Asset Management Plan 2012

Size: px
Start display at page:

Download "Asset Management Plan 2012"

Transcription

1 Asset Management Plan 2012 Period Covered: 1 April 2012 to 31 March 2022 Approved by: Network Waitaki Directors 27 February 2012

2 Table of Contents 1.0 Summary Purpose of the Plan Date Completed & Period Covered Asset Management Systems & Information Network & Asset Description Service Level Objectives Life Cycle Asset Management Risk Assessment Performance and Plans for Improvement Cross-reference to Requirement 24 AMP Prescription Background Interaction with Business Planning Process & Other Corporate Goals Period Covered Stakeholder Interests Conflicts of Interest Accountabilities and Responsibilities Asset Management Systems & Processes Asset Data Accuracy Asset Description Network Configuration Transpower Substations Secondary Network Assets Asset Justification Level of Service Introduction Customer Orientated Service Levels Adopted Service Level Targets Historic Service Levels Service Level Strategies Distribution Network Reliability Targeted Design Features Security Standard and Fault Restoration Targets Analysis of Outages Asset Performance and Efficiency Targets Adopted Service Level Targets Loss Ratio Distribution Transformer Capacity Utilisation Operational Expenditure per Connection Point Direct Line Cost per Circuit km of Line Other Service Level Targets Quality of Supply Justification for Service Level Targets Customer Oriented Service Levels Asset Performance and Efficiency Targets Network Development Introduction Planning Criteria Network Security Criteria Network Capacity Criteria Quality of Supply Criteria Network Reliability Criteria Prioritisation of Network Developments Demand Forecast 48 Page 2

3 5.4.1 Methodology Demand Forecast Assumptions for Large Uncertain Developments The Impact of Distributed Generation and Embedded Generation on the Demand Forecast The Impact of Demand Side Management on the Demand Forecast The Demand Forecasts Constraints within the Planning Period Distributed Generation The History of DG in Network Waitaki s Area of Supply Policies for Connecting Distributed Generation The Effect of Distributed Generation on Network Development Planning Non-Network Options Development Plan Transpower 110kV Transmission Development GXP Development Sub-transmisson Development Distribution Development Other Non-Network Developments Capital Expenditure Plan Life Cycle Assessments kV Sub-transmission Lines Zone Substations Zone Transformers kV & 11kV Switchgear Protection & Metering kV Distribution kV Overhead Lines kV Cables kV Distribution Switchgear kV Oil Switches Distribution Transformers Distribution Voltage Regulators LV Distribution - Overhead Lines LV Distribution - Cables Communications Maintenance Planning kV Sub-transmission Line Zone Transformers Indoor 11kV Switchboards kV Overhead Lines Distribution Substations LV Distribution Lines and Cables Communications Maintenance Plan Risk Management Risk Analysis Specific Risk Management Policy and Provisions Performance Evaluation Financial Performance and Reconciliation Financial Performance Improvements Service Level Performance Service Level Performance Improvements Power Quality Power Quality Improvements 97 Page 3

4 10.0 Expenditure Forecast Year Forecast of Capital and Operational Expenditure Reconciliation of Actual Expenditure against Budget for Year Ending Significant Assumptions 100 Appendix A 106 Summary of Assets (Based on 31/03/04 ODV) 106 Appendix B 107 Summary of Optimised Assets (Based on 31/03/04 ODV Draft Handbook) 107 Appendix C 108 Area of Supply 108 Appendix D 109 Fit of National Guidelines to Network Waitaki s Size 111 Methods of Providing Security 111 Deterministic verses Probabilistic Standards 113 Appropriate Levels of Customer Service 113 Customer Impact 114 Contingent Ratings 114 Regulatory Issues 115 Quantification of Risk 116 Assumed Equipment Failure Rates 116 Assumed Economic Cost of Unserved Energy 116 Excess Capacity Standard for Contingency Support 117 Process for Applying the Security Standard 117 Network Waitaki Security Standard 118 Appendix E 119 Outage Management 119 Damage Minimisation 119 Damage Assessment 120 Response 121 Response Priorities 121 Response Process 122 Appendix F COVEC Load Forecast 124 Appendix G Transpower Draft Load Forecast 126 Certificate - Asset Management Plan 130 Page 4

5 1.0 Summary 1.1 Purpose of the Plan The purpose of this Plan is to disclose information about Network Waitaki Limited s management of its lines business assets, as required by regulation 7 of the Electricity Distribution (Information Disclosure) Requirements 2008, dated 31 October Network Waitaki s primary set of planning documents and processes are those that constitute its Network Development Plan and Finance Plan. The AMP is a summary of these documents that contains sufficient information to allow stakeholders to assess Network Waitaki s asset management practices. Network Waitaki is a wholly owned consumer Trust company and is locally managed to meet the Trust requirements which are documented in the company s Mission Statement as follows: 1. Owning and operating a safe, reliable and efficient distribution system that meets the evolving needs of its consumers. 2. Supporting the economic growth and wellbeing of the community it serves. Both the Asset Management Plan and the Network Development Plan serve the purpose of meeting these objectives in a coordinated manner. The reliability and efficiency targets provided in the company Statement of Corporate Intent have been agreed between the Board and the Trust as appropriate performance measures supporting the above Mission Statement, and form the basis of the service levels in the Asset Management Plan (refer Section 4). The purpose of the Asset Management Plan is therefore to demonstrate how Network Waitaki Ltd intends to sustain a safe, reliable, and efficient network that services the needs of its consumers. 1.2 Date Completed & Period Covered The previous plan covered a period of 10 years from 1 April This plan covers a period of 10 years from 1 April 2012 and reviews action against the plan back to 2010/11. Updates will remain on an annual cycle until Network Waitaki completes its first valuation update (now due 31 March 2012) per the most recent regulatory changes. The ultimate intention is to align updates with the proposed new 5 yearly update cycle. 1.3 Asset Management Systems & Information Asset management systems used by Network Waitaki include a Geographic Information Systems (GIS), asset databases, outage database, and SCADA records. The Asset Data on which life cycle analysis is based in this revision is a snapshot of Network Waitaki s main asset database. This database records the asset, site, Page 5

6 and installation data associated with all line and equipment assets on Network Waitaki s network and is maintained up to date within a monthly cycle of work on the network being completed. The Network Development Plan (NDP) on which the development section of this plan is based was prepared in 2010 (based on 2009 data). This is a 10 year forecast of growth on which an associated capital development action plan is derived. Network Waitaki will next be updating the NDP in 2013 as part of its business planning cycle. In 2008/09 Network Waitaki initiated an IT project to select and install Asset Management software to further support its management and reporting systems. This project is underway and is expected to be completed by the end of 2012/13 financial year. This asset management system will replace the old asset database and will integrate with the GIS, Financial, and other IT systems. 1.4 Network & Asset Description The Network Waitaki network is a predominantly rural network supplying the North Otago, Hakataramea, and Ahuriri regions. Based on the 2011 Disclosures, the network comprises 176km of 33kV sub-transmission line, 1,344km of 11kV distribution line, and 210km of LV distribution line, and 13 zone substations. It supplies approximately 12,318 ICP s, has an average ICP density of 7.12 ICP/km of line, and has a coincidental maximum demand of approximately 52MW, which is inclusive of the Black Point GXP. The network is supplied from four, Transpower Grid Exit Points (GXP) at Oamaru, Black Point, Waitaki, and Twizel. A breakdown of the assets, their relative value and quantities is given in Appendix A. This is based on Network Waitaki s last ODV dated 31 March 2004 and therefore is not up to date with the relatively intensive developments in Network Waitaki s sub-transmission system over recent years. This table will be updated annually when the new AIMS is operational by the end of 2012/13. A plan of the supply area and sub-transmission system is in Appendix C. 1.5 Service Level Objectives Network development in the last two years has not adversely impacted Network Waitaki s planned outage levels due to the 11kV line upgrades required to supply the dairy conversion and irrigation load growth. Network Waitaki seeks to sustain a long term benchmark comparison to other networks that is in the above average to upper quartile range of performance. The following table shows the reliability indices for the years 2007/8 2010/11 and forecast for 2011/12. The results include class b, c, and d outages, exclusive of transmission grid (Transpower-related) a outages. Page 6

7 Reliability Indices Long-Term 2007/ / / / /12 Target Actual Actual Actual Actual Forecast SAIDI < SAIFI < CAIDI < The PricewaterhouseCoopers Electricity Line Business 2010 Information Disclosure Compendium indicates that the year average threshold benchmarks are as follows: National SAIDI 178.6, Network Waitaki SAIDI 70.3 National SAIFI 2.4, Network Waitaki SAIFI 1.1 National CAIDI 74.4, and Network Waitaki CAIDI 63.9 Network Waitaki is meeting top industry performance levels and these results have been well under the 5 year average set in the Price Path Threshold legislation for 2008/2009 and 2009/2010 even though there was a high growth phase being driven by irrigation and dairy conversions. The network development required to meet these demands for additional load have resulted in an increase in live line works to accommodate this work without outages where possible. Network Waitaki took steps to address the impact created by these development outages by purchasing three 635kVA diesel generator sets. The generators target wide area/long duration outages only, and are normally established at standby sites where they can be used to address Network Waitaki loadings under a national grid emergency. These standby sites are also covered by Retailer energy purchase agreements. To date one generator has been used to provide supply to the Black Point GXP when snow damaged Transpower s 110kV line (5 weeks). They were deployed during the major upgrade in the Hakataramea Valley following the Snow Storm, the upgrade of the Broken Hut line (long remote spur) and they cover the Waitaki GXP constraint over summer. In 2010, one of the generators was used to provide continuous supply to Oamaru New World when the HV cable supplying Oamaru New World failed. One of the three diesel generators is now permanently deployed at the Waitaki District Council s main water reservoir. This ensures the continuity of water supply during any large scale power outages, while also leaving the generator available for use in times of grid emergencies. Page 7

