Analysis II Façade Redesign: Architectural Precast Panels
|
|
- Corey Stewart
- 8 years ago
- Views:
Transcription
1 Analysis II Façade Redesign: Architectural Precast Panels
2 Analysis II Façade Redesign: Architectural Precast Panels Overview: This analysis covers the comparison of the current EIFS façade and my proposed change to architectural precast panels. It compares several important factors and shows the results of a structural analysis showing that the existing building can support the heavier façade. The precast is a higher quality and more durable system that will last the life of the building. It has a greater cost associated with it, but is well worth having confidence in the performance of the façade when it needs to last for the life of the building. Background: The façade of a building is the main barrier between the outside weather, and the interior of the building. It is crucial that the façade can keep water and moisture out of the building, and that it can handle the type of weather it is going to be exposed to. In the case of the Goizueta Foundation Center, the façade chosen was an exterior insulating finish system, which I will refer to as EIFS from here on. This system consists of several layers, shown in Figures 5 and 6 below. A. Substrate/Sheathing B. Adhesive C. EPS Insulation Board D. Reinforcing Mesh E. Base Coat F. Finish Coat Figure 5: Layers of the EIFS system used on the Foundation Center Figure 6: Isometric section of EIFS layers 21
3 EIFS has several benefits, but also many drawbacks. Mainly, it is not a good system to install in an area that receives a moderate amount of rainfall. This is the case with Atlanta. The average annual rainfall in Atlanta is 51. For a system that can have problems in wet areas, Atlanta does not seem to be a good place to be installing it. Not to say that EIFS may perform well in its initial testing for moisture penetration, but over the life of the building it will certainly need maintenance and/or repair. Moisture damage to a building with an EIFS façade can be extremely expensive to repair and replace. In some cases, the remediation costs more than the initial construction itself. The drawbacks of EIFS certainly validate a redesign of the façade. The foundation center is an educational building on a university campus. Universities build buildings that are going to be in use for 100 years or more. With this in mind, the building must then be exposed to 100 years of weather and storms. EIFS was first used in the United States in It is barely more than 35 years old. There is no guarantee that it can withstand 100 years of weather and storms because it hasn t been around even half that time for it to be tested. A university wants a building with a high quality façade, and that is why I chose architectural precast panels. I have compiled a list of factors that I feel are important when choosing a façade (see Table 4 below). Cost Weight Insulation Value Ease of Installation Water Tightness Factors EIFS Precast Panels EIFS is very cost effective, at about $10/sf. Second advantage, EIFS is a very light façade system The insulating board in the EIFS system has an R-value of 3.8 per inch thickness. Labor intensive, requires scaffolding and all work is done from the exterior. Entirely dependent on the quality of the installation. More expensive, Architectural Panels costing roughly $40/sf Architectural Panels weight 62.5lb/sf Concrete suffers here with an R-value of only.1 per inch thickness. Panels are placed by crane, and insulation is done from the inside. Water tightness can be achieved through sealants and is very effective. 22
4 Time of Installation Maintenance Durability Fire Resistance Quality Control In this case, 115 days, and requires steel construction to be completed before it can begin. Can be very costly, and is also labor intensive. EIFS has only been around for 35 years, no guarantee it can last for the typical life of a university building. Also only comes with a 5 year warranty, 10 year was purchased for this project. Tested for fire resistance, but materials are still combustible. Left up to field installation. Must be installed 100% per specifications or water penetration becomes a serious issue. Can be placed at a rate of 12 panels per day. Does not require steel structure to be complete to hang panels on lower levels. Little to no maintenance required. Extremely durable, can easily last 100 years under normal weather conditions. Concrete is noncombustible. All Panels are made in the factory in a quality-controlled environment. Table 4: Comparison between EIFS and Precast Panels Proposed Solution: Through the use of a precast panel façade, I hope to show that it would be a higher quality building that will last as long as the building will be expected to. Precast concrete is an extremely durable material, withstands all types of weather, and will be able to protect a building for 100 years. There are many other advantages that precast has over EIFS. EIFS is a labor intensive system to install. It requires scaffolding which increases the time it takes to install. Not only does the scaffolding make the installation time longer, but the fact that the steel erection must be completed before the EIFS can be installed. The foundation center was erected in two sequences. After sequence A was complete, the EIFS started installation there while the crane erected sequence B (see Figure 7 on the following page). 23
