I&C Status in France & Recommendations to IAEA

Size: px
Start display at page:

Download "I&C Status in France & Recommendations to IAEA"

Transcription

1 I&C Status in France & Recommendations to IAEA IAEA TWG-NPPIC Meeting May 2013 Vienna Patrick SALAUN EDF R&D

2 Contents 1. I&C projects at EDF NPPs The 900 MW series 3 rd Ten-Yearly Outage 4 th Ten-Yearly Outage The 1300 Mw Series 3rd Ten-Yearly Outage The N4 Series 2nd Ten-Yearly Outage The EPR Plant 2. R&D Topics at EDF 3. Some Recommendations to IAEA IAEA - TWGNPPIC Meeting May

3 Nuclear Power Plants in France Nuclear power in France : 74,8% (2012) 59 nuclear units, erected following 4 different standards: PWR 900 MW series : 34 units 6 CP0, 18 CP1, 10 CP2 units Connection to the grid: rd ten-yearly outage: th ten-yearly outage : PWR 1300 MW series : 20 Units 6 P4 / 14 P 4 units Connection to the grid: nd ten-yearly outage: rd ten-yearly outage: PWR 1450 MW series : 4 units Connection to the grid: nd ten-yearly outage: PWR EPR series : The first unit in France, currently being built Flamanville Chinon Civaux Le Blayais Golfech Paluel Penly Gravelines Chooz Cattenom Nogent Fessemheim Dampierre St-Laurent Belleville Bugey St-Alban Cruas Tricastin Life time extension : up to 60 years for most units IAEA - TWGNPPIC Meeting May

4 I&C Technologies in the NPPS in France Various technologies from analog components to microprocessor-based products N4 EPR Turbine Control Electronic components (REC 70) REC 70 Digital equipment (MicroRec) Digital equipment. (MicroRec) Digital equipment (P320) Analog Automation Analogue electronic components (8720 & 9020 series) 9020 series COTS DCS (Micro Z) DCS (Contronic E) Specific PLC (SCAP) DCS (T2000) Logic Automation Electromagnetic relays COTS PLC (Controbloc) DCS (Contronic E) Specific 1E PLC (CS3) DCS (T2000) Reactor Protection Electromagnetic relays Analogue electronic components Specific 1E digital system (SPIN) Specific 1E digital system (SPIN-N4) Specific F1A digital system (TXS) Control Room Systems Conventional panel Computerized aids Conventional panel Computerized aids Computerized CR Conventional panels (Remote & back-up) Computerized CR Conventional panels (Back-up ) IAEA - TWGNPPIC Meeting May

5 Mission US EDF 5 EDF NPPs Life Cycle Management Life cycle management of Nuclear plants is based on: Global initial strategy regarding critical I&C systems: Spare part of components Long term agreement with the suppliers : competencies and tools Daily routine operation and maintenance activities incorporating an important feedback experience (with related activities of systems support) Exceptional maintenance program: applied to generic hazards or degradations concerning the whole Fleet of NPPs or part of it, decided and planned at national level on several years, implemented once (or twice) in the life of the plant. Periodic safety reviews (PSR) (every 10 years) including ageing evaluation to check agreement to safety requirements. Long outage every 10 years (TYO) Best time is large modernisation or replacement Research activities (R&D and international projects) EDF specific programs led by Engineering Division and Operation Division 5

6 The I&C Projects at EDF The 900 MW Series I&C Projects IAEA - TWGNPPIC Meeting May

7 900 MW Series I&C Technologies Electromagnetic relays for logic control (about per unit) Discrete modules for the analog acquisition and control loops (Bailey 8720 & 9020) Hardwired panels in the control room IAEA - TWGNPPIC Meeting May

8 900 MW Series I&C Projects for the 3 rd TYO (1) The I&C ageing observation phase ( ) results : Most of the I&C components can last up to the next TYO (40 years) at least : For example : The relay-based systems and the panels of the Control Room don t need to be changed, for ageing or obsolescence reasons Good long-term agreement with suppliers for critical systems. No large I&C modernization projects but some partial renovation such as : Modernization of the Turbine Control system (on CP0, only). Same architecture : Card-by-card replacement. Redesign of the cards with new analog components. Renovation of Diesel Alarm System : replacement of the relay-based system by a PLC Partial modernization of the Rod Control system (IPS-NC) : No modification of the instrumentation (1E) and of the power modules (gripper coil current generator). The new system is based on PLCs (computation), networks and FPGA-Based modules (slave cycler. Time constraint : 1 ms). Renovation of the In-Core Instrumentation system. New system based on PLCs (same as for Rod Control system) and a supervisor shared with the RCS Some modules of the Process Instrumentation System (Bailey 8720 on CP0 : discrete analog technology) were replaced (redesign with new components but same technology) The 3rd ten-yearly outage in progress, from 2008 (Head unit) up to 2018, with 3 or 4 outages per year. IAEA - TWGNPPIC Meeting May

9 900 MW Series I&C Projects for the 3 rd TYO (2) Renovation of the Rod Control System Renovation of the In-core Instrumentation system IAEA - TWGNPPIC Meeting May

10 900 MW Series I&C Projects for the 4th TYO Context : Plant life extension : up to 60 years Little I&C modernization has been done up to now Large scale I&C renovation may be necessary The best time : the 4th Ten-yearly Outage, from 2019 Constraints : Limited physical space in the electrical buildings for new equipment Licensing duration Process for defining the renovation strategy & solutions : Three steps before making the decision regarding I&C modernization: Phase 1: Evaluation of the health of each I&C system, through an observation phase Phase 2: Identification of external influences potentially impacting the current I&C systems, such as functional or safety improvements (DIN/DPN requirements) Phase 3: Identification of possible technical solutions (DCS, relays ) and detailed analysis of renovation scenarios (pre-project studies) Phases1 & 2 started in 2010 and the phase 3 is about to be finished mid IAEA - TWGNPPIC Meeting May

11 900 MW Series the 4th TYO planning for I&C Projects June Large I&C renovations likely DIN/DPN Requirements Requirement specifications Call for tender, consultation, contracts 1 year Pre-Project Studies Supplier studies, development and testing I&C Aging Analysis Software licensing begins 2015 : 4 years before TTS Installation plan, site preparation and training Project SF60 : Safety modifications 6 ½ years ASN Approval of Cat A software modifications: 9 months before TTS Outage first unit (TTS) IAEA - TWGNPPIC Meeting May

12 900 MW Series 4 th TYO - Results of phase 1 Diagnostic phase directed by the Engineering Division (SEPTEN) and R&D in 2011 : Concerns all I&C systems important for plant safety or availability on levels 1 and 2 of the I&C architecture All systems classified into 4 families : Family 0: can be maintained until the fifth ten-yearly outage at least Family 1: the conclusions are not yet finalized Family 2: conclusions clear (renovation or replacement required) but having only a minor impact in terms of installation or outage planning Family 3: diagnostic is clear but due to potential impact on the outage and installation, several renovation scenarios must be studied Equipment Diagnostic Forecast VD years Aging Obsolescence Result Qualification Margins Evolutions Capacity Result Family Alternator protection Water level regulation Reactor protection and tester Elementary system relays N/A N/A N/A 0 N/A IAEA - TWGNPPIC Meeting May

