1 ASX Code: KIN 29 th October 2015 Board of Directors Terry Grammer Chairman QUARTERLY ACTIVITIES REPORT For the Period ending 30 th September 2015 Trevor Dixon Managing Director Highlights Fritz Fitton Technical Director Joe Graziano Non-Executive Director and Company Secretary Optimisation and mine scheduling has been revised for the Lewis Trial Mine. The new mine design generates a more economically robust mining schedule incorporating >30% less waste. The operation is seen as a low cost entry to gold production via vat leaching. Contact Details Post PO Box 565 Mount Hawthorn Western Australia 6915 Office 342 Scarborough Beach Road Osborne Park Western Australia 6017 Analysis of north-west structural faults intersecting the Gwalia mine sequence has identified untested Sons of Gwalia and Tower Hill style drill targets at Gwalia South, 2.5km south of the Sons of Gwalia Mine (7Moz). Five gold anomalous zones (+5ppb Au) have been identified at Mt Flora following a regional geochemical auger soil sampling programme. The largest gold-in-soil anomaly covers a lateral extent of 3.5km peaking at 2,635ppb Au (2.635g/t Au). Phone (08) info@kinmining.com.au Website Shares on Issue: 60, Unlisted Options: 5,856,000 ASX: KIN Kin Mining (ASX: KIN) is pleased to update the market with a summary of Quarterly activities. Lewis Open Pit Optimisation Progress on the Lewis Trial Mine at the Bruno-Lewis deposit continues on schedule (KIN:ASX announcement 19/10/13). A new pit optimisation study has been completed for the proposed mining operation. Revised inputs generated a more economically robust mine schedule which resulted in a tighter constrained pit design that incorporates >30% less waste than previous pit designs. Site works has comenced, with the refurbishment of the haul road (L37/195) within the Cardinia area. Procurement of key infrustructure is under way and a mining engineer and mine geologist have been appointed to manage the Lewis trial mining operation. 1 P a g e

2 Managing Director Trevor Dixon said The Lewis Trial Mining is seen as a stepping stone for the company to become an emerging gold producer. The trial mine will answer fundamental questions about the properties and characteristics of the supergene ore that we will be able to incorporate into the larger Cardinia resource. This is an exciting time and it places the company closer to our ultimate business goal of becoming a gold producer. Figure 1 Plan view of the new Lewis Trial pit, which incorporates considerably less waste than previous pit designs. Resource ore blocks are coloured by grade Au g/t (green g/t, red 1-3g/t and pink >3g/t). Gwalia South Targets Following a review of the Desdemona project four high priority drill targets have been identified at Gwalia South. Exploration targeting has focused on north-west structural faults and the greenstone sequence that hosts the Gwalia type (Gwalia Mine sequence) and the Tower Hill type (graniteultramafic contact) gold mineralisation. The primary targets (GS1) are the intersection of the Gwalia Mine sequence and interpreted northwest faults (310 ) and the ductile deformation zones along these faults, positioned west of the Mt George Shear and east of the granite contact (KIN: ASX Announcement 12/10/15). 2 P a g e

3 The second target type (GS2) is Tower Hill style mineralisation positioned along the Raeside Granitoid/ultramafic contact that marks the edge of the greenstone belt. The sequence denotes the preferred host rocks for localised gold mineralisation and the oldest sheared greenstones in the district (2.8Ga). Historical old workings (pink squares) along the Gwalia Slate GS1 intersection of the Gwalia Mine sequence and NW faults GS2 Tower Hill granite/ultramafic contact GS1 intersection of the Gwalia Mine sequence and NW faults Figure 2 Gwalia South Prospect with geological and structural interpretation and defined drill target areas 3 P a g e

4 The prospective lithologies south of the Sons of Gwalia mine are traceable into the northern end of Kin s Gwalia South tenements. Gwalia South displays the same continuous greenstone sequence cut by a number of structural faults similar to that at the Sons of Gwalia and the Tower Hill gold mines. There has not been a significant gold discovery along this southern section of the prospective Gwalia Shear Zone. Kin believe this is due to lack of outcrop and ineffective previous exploration techniques. The tenements have been inadequately explored by former tenement owners. The majority of previous exploration is shallow vertical RAB or Aircore drilling, predominantly conducted on 400m line spacings. Historic drilling has failed to intersect the north-west striking faults or drill completely through the prospective lithological contact zones or adequately test the Gwalia Mine sequence at depth. A Programme of Work (POW) has been submitted to the Department of Mines and Petroleum (DMP), the application includes both RC and diamond drilling proposals. The tenements are within 10km of Leonora and drill ready. Mt Flora Kin Mining NL has received encouraging results from a recently completed auger soil geochemical programme over the entire Mt Flora tenement package. Five separate gold-in-soil anomalies (+5 ppb Au) have been identified (Figure 3). The most coherent and largest of these soil anomalies extends over 3.5 km in a northwesterly direction. The centre portion of the main anomaly exhibits a significant higher grade core (+20ppb Au) with a maximum peak soil assay of 2,635ppb gold. The soil anomaly coincides with three groups of old workings and cross cuts Mt Flora Syncline fold axis. This large soil anomaly also encompasses a drill target where limited historical RAB drilling (20 hole programme to 30m depth) intersected a broad zone of shallow gold mineralisation returning 0.53 g/t Au from 8-30m (Payne 1988). This intersection was never followed up. Regional geology comprises a suite of NNE trending greenstones positioned on the western limb of the Kilkenny Syncline. To the north a porphyritic magnetic granite is in contact with the greenstone sequence. The greenstones at Mt Flora comprises a succession of tholeiitic mafic volcanics, high magnesian basalt, chert, ultramafic rocks and a variety of mafic intrusives including gabbroic and dioritic rocks. The area is viewed as prospective for gold mineralisation. 4 P a g e

5 2,635ppb Au Augered Soil 0.53g/t Au (8m-30m) from historic RAB g/t Au Rock chip Figure 3 - Mount Flora geological interpretation and tenement plan with recent soil anomalies (+5ppb Au) displaying the correlation between anomalous gold contours, old workings and historical RAB drilling. Aeromagnetic data covering the main anomalous zone displays several circular magnetic highs interpreted to possibly represent discrete buried syenite intrusions. Many of the region s largest gold mines, including the Wallaby deposit (7Moz) and Jupiter/Heffernans Find (1Moz) are associated with similar bullseye magnetic anomalies associated with small syenite or alkali-granite intrusives. 5 P a g e

6 Distinct Magnetic high correlating with the largest +5ppb Au soil anomaly (3.5km x 1km) Figure 4 - Mount Flora Tenement plan with anomalous gold-in-soil anomalies (+5ppb Au) and the magnetic image displaying magnetic high areas The main anomalous soil zone also encompasses a significant high-grade rock chip result, g/t Au and 0.684%ppm Pb (repeat 1.26% Pb) which was returned from a channel sample across a galena rich quartz vein in an old historic working on P39/5463. The working is located 300m north along strike from the high grade (>1oz/t Au) Spion Kop mine (KIN:ASX announcement 24/12/13). 6 P a g e

7 Correlation of the recent geochemical results indicates that auger soil sampling is an effective method to delineate prospective gold target areas within the Mt Flora Project. Kin plans to follow up significant results with an infill, closer spaced multi-element geochemical soil programme around the identified gold-in-soils anomalies, to further refine targets for a maiden drilling programme. Kin s Technical Director, Fritz Fitton said The recent soil geochemical results from Mt Flora are highly encouraging and co-incide with previous anomalous rock chip assays and numerous historical workings that have never been drilled. The presence of several NW trending discrete aeromagnetic anomalies over the largest (3.5km x 1km) gold anomaly is considered favorable for the discovery of Wallaby/Jupiter style gold mineralisation at Mt Flora. Corporate A summary of the corporate actions undertaken by the Company during the quarter are summarised below: A Share Purchase Plan Prospectus was issued on 31 July 2015 to raise up to $2m in capital at a price of $0.10c per share with a 1 for 2 free Unlisted Option exercisable at $0.20c and expiring on 31 August The Company advised the market on 18 September 2015 that it has raised $189,000 under the Share Purchase Plan. This together with a completed Placement to Sophisticated and Professional Investors raised $844,200 (before costs). Furthermore, in accordance with shareholder approval obtained on 3 September 2015, the Directors have the right to place the 18,110,000 shares and attaching options that were not subscribed by shareholders in the Share Purchase Plan ( Shortfall ) within 3 months from the date of the general meeting of shareholders with selected parties at their discretion. The issue price of any Shortfall will be on the same terms as those offered to shareholders in the Share Purchase Plan including the issue of one attaching option for every two shares issued. The Company will keep the market informed on any development in relation to the placement of the Shortfall. The Company announced during the quarter that it has received mining approval from the Department of Mines and Petroleum (DMP) to carry out mining activities on Mining Leases M37/86, M37/227, M37/277, M37/300 and M37/428, which includes a mine closure plan at Lewis. The Mining Proposal has been assessed by the Departments of Water and Aboriginal Affairs. Environmental Regulation and amendments to the schedule of conditions attached to the Mining Leases have been established by the DMP. With these approvals and departmental advice in place the Company expects to commence production at Lewis as soon as practicable. The Company is assessing the existing mine schedules to ensure that all extraction and processing alternatives have been considered prior to the commencement of open cut mining. Kin and Advanced Mining & Civil Pty Ltd ( AMC ) have entered into a Memorandum of Understanding ( MOU ) to provide open cut mining and civil earthmoving activities at Lewis and the Leonora Gold Project under certain Terms and Conditions, including: o That AMC commits to invest $500,000 in Kin Mining NL via a staged placement of shares; 7 P a g e

