Theory of Constraints Project Management
|
|
|
- Philip Carpenter
- 10 years ago
- Views:
Transcription
1 Theory of Constraints Project Management A Brief Introduction into the Basics Authored by Dee Bradbury Jacob Partner The Goldratt Institute William T. McClelland, Jr. Partner The Goldratt Institute Copyright The Goldratt Institute, All rights reserved. This work may be reproduced or used in any form or by any means only for non-commercial purposes and with the written permission of The Avraham Y. Goldratt Institute. Powerful Solutions Start with the Right Questions Page 1
2 TABLE OF CONTENTS. INTRODUCTION.. 3 THE MAIN ROOTS.. 4 IDENTIFYING WHAT TO CHANGE? THE SOLUTION FOR THE MAIN ROOTS... 5 IDENTIFYING TO WHAT TO CHANGE TO? PUTTING THE SOLUTION INTO PLACE.. 11 IDENTIFYING HOW TO CAUSE THE CHANGE? Powerful Solutions Start with the Right Questions Page 2
3 When one thinks of project environments, they mainly think of construction, engineering, technology development, and telecommunications. But, more than ever non-traditional project environments expect their managers to be capable of managing projects and programs. Why? Execution the ability to execute to plan - is essential to creating competitive advantage. More than ever, to execute to plan is to properly manage the TIME value of money and resources. In many for-cause organizations, the key to continued support of its benefactors is the stewardship of funds leading to the successful completion of projects that are of enduring value to society. What are some of AGI s customers using TOC Project Management for? Design of Manufacturing Systems Internal SAP implementation Maintenance, Repair and Overhaul (MRO) New product development Pipeline Management Production and Assembly Program Management Strategic Planning INTRODUCTION. Whether your organization manages stand-alone or multiple projects, whether those projects are small or large, whether your customers are internal or external, or whether the nature of the work performed is product development, construction, design, IT, or service; most projects are difficult to manage because of two things: 1) They involve uncertainty, and 2) They involve three different and opposing commitments: Due date, budget, and content In organizations that attempt to manage multiple concurrent projects with common, shared resources, the job is even more challenging. Managers can quickly find themselves on project overload with continual resource shortages and great difficulty in determining which tasks are truly the most important. If this is beginning to sound familiar, then you are probably experiencing some of these problems in your organization: There are difficulties completing projects on time, within budget and with full content. There is too much rework activity. Promised lead times are longer than desired. Existing project work is not complete before new projects require a shifting in priorities. Project Managers and Resource Managers have frequent conflicts about priorities and resource commitments. Existing project work is not complete before new projects require a shifting in priorities. Problems in one project cascade into problems in other projects. Some projects are abandoned or completed without the organization gaining the promised benefit. The organization is too slow responding to important opportunities. This paper provides a brief introduction into the basics of TOC Project Management, showing how the solution addresses the underlying root causes of the problems listed above. It is organized in the context of answering three very important questions: 1. What To Change? 2. To What To Change? 3. How To Cause The Change? Powerful Solutions Start with the Right Questions Page 3
4 What types of organizations have completed AGI s TOC Project Management Expert Program? Aerospace Automotive Consulting Construction Defense High-Tech Manufacturing Metals & Mining Semiconductor Telecommunications Universities and Colleges THE MAIN ROOTS IDENTIFYING WHAT TO CHANGE? In order to make significant and lasting improvements in the way projects are managed, an organization must effectively address the underlying root causes that lead to the above problems. The dominant root cause in organizations performing multiple projects with shared resources is the unavoidable conflict about when to begin new project work. In almost every organization, there are continual internal and external pressures to address important new opportunities. At the same time, managers recognize that beginning new work too soon may divert needed resources from ongoing project work, compromising their ability to meet existing commitments. Unfortunately, with imperfect knowledge of the true status of current project work, ongoing pressures to increase the organization s output, and a belief that delaying a project s start will only serve to delay it s finish, managers all too frequently make decisions that overload the organization. The root cause that dominates the execution of individual projects is a planning and scheduling process that is based on several erroneous assumptions. One such assumption is the widespread belief that placing protection time in every task will lead to optimized project performance that good individual task performance will inherently lead to good overall project performance. Couple this with the fact that today s most widely used scheduling algorithms don t provide proper protection for the effects of integrating pathways (many parallel paths of work, all of which must be completed before a common successor task may begin), don t correctly address resource dependencies, and don t properly account for task and iteration variability, and the stage is set for almost certain disaster (See Figure 1). These algorithms calculate overly optimistic schedules that will almost certainly throw the project into expensive firefighting once it is recognized that the commitment is in serious jeopardy. Rushed up-front planning aggravates this situation by missing out important task and resource dependencies. G B LG B LG Y R R M B LG B C Integrating Pathways Resource Dependency Figure 1. Today s widely used scheduling algorithms don t provide proper protection for the way in which projects are mapped. Powerful Solutions Start with the Right Questions Page 4