8 Network Waitaki also makes extensive use of Live Line maintenance techniques to minimise planned outages. Network Waitaki subsidiary contractor has two Glove & Barrier live line crews to undertake this work. 1.6 Life Cycle Asset Management The maintenance practices applied to each asset group, or type, may vary depending on the strategic importance of the asset, the cost/benefit ratio of the planned maintenance, and the maintenance/inspection techniques available. Network Waitaki uses condition-based maintenance for the majority of its assets; however some assets such as LV service fuses are replaced on failure. Network Waitaki purchased a wood pole scanner in 2011 and plans to scan suspect poles before any subsequent work is undertaken. This approach aligns with the Electricity Engineers Authority (EEA) guideline for working on poles (Guide to Work on Pole and Pole Structures -Revision 1 September 2010). 1.7 Risk Assessment Network Waitaki uses the risk management standard AS/NZ Risk Management, and appropriate planned actions are determined for all significant risks. These actions include capital development, maintenance or operational enhancement, business planning or training, and contingency planning. Network Waitaki maintenance policies include routine inspections to ascertain asset condition and regulatory compliance. These policies rank public and environmental safety as a top priority. With enactment of the new Electricity Safety Regulations on 1 April 2010, Section 61A of the Electricity Act has come into effect and electricity generation and network companies are required to have in place, by 1 April 2012, a documented and audited safety management system (SMS). The SMS shall cover all practicable steps that must be taken to prevent the electricity supply system from presenting a significant risk of serious harm to the public or significant damage to property. This SMS requirement applies to owners of generation assets greater than 10 MW and owners of network assets greater than 10 MVA. Network Waitaki is in the process of reviewing its in-house documentation and setting up a data base to comply with the Section 61A requirements. Network Waitaki undertakes an annual review of its suit of Risk Management documentation, which includes: Physical Risk Assessment Asset Failure Recovery Plan Emergency Preparedness Plan Business Continuity Plan The latest review was completed in October Page 8

9 1.8 Performance and Plans for Improvement Plans to improve the performance of the network are based on: 1. improving condition based maintenance strategies, 2. adopting new and improved maintenance techniques, 3. improving network monitoring, and 4. employing more network automation Examples of these include the use of Partial Discharge Tests (PDTs) and wood pole scanning to provide non-invasive testing of in-service assets, and the continuing deployment of remote controlled high voltage switching devices. Maintaining compliance with Network Waitaki s own design and security standards are key drivers of development planning. When load increases, or load demographics change, the deployment of network assets needs to be reviewed to ensure that they deliver the appropriate service levels. Standardisation, higher design standards, targeting of critical assets, and adopting appropriate technology updates underlie Network Waitaki s performance strategy. Identification of best practice is achieved through benchmarking with other companies via The PricewaterhouseCoopers Electricity Line Business Information Disclosure Compendium. 1.9 Cross-reference to Requirement 24 AMP Prescription The following table is intended as a cross-reference for the structure of this document to the structure of prescribed content listed in Schedule 2, Requirement 24 of the Electricity Information Disclosure Requirement Cross-reference to Requirement 24 Schedule 2 Information to be included in Asset Management Plans Req. 24 Description Report Section Section Title 1 Summary of Plan 1 Summary 2 Background and Objectives 2 Background 2a Purpose of Plan 1.1 Purpose of Plan 2b Interaction with Corporate Goals 2.1 Interaction with Business Planning 2c Period Covered by Plan 2.2 Period Covered 2d Stakeholders Interests 2.3 Stakeholders Interests 2e Accountabilities and Responsibilities 2.5 Accountabilities and Responsibilities 2f AM systems and Processes 2.6 AM systems and Processes 3 Assets Covered 3 Asset Description 3a Description of Area 1.4 Network and Asset Description 3b Network Configuration 3.1 Network Configuration 3c Description by Asset Category 3.1 Network Configuration 3c Age Profiles and Condition 6 Life Cycle Assessments Page 9

10 3d Justification for Assets 3.4 Asset Justification 4 Service Levels 4 Level of Service 4a Consumer Orientated Performance Targets 4.2 Consumer Orientated Performance Targets 4b Other Targets 4.3 Asset Performance and Efficiency Targets 4c Justification of Targets 4.5 Justification of Service Level Targets 5 Network Development Plans 5 Network Development 5a Planning criteria and Assumptions 5.2 Planning Criteria 5b Methodology 5.3 Prioritisation of Network Developments 5c Demand Forecasts 5.4 Demand Forecast 5d Policies on Distributed Generation 5.5 Distributed Generation 5e Policies on Non-Network Solutions 5.6 Non-Network Options 5f Development Options 5.7 Development Plan 5g Development Programmes and Actions 5.7 Development Plan 6 Lifecycle AM Planning - maintenance 7 Maintenance Planning 6 Lifecycle AM Planning - renewal 6 Life Cycle Assessments 6a Maintenance Planning criteria 7 Maintenance Planning - asset subsections 6b Maintenance Planning policies 7 Maintenance Planning - asset subsections 6c Renewal Policies 6 Life Cycle Assessments - asset subsections 6d Renewal Programmes and Actions 6 Life Cycle Assessments - asset subsections 6e Renewal Expenditure Capital Expenditure Plan 7 Risk Management 8 Risk Management 7a Methods and Conclusions 8 Risk Management 7b Emergency Response and Contingency Plans 8 Risk Management 8 Evaluation of Performance 9 Performance Evaluation 8a Review of Progress 9 Performance Evaluation 8b Evaluation of Actual Performance 9 Performance Evaluation 8c Gap Analysis 9 Performance Evaluation Page 10

11 2.0 Background This AMP covers all electricity distribution assets that are owned and operated by Network Waitaki within its area of supply. It also makes reference to Transpower s transmission network and GXP s where these impact on service levels. The AMP is not Network Waitaki s primary planning document but is rather a compilation of various internal documents that are produced to meet the requirements of the Disclosure Regulations. 2.1 Interaction with Business Planning Process & Other Corporate Goals Network Waitaki is a lines company with 100% of its shares held by the Waitaki Power Trust, which is a consumer trust. The Trust represents the interests of its beneficiaries, who are the end-use consumers connected to the Network Waitaki network. The Corporate objectives, goals, and related performance targets of the company are set out in the Statement of Corporate Intent (SCI), which is agreed annually between the Board of Directors and the Waitaki Power Trust. The SCI covers the coming financial year plus the two succeeding years and is updated annually. The SCI also includes policies and objectives relating to Health & Safety, Risk Management, Human Resources, Environmental Management, Social Responsibility, Compliance, and the Efficient Use of Resources. The company s strategic planning, annual business planning and budgeting processes, identifies the key initiatives that are required to achieve the targets and objectives set in the SCI and the Network Development Plan. Annual Business Plans and Budgets are prepared to schedule actions needed at a more detailed level to deliver corporate objectives, assign responsibilities, and allocate resourcing for the coming financial year. The AMP provides a summary of the information contained in these internal planning documents, to enable stakeholders to assess Network Waitaki s asset management practices. A flowchart of Network Waitaki s planning process is provided at the end of this section to aid description of the interactions of different plans and the information flows, between plans. The planning process should be viewed as a continuous cycle rather than a hierarchy of documents. 2.2 Period Covered This AMP covers the period of 10 years from 1 April 2012 to 31 March 2022 and documents the known and projected capital and maintenance projects that will be required. The programme of work indicated in the AMP is based on current knowledge. The NDP includes some major projects which are consumer driven and may vary Page 11

12 in time, scope, and firmness. Such projects have the potential to significantly impact the annual budget and will therefore be subject to Board approval. This AMP was approved by the Board of Directors on 27 February Stakeholder Interests As a wholly owned consumer trust, corporate goals and objectives are primarily driven by the Waitaki Power Trust and consumers, however there are many other stakeholders who also have input into the planning and asset management process. These inputs are derived from surveys, direct communication, complaints, and contract negotiations. Network Waitaki stakeholders include: The Waitaki Power Trust, whose requirements are documented in the SCI and agreed with the Board annually; the Trust receives quarterly reports detailing performance to date against targets, and meet regularly with the Board Chairman and CEO. The Trust is also interested in the level of annual discount that will be provided to consumers. Energy Retailers and Consumers, who require a safe and reliable power supply at reasonable cost. There is regular direct contact with Retailers and large consumers, in addition to the bi-annual consumer surveys. Consumer complaints and fault reports also provide additional feedback that is incorporated into Network Waitaki s maintenance and capital planning. Concerns normally focus on the security and quality of supply and such concerns have resulted in a new zone substation being planned for the Hampden area that will enhance the security of supply in the southern part of the network. In the mass market surveys that have been undertaken to date consumers have expressed a strong preference for continuing to pay about the same line charges to receive about the same reliability. Consumers, through the Waitaki Power Trust, are also interested in the level of annual discount that will be provided by Network Waitaki. The bi-annual consumer survey planned for 2011 has been cancelled in light of the scheduled five-yearly ownership review of Network Waitaki in The review solicits response from the consumers on the ownership of Network Waitaki. Previous reviews have mainly expressed satisfaction with the performance and have urged with the continuation of the annual discounts on the electricity bills. Transpower, who are interested in any growth in the network that will require transmission line upgrades or new GXP, and in the revenue that they generate from Network Waitaki. Network Waitaki staff, who are interested in health and safety issues, and in employment, education, and training opportunities. Local Authorities, who are not only consumers but also, have an interest in the safety and control of utility assets that are sited on Page 12

