Network Demand and Customer Connections Forecasting Procedure Power Networks

Size: px
Start display at page:

Download "Network Demand and Customer Connections Forecasting Procedure Power Networks"

Transcription

1 Network Demand and Customer Connections Forecasting Procedure Power Networks 1 Forecast Purpose Forecast Scope Reference Characteristics of a robust forecasting process Forecast improvement Forecast documentation Forecast reconciliation Outline of demand forecast process Demand forecast overview Outline of customer connections forecast process Customer connections forecast overview Timing and change control Information requirements Load forecast timing Network forecasting data repository Load Log Regional forecast Spatial demand forecast processes High Voltage feeder forecast Determine the real load history Extract non growth related load changes Project future base demand from the historical data Forecast demand growth Feeder forecast calculations Zone substation forecast Determine the real load history Extract non growth related demand changes Weather correction of demand data Project future base demand from the historical data Forecast demand growth...16 Approved by: Prepared by: Issue Date: June 2013 Status: Approved Paul Ascione Group Manager Strategy and Planning Jim McKay Manager Network Development and Planning File No: F2012/ Version: 3.0

2 8.2.6 Zone substation forecast calculations Transmission system demand forecast Customer connections forecast Forecast reconciliation Forecast distribution Further Information Appendix 1 Demand Forecasting Document Use and Process Flow Attachment 1 Weather correction A1.1 Weather variables...28 A1.2 Demand data exclusions...28 A1.3 Statistical correlation between demand and weather...29 A1.4 Process to correct historical demand data for daily maximum temperature...30 Attachment 2 Diversity of demand... 32

3 1 Forecast Purpose The network demand and customer connections forecasts underpin Power and Water Network s capital and operating expenditure programs, by highlighting where network constraints are expected to emerge. 2 Forecast Scope The overall objective of the network forecasting process is to develop the projections of peak demand and customer connections shown in Table 1. Table 1 Network demand and customer connections forecasting requirements Forecast Period Purpose Region 10* years Overall demand, based on economic considerations, for comparison with corporate forecasts and lower level forecasts. Transmission substations (132/66 kv), transmission connected customers and generators To plan the development of the transmission network and existing and new transmission connected substations. Zone substations (132 or 66/22 or 11 kv) High Voltage feeders (22 or 11 kv) Customer connections (all voltages) *Current year plus. ie = * years To plan the development of the subtransmission network and existing and new subtransmission connected zone substations. To plan the development of the High Voltage network. The primary demand forecasts above form the basis of other forecasts used for planning at different levels within the network and for reconciliation with the Corporate Regional forecasts. The customer connections forecast is reconciled with the tariff forecast used for estimating network revenue. 3 Reference This document should be read in conjunction with the Power and Water Network Technical Code and Network Planning Criteria. 4 Characteristics of a robust forecasting process An adequate, soundly based approach robust forecasting process should embody the following characteristics: Secure and reliable data collection and storage, to ensure the integrity of the base data from which the forecast is prepared; Identification of the exogenous drivers of electricity consumption and demand; A forecast modelling process which will provide consistent and repeatable results, which accommodates all of the material drivers of consumption or demand and has a level of sectoral breakdown consistent with the identified drivers;

4 Quantification of the historic relationship between the identified exogenous drivers and corresponding changes in electricity consumption and demand; Statement of the means by which the exogenous drivers will be calculated or estimated to produce the forecast; Where there can be a degree of judgement in determining factors influencing consumption or demand, definition of the factors to be considered in making that judgement; Production of electricity forecasts by inputting projections of those exogenous drivers into forecast models; Ongoing monitoring and review of the forecasts against outcomes, with the view to process improvement; A level of documentation sufficient to be used by staff as a work instruction and by third parties to review the appropriateness of the processes; and Appropriate governance and approval processes on key input assumptions, process and outputs. The network peak demand forecasting process employed by Power and Water Networks is very similar to that employed by other Australian distributors. The process makes use of the available relevant data and has been logically structured and documented. This written procedure has been designed to ensure the quality and repeatability of forecast outcomes. The network peak demand forecasting process is therefore an appropriate basis from which to construct capital and operating cost forecasts, which reasonably reflect a realistic expectation of the requirement to meet or manage demand growth on the network. 4.1 Forecast improvement An understanding of the factors driving peak network demand and the duration of that demand is the key to improving the forecast process so that emerging constraints can be better anticipated and managed, using network and non-network approaches. In most cases, these drivers will have been anticipated and will fall within expected bounds. Where peak demand growth falls outside expected bounds (eg. if the growth rate were to differ by more than a few percent from recent trends) or appears to be the result of a change in drivers, special investigations shall be undertaken as part of the forecast process, and the factors deemed to be driving peak demand growth determined. The objective is to improve the forecast accuracy by identifying the main drivers of peak demand, any changes in these drivers and the factors behind those changes, and the specific level of growth expected, either at an overall or local level. 4.2 Forecast documentation The forecast process is to be accompanied by documentation sufficient to ensure the forecast is repeatable and able to withstand external and regulatory scrutiny. This includes the documentation of any associated investigations on peak demand drivers in section Forecast reconciliation The network demand forecast shall be reconciled as described in section 10 to demonstrate its internal consistency. It shall also be reconciled with the Regional Corporate level forecasts through the application of suitable diversity factors to lower level inputs.

5 4.4 Outline of demand forecast process The formal reporting of forecasts is made at four levels: The Regional level, for comparison with Corporate and lower level forecasts; The transmission level, for the planning of the transmission network; The Zone substation level for the planning of substation capacity; and For High Voltage feeders, to plan their capacity. The latter two of these forecasts are normally termed spatial demand forecasts. The forecasting process is illustrated in overview form in Figure 1 and described below. Figure 1 Network Demand forecast process Demand forecast overview The forecasting process comprises the following basic steps: 1. Collate and update input information; 2. Determine the real load history; 3. Extract non growth related loads; 4. Correct for weather conditions if required and extrapolate a trend line;

6 5. Consider adjustments for changes in key drivers; 6. Add back non growth related loads; and 7. Reconcile/validate the forecast. Each of these steps is explained in detail in subsequent sections 6 to 9 of this document. 4.5 Outline of customer connections forecast process The customer connections forecast process is similar to the demand forecast process but contains a smaller number of steps. The process overview is shown in Figure 1. Figure 2 Network customer connections process Customer connections forecast overview The customer connections forecasting process contains the following steps: 1. Collate and update input information; 2. Correlate with economic drivers 3. Project historical information with regard to forecast economic trends; 4. Consider adjustments for known developments such as housing lot releases or developments; 5. Reconcile/validate the forecast.

7 5 Timing and change control The network forecasts are produced annually, after each summer or wet season peak demand period, thereby incorporating the most up-to-date information on consumption trends. The approved forecasts shall be completed by 31 August each year and available for inclusion into the Network Management Plan. These forecasts shall be used for the purpose of network analysis by planning personnel and as the basis to determine the capital and operating expenditure forecasts for Power and Water s network. During the course of the year, the forecasts may be found to be inaccurate due to events that may occur, or by calculation issues. This can have a direct impact on the current forecasts and therefore the timing of or need for proposed projects. In order for the forecasts to be changed during the course of the year, the following must occur: The Senior Manager Network Planning and Development shall be advised of the proposed change to the forecast; The proposed change must be demonstrated to be material and not adequately captured in the current forecast (which is principally derived from historical data); All affected feeder and substation forecast demands shall be assessed using the new information, to ensure a consistent result; If a new forecast is issued, all relevant staff shall be advised by of the change; and If such a change is sufficiently material to affect Regional forecasts, the Manager Network Planning and Development shall advise the General Manager Networks.

8 6 Information requirements This section details the information which shall be used in the demand forecast process. Load records: May include the following sources of data: o Half hourly records from metering used for operational purposes (termed Supervisory Control and Data Acquisition or SCADA records) at zone substations and other network locations; o interval metering records for meters installed at locations within the network; o interval metering records installed at major and minor customers premises; o from meters at minor substations which record the maximum demand at the substation; and o portable metering survey equipment used to record the demand. Spot loads: Refers to committed 1 single load increases of above 1000 kva or multiple related load increases totalling above 1000 kva. This information is gathered by the Distribution planners with input from Customer Connections and is stored in a database or Load Log against individual feeders and zone substations. Temporary switching and load transfers: Refers to planned 11 and 22 kv load transfers between HV feeders or between zone substations. The information is gathered by the Distribution and Subtransmission planners from control room records and is stored in the database against individual zone substations. Known network augmentation or reconfiguration: Refers to committed projects that will impact on the capacity of a feeder or zone substation to supply the associated load area, such as new zone substations, additional zone substation transformers, upgraded switchgear or feeders etc. This information is gathered from plans prepared by Distribution or Subtransmission planners. These events may be reflected in existing zones as spot load increases or load transfers and are stored as above. Embedded generation and capacitors: Are identified by the Distribution or Subtransmission planners and are treated either as negative spot loads, or in the case of small generators like solar PV, as negative load growth. Other relevant information such as economic activity, air conditioner penetration, demographics of individual zones, building construction activity etc. is not quantified but considered as described in sections and below. 6.1 Load forecast timing Forecast spot loads, temporary switching or system augmentation may occur anytime throughout the year and is generally segmented by financial year. Given the purpose of this procedure is to forecast peak demand, loads that occur late in a financial year may be delayed from impacting the actual peak demand until the following financial year. As such these loads should be forecast according to when they will next impact the peak demand. 1 A committed load is one for which a connection application has been lodged with Power and Water.

