1 LANDSLIDE RISK MANAGEMENT AT BC HYDRO Experience with Landslide monitoring and drainage Tom Stewart, January 2017

2 PRESENTATION OVERVIEW 1. BC Hydro - Overview 2. Landslide / Reservoir Slopes Program 3. Landslide Case Histories Downie Slide Dutchman s Ridge Revelstoke Dam 4. BC Hydro Experience Lessons Learned 2

3 1. About BC Hydro BC Hydro is a Crown (State-run) corporation, established in 1961, owned by the Province of British Columbia and regulated by the British Columbia Utilities Commission (BCUC), an independent body. one of North America s leading providers of clean, renewable energy largest electric utility in British Columbia approximately 1.8 million customers serves about 95 per cent of the province s population Capacity 43 dam sites - 11,300 megawatts (MW) installed capacity 97% of generation based on clean, renewable hydroelectricity BC Hydro customers enjoy some of the world's lowest electricity rates Transmission 18,600 kilometres of transmission lines 57,278 kilometres of distribution lines 3

4 BC HYDRO DAMS GEOGRAPHIC CONTEXT 1. Aberfeldie Dam 2. Alouette Dam 3. Bear Creek Dam 4. Buntzen Dam 5. Cheakamus Dam 6. Clayton Falls Dam 7. Clowhom Dam 8. Comox Dam 9. Coquitlam Dam 10. Coursier Dam (decommissioned) 11. Duncan Dam 12. Elko Dam 13. Elliott Dam 14. Elsie Dam 15. Falls River Dam 16. Heber Diversion Dam 17. Hugh Keenleyside Dam 18. John Hart Dam 19. Jordan Diversion Dam 20. Kootenay Canal Dam 21. La Joie Dam 22. Ladore Dam 23. Mica Dam 24. Peace Canyon Dam 25. Puntledge Diversion Dam 26. Quinsam Diversion Dam 27. Quinsam Storage Dam 28. Revelstoke Dam (1902) (1985) (2001) 29. Ruskin Dam 30. Salmon River Diversion Dam 31. Seton Dam 32. Seven Mile Dam 33. Spillimacheen Dam 34. Stave Falls Dam 35. Strathcona Dam 36. Sugar Lake Dam 37. Terzaghi Dam 38. W.A.C. Bennett Dam 39. Wahleach Dam 40. Walter Hardman Dam 41. Whatshan Dam 42. Wilsey Dam 43. Site C - current 4

5 2. BC Hydro Landslide Program Peace Upper Columbia 8 of 15 monitored landslides in this area 43 Dam sites 15 Monitored Landslides Kootenays 3000 km Reservoir Shoreline Vancouver Island Fraser Valley- Bridge 5

6 3. Upper Columbia - Landslide Factors Dutchman s Ridge Large topographic relief (3500 m+) steep slopes (20 60 o ) Adverse geologic conditions (continuous structures: faults, foliation) Extensive precipitation mm/yr Downie Slide 6

7 3. Landslide - Drainage Case Histories Dutchman s Ridge All on west side of Columbia valley All structurally controlled along foliation / shears Downie Slide Precedent for large, rapid rock slides (2 in last 200 yrs) Revelstoke Dam Moderate seismic zone (pga ~ 0.3 g) 7

8 DOWNIE SLIDE - OVERVIEW Head scarp Identified 1950 s Extensively investigated (1965-present) 1.5 B m 3 (9.5 km 2 x 250m deep) 8

9 Downie Slide Key Dam Safety Issues 1. Landslide generated wave - Dam over-topping dam breach 2. Reservoir blockage 3. Dam flooding (Mica) 9

10 Downie Slide Revelstoke Dam Figure 1: Key physiographic features of Downie Slide; bounding scarps and steep bulging toe Dam Approval linked to Downie Stabilization Extensive Public Consultation and review process Drainage selected to more than offset filling of reservoir 10

11 Downie Slide Geologic Section Detailed geologic model required for drainage design Head scarp Identified 1950 s Extensively drilled B m3 Slowly moving (3 to 200 mm/yr) Drilling - Monitoring installed o downslope dip drainage Geology Mica schist/gneiss; continuous structures 2008 drainage upgrades Groundwater Multiple water levels Extensive ADAS Movement Slowly moving (3 to 200 mm/yr) DS Issues: Overtopping wave / reservoir blockage / impact to reservoir users (on 2 main surfaces) 11

12 Downie Slide Drainage Program Head scarp Drainage Adit Adits - constructed using Observational approach (piezometers) Completed in three stages

13 Downie Slide Drainage Program Head scarp Identified 1950 s Extensively drilled B m3 Slowly moving (3 to 200 mm/yr) Drainage Adit drainage 2008 Adits drainage primarily upgrades in slide mass Extensive 2.45 km ADAS of adit DS Issues: Overtopping wave / reservoir blockage / impact to reservoir users 24,000 m of drain holes 13

14 Downie Slide Drainage Adits JHT Conventional drill and blast; horseshoe shape; extensively supported 14

15 Downie Slide - Groundwater Response Rsp Test 2500 Piezometric Elevation (feet) Drain Const 77 -Rsp Test -Rsp Test Drain Const 81 1 Res Fill Start Res Fill End S49 P1/P2 connected to ADAS Nov 2007 P2 above Lower Shear 2300 Piezometric Elevation (ft) P1 below Lower Shear Drainhole drilling Nov Jun Y1 Legend DHS25P1 DHS49P1 Y2 Legend DHS49P1 A DOWNIE SLIDE STANDPIPE PIEZOMETERS (MANUAL) North Knob Area S25 P1 and P2 TWS PZ77 January 27, Significant drainage effects up to 100 m pressure reductions 2. Met initial objective but increasing pressure trends observed 15

16 Downie Slide - Groundwater Response Piezometric Elevation (feet) Drain Const 81 Res Fill Start Res Fill End S42 Sensor tip elevations: P P ' P ' P P ' 1 2 On ADAS P4 above Lower Shear 2265' P3 Stability Check Level 2236' P3 Base Level P3 in Lower Shear 2177' P2 Base Level 3 P1 / P2 below Lower Shear Piezometric Elevation (feet) Y1 Legend DHS42P5 DHS42P4 DHS42P3 DHS42P2 DHS42P1 Y2 Legend DHS42P5 A DHS42P4 A DHS42P3 A DHS42P2 A DHS42P1 A DOWNIE SLIDE STANDPIPE PIEZOMETERS South Scarp area near toe S42 P1 to P5 TWS PZ18 January 17, Most piezometers encountered perched water levels 2. Water typically perched above the 2 active zones 16

17 Downie Slide - Displacement 3 (2 mm/yr) Slope displacement response to drainage, measured across lower slide plane: 1. Slight reduction following drainage (5 > 3 mm/yr) Increase during reservoir filling (10 mm/yr) 3. Relatively consistent post reservoir fill ( 2 3 mm/yr) 17