8 o o o Kin commits to provide AMC with up to $2 million of open cut mining and civil earthmoving activities in accordance with AMC s schedule of rates and Load and Haul tender provided to the company, subject to Kin receiving all regulatory approvals and completing all resource modelling to its satisfaction. Kin provides all fuel for the mining operation at Lewis; Kin provides a first right of refusal to AMC over any open cut mining and civil earthmoving activities at its Leonora Gold Project during the next 24 months. The Company announced that the $1 million loan provided by Mr. Fritz Fitton, the company s technical director, to assist with the acquisition of the Leonora Gold Project in October 2014 will be extended for a further 12 month term commencing on the 24 th October 2015 on the same terms and interest rate as previously announced. The Company convened a General Meeting of Shareholders on 3 September 2015 and announced the results of the meeting on the same day with all Resolutions passed at the meeting. Cultural and Community Activities The Children's Charity Network is an umbrella for different programs/initiatives one of which being the Young Indigenous Art & Writers Awards. Kin Mining is proud to be a contributor to the Young Indigenous Art & Literacy programe for the Leonora Remote School. Kin s contribution will give our Aboriginal and non-aboriginal children at the local school the opportunity to experience the love of writing and art. The writers and illustrators who attend the schools are passionate about their work as it is the chosen career they have taken and love sharing it with the students. Awards will be presented in Melbourne at the Young Australian Art Awards function in November Representative pieces of art from the program can be seen below. Figure 5 Examples from the Art and Literacy workshops 8 P a g e

9 References Payne, C. 1988, Abednego Project, Progress Report on Exploration to March 1988 P39/1038, P339/1037. Avaliable from WAMEX report no. A Maynard, Al. 2012, Kin Mining NL Prospectous. Independent Geological Report for an initial public offering prepared for Kin Mining NL. Competent Persons Statement The information in this report that relates to mineral resources and exploration results at Mt Flora is based on information compiled by Mr. Marvyn John (Fritz) Fitton who is a Member of the Institute of Geoscientists and a Member of the Australian Institute of Mining and Metallurgy. Mr. Fitton is the Technical Director of Kin Mining NL and has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2012 edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr. Fitton has given his consent to the inclusion in this report of the matters based on the information in the form and context in which it appears. Competent Persons Statement The information contained in this report that relates to mineral resources and exploration results is based on information compiled and reviewed by Paul Maher who is a member of the Australasian Institute of Mining and Metallurgy (AusIMM) and Mr. Simon Buswell-Smith who is a Member of the Australian Institute of Geoscientists (MAIG), both are employees of the company and fairly represents this information. Mr. Maher and Mr. Buswell- Smith have sufficient experience of relevance to the styles of mineralisation and the types of deposit under consideration, and to the activities undertaken to qualify as a Competent Person as defined in the 2012 edition of the JORC Australian code for reporting of Exploration Results, Mineral Resources and Ore Reserves. Mr. Maher and Mr. Buswell-Smith consent to the inclusion in the report of the matters based on information in the form and context in which it appears. Forward Looking Statements Certain information in this document refers to the intentions of Kin Mining NL, but these are not intended to be forecasts, forward looking statements or statements about future matters for the purposes of the Corporations Act or any other applicable law. The occurrence of events in the future are subject to risks, uncertainties and other factors that may cause Kin Mining NL s actual results, performance or achievements to differ from those referred to in this announcement. Accordingly, Kin Mining NL, its directors, officers, employees and agents do not give any assurance or guarantee that the occurrence of the events referred to in this announcement will actually occur as contemplated. 9 P a g e

10 Appendix A Company Announcement SECTION 1 Sample Techniques and Data Criteria Sampling techniques Drilling techniques Drill sample recovery Commentary Composite sieved auger samples collected at Mt Flora totaled 441. Samples were collected over varying intervals to a maximum depth of 1.2m, the average hole depth was 0.213m. Approximately grams of sample was collected via scoop from each sample point and stored in paper geochemical bags prior to submission for geochemical analysis. All samples were mixed drill spoil collected from surface to the end of hole. Samples were collected directly from the drill spoil around the 100mm auger drill hole and collected dry. Sample lines were systematically grid based and orientated east-west (GDA94 zone51). The majority of samples were collected on a 400m x 100m grid and on occasion 200m x 100m and 1200m x 200m grids were utilised. Auger soil sampling was completed using a Land Cruiser mounted power auger, 100mm diameter with standard flights and drill bits capable of a 1,200mm drill hole. The programme was conducted by Leonora based RLG Exploration Services. Composite, sieved to 1mm, soil samples were collected over a maximum of 1.2m, the total auger rod length. The average sample length was 0.213m which reflects the average hole depth. Samples were a sieved composites collected directly from the drill spoil at the hole collar. Only grams of sample was collected for analysis. Samples were stored in pre-numbered paper geochemical bags. The sample is considered to represent a composite sample. No relationship was observed between sample recovery and grade. Logging Kin s procedure for logging of sample included recording the sample colour, landform, grid coordinates and total hole depth, data is physically and electronically stored. Areas of affected by drainage (i.e. creeks) were avoided and on very rare occasions a standard sieved surface soil sample was collected if the auger rig could not penetrate the surface. All drill holes are logged to the end of hole. Subsampling techniques and sample preparation Quality of assay data and laboratory tests See Sampling techniques in the above section. All samples were collected dry, no ground water was encountered. Some residual moisture was present as the sample was collected however it evaporated upon exposure to the atmosphere and was not of sufficient concentration to affect the sieving process. No field standards or blanks were submitted with the sample batches however the assay lab, Nagrom, included its own internal checks and balances consisting of 6 repeats and 5 standards per 100 samples submitted; repeatability and standard results were within acceptable limits. Geochemical analysis was conducted by Nagrom Laboratories in Kelmscott. Sample preparation included drying samples (105 C) and pulverising to 95% passing 75µ. Samples were riffel split to secure a sample charge of 25 grams. Analysis was via Aqua Regia digest (25 gram charge) with ICP finish (ppm detection). Elements assayed include Au, Bi, As, Cr, Cu, W, Ni, Pb & Zn. The analytical process and the level of detection are considered appropriate for this current early stage of exploration. Aqua Regia acid digest is not a complete digest. As such the analysis should only be considered as partial for some elements. 10 P a g e

11 Criteria ASX Code: KIN Commentary No geophysical tools were used to determine any element concentrations. Only internal laboratory quality control procedures have been adopted. Verification of sampling and assaying Location of data points Data spacing and distribution All the logged samples have been assayed; the assay data has been stored physically and electronically in the database using Kin Mining s protocols. The sampling and assay data has been compiled and interpreted by company geologists and the competent person. No holes were twined. No adjustments, averaging or calibrations are made to any of the assay data recorded in the database. Sample points were located in the field using a hand held GPS with a four metre or better accuracy. The grid system utilised is (GDA94 zone51). No topographic control was required. The drill hole spacing is tenement specific; the auger drilling patterns employed were dependent on lithology and proximity to old workings. Areas of interest were sampled at a denser grid interval. Samples were collected on east-west lines. The majority of samples were collected on a 400m x 100m grid, although on occasion 200m x 100m and 1200m x 200m grids were utilised. The sample spacing is broad however it s close enough to identify modest sized zones of mineralisation. The sampling programme is a first pass exercise that was designed to identify areas of geological interest and anomalous metal zones. A closer spaced sampling programme is required to determine the size and extent of identified anomalous zones of gold mineralisation. Drill spacing and drill technique is not sufficient to establish the degree of geological and grade continuity appropriate for the mineral resources and ore reserve estimation procedures and classifications applied. Sample composting occurred in every sample, the width of the sample is dependent on the depth of the auger drill hole, some were 1.2m others 0.1m, average sampling width was 0.213m. In all cases a sample weight of gm was collected. Orientation of data in relation to geological structure Sample security The greenstone sequence displays a NNE trend. The tenement package is contiguous; the sampling programme was designed to provide, as best as practicable, an unbiased location of point sample data. The sample grid pattern is controlled by east-west lines, the majority at 400m intervals, occasionally the north-south interval was closed down to 200m and extended to 1200m, sample intervals are stationed at 100m or 200m spacing in an east west direction No orientation sampling bias has been identified in the data thus far. Holes are drilled vertically to blade refusal. Samples were collected daily in the field and stored in a secure, lockable location overnight in Leonora. Upon completion of the programme all samples were transported to Perth by a company employee. The samples were then stored in a secure lockable building. They were renumbered, checked against the field manifest and sorted. Samples were then transported, by a company employee, to the analytical laboratory in Kelmscott. Once in the laboratories possession adequate sample security measures are utilised. 11 P a g e

