ROXBURY PARK PLAY AREAS RENOVATION CITY OF BEVERLY HILLS TECHNICAL SPECIFICATIONS TABLE OF CONTENTS

Size: px
Start display at page:

Download "ROXBURY PARK PLAY AREAS RENOVATION CITY OF BEVERLY HILLS TECHNICAL SPECIFICATIONS TABLE OF CONTENTS"

Transcription

1 ROXBURY PARK PLAY AREAS RENOVATION CITY OF BEVERLY HILLS TECHNICAL SPECIFICATIONS TABLE OF CONTENTS DIVISION 2 SITE CONSTRUCTION SITE DEMOLITION SITE CLEAR AND GRUB SITE GRADING SUBGRADE PREPARATION EARTHWORK TEMPORARY CHAIN LINK FENCING PLAY EQUIPMENT SITE FURNISHINGS CONCRETE PAVING AND CURBS RESILIENT SURFACING UNIT PAVERS SYNTHETIC TURF DIVISION 3 CONCRETE CONCRETE FORMWORK CONCRETE REINFORCEMENT CAST-IN-PLACE CONCRETE FOOTINGS AND FOUNDATIONS CONCRETE CURING

2 SECTION SITE DEMOLITION PART 1 - GENERAL 1.01 RELATED DOCUMENTS: The requirements of the Standard Specifications for Public Works Construction (SSPWC), latest edition, Parts 2 through 6, apply to this project and are incorporated herein by this reference. Part 1 is specifically excluded. Drawings, project manual, and general provisions of the Contract, including, without limitation, General Conditions of the Contract, additional General Conditions of the Contract, and Division 1 specification sections, apply to this section SCOPE OF WORK A. Furnish materials, labor, transportation, services, and equipment necessary to perform all site demolition work as indicated on the Drawings complete as shown and as specified herein. B. Related Work: Sub-grade Preparation Section Earthwork Section REFERENCES A. Comply with the applicable reference specifications as specified in the GENERAL PROVISIONS and in accordance with applicable laws, codes and regulations required by the City. B. Comply with the current provisions of the following Codes and Standards: 1. ASTM - American Society for Testing and Materials. 2. Standard Specifications B Agency Specified 3. Uniform Building Code 1.04 QUALITY ASSURANCE A. Regulatory Requirements: Demolish existing site improvements as indicated on the Drawings, in an orderly and careful manner. Comply with all local codes and ordinances. B. Equipment: Use equipment specifically designed for the demolition of each type of material. C. Labor: Employ workmen skilled in the use of the equipment being utilized for demolition DELIVERY, STORAGE, AND DISPOSAL A. Delivery and Storage: Do not deliver to the job site nor store thereon demolition equipment and materials prior to receiving written notice to proceed. Confine storage to areas approved by the City. Site Demolition

3 B. Disposal: Legally dispose of off site products of demolition during or at end of each day's work. Contractor shall pay all disposal costs associated with the project PROJECT CONDITIONS A. Existing Conditions: Inspect site prior to commencing work. Determine scope of applicable site conditions. Prior to commencement of demolition activities, Contractor shall document in writing and photograph all existing conditions, including, without limitation, sidewalks, curbs, walls, trees, fencing, and other elements. Digital copies of all photos, at a size no smaller than 4" x 6" at 150 dpi minimum resolution, shall be provided to the City and Project Landscape Architect for future reference. The contractor shall be held responsible for any damages not documented in the submittal prior to commencement of demolition activities. B. Access and Testing: Make test excavations and borings required to determine existing conditions, subject to City's convenience. C. Acceptance: Commencing work constitutes Contractor's acceptance of site conditions, both surface and subsurface. No extra payment shall accrue to Contractor by virtue of unknown conditions or difficulties of performing this demolition work PROTECTION A. Protection of Existing Trees and Shrubs to Remain 1. Operations: Do not store materials or equipment, permit burning, or operate or park equipment under the branches of existing plants to remain except as actually required for construction in those areas. 2. Barriers: Provide barricades, fences or other barriers as necessary at the drip line to protect existing plants to remain from damage during construction. 3. Notification: Notify City representative when Contractor feels construction activities may damage existing plants to remain. 4. Replacement of Damaged Plants: a. Replace existing plants to remain that are damaged during construction with accepted plants of the same species and size as those damaged at no cost to City. b. The City representative will determine extent of damage and value of damaged plants. B. Protection of Existing Site Improvements 1. References: Verify and maintain benchmarks, monuments and other reference points. Replace if disturbed or destroyed. 2. Protection: Protect existing improvements noted to remain within designated limit(s) of work. Supply shoring, bracing, reinforcing and barricades as required. Refer to drawings for limit of work. Site Demolition

4 Hand excavate, expose, and report any root(s) below the surface of the concrete pavers that is 3 in diameter of larger. Do not cut any root larger than 3 prior to inspection, and direction from City representatives. 3. Utilities: Keep in operation existing utility circuits and piping to remain including sprinkler irrigation except at the direction of the Project Engineer. Provide 48-hour notice of interruption of service. Notify Project Engineer should utilities not shown on Drawings be found during demolition. 4. Repair: If damage to site improvements to remain occurs during the course of the work, restore to the satisfaction of the City at no additional cost. PART 2 B NOT APPLICABLE PART 3 B EXECUTION 3.01 PREPARATION A. Verification: Verify with the City representative items to be removed prior to commencement of work. B. Compliance: Proceed with demolition in an orderly and careful manner, in compliance with local codes and ordinances. C. Disposal: Legally dispose of demolished materials off site unless otherwise directed by the City representative DEMOLITION A. Utilities: 1. Capping: Disconnecting and capping of utilities must be in accordance with the regulations of the utility company affected. B. Paving and Walls: 1. Sawcutting: Accurately and cleanly sawcut existing concrete paving, if necessary, and as directed in field by City representative and/or Landscape Architect. 2. Finishing: Rough grade excavated areas as necessary to achieve the final line and grade to match existing, surrounding areas. Compact the grade to the density of the surrounding area. The final surface shall be smooth, even and tight, free from loose or soft areas. C. Subgrade: Fill depressions made by demolition and restore excavated areas to a smooth and even grade. Compact the grade to the density of the surrounding soil. Site Demolition

5 3.03 DE-WATERING A. General: Provide and operate equipment and do ditching and pumping necessary to keep the project area free from water. B. Storm Water: Pump off storm runoff or other water until such time as new work in other Sections shall effectively remove such water. C. Protection: Take measures required to dispose of surface and subsurface water in compliance with municipal requirements. D. Debris: Prevent transport of soil, aggregate or debris off site where practical. END OF SECTION Site Demolition

6 SECTION SITE CLEAR AND GRUB PART 1 - GENERAL 1.01 RELATED DOCUMENTS: The requirements of the Standard Specifications for Public Works Construction (SSPWC), latest edition, Parts 2 through 6, apply to this project and are incorporated herein by this reference. Part 1 is specifically excluded. Drawings, project manual, and general provisions of the Contract, including, without limitation, General Conditions of the Contract, additional General Conditions of the Contract, and Division 1 specification sections, apply to this section SCOPE OF WORK: Furnish all material, equipment and labor necessary to perform all clearing and grubbing work complete, including but not limited to the following: Protection of trees indicated on drawings to remain. Clearing and grubbing of all vegetation from site work areas. Removal and disposal of all deleterious materials. Furnishing, developing, applying and providing dust control watering equipment as required for the project RELATED WORK SPECIFIED ELSEWHERE: Site grading Section RESPONSIBILITY AND COORDINATION: Contractor shall secure and maintain all required permits and licenses, and pay all fees necessary to legally complete the work of this section. Contractor shall notify utility companies for all utilities to be cut off, modified or relocated, and shall maintain and protect all active utilities PROTECTION AND SAFETY: Contractor shall provide signs in necessary places to exclude persons, except those connected with the work, from entering the working area. Contractor is responsible for preventing unauthorized persons from entering working area. Protect the project site and adjacent properties from dirty water, mud and water accumulated due to Contractor's operations, rainfall runoff or water that enters the project site from any other sources. Site Clear and Grub