9 Practically, loads that are forecast to occur in the April June quarter should be attributed to the following year s peak demand. 6.2 Network forecasting data repository The data used for spatial demand forecasting are derived from Supervisory Control and Data Acquisition (SCADA) records, and may be compared to, or supported by customer and other energy meters as necessary. Spatial demand forecasting is carried out primarily with Microsoft Excel. The electronic versions of the forecasts are stored in TRIM, Power and Water Corporation s Electronic Document Management System. 6.3 Load Log The Load Log is a MS Excel spread sheet that records all loads expected to impact the Network in the coming years. Certainty around the likelihood of these loads proceeding is generally limited to 6-12 months in advance. Typically loads that are beyond this window are less likely to proceed, or at least not in the magnitude provided by the developer or customer. In addition to the uncertainty of the load, expected maximum demands can be calculated with differing methods and, in the PWC experience, tend to be overstated. To overcome the excessive maximum demand the Load log contains a PWC estimate of the demand as is expected to be experienced from the HV feeder, after some diversification. This figure is determined based on engineering assessment and comparisons to other similar installations if possible. This is the demand figure used for the forecast (only). To adjust the number of new loads expected in the outer years of the forecast, the resulting spatial forecast will be scaled at the regional level to provide a long term trend inline with other indicators. Zone substation and feeder forecasts need not be scaled as the diversification is less and forecasts are reviewed annually.

10 7 Regional forecast Power and Water prepares regional forecasts for the three separate systems (Darwin- Katherine, Tennant Creek and Alice Springs). These forecasts moderate the growth trends in historic demand with the growth expectations of a number of economic indicators that have been demonstrated to drive changes in electricity demand. The process used to determine the regional demand forecast is as follows: Known large step changes in demand, (spot loads) such as those arising from the connection of large customers or embedded generators, are used to adjust the historical recorded demands; Historical maximum demand records are corrected to the Standard Weather Maximum Demand (SWMD), using the process described in Appendix 1; A trend line and the historical growth rate are established from the SWMD. This is used as the starting point for demand projections (ie. forecast trends are extrapolated from the SWMD rather than the recorded peak demand in the most recent summer or wet season); The projection of regional demand is made after the consideration of economic indicators that may include, but are not limited to, the following: o o o o o o o The historical Northern Territory Gross State Product (GSP) and Treasury GSP projections 2, 3 ; Historical and forecast population growth; Dwelling starts; Historical network connections and connection inquiries; Trends in major appliance penetration and consumption patterns; Trends in energy conservation; and The outcomes of any customer surveys and load research. 2 3 The correspondence between the historical growth of the Darwin-Katherine system and the GSP is 90%. The annual variation in GSP may be used to construct high and low forecast scenarios.

11 The outcome of this process is the regional demand forecast. As an indication of the required outcome, the forecast for is shown in Figure 1. This forecast is normally extrapolated for a period of 10 years. Although the difference is very small, for this forecasting procedure percentage growth rates are determined arithmetically, rather than geometrically. Figure 3 Indicative regional forecast for Darwin Katherine 360 Maximum demand, MW Raw MD Temp corrected MD temp corrected trend Historical trend 2.51% P10 Forecast trend 2.75% High 3.25% Low 2.25% Financial year ending

12 8 Spatial demand forecast processes Power and Water undertakes spatial demand forecasts at two separate but aligned levels of the network. These are: The High Voltage feeder forecast; and The Zone substation feeder forecast. Other forecasts are developed for the purpose of planning the development of particular sections of the network and for the subtransmission and transmission networks. These are built up from the relevant elements of the above two forecasts. 8.1 High Voltage feeder forecast The demand of each 22 kv and 11 kv feeder is forecast using the process illustrated in Figure 4. The base data for the forecast is derived from the historical SCADA records for the feeder concerned, where these are available. Alternatively, maximum demand indicators located at Zone substations may be used Figure 4 - High Voltage feeder forecast Feederload,Amps Illustra ve Rawdata Loadcorrec on Corrected 120 Trend 100 Rawprojec on Adjustedprojec on Year Figure 4 displays the forecast process, which is undertaken in year 0 for a period of five future years. The following corrections sections describe the steps involved Determine the real load history The load history for feeders is determined on the basis of each feeder s maximum demand for the summer or wet season (November to March inclusive), extracted from SCADA records or other sources of information. Corrections are made to the load history as part of the feeder forecast process, to allow for known load transfers that were in place between HV feeders at the time of the peak demand are identified from inspection of the SCADA history and confirmed from operational records. In the example, load transfers are shown in years -5 and -3;

13 8.1.2 Extract non-growth related load changes Corrections are also made to the load history, to allow for: Any known abnormal fluctuations in large customer demands at the time of peak load would be corrected; The demand would be increased to exclude medium and large scale embedded generation in service at the time of peak demand. Unless such generation is subject to a network support agreement it would potentially not be available for service. Smaller embedded generators are not separately considered but form part of the historical demand records and are thus included in the growth trends; Load which had been curtailed, potentially at the request of Power and Water Networks or a Retailer, or because of system limitations, would be estimated and added back to the historical data; and Any material known block load increase would be identified. In the example, a block load is connected in year These corrections are all made to provide the Corrected load history (red) Project future base demand from the historical data Ordinary Least-Squares (OLS) regression is then used to fit a trend line (green) to the Corrected load history. The trend is projected for the duration of the forecast period (dashed green). As with previous the regional forecast, percentage growth rates are determined arithmetically, rather than geometrically. Some modification of this process may be required for recently commissioned or rearranged feeders, where growth rates may need to be determined from the original sources of the demand Forecast demand growth In formulating the spatial forecasts, further adjustments to the demand projections at individual locations may need to be made, to accommodate the following factors: To add back any block loads excluded from the load history, in section 8.1.1; Network configuration changes, which can result in the transfer of load between locations and in changes to the proportion of demand met by individual components of the network; Planned network load transfers; Customer driven changes to historical trends (such as changes in major appliance consumption); Lot developments proposed by developers (which are reconciled against the forecast number of new customer connections); New large customer connections and demand, either committed or highly probable; and Large customer reductions or closures. 4 The block load would form part the base projection in future years, after it had been included in each year of the load history.

14 This trend line thus needs further adjustment to establish the forecast of feeder demand. In the final two stages of the example: The block load, which was excluded before establishing the trend line, is added back; and Material committed load changes (not included in the base load growth) are made. In this example, a further load is added in year 2. The outcome of this process is the Adjusted projection of HV feeder demand (in black) Feeder forecast calculations The HV feeder peak demand data and forecast calculations described in sections to are contained within a spreadsheet. Once finalised, this spreadsheet becomes a controlled document. 8.2 Zone substation forecast A similar but slightly more detailed process is followed at the next network level, in developing the zone substation forecast. The following additional steps are involved in the development of the forecast for each zone substation. This is illustrated with reference to Figure 5. Figure 5 - Zone substation forecast 1,900 1,800 1,700 Illustra ve Zonesubsta onload,amps 1,600 1,500 Rawdata Loadcorrec on 1,400 Rawcorrected 1,300 Tempcorrec on Tempcorrected 1,200 Trend 1,100 Rawprojec on Adjustedprojec on 1, Year Determine the real load history The real load history of each zone substation is determined through the following process: The peak load is monitored during the summer or wet season for a sufficient duration to ensure that the effects of both early and late weather extremes (and therefore the seasonal peak) have been captured. This is ordinarily the months of November to March, inclusive;

15 The required months of raw SCADA load data are downloaded for each zone transformer and for the diversified zone total, in order to process loads on a seasonal basis. If the (Primary side MW/MVAr) SCADA data is not available, or determined to be unsatisfactory, other metering data is requested if available; The top ten maximum demand days from this output are reviewed, and whenever an abnormality is apparent, the outputs for each transformer and each substation are scanned for gaps, step changes and signs of abnormal switching between zone substations, etc. If the abnormality is the result of switching, the load is adjusted to compensate; and The daily maximum temperature for the corresponding period and Region is obtained Extract non-growth related demand changes The process in section is followed for each zone substation, to remove the effect of abnormal loads on the historical data Weather correction of demand data An additional step applied to the zone substation demand forecast is the weather correction of the historical load data, following the removal of abnormal load and generator fluctuations. This process is described in Attachment 1. The maximum daily temperature has been found to exhibit good correlation with the maximum daily system demand on those occasions of high network demand, namely summer or wet season working weekdays. This regional level correspondence is used to temperature correct the historical spatial demand data, as follows: The maximum daily temperature is recorded for each day of maximum demand forming part of the load history; A proportionate adjustment is made to the daily demand, to obtain the SWMD (or P 50 demand), using the %/ o C correction factors of Table 2; For Zone substations that are radially supplied, a proportionate adjustment is made to the daily demand, to obtain the demand which would have occurred at the average daily maximum P 10 temperature. Again, this uses the relevant correction factor from Table 2 The temperature adjusted historical demand is used for the projections in the following section This adjustment and the normalised results are depicted in black in Figure Project future base demand from the historical data As with the feeder forecast, Ordinary Least-Squares (OLS) regression is then used to fit a trend line (green) to the Corrected load history. The trend is projected for the duration of the forecast period (dashed green). As with previous the regional forecast, percentage growth rates are determined arithmetically, rather than geometrically. Some modification of this process may also be required for recently commissioned or rearranged zone substations, where growth rates may need to be determined from the original sources of the demand.

