1 Number: Revision 0.2 Publication: 8/1/2014 Effective Date: 3/26/2013 Next Review Date: 8/1/2017 Procedure: Initiating a Change to a Contract 31 Requirement 1. Purpose This document describes the procedure for initiating a requirement change in the Department of Energy (DOE) contract that defines the operational parameters for. 2. Applicability who this is for This process applies primarily to persons who have responsibility for review and implementation of DOE contract requirements. 2.1 Exceptions ne 3. Pre-requisites Users of this procedure should review the Requirements Management Process, , and the Managing Contract Deliverables Process, Definitions Term Case Change Contract 31 Contract 31 Modification Deliverable Definition An instance of change or focused discussion of one or more institutional requirements and/or institutional documents. This is a RM and RMS term. Refers to (a) introduction of a new item, (b) retirement of an existing item, or (c) modification of an existing item Contract 31 refers to Contract No. DE AC02 05CH11231, the contract between the U.S. Department of Energy and the University of California (UC) describing the terms for UC to manage Berkeley Lab. The contract includes a statement of work (SOW) for the science missions, and details the requirements for managing the operations and business of Berkeley Lab. Refers to a formal agreement of change to Contract 31. Signed by DOE site office (BSO) and formally accepted by UCOP. Contract Mods are numbered and dated. The Mod address impact on any associated Contract deliverables. A Mod may contain any number of changes to the Contract. Any measurable, tangible, verifiable outcome, product, result, or item that must be produced to satisfy a requirement under the terms of an agreement, contract, or implementing mechanism. These include but are t limited to reports, plans, inventories, inspections, assessments, documents, procedures, programs, data, etc. A requirement specifies a deliverable, and therefore a deliverable is subject to requirements management practices Page 1 of 5 Printed or electronically transmitted copies are t official. Users are responsible for working with the latest approved revision.
2 Term Modification Record of Decision (ROD) Requirement RMS database Tri party Definition Used interchangeably with Change. A summary statement that describes a specific decision about an institutional requirement and/or document and/or implementation. The decision is based on analysis as described by the RM Analysis procedure (see Section 7.2 this document). A specific obligation to perform an action mandated by senior management or the federal, state, or local government; or to comply with the Laboratory s contract with the Department of Energy; or to comply with agreements made between the Laboratory and its corporate manager, the University of California. Requirements Management System the database tool for managing requirements and related information, including tracking requirements, their associated owners, records of implementing mechanisms, and their flow down to implementing documents. The RM Program Manager is responsible for managing the RMS. Refers to a group with representatives from BSO, UC Office of the President, and Berkeley Lab 5. Roles and Responsibilities These are adopted from Requirements Management Governance, Document , and emphasize responsibilities pertinent to this procedure. Refer to the Governance document for the most comprehensive, up todate version. Role Responsibilities Subject Matter Expert (SME) A Laboratory employee or consultant with specialized kwledge about a certain topic or field of interest. Provides technical expertise to the RMC and/or Working Group as it relates to the interpretation and implementation of requirements, including the development and review of policies and implementing documents. May be a Working Group member, may be an author or reviewer Working Group (WG) Comprised of members from affected and/or responsible divisions, having related special kwledge on the particular requirement or case in question. Members are recommended by SME, RMC in collaboration with Laboratory standing committee(s). Recommendations for WG member and SME participation are approved by respective Senior Line Managers. Perform detailed analyses, and determine detailed and practical implementation plans, with consideration of cost, simplicity, impact, and overall risk. Make recommendations in a timely fashion to the RMC, RM PM, Sr. Line Manager, and if applicable, the WG s sponsoring standing committee. Sr. Line Manager Has full responsibility and authority to make and enforce policies related to his/her respective area of expertise and responsibility. Has ownership and accountability for the technical content, accuracy and completeness of respective Function s documents. Ensures compliance with requirements and document management policies and procedures. Approves institutional documents upon completion of required reviews. Ensures compliance with requirements and document management policies and procedures. Works with the RM PM and RMC to resolve issues that may arise in the process of review and translation of requirements, policy into implementation. Appoints RMC Representative, WG members, SMEs, Document Authors. Has option to delegate approval authority to RMC member Page 2 of 5 Printed or electronically transmitted copies are t official. Users are responsible for working with the latest approved revision.
