1 AGENDA ITEM No: 11 BRISTOL CITY COUNCIL RESOURCES SCRUTINY COMMISSION 28 March 2008 Report of: Director of Central Support Services Title: ICT Division - progress report Ward: City wide Officer presenting report: Stewart Long Contact telephone number: Recommendation Members are asked to note the report. Summary This report summarises recent developments within the ICT Division and also looks forward to planned changes and developments in the context of the Council's Business Transformation Programme. Policy Consultation None. Background - ICT Best Value Review 1. As part of the Council's overall Best Value Review process Council wide ICT services were reviewed in 2002/03. Embracing both central and departmental ICT services, a wide range of recommendations were made designed to improve and sharpen ICT within the Council. 2. The main recommendation was for the Council to move to an internal shared services organisational model. Historically the Council's ICT had been organised with many services arranged departmentally with a Central ICT Division providing a range of corporate services. This 1

2 arrangement led to duplication, fragmentation and inconsistency. 3. Moving to the centralised shared services model has delivered significant improvements. All technical/infrastructure services are now delivered from one central organisation and all technical staff are directly employed by the central unit. Common job descriptions and career structures provide a coherent and consistent organisational arrangement. The previous five separate ICT Help Desks have been rationalised into a single ICT Service Desk open, 12 hours a day and delivering significant economies of scale and expertise. 4. In parallel with the organisational changes significant infrastructure investment and rationalisation has been undertaken. Previously the technical infrastructure had been developed departmentally. This had led to a patchwork quilt of provision with some parts of the infrastructure modern and up to date with other parts old and in need of upgrade. 5. A major infrastructure project has now replaced the fragmented infrastructure with a new rationalised arrangement which is fit for purpose and affords significant advantages in terms of flexibility, office moves, mobile working etc. 6. It had initially been agreed that the changes described above would not apply within the former Education department (now CYPS). Subsequently, this decision has been modified and now the whole of CYPS, including technical support to primary schools, has been included. Some organisational changes within CYPS have already been made and more will follow over the next few months and detailed planning for infrastructure upgrades within CYPS is underway. 7. Appendix A outlines recent progress. There has been much enabling work following the infrastructure consolidation. Improved facilities have been delivered to all desktops, and the roll out of modern printing and flexible working facilities has helped achieve savings with the closure of Zion House and the forthcoming closure of College House. 8. However, while progress has been made on the Council's ICT infrastructure, the position in relation to the contribution of ICT to the achievement of the Council's business strategy is less satisfactory. This is referred to in the section on Business Transformation below. Performance and Benchmarking 9. Appendix B summarises benchmarking and performance for the ICT Division. Working with SOCITM we have access to a comprehensive set of comparative information, and we have adopted several of the Audit Commission's recently produced Value for Money Indicators. Customer 2

3 satisfaction has improved significantly and although there is still some way to go the direction of travel is positive and our monthly samples of customer feedback based on specific calls to the ICT Service Desk shows very high satisfaction ratings. 10. Other positive areas include excellent value for money in PC Procurement and desktop software provision. There are some areas for concern and these have been targeted with specific actions over the next few months. Connecting Bristol 11. The City Council has always had a good reputation for initiatives which support ICT within the wider City. The IT in the Community project in the late 90s was ground breaking at the time delivering widespread free public access to the Internet in community buildings and libraries and through street based access kiosks. The Connecting Bristol initiative which arose initially as part of the national Digital Challenge initiative will be important in taking this forward. 12. Bristol, along with nine other cities, has been chosen to take forward a number of projects (under the DC10 Programme) which aim to use ICT to 'make a difference' within the wider community and city. 13. Significant progress has already been made with Stephen Hilton taking the lead as Programme Manager on a full time basis. Many other partners in the City are fully engaged on specific projects. This includes wireless Internet projects to cover the new Cabot Circus shopping centre and projects furthering transport information and Internet connectivity within local communities. 14. Two projects are planned this year which have great potential for economic regeneration and improving job opportunities. Using ICT we intend to develop a 20 seat community based call centre in Filwood. This will provide local jobs for local people who will become part of a local hub connected to the Council's main Customer Contact Centre. This project will be linked to ICT skills training for local people and has significant potential to be replicated in other parts of the City in future years and has further scope to see call centre staff located in their own homes as well as at the community call centre. 15. 'Silvers of Time' is another technology-enabled project which should benefit those seeking work but unable to commit to regular or full time working. Using a powerful computerised database employers (including the City Council) and potential employees can 'match' jobs with potential applicants using the Internet. A potential employee enters their 3

4 availability (which might be just a few hours a week) and the Silvers of Time software matches this with possible jobs. Effectively an ultra flexible electronic 'labour exchange'. Underpinned by an agency arrangement dealing with references and CRB checks, payments etc, this has real scope to offer jobs to people who otherwise would find it impossible to find work. 16. These two projects are practical examples of how the Digital Challenge can use technology to advance wider City Council objectives in terms of regeneration and job creation. Business Transformation / KPMG findings 17. Members will be aware that KPMG are advising the City Council on its Business Transformation Programme. Recommendations are being formulated with a number of specific opportunities being developed for further work. Several planned ICT activities will need to take account of these recommendations when agreed. 18. KPMG's findings echo many of the themes in the Council's draft IS&T Strategy. Their summary key findings are: The lack of direction and Business Strategy appeared to be a recurring theme. With no guidance, ICT have been undertaking preparatory work in terms of consolidating and centralising the function in readiness of a future transformation. There was a lack of co-ordination between ICT and the other departments, which was compounded with the fact that ICT were often excluded from major IT procurement. This lack of engagement resulted in unfit systems being procured with poor integration. The ongoing operation of these systems was a cause of major pain to the Departments, who looked to ICT for resolution. With no discretionary budget, ICT were unable to implement improvement programmes and end up doing the best they can with resources available. ICT as an organisation were found to be in good health in terms of preparedness to react to departments needs, but the proliferation of systems have resulted in an overly large number of personnel in the ICT function. 19. It is clear that ICT will be crucial as an enabler of transformation. Technology solutions will underpin much of the change programme which is envisaged and will enable many processes to be improved and rationalised with consequent significant cost reductions. This will require investment in ICT infrastructure and skills but with a properly planned investment strategy this will enable significant savings and service 4

5 improvements to be delivered throughout the Council in future years. Legal and Resource Implications Legal : None sought. Financial : None sought. Appendix : 1 - ICT Progress. 2 - ICT Benchmarking. ACCESS TO INFORMATION: Background Papers: IS and T Strategy. SOCITM benchmarking data. 5