16 8.2.5 Forecast demand growth As with the feeder demand forecast, further adjustments to the demand projections at individual locations may need to be made, to accommodate the range of factors described in Where such factors are considered to require adjustment of the trend they shall be documented. This trend line thus needs further adjustment to establish the forecast of feeder demand. In the final two stages of the example: The block load, which was excluded before establishing the trend line, is added back; and Material committed load changes (not included in the base load growth) are made. In this example, a further load is added in year 2; The outcome of this process is the Adjusted projection of HV feeder demand (in black) Zone substation forecast calculations The zone substation peak demand data and forecast calculations described in sections to are contained within a spreadsheet. Once finalised, this spreadsheet becomes a controlled document.

17 9 Transmission system demand forecast The transmission system forecast is used for the consideration of normal and contingency flows on the network and underpins proposals to develop that network. It comprises a forecast of the load and generation at each of the existing and new connection points to the transmission network. The process used to determine the transmission system forecast is as follows: Existing and known generation developments that, taken together, broadly match the regional demand forecast described in section 10 are determined; Known step changes in demand, such as those arising from the connection of new transmission customers or changes in demand for existing customers, are determined; The forecast of zone substation demands described in section 8.2 is used as the basis to determine the demand at each connection point to the transmission network. The demand of the relevant zone substations normally supplied from each transmission connection point are aggregated, with an appropriate allowance for the diversity of their demands determined from comparison of SCADA records of individual zone substation demands and the transmission connection point demand. Average Zone substations power factor are determined and applied to determine MW, MVA and MVAr values for forecasting. The methodology used for the transmission forecasting is outlined in the Transmission Planning Report 2012, Trim Ref: D2012/

18 10 Customer connections forecast At this stage the input information for the customer connections forecast is derived from the tariff service availability charge volumes. Year on year changes in the historical tariff customer numbers represent the net of customer connections and disconnections and are therefore scaled up by a factor to account for new customer connections only. As Maximo is developed, the historical information on customer connections will be drawn directly from that system. The historical information on customer numbers is compared with economic indicators (Gross State Product, Dwellings and Population) to determine the correlation between the customer numbers and these drivers. The outlook for most appropriate economic driver(s) is used to guide the forecast growth in customer connections. In 2013 a good correlation was observed between the GSP and the connections (lagged by one year). The forecast outcome reflected the outlook for GSP and is shown in Figure 7. Figure 6 Indicative network customer connections forecast The customer connections forecast is used to estimate the customer connections capex and the expected level of capital contributions.

19 11 Forecast reconciliation The four primary demand forecasts that are the subject of this Procedure are: The regional forecast; The transmission system forecast; The zone substation forecast; and The HV feeder forecast Reconciliation of these forecasts shall be carried out as described below to ensure their internal consistency and to inform Power and Water s corporate forecasts. The HV feeder forecast for the feeders emanating from each zone substation shall be reconciled with that zone substation forecast; The aggregate of the zone substation forecasts in each region shall be reconciled with the regional forecast. As the transmission system forecast is built up from the zone substation forecast, its reconciliation is not required. In order for this reconciliation to be performed at different levels of the network, the diversity of loads forming a sub-component at each level need to be considered. The process described in the Attachment 2 shall be used to determine diversity factors where necessary. The objective of this reconciliation is to allow for variations to be understood and to identify where discrepancies need to be investigated. The focus of this reconciliation should be mainly to ensure that the projected growth rates are consistent between the forecasts at different levels, rather than the comparison of the magnitude of the aggregated demands with the demand at the higher level. The analysed information shall be compiled in a spreadsheet and percentage variations used to establish where material variations exist. The customer connections forecast, when derived from Maximo, will also be reconciled with the network tariff forecasts.

20 12 Forecast distribution The demand forecast should be completed by 31 August each year. The forecast shall be distributed by the Manager Network Development and Planning as a controlled document, to the following personnel: General Manager Power Networks Group Manager Strategy & Planning General Manager Strategy and Corporate Affairs General Manager Generation

21 13 Further Information If further information is required, please contact: Manager Network Planning and Development

22 14 Appendix 1 Demand Forecasting Document Use and Process Flow 1 document per ZSS, per year Document 1 Annual ZSS and Feeder Demand Review Part 1 Raw Data Part 2 FDR MD Part 3 ZSS MD Reference Data SCADA/Loads Load Log Temperature Economic data (All documents) 1 document per ZSS, per 5 years 1 document per ZSS, per 10 years Doc. 2 5yr Feeder Forecast Demand Doc. 3 10yr ZSS Forecast Demand 1 document per region, per 10 years 1 document per region, per 10 years Doc. 5 10yr Forecast Transmission Doc. 4 10yr Regional / System Forecast Document 6 Reconciliation Deliverables, including: Economic Summary GSP, Dwellings, Population (and other as used ) Summary of Reconciliation & each regional growth rates Regional LDC and Load factors curves Regional Forecast charts (each region) Zone Substation utilisation and Summary Data (such as NMP Appendix) HV feeder utilisation Transmission Line Utilisation Transmission Line Contingency Analysis

23 General Information Requirements & Process flow: Load Log (including Transfer log) One document per year Stored in: F2011/6307 Example: D2012/ Naming: 20XX Load Log for Forecasting ALL REGIONS File contains: Load / Transfer Description Date Modified Date (Qtr) Load expected Expected kva Customer Expected kva PWC Load Forecast ZSS affected (To and From) Feeder Affected Comments Annual SCADA Data (ZSS & Feeder Loads) Download from SCADA system in a.csv file. Raw data is transferred to individual substation sheets for further analysis. Downloaded.csv file is not saved. File contains: Hourly data (Date and Time) HV feeders (AMPS) including: Capacitor Banks HV feeders (XXX) for incoming (MV) transformer System Loads One document per year Stored in: F2005/12337 Overwrite: D2012/ File contains: Hourly System loads (Date and Time) Darwin- Katherine / Alice Springs / Tennant Creek (MW) All generating sites > 1MW ie SunPower Other Data Reference Data Reference data should be referenced when used and original documents need not be saved. Other supporting information, from any reputable source, may also be considered. Data includes:

24 Daily Max temperature data Bureau of Meteorology(BOM) GSP Historical - Australian Bureau od Statistics (ABS ) GSP Forecast NT Gov. Territory Economic Review Population Growth ABS Dwelling Approvals ABS Process Working Documents: Document 1 Annual ZSS and Feeder Demand Review One document per substation per year. Stored in: F2005/12337 Example: D2013/ Naming: XXXX Zone Substation SCADA Data 20XX-20XX This is the base document for annual forecast. The document contains the raw SCADA data for feeders and incomers as downloaded from the SCADA system. This data is then analysed to determine annual maximum demand figures for the ZSS and all feeders. The data is broken into 3 general parts: Part 1 - Raw SCADA Data From SCADA download for entire substation (only). Part 2 Individual feeder MD Individual feeder data o Notes on data errors o Temp / Permanent transfers with transfer log o Spot loads with reference to load log. o Base/ adjusted data o Comments o Charted data Profile + LDC o Peak value, date and time. Summary of summated feeders for ZSS MD (if required only) o Relevant data as shown above for reconciliation. Part 3 ZSS MD (Based on Transformers) Power Transformer (secondary) incomer data o Notes on data errors o Temp / Permanent transfers with transfer log (if external) o Spot loads with reference to load log. o Base/ adjusted data o Comments o Charted data Profile + LDC o Peak value, date and time.