13 900 MW Series 4 th TYO - Results of phase 3 Five possible technical solutions were under consideration: Bespoke solutions : Densification based on the existing I&C technologies : Densified relay-based system : replacement of existing 4-relay circuit boards by 8-relay boards New analog boards with densified components Field Programmable Gate Arrays (FPGA): to replace a number of relay circuits or for new functions Commercial off the shelf (COTS) solutions : Hardwired logic solvers: Deterministic logic solvers or other discrete electronic components Programmable Logic Controllers (PLC) : for Category A and for Category B or C applications Application of selection criteria for each identified scenario (based on a technology and equipment being renovated) and proposition of possible scenario : they are still studied in more detail. For the relay-based system, two scenarios for partial renovation: densification PLC (replacement Elementary System by Elementary system). For the RPS, two scenarios : Current architecture conserved : separation of signal acquisition/treatment (SIP-P) and vote/logic (RPR), densification of current technologies. Modification of the current architecture, integration of SIP-P and RPR into a digital protection system IAEA - TWGNPPIC Meeting May

14 900 MW Series 4 th TYO Selection Criteria (extr.) Intrinsic qualities Basic and additional functions Hardware and software licensing Site impact/modifications/ maintenance/training Sustainability Contextual criteria Scope of the renovation Impact on I&C architecture and on plant outage Control room impact Supplier impact EDF/engineering, operational impacts Criteria analyzed Iso-functionality at minimum, failure detection and signaling, greater accuracy/performance? Category A, B or C achievable? Configuration tools, documentation, modification, maintenance, training, cyber-security, testability Component lifetime, replaceability, portability Criteria analyzed What equipment? Space gained? Regrouping of functions/equipment, modification of interfaces and cabling, removal/installation of equipment, ventilation requirements, outage duration Commands, displays, archives Experience feedback, upgrade and maintenance possibilities, sustainability Training, expertise, operational requirements, ongoing qualification Evaluation based on expert judgment, scoring from +++ to --- Each expert adds a comment to justify the score or to propose actions to obtain further information IAEA - TWGNPPIC Meeting May

15 The I&C Projects at EDF The 1300 MW Series I&C Projects IAEA - TWGNPPIC Meeting May

16 1300 MW SERIES I&C Projects for the 3rd TYO (1) The 3rd ten-yearly outage in preparation. Head of series in The I&C Ageing Observation phase and Preliminary studies ( ) gave their results: Some I&C modernization projects are decided Modernization of the Main Control Room. Same design, hardwired panels are kept but some improvement of the Information System are decided : new tools and HIS for helping the operators (real-time control) New supervisor with more screens and with new or improved mimic diagrams, video Improvement of the alarm management, together with the renovation of part of the Controbloc ( New systems with functionalities added for monitoring the reactor behavior (connected to the power up rate) : Core 3D_monitoring Replacement of the paper recorders by digital recorders (cat. B) Integration of the Cyber Security constraints Modification of the Simulator (training) Modernization of the RPS, RCS, NIS with SPINLine4 (RRCN) technology RPS: Partial modernization at computation level. Keep the global architecture, the I/0 racks and the cabling RCS: Total modernization NIS: Partial modernization at computation level. keep the I/0 racks and cabling Common Maintenance tool for the 3 systems IAEA - TWGNPPIC Meeting May

17 1300 MW SERIES I&C Projects for the 3rd TYO (2) Logic Automation system (Controbloc): No problem (aging, obsolescence ) for the next ten years (spare parts ), but : new functionalities/alarms may be added and not enough margin : Renovation of the part of the system (UGA/B) in charge of collecting and dispatching alarms to the control room (Alstom Alspa (P320) system ) Some improvement at the system level to be considered: * Development of a bridge between the existing Controbloc and a PLC (first installation : Flamanville) * Re-design of a module URN (FPGA-based solution, in cat.b): improving the link with the plant computer (TCI) and (re)capitalize the knowledge on the original design. Conventional Island: Turbine Control & Protection: replacement of actual I&C system (REC70 or µrec) by a DCS, replacement of hydromechanics protections by a SIL3 I&C system with logic 2oo3 Feedwater flow control system: Replacement of actual I&C system (BAILEY 9020) The first unit (TTS) is Paluel 2 : the outage is planned for April 2015 IAEA - TWGNPPIC Meeting May

18 The I&C Projects at EDF The 1450 (N4) Series I&C Projects IAEA - TWGNPPIC Meeting May

19 N4 SERIES Preparation of the 2nd TYO Evaluation of the health of each I&C system (obsolescence, ageing, margins ) has been performed in 2011 & 2012/, through an observation phase Results given through 5 families: Family 0: Systems/equipment can be maintained until VD+20 years Family 1: Systems/equipment can be maintained until VD+10 years Family 2: The conclusions are not clear. Pre-studies have to be launched for renovation Family 3: Conclusions clear (renovation or replacement required) but having only a minor impact in terms of installation or outage planning. E.g. Maintenance interface for system CO3. Family 4: Diagnostic is clear (renovation partial- needed) but potential impact on the outage and installation. E.g. the synoptic in the MCR. The conclusions were presented at the end of The pre-studies have been engaged, in The first unit (TTS) is Chooz B1 : the outage is planned for IAEA - TWGNPPIC Meeting May

20 The I&C Projects at EDF The EPR project (Fla) I&C Projects IAEA - TWGNPPIC Meeting May

21 EPR FLAMANVILLE (under construction) EPR : Generation III+ PWR Design. Based on N4 (F) and KONVOI (G) experience. I&C Architecture : T2000/S5, TXS & P320 (Turbine) Current situation : Number of I&C cubicles on site. The other are on platform for tests In operation in 2016 IAEA - TWGNPPIC Meeting May

22 The I&C Projects at EDF Some R&D projects on I&C Systems IAEA - TWGNPPIC Meeting May

23 Some current R and D projects on I&C (1) Projects concerning the next NPPs (EPR) as well as for current NPPs Independent Confidence Building : Formal verification (software, FPGA) Test : functional test coverage (Testminator prototype for safety logic functions), statistical tests Verification of the sizing of the I&C architecture : time performance, Safety Cyber Security (I&C systems and connected tools) Basic Design: Proposal for a basic/generic architecture (Industrially reasonable, Acceptable in all the countries) Design of optimized (cost) I&C architectures by allocation of the functions under constraints (capacity, performance, safety ). Anticipation in the Design of the short life time of I&C systems: modularity, data models, interface. Impact (benefit & risk) of the new technologies: Wireless, FPGA Contribution of FPGA-based solutions (safety systems, diversity, Cyber Security ) Integration of operation needs (Integration of information and separation of safety classes ) Proposal of a short list of pre-qualified I&C PLCs for K3/Cat B & C : dedicated, decentralized systems Next generation of HIS: new functionalities for operation, Human Factor, classified digital products (requirements & development) IAEA - TWGNPPIC Meeting May

