1 Large Scale Generation Grid Connection Information Pack 1 st October 2015

2 Factors to consider for a Renewable Energy Project The success of a renewable energy project involves bringing many individual factors together as shown in the above. The connection of your renewable energy project to the Northern Ireland Electricity Networks (NIE Networks ) electricity grid is only one factor to consider in your overall project. This information pack will take you through the key factors to be considered and the steps required when obtaining a grid connection.

3 Connecting Large Scale Generation to the Electricity Network As renewable energy technologies become more mature and common, there is an increasing demand on Northern Ireland Electricity Networks (NIE Networks) to provide connections to the Northern Ireland network. At this point Large Scale Generation (LSG) in the main takes the form of wind farms and more recently solar parks, typically 5-40MW in size. For information on the quantities of connected generation visit: Where a developer wishes to connect and operate a generator in parallel with the NIE Networks electricity grid, the developer must apply to NIE Networks for connection. Once a connection application is successfully processed the developer will then enter into a connection agreement with NIE Networks. Large Scale Generation (LSG) may connect to either the distribution or transmission network: - For a transmission connection (i.e. at 110kV and above) please contact System Operator for Northern Ireland (SONI) for more details on this process - For a distribution connection (i.e. at up to 33kV), this document details the process for connection with NIE Networks The following information sheets outline the process, application fees and conditions for obtaining a large scale generation connection offer to connect to the NIE Networks distribution network. Customers or their representatives must register online via the NIE Networks web site, at to obtain a full application pack. Alternatively, NIE Networks can be contacted by post at the address below: Summary of the Contents in this information pack: 1. General Safety Information 2. Feasibility Study and Fees Central Processing and Registration Northern Ireland Electricity Networks 57 Dargan Road Belfast BT3 9JU Large Scale Generation Connection Process 4. Application Information and Fees 5. Connection Design 6. Transmission Connections (SONI) 7. Pre-Construction & Construction Works 8. Renewable Obligation Certificates (ROCs) 9. Complaints Annex 1- Relevant Legislation

4 1. General Safety Information NIE Networks would draw your attention to the considerable danger associated with working in the vicinity of electrical equipment, whether underground or overhead. The greatest care must be exercised not to come into contact or to bring materials, equipment, appliances or tools too close to electrical equipment, otherwise workers and indeed other persons not directly concerned may be subject to very grave risk, which may lead to a serious or even fatal accident. Site safety must be in accordance with HSE Guidance Note GS6 (Avoidance of Danger from Overhead Electric Lines) and HSE Booklet HS(G)47 (Avoiding Danger from Underground Services). Further information can be found on NIE Networks safety website at or at Clearance to NIE Networks Distribution Network (Diagram 1) Diagram 1

5 Clearance to NIE Networks Transmission Network (Diagram 2) Diagram 2 2. Feasibility Study and Fees At the request of a customer, NIE Networks can carry out a feasibility study for projects that are at an initial investment appraisal stage in order to assist customers wishing to connect generators and export energy to the electricity network. This study is optional and provides information which may help a customer develop their business plan. In order to request a feasibility study for a particular project, NIE Networks requires the customer to complete NIE Networks Generator Enquiry Form and forward it to NIE Networks with the appropriate non-refundable fee (see fee schedule below). A copy of the generator's electrical data sheet may also be attached if this is available. Generation Maximum installed Capacity Feasibility Study Fee More than 150kW 1,132 All fees listed are exclusive of VAT which should be added at the current tax point rate of 20%. Cheques should be made payable to Northern Ireland Electricity Networks Ltd. NOTE: The cost to apply for a feasibility study is linked to the Statement of Charges that is currently approved and may be subject to change in line with future approved Statement of Charges. Only on receipt of both the fee and adequate technical information will NIE Networks be in position to progress a feasibility study. It may take NIE Networks up to three months to provide a feasibility study following receipt of all required information and appropriate payment.

6 The feasibility study will consider the most appropriate connection arrangement at your specific location, at that point in time, and details of the work required to provide connection for the requested capacity and technology. The feasibility study will provide potential developers with: an indication that a connection is achievable an indicative cost for providing a suitable network connection and an outline of the work involved in constructing the connection including information on: connection voltage level connection point to NIE Networks network details of the connection arrangement This will help applicants to decide if they wish to proceed with their project as planned. Applicants should be aware that a feasibility study does not reserve network capacity for a particular project, and NIE Networks cannot guarantee that a connection will be available when an application makes a formal application for connection. The study is effectively a snapshot at a point in time. 3. Large Scale Generation Connection Process Diagram 3 provides an overview of the process for applying to NIE Networks for a large scale generation connection and outlines the basic steps to be worked through. The diagram highlights where connection offers may be impacted by any requirement for transmission work and how the process may be modified to include inputs from the Transmission Planner, SONI. More detail on this in Section (6) - Transmission Connections. It also explains the process which NIE Networks works through once an offer has been accepted by an applicant. More detail on this in Section (7) - Pre-Construction & Construction works.

7 Diagram 3 Large Scale Generation Process (Diagram 3)

8 4. Application Information and Fees A grid connection application (leading to an offer) is available to all customers. There is no requirement to have a feasibility study carried out before making a connection application. When a connection application is received by NIE Networks, it is registered and given a unique job reference number. The applicant will be informed of this number in writing and should quote this number when inquiring about their application. This study is a full technical appraisal and requires the applicant to submit a formal application (referred to as the NIE Networks Generator Questionnaire) including the full technical specification of the generators being connected, details of planning permission and the appropriate non-refundable fee. Relevant Connection Application Fees (CAF) can be found in the Statement of Charges at the following link: Statement-ver.aspx NOTE: The cost to apply for a grid connection application is linked to the Statement of Charges that is currently approved and may be subject to change to future approved Statement of Charges. Customer Category Connection Application Fee NIE Networks fee s: C D Customer requiring a generation capacity of more than 150kW and less than or equal to 2MW: 5,659 e.g. 250kW application fee = Category C = 5,659 (+VAT) Customer requiring a generation capacity of more than 2MW: e.g. 4.5MW application fee = Category D = 8,488 (+VAT) SONI fee s*: (To be paid to NIE Networks in addition to the NIE Networks fee) 8,488 S1 S2 Additional fee for a customer requiring a generation capacity of more than or equal to 5MW and less than 20MW and whose connection requires a detailed assessment by SONI for its effect on the Transmission System: e.g. 5.5MW application fee = Categories D + S1 = 8, ,696 = 34,184 (+VAT) Additional fee for a customer requiring a generation capacity of more than or equal to 20MW and whose connection requires a detailed assessment by SONI for its effect on the Transmission System: e.g. 25MW application fee = Categories D + S2 = 8, ,867 = 45,355 (+VAT) 25,696 36,867 *NIE Networks collects this cost from the customer and then pays this fee to SONI. For more information on what this fee covers please visit

