1 CVN 68 CVN 77 OVERVIEW OF NAVAL SHIPYARD s QUALITY, INNOVATION AND PRODUCTIVITY IMPROVEMENT EFFORTS SSGN/BN LA Class Virginia & Sea Wolf 1
2 Naval Shipyard Quality Program Manual (QPM) Background: Issued in early 1980s to meet Quality Standard MIL-Q Updated in 1999 to address and comply with a ANSI/ISO/ASQ Q9001 International Quality Standard. QPM focus is on ten program processes that interact with many functional organizations Technical Document and Configuration Management Control Material Control Laboratory and Calibration of Measuring and Test Equipment Control Corrective and Preventive Action Procurement Quality Control Process Controls Inspection and Verification Audit Program Training Program Surveillance Inspection
3 NAVSEA/Naval Shipyard Key Quality Processes AVAILABILITY WORK PACKAGE CUSTOMER SHIP TECHNICAL REVIEW TECHNICAL DIRECTION (TASK GROUP INSTRUCTIONS) OVERSIGHT TEST CONTROL WORK READINESS WORK CERTIFICATION WORK CONTROL WORKMANSHIP (WORK EXECUTION)
4 Managing and Measuring the Effectiveness of Naval Shipyard s Quality Program NAVSEA/Shipyard jointly developed Corporate Quality Performance System for seven key processes. Discrepancy data is collected, categorized, quantified by severity levels and analyzed for trends and quality performance metrics. Shipyard has developed a self assessment program. each internal functional area establishes desired goals, metrics used to measure performance, performs analysis to validate data collection for trend analysis and issues requiring corrective/preventive action and continuous improvement strategies. Shipyard uses audit and surveillance inspection programs to monitor compliance with technical and process procedures.
5 Naval Shipyards (NSYs) NSYs improvement timeline 80s 90s 2000s Current - Quality Circles (QC) - Leadership Education And Development (LEAD) Training - Total Quality Leadership (TQL) - Cumbersome Work Practice (CWP) NSYs have always expended and continue to expend considerable effort on productivity improvement Over 350 major local initiatives/year Over 30 corporate initiatives - Learning Organization (LO) - Continuous Process Improvement (CPI) & Lean - Community of Practice (CoP) - Warfare Center Engagement Drive For Process Improvement Is Part Of NSY Culture 5
6 Innovation Approach In NSYs Lean Lessons learned, Hitkit New Technology Insertion Cumbersome Work Practice Task Force Sub Team 1, Carrier Team 1 Product Line Tools & Methods Mil Con, OPN, SRM Collaboration w/ industry (NSRP) Utilize Warfare Center Resources Aligned Efforts Path to Excellence Behaviors & Relationships Lean Thinking Learning Organization (LO) Communities of Practice (CoP) Knowledge Management Seven Habits Leadership & Communication Current State Future State Plan/Vision 6
7 Continuous Process Improvement Cycle in NSYs 7
8 Major Performance Initiatives Product Line Management (PLM) Integrated work teams (production with support codes) responsible for planning and executing work using Lean principles. o Teams perform the same type of work across multiple projects/availabilities within project schedules. o Teams are stable and designed to improve coordination of work and eliminate handoffs between trades (transactional waste). 8
9 Innovation Initiatives Warfare Center Engagement PSNS&IMF Visit in December Items identified for potential Warfare Center assistance Some quick wins ; others long term Focusing on strategic 7 innovation items PHNS&IMF Visit in July 2015 PNS & NNSY to be scheduled for later in the year Rapid Prototyping/Moonshine Design and development capabilities to meet unique needs Workforce generated ideas to improve efficiency and worker quality of life Ergonomic Innovations Mechanical Assist Arms Industrial Human Augmentation System (ihas) New Technology Insertion Ex 1) Laser ablation for coating removal Ex 2) Improved blast respirator hood Ex 3) Exploring robotics for coating removal and inspection 9
10 Naval shipyards originally built for ship construction. Many buildings from the shipbuilding era are still in use. Not configured for ship repair processes. Dispersed workforce and not efficient for current demands and operations. The hub concept realigns processes and infrastructure for more efficient product line maintenance. FY12 National Defense Authorization Act required Navy to submit to Congress the plan to address the facility and infrastructure requirements at each NSY due to history of under investment in this area. The plan submitted focused on continuous mission effectiveness of NSYs by focusing on five key areas: (1) Maintain drydock certification, (2) Eliminate mission essential facility maintenance backlog, (3) Remediate seismic deficiencies, (4) Centralize maintenance operations for product lines in specific waterfront areas of the naval shipyards, & (5) Improve utility system reliability. Fully Funded Infrastructure: April 2013 Report to Congress On Investment Plan for The Modernization of NSYs 10
11 IT Transition Strategy 11
12 BACK UP SLIDES
13 Innovation and Productivity Improvements In NSYs Major Performance Initiatives Continuous Training & Development (CTD) Communities of Practice (CoP) Product Line Management (PLM) Learning Organization (LO) Innovation and Cumbersome Work Practice Examples Carrier Team 1 (CT1) & Submarine Team 1 (ST1) Major Initiatives Infrastructure Modernization for Efficiency Information Technology (IT) Productivity Enhancer Various Corporate and Local Productivity Improvement Efforts at NSYs Execution Barriers 13