6 Appendix 1 ICT PROGRESS WORK ITEM PROGRESS NEXT STEPS STRATEGIC WORK ICT Strategy Substantial progress. New strategy produced. Will form an integral part of going forward in context of business transformation Internal shared ICT services Real progress with CYPS - they will now be included for both HQ and schools, mirroring rest of council arrangement. Organisational implementation by April 2008 Discussions with Director of NHS on revised model for departmental IS management Agreement on transfer of GIS staff to Property / ICT Business transformation Data provided for both council-wide and ICT-specific baseline exercises Organisation Blueprint and Opportunity Assessment expected March 08 Information management Progress slower than ideal but progress in areas of Finance and HR CYPS information management - director and management team have identified priority areas and systems replacement. Management information plan emerging Customer satisfaction Third year of participation in SOCITM external benchmarking. One of most improved ICT units. 30% improvement in two years New Fast Track process for ordering IT equipment Introduction of industry standard processes (ITIL) in progress, improvements gained in system reliability and customer communication. Business continuity Disaster plans for technology sound and robust. Detailed work with Emergency Planning to improve overall business continuity planning and readiness Progress core projects Review against BT Programme Apr 2008 Implementation Pilot during 2008 Implementation 2008 Review ICT Strategy Apr 2008 Develop more focussed plan Jun 2008 Detailed plan by April 2008 Review & improve ICT processes 2008 Streamline support activities Plans by Apr 2008 Implement data centre 2

7 INFRASTRUCTURE / SYSTEMS Corporate infrastructure Novell and managed desktop roll-out completed and consolidated Improved facilities at the desktop including controlled Internet access for all and Spam filtering. CYPS migration to standard desktop and council Novell infrastructure planned Detailed plan May 2008 End-of-life/replacement planning for current infrastructure begun Procurement Dec 2008 New services Online carers self-assessment. HomeChoice Bristol (on-line registration for rehousing applications) Submit-a-plan (Building Control and Planning services website) Wi-Fi in public libraries Online consultation on the Local Development Plan Automated HR Information Compendium CRM infrastructure Benefits, Rents and other NH&S & PTSD services transferred into CSC Recommendation expected Knowledge management software implemented for selected services from BT. BPR / integration approach The Source Major redevelopment and re-branding of corporate intranet - The Source. New look and feel, one stop shop for internal information / more information Simplified system for content authoring and management Home and mobile working Colston 33 and St Annes House implemented on time and budget. Major new technologies applied. Romney House project & vacation of College House on track. Comprehensive menu of technology choices now available which will support flexible working into the future. Enterprise application integration Identity / access management Detailed research into options completed. Evaluation and price/performance comparison in progress. Formal project launched to consolidate a number of pieces of work - secure extranet, single sign on and egov facilities Promote use and improve content 2008 Roll out improved facilities Jun 2008 Final evaluation by Apr 2008 Complete work package planning by Apr 2008

8 Electronic document management (EDM) Progress with DIP in major business units consolidated. Additional software with more flexible capabilities to meet flexible working requirements being evaluated. Printer strategy Colston 33 pilot very successful. Approach will be phased rollout in context with HQ accommodation strategy In-house systems Software licence costs reduced by replacement of obsolete PL/1 code Members use of ICT After a pilot all members have been offered a Blackberry device to allow them to work on the move A new portal page for members implemented as part of The Source Wireless networking being deployed to all CH Committee Rooms Implementation May 2008 To match accommodation plans Assess feasibility of handling all council papers electronically Complete rollout May 2008

9 Appendix 2 Benchmarking ICT Performance 2007 The ICT Service benchmarks annually with SOCITM (Society of IT Management ), and has this year adopted several new Value For Money indicators proposed by the Audit Commission. Table 1 summarises the results of our 2007 benchmarking exercise. Indicator BCC Median User Satisfaction (scored 1-7) Total cost of acquiring a PC Annual cost of a connection to the telephone network Annual cost of a connection to the data network Annual support costs per workstation Workstations supported per support specialist Service Availability (Weighted index over a set of key services 55% 64% for year 06-07) ICT problems resolved within agreed timescale 83% 91% Cost of the ICT function as a percentage of organisational 2.91% 2.04% running costs Average number of support calls per user per year 4 4 Management good practice indicator (see below) 7 - User Satisfaction User satisfaction has improved but remains below average. A comprehensive review of all ICT processes has been initiated to improve them from the customer perspective. Use of Resources The ratio of workstations to support staff has improved from 215 last year. Further improvement will result from ongoing improvements in both support processes and the underlying Infrastructure. Unit costs for telephone networks, data networks and PC provision are acceptable but can be improved. Recent investment in infrastructure and work within the corporate Accommodation Programme will lead to further reductions. BCC cost per user for desktop efficiency software is much lower than any other authority at 7.50 pa due to our use of StarOffice. However, desktop support costs are high. Standardised desktop provision, plus a review of ICT Division processes and organisation during 2008 will target a reduction in costs as well as improvements in user satisfaction. Cost of the ICT Service is significantly above average as a percentage of overall organisational costs, and has risen by 0.11% over the previous year. The figures partly 9

10 reflect a bulge in project work in the years concerned (eg infrastructure upgrades), and support costs for the internally-written finance system (CFS). The unusual complexity of the council's IT environment is also a factor, and proposals are emerging within the Business Transformation recommendations to address this. Reliability The figures quoted are for Intensive work on Service Availability during Jan Mar 2007 will produce a considerable improvement in the current year's figures. The introduction of a standard desktop in 2007 has already improved the number of problems resolved within agreed times, with figures for Apr Dec 2007 averaging over 90%. Work continues. Good Practice The ICT Service has 7 out of 10 indicators of good practice recommended by the Audit Commission in place. The three still to be achieved are: Good Practice Indicator Information security management capability is in place with BS7799 / ISO 27001accreditation already achieved. The organisation has a designated individual with the role of Chief Information Officer who has a seat on the board. The organisation has assessed the ICT competence of end users within the last 12 months and put in place an appropriate training and development programme BCC Progress Implementation project planned and Project Manager recruitment in progress. Planned within IS&T Strategy awaits next phase of Business Transformation programme. Currently this is a departmental responsibility. Corporate approach to staff skills and development proposed within Business Transformation programme. Bristol's ICT Project Management is mentioned by SOCITM as an example of good practice for routinely carrying out post-project reviews. 10

