1 Waste Management System for the City of Poznan PPP Incineration Plant Project December 2011

2 Project Background Financial situation of the City limited City resources, high indebtedness of the City EU grant New waste legislation in Poland (July 2011) Complex Project New PPP legislation (2009) no large PPP projects completed successfully so far Timetable Experience first large hybrid PPP in Poland, first large incineration plant project in Poland 01/12/2011 Page 2

3 Contract (EPC) Contract (O&M) PPP agreement Project Structure Residents Municipal waste management fee Charges for collection and delivery of municipal waste from residents EU funds Private Partner s remuneration Poznan City Cession of PPP agreement payments (or other collateral) excessive third party revenue / profit or deductions/ contractual penalties The Poznan project will be carried out in DBFO (design-buildfinance-operate) scheme Transport companies Private Partner (or SPV) Loan agreements Financing institutions Recipients of the products Third party revenues, e.g.: from sale of heat from sale of electricity from sale of green certificates from sale of recovered recyclables Equity and/or subordinated debt Investors * Private Partner (or SPV) General contractor Operator (*) Subcontractors Collaborators 12/1/2011 Page 3

4 UE Grant (5) Qualified expenses refund (6) Transfer of project own contribution (2) Payment for construction works executed Implementation Body Poznan City Private Partner Construction work subcontractor (4) Request for payment (3) Transfer of the paid invoice for construction works (1) Invoice for construction works executed Expenses related to the implementation of the Project, namely the construction of the installation (qualified expenses) will be covered by the Private Partner (authorized entity) who will transfer the invoices received from subcontractors to the City. Invoices will be the basis for submitting the request for payment and obtaining reimbursement by the City of expenditure incurred by the Private Partner from the EU grant. 12/1/2011 Page 4

5 Challenges timetable (1/3) Timetable interdependence between the PPP tender process and the EU grant application 30/06/ /10/2011 Current project stage 03/2012* 10/2012* Application form Application form appraisal Conditional financing agreement JASPERS appraisal Submitting application form to EC UE appraisal UE decision Application form update Suggestion To make project viable in the assumed timeframe - either the approach of the EC should be more flexible or the interdependence should be broken otherwise. 12/1/2011 Tender announcement Private Parters submitting bid applications Competitive dialogue procedure Selection of Private Partner * Preliminary schedule The financial structure of the project will be discussed and prepared with shortlisted bidders during the competitive dialogue Page 5

6 Challenges timetable (2/3) Timetable EC requires mature projects (EIA, building permits, etc.) The regulation 1083/2006 determines the scope of information on major projects to be sent to the EC. However, in practice, the EC demands more information than required e.g. results of PPP tender. Suggestion EU grant approved at an earlier stage on conditional terms. 01/12/2011 Page 6

7 Challenges timetable (3/3) Timetable PPP process is lengthy and sometimes may overlap with subsequent programming periods It may take up to 10 years to implement a PPP project since the conceptual phase. The EU programming periods assume there are only 9 years to implement the project and settle EU grant. In practice the period is shorter because the negotiations on cohesion policy and operational programs with Member States often end later than the start of eligiblity period. Suggestion Conditions of EU grant approval in each programming period should be known as early as possible. The rules relating to phasing of large projects should be absolutely clear from the outset of each programming period 01/12/2011 Page 7

8 Challenges: EU grant uncertainty to obtain the grant / uncertainty of the level of grant (1/3) Who can and who should take the risk of not getting EU grant or getting it lower than expected? Beneficiary Private partner may apply for the EU grant Solution: Allowing for a switch between public and private beneficiary during the PPP process Questions: In practice, are the private partners willing to take a risk of applying for EU grant? Should they include EU grant in their bids or be obliged to apply for it having been selected? Will the EC change policy and allow for switching a private partner beneficiary during the PPP process? How to incentivise private partner to apply for EU grant? Poznan solution: The City controls the grant process and takes the risk of applying for EU grant. In case EU grant is not obtained higher costs are to be borne by inhabitants. The clear split of obligations between the city and a private partner should be included in the PPP contract in relation to EU grant management and settlements. 01/12/2011 Page 8

9 Challenges: EU grant uncertainty to obtain grant / uncertainty of level of grant (2/3) Funding gap might be revised based on the private partners tenders Risk of loss or reduction of the amount of grant as a result of tender results or changes in the Project New revenue sources (e.g. green certificates after 2017) or fundamental change in tariff policy - the obligation to recalculate the funding gap. For funding gap calculation purposes project revenues are revenues of the City of Poznan (fees from residents and infrastructure) - the risk of grant reduction due to changes in income controlled by the City. The risk of grant reduction due to decrease in capex (change in grant amount without the necessity to recalculate the funding gap). Considered solution: Project structure based on availability payments. The changes in CAPEX will have impact on EU grant level. Suggestion: In the next financial perspective safeguards on the EU grant level is a good solution 01/12/2011 Page 9

10 Challenges: EU grant uncertainty to obtain grant / uncertainty of level of grant (3/3) Funding gap might be revised based on the private partners tenders Unknown project revenues Unknown funding gap level Unknown private partner bids Unknown EU grant level Unknown financing costs Unknown private equity 01/12/2011 Page 10

11 Document purpose This document was compiled by Corporate Finance sp. z o.o. ( EYCF ) and has been prepared solely for information purposes in connection with utilizing EU funds in PPP projects. This document is not intended to provide a basis for financing the Project and should not be seen as a recommendation to participate in the Project. Any entity interested in participating in the financing or other activities in relation to the Project is responsible for conducting their own analysis. This document is based on publicly available data and the information contained in it has not been verified by EYCF and EYCF do not bear any responsibility to any parties that may obtain a copy of this document. 12/1/2011 Page 11