9 All the fees listed above are exclusive of VAT which should be added at the current tax point rate of 20%. Application fees must be paid by cheque all cheques should be made payable to Northern Ireland Electricity Networks Ltd. The application will be checked to ensure it contains: Completed Generator Questionnaire and all documentation referred to within the questionnaire Technical specifications of generators including: Flicker co-efficient Starting currents and type of starter for each generator installed Impedance data for each generator installed and connecting network to the point of connection Harmonic studies Single line diagram 1: 25000, 1:2500 and 1:500 scale site location plans Site layout plan, including proposed substation location Easting and Northing co-ordinates of each generator Easting and Northing co-ordinates of customer substation Total Generator(s) Capacity along with Maximum Export Capacity (MEC) 1 Required The relevant Connection Application Fee If Maximum Import Capacity (MIC) 2 >200kVA then load details required If the application does not have all the required information, NIE Networks will write to the applicant and request this information. In relation to timeline to make the offer, the job will be put on hold until all this information is received. Planning permission is no longer a pre-requisite for an application, however if you do have planning permission for your development (or do not require planning permission), please send evidence of this and any relevant details. Following the receipt of all information and payments, the processing of a formal connection offer, which includes only distribution works, may take three months to complete. Note that if transmission works are required SONI may need to input into the offer - see Section (6) Transmission connections. The connection offer will outline the connection voltage, connection costs, terms and conditions for connection and details of the work required to provide the connection for the requested capacity and technology. 5. Connection Application Design A preliminary design will be carried out to determine how the generator would be connected, including: Studies to determine technical feasibility Route considered Preliminary specification of design Going forward it is likely that in many instances large scale generation will be connected to cluster substations. These cluster substations are effectively extensions of the transmission network at 110kV to bring a main connection node closely to groups of renewable generation. NIE Networks published Statement of Charges provides details of the criteria which apply to clusters. At the preliminary design stage, consideration will be given to connecting the generator to a cluster or to an existing main substation depending on the specific circumstances. Where further transmission related assessment is required then SONI will be required to carry out transmission design work and provide design and cost information to NIE Networks. More detail on this in Section (6) - Transmission Connections (SONI). 1 Maximum Export Capacity (MEC) is the value you are requesting to be recorded against Your connection in NIE Networks system as the maximum capacity that can be generated/exported by your connection 2 Maximum Import Capacity (MIC) means the value recorded against Your connection in NIE Networks system as the maximum capacity that can be used/imported by your connection

10 When the connection method has been agreed, then NIE Networks will carry out a detailed design of the connection including: Plant requirements including Switchgear Protection requirements Overhead Line route (and options) Underground cable route Environmental considerations/constraints Civil works Scada and Communications requirements Site visits will carried out to the determine detailed route and plant requirements The offer will then be issued to the applicant within 90 days. It will include Details of the connection design with diagrams The cost of the connection. Details of how to accept the offer and the necessary deposit required Details of security payments if applicable Estimated timeframe for completion This offer is valid for 90 days from the date of issue and the applicant must forward their acceptance of terms and deposit to NIE Networks within this 90 day period. Once the offer has been accepted and the deposit paid, NIE will proceed with the activities required to connect the generator to the Distribution System. More detail on this in Section (7) - Pre-Construction & Construction works. If the offer is not accepted within the stipulated 90 day period, then the application will become void and the applicant will need to re-apply if they wish to continue to pursue a connection. NOTE: The costs of your grid connection will be linked to the Statement of Charges that is approved at that point in time when the offer is made, and may be subject to change to future approved Statement of Charges if a re-quote is required. 6. Transmission Connections (SONI) To satisfy the requirements of the EU s IME3 directive, the transmission planning function of NIE Networks transferred to the System Operator for Northern Ireland (SONI) on 1st May SONI now undertake all transmission investment planning activities (including transmission connections) and are responsible for establishing the location and routing arrangements, along with securing consents for transmission projects. NIE Networks is responsible for the construction of transmission projects. In some circumstances transmission works are required to produce the complete offer. This may be the case where a cluster is involved. In this scenario NIE Networks will request an extension of time from the UR to provide an offer to allow for SONI to determine any necessary transmission works. NIE Networks will inform the customer if an extension is required and how long the extension has been granted for. The job will be put on hold during this time.

11 7. Pre-Construction & Construction Works The cost basis of the connection depends on the extent of the construction work required to connect the scheme along with any appropriate reinforcement and maintain the electricity network within statutory voltage and reactive power limits. Please refer to the Statement of Charges for Connection to the Northern Ireland Distribution System for indications of costs for connection: Statement-ver.aspx When you accept the Terms of Connection of Generation and make any necessary payment, NIE Networks will: Complete a full survey of the route Seek to obtain wayleaves from landowners Seek to obtain DOE Planning Permission for overhead line work. Obtain DETI Article 40 consent for the overhead line if required. Procure major items of plant Agree suitable earthing design for the site. Stage 3 harmonics to be approved by NIE Networks Complete necessary legalities Final construction and energisation works Generation however cannot begin until both the owner of the generator and NIE Networks have signed the Generator Agreement (which will be supplied by NIE Networks). The Agreement must be signed by you, witnessed and returned to NIE Networks. Your installer is required to complete G59 3 testing and submit the test results and Schedule 1A form (supplied by NIE Networks along with your connection offer) to NIE Networks for approval. If approved, NIE Networks will sign the Generator Agreement and schedule 1A form and return a copy to you for your records. 8. Renewable Obligation Certificates The Renewables Obligation (RO) is the main support mechanism for renewable electricity projects in the UK. It places an obligation on all UK suppliers of electricity to source an increasing proportion of their electricity from renewable sources. A Renewable Obligation Certificate (ROC) is a green certificate issued by OFGEM to an accredited renewable energy generator for eligible renewable electricity generated within the United Kingdom and supplied to customers within the United Kingdom by a licensed electricity supplier. In Northern Ireland OFGEM manage the ROC administration process on behalf of the Nl Utility Regulator. For further information you can contact: Utility Regulator, Queens House, 14 Queen Street, Belfast, Bt1 6ED - Tel No: or log on to their website DETI, Department of Enterprise Trade and Investment, Netherleigh, Massey Avenue, Belfast BT4 2JP - Tel No: or log on to their website 3 NIE Networks Engineering Recommendation G59/1/NI