5 Figure 7: Steel erection and building skin sequence The entire steel sequence was approximately 85 days, 40 for the first sequence, and 45 for the second. The entire EIFS installation took a total of 115 days. This is 115 days after the first steel sequence was completed (see Figure 8 on the next page). Please refer to the schedule on the next page. The exterior skin installation lasted from October through March, so the building was exposed for the entire winter. If precast were being installed, there is no need for the steel structure to be complete for panels to be hung. There are a few opportunities to save schedule time here. First, a smaller crane could be used to hang panels on the lower levels of the building until it is out of reach, at which time the tower crane could take over placing panels. Second, the tower crane could set steel in the morning and panels in the evening. Either way, the building would be enclosed much sooner than in the case of the EIFS. It would likely be enclosed by the end of the year, being that there is no wait for the structure to be complete, and the precast would be insulated from the inside (see Table 5). EIFS Precast Panels 115 Days 60 Days 35, 25 10/11/2004 3/18/2005 Sequence A: 9/6/ /22/2005 Sequence B: 10/25/ /26/2004 Table 5: EIFS and Precast Panel schedule comparison 24
6 Figure 8: Detailed schedule of structural steel and EIFS construction sequences 25
7 Cost: Now to speak of the downsides of precast; its cost, weight, and insulation value. For the cost comparison, Table 6 shows the difference between the systems: Material Quantity Unit Unit Cost Total Cost EIFS façade sf $9.73 $554, Architectural Preacast sf $40.00 $2,280, Table 6: EIFS and Precast Panel cost comparison This is a substantial increase in cost. Not only does the material itself cost more than the EIFS, but precast also requires additional framing and insulation. I have added the rough cost of the framing and insulation into the per square foot cost of the precast panels. Insulation: For insulation, the precast system will use R-19 batt insulation. This will have a U-value around 0.05 vs for the EIFS system. To increase the efficiency of the precast system, a thicker insulation could be used, such as R-22. This is an important aspect of the façade because of its direct affect on heating and cooling costs. Structural Analysis: Lastly, I will discuss the weight issue. The architectural precast panels I have proposed to use are a solid 5 panel, made of normal weight concrete, and weighing 62.5 lb/sf. I analyzed a column on the NW (rear) elevation (see highlighted section in Figure 9 below). Figure 9: NW (Rear) Elevation with the analyzed column and surrounding precast panels highlighted 26
8 The panel connections are column bearing, so the spandrel beams do not require testing. I calculated the loads from the floor deck, beams and girders, façade, and roof that are carried by that column. The specifications state that the combined dead and live load carried to the columns from the floor deck is 225lb/sf. The composite deck is 3 18 gage with 6-¼ lightweight structural concrete and wwf 6x6 w1.4xw1.4. Using this information, I drew a model in the structural program RAM Advanse, and applied the loads I calculated at each floor level (see Table 7). I drew the column, defined the steel type and section sizes, and then analyzed it. After analyzing, I ran the check for code compliance, and the column was labeled OK under the applied load scenario. Screenshots from this analysis, as well as analysis reports can be found in the appendix of this document. Figure 10 (on the following page) shows the column, beams, and girders that were involved. Note that the column was spliced between the 3 rd and 4 th levels, as the drawing is not clear in showing this. Floor Level Lower Roof Level 5 Level 4 Level 3 Level 2 Load Type Loads Unit Total Load Roof 17.5 Façade 17.0 kip 19.4 Members 1.9 Slab Façade 15.7 kip 17.8 Members 2.1 Slab Façade 19.0 kip 1.9 Members 1.9 Slab Façade 21.8 kip 24.2 Members 2.4 Slab Façade 0.0 kip Members Table 7: Summary of loads from each level of the building transferred to the analyzed column 27
9 Lower Roof W18x35 W18x35 14 W24x55 W14x61 Level 5 Level 4 13 W24x55 W14x61 16 W14x99 Level 3 W21x W24x55 W14x99 Level W24x68 W14x99 Figure 10: Diagram of the analyzed column, with beams, girders, and floor heights shown The column I selected to analyze was the smallest in the rear elevation that was under the typical load I determined. Being that it was successful under the additional load of the precast, the remainder of the exterior columns would be as well. Conclusions: This analysis has brought to light the shortcomings of an EIFS façade and the benefits of using precast panels. After comparing all the important factors that are a part of façade selection, I feel that the precast panels would be a much smarter choice for this building. The main reasons being that it is a university building that will be standing and in use for the next 100 years, and precast is more than capable of protecting a building for this amount of time. The additional cost is a substantial increase, but to avoid repair and maintenance costs that will come in due time with EIFS, it will be a very wise decision to pay the greater initial cost. 28
Hunter College school of Social Work Thesis Proposal
Fall 2009 Hunter College school of Social Work Thesis Proposal To analyze how energy efficiency can be implemented using facade and green roof redesign. It ties structural engineering concepts with existing
More informationThe Prefab Package. Modular EIFS construction offers benefits to today s busy jobsites. Building Envelope. Roland Serino, P.E., of Dryvit Systems Inc.