7 PART 2 - MATERIALS - Not applicable. PART 3 - EXECUTION 3.01 SUBMITTALS: Pre-demolition Photographs: Show conditions of existing adjacent construction, and site improvements that might be misconstrued as damaged by demolition operations. Submit before work begin as specified in Site Demolition, 1.07 A. Record Documents: Accurately record locations of utilities and subsurface obstructions GENERAL REMOVAL WORK: Removal work shall be carefully done to avoid damage to all existing facilities to remain SITE CLEARANCE AND DISPOSAL: Clear the sites to be improved of grass, shrubs, weed growth, rubbish and debris, and existing concrete/ asphalt slabs, etc., that are to be removed for construction of the improvements shown on the construction plans. Rocks and broken masonry larger than four inches in the greatest dimension, shall be removed to a minimum depth of l2" below finished grade within areas to be planted, and within full depth of overexcavation in all other areas. Hand excavate, expose, and report any root(s) below the surface of the concrete pavers that is 3 in diameter of larger. Do not cut any root larger than 3 prior to inspection, and direction from City representatives. All deleterious materials shall be disposed of off the site in a legal manner by the Contractor, who shall make all necessary arrangements and pay all related costs. Miscellaneous existing underground facilities, drainage devices, secondary water lines, cables, abandoned oil and water lines, leaching fields, irrigation pipes, wiring, etc, located l2 inches or more below finish grade may be abandoned in place or removed as necessary for proper completion of the work, after notification is made to the City representative. All miscellaneous active lines that are uncovered during the grading operations shall be protected UTILITIES: Inactive or abandoned utilities shall be disconnected, removed, and plugged or capped subject to the local governing ordinances. Should the Contractor encounter any existing underground utilities not shown on the drawings, he shall at once notify the City representative who will determine further procedure DEBRIS BURNING: Burning of debris will not be permitted DUST CONTROL: Dust shall be kept to a minimum during site clearing operations by means of wetting the site or Site Clear and Grub

8 other approved method. Wash down all existing sidewalks and roadways on and off the site daily and after all operations are complete. Comply with all dust control requirements, SWPPP and NPDES. END OF SECTION Site Clear and Grub

9 SECTION SITE GRADING PART 1 - GENERAL 1.01 RELATED DOCUMENTS: See Section Earthwork - for further information The requirements of the Standard Specifications for Public Works Construction (SSPWC), latest edition, Parts 2 through 6, apply to this project and are incorporated herein by this reference. Part 1 is specifically excluded. Drawings, project manual, and general provisions of the Contract, including General Conditions of the Contract, additional General Conditions of the Contract, and Division 1 specification sections, apply to this section SCOPE OF WORK: Furnish all material, equipment and labor as necessary to perform all earthwork complete, including, but not limited to, the following: Subgrade preparation for walks, slabs and other facilities Finish grading of the site Excavation and backfill for all footings, trenches, structures, etc. Soil compaction as required Protective measures Dust and noise abatement 1.03 RELATED WORK SPECIFIED ELSEWHERE: Site Clear and Grub - Section Excavation and backfill for any mechanical, plumbing, irrigation, drainage or electrical work - appropriate sections 1.04 QUALITY ASSURANCE: A. All work shall comply, without limitations, with the requirements of the following: (1) Storm Water Quality Associations - Stormwater Best Management Practice Handbook (BMP Handbook) Construction Edition. (2) SWPPP & NPDES Requirements B. Tests and Inspections: (1) All work in this section shall be subject to the observation and testing as required by the Soils Engineer selected by the City. The Soils Engineer shall submit a compaction report to the City, certifying the Contractor's compliance with the plans, specifications, soils reports and City grading ordinance in placing all fills and backfills. The Soils Engineer shall conduct all specified tests to insure compliance. Soils Engineer shall also test, identify and make recommendations on Site Grading

10 borrow site fill materials as specified in this section. (2) Number and location of soils tests to be at the discretion of the Soils Engineer to assure uniformity and compliance with the City grading ordinance, but at least one test per two vertical feet of fill, but not less than one test per 500 cubic yards, all as approved by the City. (3) The costs of services of the Soils Engineer, specified field density and maximum density tests, compaction reports and certificates of compliance, shall be borne by the City. Additional tests and re-compactions made necessary by inadequate compaction, inadequate materials provided by contractor, and inaccurate excavations shall be paid for by the Contractor at no additional cost to the City GRADING OPERATIONS: The grading contractor shall be responsible for determining their own earthwork quantities for bidding purposes. The quantities shown on the plans are the engineer=s estimate only and are for the sole purpose of determining city plan check and permit fees. All import or export necessary to achieve the grade to match existing surrounding areas is the responsibility of the contractor and shall be included in the contract prices including, but not limited to, spoils WATER: Contractor shall make arrangements with the City of Beverly Hills Public Works to obtain construction water. This includes, without limitation, payment for a hydrant meter and water usage for entire job JOB CONDITIONS: A. Protection of Existing Items: (1) The Contractor shall furnish, place and maintain all shoring and bracing as may be required for protection of existing structures and utility services during execution of the work. The adequacy of and responsibility for this shall be the Contractor's completely. (2) All bench marks, monuments and other reference points shall remain undisturbed unless specifically directed otherwise by the City representative. (3) Contractor shall dig by hand as necessary to protect existing underground utilities and existing irrigation lines, in all areas where existing utilities and/or irrigation lines and wires are located. B. Protection of Public: The Contractor shall provide such barricades, temporary fences, gates, lights, warning signs, guards, and other measures as may be necessary to assure safety and to deter trespassers. These provisions shall be maintained during the entire duration of the work. These temporary facilities shall be constructed, painted, and maintained in strict Site Grading

11 conformance with the requirements of applicable codes and other governing authorities. C. Coordination with Others: (1) Contractor shall give written notice to the City representative, utility agencies, and other legal authorities prior to starting work. (2) Contractor shall coordinate his operations with other trades, utility firms, and other affected public departments to assure continuity for both access and service of all utility, service distribution lines, in conformance with applicable requirements of these organizations. No services to any property shall be impeded. D. Abandoned and Unknown Utilities: PART 2 - MATERIALS 2.01 DRAIN ROCK: 2.02 IMPORT: (1) Abandoned lines, meters and boxes, obstructions or piping, shall be removed, plugged, or capped in accordance with the requirements and approval of the agencies affected, or as directed by the City representative. Coordinate all such work with applicable mechanical or electrical trade having responsibility. Remove all abandoned utility lines, pipes, or conduits, to a point outside new construction lines. (2) Where unmarked utility lines or other underground obstructions or piping are uncovered within the work area, notify the City representative or the agencies or service utility companies having jurisdiction and take necessary measures to prevent interruption of service. Should such lines or services be damaged, broken, or interrupted through the Contractor's own negligence, those services shall be repaired immediately and restored by him at his own expense. Drain rock for all sumps shown on plan shall be ASTM C33 #57 rock, unless otherwise directed by the City representative. A. All import soil used for fill in landscape areas (if deemed necessary) shall be Class `A' topsoil per Standard Specifications, Section 212. B. All import soil used for structural fill shall be non-expansive, predominantly granular material free from organic contaminants, and capable of attaining the required compacted densities. C. All import soil must be approved at the borrow site by the Soils Engineer FILL MATERIAL: A. All fill material must be approved by the Soils Engineer. B. On-site excavated materials may be used as approved by the Soils Engineer. Landscape fill Site Grading

12 shall be Class `A' topsoil. C. Rocks larger than 3 inches in diameter shall be removed from all fills to be compacted. PART 3 - EXECUTION 3.01 GENERAL: A. All demolition and clearing and grubbing of objectionable materials must be completed to the satisfaction of the Soils Engineer before starting earthwork grading and excavation. B. Survey/Staking: Contractor shall provide all survey services necessary for horizontal and vertical control points, layouts, lines and levels, staking of work. Any corrections to the grading work required to obtain proper drainage and to bring it into conformance with the intent of the plans and specifications and City codes shall be performed by Contractor at no additional cost to the City. C. Contractor shall check all existing grades prior to initiating grading work as necessary to verify that the project can be graded as proposed. Any discrepancies found should immediately be brought to the attention of the City in writing ROUGH GRADING: A. Rough grading of the site shall be sufficient to allow for the depths of paving, sub-base, topsoil, and compacted fills. Tolerance for rough grading is 1/10th of a foot. In all areas, appearance and positive drainage will be governing factors in acceptability of grades. B. Graded material shall not be left in loose layers, but shall be stockpiled for use as compacted fill or compacted in thin layers as grading takes place in accordance with the requirements for compacted fill. C. Scarification to a minimum depth of six (6) inches or to a depth permitting twelve (12) inches of controlled compacted fill shall be performed on all areas indicated to be overexcavated. D. The Soils Engineer shall inspect all scarified surfaces prior to placement of compacted fill CONTROLLED FILL: A. Fill material shall be spread in uniform lifts of six (6) to eight (8) inches of uncompacted thickness. B. Prior to starting compaction, the fill material shall be brought to optimum moisture content by spraying with water if too dry, and aeration if too wet. C. Thoroughly mix each lift to assure uniform distribution of water content. D. Bring fills to suitable elevations above required grades to provide for effects of shrinkage Site Grading