12 9. Complaints At NIE Networks, customer service is very important to us. However, if you are unhappy with any aspect of our customer service you can submit a complaint: Online: visit Our customer helpline, , is open from 8am-5pm, Monday- Friday. In writing to: Customer Relations Manager Northern Ireland Electricity Networks Limited Carn Industrial Estate Portadown, BT63 5QJ Consumer Council If your complaint is not resolved to your satisfaction or if at any time you are unhappy with our response, the Consumer Council, an independent body, may be able to help: Online : visit By phone In writing to: The Consumer Council Floor 3, Seatem House, Alfred street Belfast, BT2 8EN

13 Relevant legislation regarding connections includes: ANNEX 1- LEGISLATION The Electricity (Northern Ireland) Order 1992 o Article 19- Duty to connect on request o Article 20- Procedure for requiring a connection o Article 21- Exceptions from duty to connect NIE Networks Distribution Licence. o Condition 30- Requirement to Offer terms for Connection to and Use of Distribution System

14 Applications should be sent in hard copy to: Central Processing & Registration Northern Ireland Electricity Networks Limited 57 Dargan Road BELFAST BT3 9JU Telephone: For further information visit nienetworks.co.uk

What do you need to do?

What do you need to do? COMMERCIAL CONNECTION your Business. What do you need to do? Complete an application Please complete your application and attach your plans listed in the checklist below (you can tear off and retain the

More information

NORTHERN IRELAND ELECTRICITY Ltd STATEMENT OF CHARGES FOR USE OF. THE NORTHERN IRELAND ELECTRICITY Ltd ELECTRICITY DISTRIBUTION SYSTEM

NORTHERN IRELAND ELECTRICITY Ltd STATEMENT OF CHARGES FOR USE OF. THE NORTHERN IRELAND ELECTRICITY Ltd ELECTRICITY DISTRIBUTION SYSTEM NORTHERN IRELAND ELECTRICITY Ltd STATEMENT OF CHARGES FOR USE OF THE NORTHERN IRELAND ELECTRICITY Ltd ELECTRICITY DISTRIBUTION SYSTEM BY AUTHORISED PERSONS Effective from 1 October 2011 to 30 September

More information

Viking Link Interconnector

Viking Link Interconnector Viking Link Interconnector Public information event for Bicker Parish Why we re here today We re here today to introduce the Viking Link project, to explain what we want to build and to answer any questions

More information

Re: Connection to the Electricity Distribution System at: [GV_SINGLE_LINE_ADDR_PREM]

Re: Connection to the Electricity Distribution System at: [GV_SINGLE_LINE_ADDR_PREM] [GV_AUTH_OFFICER] [GV_NAME_LINE] [GV_ADDRESS_LINE1] [GV_ADDRESS_LINE2] [GV_ADDRESS_LINE3] [GV_ADDRESS_LINE4] [GV_ADDRESS_LINE5] Date: [GV_ISSUE_DATE ] Job No: [GV_NOTIFNUMZ2] MPRN: [GV_MPRN] Re: Connection

More information

STATEMENT OF CHARGING METHODOLOGY FOR USE OF ELECTRICITY NORTH WEST LIMITED S ELECTRICITY DISTRIBUTION NETWORK

STATEMENT OF CHARGING METHODOLOGY FOR USE OF ELECTRICITY NORTH WEST LIMITED S ELECTRICITY DISTRIBUTION NETWORK STATEMENT OF CHARGING METHODOLOGY FOR USE OF ELECTRICITY NORTH WEST LIMITED S ELECTRICITY DISTRIBUTION NETWORK This statement is effective from 1 April 2010 This statement is approved by the Gas and Electricity

More information

A GUIDE TO. Connecting Renewable and CHP Electricity Generators to the Electricity Network

A GUIDE TO. Connecting Renewable and CHP Electricity Generators to the Electricity Network A GUIDE TO Connecting Renewable and CHP Electricity Generators to the Electricity Network A Guide to Connecting Renewable and CHP Electricity Generators to the Electricity Network October 2008 Guide prepared

More information

Generating a Return. July 2008 BHA SEMINAR

Generating a Return. July 2008 BHA SEMINAR Generating a Return July 2008 BHA SEMINAR Why invest in renewable generation? Reduces CO 2 emissions and climate change Reduces cost of electricity at the site as not paying for transmission of electricity

More information

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 SHE Transmission 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 Summary This paper presents SHE Transmission s views and approach on the impact of transmission losses on the transmission

More information

Networks. ESB Networks Ltd Basis of Charges for Connection to the Distribution System. Commercial and Customer Asset Management ESB Networks Ltd.