24 Some current R and D projects on I&C (2) Harmonics Project (China-Europe): Harmonized Assessment of the Reliability of MOdern Nuclear I&C Software Objective : to ensure that the nuclear industry has well founded and up-to-date methods and data for assessing software of computer-based safety systems of Gen-II and Gen-III NPPs. the project should foster an international consensus based on a sound scientific and technical approach, and hopefully provide a good basis for harmonization Model Driven Engineering: methods & tools To ensure the continuity of the studies: Throughout the project lifecycle, between functional and equipment and from plant design to plant operation To have an updated knowledge database: To understand design choices and to pass knowledge across generations Concept PLM (Product Lifecycle Management) : clarification of justifications in the documentary reference frame. Requirements Traceability. Multi-views diagrams. Common Database for the various designers (process, mechanical, I&C ) European MODRIO Project (ITEA2): Bridging the gap between system design and system operation. Use of open standards : Modelica and FMI. IAEA - TWGNPPIC Meeting May

25 Some current R and D projects on I&C(3) Knowledge management: retrieve, rebuild, and structure useful knowledge to maintain ageing units. First application : 900 MW plants Instrumentation: Assessment of measurement uncertainties, Measurement environment monitoring (EMC, temperature, radiation ), Innovative technologies (chemical tracer, ultrasonic, fiber optics sensing ) Monitoring (of plant performance, and of equipment/component/system reliability): based on physical (Modelica/Dymola) and/or statistical models for early detection and quantification (e.g. Steam Generator fouling/clogging, MW loss, equipment failure prognostics,...) IAEA - TWGNPPIC Meeting May

26 Recommendations To IAEA IAEA - TWGNPPIC Meeting May

27 Recommendation to the IAEA : Topics to focus on (1) EDF considers that most of the topics provided at the previous TWG-NPPIC meeting (2011) are still current topics on which IAEA should focus. Maintaining the existing Nuclear Power Plants (old and recent) with a High Safety level: Rising up the Safety Level of old plants, in order to achieve the best accessible Safety level (but not necessary the current Safety level applicable to the new NPPs). Arrive at an international consensus which leaves few margins of interpretation to each country Methodology and framework for re-examination of the level of safety of the units before renovation or periodically Perform audits on current situation and propose risks reduction (process, I&C, Human ) Post-Fukushima actions: exchange on the best practices. Survey the ageing of I&C equipment and control the Obsolescence (analog as well as digital equipment, cabling, connectors ): Understanding of ageing mechanisms. Maintenance strategies: e.g. periodic replacement or on failure? Evaluation of costs, risks, benefits of different I&C maintenance options: modernization, repair. How to deal with the short life time of the new digital system (software evolution )? Implement each new software release? Integrate the ageing workforce, the inadequate existing documentation and the new generation in a long-term management of I&C expertise : Identification and documentation of key knowledge, including I&C design basis. How to retrieve, rebuild, structure and pass the documented knowledge to the new generation? How to attract and keep the new generation? How to train the current I&C engineers to the new technologies? IAEA - TWGNPPIC Meeting May

28 Recommendation to the IAEA : Topics to focus on (2) Safe Aspects : International consensus on Safety requirements for new NPPs Define more precisely the Safety Level to reach: between the high level requirements and the National Regulator requirement/iec Standards. Define a minimal number of unavoidable requirements (from various standards, norms, rules ) that all the units must satisfy for their I&C architecture and components. Efficiency Aspect Specification & Design of I&C architecture taking lifetime into account. Product Lifecycle Management (PLM) : requirements traceability, Modification Methods & tools for Plant performance improvement: New technologies for reduction of uncertainties in measurements to increase power output while maintaining safety margins Reduction of likelihood of human errors Reduction of operation & maintenance costs (information systems, on-line monitoring, diagnostic ) New Technologies - Impact Evaluation of COTS I&C equipment and I&C architecture I&C platforms, architecture, smart devices (we are at the limits of the acceptable complexity) Representation of digital systems in probabilistic models Realistic consideration for assessment of software (system + application) : Verification and Validation (tests) as complementary tools. Test coverage. Software common cause failures Classified HIS : same interface for the operator (HF aspect) IAEA - TWGNPPIC Meeting May

29 Recommendation to the IAEA : Topics to focus on (3) New Technologies - Impact (cont.) Regulatory uncertainties regarding new technologies : ASICs / FPGAs, Smart Devices, Data communication networks (including fieldbus), Wireless technologies, Cyber-security SMR (Small Modular Reactor) Impact on Safety and Security rules of a centralized CR for multiple small reactors Level of automation (because of reduced team for operation) IAEA - TWGNPPIC Meeting May

30 I&C Status in France & Recommendations to IAEA Thank you for your attention IAEA - TWGNPPIC Meeting May

Long term support solutions for Nuclear Instrumentation & Control

Long term support solutions for Nuclear Instrumentation & Control Long term support solutions for Nuclear Instrumentation & Control...ensuring the long-term safety and availability of your I&C systems. 02 LONG TERM SUPPORT SOLUTIONS Maintaining the safe and reliable

More information

IAEA-TECDOC-1328 Solutions for cost effective assessment of software based instrumentation and control systems in nuclear power plants

IAEA-TECDOC-1328 Solutions for cost effective assessment of software based instrumentation and control systems in nuclear power plants IAEA-TECDOC-1328 Solutions for cost effective assessment of software based instrumentation and control systems in nuclear power plants Report prepared within the framework of the Technical Working Group

More information

Announcement of a new IAEA Co-ordinated Research Programme (CRP)

Announcement of a new IAEA Co-ordinated Research Programme (CRP) Announcement of a new IAEA Co-ordinated Research Programme (CRP) 1. Title of Co-ordinated Research Programme Design and engineering aspects of the robustness of digital instrumentation and control (I&C)

More information

Post-Fukushima development of operating severe accident management and ERO. Vienna (Autriche) 19/03/2014

Post-Fukushima development of operating severe accident management and ERO. Vienna (Autriche) 19/03/2014 Post-Fukushima development of operating severe accident management and ERO Vienna (Autriche) 19/03/2014 SEVERE ACCIDENT DEVELOPMENT IN THE LIGHT OF POST-FUKUSHIMA 2 IAEA Vienna - 19 March 2014 SEVERE ACCIDENT

More information

Application of FPGA-based Safety Controller for Implementation of NPPs I&C Systems Vladimir Sklyar, Technical Director

Application of FPGA-based Safety Controller for Implementation of NPPs I&C Systems Vladimir Sklyar, Technical Director Application of FPGA-based Safety Controller for Implementation of NPPs I&C Systems Vladimir Sklyar, Technical Director Seminar FPGA-based I&C Systems in Nuclear Applications February 4, 2015, Energiforsk,

More information

Nuclear Power Plant Instrumentation and Control in MEXICO

Nuclear Power Plant Instrumentation and Control in MEXICO 25 th Meeting of the IAEA Technical Working Group on Nuclear Power Plant Instrumentation and Control (TWG -NPPIC) Nuclear Power Plant Instrumentation and Control in MEXICO Dr. Francisco Javier Ramírez-Jiménez

More information

Development and Application of POSAFE-Q PLC Platform

Development and Application of POSAFE-Q PLC Platform Development and Application of POSAFE-Q PLC Platform MyeongKyun Lee a, SeungWhan Song a, DongHwa Yun a a POSCO ICT Co. R&D center, Korea Techno-complex 126-16, 5-ka, Anam-dong, Sungbuk, Seoul, Republic