13 and settlement. E. For all areas designated to receive slabs and pavement and within a perimeter five (5) feet outside these areas, each lift shall be compacted to a minimum of 95% of maximum density as determined by ASTM D F. Where fill is required in planting areas each lift shall be compacted to a minimum of 85% maximum density. G. Perform all compaction by suitable mechanical equipment and methods approved by the Soils Engineer. H. Inspection and field tests shall be carried on during grading by the Soils Engineer to assist the Contractor in obtaining the required degree of compaction and the proper moisture content. Where compaction of less than 90% is indicated, additional compactive effort shall be made with adjustment of the moisture content as necessary until a minimum of 90% compaction is obtained. I. The material in any soft or spongy spots shall be removed to such depth as directed by the Soils Engineer and replaced with suitable material, properly compacted. J. Sub-grades to receive slabs and pavements shall be finished to a tolerance of plus or minus one-half (l/2) inch FINE GRADING: Finish grades shall slope to drain without water pockets or irregularities and shall conform to the intent of all plans and specifications after thorough shrinkage, settlement and compaction of the soil. Finish grades shall meet all existing or established controls of sidewalks and curbs, and shall be of uniform slope and grade between points of fixed elevations or elevation controls and from such points to established grades. Tolerance for finish grading is l/4 inch, plus or minus. Any corrections to the grading work required to obtain proper drainage and to bring it into conformance with the intent of the plans and specifications and City codes shall be performed by Contractor at no additional cost to the City EXCAVATION: The Contractor shall make all necessary excavation for footings and slabs and to any additional excavation necessary to provide ample room for installation of concrete forms where required. Bottom of excavations shall be level, free from loose material and brought to the indicated or required grades in undisturbed earth. All excavations shall be kept free from standing water. The Contractor shall do all pumping or draining that may be necessary in carrying on the work. Should excavations for footings, through error, be excavated to a greater depth of size than indicated or required, such additional depth or size shall be filled with concrete, at the Contractor's expense BACKFILLING: Select site material shall be used for backfill of trenches and shall be free from large stones and Site Grading

14 clods. All bedding to be per codes. Backfill shall be deposited in layers of maximum six inch thickness. Layers of backfill shall be moistened with water, the amount to be rigidly controlled to insure optimum moisture conditions for the type of fill material used. Excess water causing saturated earth beneath footings, walks, and curbs will not be permitted. Backfill shall be compacted by suitable means to a minimum 90% DUST AND NOISE ABATEMENT: During the entire period of construction, site areas shall be kept sprinkled as necessary to reduce dust in the air and annoyance to surrounding properties. Adhere to the requirements of City ordinances for dust and noise control and NPDES. END OF SECTION Site Grading

15 SECTION SUB-GRADE PREPARATION PART 1 - GENERAL 1.01 GENERAL CONDITIONS Requirements of the Contract Documents, including but not limited to, the General, Special, and Technical Provisions, apply to work in this Section with the same force and effect as though repeated in full herein SCOPE OF WORK Furnish materials, labor, transportation, services, and equipment necessary to perform all subgrade preparation work for the park as indicated on the Drawings complete as shown and as specified herein. Related Work: Earthwork Section Concrete Formwork Section Concrete Reinforcement Section Cast-In-Place Concrete Section REFERENCES Comply with the applicable reference specifications as specified in the GENERAL PROVISIONS and in accordance with applicable laws, codes and regulations required by the City of Beverly Hills, CA. Comply with the current provisions of the following Codes and Standards: ASTM - American Society for Testing and Materials. Standard Specifications Uniform Building Code PART 2 - MATERIALS 2.01 SUITABLE MATERIALS General: Fill, backfill, and embankment materials shall be suitable selected or processed clean, fine earth, rock, or sand, and free from grass, roots, brush, or other vegetation; contamination; or deleterious material. The size, gradation, and properties of the materials shall be in accordance with the requirements of the Soil Report and these specifications. Aggregate base materials under pavements shall be crushed aggregate base material constructed to the thickness shown or specified. The percentage composition by weight of aggregate base shall conform to the Standard Specifications. PART 3 - EXECUTION 3.01 SUBGRADE PREPARATION Excavate and shape subgrade to line, grade, and cross-section shown on the Drawings. Subgrade Preparation

16 3.02 BASE Subgrade is that area on which pavement, surfacing, base, sub-base, or a layer of other material which may be specified, is to be placed. Plow or scarify subgrade to a depth of 6" below the final subgrade elevation; and by harrowing, dry rolling and breaking clods, the earth shall be brought to finely divided condition. Remove boulders, hardened material, or rock encountered. The earth shall be uniform for the full depth and width of the subgrade. Water loose earth to a uniform depth of 4". Harrow the earth to mix the wet earth with the dry beneath, until the whole mass of loose material is at the proper state of moisture for compaction. The finished subgrade, immediately prior to placing subsequent material thereon, shall be in accordance with the Standard Specifications. The finished surface of the subgrade, at any point, shall not vary more than 0.05' above or 0.2' below the elevation indicated on the drawings unless approved in writing by the City representative. Hand excavate, expose, and report any root(s) below the surface of the concrete pavers that is 3 in diameter of larger. Do not cut any root larger than 3 prior to inspection, and direction from City representatives. The City will not provide any additional compensation to the Contractor for hard rock or caliches excavation. Base shall be readily compacted and spread with equipment that will provide a uniform layer conforming to the planned section CLEANUP Upon completion of the subgrade preparation and base, remove surplus construction materials, earth and debris so that the job site is left in a neat and orderly condition. END OF SECTION Subgrade Preparation

17 SECTION EARTHWORK PART 1 - GENERAL 1.01 RELATED DOCUMENTS: Section Site Grading The requirements of the Standard Specifications for Public Works Construction (SSPWC), latest edition, Parts 2 through 6 (except as modified herein), apply to this project and are incorporated herein by this reference. Part 1 is specifically excluded. Drawings, project manual, and general provisions of the Contract, including, without limitation, General Conditions of the Contract, additional General Conditions of the Contract, and Division 1 specification sections, apply to this section SCOPE OF WORK Furnish materials, labor, transportation, services, and equipment necessary to perform all earthwork operations related to the park as indicated on the Drawings complete as shown and as specified herein. The work of this Section includes all earthwork required for construction of the WORK. Such earthwork shall include, but not be limited to, the loosening, overexcavation and recompaction, removing, loading, transporting, depositing, and compacting in its final location of all materials wet and dry, as required for the purposes of completing the work specified in the Contract Documents, which shall include, but not be limited to, the furnishing, placing, and removing of sheeting and bracing if necessary to safely support the sides of all excavation; all pumping, ditching, draining, dewatering, and other required measures for the removal or exclusion of water from the excavation; the supporting of structures above and below the ground; all backfilling around structures and all backfilling of trenches and pits; the disposal of excess excavated materials; alluvial removals, selective grading of expansive soils, soil importing or exporting, borrow of materials to make up deficiencies for fills, and all other incidental earthwork, all in accordance with the requirements of the Contract Documents. Related Work: Site Demolition Section Site Grading Section Sub-grade Preparation Section REFERENCES All work will be done in accordance with applicable laws, codes and regulations required by the City of Beverly Hills, CA. Work shall comply with the rules and regulations of local, state and federal agencies having jurisdiction, including, without limitation, SWPPP and NPDES. Nothing contained herein shall be construed as permitting work that is contrary to such rules, regulations and codes.

18 Comply with the current provisions of the following Codes and Standards, without limitation: 1. ASTM - American Society for Testing and Materials 2. Standard Specifications (as specified in the General Provisions [Part 1 is specifically excluded]) 3. CBC B California Building Code, Title 24, Part 2, Chapter 18 and Chapter Storm Water Quality Association B Stormwater Best Management Practice Handbook (BMP Handbook) Construction Edition. 5. State Water Resources Control Board Order No DWQ 6. ASTM C136 B Method for Sieve Analysis of Fine and Coarse Aggregation 7. ASTM D448 B Sizes of Aggregate for Roadway and Bridge Construction 8. ASTM D1556 B Test Method for Density of Solid in Place by the Sand-Cone Method 9. ASTM D1557 B Test Methods for Moisture-Density Relations of Soils and Soil-Aggregate Mixtures Using 10 lb. Rammer and 18 inch Drop 10. ASTM D2922 B Test Methods for Density of Soil and Soil-Aggregate in Place by Nuclear Methods (Shallow Depth) 11. ASTM D2937 B Test Method for Density of Solid in Place by the Drive-Cylinder Method 12. ASTM D3017 B Standard Test Method for Water Content of Soil and Rock in Place by Nuclear Methods (Shallow Depth) 13. Coordinate work of this section with Permit provisions of State Water Resources Control Board Order No DWQ and the Storm Water Pollution Prevention Plan SUBMITTALS Submittals, including samples of materials, shall be in accordance with the GENERAL PROVISIONS. Samples: Submit a one-half cubic foot sample of proposed import soils (if required) per the project s soil report for Soils Engineer=s review and approval; identify location and source of import soil QUALITY ASSURANCE General: All soils testing and inspection during earthwork operations, other than agricultural suitability and chemical analysis of proposed soils, will be done by a testing laboratory of the City representative s choice, at the City s expense except as specified in Paragraph 1.5.C below. Where soil material is required to be compacted to a percentage of maximum dry density, the maximum dry density at optimum moisture content will be determined in accordance with the Earthwork