12 Criteria ASX Code: KIN Commentary Audits or reviews Sampling methodologies and assay techniques used in this geochemical auger sampling survey are considered to be mineral exploration industry standard and any audits or reviews are not considered necessary at this early exploration stage. Section 2 Reporting of Exploration Results Criteria Mineral tenement and land tenure status Commentary The soil sampling auger programme was conducted on tenements P39/ , P39/ , P39/ , P39/5185 and P39/5463, the area is named the Mt Flora project. All tenements are held in the name of Mr. Trevor John Dixon although the tenements are managed, explored and maintained by Kin Mining NL. The tenements are located on Minara Station mostly within the Shire of Leonora in the Mt Morgan District of the Mt Margaret Mineral Field in the centre of the North Eastern Goldfields. The tenements are subject to an option agreement between Kin Mining NL and the vendor (T. Dixon) who maintains a 2% gross royalty as detailed in the Kin Mining NL Prospectus. The option agreement has been exercised but the transfer process is yet to be completed, as the agreement is currently with the Office of State Revenue for assessment and stamping. The Company retains an executed transfer document that will be lodged with the DMP following the assessment process. Tenements P39/ & 5185 are subject to an application for an extension of term pursuant to Regulation 16B(1)(c)(iii) of the Mining Act 1978 and Mining Regulations M39/459 is enclosed within and surrounded by the Mt Flora tenement holding, it is excised and not part of the companies land tenure Exploration done by other parties There are no other existing impediments to the tenements. Gold was initially discovered in the area in 1895 however no substantial gold mines are contained within the project area although numerous shallow gold workings along narrow, sulphidic quartz reefs are found within the leases. In addition several small rich historic workings (+1oz/t) are outside the lease area but in the immediate vicinity (i.e. Lady Susan, Abednego Hill, Australia United, Federation and Mt Flora mines). The area is known for near surface alluvial and colluvial gold in laterite. Historically the gold has been won by dry blowing and in recent times by metal detecting, numerous detecting patches have been discovered at Mt Flora, mainly surrounding P39/4617. In Sons of Gwalia explored the area; work conducted included geological mapping, rock chip sampling and RAB drilling. The drilling followed up a previous vertical RAB soil sampling programme, holes were confined to P39/5463 for an advance of 600m (20x30m holes) the best drill intersections returned 1.18g/t Au from 24m in AR014 and 0.53g/t Au from 8m in AR017. The work was never followed up. (A Report 23825, Payne 1988) Geology The regional geology comprises a suite of NNE trending greenstones positioned on the western limb of the Kilkenny Syncline in contact, to the north, with a large porphyritic magnetic granite (Nambi Granite). The greenstones comprise a succession of tholeiitic mafic volcanics, high magnesian basalts, chert, ultramafic rocks and a variety of mafic intrusives, 12 P a g e

13 Criteria ASX Code: KIN Commentary including mid-coarse gabbroic and dioritic rocks sometimes with large phenocrysts of altered feldspar locally known as cat rock. Exploration is targeting modest sized but high grade lode and/or shear hosted gold mineralisation similar to other deposits in the local district. Drill hole Information Data Aggregation methods In all 441 vertical auger drill holes have been completed, the maximum hole depth is 1.2m. The location of the hole collars is presented as a plan in the in the body of this report. The gold-in-soil results have been plotted and contoured (+5ppb Au). It is considered impractical to list a table of drill hole details in this report format. No averaging of the raw assay data was applied. Raw data was used to determine the location of gold-in-soil anomalies and anomalous gold trends. Geological assessment and interpretation was used to determine the relevance of the plotted anomalies with respect to the sampled regolith. No upper cuts were applied to determine anomalous gold areas, however results <5ppb Au are considered to represent background values and are considered to be below what is regarded as anomalous or significant. Relationship Between Mineralisation widths and intercept lengths Diagrams Balanced Reporting Other Substantive exploration data Further work All assay results are collected from individual auger drill holes, only one sample was collected from each hole. Samples are regarded as composite samples. The maximum sample width is 1.2m, 441 samples were collected, and the average sample width is 0.213m. Relevant type example plans and diagrams are included in this report. Detailed assay results are diagrammatically displayed in this report. Only the gold results are discussed and reported however analysis for several elements including Bi, As, Cr, Cu, W, Ni, Pb & Zn (ppm detection) was also conducted. Regarding the results received no other substantive data is currently considered necessary, given the early stage of exploration activities at this time. The gold-in-soil anomalies will be assessed to determine which anomalies should be tested further. An additional soil sampling programme is required over areas that returned significant results. Any follow up soil sampling programme will be closer spaced and designed to target the higher order gold-in-soil results. Once additional point data is collected, assayed and interrogated anomalies can be followed up via drill tested. 13 P a g e

14 KIN MINING NL TENEMENT SCHEDULE TENEMENT INFORMATION AS REQUIRED BY LISTING RULE DESDEMONA - 20 kms South of Leonora Townsite REDCASTLE - 65 kms South West of Laverton Tenement ID Ownership at end of Quarter Change During Quarter Tenement ID Ownership at end of Quarter Change During Quarter E37/ % P39/4528 0% Expired E37/ % P39/ % E37/ % P39/ % E37/ % P39/ % P37/ % P39/ % P37/ % P39/ % E40/ % P39/ % E40/ % P39/ % E40/320 0% Forfeited P39/ % E40/ % P39/ % M40/ % P39/ % P37/ % P39/ % P37/ % P39/ % P40/ % P39/ % P40/ % MT FLORA - 50 kms East North East of Leonora P40/ % Tenement ID Ownership at end of Quarter Change During Quarter P40/ % P39/ % P40/ % P39/ % P40/ % P39/ % IRON KING / VICTORY - 45 kms North North West of Leonora P39/ % Tenement ID Ownership at end of Quarter Change During Quarter P39/ % P37/ % P39/ % P37/ % P39/ % P37/ % P39/ % P37/ % P39/ % P37/ % P39/ % P37/ % P39/ % P37/ % P39/ % P37/ % P39/ % P37/ % RANDWICK - 45 kms North East of Leonora P37/ % Tenement ID Ownership at end of Quarter Change During Quarter P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % MURRIN MURRIN - 50 kms East of Leonora P37/ % Tenement ID Ownership at end of Quarter Change During Quarter P37/ % M39/ % P37/ % P39/ % P37/ % P39/ % P37/ % P39/ % P37/ % P39/ % P37/ % P39/ % P39/ % P39/ % P39/ % P39/ % P39/ % P39/ % P39/ % P39/ % P39/ % 14 P a g e

15 NAVIGATOR MINING PTY LTD TENEMENT SCHEDULE (a wholly owned subsidry of Kin Mining NL) TENEMENT INFORMATION AS REQUIRED BY LISTING RULE RAESIDE - 8 kms East of Leonora Townsite Tenement ID Ownership at end of Quarter Change During Quarter Tenement ID Ownership at end of Quarter Change During Quarter E37/ % P37/ % E37/ % P37/ % L37/ % P37/ % L37/77 100% P37/ % M37/ % P37/ % CARDINIA / MERTONDALE - 35 kms East & North East of Leonora Townsite P37/ % Tenement ID Ownership at end of Quarter Change During Quarter P37/ % L37/ % P37/ % L37/ % P37/ % L37/ % P37/ % L37/ % P37/ % L37/ % P37/ % L37/65 100% P37/ % M37/ % P37/ % M37/ % P37/ % M37/ % P37/ % M37/ % P37/ % M37/ % P37/ % M37/ % P37/ % M37/ % P37/ % M37/ % P37/ % M37/ % P37/ % M37/ % P37/ % M37/ % P37/ % M37/ % P37/ % M37/ % P37/ % M37/ % P37/ % M37/ % P37/ % M37/646 80% P37/ % M37/ % P37/ % M37/81 100% P37/ % M37/82 100% P37/ % M37/86 100% P37/ % M37/88 100% P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % CARDINIA / MERTONDALE - 35 kms East & North East of Leonora Townsite 15 P a g e