25 Document 2 (5 Yrly Feeder Demand Forecast) One document per ZSS per 5 years (rolling) Stored in: F2005/12337 Example: D2012/ Naming: Feeders XXXX Zone Substation 20XX Document is based on the output of annual MD figures determined from Document 1 noted above. Document contains: Individual Feeder Forecast o Raw MD data (each year) o Temp / Permanent transfers with transfer log (if external) o Spot loads with reference to load log. o Base/ adjusted data o Forecast data (incl 5yr arithmetic growth) o Charted feeder data Zone Substation - Feeder Summary o Feeder details o Feeder ratings o Alternative feeders o Feeder utilisation o ZSS max demand (undiversified) Document 3 10 yrly ZSS Demand Forecast One document per ZSS per 10 years (rolling) Stored in: F2005/12337 Example: D2012/ Naming: ZSS XXXX (location) 20XX/XX MD Forecast Document is based on the output of annual MD figures determined from Document 1 noted above. Document contains: Zone substation Forecast o Raw MD data (each year) o Temp / Permanent transfers with transfer log (if external) o Spot loads and comments with reference to load log. o Base/ adjusted data o ZSS Max MD with date, date and daily max temperature. o ZSS Temperature corrected MD o ZSS Temperature corrected Forecast data (incl 10yr arithmetic growth) o Charted data

26 Document 4 System/Region Demand Forecast One document per region per year Stored in: F2012/4829 Example: D2012/ Naming: 20XX Network Demand Forecasting Data XX( region) Load analysis Document is based on system loads and other reference material. Document contains: Regional Spatial Forecast o Raw System MD data o System Max MD with date, date and daily max temperature. o System Temperature corrected MD o System Temperature corrected Forecast data (incl 5yr arithmetic growth) o Charted data LDC and Load Factor* *Due to the MB size the calculation of LDC is in separate sheets see D2012/ Regional economic forecast o GSP forecast o Dwellings forecast o Population forecast o Corporate Sales / energy forecast data if available. Document 5 Transmission One document per year Stored in: F2005/12337 Example:D2012/ Naming: Transmission Utilisation from 20XX to 20XX Document is based on the reconciled, diversified ZSS loads as determine in Document 5. This information is modelled to determine transmission loads under normal and contingency conditions. Document contains: Transmission Line Ratings (normal & contingency) Line Maximum Demand % Utilisation (normal) Contingency utilisation and inter-relationships of lines.

27 Document 6 Reconciliation One document per region per year Stored in: F2012/4829 Example: D2012/ Naming: 20XX ZSS to System Forecast Reconciliation XXXX(region) System Document is based on Documents 2,3 &4. Document contains: Fdr to ZSS Spatial reconciliation (per ZSS from Fdr & ZSS) o Diversified vs Undiversified ZSS MD (raw & TC) o Annual ZSS % growth comparison ZSS to regional spatial reconciliation (System level) o Diversified vs Undiversified ZSS MD (raw & TC) o Annual ZSS % growth comparison Regional Spatial to Regional economic reconciliation o Spatial scaling and reasons o Spatial forecast P50, P10 o Regional forecast P50 and high and low window o Regional forecast P10 Deliverable Documents : Process documents contain vast amount of detail, and at selected data is summarised and can be provided for information. The following list is the key deliverable information from this forecasting process and is generally included in the Network management Plan, although all supporting process documents can be available for further in depth review and development of subsequent works etc. Economic Summary GSP, Dwellings, Population (and other as used ) Summary of Reconciliation & each regional growth rates Regional LDC and Load factors curves Regional Forecast charts (each region) Zone Substation utilisation and Summary Data (such as NMP Appendix) HV feeder utilisation Transmission Line Utilisation Transmission Line Contingency Analysis

28 15 Attachment 1 Weather correction Weather correction of the spatial demand history in order to develop the forecast is a desirable improvement as to a certain degree it explains the impact of one of the most significant drivers of demand. Ideally, correction for the weather at each forecast point would be carried out, using the nearest weather station data and individual load dependencies. The intensive nature of this analysis means that it would not be possible to implement such an approach in the short term. As a consequence, the weather correction of historical data using the parameters of the Regional load is carried out. A1.1 Weather variables To this end, Power and Water s peak demand for the Darwin-Katherine Area was analysed to determine the weather variable that provided the best statistical fit of those available. The dependencies between this range of weather variables and the network demand at times likely to affect the need for augmentation of the network were analysed. The weather variables that were tested included the following: Maximum daily temperature Tmax; Average daily temperature (Tmax + Tmin)/2.; Maximum daily enthalpy (a combination of temperature and humidity intended to represent the perceived level of heat); Average daily enthalpy; Average enthalpy over two days, the day of demand and the prior day. This parameter was included to determine whether there was a build up effect in the use of air conditioning during a hot, humid spell of weather; Average enthalpy over three days. A1.2 Demand data exclusions The demand against which the weather variables were tested was the Darwin-Katherine total hourly demand for all days. The periods most likely to result in a high system demand were isolated for testing of statistical fit. The following exclusions were made: The wet season period was taken to be the months of November through to March; Weekends and NT public holidays were excluded (leaving working weekdays); The period between Christmas and 15 January was excluded, as most commercial and industrial businesses do not resume normal activity until well into the new year. These exclusions were directed at improving the statistical correlation by confining the analysis to those periods most likely to result in a high system demand and consequently the need to augment the network.

29 A1.3 Statistical correlation between demand and weather Of the weather variables described in section A1.1, the best fit with network demand was displayed by the daily maximum temperature, with a very good R 2 of The outcome of this comparison is displayed in Figure 7. Figure 7 Wet Season day demand vs maximum daily temperature, Darwin - Katherine The slope of the line of best fit in Figure 7 (expressed in percent of maximum demand per degree) is 3.20%. This relationship is used to normalise the historical demand records (after other adjustments have been made for major loads or load transfers).

30 A1.4 Process to correct historical demand data for daily maximum temperature The long-term distribution of maximum daily temperature for Darwin is set out in Figure 8. This is used to determine the Standard Weather Maximum Demand or SWMD for this system, at a temperature of 35.9 o C. Other things being equal, the SWMD will be exceeded on average during 50% of wet seasons and the demand corrected to this temperature is also known as the P 50 demand. Figure 8 - Temperature correction of demand The distribution of the temperature maxima may also be used to determine the temperature which is exceeded in 10% of wet seasons, of 36.7 o C. This is also shown in Figure 8, and the demand at this temperature would give rise to a higher P 10 demand. The slope of 3.20% per degree means that the Darwin-Katherine P 10 demand will be 2.6% higher than the P 50 demand. The P 10 demand adjustment is used for planning the supply security to radially supplied areas. Where there is no capacity available to meet a supply contingency or high load caused by high temperatures, the radial supply must also be capable of meeting that higher demand, and the P10 demand is used for planning the capacity of that portion of the network.

31 A similar process was followed for the Alice Springs system, for its summer season from November to March. As limited load data is available for Tennant Creek, the Alice Springs temperature sensitivity was used, with the local temperature distribution. sets out the temperature correction parameters for the three regions. Table 2 - Temperature correction parameters Region Darwin-Katherine Tennant Creek Alice Springs Temperature sensitivity 3.20%/ o C 2.88%/ o C 2.88%/ o C P 50 temperature o C 35.9 o C 42.3 o C 42.9 o C P 10 temperature o C 36.7 o C 43.8 o C 44.2 o C P 10 demand increase over P % 4.3% 3.7%

32 Attachment 2 Diversity of demand The following simplified example is intended to illustrate the effect of diversity of demand. Account needs to be taken of the diversity of demand in reconciling the HV feeder level forecast with the zone substation forecast. The diversity of demand between zone substations also needs to be taken into account in developing a regional forecast. In the chart below, two loads with different profiles are to be summed over a period of 24 hours: Load A has a peak demand of 15 MW and a domestic profile; and Load B has an industrial profile and a peak demand of 10 MW. The timing of the maximum demands differs, with the domestic load peaking at 17:00 and the industrial load at 13:00. When the two loads are summed for each hour, the resultant total load has a maximum demand of MW. This maximum demand occurs at 14:00, which does not align with the peak time of either of its components. The diversity factors for the two component loads are calculated from their contribution to the total load, at the time of its peak of MW. This calculation is shown in the table below. Demand at time of Maximum demand Diversity factor total peak maximum Load A /15 = 0.95 Load B /10 = 0.98 This process described above is applied with multiple components to determine the diversity factors for feeder loads that make up a zone substation total and for the zone substation loads that make up a Regional total. The process is applied to over a full year, rather than for the 24 hour period shown above, and involves the summation of component loads that may have demands taking place in different months of the year. The effect of diversity is also considered in reconciling the Region forecast with the aggregate of the zone substation forecasts.