ICT Strategy 2010-2013

ICT Strategy 2010-2013 ICT Strategy 2010-2013 If you would like to receive this publication in an alternative format (large print, tape format or other languages) please contact us on 01832 742000. East Northamptonshire Council

More information

Technology Review Feedback Vale of Glamorgan Council

Technology Review Feedback Vale of Glamorgan Council Technology Review Feedback Vale of Glamorgan Council Audit year: Annual Improvement Assessment 2011 Issued: October 2011 Document reference: 538A2011 Status of report The person who delivered the work

More information

Manchester City Council Report for Information. Managing Attendance (Real Time Absence Reporting)

Manchester City Council Report for Information. Managing Attendance (Real Time Absence Reporting) Manchester City Council Report for Information Report to: Subject: Overview and Scrutiny Human Resources Subgroup - 25 January 2011 Managing Attendance (Real Time Absence Reporting) Report of: Assistant

More information

Joint ICT Service ICT Strategy 2014-17

Joint ICT Service ICT Strategy 2014-17 Document History Document Location This document is only valid on the day it was printed. The source of the document will be found in (see footer) Revision History Date of this revision: 19 th May 2014

More information

THE HIGHLAND COUNCIL Resources Committee 27 May 2015

THE HIGHLAND COUNCIL Resources Committee 27 May 2015 THE HIGHLAND COUNCIL Resources Committee 27 May 2015 Agenda Item 21 Unified Communications Project Report by the Depute Chief Executive/Director of Corporate Development Report No RES/ 48/15 Summary This

More information

Service Improvement Plan. DRAFT v.0.1. Harrow IT Services

Service Improvement Plan. DRAFT v.0.1. Harrow IT Services Harrow IT Services Service Improvement Plan DRAFT v.0.1 Harrow IT Services October 20 Contents 1. Introduction... Error! Bookmark not defined. 2. The Vision for HITS... Error! Bookmark not defined. 3.

More information

2.1 We are progressing towards the implementation of the future model approved by Ascham Homes Board in November 2014.

2.1 We are progressing towards the implementation of the future model approved by Ascham Homes Board in November 2014. Date: 18 th May 2015 Ascham Homes Board Agenda item: 6 Digital Service Design Update Author: Jo Murphy, Deputy Chief Executive Status: Public For: Decision Telephone: 020 8496 4023 1. PURPOSE 1.1 To provide

More information

Quarterly Performance Report ICT & Customer Services

Quarterly Performance Report ICT & Customer Services Quarterly Performance Report ICT & Customer Services Report Author Head of ICT & Customer Services Report Date 11th May 2012 Report Period Quarter 4: 1 st January 2012 to 31 st March 2012 Introduction

More information

CABINET 18 th May 2006. Report of the Director of Partnerships and Customer Services

CABINET 18 th May 2006. Report of the Director of Partnerships and Customer Services CABINET 18 th May 2006 Report of the Director of Partnerships and Customer Services ITEM 12 CRM Development Purpose of the Report To present the business case for replacement of the Council s Customer

More information

1. Introduction. 2. Performance against service levels 1 THE HIGHLAND COUNCIL. Agenda Item. Resources Committee 26 th March 2003 RES/43/03

1. Introduction. 2. Performance against service levels 1 THE HIGHLAND COUNCIL. Agenda Item. Resources Committee 26 th March 2003 RES/43/03 1 THE HIGHLAND COUNCIL Resources Committee 26 th March 2003 Performance report for January / February 2003 Report by the Information Systems Client Manager Agenda Item Report No 18 RES/43/03 Summary This

More information

Jenny Obee, Head of Information Management jenny.obee@barnet.gov.uk, Tel: 020 8359 4859. Micailah Fleming, IT Director micailah.fleming@capita.co.

Jenny Obee, Head of Information Management jenny.obee@barnet.gov.uk, Tel: 020 8359 4859. Micailah Fleming, IT Director micailah.fleming@capita.co. Performance and Contract Management Committee 7 January 2016 Title Report of Wards Status ICT Operations ITIL Methodology Assessment Chief Operating Officer All Public Urgent Key No No Enclosures None

More information

BPU Head of Service Position Statement

BPU Head of Service Position Statement BPU Head of Service Position Statement The aim of this paper is to provide a position statement regarding the identified BPU functions within the Annual Council Reporting Framework. Workforce It is considered

More information

Agenda Item No.6 (j) DERBYSHIRE COUNTY COUNCIL CABINET. Report of the Director of Transformation

Agenda Item No.6 (j) DERBYSHIRE COUNTY COUNCIL CABINET. Report of the Director of Transformation DERBYSHIRE COUNTY COUNCIL CABINET 26 th September 2012 Report of the Director of Transformation Agenda Item No.6 (j) INFORMATION AND COMMUNICATION TECHNOLOGY (ICT) STRATEGY Purpose of Report To seek Cabinet

More information

Efficiency Scrutiny Committee 16 th September 2014 IT - Scrutiny of the Service Review process and viability of options for change

Efficiency Scrutiny Committee 16 th September 2014 IT - Scrutiny of the Service Review process and viability of options for change Efficiency Scrutiny Committee 16 th September 2014 IT - Scrutiny of the Service Review process and viability of options for change For Decision Member Champion(s): Cllr A Alford, Corporate - Director:

More information

Appendix A: ICT and Information Management Strategy

Appendix A: ICT and Information Management Strategy Appendix A: ICT and Information Management 2014 2019 Head of Information and Business Change Sarah Caulkin October 2014 1 Version Control: Date Version Author Comments 04/08/14 0.1 Jo Harley First draft

More information

LOCAL GOVERNMENT NEW ZEALAND TECHNICAL ASSISTANCE FACILITY

LOCAL GOVERNMENT NEW ZEALAND TECHNICAL ASSISTANCE FACILITY PacificTA LOCAL GOVERNMENT NEW ZEALAND TECHNICAL ASSISTANCE FACILITY COOK ISLANDS MINISTRY OF INFRASTRUCTURE AND PLANNING NOVEMBER 2013 This report has been prepared for the Ministry of Infrastructure

More information

Overview and Scrutiny Forum Resources

Overview and Scrutiny Forum Resources Overview and Scrutiny Forum Resources Part 1 17 th December 2004 Item No 4 Subject Purpose Author Ward Summary Implementation of Oracle iprocurement Suite The purpose of this report is to update members

More information

Service and Improvement Plan 2015 18

Service and Improvement Plan 2015 18 Service and Improvement Plan 2015 18 Property and Risk 1. Introduction Property and Risk Service and Improvement Plan 2015 2018 1.1 The Property and Risk Service and Improvement Plan covers the period

More information

Derbyshire County Council Performance and Improvement Framework. January 2012

Derbyshire County Council Performance and Improvement Framework. January 2012 Derbyshire County Council Performance and Improvement Framework January 2012 Contents 1. Introduction 3 2. About the framework 4 3. Planning 7 5. Monitoring Performance 8 6. Challenge and Review 11 7.