14 Various Corporate and Local Productivity Improvements in NSYs Initiative Previous Process Current Process Benefits % Improved Efficiency UT for Weld Inspection Radiographic Testing (RT) Phased Array Ultrasonic Testing (UT) Achieved 4968 mandays (MD) capacity across 10 CVN availabilities 90% MDs reduction Paint Receipt Inspection Paints required 8 test to be performed Requirement changed to allow shipyards to use paint with manufacturer provided QA data In CY14, estimated cost avoidance of $227k/yr 44% cost avoidance Spray Shields Eliminated 1000 spray shields per (LA CL requirement) submarine needed to project lagged joints NAVSEA changed the LA CL standard to VA CL standard, which eliminated >700 shields Cost Avoidance of $35K per availability 70% cost avoidance Job readiness Cell/ POU Lost material and duplication of ordering Tool, material, & consumable were kitted for the mechanic in execution cells & at point of use (POU) Achieved 0.15 increase in CP. IKE FY11 CP of.79 to the FY12 BUSH CP of.94 16% CP improvement ICCP Testing Jig Using old Impressed Current Cathodic Protection (ICCP) Testing jig design Improved testing jig design-more efficient design, using cheaper material for VA CL Old design $39,727 New Design - $1,374 97% cost avoidance Generic I&C Improvement Complex nuclear Shipalt production work with rad exposure, 19,977 MDs on USS NIMITZ Reduced process cycle time and reduced exposure using lean principles, 15,583 MDs on USS RONALD REAGAN 4,394 MD reduction, OT reduced from 21% to 13.5%, exposure reduction 8,605mrem & 5,804 fewer RC hours. 22% MDs reduction CVN Shafting System and processes that supported CVN Shafting was grossly inefficient and was identified as a hold up to undocking. A strategic approach was taken to focus value stream analysis on the executable work breakdown structure across five job summaries supporting CVN Shafting 1,836 MD & 5.9 ave CU duration on USS RONALD REAGAN 1,541 MDs & 4.1 ave CU duration on USS STENNIS 16% MDs reduction Safety Draft Marker Adjusting AFT safety draft marks on upper rudder of submarines afloat suspended workers in crane-rigged personnel basket Upper rudder Safety Draft Marker is autonomous and adjustable from the pier by wireless remote control Old design $46,140 New Design - $34,813 25% cost avoidance Contractor Conversion 28 IT contractors were used to support various NSY IT positions Added government overhead FTEs to support the contractor billet Achieved cost reduction of $750K per year (reduction of IT support costs) 18% cost avoidance Hull & Back-up (H&Bu) Valve Timely maintenance of H&Bu were identified as a key contributor to undocking for Trident EROs Minimize personnel churn which degraded the building up of proficiency, took action on improvement initiatives Reduced 100 MDs per valve, Improved CPs: MMP1.89, MMP2.92, MMP & MMP % CP improvement 14
15 Infrastructure Modernization for Efficiency Norfolk Naval Shipyard P527 Submarine Maintenance Pierside Facility (Pier 3) P258 Submarine Maintenance Execution Facility P526 CVN Maintenance Facility Portsmouth Naval Shipyard P293 Consolidate Paint and Blast Facilities P294 Mechanical Shops Consolidation, B80 P352 Dry Dock 1 Pure water & Emergency Response Facility P356 Electrical & Pipe Temp Service Consolidation Puget Sound Naval Shipyard & IMF P431 Dry Dock 6 Modernization & Utility /Site Improvements P417 Abrasive Blast And Paint Work Center P410 Hazmat/Waste Handling Facility Consolidation Pearl Harbor Naval Shipyard & IMF P036 Welding School Shop Consolidation P227 Submarine Maintenance Pier Modernization P035 Submarine Project Support Offices (BLDG 1670) P290 Ship/Submarine Training Center Expected Improvement: Developing Maintenance hubs will realign processes, infrastructure, people, and tools/materials will help gain efficiency. Maintenance hubs approved by SECNAV, April 2013 Navy Report to Congress On Investment Plan for The Modernization of Naval Shipyards 15
16 Execution Top 4 Barriers The top 4 barriers for execution performance not meeting execution guidance: Personnel Readiness: - Resource to workload imbalance - Shipyard performance is not where it should be - Inexperienced Workforce - Support functions needed for efficient & effective maintenance project execution have not grown over time Improve Productivity: - Rate of process improvement is not overcoming counter forces - Improving rotatable pools and in stock material would assist project execution - Instability / churn in avail work packages Information Technology & Infrastructure - Shore based maintenance IT & infrastructure has been historically underfunded, underresourced, and intermittently addressed Improve Planning: - Divergence between NSY planning estimates and Corporate Planning Estimates, new work, late Ship's Force work integration, and/or NSY performance issues - Availability work packages are consistently exceeding the programmed avail notional 16
Captain Joseph Campbell Commander, Norfolk Naval Shipyard Portsmouth, Virginia. Statement A: Approved for public release; distribution is unlimited
2005 DOD Maintenance Symposium & Exhibition Tuesday (10/25), 14:00-16:00 Breakout/Technical Session: Reinventing the Wheel or an Idea Whose Time has Come? Ideas that are Transforming Defense Maintenance
More informationStrategic Design. To learn more about the Naval Facilities Engineering Command, please visit us at www.navfac.navy.mil and www.facebook.