12 Contacts Jarosław Błaszczak Partner Corporate Finance Sp. z o.o. Rondo ONZ 1, Warsaw Tel: Łukasz Piekarski Chief Expert, Department for Individual Projects' Preparation Lukasz.Piekarski@mrr.gov.pl Ministry of Regional Development ul. Wspólna 2/4, Warsaw Tel.: /1/2011 Page 12

eeef - European Energy Efficiency Fund

eeef - European Energy Efficiency Fund eeef - European Energy Efficiency Fund Agenda 1 2 3 Introduction to eeef Eligibility check for projects Technical Assistance 4 Potential project structures 5 Case Studies 2 eeef at a glance Objective Beneficiaries

More information

Annex 2: Rules and Procedures for the Swiss-Polish Cooperation Programme

Annex 2: Rules and Procedures for the Swiss-Polish Cooperation Programme Annex 2: Rules and Procedures for the Swiss-Polish Cooperation Programme Annex 2 is an integral part of the Framework Agreement between the Swiss Federal Council and the Government of the Republic of Poland

More information

International Seminar on Strengthening Public Investment and Managing Fiscal Risks from Public-Private Partnerships

International Seminar on Strengthening Public Investment and Managing Fiscal Risks from Public-Private Partnerships International Seminar on Strengthening Public Investment and Managing Fiscal Risks from Public-Private Partnerships Budapest, Hungary March 7 8, 2007 The views expressed in this paper are those of the

More information

Guidance on the template contract for social impact bonds and payment by results

Guidance on the template contract for social impact bonds and payment by results Guidance on the template contract for social impact bonds and payment by results Introduction These guidance notes have been prepared to assist users of the Cabinet Office template contract. The guidance

More information

SUPPLEMENTARY GREEN BOOK GUIDANCE

SUPPLEMENTARY GREEN BOOK GUIDANCE SUPPLEMENTARY GREEN BOOK GUIDANCE ADJUSTING FOR TAXATION IN PFI vs PSC COMPARISONS 1 INTRODUCTION 1.1 This guidance looks at the differential tax receipts that arise from the use of the Private Finance

More information

Preliminary Draft JOB DESCRIPTIONS AND QUALIFICATIONS OF KEY PERSONNEL. XXXXX PPP Unit

Preliminary Draft JOB DESCRIPTIONS AND QUALIFICATIONS OF KEY PERSONNEL. XXXXX PPP Unit Preliminary Draft JOB DESCRIPTIONS AND QUALIFICATIONS OF KEY PERSONNEL XXXXX PPP Unit Chief Executive Officer Job Description: The CEO is tasked with the establishment of a PPP Unit for the Government

More information

Combining EU Grant Funding with PPP for Infrastructure: Conceptual Models and Case Examples

Combining EU Grant Funding with PPP for Infrastructure: Conceptual Models and Case Examples JASPERS Horizontal Task Outputs Working Paper Combining EU Grant Funding with PPP for Infrastructure: Conceptual Models and Case Examples Report prepared on the basis of a Consultancy Contract with PricewaterhouseCoopers

More information

PPP GLOSSARY. Availability. Base Case. Bidder BOOT BOT. Business Case. Commercial Operations Date (COD) Concession

PPP GLOSSARY. Availability. Base Case. Bidder BOOT BOT. Business Case. Commercial Operations Date (COD) Concession PPP GLOSSARY Availability Base Case Bidder Bond BOOT BOT Term Business Case Capex Commercial Operations Date (COD) Concession Meaning The period when the facility (or the relevant part thereof) is able

More information

Developing by Public Private Partnership (PPP): Meeting infrastructure needs successfully.

Developing by Public Private Partnership (PPP): Meeting infrastructure needs successfully. Developing by Public Private Partnership (PPP): Meeting infrastructure needs successfully. Vicky D. Kefala Head, Investments & Development Projects Consolidated Contractors Company (CCC) MBA Finance, BA

More information

METHOD FOR PROJECT APPRAISAL: NET PRESENT VALUE OR NPV The sum of discounted cash flows.

METHOD FOR PROJECT APPRAISAL: NET PRESENT VALUE OR NPV The sum of discounted cash flows. OBJECTIVE: ECONOMIC ANALYSIS OF A PROJECT, consisting of the operation of a new incineration plant by the municipality. In particular we are interested in the computaton of a Solid Waste Tariff, consistent

More information

II ENPCOM MEETING Models of interaction between the public and private sector in transport and housing

II ENPCOM MEETING Models of interaction between the public and private sector in transport and housing II ENPCOM MEETING Models of interaction between the public and private sector in transport and housing Financial tools in energy efficiency projects under PPP schemes Piero Atella 22-25 Giugno 2014 Bruxelles

More information

Scheme and Guidelines for India Infrastructure Project Development Fund

Scheme and Guidelines for India Infrastructure Project Development Fund Scheme and Guidelines for India Infrastructure Project Development Fund Department of Economic Affairs Ministry of Finance Government of India Contents Preamble. iii Acronyms and definitions vii 1. The

More information

PPP Basics and Principles of a PPP Framework

PPP Basics and Principles of a PPP Framework Note 1 May 2012 PPP Basics and Principles of a PPP Framework This note is the first in a series of notes on developing a comprehensive policy, legal, and institution framework for public-private partnership

More information

PUBLIC PRIVATE PARTNERSHIP HANDBOOK

PUBLIC PRIVATE PARTNERSHIP HANDBOOK PUBLIC PRIVATE PARTNERSHIP HANDBOOK VERSION 2 March 2012 1 CONTENTS Section 1: Introduction to Public Private Partnerships... 3 1.1 What is Public Private Partnership?... 4 1.2 Typical PPP Delivery Models...