More information

Oxford City Council ICT Strategy 2015 2018

Oxford City Council ICT Strategy 2015 2018 Oxford City Council ICT Strategy 2015 2018 1 Contents 2 Overview... 2 3 OCC Business Drivers... 2 4 ICT Principles... 3 4.1 Business Requirements... 3 4.2 Information Management... 3 4.3 Applications...

More information

ICT PROGRAMMES AND PERFORMANCE QUARTER 3 2013-14

ICT PROGRAMMES AND PERFORMANCE QUARTER 3 2013-14 Report to Finance and Property Committee 24 February 2014 Agenda Item: 5 REPORT OF THE SERVICE DIRECTOR, ICT ICT PROGRAMMES AND PERFORMANCE QUARTER 3 2013-14 Purpose of the Report 1. To provide the Finance

More information

ICT Indicators. The scope of the ICT function covers all aspects of infrastructure, systems, processes and disciplines required to support:

ICT Indicators. The scope of the ICT function covers all aspects of infrastructure, systems, processes and disciplines required to support: ICT Indicators ICT value for money indicators guidance 1) Introduction This document sets out the indicators for the ICT Function. The guidance below starts by defining the scope of the function and goes

More information

AUDIT & PERFORMANCE REVIEW COMMITTEE ON 26 TH SEPTEMBER 2007

AUDIT & PERFORMANCE REVIEW COMMITTEE ON 26 TH SEPTEMBER 2007 PAGE: 1 REPORT TO: SUBJECT: BY: AUDIT & PERFORMANCE REVIEW COMMITTEE ON 26 TH SEPTEMBER 2007 ASSET MANAGEMENT CHIEF FINANCIAL OFFICER 1. REASON FOR REPORT 1.1 To provide the Audit and Performance Review

More information

BRENT COUNCIL IT STRATEGY 2010-13

BRENT COUNCIL IT STRATEGY 2010-13 BRENT COUNCIL IT STRATEGY 2010-13 Contents 1 Introduction... 2 2 Empowering our customers... 3 2.1 Client Index... 3 2.2 Customer contact... 3 3 Tools for the Job... 4 3.1 Printing and scanning... 4 3.2

More information

Customers and Corporate Services Directorate (Corporate Support) Plan 2015-16

Customers and Corporate Services Directorate (Corporate Support) Plan 2015-16 Appendix 2 Action Plan Due Date Status Customers and Corporate Services Directorate (Corporate Support) Plan 2015-16 CS1027 ICT Improvement Programme 31 January 2016 Objectives: CORPORATE SERVICES: ICT

More information

Bedfordshire Fire and Rescue Authority Corporate Services Policy and Challenge Group 9 September 2014 Item No. 6

Bedfordshire Fire and Rescue Authority Corporate Services Policy and Challenge Group 9 September 2014 Item No. 6 For Publication Bedfordshire Fire Rescue Authority Corporate Services Policy Challenge Group 9 September 2014 Item No. 6 REPORT AUTHOR: SUBJECT: ASSISTANT CHIEF OFFICER (HUMAN RESOURCES AND ORGANISATIONAL

More information

Performance Detailed Report. May 2008. Review of Performance Management. Norwich City Council. Audit 2007/08

Performance Detailed Report. May 2008. Review of Performance Management. Norwich City Council. Audit 2007/08 Performance Detailed Report May 2008 Review of Performance Management Audit 2007/08 External audit is an essential element in the process of accountability for public money and makes an important contribution

More information

FUNDING APPROVAL FOR IMPLEMENTATION OF CLOUD-BASED PRODUCTIVITY AND COLLABORATION TOOLS (OFFICE 365)

FUNDING APPROVAL FOR IMPLEMENTATION OF CLOUD-BASED PRODUCTIVITY AND COLLABORATION TOOLS (OFFICE 365) London Borough of Hammersmith & Fulham CABINET 2 NOVEMBER 2015 FUNDING APPROVAL FOR IMPLEMENTATION OF CLOUD-BASED PRODUCTIVITY AND COLLABORATION TOOLS (OFFICE 365) Report of the Leader - Councillor Stephen

More information

ARGYLL AND BUTE COUNCIL SUPPORT SERVICES REVIEW HR & PAYROLL EXECUTIVE SUMMARY- 2 NOVEMBER 2011

ARGYLL AND BUTE COUNCIL SUPPORT SERVICES REVIEW HR & PAYROLL EXECUTIVE SUMMARY- 2 NOVEMBER 2011 ARGYLL AND BUTE COUNCIL SUPPORT SERVICES REVIEW HR & PAYROLL EXECUTIVE SUMMARY- 2 NOVEMBER 2011 1 Introduction 1.1 The Heads of Customer & Support Services, Improvement & HR and the workstream leads for

More information

ISEB MANAGER S CERTIFICATE IN ITIL INFRASTRUCTURE MANAGEMENT. Guidelines for candidates who are taking the ICT Infrastructure Examination

ISEB MANAGER S CERTIFICATE IN ITIL INFRASTRUCTURE MANAGEMENT. Guidelines for candidates who are taking the ICT Infrastructure Examination ISEB MANAGER S CERTIFICATE IN ITIL INFRASTRUCTURE MANAGEMENT Guidelines for candidates who are taking the ICT Infrastructure Examination This qualification is based on ITIL Infrastructure Management as

More information

Portal Annual Report 2012/13

Portal Annual Report 2012/13 Portal Annual Report 2012/13 Introduction This report is provided for a diverse audience and covers the year 1st September 2012 31st August 2013, the seventh year of operation of the Portal. The Portal

More information

Information Services Strategy 2011-2013

Information Services Strategy 2011-2013 Information Services Strategy Issue 1 1 Introduction The States of Jersey public sector is facing significant pressure for efficiencies and savings. This has created the context to take a fresh look at

More information

Item No. 15.2.2 Capital Project Appraisal & Procurement Report. Target Completion Date November 2008

