1 Request For Washington Metropolitan Area Transit Authority Information (RFI) Enterprise Process Scheduling Date: September 26, 2011
2 INTRODUCTORY INFORMATION RFI Enterprise Process Scheduling APPROVED FOR RELEASE END OF SECTION
3 Background/Introduction Introduction This project involves procurement and implementation of an enterprise-level job/process scheduling solution (also known as IT Workload Automation Broker (ITWAB)) which can provide a unified mechanism for managing and monitoring critical applications/os across the organization. This RFI is issued by WMATA on behalf of Data Center and Infrastructure (DCI) Department, hereinafter referred to as Authorized POC. The objective of the project described in this RFI is hereafter referred to as Solution. The terms vendor and supplier will be used synonymously to refer to the entity responsible for providing services to WMATA. Background WMATA s IT business systems involve routine execution of critical background support jobs, with varying frequencies, to perform tasks such as background data transfers within systems, cleanup and relocation of systems logs, systems health checks, nightly systems memory clean up/reboots. Currently, these jobs are either manually executed or automatically scheduled on per-system basis. There is a need for an enterprise-level unified approach for scheduling, ensuring the execution and alerting the subject matter experts. WMATA s IT infrastructure uses heterogeneous operating systems environment which is comprised of AIX, Windows, Solaris and Linux and other flavors of UNIX. Some of the key application platforms included but not limited to PeopleSoft, Maximo, WebSphere, WebLogic, BizTalk, Oracle App Servers, MS-SQL Server Scheduler. The scheduled jobs are exists at multiple tiers to include but not limited to, application servers, Operating System and custom developed application code executed at scheduled intervals. The scheduled jobs functionality spans a broad range to include but not limited to crossapplications data transfers, backups, applications housekeeping functions, internal systems housekeeping functions, and automated systems/application processes restarts. WMATA is using CA Spectrum Suite for Enterprise Monitoring. The backup environment consists of TSM. The backend database platforms supported are Oracle and Microsoft SQL Server (preferred). Systems operate in Microsoft Active Directory and Microsoft Exchange environments. This business initiative is focused towards implementation of a centrally managed Enterprise-level job/process scheduling solution which will minimize chances of human error, proactively ensure critical jobs are attended within timely manner. WMATA intends to implement an enterprise-level job/process scheduling solution in The specific schedule, deliverables and roles and responsibilities are yet to be determined. Vendors are encouraged to provide a best practice solution. Purpose and Objectives WMATA is seeking a geo-redundant job/process scheduling solution based on commercially available well known software product. The proposed software product must carry perpetual licenses and include 3- year maintenance support.
4 The solution must incorporate disaster recovery and high availability as part of design and implementation. The JGB will serve as the primary site for job scheduler with CTF as the secondary site. The proposed solution must have none to minimal interruption to the existing automation processes, during and after the implementation of the solution. The software product proposed in the solution must support WMATA s current environment as indicated in the previous section. The vendor must incorporate post implementation support hours for providing remote/onsite assistance during the first year of the solution rollout. Contract Products and Services to Support the Requirements a. Technical Specification It is WMATA s preference to use Virtual Servers Technology. The current virtual servers environment is based on VMware vsphere 4x infrastructure. WMATA will provision Microsoft Widows Server Operating System. WMATA will also provide physical server hardware, should the accepted solution requires the physical servers. If during analysis, vendor requires physical servers which WMATA needs to procure; vendor must allow 4 to 5 weeks for the hardware procurement, when developing implementation plans. If the proposed solution requires special purpose software and/or non-server hardware, the vendor must provide cost of the software/hardware as a separate line item in the response. It is WMATA s preference to use a single software product to provide job scheduling capabilities. Some of the required key features (which is not an all inclusive list): Ability to schedule jobs across multiple platforms, Workflow-based job executions Ability to trigger existing jobs in the native environment of target system (for cases where WMATA decides to keep certain jobs on the original system). Provide full visibility into execution history of the jobs Ability to detect success/failures of the jobs, ability Event-drive Processing Security and Auditing Queue Management and Job Prioritization Dependencies Management Workload Management Calendaring Role-based Access Control Graphical Reporting Administrator Alerts/Notifications Job-owner Alerts/Notifications Customizable Execution Status Summaries and Reports transmissions to Job-owners Integration with WMATA s Enterprise Monitoring Solution Self-Recovering High Availability Disaster Recovery Scalability SQL Server and Oracle DBMS Support