More information

AP1000 European 18. Human Factors Engineering Design Control Document

AP1000 European 18. Human Factors Engineering Design Control Document 18.2 Human Factors Engineering Program Management The purpose of this section is to describe the goals of the AP1000 human factors engineering program, the technical program to accomplish these goals,

More information

OPERATIONS CAPITAL. The Operations Capital program for the test years is divided into two categories:

OPERATIONS CAPITAL. The Operations Capital program for the test years is divided into two categories: Filed: September 0, 00 EB-00-0 Tab Schedule Page of OPERATIONS CAPITAL.0 INTRODUCTION Operations Capital funds enhancements and replacements to the facilities required to operate the Hydro One Transmission

More information

Testing Automated Manufacturing Processes

Testing Automated Manufacturing Processes Testing Automated Manufacturing Processes (PLC based architecture) 1 ❶ Introduction. ❷ Regulations. ❸ CSV Automated Manufacturing Systems. ❹ PLCs Validation Methodology / Approach. ❺ Testing. ❻ Controls

More information

AN APPLICATION STUDY FOR THE CLASS IE DIGITAL CONTROL AND

AN APPLICATION STUDY FOR THE CLASS IE DIGITAL CONTROL AND - 39 - AN APPLICATION STUDY FOR THE CLASS IE DIGITAL CONTROL AND MONITORING SYSTEM m,,,.,.., HIROYUKIFUKUMITSU Nuclear Power Plant Department, EISC MITSUBISHI ELECTRIC CORPORATION Kobe, Japan XA9846493

More information

COST EFFECTIVE MODERNISATION OF SYSTEMS IMPORTANT TO SAFETY (CEMSIS)

COST EFFECTIVE MODERNISATION OF SYSTEMS IMPORTANT TO SAFETY (CEMSIS) COST EFFECTIVE MODERNISATION OF SYSTEMS IMPORTANT TO SAFETY (CEMSIS) D. Pavey (British Energy, Gloucester), R. Bloomfield (Adelard, London), P-J. Courtois (AVN, Brussels), P. Caspall-Askew (BNFL, Risley),

More information

Protect Your Assets. Cyber Security Engineering. Control Systems. Power Plants. Hurst Technologies

Protect Your Assets. Cyber Security Engineering. Control Systems. Power Plants. Hurst Technologies Protect Your Assets Cyber Security Engineering Control Systems. Power Plants. Hurst Technologies Cyber Security The hackers are out there and the cyber security threats to your power plant are real. That

More information

PLCs and SCADA Systems

PLCs and SCADA Systems Hands-On Programmable Logic Controllers and Supervisory Control / Data Acquisition Course Description This extensive course covers the essentials of SCADA and PLC systems, which are often used in close

More information

SMART ASSET MANAGEMENT MAXIMISE VALUE AND RELIABILITY

SMART ASSET MANAGEMENT MAXIMISE VALUE AND RELIABILITY SMART ASSET MANAGEMENT MAXIMISE VALUE AND RELIABILITY Electrical equipment is a critical component of your asset portfolio. Beyond its financial value, it plays an even greater role in your business performance.

More information

Long term operation integrated processes for delivering extended asset performance

Long term operation integrated processes for delivering extended asset performance Long term operation integrated processes for delivering extended asset performance 15 04 2015 Agenda 1. Introduction 2. Long term operation process for delivery 3. Business planning and key assumptions

More information

IEC 61508 Overview Report

IEC 61508 Overview Report IEC 61508 Overview Report A Summary of the IEC 61508 Standard for Functional Safety of Electrical/Electronic/Programmable Electronic Safety-Related Systems exida Sellersville, PA 18960, USA +1-215-453-1720

More information

Selecting Sensors for Safety Instrumented Systems per IEC 61511 (ISA 84.00.01 2004)

Selecting Sensors for Safety Instrumented Systems per IEC 61511 (ISA 84.00.01 2004) Selecting Sensors for Safety Instrumented Systems per IEC 61511 (ISA 84.00.01 2004) Dale Perry Worldwide Pressure Marketing Manager Emerson Process Management Rosemount Division Chanhassen, MN 55317 USA

More information

COMPUTER SYSTEMS IN THE OPERATION, MAINTENANCE AND TECHNICAL SUPPORT OF LOVIISA NPS

COMPUTER SYSTEMS IN THE OPERATION, MAINTENANCE AND TECHNICAL SUPPORT OF LOVIISA NPS COMPUTER SYSTEMS IN THE OPERATION, MAINTENANCE AND TECHNICAL SUPPORT OF LOVIISA NPS Markku Tiitinen Imatran Voima Oy, Loviisa NPS P.O.Box 23, SF-07901 LOVIISA, Finland Fax +358 15 550 4435 Keywords: computers,

More information

Long Term Operation R&D to Investigate the Technical Basis for Life Extension and License Renewal Decisions

Long Term Operation R&D to Investigate the Technical Basis for Life Extension and License Renewal Decisions Long Term Operation R&D to Investigate the Technical Basis for Life Extension and License Renewal Decisions John Gaertner Technical Executive Electric Power Research Institute Charlotte, North Carolina,

More information

Alain Nifenecker - General Electric Manager Controls Engineering

Alain Nifenecker - General Electric Manager Controls Engineering GE Energy Benefits of Integrating a Single Plant-Wide Control System Into a Standard Plant Design Philosophy Authors: Luis Cerrada Duque - Empresarios Agrupados Director of I&C Department Charles Weidner

More information

FPGA- based technology and systems for I&C of existing and advanced reactors

FPGA- based technology and systems for I&C of existing and advanced reactors International Conference on Opportunities and Challenges for Water Cooled Reactors in the 21st Century Vienna, Austria, 27 30 October 2009 FPGA- based technology and systems for I&C of existing and advanced

More information

Checking of quality on production

Checking of quality on production Checking of quality on production Jean CORCOS Industrial Division Industrial Waste Management Solution Unit Waste Acceptance Department, and Major-Producer Relations Denis POMBET Risk Management Division

More information

Fire Protection Program Of Chashma Nuclear Power Generating Station Pakistan Atomic Energy Commission 5/28/2015 1

Fire Protection Program Of Chashma Nuclear Power Generating Station Pakistan Atomic Energy Commission 5/28/2015 1 Fire Protection Program Of Chashma Nuclear Power Generating Station Pakistan Atomic Energy Commission 5/28/2015 1 Nuclear Power in Pakistan Nuclear Power Plants Capacity (MWe) Year of Commissioning In

More information

Hardware safety integrity Guideline

Hardware safety integrity Guideline Hardware safety integrity Comments on this report are gratefully received by Johan Hedberg at SP Swedish National Testing and Research Institute mailto:johan.hedberg@sp.se Quoting of this report is allowed

More information

Efficient Verification for Avionic Product Development

Efficient Verification for Avionic Product Development YAVE Test Systems Efficient Verification for Avionic Product Development With YAVE FTI offers the full range of test systems from compact budget units up to complex systems configured to customers individual

More information

RC-17. Alejandro V. Nader National Regulatory Authority Montevideo - Uruguay

RC-17. Alejandro V. Nader National Regulatory Authority Montevideo - Uruguay RC-17 Radiation Protection in Waste Management and Disposal Implementing the Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management Alejandro V. Nader