More information

FINANCING PPP IN INTESA SANPAOLO GROUP

FINANCING PPP IN INTESA SANPAOLO GROUP FINANCING PPP IN INTESA SANPAOLO GROUP Bulgaria Italy Bilateral Cooperation Project Models and Strategies for Public-Private Partnership Rome, 23 rd October 2007 Intesa Sanpaolo Group - Overview Intesa

More information

VAT in the European Community APPLICATION IN THE MEMBER STATES, FACTS FOR USE BY ADMINISTRATIONS/TRADERS INFORMATION NETWORKS ETC.

VAT in the European Community APPLICATION IN THE MEMBER STATES, FACTS FOR USE BY ADMINISTRATIONS/TRADERS INFORMATION NETWORKS ETC. EUROPEAN COMMISSION DIRECTORATE-GENERAL TAXATION AND CUSTOMS UNION Indirect Taxation and Tax administration VAT and other turnover taxes VAT in the European Community APPLICATION IN THE MEMBER STATES,

More information

Developing a Public-Private Partnership Framework: Policies and PPP Units

Developing a Public-Private Partnership Framework: Policies and PPP Units Note 4 May 2012 Developing a Public-Private Partnership Framework: Policies and PPP Units This note is the fourth in a series of notes on developing a comprehensive policy, legal, and institution framework

More information

Wind Farm Project Finance

Wind Farm Project Finance Wind Farm Project Finance Financing and Technical Requirements Gabriele Ferrante PPP Task Force, Presidency of the Council of Ministers, Italy Models and Strategies for Public-Private Private Partnerships

More information

LAW OF MONGOLIA ON CONCESSIONS CHAPTER ONE. GENERAL PROVISIONS

LAW OF MONGOLIA ON CONCESSIONS CHAPTER ONE. GENERAL PROVISIONS LAW OF MONGOLIA 28 January 2010 State Palace, Ulaanbaatar city Article 1. Purpose of the law ON CONCESSIONS CHAPTER ONE. GENERAL PROVISIONS 1.1. The purpose of this law is to regulate matters related to

More information

PUBLIC-PRIVATE PARTNERSHIP (PPP)

PUBLIC-PRIVATE PARTNERSHIP (PPP) PUBLIC-PRIVATE PARTNERSHIP (PPP) Virginia Tan, Allen & Overy Type: Published: Last Updated: Keywords: Legal guide June 2012 June 2012 PPP, infrastructure assets, public and private sectors This document

More information

Guidelines on Allowable Project Costs

Guidelines on Allowable Project Costs Guidelines on Allowable Project Costs 2013/2014 LIST OF CONTENTS 1. INTRODUCTION 3 2. BUDGET CATEGORIES 5 2.1 HUMAN RESOURCES 5 2.2 RUNNING COSTS (DIRECT COSTS) 7 2.3 OVERHEADS (INDIRECT COSTS) 8 2.4 CAPEX

More information

How To Fund A Project

How To Fund A Project PREPARATORY ACTION IN THE FIELD OF SPORT Administrative and Financial Management Handbook The rules outlined in this Administrative and Financial Handbook apply to the projects funded by the Preparatory

More information

Employment in Poland 2012

Employment in Poland 2012 BRIEFING NOTE Employment in Poland 2012 1. Employment Cost 2. Legal System 3. Employer s obligations 4. Types of employment contract 5. Working time 6. Holiday 7. Sick pay 8. Parenthood rights 9. Mass

More information

PPP seminar. High Level Regional Workshop on PPPs in the Middle East Jordan. June 2010

PPP seminar. High Level Regional Workshop on PPPs in the Middle East Jordan. June 2010 PPP seminar High Level Regional Workshop on PPPs in the Middle East Jordan June 2010 Suez Environnement EMPLOYEES > 65,000 CONSOLIDATED REVENUES 2008 12,4 Billion SUEZ ENVIRONNEMENT IS THE SOLE PLAYER

More information

SKANSKA SPECIFICATIONS TO GENERAL CONDITIONS FOR BUILDING CONTRACTS 1998

SKANSKA SPECIFICATIONS TO GENERAL CONDITIONS FOR BUILDING CONTRACTS 1998 1 (6) SKANSKA SPECIFICATIONS TO GENERAL CONDITIONS FOR BUILDING CONTRACTS 1998 Offer If the offer diverges from the invitation to tender, it must be mentioned explicitly and relevantly in order to be able

More information

SKAGIT COUNTY DEBT POLICY. Page 1 of 12

SKAGIT COUNTY DEBT POLICY. Page 1 of 12 SKAGIT COUNTY DEBT POLICY Page 1 of 12 SKAGIT COUNTY DEBT POLICY INDEX Page I. Roles and Responsibilities 3 II. Debt and Capital Planning 3-4 III. Credit Objectives 4-5 IV. Purpose, Type and Use of Debt

More information

8 Operation of the Emergency Call Answering Service

8 Operation of the Emergency Call Answering Service 8 Operation of the Emergency Call Answering Service 8.1 All emergency calls made in the State are handled by the Emergency Call Answering Service (ECAS). The ECAS is operated from three centres, located

More information

Tender Procedures for EU-funded Projects

Tender Procedures for EU-funded Projects Tender Procedures for EU-funded Projects Membership in the European Union opens up an opportunity for Bulgaria to utilize up to 7 billion EUR during the period 2007-2013. The economic and social areas