5 The proposed software product must carry perpetual licenses and include 3-year maintenance support for software/hardware provided by the vendor. The software product proposed in the solution must support WMATA s current environment as indicated in the previous section. The vendor must adhere to the industry best practices for implementation. The vendor must comply with the WMATA IT infrastructure standards and policies. b. Training and Knowledge Transfer It is WMATA s requirement to become self-sufficient in operating or maintaining the solution at its completion. The vendor must determine the type of technical knowledge transfer necessary or such user self-sufficiency. The designated authorized POCs will shadow the vendor throughout the project. The vendor will be responsible for the knowledge transfer of the solution. Vendor must provide formal training of WMATA s support staff for day to day management and administration of the system. c. Support The vendor must incorporate post implementation support hours for providing remote/onsite assistance during the first year of the solution rollout. RFI Response Instructions Interested vendors should review and respond to the RFI. RFI key dates are as follows, 2:00 pm ET: Sept 26, 2011 Sept 30, 2011 October 13, 2011 TBA 2011 RFI made available to the respondents Deadline for submitting questions Deadline to receiving response + supporting documents Decision to launch an RFP / Solicitation All questions related to this RFI should be directed in writing ( ) to: Celena Cochrane Contract Administrator ccochrane@wmata.com Vendors must ensure that your response is delivered to the following address on or before October 13, 2011, 2:00 pm EST with an electronic copy to ccochrane@wmata.com: WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY th Street, NW Washington, DC Room 3C-01 Attn: Celena Cochrane Disclaimer
6 WMATA does not intend to award a contract on the basis of this RFI or otherwise pay for the information solicited. This RFI does not constitute a solicitation for proposals for WMATA to enter into negotiations to award a contract. This RFI is for planning purposes only and shall not be considered as a request for proposal or as an obligation on the part of WMATA to acquire any products or services. No entitlement to payment of direct or indirect costs or charges by WMATA will arise as a result of contractor submission of responses to this RFI or WMATA s use of such information. Responses to this RFI will not be returned. Whatever information is provided in response to this RFI may be used to access tradeoffs and alternatives available for determining how to proceed with the acquisition. Any proprietary information that is submitted may be used in establishing requirements but specific contractor submitted information will be safeguarded as proprietary. The information, responses received in response to this RFI may be shared with other local and federal agencies at the discretion of WMATA. Evaluation Criteria WMATA will select the best value solution for the agency. The following key factors will be used for evaluating the vendor solutions. WMATA may reject disqualify proposals which do not fully and clearly address the requirements of the evaluation criteria. a. Technical Solution - Industry Reputation of the Proposed Software Product - Flexibility and support capabilities of the Software Product (see Contract Products and Services to Support the Requirements) - Simplicity of the Solution - Strength of Technical Implementation Approach to address requirements of this RFI b. Vendor s Past Performance Vendor must be able to demonstrate extensive experience with Job/Enterprise Scheduling Systems Implementation - Vendor has supported at least 3 large implementations with Enterprise Scheduling Implementations for separate customers. Vendor must cite references to the projects, customers, date and duration for the work, description of the technical work performed in direct relation to this project. - Enterprise Scheduling implementation is one of the core competencies of the vendor c. Vendor s Bench Strength The vendor must clearly show its ability to quickly and seamlessly provision an equivalent or better technical resources should such as need arise. - Provide bench strength, for enterprise job scheduling resources, maintained over the past 12 months - Clearly indicate the maximum number of days it will take for the vendor to replace the onsite resource should such a need arise Submittal Requirements Vendor must provide the following as part of the RFP: a. A detailed technical solution - The vendor must specifically address how it will achieve the services availability objectives asked for in this RFI - The vendor must specially address Disaster Recovery of the solution b. Past performance related to the scope of this RFI.
7 - Provide core competency of your business - Provide number of years for which the vendor has been in business - Provide number of years performing the work similar to this RFI - Provide at least 3 separate customers references which WMATA may call - Provide the type of support contract providing similar servers as required in this RFI, duration of the contact, date of award of the contract - Provide the sizes of the organizations supported thru the contracts submitted as an evidence of the past performance - Provide size and type of the RFI-scope-specific environment supported on each of contracts submitted as evidence of the past performance - Clearly indicate if the past contracts completed their period of performance. If the period of performance was not completed, an explanation must be provided. c. Personnel resumes which reflect potential technical resources which may work on the project. The vendor should clearly indicate if the proposed technical personnel will actually be assigned to the project or if the resumes are provided only as a sample only.