Item No. 15.2.2 Capital Project Appraisal & Procurement Report. Target Completion Date November 2008 Item No. 15.2.2 Capital Project Appraisal & Procurement Report Project Title Supply, installation, maintenance, support and upgrade of car park Pay on Foot and Associated Control Equipment (Phased approach)

More information

Angus Council Corporate IT Strategy November 2012

Angus Council Corporate IT Strategy November 2012 Angus Council Corporate IT Strategy November 2012 Contributors: Neil Munro Hugh Robertson Craig Clement Alastair Wilson John Pearson Stewart Ball Les Hutchinson Gordon Fenton Steve Roud Corporate Services

More information

Attachment 1. Bath & North East Somerset Council. Information Management & Technology Strategy 2008

Attachment 1. Bath & North East Somerset Council. Information Management & Technology Strategy 2008 Attachment 1 Bath & North East Somerset Council Information Management & Technology Strategy 2008 Contents 1 Purpose...2 2 Aim...2 3 Our Vision...2 4 Benefits...2 5 Scope...3 6 Key Stakeholder Engagement...3

More information

Investors in People 2013 - Communications Plan. Introduction What is IiP?

Investors in People 2013 - Communications Plan. Introduction What is IiP? Investors in People 2013 - Communications Plan Introduction What is IiP? Investors in People specialises in transforming business performance through our employees. It is designed to help the Council achieve

More information

SUBJECT: DESIGNING BETTER SERVICES PROGRAMME PHASE 3 (IMPLEMENTATION): PROGRAMME PROGRESS UP-DATE CORPORATE DIRECTOR (CORPORATE SERVICES)

SUBJECT: DESIGNING BETTER SERVICES PROGRAMME PHASE 3 (IMPLEMENTATION): PROGRAMME PROGRESS UP-DATE CORPORATE DIRECTOR (CORPORATE SERVICES) PAGE: 1 REPORT TO: POLICY AND RESOURCES COMMITTEE ON 8 th OCTOBER 2013 SUBJECT: DESIGNING BETTER SERVICES PROGRAMME PHASE 3 (IMPLEMENTATION): PROGRAMME PROGRESS UP-DATE BY: CORPORATE DIRECTOR (CORPORATE

More information

Payroll Services and the Advantages of a Shared Service

Payroll Services and the Advantages of a Shared Service Cambridge City Council Item To: Report by: Relevant scrutiny committee: Wards affected: Executive Councillor for Customer Services and Resources: Councillor Julie Smith Director of Resources Strategy &

More information

Bedfordshire Fire and Rescue Authority Corporate Services Policy and Challenge Group 16 September 2015 Item No. 11

Bedfordshire Fire and Rescue Authority Corporate Services Policy and Challenge Group 16 September 2015 Item No. 11 For Publication REPORT AUTHOR(S): Bedfordshire Fire and Rescue Authority Corporate Services Policy and Challenge Group 16 September 2015 Item No. 11 ASSISTANT CHIEF OFFICER (HUMAN RESOURCES AND ORGANISATIONAL

More information

Connect Renfrewshire

Connect Renfrewshire How the council will use its information and technology assets to achieve successful change Contents Strategy Context 2 Digital Delivery and Citizen Engagement 4 Operational Excellence and Transformation

More information

University of Strathclyde: Information Services Directorate Operational Plan for 2014/15

University of Strathclyde: Information Services Directorate Operational Plan for 2014/15 University of Strathclyde: Information Services Directorate Operational Plan for 2014/15 Enabling the future: transforming our information systems and technology 2014/15 2014/2015 CONTENTS 1 DRIVERS, STRATEGIC

More information

Project title (in Chinese) 項 目

Project title (in Chinese) 項 目 II Project Information Project title (in English) Project title (in Chinese) HKCAAVQ IT Infrastructure Development 香 港 學 術 及 職 業 資 歷 評 審 局 資 訊 系 統 基 建 發 展 Project 項 目 Project summary (Please provide an

More information

Full Business Case: Collaboration Software. Document Information

Full Business Case: Collaboration Software. Document Information Full Business Case: Collaboration Software Document Information This Business Case provides justification for the business change in terms of its strategic fit, value for money, affordability and achievability.

More information

Central Hosting. Case Study

Central Hosting. Case Study Central Hosting Case Study October, 2014 Central Hosting Case Study Background An Chéim was originally set up to procure, distribute and implement key MIS systems (hardware and software) for the Institutes

More information

STL Microsoft Dynamics CRM Consulting and Support Services

STL Microsoft Dynamics CRM Consulting and Support Services STL Microsoft Dynamics CRM Consulting and Support Services STL Technologies Equis House Eastern Way Bury St Edmunds Suffolk IP32 7AB Service Description and Pricing Specialist Cloud Services www.stl.co.uk

More information

CABINET 9 th February 2006. Report of the Director of Partnerships and Customer Services

CABINET 9 th February 2006. Report of the Director of Partnerships and Customer Services CABINET 9 th February 2006 Report of the Director of Partnerships and Customer Services ITEM 11 CRM DEVELOPMENT Purpose of the Report To seek approval to the replacement for the Council s Customer Relationship

More information

IT Strategy 2013 2017

IT Strategy 2013 2017 IT Strategy 2013 2017 V3.2 August 2013 Contents Part I Context Drivers Workplace Strategy Benefits of the Strategy Contents Part II Business Strategy Strategic Themes: Strong Line of Business Applications

More information

SCRUTINY PANEL. 12 February 2015 REVIEW OF ICT SERVICES. Report of the Director of Resources

SCRUTINY PANEL. 12 February 2015 REVIEW OF ICT SERVICES. Report of the Director of Resources REPORT NO: 49/2015 SCRUTINY PANEL 12 February 2015 REVIEW OF ICT SERVICES Report of the Director of Resources STRATEGIC AIM: All 1. PURPOSE OF THE REPORT 1.1 To update the panel on the plan for the review

More information

2.0 RECOMMENDATIONS Members of the Committee are asked to note the information contained within this report.

2.0 RECOMMENDATIONS Members of the Committee are asked to note the information contained within this report. REPORT TO: SCRUTINY COMMITTEE 25 JUNE 2013 REPORT ON: REPORT BY: INTERNAL AUDIT REPORTS CHIEF INTERNAL AUDITOR REPORT NO: 280-2013 1.0 PURPOSE OF REPORT To submit to Members of the Scrutiny Committee a