Jemena Electricity Networks (Vic) Ltd

Jemena Electricity Networks (Vic) Ltd Jemena Electricity Networks (Vic) Ltd 2016-20 Electricity Distribution Price Review Regulatory Proposal Attachment 7-12 - Independent analysis of augmentation expenditure Public 30 April 2015 AER augex

More information

Committee on the Northern Territory s Energy Future. Electricity Pricing Options. Submission from Power and Water Corporation

Committee on the Northern Territory s Energy Future. Electricity Pricing Options. Submission from Power and Water Corporation Committee on the Northern Territory s Energy Future Electricity Pricing Options Submission from Power and Water Corporation October 2014 Power and Water Corporation 1. INTRODUCTION On 21 August 2014, the

More information

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited PB ASSOCIATES COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN Prepared for PB Associates Quality System: Document Identifier : 153162 Top Energy Final Report Revision : 2 Report Status : Final Date

More information

2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology

2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology 2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology Version Number 1 26 June 2015 Tasmanian Networks Pty Ltd (ACN 167 357 299) Table of contents 1 Introduction... 1 2 Meeting our

More information

Daily Daily Network Network Network Energy Rates Step Rates Capacity. Price Rates Rates

Daily Daily Network Network Network Energy Rates Step Rates Capacity. Price Rates Rates Excludes GST Effective from 1 July 2010 Tariff Class Daily Daily Network Network Network Energy Rates Step Rates Capacity Capacity Price Rates Rates No. Network Price DLF Access Non-ToU Time of Use (ToU)

More information

Energy consumption forecasts

Energy consumption forecasts Pty Ltd ABN 85 082 464 622 Level 2 / 21 Kirksway Place Hobart TAS 7000 www.auroraenergy.com.au Enquiries regarding this document should be addressed to: Network Regulatory Manager Pty Ltd GPO Box 191 Hobart

More information

Water Demand Forecast Approach

Water Demand Forecast Approach CHAPTER 6 2009 REGIONAL WATER SUPPLY OUTLOOK Water Demand Forecast Approach 6.1 Introduction Long-range water demand forecasting is a fundamental tool that water utilities use to assure that they can meet

More information

Network Price List (excludes GST)

Network Price List (excludes GST) Network Price List (excludes GST) Effective from 1 July 2007 Monthly Monthly Monthly Network Network Network Energy Rates Step Rates Demand Capacity Capacity Price Network Price DLF Access Rates Rates

More information

Executive summary 2. 1 Introduction 4

Executive summary 2. 1 Introduction 4 Flexible Networks for a Low Carbon Future Future Network Monitoring Strategy September 2015 Contents Executive summary 2 Glossary 3 1 Introduction 4 2 Fundamental principles of monitoring 5 2.1 LCT monitoring

More information

How To Allocate Costs In The Ntraven Tt

How To Allocate Costs In The Ntraven Tt Power Networks Cost Allocation Method (Public Version) Version: 2.0 Last Updated: August 2013 Table of Contents Structure of this document... 1 1 Introduction and regulatory requirements... 2 1.1 Requirements

More information

Safety Monitor Requirements. October 2015

Safety Monitor Requirements. October 2015 Introduction This document sets out Safety Monitors for the 2015/16 winter, pursuant to National Grid s obligations under the Uniform Network Code (UNC), Section Q. Safety Monitors were introduced in 2004

More information

APRIL 2014 ELECTRICITY PRICES AND NETWORK COSTS

APRIL 2014 ELECTRICITY PRICES AND NETWORK COSTS APRIL 2014 ELECTRICITY PRICES AND NETWORK COSTS 1 WHAT MAKES UP THE RETAIL ELECTRICITY BILL? Retail electricity bills are made up of a number of components: Wholesale costs reflecting electricity generation

More information

Short-Term Forecasting in Retail Energy Markets

Short-Term Forecasting in Retail Energy Markets Itron White Paper Energy Forecasting Short-Term Forecasting in Retail Energy Markets Frank A. Monforte, Ph.D Director, Itron Forecasting 2006, Itron Inc. All rights reserved. 1 Introduction 4 Forecasting

More information

NATIONAL ELECTRICITY FORECASTING REPORT FOR THE NATIONAL ELECTRICITY MARKET

NATIONAL ELECTRICITY FORECASTING REPORT FOR THE NATIONAL ELECTRICITY MARKET NATIONAL ELECTRICITY FORECASTING REPORT FOR THE NATIONAL ELECTRICITY MARKET Published: JUNE 2014 Copyright 2014. Australian Energy Market Operator Limited. The material in this publication may be used

More information

APPENDIX 15. Review of demand and energy forecasting methodologies Frontier Economics

APPENDIX 15. Review of demand and energy forecasting methodologies Frontier Economics APPENDIX 15 Review of demand and energy forecasting methodologies Frontier Economics Energex regulatory proposal October 2014 Assessment of Energex s energy consumption and system demand forecasting procedures

More information

POWER NETWORKS. 2014-15 Electricity Network Tariffs and Charges and Future Price Trends

POWER NETWORKS. 2014-15 Electricity Network Tariffs and Charges and Future Price Trends POWER NETWORKS 2014-15 Electricity Network Tariffs and Charges and Future Price Trends August 2014 Power and Water Corporation Table of Contents 1 Business Characteristics... 3 2 2014 Network Price Determination...

More information

GLOSSARY. Glossary of Terms for Capacity Based Demand Response PUBLIC. Issue 3.0 GOT-1

GLOSSARY. Glossary of Terms for Capacity Based Demand Response PUBLIC. Issue 3.0 GOT-1 PUBLIC GOT-1 GLOSSARY Glossary of Terms for Capacity Based Demand Response Issue 3.0 This document provides a glossary of terms with definitions used in the Capacity Based Demand Response program. Public

More information

Economic Concepts for Pricing Electricity Network Services A Report for the Australian Energy Market Commission

Economic Concepts for Pricing Electricity Network Services A Report for the Australian Energy Market Commission Economic Concepts for Pricing Electricity Network Services A Report for the Australian Energy Market Commission 21 July 2014 Project Team Adrian Kemp Oliver Nunn Martin Chow Stephanie Gainger NERA Economic

More information

2014 Residential Electricity Price Trends

2014 Residential Electricity Price Trends FINAL REPORT 2014 Residential Electricity Price Trends To COAG Energy Council 5 December 2014 Reference: EPR0040 2014 Residential Price Trends Inquiries Australian Energy Market Commission PO Box A2449

More information

Demand (Energy & Maximum Demand) Forecast - IRP 2010 O Parameter Overview sheet

Demand (Energy & Maximum Demand) Forecast - IRP 2010 O Parameter Overview sheet Demand (Energy & Maximum Demand) Forecast - IRP 2010 O Parameter Overview sheet This sheet is to be used as the primary stakeholder engagement tool. This document provides the information that will allow

More information

2016 ERCOT System Planning Long-Term Hourly Peak Demand and Energy Forecast December 31, 2015

2016 ERCOT System Planning Long-Term Hourly Peak Demand and Energy Forecast December 31, 2015 2016 ERCOT System Planning Long-Term Hourly Peak Demand and Energy Forecast December 31, 2015 2015 Electric Reliability Council of Texas, Inc. All rights reserved. Long-Term Hourly Peak Demand and Energy

More information

NORTHERN IRELAND ELECTRICITY Ltd STATEMENT OF CHARGES FOR USE OF. THE NORTHERN IRELAND ELECTRICITY Ltd ELECTRICITY DISTRIBUTION SYSTEM

NORTHERN IRELAND ELECTRICITY Ltd STATEMENT OF CHARGES FOR USE OF. THE NORTHERN IRELAND ELECTRICITY Ltd ELECTRICITY DISTRIBUTION SYSTEM NORTHERN IRELAND ELECTRICITY Ltd STATEMENT OF CHARGES FOR USE OF THE NORTHERN IRELAND ELECTRICITY Ltd ELECTRICITY DISTRIBUTION SYSTEM BY AUTHORISED PERSONS Effective from 1 October 2011 to 30 September

More information

VOLATILITY AND DEVIATION OF DISTRIBUTED SOLAR

VOLATILITY AND DEVIATION OF DISTRIBUTED SOLAR VOLATILITY AND DEVIATION OF DISTRIBUTED SOLAR Andrew Goldstein Yale University 68 High Street New Haven, CT 06511 andrew.goldstein@yale.edu Alexander Thornton Shawn Kerrigan Locus Energy 657 Mission St.

More information

ELECTRICITY DEMAND DARWIN ( 1990-1994 )

ELECTRICITY DEMAND DARWIN ( 1990-1994 ) ELECTRICITY DEMAND IN DARWIN ( 1990-1994 ) A dissertation submitted to the Graduate School of Business Northern Territory University by THANHTANG In partial fulfilment of the requirements for the Graduate

More information

Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process

Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process Green Power Connection Net Energy Metering Engineering Review Process in Delaware and Speeding Up the Application Fee Process Presented by: Marianne Mannschreck Date: Welcome A Look at the Net Energy Metering

More information

August 2014. Industry Report: SolarBusinessServices. Solar Businesses in Australia. Prepared for: Rec Agents Association

August 2014. Industry Report: SolarBusinessServices. Solar Businesses in Australia. Prepared for: Rec Agents Association August 2014 Prepared by: Industry Report: SolarBusinessServices Prepared for: Solar Businesses in Australia Rec Agents Association P a g e 1 RAA Industry Report Solar Businesses in Australia Final 2014

More information

1.0 03/02/2014 N/A Adrian Searle N/A Initial version (ED1 July 2013 submission baseline) 1.1 13/02/2014 Chris Ong All Reformatting of initial version

1.0 03/02/2014 N/A Adrian Searle N/A Initial version (ED1 July 2013 submission baseline) 1.1 13/02/2014 Chris Ong All Reformatting of initial version Document History Version Date Revision Class Originator Section Update Details 1.0 03/02/2014 N/A Adrian Searle N/A Initial version (ED1 July 2013 submission baseline) 1.1 13/02/2014 Chris Ong All Reformatting

More information

CUS TOMER INITIATED CAPITAL WORKS (CICW) MANAGEMENT PLAN

CUS TOMER INITIATED CAPITAL WORKS (CICW) MANAGEMENT PLAN ABN 85 082 464 622 CUS TOMER INITIATED CAPITAL WORKS (CICW) MANAGEMENT PLAN DOCUMENT NUMBER: NW-#30171121 DATE: MARCH 2011 This page should either be left blank or used for any disclaimers. Page 2 of 19

More information

Measurement of Banks Exposure to Interest Rate Risk and Principles for the Management of Interest Rate Risk respectively.