16 CARDINIA / MERTONDALE - 35 kms East & North East of Leonora Townsite Tenement ID Ownership at end of Quarter Change During Quarter P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % P37/ % Expired P37/ % Expired P37/ % Expired P37/ % P37/ % P37/ % P37/ % P37/ % P39/ % Expired P a g e

Quarterly Report Highlights. Ulysses Gold Project, Western Australia. Viking Gold Project, Western Australia

Quarterly Report Highlights. Ulysses Gold Project, Western Australia. Viking Gold Project, Western Australia ASX Announcement Quarterly Activities Report For the Quarter Ended 31 December 2015 29 January 2016 Genesis Minerals Limited ASX Code: GMD Issued Capital 446 million shares 27.2 million options Current

More information

GEOLOGICAL REINTERPETATION LEADS TO MAJOR DRILL PROGRAM AT JUPITER

GEOLOGICAL REINTERPETATION LEADS TO MAJOR DRILL PROGRAM AT JUPITER GEOLOGICAL REINTERPETATION LEADS TO MAJOR DRILL PROGRAM AT JUPITER Dacian Gold Ltd ( Dacian or the Company ) (ASX:DCN) is pleased to announce that it has completed a major geological review and reinterpretation

More information

Australian Stock Exchange Limited Company Announcements NO. OF PAGES : (5) Level 10, 20 Bond Street SYDNEY NSW 2000

Australian Stock Exchange Limited Company Announcements NO. OF PAGES : (5) Level 10, 20 Bond Street SYDNEY NSW 2000 6 November 2006 Australian Stock Exchange Limited Company Announcements NO. OF PAGES : (5) Level 10, 20 Bond Street SYDNEY NSW 2000 TROPICANA JV (IGO 30%) PROJECT UPDATE KEY POINTS: New significant drill

More information

QUARTERLY ACTIVITIES REPORT

QUARTERLY ACTIVITIES REPORT ASX Announcement 30 January 2008 QUARTERLY ACTIVITIES REPORT FOR THE PERIOD ENDING 31 DECEMBER 2007 OVERVIEW Electromagnetic (EM) geophysical surveys were conducted during the quarter within the Nagambie

More information

HIGH GRADE GOLD DRILL RESULTS MT EGERTON PROJECT

HIGH GRADE GOLD DRILL RESULTS MT EGERTON PROJECT July 7 th, 2015 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 HIGH GRADE GOLD DRILL RESULTS MT EGERTON PROJECT RC Drilling has returned shallow high grades at the Gaffney

More information

ST GEORGE ACQUIRES NICKEL SULPHIDE PROJECTS

ST GEORGE ACQUIRES NICKEL SULPHIDE PROJECTS ASX / MEDIA RELEASE 18 September 2015 HIGHLIGHTS: ST GEORGE ACQUIRES NICKEL SULPHIDE PROJECTS St George acquires 100% of the Hawaii and Mt Alexander North nickel sulphide exploration projects from BHP

More information

Exploration Update - Corunna

Exploration Update - Corunna ASX RELEASE 27 th August 2015 ASX: MGV Exploration Update - Corunna Anomalous lead, zinc and silver identified in aircore drilling at the Corunna project in South Australia Anomalous silver-lead-zinc zone

More information

For personal use only

For personal use only Investigator Resources Limited Date: 7 th February 2012 up to 2.25% Ag at the new Paris prospect in South Australia First assays received for new drilling on Paris Line 7 with all three holes assayed returning

More information

De Grey Mining Ltd. Wingina Deeps Drilling Commenced (Turner River Project) Highlights. Turner River Unlocking Shareholder Value

De Grey Mining Ltd. Wingina Deeps Drilling Commenced (Turner River Project) Highlights. Turner River Unlocking Shareholder Value De Grey Mining Ltd ASX RELEASE 5 July 2016 ASX Code DEG ABN 65 094 206 292 Wingina Deeps Drilling Commenced (Turner River Project) Highlights Diamond drilling programme of approximately 1,500m has COMPANY

More information

QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 30 SEPTEMBER 2015

QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 30 SEPTEMBER 2015 ASX RELEASE ASX:AWV 30 October 2015 QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 30 SEPTEMBER 2015 HIGHLIGHTS Pit optimisation and final mine design completed Metallurgical test work completed Engineering

More information

QUARTERLY ACTIVITIES REPORT FOR THE PERIOD ENDED 30 SEPTEMBER 2015

QUARTERLY ACTIVITIES REPORT FOR THE PERIOD ENDED 30 SEPTEMBER 2015 ASX ANNOUNCEMENT MEDIA RELEASE 30 October 2015 QUARTERLY ACTIVITIES REPORT FOR THE PERIOD ENDED 30 SEPTEMBER 2015 HIGHLIGHTS RC drilling identified wide mineralised gold zones north of original Namdini

More information

Queensland Mining Corporation L I M I T E D. Maiden JORC Resources Estimate for Horseshoe Copper Deposit, Duck Creek, South Cloncurry District

Queensland Mining Corporation L I M I T E D. Maiden JORC Resources Estimate for Horseshoe Copper Deposit, Duck Creek, South Cloncurry District ASX Release 12 October 2012 Maiden JORC Resources Estimate for Horseshoe Copper Deposit, Duck Creek, South Cloncurry District Total mineral resource at Duck Creek Project area of 960,000t @ 1.47% Cu (0.2%

More information

Mining Indaba Presentation. Capetown, South Africa 8 th 10 th February 2016

Mining Indaba Presentation. Capetown, South Africa 8 th 10 th February 2016 Mining Indaba Presentation Capetown, South Africa 8 th 10 th February 2016 www.birimiangold.com 1 Disclaimer This presentation has been prepared by Birimian Gold Limited (BGS) for general information purposes

More information

Falcon Minerals Ltd ACN 009 256 535 Company Announcement

Falcon Minerals Ltd ACN 009 256 535 Company Announcement Falcon Minerals Ltd ACN 009 256 535 Company Announcement First Floor, 14 Outram Street, West Perth WA 6005 Telephone: +61 8 9481 3322 PO Box 913 West Perth WA 6872 Facsimile: +61 8 9481 3330 Date: 30 April

More information

COPPER DISCOVERY GROWS AT TURKEY CREEK

COPPER DISCOVERY GROWS AT TURKEY CREEK 28 October 2014 ASX: AOH, FSE: A2O COPPER DISCOVERY GROWS AT TURKEY CREEK HIGHLIGHTS RC drilling highlights prospectivity of Cloncurry Copper Project Infill and Extension RC drilling about to recommence

More information

Chalice advances gold exploration initiatives in Australia and Canada

Chalice advances gold exploration initiatives in Australia and Canada ABN 47 116 648 956 ASX Announcement 4 July 2016 Chalice advances gold exploration initiatives in Australia and Canada Low-cost exploration planned to evaluate opportunities in two world-class gold provinces

More information

ALCYONE REPORTS JORC SILVER RESOURCES

ALCYONE REPORTS JORC SILVER RESOURCES ASX ANNOUNCEMENT & MEDIA RELEASE 29 March 2010 ALCYONE REPORTS JORC SILVER RESOURCES +15Moz RESOURCE INVENTORY UNDERPINS PROGRAM TARGETING RESUMPTION OF SILVER PRODUCTION AT TEXAS PROJECT LATER THIS YEAR

More information

New technology and new approach uncovers new opportunities in WA s Fraser Range

New technology and new approach uncovers new opportunities in WA s Fraser Range ASX Code: WIN New technology and new approach uncovers new opportunities in WA s Fraser Range Investor Update May 2016 Bronwyn Barnes, Executive Chair Important Information The information contained in

More information

Positioned for Production: Exploring for Growth

Positioned for Production: Exploring for Growth ASX Code: AYN Positioned for Production: Exploring for Growth Andrew King, Managing Director May 2010 Pg 1 Disclaimer and Key Information Disclaimer This presentation has been prepared by the Directors