More information

SUEZ ENVIRONNEMENT GROUP WATER SECTOR:

SUEZ ENVIRONNEMENT GROUP WATER SECTOR: Workshop on PPP Amman, June 6 & 7, 2010 J. Ouechec SUEZ ENVIRONNEMENT GROUP WATER SECTOR: PPP references & lessons learnt in Near & Middle East region Tripoli Lebanon Management Contract Case Funds: Agence

More information

Agreements, bonds and guarantees

Agreements, bonds and guarantees Agreements, bonds and guarantees SPV Formation The Special Project Vehicle (SPV) may take a variety of forms, including a corporation, limited liability company, general partnership, limited partnership,

More information

REQUEST FOR QUOTATION No. 34/2013 Date of issuance: 13.12.2013. Training courses may be conducted in English or Polish.

REQUEST FOR QUOTATION No. 34/2013 Date of issuance: 13.12.2013. Training courses may be conducted in English or Polish. REQUEST FOR QUOTATION No. 34/2013 Date of issuance: 13.12.2013 The Foundation for Polish Science runs the SKILLS project, cofounded by the European Union within the European Social Fund (The Operational

More information

GESTAMP WIND 10 SP. Z O.O.

GESTAMP WIND 10 SP. Z O.O. Warszawa, 15 September 2014 REQUEST FOR QUOTATION for services of CONSTRUCTION SUPERVISION for project Construction of Szerzawy Wind Farm 10 MW together with associated infrastructure GESTAMP WIND 10 SP.

More information

Copernicus Information Day Q&A presentation

Copernicus Information Day Q&A presentation COPERNICUS CLIMATE CHANGE SERVICE COPERNICUS ATMOSPHERE MONITORING SERVICE Copernicus Information Day Q&A presentation 2 February 2015 Introduction Quite a number of delegates submitted questions in advance

More information

CABINET 26 JULY 2011 PROCUREMENT OF LONG TERM WASTE TREATMENT FACILITIES REPORT OF THE DIRECTOR OF ENVIRONMENT AND TRANSPORT

CABINET 26 JULY 2011 PROCUREMENT OF LONG TERM WASTE TREATMENT FACILITIES REPORT OF THE DIRECTOR OF ENVIRONMENT AND TRANSPORT K CABINET 26 JULY 2011 PROCUREMENT OF LONG TERM WASTE TREATMENT FACILITIES REPORT OF THE DIRECTOR OF ENVIRONMENT AND TRANSPORT Purpose of Report PART A 1. The purpose of this report is to seek Member approval

More information

How To Improve Energy Efficiency

How To Improve Energy Efficiency Energy Efficiency in the Public Sector through ESCOs Steps forward to developing the ESCO market Toivo Miller Energy Efficiency and Climate Change EBRD - London HQ millert@ebrd.com European Bank for Reconstruction

More information

2.6 Select a. procurement route. cabe. Contents

2.6 Select a. procurement route. cabe. Contents 2.6 Select a procurement route 2.6.1 Procurement routes Procurement is the purchasing of products, work and services. It is more important than its unglamorous name suggests and plays a major part in any

More information

METHODOLOGICAL NOTE GENERAL GOVERNMENT DEBT COMPILED ACCORDING TO THE METHODOLOGY OF THE EXCESSIVE DEFICIT PROCEDURE (EDP)

METHODOLOGICAL NOTE GENERAL GOVERNMENT DEBT COMPILED ACCORDING TO THE METHODOLOGY OF THE EXCESSIVE DEFICIT PROCEDURE (EDP) METHODOLOGICAL NOTE GENERAL GOVERNMENT DEBT COMPILED ACCORDING TO THE METHODOLOGY OF THE EXCESSIVE DEFICIT PROCEDURE (EDP) Introduction The functions attributed to the Banco de España by Spanish legislation

More information

6 STEP 6 - PREPARING THE ACTION PLAN 2

6 STEP 6 - PREPARING THE ACTION PLAN 2 CONTENTS 6 STEP 6 - PREPARING THE ACTION PLAN 2 6.1 USER GUIDE TO THIS STEP 2 6.2 KEY MESSAGES OF THIS STEP 4 6.3 PREPARING THE ACTION PLAN 5 6.4 PRE-FEASIBILITY STUDY 8 6.5 PREPARING AN INVESTMENT PLAN

More information

Guidance on Framework Agreements

Guidance on Framework Agreements 1. Introduction Guidance on Framework Agreements The purpose of this document is to provide guidance to public purchasers on the operation of framework agreements as provided for under current public procurement

More information

EnPC/ESCO in Romania (public buildings and public lighting)

EnPC/ESCO in Romania (public buildings and public lighting) EnPC/ESCO in Romania (public buildings and public lighting) Dana Ionescu EBRD Bogdan Anton Tractebel Engineering 17 November 2014 Content: EU Context Romanian Context Benefits of EnPC / ESCO EBRD specific

More information

PRACTICE NOTE 22 THE AUDITORS CONSIDERATION OF FRS 17 RETIREMENT BENEFITS DEFINED BENEFIT SCHEMES

PRACTICE NOTE 22 THE AUDITORS CONSIDERATION OF FRS 17 RETIREMENT BENEFITS DEFINED BENEFIT SCHEMES PRACTICE NOTE 22 THE AUDITORS CONSIDERATION OF FRS 17 RETIREMENT BENEFITS DEFINED BENEFIT SCHEMES Contents Introduction Background The audit approach Ethical issues Planning considerations Communication