Networks. ESB Networks Ltd Basis of Charges for Connection to the Distribution System. Commercial and Customer Asset Management ESB Networks Ltd. Networks ESB Networks Ltd Basis of Charges for Connection to the Distribution System Revision Date: 14/01/20010 Revision No.: 1 Document No: DOC-10129-AXQ Issued by: ESB Networks Ltd Approved by : CER

More information

NEW CABLE? - Understanding the cost to connect renewable generation in Orkney

NEW CABLE? - Understanding the cost to connect renewable generation in Orkney New Holland, Holm 500kW Partner of Choice in Mid-Size Wind NEW CABLE? - Understanding the cost to connect renewable generation in Orkney Hammer, Westray 500kW Colin Risbridger Windflow UK Development Manager

More information

Supporting business our structure

Supporting business our structure Supporting AgriFood Agenda First Trust Bank structure Supporting agri business AgriFood Funds Renewable energy projects (estimated costs & returns) Funding renewable energy projects Recent renewable energy

More information

npower Microgeneration Scheme Feed In Tariffs A Guide to the Clean Energy Cashback Scheme RF8148 npm7523 Solar brochure.indd 1

npower Microgeneration Scheme Feed In Tariffs A Guide to the Clean Energy Cashback Scheme RF8148 npm7523 Solar brochure.indd 1 npower Microgeneration Scheme Feed In Tariffs A Guide to the Clean Energy Cashback Scheme RF8148 npm7523 Solar brochure.indd 1 28/03/2011 15:52 What s inside Make money from the energy you generate An

More information

Supplier Registration System

Supplier Registration System Supplier Registration System www.sse.com/potentialsuppliers A guide for Suppliers www.sse.com/potentialsuppliers 03 ONE WAY OF WORKING We are keen to introduce one way of working in procurement, making

More information

Becoming Gas Safe Registered

Becoming Gas Safe Registered Becoming Gas Safe Registered all businesses and engineers that undertake gas work must be registered with Gas Safe Register. BECOMING REGISTERED WITH GAS SAFE REGISTER IS EASY AND FAST. The gas registration

More information

e-factsheet Feed-in Tariffs what we have to offer

e-factsheet Feed-in Tariffs what we have to offer e-factsheet Feed-in Tariffs what we have to offer 2 of 12 Feed-in Tariffs (FITs) make renewable generation more financially rewarding for smaller installations and help reduce the UK s carbon emissions.

More information

Methodology for Solar Power Projects

Methodology for Solar Power Projects Annexure E Methodology for Solar Power Projects This methodology is applicable to the solar power projects included in the composite policy for new and renewable (non-conventional energy sources) power

More information

Apex Risk Advisors Limited trading as Apex Insurance Brokers 7 South Mall, Cork. Fax: 021 2399204 www.apexinsurance.ie

Apex Risk Advisors Limited trading as Apex Insurance Brokers 7 South Mall, Cork. Fax: 021 2399204 www.apexinsurance.ie Apex Risk Advisors Limited trading as Apex Insurance Brokers Tel: 021 2398864 7 South Mall, Cork. Fax: 021 2399204 www.apexinsurance.ie General Terms of Business These terms of business set out the basis

More information

G8 - Contracts for Difference Metering

G8 - Contracts for Difference Metering PUBLIC G8 - Contracts for Difference Metering EMRS Guidance EMR Settlement Limited Version 1.0 12 October 2015 CONTENTS Change Amendment Record...4 1. Introduction...5 2. Purpose...5 3. What is the Electrical

More information

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment March 20, 2009 Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Table of Contents:

More information

Tidal Energy. Wind Energy. Transmission & Distribution Network. Offshore Substation. Onshore Substation. Tidal Stream Energy.

Tidal Energy. Wind Energy. Transmission & Distribution Network. Offshore Substation. Onshore Substation. Tidal Stream Energy. Offshore Renewables Tidal Energy Transmission & Distribution Network Offshore Substation Wind Energy Onshore Substation Tidal Stream Energy Consumer Atkins in Offshore Renewables The offshore wind journey

More information

Please find enclosed with our compliments, a memory stick with the following information on for your reference 1 :

Please find enclosed with our compliments, a memory stick with the following information on for your reference 1 : E Classic Boiler Servicing Plan It is coming to that time of year when your E-Classic is going to be under high demand. It is therefore essential that it has been maintained and serviced according to manufacturer

More information

Application Procedures For Electricity Connection To Consumers Electrical Installations In The New Electricity Market

Application Procedures For Electricity Connection To Consumers Electrical Installations In The New Electricity Market Application Procedures For Electricity Connection To Consumers Electrical Installations In The New Electricity Market October 2002 Forms & presentation material will be published in the EMA website www.ema.gov.sg

More information

Contract for Difference for non-uk Renewable Electricity Projects

Contract for Difference for non-uk Renewable Electricity Projects Contract for Difference for non-uk Renewable Electricity Projects August 2014 Crown copyright 2014 URN 14D/291 You may re-use this information (not including logos) free of charge in any format or medium,

More information

Consultation on proposals for the levels of banded support for solar PV under the Renewables Obligation for the period 1 April 2013 to 31 March 2017

Consultation on proposals for the levels of banded support for solar PV under the Renewables Obligation for the period 1 April 2013 to 31 March 2017 Consultation on proposals for the levels of banded support for solar PV under the Renewables Obligation for the period 1 April 2013 to 31 March 2017 7 September 2012 Department of Energy and Climate Change

More information

Preliminary Information Memorandum. Thanet Offshore Transmission Assets. July 2009

Preliminary Information Memorandum. Thanet Offshore Transmission Assets. July 2009 Preliminary Information Memorandum Thanet Offshore Transmission Assets July 2009 SUMMARY In April 2009 Ofgem distributed a teaser document, UK Offshore Transmission Investment Opportunity, to investors

More information

How To Pay For A Tutor In Ireland

How To Pay For A Tutor In Ireland CLAIM FORM FOR HOME TUITION PAYMENTS TO BE PAID DIRECTLY BY AGREEMENT TO COMPANIES DURING THE 2015.16 SCHOOL YEAR Name of Company: Parents are advised that, as an exceptional measure and for an agreed

More information

Terms of Business FBD Insurance plc

Terms of Business FBD Insurance plc Terms of Business FBD Insurance plc Why have terms of business? This document protects you. It is required by the Central Bank of Ireland. It is important that you read it in full. If there is anything

More information

Your Options. A simple guide to available debt options

Your Options. A simple guide to available debt options Your Options A simple guide to available debt options Contents Welcome 3 Our Customer Service Charter 3 Protected Trust Deeds 4 Debt Arrangement Scheme 6 Sequestration 8 Debt Management Plan 10 Minimal