3 Role Responsibilities Requirements Management Program Manager (RM PM) Manages the Laboratory s requirements management and institutional document management processes. Is the main driver and champion of these processes. Has author/review/recommendation responsibilities for quality and completeness of RM process and institutional document management process documentation. Serves as the Laboratory s contact point on requirements and institutional document management related matters. Oversees management of Laboratory s policy manual. Maintains the Requirements Management (RM) database for tracking requirements, their associated policy areas (PA), owners, records of implementing mechanisms, and their flow down to implementing documents. Maintains accuracy and currency of the RM tracking system. Has review/approval responsibility for quality and completeness of requirement, policy, and document metadata. Requirements Management Committee (RMC) Reviews and oversees disposition of Requirements Review Cases related to requirements, Laboratory policies, and on a case by case basis Laboratory implementing documents. Applies cross functional kwledge on requirements matters. Assesses the Laboratory wide impacts of new or changed requirements, and adopts a holistic response. Reviews and recommends best qualified team members to address requirements analyses, implementation mechanisms and plans, policy and procedure documents. Such team members include Working Group (WG) members, and subject matter experts (SME), and stakeholders. Ensures teams are cross functionally represented. Recommends collaboration with other Laboratory standing committees whenever possible. Advises responsible Sr. Line Manager on WG/ SME work products. Reports to ALDO/COO. Champions RM and institutional document management processes. RMC Representative Represents a specific division or function on the RMC Fulfills the responsibilities described for RMC. University of Is the corporate entity responsible for the management of Berkeley Lab California Office of Has authority to negotiate/agree with BSO on matters regarding Contract 31. the President (UCOP) DOE/Berkeley Site Office (BSO) Reviews and approves those n policy institutional documents that are explicitly delineated by Contract 31 requirements as needing DOE review. BSO SME Has oversight responsibilities for specific Lab function or division BSO Contracting Officer (CO) Has approval authority regarding contents of Contract Procedure Figure 1 highlights (a) where this procedure fits in the overall RM process flow (see document number ) and (b) the pertinent steps of this procedure Page 3 of 5 Printed or electronically transmitted copies are t official. Users are responsible for working with the latest approved revision.
4 FIGURE 1 (RM Process) SME/WG interprets, analyzes impact, recommends Continue RM Process Does this req have associated Deliverables RMC, Sr. LM, review analysis SME/WG delineate deliverables. Review with BSO SME. Is there reason to question req? Continue pursuit? SME informs RMC rep or RM PM SME seeks assistance RMC rep, RM PM, Line Mgr SME revises package. Presents to BSO SME SME/WG prepare analyses (cost, risk, applicability) for BSO SME review. BSO SME concurrence? Lab SME, BSO SME present to BSO Contracting Officer SME provides final package (approvals, analyses,rod, plan) to RMC rep or RM PM 11 BSO CO concurrence? SME informs RMC rep or RM PM. KEY: Initiate Develop Review Approve Close Outside RM Scope RM PM or RMC rep logs ROD, uploads analysis, plan. RM PM updates Deliverables. End RM Process C31 change recommended? RM PM submits formal request (Go to BSO-UCOP-Lab Contract Mod process) Step Role Action 1 SME, Sr. LM Determine during Requirement Analysis process that there is reason to question the requirement and/or deliverable. 2 SME Informs RMC Rep and RM PM 3 SME/WG Prepares analysis package for BSO SME review 4 SME If Then BSO SME concurs Proceed with Step 7 BSO SME does t concur Seek assistance of RMC Rep, RM PM, Line Manager 5 SME, RMC Rep, RM PM, Evaluate and consider whether to continue to pursue Line Manager 6 SME If Then Continue pursuit of change Revise analysis package and present to Page 4 of 5 Printed or electronically transmitted copies are t official. Users are responsible for working with the latest approved revision.
5 Step Role Action BSO SME, go to step 4 Stop pursuit Continue along main RM process flow (see x) 7 Lab SME, BSO SME Present analysis to BSO Contracting Officer 8 SME If Then BSO CO concurs Proceed with Step 9 BSO CO does t concur 9 SME Informs RM PM and RMC Rep of result 10 RM PM If Then Seek assistance of RMC Rep, RM PM, Line Manager, go to Step 5 No C31 changes Proceed with Step 11 C31 change recommended Submit formal request to BSO-UCOP- Lab Contract Mod process 11 SME Completes final RM Case package per RM Process, including Record of Decision. Gives to RMC Rep or RM PM 12 RM PM or RMC Rep Complete upload of information into RMS database 7. References 7. 1 Source Requirements Documents Requirement ID Title Requirements Management Policy Document Management Policy Requirements Management Process Description Contract Deliverables Management Process 7. 2 Related Implementing Documents (including procedures, forms, training) Document Number Title Procedure - Analyzing Requirements and Determining Significance Rating from Impact and Risk Analysis Form - Analyzing Requirements Form Significance Rating Form - Record of Decision 8. Contact requirementsmgmt@lbl.gov Requirements Management Program Manager Office of Contractor Assurance 9. Revision History Date Revision By whom Revision Description Sections affected 8/1/ L. Young Review to release. Add #s to diagram Diagram 3/22/ L.Young Initial Amend dwg Page 5 of 5 Printed or electronically transmitted copies are t official. Users are responsible for working with the latest approved revision.
