Internal Audit Report. Receivables Management Statement of Cost TxDOT Office of Internal Audit

Size: px
Start display at page:

Download "Internal Audit Report. Receivables Management Statement of Cost TxDOT Office of Internal Audit"

Transcription

1 Internal Audit Report Receivables Management Statement of Cost TxDOT Office of Internal Audit

2 Objective The audit objective is to evaluate whether monitoring and accounting for outstanding construction and right of way receivables is occurring and adequate. Opinion Based on the audit scope areas reviewed, control mechanisms are unreliable in addressing risk factors and exposures considered significant relative to impacting reporting reliability, operational execution, and compliance. The organization's system of internal controls does not provide reasonable assurance that key goals and objectives will be achieved. Control gap corrections are pervasive and resulting in material negative impacts to the organization. Progress can be made within 2 quarters in addressing the highest risk areas. Management concurs with the above findings and prepared management action plans to address deficiencies. Internal Environment In the early 1990 s, local governments began contributing funds to TxDOT projects in order to have additional work completed for the benefit of the local government. Over the years, this became more popular and complex when more than one local entity became involved and the participation had a ceiling. The Financial Information Management System (FIMS) used by Finance Division (FIN) was not designed to accurately track some of these complex projects. FIN produces a monthly report through data obtained from FIMS showing amounts owed to TxDOT by third party entities, such as cities, counties and similar local governments. This FIMS report is intended to be used by the districts and Right of Way Division (ROW) to collect funds from the third parties. TxDOT policy mandates that the districts are responsible to collect the monies owed as they accrue; however, they do not all reconcile to the FIMS balance until the project is complete. April 2,

3 Summary Results Finding Scope Area Evidence 1 Interim Monitoring of Project Costs & Receivables/Collection Project Close Final Project Collection of Outstanding Receivables (Demand Process) Completed Construction/ROW Projects: Sixteen completed projects were reviewed (13 construction/3 ROW), and the following was noted in relation to close or collection activities: 9 of 16 (56%) completed projects did not execute the demand letter process as required by the Texas Administrative Code 9 of 13 (69%) completed construction projects did not have the final Statement of Cost (SOC) completed within the allotted 90-day timeframe 2 Interim Monitoring of Project Costs & Receivables/Collection Project Close Active and Completed Construction/ROW Projects: Forty active and completed construction and ROW projects were reviewed (24 active/16 completed). The following were noted in relation to misstated balances: 12 of 40 (30%) project receivables totalling $9,912,327 of the total $28,051,307 (35%) reviewed had financial errors (i.e., federal money not applied or fixed sum participation required manual process to reduce charges over their maximum) and/or charges that were incorrectly coded against the project Utility Adjustments: 4 of 18 (22%) ROW receivables for utility adjustments included in the construction phase did not have supporting documentation Audit Scope The scope of this audit was based on contracts and related receivables as reported in the January 2, 2013, Statewide Receivables Report posted on the FIN website. The total amount due at this time was $53,272,987. The audit was performed by Omar Elsaad, Romy Grimmell, Sabra Vaughan, and Jill Emery, Engagement Lead. The audit was conducted during the period from January 14, 2013 to November 22, April 2,

4 Methodology The methodology used included testing a sample of projects with receivable balances over $100,000 in the Houston, Dallas, Austin, San Antonio, Lufkin, Atlanta, Laredo, and El Paso Districts, as well as, the Right of Way (ROW) Division. Information collected and reviewed to complete the objectives of this audit included: applicable federal/state laws and regulations, department policies/procedures, and manuals prior audit reports to include reports from State Auditor s Office and TxDOT Audit Office internal documents including o Statewide Receivables Reports o Advance Funding Agreements (AFAs), proposals, budgets and plans o documentation associated with expense reviews against FIMS o documentation associated with the collection of funds o various FIMS reports reflecting participation and payment Procedures and testing performed included: interviews of key TxDOT personnel evaluation of control design and operating effectiveness for the receivables collection process Fieldwork testing included a sample of 40 receivables from the January 2, 2013 Statewide Receivables Report listing. These 40 receivables represent $28,051,307 of $53,272,987 (53%) total outstanding receivables per the report. 9 receivables for active construction projects = $8,954,664 (32%) of the sample 13 receivables for completed construction projects = $6,754,131 (24%) of the sample 15 receivables for active ROW projects = $11,869,313 (42%) of the sample 3 receivables for completed ROW projects = $473,200 (2%) of the sample Background This report is prepared for the Texas Transportation Commission, TxDOT Administration and Management. The report presents the results of the Receivables Statement of Cost Audit which was conducted as part of the Fiscal Year 2013 Audit Plan. FIN publishes a monthly Statewide Receivables Report that shows the FIMS balance to be collected by District for active/completed construction projects and ROW projects. This report helps the districts to verify the balances and open communication with the local governments to collect the funds. ROW maintains third party contracts for land acquisition separate from the construction project and uses Right of Way Information System (ROWIS) to track balances owed. Utility adjustment costs are part of ROW and may show on the Statewide Receivables Report April 2,