To learn more about the Naval Facilities Engineering Command, please visit us at www.navfac.navy.mil and www.facebook.com/navfac Strategic Design Naval Facilities Engineering Command 1322 Patterson Avenue,
More informationUNDERWATER MAINTENANCE AND REPAIR IN LIEU OF DRY DOCKING. USS MIDWAY Museum Installation of Hull Suction and Discharge Blank Patches
UNDERWATER MAINTENANCE AND REPAIR IN LIEU OF DRY DOCKING USS MIDWAY Museum Installation of Hull Suction and Discharge Blank Patches 1 Phoenix Who we are In Water Repair Capabilities The tool kit Hull Cleaning
More informationThe US Navy s Submarine Safety Standards
The US Navy s Submarine Safety Standards Presentation to International and Domestic Standards Conference May 8, 2015 Roger W. Schaffer, P.E. Deputy Director, Submarine Safety and Quality Assurance The
More informationElectric Boat Business Update
Electric Boat Business Update Presentation to Commission for Connecticut s Future September 30, 2014 Copyright Electric Boat Corporation - Use Only With Permission Electric Electric Boat Proprietary Boat
More informationInternal Surveillance
Page 1 of 18 Internal Surveillance A contract having Earned Value Management System (EVMS) requires the contractor to maintain an effective management control system consistent with EVM industry standards
More informationNNPP Enterprise Overview
NNPP Enterprise Overview NR Program Background Navy Nuclear Propulsion Program founded in 1948 Currently operating: 104 reactors (US commercial industry) 11 nuclear powered aircraft carriers (more under
More informationSubj: FY13 NAVSEA SHIP PROPELLER AND PROPULSOR TRAINING COURSES
CONSOLIDATED TRAINING DIVISION NORFOLK NAVAL SHIPYARD PORTSMOUTH, VA 23709-5000 Ser 900T-041-12 August 2012 RDG rg From: Deputy Superintendent, Code 900T To: Distribution List Subj: FY13 NAVSEA SHIP PROPELLER
More informationThe New Program in Marine Engineering Technology
The New Program in Marine Engineering Technology Dr. Alok K. Verma P.E., CMfgE Ray Ferrari Professor Chief Technologist Lean Institute Department of Engineering Technology Batten College of Engineering
More informationDepartment of Defense
OFFICE OF THE INSPECTOR GENERAL ACCOUNTS RECEIVABLE FOR DOD MATERIEL Report No. 94-119 June 3, 1994 Department of Defense Additional Copies To obtain additional copies of this report, contact the Secondary
More informationLinac Coherent Light Source (LCLS)
Linac Coherent Light Source (LCLS) An X Ray Free Electron Laser LLNL Quality Implementation Plan PMD 003 r0 May 2004 Prepared for the US Department of Energy under contract numbers: SLAC DE AC03 76SF00515
More informationReport No. DoDIG-2012-081 April 27, 2012. Navy Organic Airborne and Surface Influence Sweep Program Needs Defense Contract Management Agency Support
Report No. DoDIG-2012-081 April 27, 2012 Navy Organic Airborne and Surface Influence Sweep Program Needs Defense Contract Management Agency Support Additional Copies To obtain additional copies of this
More informationEnterprise Asset Management for Shipyards
Enterprise Asset Management for Shipyards Shipyard Production Process Technologies Panel Joe Hellmers Program Manager September 17, 2009 Enterprise Asset Management (EAM) Defined: A computer system used
More informationMODERN SHIPBUILDING PRACTICE
MODERN SHIPBUILDING PRACTICE GROUP TECHNOLOGY/PWBS/IPC GT is not new Has only had limited application in shipyards. Typical uses have been structural part variety reduction and development of pipe piece
More informationSECRETARY OF THE NAVY SAFETY EXCELLENCE AWARDS
1. Background SECNAVINST 5100.10K SECRETARY OF THE NAVY SAFETY EXCELLENCE AWARDS a. The SECNAV Safety Excellence Awards were established to recognize and congratulate those Navy and Marine Corps commands
More informationDEPARTMENT OF COMMERCE
DEPARTMENT OF COMMERCE SERVICE CONTRACT INVENTORY ANALYSIS REPORT FISCAL YEAR 2012 December 31, 2013 Analysis of Service Contract Inventory for Fiscal Year 2012 I. Executive Summary The historic mission
More informationNavy and Marine Corps Have Weak Procurement Processes for Cost reimbursement Contract Issuance and Management
Inspector General U.S. Department of Defense Report No. DODIG-2014-092 JULY 11, 2014 Navy and Marine Corps Have Weak Procurement Processes for Cost reimbursement Contract Issuance and Management INTEGRITY
More informationNAVAL SEA SYSTEMS COMMAND STRATEGIC BUSINESS PLAN