Process Description: Managing Institutional Documents
Number: 10.06.001.001 Revision 1.0 Publication Date: 8/9/2014 Next Review Date: 8/9/2017 Process Description: Managing Institutional Documents 1. Purpose This document describes the process for managing
More informationState of California Department of Transportation. Transportation System Data Business Plan
DRAFT Page i State of California Department of Transportation Transportation System Data Business Plan RFO# TSI DPA-0003 September 29, 2011 DRAFT Page ii Table of Contents Executive Summary... 4 Chapter
More informationOE PROJECT CHARTER Business Process Management System Implementation
PROJECT NAME: PREPARED BY: DATE (MM/DD/YYYY): Andrea Lambert, Senior Business Process Consultant, OE Program Office 09/15/2014 PROJECT CHARTER VERSION HISTORY VERSION DATE COMMENTS (DRAFT, SIGNED, REVISED
More informationVoice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview
Voice Over IP Network Solution Design, Testing, Integration and Implementation Program Overview 1/1 Table of Contents 1. Introduction...3 2. Executive Summary...4 3. Program Definition...5 3.1. Program
More informationChange Management Procedure For Increase Bandwidth to University Buildings Project
Change Management Procedure For Increase Bandwidth to University Buildings Project Version number 1.0 Draft as of 4/11/2011 Printed on 7/1/2011 Author William M. Jones Owner William M. Jones Change Management
More informationDESIGNING OUR FUTURE
MIDDLE STATES ASSOCIATION OF COLLEGES AND SCHOOLS COMMISSIONS ON ELEMENTARY AND SECONDARY SCHOOLS An Introduction to DESIGNING OUR FUTURE A Protocol for Self Study and Accreditation 3624 Market Street
More informationInformation Technology Governance Overview and Charter
Information Technology Governance Overview and Charter Prepared by: Project #: Date submitted Document version: IT Governance Charter v03.05.2012 1.0 48.0 - Page 1 of 34 Document History Version Date Author
More informationNUMBER 107-004-030 PO EFFECTIVE DATE. July 1, 2015 REFERENCE/AUTHORITY. Procedure: 107-004-030 PR APPROVED SIGNATURE
STATEWIDE POLICY DIVISION NUMBER 107-004-030 PO EFFECTIVE DATE July 1, 2015 REFERENCE/AUTHORITY SUPERSEDES Policy #107-004-030 Feb. 1, 2004 PAGE NUMBER Pages 1 of 7 Chief Information Office POLICY OWNER
More informationSpecial Permits Program Desk Guide
Special Permits Program Desk Guide Version 2.2 March 2016 Approvals Program Standard Operating Procedures Version 1.0 i Disclaimer The materials contained in this document consist of guidance and other
More informationCourse Objectives: COR 206 - Contracting Officer's Representatives in a Contingency Environment
Course Objectives: COR 206 - Contracting Officer's Representatives in a Contingency Environment (course Learning/Performance Objectives followed by enabling learning objectives) 1. Recognize the duties,
More informationLOBLAW COMPANIES LIMITED MANDATE OF THE BOARD OF DIRECTORS
LOBLAW COMPANIES LIMITED MANDATE OF THE BOARD OF DIRECTORS LOBLAW COMPANIES LIMITED MANDATE OF THE BOARD OF DIRECTORS 1. ROLE The role of the Board is to provide governance and stewardship to the Corporation.