More information

PROCEDURE FOR ISSUANCE OF RENEWABLE ENERGY CERTIFICATE TO THE ELIGIBLE ENTITY BY CENTRAL AGENCY

PROCEDURE FOR ISSUANCE OF RENEWABLE ENERGY CERTIFICATE TO THE ELIGIBLE ENTITY BY CENTRAL AGENCY PROCEDURE FOR ISSUANCE OF RENEWABLE ENERGY CERTIFICATE TO THE ELIGIBLE ENTITY BY CENTRAL AGENCY 1. OBJECTIVE 1.1. This procedure shall provide guidance to the entities to implement Renewable Energy Certificate

More information

CUSTOMER CONNECTION GUIDE

CUSTOMER CONNECTION GUIDE CUSTOMER CONNECTION GUIDE A GUIDE TO CONNECTING ELECTRICITY SUPPLY TO YOUR PROPERTY IN UNITED ENERGY S AREA Document No: UE4309 Issue: 4 Issue Date: 1 April, 2014 1 CUSTOMER CONNECTION GUIDE A GUIDE TO

More information

Obtaining Pre-Application Planning Advice

Obtaining Pre-Application Planning Advice Obtaining Pre-Application Planning Advice Summary of Services Available and Charges 2014/15 Contents Page 2 Page 5 Page 7 Page 8 Page 9 Section A Pre-Application Planning Advice that requires a Fee and

More information

-1- PSEG-LI Update of LIPA SGIP Full Docw-NYISO reqmts above 10 MW 10-27-14

-1- PSEG-LI Update of LIPA SGIP Full Docw-NYISO reqmts above 10 MW 10-27-14 PSEG-Long Island Smart Grid Small Generator Interconnection Procedures for New Distributed Resources 20 MW or Less Connected in Parallel with LIPA s Radial Distribution Systems -1- PSEG-LI Update of LIPA

More information

Terms of Reference Annex: Energy Sector

Terms of Reference Annex: Energy Sector Terms of Reference Annex: Energy Sector 1. Interpretation 1.1 The definitions, below, apply to both this Annex and the Terms of Reference in relation to complaints brought to Ombudsman Services: Energy

More information

Redundancy Payments Services. A Statement of Charter Standards

Redundancy Payments Services. A Statement of Charter Standards Redundancy Payments Services A Statement of Charter Standards How can we help you? Losing your job through redundancy can come as quite a shock. One of the first things you will want to know is what payments

More information

Your Professional Indemnity Solution.

Your Professional Indemnity Solution. Pinsure Your Professional Indemnity Solution. 18 Henfield Business Park, Shoreham Road, Henfield, West Sussex, BN5 9SL Tel. 01273 494914 ~ Fax. 01273 494964 Email: pinsure@pinsure.co.uk Web: www.pinsure.co.uk

More information

Retailers summary of cover

Retailers summary of cover Retailers summary of cover September 2015 Why choose AXA s Retailers Insurance policy? The Retailers Insurance offers a range of covers and caters for customers who operate retail premises or other retail

More information

Engineering Recommendation G81 Issue: October 2004

Engineering Recommendation G81 Issue: October 2004 Engineering Recommendation G81 Issue: Part 4 - Framework for design and planning of industrial and commercial underground connected loads up to and including 11kV 2004 Energy Networks Association All rights

More information

ELECTRICITY SUPPLY/ TRADE LICENSE KORLEA INVEST A.S

ELECTRICITY SUPPLY/ TRADE LICENSE KORLEA INVEST A.S Hamdi Mramori Street, No 1 Prishtina 10000 Kosovo Tel: +381 (0) 38 247 615 ext. 103 Fax: +381 (0) 38 247 620 e-mail: info@ero-ks.org www.ero-ks.org ELECTRICITY SUPPLY/ TRADE LICENSE GRANTED TO: KORLEA

More information

Cost to Northern Ireland of Workplace Injuries and Ill-health

Cost to Northern Ireland of Workplace Injuries and Ill-health Cost to Northern Ireland of Workplace Injuries and Ill-health Economic Research March 2013 Prepared by DETI Analytical Services for the Health and Safety Executive Northern Ireland (HSENI) Introduction

More information

Choice Home Loans Penrith & Blue Mountains

Choice Home Loans Penrith & Blue Mountains Credit Guide This document provides you with information relating to our activities and those of our credit representatives. It contains information about various fees and charges that may be payable by

More information

SQS SUPPLIER FREQUENTLY ASKED QUESTIONS

SQS SUPPLIER FREQUENTLY ASKED QUESTIONS SQS SUPPLIER FREQUENTLY ASKED QUESTIONS Page 1 of 17 CONTENTS 1. BACKGROUND... 5 What is SQS?... 5 Who is Achilles?... 5 What is the role of Achilles?... 6 2. REGISTRATION... 6 Which suppliers are required

More information

Your Van Insurance Motor Legal Protection Policy Booklet

Your Van Insurance Motor Legal Protection Policy Booklet Your Van Insurance Motor Legal Protection Policy Booklet Contents Motor Legal Protection Insurance...3 Motor Legal Expenses...3 Helpline Services...3 Motor Legal Expenses Policy Summary...4 Cancellation

More information

Terms of Reference Annex: Energy Sector

Terms of Reference Annex: Energy Sector Terms of Reference Annex: Energy Sector 1. Interpretation 1.1 The definitions, below, apply to both this Annex and the Terms of Reference in relation to complaints brought to Ombudsman Services: Energy

More information

Your Van Policy Summary

Your Van Policy Summary Your Van Policy Summary Your Summary of Cover Dear customer This booklet is your policy summary, so please keep the booklet safe for when you need it. There are also some useful tips on what to do in an

More information

NIRIG response to EMR: Consultation on Proposals for Implementation

NIRIG response to EMR: Consultation on Proposals for Implementation 90% NIRIG response to EMR: Consultation on Proposals for Implementation 23 rd December 2013 The Northern Ireland Renewables Industry Group (NIRIG) is a joint collaboration between the Irish Wind Energy

More information

Solar PV For Surrey Schools - Information Pack

Solar PV For Surrey Schools - Information Pack Solar PV For Surrey Schools - Information Pack Solar PV for Surrey Schools: Summary of options and key considerations School interested in solar PV OPTION 1 Own investment: School is responsible for the

More information

0800 121 6022 www.consumercouncil.org.uk

0800 121 6022 www.consumercouncil.org.uk a series of guides for energy users from the Consumer Council Switching domestic natural gas supplier 0800 121 6022 www.consumercouncil.org.uk March 2013 Switching domestic natural gas supplier Contents