5 Ultimately, firefighting becomes rampant, most people become severely multi-tasked, and management institutes coping mechanisms for more and more tracking of individual task and budget performance - ultimately resulting in more overhead and adding even more protection time to task estimates in an attempt to guarantee that people s work will meet management s expectations. BEHAVIORAL REALITIES IN PROJECT ENVIRONMENTS ADDITIVE RULE: The commitments for duration and total cost of a project are based upon adding up the duration and cost of the individual tasks. PARKINSON s LAW: Work expands to fill its time. 3-MINUTE EGG RULE: It s not quality if it s finished before the time is up. STUDENT SYNDROME: Waiting to start a task due to more important work at hand. Under such circumstances, people begin to place a higher priority on self-preservation. Being measured on individual task performance, people realize that it is not in their best interest to report early finishes. They may feel it will compromise their future negotiations or they may worry about being blamed for problems in their work because they did not take all the time they were given. More than likely, the task completion criteria are also very vague and people even feel encouraged to work well beyond what is truly good enough. At the same time, since most people carry such heavy loads, just the knowledge that the protection time is there makes them believe it is possible to use some of that time to finish other, more time-critical work. The net result is that work that could have been turned in early is not and the project has little chance to take advantage of any positive variation. The effect of late tasks accumulates day-by-day while any potential for early task completion is almost completely masked. Unless these two major root causes are addressed effectively, there is little chance for any organization to make significant and lasting improvements in project management performance. In some engineering environments, a performance measurement baseline (PMB) is used to track technical performance in relationship to cost and schedule. Undistributed Budget is an element of the PMB. It is authorized work held at top level until it can be planned in detail. In these environments, Network Building is critical in establishing the PMB, and therefore the Contract Budget Base. By gaining any needed insight and detail upfront, this process helps identify and assess risk early on in the program. THE SOLUTION FOR THE MAIN ROOTS. IDENTIFYING TO WHAT TO CHANGE TO? The TOC Project Management provides a comprehensive solution to address these root causes and coping mechanisms. The solution includes 1) a robust planning process, 2) a more effective scheduling process, 3) a methodology for introducing work that actually leads to increased capacity, 4) execution processes that provide excellent project control, visibility and decision support, and 5) work behaviors that are more conducive to good project performance. TOC Project Management: Project Planning Project planning (called Network Building) begins with a combined meeting of project stakeholders to gain complete clarity on the intended objectives, deliverables, and success criteria of the project. This gets everyone on the same page at the earliest possible moment, identifies areas where more definition may be required, and typically prevents mid-project Powerful Solutions Start with the Right Questions Page 5
6 surprises and rework. This session also surfaces any constraints (boundary conditions) within which the project s objectives must be accomplished. Starting with the project deliverables, the project network is constructed backwards in time with the participation of the project manager and key content experts. The process identifies the important task, path, and resource dependencies. Each individual task is defined in terms of its completion criteria and the resources and skills that will be required to accomplish it. This results in the same clarity of path identification as working a maze from its ending point, back toward its start, while ensuring the project work itself is planned to deliver the complete, necessary scope. While constructing the project networks, the leader of the network building activity works with the content experts to define the minimum skills required for each task, identifying the few tasks that truly need limited, specialist skills versus the many tasks that can be accomplished by lesser skilled personnel. This aids the reduction of resource dependencies within the project, which can reduce project cycle time. It also helps to reserve the highest skilled personnel for where they are truly needed. Network Building differs from traditional planning by: Building precedence: Necessity vs. Flow Starting Point Checks for missing dependencies Capturing time estimates: Account for task and iteration variability Drive desired work behaviors Once the resources and required skills are defined, the network building team estimates the potential variability associated with each task and the potential iteration variability associated with specific sequences of tasks. Each task is characterized in terms of a highly probable time to complete and an aggressive, but possible time to complete. A similar process is followed for identifying iteration variability. The team estimates a highly probable number of iterations that may be required for the appropriate task sequences. They also estimate an aggressive but possible number of iterations. Both task and iteration variability estimates feed into the scheduling process defined below. In all, there are six independent safety nets in the TOC Project Management process of building project networks. People who follow the process rarely experience difficulties that can be traced back to faulty planning. In fact, the results of this process are frequently so dramatic that many users report this is the first time they have truly understood the work that needs to be done! TOC Project Management: Project Scheduling Upon completion of the network building process, the resulting network is used to determine the project schedule with a process commonly called Critical Chain Scheduling. Powerful Solutions Start with the Right Questions Page 6
7 Task, resource, and iteration dependencies are analyzed to determine the longest chain of work, called the Critical Chain. The process then separates what can be thought of as the fixed component of the work from the variable component of the work. The fixed component of each task (and each iteration sequence) is the aggressive but possible estimate. The variable component (also called safety ) is the difference between the aggressive but possible estimate and the corresponding highly probable estimate. This safety is then removed from each task location and aggregated with the safety from other tasks in the same chain of work. A portion of the aggregated safety is placed in strategic locations where it will serve to protect the project as a whole. These placements are called buffers. A Project Buffer, located between the end of the Critical Chain and the project s commitment date, protects the project from the effects of execution variability along the Critical Chain. Feeding Buffers, located every place a non-critical Chain task feeds a Critical Chain task, protect the Critical Chain from execution variability along the paths that feed it. A2-8 A4-5 B6-5 FEEDING BUFFER C2-8 E4-3 E2-8 C4-3 FB G2-8 FB G4-8 F6-3 PROJECT BUFFER LEGEND Project Critical Chain FB = Feeding Buffer Figure 2. A simple project to illustrate the placement of time buffers. The proper placement of safety protects project performance from the effects of task and path variability, and signals the start of work at the appropriate time. There are two places to protect: Due date - from variability within the longest path of dependent events Longest path - from variability of shorter paths that join it (integration) The mathematical properties of aggregation, combined with new ways of working (see below) on project tasks, lead to a reduction in the total amount of safety that is required much less than traditional methods would require to protect each task separately. This leads to shorter overall project duration and, in some cases, reduced project costs. The resulting Critical Chain schedule is both feasible and immunized. Feasible, in that resource contention is properly accounted for and immunized, in that safety is placed in strategic locations where it will protect the project as a whole. The insertion of buffers also staggers path starts, leading to clearer priorities for resources, a reduction in the tendency for significant bad multitasking, and a reduced potential for mistakes. Powerful Solutions Start with the Right Questions Page 7