5 before ROW receives notification from the district to support the charges; therefore, ROW uses the report to reconcile their records with FIMS. We conducted this performance audit in accordance with Generally Accepted Government Auditing Standards and in conformance with the International Standards for the Professional Practice of Internal Auditing. Those standards require that we plan and perform the audit to obtain sufficient, appropriate evidence to provide a reasonable basis for our findings and conclusions based on our audit objectives. Recommendations to mitigate risks identified were provided to management during the engagement to assist in the formulation of the management action plans included in this report. We believe that the evidence obtained provides a reasonable basis for our findings and conclusions based on our audit objectives. The Office of Internal Audit transitioned to Committee of Sponsoring Organizations of the Treadway Commission (COSO) Internal Control Integrated Framework version 2013 in December A defined set of control objectives was utilized to focus on financial, operational and regulatory goals for the identified scope areas. Our audit opinion is an assessment of the health of the overall control environment based on (1) the effectiveness of the enterprise risk management activities throughout the audit period and (2) the degree to which the defined control objectives were being met. Our audit opinion is not a guarantee against reporting misstatement and reliability, operational sub-optimization, or non-compliance, particularly in areas not included in the scope of this audit. April 2,

6 Detailed Findings and Management Action Plans (MAP) Finding No. 1: Project Close and Collection Process Condition Texas Administrative Code (TAC) rules and TxDOT policy for collecting third party receivables are not being followed by Districts or Right Of Way (ROW) staff. Districts are not submitting the final Statement of Cost (SOC) within days after the construction projects final estimates, as required. Additionally, districts are not timely in sending the First Notice Letter explaining the obligation to the third party and when the payment is due, which would commence the collection. Effect/Potential Impact untimely resolution of aging receivables non-compliance with TAC, department policy, agreement terms higher risk of losing supporting documentation as receivables age Criteria & Cause The Financial Management Policy Manual states in Chapter 4, Section 13, Certified SOCs shall be submitted to FIN no earlier than 60 days and no later than 90 days after the final payment to the contractor; FIN will review the SOC for completeness and accuracy. Once all discrepancies have been addressed, FIN will send a Concurrence Memo to the District. District will send a request for additional funds to the Local within 2 weeks of the date of the concurrence memo. If payment is not received by the due date, districts shall follow 43 TAC 5.10 Collection of Debts. Title 43, Texas Administrative Code, Subchapter B, 5.10 Collection of Debts states: (1) The division or district sends the debtor written notice of the obligation. (2) If not paid by the due date, the district or division sends a first demand letter within 30 days. (3) If not paid, the division or district sends a final demand letter. The final demand letter may include a statement that the obligation, if not paid, will be referred to the attorney general. (4) The department can refer a delinquent obligation to the attorney general for further collection efforts or utilize the "warrant hold" procedures of the Comptroller of Public Accounts authorized by Government Code, , to ensure that no treasury warrants are issued to debtors until the debt is paid. The Records Management Manual states, The record copy is the official record that must be retained to fulfil statutory retention requirements it originates or is retained at the office responsible for the operations or function the record or file concerns. The State of Texas Record Retention Schedule states that contract records, including all related documents, must be kept for four years after completion of the contract with the note: AFAs are not considered complete until the structure is removed, replaced or an original agreement is superseded by another agreement. April 2,

7 Causes for delay in finalizing SOCs include: training needed for FIN and District staff (i.e., DEV505 FIMS Third Party Funding which teaches how to generate FIMS reports and determine the status of a project's funding) staff turnover at FIN and District levels project under FIN review for concurrence of final SOC transmitted from the District Causes for not pursuing collection include: third party entities dispute the amount and collection put on hold until resolved changes that will impact the receivable balance may not exist on older receivables (i.e., change orders, other financial impacts to the project) FIMS is not programmed to detect when a maximum limit is reached and manual processes are needed to adjust amounts due staff turnover at FIN and District levels Evidence Documents were reviewed in each sampled completed project to determine whether TxDOT policy and/or TAC 5.10 was followed in collection of third party debt. Completed Construction/ROW Projects: Sixteen completed projects were reviewed (13 construction/3 ROW): 16 of 40 (40%) receivables reviewed were for completed projects totalling $7,227,330 of the total $28,051,307 (26%) 9 of 16 (56%) completed construction and ROW projects did not execute the demand letter process as required by the Texas Administrative Code 9 of 13 (69%) completed construction projects did not have the final SOC completed within the allotted 90-day timeframe 1 district did not have documentation of FIN s concurrence with the SOC Management Action Plan (MAP): MAP Owners: Brian Ragland, Director, Finance Division Bill Hale, P.E., Dallas District Engineer Michael W. Alford, P.E., Houston District Engineer Catherine Hejl, P.E., Bryan District Engineer Randy Hopmann, P.E., Tyler District Engineer John Campbell, Director, Right-of-Way Division MAP 1.1: Assess and work with necessary teams at TxDOT to implement a Fixed Participation policy with Local Government (LG) entities on future construction and ROW projects/contracts. Work with Contract Services to assess and implement a Fixed Participation policy with future LG projects/contracts in the Advanced Funding Agreement stage. Discuss April 2,

8 with LGs or other entities, as necessary, the impacts of these changes to collection activities. Finance Division personnel and respective Districts with outstanding receivables to assess, reconcile, and concur on final balances owed on Completed Construction by LG/other entities by project. A root cause assessment should be conducted and documented to understand where lapses existed in collection or between FIMS and Site Manager to eliminate future variances for each District. Further assess if both reporting systems are needed in a pre and post-erp world to avoid confusion in the future. After establishing final balances on Completed Construction, Finance will deliver new Dunning Letters (collection letters) to applicable LGs. Further explanation and guidance around deadlines and Texas Administrative Code (TAC) protocol on collecting should accompany these letters to allow the LG to better understand the approach and expectations. A periodic (to be determined by Districts/Finance) notification or confirmation process with the LGs should be created and communicated. TAC protocol should still be followed, but this process will highlight where disconnects with the LGs may exist so that they can be resolved and no longer delay payments. Collection and reporting steps surrounding the collection of receivables and the Statement of Cost process need to be documented and discussed with all relevant parties at the Division and District levels on an on-going basis. Training (in addition to DEV505) should be created and implemented to provide for the appropriate level of accountability/roles/responsibilities both internally and externally, as needed. The process and responsibilities for sending uncollectable amounts to either the Office of Attorney General or the Comptroller of Public Accounts will be developed and communicated to relevant parties. Records Management/Retention efforts also need to be strengthened to train and identify with Division/District personnel which essential records need to be stored and where (i.e., EDMS) Completion Date: October 15, 2014 April 2,