More informationCOMPENSATION AND CORPORATE GOVERNANCE COMMITTEE CHARTER
Name COMPENSATION AND CORPORATE GOVERNANCE COMMITTEE CHARTER There shall be a committee of the Board of Directors (the "Board") of Aurcana Corporation (the "Company") known as the Governance and Compensation
More informationInfrastructure Information Security Assurance (ISA) Process
Infrastructure Information Security Assurance (ISA) Process Handbook AS-805-B March 2005 Transmittal Letter A. Explanation. As part of the Postal Service s efforts to enhance security across all technology
More informationATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES
1. ROLE DEFINITIONS ATTACHMENT 3 SPS PROJECT SENIOR PROGRAM MANAGER (SPM) DUTIES & RESPONSIBILITIES The purpose of this section is to distinguish among the roles interacting with the SPM obtained through
More informationAUDIT OF THE MILLENNIUM CHALLENGE CORPORATION S CONTRACT MANAGEMENT PROCESS
OFFICE OF INSPECTOR GENERAL AUDIT OF THE MILLENNIUM CHALLENGE CORPORATION S CONTRACT MANAGEMENT PROCESS AUDIT REPORT NO. M-000-12-006-P September 18, 2012 WASHINGTON, D.C. Office of Inspector General September
More informationProject Team Roles Adapted for PAAMCO
Project Team Roles Adapted for PAAMCO Project Roles, Authority & Responsibilities Role a defined funciton assumed by or assigned to a person in the project Authority the right to apply project resources,
More informationQUALITY MANAGEMENT PROCESS
QUALITY MANAGEMENT PROCESS The Quality Management Program s Process for Quality Assurance This Quality Management Process has been issued by authority of the CEO of Kforce Government Solutions, Inc. (KGS)
More informationManag. Roles. Novemb. ber 20122
Information Technology Manag gement Framework Roles and Respo onsibilities Version 1.2 Novemb ber 20122 ITM Roles and Version History Version ed By Revision Date Approved By Approval Date Description of
More information- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021
- ATTACHMENT - PROGRAM MANAGER DUTIES & RESPONSIBILITIES MARYLAND STATE POLICE W00B0400021 About this document this is a detailed description of typical Project Manager (PM) duties, responsibilities, and
More informationUNITED STATES DEPARTMENT OF THE INTERIOR BUREAU OF LAND MANAGEMENT MANUAL TRANSMITTAL SHEET. 1283 Data Administration and Management (Public)
Form 1221-2 (June 1969) Subject UNITED STATES DEPARTMENT OF THE INTERIOR BUREAU OF LAND MANAGEMENT MANUAL TRANSMITTAL SHEET 1283 Data Administration and Management (Public) Release 1-1742 Date 7/10/2012
More informationSumitomo Forestry Basic Policy on Corporate Governance
(Translation) Sumitomo Forestry Basic Policy on Corporate Governance Chapter 1. Article 1. General Provisions (Basic Philosophy on Corporate Governance) Sumitomo Forestry Co., Ltd. (the Company ) seeks
More informationAppendix A - Charter of the Academic and Student Affairs Committee
ATTACHMENT 2 Appendix A - Charter of the Academic and Student Affairs Committee A. Purpose. The Academic and Student Affairs Committee shall be well informed about, provide strategic direction and oversight,
More informationTechnology Delivery Co Ordinator
Technology Delivery Co Ordinator Information Package Full Time Technology Delivery Co Ordinator (IT Project & Service Desk Co Ordinator) The Sydney Anglican Schools Corporation caters for the academic,
More informationThe Monitoring Visit. Denise Owensby, CCRP Sr. Clinical Research Coordinator Clinical & Translational Science Center University of California, Davis
The Monitoring Visit Denise Owensby, CCRP Sr. Clinical Research Coordinator Clinical & Translational Science Center University of California, Davis Disclosure The information herein is not intended to
More informationBrookhaven Site Office Environment, Safety & Health Management Plan. January 2013
Brookhaven Site Office Environment, Safety & Health Management Plan January 2013 Brookhaven Site Office (BHSO) Environment, Safety & Health Management Plan January 2013 Prepared by: Signature and Date
More informationITIL Roles Descriptions
ITIL Roles s Role Process Liaison Incident Analyst Operations Assurance Analyst Infrastructure Solution Architect Problem Manager Problem Owner Change Manager Change Owner CAB Member Release Analyst Test
More informationITSM Roles. 1.0 Overview
ITSM Roles 1.0 Overview The IT Management lifecycle involves a large number of roles, some of which are limited in scope to one specific, others of which have responsibilities in several different es.
More informationPROCEDURE. The permission rights assigned to allow data custodians to view, copy, enter, download, update or query data.
Section: Subject: Administration (AD) Data Governance AD.3.3.1 DATA GOVERNANCE PROCEDURE Legislation: Alberta Evidence Act, RSA 2000, c.a-18; Electronic Transactions Act, SA 2001, c.e- 5.5; Freedom of
More information11. Extension Potential Financial Benefits
11. Extension Potential Financial Benefits Estimating the financial value of using electronic health records (EHR) for clinical research is fraught with difficulties for a number of reasons, some of which
More informationD. Student and Academic. Academic Scheduling and Timetabling
OLDS COLLEGE POLICY Olds College recognizes the need for Policies and Procedures, and the need for staff and students to be familiar with and follow such policies and procedures. It is the intent of Olds
More informationHow To Qualify For A Technical Qualification Program
u.s. DEPART ENT of Office of ENERGY I Science Integrated Support Center Chicago Office Technical Qualification Program Description ~~~~~~'? H(.k:1/Zi.':"r'fl. ; ;!. /; h tj/ tl oxanne E. Purucker, M anager
More informationAppendices to Practice Guide to Project Management for IT Projects under an Outsourced Environment
Appendices to Practice Guide to Project Management for IT Projects under an Outsourced Environment [S19a] Version 2.1 March 2011 COPYRIGHT NOTICE 2011 by the Government of the Hong Kong Special Administrative
More informationInstitutional Data Governance Policy
Institutional Data Governance Policy Vanderbilt University and Medical Center Effective Date: 07/09/2014 Revision Date: N/A DOCUMENT CONTROL Document Title Institutional Data Governance Policy Summary:
More informationFacilities Division Integrated Safety Management Plan March 16, 2006
Facilities Division Integrated Safety Management Plan March 16, 2006 Contents Facilities Division Introduction 1.0 Integrated safety Management 2.0 Accountability 3.0 Satellite Accumulation Area 4.0 Facilities
More informationHow To Develop An Enterprise Architecture
OSI Solution Architecture Framework Enterprise Service Center April 2008 California Health and Human Services Agency Revision History REVISION HISTORY REVISION/WORKSITE # DATE OF RELEASE OWNER SUMMARY
More informationTABLE OF CONTENTS Licensure and Accreditation of Institutions and Programs of Higher Learning ARTICLE ONE Policies and Procedures
Board of Governors for Higher Education Sec. 10a-34 page 1 (12-96) TABLE OF CONTENTS Licensure and Accreditation of Institutions and Programs of Higher Learning ARTICLE ONE Policies and Procedures Introduction....