8 TOC Project Management: Synchronized Project Work Introduction Some AGI customers that have applied TOC Project Management: Air Force Flight Test Center Air Force Operational Test & Evaluation Center (AFOTEC) Balfour Beatty BHP Copper CAE USA The Boeing Company EATON Corporation Eli Lilly and Company Fairchild Semiconductor F-22 System Program Office General Motors Corporation Herman Miller, Inc. Intel Israel Platform Networking Group Israeli Air Force Material Management Division Lockheed Martin-Aero LSI Logic Lucent Technologies Seagate Technology Shea Homes Smiths Industries TOC Project Management has a Budget Planning and Execution Process that compliments Critical Chain. It turns out that just the act of introducing project work that exceeds the organization s capacity will, in itself, lead to further capacity reductions because of increased bad-multitasking. Instead, TOC Project Management pre-selects a more heavily loaded resource to serve as a gate for work release. New project work will be scheduled to begin in an interval of time where its need for that resource (Synchronizer) can be accommodated. Projects must be scheduled and synchronized before a completion date can be committed. This way, commitments are made based on feasible, immunized schedules that are in alignment with the organization s true capacity to accomplish its work. Although it seems counter-intuitive to what many have come to believe over the years, the staggering of work introduction actually increases an organization s capacity and shortens overall project durations. More work can be accomplished in the same interval of time. TOC Project Management: Project Control and Impact Visibility Project Control is accomplished though Buffer Management, which is a process of managing the aggregated safety that was placed between the final task of the Critical Chain and the project completion date. Delays along the Critical Chain consume Project Buffer time. Early finishes add to the Project Buffer. Senior management typically watches Project (and Budget) Buffer performance versus progress along the Critical Chain. Functional (resource) managers assign resources to tasks, using the associated Project Buffer status to determine the relative urgency of the available tasks. Functional managers also use resource load profiles that highlight potential resource overloads early enough for effective and inexpensive resolution. Project managers monitor their project status using Project Buffer and Critical Chain status. A Planning Threshold initiates their planning and an Action Threshold calls those plans into implementation. Most TOC Project Management software tools provide powerful what-if capabilities to assist project managers in their efforts to determine what actions will help them to recover a project with a collapsing Project Buffer. Visibility to project status, visibility to current and future resource loading, and powerful what if analysis takes all the guesswork (and emotion) out of managing projects. Powerful Solutions Start with the Right Questions Page 8
9 Senior managers, project managers, and resource managers have a clear and factual basis from which to make their decisions. This leads to shorter, more effective meetings that result in decisions that are more beneficial to good project performance. Resource: Resource Histogram Current Task All Tasks & Projects Availability 8 EE Qtr3, 2002 Qtr4, 2002 Qtr1, 2003 Qtr2, July August September October November December January February March April M Units in Days Page [ 1, 1 ] of [ 1, 1 ] 0 Figure 3. An illustration of a Resource Load Profile. TOC Project Management: Appropriate Work Behaviors As discussed earlier, the coping mechanisms that managers put in place to deal with the variable nature of project work accomplish the exact opposite of what was intended safety is placed everywhere and then wasted by the behaviors that people must adopt to protect themselves. At the core of TOC Project Management is a work behavior called the Relay Runner work ethic. Briefly stated, this behavior calls for people to begin work as soon as they have been assigned to a task, to work continuously until the task s completion criteria have been met, and to provide immediate notification of that completion. The project network is based upon the aggressive but possible times, but people are held accountable only to the work behavior, not achieving the aggressive but possible task duration estimate. By its very definition, all concerned recognize that there is some probability that the aggressive but possible time can be beat, but also some probability that the time estimate cannot be met. Powerful Solutions Start with the Right Questions Page 9
10 In most overloaded, heavily multi-tasked work environments, people are frequently shifted back and forth between tasks as priorities change. That unavoidably results in a large number of tasks being idle for significant amounts of time, essentially queuing to be worked on. People utilization is very high, probably too high. Task utilization is low, definitely too low. Suppose, for example, a person is given a ten-day task to do one of the many they are expected to perform simultaneously. Every other day, they get pulled off that task to do other, more urgent task work. That means the ten-day task will take 19 days to complete 19 days of elapsed time to accommodate 10 days of touch time. If that task is on the longest path of the project, those 9 days of task idle time translate directly into a 9- day delay in project completion. The unfortunate thing is that, in many heavily multi-tasked work environments, overall task idle time is a depressingly large number. The focus of change is typically on the new work process, the new technology, or the new strategy rather than on the people who must implement change....we ignore the most important question of the three: How to cause the change? To make improvements, an organization must recognize the need for work behaviors to change and make it safe for people to resist unmerited requests for multi-tasking, to report early finishes, and to come forward to ask for help when they are stuck without fearing a lowered performance evaluation. This requires a significant shift in people s thinking at all levels of the organization but, properly executed, delivers dramatically improved results. TOC Project Management: Summary of Benefits TOC PROJECT MANAGEMENT SOLUTION ELEMENTS SYNCHRONIZATION MECHANISM Effectively handles the sequencing of committed and new