keeping system Respond to contractor s requests for information The continuing involvement of the architect during the construction phase helps assure the client that the completed building Review contractor s requests for payment Track changes in construction documents will reflect the design intent, and further ensures the quality of materials and workmanship. When the architect is retained by the owner Prepare field reports and records Review shop drawings and product information to administer the construction contract, the architect is the owner s Supervise completion and closeout representative in dealing with the contractor. The architect will be available for advice and consultation with the owner. In monitoring the construction, the architect will be alert to whether the contractor has carried out the design intent and the contract requirements relating to quality of workmanship and materials. The architect will endeavor to guard the owner against defects and deficiencies in the work. Clients who are building or renovating small commercial buildings or single-family residences are good markets for this service because they often lack experience with the building process and do not have the ability to oversee construction themselves. These clients should readily recognize the benefit of having the architect interact with building contractors and code inspectors on their behalf. Developers of multifamily residential or larger commercial facilities generally do not see the need for these services, as they prefer to use their own personnel. Architects who are not retained for services during the construction PATRICK MAYS is a principal and chief information officer at NBBJ Architecture Design & Planning. He is a co-author of Construction Administration: An Architect s Guide to Surviving Information Overload (1997). Supplemental Architectural Services 2000 AIA 1
2 The Architect Wears Three Hats Legally, the architect occupies three different positions as the professional service phases progress from inception of design to completion of construction contract administration. In 1977 a California appellate court clarified the tripartite legal position of an architect (Huber, Hunt & Nichols, Inc. v. Moore, 67 Cal App 3d 278, 136 Cal Reptr 603). The three separate and distinct roles recognized in law are: As an independent contractor As an agent of the owner As a quasi-judicial officer All of the standard AIA documents are based on these principles. As Independent Contractor An independent contractor is one who contracts to do something for another according to its own means and methods and not under control of the employer except as to the end result. During the time the architect is conferring with the owner, designing the project, preparing the contract documents, and administering the contract, the architect s relationship to the owner is as an independent contractor. The architect contracts with the owner to furnish architectural services for which the owner agrees to pay a fee. The architect s and owner s duties are spelled out in the owner-architect agreement. As Agent of the Owner An agent is one who has the authority to act for another, called the principal. After a contract has been entered into between the owner and the contractor, the architect s position changes. During the construction period, when the architect deals with the contractor and others in behalf of the owner, the architect is serving as the owner s agent. This is provided for in the owner-architect agreement (B , subparagraph ) and in the general conditions (A , subparagraph 4.2.1). However, the architect s powers to obligate the owner are restricted to the extent provided in the owner-architect agreement. When dealing with the contractor, the architect acts in a fiduciary capacity for the owner and in this position of trust must represent the owner s best interests. As a fiduciary, the architect has the duty to disclose to the owner all information that is material to the owner s interests. Some architects are inclined to shield the owner from some of the unpleasant technical details that plague the construction process. This could very well be a mistake, as some owners or their legal counsel might interpret this to be a violation of the architect s duty, as an agent, to disclose. Concealment of relevant information from the owner could be construed as fraud when there is a duty to disclose. Silence is often interpreted as concealment. Keeping the owner informed is also required by the general conditions (A , subparagraph 4.2.2), which state, in part, On the basis of on-site observations as an architect, the Architect will keep the Owner informed of progress of the Work. stage should refrain from visiting the site or volunteering uncompensated services. The standard of care requires design professionals to render the same quality of service whether properly compensated or not. In these cases, the architect might seek indemnification for lack of involvement mandated by the client. Among owners of owner-occupied buildings, concern for quality is a major motivator. Institutional and public owners of complex facilities such as sports arenas, hospitals, and schools are usually more than willing to pay for the architect s oversight and administration services. Most federal, state, and local government agencies are interested in architect-provided construction administration services, regardless of the type of facility involved. On the other hand, corporate clients who are constantly in the building market may be more confident of their ability to administer the construction phase, since they are more likely to have on-staff experts who are competent to handle it. A general rule of thumb is that about 25 percent of the architect s total compensation for services accounts for construction administration. This fee percentage is generally sufficient to compensate the architect for the following services during construction: Spending one day per week on site, attending a meeting and observing the progress of construction Responding to questions from the contractors and material suppliers Reviewing shop drawings and submittals Reviewing and certifying monthly applications for payment Authoring clarifications and minor changes to the documents Assisting consultants with construction administration duties Record keeping Project closeout responsibilities 2 Supplemental Architectural Services 2000 AIA
3 The architect is not in control of or in charge of the contractor but is authorized to reject work that does not conform to the contract documents. Although the owner is allowed to accept nonconforming work, the architect does not have this power, even as the owner s agent. If the owner wishes to confer this power on the architect, it should be done in writing. The architect s duty to represent the owner in dealing with the contractor should not be confused with the vigorous partisan advocacy commonly practiced by lawyers, since this would conflict with the third position of the architect. As Quasi-Judicial Officer The architect s third position is one of judge of the performance of the owner and the contractor under terms of the contract. Some have termed this position of the architect as being a friend of the contract. All claims by the owner or contractor against each other should be referred to the architect for initial decision as a condition precedent to more formal procedures such as mediation and arbitration. Some claims will be those alleging errors or omissions in the architect s own actions or work product. The architect must make even-handed, fair decisions strictly in accordance with the contract, not siding with either party. The architect also must be a fair interpreter of the documents. This can be difficult when the documents are imperfect and the architect s fair ruling will expose the documents to be at fault. When decisions on the intent of the documents are made, they must be based on some tangible evidence within the documents as to what is reasonably inferable and not merely on what is in the architect s mind. The architect s decisions must be formulated pursuant to procedural due process. This means that the architect must give reasonable notice to each party to allow its position to be made known before the architect makes a final decision. Arbitration tribunals and courts are inclined to look with suspicion on contracts where final decisions on the performance of the parties are made by a person under the control of one of the parties. Thus an architect s decision that is not fair, and is not seen to be fair, will be easily overturned by arbitrators and judges on appeal. The Architect s Liability The architect can be sued for negligence and breach of duty as an independent contractor and as an agent of the owner. These suits might be brought by the architect s client or by a third party such as the contractor, subcontractors, later owners, tenants, or passers-by. Third-party claims may be made even though the architect s client is satisfied with the professional service and has no complaint. However, the architect has immunity from suit for decisions made in the quasi-judicial capacity, provided they are made in good faith. The architect is liable only when acting fraudulently or with willful or malicious intent to injure the owner or contractor. Adapted from Arthur F. O Leary, FAIA, A Guide to Successful Construction: Effective Contract Administration, 3rd ed. (1999) One successful strategy for negotiating adequate fees for construction administration is to agree on a base fee for general services and then go through a construction administration checklist with the client and add each construction administration task as a supplemental service. This provides an opportunity to explain the value of each task to the client. Knowledgeable owners realize that the architect can often save them money through proper construction administration practices that, in effect, quality construction administration can pay for itself in risk reduction and in savings on time, materials, and change orders during the construction process. In most cases the architect who developed the drawings and specifications is in the best position to interpret them. Some architects make an analogy: If an attorney writes a contract, wouldn t you return to the same attorney when it came time to interpret the contract? The drawings and specifications written by the architect become part of the legal contract between the builder and the owner and that part of the contract is best interpreted by the professional who wrote it. No set of drawings and specifications is so tightly written that everything will be built exactly as designed. When the design architect is involved in contract administration, appropriate adjustments can be made as necessary to maintain quality, economy, and design integrity. This point can be a double-edged sword, however. Clients who perceive the architect as preoccupied with aesthetics may lack confidence in the architect s ability to recommend appropriate trade-offs. The architect must achieve credibility with the owner as a professional who will be attentive to cost and performance concerns. Construction administration is a traditional service that many architects provide within the scope of services defined in AIA Document B , Standard Form of Agreement Between Owner and Architect, and AIA Document B163, Owner-Architect Agreement for Designated Services. Supplemental Architectural Services 2000 AIA 3