9 Finding No. 2: Construction/ROW Receivables Report Misstated Condition The process to account for Construction and ROW receivables does not include sufficient reconciliation and monitoring to ensure accurate reporting. Finance Division (FIN) posts a monthly receivables report for construction and ROW projects where third parties have accrued debt to TxDOT. From the January 2, 2013 Statewide Receivables Report, the total balance of $53,272,987 of receivables was overstated by $9,912,327 (19%) due to adjustments identified from projects reviewed in this audit. ROW is also not monitoring and reconciling the FIN monthly receivables report to determine validity of the amounts owed to TxDOT. There is a communication breakdown between the districts and ROW regarding utility adjustments in construction projects. Effect/Potential Impact inaccurate financial figures will affect the reliability of TxDOT financial reports Construction/ROW Receivables Report may be over/under stated due to project financial errors, on-going project cost errors, and communication breakdowns regarding potential utility adjustments Criteria & Cause The Contract Management Manual, Chapter 7, Section 4 states that the project manager must verify that the funding set-up in the accounting record matches the funding requirements spelled out in the Advance Funding Agreement (AFA), and that the associated cash deposits have been collected and posted properly. Further, the project managers are responsible for ensuring the accuracy of TxDOT s financial records in regards to AFAs. Various demand and monthly reports are available for reviewing by the project managers. ROW Division Standard Operating Procedures (SOP) are written for District ROW employees, and they have not been updated since ROW consolidated under ROW Division. The SOPs do not apply to the current organizational structure; therefore, no guidance for monitoring. The ROW Utility Manual, Chapter 5, Section 5 states, Preliminary plan estimates and Advance Funding Agreements (if applicable) for utility work must be forwarded to ROW Division. The Texas Transportation Code Title 6, Subtitle B, Chapter 224 Utility Relocation Costs states, In the acquisition of a highway right-of-way by or for the department, the cost of relocating or adjusting utility facilities, which cost may be eligible under law, is a cost of the acquisition. FIMS is not capable of tracking when a ceiling on fixed participation third party funding agreements is reached and manual oversight by FIN staff is required. FIN must review the account and transfer the expenditures manually or these projects will show up on the receivable list. Training to generate and interpret the FIMS reports is available on-line only, but not mandatory for District or ROW staff that should be monitoring the project costs. April 2,

10 Four ROW receivables were due to utility adjustments incurred during construction, but the Districts did not communicate/coordinate these additional charges with ROW. In addition, ROW did not monitor the receivables in a timely manner and as a result, incomplete documentation was not discovered in a timely manner. Evidence Sampled Construction/ROW Projects: 12 of 40 (30%) project receivables totalling $9,912,327 of the total $28,051,307 (35%) reviewed had financial errors (i.e., federal money not applied or fixed sum participation required manual process to reduce charges over their maximum) and/or charges that were incorrectly coded against the project. Utility Adjustments: 4 of 18 (22%) sampled ROW receivables were for utility adjustments incurred during construction in which ROW had no supporting documentation from the District. Management Action Plan (MAP): MAP Owners: Bruce Matusek - Manager, Projects Ledgers and Federal Billing Maria Maldonado - Accounting Specialist and Lead Worker Vilma Ruiz - Accounting Specialist MAP 2.1: FIN will continue to informally extend this training offer to all districts through the Accounting Specialist and formally through a written invitation by the Director of Finance on the next distribution of the subject report the online DEV 505-Third Party Funding class will continue to be available for use to educate and train the districts FIN will include a note on the Statewide Receivables Report stating that the report is an unaudited working document meant to provide timely third party receivable inform and assist the D/D/Os in identifying errors in third party receivable balances so that corrections can be made in FIMS and on subsequent reports Completion Date: April 15, 2013 incorporate into the Statewide Receivables Report the identification of those third party deposits recognized as fixed contributions for the ability to easily identify fixed third party deposits and provide greater clarity and efficiency in monitoring the report while ensuring increased accuracy Completion Date: September 15, 2013 April 2,

11 MAP Owners: Sheila Mills Director of Project Delivery Gus Cannon Director of Resource Management Section MAP 2.2: ensure Right of Way Delivery Staff (R/WPD) is made aware of any Advance Funding Agreements for Voluntary Utility Relocation Contributions on State Highway Improvement Projects in the construction contract which covers utilities in the construction contract reinstate the process of sending a monthly to ROW Project Delivery staff calling for their printing of the FIMS Demand Reports CST.5801 and CST.5202, and the reconciliation of those reports with ROWIS, and to initiate the collection of any receivables enforce SOP ROW Division Headquarters, Resource Management Section (RSM), and Financial Management Branch (FMB) will be point of contact for the Finance Division RSM FMB will print FIMS demand reports CST.5801 and REC.8501 to verify and document ROW files for project funding and local deposits in regard to ROW Agreement with local government within 5 days of set up in FIMS revise current SOP for Monitoring and Collection of Receivables to combine ROW Project Delivery and ROW Division headquarters responsibilities for monitoring and collection of ROW project receivables; project monitoring includes receivables on utility relocation for Collection of Debt by monitoring collection of debt monthly, require R/WPD staff to send documentation of collection letters sent to the local to the ROW Division headquarters office as Office of Permanent Record and to maintain copies in R/WPD files. If no response from the LPA after the last demand letter is sent, Right of Way Division will forward all demand letters to the Finance Division recommending the Comptroller of Public Accounts utilize the warrant hold procedures or the referral of the delinquent debt to the attorney general, if necessary sponsor training for district staff in collaboration with Contract Services Office and FIN for collection of ROW receivables when utility relocation adjustments are in the construction contract. Sponsor training from Right of Way Division with assistance from the Finance Division and Contract Services Office on how to utilize the FIMS reports CST.5801 and CST.5202 for monitoring deposits and understanding the project funding on Advance Funding Agreements when utility relocation adjustments are in the construction contract implement classroom training to ROW Project Delivery staff for generating and accessing FIMS reports to help understand project funding set up, reconciliation of expenditures, and ROW project funding when utility relocation adjustments are in the construction contract Completion Date: January 15, 2014 April 2,