More information

The Solar Power Specialists. Elm Park House, Elm Park Court, Pinner, Middlesex, HA5 3NN Solutions House, Unit A19, 20 Heron Road, Belfast, BT3 9LE

The Solar Power Specialists. Elm Park House, Elm Park Court, Pinner, Middlesex, HA5 3NN Solutions House, Unit A19, 20 Heron Road, Belfast, BT3 9LE The Solar Power Specialists GB: 0845 64 39 772 NI: 0845 50 40 444 Email: info@metartecsolar.com Visit: www.metartecsolar.com Elm Park House, Elm Park Court, Pinner, Middlesex, HA5 3NN Solutions House,

More information

Public Limited Company, Limited Company or Limited Liability Partnership

Public Limited Company, Limited Company or Limited Liability Partnership Public Limited Company, Limited Company or Limited Liability Partnership Mandate for transacting with Bank of Ireland Global Markets in the United Kingdom (UK) Global Markets Your Business Details Business/Trading

More information

GUIDANCE FOR APPLICANTS AND LANDOWNERS AND/OR OCCUPIERS

GUIDANCE FOR APPLICANTS AND LANDOWNERS AND/OR OCCUPIERS GUIDANCE FOR APPLICANTS AND LANDOWNERS AND/OR OCCUPIERS Application to the Secretary of State for Energy and Climate Change for the grant of a Necessary (Compulsory) Electricity Wayleave in England and

More information

AVOIDANCE OF ELECTRICAL HAZARDS WHEN WORKING NEAR OVERHEAD ELECTRIC LINES

AVOIDANCE OF ELECTRICAL HAZARDS WHEN WORKING NEAR OVERHEAD ELECTRIC LINES overhead 23/11/04 2:28 PM Page 1 AVOIDANCE OF ELECTRICAL HAZARDS WHEN WORKING NEAR OVERHEAD ELECTRIC LINES ESB Code 9803203 overhead 23/11/04 2:28 PM Page 2 overhead 23/11/04 2:28 PM Page 3 Page 1 of 20

More information

Welcome Pack. Fixed Rate Business Bond

Welcome Pack. Fixed Rate Business Bond Welcome Pack Fixed Rate Business Bond Creating better futures Cambridge & Counties Bank is a unique partnership between two established and respected institutions Trinity Hall, Cambridge and Cambridgeshire

More information

Engineering Recommendation G81 - Part 1: Design and Planning

Engineering Recommendation G81 - Part 1: Design and Planning PRODUCED BY THE ENGINEERING DIRECTORATE OF THE ENERGY NETWORKS ASSOCIATION Engineering Recommendation G81 - Part 1: Design and Planning Issue 2 Ammendment 1 January 2008 Framework for design and planning,

More information

2. What is the VAT Retail Export Scheme?

2. What is the VAT Retail Export Scheme? 1. Introduction This Notice tells you how to get a tax refund on goods bought in the UK from shops operating the VAT Retail Export Scheme. Full details on the operation of the Scheme can be found in VAT

More information

Customer Charter. Networks. Networks. www.esb.ie

Customer Charter. Networks. Networks. www.esb.ie www.esb.ie Dear Customer ESB has always been committed to putting the needs of our customers first. This is reflected in our 12 Service Guarantees that were first introduced in our Customer Charter some

More information

FP Marine Risks Limited

FP Marine Risks Limited FP Marine Risks Limited Terms of Business CONTENTS Introduction and Scope... 3 Management and Service Standards... 3 Placing Services... 4 Duty of Disclosure... 6 Solvency of Underwriters... 6 Confidentiality

More information

Standard conditions of the Electricity Distribution Licence

Standard conditions of the Electricity Distribution Licence Gas and Electricity Markets Authority ELECTRICITY ACT 1989 Standard conditions of the Electricity Distribution Licence Statutory Consultation: 29 April 2008 SECTION A: STANDARD CONDITIONS FOR ALL ELECTRICITY

More information

How to become an Approved Contractor

How to become an Approved Contractor How to become an Approved Contractor The SIA Approved Contractor scheme gives your organisation the opportunity to distinguish itself as amongst the best providers of private security services in the UK.

More information

KnocKdown Rebuild PRoceSS Guide

KnocKdown Rebuild PRoceSS Guide Knockdown Rebuild PROCESS GUIDE With Boutique you can have it all location, space, quality, convenience and lifestyle 02 03 04 05 If you're knocking down your existing home and rebuilding, Boutique has

More information

Key information pack. Fixed Rate Cash ISA

Key information pack. Fixed Rate Cash ISA Fixed Rate Cash ISA Key information pack Post Office Money Fixed Rate Cash ISA is provided by OneFamily. Savings in Post Office Money cash ISAs are deposited with Bank of Ireland UK. PostOfficeMoney.co.uk

More information

Dakota Energy Cooperative, Inc. POLICY STATEMENT

Dakota Energy Cooperative, Inc. POLICY STATEMENT Dakota Energy Cooperative, Inc. POLICY STATEMENT Subject: Member Owned Small Renewable Energy Policy No. 57 Rate and Interconnection Requirements Issue Date: May 21, 2008 Revised Date: December 16, 2014

More information

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114.