4 G701 G701/CMa G702 G702/CMa G703 G704 G704/CMa G706 G706A G707 G707A G709 G710 G711 G712 G714 G714/CMa G722 G722/CMa G723 G723/CMa G805 G810 AIA Standard Forms Used in Construction Contract Administration Change Order Change Order Construction Manager Advisor Edition Application and Certificate for Payment Application and Certificate for Payment Construction Manager Advisor Edition Continuation Sheet for G702 Certificate of Substantial Completion Certificate of Substantial Completion Construction Manager Advisor Edition Contractor s Affidavit of Payment of Debts and Claims Contractor s Affidavit of Release of Liens The services grouped under Contract Administration Services in Document B141 include a mixture of tasks, some of which clearly fall under construction administration as discussed here (e.g., general administration, submittals, site visitation, administration of testing and inspection, supplemental documentation, administration of changes in the work, interpretations and decisions), and some of which are more in the realm of construction management (e.g., onsite project representation, payment certification, project closeout, construction management). The trend toward the design-build method of project delivery strongly influences the demand for construction administration. As already noted, the initial introduction of fasttrack construction reduced the architect s market for construction administration services, particularly among developers. Now the demand for design-build continues to grow, but owners in the corporate, institutional, and governmental markets more readily understand the benefits of architect-led design-build teams, providing architects with growing opportunities to offer construction administration services as part of more comprehensive construction management or design-build project delivery. It is useful to distinguish between construction management and construction administration. Construction managers oversee the field operations: administering construction contracts, scheduling materials shipments, and coordinating construction processes. The construction administrator does not oversee construction contracts and has no authority over or legal relationship with construction contractors. The construction administrator has only one way to assert control over construction rules, procedures, or requirements: to write them into the specifications. Other related services include construction documentation, commissioning, facility management and operations, and postoccupancy review. Consent of Surety to Final Payment Consent of Surety to Reduction in or Partial Release of Retainage SKILLS Proposal Request Architect s Supplemental Instructions A construction administrator needs Architect s Field Report substantial design and construction experience, a thorough understanding of construc- Shop Drawing and Sample Record Construction Change Directive tion techniques and methods, and the ability Construction Change Directive Construction Manager Advisor Edition to interpret the intent of construction documents. The construction administrator also Project Application and Project Certificate needs a thorough understanding of building Project Application and Project Certificate Construction codes, standards, and regulations as well as Manager Advisor Edition the ability to communicate, negotiate, and Project Application Summary resolve disputes with trade personnel. Project Application Summary Construction Manager Advisor Edition Much of the work of construction List of Subcontractors administration involves recording decisions Transmittal Letter that are made and events that take place on the job site. Keen observational skills are important. Perhaps most important of all is the ability to thoroughly document observations and decisions and to effectively manage the flow and retrieval of project records. For a typical project, the construction administration team would include the following: Construction administrator a senior person who possesses the necessary management and technical skills. This usually is a registered architect. Project architect someone with intimate knowledge of the project drawings. Often this is the same person as the construction administrator on smaller projects. 4 Supplemental Architectural Services 2000 AIA
5 Getting Started in Field Administration Professional work in an architect s office should be performed under the direct control and supervision of qualified architects. All offices are organized around this elementary principle. How can it be otherwise? Clients have the right to expect that the architect s services will be performed with professional skill and care. Experienced architects must direct, supervise, and check the work of the less qualified until the latter are able to work without such close control and guidance. This is the usual method by which recent university graduates can make the transition from the academic phase of their professional education through the practical experience phase and ultimately into professional competence and licensing. Work on clients projects is the medium through which all this educational and professional development in architects offices takes place. We cannot subject our clients to the possibility of substandard design, defective construction documentation, or incompetent contract administration. These negative prospects not only would be injurious to our clients but would also expose us to professional liability lawsuits. All office work should be reviewed in process and on completion by qualified personnel who are capable of recognizing errors, both of commission and of omission. Senior people must always be available to make the decisions that require professional judgment. Getting onto the Job Site All developing architects want to see how their office work looks on the construction site. The transition from office activities to field duties raises the problem of how to provide effective supervision of trainees. The client s project must not be allowed to deteriorate at any stage, least of all during the construction period. In addition, the contractor must not be deprived of the expected administration, advice, and judgment of a competent architect, as promised in the construction contract. Some of the architect s duties during the construction period will be carried out in the office, where competent supervision is generally available, while others must occur at the construction site. Common sense dictates that the first few site visits in the career of a trainee architect be in the presence of a fully qualified architect experienced in contract administration. The qualified architect will carry the main burden of responsibility, with the trainee observing, assisting, and learning. The trainee should take the notes in the field and write the reports in the office. Gradually, as the trainee is exposed to more of the process, the senior person can fall back to a position of monitoring and mentoring. Preparing for the First Field Trip Before assuming any duties in the field, the trainee should review the files of similar projects to get an idea of the general scope of documentation and administration, and to learn the language and procedures of contract administration. In preparation for the first field administration assignment, the trainee must become fully familiar with the requirements of the contract at hand. This means thorough review of the project s contract documents sufficient to gain a comprehensive understanding of their requirements. The trainee must also have an accurate understanding of the architect s duties and authority, as well as any limitations. In addition, the trainee should review the design file, and possibly interview the designer, to become acquainted with the design objectives and to find out what is important. The Architect s Duties and Responsibilities A good description of the architect s contract administration duties in the field and in the office will be found in the ownerarchitect agreement. The architect s duties, promised by the owner to the contractor, are in the general conditions. The main purposes of the architect s site visits are To become generally familiar with the progress and quality of the work completed To determine in general if the work is being performed in a manner indicating that the work, when completed, will be in accordance with the contract documents The architect s site observation should not be confused with the direct and constant supervision of workers exercised by contractors and subcontractors. The architect should not get involved in the details of how the work is being performed, but rather focus on whether the work will result in the specified outcome. The architect s principal duties on the job site are to observe, evaluate, and report; the contractor is responsible for controlling and directing the work. Frequency of Architect s Site Visits There is no specific frequency of site visits necessary to satisfy the contract or the standard of care. It is left up to the architect s professional judgment. Both B141 and A201 specify that the visits should be appropriate to the stage of construction. This implies that the frequency would vary depending on the character of the contractor s work on the site. Some architectural contracts specify the number, duration, or frequency of site visits. Some architects prefer to visit the site at the same time and day each week, biweekly, or monthly, so the contractor and subcontractors can be on hand to answer specific questions. Others prefer to appear at the site unannounced. In any event, the architect should conduct the site visit in the company of the contractor s representative usually the superintendent who can facilitate access to all parts of the work and receive instructions on behalf of the contractor. Defective Work The hope is that the architect on the site will recognize defective work. Defective work is anything that fails to meet some applicable criteria, such as the contract documents, the building code, or specified building standards. The architect does not have the power to (continued) Supplemental Architectural Services 2000 AIA 5