More information

Safety controls, alarms, and interlocks as IPLs

Safety controls, alarms, and interlocks as IPLs Safety controls, alarms, and interlocks as IPLs Angela E. Summers, Ph.D., P.E. SIS-TECH Solutions 12621 Featherwood Dr. Suite 120, Houston, TX 77034 Keywords: safety controls, alarms, interlocks, SIS,

More information

Ames Consolidated Information Technology Services (A-CITS) Statement of Work

Ames Consolidated Information Technology Services (A-CITS) Statement of Work Ames Consolidated Information Technology Services (A-CITS) Statement of Work C.1 Mission Functions C.1.1 IT Systems & Facilities Support System Administration: The Contractor shall provide products and

More information

Safety Requirements Specification Guideline

Safety Requirements Specification Guideline Safety Requirements Specification Comments on this report are gratefully received by Johan Hedberg at SP Swedish National Testing and Research Institute mailto:johan.hedberg@sp.se -1- Summary Safety Requirement

More information

ISA CERTIFIED AUTOMATION PROFESSIONAL (CAP ) CLASSIFICATION SYSTEM

ISA CERTIFIED AUTOMATION PROFESSIONAL (CAP ) CLASSIFICATION SYSTEM ISA CERTIFIED AUTOMATION PROFESSIONAL (CAP ) CLASSIFICATION SYSTEM Domain I: Feasibility Study - identify, scope and justify the automation project Task 1: Define the preliminary scope through currently

More information

MDEP Generic Common Position No DICWG 02

MDEP Generic Common Position No DICWG 02 MDEP Generic Common Position No DICWG 02 Related to: Digital Instrumentation and Controls Working Group activities COMMON POSITION ON SOFTWARE TOOLS FOR THE DEVELOPMENT OF SOFTWARE FOR SAFETY SYSTEMS 1

More information

T146 Electro Mechanical Engineering Technician MTCU Code 51021 Program Learning Outcomes

T146 Electro Mechanical Engineering Technician MTCU Code 51021 Program Learning Outcomes T146 Electro Mechanical Engineering Technician MTCU Code 51021 Program Learning Outcomes Synopsis of the Vocational Learning Outcomes* The graduate has reliably demonstrated the ability to: 1. fabricate

More information

Published in the Official State Gazette (BOE) number 166 of July 10th 2009 [1]

Published in the Official State Gazette (BOE) number 166 of July 10th 2009 [1] Nuclear Safety Council Instruction number IS-22, of July 1st 2009, on safety requirements for the management of ageing and long-term operation of nuclear power plants Published in the Official State Gazette

More information

Radiological Assessment Display and Control System

Radiological Assessment Display and Control System Features Fast, real-time data acquisition and control Highly reliable communication with remote terminal units Collecting, converting, integrating and analyzing data from all monitors Detecting, annunciating

More information

Presentation: May 15 th 2013 Location: Saskatoon Speaker: Robert Picard. Airport Expertise. Holistic Approach to IT Solutions Automation Intelligence

Presentation: May 15 th 2013 Location: Saskatoon Speaker: Robert Picard. Airport Expertise. Holistic Approach to IT Solutions Automation Intelligence Presentation: May 15 th 2013 Location: Saskatoon Speaker: Robert Picard Airport Expertise Holistic Approach to IT Solutions Automation Intelligence Agenda Automation Intelligence (AI) Concept Responding

More information

Industrial IT System 800xA Satt Products and Systems

Industrial IT System 800xA Satt Products and Systems Industrial IT System 800xA Satt Products and Systems Overview Features and Benefits Reducing Time to Decision and Action: System 800xA Process Portal delivers the exact information, filters out noise to

More information

Drivers and approach for the design of the EPR reactor

Drivers and approach for the design of the EPR reactor Drivers and approach for the design of the EPR reactor Martine Mayousse Reactor & Services / Safety & Licensing IAEA Vienna June 27, 2013 1 Agenda 1. Introduction 2. EPR design objectives and principles

More information

Nuclear Consultancy & Engineering Services

Nuclear Consultancy & Engineering Services Insert a caption to go with the photograph in here ITER, France Wednesday, 14 December 2011 Nuclear Consultancy & Engineering Services T H E N U C L E A R A T K I N S A S S Y S T E M A L L I A N C E CONSTRUCTION

More information

IEC 61508 Functional Safety Assessment. Project: K-TEK Corporation AT100, AT100S, AT200 Magnetostrictive Level Transmitter.

IEC 61508 Functional Safety Assessment. Project: K-TEK Corporation AT100, AT100S, AT200 Magnetostrictive Level Transmitter. 61508 SIL 3 CAPABLE IEC 61508 Functional Safety Assessment Project: K-TEK Corporation AT100, AT100S, AT200 Magnetostrictive Level Transmitter Customer: K-TEK Corporation Prairieville, LA USA Contract No.:

More information

NAVFAC EXWC Platform Information Technology (PIT) Cyber Security Initiatives

NAVFAC EXWC Platform Information Technology (PIT) Cyber Security Initiatives NAVFAC EXWC Platform Information Technology (PIT) Cyber Security Initiatives Center of excellence for secure integration, deployment and sustainment of Industrial Control Systems and Operational Technology

More information

Cyber Security Design Methodology for Nuclear Power Control & Protection Systems. By Majed Al Breiki Senior Instrumentation & Control Manager (ENEC)

Cyber Security Design Methodology for Nuclear Power Control & Protection Systems. By Majed Al Breiki Senior Instrumentation & Control Manager (ENEC) Cyber Security Design Methodology for Nuclear Power Control & Protection Systems By Majed Al Breiki Senior Instrumentation & Control Manager (ENEC) 1. INTRODUCTION In today s world, cyber security is one

More information

Poznan University of Technology Faculty of Electrical Engineering

Poznan University of Technology Faculty of Electrical Engineering Poznan University of Technology Faculty of Electrical Engineering Contact Person: Pawel Kolwicz Vice-Dean Faculty of Electrical Engineering pawel.kolwicz@put.poznan.pl List of Modules Academic Year: 2015/16

More information

FIRE RISK ASSESSMENT IN GERMANY - PROCEDURE, DATA, RESULTS -

FIRE RISK ASSESSMENT IN GERMANY - PROCEDURE, DATA, RESULTS - International Conference Nuclear Energy in Central Europe 2000 Golf Hotel, Bled, Slovenia, September 11-14, 2000 FIRE RISK ASSESSMENT IN GERMANY - PROCEDURE, DATA, RESULTS - H.P. Berg Bundesamt für Strahlenschutz

More information

AREVA, an unparalleled experience in building nuclear reactors

AREVA, an unparalleled experience in building nuclear reactors AREVA, an unparalleled experience in building nuclear reactors Frank APEL Senior Vice President Sales Central Europe and Nordic Countries AREVA, International Commercial Organisation 9 th Annual European

More information

N.K. Srivastava GM-R&M-Engg.Services NTPC- CC/Noida nksrivastava@ntpceoc.co.in

N.K. Srivastava GM-R&M-Engg.Services NTPC- CC/Noida nksrivastava@ntpceoc.co.in N.K. Srivastava GM-R&M-Engg.Services NTPC- CC/Noida nksrivastava@ntpceoc.co.in JULY 2012 ARC- Transforming Industry and Infrastructure through New Processes and Technologies Presentation Road Map Introduction