projects PROJECT PLANNING - Identifies the effects of dependencies and errors from time estimates PROJECT SCHEDULING Minimizes errors of the Additive Rule and prevents releasing work too early RESOURCE BEHAVIOR Encourages reporting of Early Finishes, identifies goldplating, reinforces strict adherence to schedule and task PROJECT CONTROL and VISIBILITY - Focuses on overall project performance instead of task and milestone performance The network building process results in up-front agreement of all major stakeholders regarding important project objectives and deliverables; early identification of the key interdependencies that will dominate the project; clear task completion criteria; realistic resource needs; and a much more complete understanding of the project to be undertaken. The project scheduling process yields a feasible, immunized schedule centered on a Critical Chain of work that will dominate the project throughout execution - a shorter, better protected schedule that is able to absorb many known and unknown risks. This allows project mangers to focus on the critical few tasks, separated from the important many. The synchronization of a portfolio of projects around a more heavily loaded resource staggers competing concurrent project demands on all resources, aligning project work to the organization s true capacity to handle the work. This enables the organization to make realistic commitments that can be reliably met. Projects are Powerful Solutions Start with the Right Questions Page 10
11 The 6 Steps to Achieving Buy-In Step 1: Secure agreement on the problem to be solved. Step 2: Secure agreement on the direction of a solution. Step 3: Verify that the proposed solution will deliver the desired results. Step 4: Ensure that all significant potential negative side effects have been identified and prevented from happening. Step 5: Identify and address all significant potential obstacles that could block implementation of the solution. Step 6: Ensure that all the necessary leadership is committed to making the implementation successful. accomplished in less time starting later than they normally would using traditional methods yet finishing earlier. Managers also have a tool for assessing the impact of any major changes on the entire portfolio. The project control mechanisms such as Buffer Management provide a clear indication of the health of each project. This, in turn, provides a sound basis for prioritizing the tasks for resource assignment. For the first time, managers have a tool that allows them to always assign their people to the task work that will benefit the organization most. Because project managers are able to focus in the right places and quickly determine recovery plans, project management becomes more proactive and less reactive, with a dramatically increased ability to meet schedule, cost and scope commitments without crisis spending. The new work behaviors ensure high resource productivity, high task productivity, improved overall project performance and a much higher quality of work life. PUTTING THE SOLUTION INTO PLACE. IDENTIFYING HOW TO CAUSE THE CHANGE? For many organizations, projects are what we do for a living. Projects are their business. In such environments, changing how people manage projects is tantamount to changing the basic fabric of the business. Clearly, one must approach such change with great care. The right people must be brought into the picture at the right time, in just the right way. The process must move slowly enough to permit identification of essential changes, yet fast enough that it does not lose the momentum that is necessary to sustain continued progress. The Goldratt Institute has developed a very robust implementation process consisting of six distinct phases. Each phase builds upon the next and each is specifically designed around a logical progression of obtaining the true support and collaboration of the participants. In the first phase, senior management learns what changes are required and what their roles need to be in facilitating that change. In order for change to succeed, they need to be in consensus that they will continue to champion the change for the long term. Once they are aligned, management needs to inform the organization about what will change, why the change is necessary, how the organization and each of its people will benefit, and when and how they will be brought on board. Following the informational briefing, the hard work begins. Powerful Solutions Start with the Right Questions Page 11
12 There is a third phase, where previously trained experts begin to use the generic solution to identify areas where customization will be required to address the unique needs of the organization. In order to minimize disruption to the organization, only a few necessary people are brought into the activities of Phase three. During the fourth phase, the rest of the organization is brought into the picture. People are trained and begin to participate in their designated roles. This is also the phase where the readiness of all support systems is verified. TOC Project Management Solution For organizations and project managers who are working to improve their ability to continually meet the three seemingly illusive project commitments budget, time and content, the TOC Project Management Solution provides a comprehensive tool set that addresses: The nature of project planning Project scheduling Resource behavior Project visibility and control Multiple project synchronization The fifth phase is more of an event than a phase of significant time duration. It is analogous to throwing the switch to take the system live. This is the point at which TOC Project Management truly becomes the way we do our work. If everything has been done properly up to that point, much of the chaos has now been driven out of the organization, setting up the final stage. The sixth phase begins the process of ongoing improvement. A this stage, the organization has so much visibility to every aspect of its project management system that people can begin to systematically pinpoint and implement changes that will bring the most improvement to the bottom line. Market Demand-Pull SM AGI s TOC Supply Chain Management Solution For supply chain, plant operations and distribution managers who are dealing with the challenges of ensuring availability of the right products at the right place and time while maintaining profitable operations, the TOC Supply Chain Solution enables the organization to: Rapidly respond to actual market demand Improve on-time deliveries Reduce the need for overtime and expediting Better utilize capacity to meet customer expectations Market Demand-Pull SM is a service mark of The Goldratt Institute. For more information regarding the The Goldratt Institute s course offerings, products or services, please contact us at GOAL, or , or visit us at Copyright The Goldratt Institute, All rights reserved. The Goldratt Institute 442 Orange Street New Haven, Connecticut USA [email protected] Powerful Solutions Start with the Right Questions Page 12
Gaining Competitive Advantage through Reducing Project Lead Times Duncan Patrick, CMS Montera Inc. Jack Warchalowski, CMS Montera Inc.