6 Getting Started in Field Administration (continued) accept nonconforming work unilaterally. However, the owner may allow nonconforming work to remain, with the contract sum reduced accordingly. The architect should advise the owner when such acceptance would be advantageous or inadvisable. Contractor s Responsibilities While on the construction site, the architect must not interfere in any way with the contractor s responsibility for job site safety and other safety programs. It is the contractor s sole responsibility to determine and control construction means, methods, techniques, sequences, and procedures. The contractor is in charge of the job site and is responsible for coordination of all portions of the work. The architect s prime interest should be to determine that the work, when finished, will conform with the contract documents. Adapted from Arthur F. O Leary, FAIA, A Guide to Successful Construction: Effective Contract Administration, 3rd ed. (1999) Project assistant may be a college graduate but not necessarily a registered professional Administrative assistant someone who can handle word processing, organizing, and filing As always, the key to success is to organize the work so that time-consuming and routine tasks can be assigned to the lower-paid team members, freeing senior professionals to concentrate on matters that require their judgment and expertise. An architect administering a construction contract will be called upon first to resolve claims by the owner or contractor against the other. The architect must be diplomatic, fair, and studious in all decision making, since the decisions will be final and binding if not appealed in accordance with the contract. Cost estimators and specifications writers are very important resources for the construction administration team. Cost estimators know how to determine the prevailing market value of various services for a given area, and specifications writers can contribute detailed knowledge about the characteristics and performance of building products. On complex projects, the team will benefit from the inclusion of a project management specialist who is familiar with techniques and computer software for managing project resources and costs in real time. The construction administration team works closely with other disciplines involved in the project, including structural, mechanical, electrical, and civil engineers; landscape architects; and other special consultants. Special equipment used for construction administration includes hard hats, steel-toed nonskid boots, tape measure, camera with date stamp, carpenter s level, portable tape recorder, a rip-proof jacket and gloves (good inspection involves crawling in some tight spaces), a utility knife, a pocket compass, field glasses, a laptop computer, and a cellular phone. PROCESS The scope of services as stated in the owner-architect agreement will depend on the delivery approach being used (e.g., fast-tracking, design-build), which in turn will affect the expected turnaround times for shop drawings and requests for information (RFIs). The project scope will depend on the size and number of buildings in the project, the phasing of construction, and the distance from the construction site to the architecture firm s location. The contract administration service is heavily oriented toward the legal rights of the owner and contractor. Therefore the architect must be careful and meticulous in all actions, decisions, and record keeping. Communications. The contract administrator is responsible for two types of communications: reporting to the client and facilitating communications among the owner, constructors, and design professionals. A preconstruction meeting is a valuable first step toward good communications in the contract administration process. Here the project work plan and schedule are reviewed. The relationships among the participants are clarified, including the processes for submitting RFIs and change orders. 6 Supplemental Architectural Services 2000 AIA
7 Subcontractors ordinarily are not allowed to communicate directly with the architect but must submit queries through the prime contractor. Record keeping. Clear record keeping plays an important role in communications and conflict avoidance. If all events and decisions are clearly recorded, it is easier to talk matters through when issues arise. Good record keeping is also of enormous value should the owner or contractor make legal claims. Establishing an effective filing system is another fundamental to success. One tip is to organize files by anticipating how contract administration materials will be searched. For example, some sample headings would be communications; meeting minutes; contracts for construction, including change orders and change directives; reports/program data; photographs; specifications and addenda; drawings; accounting records; and construction administration forms. Accurate telephone records are important in establishing complete project records because so many decisions are made over the telephone. A log of calls made and notes recording the time, date, results of all telephone conversations are recommended. In addition, all correspondence (letters, faxes, and s) must be logged and filed. Written records of conversations usually are distributed in order to confirm understandings reached verbally. Requests for information. Responding to RFIs from the contractor is an important duty of the construction administrator, and keeping up with RFIs and submittals can be challenging. A critical point is usually about one-third of the way into the job schedule, when submittals often peak. To avoid misunderstandings, it is important that the contract administrator answer questions from the job site through proper communication channels, in writing, and within a specified time frame. Requests for information are generally handled by an RFI form, which usually is provided by the general contractor and submitted to the construction administrator. As with telephone and correspondence records, it is necessary to keep a log that summarizes the status of all the RFIs. Document changes. The construction administrator tracks all changes in the construction documents. An addendum is a change made to the construction documents after they have been released for bidding but before the owner and contractor have signed a contract. A modification can take one of four forms: A written amendment to the contract signed by both parties A change order A construction change directive A written order for a minor change in the work issued by the architect A common sequence of steps toward implementing a change order a change in the drawings or specifications with cost and/or time implications would usually include a contractor s RFIs, the architect s proposal request (PR) describing what is being changed and why, the contractor s cost proposal, and the architect s change order (CO). An additional important inclusion is a revision sketch or revised specification issued by the architect. A change order becomes part of the owner-contractor agreement when it is signed by the owner and contractor. Contractor s payments. As the owner s representative, the construction administrator is expected to review the contractor s requests for payment, sometimes known as requisitions or applications for payment. Upon receipt of the contractor s application for payment, the contract administrator should visit the job site, observe the quantity and Record Keeping Required by the Owner-Architect Agreement The B owner-architect agreement requires the architect, during the bidding or negotiation phase, to Maintain a log of distribution and retrieval of the bidding documents and the amounts of deposits received from and returned to prospective bidders ( ) Document and distribute the bidding results ( ) In addition to whatever records an architect may keep in the normal process of performing contract administration duties, the owner-architect agreement specifically requires these three records to be maintained: Record of the contractor s applications for payment ( ) Record of submittals and copies of submittals supplied by the contractor ( ) Records relative to changes in the work ( ) Although the agreement does not specify the ultimate disposition of these records, presumably they are kept for the benefit of the owner. Thus it seems reasonable to provide copies at any time the owner requests them and at completion of the work. Communications Although the communication system among the parties during the construction period is defined in the AIA General Conditions, it is advisable to review the requirements so that all may understand and abide by them in practice. All communications between the owner and contractor should be channeled through the architect. All communications by and with the architect s consultants should be through the architect. All communications to or from the subcontractors and suppliers should be through the contractor. All communications with separate contractors should be through the owner (A201, 4.2.4). The superintendent on the job site is a representative of the contractor, and communications given to the superintendent are as binding as if given to the contractor. (A201, 3.9.1) All important communications should be in writing, or if given orally should be confirmed in writing Contract Administration Supplemental Architectural Services 2000 AIA 7
8 Agenda for Preconstruction Conference The specific agenda, of course, depends on the needs of the project. Some topics for discussion may include the following: Notice to proceed. The owner may issue written notice to proceed to the contractor; any questions should be discussed. Explanation of chain of command. Included are routing of shop drawings, catalogs, samples, project reports, scheduling reports, test reports, maintenance instructions, and so on. Communications channels. This is a reminder of the contractually mandated paths for communications among the participants. Project meetings. Scheduling, agenda, and attendance at project meetings are discussed. Duties of the owner and contractor. The general conditions and how the contract is intended to work are briefly reviewed. Insurance. Requirements for amounts and types of coverage and submittal of insurance certificates are reviewed. Financing. Evidence of the owner s ability to meet financial obligations is given. Submittals. Schedules are outlined for submittal of engineering data, shop drawings and operation and maintenance manuals, tests and inspections, and other submittals (including items required, procedures, number of copies, and distribution). Contractors are asked to send project representatives an unofficial preliminary copy and to identify specification section with each submittal. Contractors are reminded of their obligations with respect to shop drawing review and submittal as well as the language of the contractor s approval stamp. Progress payments. A schedule of values is established for the work of all trades, as well as procedures for progress payments. These procedures cover the handling of retainage and partial lien waivers; payment for materials on hand and materials stored off site; inspection, insurance, and title for stored materials; any special requirements for government agencies (e.g., the Department of Housing and Urban Development or the Federal Housing Administration) or the construction