More information

AGENDA ITEM NO. 6.b CUSTOMER SERVICES REVIEW CONSIDERATION OF DRAFT IMPROVEMENT PLAN

AGENDA ITEM NO. 6.b CUSTOMER SERVICES REVIEW CONSIDERATION OF DRAFT IMPROVEMENT PLAN AGENDA ITEM NO. 6.b CUSTOMER SERVICES REVIEW CONSIDERATION OF DRAFT IMPROVEMENT PLAN Committee: Personnel Corporate Committee Date: 7 February 2013 Author: Annette Wade,, Councillor Sue Willows Andrew

More information

PUBLIC MINUTES. of the HCA Audit & Risk Committee meeting held at 1.30pm on Wednesday 11 June 2014 at Maple House, 149 Tottenham Court Rd, London

PUBLIC MINUTES. of the HCA Audit & Risk Committee meeting held at 1.30pm on Wednesday 11 June 2014 at Maple House, 149 Tottenham Court Rd, London PUBLIC MINUTES of the HCA Audit & Risk Committee meeting held at 1.30pm on Wednesday 11 June 2014 at Maple House, 149 Tottenham Court Rd, London Present: Ian Robertson Richard Hyde Inge Kettner Robert

More information

JOB DESCRIPTION. Financial Services and Support. Lead Service Desk Analyst

JOB DESCRIPTION. Financial Services and Support. Lead Service Desk Analyst a JOB DESCRIPTION Job Title: Division: Department/Region/Section: Location: Reports to: Responsible for: Grade: Service Desk Analyst Financial Services and Support Information Systems & Support HQ, Southwater

More information

THE NEWCASTLE UPON TYNE HOSPITALS NHS FOUNDATION TRUST COUNCIL OF GOVERNORS REAL-TIME PATIENT FEEDBACK

THE NEWCASTLE UPON TYNE HOSPITALS NHS FOUNDATION TRUST COUNCIL OF GOVERNORS REAL-TIME PATIENT FEEDBACK THE NEWCASTLE UPON TYNE HOSPITALS NHS FOUNDATION TRUST COUNCIL OF GOVERNORS Agenda item 4(vi) Paper D REAL-TIME PATIENT FEEDBACK Report Purpose: Decision / Approval Discussion Information Brief description

More information

Web & Customer Access Strategy

Web & Customer Access Strategy Page 1 of 14 DACORUM BOROUGH COUNCIL Web & Customer Access Strategy AUTHOR RESPONSIBLE OFFICER Katie Warner, Customer Insight Officer Murtaza Maqbool, Web Development Officer David Gill, Group Manager

More information

Executive has authority to determine the above recommendation.

Executive has authority to determine the above recommendation. REPORT OF: HEAD OF CORPORATE DEVELOPMENT AUTHOR: FIONA CULLEN TELEPHONE: 01737 276296 C E-MAIL: TO: fiona.cullen@reigate-banstead.gov.uk EXECUTIVE DATE: 13 JULY 2006 EXECUTIVE MEMBER: COUNCILLOR J.M. ELLACOTT

More information

Performance Detailed Report. Date. Last saved: 12/10/2007 13:18:00. Property asset management. Bristol City Council. Audit 2006/07

Performance Detailed Report. Date. Last saved: 12/10/2007 13:18:00. Property asset management. Bristol City Council. Audit 2006/07 Performance Detailed Report Date Last saved: 12/10/2007 13:18:00 Property asset management Audit 2006/07 - Audit Commission descriptor to be inserted by Publishing- Document Control Author Filename Bob

More information

Appendix D Programme Stream 6 CRM Procurement. Programme Stream 6 Remodelling of Customer Services Programme CRM Procurement

Appendix D Programme Stream 6 CRM Procurement. Programme Stream 6 Remodelling of Customer Services Programme CRM Procurement Programme Stream 6 Remodelling of Customer Services Programme CRM Procurement Recommendations That the Executive note CRM procurement will be put out to tender in 2010/11 and note the proposed phasing

More information

Informatics Strategy June 2012

Informatics Strategy June 2012 June 2012 Version 5.2 Author: Chris Cook, Interim Chief Informatics Officer 1. Document Purpose This document outlines the Bolton NHS Foundation Trust Informatics Strategy which has been approved in principle

More information

Health Informatics Service Accreditation Manual. Assessment Process. May 2013, Version 1

Health Informatics Service Accreditation Manual. Assessment Process. May 2013, Version 1 Health Informatics Service Accreditation Manual Assessment Process May 2013, Version 1 Contents 1. Contacts... 2 2. Introduction... 3 3. Assessment principles... 6 4. Assessment outcome... 7 5. Planning

More information

To: FINANCE COMMITTEE Subject: BEST VALUE SERVICE REVIEW (I.T. Services - Desktop Support)

To: FINANCE COMMITTEE Subject: BEST VALUE SERVICE REVIEW (I.T. Services - Desktop Support) REPORT To: FINANCE COMMITTEE Subject: BEST VALUE SERVICE REVIEW (I.T. Services - Desktop Support) From: DIRECTOR OF FINANCE I Date: 9~Nov2000 I Ref:MG/RMcB 1. Background The Desktop Support section is

More information

Managing ICT contracts in central government. An update

Managing ICT contracts in central government. An update Managing ICT contracts in central government An update Prepared by Audit Scotland June 2015 Auditor General for Scotland The Auditor General s role is to: appoint auditors to Scotland s central government

More information

STL Microsoft SharePoint Consulting and Support Services

STL Microsoft SharePoint Consulting and Support Services STL Microsoft SharePoint Consulting and Support Services STL Technologies Equis House Eastern Way Bury St Edmunds Suffolk IP32 7AB Service Description and Pricing Specialist Cloud Services www.stl.co.uk

More information

Cabinet Member for Corporate Relations

Cabinet Member for Corporate Relations Cabinet Member for Corporate Relations Proposal for new customer experience October 2015 Report by the Executive Director Residents Services and the Director of Customer Services Ref No: CR05(15/16) Key

More information

Role Profile. Job No. (Office Use) A79

Role Profile. Job No. (Office Use) A79 Role Profile Job Title Team Leader Service Desk Job No. (Office Use) A79 Band/Band Range- (for career grades) Grade I Directorate Corporate Support Department ICT Division Operational Service Delivery

More information

Digital Britain One: Shared infrastructure and services for government online

Digital Britain One: Shared infrastructure and services for government online REPORT BY THE COMPTROLLER AND AUDITOR GENERAL HC 1589 SESSION 2010 2012 9 DECEMBER 2011 Cross government Digital Britain One: Shared infrastructure and services for government online 4 Key facts Digital