18 Downie Slide Summary 1. Groundwater levels reduced to below pre-reservoir levels 2. Displacement rates are similar or less than pre-reservoir conditions 3. Stability increased by ~ 7% (FOS) 4. Water License Requirement must maintain system 18

19 BC HYDRO LANDSLIDES Mica Dam DR LCS Mica Dam m high earthfill dam The most upstream of 14 dams on Columbia River Major upstream landslides 19

20 Dutchman s Ridge Potential Slide Identified mid-1960 s (airphotos) 1969 drilling 30 M m 3 Physical wave model studies (50 m+ waves) Dam construction revised to accommodate slide waves Decision not to drain 20

21 Dutchman s Ridge - Displacement 1. Pre-reservoir negligible displacement detected Reservoir filling (190 m) initiated movements of 25 mm/yr 3. Slope displacement acceleration resulted in decision to further investigate 1 Slope displacement response to reservoir filling (pre-drainage) 21

22 Dutchman s Ridge Investigations Slide Base Geological Model (Updated): Well defined continuous basal sliding surface Depth of sliding 75 to 150 m Movements of up to 200mm occurred during reservoir filling 115 M m3 (~4x original) Drainage Adit Analyses concluded: Raising of reservoir reduced stability by ~ 10% Large, first time slide possible Remediation preferred drainage option selected 22

23 Dutchman s Ridge Slide - Reservoir Outline of currently active slide 1969 estimate of slide volume 30 M m 3 Post - reservoir reevaluation (1982) Slide size reassessed 115 M m 3 Drainage Adit Additional analyses (larger wave) Decision to install drainage system 23

24 Relevance of Dutchman s Ridge Aknes Aknes Similarities: Size Geology Setting Landslide wave hazard Dutchman s Ridge British Columbia 24

25 Dutchman s Ridge Drainage Design Extensive monitoring system installed (350 measurement ports): To identify where water pressures could be drained To evaluate effectiveness of drainage system 25

26 Dutchman s Ridge Drilling Observations Piezo profiling during drilling Slide Base Open hole measurements could be dry below slide Most drill holes showed perched water levels Testing allowed optimum design of piezo installation 26

27 Dutchman s Ridge Piezo Testing Piezometric testing during drilling Custom through-the-drill-string set up Reliable no issues with getting stuck Data immediately available 27

28 Dutchman s Ridge Drainage Layout 982 m of Adit installed ( ) ; 20,000 m of drainholes 28

29 Dutchman Ridge Groundwater TH Drainage - Construction Elevation (Metres) Potential Slide Base m MP s dry MP MP MP MP MP MP27 MICA RESERVOIR SLOPES Dutchman's Ridge Multi-Point Piezometers 86-33A Ports (2 of3) PBS DMR PZ27 January 18, Large portions of potential slide fully drained. 2. Up to 100 m pressure drawdown lasting effect 29

30 Dutchman s Ridge - Displacement Inclinometer Across Slide Base Pre-drainage ~15 mm/yr Post-drainage 0.5 mm/yr Slope displacement response to drainage - rate reduced by > order of magnitude 30

31 Dutchman s Ridge Adit Conditions Flow rates have reduced but pressures have remained fully drained 31

32 Dutchman s Ridge Compared to Downie Slide Base Drainage Adit Smaller slide mass - easier to effectively drain Single sliding plane (DMR) vs two + planes (Downie) Slightly better rock quality less previous slide displacement Adit below slide in competent rock Nearly fully drained condition effectively halted movements 32

33 Revelstoke Dam Marble Shear Block 175 m high concrete gravity; with earthfill wing dam 1985 dam completion Slope instability on right bank (Marble Shear Block) 200,000 m3 Potential to undermine spillway; block tailrace 33

34 Marble Shear Block - Geology 1. Quartzite / Mica Gneiss Pre-drainage 13 mm/yr Post-drainage 2. Persistent planes of weakness (foliation / shears) dipping down slope 3. Considerable groundwater Risk Management 1. Risk to spillway / discharge facilities considered unacceptable 2. Drainage selected as remedial option 34

35 Marble Shear Block Drainage 1. Spillway Structure 2. Sliding Plane 3. Adit (40 m long) 4. With ~1000 m of drainholes 35

36 Marble Shear Block Groundwater TH Start of MSB Drainage Adit and Drainhole Drilling Aug 1998 Falling Head Test 2014 drilling Piezometric Elevation (ft) Tip 1544' 79AT25 Threshold 1563' 1 79AT24 Threshold 1513' Drain cleaning and reaming in MSB adit, Feb & May Tip 1483' AT24 79AT24 A 79AT25 A 79AT25 D 79AT25 REVELSTOKE ROCKSLOPES Marble Shear Block - Piezometric Pressures Piezometers Near Section C (6+35) Threshold Levels TWS PZ56 August 19, Significant pressure reductions (up to 15 m) from drainage 2. Remedial effects are persisting over 15 years lasting results 36

37 Marble Shear Block - Displacement 1 Inclinometer slide plane Minor displacement prior to drainage installation (2mm/yr) 2. Drainage Slope displacement effectively stopped following drainage 37

38 LANDSLIDE REMEDIATION THROUGH DRAINAGE Lessons Learned Summary: 1. Drainage has been effective objectives achieved 940 Dewatering /depressurizing Displacement reduced/stopped Improved stability (5-10% FOS) Elevation (Metres) Drainage - Construction Potential Slide Base m MP MP MP MP MP MP27 MICA RESERVOIR SLOPES Dutchman's Ridge Multi-Point Piezometers 86-33A Ports (2 of3) PBS DMR PZ27 January 18, 2017 Tom Stewart, January 2017

39 LANDSLIDE REMEDIATION THROUGH DRAINAGE Lessons Learned Summary: 2. Well positioned monitoring system required (plan/evaluate) Need to understand where water is located Detailed site investigation and monitoring required Needs to be installed before drainage Tom Stewart, August 2015

40 LANDSLIDE REMEDIATION THROUGH DRAINAGE Lessons Learned Summary: 3. Well positioned monitoring system required (plan/evaluate) 1. Need to conduct in situ testing during drilling to understand where water is located 2. Identifies perched zones and downhole gradients that are otherwise missed 3. Allows planning for permanent piezometric monitoring. 4. Use of multi-port type piezometers highly effective (i.e. Westbay type).