More information

SCARBOROUGH BOROUGH COUNCIL

SCARBOROUGH BOROUGH COUNCIL SCARBOROUGH BOROUGH COUNCIL CABINET 4 APRIL 2006 A ITEM AGENDA ITEM NO A8 JOINT REPORT OF THE HEAD OF LEGAL SERVICES HLS/06/17 AND THE STRATEGIC DIRECTOR OF OPERATIONS SDO/06/16 on THE COUNCIL S PROCUREMENT

More information

ADMINISTRATIVE REGULATION AR: 6.03 DATE APPROVED September 10, 2002 ORIGINATING DEPARTMENT:

ADMINISTRATIVE REGULATION AR: 6.03 DATE APPROVED September 10, 2002 ORIGINATING DEPARTMENT: ADMINISTRATIVE REGULATION AR: 6.03 DATE APPROVED September 10, 2002 SUBJECT: ORIGINATING DEPARTMENT: Debt Management Policy Office of Management & Budget Page 1 of 8 I. PURPOSE: The County recognizes the

More information

Financing PPPs with project bonds

Financing PPPs with project bonds European PPP Expertise Centre European PPP Expertise Centre European PPP Expertise Centre European PPP Expertise Centre European PPP Expertise Centre Financing PPPs with project bonds Issues for public

More information

Environment and energy briefing from Burges Salmon published in the March 2014 issue of The In-House Lawyer:

Environment and energy briefing from Burges Salmon published in the March 2014 issue of The In-House Lawyer: Environment and energy briefing from Burges Salmon published in the March 2014 issue of The In-House Lawyer: Electricity market reform: an update on contracts for difference Electricity market reform:

More information

Electricity Settlements Company Ltd Framework Document

Electricity Settlements Company Ltd Framework Document Electricity Settlements Company Ltd Framework Document This framework document has been drawn up by the Department of Energy and Climate Change in consultation with the Electricity Settlements Company.

More information

The Electricity Supply Bill 1

The Electricity Supply Bill 1 Bill no. 234 Folketinget (Danish Parliament) 1998-99 Unauthorised translation 30 June 1999 Submitted on 29 April 1999 by the Minister for Environment and Energy (Svend Auken) Adopted by Folketinget on

More information

Introduction from the Chair - Michael Burnett

Introduction from the Chair - Michael Burnett OECD International Transport Forum Roundtable: Public-Private Partnerships for Transport Infrastructure Renegotiations - How to approach them and economic outcomes, George Mason University, Washington

More information

Department of Health PFU & PPP Forum. Benchmarking and market testing in NHS PFI projects. Code of Best Practice

Department of Health PFU & PPP Forum. Benchmarking and market testing in NHS PFI projects. Code of Best Practice Department of Health PFU & PPP Forum Benchmarking and market testing in NHS PFI projects Code of Best Practice This Code of Best Practice provides guidance and advice on good practice to NHS Trusts, Project

More information

Negotiations feedback for successful project preparation. ERANIS workshop, 27.11.2007, Minsk

Negotiations feedback for successful project preparation. ERANIS workshop, 27.11.2007, Minsk Negotiations feedback for successful project preparation Negotiations procedure Feedback from the Commission on the project plan issues that need to be explained in more detail Request to formulate Annex

More information

Business Plan. Recycling Project

Business Plan. Recycling Project Business Plan Recycling Project Prepared by Sustainable Environmental Technologies For Makana Municipality Contact Mark Horan - m.horan@ru.ac.za Tel. 046 603 8834 Cell. 072 186 7518 Shirley Horan - s.horan@ru.ac.za

More information

Maintaining value for money in the operational phase of PPP contracts

Maintaining value for money in the operational phase of PPP contracts Maintaining value for money in the operational phase of PPP contracts Michael Burnett, Director, European PPP Forum, European Institute of Public Administration, OECD meeting of Senior PPP Officials, 18

More information

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s. PPP Modalities

T o o l k i t f o r P u b l i c - P r i v a t e P a r t n e r s h i p s i n r o a d s & H i g h w a y s. PPP Modalities PPP Modalities Types and characteristics of PPP are presented in several sections of the Toolkit: refer Types of PPP in Key Issues. This section provides some consideration of which modality, or which

More information

Export Initiative Renewable Energy

Export Initiative Renewable Energy Export Initiative Renewable Energy Wind Energy Sector Tunisia Financing Opportunities and Risk Mitigation Project Finance International: Dr. Joachim Richter www.export-erneuerbare.de PFI Corporate Profile

More information

https://www.ofgem.gov.uk/publications-and-updates/ofto-build-providing-additional-flexibility-through-extendedframework

https://www.ofgem.gov.uk/publications-and-updates/ofto-build-providing-additional-flexibility-through-extendedframework All interested parties Direct Dial: 020 7901 1849 Email: transmissioncompetition@ofgem.gov.uk Date: 17 November 2015 Dear Colleague EPC Contract Principles for OFTO Build Tenders This letter provides guidance

More information

HOME EQUITY LINE OF CREDIT/CLOSED-END MORTGAGE COST PROGRAM. Program special for loans approved from January 1, 2016 February 29, 2016.