More information

Charnwood Borough Council. Corporate Performance Management Framework

Charnwood Borough Council. Corporate Performance Management Framework Charnwood Borough Council Corporate Performance Management Framework Contents 1 Introduction... 1 2 Background... 1 3 Role of the Performance Team... 2 4 Charnwood Framework... 2 4.1 Corporate Plan...2

More information

Page 97. Executive Head of Asset Planning, Management and Capital Delivery

Page 97. Executive Head of Asset Planning, Management and Capital Delivery Page 97 Agenda Item 7 Report to: Strategy and Resources Committee Date: 16 December 2013 Report of: Executive Head of Asset Planning, Management and Capital Delivery Ward Location: Not applicable Author

More information

North Middlesex University Hospital NHS Trust. Annual Audit Letter 2005/06. Report to the Directors of the Board

North Middlesex University Hospital NHS Trust. Annual Audit Letter 2005/06. Report to the Directors of the Board North Middlesex University Hospital NHS Trust Annual Audit Letter 2005/06 Report to the Directors of the Board 1 Introduction The Purpose of this Letter 1.1 The purpose of this Annual Audit Letter (letter)

More information

Tri-Borough Cabinet Member Decision Report

Tri-Borough Cabinet Member Decision Report Tri-Borough Cabinet Member Decision Report Decision maker(s) at each authority and date of Cabinet meeting, Cabinet Member meeting or (in the case of individual Cabinet Member decisions) the earliest date

More information

Information Management Strategy. July 2012

Information Management Strategy. July 2012 Information Management Strategy July 2012 Contents Executive summary 6 Introduction 9 Corporate context 10 Objective one: An appropriate IM structure 11 Objective two: An effective policy framework 13

More information

INFORMATION TECHNOLOGY & MEDIA SERVICES

INFORMATION TECHNOLOGY & MEDIA SERVICES INFORMATION TECHNOLOGY & MEDIA SERVICES Head of IT Operations Permanent, Full-time Grade SENIOR STAFF: Salary to be determined by the Vice Chancellor De Montfort University is home to more than 27,000

More information

Services shared: costs spared?

Services shared: costs spared? Improvement Services shared: costs spared? An analysis of the financial and non-financial benefits of local authority shared services Appendix 4: Review of Hoople Ltd, a shared services arrangement between

More information

Mike Hill, Cabinet Member, Community Services Amanda Honey, Corporate Director Customer & Communities

Mike Hill, Cabinet Member, Community Services Amanda Honey, Corporate Director Customer & Communities From: To: Mike Hill, Cabinet Member, Community Services Amanda Honey, Corporate Director Customer & Communities Communities Cabinet Committee Date: 17 December 2013 Decision No: 13/00086 Subject: Procurement

More information

ITlL SERVICE DESK IMPLEMENTATION

ITlL SERVICE DESK IMPLEMENTATION Report Asset Management Committee 31 January 2006 14 ITlL SERVICE DESK IMPLEMENTATION 1. Reason for Report To seek Member's approval for the procurement and implementation of the Infra Service Desk software

More information

Delivering progress towards meeting HMG targets on the SME growth agenda

Delivering progress towards meeting HMG targets on the SME growth agenda Delivering progress towards meeting HMG targets on the SME growth agenda Action Plan Version 1.1 dated 16 th August 2013 Author: Robert Astall, Head of Commercial Profession and Capability Background The

More information

Glasgow City Council. Assurance and Improvement Plan Update 2013 16

Glasgow City Council. Assurance and Improvement Plan Update 2013 16 Glasgow City Council Assurance and Improvement Plan Update 2013 16 April 2013 Introduction Contents Introduction... 3 Summary... 4 National risk... 5 Areas that remain no scrutiny... 8 Areas that remain

More information

Human Resources and Training update

Human Resources and Training update 4 November 2014 Performance and Resources Board 11 To consider Human Resources and Training update Issue 1 This report provides an update on policy developments relating to Human Resources and Training.

More information

MANAGEMENT INFORMATION SERVICES

MANAGEMENT INFORMATION SERVICES MANAGEMENT INFORMATION SERVICES Version 3.1 May 2011 Strategic Objectives 2011-2015 1 Introduction to Management Information Services Division (MISD) MISD is a Division of the Unified Administrative Service

More information

CORPORATE IT STRATEGY 2008-2013

CORPORATE IT STRATEGY 2008-2013 CORPORATE IT STRATEGY 2008-2013 IT Review July 2008 (17 September 2008) 1 17 September 2008 Index Paragraph 1. Purpose and Scope 1.1 1.3 2. Organisational Context 2.1 2.7 3. Where are we now? 3.1 3.31

More information

DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA REVIEW OF THE IT STRATEGY AND IMPLEMENTATION CONTROL FRAMEWORK

DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA REVIEW OF THE IT STRATEGY AND IMPLEMENTATION CONTROL FRAMEWORK Appendix 1b DIRECTORATE OF AUDIT, RISK AND ASSURANCE Internal Audit Service to the GLA REVIEW OF THE IT STRATEGY AND IMPLEMENTATION CONTROL FRAMEWORK DISTRIBUTION LIST Audit Team Steve Hutton, Head of

More information

ICT Strategy 2012-13 summary

ICT Strategy 2012-13 summary Item 7 GCP(12)30 ICT Strategy 2012-13 summary For Board approval For Board discussion For Board information Prepared by: Alistair Quigley Programme director Support Services Date: 17 May 2012 Executive

More information

SUBJECT: Talent Management Strategy 2016 2020. Councillor Sandra Walmsley (Cabinet Member for Resources and Regulation)

SUBJECT: Talent Management Strategy 2016 2020. Councillor Sandra Walmsley (Cabinet Member for Resources and Regulation) REPORT FOR DECISION DECISION OF: CABINET DATE: 13 APRIL 2016 SUBJECT: Talent Management Strategy 2016 2020 REPORT FROM: Councillor Sandra Walmsley (Cabinet Member for Resources and Regulation) CONTACT

More information

First National Data Quality Review: Executive Summary Quality Information Committee

First National Data Quality Review: Executive Summary Quality Information Committee First National Data Quality Review: Executive Summary Quality Information Committee Executive Summary Introduction to the report This report has been produced by the Quality Information Committee (QIC)

More information

POSITION INFORMATION DOCUMENT

POSITION INFORMATION DOCUMENT POSITION INFORMATION DOCUMENT Position Title: ICT Service Desk Manager Classification Code: AS07 Division: ICT Services Directorate: ICT Customer Services Type of Appointment: Branch: ICT Central Ongoing