13 public property including street lighting. They are also interested in minimising the environmental impact of installed Network Waitaki assets, and in fostering economic development within the region. Regular contact with the local council also enables both parties to benefit from any conjoint installation opportunities. New Zealand Transport Agency, who have an interest in the safety and control of assets installed within the road reserve, and also in street lighting. NZTA requirements impact at both the planning and installation stages and can have a significant impact on cost. Farmers and Developers, who want power to be made available for their developments in a timely manner and at a fair and reasonable cost. Discussions normally centre on the capacity that is available, the cost of establishing the supply, and the lead time that will be required. Government Agencies, who legislate and audit compliance. Contractors, who are interested in the magnitude of both the current and projected annual work programmes and in any changes to policies or standards that may impact on their business. An annual forum is held for local electricians and electrical inspectors to bring them up to date with any changes in the Network Waitaki connection standards and any issues that have arisen. The last forum included a session on variable speed motor starters and the harmonic issues caused by these devices. 2.4 Conflicts of Interest Any conflicts in stakeholder requirements are normally resolved by prioritising the requirements on a risk and obligation basis. All stakeholders want to minimise the risk of injury to the public, staff or contractors and these concerns are given the highest priority. Network Waitaki has obligations to maintain supply to existing consumers at the security levels set out in the SCI. With a predominantly rural network, Network Waitaki has a number of lines that are essentially uneconomic. A significant number of these lines are in snow prone areas, and would not meet our current design standards. However, the number of uneconomic lines is decreasing as a result of the significant growth in dairy conversions and associated irrigation. Whilst the growth rate has been slowing down, there are potentially large irrigation and dairy-related loads and significant industrial growth within the period of this AMP. In addition to these capital requirements the Trust requires that a portion of the annual profit be returned to consumers. These conflicts have been resolved by closely monitoring line condition and prioritising capital replacement based on risk assessment, and by the introduction of a Connection Charge that in part recovers the cost of new developments from the developer. Page 13

14 2.5 Accountabilities and Responsibilities The ultimate accountability for the network assets lies with the Directors of Network Waitaki, who are appointed by the Trustees, and who approve the Asset Management Plan. Directors are also accountable to the Trustees for meeting the requirements set out in the Statement of Corporate Intent, which includes specific asset management objectives and service targets. Directors have an involvement in approving projects and budgets needed to support the AMP. For larger projects, new investments, and projects committing the company to expenditure over several years the approval process includes a formal Sanction for Expenditure. This provides Directors with technical detail and presents the business case for the proposal. Directors review Sanctions, post implementation, to confirm delivery on benefits and continued need. The Asset Management Plan, Network Development Plan and Strategic Plan all signal the need for future investments so that Directors can assess the long term issues such as funding requirements. Management report outage statistics, network performance, and work programme progress to the Directors on a monthly basis. Quarterly reports comparing year to date performance against the SCI are provided to the Trust. Annual reports are prepared by both Network Waitaki and the Waitaki Power Trust. The management of the assets is the responsibility of Network Waitaki s executive management organised per the Network Waitaki Organisational Structure shown on page 16. Asset management responsibilities are allocated between the engineering managers as follows: Network Planning and Operations Manager This manager has responsibility for the long term network performance and planning activities, and the day to day operation of the network. This includes the management of the annual capital and maintenance work programmes, control room operations, contractor interface, and the development of standards and policies. Planning and Development Manager This manager has responsibility for special projects such as distributed generation, fibre network development, factory acceptance inspections. Industrial scale installations may also be resourced from this position. General Pricing and disclosure duties are shared by the both the Network and Commercial Managers with assistance and input from the Finance Manager. Network Waitaki s fault service is currently resourced by Network Waitaki Contracting Ltd, a distribution contracting company, which is 100% owned by Page 14

15 Network Waitaki. The service is secured via a monthly fee to ensure resource availability is always maintained in Oamaru. Performance is reviewed annually and compared with industry benchmarks. The majority of the annual work programme is undertaken by Network Waitaki Contracting Ltd (NWCL), who has a staff of approximately 20 people located in Oamaru. NWCL does not provide technician services and these have to be out sourced. Network Waitaki has a relatively small staffing establishment intended to resource a narrow business model i.e. operational management of a lines business. Work activity is shared by a discipline based team and assigned on the basis of competence to do the task not seniority of an individual position e.g. the entire engineering team, from the Network Manager to the Engineering Officer, man the Control Room on a roster basis. Page 15

16 Network Waitaki Organisational Structure (as at 1 October 2011) Page 16

17 2.6 Asset Management Systems & Processes The following asset management systems are used in managing Network Waitaki assets: An Intergraph (G-Electric) Geographic Information System, which is used to record and display the location and condition of network assets. The primary functionality of the GIS is that it provides a connectivity model of the network and therefore delivers a powerful query tool for asset management applications An Asset Database, which is used to record the attributes, current status, and service history of network assets. The asset database also includes the financial asset register, and is used for both asset management and financial planning. A suite of valuation and asset management systems is linked to the Asset Database. This database is linked to the GIS i.e. provides the attribution for the connected asset elements. An Outage Database, which is used to record and analyse outage reports and calculate the reliability indices. The GIS is used to identify consumers affected during switching. A condition based inspection and assessment programme, which is used to determine asset maintenance and replacement requirements and priorities. Each asset group has an appropriate inspection/testing action and frequency cycle identified. These may trigger more detailed inspection, more frequent inspection (closer management), maintenance actions, or a planned replacement action. Network Waitaki selects the inspection technique it considers the best practice for its network and ensures its effectiveness by analysis of results. A financial management system (ACPAC) which is used to record and track the value of installed assets and stock inventory. ETAP load flow modelling software is used to model the impact of load growth. Network Waitaki is currently replacing the asset database, works order database, and faults database with an Asset Management Information System. This system will integrate with the GIS and financial systems and will significantly enhance and streamline the processes already employed. This project commenced in November 2009 and is approximately 75% complete. 2.7 Asset Data Accuracy The accuracy and completeness of the data Network Waitaki has at its disposal to plan and manage assets is limited by the following issues: Original data capture: the data contained in Network Waitaki s data systems was originally captured from limited hard copy records and field inspections. For some key data items, such as age, it is not possible to get an accurate determination by looking at the asset or testing it. Such data is therefore an Page 17

18 informed estimate; however by basing asset management actions on condition assessment rather than age overcomes this issue. In some instances, data was captured for a specific regulatory application, for example valuation. This data is subject to independent audit. Conversion errors: Converting data from one record system to another and applying it to a different application can introduce errors. Such projects are therefore inclusive of quality control measures. Occasionally it is found that where the accuracy of data is acceptable for one application it is not for another. Similarly, additional data is often required for new applications. Data washing is generally undertaken prior to conversion in these cases. Data maintenance: Keeping data up to date with physical changes on the network can be a challenge when new investment and upgrade is intensive. The multiple entries of the same data that are required to maintain the existing database records and GIS lead to data errors. It also does not make the most effective use of the limited staff resources available in this area. Network Waitaki is currently transferring its data to the new system. Many of these issues are being resolved by the implementation of the Asset Information Management System (AIMS) as it removes the current duplication in data entry that is required to populate the various databases. It will also significantly enhance Network Waitaki s ability to produce reports and disclosures as all of the data will be linked. To transfer the data from the Asset Database to the Asset Management Information System will require any inaccuracies in the current Network Waitaki asset records to be addressed. This work is nearing completion. The faults, planned outage data, and switching times are recorded from contractor fault response sheets, switching programmes, and SCADA records, which are manually loaded into an access database. A list of the number of consumers that are located between the various switching points on the network is derived from the GIS and is updated annually. Many outages have various stages during restoration when the number of consumer affected by a fault will vary. The customer minutes from each of these stages is calculated manually to provide a single SAIDI, SAIFI, and CAIDI figure for each outage. The number of ICPs affected by the fault takes no account of the status of the ICPs, and the total number of ICPs is simply the average of the start and finish number of ICPs for that financial year. Temporary changes to the configuration of the network can result in errors in the number of ICPs counted if these changes are not known at the time the fault calculations are undertaken. This process was based on the guidelines produced by the long defunct Electricity Supply Association of NZ as the default for standard industry practice. It is subject to the annual disclosure audit and no changes to the process have been required. However this process will be replaced by the new AIMS which will calculate the SAIDI, SAIFI, and CAIDI results based on a GIS line trace and the Registry to determine the actual number of active ICPs that were affected by the outage and actual number of active ICPs that were connected to the network at the time the outage occurred, which will eliminate the necessity for manual calculations, and improve reporting accuracy. Page 18

19 NWL Asset Management Process Influencers Drivers Determine AM Drivers The Stakeholders Safety Corporate Vision Customer Service Operational Efficiency Security and Quality of Supply Regulatory Compliance Shareholder Returns Statement of Corporate Intent Strategic Plan Inputs Process Outputs Asset Management Process Network Strategy Policies & Standards Service Targets Load Forecasts Asset Valuation Data Asset Condition Data Outage Statistics Cost Tracking Network Development Plan Life Cycle Assesment Performance Assesment Risk Assesment Capital Programmes Maintenance Programmes Standards & Specifications Annual Work Programmes and Budgets Annual Reports Financial Service Compliance Performance Review Page 19