More informationCorporate Compliance and Ethics Program Effective as adopted on February 21, 2012
Corporate Compliance and Ethics Program Effective as adopted on February 21, 2012 Page 1 of 7 SECTION 1. STATEMENT OF INTENT As a specialty pharmaceutical company and diagnostic laboratory, Prometheus
More informationUNIVERSITY OF GUELPH PROJECT MANAGEMENT FRAMEWORK
UNIVERSITY OF GUELPH PROJECT MANAGEMENT FRAMEWORK Table of Contents Document Purpose:... 3 What is a Project?... 3 What is not a Project? (e.g. Operational Tasks)... 3 What is Project Management?... 4
More informationNC SBI QUALITY ASSURANCE PROGRAM
NC SBI QUALITY ASSURANCE PROGRAM for the SBI Reviewed by: Deputy Assistant Director Bill Weis Date: Approved by: Assistant Director Jerry Richardson Date: Originating Unit: SBI Effective Date: July 25,
More informationEffort Reporting Certifying Effort on Sponsored Projects
University of California, Berkeley Policy Issued: October 1, 2012 Effective Date: January 1, 2014 Supersedes: Effort Reporting Certifying Effort on Sponsored Projects, Issued September 1, 2009 Next Review
More informationCHARTER. Interagency Information Systems Working Group. Timber Regulation and Forest Restoration Program June 23, 2015
Mission and Background CHARTER Interagency Information Systems Working Group Timber Regulation and Forest Restoration Program June 23, 2015 The Mission of the Interagency Information Systems (IIS) Working
More informationNATIONAL ASSOCIATION OF SOCIAL WORKERS
NATIONAL ASSOCIATION OF SOCIAL WORKERS National Association of Social Workers Gary Bailey, MSW NASW President (2003 2005) Prepared by Continuing Education (CE) Committee Sheryl Brissett-Chapman, EdD,
More information4.0 Receiving Process
4.0 Receiving Process Delivery of requested products or services marks a transition in the Purchase-to-Pay process from a purchasing activity to a payables activity. All purchases must be received to release
More informationEXECUTIVE DEAN, INSTRUCTIONAL SERVICES
EXECUTIVE DEAN, INSTRUCTIONAL SERVICES Board Approved November 12, 2014 FLSA: EXEMPT DEFINITION Under administrative direction of the Vice President of Instruction, plans, organizes, controls, and provides
More informationThe Bureau of the Fiscal Service. Privacy Impact Assessment
The Bureau of the Fiscal Service Privacy Impact Assessment The mission of the Bureau of the Fiscal Service (Fiscal Service) is to promote the financial integrity and operational efficiency of the federal
More informationRegulations for Licensure and Accreditation of Institutions and Programs of Higher Learning
Note: These regulations are in effect while being revised to comply with Public Act 13-118. All references to the Board of Governors for Higher Education, Department of Higher Education and Commissioner
More informationCHAPTER 5 QUALITY CONTROL AND QUALITY ASSURANCE
Bridge Inspection Handbook 5-1 CHAPTER 5 QUALITY CONTROL AND QUALITY ASSURANCE 5.1 QUALITY CONTROL and QUALITY ASSURANCE are integrated into all aspects of bridge inspection. They contain the essential
More informationService Level Policy. San Diego Geographic Information Source. City and County of San Diego. by and between. and. Version 1.1 Revised January 12, 2011
Service Level Policy by and between San Diego Geographic Information Source and City and County of San Diego Version 1.1 Revised January 12, 2011 TABLE OF CONTENTS REVISION HISTORY... 3 INTRODUCTION...