12 Observation and Recommendation Audit Observation (a): Financial Information Management System (FIMS) Monitoring of Complex Agreements Statewide Receivables Report adjustments are sometimes attributable to the limitation of FIMS to handle complex agreements that are not being monitored and reconciled by Districts and ROW until the construction project is complete; therefore, a receivable balance could age for months before an error is discovered. Effect/Potential Impact 9 of 11 (82%) District receivables reviewed are not monitored with FIMS reports 10 of 15 (67%) ROW receivables reviewed are not monitored with FIMS reports Audit Recommendation Identify specialized programming resources to assist in finishing the IRR submission for changes to FIMS noted below: o produce a new web-based report to replace and/or supplement FIMS CST.5801 report that will allow for easy access from a PC or laptop; this new web based report should mitigate much of the uneasiness and inability to access FIMS Mainframe reports providing a greater comfort level to the users o adding front-end FIMS validity to segment 27 will mitigate number and frequency of miscoded third party deposits by verifying district, project number, and third party entity code against records in DCIS Future changes should also be considered for the pending rollout of the Enterprise Resource Planning modules impacting the Finance Division. April 2,

13 Summary Results Based on Enterprise Risk Management Framework Closing Comments The results of this audit were discussed with FIN, ROW, and the respective Districts. We appreciate the assistance and cooperation received from FIN, ROW and district management and employees contacted during this audit. April 2,

Internal Audit Report. Right of Way Acquisition TxDOT Office of Internal Audit

Internal Audit Report. Right of Way Acquisition TxDOT Office of Internal Audit Internal Audit Report Right of Way Acquisition TxDOT Office of Internal Audit Objective Evaluate the right of way acquisition process for efficiency and compliance. Opinion Based on the audit scope areas

More information

Internal Audit Report. Toll Operations Contract Management TxDOT Office of Internal Audit

Internal Audit Report. Toll Operations Contract Management TxDOT Office of Internal Audit Internal Audit Report Toll Operations Contract Management TxDOT Office of Internal Audit Objective To determine whether the Toll Operations Division (TOD) contract management structure is designed and

More information

Audit of the Administrative and Loan Accounting Center, Austin, Texas

Audit of the Administrative and Loan Accounting Center, Austin, Texas Department of Veterans Affairs Office of Inspector General Audit of the Administrative and Loan Accounting Center, Austin, Texas The Administrative and Loan Accounting Center needed to strengthen certain

More information

Report of independent certified public accountants in accordance with Government Auditing Standards and Circular A-133 State of Hawaii, Department of

Report of independent certified public accountants in accordance with Government Auditing Standards and Circular A-133 State of Hawaii, Department of Report of independent certified public accountants in accordance with Government Auditing Standards and Circular A-133 State of Hawaii,, June 30, 2004 2 C O N T E N T S REPORT OF INDEPENDENT CERTIFIED

More information

Internal Audit Report. Highway Condition Reporting TxDOT Office of Internal Audit

Internal Audit Report. Highway Condition Reporting TxDOT Office of Internal Audit Internal Audit Report Highway Condition Reporting TxDOT Office of Internal Audit Objective To evaluate data integrity in the Highway Condition Report. Opinion Based on the audit scope areas reviewed, control

More information

NASA Financial Management

NASA Financial Management Before the Government Reform Subcommittee on Government Efficiency and Financial Management U.S. House of Representatives For Release on Delivery expected at 2:00 p.m. EDT Wednesday May 19, 2004 NASA Financial

More information

October 2007 Report No. 08-006. An Audit Report on The Medical Transportation Program at the Texas Department of Transportation

October 2007 Report No. 08-006. An Audit Report on The Medical Transportation Program at the Texas Department of Transportation John Keel, CPA State Auditor An Audit Report on The Medical Transportation Program at the Texas Department of Transportation Report No. 08-006 An Audit Report on The Medical Transportation Program at the

More information

June 2008 Report No. 08-037. An Audit Report on The Texas Education Agency s Oversight of Alternative Teacher Certification Programs

June 2008 Report No. 08-037. An Audit Report on The Texas Education Agency s Oversight of Alternative Teacher Certification Programs John Keel, CPA State Auditor An Audit Report on The Texas Education Agency s Oversight of Alternative Teacher Certification Programs Report No. 08-037 An Audit Report on The Texas Education Agency s Oversight

More information

Texas Department of Transportation

Texas Department of Transportation Consultant Errors & Omissions Correction and Collection Procedures July 2014 July 2014 Consultant Errors & Omissions Correction and Collection Procedures 1.0 Consultant Contract Administration... 2 2.0