Gaining Competitive Advantage through Reducing Project Lead Times Duncan Patrick, CMS Montera Inc. Jack Warchalowski, CMS Montera Inc. Introduction We all know that any successfully completed project has
The Theory of Constraints Critical Chain Management using MS Project 2010 and ProChain
The Theory of Constraints Critical Chain Management using MS Project 2010 and ProChain Variability Is A Fact Of Life Presentation Delivered by: Gerald Leonard, PMP, MCTS, CQIA, ITIL Objective Define Theory
Project Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
CRITICAL CHAIN AND CRITICAL PATH, CAN THEY COEXIST?
EXECUTIVE SUMMARY PURPOSE: This paper is a comparison and contrast of two project management planning and execution methodologies: critical path methodology (CPM) and the critical chain project management
CCPM: TOC Based Project Management Technique
CCPM: TOC Based Project Management Technique Prof. P.M. Chawan, Ganesh P. Gaikwad, Prashant S. Gosavi M. Tech, Computer Engineering, VJTI, Mumbai. Abstract In this paper, we are presenting the drawbacks
Program Management. Turning Many Projects into Few Priorities with TOC
Program Management Turning Many Projects into Few Priorities with TOC Francis. Patrick Focused Performance 908-874-8664 [email protected] The way to get something done is quoting the wellknown
Chapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072
Chapter 6: Project Time Management King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Learning Objectives Understand the importance of project schedules Define
50% task time estimate A task time estimate that has a 50% probability of being achieved.
1 2 nd edition CC terms 50% task time estimate A task time estimate that has a 50% probability of being achieved. Perspective: The distribution of task times is generally viewed as an asymmetrical positive
Critical Chain and Critical Path What s the Difference? By Gerald I. Kendall (www.tocinternational.com)
Introduction Critical Chain and Critical Path What s the Difference? By Gerald I. Kendall (www.tocinternational.com) I have some good news and some bad news. The bad news is that Critical Chain is a paradigm
15 Principles of Project Management Success
15 Principles of Project Management Success Project management knowledge, tools and processes are not enough to make your project succeed. You need to get away from your desk and get your hands dirty.
Project Time Management
Project Time Management By Augsburg College 1 Learning Objectives Understand the importance of project schedules and good project time management Define activities as the basis for developing project schedules
The Distinction between Manufacturing and Multi-Project And the Possible Mix of the Two. By Eli Schragenheim and Daniel P. Walsh
vector strategies The Distinction between Manufacturing and Multi-Project And the Possible Mix of the Two By Eli Schragenheim and Daniel P. Walsh The floor looks similar to any other manufacturing floor.
Information Technology Project Management, Sixth Edition. Note: See the text itself for full citations. More courses at cie-wc.edu
Note: See the text itself for full citations. More courses at cie-wc.edu Understand the importance of project schedules and good project time management Define activities as the basis for developing project
Critical Chain Concepts
Critical Chain Concepts Introduction Traditional project management concepts have been around for over thirty years. If you look at the impetus for their development in the 1950s, you find that early studies
Chapter 4: Project Time Management
Chapter 4: Project Time Management Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
Critical Chain Project Management The Basics
Critical Chain Project Management The Basics Marcia Pasquarella, Jonah, CFPIM, CIRM 310-416-3035 [email protected] BOEING is a trademark of Boeing Management Company. Copyright 2009 Boeing.
Chapter 6: Project Time Management
CIS 486 Managing Information Systems Projects Fall 2003 (Chapter 6), PhD [email protected] California State University, LA Computer and Information System Department Chapter 6: Project Time Management
Process Intelligence: An Exciting New Frontier for Business Intelligence
February/2014 Process Intelligence: An Exciting New Frontier for Business Intelligence Claudia Imhoff, Ph.D. Sponsored by Altosoft, A Kofax Company Table of Contents Introduction... 1 Use Cases... 2 Business
Expert Reference Series of White Papers. Intersecting Project Management and Business Analysis
Expert Reference Series of White Papers Intersecting Project Management and Business Analysis 1-800-COURSES www.globalknowledge.com Intersecting Project Management and Business Analysis Daniel Stober,
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
Importance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects
Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
Scheduling Glossary Activity. A component of work performed during the course of a project.
Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the
Critical Chain and Risk Management. Protecting Project Value from Uncertainty
Critical Chain and Risk Management Protecting Project Value from Uncertainty Francis S. Frank Patrick Focused Performance, Hillsborough, NJ, USA [email protected] Protecting the value of
Learning Objectives. Learning Objectives (continued) Importance of Project Schedules
Chapter 6: Project Time Management Information Technology Project Management, Fifth Edition Learning Objectives Understand the importance of project schedules and good project time management Define activities
Schedule Compression
Schedule Compression The need to reduce the time allowed for a schedule, or a part of a schedule is routine, some of the times the need arises include: When the initial schedule is too long to meet contractual
Seven Principles of Change:
Managing Change, LLC Identifying Intangible Assets to Produce Tangible Results Toll Free: 877-880-0217 Seven Principles of Change: Excerpt from the new book, Change Management: the people side of change
Chapter 2: Project Time Management
Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.