. Request For Information
M met rd Washington Metropolitan Area Transit Authority.. Request For Information IT RFI NO. IT-IVR/JF Date: December 5, 2014 Date: December 5, 2014 SUBJECT: RFI No. IT-IVR/JF Dear Sir/Madam: The Washington
More informationRequest. For. Information (RFI) Years of Service Employee Recognition Program. Washington Metropolitan Area Transit
Request For Washington Metropolitan Area Transit Information (RFI) Years of Service Employee Recognition Program Date Published: January 3, 2014 1. Executive Summary The 12,000 employees of Metro make
More informationRequest for Proposal. Contract Management Software
Request for Proposal Contract Management Software Ogden City Information Technology Division RETURN TO: Ogden City Purchasing Agent 2549 Washington Blvd., Suite 510 Ogden, Utah 84401 Attn: Sandy Poll 1
More informationRFP-FQ-11229/JP SQL Server Questions and Answers January 7, 2010
RFP-FQ-11229/JP SQL Server Questions and Answers January 7, 2010 Note: Availability requirements have been updated from 99.999% to 99.99% or higher. Q1. How many physical servers are in the WMATA environments
More informationREQUEST FOR INFORMATION (RFI) Health Interface Engine Solution
City of Philadelphia Department of Public Health 1401 JFK Blvd Suite 600 Philadelphia, PA 19102 REQUEST FOR INFORMATION (RFI) This document contains a Request for Information (RFI) for an interface engine
More informationRequest for Proposals (RFP) Managed Services, Help Desk and Engineering Support for Safer Foundation www.saferfoundation.org
Request for Proposals (RFP) Managed Services, Help Desk and Engineering Support for Safer Foundation www.saferfoundation.org IMPORTANT NOTICE All proposal question and inquiries must be sent by email to
More informationManaged Service Plans
Managed Service Plans www.linkedtech.com 989.837.3060 989.832.2802 fax Managed Information Technology Services System downtime, viruses, spy ware, losses of productivity Are the computer systems you rely
More informationState of Texas Office of the Attorney General (OAG)
State of Texas Office of the Attorney General (OAG) REQUEST FOR INFORMATION (RFI) CLASS:920 ITEM: 22 CLASS:920 ITEM: 30 KEY DATES: RFI Posting Date: June 5, 2015 Questions Deadline: 3:00 p.m. Local Time
More informationSymantec and VMware: Virtualizing Business Critical Applications with Confidence WHITE PAPER
Symantec and VMware: Virtualizing Business Critical Applications with Confidence WHITE PAPER Challenges of Using Traditional High-Availability Solutions Business-critical applications and the systems they
More informationPC-WARE realises a consistent backup system for 70 international locations with CA ARCserve
CUSTOMER SUCCESS STORY PC-WARE realises a consistent backup system for 70 international locations with CA ARCserve CUSTOMER PROFILE Company: PC-Ware Information Technologies AG Industry: ICT services Employees:
More informationREQUEST FOR PROPOSAL
CITY OF MUKILTEO 11930 Cyrus Way Mukilteo, Washington 98275 425-263-8030 www.ci.mukilteo.wa.us REQUEST FOR PROPOSAL IT SERVICES ACQUISTION SCHEDULE The Acquisition Schedule is as follows, with all times
More informationFDR/UPSTREAM. Simplified Enterprise Backup
FDR/UPSTREAM Simplified Enterprise Backup FDR/UPSTREAM If you need a backup product that is flexible, simple-to-use and very cost-effective, with a personalized technical support model, look no further!
More information14-ITN-001-KH Workforce Services IT Procurement Project Questions and Answers
Respondent Question Number ITN Page Number, Section Number, Subsection Reference 1. Attachment R, Page #1, REQ #9, REQ Section: General System 2. Attachment R, Page #5, REQ #41, REQ Section: Case 3. Attachment
More information3.1. Broad Use. 3.2. Presence
City of Asheville Specifications Enterprise Asset Management RFP # 298-WaterAssetManagement July 1, 2016 Jade Dundas, Water Resources Director (828) 259-5955 Table of Contents 1. Introduction... 2 2. General
More informationState of Iowa REQUEST FOR INFORMATION. RFI #1217005002 State of Iowa ERP System Maintenance, Upgrades and Services
State of Iowa REQUEST FOR INFORMATION RFI #1217005002 State of Iowa ERP System Maintenance, Upgrades and Services Section 1- Background and Objectives 1.1 Purpose The objective of this Request for Information
More informationAdditional Offeror Qualifications: Not applicable.
Category 1: IBM Host Systems Support Services shall include configuration design, installation, maintenance, modification, monitoring and/or evaluation of operating systems and secondary support software
More informationTexas Skyward User Group Conference Skyward Server Management Options Jeffery Thompson
Texas Skyward User Group Conference Skyward Server Management Options Jeffery Thompson Server Management Options Managed Services Overview Secure Cloud Computing (SCC) Hosted Overview OpenEdge Management
More informationHow To Find A Vendor For Parcc, Inc.
1 Cover Page Date: January 28, 2015 Customer Name: Parcc, Inc. Vendor Name: 2 Section 1: Background, Purpose, and Scope Parcc, Inc. is a separate education policy nonprofit organization. Parcc, Inc. is
More informationSENIOR SYSTEMS ANALYST
CITY OF MONTEBELLO 109 DEFINITION Under general administrative direction of the City Administrator, provides advanced professional support to departments with very complex computer systems, programs and
More informationSapphireIMS 4.0 BSM Feature Specification
SapphireIMS 4.0 BSM Feature Specification v1.4 All rights reserved. COPYRIGHT NOTICE AND DISCLAIMER No parts of this document may be reproduced in any form without the express written permission of Tecknodreams
More informationRequest for Information RFI #15/16-300 for Enterprise Password Management Software
Company Name: This RFI response has been submitted by: Address: (Street, Su. # City, State, Zip) Request for Information RFI #15/16-300 for Enterprise Password Management Software Contact Name: Telephone
More informationREQUEST FOR PROPOSAL Website Design and Development. DUE DATE: FEBRUARY 19, 2016-12:00 p.m.