NAVAL SEA SYSTEMS COMMAND STRATEGIC BUSINESS PLAN 2013-2018 2 NAVAL SEA SYSTEMS COMMAND Foreword Everything the United States Navy brings to the fight, and ultimately does for the nation, is delivered
More informationHow To Decommission A Nuclear Plant
International Atomic Energy Agency Decommissioning of Nuclear Facilities Management of Decommissioning Projects Lawrence E. Boing Manila, Philippines, October 2006 1 Lesson Objectives Understand the management
More informationCurriculum Vitae SAN FRANCISCO, USA, RESIDENT SURVEYOR. British Subject and USA permanent resident
Curriculum Vitae SAN FRANCISCO, USA, RESIDENT SURVEYOR Name: Status: GRAHAM WILLIAM ARCHER British Subject and USA permanent resident CONTACT: Email: garcher@bmtmarinerisk.com Phone: +1 415 389-0608 Mobile:
More informationFlexible, Life-Cycle Support for Unique Mission Requirements
Flexible, Life-Cycle Support for Unique Mission Requirements We Meet the Need Anytime, Anywhere, Any Mission The customers we serve are diverse and so are their requirements. Transformational logistics
More informationNAVAL POSTGRADUATE SCHOOL THESIS
NAVAL POSTGRADUATE SCHOOL MONTEREY, CALIFORNIA THESIS COMPARISON OF THE NAVY WORKING CAPITAL FUND AND MISSION FUNDING AS APPLIED TO NAVY SHIPYARDS by Andrew M. Cain June 2006 Thesis Co-Advisors: Jerry
More informationTake control of your inbox and make Outlook work harder for you
This class was well worth the time! It is the only class that I have taken that has had a direct and measurable impact on work efforts. I have already recommended this class to personnel who work for,
More informationDODIG-2013-105 July 18, 2013. Navy Did Not Develop Processes in the Navy Enterprise Resource Planning System to Account for Military Equipment Assets
DODIG-2013-105 July 18, 2013 Navy Did Not Develop Processes in the Navy Enterprise Resource Planning System to Account for Military Equipment Assets Additional Copies To obtain additional copies of this
More informationNON-DESTRUCTIVE TESTING FULL SCOPE OF INTEGRATED NDT SERVICES
NON-DESTRUCTIVE TESTING FULL SCOPE OF INTEGRATED NDT SERVICES RIGHT SERVICE MAXIMUM RETURN Whether it is in fabrication, pipe manufacturing, pipeline, plant construction, chemical, petrochemical plants,
More informationCQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES
1.0 SCOPE CQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES This document establishes the minimum quality program requirements for a contractor providing equipment, material, and construction
More informationAPPENDIX B SUPPLEMENTAL INSPECTION PROGRAM A. OBJECTIVES AND PHILOSOPHY OF THE SUPPLEMENTAL INSPECTION PROGRAM
APPENDIX B SUPPLEMENTAL INSPECTION PROGRAM A. OBJECTIVES AND PHILOSOPHY OF THE SUPPLEMENTAL INSPECTION PROGRAM The supplemental inspection program is designed to support the NRC s goals of maintaining
More informationU.S. Army Corps of Engineers, New York District Monitoring of a Hurricane Sandy Contract Needs Improvement
Inspector General U.S. Department of Defense Report No. DODIG-2016-028 DECEMBER 3, 2015 U.S. Army Corps of Engineers, New York District Monitoring of a Hurricane Sandy Contract Needs Improvement INTEGRITY
More informationQualified Contractor Management System
FCIA Education Program Quality Module UL Qualified Contractor Firm Candidates Management System & Audit Preparation Education FCIA July 8, 2007; November 2007; March 2008 FCIA Management System Education
More informationQUALITY MANAGEMENT SYSTEM REVIEW AND APPROVAL TEMPLATE (DOE G 414.1-2A, Appendix A, 6-17-05)
QUALITY MANAGEMENT SYSTEM REVIEW AND APPROVAL TEMPLATE (DOE G 414.1-2A, Appendix A, 6-17-05) This review template is intended for use by the DOE for evaluating a DOE Site Office or Contractor Quality Assurance
More informationOPNAVINST 3000.15A USFF/CNO N3/N5 10 Nov 2014
DEPARTMENT OF THE NAVY OFFICE OF THE CHIEF OF NAVAL OPERATIONS 2000 NAVY PENTAGON WASHINGTON, DC 20350-2000 OPNAVINST 3000.15A USFF/CNO N3/N5 OPNAV INSTRUCTION 3000.15A From: Chief of Naval Operations
More informationNewport RI Naval history
Newport RI Naval history During the years of the Newport s heavy involvement in the Triangular Trade, the English considered establishing a navy yard at Newport. Robert Melville was hired to conduct a
More informationFor More Information
THE ARTS CHILD POLICY CIVIL JUSTICE EDUCATION ENERGY AND ENVIRONMENT HEALTH AND HEALTH CARE INTERNATIONAL AFFAIRS NATIONAL SECURITY POPULATION AND AGING PUBLIC SAFETY SCIENCE AND TECHNOLOGY SUBSTANCE ABUSE
More informationCUSTOMER KEYNOTE Hal Buddenbohm