Measurement of Banks Exposure to Interest Rate Risk and Principles for the Management of Interest Rate Risk respectively. INTEREST RATE RISK IN THE BANKING BOOK Over the past decade the Basel Committee on Banking Supervision (the Basel Committee) has released a number of consultative documents discussing the management and

More information

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe NETWORKS ESB Networks Response to ERGEG Consultation on Voltage Quality Regulation in Europe Date: 22 February 2007 Distribution System Operator ESB Networks Page 1 of 12 Contents 1.0 INTRODUCTION...3

More information

ESKOM DISTRIBUTION NETWORK PLANNING, A QUANTUM LEAP TO MEET INCREASED LOAD GROWTH AND IMPROVED NETWORK RELIABILITY

ESKOM DISTRIBUTION NETWORK PLANNING, A QUANTUM LEAP TO MEET INCREASED LOAD GROWTH AND IMPROVED NETWORK RELIABILITY ESKOM DISTRIBUTION NETWORK PLANNING, A QUANTUM LEAP TO MEET INCREASED LOAD GROWTH AND IMPROVED NETWORK RELIABILITY Author & Presenter: CG Carter-Brown PhD Eskom, Chief Engineer IARC Co-author: R Stephen

More information

Long Term Financial Planning

Long Term Financial Planning Long Term Financial Planning Framework and Guidelines Long Term Financial Planning Framework and Guidelines for Western Australian Local Governments p1. Contents Foreword 4 1. Introduction 7 2. Purpose

More information

TRANSMISSION SERVICE RATE SCHEDULE Effective from 1 April 2015

TRANSMISSION SERVICE RATE SCHEDULE Effective from 1 April 2015 TRANSMISSION SERVICE RATE SCHEDULE Effective from 1 April 2015 A SERVICE CONNECTION CHARGES Note : All charges in this Schedule are exclusive of GST. 1 Service Connection This includes cables, associated

More information

Design of a Weather- Normalization Forecasting Model

Design of a Weather- Normalization Forecasting Model Design of a Weather- Normalization Forecasting Model Project Proposal Abram Gross Yafeng Peng Jedidiah Shirey 2/11/2014 Table of Contents 1.0 CONTEXT... 3 2.0 PROBLEM STATEMENT... 4 3.0 SCOPE... 4 4.0

More information

EXECUTIVE SUMMARY. Key observations. AEMO to include rooftop PV generation in annual forecasting reports

EXECUTIVE SUMMARY. Key observations. AEMO to include rooftop PV generation in annual forecasting reports EXECUTIVE SUMMARY Key observations The key observations for rooftop PV forecasts detailed in this report are: The NEM has experienced a rapid uptake of rooftop PV over the last four years, with total estimated

More information

TEC Capital Asset Management Standard January 2011

TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard Tertiary Education Commission January 2011 0 Table of contents Introduction 2 Capital Asset Management 3 Defining

More information

ELECTRIC ENERGY EFFICIENCY POTENTIAL FOR PENNSYLVANIA

ELECTRIC ENERGY EFFICIENCY POTENTIAL FOR PENNSYLVANIA GDS Associates, Inc. Engineers and Consultants ELECTRIC ENERGY EFFICIENCY POTENTIAL FOR PENNSYLVANIA Final Report Prepared for: PENNSYLVANIA PUBLIC UTILITY COMMISSION May 10, 2012 Prepared by GDS Associates

More information

2013 2017 Gas Access Arrangement Review (GAAR) SP AusNet s Revised Access Arrangement Proposal (RAAP) RAAP Chapter 1: Demand Forecasts

2013 2017 Gas Access Arrangement Review (GAAR) SP AusNet s Revised Access Arrangement Proposal (RAAP) RAAP Chapter 1: Demand Forecasts 2013 2017 Gas Access Arrangement Review (GAAR) SP AusNet s Revised Access Arrangement Proposal (RAAP) RAAP Chapter 1: Demand Forecasts Submitted: 9 November 2012 RAAP Chapter 1: Demand Forecasts This chapter

More information

Power System Operation Procedure: Short Term Projected Assessment of System Adequacy (ST PASA)

Power System Operation Procedure: Short Term Projected Assessment of System Adequacy (ST PASA) ELECTRICITY INDUSTRY ACT ELECTRICITY INDUSTRY (WHOLESALE ELECTRICITY MARKET) REGULATIONS 2004 WHOLESALE ELECTRICITY MARKET RULES Power System Operation Procedure: Short Term Projected Assessment of System

More information

Methodology for Merit Order Dispatch. Version 1.0

Methodology for Merit Order Dispatch. Version 1.0 Methodology for Merit Order Dispatch Version 1.0 25 th April 2011 TABLE OF CONTENTS 1. OBJECTIVES... 1 2. ROADMAP FOR IMPLEMENTATION... 1 3. DEFINITIONS... 3 4. OPERATIONS PLANNING... 3 4.1. General Considerations...

More information

RCP2 Portfolio Overview Document

RCP2 Portfolio Overview Document RCP2 Portfolio Overview Document Portfolio: Expenditure Class: Base Capex Expenditure Category: Grid Replacement & Refurbishment As at date: 15 November 2013 Expenditure Forecast Real 2012/13 NZ$ (m) 2015-2016

More information

The Virtual Power Station - achieving dispatchable generation from small scale solar

The Virtual Power Station - achieving dispatchable generation from small scale solar The Virtual Power Station - achieving dispatchable generation from small scale solar John K Ward, Tim Moore, Stephen Lindsay CSIRO Energy Technology, Newcastle, NSW 24 Australia Keywords: forecasting,

More information

Possible future retail electricity price movements: 1 July 2012 to 30 June 2015

Possible future retail electricity price movements: 1 July 2012 to 30 June 2015 ELECTRICITY PRICE TRENDS FINAL REPORT Possible future retail electricity price movements: 1 July 2012 to 30 June 2015 22 March 2013 Reference: EPR0029 Electricity price trends report EMBARGO until 22 March

More information

AusNet Electricity Services Pty Ltd. Tariff Structure Statement 2017-20

AusNet Electricity Services Pty Ltd. Tariff Structure Statement 2017-20 AusNet Electricity Services Pty Ltd Submitted: 26 October 2015 About AusNet Services AusNet Services is a major energy network business that owns and operates key regulated electricity transmission and

More information

CHAPTER 2 LOAD FORECAST

CHAPTER 2 LOAD FORECAST CHAPTER 2 LOAD 2.1 METHODS The Company uses two econometric models with an end-use orientation to forecast energy sales. The first is a customer class level model ( sales model ) and the second is an hourly

More information

SSE s criteria used for GHG emissions reporting

SSE s criteria used for GHG emissions reporting SSE s criteria used for reporting 1 Introduction This document details the annual greenhouse gas emissions reporting approach used by SSE Plc to report the tonnes of carbon dioxide equivalent (CO2e) during

More information

2013 Residential Electricity Price Trends

2013 Residential Electricity Price Trends FINAL REPORT 2013 Residential Electricity Price Trends 13 December 2013 Reference: EPR0036 Final Report Inquiries Australian Energy Market Commission PO Box A2449 Sydney South NSW 1235 E: aemc@aemc.gov.au

More information

NATIONAL ELECTRICITY FORECASTING REPORT. For the National Electricity Market

NATIONAL ELECTRICITY FORECASTING REPORT. For the National Electricity Market NATIONAL ELECTRICITY FORECASTING REPORT For the National Electricity Market 2013 NATIONAL ELECTRICITY FORECASTING REPORT Important Notice This document is subject to an important disclaimer that limits

More information

Low Voltage Asset Management (LVAM) The key to reliable and safe electricity

Low Voltage Asset Management (LVAM) The key to reliable and safe electricity Low Voltage Asset Management (LVAM) The key to reliable and safe electricity Archie Jaykaran Distribution Division Eskom SA Contents Change drivers Scope, Approach, Project status LV Planning and Design

More information

Conservation Voltage Reduction (CVR)

Conservation Voltage Reduction (CVR) Conservation Voltage Reduction (CVR) Nicholas Abi-Samra Senior Vice President October 15, 2013 DNV GL Energy Table of Contents What does CVR do? Why Does CVR Work? DNV GL s CVR Project Experience Needs

More information

HEATWAVE 13 17 JANUARY 2014. DATE: 26 January 2014

HEATWAVE 13 17 JANUARY 2014. DATE: 26 January 2014 PREPARED BY: Systems Capability DATE: 26 January 2014 Contents 1 INTRODUCTION... 3 2 RESERVE LEVELS DURING THE HEATWAVE... 3 2.1 EVENTS ON THE NEM POWER SYSTEM CONTRIBUTING TO LOW RESERVES... 4 2.2 RISKS

More information

Victorian electricity sales and peak demand forecasts to 2024-25 SUMMARY REPORT

Victorian electricity sales and peak demand forecasts to 2024-25 SUMMARY REPORT Victorian electricity sales and peak demand forecasts to 2024-25 SUMMARY REPORT Prepared by the National Institute of Economic and Industry Research (NIEIR) ABN: 72 006 234 626 416 Queens Parade, Clifton

More information

Networks. ESB Networks Ltd Basis of Charges for Connection to the Distribution System. Commercial and Customer Asset Management ESB Networks Ltd.