HOME EQUITY LINE OF CREDIT/CLOSED-END MORTGAGE COST PROGRAM. Program special for loans approved from January 1, 2016 February 29, 2016. HOME EQUITY LINE OF CREDIT/CLOSED-END MORTGAGE COST PROGRAM Program special for loans approved from January 1, 2016 February 29, 2016. U.S. Postal Service Federal Credit Union offers its members a Home

More information

The European Fund for Strategic Investments (EFSI)

The European Fund for Strategic Investments (EFSI) The European Fund for Strategic Investments (EFSI) Europaforum Norra Sverige Monica Peña Sastre, Policy Adviser 09.10.2015 European Investment Bank Group 1 EIB: The EU Bank Natural financing partner for

More information

PPP Seminar : Health Royal Liverpool Hospital Case study

PPP Seminar : Health Royal Liverpool Hospital Case study PPP Seminar : Health Royal Liverpool Hospital Case study Gavin Quantock Deloitte Corporate Finance 23 July 2014 Case study Royal Liverpool hospital PPP and Health Background Deloitte involvement Structure

More information

TAX PRESS REVIEW 9/2008 VAT

TAX PRESS REVIEW 9/2008 VAT TAX PRESS REVIEW 9/2008 We are proud to present the eighth edition of our Tax Press Review which contains a selection of rulings and interpretations that had been issued or published in August. We hope

More information

Date: 26/01/2004. MEETING NAME Executive Delegation of award of energy supply contracts

Date: 26/01/2004. MEETING NAME Executive Delegation of award of energy supply contracts Item No. Classification: Open Report title: Ward(s) or groups affected: From: Date: 26/01/2004 MEETING NAME Executive Delegation of award of energy supply contracts ALL Assistant Chief Executive Strategy

More information

Construction Contracts

Construction Contracts STATUTORY BOARD FINANCIAL REPORTING STANDARD SB-FRS 11 Construction Contracts This version of SB-FRS 11 does not include amendments that are effective for annual periods beginning after 1 January 2015.

More information

private finance initiative

private finance initiative private finance initiative Lessons Learned We recently held a series of PFI Roundtable Discussions in collaboration with Trowers & Hamlins LLP. Finance managers from throughout the UK were invited to share

More information

eeef European Energy Efficiency Fund

eeef European Energy Efficiency Fund eeef European Energy Efficiency Fund Agenda 1 introduction to eeef - key elements 2 eeef investments: eligibility, process and project structures 3 Case studies 4 Final Remarks 2 1a eeef at a glance Objective

More information

Annual Consolidated Financial Statements of the ING Bank Śląski S.A. Group

Annual Consolidated Financial Statements of the ING Bank Śląski S.A. Group Annual Consolidated Financial Statements of the ING Bank Śląski S.A. Group for the year 2008 Table of contents Annual consolidated financial statements of the ING Bank Śląski S.A. Group Consolidated profit

More information

Agenda item: Environment & Community Safety Decision meeting

Agenda item: Environment & Community Safety Decision meeting Title of meeting: Agenda item: Environment & Community Safety Decision meeting Date of meeting: 14 th November 2014 Subject: Report by: Wards affected: Key decision: Full Council decision: Waste Disposal

More information

UNECE PPP Healthcare Standard

UNECE PPP Healthcare Standard INTERNATIONAL SPECIALIST CENTRE OF EXCELLENCE ON PPPs IN HEALTH MANILA, PHILIPPINES UNECE PPP Healthcare Standard Questions on lessons learned in the development of Public-Private Partnership ( PPP ) programmes

More information

Financing PPPs: Project Finance June 2006

Financing PPPs: Project Finance June 2006 Financing PPPs: Project Finance June 2006 Index Section I. Section II. Section III. Project Finance Spanish Market Advantages Risk Matrix P. 2 Section I Project Finance Project Finance Definition Definition:

More information

General Conditions for Loans reference No.: General Terms and Conditions for Loans dated 1 March 2016

General Conditions for Loans reference No.: General Terms and Conditions for Loans dated 1 March 2016 General Conditions for Loans reference No.: General Terms and Conditions for Loans dated 1 March 2016 These General Conditions for Loans is made between ( Lender )and the Entity who signs the Schedule

More information

The Eligible Asset Pools Program

The Eligible Asset Pools Program Legacy Loans Program Summary of Terms The Federal Deposit Insurance Corporation ( FDIC ) and the United States Department of the Treasury ( UST ) will coordinate public-private investment funds ( PPIFs

More information

Advanced training for tax auditors in the field of computer audit. 1.1 CRIS Number: 2006/018-180.01-03 Twinning No: PL/06/IB/FI/01/TL

Advanced training for tax auditors in the field of computer audit. 1.1 CRIS Number: 2006/018-180.01-03 Twinning No: PL/06/IB/FI/01/TL 1. Basic Information Advanced training for tax auditors in the field of computer audit 1.1 CRIS Number: 2006/018-180.01-03 Twinning No: PL/06/IB/FI/01/TL 1.2 Title: Advanced training for tax auditors in

More information

ARKANSAS DEVELOPMENT FINANCE AUTHORITY REQUEST FOR PROPOSALS FOR WATER FINANCIAL ADVISORY SERVICES FOR PROGRAMS OF THE

ARKANSAS DEVELOPMENT FINANCE AUTHORITY REQUEST FOR PROPOSALS FOR WATER FINANCIAL ADVISORY SERVICES FOR PROGRAMS OF THE ARKANSAS DEVELOPMENT FINANCE AUTHORITY REQUEST FOR PROPOSALS FOR WATER FINANCIAL ADVISORY SERVICES FOR PROGRAMS OF THE SPECIAL NOTE: YOUR IMMEDIATE ATTENTION IS CALLED TO SECTION I.C. YOU NEED TO SEND

More information

Building and Planning

Building and Planning Description of Services Building and Planning 2012 Danish Association of Consulting Engineers The Danish Association of Consulting Engineers (FRI) and the Danish Association of Architectural Firms (DANSKE