41 LANDSLIDE REMEDIATION THROUGH DRAINAGE Lessons Learned Summary: 4. Drainage response typically confined to treated area only overage installation network spatially Tom Stewart, August 2015

42 LANDSLIDE REMEDIATION THROUGH DRAINAGE Lessons Learned Summary: 5. Plan for maintenance successful results come from longterm commitment Lighting, ventilation, power supply Drainhole replacement (cleaning ineffective) Requirement to install additional monitoring Rock support Tom Stewart, January 2017

43 LANDSLIDE REMEDIATION THROUGH DRAINAGE Questions / Discussion? Tom Stewart, January 2017

44 BRITISH COLUMBIA NORWEGIAN CONTEXT 23. Mica Dam 28. Revelstoke Dam British Columbia 944,735 sq. km 1900 km long 505 km wide Mountainous Lots of snow Lots of fjords 3% of population of Norwegian descent Norway 304,282 sq. km 1347 km long 304 km wide Mountainous Lots of snow Lots of fjords 44

CHAPTER 9 CONCLUSIONS AND RECOMMENDED MITIGATION

CHAPTER 9 CONCLUSIONS AND RECOMMENDED MITIGATION CHAPTER 9 CONCLUSIONS AND RECOMMENDED MITIGATION 9.1 Conclusions Based on the stability cross-sections down the SE flank of Snodgrass Mountain, most landslides on low- to moderate-gradient slopes have

More information

Consulting Boards for Large Civil Engineering Projects

Consulting Boards for Large Civil Engineering Projects Consulting Boards for Large Civil Engineering Projects Evert Hoek and Alan S. Imrie Published in Water Power and Dam Construction, Vol. 47, No. 8, pp 33-34, August 1995. Consulting Boards for Large Civil

More information

The correct answers are given below. Some talking points have been added for the teachers use.

The correct answers are given below. Some talking points have been added for the teachers use. Natural Resources Canada 2011: Lesson Plan Grades 11 and 12 Landslide activity 5b: Landslides in Canada quiz Description: This is an independent study activity for grades 11 and 12. Students will read

More information

Site C Clean Energy Project Topic Specific Sessions: Presentation by Natural Resources Canada

Site C Clean Energy Project Topic Specific Sessions: Presentation by Natural Resources Canada Site C Clean Energy Project Topic Specific Sessions: Presentation by Natural Resources Canada Fort St. John, British Columbia January 13, 2014 Outline 1. Context for NRCan s Participation in the Joint

More information

ICOLD POSITION PAPER ON DAM SAFETY AND EARTHQUAKES

ICOLD POSITION PAPER ON DAM SAFETY AND EARTHQUAKES ICOLD POSITION PAPER ON DAM SAFETY AND EARTHQUAKES August 2012 Dam Safety and Earthquakes Position Paper of International Commission on Large Dams (ICOLD) Prepared by ICOLD Committee on Seismic Aspects

More information

Engineering Geological Asset Management for Large Dams. Yasuhito SASAKI (1)

Engineering Geological Asset Management for Large Dams. Yasuhito SASAKI (1) Engineering Geological Asset Management for Large Dams Yasuhito SASAKI (1) (1) Geology Research Team, Public Works Research Institute, Japan E-mail:ya-sasa@pwri.go.jp Abstract Comprehensive inspection

More information

A CASE-STUDY OF CUA_DAT CFRD IN VIETNAM

A CASE-STUDY OF CUA_DAT CFRD IN VIETNAM A CASE-STUDY OF CUA_DAT CFRD IN VIETNAM Giang Pham Hong, Michel Hotakhanh, Nga Pham Hong, Hoai Nam Nguyen, Abstract:Dams have been taken an important role in time and surface redistribution of water for

More information

Earthquakes: Interesting Facts and F.A.Q.

Earthquakes: Interesting Facts and F.A.Q. Earthquakes: Interesting Facts and F.A.Q. Earthquakes kill approximately 8,000 people each year and have caused an estimated 13 million deaths in the past 4,000 years. The moment magnitude scale (MMS)

More information

ANNEX D1 BASIC CONSIDERATIONS FOR REVIEWING STUDIES IN THE DETAILED RISK ASSESSMENT FOR SAFETY

ANNEX D1 BASIC CONSIDERATIONS FOR REVIEWING STUDIES IN THE DETAILED RISK ASSESSMENT FOR SAFETY ANNEX D1 BASIC CONSIDERATIONS FOR REVIEWING STUDIES IN THE DETAILED RISK ASSESSMENT FOR SAFETY ANNEX D1: BASIC CONSIDERATIONS FOR REVIEWING STUDIES IN DRA FOR SAFETY D1-1 ANNEX D1 BASIC CONSIDERATIONS

More information

Instrumentation and Real Time Monitoring of a Landslide on Highway No. 302 Near Prince Albert, Saskatchewan

Instrumentation and Real Time Monitoring of a Landslide on Highway No. 302 Near Prince Albert, Saskatchewan Instrumentation and Real Time Monitoring of a Landslide on Highway No. 302 Near Prince Albert, Saskatchewan R. Allan Widger, Saskatchewan Department of Highways and Transportation awidger@highways.gov.sk.ca,

More information

THE TRANSITION FROM OPEN PIT TO UNDERGROUND MINING: AN UNUSUAL SLOPE FAILURE MECHANISM AT PALABORA

THE TRANSITION FROM OPEN PIT TO UNDERGROUND MINING: AN UNUSUAL SLOPE FAILURE MECHANISM AT PALABORA THE TRANSITION FROM OPEN PIT TO UNDERGROUND MINING: AN UNUSUAL SLOPE FAILURE MECHANISM AT PALABORA Richard K. Brummer*, Hao Li* & Allan Moss *Itasca Consulting Canada Inc., Rio Tinto Limited ABSTRACT At

More information

Project Layout & Design Features of the Project

Project Layout & Design Features of the Project Project Layout & Design Features of the Project 1 PROJECT LAYOUT DRI DAM DRI DAM TOE P/H U/G POWER HOUSE COMPLEX DRI DAM TOE POWER HOUSE TANGON DAM TOE POWER HOUSE TOTAL 3070 MW 19.60 MW 7.40 MW 3097 MW

More information

HOMEOWNER S GUIDE. to LANDSLIDES. and MITIGATION RECOGNITION, PREVENTION, CONTROL, Compiled by Dr. Scott F. Burns Tessa M. Harden Carin J.