26 D+D MARCH 2015 Building Envelope Roland Serino, P.E., Dryvit Systems Inc. here has always been a need for a more efficient way to build in large cities like Chicago, New York, Los Angeles or other central
More informationBUILDING SAFETY UNIT
POLICY Page 1 of 5 SUBMITTAL REQUIREMENTS FOR ONE AND TWO FAMILY DWELLINGS, ADDITIONS AND RENOVATIONS All submittals shall be site specific and designed to the provisions of the 2012 International Residential
More informationCOMMERCIAL BUILDING APPLICATIONS
EXPANDED POLYSTYRENE FOR COMMERCIAL BUILDING APPLICATIONS www.falconfoam.com Commercial Building Ap Expanded Polystyrene Insulation Falcon Foam leads the commercial building industry with products that
More informationSTAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM
STAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM Installed in Pre-engineered Steel Buildings Provides Lowest Cost Construction Method for CORROSIVE AND WET Environments PREFERRED SOLUTIONS, INC.
More informationCOLUMN-FREE OFFICE SPACE RISES IN CHICAGO S LOOP
COLUMN-FREE OFFICE SPACE RISES IN CHICAGO S LOOP 30 x45 bay provides maximum tenant flexibility and increases leasing marketability By David E. Eckmann AIA, S.E. P.E. SURGING DEMANDS FOR RENTABLE OFFICE
More informationPROJECT SUMMARY. Scope of work details: (If phased construction, please see plan submittal guidelines.)
APPENDIX B BUILDING CODE SUMMARY FOR ALL COMMERCIAL FIRE RESTORATION PROJECTS (EXCEPT 1 AND 2-FAMILY DWELLINGS AND TOWNHOUSES) (Reproduce the following data on the building plans sheet 1 or 2) Name of
More informationCOMMONLY USED RESIDENTIAL BUILDING CODES
COMMONLY USED RESIDENTIAL BUILDING CODES INTERNATIONAL RESIDENTIAL CODE (2009) form revised 5/10 FOUNDATION 1. DESIGN OF FORMWORK. Section 1906.1 IBC 2009, Section R404.1.2.3.6 IRC 2009, ACI 318 Section
More informationChapter 3 Pre-Installation, Foundations and Piers
Chapter 3 Pre-Installation, Foundations and Piers 3-1 Pre-Installation Establishes the minimum requirements for the siting, design, materials, access, and installation of manufactured dwellings, accessory
More informationSCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM
Shepherd University Board of Governors June 9, 2005 Agenda Item No. 9 SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM In 1994 construction began on the Byrd Science and
More informationISO Types 1-6: Construction Code Descriptions
ISO 1 Frame (combustible walls and/or roof) Class 1B Buildings where the exterior walls are wood or other combustible materials, including construction where the combustible materials are combined with
More informationNCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)
NCMA TEK National Concrete Masonry Association an information series from the national authority on concrete masonry technology CONCRETE MASONRY FOUNDATION WALL DETAILS TEK 5-3A Details (2003) Keywords:
More informationBuilding Code Clarifications - 7. Fire Resistance
Building Code Clarifications - 7. Fire Resistance 7.1 (15-12-030) Use of combustibles in Type III construction roof assemblies Code Section (15-12-030) Use of Combustibles was revised on May 17, 2000,
More informationWhen is a Permit Required? What Types of Permits are Required? The most common types of projects that require permits are:
When is a Permit Required? The most common types of projects that require permits are: -New Houses or buildings -Room Additions or Expansions -Structural repairs, remodeling and alterations -Accessory
More informationBuilding Owners Guide to a Duro-Last System!