Networks. ESB Networks Ltd Basis of Charges for Connection to the Distribution System. Commercial and Customer Asset Management ESB Networks Ltd. Networks ESB Networks Ltd Basis of Charges for Connection to the Distribution System Revision Date: 14/01/20010 Revision No.: 1 Document No: DOC-10129-AXQ Issued by: ESB Networks Ltd Approved by : CER

More information

4.1.1 Generator Owner 4.1.2 Transmission Owner that owns synchronous condenser(s)

4.1.1 Generator Owner 4.1.2 Transmission Owner that owns synchronous condenser(s) A. Introduction 1. Title: Verification and Data Reporting of Generator Real and Reactive Power Capability and Synchronous Condenser Reactive Power Capability 2. Number: MOD-025-2 3. Purpose: To ensure

More information

Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid

Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid Pakistan Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid Final Report: Executive Summary - November 2015 for USAID Energy Policy

More information

A Guide For Preparing The Financial Information Component Of An Asset Management Plan. Licensing, Monitoring and Customer Protection Division

A Guide For Preparing The Financial Information Component Of An Asset Management Plan. Licensing, Monitoring and Customer Protection Division A Guide For Preparing The Financial Information Component Of An Asset Management Plan Licensing, Monitoring and Customer Protection Division July 2006 Contents 1 Important Notice 2 2 Scope and purpose

More information

red zone management white paper Making the most of Distribution Use of System (DUoS) Charges

red zone management white paper Making the most of Distribution Use of System (DUoS) Charges red zone management white paper Making the most of Distribution Use of System (DUoS) Charges 1. Distribution charges 2. Measuring usage 3. Component parts 4. Time is of the essence 5. Solution provider

More information

Methodology For Illinois Electric Customers and Sales Forecasts: 2016-2025

Methodology For Illinois Electric Customers and Sales Forecasts: 2016-2025 Methodology For Illinois Electric Customers and Sales Forecasts: 2016-2025 In December 2014, an electric rate case was finalized in MEC s Illinois service territory. As a result of the implementation of

More information

NETWORK MANAGEMENT STRATEGY

NETWORK MANAGEMENT STRATEGY ABN 85 082 464 622 NETWORK MANAGEMENT STRATEGY DOCUMENT NUMBER: NW-#30065608-V6 DATE: 12 MAY 2011 NW-#30065608-v6-Network_Management_Strategy.DOC Page 1 of 20 This page is intentionally blank. NW-#30065608-v6-Network_Management_Strategy.DOC

More information

pwc.com.au NT WorkSafe Actuarial review of Northern Territory workers compensation scheme as at June 2014

pwc.com.au NT WorkSafe Actuarial review of Northern Territory workers compensation scheme as at June 2014 pwc.com.au NT WorkSafe Actuarial review of Northern Territory workers compensation scheme as at June 2014 30 June 2013 Key findings Funding ratio The following table shows the funding ratio for the scheme

More information

NEW COMMERCIAL Rates. Understanding the. Commercial Customers

NEW COMMERCIAL Rates. Understanding the. Commercial Customers Understanding the NEW COMMERCIAL Rates The Austin City Council increased Austin Energy s base rates, which pay for operations and maintenance, for the first time in 18 years. The new rates, which amount

More information

PREDICTIVE AND OPERATIONAL ANALYTICS, WHAT IS IT REALLY ALL ABOUT?

PREDICTIVE AND OPERATIONAL ANALYTICS, WHAT IS IT REALLY ALL ABOUT? PREDICTIVE AND OPERATIONAL ANALYTICS, WHAT IS IT REALLY ALL ABOUT? Derek Vogelsang 1, Alana Duncker 1, Steve McMichael 2 1. MWH Global, Adelaide, SA 2. South Australia Water Corporation, Adelaide, SA ABSTRACT

More information

Rule change request. 18 September 2013

Rule change request. 18 September 2013 Reform of the distribution network pricing arrangements under the National Electricity Rules to provide better guidance for setting, and consulting on, cost-reflective distribution network pricing structures

More information

PG&E s Distribution Resource Plan

PG&E s Distribution Resource Plan PG&E s Distribution Resource Plan The Utility Energy Forum Spring 2016 Conference Presentation Developed for Panel Discussion Lake Tahoe, California May 2016 READ AND DELETE For best results with this

More information

POWER NETWORKS. 2015-16 Electricity Network Tariffs and Charges and Future Price Trends

POWER NETWORKS. 2015-16 Electricity Network Tariffs and Charges and Future Price Trends POWER NETWORKS 2015-16 Electricity Network Tariffs and Charges and Future Price Trends July 2015 Power and Water Corporation 1 Table of Contents 1 Business Characteristics 3 2 2014 Network Price Determination

More information

COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011

COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011 COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011 I. Background The Solar Alliance is a group of approximately 30 of the largest photovoltaic (PV) solar development and

More information

THE COMED RESIDENTIAL REAL-TIME PRICING PROGRAM GUIDE TO REAL-TIME PRICING

THE COMED RESIDENTIAL REAL-TIME PRICING PROGRAM GUIDE TO REAL-TIME PRICING THE COMED RESIDENTIAL REAL-TIME PRICING PROGRAM GUIDE TO REAL-TIME PRICING 2014-2015 COMED RESIDENTIAL REAL-TIME PRICING PROGRAM GUIDE TO REAL-TIME PRICING CONTENTS ComEd Residential Real-Time Pricing

More information

Calculating Total Power Requirements for Data Centers

Calculating Total Power Requirements for Data Centers Calculating Total Power Requirements for Data Centers By Richard Sawyer White Paper #3 Executive Summary Part of data center planning and design is to align the power and cooling requirements of the IT

More information

Attachment 20.27 SA Power Networks: Network Program Deliverability Strategy

Attachment 20.27 SA Power Networks: Network Program Deliverability Strategy Attachment 20.27 SA Power Networks: Network Program Deliverability Strategy Network Program Deliverability Strategy 2015-20 Regulatory Control Period SA Power Networks www.sapowernetworks.com.au Internal

More information

Network Price List and Explanatory Notes

Network Price List and Explanatory Notes Essential Energy Network Price List (Excluding GST) Effective 1 July 2014 Tariff Code Obsolete tariffs on same rate Description Network Energy Energy Energy Energy Energy Energy Energy Peak Shoulder OffPeak

More information

STOCHASTIC MODELLING OF WATER DEMAND USING A SHORT-TERM PATTERN-BASED FORECASTING APPROACH

STOCHASTIC MODELLING OF WATER DEMAND USING A SHORT-TERM PATTERN-BASED FORECASTING APPROACH STOCHASTIC MODELLING OF WATER DEMAND USING A SHORT-TERM PATTERN-BASED FORECASTING APPROACH Ir. LAM Shing Tim Development(2) Division, Development Branch, Water Supplies Department. Abstract: Water demand

More information

Project Management Competency Standards

Project Management Competency Standards BSB01 Business Services Training Package Project Management Competency Standards CONTENTS BSBPM401A Apply scope management techniques...3 BSBPM402A Apply time management techniques...8 BSBPM403A Apply

More information

Modeling of PV Based Distributed Generator Systems with Diverse Load Patterns

Modeling of PV Based Distributed Generator Systems with Diverse Load Patterns Modeling of PV Based Distributed Generator Systems with Diverse Load Patterns Mehmet H. Cintuglu, mcint015@fiu.edu, Armando Altamirano, araltami@fiu.edu Osama A. Mohammed, mohammed@fiu.edu Energy Systems

More information

GENERAL RULES AND REGULATIONS FOR ELECTRIC SERVICE CUSTOMER'S UTILIZATION OF ELECTRIC SERVICE

GENERAL RULES AND REGULATIONS FOR ELECTRIC SERVICE CUSTOMER'S UTILIZATION OF ELECTRIC SERVICE Filed with the I. U. B. Substitute Fourth Revised Sheet No. 217 ORIGINAL TARIFF NO. 1 Canceling Third Revised Sheet No. 217 SECTION 5 5.01 APPLICATION FOR SERVICE: Any person, firm, association, or corporation,