lender; scheduling of consultant s site visits; and submission of payroll records if required with requisitions for payment. List of subcontractors. A reminder is given that the general conditions may require the contractor, after award of the contract, to notify the architect in writing of the names of subcontractors or other persons or organizations proposed for portions of the work designated in the bidding requirements. Further is the requirement that the contractor shall not employ any subcontractor about whom the architect or owner has any reasonable objection. Employment practices. Any requirements regarding wage rates or similar issues are clarified. Utilities. Local regulations vary. Applications for temporary and permanent electric, gas, water, and telephone services must usually be made directly by the owner to the utility furnishing the service; the owner should be notified in sufficient time for the services to be in place when they are required. Scheduling. Job progress scheduling requirements include frequency of updates, times for submittals and approvals, and dates when owner-furnished equipment and furnishings are required. Contract changes and clarification. Procedures are set up for handling proposals, requests for backup information for change proposals, change orders, and construction change directives. Supplemental instructions are developed, such as procedures for obtaining interpretations of the contract documents (no changes should be made without appropriate authorization in writing). Security. Job site security during nonworking hours is determined. Parking. Parking areas are designated. Storage. Areas are assigned for temporary storage of equipment and materials; special protection is required for stored materials and equipment. Permits. Licenses, permits, and inspections required by local building authorities are reviewed. Right-of-way. Restrictions are reviewed on use of the site, access, or availability of rights-of-way, as are special requirements or cautions regarding adjacent property, protection of trees, and similar issues. Testing. The extent of testing laboratory and inspection services is decided, as well as who will be responsible for coordinating and scheduling their services. Routing of reports is also established. Overtime. Notice and scheduling necessary for overtime work are arranged. Cleanup. Responsibilities for cleanup and trash removal are assigned. Owner-furnished equipment and furnishings. Responsibilities for receipt, unloading, handling, storage, and security information on mechanical and electrical connections are clarified. Closeout. Procedures for closing out the project are delineated, including record drawings and other required submissions. Public relations. Policies regarding statements to the media, anticipated public interest in the project, and restrictions on construction operations and other public relations activities are discussed. Construction sign requirements are determined. Separate contracts. Their impact on the work of the project is evaluated. Requirements for coordination with other contractors on the site are discussed. 8 Supplemental Architectural Services 2000 AIA
9 quality of the work and materials suitably stored on the site, and compare them, item by item, with the contractor s request. Often contractors include the value of work that is expected to be completed by the time the payment is made. The architect cannot approve any work that is not in place at the time of the inspection. If the application includes the value of materials stored off the site or work in process in off-site workshops, the architect cannot approve payment unless the owner and contractor have so agreed in writing. In signing the requisition form or application and certification for payment, the construction administrator certifies that he or she has reviewed the work at the site, has found it in accordance with the schedule, and approves the release of money for that work. This is not to be taken lightly. All those who rely on the integrity of the architect s certificate, including the owner, contractor, subcontractors, suppliers, and lenders, expect that the architect will perform this function carefully, honestly, and with due diligence. Submittal review. Submittals are prepared by the contractor and include shop drawings, product literature, or actual samples of specific products to be installed; reports from independent testing agencies; operating instructions and maintenance manuals for installed equipment; and warranties from product suppliers and equipment manufacturers. The submittals are reviewed by the construction administrator, or the appropriate consultant, and become part of the permanent record of the project. Some or all of them are eventually given to the building owner for operations purposes. Field reports and records. Field reporting is a core activity for the construction administrator. The effective professional knows both how to conduct a thorough field observation and how to properly report relevant information to the owner. When on site it is important to be accompanied by a contractor s representative to facilitate communication with the contractor and to avoid any appearance that the construction administrator is providing supervision or instruction to contractor personnel. Ideally the field report will include notation of the date, time, weather, and temperature; notes about conditions, especially potential problems; a plan of the site that is annotated and keyed to the written report; and photographs to document the condition of the work in progress and to show its degree of completion. It is useful to have a system in place to track the status of issues from field reports until they are resolved. Completion and closeout. The construction administrator s role becomes especially important during the construction closeout. As the project nears completion, typically the owner is anxious to move in and the contractor is anxious to move on. Both are inclined to want to ignore small details that may cause performance problems later. The construction administrator is in a position to maintain the focus on quality construction through the contract requirements that require the architect to prepare the certificate of substantial completion for submission to the lender. When the contractor considers the work substantially complete, usually the contract administrator will be asked to perform an inspection. The lender often holds a 10 percent retainer until the construction administrator prepares a punch list that includes all the work that the contractor needs to address before the project is complete. Once completed, the punch list is sent to the contractor and owner along with a certificate of substantial completion. This acknowledges that the job is substantially complete and that the contractor can begin billing for monies retained from the construction fee. In signing the certificate, the contractor acknowledges that it will complete all the work on the punch list. A portion of the monies will continue to be retained until the punch list items are completed. Commissioning is one of several postconstruction services that rely on information generated during the construction phase. Supplemental Architectural Services 2000 AIA 9
10 Contract Administration was originally published in The Architect s Handbook of Professional Practice, 13 th edition, 2000 by the American Institute of Architects, published by John Wiley & Sons, Inc. The AIA provides a contract document designed especially for these types of architectural services. The AIA suggests a two-part agreement: B , Standard Form of Agreement Between Owner and Architect without a Predefined Scope of Architect s Services provides terms and conditions only. B , Standard Form of Architect s Services: Construction Contract Administration, for use where the Owner has retained another Architect for Design Services provides the architect s scope of services only. Together they equal a complete owner-architect agreement. AIA Document B establishes duties and responsibilities when an architect provides only construction phase services and the owner has retained another architect for design services. This scope requires the architect to perform the traditional contract administration services while design services are provided by another architect. B is a scope of services document only and may not be used as a stand-alone owner/architect agreement. NOTE: B replaces AIA Document B (expired May 31, 2009). B , Standard Form of Architect s Services: Design and Construction Contract Administration may be used when design services are also provided. AIA Document B replaces AIA Document B Part 2. AIA Document B defines the architect s traditional scope of services for design and construction contract administration in a standard form that the owner and architect can modify to suit the needs of the project. The services set forth in B parallel those set forth in AIA Document B : the traditional division of services into basic and additional services, with five phases of basic services. B is a scope of services document only and may not be used as a stand-alone owner/architect agreement. For more information about AIA Contract Documents, visit May 2011 The American Institute of Architects 10 Supplemental Architectural Services 2000 AIA
Memorandum Potentially Affected AIA Contract Documents AIA Document A105 2007 AIA Document B105 2007 Important Information
Memorandum Important information related to requirements of state or local laws to include additional provisions in residential construction contracts Potentially Affected AIA Contract Documents AIA Document
How To Get Construction Procurement Services
Construction Procurement William C. Charvat, AIA, CSI Excerpt from The Architect s Handbook of Professional Practice, 13th edition 2000 The procurement of construction services brings together the team
Document Commentary. B101 2007 Standard Form of Agreement Between Owner and Architect
Document Commentary B101 2007 Standard Form of Agreement Between Owner and Architect INTRODUCTION AIA Document B101 2007, Standard Form of Agreement Between Owner and Architect, is part of the A201 2007
Document B101 TM. Standard Form of Agreement Between Owner and Architect
Document B101 TM 2007 Standard Form of Agreement Between Owner and Architect AGREEMENT made as of the day of in the year 2014 (In words, indicate day, month and year.) BETWEEN the Architect s client identified
Document B101 TM. Standard Form of Agreement Between Owner and Architect
Document B101 TM 2007 Standard Form of Agreement Between Owner and Architect AGREEMENT made as of the th day of in the year 2014 (In words, indicate day, month and year.) BETWEEN the Architect s client
Checklist 26: How Owners Can Avoid Litigation on Construction Projects
Checklist 26: How Owners Can Avoid Litigation on Construction Projects While it is impossible to completely avoid litigation on construction projects, certain steps can be taken to minimize the potential