19 latest version of ASTM D In-place field density tests will be performed in accordance with ASTM D 1556, (sand cone) and/or ASTM D 2922 and ASTM D 3017 (nuclear gauge). The number and location of field density tests will be determined by the Soils Engineer. In case the tests of the fill or backfill show non-compliance with the required density, the CONTRACTOR shall accomplish such remedy as may be required to ensure compliance. Subsequent testing to show compliance shall be by a testing laboratory selected by the City and shall be at the CONTRACTOR=s expense. All imported fill material not specified in the contract shall be tested at the CONTRACTOR=s expense and approved by the Soils Engineer PROJECT CONDITIONS Existing Conditions: The existing topographic conditions are shown on the drawings for reference only. Upon beginning the earthwork, Contractor represents that he has inspected the site and satisfied himself as to actual grades and levels and the true conditions under which the work is to be performed. Promptly notify the City=s representative of unexpected subsurface conditions. The Contractor is required to submit a "Site Acceptance" letter before earthwork operations begin. Soil Classification: Excavated materials are not classified as to type PROTECTION Protection: 1. Protect excavations by shoring, bracing, sheeting, underpinning, or other methods, as required to prevent cave-ins or loose dirt from entering excavations. Barricade open excavations and post warning lights at work adjacent to public streets and walks. Coordinate with all ordinances. 2. Cover holes and trenches when work is not in progress. Fence or barricade changes of plane more than 45 degrees horizontally and more than 3 feet vertically. 3. Maintain bench marks, monuments, and other reference points. If disturbed or destroyed, replace as directed, at no cost to the owner 4. Protect existing berms and slopes from disruption. If slopes are disturbed, return to existing conditions at no additional cost to the City. 5. Underpin adjacent structure(s), including utility service lines, which may be damaged by excavation operations. 6. Protect existing natural areas and landscape improvements from damage. 7. Promptly repair damage to adjacent facilities caused by earthwork operations. Cost of repair at Contractor's expense. Provide erosion and sedimentation control measures to prevent soil erosion and discharge of soilbearing water runoff or airborne dust to adjacent properties and walkways according to requirements of the Storm Water Pollution Prevention Plan. Earthwork

20 Inspect, repair, and maintain erosion and sedimentation control measures during earthwork operations. PART 2 - MATERIALS 2.01 SUITABLE FILL AND BACKFILL MATERIAL REQUIREMENT General: Fill, backfill, and embankment materials shall be suitable selected or processed clean, fine earth, rock, or sand, and free from grass, roots, brush, or other vegetation; contamination; or deleterious material. The size, gradation, and properties of the materials shall be in accordance with the requirements of these specifications. Suitable materials may be obtained from onsite excavations, may be processed onsite materials, or may be imported provided these materials meet all the requirements in the Contract Documents. If imported materials are required to meet the requirements of this Section or to meet the quantity requirements of the project, the Contractor shall provide the imported fill materials and the required conformance reports of test results at no additional expense to the City, unless a unit price item is included for imported materials (including the appropriate required testing reports) in the bidding schedule USE OF FILL AND BACKFILL MATERIAL TYPES The Contractor shall use the types of materials as designated on the Drawings and herein for all required fill, backfill, and embankment construction hereunder. Where these Specifications conflict with the requirements of any local agency having jurisdiction, or with the requirements of a material manufacturer, the City shall be immediately notified. In case of conflict therewith, the order or precedence in the Contract or Terms and Conditions shall govern. PART 3 - EXECUTION 3.01 PREPARATION Establish extent of grading and excavation by area and elevation. Designate and identify datum elevation and project engineering reference points. Set required lines, levels and elevations. Do not cover or enclose work of this Section before obtaining required inspections, tests, approvals, and location recording EXISTING UTILITIES Before starting grading and excavation, establish the location and extent of underground utilities in the work area. Exercise care to protect existing utilities during earthwork operations. Perform excavation work near utilities by hand and provide necessary shoring, sheeting, and supports as the work progresses. Maintain, protect, relocate, or extend, as required, existing utility lines to remain which pass through the work area. Earthwork

21 Protect active utility services uncovered by excavation. Notify respective utility companies and City representative of damage caused to active utilities immediately. Remove abandoned utility service lines from areas of excavation. Cap, plug, or seal abandoned lines at source of connection and identify termination points at grade level with markers, after notification is provided to the City representative. Accurately locate and record abandoned and active utility lines rerouted or extended on project record documents SITE GRADING B GENERAL Perform grading within contract limits, including adjacent transition areas, to new elevations, levels, profiles, and contours indicated. Provide uniform levels and slopes between new elevations and existing grades. Obtain approval of scarified subgrade surfaces by City's representative prior to filling operations. Scarify, dry, and compact soft and wet areas; remove and replace unsuitable subgrade materials with an approved fill material. Take corrective measures before placing fill materials. Thoroughly scarify existing soil surface to a depth of 10" and as shown on the Soils Report and verify scarification with City's representative prior to placing fill material in mounded areas. Spread approved fill material uniformly in layers not greater than 12" of loose thickness over entire fill zones of planting areas. 1. Lift thickness requirements may be modified by City s representative to suit equipment and materials or other conditions when required to assure satisfactory compaction. 2. Place and compact each layer of fill before placing additional fill material. Repeat filling until proposed grade, profile or contour is attained. 3. Suspend fill operations when satisfactory results cannot be obtained because of environmental or other unsatisfactory site conditions. Do not use over-saturated fill materials. Do not place fill material on over-saturated subgrade surface. 4. Grade surfaces to assure positive drainage and to prevent ponding and pockets of surface drainage. 5. Protect finish graded areas from traffic and erosion. Keep free of trash and debris. Repair and reestablish grades in settled, eroded and damaged areas. If, in the opinion of the City, the completed site grading does not reflect the intent of the Contract Documents, an independent surveyor may be hired to verify the grades. If the grades are correct, the City will pay for the survey. If the grades are incorrect, the cost of the survey will be deducted from the Contract price. Earthwork

22 3.04 BACKFILLING / FILLING FOR PAVING & WALLS Before filling, remove debris, large rocks, formwork and loose material. Proof-roll areas to receive fill with rubber tired roller of sufficient weight. Weak areas or areas where excessive pumping is noted shall be removed, and if required by the City, replaced with select fill. Prior to placing fill, scarify surface to a depth of 6 inches. Moisture content of loosened material shall be such that first layer of fill will readily bond to surface. Top 6 inches shall be free from rocks larger than 3 inches diameter. Place in maximum 8-inch lifts and compact per ASTM D 1557 at optimum moisture content (-1% to +3%). This lift and compaction requirement does not apply to planting areas. Moisten fill to allow drying to correct moisture content before compaction. Do not place fill on subgrade that is over-saturated. Paving subgrade per plan. Allowing for total thickness of finish paving and base material, fill under paving to bring subgrade to proper elevation. Soft areas that develop under construction operations shall be scarified, aerated or moistened. Compact to full depth required to obtain specified density for each layer EXCAVATING It is the Contractor's responsibility to investigate the likelihood of caliches or hard rock excavation. The City will not provide any additional compensation to the Contractor for hard rock or caliches excavation FINISH GRADING Grade uniformly with rounded surfaces at tops and bottoms of abrupt changes in plane. Hand grade steep slopes, areas that are inaccessible for machine work and areas around existing plants. Slope graded surfaces to drain water away from structures, walls, etc.; minimum slope is 1/4 inch per foot. Grade areas to elevation and slopes indicated without depressions causing pocketing of surface water or humps, producing localized runoff and erosion. Ponding of water on site is not allowed. Finish surfaces to be not more than 0.10 foot above or below established grade elevation DRAINAGE Provide drainage of the working area at all times. Earthwork

23 3.08 DISPOSAL OF WASTE MATERIALS Legally dispose excess excavated material, including rock from site. 309 CLEANING Upon completion of earthwork operation, clean areas within contract limits, remove tools and equipment. Provide site clear, clean, free of debris and suitable for site work operations. Remove and dispose of properly off site all rocks and other debris from grading operations. END OF SECTION Earthwork