More information

ASX ANNOUNCEMENT Date: 3 February 2016 Number: 449/030216

ASX ANNOUNCEMENT Date: 3 February 2016 Number: 449/030216 ASX ANNOUNCEMENT Date: 3 February 2016 Number: 449/030216 VERY HIGH GRADE PGM-COPPER-NICKEL IN MASSIVE NICKEL COPPER SULPHIDE AT PLATINUM SPRINGS, N.S.W. 0.6 metres at 11.5 g/t platinum, 25.6 g/t palladium,

More information

Pacifico set to commence drilling at Borroloola West Project and co-funding secured from NT Government

Pacifico set to commence drilling at Borroloola West Project and co-funding secured from NT Government CORPORATE DIRECTORY Managing Director Simon Noon Directors Richard Monti (Chairman) Peter Harold (Non-exec.) Andrew Parker (Non-exec.) Company Secretary Joshua Ward Patrick Holywell Registered office Level

More information

For personal use only. MRV Metals Launch February 2016

For personal use only. MRV Metals Launch February 2016 MRV Metals Launch February 2016 Important Information This document has been prepared by Moreton Resources Limited ( Moreton or Company ) for the purpose of providing a company and technical overview to

More information

QUARTERLY REPORT HIGHLIGHTS. Three Months Ending: 30 September 2012 BUTCHERBIRD MANGANESE:

QUARTERLY REPORT HIGHLIGHTS. Three Months Ending: 30 September 2012 BUTCHERBIRD MANGANESE: QUARTERLY REPORT Three Months Ending: 30 September 2012 ASX CODE: MZM ISSUED SHARES: 67.66M 52 WEEK HIGH: $0.80 52 WEEK LOW: $0.16 CASH ON HAND: $6.13M CONTACT: JUSTIN BROWN Managing Director +61 8 6315

More information

DRILLING COMMENCES AT REMBRANDT GOLD PROJECT

DRILLING COMMENCES AT REMBRANDT GOLD PROJECT ASX Release 8 th October 2015 DRILLING COMMENCES AT REMBRANDT GOLD PROJECT HIGHLIGHTS Terrain has commenced drilling at the Rembrandt Gold Project and is targeting high grade near surface gold at the Monet

More information

For personal use only

For personal use only January, 202 Silver Swan Group Limited December 20 Quarterly Activities Report HIGHLIGHTS STAKEWELL Gold Project: Drilling intersected high and low grade gold mineralisation at Kohinoor, including surface

More information

AIM: KEFI 6 March 2014. KEFI Minerals Plc. ( KEFI or the Company ) SAUDI ARABIAN EXPLORATION AND DEVELOPMENT UPDATE

AIM: KEFI 6 March 2014. KEFI Minerals Plc. ( KEFI or the Company ) SAUDI ARABIAN EXPLORATION AND DEVELOPMENT UPDATE KEFI Minerals Plc Doğu Akdeniz Mineralleri San. Tic. Ltd. Şti. Cemal Gürsel Cad. Yalı Apt. No:304 K:4 D:9 Karşıyaka İZMİR Tel: +90 232 381 9431 Fax: +90 232 381 9071 Email: info@kefi-minerals.com AIM:

More information

For personal use only

For personal use only ASX Release 27 September 2012 OPTION TO ACQUIRE 560,000oz PEAK HILL GOLD PROJECT RESOURCE AND INVESTMENT NL (ASX: RNI) (RNI or the Company) has reached agreement with Montezuma Mining Company Limited for

More information

NEW DRILLING RESULTS FROM THE CLONCURRY PROJECT

NEW DRILLING RESULTS FROM THE CLONCURRY PROJECT 8 October 2015 ASX: AOH, FSE: A2O NEW DRILLING RESULTS FROM THE CLONCURRY PROJECT Excellent results from previously un-assayed drill core. Best intersection of 29.1 metres at 1.41% copper, 0.11g/t gold.

More information

MULTIPLE NEW GOLD ZONES DISCOVERED IN REGIONAL EXPLORATION DRILLING AT DALGARANGA

MULTIPLE NEW GOLD ZONES DISCOVERED IN REGIONAL EXPLORATION DRILLING AT DALGARANGA February 8 th, 2016 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 MULTIPLE NEW GOLD ZONES DISCOVERED IN REGIONAL EXPLORATION DRILLING AT DALGARANGA Significant new gold

More information

JACQUES GOLD PROSPECT RETURNS 37.7g/t. Re-assay of 1m samples from initial drilling program at Jacques returns gold grades of up to 37.

JACQUES GOLD PROSPECT RETURNS 37.7g/t. Re-assay of 1m samples from initial drilling program at Jacques returns gold grades of up to 37. ASX Announcement 15 January 2013 JACQUES GOLD PROSPECT RETURNS 37.7g/t Re-assay of 1m samples from initial drilling program at Jacques returns gold grades of up to 37.7g/t Second phase drilling program

More information

HORSE WELL GOLD PROJECT W.A

HORSE WELL GOLD PROJECT W.A December 2015 Quarterly Activities Report ABN 20 109 361 195 ASX Release 29 January 2016 Alloy Resources Ltd Suite 6, 7 The Esplanade Mount Pleasant WA 6153 Tel: +61 8 9316 9100 Fax: +61 8 9315 5475 Email:

More information

HIGH GRADE DRILL RESULTS CONTINUE AT THE KYLYLAHTI MINE

HIGH GRADE DRILL RESULTS CONTINUE AT THE KYLYLAHTI MINE 22 August 2013 ASX: AOH, FSE: A2O HIGH GRADE DRILL RESULTS CONTINUE AT THE KYLYLAHTI MINE Upper part of Wombat zone returns excellent drilling intersections: - 29.0m at 4.7% copper - 37.6m at 3.2% copper

More information

Expansion drilling at Mt Marion Lithium Project yields positive results

Expansion drilling at Mt Marion Lithium Project yields positive results 29 January 2016 Level 1, 672 Murray Street West Perth WA 6005 Locked Bag 8 West Perth WA 6872 t. +61 8 9322 1182 f. +61 8 9321 0556 info@neometals.com.au neometals.com.au Neometals Ltd ABN 89 099 116 631

More information

FINAL FURTHER HIGH GRADE COPPER RESULTS IN SURFACE FLOAT SAMPLES AT NAKRU

FINAL FURTHER HIGH GRADE COPPER RESULTS IN SURFACE FLOAT SAMPLES AT NAKRU 5 June 2015 ASX Code: COY FINAL FURTHER HIGH GRADE COPPER RESULTS IN SURFACE FLOAT SAMPLES AT NAKRU Mineral explorer Coppermoly Limited (Coppermoly and the Company) is pleased to announce final assay results

More information

Further Basement Gold Results Confirm Yamarna Gold Potential

Further Basement Gold Results Confirm Yamarna Gold Potential ABOUT MONTEZUMA MINING Listed in 2006, Montezuma Mining Company Ltd (ASX: MZM) is a diversified explorer primarily focused on manganese, copper and gold. The Company s primary objective is to achieve returns

More information

RC drilling identifies high grade gold in bedrock at Pacific Dunes Corkwood Camp Scale Target

RC drilling identifies high grade gold in bedrock at Pacific Dunes Corkwood Camp Scale Target ASX Announcement 29 January 2016 Quarterly Report For the period ending 31 December 2015 ASX Code GOR ABN 13 109 289 527 Highlights Solid progress on Gruyere Pre Feasibility Study Gruyere PFS remains on

More information

Quarterly Activities Report - for the period ended 31 December 2015

Quarterly Activities Report - for the period ended 31 December 2015 ASX Release: 27 January 2016 Quarterly Activities Report - for the period ended 31 December 2015 ASX Code: WRM Issued Securities Shares: 271.9 million Options: 7 million Cash on hand (31 Dec 2015) $0.4M

More information

f or the P ROJECT Agreement with copper-gold Bluebird. comprises a 1.6 mineralisation are often discordant to the Proterozoic deposits found in HIG

f or the P ROJECT Agreement with copper-gold Bluebird. comprises a 1.6 mineralisation are often discordant to the Proterozoic deposits found in HIG ASX ANNOUNCEMENT 30 April 2015 QUARTERLY ACTIVITIES f or the quarterr ended REPORT 31 Mar ch 2015 BARKLY COPPER-GOLD Limited is in a Farm-In Joint Venture P ROJECT Blaze International Agreement with Meteoric

More information

ACTIVITIES REPORT FOR THE QUARTER ENDED 31 DECEMBER 2014

ACTIVITIES REPORT FOR THE QUARTER ENDED 31 DECEMBER 2014 Second Floor, 9 Havelock Street West Perth WA 6005 Postal Address: PO Box 689, West Perth WA 6872 ABN 60 060 628 524 Telephone: (618) 9481 8444 Facsimile: (618) 9481 8445 Email: info@hamptonhill.com.au