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114. Generation Interconnection System Impact Study Report For PJM Generation Interconnection Request Queue Position X1-114 Sandyston January 2012 Preface The intent of the System Impact Study is to determine

More information

Welcome Pack. Fixed Rate Business Bond

Welcome Pack. Fixed Rate Business Bond Welcome Pack Fixed Rate Business Bond Creating better futures Cambridge & Counties Bank is a unique partnership between two established and respected institutions Trinity Hall, Cambridge and Cambridgeshire

More information

Contestability on the Distribution System ESB Networks Key Principles and Processes Paper

Contestability on the Distribution System ESB Networks Key Principles and Processes Paper Contestability on the Distribution System ESB Networks Key Principles and Processes Paper Revision Date: 01/09/2010 Revision No.: 0 Document No: DOC-090211-BGY Issued by: ESB Networks Ltd. Approved by:

More information

Market Research Commercial Questions

Market Research Commercial Questions Market Research Commercial s This document brings together the commercial questions asked at Request for Information (RFI) and Request for Quotation (RFQ) stages of the procurement exercise. All suppliers

More information

Connecting to the network information pack Version 2

Connecting to the network information pack Version 2 Connecting to the network information pack Version 2 Updated: Contents 1.0 What is a new connection or connection alteration?... 3 2.0 Connection enquiry... 3 3.0 Connection application... 3 3.1 Processing

More information

card account Terms and Conditions Handled with care Your account credit card

card account Terms and Conditions Handled with care Your account credit card card account Your account Handled with care credit card Contents These tell you about the services that are available with your Post Office card account. Please read this booklet carefully as a Post Office

More information

Eldorado-Ivanpah Transmission Project WELCOME To Southern California Edison Company s Eldorado-Ivanpah Transmission Project OPEN HOUSE

Eldorado-Ivanpah Transmission Project WELCOME To Southern California Edison Company s Eldorado-Ivanpah Transmission Project OPEN HOUSE WELCOME To Southern California Edison Company s Eldorado-Ivanpah Transmission Project OPEN HOUSE 1 1 Welcome to The Eldorado-Ivanpah Transmission Project Open House How is the open house organized? This

More information

Gas turbine power plants

Gas turbine power plants Gas turbine power plants A global challenge Apart from other sources of energy such as water, coal and uranium, the use of natural gas and fuel oil is an important factor in assuring a reliable supply

More information

1/ 9 TED19_NRI 13/03/2016- ID:2016-000709 Standard form 2 - EN PSNI - Supply of Pyrotechnics

1/ 9 TED19_NRI 13/03/2016- ID:2016-000709 Standard form 2 - EN PSNI - Supply of Pyrotechnics 1/ 9 TED19_NRI 13/03/2016- ID:2016-000709 Standard form 2 - EN CONTRACT NOTICE - ABOVE THRESHOLD SECTION I: CONTRACTING AUTHORITY I.1) NAME, ADDRESSES AND CONTACT POINT(S) Official name: Police Service

More information

Tradesman Essential Per Capita Liability Insurance Summary of Cover

Tradesman Essential Per Capita Liability Insurance Summary of Cover Tradesman Essential Per Capita Liability Insurance www.towergate.co.uk This leaflet provides a summary of the significant features, benefits and limitations of the cover provided by your Tradesman Essentials

More information

JAGUAR INSURANCE ASSET PROTECTION

JAGUAR INSURANCE ASSET PROTECTION JAGUAR INSURANCE ASSET PROTECTION 1 INTRODUCTION Did you know that if your vehicle is written off as a total loss through an accident, fire, theft or adverse weather conditions, most motor insurance companies

More information

1/ 10 TED19_NRI 10/04/2016- ID:2016-000795 Standard form 2 - EN DETI / Invest NI Design for Business Support Service

1/ 10 TED19_NRI 10/04/2016- ID:2016-000795 Standard form 2 - EN DETI / Invest NI Design for Business Support Service 1/ 10 TED19_NRI 10/04/2016- ID:2016-000795 Standard form 2 - EN CONTRACT NOTICE - ABOVE THRESHOLD SECTION I: CONTRACTING AUTHORITY I.1) NAME, ADDRESSES AND CONTACT POINT(S) Official name: Invest NI National

More information

1/ 9 TED19_NRI 05/08/2015- ID:2015-000048 Standard form 2 - EN Invest NI - Provision of Patent Appraisal Services

1/ 9 TED19_NRI 05/08/2015- ID:2015-000048 Standard form 2 - EN Invest NI - Provision of Patent Appraisal Services 1/ 9 TED19_NRI 05/08/2015- ID:2015-000048 Standard form 2 - EN CONTRACT NOTICE - ABOVE THRESHOLD SECTION I: CONTRACTING AUTHORITY I.1) NAME, ADDRESSES AND CONTACT POINT(S) Official name: CPD - Supplies

More information

Guild Accreditation Information Pack

Guild Accreditation Information Pack Guild Accreditation Information Pack Guild Accreditation Of Short Training Courses Accreditation of training courses is vital for any school as it means your students will be able to obtain insurance with

More information

Private Motor Vehicle Excess Protect

Private Motor Vehicle Excess Protect Private Motor Vehicle Excess Protect Insurance Policy Flux Direct 2 The Causeway, Bishops Stortford, Herts, CM23 2EJ In the event of a claim please call: 0844 888 7361 Customer Service: 0800 089 0154 Or

More information

SSE s criteria used for GHG emissions reporting

SSE s criteria used for GHG emissions reporting SSE s criteria used for reporting 1 Introduction This document details the annual greenhouse gas emissions reporting approach used by SSE Plc to report the tonnes of carbon dioxide equivalent (CO2e) during

More information

Caithness-Moray Needs Case Consultation

Caithness-Moray Needs Case Consultation Caithness-Moray Needs Case Consultation Introduction RenewableUK and Scottish Renewables are the leading trade associations for renewable technologies in the UK and Scotland respectively, and welcome the

More information

OFFSHORE WIND PROCUREMENT

OFFSHORE WIND PROCUREMENT OFFSHORE WIND PROCUREMENT Raymond Cravitz Procurement Manager 17 09 2015 Irish Sea DONG Energy is a leading energy group in Northern Europe Overview #1 in Danish energy markets Global leader in offshore

More information

We keep Britain on the move

We keep Britain on the move Owner Driver Scheme We keep Britain on the move Parcelforce Worldwide Parcelforce Worldwide is part of the Royal Mail Group Ltd (turnover 8.4 billion) and is one of the top five express carrier businesses

More information

TERMS OF BUSINESS AGREEMENT

TERMS OF BUSINESS AGREEMENT Insurance and Reinsurance Brokers Iris Insurance Brokers Ltd 7 th Floor, New London House 6 London Street, London, EC3R 7LP United Kingdom. Tel: +44 (0)20 3178 7872 Fax: +44 (0)1702 431 644 Email: mail@irisib.com

More information

Opportunities for the Georgian Hydropower industry to benefit from Directive 2009/28EC of the European Parliament