24 1.01 TEMPORARY FENCING: SECTION TEMPORARY CHAINLINK FENCING Install a 6' tall (min.) temporary construction fence prior to beginning any site work, at the frontage of the park property. The fence shall be chain link (new or used), free of openings or breaks in the fabric, with fence posts at 10' O/C maximum. Fencing shall incorporate green tennis court windscreen material, securely fastened to top and bottom of chain link fabric, for the entire secured perimeter of the fence line. The fence shall be maintained in place throughout the construction phase period through to the end of the ninety (90) day landscape maintenance period. Install No Trespassing signs minimum 20' o.c., with wording presented in both English and Spanish. The temporary fence shall be removed prior to final inspection/project acceptance at the end of the maintenance period. END OF SECTION Temporary Chainlink Fencing

25 SECTION PLAY EQUIPMENT PART 1 - GENERAL 1.01 RELATED DOCUMENTS: The requirements of the Standard Specifications for Public Works Construction (SSPWC), latest edition, Parts 2 through 6, apply to this project and are incorporated herein by this reference. Part 1 is specifically excluded. Drawings, project manual, and general provisions of the Contract, including, without limitation, General Conditions of the Contract, additional General Conditions of the Contract, and Division 1 specification sections, apply to this section SCOPE OF WORK: The work under this section shall include, without limitation, all labor, materials, and equipment required to install the play equipment complete as specified. The equipment shall be assembled on site as per manufacturing recommendations and this section. All work and equipment provided shall be subject to approval of the City representative SHOP DRAWINGS OR CATALOGS: Six (6) copies of shop drawings which show complete details will be provided for all items requiring shop fabrication in accordance with Section of the Standard Specifications GUARANTEE & LIABILITY INSURANCES: A. Manufacturer shall guarantee all materials and workmanship for a period of one (1) year exclusive of vandalism. Manufacturer will be required to provide product liability insurance coverage in the minimum amounts of $1,000, per incident. The Manufacturer will be required to provide complete installation drawings including specifications and a replacement parts list for all products. B. Contractor shall provide a written guarantee on his firm s letterhead using City format, for all materials and workmanship for a period of one (1) year exclusive of vandalism. Written guarantee shall be submitted to the City representative at the final inspection prior to final acceptance of the work PROPOSED SUBSTITUTIONS: Products proposed for substitution as "equals" to those specified are subject to the approval of City representative. If at the time proposed equals are delivered to the site it is determined by the City representative that they are not equal to those specified, they shall be removed and products as specified provided by the contractor at no additional cost to the City LOCATION INSPECTION: No equipment or apparatus or foundations for same shall be placed until location stakes have been Play Equipment

26 inspected by the City representative. PART 2 - MATERIALS 2.01 CHILD PLAY & TOT LOT STRUCTURES: Shall consist of custom Kompan play equipment per quote #14450, prepared by Recreation Republic, (760) , or approved equal WATER/SAND PLAY STRUCTURES (ADD ALTERNATE #1): Shall consist of the following: 1. Kompan Waterfall, model #M591P, or approved equal. Structure to be plumbed for water tap per construction plans and details. Available from Recreation Republic, (760) Kompan Rotating Table, model #M571P, or approved equal. Available from Recreation Republic, (760) Kompan Starfish, model #M584P, or approved equal. Available from Recreation Republic, (760) Two (2) Landscape Structures Superscoops, model #123831A, or approved equal. Colors per construction plans. Available from Coast Recreation, (714) One (1) Landscape Structures Accessible Superscoops, model #123832A-B, or approved equal. Colors per construction plans. Available from Coast Recreation, (714) Three (3) existing Palm Trees to be protected in place per demolition and construction plans. Palms are to be plumbed for misting system with Mee Industries. Contact Dave Sola at Mee Industries, (626) , for proposal and installation scope of work for both Contractor and Mee Industries. 7. Vortex Foot Activator, model #VOR0606, or approved equal. Activator to be connected to water play controls via control wire per construction detail. Available from Vortex West, (866) Precast concrete underground vault with galvanized steel lockable cover option, model #K44-FP48-05PG, to house water play equipment. Available from Jensen Precast, (909) SAFETY SURFACING Shall consist of one of the following dependent upon award by the City: 9. A custom mix blend (as specified per construction plans) of Surface America Playbound poured-in-place aliphatic rubber surfacing product, represented by Coast Recreation (714) , or approved equal. Install per manufacturer s specifications, and Section Resilient Surfacing. 10. Deductive Alternate #1: FieldTurf Olive Lush artificial turf surfacing, represented by Recreation Republic, (760) , or approved equal. Installation per manufacturer s specifications, subject to product warranties and guarantees. The installer shall specialize in performing the work, and provide competent workmen skilled in this specific type of installation. Supervisory personnel shall be certified in writing by the manufacturer, licensed, with a minimum of 5 years experience in managing or supervising synthetic turf installations. Installation methods and details shall be presented to City representative at time of pre-construction meeting prior to installation. The City reserves the right to request additional securing methods or measures to ensure that the surface is safe and Play Equipment

27 secure without additional cost to the City. 11. Deductive Alternate #2: Fibar engineered wood fiber surfacing, represented by Recreation Republic, (760) , or approved equal. Shall be manufactured primarily from softwood; shall contain no plywood, particle board, or contaminated wood; shall be free of all foreign objects such as metal, glass, and stones; shall contain no chemicals or additives; shall be completely non-toxic; and shall be guaranteed against decay and biochemical degradation for a period of three (3) years from the date of installation. PART 3 - EXECUTION 3.01 GENERAL: Installation shall be in the approximate locations shown on the drawings. Final approval of precise location by the City is required. In case of conflict between construction plans and manufacturer's requirements, the more stringent shall apply VANDAL RESISTANCE: All fasteners shall be either deformed or tack welded together to prevent unauthorized removal of the fasteners. Paint with galvi-con after deformation/welding CONCRETE WORK: All concrete foundation work shall be performed in accordance with the Standard Specifications, Section 201. Per recommendations listed within the Soils Report, all concrete shall conform to Concrete Class Use Table, Section (A), of the Standard Specifications and shall be 520-C (2,500 pounds per square inch ultimate compressive strength at 28 days) unless otherwise noted. Concrete mix shall have a maximum water/ cement ratio of CLEAN-UP: Project area shall be left clean and orderly upon completion. END OF SECTION Play Equipment

SECTION 31 20 00 EARTH MOVING

SECTION 31 20 00 EARTH MOVING SECTION 31 20 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for excavating, filling, and grading for earthwork at Parking Structure, new exit stair and as required to

More information

SECTION 02100 SITE PREPARATION

SECTION 02100 SITE PREPARATION SECTION 02100 SITE PREPARATION PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and General Provisions of Contract, including General Conditions and Supplementary Conditions and Division 1 through Division

More information

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition. Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer

More information

C. Section 014510 TESTING LABORATORY SERVICE.

C. Section 014510 TESTING LABORATORY SERVICE. SECTION 014500 QUALITY CONTROL PART 1 GENERAL 1.01 RELATED REQUIREMENTS A. Drawings and General Provisions of Contract, including General and Special Conditions and other Division 1 Specification Sections,

More information

CW 3110 SUB-GRADE, SUB-BASE AND BASE COURSE CONSTRUCTION TABLE OF CONTENTS

CW 3110 SUB-GRADE, SUB-BASE AND BASE COURSE CONSTRUCTION TABLE OF CONTENTS December 2014 CW 3110 SUB-GRADE, SUB-BASE AND BASE COURSE CONSTRUCTION TABLE OF CONTENTS 1. DESCRIPTION... 1 1.1 General... 1 1.2 Definitions... 1 1.3 Referenced Standard Construction Specifications...

More information

SECTION 02221 SELECTIVE DEMOLITION

SECTION 02221 SELECTIVE DEMOLITION SECTION 02221 PART 1 -GENERAL 1.01 DESCRIPTION This section includes all material, labor, machinery and supervision required to demolish and remove the following items where applicable and as noted on

More information

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary

More information

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains

More information

SECTION 311 PLACEMENT AND CONSTRUCTION OF CEMENT TREATED SUBGRADESOIL CEMENT BASE COURSE

SECTION 311 PLACEMENT AND CONSTRUCTION OF CEMENT TREATED SUBGRADESOIL CEMENT BASE COURSE PLACEMENT AND CONSTRUCTION OF CEMENT TREATED SUBGRADESOIL CEMENT BASE COURSE 311.1 DESCRIPTION: This item shall consist of a cement treated subgrade base course composed of a mixture of local soil, portland

More information

DIVISION 300 BASES SECTION 304 AGGREGATE BASE COURSE DESCRIPTION MATERIALS CONSTRUCTION REQUIREMENTS

DIVISION 300 BASES SECTION 304 AGGREGATE BASE COURSE DESCRIPTION MATERIALS CONSTRUCTION REQUIREMENTS 304.06 DIVISION 300 BASES SECTION 304 AGGREGATE BASE COURSE DESCRIPTION 304.01 This work consists of furnishing and placing one or more courses of aggregate and additives, if required, on a prepared subgrade.