More informationALLINA HOSPITALS & CLINICS System-wide Policy
ALLINA HOSPITALS & CLINICS System-wide Policy Department: Allina Hospitals & Clinics Corporate Compliance Privacy & Security Compliance Page: 1 of 6 Approved by: Ethics & Compliance Oversight Committee
More informationCorporate Governance for Raising Corporate Value
A Message from the Chairman Corporate Governance for Raising Corporate Value Teruo Asada Chairman of the Board In accordance with its Company Creed of Fairness, Innovation and Harmony, the Marubeni Group
More informationWriting Performance Objectives for Job Components: A Brief Tutorial
Writing Performance Objectives for Job Components: A Brief Tutorial Under the State of Missouri s PERforM employee appraisal system, each employee must have at least one (1) performance objective for each
More informationHarmonized Use Case for Electronic Health Records (Laboratory Result Reporting) March 19, 2006
Harmonized Use Case for Electronic Health Records (Laboratory Result Reporting) March 19, 2006 Office of the National Coordinator for Health Information Technology (ONC) Table of Contents American Health
More informationInformation Technology Project Oversight Framework
i This Page Intentionally Left Blank i Table of Contents SECTION 1: INTRODUCTION AND OVERVIEW...1 SECTION 2: PROJECT CLASSIFICATION FOR OVERSIGHT...7 SECTION 3: DEPARTMENT PROJECT MANAGEMENT REQUIREMENTS...11
More information1.0 Purpose. 2.0 Roles and Responsibilities. Management System Description: Project Management. Management System Owner: Lorie Howard
Management System Description: Project Management Management System Owner: Lorie Howard Point of Contact: Lorie Howard EMCBC Home Page Issue Date: Revision: 1 1.0 Purpose The purpose of the Office of Environmental
More informationFIPS 201 Evaluation Program Development - Configuration Management Plan
FIPS 201 Evaluation Program Development - Configuration Management Plan Version 1.0.0 February 28, 2006 Document History Status Version Date Comment Audience Draft 0.0.1 02/01/06 Document creation. Limited
More informationQuality Management Plan
Quality Management Plan 6666 West Quincy Avenue Denver, Colorado 80235-3098 Telephone (303) 347-6100 September 1, 2011 CONTENTS Page APPROVALS ACRONYMS AND ABBREVIATIONS ii vi 1 INTRODUCTION 1 2 FOUNDATION
More informationFederal Acquisition Certification for Contracting Officer s Representatives (FAC-COR) Handbook
DEPARTMENT OF HEALTH AND HUMAN SERVICES Federal Acquisition Certification for Contracting Officer s Representatives (FAC-COR) Handbook Issued by the Office of the Secretary Office of the Assistant Secretary
More informationINTERNAL SERVICES GROUP PMO
Ownership & Awareness Program 1 Program 3 Program 4 Program 5 Program 6 Program 7 Program 2 Cap ability Development Infra structure Program n INTERNAL SERVICES GROUP ESSENTIAL FUNCTIONS Act as an interface
More informationSample Quality Management Plan
This reference documents project-specific quality assurance and quality control procedures appropriate to the size, complexity, and nature of the project. Quality improvements are also documented and may
More informationProject Governance Plan Next Generation 9-1-1 Project Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1)
Oregon Military Department, Office of Emergency Management, 9-1-1 Program (The OEM 9-1-1) Date: October 1, 2014 Version: 3.1 DOCUMENT REVISION HISTORY Version Date Changes Updated By 0.1 02/13/014 Initial
More informationJob Description. Business Improvement and Support Manager
Job Description Job Title: Band: Reports to: Accountable to: Location: Scanning Centre Team Leader 5 ( 21,388-27,901 per annum) Business Improvement and Support Manager Chief Executive Applicants should
More informationUC Risk Management Workgroup Requirements. University of California Risk Management Workgroup Requirements
University of California Risk Management Workgroup Requirements July 2007 Overview Risk Management Offices at UC Campuses, Medical Centers, Office of the President, and Agriculture and Natural Resources
More informationDEALERSHIP IDENTITY THEFT RED FLAGS AND NOTICES OF ADDRESS DISCREPANCY POLICY
DEALERSHIP IDENTITY THEFT RED FLAGS AND NOTICES OF ADDRESS DISCREPANCY POLICY This Plan we adopted by member, partner, etc.) on Our Program Coordinator (date). (Board of Directors, owner, We have appointed
More informationIBM Implementation Services for Power Systems IBM Systems Director
Sample Statement of Work for Services This an example and your Statement of Work may vary given your specific requirements and the related IBM engagement. IBM Implementation Services for Power Systems
More informationProject Management Office (PMO) Charter