Opportunities for the Georgian Hydropower industry to benefit from Directive 2009/28EC of the European Parliament Promotion hidroenergetikasi Project investiciebis (HIPP) Opportunities for the Georgian Hydropower industry to benefit from Directive 2009/28EC of the European Parliament What Europe wants to do Comply

More information

Post Office Personal Loans Terms & Conditions

Post Office Personal Loans Terms & Conditions Post Office Personal Loans Terms & Conditions 1. INTRODUCTION Post Office Personal Loans are provided by Bank of Ireland Personal Finance Limited. In this Agreement, we, Bank of Ireland Personal Finance

More information

The Electrical Safety Regulation (pre and post 1 January 2014)

The Electrical Safety Regulation (pre and post 1 January 2014) The Electrical Safety Regulation (pre and post 1 January 2014) The following table provides an overview comparison between the Electrical Safety Regulation 2002 (the ESR 2002) current as at 1 July 2013

More information

EXPLANATORY NOTES & CONDITIONS

EXPLANATORY NOTES & CONDITIONS ON FARM SCHEME OF GRANT AID FOR THE DEVELOPMENT OF THE ORGANIC SECTOR EXPLANATORY NOTES & CONDITIONS It is important to read the Explanatory Notes and Conditions before making application under this Scheme

More information

UKLPG APPROVED AUTOGAS INSTALLER CONSUMER CODE

UKLPG APPROVED AUTOGAS INSTALLER CONSUMER CODE UKLPG APPROVED AUTOGAS INSTALLER CONSUMER CODE e-mail autogas@uklpg.org Website www.drivelpg.co.uk Office 2.2, Christchurch Business Centre, Grange Road, Christchurch, Dorset, BH23 4JD. CONTENTS SECTION

More information

Next Directory RPC Policy Document

Next Directory RPC Policy Document Introduction to the insurance This is your policy document for your product valued up to but not exceeding 150 and should be read in conjunction with your certificate of insurance. In return for the payment

More information

Version: 3.3 November 2011

Version: 3.3 November 2011 Version: 3.3 November 2011 This booklet has been designed to inform RevenueSA clients using the Stamp Duty and Stamp Duty Opinions section of RevNet of their responsibilities and sets out the guidelines

More information

Distributed Generation Standards under the ENC Licence

Distributed Generation Standards under the ENC Licence Distributed Generation Standards under the ENC Licence Effective from: February 2012 BK-CSR-IG-0127 GTC Distributed Generation Standards under ENC Licence Rev 01 Page 1 of 7 Introduction The following

More information

WHAT HAPPENS NEXT? No: S092

WHAT HAPPENS NEXT? No: S092 WHAT HAPPENS NEXT? No: S092 CONTENTS About us Your quotation Insurance Postponement waiver Waiting time Packing services What to do next Payment Contacting us About us Simpsons Removals & Storage Ltd is

More information

APPLICATION FOR A STREET TRADING CONSENT

APPLICATION FOR A STREET TRADING CONSENT LOCAL GOVERNMENT (MISCELLANEOUS PROVISIONS) ACT 1982 APPLICATION FOR A STREET TRADING CONSENT 1. APPLICANT DETAILS Full Name: Current Residential Address: Telephone Number: Mobile Number (optional): Email:

More information

SERVICE CLASSIFICATION NO. 14-RA STANDBY SERVICE

SERVICE CLASSIFICATION NO. 14-RA STANDBY SERVICE Fourth Revised Leaf No. 135 Consolidated Edison Company Superseding Second Revised Leaf No. 135 of New York, Inc. (Third Revised Leaf No. 135 Canceled) Applicable to Use of Service for SERVICE CLASSIFICATION

More information

Simulation of Cable Overloading Problem on a University Distribution System

Simulation of Cable Overloading Problem on a University Distribution System Advance in Electronic and Electric Engineering. ISSN 2231-1297, Volume 3, Number 6 (2013), pp. 765-770 Research India Publications http://www.ripublication.com/aeee.htm Simulation of Cable Overloading

More information

Property & Terrier Team Leader. Office based hot desk/touch down worker

Property & Terrier Team Leader. Office based hot desk/touch down worker ROLE PROFILE Role profile Career Grades C, D & E Role Title Property & Terrier Officer (Level 1) Role Grade: GRADE C Role Reference: Reports to: Behavioural Competency Job Type: Work Style Definition Primary

More information

Getting Connected. A guide to how to apply for a New Connection to the Network

Getting Connected. A guide to how to apply for a New Connection to the Network Getting Connected A guide to how to apply for a New Connection to the Network About Us SP Energy Networks is part of the ScottishPower Group of companies. We provide power on behalf of supply companies

More information

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited TABLE OF CONTENTS 1.0 Purpose and Scope...2 1.1 Methodology Purpose...2

More information

Feed-in Tariff Application Form

Feed-in Tariff Application Form Feed-in Tariff Application Form How to complete this form This is an application form for ScottishPowers Feed-in Tariff (FIT) Scheme. ScottishPower is a mandatory FIT licensee and is required to register

More information

Electricity in Egypt

Electricity in Egypt T: (+20) 2 3760 4592 F: (+20) 2 3760 4593 A: 16 Hussein Wassef Street, Messaha Square Dokki, Giza, Egypt 12311 www.ide.com.eg Electricity in Egypt Policy and Regulatory Reform November 2015 Electricity

More information

SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-33 EXPERIMENTAL PRICE PLAN FOR SUPER PEAK TIME-OF-USE GENERAL SERVICE

SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-33 EXPERIMENTAL PRICE PLAN FOR SUPER PEAK TIME-OF-USE GENERAL SERVICE SALT RIVER PROJECT AGRICULTURAL IMPROVEMENT AND POWER DISTRICT E-33 EXPERIMENTAL PRICE PLAN FOR SUPER PEAK TIME-OF-USE GENERAL SERVICE Effective: April 2015 Billing Cycle Supersedes: November 2012 Billing

More information

Bell does not make personal recommendations as to the suitability of the Policy to individual circumstances.

Bell does not make personal recommendations as to the suitability of the Policy to individual circumstances. Car Hire Cover Demands and Needs Statement This Policy meets the demands and needs of a driver whose vehicle has been rendered a total loss in a road traffic accident or stolen recovered incident or had

More information