More information

CUSTOM BUILD SERVICED PLOTS LOAN FUND PROSPECTUS CONTINUOUS MARKET ENGAGEMENT. June 2015

CUSTOM BUILD SERVICED PLOTS LOAN FUND PROSPECTUS CONTINUOUS MARKET ENGAGEMENT. June 2015 CUSTOM BUILD SERVICED PLOTS LOAN FUND PROSPECTUS CONTINUOUS MARKET ENGAGEMENT June 2015 Contents Introduction and aims 3 The Custom Build Serviced Plot Loan Fund 4 Eligibility criteria 6 Further information

More information

INQUIRY. www.synthosgroup.com

INQUIRY. www.synthosgroup.com INQUIRY CONTRACTOR SELECTION for EPCM quote for investment deal: Construction of Waste to Energy (WTE) facility for SYNTHOS DWORY 7 Sp. z ograniczoną odpowiedzialnością S.K.A. in Oświęcim Extent of inquiry:

More information

Electricity Market Reform:

Electricity Market Reform: Electricity Market Reform: Consultation on Low Carbon Contracts Company s and Electricity Settlements Company s operational costs 2015/16 Government Response January 2015 Crown copyright 2015 URN 15D/001

More information

Edmonton Waste Management Centre Contract Review November 2, 2015

Edmonton Waste Management Centre Contract Review November 2, 2015 Edmonton Waste Management Centre Contract Review November 2, 2015 The Office of the City Auditor conducted this project in accordance with the International Standards for the Professional Practice of Internal

More information

REGULATION OF THE MINISTER OF ECONOMY 1 of 15 June 2007 on Financial Support granted by the National Capital Fund

REGULATION OF THE MINISTER OF ECONOMY 1 of 15 June 2007 on Financial Support granted by the National Capital Fund REGULATION OF THE MINISTER OF ECONOMY 1 of 15 June 2007 on Financial Support granted by the National Capital Fund Pursuant to Article 14, Section 2 of the Act of 4 March 2005 on the National Capital Fund

More information

City of Chicago TAX INCREMENT FINANCING POLICY GUIDELINES

City of Chicago TAX INCREMENT FINANCING POLICY GUIDELINES TAX INCREMENT FINANCING POLICY GUIDELINES Department of Housing and Economic Development 121 N. LaSalle St. #1000 Chicago, IL 60602 2012 Policy guidelines for the Tax Increment Financing program are subject

More information

Impacts on the construction industry of the new revenue standard

Impacts on the construction industry of the new revenue standard IFRS Impacts on the construction industry of the new revenue standard September 2014 kpmg.com/ifrs Contents The devil is in the detail 1 1 Critical judgements at contract inception 2 1.1 Pre-contract costs

More information

Auditor General Procurement Processes Review - Bid Bonds/Performance Bonds

Auditor General Procurement Processes Review - Bid Bonds/Performance Bonds STAFF REPORT June 22, 2005 To: From: Subject: Administration Committee Deputy City Manager and Chief Financial Officer Auditor General Procurement Processes Review - Bid Bonds/Performance Bonds Purpose:

More information

1.2 These Financial Regulations shall come into force on 19 th December 2012

1.2 These Financial Regulations shall come into force on 19 th December 2012 Part 4F FINANCIAL REGULATIONS GENERAL FR1 1.1 These Financial Regulations are made pursuant to the Local Government Act 1972 Section 151 the Accounts and Audit (England) Regulations 2011 (as amended) and

More information

Law on Bankruptcy and Liquidation of Banks and Insurance Companies (Official Gazette of the Republic of Serbia, No. 14/2015)

Law on Bankruptcy and Liquidation of Banks and Insurance Companies (Official Gazette of the Republic of Serbia, No. 14/2015) Law on Bankruptcy and Liquidation of Banks and Insurance Companies (Official Gazette of the Republic of Serbia, No. 14/2015) (Unofficial Translation) I. BASIC PROVISIONS Article 1 This Law governs the

More information

PRE-QUALIFICATION ANNOUNCEMENT

PRE-QUALIFICATION ANNOUNCEMENT Warsaw March 9, 2011 PRE-QUALIFICATION ANNOUNCEMENT The contracting authority 00-526 Warsaw, ul. Krucza 24/26, Poland Website: www.elektrowniapolnoc.pl Contact person: Mr. Marek Obuchowicz E-mail: info@elektrowniapolnoc.pl

More information

This bill creates the following section of the Florida Statutes: 627.4138

This bill creates the following section of the Florida Statutes: 627.4138 BILL: SB 810 The Florida Senate BILL ANALYSIS AND FISCAL IMPACT STATEMENT (This document is based on the provisions contained in the legislation as of the latest date listed below.) Prepared By: The Professional

More information

Appendix 5D Ernst & Young Accounting Treatment

Appendix 5D Ernst & Young Accounting Treatment Appendix 5D Accounting Treatment (Ernst & Young) Appendix 5D Ernst & Young Accounting Treatment Introduction An off balance sheet treatment from the position of the Authorities is a fundamental requirement

More information

ESCO Financing. State of Israel Ministry of National Infrastructure. Pierre Baillargeon. March 2007 ECONOLER INTERNATIONAL

ESCO Financing. State of Israel Ministry of National Infrastructure. Pierre Baillargeon. March 2007 ECONOLER INTERNATIONAL ESCO Financing State of Israel Ministry of National Infrastructure Pierre Baillargeon March 2007 Agenda Evaluation of the EE market Introduction to the ESCO concept Introduction to performance contracts