Project Management Office (PMO) Charter Information & Communication Technologies 10 January 2008 Information & Communication Technologies Enterprise Application DISCLAIMER Services Project Management Office
More information5 FAM 630 DATA MANAGEMENT POLICY
5 FAM 630 DATA MANAGEMENT POLICY (Office of Origin: IRM/BMP/OCA/GPC) 5 FAM 631 GENERAL POLICIES a. Data management incorporates the full spectrum of activities involved in handling data, including its
More information<project name> COMMUNICATIONS PLAN
COMMUNICATIONS PLAN Version [n.n Month Day, Year] Project Sponsor: [Name of Business Sponsor] Project Manager: [Name of Project Manager] Project Number: [Number Assigned to the Project] Document History
More informationIMATS - SAMS User Registration Webinar
Secure Access Management Services (SAMS) Electronic Authentication Process for the Inventory Management and Tracking System (IMATS) IMATS - SAMS User Registration Webinar Objective To provide information
More informationDIVISION OF INFORMATION SECURITY (DIS) Information Security Policy IT Risk Strategy V0.1 April 21, 2014
DIVISION OF INFORMATION SECURITY (DIS) Information Security Policy IT Risk Strategy V0.1 April 21, 2014 Revision History Update this table every time a new edition of the document is published Date Authored
More informationTable of Contents. 1. Purpose/Policy
Responsible Office/Division Title: Regulatory Authority Council and Lead Project Managers -Authorities, Responsibilities, Page 1 of 10 Version Date: Effective Date: 2013-08-01 2012-12-10 Project Manager:
More informationWhitepaper Data Governance Roadmap for IT Executives Valeh Nazemoff
Whitepaper Data Governance Roadmap for IT Executives Valeh Nazemoff The Challenge IT Executives are challenged with issues around data, compliancy, regulation and making confident decisions on their business
More informationCONTENTS. University of California Regents Policy 7706 Reemployment of UC Retired Employees Into Senior Management Group and Staff Positions
Reemployment of UC Retired Employees Into Senior Management Group and Staff Positions Approved September 18, 2008 Amended February 9, 2009 and September 18, 2013 Responsible Officer: Vice President Human
More informationSolutions Master Data Governance Model and Mechanism
www.pwc.com Solutions Master Data Governance Model and Mechanism Executive summary Organizations worldwide are rapidly adopting various Master Data Management (MDM) solutions to address and overcome business
More informationCalifornia State University, Sacramento INFORMATION SECURITY PROGRAM
California State University, Sacramento INFORMATION SECURITY PROGRAM 1 I. Preamble... 3 II. Scope... 3 III. Definitions... 4 IV. Roles and Responsibilities... 5 A. Vice President for Academic Affairs...
More informationProject Zeus. Risk Management Plan
Project Zeus Risk Management Plan 1 Baselined: 5/7/1998 Last Modified: N/A Owner: David Jones/Zeus Project Manager Page Section 1. Introduction 3 1.1 Assumptions, Constraints, and Policies 3 1.2 Related
More informationHow the Information Governance Reference Model (IGRM) Complements ARMA International s Generally Accepted Recordkeeping Principles (GARP )
The Electronic Discovery Reference Model (EDRM) How the Information Governance Reference Model (IGRM) Complements ARMA International s Generally Accepted Recordkeeping Principles (GARP ) December 2011
More informationLGS Project Management Methodology
Page: 32 LGS Project Management Methodoy The LGS project management methodoy is integral to our overall delivery methodoy. Based on inpro, one of the LGS inspiration series documents, our methodoy is compliant
More informationCopyright 2014 Carnegie Mellon University The Cyber Resilience Review is based on the Cyber Resilience Evaluation Method and the CERT Resilience
Copyright 2014 Carnegie Mellon University The Cyber Resilience Review is based on the Cyber Resilience Evaluation Method and the CERT Resilience Management Model (CERT-RMM), both developed at Carnegie
More informationBusiness Analyst Position Description
Analyst Position Description September 4, 2015 Analysis Position Description September 4, 2015 Page i Table of Contents General Characteristics... 1 Career Path... 2 Explanation of Proficiency Level Definitions...
More informationIntellectual Property Guidelines at Queen s University. (Prepared by the School of Graduate Studies, revised August, 2013)
Intellectual Property Guidelines at Queen s University (Prepared by the School of Graduate Studies, revised August, 2013) Intellectual Property Guidelines at Queen s University Dear Graduate Students,
More informationThis directive applies to all DHS organizational elements with access to information designated Sensitive Compartmented Information.