Automated Scheduling Methods. Advanced Planning and Scheduling Techniques
Advanced Planning and Scheduling Techniques Table of Contents Introduction 3 The Basic Theories 3 Constrained and Unconstrained Planning 4 Forward, Backward, and other methods 5 Rules for Sequencing Tasks
Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire. P3M3 Project Management Self-Assessment
Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire P3M3 Project Management Self-Assessment Contents Introduction 3 User Guidance 4 P3M3 Self-Assessment Questionnaire
Lecture 6: Project Time Management By: Prof. Lili Saghafi. Information Technology Project Management, Fifth Edition
Lecture 6: Project Time Management By: Prof. Lili Saghafi Information Technology Project Management, Fifth Edition Learning Objectives 2 Understand the importance of project schedules and good project
The only person who likes change is a baby with a wet diaper. Mark Twain. Charan CA Atreya
The only person who likes change is a baby with a wet diaper. Mark Twain Charan CA Atreya November - Evolutionary adoption of agile principles in traditional organizations First introduce Kanban and get
Expert Reference Series of White Papers. Importance of Schedule and Cost Control
Expert Reference Series of White Papers Importance of Schedule and Cost Control 1-800-COURSES www.globalknowledge.com Importance of Schedule and Cost Control Bill Scott, PE, PMP, PgMP Outline I. Project
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
Finite Capacity Portfolio and Pipeline Management
Finite Capacity Portfolio and Pipeline Management Under pressure to develop more products while holding their budgets constant, New Product Development (NPD) organizations are operating under severe resource
Amajor benefit of Monte-Carlo schedule analysis is to
2005 AACE International Transactions RISK.10 The Benefits of Monte- Carlo Schedule Analysis Mr. Jason Verschoor, P.Eng. Amajor benefit of Monte-Carlo schedule analysis is to expose underlying risks to
Project Time Management
Project Time Management Study Notes PMI, PMP, CAPM, PMBOK, PM Network and the PMI Registered Education Provider logo are registered marks of the Project Management Institute, Inc. Points to Note Please
DESCRIBING OUR COMPETENCIES. new thinking at work
DESCRIBING OUR COMPETENCIES new thinking at work OUR COMPETENCIES - AT A GLANCE 2 PERSONAL EFFECTIVENESS Influencing Communicating Self-development Decision-making PROVIDING EXCELLENT CUSTOMER SERVICE
CONSTRUCTION PROJECT BUFFER MANAGEMENT IN SCHEDULING PLANNING AND CONTROL
CONSTRUCTION PROJECT BUFFER MANAGEMENT IN SCHEDULING PLANNING AND CONTROL Jan, Shu-Hui Ph.D. Student Construction Engineering & Management Program Department of Civil Engineering National Taiwan University
THEORY OF CONSTRAINTS AS AN EFFECTIVE TOOL FOR SUPPLY CHAIN MANAGEMENT JOANNA NOWAKOWSKA-GRUNT 1 EWA MOROZ 2
Advanced Logistic Systems, Vol. 7, No. 1 (2013), pp. 71 78. THEORY OF CONSTRAINTS AS AN EFFECTIVE TOOL FOR SUPPLY CHAIN MANAGEMENT JOANNA NOWAKOWSKA-GRUNT 1 EWA MOROZ 2 Abstract: Supply chain management
Multi-Project Management using Critical Chain Project Management (CCPM) The Power of Creative Engineering
Multi-Project Management using Critical Chain Project Management (CCPM) The Power of Creative Engineering Prof. Siddesh K. Pai Assistant Professor & Research scholar National Institute of Construction
Attribute 1: COMMUNICATION
The positive are intended for use as a guide only and are not exhaustive. Not ALL will be applicable to ALL roles within a grade and in some cases may be appropriate to a Attribute 1: COMMUNICATION Level
Errata. 133 Figure 5-15 Corrected the output for 8.3 Control Quality to read verified deliverables
Errata NOTE: The following errata only pertain to the first printing of the PMBOK Guide Fifth Edition. In order to verify the print run of your book (or PDF), refer to the bottom of the copyright page
The Roles of Functional and Cross-functional Planning in Managing the Enterprise Elliot Chocron Matthew Steigerwald Introduction
The Roles of Functional and Cross-functional Planning in Managing the Enterprise Elliot Chocron Matthew Steigerwald Introduction In 2003, General Motor s GVDP Operations Planning & Scheduling group responded
Portfolio Management 101:
THOUGHT LEADERSHIP WHITE PAPER In partnership with Portfolio Management 101: Moving from Just Project Management to True PPM A lot of organizations claim that they carry out project & portfolio management
Governments information technology
So l u t i o n s Blending Agile and Lean Thinking for More Efficient IT Development By Harry Kenworthy Agile development and Lean management can lead to more cost-effective, timely production of information
Too Big to Change The Cost Side of CCPM
Too Big to Change The Cost Side of CCPM Presented By: CMS Montera Date: June 11, 2014 1 Agenda CCPM solution CCPM benefits Corporate environment requirements Scheduling conflict Direction of the solution
PROJECT TIME MANAGEMENT
6 PROJECT TIME MANAGEMENT Project Time Management includes the processes required to ensure timely completion of the project. Figure 6 1 provides an overview of the following major processes: 6.1 Activity
Software Engineering. What is a system?