REQUEST FOR PROPOSAL Website Design and Development DUE DATE: FEBRUARY 19, 2016-12:00 p.m. City of Willow Park 516 Ranch House Rd. Willow Park, Texas 76087 (817) 441 7108 www.willowpark.org Inquiries Inquiries
More informationCA Scheduler Job Management r11
PRODUCT SHEET CA Scheduler Job Management CA Scheduler Job Management r11 CA Scheduler Job Management r11 (CA Scheduler JM), part of the Job Management solution from CA Technologies, is a premier z/oscentric
More informationCity of Crestview, Florida Website Design & Development
No. 16-02 City of Crestview, Florida Website Design & Development City of Crestview 198 Wilson North Street Crestview, Florida 32536 Inquiries Inquiries about this should be directed to: Elizabeth Roy
More informationMARION COUNTY Information Technology. REQUEST FOR INFORMATION Integrated IT Help Desk Client Management Software Suite
MARION COUNTY Information Technology REQUEST FOR INFORMATION Integrated IT Help Desk Client Management Software Suite DATE & TIME RESPONSES ARE DUE: January 2, 2015, at 2:00 PM Envelope(s) shall be sealed
More informationProsecutorial Case Management System Maintenance/Enhancement Support Services. Request for Proposal: RFP # 7549208
RFP # 7549208 Solicitation Information December 12, 2014 TITLE: Prosecutorial Case Management System Maintenance/Enhancement Support Services Submission Deadline: Wednesday, January 14, 2015 at 2:00 PM
More informationSolicitation 1210-014. Web Hosting Services for the Disaster Volunteer Network. State of California
Solicitation 1210-014 Web Hosting Services for the Disaster Volunteer Network State of California Oct 12, 2012 4:28:36 PM PDT p. 1 Bid 1210-014 Web Hosting Services for the Disaster Volunteer Network Bid
More informationREQUEST FOR INFORMATION FLORIDA AGENCY FOR STATE TECHNOLOGY CLOUD SERVICES AND SOLUTIONS RFI NO.: 150925
I. PURPOSE REQUEST FOR INFORMATION FLORIDA AGENCY FOR STATE TECHNOLOGY CLOUD SERVICES AND SOLUTIONS RFI NO.: 150925 The State of Florida, Agency for State Technology (AST), hereby issues this Request for
More informationRFP-00118 ADDENDUM NO. 1
INTERNAL SERVICES DEPARTMENT PROCUREMENT MANAGEMENT SERVICES 111 NW 1 ST Street Suite 1300 Miami, Florida 33128-1974 Telephone: 305-375-4725 Fax: (305) 375-5688 RFP-00118 ADDENDUM NO. 1 DATE: March 26,
More informationAttachment E. RFP Requirements: Mandatory Requirements: Vendor must respond with Yes or No. A No response will render the vendor nonresponsive.
Attachment E RFP Requirements: Mandatory Requirements: Vendor must respond with Yes or No. A No response will render the vendor nonresponsive. Questions Support for Information Security 1. The Supplier
More informationCITY OF WICHITA FALLS
CITY OF WICHITA FALLS RFP #09-09 LASERFICHE DOCUMENTS MANAGEMENT SOLUTION PROPOSAL DUE DATE DECEMBER 17, 2009 2:00PM REQUEST FOR ADDITIONAL INFORMATION NOVEMBER 24, 2009 2:00PM ADDENDUM ISSUED DECEMBER
More informationConverse County Website Design & Development
No. IT-16-01 Converse County Website Design & Development Converse County 107 North 5 th Street Suite B4 Douglas, WY 82633 Inquiries Inquiries about this must be in writing and directed to: Justin Lane
More information2. Highlights and Updates: ITSM for Databases
IBM Tivoli Storage Manager Data Protection for Oracle Neil Rasmussen Software Development for Tivoli Data Protection Tivoli Software, IBM SWG rasmussn@us.ibm.com Agenda 1. Overview: Tivoli Storage Manager
More informationHow To Write An Ets Request For Proposal (Rfp)
Oregon Enterprise Technology Services (ETS) Customer Requests ETS customers issuing RFPs to support application development initiatives often have hardware requirements. Standards and guidelines for equipment
More informationRequest for Proposal Mobile Device Management System
Request for Proposal Mobile Device Management System Introduction The Hall County School System (HCSS) in Northeast Georgia has thirty-three schools with approximately 27,000 students and 3,000 staff members.