More information

IP survey expands gold prospectivity at Dixon, Doolgunna Marymia Project

IP survey expands gold prospectivity at Dixon, Doolgunna Marymia Project 27 January 2016 IP survey expands gold prospectivity at Dixon, Doolgunna Marymia Project 200 metre long chargeability zone detected at the Dixon gold prospect o Sulphidic quartz veining the likely source

More information

JUNE 2015 QUARTERLY REPORT

JUNE 2015 QUARTERLY REPORT ANNOUNCEMENT TO THE AUSTRALIAN SECURITIES EXCHANGE: 31 JULY 2015 JUNE 2015 QUARTERLY REPORT WCP Resources Limited ( WCP or Company ) presents its June 2015 quarterly report. Highlights during the quarter

More information

ANNUAL GENERAL MEETING. Investor Presentation 24 November 2015

ANNUAL GENERAL MEETING. Investor Presentation 24 November 2015 ANNUAL GENERAL MEETING Investor Presentation 24 November 2015 Corporate Structure ASX Code: OVR Shares on Issue 205.4 million Top 20 133.0 million (64.8%) Market Capitalisation $1.23 million (share price

More information

Core : CXO. and. Uranium Session SAREIC Conference Adelaide 13th April 2015

Core : CXO. and. Uranium Session SAREIC Conference Adelaide 13th April 2015 Core : CXO and Uranium Session SAREIC Conference Adelaide 13th April 2015 Disclaimer The information in this report that relates to Exploration Results and Mineral Resources is based on information compiled

More information

Exploration and Development Activity

Exploration and Development Activity For the period ending 30 June 2008 Exploration and Development Activity Over the last year, exploration and development work at the Company s Nullagine Gold Project in Western Australia s eastern Pilbara

More information

Punching Above Its Weight

Punching Above Its Weight Punching Above Its Weight Stephen Stone Managing Director Helmsec Global Capital New Dawn Resources Forum Hong Kong 25 th March 2010 Leveraged to Gold Price, Resource Upgrades Very modest ~A$45M market

More information

POTENTIAL NEW SYENITE CORRIDORS IDENTIFIED FOLLOWING DETAILED MAGNETIC SURVEY AT JUPITER

POTENTIAL NEW SYENITE CORRIDORS IDENTIFIED FOLLOWING DETAILED MAGNETIC SURVEY AT JUPITER 4 NOVEMBER 2015 POTENTIAL NEW SYENITE CORRIDORS IDENTIFIED FOLLOWING DETAILED MAGNETIC SURVEY AT JUPITER Dacian Gold Ltd ( Dacian or the Company ) (ASX:DCN) is pleased to announce an update on the exploration

More information

MAXIMUS RESOURCES LIMITED QUARTERLY REPORT

MAXIMUS RESOURCES LIMITED QUARTERLY REPORT MAXIMUS RESOURCES LIMITED QUARTERLY REPORT PERIOD ENDING 31 December 2015 SUMMARY CORPORATE Private share placement to sophisticated Investors was completed with $200,000 received A Share Purchase Plan

More information

FOCUS MINERALS LIMITED

FOCUS MINERALS LIMITED FOCUS MINERALS LIMITED Aggressively Expanding into a Rising Gold Price Campbell Baird, Chief Executive Officer ASX: FML www.focusminerals.com.au 2 Disclaimer and Competent Person s Statement This presentation

More information

New Cascade drill results and Ulanzi drill update

New Cascade drill results and Ulanzi drill update New Cascade drill results and Ulanzi drill update 1 October 2015 Highlights Assays from the next two Cascade drill holes continue returning excellent intervals: o 98m@ 8.92% TGC including 40m@ 10.18% from

More information

ALCYONE TO RAISE $5M TO UNDERPIN TRANSITION TO SILVER PRODUCTION AT TEXAS PROJECT

ALCYONE TO RAISE $5M TO UNDERPIN TRANSITION TO SILVER PRODUCTION AT TEXAS PROJECT ASX ANNOUNCEMENT & MEDIA RELEASE 25 November 2010 ALCYONE TO RAISE $5M TO UNDERPIN TRANSITION TO SILVER PRODUCTION AT TEXAS PROJECT ENTITLEMENT OFFER TO FUND FURTHER EXPLORATION, ACQUISITION OF LONG-LEAD

More information

For personal use only

For personal use only Investor Presentation August 2012 Disclaimer/Competent Person s Disclaimer: This presentation has been prepared by Buxton Resources ( Buxton ). The information contained in this presentation is a professional

More information

ASX Announcement (ASX: HMX)

ASX Announcement (ASX: HMX) ASX Announcement (ASX: HMX) 18 th March 2015 Drilling at Hammertime and Overlander to commence 3D-IP enhances gravity and magnetic target at Overlander North IOCG Hammer Metals Limited (ASX: HMX) ( Hammer

More information

SILVERCORP INTERCEPTS 18.8 METRES TRUE WIDTH GRADING 368 G/T SILVER AND 1.78 PERCENT LEAD AT THE LM MINE WEST, YING MINING DISTRICT, CHINA

SILVERCORP INTERCEPTS 18.8 METRES TRUE WIDTH GRADING 368 G/T SILVER AND 1.78 PERCENT LEAD AT THE LM MINE WEST, YING MINING DISTRICT, CHINA NEWS RELEASE Trading Symbol: TSX: SVM NYSE: SVM SILVERCORP INTERCEPTS 18.8 METRES TRUE WIDTH GRADING 368 G/T SILVER AND 1.78 PERCENT LEAD AT THE LM MINE WEST, YING MINING DISTRICT, CHINA VANCOUVER, British

More information

QUARTERLY ACTIVITIES REPORT TO 30 SEPTEMBER 2015

QUARTERLY ACTIVITIES REPORT TO 30 SEPTEMBER 2015 29 October 2015 QUARTERLY ACTIVITIES REPORT TO 30 SEPTEMBER 2015 Scoping Study Highlights Mt Morgans Gold Project (MMGP) Scoping Study was released during the quarter. Key outcomes include: An estimated

More information

Barkly Phosphate Project Tenement Granted

Barkly Phosphate Project Tenement Granted MANTLE MINING ASX: MNM DIRECTORS Mr Martin Blakeman Non-Executive Chairman Mr Ian Kraemer Managing Director Mr Peter Anderton Non-Executive Director Mr Stephen de Belle Non-Executive Director ASX Release

More information

Resources Rising Stars

Resources Rising Stars ASX Code: AYN Resources Rising Stars Andrew King, Managing Director September 2010 Pg 1 Disclaimer and Key Information Disclaimer This presentation has been prepared by the Directors of Alcyone Resources

More information

INVESTOR PRESENTATION

INVESTOR PRESENTATION BUREY GOLD LIMITED BYR INVESTOR PRESENTATION Klaus Eckhof, Mark Gasson August 2014 1 Disclaimer The Material in this presentation ( material ) is not and does not constitute an offer, invitation or recommendation

More information

Tsunsten and Tin Imprints in South East Asia

Tsunsten and Tin Imprints in South East Asia ASX/ Media Announcement 13 October 2014 Vital Metals Limited ASX Code: VML ACN: 112 032 596 VITAL METALS DELIVERS NEW TUNGSTEN PROSPECT BUILDS EXPLORATION PIPELINE TO SUPPORT DEVELOPMENT OF WATERSHED PROJECT

More information

MORE STRONG NICKEL HITS FOR MINCOR AS KAMBALDA DISCOVERIES GROW

MORE STRONG NICKEL HITS FOR MINCOR AS KAMBALDA DISCOVERIES GROW MEDIA RELEASE Thursday, 11 December 2014 MORE STRONG NICKEL HITS FOR MINCOR AS KAMBALDA DISCOVERIES GROW High-grade intersections at Cassini and Burnett Drilling ramps up Strong new intersections returned

More information

NORTH PORTIA RESOURCE SUPPORTED BY NEW DRILLING RESULTS

NORTH PORTIA RESOURCE SUPPORTED BY NEW DRILLING RESULTS Havilah Resources Limited plans to sequentially develop its portfolio of gold, copper, iron, cobalt, tin and other mineral resources in South Australia. Our vision is to become a new mining force, delivering

More information

Leapfrog : new software for faster and better 3D geological modelling

Leapfrog : new software for faster and better 3D geological modelling Leapfrog : new software for faster and better 3D geological modelling Paul Hodkiewicz, Principal Consultant (Geology), SRK Consulting, 10 Richardson Street, West Perth WA 6005, Australia, phodkiewicz@srk.com.au