What is a system? Software Engineering Software Processes A purposeful collection of inter-related components working together to achieve some common objective. A system may include software, mechanical,
TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT. Hazar Hamad Hussain *
TIME MANAGEMENT TOOLS AND TECHNIQUES FOR PROJECT MANAGEMENT Hazar Hamad Hussain * 1. Introduction The definition of Project as a temporary endeavor... refers that project has to be done within a limited
LECTURE 1. SYSTEMS DEVELOPMENT
LECTURE 1. SYSTEMS DEVELOPMENT 1.1 INFORMATION SYSTEMS System A system is an interrelated set of business procedures used within one business unit working together for a purpose A system has nine characteristics
Essential Elements for Any Successful Project
In this chapter Learn what comprises a successful project Understand the common characteristics of troubled projects Review the common characteristics of successful projects Learn which tools are indispensable
Ten Steps to Comprehensive Project Portfolio Management Part 3 Projects, Programs, Portfolios and Strategic Direction By R.
August 2007 Ten Steps to Comprehensive Project Portfolio Management Part 3 Projects, Programs, Portfolios and Strategic Direction By R. Max Wideman This series of papers has been developed from our work
Ensuring Reliability in Lean New Product Development. John J. Paschkewitz, P.E., CRE
Ensuring Reliability in Lean New Product Development John J. Paschkewitz, P.E., CRE Overview Introduction and Definitions Part 1: Lean Product Development Lean vs. Traditional Product Development Key Elements
The Manager s Guide to Avoiding 7 Project Portfolio Pitfalls
The Manager s Guide to Avoiding 7 Project Portfolio Pitfalls In today s management by projects mindset, portfolio managers and PMO directors are challenged with ensuring successful delivery in addition
P3M3 Portfolio Management Self-Assessment
Procurement Programmes & Projects P3M3 v2.1 Self-Assessment Instructions and Questionnaire P3M3 Portfolio Management Self-Assessment P3M3 is a registered trade mark of AXELOS Limited Contents Introduction
Scheduling. Anne Banks Pidduck Adapted from John Musser
Scheduling Anne Banks Pidduck Adapted from John Musser 1 Today Network Fundamentals Gantt Charts PERT/CPM Techniques 2 WBS Types: Process, product, hybrid Formats: Outline or graphical organization chart
Lean in Product Development
Lean in Product Development Key Strategies to Successfully Implement Lean Development and the Synergies with Advanced Product Quality Planning by Marc Lind 2008 Aras Corporation. All Rights Reserved. Contents
Basics Workshop: Project and Multi-Project Management (English)
Basics Workshop: Project and Multi-Project Management (English) Presented By: James R. Holt, Ph.D., PE FE, BSCI, PMCI, SCLCI, TPCI Date: June 2013 If you have already implemented Critical Chain Project
Thought Leadership White Paper Strategies for Effective Job Scheduler Consolidation
Thought Leadership White Paper Strategies for Effective Job Scheduler Consolidation Strategies for Overcoming Obstacles to Consolidation Table of Contents 1 EXECUTIVE SUMMARY 2 MOVE FROM FRAGMENTATION
Share the webinar Ask a question Votes (polling questions) Rate (before you leave) Attachments (you can download today s presentation)
Data Center Migration Primer Mark Smith Wednesday, June 27, 2012 General Information Share the webinar Ask a question Votes (polling questions) Rate (before you leave) Attachments (you can download today
Software Project Management Fifth Edition
Software Project Management Fifth Edition Chapter 8 Resource allocation 1 Schedules Activity schedule - indicating start and completion dates for each activity Resource schedule - indicating dates when
Depicting Schedule Margin in Integrated Master Schedules
Depicting Schedule Margin in Integrated Master Schedules National Defense Industrial Association Program Management Systems Committee Schedule Working Group FORWARD The objective of this paper is to discuss
ITPMG. February 2007. IT Performance Management: The Framework Initiating an IT Performance Management Program
IT Performance Management: The Framework Initiating an IT Performance Management Program February 2007 IT Performance Management Group Bethel, Connecticut Executive Summary This Insights Note will provide
HOW TO USE THE DGI DATA GOVERNANCE FRAMEWORK TO CONFIGURE YOUR PROGRAM
HOW TO USE THE DGI DATA GOVERNANCE FRAMEWORK TO CONFIGURE YOUR PROGRAM Prepared by Gwen Thomas of the Data Governance Institute Contents Why Data Governance?... 3 Why the DGI Data Governance Framework
Critical Chain. November 14 th 2011 - Revision Draft
Critical Chain November 14 th 2011 - Revision Draft This document, as well as the software described in it, is furnished under license and may only be used or copied in accordance with the terms of such
Overview. The Concept Of Managing Phases By Quality and Schedule
The Project Management Dashboard: A Management Tool For Controlling Complex Projects Project Management White Paper Series--#1001 John Aaron, Milestone Planning And Research, Inc. 5/14/01 Overview The
How To Compare Six Sigma, Lean and the Theory of Constraints
P R O C E S S M P R O V E M E N T How To Compare Six Sigma, Lean and the Theory of Constraints A framework for choosing what s best for your organization WTHN THE AMERCAN business community a multitude
Develop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
Lean manufacturing in the age of the Industrial Internet
Lean manufacturing in the age of the Industrial Internet From Henry Ford s moving assembly line to Taiichi Ohno s Toyota production system, now known as lean production, manufacturers globally have constantly
Ten Steps to Comprehensive Project Portfolio Management Part 1 An Introduction By R. Max Wideman Introduction Project
August 2007 Ten Steps to Comprehensive Project Portfolio Management Part 1 An Introduction By R. Max Wideman This series of papers has been developed from our work in upgrading TenStep's PortfolioStep.