More informationCounselorMax and ORS Managed Hosting RFP 15-NW-0016
CounselorMax and ORS Managed Hosting RFP 15-NW-0016 Posting Date 4/22/2015 Proposal submission deadline 5/15/2015, 5:00 PM ET Purpose of the RFP NeighborWorks America has a requirement for managed hosting
More informationHow To Use Ibm Tivoli Monitoring Software
Monitor and manage critical resources and metrics across disparate platforms from a single console IBM Tivoli Monitoring Highlights Help improve uptime and shorten Help optimize IT service delivery by
More information1 OPPORTUNITY SUMMARY
REQUEST FOR PROPOSALS: MANAGED SERVICES FOR INFRASTRUCTURE AND IT SUPPORT SERVICES Posting Date: Thursday, January 7, 2016 Due Date: Friday, February 5, 2016 1 OPPORTUNITY SUMMARY The Massachusetts Clean
More informationVendors Questions for RFP DBA and System Administration Support
Vendors Questions for RFP DBA and System Administration Support Vendor A 1. Page 16 of 33 under scalability of services provided: "The Respondent should also be prepared to manage the transition of all
More informationIBM Tivoli Service Request Manager
Deliver high-quality services while helping to control cost IBM Tivoli Service Request Manager Highlights Streamline incident and problem management processes for more rapid service restoration at an appropriate
More informationADDENDUM #1 TO RFP #16-608794-cs Facilities Project Management Software
ADDENDUM #1 TO RFP #16-608794-cs Facilities Project Management Software DATE OF RELEASE OF ADDENDUM #1: 3/17/16 1. In the RFP Proposed Schedule of Events, the submission deadline is March 31, 2016. Will
More informationIBM Maximo Asset Management for IT
Cost-effectively manage the entire life cycle of your IT assets IBM Highlights Help control the costs and financial impact of IT assets with a single solution that tracks and manages your hardware, software
More informationCompliance Procedure
Old Dominion University Compliance Procedure Title: Reference Number: System Backups and Restoration (Non- Db) Procedure 3.4.2.2 Purpose The purpose of this compliance procedure is to define the methods
More informationElectoral Commission. Auction # 10220759. Patch Management Solution
Electoral Commission Auction # 10220759 Patch Management Solution IMPORTANT NOTICE Failure to comply with the completion of the auction conditions and the required information (i.e. Make, model and size
More informationREDCENTRIC MANAGED BACKUP SERVICE SERVICE DEFINITION
REDCENTRIC MANAGED BACKUP SERVICE SERVICE DEFINITION SD003 V2.3 Issue Date 02 July 2014 1) SERVICE OVERVIEW The Managed Backup Service (MBS) is a streamlined alternative to traditional backup and restore
More informationModule 5 Introduction to Processes and Controls
IT Terminology 1. General IT Environment The general IT environment is the umbrella over the following IT processes: 1. Operating Systems 2. Physical and Logical Security 3. Program Changes 4. System Development
More informationOptimos Enterprise Helpdesk Automation Solution Case Study
Optimos Enterprise Helpdesk Automation Solution Case Study IT Help Central National Science Foundation Optimos Incorporated 4455 Brookfield Corporate Drive Chantilly, VA 20151 Telephone: (703) 488-6900
More information2013 USER GROUP CONFERENCE
2013 USER GROUP CONFERENCE Server Management Options Managed Services Overview ASP Hosted Overview OpenEdge Management / OpenEdge Explorer OpenEdge Managed Demo Skyward Managed Services The intent of the
More informationREQUEST FOR PROPOSAL (RFP) for Provide Document Imaging & Archiving Solution And Develop Application Process Workflow on MS SharePoint
REQUEST FOR PROPOSAL (RFP) for Provide Document Imaging & Archiving Solution And Develop Application Process Workflow on MS SharePoint May 2016 Housing Development Finance Corporation Plc. Information
More informationProduct Overview. UNIFIED COMPUTING Managed Hosting - Storage Data Sheet
Product Overview Interoute offers a range of managed storage solutions to provide the best fit for our customers budget, capacity, performance and compliance needs. By taking advantage of our unrivalled
More informationDomain Name Service Service Level Agreement (SLA) Vanderbilt Information Technology Services
Service Level Agreement Page 1 of 7 Domain Name Service Service Level Agreement (SLA) Vanderbilt Information Technology Services 1. Agreement This agreement is to define Domain Name Service (DNS) provided
More informationIBM Implementation Services for Power Systems IBM Systems Director
Sample Statement of Work for Services This an example and your Statement of Work may vary given your specific requirements and the related IBM engagement. IBM Implementation Services for Power Systems
More informationHigh Availability Implementation for JD Edwards EnterpriseOne
High Availability Implementation for JD Edwards EnterpriseOne Ken Yeh, Manager, ERP Systems/JDE Enersource Colin Dawes, Director of Technology Services, Syntax Presentation Abstract Enersource Corporation
More informationRequest for Information (RFI) For providing An Information Technology Services Management Solution. RFI No. R25CD14213
Request for Information (RFI) For providing An Information Technology Services Solution RFI No. R25CD14213 RFI No. R25CD14213 Overview The Information Technology Department (ITS) at the Toronto Transit
More informationSOLICITATION AMENDMENT
SOLICITATION AMENDMENT Solicitation No: P08-0076 Description: Business Continuity Plan Amendment No: One (1) Solicitation Due Date: April 15, 2008 Solicitation Due Time: 4:00PM Local Arizona Time Telephone:
More informationUniversity at Buffalo Learning Management and Performance Management System Request for Information # 14CBW0036
University at Buffalo Learning Management and Performance Management System Request for Information # 14CBW0036 Background The University at Buffalo (UB), The State University of New York is a major public
More informationSystem Center 2012 Suite SYSTEM CENTER 2012 SUITE. BSD BİLGİSAYAR Adana
2013 System Center 2012 Suite SYSTEM CENTER 2012 SUITE BSD BİLGİSAYAR Adana Configure and manage apps, services, computers, and VMs... 1 Operations Manager... 3 Configuration Manager... 4 Endpoint Protection...