20 Asset Description 3.0 Asset Description 3.1 Network Configuration The Network Waitaki network is predominantly a rural network supplying the North Otago, Hakataramea, and Ahuriri regions. Based on the 2010 Disclosures, the network comprises 176km of 33kV sub-transmission line, 1344km of 11kV distribution line, and 210km of LV distribution line, and 13 zone substations. It supplies approximately 12,318 ICP s, has an average ICP density of 7.12 ICP/km of line, and has a maximum coincidental demand of approximately 52MW, which is inclusive of the Black Point GXP. The network is supplied from four Transpower Grid Exit Points (GXP), Oamaru, Black Point, Waitaki, and Twizel. A 33kV sub-transmission network connects the zone substations to three grid exit points (GXP) at Oamaru, Waitaki, and Twizel. The Oamaru GXP has a maximum demand of approximately 36MW, and supplies 9 zone substations. The Waitaki GXP has a maximum demand of approximately 4.7MW and supplies 3 zone substations. The Twizel GXP was previously utilised solely as a backup supply for the Waitaki GXP to facilitate both Network Waitaki and Transpower planned maintenance. However to cope with peak demand and to maintain contingent capacity at Benmore Dam, Network Waitaki has now permanently shifted the Ohau Zone Substation and the Ruataniwha 33kV connected farm supply, approximately 1.7MW of load, from the Waitaki GXP to the Twizel GXP. The 25MVA 110/11kV GXP at Black Point was commissioned in 2006 and has three 11kV feeders dedicated to the NOIC irrigation scheme which is Network Waitaki s largest single consumer. NOIC take supply at 110kV and therefore own the transformer and 11kV switchboard. The point of common coupling to Network Waitaki s network is at 110kV to manage voltage quality issues associated with starting 11kV rated motors. Phase displacement precludes any interconnection between the Network Waitaki and NOIC 11kV networks. The majority of Network Waitaki zone substations are radially connected to their GXP. Therefore supply restoration is dependent on 11kV interconnection between substations. The main urban substation, Chelmer Street, which supplies 30% of Network Waitaki s peak winter load, has an N-1 security configuration with dual 33kV lines and transformers that have recently been upgraded to 28MVA (ONAF) units. The second urban zone substation at Redcastle Road has also been upgraded to a dual 12.5MVA transformer configuration with the transformers being relocated from Chelmer St. A 33kV ring interconnects Oamaru GXP, Redcastle Substation and Pukeuri Substation, which supplies Network Waitaki s second largest consumer the Alliance Pukeuri Works. This 33kV ring provides N-1 security to both substations. Two zone substations were established and commissioned at Enfield and Papakaio, in These are both N security, 5/7MVA 33/11kV substations, which is Network Waitaki s standard for a rural substation. Enfield Substation is an intermediate substation that is supplied from the Ngapara 33kV sub-transmission line and has three 11kV feeders. Page 20

21 Duntroon Substation was commissioned in 2010/2011 to meet the increasing dairy and irrigation loads in the general Waitaki Plains area. The 5/7MVA 33/11kV substation, which is Network Waitaki s standard for a rural substation, is supplied from Oamaru GXP. A new 15km 33kV line extension utilising Jaguar conductor was established between Ngapara and Duntroon Substation. The substation has three outgoing 11kV feeders. The Ngapara 33kV line has been upgraded to Jaguar conductor to maximise its development potential. The Weston Pukeuri 33kV line has enough capacity for Papakaio Substation and to carry the full load of the Oamaru GXP/Pukeuri/Redcastle ring in the event of a line fault. This ring between Pukeuri and Redcastle provides improved security to all three substations. This consists of 1,507m of 300mm 2 Al underground cable and 6,445m of Neon overhead conductor. The 33kV protection has been upgraded to allow these lines to operate as a closed ring providing N-1 security to both Redcastle and Pukeuri substations. The 33kV line to Papakaio was extended by 7.9km to a new substation at Papakaio, constructed in The extension uses Neon overhead conductor and 110m of 33kV underground cable. The Papakaio Substation has four 11kV feeders. A plan of the supply area and sub-transmission system is provided in Appendix C. One of the three Network Waitaki 635kVA diesel generator sets is connected onto the 11kV bus at Enfield, with the second being connected into the 11kV bus at Otematata Substation. These two generator sets are normally used for meeting network or transmission grid emergencies. They are currently not being used for peak load management. The generator sets at Otematata and Enfield are reconfigurable to enable them to be transported to other locations to maintain supply to consumers during major line reconstruction projects or unplanned outages. The third generator is now permanently deployed to the Waitaki District Council s main water reservoir to ensure continuity of water supply during any large scale power outages. There are a total of forty-nine 11kV distribution feeder lines emanating from the thirteen 33/11kV zone substation. As the zone substations are radial connected to their GXP, supply restoration is therefore dependent on 11kV interconnection between substations. To further assist in a speedier supply restoration, Network Waitaki has embarked on a programme of having automated opening points on 11kV interconnection between substations. The only zone substations with N-1 security are the two urban substations, Chelmer and Redcastle which supply approximately half of Network Waitaki s total consumer base. Where 11kV feeders interconnect, they are normally configured as open points. Network Waitaki s loadings are such that security provisions are generally focussed on switching to restore supply quickly rather than targeting nil interruptions. Rural 11kV lines are fitted with Reclosers and Sectionalisers to provide automatic sectionalising and thereby reduce the numbers of consumers affected by line faults. The majority of these devices are linked to the SCADA system and can be remotely operated. Fault indicators are also used extensively in the rural 11kV network to reduce the time taken for field staff to locate and isolate faulted sections of line. Page 21

22 Approximately one third of the 11kV network is 2 wire single phase and features a large amount of spur configuration, which limits interconnection. This reflects the geographic remoteness of much of the network and the historical predominance of low energy intensity sheep farming. The 11kV distribution network supplies 2,607 distribution transformers, 593 of which have a capacity in excess of 100kVA. All new transformers, 200kVA or over, are ground mount mini-sub configured, irrespective of whether they are installed in an underground or overhead reticulated area. LV reticulation in urban areas is typically supplied by kVA distribution substations which are located to accommodate four LV feeders. Transformer capacity is normally based on an average After Diversity Maximum Demand (ADMD) of approximately 5.6kW for a domestic consumer. An LV switchboard is normally housed in the transformer cabinet with each LV feeder being independently fused. The LV switchboard is mounted independently of the transformer cabinet and is fitted with an incomer switch to facilitate isolation and removal of the transformer independent of the LV board. In overhead reticulated areas transformers are protected by pole mounted expulsion fuses and in underground reticulated areas with ground mounted fused oil switches. In urban areas the LV system is run in open rings with tie points brought into ground mounted distribution boxes or jumper cuts in the overhead reticulated system. Ground mounted transformers earths in urban areas incorporate an equipotential earth loop to control step and touch voltages. Transformers are arranged in a mesh layout such that neighbouring units can support an outage via LV interconnection. Both transformers and cables are designed with sufficient spare capacity for this purpose. Maximum Demand Indicators (MDI s) are fitted to determine the need for capacity upgrade and phase balancing. Larger supplies may have dedicated LV cables back to the LV distribution frame and/or a dedicated transformer on their own site. Rural supplies tend to have smaller dedicated transformers which are pole mounted. LV lines amount to 210km or 12.1% of Network Waitaki s network, with LV reticulation being largely restricted to Oamaru and rural townships. Rural network design does not include LV interconnection between distribution transformers due to distance limitations on LV capacity. Approximately 56% of the LV network is under-built on HV pole lines, with only 13% of LV service connections being via underground cable. In overhead reticulated areas road crossing is via Telecom poles where they exist and are in an acceptable condition. The Waitaki District Plan requires any new reticulation to be placed underground in areas that are specified as urban or residential. There are no undergrounding programmes in progress as the community has not expressed a desire for this in community planning processes (LTCCP and DP). Asset management drivers, including cost and outage minimisation, favour the retention of overhead assets. Underground reticulation is a minority feature of Network Waitaki s network: 33kV cable accounts for 8km or 0.5% of the network, 11kV cable accounts for 49km or 2.8% of the network, and LV cable accounts for 28km or 1.6% of the network. The District Plan requirements introduced after initial reticulation programs only impacts new extension work or new interconnections for security purposes with regard to under-grounding. Capacity upgrades in urban areas where under-grounding rules Page 22

23 apply are often achieved by the installation of intermediate distribution substations rather than by conductor upgrades. A breakdown of the assets, their relative value and quantities is given in Appendix A. This is based on the Network Waitaki last ODV dated 31 March 2004 and therefore is not up to date with the relatively intensive developments in Network Waitaki s subtransmission system over recent years. This table will be updated annually when the new AIMS is operational. The growth in irrigation load resulted in Network Waitaki becoming a summer peaking network for the first time during the 2006/07 irrigation season. Diversity between GXP s and zone substations therefore change significantly with the weather conditions in each area. The Waitaki GXP is constrained to 5.5MVA. During the 2007/08 peak period Meridian Energy called on their 2MW of backup supply for Benmore, which required Network Waitaki to manage the constraint at Waitaki by shifting some load onto Twizel. There are indications from Meridian Energy that a revised backup demand of 1MW may only be required from Network Waitaki. Continued load growth in the Waitaki GXP supplied area has necessitated a permanent shift of 1.7MW of load on to the Twizel GXP. Network Waitaki will continue with this strategy of re-distributing load between Waitaki and Twizel. In total Network Waitaki transported 222GWh of energy across its network in 2010/11 plus an additional 19GWh to the NOIC irrigation scheme via the Black Point GXP. This figure is 4% above the 5 year rolling average (2005/2006 to 2009/2010). It should be noted that energy consumption is now dominated by irrigation load which is driven by dry weather conditions. For example in the 2011 year the monthly variance in consumption to the previous year ranged between % to %. This load is shared between GXP s as follows: approximately 197GWh through the Oamaru GXP, 22GWh through the Waitaki GXP and 8GWh through the Twizel GXP. Network Waitaki has only four consumers who could be considered as large by national standards. These are: North Otago Irrigation Company: supplied from the dedicated Black Point GXP with n level security and no 11kV interconnection to Network Waitaki s network. Alliance Pukeuri Works: supplied from the Pukeuri Substation via dedicated dual 11kV connections to their own 11kV network. Pukeuri is an n-security level substation but has an N-1 33kV sub transmission supply and multiple 11kV substation interconnections. The 11kV interconnections cannot supply the full load of the factory but do provide sufficient capacity to maintain the freezers and essential services. Summit Wool Spinners: able to be supplied from both Redcastle and Chelmer Substations. 11kV feeders are not dedicated but there are multiple alternative supply options. Lean Meats: supplied from Redcastle Substation. The 11kV feeders supplying Lean Meats are not dedicated but there are multiple alternative supply options. Page 23