HOMEOWNER S GUIDE. to LANDSLIDES. and MITIGATION RECOGNITION, PREVENTION, CONTROL, Compiled by Dr. Scott F. Burns Tessa M. Harden Carin J. HOMEOWNER S GUIDE to LANDSLIDES RECOGNITION, PREVENTION, CONTROL, and MITIGATION Compiled by Dr. Scott F. Burns Tessa M. Harden Carin J. Andrew Federal Emergency Management Agency Region 10 If you are

More information

Flood mitigation program for Gatun lake. Programa de mitigación de inundaciones del lago Gatún

Flood mitigation program for Gatun lake. Programa de mitigación de inundaciones del lago Gatún Flood mitigation program for Gatun lake Programa de mitigación de inundaciones del lago Gatún Moffatt & Nichol Engineers 10 de febrero de 2005 Contrato No. 126161 Introducción y Recomendaciones 1 INTRODUCTION

More information

Introduction to Architecture. Lesson 13: Hoover Dam

Introduction to Architecture. Lesson 13: Hoover Dam Introduction to Architecture Lesson 13: Hoover Dam Back in 2010, my family and I flew to California and then drove to the Grand Canyon via the Hoover Dam. Named after President Herbert Hoover, the Hoover

More information

Plan Plus Volume 1 No 1 2002 (117-123)

Plan Plus Volume 1 No 1 2002 (117-123) Plan Plus Volume 1 No 1 2002 (117-123) APPLICATION OF GIS (GEOGRAPHIC INFORMATION SYSTEM) FOR LANDSLIDE HAZARD ZONATION AND MAPPING DISASTER PRONE AREA: A STUDY OF KULEKHANI WATERSHED, NEPAL Purna Chandra

More information

Appendix B. Introduction to Landslide Evaluation Tools Mapping, Remote Sensing, and Monitoring of Landslides

Appendix B. Introduction to Landslide Evaluation Tools Mapping, Remote Sensing, and Monitoring of Landslides Appendix B. Introduction to Landslide Evaluation Tools Mapping, Remote Sensing, and Monitoring of Landslides 66 The Landslide Handbook A Guide to Understanding Landslides Part 1. Mapping Maps are a useful

More information

Jackson Gulch Outlet Canal Rehabilitation Project

Jackson Gulch Outlet Canal Rehabilitation Project Jackson Gulch Outlet Canal Rehabilitation Project Preliminary Budgetary Estimate for Rehabilitation February 2004 Prepared for the Mancos Water Conservancy District Jackson Gulch Reservoir 42888 County

More information

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1 6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT

More information

US Army Corps of Engineers BUILDING STRONG

US Army Corps of Engineers BUILDING STRONG Fort Worth District Public Meeting 20 August 2013 US Army Corps of Engineers Lewisville Dam - Authorization Authorized by the River and Harbor Act, approved 2 March 1945 (Public Law 14, 79th Congress,

More information

NOTE. Note on the pumped storage potential of the Onslow-Manorburn depression, New Zealand

NOTE. Note on the pumped storage potential of the Onslow-Manorburn depression, New Zealand Journal of Hydrology (NZ) 44 (2): 131-135, 2005 New Zealand Hydrological Society (2005) NOTE Note on the pumped storage potential of the Onslow-Manorburn depression, New Zealand W. E. Bardsley Department

More information

Columbia River Project Water Use Plan. Monitoring Program Terms of Reference LOWER COLUMBIA RIVER FISH MANAGEMENT PLAN

Columbia River Project Water Use Plan. Monitoring Program Terms of Reference LOWER COLUMBIA RIVER FISH MANAGEMENT PLAN Columbia River Project Water Use Plan LOWER COLUMBIA RIVER FISH MANAGEMENT PLAN CLBMON-45 Lower Columbia River Fish Indexing Surveys 31 August 2007 1.0 OVERVIEW LOWER COLUMBIA RIVER FISH MANAGEMENT PLAN

More information

Walter Andreeff, BSc. Applied and Environmental Geology

Walter Andreeff, BSc. Applied and Environmental Geology The Peace River Environmental Society www.peaceriverenvironmentalsociety.org Apri1 4, 2013 Ms. Linda Jones, Panel Manager Review Panels Canadian Environmental Assessment Agency 22 nd. Floor, 160 Elgin

More information

FAILURE OF TETON DAM

FAILURE OF TETON DAM BACKGROUND ON FAILURE OF TETON DAM Near Rexburg, Idaho June 5, 1976 J. David Rogers, Ph.D., P.E., R.G. Karl F. Hasselmann Chair in Geological Engineering Department of Geological Sciences & Engineering

More information

Seismic Design and Performance Criteria for Large Storage Dams

Seismic Design and Performance Criteria for Large Storage Dams Seismic Design and Performance Criteria for Large Storage Dams Dr. Martin Wieland Chairman, ICOLD Committee on Seismic Aspects of Dam Design Poyry Switzerland Ltd., Zurich, Switzerland Integral Dam Safety

More information

SITE C CLEAN ENERGY PROJECT: BUSINESS CASE SUMMARY

SITE C CLEAN ENERGY PROJECT: BUSINESS CASE SUMMARY SITE C CLEAN ENERGY PROJECT: BUSINESS CASE SUMMARY UPDATED MAY 2014 A HERITAGE BUILT FOR GENERATIONS Clean, abundant electricity has been key to British Columbia s economic prosperity and quality of life

More information

Dam Safety Guidelines Ministry of Environment, Lands and Parks Water Management Branch Inspection & Maintenance of Dams ii Canadian Cataloguing in Publication Data BC Environment. Water Management Branch.

More information

Columbia River Project Water Use Plan. Monitoring Program Terms of Reference

Columbia River Project Water Use Plan. Monitoring Program Terms of Reference Columbia River Project Water Use Plan Revelstoke Flow Management Plan Monitoring Program Terms of Reference CLBMON-15a Middle Columbia River Physical Habitat Monitoring Revision January 29, 2015 Monitoring

More information

Assessment. Ian Uglow Technical Director, SLR Consulting iuglow@slrconsulting.com. 7 th October 2010

Assessment. Ian Uglow Technical Director, SLR Consulting iuglow@slrconsulting.com. 7 th October 2010 Peat Stability Risk and Hazard Assessment Ian Uglow Technical Director, SLR Consulting iuglow@slrconsulting.com 7 th October 2010 What goes into a Peat Stability Risk Assessment? You will need: An understanding

More information

Small Dam Hazard Assessment Inventory

Small Dam Hazard Assessment Inventory Small Dam Hazard Assessment Inventory What would happen if your dam were to fail? This is a question that most dam owners hope they will never have to answer. However it is a question you, as a responsible

More information

How To Fix A Creek In Sandon

How To Fix A Creek In Sandon Valhalla Wilderness Society Box 329, New Denver, British Columbia, Canada V0G 1S0 Phone: (250) 358-2333, Fax: (250) 358-7950, E-mail: vws@vws.org, Web: http://www.vws.org Robyn Roome Regional Director,

More information

GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES. Materials Engineering Report No. 2009-8M (Supersedes Report No.

GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES. Materials Engineering Report No. 2009-8M (Supersedes Report No. GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES Materials Engineering Report No. 2009-8M (Supersedes Report No. 21) F CHOWDHURY GEOMECHANICS AND STRUCTURAL MATERIALS ENGINEER S REHMAN GEOTECHNICAL

More information

NZSOLD Reconnaissance Report. Taiwan Dams March 2000

NZSOLD Reconnaissance Report. Taiwan Dams March 2000 NZSOLD Reconnaissance Report Taiwan Dams March 2000 Peter Foster Opus International Consultants Grant Campbell Contact Energy Ltd Introduction On 21 September 1999, a magnitude M w 7.6 earthquake occurred

More information

6.0 Results of Risk Analyses

6.0 Results of Risk Analyses 6. Results of Risk Analyses A risk analysis of the optimized embankment designs for the Salton Sea restoration project was conducted jointly by Kleinfelder and representatives from Reclamation. A risk

More information

MANITOBA FLOOD PROTECTION PROJECTS Project Justification and Benefits. Science Imagination Collaboration

MANITOBA FLOOD PROTECTION PROJECTS Project Justification and Benefits. Science Imagination Collaboration MANITOBA FLOOD PROTECTION PROJECTS Project Justification and Benefits Science Imagination Collaboration Presentation Outline Extreme events on Red and Assiniboine Manitoba Flood Protection Works KGS Group

More information

Peace River Project Water Use Plan

Peace River Project Water Use Plan Peace River Project Water Use Plan Boat Ramp Hudsons Hope Reference: GMSWORKS-51 Dinosaur Boat Ramp Replacement Project Study Period: Sep 4, 2012 Jun 28, 2013 Christine Boehringer, MBA, PMP Project Manager

More information

Earthquakes. Earthquakes: Big Ideas. Earthquakes

Earthquakes. Earthquakes: Big Ideas. Earthquakes Earthquakes Earthquakes: Big Ideas Humans cannot eliminate natural hazards but can engage in activities that reduce their impacts by identifying high-risk locations, improving construction methods, and

More information

Landslide Hazard Zonation Mapping Using GIS

Landslide Hazard Zonation Mapping Using GIS 1 Weerasinghe K. M. 1 Landslide Hazard Zonation Mapping Using GIS Abstract: The central highlands of Sri Lanka comprising 20% of the total land area of the country is often threatened by landslides. The

More information

Thin Air and Thick Ice Unusual Challenges at a High Elevation Hydro Plant

Thin Air and Thick Ice Unusual Challenges at a High Elevation Hydro Plant Thin Air and Thick Ice Unusual Challenges at a High Elevation Hydro Plant By Ginger Gillin, John Pizzimenti, and Doug Foss, GEI Consultants, Inc., USA, and Jon Jourdonnais, PPL Montana, USA. Abstract The

More information

Outlet stabilization structure

Outlet stabilization structure Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural

More information

Welcome to our open house. Thanks for coming. Please sign in and help yourself to refreshments. Energizing your community. www.fortisbc.

Welcome to our open house. Thanks for coming. Please sign in and help yourself to refreshments. Energizing your community. www.fortisbc. Welcome to our open house Thanks for coming Please sign in and help yourself to refreshments Integrated System Plan (ISP) Looks ahead 20 years to identify the energy and infrastructure needs of our customers

More information

Small Dam Repair The Stone Lake Dam Story. Joe Barron, P.E. SynTerra formerly the Fletcher Group, Inc. 148 River St. Suite 220 Greenville, S.C.

Small Dam Repair The Stone Lake Dam Story. Joe Barron, P.E. SynTerra formerly the Fletcher Group, Inc. 148 River St. Suite 220 Greenville, S.C. Small Dam Repair The Stone Lake Dam Story Joe Barron, P.E. SynTerra formerly the Fletcher Group, Inc. 148 River St. Suite 220 Greenville, S.C. 29601 1 Historical background of Stone Lake A series of three

More information

Siting Geologic Sequestration Projects for Commercial Power Plants

Siting Geologic Sequestration Projects for Commercial Power Plants Siting Geologic Sequestration Projects for Commercial Power Plants B. Peter McGrail Laboratory Fellow Pacific Northwest National Laboratory Richland, Washington Axioms There is no mainstream process for

More information

1 Mobilisation and demobilisation 1 Deep boring sum 2 Cone penetration tests sum 3 Miscellenous tests sum

1 Mobilisation and demobilisation 1 Deep boring sum 2 Cone penetration tests sum 3 Miscellenous tests sum Malaysian Civil Engineering Standard Method of Measurement (MyCESMM) CLASS D: SITE INVESTIGATION WORK Measurement covered under other classes: Excavation not carried out for the purpose of soil investigation

More information

Nuevas tendencias de la Minería Subterránea profunda Planeación, operación y estabilización del macizo rocoso

Nuevas tendencias de la Minería Subterránea profunda Planeación, operación y estabilización del macizo rocoso Nuevas tendencias de la Minería Subterránea profunda Planeación, operación y estabilización del macizo rocoso By Ernesto Villaescusa, PhD Chair in Rock Mechanics WA School of Mines, CRC Mining & Curtin

More information

STAFF REPORT TO COMMITTEE OF THE WHOLE

STAFF REPORT TO COMMITTEE OF THE WHOLE STAFF REPORT TO COMMITTEE OF THE WHOLE DATE: November 7 2012 TO: FROM: SUBJECT: ATTACHMENT(S): COMMITTEE OF THE WHOLE GINA LAYTE-LISTON, SUPERVISOR, WASTEWATER Stormwater Management Funding Strategy None

More information

Source: Port Mann Bridge Plans Unveiled Today, CBC News, February 4, 2009.

Source: Port Mann Bridge Plans Unveiled Today, CBC News, February 4, 2009. Total project cost $2.5 billion (Canadian) Financed by tolls about $3 each direction. Total project length 37 km (McGill St in Vancouver to 216 th in Langley) The new Port Mann bridge 10 lanes (existing

More information

Module 7 (Lecture 24 to 28) RETAINING WALLS

Module 7 (Lecture 24 to 28) RETAINING WALLS Module 7 (Lecture 24 to 28) RETAINING WALLS Topics 24.1 INTRODUCTION 24.2 GRAVITY AND CANTILEVER WALLS 24.3 PROPORTIONING RETAINING WALLS 24.4 APPLICATION OF LATERAL EARTH PRESSURE THEORIES TO DESIGN 24.5

More information

Table 4.9 Storm Drain Inlet Protetion Applicable for

Table 4.9 Storm Drain Inlet Protetion Applicable for BMP C220: Storm Drain Inlet Protection Purpose To prevent coarse sediment from entering drainage systems prior to permanent stabilization of the disturbed area. Conditions of Use Type of Inlet Protection

More information

Preventing Basement Flooding Through Early Site Evaluation

Preventing Basement Flooding Through Early Site Evaluation Preventing Basement Flooding Through Early Site Evaluation Perry Lindquist Land Resources Manager Waukesha County Dept. of Parks & Land Use July 22, 2015 Waukesha County Land Use Planners meeting Presentation