Department of Homeland Security Management Directives System MD Number: 11043 Issue Date: 09/17/2004 SENSITIVE COMPARTMENTED INFORMATION PROGRAM MANAGEMENT I. Purpose This directive establishes Department
More informationCompliance and Ethics Program Structure
Compliance and Ethics Program Structure The University of Texas at Austin COMPLIANCE AND ETHICS PROGRAM CHARTER Purpose The purpose of the University of Texas at Austin ( University ) Compliance and Ethics
More informationData Conversion Best Practices
WHITE PAPER Data Conversion Best Practices Thomas Maher and Laura Bloemer Senior Healthcare Consultants Hayes Management WHITE PAPER: Data Conversion Best Practices Background Many healthcare organizations
More informationPrivacy Impact Assessment (PIA) for the. Certification & Accreditation (C&A) Web (SBU)
Privacy Impact Assessment (PIA) for the Cyber Security Assessment and Management (CSAM) Certification & Accreditation (C&A) Web (SBU) Department of Justice Information Technology Security Staff (ITSS)
More informationFacilities Portfolio Management Tool
2016 Facilities Portfolio Management Tool Project Charter Budget- Facilities Oversight Office of Financial Management 4/10/2016 CONTENTS Overview... 2 Purpose Statement... 2 Background... 2 Goals & Objectives...
More informationVendor Orientation Guide
Vendor Orientation Guide Presentation to: Department of Community Health s Contract and Grant Vendors Presented by: Office of Vendor Management Date: September 2014 0 Mission The Georgia Department of
More informationSTANDARD OPERATING PROCEDURE NO. CM.13-00 - 00
STANDARD OPERATING PROCEDURE NO. CM.13-00 - 00 Version date: Effective Date: Replaces SOP No.: 1 5 January 20 13 15 February 20 13 Approved by: Date No: CM.13 00 00 Effective Date: 15 February 2013 Version
More informationINTERNATIONAL STANDARD ON AUDITING 260 COMMUNICATION WITH THOSE CHARGED WITH GOVERNANCE CONTENTS
INTERNATIONAL STANDARD ON AUDITING 260 COMMUNICATION WITH THOSE CHARGED WITH GOVERNANCE (Effective for audits of financial statements for periods beginning on or after December 15, 2009) CONTENTS Paragraph
More informationStandard Operating Procedure
Standard Operating Procedure IT System Certification & Accreditation Process For Effective Date: 20080707 Expiration Date: 20110707 Responsible Office: Office of the Chief Information Officer Document
More informationUniversity of California Regents Policy 7702 Senior Management Group Performance Management Review Process
Senior Management Group Performance Management Review Process Approved July 17, 2008 Amended September 16, 2010 and March 29, 2012 Responsible Officer: Vice President Human Resources Responsible Office:
More informationSECTION 504/ADA PROHIBITION AGAINST DISCRIMINATION BASED ON DISABILITY
COUNTY SCHOOLS 2260.01/page 1 of 9 REVISED POLICY - VOL. 8, NO. 1 SECTION 504/ADA PROHIBITION AGAINST DISCRIMINATION BASED ON DISABILITY Pursuant to Section 504 of the Rehabilitation Act of 1973 ( Section
More informationGoverning Boards: Middle States Commission on Higher Education
Governing Boards: Understanding the Expectations of the Middle States Commission on Higher Education Middle States Commission on Higher Education Governing Boards: Understanding the Expectations of the
More informationBPA Policy 482-1 Contract Lifecycle Management
B O N N E V I L L E P O W E R A D M I N I S T R A T I O N -1 Contract Lifecycle Management Customer Contracting Table of Contents 482-1.1 Purpose & Background... 2 482-1.2 Policy Owner... 2 482-1.3 Applicability...
More informationBoard Approved March 25, 2015 FLSA: EXEMPT DEAN, DISABLED STUDENT PROGRAMS & SERVICES
Board Approved March 25, 2015 FLSA: EXEMPT DEAN, DISABLED STUDENT PROGRAMS & SERVICES DEFINITION Under administrative direction, plans, organizes, manages, and provides administrative direction and oversight
More informationMedicare Program Integrity Manual
Medicare Program Integrity Manual Chapter 11 - Fiscal Administration Transmittals for Chapter 11 Table of Contents (Rev. 220, 08-24-07) 11.1 - Medical Review (MR) 11.1.1 - MR Overview 11.1.2 - Reporting
More informationPolicy on the Security of Informational Assets
Policy on the Security of Informational Assets Policy on the Security of Informational Assets 1 1. Context Canam Group Inc. recognizes that it depends on a certain number of strategic information resources
More informationStandard Monitoring Procedures
Standard Monitoring Procedures GEO Certified Club and Course Management Golf Environment Organization 2 Quality Street North Berwick Scotland EH39 4HW T: +44 (0) 1620 895100 W: golfenvironment.org Reference:
More informationMU2E PROCUREMENT MANAGEMENT PLAN
MU2E PROCUREMENT MANAGEMENT PLAN Version 1.1 June 29, 2012 Mu2e-doc-xxx Approved By: R. Ray date Mu2e Project Manager J. Collins date Fermilab Procurement Department Head G. Bock date Fermilab Associate
More information702 IT/Technology Service Help Desk and Incident Management
702 IT/Technology Service Help Desk and Incident Management This sub-discipline is about the competencies required to manage the contacts made by customers of IT/technology systems, services and assets,
More information