More information

MAJOR NEW COPPER EXPLORATION PROGRAM UNDERWAY IN NORTH QUEENSLAND

MAJOR NEW COPPER EXPLORATION PROGRAM UNDERWAY IN NORTH QUEENSLAND Assets, Experience, Growth ASX ANNOUNCEMENT 7 July 2015 MAJOR NEW COPPER EXPLORATION PROGRAM UNDERWAY IN NORTH QUEENSLAND DEEP DIAMOND DRILLING COMMENCING AT BARBARA THIS WEEK, AIRBORNE VTEM UNDERWAY AND

More information

QUARTERLY REPORT December 2015

QUARTERLY REPORT December 2015 December 2015 HIGHLIGHTS Outstanding aircore results pave way for imminent RC drilling program to test potentially major greenfields discovery Lake Roe Gold Project km east of Kalgoorlie (% Breaker) Two

More information

EXTENSIVE GOLD IN SOILS TARGET IDENTIFIED AT MOMBUCA GOLD PROJECT, SE BRAZIL

EXTENSIVE GOLD IN SOILS TARGET IDENTIFIED AT MOMBUCA GOLD PROJECT, SE BRAZIL 9 July 2015 EXTENSIVE GOLD IN SOILS TARGET IDENTIFIED AT MOMBUCA GOLD PROJECT, SE BRAZIL Open ended target zone up to 1.5km long identified Key Points Prospectivity of Centaurus recently secured Mombuca

More information

For personal use only

For personal use only 22 September 2015 The Manager Market Announcements Office ASX Limited PO Box H224 Australia Square SYDNEY NSW 2001 Dear Sir/Madam EXPLORATION UPDATE PRESENTATION Please find attached a presentation which

More information

New Lithium Project includes largest tin tantalum mine in NT HIGHLIGHTS. Core has extended its lithium focus in the prospective Bynoe pegmatite field

New Lithium Project includes largest tin tantalum mine in NT HIGHLIGHTS. Core has extended its lithium focus in the prospective Bynoe pegmatite field ASX ANNOUNCEMENT ASX : CXO 8 th February 2016 New Lithium Project includes largest tin tantalum mine in NT HIGHLIGHTS Core has extended its lithium focus in the prospective Bynoe pegmatite field NT into

More information

Johnnycake (EPM 18986) - background

Johnnycake (EPM 18986) - background Forte Consolidated Limited QUARTERLY REPORT 1 October 2015 to 31 December 2015 ASX: FRC Forte Consolidated Limited ABN 37 148 168 825 Board of Directors Chairman Executive Director John Terpu Non-Executive

More information

ST GEORGE COMMENCES MAJOR NICKEL SULPHIDE DRILLING CAMPAIGN. High impact drilling campaign has commenced at the East Laverton Project

ST GEORGE COMMENCES MAJOR NICKEL SULPHIDE DRILLING CAMPAIGN. High impact drilling campaign has commenced at the East Laverton Project ASX / MEDIA RELEASE 6 October 2015 ST GEORGE COMMENCES MAJOR NICKEL SULPHIDE DRILLING CAMPAIGN HIGHLIGHTS: High impact drilling campaign has commenced at the East Laverton Project Testing priority nickel

More information

For personal use only

For personal use only Korab Resources Limited Gold Operations Update November 2012 Andrej K. Karpinski Executive Chairman Korab Projects BOBRIKOVO MELROSE 1 Korab Gold Projects Other Korab Projects Robust Undervalued Gold Portfolio

More information

Akjoujt South Project: Drilling Update and Ground Magnetic Anomalies Identified

Akjoujt South Project: Drilling Update and Ground Magnetic Anomalies Identified ANNOUNCEMENT TO THE AUSTRALIAN SECURITIES EXCHANGE Akjoujt South Project: Drilling Update and Ground Magnetic Anomalies Identified The Board of OreCorp Limited (OreCorp or the Company) is pleased to provide

More information

RIDDARHYTTAN RESOURCES PRESS RELEASE August 11, 2003

RIDDARHYTTAN RESOURCES PRESS RELEASE August 11, 2003 1 RIDDARHYTTAN RESOURCES PRESS RELEASE August 11, 2003 New drill holes in the Suurikuusikko area, Finland, have further intersected high gold grades over considerable widths, increasing the depth extent

More information

HALF-YEAR REPORT TO 30 JUNE 2003

HALF-YEAR REPORT TO 30 JUNE 2003 HALF-YEAR REPORT TO 30 JUNE 2003 PO Box 2000, Subiaco, Western Australia 6904 Registered Office: 230 Rokeby Road, Subiaco, Western Australia 6008 Telephone: +61 8 9388 9697, 9381 5771 Facsimile: +61 8

More information

QUARTERLY ACTIVITY REPORT FOR THE PERIOD ENDED 31 st December 2015

QUARTERLY ACTIVITY REPORT FOR THE PERIOD ENDED 31 st December 2015 STRATEGIC MINERALS CORPORATION N.L. 29th January 2016 ASX Release ASX Code: SMC QUARTERLY ACTIVITY REPORT FOR THE PERIOD ENDED 31 st December 2015 WOOLGAR GOLD PROJECT QUEENSLAND (100% SMC) Highlights

More information

MOMBUCA GOLD PROJECT: STRONG GOLD GRADES FROM TRENCHING CONFIRM PRESENCE OF STACKED QUARTZ VEIN SYSTEM

MOMBUCA GOLD PROJECT: STRONG GOLD GRADES FROM TRENCHING CONFIRM PRESENCE OF STACKED QUARTZ VEIN SYSTEM 2 February 2016 MOMBUCA GOLD PROJECT: STRONG GOLD GRADES FROM TRENCHING CONFIRM PRESENCE OF STACKED QUARTZ VEIN SYSTEM Grades of up to 3.1 g/t Au from new trenching program; Induced Polarisation (IP) survey

More information

Significant Nickel Sulphides at Killaloe JV Project

Significant Nickel Sulphides at Killaloe JV Project Decem000000000000000000000000000000000000000 000ber 2012 LIMITED ABN 48 106 732 487 ASX Announcement 16 June 2014 Significant Nickel s at Killaloe JV Project Highlights 14.65m of komatiite hosted nickel

More information

CHALICE GOLD MINES AND SUB SAHARA RESOURCES ANNOUNCE PROPOSED MERGER TO CONSOLIDATE AND FUND ERITREAN GOLD PROJECT

CHALICE GOLD MINES AND SUB SAHARA RESOURCES ANNOUNCE PROPOSED MERGER TO CONSOLIDATE AND FUND ERITREAN GOLD PROJECT 3 APRIL 2009 CHALICE GOLD MINES AND SUB SAHARA RESOURCES ANNOUNCE PROPOSED MERGER TO CONSOLIDATE AND FUND ERITREAN GOLD PROJECT Key Points Chalice Gold Mines and Sub Sahara Resources agree to merge by

More information

Quarterly Report. For the Quarter Ended 30 June 2004. Vulcan is maintaining its low cost exposure to West Australian gold exploration.

Quarterly Report. For the Quarter Ended 30 June 2004. Vulcan is maintaining its low cost exposure to West Australian gold exploration. Quarterly Report For the Quarter Ended 30 June 2004 Vulcan is maintaining its low cost exposure to West Australian gold exploration. Yerilla Joint Venture (Sons of Gwalia earning 75%) Sons of Gwalia are

More information

BOADICEA RESOURCES. Additional Conductors Identified at Symons Hill in the Fraser Range from VTEM max Survey.