Building Owners Guide to a Duro-Last System Table of Contents Section 1: Introduction to Duro-Last Roofing Systems Section 2: Benefits of a Duro-Last Roofing System Section 3: Comparing a Duro-Last Roof
More informationHow To Design A Post Tensioned Deck For A Building
SAMUEL ÁVILA STRUCTURAL OPTION FACULTY CONSULTANT: THOMAS BOOTHBY UNIVERSITY OF CENTRAL FLORIDA S ACADEMIC VILLAGES ORLANDO, FL THESIS PROPOSAL EXECUTIVE SUMMARY DECEMBER 12, 2005 Introduction: The University
More informationBuilt to Last. Built for Beauty. Good. Solid. Logix. TM
Built to Last. Built for Beauty. Good. Solid. Logix. TM Quality, Value and Service Introducing LOGIX Insulated Concrete Forms. Based on the simple concept of interlocking blocks, LOGIX ICF gives you a
More informationExterior Elevated Elements Inspection Guidelines
Exterior Elevated Elements Inspection Guidelines Planning and Development 1. Guideline Purpose These guidelines are intended to assist practicing professionals in complying with Berkeley Municipal Code
More informationBuilding Condition Assessment: 109-111 North Howard Street Baltimore, Maryland
KPA The Joint Venture of EBA Engineering, Inc. and Kennedy Porter & Associates, Inc. 4813 Seton Drive, Baltimore, MD 21215 Phone: (410-358-7171) Fax: (410)358-7213 Building Condition Assessment: Baltimore,
More informationTechPractices: Home Front Homes:
TechPractices: Home Front Homes: PATH's Technologies in Practice are large scale housing projects throughout the U.S. where innovative technologies are being installed and used. Information is presented
More information201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE
STRUCTURAL INSPECTION REPORT DRAFT 201 WATER STREET FORWARDERS MUSEUM AND VISITORS INFORMATION CENTRE TOWN OF PRESCOTT Date: November 2013 GENIVAR No.: 131-20617-00 2611 Queensview Drive, Suite 300, Ottawa,
More informationGYPSUM AREA SEPARATION FIREWALLS GA-620-2011
GYPSUM AREA SEPARATION FIREWALLS GA-620-2011 GA-620-2011 Copyright 2011 Gypsum Association All rights reserved. Printed in U.S.A. Characteristics, properties, or performance of materials or systems herein
More informationGeorgia State University. Urban Life Building Roof Replacement
ENGINEERING AND ENVIRONMENTAL 140 DECATUR STREET SE, ATLANTA, GA 30303 GEORGIA STATE UNIVERSITY - FACILITIES DESIGN & CONSTRUCTION 34 BROAD STREET, SUITE 100 ATLANTA, GA 30303 DRAWING INDEX A-0 PROJECT
More informationTechnical Assignment 2 TABLE OF CONTENTS
2 TABLE OF CONTENTS Executive Summary...3 Introduction..5 Gravity Loads......6 Design Codes......7 Materials..8 Existing Structural System.. 10 Existing Floor System 15 Alternate Floor Framing Systems...17
More informationCHAPTER 6 CONSTRUCTION TYPES
CHAPTER 6 CONSTRUCTION TYPES SECTION 601 GENERAL 601.1 Scope. Provisions of this chapter shall govern the classification of construction type by materials and fire resistance of its elements and the use
More informationCivil Engineering and Architecture (CEA) Detailed Outline
Civil Engineering and Architecture (CEA) Detailed Outline Unit 1: Overview of Civil Engineering and Architecture (23 days) Lesson 1.1: History of Civil Engineering and Architecture 1. Many features of
More informationThe Collapse of Building 7 by Arthur Scheuerman December 8, 06
The Collapse of Building 7 by Arthur Scheuerman December 8, 06 WTC s Building 7 was a 47-story office building completed in 1987 by Silverstein Properties on land owned by the Port Authority. It was built
More informationResidential Deck Safety, Construction, and Repair
Juneau Permit Center, 4 th Floor Marine View Center, (907)586-0770 This handout is designed to help you build your deck to comply with the 2006 International Residential Building code as modified by the
More informationBertrand Goldberg Archive. Inscription. Details. Erie Project. RX23664/43.1-31 Project Name Building Name AIC Reference Number
RX23664/43.1-31 Architectural drawings for housing. 589, 02 31 Feb. 14, 1985 Graphite, colored pencil, correction fluid, sepia marker, blackline on trace, mylar, vellum. working, design drawings Varies.
More informationWhat is QuickBase? Traditional foundations (left) compared with QuickBase (right)
QuickBase is an innovative new foundation and floor system for conservatories and lightweight structures which was launched in prototype form at last year s Interbuild exhibition, where it was hailed as
More informationfirst look at GigaCrete s revolutionary new New Construction GigaHouse GigaHouse Utilizing GigaPanel
first look at GigaCrete s revolutionary new New Construction GigaHouse GigaHouse Utilizing GigaPanel What is GigaCrete GigaCrete is a family of products based on low carbon footprint Green ceramic binders