CUSTOMER KEYNOTE Hal Buddenbohm Supply Chain Director ITT Force Protection Systems Hal Buddenbohm is the Supply Chain Director at ITT Force Protection Systems in Thousand Oaks, CA. Prior to joining ITT,
More informationa GAO-06-530 GAO DEFENSE WORKING CAPITAL FUND Military Services Did Not Calculate and Report Carryover Amounts Correctly
GAO United States Government Accountability Office Report to the Chairman, Subcommittee on Defense, Committee on Appropriations, House of Representatives June 2006 DEFENSE WORKING CAPITAL FUND Military
More informationAmerican Recovery and Reinvestment Act Project Repair and Modernization of Littoral Combat Ship Squadron Building at Naval Base San Diego, California
Memorandum No. D2010-RAM-008 June 11, 2010 American Recovery and Reinvestment Act Project Repair and Modernization of Littoral Combat Ship Squadron Building at Naval Base San Diego, California Additional
More informationDocument Control. Background and Exhibits
Plan Do Check/Act Document Control Background and Exhibits To ensure that personnel are consistently performing their jobs in the right way, the facility must provide them with the proper tools. In the
More informationNaval Personnel Can Improve Compliance With the Berry Amendment and the Buy American Act
Inspector General U.S. Department of Defense Report No. DODIG-2015-161 AUGUST 12, 2015 Naval Personnel Can Improve Compliance With the Berry Amendment and the Buy American Act INTEGRITY EFFICIENCY ACCOUNTABILITY
More informationShip Repair, Maintenance & Modernization Cost Model. March 2014
Ship Repair, Maintenance & Modernization Cost Model March 2014 1 The Cost Model is a Microsoft EXCEL workbook that contains various tabbed worksheets. There are worksheets to enter basic project information
More informationQuality Assurance Manual. QAM-2013-Rev2
QAM-2013-Rev2 President s Policy and Authorization of Quality Control The management system for the Steel Structural Fabrication of Pinnacle Industrial Services entrusted through furnishing high quality
More informationIntroduction to the ITS Project Management Methodology
Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer
More informationOutline. Intro Navy at Large NUPOC Program. NUPOC Eligibility How to Apply. Job Options and Descriptions
Outline Intro Navy at Large NUPOC Program Job Options and Descriptions NUPOC Eligibility How to Apply The Nuclear Navy Today 82 Nuclear Powered Ships: A total of 92 naval reactors 28% of Navy s Total Deployable
More informationU.S. Department of Energy Office of Inspector General Office of Audits and Inspections
U.S. Department of Energy Office of Inspector General Office of Audits and Inspections Audit Report The Department of Energy's Management and Use of Mobile Computing Devices and Services DOE/IG-0908 April
More informationNational Ship Building Research Program, Norfolk, VA October 30, 2006
National Ship Building Research Program, Norfolk, VA October 30, 2006 Barbara Murray, Program Director Maritime and Transportation Center bmurray@tcc.edu Ship Repair and Ship Building Industry in Hampton
More informationU.S. Defense Priorities OSD PA&E
1 U.S. Defense Priorities Deter potential adversaries and defend America and American interests Counter asymmetric threats including terrorism, cyber attacks and ballistic and cruise missiles Fight and
More informationFEDERAL RÉSUMÉ. Client Name PROFILE SUMMARY
A d d r e s s C i t y, S t a t e Z i p FEDERAL RÉSUMÉ Client Name E m a i l A d d r e s s P h o n e N u m b e r Citizenship: U.S. Citizen Veteran Status: Retired Job Announcement Number: ABDC-4894892 Job
More informationAFLOAT ASBESTOS CONTROL
SAFETY TRAINING GOUGE #7 AFLOAT ASBESTOS CONTROL April 2012 Published by the Naval Safety and Environmental Training Center www.public.navy.mil/navsafecen/navsafenvtracen/ About Safety Training Gouge If
More informationCDI Government Services
CDI Government Services Capabilities Overview CDI Corporation proprietary information. Use or dissemination without prior consent is strictly prohibited. Who We Are For more than 60 years CDI Corporation
More informationFleet Logistics Center, Puget Sound
Naval Supply Systems Command Fleet Logistics Center, Puget Sound FLEET & INDUSTRIAL SUPPLY CENTER, PUGET SOUND NAVY/PTAC Small Business Training and Outreach Lucy Leu Deputy for Small Business Topics for
More informationDepartment of Defense