1 OF 7. there will be few "surprises" as the work progresses.
1 OF 7 FP-G1.94 GUIDELINES FOR SUCCESSFUL SUPERVISION OF SCHOOL DISTRICT CAPITAL CONSTRUCTION PROJECTS There is no doubt that the successful completion of any capital construction project is the result
Construction Management
Construction Management Robert C. Mutchler, FAIA, and Christopher R. Widener, AIA Excerpt from The Architect s Handbook of Professional Practice, 13th edition 2000 The construction manager is responsible
AGREEMENT FOR PROFESSIONAL DESIGN SERVICES
AGREEMENT FOR PROFESSIONAL DESIGN SERVICES This Professional Design Services (this "Agreement"), made as of 20 by and between the University of Cincinnati (the "University") by the Division of Administration
How To Build A House
CONTRACT TO BUILD A HOUSE AT I. Contract Parties Now comes (builder s name) (address) and (buyer s name) (address) to hereby agree to build a house on property located at (common address) and legally described
How To Write A Short Form Prime Prime Prime Contract Between A Contractor And Owner
SHORT FORM PRIME CONTRACT BETWEEN OWNER & CONTRACTOR This Agreement ( Contract ) is made this day of, 20, between ( Contractor ) and ( Owner ) at The work described in Section 1 below shall be performed
Depending on the size and complexity of your project, you may choose to work with a number of different professionals:
FEDERAL TRADE COMMISSION CONSUMER INFORMATION consumer.ftc.gov Hiring a Contractor Whether you re planning an addition for a growing family or simply getting new storm windows, finding a competent and
Client Contracts: Business Risk, Professional Liability & Insurance Coverage
Hanover Architects & Engineers Advantage Client Contracts: Business Risk, Professional Liability & Insurance Coverage Many client-drafted contracts endeavor to transfer unreasonable risk to the design
Document Comparison. AIA Documents A134 2009 and A131CMc 2003
Document Comparison AIA Documents A134 2009 and A131CMc 2003 AIA Document A134 2009 is in the right-hand column. Corresponding sections of AIA Document A131 CMc 2003 are in the left-hand column. Sections
NPSA GENERAL PROVISIONS
NPSA GENERAL PROVISIONS 1. Independent Contractor. A. It is understood and agreed that CONTRACTOR (including CONTRACTOR s employees) is an independent contractor and that no relationship of employer-employee
GOODS AND SERVICES AGREEMENT BETWEEN SOUTHERN CALIFORNIA PUBLIC POWER AUTHORITY AND COMPANY/CONTRACTOR NAME
GOODS AND SERVICES AGREEMENT BETWEEN SOUTHERN CALIFORNIA PUBLIC POWER AUTHORITY AND COMPANY/CONTRACTOR NAME This GOODS AND SERVICES AGREEMENT ("Agreement") is entered into and effective [DATE], by and
By: Pat Derdenger, Partner Steptoe & Johnson LLP 201 East Washington Street, 16 th Floor Phoenix, Arizona 85004-2382. Sub
ARIZONA TAX: CONSTRUCTION MANAGEMENT AND THE ORMOND CASE; THE COURT OF APPEALS FINALLY ANSWERS THE QUESTION OF WHETHER A CONSTRUCTION MANAGER IS A PRIME CONTRACTOR SUBJECT TO THE ARIZONA TRANSACTION PRIVILEGE
The Georgia Brokerage Relationships in Real Estate Transactions Act
Chapter 9 The Georgia Brokerage Relationships in Real Estate Transactions Act A. OVERVIEW PURPOSE OF THE ACT The Brokerage Relationships in Real Estate Transactions Act (BRRETA) http://www.crowngeorgia.com/brreta.htm
Attachment 5 Electrical Engineering
A. Phase 1, Preliminary Design: The CONSULTANT shall: Attachment 5 Electrical Engineering 1. Ascertain the requirements for each project through a meeting with the Capital Projects Division Manager or
LISA MADIGAN. Home Repair and Construction
OFFICE OF THE ATTORNEY GENERAL STATE OF ILLI NOIS LISA MADIGAN ILLINOIS ATTORNEY GENERAL Home Repair and Construction If you are like most Illinoisans, your home is your most valuable financial asset.