More information

SECTION 13421 PROGRAMMABLE LOGIC CONTROLLERS AND COMPUTER CONTROL SYSTEM PART 1 GENERAL. 1.01 Summary. A. Section Includes:

SECTION 13421 PROGRAMMABLE LOGIC CONTROLLERS AND COMPUTER CONTROL SYSTEM PART 1 GENERAL. 1.01 Summary. A. Section Includes: SECTION 13421 PROGRAMMABLE LOGIC CONTROLLERS AND COMPUTER CONTROL SYSTEM PART 1 GENERAL 1.01 Summary A. Section Includes: 1. The ISS shall furnish all labor, materials, equipment, services and incidentals

More information

Emulated Digital Control System Validation in Nuclear Power Plant Training Simulators

Emulated Digital Control System Validation in Nuclear Power Plant Training Simulators Digital Control System Validation in Nuclear Power Training s Gregory W. Silvaggio Westinghouse Electric Company LLC silvaggw@westinghouse.com Keywords: Validation, nuclear, digital control systems Abstract

More information

DACAAM-NET AN INTRANET APPLICATION FOR MANAGEMENT OF AGEING RELATED DATA

DACAAM-NET AN INTRANET APPLICATION FOR MANAGEMENT OF AGEING RELATED DATA DACAAM-NET AN INTRANET APPLICATION FOR MANAGEMENT OF AGEING RELATED DATA K. Baumann-ne Tanits a, Á. Jánosiné Bíró a, M Osztheimer a, L. Czibolya a, S. Rátkai b, L. Mátis b, T. Katona b a Institute for

More information

Life-cycle automation and services

Life-cycle automation and services Life-cycle and services A holistic approach to photovoltaic plant, operation and maintenance ADRIAN TIMBUS, MARC ANTOINE, LUIS DOMINGUEZ The photovoltaic power industry is rapidly growing, with worldwide

More information

7.0 Instrumentation and Controls

7.0 Instrumentation and Controls 7.0 Instrumentation and Controls 7.1 Introduction Chapter 7 describes the instrumentation and controls (I&C) systems for the U.S. EPR. The description of the I&C systems includes system classifications,

More information

RecipCOM. Expertise, reciprocating compressor monitoring and protection tailored to your needs

RecipCOM. Expertise, reciprocating compressor monitoring and protection tailored to your needs RecipCOM Expertise, reciprocating compressor monitoring and protection tailored to your needs Do your reciprocating compressors have sufficient protection? Due to the increasing demands on availability

More information

ABB PSPS Erich Steinmann; Generator control-2013

ABB PSPS Erich Steinmann; Generator control-2013 ABB PSPS Erich Steinmann; Generator control-2013 GENERATOR CONTROL THE MODULAR SOLUTION FOR GENERATORS To make sure that power is efficiently converted into electric energy, it is necessary to supervise

More information

Introduction To SCADA and Telemetry

Introduction To SCADA and Telemetry Introduction To SCADA and Telemetry Joe Mullaney Senior I&C Engineer MSE Technology Applications, Inc. Tetragenics Division joe.mullaney@mse-ta.com Overview Definitions What is SCADA? What is Telemetry?

More information

Power Automation and Controls

Power Automation and Controls automation and control SOLUTIONS Hydro Wind Geothermal Solar Ocean Biomass Nuclear Coal Gas Oil Air Quality Control Systems Power Automation and Controls Lifecycle Management CO2 Solutions POWER 25 52,000

More information

IP Video Surveillance

IP Video Surveillance IP Video Surveillance Solutions and Services Wireless IP PDA Administration Wireless Access Point Viewer Remote Control IP Video Server IP Network Alarm Management Video Recording Analog Video Server Access

More information

Is your current safety system compliant to today's safety standard?

Is your current safety system compliant to today's safety standard? Is your current safety system compliant to today's safety standard? Abstract It is estimated that about 66% of the Programmable Electronic Systems (PES) running in the process industry were installed before

More information

SCADA. The Heart of an Energy Management System. Presented by: Doug Van Slyke SCADA Specialist

SCADA. The Heart of an Energy Management System. Presented by: Doug Van Slyke SCADA Specialist SCADA The Heart of an Energy Management System Presented by: Doug Van Slyke SCADA Specialist What is SCADA/EMS? SCADA: Supervisory Control and Data Acquisition Retrieves data and alarms from remote sites

More information

Secure your electrical network. PACiS The Safety Solution for Healthcare Institutions

Secure your electrical network. PACiS The Safety Solution for Healthcare Institutions Secure your electrical network The Safety Solution for Healthcare Institutions Fast Secure : the solution for fault isolation and electrical network restoration in less than 500 ms 03 A Real Time System

More information

A Modern Process Automation System Offers More than Process Control. Dick Hill Vice President ARC Advisory Group dhill@arcweb.com

A Modern Process Automation System Offers More than Process Control. Dick Hill Vice President ARC Advisory Group dhill@arcweb.com A Modern Process Automation System Offers More than Process Control Dick Hill Vice President ARC Advisory Group dhill@arcweb.com Modern Business Requirements Dynamic Customer Requirements Requiring Agility

More information

OECD SERIES ON PRINCIPLES OF GOOD LABORATORY PRACTICE AND COMPLIANCE MONITORING NUMBER 10 GLP CONSENSUS DOCUMENT

OECD SERIES ON PRINCIPLES OF GOOD LABORATORY PRACTICE AND COMPLIANCE MONITORING NUMBER 10 GLP CONSENSUS DOCUMENT GENERAL DISTRIBUTION OCDE/GD(95)115 OECD SERIES ON PRINCIPLES OF GOOD LABORATORY PRACTICE AND COMPLIANCE MONITORING NUMBER 10 GLP CONSENSUS DOCUMENT THE APPLICATION OF THE PRINCIPLES OF GLP TO COMPUTERISED

More information

The product. SIMAC a machine simulator. Plan. Presentation of the simulation. Simulation, why? What : SIMAC product. Page 1 SIMAC

The product. SIMAC a machine simulator. Plan. Presentation of the simulation. Simulation, why? What : SIMAC product. Page 1 SIMAC SIMAC a machine simulator SIMAC The product SIMAC 10-2003 - 1 Plan 1 Presentation of the simulation 2 Simulation, why? 3 What : SIMAC product SIMAC 10-2003 - 2 Page 1 SIMAC objectives Different from others

More information

Energy Storage System Performance Testing

Energy Storage System Performance Testing Energy Storage System Performance Testing Peter Blume President Bloomy Windsor, CT Abstract This paper describes the energy storage system data acquisition and control (ESS DAC) system used for testing

More information

Vetting Smart Instruments for the Nuclear Industry

Vetting Smart Instruments for the Nuclear Industry TS Lockhart, Director of Engineering Moore Industries-International, Inc. Vetting Smart Instruments for the Nuclear Industry Moore Industries-International, Inc. is a world leader in the design and manufacture

More information

Cyber Security Considerations in the Development of I&C Systems for Nuclear Power Plants