More information

Lecture 12 Earthquake Magnitude

Lecture 12 Earthquake Magnitude Lecture 12 Earthquake Magnitude Locating Earthquakes Last time, we learned that we could obtain a rough estimate of the distance in miles to an earthquake epicenter by multiplying the S - P time interval

More information

CLIFTY CREEK PLANT MADISON, INDIANA

CLIFTY CREEK PLANT MADISON, INDIANA 2015 DAM AND DIKE INSPECTION REPORT GERS-15-018 CLIFTY CREEK PLANT MADISON, INDIANA PREPARED BY GEOTECHNICAL ENGINEERING AEP SERVICE CORPORATION 1 RIVERSIDE PLAZA COLUMBUS, OHIO Annual Dam and Dike Inspection

More information

NEWS RELEASE. Government takes action on Chief Inspector of Mines recommendations

NEWS RELEASE. Government takes action on Chief Inspector of Mines recommendations For Immediate Release 2015MEM0030-002119 Dec. 17, 2015 NEWS RELEASE Government takes action on Chief Inspector of Mines recommendations VICTORIA In response to the findings and recommendations of the Chief

More information

Types of flood risk. What is flash flooding? 3/16/2010. GG22A: GEOSPHERE & HYDROSPHERE Hydrology. Main types of climatically influenced flooding:

Types of flood risk. What is flash flooding? 3/16/2010. GG22A: GEOSPHERE & HYDROSPHERE Hydrology. Main types of climatically influenced flooding: GG22A: GEOSPHERE & HYDROSPHERE Hydrology Types of flood risk Main types of climatically influenced flooding: 1. Flash (rapid-onset) 2. Lowland (slow-rise) 3. Coastal (not covered here) But! Causal factors

More information

SOUTH AFRICAN NATIONAL INSTITUTE OF ROCK MECHANICS CHAMBER OF MINES OF SOUTH AFRICA CERTIFICATE IN ROCK MECHANICS PART 4

SOUTH AFRICAN NATIONAL INSTITUTE OF ROCK MECHANICS CHAMBER OF MINES OF SOUTH AFRICA CERTIFICATE IN ROCK MECHANICS PART 4 SOUTH AFRICAN NATIONAL INSTITUTE OF ROCK MECHANICS CHAMBER OF MINES OF SOUTH AFRICA CERTIFICATE IN ROCK MECHANICS PART 4 ROCK MECHANICS PRACTICAL (SURFACE AND UNDERGROUND) SYLLABUS PREAMBLE... 5 TOPIC

More information

What is geotechnical risk?

What is geotechnical risk? 1 MANAGING GEOTECHNICAL RISK Dr David Cathie, Cathie Associates What is geotechnical risk? The saying "ignorance is bliss" applies well to geotechnical problems. Out of sight, out of mind often applies

More information

Flash Flood Science. Chapter 2. What Is in This Chapter? Flash Flood Processes

Flash Flood Science. Chapter 2. What Is in This Chapter? Flash Flood Processes Chapter 2 Flash Flood Science A flash flood is generally defined as a rapid onset flood of short duration with a relatively high peak discharge (World Meteorological Organization). The American Meteorological

More information

Safety of Small/Rural Dams and Barrier Lake Management

Safety of Small/Rural Dams and Barrier Lake Management Safety of Small/Rural Dams and Barrier Lake Management A. Introduction 1. Lessons learnt and recommendations are provided for artificial dams and barrier lakes. In the case of artificial dams, emphasis

More information

Proceedings 2005 Rapid Excavation & Tunneling Conference, Seattle

Proceedings 2005 Rapid Excavation & Tunneling Conference, Seattle Proceedings 2005 Rapid Excavation & Tunneling Conference, Seattle EPB-TBM Face Support Control in the Metro do Porto Project, Portugal S. Babendererde, Babendererde Engineers LLC, Kent, WA; E. Hoek, Vancouver,

More information

SEISMIC MICROZONATION ASSESSMENT AND MAPPING FOR LAND- USE PLANNING: DATA AVAILABILITY, SURVEY RESULTS AND REVISED DATA MODEL

SEISMIC MICROZONATION ASSESSMENT AND MAPPING FOR LAND- USE PLANNING: DATA AVAILABILITY, SURVEY RESULTS AND REVISED DATA MODEL SEISMIC MICROZONATION ASSESSMENT AND MAPPING FOR LAND- USE PLANNING: DATA AVAILABILITY, SURVEY RESULTS AND REVISED DATA MODEL Bryan D. Watts S.W. Hollingshead Klohn-Crippen Consultants Ltd. INTRODUCTION

More information

FERC Engineering Guidelines Risk-Informed Decision Making

FERC Engineering Guidelines Risk-Informed Decision Making FERC Engineering Guidelines Risk-Informed Decision Making Chapter R1 Introduction to Risk-Informed Decision Making Chapter R1, Risk-Informed Decision Making Table of Contents Chapter R1 Introduction to

More information

Hot tpot tproject A Demonstration of How Groundwater Chemistry is being Used to Discover a Gravel Covered Gold Deposit

Hot tpot tproject A Demonstration of How Groundwater Chemistry is being Used to Discover a Gravel Covered Gold Deposit Hot tpot tproject A Demonstration of How Groundwater Chemistry is being Used to Discover a Gravel Covered Gold Deposit April 2, 2009 General Cautionary Statement Warning! The business of Gold Exploration

More information

Sä Dena Hes Tailings Management Facility Decommissioning Design Report

Sä Dena Hes Tailings Management Facility Decommissioning Design Report Sä Dena Hes Tailings Management Facility Decommissioning Design Report Prepared for Teck Resources Limited Prepared by SRK Consulting (Canada) Inc. 1CT008.035 March 2014 Sä Dena Hes Tailings Management

More information

PIPELINE ROUTES - GROUND MOTION MONITORING USING OTDR

PIPELINE ROUTES - GROUND MOTION MONITORING USING OTDR PIPELINE ROUTES - GROUND MOTION MONITORING USING OTDR OTDR (optical time domain reflectometry) appears to be particularly applicable to monitoring ground motion along pipeline routes. Pipelines are a very

More information

How To Check For Scour At A Bridge

How To Check For Scour At A Bridge Case Studies Bridge Scour Inspection and Repair Edward P. Foltyn, P.E. Senior Hydraulic Engineer ODOT Bridge Unit 2013 PNW Bridge Inspectors Conference April 2013 REFERENCES Stream Stability at Highway