More information

Power & Water Corporation. Review of Benchmarking Methods Applied

Power & Water Corporation. Review of Benchmarking Methods Applied 2014 Power & Water Corporation Review of Benchmarking Methods Applied PWC Power Networks Operational Expenditure Benchmarking Review A review of the benchmarking analysis that supports a recommendation

More information

Integrated Resource Plan

Integrated Resource Plan Integrated Resource Plan March 19, 2004 PREPARED FOR KAUA I ISLAND UTILITY COOPERATIVE LCG Consulting 4962 El Camino Real, Suite 112 Los Altos, CA 94022 650-962-9670 1 IRP 1 ELECTRIC LOAD FORECASTING 1.1

More information

Project Management Guidebook

Project Management Guidebook METHOD 12 3 empowering managers to succeed Project Management Guidebook ISBN 0-473-10445-8 A bout this e-book This e-book was created by Method123 (see www.method123.com) to help provide you with a simple

More information

How To Manage Assets

How To Manage Assets INSTITUTE OF CERTIFIED PUBLIC ACCOUNTANTS OF KENYA ASSET MANAGEMENT SEMINAR SEPTEMBER 9 TH -11 TH, 2015 Asset Information Credibility. Professionalism. AccountAbility 1 Asset Information 2 Content 1. Stakeholders

More information

The Economic Impacts of Reducing. Natural Gas and Electricity Use in Ontario

The Economic Impacts of Reducing. Natural Gas and Electricity Use in Ontario The Economic Impacts of Reducing Natural Gas and Electricity Use in Ontario Prepared for Blue Green Canada July 2013 Table of Contents Executive Summary... i Key Findings... i Introduction...1 Secondary

More information

FINAL INTERNAL AUDIT REPORT - REVIEW OF PERFORMANCE INDICATORS (PIs) 2008/09

FINAL INTERNAL AUDIT REPORT - REVIEW OF PERFORMANCE INDICATORS (PIs) 2008/09 Sandy Pacek Project Manager Squares and Business Development Dear Sandy, FINAL INTERNAL AUDIT REPORT - REVIEW OF PERFORMANCE INDICATORS (PIs) 2008/09 INTRODUCTION This review forms part of the agreement

More information

APPLICATION NOTE. Increasing PV Hosting Capacity on LV Secondary Circuits with the Gridco System empower TM Solution

APPLICATION NOTE. Increasing PV Hosting Capacity on LV Secondary Circuits with the Gridco System empower TM Solution APPLICATION NOTE Increasing PV Hosting Capacity on LV Secondary Circuits with the Gridco System empower TM Solution INCREASING PV HOSTING WITH EMPOWER TM SOLUTION Executive Summary Distributed solar photovoltaic

More information

NETWORK PRICE LIST 2014/2015. Effective 1 July 2014

NETWORK PRICE LIST 2014/2015. Effective 1 July 2014 NETWORK PRICE LIST 2014/2015 Effective 1 July 2014 Document Amendment History Version No. Publication Date Comments 1.0 17 June 2014 AER Approved Pricing 2.0 15 July 2014 Updated Substation and Transformer

More information

UNDERSTANDING ENERGY BILLS & TARRIFS

UNDERSTANDING ENERGY BILLS & TARRIFS UNDERSTANDING ENERGY BILLS & TARRIFS as part of the Energy Efficiency Information Grants Program Reading and understanding your energy and gas bills is a good first step to help you to identify where you

More information

AMI and DA Convergence: Enabling Energy Savings through Voltage Conservation

AMI and DA Convergence: Enabling Energy Savings through Voltage Conservation AMI and DA Convergence: Enabling Energy Savings through Voltage Conservation September 2010 Prepared for: By Sierra Energy Group The Research & Analysis Division of Energy Central Table of Contents Executive

More information

Data Analytics for Future Energy Systems

Data Analytics for Future Energy Systems Data Analytics for Future Energy Systems Dr Stuart Galloway & Dr Bruce Stephen Advanced Electrical Systems Group Institute for Energy and Environment Department of Electronic and Electrical Engineering

More information

Agenda do Mini-Curso. Sérgio Yoshio Fujii. Ethan Boardman. sergio.fujii@areva-td.com. ethan.boardman@areva-td.com

Agenda do Mini-Curso. Sérgio Yoshio Fujii. Ethan Boardman. sergio.fujii@areva-td.com. ethan.boardman@areva-td.com Agenda do Mini-Curso Sérgio Yoshio Fujii sergio.fujii@areva-td.com Ethan Boardman ethan.boardman@areva-td.com Agenda do Mini-Curso Sistemas de Distribuição (DMS) Characteristics of Distribution Network

More information

gasnetworks.ie Methodology for forecasting gas demand

gasnetworks.ie Methodology for forecasting gas demand gasnetworks.ie Methodology for forecasting gas demand 1 Contents 1 Introduction 2 1.1 Scope of the report 3 1.2 Use and publication of the forecasts 4 1.3 Structure of the document 5 2 Conceptual background

More information

16 West Coast Regional Plan

16 West Coast Regional Plan 16 West Coast Regional Plan 16.1 Regional overview 16.2 West Coast transmission system 16.3 West Coast demand 16.4 West Coast generation 16.5 West Coast significant maintenance work 16.6 Future West Coast

More information

SA Power Networks Network Tariffs - Residential APPLIES TO USAGE FROM 1 JULY 2015

SA Power Networks Network Tariffs - Residential APPLIES TO USAGE FROM 1 JULY 2015 SA Power Networks Network Tariffs - Residential Low Voltage Residential - Single Rate DUOS excl TUOS excl PV JSO excl Total excl Total incl Block 1 Usage Rate $/kwh First 333.3 kwh/mth 0.0745 0.0300 0.0130

More information

Asset Management Strategy

Asset Management Strategy Asset Management Strategy ElectraNet Corporate Headquarters 52-55 East Terrace, Adelaide, South Australia 5000 PO Box, 7096, Hutt Street Post Office, Adelaide, South Australia 5000 Tel: (08) 8404 7966

More information

Deriving Value from ORSA. Board Perspective

Deriving Value from ORSA. Board Perspective Deriving Value from ORSA Board Perspective April 2015 1 This paper has been produced by the Joint Own Risk Solvency Assessment (ORSA) Subcommittee of the Insurance Regulation Committee and the Enterprise

More information

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited TABLE OF CONTENTS 1.0 Purpose and Scope...2 1.1 Methodology Purpose...2

More information

Asset Management Plan

Asset Management Plan 2014 Asset Management Plan www.topenergy.co.nz INTRODUCTION Introduction It gives me great pleasure to present Top Energy s 2014-2024 Network Asset Management Plan (AMP). The 2014 AMP follows on from the

More information

Ausgrid Network Pricing Proposal For the Financial Year Ending June 2013. May 2012

Ausgrid Network Pricing Proposal For the Financial Year Ending June 2013. May 2012 Ausgrid Network Pricing Proposal For the Financial Year Ending June 2013 May 2012 Table of Contents PART 1 APPROACH TO PRICE SETTING 1. INTRODUCTION AND OVERVIEW... 4 2. BACKGROUND... 6 3. PRICING METHODOLOGY...

More information

Power NI: tariff methodology

Power NI: tariff methodology Research and Information Service Paper 12/14 23 September 213 NIAR 640-13 Aidan Stennett Power NI: tariff methodology 1 Introduction The following paper supplements Northern Ireland Assembly Research and

More information

1. This Prudential Standard is made under paragraph 230A(1)(a) of the Life Insurance Act 1995 (the Act).

1. This Prudential Standard is made under paragraph 230A(1)(a) of the Life Insurance Act 1995 (the Act). Prudential Standard LPS 110 Capital Adequacy Objective and key requirements of this Prudential Standard This Prudential Standard requires a life company to maintain adequate capital against the risks associated

More information

Consultation on Global Settlement in the SEM for Northern Ireland

Consultation on Global Settlement in the SEM for Northern Ireland Consultation on Global Settlement in the SEM for Northern Ireland 1 Table of Contents 1. Purpose of this Paper... 3 2. Introduction... 3 3. Background... 5 4. Residual Volume... 6 5. Drivers for Change...

More information

ATTACHMENT G. Network Operating Agreement

ATTACHMENT G. Network Operating Agreement ATTACHMENT G Network Operating Agreement 1. PURPOSE OF NETWORK OPERATING AGREEMENT The purpose of this Agreement is to identify contractual requirements related to Network Integration Transmission Service

More information

Updated SCER Demand Side Participation Program December 2013

Updated SCER Demand Side Participation Program December 2013 Updated SCER Demand Side Participation Program December 2013 The Standing Council on Energy and Resources (SCER) has adopted this framework to guide its demand side participation (DSP) work. The framework

More information