More information

815 CMR 9.00: DEBT COLLECTION AND INTERCEPT. Section

815 CMR 9.00: DEBT COLLECTION AND INTERCEPT. Section 815 CMR 9.00: DEBT COLLECTION AND INTERCEPT Section 9.01: Purpose, Application and Authority 9.02: Definitions 9.03: Billing Entity Requirements for Collection of Debts 9.04: Simultaneous Submission of

More information

815 CMR: COMPTROLLER'S DIVISION 815 CMR 9.00: DEBT COLLECTION AND INTERCEPT. Section

815 CMR: COMPTROLLER'S DIVISION 815 CMR 9.00: DEBT COLLECTION AND INTERCEPT. Section 815 CMR 9.00: DEBT COLLECTION AND INTERCEPT Section 9.01: Purpose, Application and Authority 9.02: Definitions 9.03: Billing Entity Requirements for Collection of Debts 9.04: Simultaneous Submission of

More information

2015 UNIFIED TRANSPORTATION PROGRAM (UTP) UPDATE

2015 UNIFIED TRANSPORTATION PROGRAM (UTP) UPDATE 2015 UNIFIED TRANSPORTATION PROGRAM (UTP) UPDATE Texas Transportation Commission Footer Text April 30, 2015 Date UTP development and public involvement process Administration revisions and program category

More information

Student Accounts Receivable

Student Accounts Receivable Student Accounts Receivable Original Implementation: July 15, 2008 Last Revision: April 14, 2015 PURPOSE This document establishes guidelines for the prudent collection of student accounts receivable in

More information

Aboriginal Affairs and Northern Development Canada. Internal Audit Report. Audit of Internal Controls Over Financial Reporting.

Aboriginal Affairs and Northern Development Canada. Internal Audit Report. Audit of Internal Controls Over Financial Reporting. Aboriginal Affairs and Northern Development Canada Internal Audit Report Audit of Internal Controls Over Financial Reporting Prepared by: Audit and Assurance Services Branch Project #: 14-05 November 2014

More information

Version Date: 10/16/2013

Version Date: 10/16/2013 2004094 Accounting Documents (ADVANTAGE Financial System Input) This record series is used to input information into the ADVANTAGE Financial System. The files may contain, but are not limited to: copies

More information

June 2008 Report No. 08-038. An Audit Report on The Department of Information Resources and the Consolidation of the State s Data Centers

June 2008 Report No. 08-038. An Audit Report on The Department of Information Resources and the Consolidation of the State s Data Centers John Keel, CPA State Auditor An Audit Report on The Department of Information Resources and the Consolidation of the State s Data Centers Report No. 08-038 An Audit Report on The Department of Information

More information

TxDOT Internal Audit Report Disaster Recovery - IT

TxDOT Internal Audit Report Disaster Recovery - IT TxDOT Internal Audit Report Disaster Recovery - IT Objective Determine if adequate plans and the ability to ensure critical TxDOT operations are not impacted by business interruptions to IT infrastructure.

More information

The Requirements Compliance Matrix columns are defined as follows:

The Requirements Compliance Matrix columns are defined as follows: 1 DETAILED REQUIREMENTS AND REQUIREMENTS COMPLIANCE The following s Compliance Matrices present the detailed requirements for the P&I System. Completion of all matrices is required; proposals submitted

More information

AUDITOR GENERAL DAVID W. MARTIN, CPA

AUDITOR GENERAL DAVID W. MARTIN, CPA AUDITOR GENERAL DAVID W. MARTIN, CPA AGENCY FOR HEALTH CARE ADMINISTRATION ADMINISTRATIVE ACTIVITIES Operational Audit SUMMARY This operational audit of the Agency for Health Care Administration (Agency)

More information

Audit of Financial Reporting Controls

Audit of Financial Reporting Controls Audit of Financial Reporting Controls WESTERN ECONOMIC DIVERSIFICATION CANADA Audit & Evaluation Branch February 2012 Table of Contents 1.0 Executive Summary 1 2.0 Statement of Assurance 1 3.0 Introduction

More information

UNIVERSITY OF NEVADA, RENO PARKING AND TRANSPORTATION SERVICES Internal Audit Report July 1, 2011 through June 30, 2013

UNIVERSITY OF NEVADA, RENO PARKING AND TRANSPORTATION SERVICES Internal Audit Report July 1, 2011 through June 30, 2013 UNIVERSITY OF NEVADA, RENO PARKING AND TRANSPORTATION SERVICES Internal Audit Report July 1, 2011 through June 30, 2013 GENERAL OVERVIEW The University of Nevada, Reno (UNR) Parking and Transportation

More information

OFFICE OF THE STATE COMPTROLLER DIVISION OF LOCAL GOVERNMENT SERVICES

OFFICE OF THE STATE COMPTROLLER DIVISION OF LOCAL GOVERNMENT SERVICES OFFICE OF THE STATE COMPTROLLER DIVISION OF LOCAL GOVERNMENT SERVICES AND ECONOMIC DEVELOPMENT TECHNICAL ASSISTANCE Comptroller OFFICE OF THE STATE COMPTROLLER DIVISION OF LOCAL GOVERNMENT SERVICES & ECONOMIC

More information

Accounts Receivable Toolkit

Accounts Receivable Toolkit Accounts Receivable Toolkit TABLE OF CONTENTS OBJECTIVE... 1 BACKGROUND... 1 MANAGEMENT AND INTERNAL AUDIT RESPONSIBILITIES... 1 PREVENTION... 2 COLLECTIONS... 3 Best Practices... 3 EMPLOYEE ARs... 6 Managing