BOADICEA RESOURCES. Additional Conductors Identified at Symons Hill in the Fraser Range from VTEM max Survey. ASX Announcement- 17th June 2014 ASX Code: BOA BOADICEA RESOURCES Additional Conductors Identified at Symons Hill in the Fraser Range from VTEM max Survey. Highlights The final interpretation of the 2013

More information

Keras Resources plc ( Keras or the Company ) Moving Towards First Production in Q2 2016 at Grants Patch Gold Tribute Project, Australia

Keras Resources plc ( Keras or the Company ) Moving Towards First Production in Q2 2016 at Grants Patch Gold Tribute Project, Australia Keras Resources plc / Index: AIM / Epic: KRS / Sector: Mining 14 January 2016 Keras Resources plc ( Keras or the Company ) Moving Towards First Production in Q2 2016 at Grants Patch Gold Tribute Project,

More information

TORONTO STOCK EXCHANGE COMPANY MANUAL APPENDIX B DISCLOSURE STANDARDS FOR COMPANIES ENGAGED IN MINERAL EXPLORATION, DEVELOPMENT & PRODUCTION

TORONTO STOCK EXCHANGE COMPANY MANUAL APPENDIX B DISCLOSURE STANDARDS FOR COMPANIES ENGAGED IN MINERAL EXPLORATION, DEVELOPMENT & PRODUCTION B-1 APPENDIX B DISCLOSURE STANDARDS FOR COMPANIES ENGAGED IN MINERAL EXPLORATION, DEVELOPMENT & PRODUCTION 1.0 INTRODUCTION The disclosure of the results of exploration and development activity on mineral

More information

For personal use only

For personal use only Quarterly Activities Report For For the the 33 months ending 3130 st December September 2015 ASX: WIN DATE: 27 January DATE 2016 Quarterly Activities Report December 2015 CORPORATE DIRECTORY Executive

More information

Savannah North Scoping Study Looking into the future 3 February 2016

Savannah North Scoping Study Looking into the future 3 February 2016 Savannah North Scoping Study Looking into the future 3 February 2016 ASX: PAN Disclaimer Cautionary Statements This presentation includes information extracted from Panoramic Resources Limited ASX announcement

More information

December 2015 Quarterly Activities Report

December 2015 Quarterly Activities Report December 2015 Quarterly Activities Report Musgrave Minerals Ltd is an Australian focused gold and base metal exploration company. Musgrave plans to grow through the discovery and development of gold and

More information

Discovery at Manwe. Infill and Extension Drilling Commenced. Duri Aircore Programme Completed Results Awaited

Discovery at Manwe. Infill and Extension Drilling Commenced. Duri Aircore Programme Completed Results Awaited Discovery at Manwe ASX & Media Release ASX Code AZM 19th January 2016 First Pass RC Drilling Returns 14m @ 4.92g/t Au from 48m incl 6m at 6.30g/t Au from 54m and 32m @ 2.10g/t Au from surface incl 6m @

More information

BEACONSFIELD GOLD NL Report on Activities for the Quarter ended 30 June 2008

BEACONSFIELD GOLD NL Report on Activities for the Quarter ended 30 June 2008 JUNE 2007 QUARTERLY REPORT BEACONSFIELD GOLD NL Report on Activities for the Quarter ended 30 June 2008 HIGHLIGHTS FOR THE QUARTER OPERATIONAL BEACONSFIELD GOLD MINE The site had operated for 216 days

More information

Quarterly Report December 2015

Quarterly Report December 2015 Quarterly Report December 2015 Highlights Major Asset Acquisition In October TGN announced that it had agreed terms for the acquisition of the Australian tungsten exploration assets of Hazelwood Resources

More information

SILVERCORP REPORTS RESULTS FROM ITS 2012 EXPLORATION PROGRAM AT THE SGX MINE, YING MINING DISTRICT, CHINA

SILVERCORP REPORTS RESULTS FROM ITS 2012 EXPLORATION PROGRAM AT THE SGX MINE, YING MINING DISTRICT, CHINA NEWS RELEASE Trading Symbol: TSX: SVM NYSE: SVM SILVERCORP REPORTS RESULTS FROM ITS 2012 EXPLORATION PROGRAM AT THE SGX MINE, YING MINING DISTRICT, CHINA VANCOUVER, British Columbia June 4, 2013 Silvercorp

More information

Cannon Mine on Track

Cannon Mine on Track ASX Release Thursday 1 October 2015 Cannon Mine on Track Pit development running to schedule Good progress on big pit negotiations with Metals X Stage 1 Open Pit Now At the 347.5m Bench ASX Code: SAU Issued

More information

SILVERCORP INTERCEPTS HIGH GRADE SILVER LEAD ZINC MINERALIZATION AT THE TLP MINE, YING MINING DISTRICT, HENAN PROVINCE, CHINA

SILVERCORP INTERCEPTS HIGH GRADE SILVER LEAD ZINC MINERALIZATION AT THE TLP MINE, YING MINING DISTRICT, HENAN PROVINCE, CHINA NEWS RELEASE Trading Symbol: TSX: SVM NYSE: SVM SILVERCORP INTERCEPTS HIGH GRADE SILVER LEAD ZINC MINERALIZATION AT THE TLP MINE, YING MINING DISTRICT, HENAN PROVINCE, CHINA VANCOUVER, BRITISH COLUMBIA,

More information

Chalcophile and Key Element Distribution in the Eastern Goldfields: seismic traverse EGF01. Aleks Kalinowski Geoscience Australia, pmdcrc Y2 project

Chalcophile and Key Element Distribution in the Eastern Goldfields: seismic traverse EGF01. Aleks Kalinowski Geoscience Australia, pmdcrc Y2 project pmd CR C Chalcophile and Key Element Distribution in the Eastern Goldfields: seismic traverse EGF01 predictive mineral discovery Aleks Kalinowski Geoscience Australia, pmdcrc Y2 project Aleks.Kalinowski@ga.gov.au

More information

For personal use only

For personal use only ASX ANNOUNCEMENT 7 MARCH 2012 Phoenix Copper Limited ABN 67 127 446 271 Level 1, 135 Fullarton Road Rose Park, SA 5067 Australia Telephone +61 (0)8 8364 3188 Facsimile +61 (0)8 8364 4288 info@phoenixcopper.com.au

More information

For personal use only

For personal use only ORA BANDA SOUTH GOLD PROJECT KALGOORLIE GOLDFIELDS WESTERN AUSTRALIA ASX RELEASE 17 FEBRUARY 2016 HIGHLIGHTS Aircore drilling program confirms the presence of primary bedrock gold mineralisation in the

More information

For personal use only

For personal use only 23 August 2013 Technical data supports copper porphyry potential Highlights: Data room initiated following unsolicited approaches from major copper resource companies Technical data supports intact high

More information

How To Mine And Treat Ore From Castle Hill Stage 1

How To Mine And Treat Ore From Castle Hill Stage 1 ` Dated: 5 th August 2014 NORTON TAKES UP OPTION TO MINE AND TREAT ORE FROM CASTLE HILL STAGE 1 ASX: PXG, PXGOA HIGHLIGHTS Development of Castle Hill Stage 1 with Norton Gold Fields potentially adds a

More information

QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 31 DECEMBER 2015

QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 31 DECEMBER 2015 ASX RELEASE ASX:AWV 29 January 2015 QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 31 DECEMBER 2015 HIGHLIGHTS Review of updated pit optimisation undertaken Metallurgical testwork report received confirming

More information

Quarterly Activities Report

Quarterly Activities Report ASX Release Thursday 28 January 215 Quarterly Activities Report ASX Code: SAU Issued Shares: 36.53M Directors Greg Boulton AM (Chair) Simon Mitchell (MD) Michael Billing David Turvey Head Office Southern

More information

TURKEY CREEK PIT OPTIMISATION STUDY ADDS 2 YEARS MINE LIFE TO THE LITTLE EVA PROJECT AT CLONCURRY

TURKEY CREEK PIT OPTIMISATION STUDY ADDS 2 YEARS MINE LIFE TO THE LITTLE EVA PROJECT AT CLONCURRY 10 August 2015 ASX: AOH, FSE: A2O TURKEY CREEK PIT OPTIMISATION STUDY ADDS 2 YEARS MINE LIFE TO THE LITTLE EVA PROJECT AT CLONCURRY Estimated oxide and sulphide resources within the optimum pit is 17.3

More information

DRILLING INTERSECTS WIDE ZONES OF GOLD MINERALISATION AT DUSK TIL DAWN

DRILLING INTERSECTS WIDE ZONES OF GOLD MINERALISATION AT DUSK TIL DAWN ASX Announcement 21 st October 2015 DRILLING INTERSECTS WIDE ZONES OF GOLD MINERALISATION AT DUSK TIL DAWN Intersections of significant thick zones of gold mineralisation confirm a new greenfields gold

More information

EXPLORING WORLD CLASS MINERAL FRONTIERS

EXPLORING WORLD CLASS MINERAL FRONTIERS EXPLORING WORLD CLASS MINERAL FRONTIERS February 2015 1 Disclaimer This presentation has been prepared by Apollo Minerals Limited ( Apollo or the Company ). It should not be considered as an offer or invitation

More information

DRILLING COMMENCES AT STRONG WINDSOR DHEM TARGET

DRILLING COMMENCES AT STRONG WINDSOR DHEM TARGET ASX / MEDIA RELEASE 14 December 2015 HIGHLIGHTS: DRILLING COMMENCES AT STRONG WINDSOR DHEM TARGET Diamond drilling of electromagnetic (EM) plate WINRC016_v1 (210,469 Siemens) has commenced New off hole

More information