24 None of these installations have a significant impact on network operations other than they are 11kV connected via dedicated assets and their security arrangements are more directly related to the connection asset they are prepared to pay for. However the network is configured to specifically service the load they present at their existing locations. 3.2 Transpower Substations Network Waitaki owns and operates the 33kV Indoor switchboard associated with the Oamaru GXP. This consists of 2 Incomer CB s, a Bus Coupler, and 8 Feeder CB s (including 1 spare). This was commissioned in 2007 and overcomes the configuration/operational issues associated with the previous Transpower outdoor 33kV bus. Until June 2010, there were voltage control issues with Transpower s 110/33kV transformers due to the on-board tap changers not working automatically. These tap changers have been replaced by Transpower with fully automatic and remote controlled units. Remaining operational issues at Oamaru GXP include: No 110kV bussing which results in Network Waitaki s 33kV board carrying the imbalance between circuits on the transmission system. This is unacceptable to Network Waitaki and is to be addressed with bussing upstream of Oamaru as part of the Waitaki Valley Reliability Project, which is still undetermined. The directional protection schemes do not grade between Network Waitaki s 33kV incomer CBs and the Transpower 110/33KV CBs. This should also be able to be resolved by bussing the 110kV lines. The Oamaru GXP needs Power Factor Correction capacitors which are scheduled to be installed in 2011/2012 at 11kV on Network Waitaki s network to improve cost efficiency and technical effectiveness. Operational control of the Waitaki and Twizel 33kV sub-transmission circuit breakers has been retained by Transpower for logistical reasons. Network Waitaki has operational control of the Black Point GXP which feeds out at 11kV and is currently dedicated to a single customer. More discussion on the transmission and GXP issues relating to Network Waitaki can be found in Transpower s Annual Planning Report. There are significant constraint issues with Transpower s 110kV network that limit its ability to meet future demand. This has initiated upgrade investigations, which have progressed to the shortlist stage of the GUP (Grid Upgrade Plan) and GIT (Grid Investment Test) processes. Details can be found on Transpower s website by referencing the Lower Waitaki Valley Reliability Project. How Network Waitaki will ultimately develop its sub-transmission system will depend on the outcome from Transpower s Lower Waitaki Valley Reliability Project. There are no GXP s with more than 1MW of permanent generation connected. Page 24

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited PB ASSOCIATES COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN Prepared for PB Associates Quality System: Document Identifier : 153162 Top Energy Final Report Revision : 2 Report Status : Final Date

More information

Asset Management Plan

Asset Management Plan 2013 Asset Management Plan www.topenergy.co.nz INTRODUCTION Introduction It gives me great pleasure to present Top Energy s 2013-2023 Network Asset Management Plan (AMP). The 2013 plan follows on from

More information

EDB Information Disclosure Requirements Information Templates for Schedules 11a 13

EDB Information Disclosure Requirements Information Templates for Schedules 11a 13 EDB Information Disclosure Requirements Information Templates for Schedules 11a 13 Disclosure Date 31 March 2015 Start Date (first day) 1 April 2015 Templates for Schedules 11a 13 (Asset Management Plan)

More information

NETWORK MANAGEMENT STRATEGY

NETWORK MANAGEMENT STRATEGY ABN 85 082 464 622 NETWORK MANAGEMENT STRATEGY DOCUMENT NUMBER: NW-#30065608-V6 DATE: 12 MAY 2011 NW-#30065608-v6-Network_Management_Strategy.DOC Page 1 of 20 This page is intentionally blank. NW-#30065608-v6-Network_Management_Strategy.DOC

More information

16 West Coast Regional Plan

16 West Coast Regional Plan 16 West Coast Regional Plan 16.1 Regional overview 16.2 West Coast transmission system 16.3 West Coast demand 16.4 West Coast generation 16.5 West Coast significant maintenance work 16.6 Future West Coast

More information

Asset Management Plan

Asset Management Plan 2014 Asset Management Plan www.topenergy.co.nz INTRODUCTION Introduction It gives me great pleasure to present Top Energy s 2014-2024 Network Asset Management Plan (AMP). The 2014 AMP follows on from the

More information

Agenda do Mini-Curso. Sérgio Yoshio Fujii. Ethan Boardman. sergio.fujii@areva-td.com. ethan.boardman@areva-td.com

Agenda do Mini-Curso. Sérgio Yoshio Fujii. Ethan Boardman. sergio.fujii@areva-td.com. ethan.boardman@areva-td.com Agenda do Mini-Curso Sérgio Yoshio Fujii sergio.fujii@areva-td.com Ethan Boardman ethan.boardman@areva-td.com Agenda do Mini-Curso Sistemas de Distribuição (DMS) Characteristics of Distribution Network

More information

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe NETWORKS ESB Networks Response to ERGEG Consultation on Voltage Quality Regulation in Europe Date: 22 February 2007 Distribution System Operator ESB Networks Page 1 of 12 Contents 1.0 INTRODUCTION...3

More information

Asset Management Plan 2014 2024

Asset Management Plan 2014 2024 Asset Management Plan 2014 2024 Clarks Substation in winter Publicly disclosed in March 2014 CONTENTS Contents 0. SUMMARY OF THE PLAN...5 0.1 BACKGROUND AND OBJECTIVES...5 0.2 DETAILS OF THE NETWORK...6

More information

SUMMARY ASsET MANAGEMENT PLAN

SUMMARY ASsET MANAGEMENT PLAN SUMMARY ASsET MANAGEMENT PLAN INFORmATION DISCLOSURE FOR ELECTRICITY NETWORKS JUNE 2010 2019 ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2010 FY2019 1 contents CHIEF EXECUTIVE S STATEMENT... 2 POWERCO

More information

Asset Management Plan 2012 2022

Asset Management Plan 2012 2022 Asset Management Plan 2012 2022 April 2012 safe, reliable, hassle free service safe, reliable, hassle free service Table of Contents Section 1: Summary Section 2: Background and Objectives Section 3: Assets

More information

Asset Management Plan. A 10-year management plan for Orion s electricity network from 1 April 2014 to 31 March 2024

Asset Management Plan. A 10-year management plan for Orion s electricity network from 1 April 2014 to 31 March 2024 Asset Management Plan A 10-year management plan for Orion s electricity network from 1 April 2014 to 31 March 2024 Front cover: A team from Connetics installs 11,000 volt and 400 volt cables into a supply

More information

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited TABLE OF CONTENTS 1.0 Purpose and Scope...2 1.1 Methodology Purpose...2

More information

Asset Management Plan. A 10-year management plan for Orion s electricity network from 1 April 2015 31 March 2025

Asset Management Plan. A 10-year management plan for Orion s electricity network from 1 April 2015 31 March 2025 Asset Management Plan A 10-year management plan for Orion s electricity network from 1 April 2015 31 March 2025 Front cover: A team from Independent Line Services removing conductors prior to dismantling

More information

Power products and systems. Intelligent solutions for power distribution Zone concept

Power products and systems. Intelligent solutions for power distribution Zone concept Power products and systems Intelligent solutions for power distribution Zone concept Securing continuous power supply ABB is one of the world's leading power and automation technology companies whose products,

More information

Chapter 1. Network Structures

Chapter 1. Network Structures Chapter 1 Network Structures Definition Standard IEC 60038 defines voltage ratings as follows: Low voltage (): for a phase-to-phase voltage of between 100 V and 1,000 V, the standard ratings are: 400 V

More information

For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690 V - 1000 V (at 50 Hz)

For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690 V - 1000 V (at 50 Hz) 24 1. NETWORK CONFIGURATIONS definition Standard IEC 38 defines voltage ratings as follows: - Low voltage () For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690

More information

EA NETWORKS ASSET MANAGEMENT PLAN 2015-25

EA NETWORKS ASSET MANAGEMENT PLAN 2015-25 EA NETWORKS ASSET MANAGEMENT PLAN 2015-25 2 ASSET MANAGEMENT PLAN FOR EA NETWORKS' ELECTRICITY NETWORK Planning Period: 1 April 2015 to 31 March 2025 Disclosure Year: 2015-16 Disclosure Date: 31 March

More information

Vision 2050 An Asset Management Strategy. Jaclyn Cantler Manager, Transmission Planning, PHI

Vision 2050 An Asset Management Strategy. Jaclyn Cantler Manager, Transmission Planning, PHI 1 Vision 2050 An Asset Management Strategy Jaclyn Cantler Manager, Transmission Planning, PHI 2 Agenda Case for Change About Vision 2050 Status Closing System Design Cybersecurity Interface with distributed/dispersed

More information

Table of Contents Introduction... 1 Summary... 2 Reconciliation with Previous Valuation... 5 Asset Databases... 6 Quantities... 9 Asset Lives...