ACCIDENT INVESTIGATION GUIDELINES WITH LITIGATION IN MIND
ACCIDENT INVESTIGATION GUIDELINES WITH LITIGATION IN MIND Introduction The purpose of this paper is to alert the reader to concepts used in the defense of construction related lawsuits and to suggest how
Notes. Score. 1 Basic Services 1.1. A few instances; could have been more proactive
Jacobs Contract performance Tracking spreadsheet = Excellent 2 = Meets performance standards 1 = Improvement needed 0= Unsatisfactory Report for the time period: Annual report 210 Total average score 2.86
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. Part I: Proposal Information
REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES Part I: Proposal Information A. General Information The Berwick Area School District is soliciting proposals for construction management services
Document A312" 2010. of business) OWNER'S REPRESENTATIVE: (Architect, Engineer or other party:) 500 North Main Street Monroe, North Carolina 28112
Document A312" 2010 Payment Bond CONTRACTOR: (Name, legal status and address) OWNER: (Name, legal status and address) Union County 500 North Main Street Monroe, North Carolina 28112 CONSTRUCTION CONTRACT
AGREEMENT BETWEEN COUNTY AND CONTRACTOR FOR GOODS AND SERVICES. THIS AGREEMENT, effective this 20th day of April in the year, 2015, between:
AGREEMENT BETWEEN COUNTY AND CONTRACTOR FOR GOODS AND SERVICES THIS AGREEMENT, effective this 20th day of April in the year, 2015, between: MARTIN COUNTY BOARD OF COUNTY COMMISSIONERS, a political subdivision
Shawnee County ATTN: Bill Kroll 200 SE 7 th Street, Rm B-30 Topeka, KS 66603 Phone 785.251-4490 [email protected]
SECTION I Shawnee County is requesting qualifications/proposals for the renovation of 2600 SW East Circle Drive, Topeka, Kansas 66606 which will be utilized by the Shawnee County Health Agency per the
Contractor s Guide. April 2016
Contractor s Guide April 2016 The Minnesota Housing Finance Agency does not discriminate on the basis of race, color, creed, national origin, sex, religion, marital status, status with regard to public
STANDARD FORM OF AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR (Where Contractor and Subcontractor Share Risk of Owner Payment)
State License #CGC048773 STANDARD FORM OF AGREEMENT BETWEEN CONTRACTOR AND SUBCONTRACTOR (Where Contractor and Subcontractor Share Risk of Owner Payment) This Agreement is made this day of, 200, by and
REQUEST FOR PROPOSAL. Insurance Broker Services. Property Liability Casualty Fleet Workers Compensation
925 Felix Street St. Joseph, MO 64501 Telephone: 816-671-4000 Fax: 816-671-4469 REQUEST FOR PROPOSAL Insurance Broker Services Property Liability Casualty Fleet Workers Compensation CONTACT: RESPONSE DUE:
Construction Contract
Construction Contract Case Number: Date: Borrower Name(s): Phone #: Phone #: THIS IS A MODEL DOCUMENT FOR USE IN RENOVATION OR CONSTRUCTION LOAN TRANSACTIONS. THIS FORM IS PROVIDED AS AN EXAMPLE AND IS
REQUEST FOR PROPOSAL MECHANICAL, ELECTRICAL, PLUMBING ENGINEERING SERVICES VARIOUS BUILDING RENOVATIONS AND NEW CONSTRUCTION
REQUEST FOR PROPOSAL For MECHANICAL, ELECTRICAL, PLUMBING ENGINEERING SERVICES For VARIOUS BUILDING RENOVATIONS AND NEW CONSTRUCTION CITY OF ROCHESTER November 2009 TABLE OF CONTENTS GENERAL INFORMATION
CONSENSUSDOCS 300 STANDARD FORM OF TRI-PARTY AGREEMENT FOR COLLABORATIVE PROJECT DELIVERY
CONSENSUSDOCS 300 STANDARD FORM OF TRI-PARTY AGREEMENT FOR COLLABORATIVE PROJECT DELIVERY This document was developed through a collaborative effort of entities representing a wide cross-section of the
Construction Defect Action Reform Act
COLORADO REVISED STATUTES Title 13. Courts and Court Procedure Damages Regulation of Actions and Proceedings Article 20. Actions Part 8. Construction Defect Actions for Property Loss and Damage Construction
Document A101. Standard Form of Agreement Between Owner and Contractor where the basis of
TM Document A101 2007 Instructions Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum GENERAL INFORMATION Purpose. AIA Document A101 2007 is intended
AIA Contract Documents, by Family as of 10/20/2015
A101 2007 A101 1997 Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum A101 2007 SP A102 2007 A111 1997 A103 2007 A114 2001 Agreement Between Owner and Contractor, for
ASBESTOS/LEAD SURVEY AND CONSULTING AGREEMENT BY AND BETWEEN NEW YORK UNIVERSITY / NYU HOSPITALS CENTER - OWNER - AND - CONSULTANT - --------- PROJECT
APPENDIX A ASBESTOS/LEAD SURVEY AND CONSULTING AGREEMENT BY AND BETWEEN NEW YORK UNIVERSITY / NYU HOSPITALS CENTER - OWNER - AND - CONSULTANT - --------- PROJECT DATED AS OF ASBESTOS/LEAD SURVEY AND CONSULTING
Retaining Wall Replacement at the Currituck County Veterans Memorial Park
CONTRACT DOCUMENTS FOR Retaining Wall Replacement at the Currituck County Veterans Memorial Park Coinjock, NC May 24, 2016 NOTICE TO BIDDERS Bids will be received until 4:00 pm on June 17, 2016 at the
FOR PROPERTY LOSS AND DAMAGE 1
13-20-801. Short title Colorado Revised Statutes Title 13; Article 20; Part 8: CONSTRUCTION DEFECT ACTIONS FOR PROPERTY LOSS AND DAMAGE 1 This part 8 shall be known and may be cited as the Construction
TAFT LIBRARY ADDENDUM STANDARD FORM OF AGREEMENT BETWEEN TOWN OF MENDON ( THE TOWN ) AND ( ARCHITECT ) 1.1 Delete space if no additional information.
TAFT LIBRARY ADDENDUM STANDARD FORM OF AGREEMENT BETWEEN TOWN OF MENDON ( THE TOWN ) AND ( ARCHITECT ) This Addendum is attached to and modifies the Standard Form of Agreement between the Town and Architect,
REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT AT-RISK FOR LOGANVILLE ELEMENTARY SCHOOL (REPLACEMENT) FOR THE WALTON COUNTY SCHOOL DISTRICT
ADVERTISEMENT: REQUEST FOR PROPOSALS FOR CONSTRUCTION MANAGEMENT AT-RISK FOR LOGANVILLE ELEMENTARY SCHOOL (REPLACEMENT) FOR THE WALTON COUNTY SCHOOL DISTRICT The WALTON COUNTY SCHOOL DISTRICT will receive
REQUEST FOR PROPOSALS For. Kelowna and Vernon Hospitals Project
REQUEST FOR PROPOSALS For The Kelowna and Vernon Hospitals Project VOLUME 2 of 4 Instructions to Proponents Closing Time: Delivery Address: 3:00 pm (local time) Thursday, March 6,2008 Kelowna and Vernon
Cayo Software Reseller Agreement
Cayo Software Reseller Agreement Reseller Company Name: Contact Email Address: Phone: Website: Coverage Area: This agreement is between Cayo Software, LLC an Ohio Limited Liability Corporation (the VENDOR
Hiring and Working with. Contractors
Hiring and Working with Contractors Thank you for taking the time to learn more about hiring a contractor for your home repair or remodeling project. By taking the time to learn about the process of hiring
AIA Document A107 TM 2007
AIA Document A107 TM 2007 Standard Form of Agreement Between Owner and Contractor for a Project of Limited Scope AGREEMENT made as of the day of in the year (In words, indicate day, month and year.) BETWEEN
OWNER-ARCHITECT AGREEMENT FOR DESIGN AND ADMINISTRATION SERVICES
OWNER-ARCHITECT AGREEMENT FOR DESIGN AND ADMINISTRATION SERVICES MICHIGAN STATE HOUSING DEVELOPMENT AUTHORITY 735 East Michigan Avenue, Lansing, Michigan 48912 THIS AGREEMENT made on by and between (the
ON-TIME AND ON-BUDGET: KEY ISSUES IN NEGOTIATING CONSTRUCTION CONTRACTS
ON-TIME AND ON-BUDGET: KEY ISSUES IN NEGOTIATING CONSTRUCTION CONTRACTS ACC REAL ESTATE COMMITTEE PRESENTATION SEPTEMBER 17, 2009 SEAN T. BOULGER, ESQ. WILMER CUTLER PICKERING HALE AND DORR LLP I. Introduction
A. For the consideration agreed below to be paid to Contractor by City, Contractor shall provide
STATE OF TEXAS CONTRACT FOR SERVICES COUNTY OF DALLAS THIS CONTRACT is made and entered into by and between the CITY OF DALLAS, a Texas municipal corporation, located in Dallas County, Texas (hereinafter
AIA Contract Documents, by Series as of 10/20/2015
A101 2007 A101 1997 A101 2007 SP Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum Standard Form of Agreement Between Owner and Contractor, for use
Residential Construction
Office of the Attorney General Residential Construction LAWRENCE WASDEN Attorney General 700 West Jefferson Street Boise, ID 83720-0010 www.ag.idaho.gov State of Idaho Office of Attorney General Lawrence
AGREEMENT FOR CONSTRUCTION MANAGEMENT SERVICES. Responsibilities of Construction Manager Scope of Construction Manager s Basic Services
AGREEMENT FOR CONSTRUCTION MANAGEMENT SERVICES Article I Article II Article III Article IV Article V Article VI Article VII Article VIII Article IX Responsibilities of Construction Manager Scope of Construction
STANDARD SUBCONTRACT AGREEMENT FOR BUILDING CONSTRUCTION
STANDARD SUBCONTRACT AGREEMENT FOR BUILDING CONSTRUCTION THIS AGREEMENT made at Columbus, Ohio on by and between Lincoln Construction, Inc., hereinafter referred to as the Contractor, and, hereinafter
Make sure your builder is registered.