More information1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona
for Earthen Material and Straw Bale Structures SECTION 70 - GENERAL "APPENDIX CHAPTER 7 - EARTHEN MATERIAL STRUCTURES 70. Purpose. The purpose of this chapter is to establish minimum standards of safety
More informationCONSTRUCTION DETAILS & LOAD DESIGN CHARTS
Office and Production 126 New Pace Rd., PO Box 279 Newcomerstown, OH 43832 1-800-446-2188, Fax: 740-498-4184 www.buildwithsips.com CONSTRUCTION DETAILS & LOAD DESIGN CHARTS Table of Contents Description
More informationEAST LYME HIGH SCHOOL
Overview: 1971 N 1966 GYM 1966 CLASSROOM WING 1966 AUD. 1971 GYM 1998 1998 POOL EAST LYME HIGH SCHOOL Original 1966 Building: The original East Lyme High School was constructed in 1966 and was composed
More informationThe minimum reinforcement for the stem wall is the placement of:
PolySteel creates an ideal insulated stem wall for concrete slabs that can make this part of your project easier and faster, in addition to making your finished project more energy-efficient. Figures 3.20
More informationEnvelope INSULATION BATT (2) Avoid Using Batt Insulation With Metal Framing. Pressure or Friction Fit
R-H-DI1 INSULATION BATT NR-E-IB1 Avoid Using Batt Insulation With Metal Framing Batt insulation should not be used with metal framing systems. Although it is common to see fiberglass batt insulation installed
More informationBuilding Construction. Structural Systems 1. Load-bearing wall construction 2. Skeleton framing 3. Combination of the two
Structural Systems 1. Load-bearing wall construction 2. Skeleton framing 3. Combination of the two Factors governing type selection Economics not necessarily the one that requires the least structural
More information8 EXTRA LIGHT GRC SANDWICH ELEMENTS FOR ROOFING IN INDUSTRIAL BUILDINGS
8 EXTRA LIGHT GRC SANDWICH ELEMENTS FOR ROOFING IN INDUSTRIAL BUILDINGS MARICA DELLA BELLA and DIEGO CIAN Precompressi Centro Nord S.p.A., Italy SUMMARY: Secondary roofing elements, complementary to the
More informationHanson Building Products. precast basement solutions
Hanson Building Products precast basement solutions Hanson Building Products Basement Systems Add an extra dimension and combine the inherent flexible, structural and waterproof properties of concrete
More information2008-2009 Cost Comparisons for Common Commercial Wall Systems
An Independent Study LA MS KY TN AL GA SC NC FL 2008-2009 Cost Comparisons for Common Commercial Systems CAPITAL BUILDING CONSULTANTS PROFESSIONAL CONSTRUCTION ESTIMATORS 2008 2009 INDEPENDENT COST COMPARISONS
More informationIs Your Envelope Effective? Mark Lawton P.Eng Morrison Hershfield Limited Vancouver
Is Your Envelope Effective? Mark Lawton P.Eng Morrison Hershfield Limited Vancouver Designing an Effective Envelope Roofs Below Grade Walls and slabs Glazing & Windows Opaque portions of walls 2 3 Energy
More informationExcerpts from the Canadian National Building Code (NBC)
Excerpts from the Canadian National Building Code (NBC) Reproduced here with Permission of the Copyright Owner, the National Research Council of Canada, Institute for Research in Construction. For more
More informationDESIGNERS GUIDE TO DOMESTIC CONSERVATORIES
WBCA 403 DESIGNERS GUIDE TO DOMESTIC CONSERVATORIES A guide to assist those intending to install or who are involved in installing conservatories. Includes information about: conservatory and component
More informationRehab Inspection Report Page 1
Rehab Inspection Report Page 1 Home Address: Construction Style: Number of bedrooms Square footage: Value of offer: Estimated rehab cost: Value of resale: Orientation of house: N S E W Note: orientation
More informationThe better way to build TM. Installation Manual. FOUNDATION SIPs & FROST WALLS SIPs
The better way to build TM Installation Manual FOUNDATION SIPs & FROST WALLS SIPs February 2016 PWF FOUNDATION & FROST WALL SIPs Installation Manual Table of Contents Topics General Requirements...................................
More information6 RETROFITTING POST & PIER HOUSES
Retrofitting Post & Pier Houses 71 6 RETROFITTING POST & PIER HOUSES by James E. Russell, P.E. 72 Retrofitting Post & Pier Houses Retrofitting Post & Pier Houses 73 RETROFITTING POST AND PIER HOUSES This
More informationROXUL Board Insulation Section 07 21 13 Master Guide Specification (CAVITYROCK ) Page 1 April 2016
Master Guide Specification (CAVITYROCK ) Page 1 Click on the pilcrow in the MS Word Toolbar to toggle ROXUL GUIDE NOTES on and off. Delete this text before incorporating the section into a Project Manual.
More informationSection 5.0. Basements. Wall insulated externally. Wall insulated internally. Ba02. Product: Polyfoam ECO Floorboard Ba01.