More information

Policy No: F&A 03-15 Approved by Council: June 26, 2013 Resolution: 2013.12.16. The policy should assist in:

Policy No: F&A 03-15 Approved by Council: June 26, 2013 Resolution: 2013.12.16. The policy should assist in: Treasury Department Policy Section: Finance & Accounting Content Updated: Supersedes Policy: Policy No: F&A 03-15 Approved by Council: June 26, 2013 Resolution: 2013.12.16 Pages: 1 of 11 GENERAL ACCOUNTS

More information

Office of Inspector General Evaluation of the Consumer Financial Protection Bureau s Consumer Response Unit

Office of Inspector General Evaluation of the Consumer Financial Protection Bureau s Consumer Response Unit Office of Inspector General Evaluation of the Consumer Financial Protection Bureau s Consumer Response Unit Consumer Financial Protection Bureau September 2012 September 28, 2012 MEMORANDUM TO: FROM: SUBJECT:

More information

Performance Audit Report. Department of Human Resources The Maryland Energy Assistance Program and the Electric Universal Service Program

Performance Audit Report. Department of Human Resources The Maryland Energy Assistance Program and the Electric Universal Service Program Performance Audit Report Department of Human Resources The Maryland Energy Assistance Program and the Electric Universal Service Program Accounting Records Cannot Be Relied Upon to Provide Accurate Expenditure

More information

Master Document Audit Program. Version 1.5, dated September 2015 B-01 Planning Considerations

Master Document Audit Program. Version 1.5, dated September 2015 B-01 Planning Considerations Activity Code 11070 Version 1.5, dated September 2015 B-01 Planning Considerations Accounting System Audit Audit Specific Independence Determination Members of the audit team and internal specialists consulting

More information

85.54 Receivables. 85.54.10 July 1, 2012. About receivables. 85.54.15 July 1, 2009. Taxes receivable 85.54.10

85.54 Receivables. 85.54.10 July 1, 2012. About receivables. 85.54.15 July 1, 2009. Taxes receivable 85.54.10 85.54.10 85.54 Receivables 85.54.10 July 1, 2012 85.54.10.a 85.54.10.b 85.54.10.c About receivables Receivables are defined as the amounts to be collected from private individuals, businesses, agencies,

More information

Aboriginal Affairs and Northern Development Canada. Internal Audit Report. Audit of Management of Negotiation Loans. Prepared by:

Aboriginal Affairs and Northern Development Canada. Internal Audit Report. Audit of Management of Negotiation Loans. Prepared by: Aboriginal Affairs and Northern Development Canada Internal Audit Report Audit of Management of Negotiation Loans Prepared by: Audit and Assurance Services Branch Project No. 12-11 February 2013 TABLE

More information

MICHIGAN OFFICE OF THE AUDITOR GENERAL THOMAS H. MCTAVISH, C.P.A. AUDITOR GENERAL

MICHIGAN OFFICE OF THE AUDITOR GENERAL THOMAS H. MCTAVISH, C.P.A. AUDITOR GENERAL MICHIGAN OFFICE OF THE AUDITOR GENERAL THOMAS H. MCTAVISH, C.P.A. AUDITOR GENERAL The auditor general shall conduct post audits of financial transactions and accounts of the state and of all branches,

More information

Audit of Accounts Receivable. Internal Audit Report

Audit of Accounts Receivable. Internal Audit Report Audit of Accounts Receivable Internal Audit Report July 2011 Table of Contents Executive Summary....3 1.0 Introduction... 5 1.1 Background... 5 1.2 Risk Assessment...6 1.3 Audit Objectives and Scope...

More information

Oversight of Information Technology Projects. Information Technology Audit

Oversight of Information Technology Projects. Information Technology Audit O L A OFFICE OF THE LEGISLATIVE AUDITOR STATE OF MINNESOTA FINANCIAL AUDIT DIVISION REPORT Oversight of Information Technology Projects Information Technology Audit May 29, 2009 Report 09-19 FINANCIAL

More information

12 16 Memorial Physician Network Billing Cycle Audit Report

12 16 Memorial Physician Network Billing Cycle Audit Report O FFICE O F T HE C ITY A UDITOR C OLORADO S PRINGS, C OLORADO 12 16 Memorial Physician Network Billing Cycle Audit Report September 2012 O FFICE O F T HE C ITY A UDITOR C OLORADO S PRINGS, C OLORADO 12

More information

Community Ambulance Service District

Community Ambulance Service District Community Ambulance Service District For the period July 1, 2011 through June 30, 2013 Oklahoma State Auditor & Inspector Gary A. Jones, CPA, CFE This publication, issued by the Oklahoma State Auditor

More information

Assessment and Collection of Selected Penalties. Workers Compensation Board

Assessment and Collection of Selected Penalties. Workers Compensation Board New York State Office of the State Comptroller Thomas P. DiNapoli Division of State Government Accountability Assessment and Collection of Selected Penalties Workers Compensation Board Report 2011-S-3

More information

August 2014 Report No. 14-043

August 2014 Report No. 14-043 John Keel, CPA State Auditor A Report on On-site Audits of Residential Child Care Providers Report No. 14-043 A Report on On-site Audits of Residential Child Care Providers Overall Conclusion Three of

More information

John Keel, CPA State Auditor. An Audit Report on The Dam Safety Program at the Commission on Environmental Quality. May 2008 Report No.