OFFICE OF THE INSPECTOR GENERAL MANAGEMENT OF THE DIGITAL PRODUCTION SYSTEM DEVELOPMENT AT THE DEFENSE MAPPING AGENCY November 28, 1994 Department of Defense Additional Copies To obtain additional copies
More informationDept 425: Instrumentation and Electronic Systems Disciplines: Computer, Computer Science, Electrical, Mathematics
Dept 425: Instrumentation and Electronic Systems Engineering personnel are responsible for the design, development and deployment of test instrumentation and data acquisition systems to support design
More informationChap 1. Software Quality Management
Chap 1. Software Quality Management Part 1.1 Quality Assurance and Standards Part 1.2 Software Review and Inspection Part 1.3 Software Measurement and Metrics 1 Part 1.1 Quality Assurance and Standards
More informationCamber Quality Assurance (QA) Approach
Camber Quality Assurance (QA) Approach Camber s QA approach brings a tested, systematic methodology, ensuring that our customers receive the highest quality products and services, delivered via efficient
More informationIndependent Security Operations Oversight and Assessment. Captain Timothy Holland PM NGEN
Independent Security Operations Oversight and Assessment Captain Timothy Holland PM NGEN 23 June 2010 Independent Security Operations Oversight and Assessment Will Jordan NGEN Cyber Security 23 June 2010
More informationAudit of the Transfer of DoD Service Treatment Records to the Department of Veterans Affairs
Inspector General U.S. Department of Defense Report No. DODIG-2014-097 JULY 31, 2014 Audit of the Transfer of DoD Service Treatment Records to the Department of Veterans Affairs INTEGRITY EFFICIENCY ACCOUNTABILITY
More informationAUDIT PLAN FOR FISCAL YEAR 2016
AUDIT PLAN FOR FISCAL YEAR 2016 This page intentionally left blank. NATIONAL RAILROAD PASSENGER CORPORATION Office of Inspector General NATIONAL RAILROAD PASSENGER CORPORATION INSPECTOR GENERAL S MESSAGE
More informationMs. Alyse C. Bullock DoN OSBP Assistant Director
Ms. Alyse C. Bullock DoN OSBP Assistant Director The Small Business Program promotes acquisition opportunities where small business can best support the needs of our Sailors and Marines. Through policy,
More informationHow To Save Money On A Data Center
Federal Data Center Consolidation Initiative Data Center Consolidation Plan for the U.S. Small Business Administration Maintained by: The Office of the Chief Information Officer Paul Christy, CIO Revised:
More informationApril 17, 2006. Human Capital. Report on the DoD Acquisition Workforce Count (D-2006-073) Department of Defense Office of Inspector General
April 17, 2006 Human Capital Report on the DoD Acquisition Workforce Count (D-2006-073) Department of Defense Office of Inspector General Quality Integrity Accountability Additional Copies To obtain additional
More informationGreat Lakes National Program Office and Office of Water Quality Management Training Modules
GLOSSARY Assessment - the evaluation process used to measure the performance or effectiveness of a system and its elements. As used here, assessment is an all-inclusive term used to denote any of the following:
More informationDeputy Chief Financial Officer Peggy Sherry. And. Chief Information Security Officer Robert West. U.S. Department of Homeland Security.
Deputy Chief Financial Officer Peggy Sherry And Chief Information Security Officer Robert West U.S. Department of Homeland Security Testimony Before the Subcommittee on Government Organization, Efficiency
More informationIndependent Evaluation of NRC s Implementation of the Federal Information Security Modernization Act of 2014 for Fiscal Year 2015
Independent Evaluation of NRC s Implementation of the Federal Information Security Modernization Act of 2014 for Fiscal Year 2015 OIG-16-A-03 November 12, 2015 All publicly available OIG reports (including
More informationOptimizing Quality Control / Quality Assurance Agents of a Global Sourcing / Procurement Strategy
Optimizing Quality Control / Quality Assurance Agents of a Global Sourcing / Procurement Strategy Global Pharma Sourcing Conference December 6-7, 2011 Philadelphia, USA Nigel J. Smart, Ph.D. Smart Consulting
More informationRobust Functional Paperless Paint Phase II
Robust Functional Paperless Paint Phase II Prepared for: National Shipbuilding Research Program Surface Preparation and Coatings Panel (SPC) Submitted by: Ross Boyd, TruQC Stephen Cogswell, BAE Systems
More informationProduct Order Quality Requirements Meggitt (Orange County), Inc.