Table of Contents Introduction... 1 Summary... 2 Reconciliation with Previous Valuation... 5 Asset Databases... 6 Quantities... 9 Asset Lives... Table of Contents 1 Introduction... 1 2 Summary... 2 2.1 Valuation Statement... 2 2.1.1 Valuation Summary as at 31 March 2004...3 2.1.2 Depreciation Summary for the year to 31 March 2004...3 2.2 Date of

More information

2006 Report. of the. Optimised Deprival Valuation of Transpower s System Fixed Assets. as at 30 June 2006

2006 Report. of the. Optimised Deprival Valuation of Transpower s System Fixed Assets. as at 30 June 2006 T R A N S P O W E R N E W Z E A L A N D L I M I T E D 2006 Report of the Optimised Deprival Valuation of Transpower s System Fixed Assets as at 30 June 2006 Prepared by Transpower New Zealand Limited Reviewed

More information

Asset Management Plan 2013-2023

Asset Management Plan 2013-2023 Asset Management Plan 2013-2023 March 2013 safe, reliable, hassle free service COPYRIGHT 2013 Northpower New Zealand Limited. All rights reserved. This document is protected by copyright vested in Northpower

More information

Pennsylvania Summer Reliability

Pennsylvania Summer Reliability A. Reliability Enhancement Programs In 2015, Pennsylvania Power Company s ( Penn Power or Company ) reliability plan incorporates projects and programs to enhance overall reliability. The plan is structured

More information

Executive summary 2. 1 Introduction 4

Executive summary 2. 1 Introduction 4 Flexible Networks for a Low Carbon Future Future Network Monitoring Strategy September 2015 Contents Executive summary 2 Glossary 3 1 Introduction 4 2 Fundamental principles of monitoring 5 2.1 LCT monitoring

More information

CONNECTING YOU TO SPECIALIST ELECTRICAL SUPPORT services

CONNECTING YOU TO SPECIALIST ELECTRICAL SUPPORT services CONNECTING YOU TO SPECIALIST ELECTRICAL SUPPORT services SpecialistS IN ELECTRICAL SUPPORT SERVICES TO MINING, UTILITIES & industry Ampcontrol is committed to supporting our customers to maintain efficient

More information

POWER NETWORKS. 2014-15 Electricity Network Tariffs and Charges and Future Price Trends

POWER NETWORKS. 2014-15 Electricity Network Tariffs and Charges and Future Price Trends POWER NETWORKS 2014-15 Electricity Network Tariffs and Charges and Future Price Trends August 2014 Power and Water Corporation Table of Contents 1 Business Characteristics... 3 2 2014 Network Price Determination...

More information

F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China

F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China ELECTRIC POWER DISTRIBUTION SYSTEMS F.C. Chan General Manager, CLP Engineering Ltd., Hong Kong SAR, China Keywords: Distribution system planning, Load characteristics, Subtransmission Lines, Distribution

More information

Electricity Distribution Business. Pricing Methodology

Electricity Distribution Business. Pricing Methodology Electricity Distribution Business Pricing Methodology Effective 1 April 2015 1. GLOSSARY Commerce Commission (Commission) EDB Electricity Authority (EA) Responsible for the regulation of EDBs as provided

More information

RCP2 Portfolio Overview Document

RCP2 Portfolio Overview Document RCP2 Portfolio Overview Document Portfolio: Expenditure Class: Base Capex Expenditure Category: Grid Replacement & Refurbishment As at date: 15 November 2013 Expenditure Forecast Real 2012/13 NZ$ (m) 2015-2016

More information

FIXED CHARGE: This is a cost that goes towards making the service available, including

FIXED CHARGE: This is a cost that goes towards making the service available, including ELECTRICITY BILL COMPONENTS FIXED CHARGE: This is a cost that goes towards making the service available, including installation and maintenance of poles, power lines and equipment, and 24-hour customer

More information

Principles of Distribution charging:

Principles of Distribution charging: Principles of Distribution charging: Electricity networks Introduction A three-stage approach involves the following steps: 1. The analysis and quantification of costs. The cost concept that is relevant

More information

2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology

2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology 2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology Version Number 1 26 June 2015 Tasmanian Networks Pty Ltd (ACN 167 357 299) Table of contents 1 Introduction... 1 2 Meeting our

More information

Commission de l énergie de l Ontario. Filing Requirements for Electricity Transmission and Distribution Applications. Chapter 5.

Commission de l énergie de l Ontario. Filing Requirements for Electricity Transmission and Distribution Applications. Chapter 5. Ontario Energy Board Commission de l énergie de l Ontario Ontario Energy Board Filing Requirements for Electricity Transmission and Distribution Applications Chapter 5 Consolidated Distribution System

More information

Low Voltage Asset Management (LVAM) The key to reliable and safe electricity

Low Voltage Asset Management (LVAM) The key to reliable and safe electricity Low Voltage Asset Management (LVAM) The key to reliable and safe electricity Archie Jaykaran Distribution Division Eskom SA Contents Change drivers Scope, Approach, Project status LV Planning and Design

More information

A MODERN DISTRIBUTION MANAGEMENT SYSTEM FOR REGIONAL ELECTRICITY COMPANIES

A MODERN DISTRIBUTION MANAGEMENT SYSTEM FOR REGIONAL ELECTRICITY COMPANIES A MODERN DISTRIBUTION MANAGEMENT SYSTEM FOR REGIONAL ELECTRICITY COMPANIES A Roberts, T Berry, W D Wilson Schneider Electric Ltd, UK SYNOPSIS This paper describes the features of a modern Distribution

More information

Market Growth and New Regulations Demand Network Modernization

Market Growth and New Regulations Demand Network Modernization CASE ESB NETWORKS: POLE TOP COMMUNICATION INCREASES EFFICIENCY IN IRELAND Viola s solution for remotely operating pole-top reclosers and switches increases reliability, cuts operating costs and helps to

More information

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited TABLE OF CONTENTS 1.0 Purpose and Scope...2 1.1 Methodology Purpose...2 2.0

More information

Pricing methodology Electricity distribution network. From 1 April 2014

Pricing methodology Electricity distribution network. From 1 April 2014 Pricing methodology Electricity distribution network From 1 April 2014 Pursuant to: The Electricity Distribution Information Disclosure Determination 2012 1. TABLE OF CONTENTS 1. Table of contents... 2

More information

ESKOM DISTRIBUTION NETWORK PLANNING, A QUANTUM LEAP TO MEET INCREASED LOAD GROWTH AND IMPROVED NETWORK RELIABILITY

ESKOM DISTRIBUTION NETWORK PLANNING, A QUANTUM LEAP TO MEET INCREASED LOAD GROWTH AND IMPROVED NETWORK RELIABILITY ESKOM DISTRIBUTION NETWORK PLANNING, A QUANTUM LEAP TO MEET INCREASED LOAD GROWTH AND IMPROVED NETWORK RELIABILITY Author & Presenter: CG Carter-Brown PhD Eskom, Chief Engineer IARC Co-author: R Stephen

More information

Asset Management Plan

Asset Management Plan Asset Management Plan 2010-2019 West Coast s Locally Owned Electricity Distributor Asset Management Plan A 10 Year Management Plan for Westpower s Electricity Network From 1 April 2009 to 31 March 2019

More information

Best Practices for Creating Your Smart Grid Network Model. By John Dirkman, P.E.

Best Practices for Creating Your Smart Grid Network Model. By John Dirkman, P.E. Best Practices for Creating Your Smart Grid Network Model By John Dirkman, P.E. Best Practices for Creating Your Smart Grid Network Model By John Dirkman, P.E. Executive summary A real-time model of their

More information

Jemena Electricity Networks (Vic) Ltd

Jemena Electricity Networks (Vic) Ltd Jemena Electricity Networks (Vic) Ltd 2016-20 Electricity Distribution Price Review Regulatory Proposal Attachment 7-12 - Independent analysis of augmentation expenditure Public 30 April 2015 AER augex

More information

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV 1. SCOPE This document details PowerSystems requirements for electrical testing of HV Equipment up to and including 33kV. 2. ISSUE RECORD This is a Reference document. The current version of Controlled

More information

Wandering Council Draft Plant Asset Management Plan

Wandering Council Draft Plant Asset Management Plan Wandering Council Draft Plant Asset Management Plan TABLE OF CONTENTS EXECUTIVE SUMMARY... 2 Context... 2 1 INTRODUCTION... 2 1.1 Background... 2 1.2 Goals and Objectives of Asset Management... 3 1.3 Pla

More information

Powerco Limited Pricing Guide 2015 ANNUAL REPORT 2015

Powerco Limited Pricing Guide 2015 ANNUAL REPORT 2015 ANNUAL REPORT 2015 PRICING GUIDE 2015 1 CONTENTS Introduction Page 03 Who we are Page 04 The Electricity Industry Page 05 Our Pricing Policy Page 08 How Powerco Performs Page 10 Pricing Methodology Page

More information

Electric Field Operations Organization

Electric Field Operations Organization NSTAR Electric Transmission Function Job Summaries Electric Field Operations Organization Vice President, Electric Field Operations (Transmission) This position has primary responsibility for the planning,

More information

Medium Voltage (MV) & High Voltage (HV) Training Module 6. Date of the presentation

Medium Voltage (MV) & High Voltage (HV) Training Module 6. Date of the presentation Medium Voltage (MV) & High Voltage (HV) Training Module 6 Date of the presentation Electrical System Basics MV vs. HV - Definitions Differences between USA and the rest of the world IEC define a high voltage

More information

CUS TOMER INITIATED CAPITAL WORKS (CICW) MANAGEMENT PLAN

CUS TOMER INITIATED CAPITAL WORKS (CICW) MANAGEMENT PLAN ABN 85 082 464 622 CUS TOMER INITIATED CAPITAL WORKS (CICW) MANAGEMENT PLAN DOCUMENT NUMBER: NW-#30171121 DATE: MARCH 2011 This page should either be left blank or used for any disclaimers. Page 2 of 19

More information

Asset Management Strategy

Asset Management Strategy Asset Management Strategy ElectraNet Corporate Headquarters 52-55 East Terrace, Adelaide, South Australia 5000 PO Box, 7096, Hutt Street Post Office, Adelaide, South Australia 5000 Tel: (08) 8404 7966