Cyber Security Considerations in the Development of I&C Systems for Nuclear Power Plants Cyber Security Considerations in the Development of I&C Systems for Nuclear Power Plants Jung-Woon Lee, Cheol-Kwon Lee, Jae-Gu Song, and Dong-Young Lee I&C and HF Research Division, Korea Atomic Energy

More information

Safety Analysis for Nuclear Power Plants

Safety Analysis for Nuclear Power Plants Regulatory Document Safety Analysis for Nuclear Power Plants February 2008 CNSC REGULATORY DOCUMENTS The Canadian Nuclear Safety Commission (CNSC) develops regulatory documents under the authority of paragraphs

More information

ELECTROTECHNIQUE IEC INTERNATIONALE 61508-3 INTERNATIONAL ELECTROTECHNICAL

ELECTROTECHNIQUE IEC INTERNATIONALE 61508-3 INTERNATIONAL ELECTROTECHNICAL 61508-3 ª IEC: 1997 1 Version 12.0 05/12/97 COMMISSION CEI ELECTROTECHNIQUE IEC INTERNATIONALE 61508-3 INTERNATIONAL ELECTROTECHNICAL COMMISSION Functional safety of electrical/electronic/ programmable

More information

The Continuously Current Enterprise: Trends in lifecycle management of automation assets

The Continuously Current Enterprise: Trends in lifecycle management of automation assets : Trends in lifecycle management of automation assets 1. Introduction 2. Managing the Automation Lifecycle 3. Return on Upgrade Investment 4. Ramping Up to the Enterprise 5. Customer FIRST Regardless of

More information

Nuclear Safety Council Instruction number IS-19, of October 22 nd 2008, on the requirements of the nuclear facilities management system

Nuclear Safety Council Instruction number IS-19, of October 22 nd 2008, on the requirements of the nuclear facilities management system Nuclear Safety Council Instruction number IS-19, of October 22 nd 2008, on the requirements of the nuclear facilities management system Published in the Official State Gazette (BOE) number 270 of November

More information

HEALTH & SAFETY EXECUTIVE NUCLEAR DIRECTORATE ASSESSMENT REPORT. New Reactor Build. EDF/AREVA EPR Step 2 PSA Assessment

HEALTH & SAFETY EXECUTIVE NUCLEAR DIRECTORATE ASSESSMENT REPORT. New Reactor Build. EDF/AREVA EPR Step 2 PSA Assessment HEALTH & SAFETY EXECUTIVE NUCLEAR DIRECTORATE ASSESSMENT REPORT New Reactor Build EDF/AREVA EPR Step 2 PSA Assessment HM Nuclear Installations Inspectorate Redgrave Court Merton Road Bootle Merseyside

More information

BUILD VERSUS BUY. Understanding the Total Cost of Embedded Design. www.ni.com/buildvsbuy

BUILD VERSUS BUY. Understanding the Total Cost of Embedded Design. www.ni.com/buildvsbuy BUILD VERSUS BUY Understanding the Total Cost of Embedded Design Table of Contents I. Introduction II. The Build Approach: Custom Design a. Hardware Design b. Software Design c. Manufacturing d. System

More information

ABB North America. Substation Automation Systems Innovative solutions for reliable and optimized power delivery

ABB North America. Substation Automation Systems Innovative solutions for reliable and optimized power delivery ABB North America Substation Automation Systems Innovative solutions for reliable and optimized power delivery Substation Automation Systems Advanced substation automation, protection and control solutions

More information

SuperIOr Controller. Digital Dynamics, Inc., 2014 All Rights Reserved. Patent Pending. Rev: 5-16-14 1

SuperIOr Controller. Digital Dynamics, Inc., 2014 All Rights Reserved. Patent Pending. Rev: 5-16-14 1 SuperIOr Controller The SuperIOr Controller is a game changer in the world of high speed embedded control. The system combines incredible speed of both control and communication with revolutionary configurable

More information

Design and Implementation of SCADA System Based Power Distribution for Primary Substation ( Monitoring System)

Design and Implementation of SCADA System Based Power Distribution for Primary Substation ( Monitoring System) Design and Implementation of SCADA System Based Power Distribution for Primary Substation ( Monitoring System) Aye Min Zaw 1, Hla Myo Tun 2 Department of Electronic Engineering, Mandalay Technological

More information

Designing an efficient Programmable Logic Controller using Programmable System On Chip

Designing an efficient Programmable Logic Controller using Programmable System On Chip Designing an efficient Programmable Logic Controller using Programmable System On Chip By Raja Narayanasamy, Product Apps Manager Sr, Cypress Semiconductor Corp. A Programmable Logic Controller (PLC) is

More information

R214 SPECIFIC REQUIREMENTS: INFORMATION TECHNOLOGY TESTING LABORATORY ACCREDITATION PROGRAM

R214 SPECIFIC REQUIREMENTS: INFORMATION TECHNOLOGY TESTING LABORATORY ACCREDITATION PROGRAM The American Association for Laboratory Accreditation Document Revised: R214: Specific Requirements: Information Technology Testing Laboratory Accreditation July 13, 2010 Program Page 1 of 26 R214 SPECIFIC

More information

ELECTRICAL & POWER DISTRIBUTION

ELECTRICAL & POWER DISTRIBUTION ELECTRICAL & POWER DISTRIBUTION END-TO-END ELECTRICAL WIRING INTERCONNECTION SYSTEMS (EWIS) Complete EWIS System Design Harness Installation Design Reconciliation of Wiring Diagrams (2D) & Harness Design

More information

International Conference on Human Resource Development for Nuclear Power Programmes: Building and Sustaining Capacity

International Conference on Human Resource Development for Nuclear Power Programmes: Building and Sustaining Capacity 1 #169 International Conference on Human Resource Development for Nuclear Power Programmes: Building and Sustaining Capacity Human Resource Management in the Belgian TSO Bel V M. Roobaert 1, B. Bernard

More information

Technical Training Module ( 30 Days)

Technical Training Module ( 30 Days) Annexure - I Technical Training Module ( 30 Days) Section 1 : Programmable Logic Controller (PLC) 1. Introduction to Programmable Logic Controller - A Brief History, Need and advantages of PLC, PLC configuration,

More information

Trust our people. Trust our expertise. eady is a professional engineering firm with highlyqualified electrical and controls personnel focused on

Trust our people. Trust our expertise. eady is a professional engineering firm with highlyqualified electrical and controls personnel focused on Nuclear Power Trust our people. R eady is a professional engineering firm with highlyqualified electrical and controls personnel focused on providing solutions to meet your specific needs. Ready provides

More information

231 XA9744368 REACTOR ALARM SYSTEM DEVELOPMENT AND APPLICATION ISSUES. J.E. Drexler, G.O. Oicese INVAP S.E. Argentina

231 XA9744368 REACTOR ALARM SYSTEM DEVELOPMENT AND APPLICATION ISSUES. J.E. Drexler, G.O. Oicese INVAP S.E. Argentina 21 XA974468 REACTOR ALARM SYSTEM DEVELOPMENT AND APPLICATION ISSUES J.E. Drexler, G.O. Oicese INVAP S.E. Argentina ASTRACT The new hardware and software technologies, and the need in research reactors