More information

Sub-sea tunnels and lake taps in Norway - a short overview

Sub-sea tunnels and lake taps in Norway - a short overview Reference: www.rockmass.net Sub-sea tunnels and lake taps in Norway - a short overview Arild Palmström, Ph.D. (May 2002) Sub-sea tunnels are those tunnels, which pass beneath the sea or a lake bottom;

More information

Web of Water. Teacher s Guide Webisode 1 Blue Ridge

Web of Water. Teacher s Guide Webisode 1 Blue Ridge Web of Water Teacher s Guide Webisode 1 Blue Ridge Table of Contents About Blue Ridge.... 3 South Carolina Science Standards.. 4 Discussion Questions.. 10 Knowitall Resources....... 13 Credits..... 14

More information

ources of Drinking Water

ources of Drinking Water The drop on water Sources of Drinking Water Did you know that 40 per cent of Nova Scotians get their water privately from a drilled well, a dug well, or a surface water source? The other 60 per cent rely

More information

USSD Workshop on Dam Break Analysis Applied to Tailings Dams

USSD Workshop on Dam Break Analysis Applied to Tailings Dams USSD Workshop on Dam Break Analysis Applied to Tailings Dams Antecedents Newtonian / non-newtonian flows Available models that allow the simulation of non- Newtonian flows (tailings) Other models used

More information

Ground Water in the Piedmont and Blue Ridge Provinces of North Carolina

Ground Water in the Piedmont and Blue Ridge Provinces of North Carolina Ground Water in the Piedmont and Blue Ridge Provinces of North Carolina Prepared by: R.L. Huffman Extension Agricultural Engineering Specialist Published by: North Carolina Cooperative Extension Service

More information

Dams and Extreme Events Reducing Risk of Aging Infrastructure under Extreme Loading Conditions

Dams and Extreme Events Reducing Risk of Aging Infrastructure under Extreme Loading Conditions Dams and Extreme Events Reducing Risk of Aging Infrastructure under Extreme Loading Conditions 34th Annual USSD Conference San Francisco, California, April 7-11, 2014 Hosted by San Francisco Public Utilities

More information

Numerical Modelling for Shallow Tunnels in Weak Rock By Evert Hoek Unpublished Notes

Numerical Modelling for Shallow Tunnels in Weak Rock By Evert Hoek Unpublished Notes Numerical Modelling for Shallow Tunnels in Weak Rock By Evert Hoek Unpublished Notes Introduction When designing a shallow tunnel in a poor quality rock mass, the designer has to face a number of problems

More information

GEOLOGIC MAPS. PURPOSE: To be able to understand, visualize, and analyze geologic maps

GEOLOGIC MAPS. PURPOSE: To be able to understand, visualize, and analyze geologic maps GEOLOGIC MAPS PURPOSE: To be able to understand, visualize, and analyze geologic maps Geologic maps show the distribution of the various igneous, sedimentary, and metamorphic rocks at Earth s surface in

More information

Advances in Slope Instrumentation: TDR and Remote Data Acquisition Systems

Advances in Slope Instrumentation: TDR and Remote Data Acquisition Systems Advances in Slope Instrumentation: TDR and Remote Data Acquisition Systems Presented at: 5 th International Symposium on Field Measurements in Geomechanics Singapore December 1-3, 1999 Kane GeoTech, Inc.

More information

Stability Assessment of Chamshir Dam Based on DEM, South West Zagros

Stability Assessment of Chamshir Dam Based on DEM, South West Zagros 2015 2nd International Conference on Geological and Civil Engineering IPCBEE vol. 80 (2015) (2015) IACSIT Press, Singapore DOI: 10.7763/IPCBEE. 2015. V80. 13 Stability Assessment of Chamshir Dam Based

More information

USACE Dam Safety Program Current Approach & Methodology

USACE Dam Safety Program Current Approach & Methodology USACE Dam Safety Program Current Approach & Methodology Siamac Vaghar, PE, MASCE Chief, Geotechnical Engineering Section Dam Safety Program Manager US Army Corps of Engineers New England District Corps

More information

Earth Science. River Systems and Landforms GEOGRAPHY 1710. The Hydrologic Cycle. Introduction. Running Water. Chapter 14.

Earth Science. River Systems and Landforms GEOGRAPHY 1710. The Hydrologic Cycle. Introduction. Running Water. Chapter 14. Earth Science GEOGRAPHY 1710 River Systems and Landforms DAVID R. SALLEE Robert W. Christopherson Charlie Thomsen Chapter 14 Introduction Rivers and streams are dynamic systems that continually adjust

More information

Analysis of the Interstate 10 Twin Bridge s Collapse During Hurricane Katrina

Analysis of the Interstate 10 Twin Bridge s Collapse During Hurricane Katrina Analysis of the Interstate 0 Twin Bridge s Collapse During Hurricane Katrina By Genda Chen, Emitt C. Witt III, David Hoffman, Ronaldo Luna, and Adam Sevi The Interstate 0 Twin Span Bridge over Lake Pontchartrain

More information

Guidelines for the Estimation and Reporting of Australian Black Coal Resources and Reserves

Guidelines for the Estimation and Reporting of Australian Black Coal Resources and Reserves Guidelines for the Estimation and Reporting of Australian Black Coal Resources and Reserves 2001 Edition (as referred to in the Joint Ore Reserves Committee Code ( The JORC Code ) 1999 edition) Prepared

More information

ENVIRONMENTAL MITIGATION AT HYDROELECTRIC PROJECTS Volume 1. Current Practices for Instream Flow Needs, Dissolved Oxygen, and Fish Passage

ENVIRONMENTAL MITIGATION AT HYDROELECTRIC PROJECTS Volume 1. Current Practices for Instream Flow Needs, Dissolved Oxygen, and Fish Passage DOEIID-10360 Distribution Category: UC-22S ENVIRONMENTAL MITIGATION AT HYDROELECTRIC PROJECTS Volume 1. Current Practices for Instream Flow Needs, Dissolved Oxygen, and Fish Passage M. J. Sale G. F. Cada

More information

Page 1 GCP-2014-00168

Page 1 GCP-2014-00168 Page 1 Page 2 Page 3 Page 4 Page 5 Page 6 Page 7 Page 8 For Immediate Release 2014PREM0128-001896 December 16, 2014 NEWS RELEASE Office of the Premier Ministry of Energy and Mines and Responsible for Core

More information

CIVL451. Soil Exploration and Characterization

CIVL451. Soil Exploration and Characterization CIVL451 Soil Exploration and Characterization 1 Definition The process of determining the layers of natural soil deposits that will underlie a proposed structure and their physical properties is generally

More information

General Insurance - Domestic Insurance - Home Contents Storm water damage policy exclusion flood damage

General Insurance - Domestic Insurance - Home Contents Storm water damage policy exclusion flood damage Determination Case number: 227307 General Insurance - Domestic Insurance - Home Contents Storm water damage policy exclusion flood damage 4 April 2011 Background 1. The Applicants insured their home contents

More information

Tunnelling and underground works in PPC hydro projects: Contracting practices & construction management Ioannis Thanopoulos Dr.