More information

DISCLOSURE OF ELECTRICITY PRICING METHODOLOGY PURSUANT TO REQUIREMENT 22 OF THE ELECTRICITY INFORMATION DISCLOSURE REQUIREMENTS 2004

DISCLOSURE OF ELECTRICITY PRICING METHODOLOGY PURSUANT TO REQUIREMENT 22 OF THE ELECTRICITY INFORMATION DISCLOSURE REQUIREMENTS 2004 DISCLOSURE OF ELECTRICITY PRICING METHODOLOGY PURSUANT TO REQUIREMENT 22 OF THE ELECTRICITY INFORMATION DISCLOSURE REQUIREMENTS 2004 Effective 1 April 2010 TABLE OF CONTENTS 1 INTRODUCTION... 1 2 DESCRIPTION

More information

Proceedings of the 38th Hawaii International Conference on System Sciences - 2005

Proceedings of the 38th Hawaii International Conference on System Sciences - 2005 The use of Multi-Attribute Trade-Off Analysis in Strategic Planning For an Electric Distribution utility: An Analysis of Abu Dhabi Distribution Company Richard D. Tabors, Ph.D. Rick Hornby Tabors Caramanis

More information

NOTES ON AURORA LINE CHARGES FOR NETWORK DESIGNERS, CONSULTANTS AND ELECTRICAL CONTRACTORS

NOTES ON AURORA LINE CHARGES FOR NETWORK DESIGNERS, CONSULTANTS AND ELECTRICAL CONTRACTORS ov 26 OTES O AURORA LIE CHARGES FOR ETWORK DESIGERS, COSULTATS AD ELECTRICAL COTRACTORS 1. PURPOSE AD SCOPE OF THIS DOCUMET This document provides general advice for personnel involved in the alteration

More information

Utilities the way we see it

Utilities the way we see it Utilities the way we see it Advanced Distribution Management Systems How to choose the right solution to improve your utility s safety, reliability, asset protection and quality of service Photo provided

More information

POWER NETWORKS. 2015-16 Electricity Network Tariffs and Charges and Future Price Trends

POWER NETWORKS. 2015-16 Electricity Network Tariffs and Charges and Future Price Trends POWER NETWORKS 2015-16 Electricity Network Tariffs and Charges and Future Price Trends July 2015 Power and Water Corporation 1 Table of Contents 1 Business Characteristics 3 2 2014 Network Price Determination

More information

Attachment 20.27 SA Power Networks: Network Program Deliverability Strategy

Attachment 20.27 SA Power Networks: Network Program Deliverability Strategy Attachment 20.27 SA Power Networks: Network Program Deliverability Strategy Network Program Deliverability Strategy 2015-20 Regulatory Control Period SA Power Networks www.sapowernetworks.com.au Internal

More information

Cost Allocation Method

Cost Allocation Method Cost Allocation Method Ergon Energy Corporation Limited Document Summary Version: 4.0 Status: AER Approved Version History and Date of Issue Version Date Issued Summary of Changes 1.0 March 2009 Initial

More information

Tasmanian Transmission Revenue Proposal

Tasmanian Transmission Revenue Proposal Tasmanian Transmission Revenue Proposal An overview for Tasmanian electricity consumers Regulatory control period 1 July 2014 30 June 2019 Tasmanian Networks Pty Ltd About TasNetworks We are Tasmania s

More information

DISTRIBUTION RELIABILITY USING RECLOSERS AND SECTIONALISERS

DISTRIBUTION RELIABILITY USING RECLOSERS AND SECTIONALISERS ABB DISTIBUTION ELIABILITY USING ECLOSES AND SECTIONALISES obert E. Goodin Chief Engineer ABB Inc. Lake Mary, FL Timothy S. Fahey, PE Sr. Application Engineer ABB Inc. aleigh, NC Andrew Hanson, PE Executive

More information

CUSTOMER-FACING PERFORMANCE MEASURES

CUSTOMER-FACING PERFORMANCE MEASURES CUSTOMER-FACING PERFORMANCE MEASURES CUSTOMER FEEDBACK AND RESPONSE Transpower New Zealand Limited March 2013 Customer-facing performance measures Transpower New Zealand Limited 2007. All rights reserved.

More information

Electricity Network Performance Report New South Wales. Transmission Annual Report Outline

Electricity Network Performance Report New South Wales. Transmission Annual Report Outline Electricity Network Performance Report New South Wales Transmission Annual Report Outline Issued April 2012 New South Wales Electricity Network Performance Report Transmission Network Service Provider

More information

PUBLIC UTILITIES COMMISSIO~t~ Docket No. DE 15-

PUBLIC UTILITIES COMMISSIO~t~ Docket No. DE 15- Th~NALZZ~ Exhibit STATE OF NEW HAMPSHIRE t~~eeee BEFORE THE FROM FILE PUBLIC UTILITIES COMMISSIO~t~ Liberty Utilities (Granite State Electric) Corp. dibla Liberty Utilities Calendar Year 2014 Reliability

More information

25 Distribution System Automation

25 Distribution System Automation Chap25 exe 21/06/02 8:30 Page 442 Distribution System Automation Introduction 25.1 Factors influencing the application of automation to distribution networks 25.2 Primary distribution system automation

More information

Lifecycle Strategy DISPOSAL AND DIVESTMENT

Lifecycle Strategy DISPOSAL AND DIVESTMENT Lifecycle Strategy DISPOSAL AND DIVESTMENT Document 07/10/2013 Page 1 of 19 C O P Y R I G H T 2013 T R A N S P O W E R N E W Z E A L A N D L I M I T E D. A L L R I G H T S R E S E R V E D This document

More information

The calm after the storm

The calm after the storm The calm after the storm Human decision support in storm outage recovery Rafael Ochoa, Amitava Sen It s a fact of life that interruptions in an electrical distribution utility happen. Although they can

More information

VOLTAGE CONTROL IN DISTRIBUTION SYSTEMS AS A LIMITATION OF THE HOSTING CAPACITY FOR DISTRIBUTED ENERGY RESOURCES

VOLTAGE CONTROL IN DISTRIBUTION SYSTEMS AS A LIMITATION OF THE HOSTING CAPACITY FOR DISTRIBUTED ENERGY RESOURCES VOLTAGE CONTROL IN DISTRIBUTION SYSTEMS AS A LIMITATION OF THE HOSTING CAPACITY FOR DISTRIBUTED ENERGY RESOURCES C. Schwaegerl*, M.H.J. Bollen, K. Karoui #, A. Yagmur + *Siemens AG, # Tractebel STRI AB

More information

Electricity Distribution Business Pricing Methodology for Prices Effective 1 April 2015 27 March 2015

Electricity Distribution Business Pricing Methodology for Prices Effective 1 April 2015 27 March 2015 Electricity Distribution Business Pricing Methodology for Prices Effective 1 April 2015 27 March 2015 Page 1 of 40 1 Table of contents 1 Table of contents... 2 2 Introduction... 3 3 Summary of 2015 pricing

More information

SP Energy Networks 2015 2023 Business Plan

SP Energy Networks 2015 2023 Business Plan Environmental Discretionary Reward Scheme 1 SP Energy Networks 2015 2023 Business Plan Executive summary SP Distribution Ltd SP Manweb plc July 2013 RIIO ED1 Business Plan 2015 to 2023 2 A Message from

More information

Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering

Title 20 PUBLIC SERVICE COMMISSION. Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES. Chapter 02 Engineering Title 20 PUBLIC SERVICE COMMISSION Subtitle 50 SERVICE SUPPLIED BY ELECTRIC COMPANIES Chapter 02 Engineering Authority: Public Utility Companies Article, 2-121, 5-101 and 5-303, Annotated Code of Maryland.

More information

Electric Power Distribution

Electric Power Distribution Electric Power Distribution A S Pabla Consulting Engineer and Former Chief Engineer Punjab State Electricity Board McGraw-Hill New York Chicago San Francisco Lisbon London Madrid Mexico City Milan New

More information

Disclaimer: The information in this document has been prepared in good faith and represents Powerco s intentions and opinions at the date of issue.

Disclaimer: The information in this document has been prepared in good faith and represents Powerco s intentions and opinions at the date of issue. ASSET MANAGEMENT PLAN 2013 Disclaimer: The information in this document has been prepared in good faith and represents Powerco s intentions and opinions at the date of issue. Powerco however, operates

More information

BL20A0501 Electricity distribution technology. Introduction Jarmo Partanen

BL20A0501 Electricity distribution technology. Introduction Jarmo Partanen BL20A0501 Electricity distribution technology Introduction Jarmo Partanen Introduction to ED Prof. Jarmo Partanen, D.Sc Jukka Lassila Topics of lectures Introduction to Electricity Distribution, 27.10

More information

Jemena Electricity Networks (Vic) Ltd

Jemena Electricity Networks (Vic) Ltd Jemena Electricity Networks (Vic) Ltd 2016-20 Electricity Distribution Price Review Regulatory Proposal Attachment 7-2 Asset management framework and governance Public 30 April 2015 Jemena Electricity

More information

TRANSPOWER NEW ZEALAND LIMITED. Request for Proposals. Demand Response Programme

TRANSPOWER NEW ZEALAND LIMITED. Request for Proposals. Demand Response Programme TRANSPOWER NEW ZEALAND LIMITED Request for Proposals Demand Response Programme Revision 1.0 (Registration Cycle 1) RELEASE DATE: 24 AUGUST 2015 CLOSING DATE: 2PM 02 OCTOBER 2015 RFP No: SUP-12707 Transpower

More information

Scorecard - Tillsonburg Hydro Inc.