More informationCloud-based Managed Services for SAP. Service Catalogue
Cloud-based Managed Services for SAP Service Catalogue Version 1.8 Date: 28.07.2015 TABLE OF CONTENTS Introduction... 4 Managed Services out of the Cloud... 4 Cloud-based Flexibility, Efficiency and Scalability...
More informationEMC Data Protection Advisor 6.0
White Paper EMC Data Protection Advisor 6.0 Abstract EMC Data Protection Advisor provides a comprehensive set of features to reduce the complexity of managing data protection environments, improve compliance
More informationDeadline for submission of completed RFP questionnaire is 8/3/2015.
I. Introduction A. Overview The LOTT Clean Water Alliance is a non-profit corporation responsible for wastewater management services for the urban area of north Thurston County, Washington. Its services
More informationApproximately 260 PST files totaling 180GB will be included in the pilot. 2. Are the Windows XP clients running XP 64 bit or 32 bit OS?
Addendum #1 1. What is the count of PST files and total aggregate size of PST files that will need to be ingested for the pilot? Approximately 260 PST files totaling 180GB will be included in the pilot.
More informationDoes my server customer need to Modernize their Active Directory infrastructure?
Does my server customer need to Modernize their Active Directory infrastructure? Top reasons customers buy new servers Top drivers to Modernize your Active Directory Update/retire obsolete systems To account
More informationIBM Service Management solutions White paper. Make ITIL actionable with Tivoli software.
IBM Service solutions White paper Make ITIL actionable with Tivoli software. June 2008 2 Contents 2 Introduction 3 ITIL: best practices for best results 4 Support ITIL best practices with comprehensive
More informationEnforcive /Cross-Platform Audit
Enforcive /Cross-Platform Audit Enterprise-Wide Log Manager and Database Activity Monitor Real-time Monitoring Alert Center Before & After Change Image Custom Reports Enforcive's Cross-Platform Audit (CPA)
More informationPUBLIC UTILITY COMMISSION OF TEXAS
PUBLIC UTILITY COMMISSION OF TEXAS REQUEST FOR INFORMATION For A Document Management System Public Utility Commission of Texas William B. Travis Building 1701 North Congress Ave. Austin, Texas 78711 Closing
More informationensurcloud Service Level Agreement (SLA)
ensurcloud Service Level Agreement (SLA) Table of Contents ensurcloud Service Level Agreement 1. Overview... 3 1.1. Definitions and abbreviations... 3 2. Duties and Responsibilities... 5 2.1. Scope and
More informationOUTAGAMIE COUNTY REQUEST FOR INFORMATION / PROPOSAL FOR ENTERPRISE BACKUP SOLUTION FOR MIS DEPARTMENT
OUTAGAMIE COUNTY REQUEST FOR INFORMATION / PROPOSAL FOR ENTERPRISE BACKUP SOLUTION FOR MIS DEPARTMENT DUE BY: April 10, 2012 ADMINISTRATIVE INFORMATION 1.0 Introduction and Background The Outagamie County
More informationRequest for Information PM07212011 CONTRACT MANAGEMENT SOLUTION
Request for Information PM07212011 CONTRACT MANAGEMENT SOLUTION July 21, 2011 1 Table of Contents I. Introduction and Purpose of Request For Information... 1 II. Background... 2 III. Description of Information
More informationLEGAL SERVICES CORPORATION REQUEST FOR PROPOSAL FOR DEVELOPMENT OF E-LEARNING TRAINING COURSE
LEGAL SERVICES CORPORATION REQUEST FOR PROPOSAL FOR DEVELOPMENT OF E-LEARNING TRAINING COURSE OCTOBER 14, 2015 INTRODUCTION Legal Services Corporation (LSC) invites your company to submit a proposal for
More informationIT Infrastructure Management
IT Infrastructure Management Server-Database Monitoring An Overview XIPHOS TECHNOLOGY SOLUTIONS PVT LIMITED 32/3L, GARIAHAT ROAD (SOUTH) KOLKATA 700 078, WEST BENGAL, INDIA WWW.XIPHOSTEC.COM Xiphos Technology
More informationREQUEST FOR PROPOSALS Technical Assistance - Networking Systems. April 26, 2013 LEGISLATIVE FINANCE COMMITTEE 325 DON GASPAR, SUITE 101