Problems that haven t happened yet Why is it hard? Some are wary of bearing bad news. Define a strategy early in your project
1 Problems that haven t happened yet Why is it hard? Some are wary of bearing bad news No one wants to be the messenger Or seen as a worrier Define a strategy early in your project 2 Identification, Analysis,
SQL Server Performance Intelligence
WHITE PAPER SQL Server Performance Intelligence MARCH 2009 Confio Software www.confio.com +1-303-938-8282 By: Consortio Services & Confio Software Performance Intelligence is Confio Software s method of
Seeing the Value in Customer Service
CCA WHITE PAPER - HOW TO PUT THE DNA OF CUSTOMER SERVICE INTO UK BOARDROOMS 13 Seeing the Value in Customer Service Dr Marco Busi Centre Manager, Centre for Business Process Outsourcing Glasgow, Scotland
Afro Ant Conversation. Change Management Return on Investment 3 April 2014
Afro Ant Conversation Change Management Return on Investment 3 April 2014 Overview This report documents the information gathered at the Afro Ant Conversation held on the 3 rd of April 2014 on the topic
PROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited
PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of
Chapter 6. (PMBOK Guide)
Chapter 6 Project Time Management (PMBOK Guide) Mohammad A. Rajabi Dept. of Geomatics Eng., University it of Th Tehran Tel: +98 21 8833 4341, Cell: +98 912 132 5823 Email: [email protected] ir Homepage:
Table of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose
1 2 Author s Preface The Medialogist s Guide to Project Time Management is developed in compliance with the 9 th semester Medialogy report The Medialogist s Guide to Project Time Management Introducing
Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras
Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology, Madras Lecture - 36 Location Problems In this lecture, we continue the discussion
Tech-Clarity Insight: Integrating PLM and MES. Realizing the Digital Factory
Tech-Clarity Insight: Integrating PLM and MES Realizing the Digital Factory Tech-Clarity, Inc. 2011 Table of Contents Executive Overview... 3 Why Now?... 4 Product Innovation and Execution Roles... 5 Integrating
FIXING PROJECT MANAGEMENT: A MUST-HAVE
FIXING PROJECT MANAGEMENT: A MUST-HAVE Consistent Standards are Key to Multi-Vendor Operating Models By Michelle Mack, Principal Consultant www.isg-one.com INTRODUCTION Today s complex multi-source operating
Is Critical Chain Project Management Really a Novel Technique?
Is Critical Chain Project Management Really a Novel Technique? Mario Špundak VIPnet usluge d.o.o. Vrtni put 1, 10000 Zagreb, Croatia [email protected] Krešimir Fertalj, Damir Kalpić University of Zagreb
Client Onboarding Process Reengineering: Performance Management of Client Onboarding Programs
KNOWLEDGENT INSIGHTS volume 1 no. 4 September 13, 2011 Client Onboarding Process Reengineering: Performance Management of Client Onboarding Programs In the midst of the worst economic environment since
Project Management Issues in the Finance Transformation Arena
Project Management Issues in the Finance Transformation Arena Projects, and the ability to deliver them on time and on budget, not only represent an ongoing challenge for any organization, but also require
Enterprise IT Portfolio Governance and Management Model
STATE OF MICHIGAN Department of Information Technology Enterprise IT Portfolio Governance and Management Model NASCIO 2007 RECOGNITION AWARDS CATEGORY: IT PROJECT AND PORTFOLIO MANAGEMENT Enterprise IT
The Plan s Journey From Scope to WBS to Schedule
The Plan s Journey From Scope to WBS to Schedule Presented by: Rick Clare, CBAP, PMP, OCP, CSM PM Centers USA, LLC. 2013 Company Background Consulting and Training (Virtual, Public and Private Training)
4 Keys to Driving Results from Project Governance
THOUGHT LEADERSHIP WHITE PAPER In partnership with Agile or Waterfall? 4 Keys to Driving Results from Project Governance You can t swing a project manager these days without hitting the debate of Agile
Integrated Risk Management:
Integrated Risk Management: A Framework for Fraser Health For further information contact: Integrated Risk Management Fraser Health Corporate Office 300, 10334 152A Street Surrey, BC V3R 8T4 Phone: (604)
Critical Chain Project Management (CCPM) at Bosch Security Systems (CCTV) Eindhoven
University of Twente School of Management and Governance Critical Chain Project Management (CCPM) at Bosch Security Systems (CCTV) Eindhoven A Survey to explore improvement opportunities in the scheduling
How To Change A Business Model
SOA governance and organizational change strategy White paper November 2007 Enabling SOA through organizational change Sandy Poi, Global SOA Offerings Governance lead, associate partner, Financial Services
pm4dev, 2007 management for development series Introduction to Project Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2007 management for development series Introduction to Project Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage
Chapter 6 (part 1) Project Time Management. (Project Scheduling)
Chapter 6 (part 1) Project Time Management. (Project Scheduling) 1 Objectives Understand the process of project decomposition into activities Understand the level of details required for activities Understand