Section 5.0 Basements Wall insulated externally Product: Polyfoam ECO Ba01 Wall insulated internally Product: Polyfoam ECO Ba02 Basements Basements Basement design Waterproofing BS 8102: 2009 Code of practice
More informationResidential Prototype III. Multi-Story. The Multi-Story. Your connection to ideas + answers. Prepared by: AISC Steel Solutions Center
Multi-Story Residential Prototype III The Multi-Story Residential Prototype III Prepared by: AISC Steel Solutions Center What s this? This package tells the story of a fictitious project with an imaginary
More informationAdvantages and Disadvantages of Timber Frame Construction
Appendix 1: Table A1.1 Advantages and Disadvantages of Timber Frame Construction Advantages of Timber Frame Construction Quick erection times Reduced site labour Reduced time to weather the structure Earlier
More informationElevating Your House. Introduction CHAPTER 5
CHAPTER 5 Elevating Your House Introduction One of the most common retrofitting methods is elevating a house to a required or desired Flood Protection Elevation (FPE). When a house is properly elevated,
More informationWilliamson and Associates, Inc. Report of Building Exterior Condition Evaluation, dated January 2 nd, 2013. (68 pages)
INNOVATIVE BUILDING AND ARCHITECTURE CONSULTANTS Mr. Bud Hall Senior Vice President of construction Turnberry Associates 19501 Biscayne Boulevard, Suite 400 Aventura, FL 33180 Subject: The Nashville Hilton
More informationComposite Panel Firewall Systems
Composite Panel Firewall Systems part of the Protecting more than your business Insulated mineral fibre panels have excellent thermal and acoustic properties, ideal for factory and office partition walls.
More informationStructural Foundation System
Structural Foundation System SLABTEK, a technological advancement in foundation designs for residential and lightweight commercial structures SlabTek is a patent allowed process for concrete foundations
More information2014 British Columbia Building Code Changes
District of Houston 250-845-2238 2014 British Columbia Building Code Changes A District of Houston interpretation of the 2014 Building Code Changes for 9.36 & 9.32 The following changes reflect the most
More informationHOOVER TREATED WOOD PRODUCTS, INC. TECHNICAL NOTE FOR ADDITIONAL INFORMATION: 1-800-TEC-WOOD (832-9663)
HOOVER TREATED WOOD PRODUCTS, INC. TECHNICAL NOTE FOR ADDITIONAL INFORMATION: 1-800-TEC-WOOD (832-9663) Fire-Retardant-Treated Wood Framed Wall Assemblies GENERAL INFORMATION Fire-resistant construction
More informationCommercial Building Valuation Report
INSURED University of Houston - Victoria Effective Date: Expiration Date: Cost as of: 09/2010 BUILDING 1 217 - University Center 77901 Location Adjustments Climatic Region: High Wind Region: Seismic Zone:
More informationPANEL CONCEPTS LLLP.
The Small Cottage Company DO-IT-YOURSELF CABINS & COTTAGES PANEL CONCEPTS INC. PANEL CONCEPTS LLLP. 2826 Gold 331 Creek N. M-33, Road Mio, Gold Michigan Creek, Montana 4864759733 (989) 826-6511 (406) 288-8585
More informationFire 2This Technical Bulletin has been commissioned by the UK SIP Association in
REV 1-12.12.11/TB002 Technical Bulletin Fire 2This Technical Bulletin has been commissioned by the UK SIP Association in conjunction with TRADA Technology and is intended to provide the reader with introductory
More informationPreventing Ice Dams on Roofs
Preventing Ice Dams on Roofs Facility Manager November/December 2005 When a roof leaks, facility managers inevitably receive complaints from building occupants. If it is winter, ice dams are often the
More informationInspecting to a higher standard.
Inspecting to a higher standard. Rob Hopkin Silver Spring, MD 20902 Monday, June 2, 2014 ProTec Inspection Services Inc. 19736 Selby Ave Poolesville, MD 20837 301-972-8531 www.protec-inspections.com rob@protec-inspections.com
More informationSUBSTANTIAL IMPROVEMENT OR SUBSTANTIAL DAMAGE NOTICE TO PROPERTY OWNER
NOTICE TO PROPERTY OWNER Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule. If your home or business is below
More informationH-Stud Area Separation Wall System
12 TH EDITION 09 21 16.33/NGC H-Stud Area Separation Wall System 09 21 16.33 139 H-STUD AREA SEPARATION WALL SYSTEM The fire-protection of gypsum-based Area Separation Walls is demonstrated in dramatic
More informationCertification: Building Plans Examiner. Exam ID: B3
Certification: Building Plans Examiner Exam ID: B3 Scope: A Building Plans Examiner will be responsible for reviewing submitted plans to determine if they meet the requirements of the various Building
More informationBuilding Foundation and Structure
Building Foundation and Structure Overview The construction of the Hall of Waters building began in 1936, and was constructed over the original site of the Siloam and Sulpho-Saline Springs. The original
More informationPatio Covers / Carports
Patio Covers / Carports Building Guides for Homeowners Why Do I need a Permit? D I D Y O U K N O W? As owner-builder you are the responsible party of record on such a permit. If your work is being performed
More informationWhitley Manufacturing Co., Inc. 201 W. First Street S. Whitley, IN 46787 Phone (260) 723-5131 Sales Fax (260) 723-6396 whitley@whitleyman.