More information

HUNTINGDONSHIRE DISTRICT COUNCIL. Internal Audit Service: Annual Report. Meeting/Date: Corporate Governance Panel 15 July 2015

HUNTINGDONSHIRE DISTRICT COUNCIL. Internal Audit Service: Annual Report. Meeting/Date: Corporate Governance Panel 15 July 2015 Public Key Decision - No HUNTINGDONSHIRE DISTRICT COUNCIL Title: Internal Audit Service: Annual Report Meeting/Date: Corporate Governance Panel 15 July 2015 Executive Portfolio: Report by: Ward(s) affected:

More information

INFORMATION COMMUNICATION TECHNOLOGY PLAN

INFORMATION COMMUNICATION TECHNOLOGY PLAN Part 3 ICT Pages 59-64 5/7/03 8:36 AM Page 59 59 PART THREE INFORMATION COMMUNICATION TECHNOLOGY PLAN INTRODUCTION There is an urgent need for the Department of Foreign Affairs to transform its current

More information

Customer Service Software System Business Case Lead Officer:

Customer Service Software System Business Case Lead Officer: Agenda item: 17 Committee: CABINET Date of meeting: 21 November 2012 Subject: Customer Service Software System Business Case Lead Officer: Head of ICT Portfolio Holder: Resources - Councillor T Oliver

More information

Case Study ISO/IEC 20000 Adds Value for Local Government

Case Study ISO/IEC 20000 Adds Value for Local Government Case Study ISO/IEC 20000 Adds Value for Local Government Tamworth Borough Council s ICT team has built up an enviable track record over the last few years, using Sostenuto to help boost the department

More information

ICT Strategy for the Secretariat

ICT Strategy for the Secretariat ICT Strategy for the Secretariat Stronger ICT for a Better United Nations Briefing for the UN Reform Series organized jointly by UNITAR and the Permanent Mission of Switzerland to the United Nations 4

More information

Audit Scotland Annual Report on Disability Equality A progress report for Dec 2007 to Nov 2008

Audit Scotland Annual Report on Disability Equality A progress report for Dec 2007 to Nov 2008 Audit Scotland Annual Report on Disability Equality A progress report for Dec 2007 to Nov 2008 Page 1 of 13 Introduction Background 1. Audit Scotland provides services to the Auditor General and the Accounts

More information

The Human Resources Department Work Plan for the period 1 April 2015 to 31 March 2016 is attached.

The Human Resources Department Work Plan for the period 1 April 2015 to 31 March 2016 is attached. Council, 25 March 2015 Human Resources Department Work Plan 2015-2016 Executive summary and recommendations Introduction The Human Resources Department Work Plan for the period 1 April 2015 to 31 March

More information

DRAFT Version 1.0 Proposal to Implement the Information Technology Infrastructure Library Framework for IT Service Management

DRAFT Version 1.0 Proposal to Implement the Information Technology Infrastructure Library Framework for IT Service Management Proposal to Implement the Information Technology Infrastructure Library Framework for IT Service Management Prepared for the ITM By Hamish Duff in consultation with the ITIL Implementation Working Party

More information

Project Appraisal and Scrutiny Committee Recommendation STRATEGY & RESOURCES 23 MARCH 2015

Project Appraisal and Scrutiny Committee Recommendation STRATEGY & RESOURCES 23 MARCH 2015 Cambridge City Council Project Appraisal and Scrutiny Committee Recommendation Project Name: Telecommunications To: Report by: Scrutiny committee: Wards affected: Recommendation/s Executive Councillor

More information

Children s Services Improvement and Business Support. Service Review 2013/14

Children s Services Improvement and Business Support. Service Review 2013/14 Children s Services Improvement and Business Support Service Review 2013/14 Service Name: Children s Services Improvement and Business Support Service Contact: Richard Williams Date of review: 2013/14

More information

REVIEW OF CORPORATE SERVICES HR BUSINESS CASE

REVIEW OF CORPORATE SERVICES HR BUSINESS CASE REVIEW OF CORPORATE SERVICES HR BUSINESS CASE 1. The Strategic Case for Integration The alignment with Council strategies 1.1 The Lewes Change Management Programme (CMP) outlines the need to redesign the

More information

REPORT TO: AUDIT AND PERFORMANCE REVIEW COMMITTEE 14 MAY 2014 CORPORATE DIRECTOR (CORPORATE SERVICES)

REPORT TO: AUDIT AND PERFORMANCE REVIEW COMMITTEE 14 MAY 2014 CORPORATE DIRECTOR (CORPORATE SERVICES) PAGE: 1 REPORT TO: AUDIT AND PERFORMANCE REVIEW COMMITTEE 14 MAY 2014 SUBJECT: BY: EMPLOYEE ENGAGEMENT UPDATE REPORT CORPORATE DIRECTOR (CORPORATE SERVICES) 1. REASON FOR REPORT 1.1 The Committee is invited

More information

EXE 210206 ITEM 11 REMOTE WORKING EXECUTIVE MEMBER: LEAD OFFICER: REPORT AUTHOR: Cllr Williams Hilary Mitchell Hilary Mitchell.

EXE 210206 ITEM 11 REMOTE WORKING EXECUTIVE MEMBER: LEAD OFFICER: REPORT AUTHOR: Cllr Williams Hilary Mitchell Hilary Mitchell. REMOTE WORKING EXE 210206 ITEM 11 EXECUTIVE MEMBER: LEAD OFFICER: REPORT AUTHOR: Summary: Recommendation: Impact on delivering Corporate Plan objectives: Cllr Williams Hilary Mitchell Hilary Mitchell To

More information

A Framework of Quality Assurance for Responsible Officers and Revalidation

A Framework of Quality Assurance for Responsible Officers and Revalidation A Framework of Quality Assurance for Responsible Officers and Revalidation Supporting responsible officers and designated bodies in providing assurance that they are discharging their statutory responsibilities.

More information

Aberdeen City Council IT Asset Management

Aberdeen City Council IT Asset Management Aberdeen City Council IT Asset Management Internal Audit Report 2014/2015 for Aberdeen City Council January 2015 Terms or reference agreed 4 weeks prior to fieldwork Target Dates per agreed Actual Dates

More information

Service Delivery Plan 2007/8 Template 1. Delivery plan

Service Delivery Plan 2007/8 Template 1. Delivery plan Delivery plan Theme Leisure & Environment Clean and safe streets and public places with the Council maintaining and enforcing high standards of cleanliness throughout the borough. 1. Deliver a proactive

More information