Marylanders purchase more than 10,000 new homes each year. The purchase of a new home is protected by Maryland law. Understanding your rights and responsibilities as a new home buyer protects your investment
Document Comparative
Document Comparative A201 2007 Compared to A201 1997 Additions to A201 1997 are underlined. Deletions from A201 1997 are in strikethrough text. TITLE General Conditions of the Contract for Construction
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK (CMAR)
REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER-AT-RISK (CMAR) For the Project: CITY OF KATY NEW KATY FIRE STATION #2 Issued: August 13, 2015 Katy Fire Station #2 August 13, 2015 Page 1 of 17 Request
COMMERCIAL CONSTRUCTION AGREEMENT. This CONTRACT AGREEMENT ( Contract ) is made on, 20, by and between <> ( Owner ) and <> ( Contractor ).
COMMERCIAL CONSTRUCTION AGREEMENT This CONTRACT AGREEMENT ( Contract ) is made on, 20, by and between ( Owner ) and ( Contractor ). A. Contractor wishes to enter into the following Contract with
KERN COMMUNITY COLLEGE DISTRICT AGREEMENT WITH INDEPENDENT CONTRACTOR
KERN COMMUNITY COLLEGE DISTRICT AGREEMENT WITH INDEPENDENT CONTRACTOR This Agreement is entered into by and between the Kern Community College District, on behalf of (Check One): District Office Bakersfield
INDEPENDENT CONTRACTOR SUPPLIER AGREEMENT. and include your affiliates. We, us, our, and ours refer to ConSol Partners, LLC. Client refers to.
Parties You, your, and yours refer to INDEPENDENT CONTRACTOR SUPPLIER AGREEMENT and include your affiliates. We, us, our, and ours refer to ConSol Partners, LLC. Client refers to. Services Provided We
Professional Services Agreement
BY ORDERING OR ACCEPTING PROFESSIONAL SERVICES FROM TASER INTERNATIONAL, INC. (TASER) YOU AGREE THAT YOU HAVE READ AND UNDERSTAND THIS AGREEMENT AND YOU ACCEPT AND AGREE TO BE BOUND BY THE FOLLOWING TERMS
CONTRACT FOR PROJECT MANAGEMENT SERVICES (Green Repair Program)
CONTRACT FOR PROJECT MANAGEMENT SERVICES () This Contract is made this day of in the year between (day) (month) (year) the, (Owner), Massachusetts (City) (State), (Zip Code) hereinafter called "the Owner"
Carmel Unified School District. Prequalification Application For Bleacher and Pressbox Replacement Project at Carmel High School
Carmel Unified School District Prequalification Application For Bleacher and Pressbox Replacement Project at Carmel High School January 4, 2016 1 NOTICE REGARDING PREQUALIFICATION FOR BLEACHER AND PRESSBOX
TOWN OF LINCOLN INVITATION TO BID EMERGENCY PLANNING, DISASTER RECOVERY AND HAZARD MITIGATION GRANT PROGRAM SERVICES RFP #2015-12
TOWN OF LINCOLN INVITATION TO BID EMERGENCY PLANNING, DISASTER RECOVERY AND HAZARD MITIGATION GRANT PROGRAM SERVICES RFP #2015-12 Sealed bids are due by 10:30 am on Friday, January 30, 2015 Bid Specs are
AGREEMENT BETWEEN THE UNIVERSITY OF TEXAS HEALTH SCIENCE CENTER AT SAN ANTONIO and PROJECT ARCHITECT for A PROJECT OF LIMITED SIZE OR SCOPE
AGREEMENT BETWEEN THE UNIVERSITY OF TEXAS HEALTH SCIENCE CENTER AT SAN ANTONIO and PROJECT ARCHITECT for A PROJECT OF LIMITED SIZE OR SCOPE This Agreement is made as of, 20 (the Effective Date ), by and
Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho
Independent School District No. 1 Strive Achieve Succeed Go Beyond Lewiston, Idaho REQUEST FOR QUALIFICATIONS Independent School District No. 1, Lewiston, Idaho ( District ) is seeking responses from individuals
Health Plan Select, Inc. Business Associate Privacy Addendum To The Service Agreement
This (hereinafter referred to as Addendum ) by and between Athens Area Health Plan Select, Inc. (hereinafter referred to as HPS ) a Covered Entity under HIPAA, and INSERT ORG NAME (hereinafter referred
APPENDIX A that is not acceptable. Arbitration settled by arbitration arbitration shall be held in New Jersey substantive law of New Jersey
APPENDIX A The attorneys in the Office of University Counsel at the University of Colorado Denver Anschutz Medical Campus review many different types of contracts on behalf of the University. Legal review
Document Commentary. A201 2007 General Conditions of the Contract for Construction
Document Commentary A201 2007 General Conditions of the Contract for Construction INTRODUCTION An integral part of the prime owner-contractor agreement, the general conditions of the contract sets forth
REQUEST FOR QUALIFICATIONS/REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES Various Projects RFQ/RFP No. 15-16-02
Banning Unified School District 161 West Williams Street, Banning, CA 92220 (951) 922-2706 phone (951) 922-0227 fax January 12, 2016 REQUEST FOR QUALIFICATIONS/REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT
CHAPTER 23. Contract Management and Administration
Date Issued: June 12, 2009 Date Last Revised: September 28, 2015 CHAPTER 23. Contract Management and Administration Table of Contents CHAPTER 23. Contract Management and Administration... 23-1 23.1 Policy...