REQUEST FOR PROPOSALS Technical Assistance - Networking Systems April 26, 2013 LEGISLATIVE FINANCE COMMITTEE 325 DON GASPAR, SUITE 101 SANTA FE, NEW MEXICO 87501 (505) 986-4550 I. INTRODUCTION A. BACKGROUND
More informationCity of Richmond Business and Financial Services Department. Contract 4595P. Security Information Event Management System
Business and Financial Services Department Request for Proposal Security Information Event Management System 1. Introduction The City of Richmond (the City ) requires a Security Information and Event Management
More informationIntroduction and Background
Ocean Springs School District Invitation to Bid Data Backup and Recovery Solution The Ocean Springs Board of Education invites you to submit a bid on a comprehensive Backup and Recovery Solution for Ocean
More informationOracle Maps Cloud Service Enterprise Hosting and Delivery Policies Effective Date: October 1, 2015 Version 1.0
Oracle Maps Cloud Service Enterprise Hosting and Delivery Policies Effective Date: October 1, 2015 Version 1.0 Unless otherwise stated, these Oracle Maps Cloud Service Enterprise Hosting and Delivery Policies
More informationREQUEST FOR PROPOSAL STORAGE AREA NETWORK SOLUTIONS FOR THE PARK CITY SCHOOL DISTRICT RFP # 032612
REQUEST FOR PROPOSAL STORAGE AREA NETWORK SOLUTIONS FOR THE PARK CITY SCHOOL DISTRICT RFP # 032612 The Park City School District is soliciting RFP s from qualified professional firms with the intention
More informationBackup and Recovery in Laserfiche 8. White Paper
Backup and Recovery in Laserfiche 8 White Paper July 2008 The information contained in this document represents the current view of Compulink Management Center, Inc on the issues discussed as of the date
More informationREQUEST FOR PROPOSAL (RFP)
REQUEST FOR PROPOSAL (RFP) Subject: Due Date/Time: Submit To: Financial Management & Utility Billing Software March 28, 201412:00 pm Eastern Standard Time Chris Wilson Village of Beverly Hills 18500 W
More informationCA SiteMinder SSO Agents for ERP Systems
PRODUCT SHEET: CA SITEMINDER SSO AGENTS FOR ERP SYSTEMS CA SiteMinder SSO Agents for ERP Systems CA SiteMinder SSO Agents for ERP Systems help organizations minimize sign-on requirements and increase security
More informationSapphireIMS Business Service Monitoring Feature Specification
SapphireIMS Business Service Monitoring Feature Specification All rights reserved. COPYRIGHT NOTICE AND DISCLAIMER No parts of this document may be reproduced in any form without the express written permission
More informationCA Virtual Assurance/ Systems Performance for IM r12 DACHSUG 2011
CA Virtual Assurance/ Systems Performance for IM r12 DACHSUG 2011 Happy Birthday Spectrum! On this day, exactly 20 years ago (4/15/1991) Spectrum was officially considered meant - 2 CA Virtual Assurance
More informationSEALED BID REQUEST FOR INFORMATION
Department of Buildings and General Services Purchasing & Contract Administration 10 Baldwin St. Agency of Administration Montpelier VT 05633 [phone] 802-828-2210 [Fax] 802-828-2222 www.bgs.state.vt.us
More informationSALEM STATE UNIVERSITY
SALEM STATE UNIVERSITY INVITATION TO BID THIS IS NOT AN ORDER 1. The university is an agency of the Commonwealth of Massachusetts and is exempt from any State tax or Federal excise tax 2. Unless otherwise
More informationTools for ITIL Capacity Management: How not to spend 100,000
Tools for ITIL Capacity Management: How not to spend 100,000 Danny Quilton Capacitas dannyquilton@capacitas.co.uk Abstract Capacity Management requires data to produce meaningful deliverables such as models
More informationEnterprise Governance and Planning
GEORGIA TECHNOLOGY AUTHORITY Title: Enterprise Operational Environment PSG Number: SO-10-003.02 Topical Area: Operations / Performance and Capacity Document Type: Standard Pages: 5 Issue Date: July 15,
More informationSubject: Request for Information (RFI) Franchise Tax Board (FTB) Security Information and Event Management (SIEM) Project.