John Keel, CPA State Auditor. An Audit Report on The Dam Safety Program at the Commission on Environmental Quality. May 2008 Report No. John Keel, CPA State Auditor An Audit Report on The Dam Safety Program at the Commission on Environmental Quality Report No. 08-032 An Audit Report on The Dam Safety Program at the Commission on Environmental

More information

SYSTEMS AND CONTROLS. Management Assurances FEDERAL MANAGERS FINANCIAL INTEGRITY ACT (FMFIA) ASSURANCE STATEMENT FISCAL YEAR (FY) 2012

SYSTEMS AND CONTROLS. Management Assurances FEDERAL MANAGERS FINANCIAL INTEGRITY ACT (FMFIA) ASSURANCE STATEMENT FISCAL YEAR (FY) 2012 SYSTEMS AND CONTROLS Management Assurances FEDERAL MANAGERS FINANCIAL INTEGRITY ACT (FMFIA) ASSURANCE STATEMENT FISCAL YEAR (FY) 2012 Management is responsible for establishing and maintaining effective

More information

REPORT 2016/035 INTERNAL AUDIT DIVISION

REPORT 2016/035 INTERNAL AUDIT DIVISION INTERNAL AUDIT DIVISION REPORT 2016/035 Audit of the use of consultants and individual contractors in the United Nations Stabilization Mission in Haiti Overall results relating to the effective hiring

More information

INTERNAL CONTROL MATRIX FOR AUDIT OF BILLING SYSTEM CONTROLS Version No. 4.2 August 2006

INTERNAL CONTROL MATRIX FOR AUDIT OF BILLING SYSTEM CONTROLS Version No. 4.2 August 2006 INTERNAL CONTROL MATRIX FOR AUDIT OF BILLING SYSTEM CONTROLS Version No. 4.2 August 2006 1. MANAGEMENT REVIEWS The contractor should have policies and procedures for periodic monitoring of the billing

More information

Auditor of Public Accounts Adam H. Edelen

Auditor of Public Accounts Adam H. Edelen Auditor of Public Accounts Adam H. Edelen FOR IMMEDIATE RELEASE Contact: Stephenie Steitzer [email protected] 502.564.5841 513.289.7667 Edelen Releases Audit of Former Owsley Clerk s Fee

More information

United States Chemical Safety and Hazard Investigation Board

United States Chemical Safety and Hazard Investigation Board United States Chemical Safety and Hazard Investigation Board Audit of Financial Statements As of and for the Years Ended September 30, 2005 and 2004 Submitted By Leon Snead & Company, P.C. Certified Public

More information

Accounts Receivable and Debt Collection Processes. Internal Controls and Compliance Audit

Accounts Receivable and Debt Collection Processes. Internal Controls and Compliance Audit O L A OFFICE OF THE LEGISLATIVE AUDITOR STATE OF MINNESOTA FINANCIAL AUDIT DIVISION REPORT Accounts Receivable and Debt Collection Processes Internal Controls and Compliance Audit July 1, 2008, through

More information

August 2008 Report No. 08-046

August 2008 Report No. 08-046 John Keel, CPA State Auditor A Report on On-site Audits of Residential Child Care Providers Report No. 08-046 A Report on On-site Audits of Residential Child Care Providers Overall Conclusion Three of

More information

Appendix C: Examples of Common Accounting and Bookkeeping Procedures

Appendix C: Examples of Common Accounting and Bookkeeping Procedures Appendix C: Examples of Common Accounting and Bookkeeping Procedures In this Appendix the use of the term monthly means on a regular cycle, based on the needs of your district. Some of the sample accounting

More information

Aboriginal Affairs and Northern Development Canada. Internal Audit Report. Prepared by: Audit and Assurance Services Branch.

Aboriginal Affairs and Northern Development Canada. Internal Audit Report. Prepared by: Audit and Assurance Services Branch. Aboriginal Affairs and Northern Development Canada Internal Audit Report Audit of Water and Wastewater Infrastructure Prepared by: Audit and Assurance Services Branch Project # 12-10 February 2013 TABLE

More information

CASH COUNT AND BANK RECONCILIATION AUDIT

CASH COUNT AND BANK RECONCILIATION AUDIT City of San Diego AUDIT REPORT CASH COUNT AND BANK RECONCILIATION AUDIT KROLL REMEDIATION OF THE CITY S BANK RECONCILIATION PROCESS April 28, 2008 Internal Audit Eduardo Luna, CIA, CGFM, Internal Auditor

More information

SBA Policy Notice. TO: All SBA Employees CONTROL NO.: 5000-1382. SUBJECT: Reauthorization of 504 Debt EFFECTIVE: 05/26/2016. Refinancing Program

SBA Policy Notice. TO: All SBA Employees CONTROL NO.: 5000-1382. SUBJECT: Reauthorization of 504 Debt EFFECTIVE: 05/26/2016. Refinancing Program SBA Policy Notice TO: All SBA Employees CONTROL NO.: 5000-1382 SUBJECT: Reauthorization of 504 Debt Refinancing Program EFFECTIVE: 05/26/2016 The Small Business Jobs Act of 2010 (Jobs Act), P.L. 111-240,

More information

Environment. Main points...226. Introduction...227. Our audit conclusions and findings...228. Internal reporting needs improvement...