CSA CONSTRUCTION, INC. 2314 McAllister Road Houston, Texas 77092 SUBCONTRACTOR AGREEMENT
CSA CONSTRUCTION, INC. 2314 McAllister Road Houston, Texas 77092 SUBCONTRACTOR AGREEMENT THIS AGREEMENT made this day of Month, Year, by and between CSA CONSTRUCTION, INC., a Texas corporation whose principal
Exclusive Booking Agent Agreement
Exclusive Booking Agent Agreement This Packet Includes: 1. General Information 2. Instructions and Checklist 3. Exclusive Booking Agent Agreement Exclusive Booking Agent Agreement 1 General Information
AIA Document A141 TM - 2004 Standard From of Agreement Between Owner and Design- Builder
AIA Document A141 TM - 2004 Standard From of Agreement Between Owner and Design- Builder AGREEMENT made as of the day of in the year of (In words, indicate day, month and year) BETWEEN the Owner: (Name,
PROFESSIONAL/CONSULTING SERVICES AGREEMENT
This SERVICES AGREEMENT ( Agreement ) is entered into by and between the undersigned, ( Contractor ), (Social Security Number or Federal I.D. No.), located at and Texas Southern University ( TSU ), an
Insurance Producer Agreement
Insurance Producer Agreement Section 1 - Producer s Authority The Producer shall periodically submit risks to the Company for its consideration as authorized by the Company. These risks shall be located
Consultancy Services Proposal
Consultancy Services Proposal August, 2007 ISO 9001 : 2000 CERTIFIED www.genivar.com 5858 Côte-des-Neiges Rd, 4 th Floor, Montreal, Quebec, Canada, H3S 1Z1 Telephone: (1) 514 340-0046 Fax: (1) 514 340-2847
REQUEST FOR PROPOSALS
REQUEST FOR PROPOSALS The Town of Ayer s Department of Planning & Development seeks proposals from qualified consultants to provide the following services in the Town of Ayer: INFRASTRUCTURE PROJECT CONSULTANT
Recitals. NOW, THEREFORE, the parties hereto agree as follows: Agreement
THIS INDEPENDENT CONTRACTOR SERVICES AGREEMENT (this Agreement ) is made this day of, 20 (the Effective Date ), regardless of the date of execution, by and between Sierra Field Services, Inc., a Nevada
PROFESSIONAL COUNSELSM
PROFESSIONAL COUNSELSM ADVICE AND INSIGHT INTO THE PRACTICE OF LAW Lawyers Toolkit 3.0: A Guide to Managing the Attorney-Client Relationship A CNA PROFESSIONAL COUNSEL GUIDE FOR LAWYERS AND LAW FIRMS The
STANDARD FORM OF GENERAL CONDITIONS OF CONTRACT BETWEEN OWNER AND DESIGN-BUILDER
STANDARD FORM OF GENERAL CONDITIONS OF CONTRACT BETWEEN OWNER AND DESIGN-BUILDER Document No. 535 Second Edition, 2010 Design-Build Institute of America Washington, DC Design-Build Institute of America
Morgan Hill Unified SCHOOL DISTRICT PREQUALIFICATION QUESTIONNAIRE FOR PROSPECTIVE BIDDERS. October 19, 2015
Morgan Hill Unified SCHOOL DISTRICT PREQUALIFICATION QUESTIONNAIRE FOR PROSPECTIVE BIDDERS October 19, 2015 The Morgan Hill Unified School District ( District ) has determined that contractors on future
AGREEMENT FOR FINANCIAL AND ACCOUNTING CONSULTATION SERVICES
AGREEMENT FOR FINANCIAL AND ACCOUNTING CONSULTATION SERVICES THIS AGREEMENT is made as of December 1, 2003, by and between the San Francisquito Creek Joint Powers Authority, a body corporate and politic
NORTH COLONIE CENTRAL SCHOOL DISTRICT 91 FIDDLERS LANE LATHAM, NEW YORK 12110-5349 INVITATION FOR CONSTRUCTION MANAGEMENT PROPOSALS
NORTH COLONIE CENTRAL SCHOOL DISTRICT 91 FIDDLERS LANE LATHAM, NEW YORK 12110-5349 INVITATION FOR CONSTRUCTION MANAGEMENT PROPOSALS The North Colonie Central School District invites your firm to submit
You & Your Architect A GUIDE FOR A SUCCESSFUL PARTNERSHIP.
A GUIDE FOR A SUCCESSFUL PARTNERSHIP. YOU AND YOUR ARCHITECT Architecture isn t only for museums, corporations, and the very wealthy. Whether you are remodeling a kitchen, creating your dream home, or
PROPERTY MANAGEMENT AGREEMENT
PROPERTY MANAGEMENT AGREEMENT OWNER: AGENT: PROPERTY: APN: Owner and Property Manager, as hereinafter identified, agree as follows: 1. APPOINTMENT OF AGENT: Owner hereby appoints and grants Property Manager
Advanced AMC, Inc. Appraiser Services Agreement (Independent Contractor Agreement)
Advanced AMC, Inc.. Appraiser Services Agreement (Independent Contractor Agreement) This Appraiser Services Agreement ( Agreement ) shall be effective as of the Effective Date by and between Advanced AMC,
Note: All terms which are defined and which are used throughout this document appear in italicized text beginning with a CAPITAL letter.
SCHEDULE OF CONSULTANT S SERVICES Note: All terms which are defined and which are used throughout this document appear in italicized text beginning with a CAPITAL letter. Project (Insert name and description
Sidewalk Rehabilitation Program
REQUEST FOR PROPOSALS FOR ENGINEERING AND CONSTRUCTION MANAGEMENT SERVICES Sidewalk Rehabilitation Program City of Maywood Building and Planning Department 4319 E. Slauson Avenue Maywood, CA 90270 Deadline:
City of Vallejo REQUEST FOR PROPOSAL WORKERS COMPENSATION CLAIMS AUDIT
City of Vallejo REQUEST FOR PROPOSAL WORKERS COMPENSATION CLAIMS AUDIT Date original issued: September 28, 2015 Qualifications Statements due: The City of Vallejo will consider Proposals submitted in response
NEWBURGH ENLARGED CITY SCHOOL DISTRIST NEWBURGH, NEW YORK REQUEST FOR PROPOSAL ARCHITECTURE SERVICES 2015 2016
NEWBURGH ENLARGED CITY SCHOOL DISTRIST NEWBURGH, NEW YORK REQUEST FOR PROPOSAL ARCHITECTURE SERVICES 2015 2016 Notice is hereby given that the Board of Education of the Newburgh Enlarged City School District,
STANDARD FORM OF CONTRACT FOR DESIGN-BUILD CONSULTANT SERVICES
STANDARD FORM OF CONTRACT FOR DESIGN-BUILD CONSULTANT SERVICES Document No 501 Second Edition, 2010 Design-Build Institute of America Washington, D.C. TABLE OF CONTENTS Article Name Page Article 1 Consultant
LEGAL SERVICES CONTRACT. THIS LEGAL SERVICES CONTRACT (this "Contract"), entered into as of
LEGAL SERVICES CONTRACT THIS LEGAL SERVICES CONTRACT (this "Contract"), entered into as of, 20 by and between PHILADELPHIA REDEVELOPMENT AUTHORITY ("Redevelopment Authority"), acting as agent for PHILADELPHIA
203K CONTRACTOR DOC REQUIREMENTS
203K CONTRACTOR DOC REQUIREMENTS CONTRACTOR REQUIREMENTS: Contractor's Resume/Contractor Profile Report Copy of Contractor Liability Insurance Evidence of Contractor License & Contractor Bonding(if required
Chase Lincoln Realty & Property Management Company 7045 Summer Place Charlotte, NC 28213 Phone: 704-921-1912, Fax: 704-921-1914
Chase Lincoln Realty & Property Management Company 7045 Summer Place Charlotte, NC 28213 Phone: 7049211912, Fax: 7049211914 EXCLUSIVE PROPERTY MANAGEMENT AGREEMENT Longterm Rental Property This Exclusive
GENERAL TERMS AND CONDITIONS
GENERAL TERMS AND CONDITIONS Contents A. SCOPE...3 B. CONFIDENTIALITY, NAME, INTELLECTUAL PROPERTY AND TAX EXEMPT STATUS OF THE WTO...3 B.1. Confidentiality...3 B.2. Use of the name, logo or official seal