Product Order Quality Requirements Meggitt (Orange County), Inc. Reference QP8-051, Purchase Order Quality Requirements QP8-055, Review/Control Supplier Documentation PP-401, Quality Assurance Codes 50-2-351,
More informationAudit Report. The National Nuclear Security Administration's Weapons Dismantlement and Disposition Program
U.S. Department of Energy Office of Inspector General Office of Audits and Inspections Audit Report The National Nuclear Security Administration's Weapons Dismantlement and Disposition Program OAS-L-13-06
More informationESH 007 Lesson Plan ESQ Training
ESH 007 Lesson Plan ESQ Training Course Number and Title Revision to LMS-PROC-125, Applying the Graded Approach to Quality Date 01/27/2015 Terminal Objective (Describes the expected outcomes of this training)
More informationJOHN HART GENERATING STATION REPLACEMENT PROJECT. Schedule 9. Quality Management
JOHN HART GENERATING STATION REPLACEMENT PROJECT Schedule 9 Quality Management SCHEDULE 9 QUALITY MANAGEMENT TABLE OF CONTENTS 1. QUALITY MANAGEMENT SYSTEM... 1 1.1 Quality Management System...1 1.2 Project
More informationPurchasing Services AOC 200 4202 East Fowler Avenue Tampa, Florida 33620 (813) 974-2481. Web Address: http://www.usf.edu/business-finance/purchasing/
Purchasing Services AOC 200 4202 East Fowler Avenue Tampa, Florida 33620 (813) 974-2481 Web Address: http://www.usf.edu/business-finance/purchasing/ January 20, 2016 Invitation to Negotiate No. Entitled:
More informationENTRY FORM. DVASE 2015 Excellence in Structural Engineering Awards Program
ENTRY FORM DVASE 2015 Excellence in Structural Engineering Awards Program PROJECT CATEGORY (check one): Buildings under $2M Buildings Over $100M Buildings $2M-$10M X Other Structures Under $5M Buildings
More informationJoint Industry/Navy Improvement Initiative (JINII) Work Force Development
Joint Industry/Navy Improvement Initiative (JINII) Work Force Development Mr. Dale Hirschman Navy Regional Maintenance Command (NRMC) 1 September 2011 Organizational Alignment and Training View 2 NRMC
More informationDefense Technical Information Center Compilation Part Notice
UNCLASSIFIED Defense Technical Information Center Compilation Part Notice ADP017725 TITLE: Restoration of drinking Water Piping with Nontoxic Epoxy Linings DISTRIBUTION: Approved for public release, distribution
More informationHEAVY WATER LEAK DETECTOR
HEAVY WATER LEAK DETECTOR WEB www.overhoff.com MODEL 1925 HEAVY WATER LEAK DETECTOR (HWLD) LOW LEVEL REAL TIME TRITIUM-IN-WATER MONITOR This monitor has been designed for real time low-level detection
More informationGLOBAL AEROSPACE PROCEDURE
1 of 13 1. PURPOSE: This procedure establishes the minimum PPG Aerospace requirements for a Supplier's Quality Plan. These requirements pertain to the documentation and inspection/testing necessary to
More informationQuality Assurance QUALITY ASSURANCE PLAN
Revision 2 Page 1 of 40 QUALITY ASSURANCE PLAN PLAN APPROVALS: Jeff Shouse Signature on File DIRECTOR OF QUALITY ASSURANCE DIRECTOR OF QUALITY ASSURANCE (signature) DATE Rodney Baltzer Signature on File
More informationa GAO-05-858 GAO DOD BUSINESS SYSTEMS MODERNIZATION Navy ERP Adherence to Best Business Practices Critical to Avoid Past Failures
GAO United States Government Accountability Office Report to Congressional Requesters September 2005 DOD BUSINESS SYSTEMS MODERNIZATION Navy ERP Adherence to Best Business Practices Critical to Avoid Past
More informationDIVISION. Quality Assurance and Continuous Improvement. Bruce Lenzer
ESH&Q DIVISION Quality Assurance and Continuous Improvement Bruce Lenzer WHAT IS QUALITY? Two historic definitions: 1) fitness for use - In order to exhibit quality a material, process, product or service
More informationNaval Nuclear Propulsion Program
Naval Nuclear Propulsion Program 96 Reactors Operating Worldwide ~ 40,000 personnel engaged in NNPP work What is the NUPOC program? In one sentence, the best deal in the Navy Nuclear Propulsion Officer
More informationVeteventer Black of Inter- Tropical Sales Contracts
The Do s & Don ts of International Contracts April 14, 2014 - McLean, VA April 15, 2014 - Norfolk, VA Presented by Vandeventer Black, in association with the VEDP Vandeventer Black LLP An International
More informationGuidance for the Quality Assurance of Fire Protection Systems
Guidance for the Quality Assurance of Fire Protection Systems Prepared for: Office of Energy Research Office of Environment, Safety and Health Technical Support Prepared by: Roy F. Weston, Inc. October
More informationU.S. Nuclear Regulatory Commission
U.S. Nuclear Regulatory Commission 2011 Data Center Consolidation Plan and Progress Report Version 2.0 September 30, 2011 Enclosure Contents 1 Introduction... 2 2 Agency Goals for Data Center Consolidation...