More information

ENGAGING A LANDSCAPE CONSULTANT GUIDANCE FOR CLIENTS ON FEES SEPTEMBER 2002

ENGAGING A LANDSCAPE CONSULTANT GUIDANCE FOR CLIENTS ON FEES SEPTEMBER 2002 ENGAGING A LANDSCAPE CONSULTANT GUIDANCE FOR CLIENTS ON FEES SEPTEMBER 2002 The Landscape Institute 33 Great Portland Street London W1W 8QG Tel: +44 (0)20 7299 4500 Fax: +44 (0)20 7299 4501 Email: mail@llandscapeinstitute.org

More information

In past years many structured finance

In past years many structured finance Securitization plugs gaps in health funding Patrizio Messina of Orrick Herrington & Sutcliffe analyzes how arise within the Italian system and describes some of the structures being used In past years

More information

ASEAN Bilateral Program 2012

ASEAN Bilateral Program 2012 ASEAN Bilateral Program 2012 Presentation on PPP Financial Structures 30 October 2012 Contents Introduction Our PPP Experience Key Elements of a PPP Project Risk Allocation The Payment Mechanism Financing

More information

eeef - European Energy Efficiency Fund Investing into Energy Efficiency Projects: why and how? November 6 2014, Brussels

eeef - European Energy Efficiency Fund Investing into Energy Efficiency Projects: why and how? November 6 2014, Brussels eeef - European Energy Efficiency Fund Investing into Energy Efficiency Projects: why and how? November 6 2014, Brussels Advancing Sustainable Energy for Europe Agenda 1 eeef - key elements 2 Implemented

More information

DELAWARE STATE HOUSING AUTHORITY REQUEST FOR PROPOSALS FOR FINANCIAL ADVISORY SERVICES

DELAWARE STATE HOUSING AUTHORITY REQUEST FOR PROPOSALS FOR FINANCIAL ADVISORY SERVICES DELAWARE STATE HOUSING AUTHORITY REQUEST FOR PROPOSALS FOR FINANCIAL ADVISORY SERVICES I. Overview The Delaware State Housing Authority (DSHA) seeks firms interested in providing independent financial

More information

Consolidated Extended Financial Statements of Echo Investment Capital Group for the 1st half of 2009

Consolidated Extended Financial Statements of Echo Investment Capital Group for the 1st half of 2009 SEMI-ANNUAL REPORT 2009 Consolidated Extended Financial Statements of Echo Investment Capital Group for the 1st half of 2009 August 31, 2009 Semi-annual Report for the 1st half of 2009 1 I. Consolidated

More information

Section 1 Summary and Recommendations

Section 1 Summary and Recommendations REPORT FOR: CABINET Date of Meeting: 13 January 2011 Subject: Key Decision: Responsible Officer: Portfolio Holder: Exempt: Decision subject to Call-in: Enclosures: Sports and Leisure Facilities Management

More information

Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000

Department of the Environment and Local Government. Project Management. Public Private Partnership Guidance Note 7. 14 April 2000 Project Management Project Management Public Private Partnership Guidance Note 7 14 April 2000 Guidance Note 7 14 April 2000 Project Management Contents Section Page I INTRODUCTION...1 SCOPE AND PURPOSE

More information

Gebze Izmir Motorway & Izmit Bay Crossing Project

Gebze Izmir Motorway & Izmit Bay Crossing Project Gebze Izmir Motorway & Izmit Bay Crossing Project F.Mehmet Coşan CFO Haluk BÜYÜKBAŞ Secretary General, TCA Gebze Orhangazi Izmir Project is the landmark transaction for the infrastructure sector in Turkey

More information

Publication of financial information pursuant to the Capital Adequacy Regulation (Pillar 3)

Publication of financial information pursuant to the Capital Adequacy Regulation (Pillar 3) Publication of financial information pursuant to the Capital Adequacy Regulation (Pillar 3) The purpose of the requirements for the public disclosure of financial information is to help various market

More information

Note 2 SIGNIFICANT ACCOUNTING

Note 2 SIGNIFICANT ACCOUNTING Note 2 SIGNIFICANT ACCOUNTING POLICIES BASIS FOR THE PREPARATION OF THE FINANCIAL STATEMENTS The consolidated financial statements have been prepared in accordance with International Financial Reporting

More information

SAMPLE. Professional Indemnity Insurance (PII) Policy 2015/16. lawcover.com.au Page 1

SAMPLE. Professional Indemnity Insurance (PII) Policy 2015/16. lawcover.com.au Page 1 Professional Indemnity Insurance (PII) Policy 2015/16 Lawcover Insurance Pty Limited ABN 15 095 082 509 Level 13, 383 Kent Street Sydney NSW 2000 DX 13013 Sydney Market Street Telephone: 1800 650 748 (02)

More information

JANNEY MONTGOMERY SCOTT LLC Statement of Financial Condition Year ended June 30, 2013 (Unaudited)

JANNEY MONTGOMERY SCOTT LLC Statement of Financial Condition Year ended June 30, 2013 (Unaudited) JANNEY MONTGOMERY SCOTT LLC Statement of Financial Condition Year ended June 30, 2013 (Unaudited) Janney Montgomery Scott LLC Financial Statements and Supplemental Information For the year ended June 30,

More information

NSSMP Technical & Financial Toolkit. Joint ADB-WB Philippine Workshop on Wastewater Management 29 January 2014

NSSMP Technical & Financial Toolkit. Joint ADB-WB Philippine Workshop on Wastewater Management 29 January 2014 NSSMP Technical & Financial Toolkit Joint ADB-WB Philippine Workshop on Wastewater Management 29 January 2014 1 Outline I. Technical and Financial Toolkit II. Parameters used in the Financial Toolkit III.

More information