Building Type Building Code Whitley Classroom Buildings BOCA, UBC, SBCCI, NEC, ADA Structural Support Outrigger construction standard, Whitley model classrooms. Main support beams to be 12 11.8# per lineal
More informationAir-Conditioning, Heating, and Refrigeration Institute. Sheet Metal and Air-Conditioning Contractors National Association
Air-Conditioning, Heating, and Refrigeration Institute Sheet Metal and Air-Conditioning Contractors National Association GUIDELINE B-1997 ACKNOWLEDGEMENT These guidelines for Roof Mounted Outdoor Air-
More informationInstallation Instructions
Installation Instructions Pedestal Models FS 500 LE FS 800 LE Insert Models IS 500 LE IS 800 LE Pecan Engineering Pty Ltd 13 Acorn Road Dry Creek South Australia 5094 Email info@pecan-eng.com.au Phone:
More informationFIRE AND SMOKE PROTECTION FEATURES
CHAPTER 7 FIRE AND SMOKE PROTECTION FEATURES SECTION 70 GENERAL 70. Scope. The provisions of this chapter shall govern the materials, systems and assemblies used for structural fire resistance and fire-resistance-rated
More informationAppendix B. 2010 Florida Building Code Building Section 423.25 Public Shelter Design Criteria
Appendix B 2010 Florida Building Code Building Section 423.25 Public Shelter Design Criteria 423.25 Public shelter design criteria. 423.25.1 New facilities. New educational facilities for school boards
More informationFiberglas, Exterior Wall Thermal Insulation
PROJECT ENGINEER RESPONSIBILITY: This is a general specification guide, intended to be used by experienced construction professionals, in conjunction with good construction practice and professional judgment.
More informationHow To Compare Roofing Material
Roofing Material Comparisons Housing Fact Sheets One of the great strengths of our market economy is the number of product choices we are provided with. So when it comes time to replace the roof on your
More informationCommercial And Industrial Steel Buildings
Commercial And Industrial Steel Buildings Arco Building Systems, Inc. Since 1979 Arco has been providing the highest quality steel buildings to contractors and owners throughout the United States. Leadership
More informationCold Weather Concrete Practices
Cold Weather Concrete Practices The Information below is an outline of common practice for residential foundation placement and winter construction utilize Edmonton and surrounding Area. Conditions in
More informationResidential Inspection Guidelines
Residential Inspection Guidelines 201 Pre-Pour Foundation Dimensions Building Location Certificate - if required in the building consent Construction and Advice Notes Check the building dimensions against
More informationTABLE OF CONTENTS" SECTION 3: Comparing Standing Seam Metal to Other Metal Roofs PAGE 7"
2 TABLE OF CONTENTS SECTION 1: What is a Standing Seam Metal Roof PAGE 3 SECTION 2: Common Types of Standing Seam Metal Roofs..PAGE 5 SECTION 3: Comparing Standing Seam Metal to Other Metal Roofs PAGE
More informationMEMORANDUM. 1509 West Swann Avenue, Suite 225 Tampa, Florida 33606 Phone (813) 258-8818 Fax (813) 258-8525
1509 West Swann Avenue, Suite 225 Tampa, Florida 33606 Phone (813) 258-8818 Fax (813) 258-8525 To: From: Date: Subject: Mr. Thomas Gibson, City of St. Petersburg Jeffrey D. Malyszek, PE and Deborah C.
More informationEstimated Cost of Repair
1 Applicant: Property: Home: Business: Assessor: Applicant Number: Type of Loss: Hurricane Date Contacted: 1/18/2014 Date of Loss: 10/29/2012 Date Received: 1/14/2014 Date Inspected: 2/4/2014 Date Entered:
More informationCOMMERCIAL PLAN SUBMISSION FOR NEW CONSTRUCTION AND/OR RENOVATIONS
COMMERCIAL PLAN SUBMISSION FOR NEW CONSTRUCTION AND/OR RENOVATIONS Permit applicants shall submit three (3) COMPLETE SETS of plans and specifications with each application for a permit. Plans and specifications
More informationCHAPTER 7: Building Systems ROOFING SYSTEMS
ROOFING SYSTEMS Purpose Examples 1. Shingle roof system 2. Metal roof with blanket insulation 3. Metal roof with rigid insulation 4. Built-up asphalt roof system 5. Single-ply roof system 6. Modified Bitumen
More informationHow To Understand The World Trade Center'S Structural Design
Emerging Technologies in Structural Engineering Proc. of the 9 th Arab Structural Engineering Conf., Nov. 29 Dec. 1, 2003, Abu Dhabi, UAE WORLD TRADE CENTER COLLAPSE, FIELD INVESTIGATIONS AND ANALYSES
More informationCERTIFICATE NAME OF PRODUCT MANUFACTURER PRODUCT DESCRIPTION CERTIFICATION PROCEDURE. No VTT C-6044-10 Date of issue 11.10.2010, Updated July 1, 2011
CERTIFICATE NAME OF PRODUCT No VTT C-6044-10 Date of issue 11.10.2010, Updated July 1, 2011 H-CONTROL REFLEX+ reflective insulating vapour control layer for roof and wall applications MANUFACTURER ACTIS