Tunnelling and underground works in PPC hydro projects: Contracting practices & construction management Ioannis Thanopoulos Dr. Tunnelling and underground works in PPC hydro projects: Contracting practices & construction management Ioannis Thanopoulos Dr. Civil Engineer Public Power Corporation, Greece Public Power Corporation

More information

Exploration. Exploration methods

Exploration. Exploration methods Exploration Activities related to establishing a mineral deposit through geological, geophysical and geochemical methods. It is preceded by Prospecting and followed by Planning & Development. Geological

More information

BEFORE THE HEARING EXAMINER FOR THURSTON COUNTY

BEFORE THE HEARING EXAMINER FOR THURSTON COUNTY BEFORE THE HEARING EXAMINER FOR THURSTON COUNTY In the Matter of the Application of ) NO. SSDP 000748 ) Kevin Robinson ) FINDINGS, CONCLUSIONS ) AND DECISION For a Shoreline Substantial Development ) Permit

More information

Alaska Energy Authority: Renewable Energy Fund and Susitna-Watana Hydro

Alaska Energy Authority: Renewable Energy Fund and Susitna-Watana Hydro Photo by: Cassandra Cerny, GVEA Alaska Energy Authority: Renewable Energy Fund and Susitna-Watana Hydro Sara Fisher-Goad, executive director Northwest Power Producers Association Oct. 29, 2015 2 Alaska

More information

Emergency Spillways (Sediment basins)

Emergency Spillways (Sediment basins) Emergency Spillways (Sediment basins) DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short-Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]

More information

Guidelines For Sealing Groundwater Wells

Guidelines For Sealing Groundwater Wells Guidelines For Sealing Groundwater Wells Government of Newfoundland and Labrador Department of Environment and Conservation Water Resources Management Division Government of Newfoundland and Labrador Department

More information

INTERPRETATION ADDENDUM CANADIAN MINING COMPANY INC. SUITE 2300-1066 WEST HASTINGS STREET VANCOUVER, BC V6E 3X2 3D INDUCED POLARIZATION

INTERPRETATION ADDENDUM CANADIAN MINING COMPANY INC. SUITE 2300-1066 WEST HASTINGS STREET VANCOUVER, BC V6E 3X2 3D INDUCED POLARIZATION INTERPRETATION ADDENDUM FOR CANADIAN MINING COMPANY INC. SUITE 2300-1066 WEST HASTINGS STREET VANCOUVER, BC V6E 3X2 3D INDUCED POLARIZATION ON THE SAN BERNARDO PROJECT EL GOCHICO GRID Approximate Location:

More information

Preventing Basement Flooding

Preventing Basement Flooding Preventing Basement Flooding Perry Lindquist Land Resources Manager Waukesha County Dept. of Parks & Land Use Waukesha County Storm Water Workshop April 10, 2013 Presentation Outline Background Case study

More information

Re: Preliminary Permit Application for the Rose Creek Pumped Storage Project

Re: Preliminary Permit Application for the Rose Creek Pumped Storage Project September 12, 2013 Kimberly D. Bose, Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: Preliminary Permit Application for the Dear Ms. Bose, Please find attached

More information

Chapter Overview. Bathymetry. Measuring Bathymetry. Echo Sounding Record. Measuring Bathymetry. CHAPTER 3 Marine Provinces

Chapter Overview. Bathymetry. Measuring Bathymetry. Echo Sounding Record. Measuring Bathymetry. CHAPTER 3 Marine Provinces Chapter Overview CHAPTER 3 Marine Provinces The study of bathymetry charts ocean depths and ocean floor topography. Echo sounding and satellites are efficient bathymetric tools. Most ocean floor features

More information

Chapter 7 Earthquake Hazards Practice Exam and Study Guide

Chapter 7 Earthquake Hazards Practice Exam and Study Guide Chapter 7 Earthquake Hazards Practice Exam and Study Guide 1. Select from the following list, all of the factors that affect the intensity of ground shaking. a. The magnitude of the earthquake b. Rather

More information

CLACKAMAS COUNTY ZONING AND DEVELOPMENT ORDINANCE

CLACKAMAS COUNTY ZONING AND DEVELOPMENT ORDINANCE 1008 STORM DRAINAGE (3/24/05) 1008.01 PURPOSE To minimize the amount of stormwater runoff resulting from development utilizing nonstructural controls where possible, maintain and improve water quality,

More information

Cloud seeding. Frequently Asked Questions. What are clouds and how are they formed? How do we know cloud seeding works in Tasmania?

Cloud seeding. Frequently Asked Questions. What are clouds and how are they formed? How do we know cloud seeding works in Tasmania? What are clouds and how are they formed? Clouds are composed of water droplets and sometimes ice crystals. Clouds form when air that is rich in moisture near the Earth s surface rises higher into the atmosphere,

More information

World Tower. Company, Inc. Classification Overview. Categories: Structure Classification Exposure Categories Topographic Effects Geological

World Tower. Company, Inc. Classification Overview. Categories: Structure Classification Exposure Categories Topographic Effects Geological Manufacturing Custom Fabricated Structures since 1979 Professional In-House Design Staff Tower Delivery Service World Tower Company, Inc. Classification Overview Categories: Structure Classification Exposure

More information

PRECIPITATION AND EVAPORATION

PRECIPITATION AND EVAPORATION PRECIPITATION AND EVAPORATION OBJECTIVES Use historical data to analyze relationships between precipitation, evaporation and stream flow in the San Antonio River Basin TOPICS Water cycle Precipitation

More information

Volcanoes Erupt Grade 6

Volcanoes Erupt Grade 6 TEACHING LEARNING COLLABORATIVE (TLC) EARTH SCIENCE Volcanoes Erupt Grade 6 Created by: Debra McKey (Mountain Vista Middle School); Valerie Duncan (Upper Lake Middle School); and Lynn Chick (Coyote Valley

More information

REAL-TIME MONITORING AND EARLY WARNING OF LANDSLIDES AT RELOCATED WUSHAN TOWN, THE THREE GORGE RESERVOIR, CHINA

REAL-TIME MONITORING AND EARLY WARNING OF LANDSLIDES AT RELOCATED WUSHAN TOWN, THE THREE GORGE RESERVOIR, CHINA J. SE Asian Appl. Geol., Sep Dec 2010, Vol. 2(3), pp. 170 184 REAL-TIME MONITORING AND EARLY WARNING OF LANDSLIDES AT RELOCATED WUSHAN TOWN, THE THREE GORGE RESERVOIR, CHINA Y. Yueping 1, H. Wang 2, Y.

More information