Environment. Main points...226. Introduction...227. Our audit conclusions and findings...228. Internal reporting needs improvement... Environment 9 Main points...226 Introduction...227 Our audit conclusions and findings...228 Internal reporting needs improvement...229 Control over capital assets needed...229 Recording and collection

More information

Clerk of the Circuit Court. Official Records & Tax Deeds Audit. August, 2006

Clerk of the Circuit Court. Official Records & Tax Deeds Audit. August, 2006 Clerk of the Circuit Court Official Records & Tax Deeds Audit August, 2006 Report by Internal Audit Division Clerk of the Circuit Court Table of Contents Transmittal Letter...2 Executive Summary...4 Background...5

More information

AUDIT REPORT. Federal Energy Regulatory Commission's Fiscal Year 2014 Financial Statement Audit

AUDIT REPORT. Federal Energy Regulatory Commission's Fiscal Year 2014 Financial Statement Audit U.S. Department of Energy Office of Inspector General Office of Audits and Inspections AUDIT REPORT Federal Energy Regulatory Commission's Fiscal Year 2014 Financial Statement Audit OAS-FS-15-05 December

More information

UCLA Policy 360: Internal Control Guidelines for Campus Departments

UCLA Policy 360: Internal Control Guidelines for Campus Departments UCLA Policy 360: Internal Control Guidelines for Campus Departments Issuing Officer: Assistant Vice Chancellor, Corporate Financial Services Responsible Dept: Financial Management Programs Effective Date:

More information

KAREN E. RUSHING. Audit of Purchasing Card Program

KAREN E. RUSHING. Audit of Purchasing Card Program KAREN E. RUSHING Clerk of the Circuit Court and County Comptroller Audit of Purchasing Card Program Audit Services Jeanette L. Phillips, CPA, CGFO, CIG Director of Internal Audit and Inspector General

More information

SOUTH CAROLINA RETIREE HEALTH INSURANCE TRUST FUND AUDITED FINANCIAL STATEMENTS YEAR ENDED JUNE 30, 2014 WITH INDEPENDENT AUDITORS REPORT

SOUTH CAROLINA RETIREE HEALTH INSURANCE TRUST FUND AUDITED FINANCIAL STATEMENTS YEAR ENDED JUNE 30, 2014 WITH INDEPENDENT AUDITORS REPORT SOUTH CAROLINA RETIREE HEALTH INSURANCE TRUST FUND AUDITED FINANCIAL STATEMENTS YEAR ENDED JUNE 30, 2014 WITH INDEPENDENT AUDITORS REPORT State of South Carolina RICHARD H. GILBERT, JR., CPA DEPUTY STATE

More information

45.241 Definitions -- State agencies and Court of Justice to develop inventory of each debt -- Liquidated debts of agency, Court of Justice, or local

45.241 Definitions -- State agencies and Court of Justice to develop inventory of each debt -- Liquidated debts of agency, Court of Justice, or local 45.241 Definitions -- State agencies and Court of Justice to develop inventory of each debt -- Liquidated debts of agency, Court of Justice, or local government submitted to Department of Revenue -- Accounting

More information

OFFICE OF INSPECTOR GENERAL. Audit Report

OFFICE OF INSPECTOR GENERAL. Audit Report OFFICE OF INSPECTOR GENERAL Audit Report Audit of the Data Management Application Controls and Selected General Controls in the Financial Management Integrated System Report No. 14-12 September 30, 2014

More information

INSPECTOR GENERAL STATEMENT ON THE FEDERAL COMMUNICATIONS COMMISSION S MAJOR MANAGEMENT CHALLENGES FISCAL YEAR 2005

INSPECTOR GENERAL STATEMENT ON THE FEDERAL COMMUNICATIONS COMMISSION S MAJOR MANAGEMENT CHALLENGES FISCAL YEAR 2005 INSPECTOR GENERAL STATEMENT ON THE FEDERAL COMMUNICATIONS COMMISSION S MAJOR MANAGEMENT CHALLENGES FISCAL YEAR 2005 05-AUD-04-08 November 15, 2005 Office of Inspector General ******* Federal Communications

More information

Fundamentals Level Skills Module, F8 (IRL)

Fundamentals Level Skills Module, F8 (IRL) Answers Fundamentals Level Skills Module, F8 (IRL) Audit and Assurance (Irish) June 2008 Answers 1 (a) Prior year internal control questionnaires Obtain the audit file from last year s audit. Ensure that

More information

Student Assessment Administrative Review Phase 1

Student Assessment Administrative Review Phase 1 Internal Audit Student Assessment Administrative Review Phase 1 Issue Date: March 2015 Report Number: FY2015-02 Executive Summary AUDIT OF: Student Assessment DATE: Fieldwork performed January 2015 February

More information

Woodward County Emergency Medical Service District

Woodward County Emergency Medical Service District Woodward County Emergency Medical Service District For the period July 1, 2011 through June 30, 2014 Oklahoma State Auditor & Inspector Gary A. Jones, CPA, CFE FOR THE PERIOD JULY 1, 2011 THROUGH JUNE

More information

Chairwoman Foxx, Ranking Member Hinojosa, and members of the Subcommittee, thank you

Chairwoman Foxx, Ranking Member Hinojosa, and members of the Subcommittee, thank you Testimony of Kathleen S. Tighe, Inspector General U.S. Department of Education Before the Education and the Workforce Committee Subcommittee on Higher Education and Workforce Training U.S. House of Representatives

More information

Accounts Receivable Report

Accounts Receivable Report Accounts Receivable Report For the Fiscal Year Ended June 30, 2004 Colorado Department of Personnel & Administration Division of Finance and Procurement Office of the State Controller Leslie M. Shenefelt,

More information

State of Georgia Commercial Revitalization Deduction Program Qualified Allocation Plan for Calendar Year 2006

State of Georgia Commercial Revitalization Deduction Program Qualified Allocation Plan for Calendar Year 2006 State of Georgia Commercial Revitalization Deduction Program Qualified Allocation Plan for Calendar Year 2006 Officially adopted by the Board of Directors of The Georgia Department of Community Affairs

More information