More informationRoof Inspection. Summary Report
Phone: (561) 866 9956 www.real-estate-inspections.com Roof Inspection Summary Report Subject Property File Number: 05-15-RF-002 Inspector: Craig Milliken, PE CPM Real Estate Inspections, Inc. Date of Inspection:
More informationRe: Damages to Alaska Building from Legislative Information Office Construction
510 L Street Suite 200 Anchorage, AK 99501-1949 (907) 274-22362236 Phone (907) 274-25202520 Fax www.bbfm.com July 22, 2015 Jim Gottstein Alaska Building 406 G Street, Suite 206 Anchorage, AK 99501 Re:
More informationLow-slope reroofing guidelines
Low-slope reroofing guidelines by Thomas Bollnow and Joan P. Crowe, AIA The NRCA Roofing and Waterproofing Manual, Fifth Edition, contains reroofing guidelines for steep- and low-slope roofing. The August
More informationRenovating Your Basement
building science.com 2006 Building Science Press All rights of reproduction in any form reserved. Renovating Your Building America Report - 0309 2003 (revised 2007) Building Science Corporation Abstract:
More informationBusiness area System/product family System/product Exterior restore group. Sto restore Advanced Restoration for Building Façades
Business area System/product family System/product Exterior restore group Sto restore Advanced Restoration for Building Façades Sto restore Restoring building exteriors to protect the value of your investment.
More informationUp-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations
Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Nathan A. Ingraffea, P.E., S.E. Associate, KPFF Consulting Engineers, Portland, Oregon, USA Abstract The use of steel sheet
More informationInsulation R-Value Comparisons
Insulation R-Value Comparisons American Ingenuity s component panels for the 22 48 domes contains seven inch thick rigid Expanded Polystyrene (E.P.S.) insulation which has an R value of 28. American Ingenuity
More informationEcoTouch Insulation with PureFiber Technology
PROJECT ENGINEER RESPONSIBILITY: This is a general specification guide, intended to be used by experienced construction professionals, in conjunction with good construction practice and professional judgment.
More informationPANELIZED HOME INSTALLATION GUIDELINE
PANELIZED HOME INSTALLATION GUIDELINE A typical home package will be constructed of Snap-N-Lock Insulated Panels clad with steel skins. 4" panels will be used for the walls, and 6" panels for the roof.
More informationBridge Type Selection
Bridge Type Selection The major consideration for bridge type selection for bridges on the State Aid system is initial cost. Future maintenance costs, construction time, and location are considered when
More informationTD AMERITRADE Park Omaha
TD AMERITRADE Park Omaha November 19, 2009 Report No. 6 MONTHLY CONSTRUCTION PROGRESS REPORT METROPOLITAN ENTERTAINMENT & CONVENTION AUTHORITY MONTHLY CONSTRUCTION PROGRESS REPORT Metropolitan Entertainment
More information7 INNOVATIONS IN SECONDARY DRAINAGE SYSTEMS
7 INNOVATIONS IN SECONDARY DRAINAGE SYSTEMS K. F. YAROSH Dow Corning S.A., Parc Industriel-Zone C, B-7180 Seneffe, Belgium SUMMARY: This paper will review innovative internal backup secondary drainage
More informationSpecial Use Commercial Properties
Contents Overview of Special Use Commercial Properties...3 Understanding Fast Food Restaurants...3 Understanding Gasoline Service Stations...4 Understanding Self-Service Cashier Booths...5 Understanding
More informationTechnical Assignment 2
Architectural Engineering 2012 Senior Thesis -+ + Technical Assignment 2 Reston Station Phase 1 Garage Reston, VA Jonathan A Fisher Oct. 12, 2012 A d v i s o r : D r. R o b e r t L e i c h t Executive
More informationFOAMULAR LT40, 400 and 600 insulations with minimum compressive strengths of
Technical Guide FOAMULAR Extruded Polystyrene Insulation For Cold Storage Applications FOAMULAR extruded polystyrene insulation is suitable for virtually all cold storage insulating needs, including floors,
More informationFIRE AND SMOKE PROTECTION FEATURES
CHAPTER 7 FIRE AND SMOKE PROTECTION FEATURES SECTION 70 GENERAL 70. Scope. The provisions of this chapter shall govern the materials, systems and assemblies used for structural fire resistance and fire-resistance-rated
More informationMaterials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections
Materials Standard shapes W sections, C channels, Structural T, Angles, Pipes, Tubes, Rods and Plates Fabricated members, Built-up sections Adding plates to beam flanges, Stiffeners to beam webs Built
More information