More information

EC 350 Simplifies Billing Data Integration in PowerSpring Software

EC 350 Simplifies Billing Data Integration in PowerSpring Software White Paper EC 350 Simplifies Billing Data Integration in PowerSpring Software Executive Summary In the current energy environment, gas-metering data must be collected more frequently and in smaller increments

More information

IAEA Safety Standards for Regulatory Activities

IAEA Safety Standards for Regulatory Activities Safety Standards for Regulatory Activities April 2010 Gustavo Caruso Regulatory Activities Section Division of Nuclear Installation Safety International Atomic Energy Agency Content Safety Standards and

More information

Nuclear Safety Council Instruction number IS- 23 on in-service inspection at nuclear power plants

Nuclear Safety Council Instruction number IS- 23 on in-service inspection at nuclear power plants Nuclear Safety Council Instruction number IS- 23 on in-service inspection at nuclear power plants Published in the Official State Gazette (BOE) No 283 of November 24 th 2009 Nuclear Safety Council Instruction

More information

OECD DRAFT ADVISORY DOCUMENT 16 1 THE APPLICATION OF GLP PRINCIPLES TO COMPUTERISED SYSTEMS FOREWARD

OECD DRAFT ADVISORY DOCUMENT 16 1 THE APPLICATION OF GLP PRINCIPLES TO COMPUTERISED SYSTEMS FOREWARD OECD DRAFT ADVISORY DOCUMENT 16 1 THE APPLICATION OF GLP PRINCIPLES TO COMPUTERISED SYSTEMS FOREWARD 1. The following draft Advisory Document will replace the 1995 OECD GLP Consensus Document number 10

More information

ENGINEERING COUNCIL OF SOUTH AFRICA. Discipline-specific Training Guideline for Candidate Engineers in Electrical Engineering

ENGINEERING COUNCIL OF SOUTH AFRICA. Discipline-specific Training Guideline for Candidate Engineers in Electrical Engineering ENGINEERING COUNCIL OF SOUTH AFRICA Standards and Procedures System Discipline-specific Training Guideline for Candidate Engineers in Electrical Engineering Status: Approved by Registration Committee for

More information

How To Write Software

How To Write Software 1 Medical Device Software - Software Life Cycle Processes IEC 62304 2 Credits John F. Murray Software Compliance Expert U.S. Food and Drug Administration Marcie R. Williams Medical Device Fellow Ph.D.

More information

SAFETY LIFE-CYCLE HOW TO IMPLEMENT A

SAFETY LIFE-CYCLE HOW TO IMPLEMENT A AS SEEN IN THE SUMMER 2007 ISSUE OF... HOW TO IMPLEMENT A SAFETY LIFE-CYCLE A SAFER PLANT, DECREASED ENGINEERING, OPERATION AND MAINTENANCE COSTS, AND INCREASED PROCESS UP-TIME ARE ALL ACHIEVABLE WITH

More information

Best Practices for the Installation and Operation of an Automation Change Management Software (CMS) System

Best Practices for the Installation and Operation of an Automation Change Management Software (CMS) System Best Practices for the Installation and Operation of an Automation Change Management Software (CMS) System Abstract...3 Introduction...3 CMS Vendor and Product Considerations...4 Vendor Criteria...5 Point

More information

ELECTRICAL AND I&C EQUIPMENT OF A NUCLEAR FACILITY

ELECTRICAL AND I&C EQUIPMENT OF A NUCLEAR FACILITY ELECTRICAL AND I&C EQUIPMENT OF A NUCLEAR FACILITY 1 Introduction 5 2 Scope of application 6 3 Requirement specification, selection, and procurement of electrical and I&C equipment and cables 7 3.1 General

More information

A MODERN DISTRIBUTION MANAGEMENT SYSTEM FOR REGIONAL ELECTRICITY COMPANIES

A MODERN DISTRIBUTION MANAGEMENT SYSTEM FOR REGIONAL ELECTRICITY COMPANIES A MODERN DISTRIBUTION MANAGEMENT SYSTEM FOR REGIONAL ELECTRICITY COMPANIES A Roberts, T Berry, W D Wilson Schneider Electric Ltd, UK SYNOPSIS This paper describes the features of a modern Distribution

More information

Industrial Communications Training

Industrial Communications Training Standards Certification Education & Training Publishing Conferences & Exhibits Industrial Communications Training Optimizing the flow and value of real-time data Expert-led training with real-world application

More information

DO-254 Requirements Traceability

DO-254 Requirements Traceability DO-254 Requirements Traceability Louie De Luna, Aldec - June 04, 2013 DO-254 enforces a strict requirements-driven process for the development of commercial airborne electronic hardware. For DO-254, requirements

More information

Model-based Testing of Automotive Systems

Model-based Testing of Automotive Systems Model-based Testing of Automotive Systems Eckard Bringmann and Andreas Krämer ICST 08 Presented by Julia Rubin on November 21, 2012 Multidisciplinary Business 2 Supply Chain of Components 3 Innovation

More information

Version: 1.0 Latest Edition: 2006-08-24. Guideline

Version: 1.0 Latest Edition: 2006-08-24. Guideline Management of Comments on this report are gratefully received by Johan Hedberg at SP Swedish National Testing and Research Institute mailto:johan.hedberg@sp.se Quoting of this report is allowed but please

More information

Bioreactor Process Plant Powered by NI LabVIEW and NI CompactRIO

Bioreactor Process Plant Powered by NI LabVIEW and NI CompactRIO Bioreactor Process Plant Powered by NI LabVIEW and NI CompactRIO Segment: Industry Country: Singapore Author(s): Sanka Hettiarachchi, Providev Kevin Kho, Technologies Unlimited Products: NI crio-9075 (Integrated

More information

REMOTE MONITORING AND CONTROL OF THE KAKKONDA GEOTHERMAL POWER PLANTS

REMOTE MONITORING AND CONTROL OF THE KAKKONDA GEOTHERMAL POWER PLANTS REMOTE MONITORING AND CONTROL OF THE KAKKONDA GEOTHERMAL POWER PLANTS Shinji Nishikawa 1, Toshiyuki Takahashi 1, Takeshi Koi 1, and Katsuyoshi Yamada 2 1 Toshiba Corporation Power Systems & Services Company,

More information

Advanced Monitoring and Diagnostics:

Advanced Monitoring and Diagnostics: Advanced Monitoring and Diagnostics: Experience at Luminant and the Benefits of Industry Collaboration Presented by Presenter Name/s Presented by: Clinton Carter, Director, Operations Services Charles

More information

unless the manufacturer upgrades the firmware, whereas the effort is repeated.

unless the manufacturer upgrades the firmware, whereas the effort is repeated. Software Validation in Accredited Laboratories A Practical Guide Gregory D. Gogates Fasor Inc., 3101 Skippack Pike, Lansdale, Pennsylvania 19446-5864 USA g.gogates@ieee.org www.fasor.com Abstract Software

More information

Siemens PLM Software. Overview. 28 th of May 2008 Bulgaria. Colin Johnson

Siemens PLM Software. Overview. 28 th of May 2008 Bulgaria. Colin Johnson Overview 28 th of May 2008 Bulgaria Colin Johnson Objective: A high level overview of Siemens Lifecycle offerings to Support Configuration Management & Plant Lifecycle at the Belene NPP Agenda: 1. overview

More information