More informationAllegations of the Defense Contract Management Agency s Performance in Administrating Selected Weapon Systems Contracts (D-2004-054)
February 23, 2004 Acquisition Allegations of the Defense Contract Management Agency s Performance in Administrating Selected Weapon Systems Contracts (D-2004-054) This special version of the report has
More informationODIG-AUD (ATTN: Audit Suggestions) Department of Defense Inspector General 400 Army Navy Drive (Room 801) Arlington, VA 22202-4704
Additional Copies To obtain additional copies of this report, visit the Web site of the Department of Defense Inspector General at http://www.dodig.mil/audit/reports or contact the Secondary Reports Distribution
More informationDoD s Efforts to Consolidate Data Centers Need Improvement
Inspector General U.S. Department of Defense Report No. DODIG-2016-068 MARCH 29, 2016 DoD s Efforts to Consolidate Data Centers Need Improvement INTEGRITY EFFICIENCY ACCOUNTABILITY EXCELLENCE INTEGRITY
More informationYour first impression of the title
MANAGEMENT & MEASUREMENT The Business of Metrics Measuring the Product of the Plan How Do You Know What You Know? REAR ADM. DAVE ANTANITUS, USN Your first impression of the title of this article may be
More informationQuality Management Plan
6500m HOV Project Stage 1: A-4500 HOV Document Control No.: 0000000 3-November-2009 WOODS HOLE OCEANOGRAPHIC INSTITUTION WOODS HOLE, MA 02543 Document Control Sheet Date Originator Description 07-28-09
More informationProducts & Services. integration or developmental supply chain program by TWMS resources.
Products & Services Time Wise Management Systems provides training and consulting services, technical platforms and problem solving tools that are relevant and complement supply and value chain management
More informationGAO CONTRACT MANAGEMENT. Small Businesses Continue to Win Construction Contracts. Report to Congressional Committees
GAO United States General Accounting Office Report to Congressional Committees June 2001 CONTRACT MANAGEMENT Small Businesses Continue to Win Construction Contracts GAO-01-746 Contents Letter 1 Results
More informationDEPARTMENT OF THE NAVY FISCAL YEAR (FY) 2007 BIENNIAL BUDGET ESTIMATES JUSTIFICATION OF ESTIMATES FEBRUARY 2006 SHIPBUILDING AND CONVERSION, NAVY
DEPARTMENT OF THE NAVY FISCAL YEAR (FY) 2007 BIENNIAL BUDGET ESTIMATES JUSTIFICATION OF ESTIMATES FEBRUARY 2006 SHIPBUILDING AND CONVERSION, NAVY UNCLASSIFIED DEPARTMENT OF THE NAVY FY 2007 PROCUREMENT
More informationReport No. DODIG-2012-026 November 23, 2011. Air Force Can Improve Controls Over Base Retail Inventory
Report No. DODIG-2012-026 November 23, 2011 Air Force Can Improve Controls Over Base Retail Inventory Additional Copies To obtain additional copies of this report, visit the Web site of the Department
More informationASBESTOS in state and local government
ASBESTOS in state and local government Inspection campaign In 2013/14, WorkSafe WA is conducting a proactive inspection campaign focusing on the management of asbestos in state and local government buildings.
More informationH-1270 - Cost Recovery
H-1270 - Cost Recovery H-1270-2 - COST RECOVERY 1. Explanation of Material Transmitted: This Handbook describes BLM's cost recovery data collection instructions, and cost recovery matrix instructional
More informationStatement for the Record by. Dr. Donald M. Kerr. Director, National Reconnaissance Office, Nominee for the Position of
Statement for the Record by Dr. Donald M. Kerr Director, National Reconnaissance Office, Nominee for the Position of Principal Deputy Director of National Intelligence, before the Senate Select Committee
More informationLeveraging Enterprise Systems for Efficient Quality Management and Regulatory Compliance
Leveraging Enterprise Systems for Efficient Quality Management and Regulatory Compliance Abstract Today s marketplace demands higher quality products and many manufacturers have adopted a corporate quality
More informationTHE NATIONAL SHIPBUILDING RESEARCH PROGRAM
SHIP PRODUCTION COMMITTEE FACILITIES AND ENVIRONMENTAL EFFECTS SURFACE PREPARATION AND COATINGS DESIGN/PRODUCTION INTEGRATION HUMAN RESOURCE INNOVATION MARINE INDUSTRY STANDARDS WELDING INDUSTRIAL ENGINEERING
More informationStrategies For Growth
Capabilities Our Company KITCO Fiber Optics is a leading provider of fiber optic connectorization products and consulting services to the military and commercial communications industry. We specialize
More informationModernizing Operations Management in the Nuclear Energy Industry
Modernizing Operations Management in the Nuclear Energy Industry About this paper Increased global demand for energy has suddenly boosted demand for nuclear reactors worldwide. The industry needs to modernize
More informationHow DCMA Helps To Ensure Good Measurements
How DCMA Helps To Ensure Good Measurements Speaker/Author: Robert Field Defense Contract Management Agency 605 Stewart Avenue Garden City, New York 11530 Email: robert.field@dcma.mil Phone: (516) 228-5886;
More informationInformation Technology
September 11, 2002 Information Technology The Defense Advanced Research Projects Agency s Transition of Advanced Information Technology Programs (D-2002-146) Department of Defense Office of the Inspector
More information9. Quality Assurance 9.1 INTRODUCTION 9.2 FIELD SAMPLING QUALITY ASSURANCE 9.3 ANALYTICAL QUALITY ASSURANCE. 9.3.1 Internal Quality Control
9. Quality Assurance Setting The overall goal of a well-designed and well-implemented sampling and analysis program is to measure accurately what is really there. Environmental decisions are made on the
More information