Scorecard - Tillsonburg Hydro Inc. Scorecard - Tillsonburg Hydro Inc. 9/18/215 Performance Outcomes Performance Categories Measures 21 211 212 213 214 Trend Industry Distributor Target Customer Focus Services are provided in a manner that

More information

The Asset Management Landscape

The Asset Management Landscape The Asset Management Landscape ISBN 978-0-9871799-1-3 Issued November 2011 www.gfmam.org The Asset Management Landscape www.gfmam.org ISBN 978-0-9871799-1-3 Published November 2011 This version replaces

More information

Underground vs. Overhead Transmission and Distribution

Underground vs. Overhead Transmission and Distribution electric power engineering Underground vs. Overhead Transmission and Distribution Your Power System Specialists June 9, 2009 1 NATIONAL TRENDS Municipalities have passed laws requiring new distribution

More information

CUSTOMER EXPERIENCE PLAN Executive Summary

CUSTOMER EXPERIENCE PLAN Executive Summary At the core of the 2012 strategy are five strategic focus areas that prescribe a suite of people, process and technology oriented solutions. These areas are: Operations To ensure satisfied customers through

More information

VERMONT ELECTRIC COOPERATIVE, INC. SERVICE QUALITY & RELIABILITY PERFORMANCE, MONITORING & REPORTING PLAN

VERMONT ELECTRIC COOPERATIVE, INC. SERVICE QUALITY & RELIABILITY PERFORMANCE, MONITORING & REPORTING PLAN Section I: General Provisions VERMONT ELECTRIC COOPERATIVE, INC. SERVICE QUALITY & RELIABILITY PERFORMANCE, MONITORING & REPORTING PLAN 1. The purpose of this plan is to establish performance standards,

More information

TECHNICAL BRIEF. Commercial PV in Australia and New Zealand Using the Enphase Microinverter System

TECHNICAL BRIEF. Commercial PV in Australia and New Zealand Using the Enphase Microinverter System TECHNICAL BRIEF Commercial PV in Australia and New Zealand Using the Enphase Microinverter System 2015 Enphase Energy Inc. All rights reserved May 2015 Table of Contents Commercial PV in Australia and

More information

Market Growth and New Regulations Demand Network Modernization

Market Growth and New Regulations Demand Network Modernization CAE EB NETWORK: POLE TOP COMMUNICATION INCREAE EFFICIENCY IN IRELAND Viola s solution for remotely operating pole-top reclosers and switches increases reliability, cuts operating costs and helps to meet

More information

Submission to the Queensland Competition Authority. Regulated Retail Electricity Prices 2013-14 Transitional Issues & Cost Components and Other Issues

Submission to the Queensland Competition Authority. Regulated Retail Electricity Prices 2013-14 Transitional Issues & Cost Components and Other Issues Submission to the Queensland Competition Authority Transitional Issues & Cost Components and Other Issues January 2013 Queensland Farmers Federation Ltd. A.C.N. 055 764 488 A.B.N. 44 055 764 488 PO Box

More information

Hyperlinks are Inactive

Hyperlinks are Inactive Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)

More information

Appendix L Network Management Plan September 2011

Appendix L Network Management Plan September 2011 Appendix L Network Management Plan September 2011 Access Arrangement Information for the period 1 July 2012 to 30 June 2017 (AAI) Access Arrangement Information for the period 1 July 2012 to 30 June 2017

More information

ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1

ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1 ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1 Design and Planning Specification for New Low Voltage Installations for Housing Developments 1. SCOPE This appendix to ENA

More information

ADMS(Advanced Distribution Management System ) in Smart Grid

ADMS(Advanced Distribution Management System ) in Smart Grid ADMS(Advanced Distribution Management System ) in Smart Grid 柯 佾 寬 博 士 Yi-Kuan Ke, Ph.D. 2014/03/28 Smart Grid Solution Smart Grid Solution Overview Smart Grid Solutions Smart Network Operation - Distribution

More information

How the National Grid System Operates. Chris Gorman Lead Account Executive Syracuse

How the National Grid System Operates. Chris Gorman Lead Account Executive Syracuse How the National Grid System Operates Chris Gorman Lead Account Executive Syracuse 2 Parts of the Electric System Parts of the Electric System 1. Generating Station: Produces Electricity. 2. Transmission

More information

Phase Attribute Identification using GPS Technology

Phase Attribute Identification using GPS Technology Phase Attribute Identification using GPS Technology Date 11 June 2009 John Sinclair Power Quality Manager Slide 1 Topics of Discussion Remote Phase Identification How it works Principals of operation Benefits

More information

TRANSMISSION BUSINESS PERFORMANCE

TRANSMISSION BUSINESS PERFORMANCE Filed: 0-0- Tx 0-0 Rates Tab Schedule Page of TRANSMISSION BUSINESS PERFORMANCE.0 INTRODUCTION 0 Hydro One is focused on the strategic goals and performance targets in the area of safety, customer satisfaction,

More information

Attachment 16.1 SA Power Networks: Customer Data Quality Plan 2015-2020 September 2014

Attachment 16.1 SA Power Networks: Customer Data Quality Plan 2015-2020 September 2014 Attachment 16.1 SA Power Networks: Customer Data Quality Plan 2015-2020 September 2014 Customer Data Quality Plan 2015-2020 V1.1 Executive Summary The commencement of Full Retail Contestability in 2004

More information

Understanding the Auckland electricity network

Understanding the Auckland electricity network Understanding the Auckland electricity network Introduction This presentation describes how electricity reaches homes and businesses in Auckland, with a particular focus on the distribution network run

More information

Western Power transmission and distribution annual asset management report. prepared by Asset Management Division

Western Power transmission and distribution annual asset management report. prepared by Asset Management Division 2006 Western Power transmission and distribution annual asset management report prepared by Asset Management Division Disclaimer The Asset Management Division of Western Power has published this document

More information

Electricity network services. Long-term trends in prices and costs

Electricity network services. Long-term trends in prices and costs Electricity network services Long-term trends in prices and costs Contents Executive summary 3 Background 4 Trends in network prices and service 6 Trends in underlying network costs 11 Executive summary

More information

ASSET MANAGEMENT STRATEGY Approved

ASSET MANAGEMENT STRATEGY Approved Approved Document TP.TG 01.01 30/10/2014 Approved Transpower New Zealand Limited 2014. All rights reserved. Page 1 of 25 C O P Y R I G H T 2014 T R A N S P O W E R N E W Z E A L A N D L I M I T E D. A

More information

ROADS ALLIANCE ASSET MANAGEMENT COMMUNIQUÉ AUGUST 2010 LOCAL GOVERNMENT ASSOCIATION OF QUEENSLAND LTD

ROADS ALLIANCE ASSET MANAGEMENT COMMUNIQUÉ AUGUST 2010 LOCAL GOVERNMENT ASSOCIATION OF QUEENSLAND LTD ROADS ALLIANCE ASSET MANAGEMENT COMMUNIQUÉ AUGUST 2010 LOCAL GOVERNMENT ASSOCIATION OF QUEENSLAND LTD Contents 4 Glossary 6 Background 9 Purpose of Communiqué 9 Australian and State Government Drivers

More information

Unitil Energy Systems, Inc. Interconnection Standards For Inverters Sized Up To 100 kva

Unitil Energy Systems, Inc. Interconnection Standards For Inverters Sized Up To 100 kva Unitil Energy Systems, Inc. Interconnection Standards For Inverters Sized Up To 100 kva Issued: August 2009 SIZED UP TO 100 KVA TABLE OF CONTENTS 1.0 Introduction... 1 1.1 Applicability... 1 1.2 Definitions...

More information

2014 ELECTRIC SYSTEM RELIABILITY REPORT CITY OF ANAHEIM PUBLIC UTILITIES DEPARTMENT

2014 ELECTRIC SYSTEM RELIABILITY REPORT CITY OF ANAHEIM PUBLIC UTILITIES DEPARTMENT 2014 ELECTRIC SYSTEM RELIABILITY REPORT CITY OF ANAHEIM PUBLIC UTILITIES DEPARTMENT Contents Overview... 3 1.0 Electric System Reliability... 4 1.1 Annual Reliability Data with Utility Comparisons... 4

More information

ENA Customer Guide to Electricity Supply

ENA Customer Guide to Electricity Supply ENA Customer Guide to Electricity Supply Energy Networks Association Limited ENA Customer Guide to Electricity Supply August 2008 DISCLAIMER This document refers to various standards, guidelines, calculations,

More information

ASSET MANAGEMENT LCNI 2014 Wednesday 22 nd October. Jennifer Woodruff Innovation & Low Carbon Networks Engineer

ASSET MANAGEMENT LCNI 2014 Wednesday 22 nd October. Jennifer Woodruff Innovation & Low Carbon Networks Engineer ASSET MANAGEMENT LCNI 2014 Wednesday 22 nd October Jennifer Woodruff Innovation & Low Carbon Networks Engineer Asset Management Efficient asset management ensures that risk is effectively managed and returns

More information

OPERATIONS CAPITAL. The Operations Capital program for the test years is divided into two categories:

OPERATIONS CAPITAL. The Operations Capital program for the test years is divided into two categories: Filed: September 0, 00 EB-00-0 Tab Schedule Page of OPERATIONS CAPITAL.0 INTRODUCTION Operations Capital funds enhancements and replacements to the facilities required to operate the Hydro One Transmission

More information

Report to the Minister Responsible for the Qulliq Energy Corporation. Respecting:

Report to the Minister Responsible for the Qulliq Energy Corporation. Respecting: Report to the Minister Responsible for the Qulliq Energy Corporation Respecting: An Application by the Qulliq Energy Corporation For Approval of Major Project Permit to Upgrade the Iqaluit Distribution

More information