More information

SECTION 4Aggegate Subbase

SECTION 4Aggegate Subbase The contractor shall moist-cure the completed Lime Treated Subbase for a minimum of days before allowing any traffic on the compacted surface. The contractor shall be responsible for repairing any damages

More information

Division 2 Section 32 14 13.19 Section 02795

Division 2 Section 32 14 13.19 Section 02795 Note: The text must be edited to suit specific project requirements. It should be reviewed by a qualified civil or geotechnical engineer, or landscape architect familiar with the site conditions. Edit

More information

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified. Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

More information

The Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11

The Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11 Page 1 of 11 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the excavation of trenches (or excavation of tunnels); the supply and placing of bedding and backfill materials;

More information

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT City of Swartz Creek 8083 Civic Drive Swartz Creek, MI 48473 810-635-4464 Fee Received: $ Date: / / Receipt No: Demolition Permit (including Right of

More information

SECTION 32 14 13.19 PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795)

SECTION 32 14 13.19 PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795) SECTION 32 14 13.19 PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795) Note: This guide specification for U.S. applications describes construction of permeable interlocking concrete

More information

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily

More information

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth

TABLE OF CONTENTS. Manhole, Frame, and Cover Installation (includes Drop Manhole) Additional Manhole Depth TABLE OF CONTENTS NO. MP-1 MP-2 MP-3 MP-4 MP-4.01 MP-4.02 MP-4.03 MP-5 MP-5.01 MP-5.02 MP-5.03 MP-5.04 MP-5.05 MP-5.06 MP-5.07 MP-5.08 MP-5.11 MP-5.12 MP-5.13 MP-5.14 MP-5.15 MP-5.16 MP-5.18 MP-5.19 MP-5.20

More information

City of Shelbyville Site Inspection Checklist

City of Shelbyville Site Inspection Checklist City of Shelbyville Site Inspection Checklist General Information Project Name: KYR10 Permit Number: Date: Project Location: Contractor: Conractor Representative: Inspector's Name: Title: Signature : Weather

More information

Building Your Interlocking Concrete Pavement to Last a Lifetime

Building Your Interlocking Concrete Pavement to Last a Lifetime Building Your Interlocking Concrete Pavement to Last a Lifetime A Guide for Consumers Contents Building Your Interlocking Concrete Pavement to Last a Lifetime.... 3 What Does Installation Involve?....

More information

CONSTRUCTION PERMIT REQUIREMENTS

CONSTRUCTION PERMIT REQUIREMENTS CONSTRUCTION PERMIT REQUIREMENTS Any work to be done in the City right-of-way (ROW), in a utility easement, and certain work on private property, requires an Engineering Inspection Permit from the Department

More information

DESCRIPTION OF WORK:

DESCRIPTION OF WORK: DEPARTMENT OF PUBLIC WORKS COUNTY OF HENRICO P.O. BOX 27032 RICHMOND, VIRGINIA 23273 PERMIT NO. One (1) copy of application and four (4) copies of plans are hereby made to the Director of Public Works

More information

SECTION 1 GENERAL REQUIREMENTS

SECTION 1 GENERAL REQUIREMENTS Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,

More information

City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements

City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements City of Paso Robles Community Development Department Construction Site Storm Water Quality Requirements Overview of the City s Construction Storm Water Program The City of Paso Robles is committed to protecting

More information

SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or

More information

SECTION 02400 - STORM DRAIN SYSTEM

SECTION 02400 - STORM DRAIN SYSTEM SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And

More information

Stormwater/Wetland Pond Construction Inspection Checklist

Stormwater/Wetland Pond Construction Inspection Checklist : Construction Inspection ChecklistsTools Stormwater/Wetland Pond Construction Inspection Checklist Project: Location: Site Status: Date: Time: Inspector: SATISFACTORY/ UNSATISFACTORY COMMENTS Pre-Construction/Materials

More information

Developer s/consultants Field Services Guidelines

Developer s/consultants Field Services Guidelines Developer s/consultants Field Services Guidelines 2007 Engineering and Works Department DEVELOPER S/CONSULTANT S FIELD SERVICES GUIDELINES Fourth Electronic Edition February 2007 STATEMENT OF COMPLETION

More information

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1 6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT

More information

Section 2100-Trenching and Tunneling

Section 2100-Trenching and Tunneling SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial

More information

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS Section Page 36-1 GENERAL... 36.1 36-2 PIPEMAKING EQUIPMENT... 36.1 36-3 TRENCH EXCAVATION... 36.1 36-4 SPECIAL FOUNDATION TREATMENT...

More information

SECTION 104 PREVENTION, CONTROL, AND ABATEMENT OF EROSION AND WATER POLLUTION

SECTION 104 PREVENTION, CONTROL, AND ABATEMENT OF EROSION AND WATER POLLUTION SECTION 104 PREVENTION, CONTROL, AND ABATEMENT OF EROSION AND WATER POLLUTION 104-1 Description. Provide erosion control measures on the project and in areas outside the right-of-way where work is accomplished

More information

4-02 Gravel Base. 4-04 Ballast and Crushed Surfacing

4-02 Gravel Base. 4-04 Ballast and Crushed Surfacing Chapter 4 Bases 4-02 Gravel Base GEN 4-02.1 General Instructions Gravel Base is typically used in the construction of the roadway section and provides support for the pavement. For the pavement to provide

More information

STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY

STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY STANDARD SPECIFICATIONS FOR PRIVATE BUILDING SEWER LINES IN PUBLIC RIGHT-OF-WAY Approved and adopted as Official Document Number 800576 this 10th day of December, 1980 Donald R. Boyd, P.E., Director Water

More information

SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING

SECTION 33 41 13 PUBLIC STORM UTILITY DRAINAGE PIPING SECTION 33 41 13 PUBLIC STORM PART 1 - GENERAL 1.01 SECTION INCLUDES A. Storm drainage piping, fittings, and accessories at proposed station areas and locations other than under and immediately adjacent

More information

STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS

STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for cleaning and lining existing cast iron and ductile iron water mains

More information

SECTION 32 14 13.19 PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795)

SECTION 32 14 13.19 PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795) SECTION 32 14 13.19 PERMEABLE INTERLOCKING CONCRETE PAVEMENT (1995 MasterFormat Section 02795) Note: This guide specification for U.S. applications describes construction of permeable interlocking concrete

More information

TECHNICAL SPECIFICATIONS CONCRETE SIDEWALKS, DRIVEWAYS AND CURB AND GUTTER

TECHNICAL SPECIFICATIONS CONCRETE SIDEWALKS, DRIVEWAYS AND CURB AND GUTTER TECHNICAL SPECIFICATIONS CONCRETE SIDEWALKS, DRIVEWAYS AND CURB AND GUTTER I. Scope of Work Work done under this item shall consist of the construction, reconstruction, or alteration of a one-course Portland

More information

Section 02317 EXCAVATION AND BACKFILL FOR UTILITIES

Section 02317 EXCAVATION AND BACKFILL FOR UTILITIES Section 02317 PART 1 G E N E R A L 1.01 SECTION INCLUDES A. Excavation, trenching, foundation, embedment, and backfill for installation of utilities, including manholes and other pipeline structures. 1.02

More information

MDWASD 8/1999 SECTION 02315 TRENCHING AND BACKFILLING FOR PIPING SYSTEMS

MDWASD 8/1999 SECTION 02315 TRENCHING AND BACKFILLING FOR PIPING SYSTEMS PART 1 - GENERAL 1.01 WORK INCLUDED SECTION 02315 TRENCHING AND BACKFILLING FOR PIPING SYSTEMS A. The work included under this Section consists of excavating, backfilling and compaction as required for

More information

PERMEABLE INTERLOCKING CONCRETE PAVEMENT

PERMEABLE INTERLOCKING CONCRETE PAVEMENT [NOTE TO SPECIFICATION WRITER: This guide specification for the use of permeable interlocking concrete pavers for pedestrian and vehicular traffic application was developed based on the use of an open-graded

More information

BMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet.

BMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet. BMP-7 BMP: STORM DRAIN INLET PROTECTION Definition A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet. To prevent sediment from entering storm drainage systems

More information

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13) Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised ) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular blocks

More information

WILDCAT CANYON ROAD SPECIFICATION NO. 16-11001 SLIDE REPAIR BIDDER'S PROPOSAL (continued)

WILDCAT CANYON ROAD SPECIFICATION NO. 16-11001 SLIDE REPAIR BIDDER'S PROPOSAL (continued) BIDDER'S PROPOSAL (continued) Item Estimated No. Description Quantity Unit Unit Cost Total Cost BASE BID 1 Traffic Control 1 LS $ $ 2 Construction Area Signs 1 LS $ $ 3 Excavation Safety 1 LS $ $ 4 Reset

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located

More information

LS 2540 SEWER LATERALS AND INSPECTION TEES

LS 2540 SEWER LATERALS AND INSPECTION TEES LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal

More information

SECTION 02401 SHEETING, SHORING AND BRACING

SECTION 02401 SHEETING, SHORING AND BRACING SECTION 02401 SHEETING, SHORING AND BRACING This section should be edited to reflect soil conditions specific to the project site and the recommendations of a Geotechnical Engineer licensed in the State

More information

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 PART 1 - GENERAL 1.01 RELATED DOCUMENTS: SECTION 16050 A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1

More information

Installation PowerPoint for Grasscrete Formers

Installation PowerPoint for Grasscrete Formers Installation PowerPoint for Grasscrete Formers 1 This document describes the two single-use tools utilized to create the Grasscrete product. The original Former is a vacuum formed light gauge plastic mold

More information

SECTION 32 14 13.19 PERMEABLE INTERLOCKING CONCRETE PAVEMENT

SECTION 32 14 13.19 PERMEABLE INTERLOCKING CONCRETE PAVEMENT PART 1 GENERAL 1.1 SECTION INCLUDES SECTION 32 14 13.19 PERMEABLE INTERLOCKING CONCRETE PAVEMENT A. The requirements for construction of permeable interlocking concrete pavement: 1. Install the interlocking

More information

SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS

SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS PART 1: GENERAL 1.01 SECTION INCLUDES A. Abandonment in place, by cutting and capping, of existing sewers, junction structures, manholes, service lines, and

More information

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

CONCRETE SEGMENTAL RETAINING WALL SYSTEM CONCRETE SEGMENTAL RETAINING WALL SYSTEM PART 1: GENERAL SPECIFICATIONS 1.01 Work Included A. Work shall consist of furnishing and constructing a Rockwood Classic 8 with PCS unit segmental retaining wall

More information

SECTION 02795 UNI PERMEABLE INTERLOCKING CONCRETE PAVEMENT

SECTION 02795 UNI PERMEABLE INTERLOCKING CONCRETE PAVEMENT SECTION 02795 UNI PERMEABLE INTERLOCKING CONCRETE PAVEMENT Note: This guide specification is intended for use in the U.S. It describes construction of permeable interlocking concrete pavers on a permeable,

More information

INDEX 03010-1 DESCRIPTION 2 03010-2 MATERIALS 2 03010-3 APPROVAL OF SUBBASE COURSE 3 03010-4 CONSTRUCTION 4 03010-5 MEASUREMENT 6 03010-6 PAYMENT 6

INDEX 03010-1 DESCRIPTION 2 03010-2 MATERIALS 2 03010-3 APPROVAL OF SUBBASE COURSE 3 03010-4 CONSTRUCTION 4 03010-5 MEASUREMENT 6 03010-6 PAYMENT 6 03010_Dec22_2009.pdf Page 1 of 5 INDEX Page 03010-1 DESCRIPTION 2 03010-2 MATERIALS 2 03010-3 APPROVAL OF SUBBASE COURSE 3 03010-4 CONSTRUCTION 4 03010-5 MEASUREMENT 6 03010-6 PAYMENT 6 03010_Dec22_2009.pdf

More information

GEOTECH ENGINEERING and TESTING

GEOTECH ENGINEERING and TESTING GEOTECH ENGINEERING and TESTING Geotechnical, Environmental, Construction Materials, and Forensic Engineering ACCREDITED GEOTECHNICAL AND CONSTRUCTION CONSIDERATIONS FOR A TYPICAL RESIDENTIAL STRUCTURE

More information

ARTICLE II (2) ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH 020001 Purpose and Application.

ARTICLE II (2) ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH 020001 Purpose and Application. ARTICLE II - REQUIRED USE OF PUBLIC SEWERS. PARAGRAPH 020001 Purpose and Application. Article II provides rules governing the allowable connection to the City POTW and the construction and inspection of

More information

STORMWATER POLLUTION PREVENTION PLAN TEMPLATE. 1.0 SITE DESCRIPTION 1.1 Project Name and Location Date

STORMWATER POLLUTION PREVENTION PLAN TEMPLATE. 1.0 SITE DESCRIPTION 1.1 Project Name and Location Date STORMWATER POLLUTION PREVENTION PLAN TEMPLATE Disclaimer: This template was developed for guidance purposes only in an effort to assist Construction Storm Water permit applicants in meeting state and local

More information

Beacon Hill Sewer District Standard Specifications

Beacon Hill Sewer District Standard Specifications Beacon Hill Sewer District Standard Specifications Residential Gravity Side Sewer Including Design Criteria and Standard Construction Drawings Residential Gravity Side Sewer Design Criteria 1. Provisions

More information

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials. PART 1 GENERAL 1.1 SCOPE A. This item shall include the work necessary for the installation of storm sewer line construction. B. Reference Section 3800 Trenching and Backfill and the General Conditions,

More information

SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS

SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING

More information

APPENDIX B. I. Background Information

APPENDIX B. I. Background Information APPENDIX B GUIDELINES FOR IDENTIFYING AND REPAIRING LOCALIZED AREAS OF DISTRESS IN AC PAVEMENTS PRIOR TO CAPITAL PREVENTIVE MAINTENANCE OR REHABILITATION REPAIRS I. Background Information A. AC Pavement

More information

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.

3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees. The following shall serve as the minimum requirements for contractors performing work in relation to the Authority s potable water and sanitary sewer system(s), appurtenances and service connections. General:

More information

Underground Commercial Electric Service

Underground Commercial Electric Service Underground Commercial Electric Service SCANA Corporation 2013 Revised: June 2013 Table of Contents SECTION PAGE I. Specification and Requirements 2 A. General B. Definition of Terms C. Company and Developer

More information

CITY OF ST. CA THARINE S. cn- Olc.4 BY-LAW NO. WHEREAS the Council of the Corporation of the City of St. Catharines, is

CITY OF ST. CA THARINE S. cn- Olc.4 BY-LAW NO. WHEREAS the Council of the Corporation of the City of St. Catharines, is ~: ~,,' " CITY OF ST. CA THARINE S BY-LAW NO. cn- Olc.4 A By-law to regulate sanitary and storm drainage. WHEREAS the Council of the Corporation of the City of St. Catharines, is authorized by the provisions

More information

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes)

SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes) SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes) Maintenance Office Administrative Office Billing Office 530-426-7802 530-426-7800 916-332-4872

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-31 31 16.19 (February 2016) -------------------------------- Preparing Activity: NAVFAC Superseding UFGS 31 31 16.19 (August 2014) UFGS 31 31 16.20 (April 2006) UFGS

More information

Storm Drain Inlet Protection

Storm Drain Inlet Protection Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Category

More information

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS TABLE OF CONTENTS I. RULES AND REGULATIONS A. TABLE OF CONTENTS... 2 B. TERMS AND DEFINITIONS... 3 C. DEVELOPER S/CONTRACTOR S RESPONSIBILITIES...

More information

STORM DRAIN DESIGN AND CONSTRUCTION STANDARDS & SPECIFICATIONS 400 SERIES

STORM DRAIN DESIGN AND CONSTRUCTION STANDARDS & SPECIFICATIONS 400 SERIES CITY OF PETALUMA STORM DRAIN DESIGN AND CONSTRUCTION STANDARDS & SPECIFICATIONS 400 SERIES AUGUST 1999 Revised 10/98 City of Petaluma Petaluma, California STORM DRAIN INSTALLATION DETAIL

More information

SECTION 33 11 00.19 ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section 01 33 00 - Submittals.

SECTION 33 11 00.19 ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section 01 33 00 - Submittals. SECTION 33 11 00.19 ABANDONMENT OF WATER MAINS PART 1: GENERAL 1.01 SCOPE A. Abandonment in place, by cutting and capping, of existing water mains, hydrants, service lines, and valves. B. Abandonment in

More information

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth

More information

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST

SITE-SPECIFIC BEST MANAGEMENT PRACTICES (SSBMP) PLAN/STORM WATER POLLUTION PREVENTION PLAN (SWPPP) REVIEW CHECKLIST This checklist may be used by applicants for encroachment permits, and contractors in development of Site Specific Best Management Practice (SSBMP) Plans or Storm Water Pollution Prevention Plans (SWPPP)

More information

Bethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL

Bethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL 155 E. Front Street (rear) Lititz, PA 17543 Phone (717) 625-1930 Fax (717) 625-1931 Bethel Township Municipal Authority (BTMA) RESIDENTIAL SEWER CONNECTION MANUAL CONSTRUCTION SPECIFICATIONS AND DETAILS

More information

Storm Drain Inlet Protection

Storm Drain Inlet Protection Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective

More information

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.

SECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions. SECTION LS 2530 SANITARY SEWERS PART 1 GENERAL 1.1 SUBMITTALS A. General: Submit the following in accordance with The General Conditions. 1. Product data for drainage piping specialties. 2. Shop drawings

More information

Specification Guidelines: Allan Block Modular Retaining Wall Systems

Specification Guidelines: Allan Block Modular Retaining Wall Systems Specification Guidelines: Allan Block Modular Retaining Wall Systems The following specifications provide Allan Block Corporation's typical requirements and recommendations. At the engineer of record's

More information

No allowance will be made for classification of different types of material encountered.

No allowance will be made for classification of different types of material encountered. PROJECT : Repair/ Maintenance of Flood Control and Drainage Structures Along Butuan City Cagayan de Oro City Iligan City Road LOCATION : San Antonio, Jasaan, Misamis Oriental SUBJECT : General Notes and

More information

SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE

SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE SECTION 02732 CLEANING AND CLOSED CIRCUIT TELEVISION (CCTV) INSPECTION OF SEWER PIPE PART 1 - GENERAL 1.01 WORK INCLUDED A. This section covers the initial and final cleaning, and the initial and final

More information

Specifications for Residential Property Owners Connection to New Public Sewer

Specifications for Residential Property Owners Connection to New Public Sewer Specifications for Residential Property Owners Connection to New Public Sewer Spalding Tract property owners are required to connect to the community sewer system when construction is complete and the

More information

SPECIAL NOTE FOR ASPHALT WATERPROOFING MIX FOR BRIDGE-DECK OVERLAYS AND ADJACENT APPROACHES

SPECIAL NOTE FOR ASPHALT WATERPROOFING MIX FOR BRIDGE-DECK OVERLAYS AND ADJACENT APPROACHES SPECIAL NOTE FOR ASPHALT WATERPROOFING MIX FOR BRIDGE-DECK OVERLAYS AND ADJACENT APPROACHES 1. DESCRIPTION. Asphalt Waterproofing Mix (AWM) is a highly elastomeric, polymermodified, impermeable asphalt

More information

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS

SECTION 33 31 00.11 GRAVITY SANITARY SEWERS SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit

More information

CITY ENGINEERS ASSOCIATION OF MINNESOTA

CITY ENGINEERS ASSOCIATION OF MINNESOTA CITY ENGINEERS ASSOCIATION OF MINNESOTA STANDARD SPECIFICATIONS 2600 Trench Excavation and Backfill/Surface Restoration 2611 Water Main and Service Line Installation 2621 Sanitary Sewer and Storm Sewer

More information

STANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES. 1. Structure Earthwork: 02200

STANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES. 1. Structure Earthwork: 02200 STANDARD SPECIFICATIONS SECTION 03461 PRECAST REINFORCED CONCRETE MANHOLES AND MANHOLE BASES PART 1 - GENERAL A. Description This section includes materials, testing, and installation of precast concrete

More information

ARTICLE VI (ALTERNATE) STANDARD SPECIFICATIONS. for (PVC) SANITARY SEWER MAIN CONSTRUCTION

ARTICLE VI (ALTERNATE) STANDARD SPECIFICATIONS. for (PVC) SANITARY SEWER MAIN CONSTRUCTION ARTICLE VI (ALTERNATE) STANDARD SPECIFICATIONS for (PVC) SANITARY SEWER MAIN CONSTRUCTION VI(A).1 General VI(A).2 Materials and Equipment VI(A).3 Installation of Sanitary Sewer Mains VI(A).4 Laying of

More information

Section 402. STORM SEWERS

Section 402. STORM SEWERS 402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide

More information

CHAPTER 2 QUANTITY TAKE-OFF

CHAPTER 2 QUANTITY TAKE-OFF CHAPTER 2 QUANTITY TAKEOFF The quantity takeoff is an important part of the cost estimate. It must be as accurate as possible and should be based on all available engineering and design data. Use of appropriate

More information

SC-07 STORM DRAIN INLET PROTECTION

SC-07 STORM DRAIN INLET PROTECTION Greenville County Technical Specification for: SC-07 STORM DRAIN INLET PROTECTION 1.0 Storm Drain Inlet Protection 1.1 Description Provide Storm Drain Inlet Protection at all existing and newly installed

More information

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION 1. SCOPE Pipe subsoil drains shall be constructed in accordance with this specification and in conformity with the lines, grades and cross-sections shown

More information

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile Chapter 3 CULVERTS Description A culvert is a closed conduit used to convey water from one area to another, usually from one side of a road to the other side. Importance to Maintenance & Water Quality

More information

FDOT Specifications List

FDOT Specifications List FDOT Specifications List TABLE OF CONTENTS DIVISION II CONSTRUCTION DETAILS CLEARING CONSTRUCTION SITE 110 Clearing and Grubbing... 152 EARTHWORK AND RELATED OPERATIONS 120 Excavation and Embankment...

More information

Exhibit A. Rules and Regulations for House Connections and Sewer Extensions

Exhibit A. Rules and Regulations for House Connections and Sewer Extensions The purpose of this application example is to provide assistance to small and medium sized rural communities in the drafting of documents necessary for the efficient operation of water, wastewater, and

More information

Riprap-lined Swale (RS)

Riprap-lined Swale (RS) Riprap-lined Swale (RS) Practice Description A riprap-lined swale is a natural or constructed channel with an erosion-resistant rock lining designed to carry concentrated runoff to a stable outlet. This

More information

SPECIAL SPECIFICATION 5757 Power Duct System

SPECIAL SPECIFICATION 5757 Power Duct System 2004 Specifications CSJ 0353-04-088 SPECIAL SPECIFICATION 5757 Power Duct System 1. Description. This Item shall govern for the furnishing and installing of all materials, equipment, and labor listed in

More information

SECTION 02630 STORM DRAINAGE SYSTEM

SECTION 02630 STORM DRAINAGE SYSTEM SECTION 02630 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for storm drainage systems including modifications and connections to existing storm drainage systems. 1.02 REFERENCE

More information

Concrete Waste Management

Concrete Waste Management Categories EC SE TC WE NS WM Erosion Control Sediment Control Tracking Control Wind Erosion Control Non-Stormwater Management Control Waste Management and Materials Pollution Control Legend: Primary Category

More information

UFGS-02362 (August 2004) UNIFIED FACILITIES GUIDE SPECIFICATIONS

UFGS-02362 (August 2004) UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-31 31 16.20 (April 2006) Change 2-11/14 ----------------------------- Preparing Activity: NAVFAC Replacing without change UFGS-02362 (August 2004) UNIFIED FACILITIES

More information

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS

MTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS Los Angeles, CA Project Manual and Specification DIVISION 1 GENERAL CONDITIONS 01 01 10 STATEMENT OF WORK 01 11 00 SUMMARY OF THE WORK 01 14 05 METRO (OWNER) - DIRECTED STOPPAGES 01 20 00 PRICE AND PAYMENT

More information

SECTION 6000 - EXCAVATION, TRENCHING AND BACKFILLING (Pipeline Construction)

SECTION 6000 - EXCAVATION, TRENCHING AND BACKFILLING (Pipeline Construction) SECTION 6000 - EXCAVATION, TRENCHING AND BACKFILLING (Pipeline Construction) 6001 SCOPE. This section covers excavation and trenching work and shall include the necessary clearing, grubbing, and preparation

More information

SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION 623.10 CONCRETE BONDING COMPOUND.

SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION 623.10 CONCRETE BONDING COMPOUND. SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION 623.10 CONCRETE BONDING COMPOUND. 623.10.1 Description. This work shall consist of preparing the surface,

More information

IAC 7/2/08 Utilities[199] Ch 9, p.1 CHAPTER 9 RESTORATION OF AGRICULTURAL LANDS DURING AND AFTER PIPELINE CONSTRUCTION

IAC 7/2/08 Utilities[199] Ch 9, p.1 CHAPTER 9 RESTORATION OF AGRICULTURAL LANDS DURING AND AFTER PIPELINE CONSTRUCTION IAC 7/2/08 Utilities[199] Ch 9, p.1 CHAPTER 9 RESTORATION OF AGRICULTURAL LANDS DURING AND AFTER PIPELINE CONSTRUCTION 199 9.1(479,479B) General information. 9.1(1) Authority. The standards contained herein

More information