chair John Chiang member Jerome E. Horton member Ana J. Matosantos August 27, 2012 To: Potential Vendors Subject: Request for Information (RFI) Franchise Tax Board (FTB) Security Information and Event
More informationRequest for Proposal Managed IT Services 7 December 2009
Request for Proposal Managed IT Services 7 December 2009 BuzzBack, LLC 25 West 45 th Street Suite 202 New York, NY 10036 Table of Contents 1 Summary... 1 2 Proposal Guidelines and Requirements... 1 2.1
More informationBuyer s Guide Checklist - What to Look For in Online Backup and Recovery Services
Introduction We are often asked, "How do I go about selecting an online data backup and recovery service?" Our Data Mountain White Paper answers that question and this accompanying Buyer s Guide Checklist
More informationReal-Time Database Protection and. Overview. 2010 IBM Corporation
Real-Time Database Protection and Monitoring: IBM InfoSphere Guardium Overview Agenda Business drivers for database security InfoSphere Guardium architecture Common applications The InfoSphere portfolio
More informationDocument Management System Request for Proposals April 22, 2013
FINANCE DEPARTMENT Office (402) 562-4231 Fax (402) 563-1380 Document Management System Request for Proposals April 22, 2013 Overview: The City of Columbus, Nebraska (hereafter referred to as City ) is
More information1 OPPORTUNITY SUMMARY
REQUEST FOR PROPOSALS: SOFTWARE IMPLEMENTATION PROJECT MANAGEMENT SERVICES Posting Date: Wednesday, September 23, 2015 Due Date: Tuesday, October 13, 2015 1 OPPORTUNITY SUMMARY The Massachusetts Clean
More informationBMC CONTROL-M AUTOMATE AND INTEGRATE YOUR BATCH AND ONLINE PROCESSES ACROSS THE ENTERPRISE.
BMC CONTROL-M AUTOMATE AND INTEGRATE YOUR BATCH AND ONLINE PROCESSES ACROSS THE ENTERPRISE. DRIVE OPTIMIZE DRIVE YOUR BUSINESS WITH ENTERPRISE SCHEDULING. BMC CONTROL-M is a best-of-breed enterprise scheduling
More informationIBM Tivoli Storage FlashCopy Manager
IBM Storage FlashCopy Manager Online, near-instant snapshot backup and restore of critical business applications Highlights Perform near-instant application-aware snapshot backup and restore, with minimal
More informationIT Sr. Systems Administrator
IT Sr. Systems Administrator Location: [North America] [United States] [Monrovia] Category: Information Technology Job Type: Open-ended, Full-time PURPOSE OF POSITION: Systems Administrators and Engineers
More informationProtecting your Data in a New Generation Virtual and Physical Environment
Protecting your Data in a New Generation Virtual and Physical Environment Read this white paper to learn how you can easily and safely protect your data in a new generation virtual and physical IT environment,
More informationHow To Move From Iseries To Iseries Content Manager On A Microsoft Computer (For A Non-Profit)
Enterprise Content Management Request For Information Issue Date: October 18, 2013 Table of Contents Request for Information: Purpose, Scope, and Objectives 4 Louisiana State Employees Retirement System
More informationMayur Dewaikar Sr. Product Manager Information Management Group Symantec Corporation
Next Generation Data Protection with Symantec NetBackup 7 Mayur Dewaikar Sr. Product Manager Information Management Group Symantec Corporation White Paper: Next Generation Data Protection with NetBackup
More informationREQUEST FOR INFORMATION (RFI) DRCI-16-2209 PREVENTATIVE MAINTENANCE OPTIMIZATION SYSTEM
Date February 1, 2016 Page 1 REQUEST FOR INFORMATION (RFI) PREVENTATIVE MAINTENANCE OPTIMIZATION SYSTEM RESPONSE DEADLINE: RFI responses are due by to Noon, Local Time on Tuesday, February 16, 2016 ADDRESS
More informationManagement Packs for Database
Management Packs for Database Diagnostics Pack for Database Oracle Diagnostics Pack for Database offers a complete, cost-effective, and easy to use solution for managing the performance of Oracle Database
More informationInfrastructure Technical Support Services. Request for Proposal
Infrastructure Technical Support Services Request for Proposal 15 May 2015 ISAAC reserves the right to reject any and all proposals, with or without cause, and accept proposals that it considers most favourable
More informationTHE LOGICAL CHOICE FOR ONLINE DATA PROTECTION. Brought to you by
THE LOGICAL CHOICE FOR ONLINE DATA PROTECTION Brought to you by VaultLogix Classic Online Backup VAULTLOGIX CLASSIC ONLINE BACKUP WHY BACK UP CRITICAL APPLICATIONS ONLINE/OFFSITE? Your financial records,
More information