Christ Church Heating, Ventilation & Air. System Procurement Overview Forum November 10, 2013
|
|
- Jessica Lawrence
- 7 years ago
- Views:
Transcription
1 Christ Church Heating, Ventilation & Air Conditioning (HVAC)Project System Procurement Overview Forum November 10,
2 System Overview Most comprehensive and expensive systems we own Church & Parish House have several systems that together provide A/C, heating, and limited ventilation Main systems date from 1950 and the remodel efforts Church: water from boiler room and Meade cellar used to heat and cool both the church and the Parish House Parish House First floor offices use window AC units and radiant floor heating Auditorium has independent cooling system and uses forced air heat Additional spaces are cooled and heated with forced air system 2
3 Diagram of the HVAC system components 3
4 Why replace the HVAC system Systems antiquated, unreliable, and components are failing Outside technical expertise required to manage controls Can not adequately control temperature and humidity impacts piano, organ, and church interior Single mode system either heat or air conditioning Poor ventilation control Controls are mechanical no central monitoring or control System is not very effective or efficient 4
5 HVAC Replacement Timeline May Increasing number of system failures Fall Vestry authorized an engineering study Mar Engineering consultant study recommended replacing the HVAC system Apr HVAC study group began bi-weekly meetings Evaluated system problems Developed an acquisition plan vestry approved Oct 2012 Developed a Request For Proposal vestry approved Nov 2012 Dec 2012 RFP Issued Mar Selected RM Thornton as the design-builder May 2013 Began development of system design 5
6 Where are we now Full design received 5 Nov 13 Initial estimate in hand now Guaranteed Maximum Price Due 15 Nov 13 Funding plan 3 sources Church contingency planning fund - reserve fund Foundation yearly allocations to the church Capital Campaign Need a loan as a cash management tool 6
7 Phased Construction Plan Phase 1 replace chiller and cooling tower Cost = $ 793,000 Estimated 3 months work mostly in basement & FH roof To have AC by Easter -we need to have a contract by 1 Dec 13 Phase 2 Church systems Cost = $ 365,000 Replace air handlers in tower & basement + new ceiling vent Estimated 3 months work Will require us to be out of the church for 2-14 weeks 7
8 Phased Construction Plan, cont. Phase 3 Memorial Parish House Cost = $ 435,000 Replace boiler, auditorium AC unit, remove crows nest storage area, & install new system duct work Estimated 6 mo. work in main office area, basement and auditorium Phase 4 Old Parish House Cost = $435,000 Replace remaining equipment and replace system duct work Estimated 6 mo. work in Meade Room and upstairs offices 8
9 Project Risks City Permits Low -medium Need to be on city calendar for their 18 Dec meeting Only minor exterior changes Need to upgrade electrical system Unknowns Lead paint, asbestos, mold, building structure Other????? Price low risk due to contractor GMP 9
10 What will the new system bring us? Will get our air conditioning working Greatly improved HVAC system reliability Ventilation for church and Parish Hall Fully automated controls Automated system controls Ability to control most spaces separately Improved maintainability Improved energy efficiency 10
11 Project Installation Schedule & Funding Option What Construction dates Project Cost Reserve $ Available For Build Foundation Property Allocation Available Loan Needed Capital Campaign Funds Needed or Received Date(s) Funding Required Comment Phase 1 Install new chiller and cooling tower -est. ~3 months 528, ,000 Available December 2013 Jan - Mar , ,523 Jan - Mar Weeks lead time required to order equipment requires signing a contract in late November 2013 Phase 2 Church AHU's, and vent changes -est. ~ 3 months Jan - Mar , , ,058 Jan - Mar 2014 Need loan in place by Jan 2014 PM Costs Thru March 15, ,058 Needed Feb & Mar 2014 To do Phases 1 & 2 consecutively we will draw from the loan funding by April 30th Phase 3 Memorial Parish House -est. ~ 6 months May-Jul , ,904 Loan requirement assuming no new funds from capital campaign Phase 4 Old Parish House -est. ~ 6 months PM and Commission Testing Costs Aug-Oct , ,000 1,212,750 May-Oct ,000 1,237,750 1,237,750 Total Project Cost 2,055,750 Loan requirement assuming no new funds from capital campaign Loan requirement assuming no new funds from capital campaign Note 1: PM cost are estimates only and are based on how fast the project proceeds Note 2: The funding requirements here assume no capital campaign funds are raised before Oct Result we need a loan of ~$1,250,000 and Capital Campaign to pay this off. Note 3: All figures are ±20% now but we will have the Guaranteed Maximum Price (GMP) NLT 15 November 11
12 Comments and Questions? 12
AT&T Global Network Client for Windows Product Support Matrix January 29, 2015
AT&T Global Network Client for Windows Product Support Matrix January 29, 2015 Product Support Matrix Following is the Product Support Matrix for the AT&T Global Network Client. See the AT&T Global Network
More informationCOMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun
More informationCOMPARISON OF FIXED & VARIABLE RATES (25 YEARS) CHARTERED BANK ADMINISTERED INTEREST RATES - PRIME BUSINESS*
COMPARISON OF FIXED & VARIABLE RATES (25 YEARS) 2 Fixed Rates Variable Rates FIXED RATES OF THE PAST 25 YEARS AVERAGE RESIDENTIAL MORTGAGE LENDING RATE - 5 YEAR* (Per cent) Year Jan Feb Mar Apr May Jun
More informationThe main steam enters the building in the basement mechanical room; this is where the condensate line also leaves the building.
MSV: Square Footage: 24,844 No. of Floors: 1 Year Built: 1963 Type of Use: Lounge and dining area open all night for snacks Steam Water-cooled condenser, 50-Ton York unit with a 6 cylinder-reciprocating
More informationAnalysis One Code Desc. Transaction Amount. Fiscal Period
Analysis One Code Desc Transaction Amount Fiscal Period 57.63 Oct-12 12.13 Oct-12-38.90 Oct-12-773.00 Oct-12-800.00 Oct-12-187.00 Oct-12-82.00 Oct-12-82.00 Oct-12-110.00 Oct-12-1115.25 Oct-12-71.00 Oct-12-41.00
More informationCase 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138. Exhibit 8
Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 1 of 138 Exhibit 8 Case 2:08-cv-02463-ABC-E Document 1-4 Filed 04/15/2008 Page 2 of 138 Domain Name: CELLULARVERISON.COM Updated Date: 12-dec-2007
More information5-Minute Primer for Commercial Building Energy Audits
5-Minute Primer for Commercial Building Energy Audits Why Energy Audits? Because an energy audit is the first step to saving energy at your facility. Putting together an energy project can be like finding
More informationEnhanced Vessel Traffic Management System Booking Slots Available and Vessels Booked per Day From 12-JAN-2016 To 30-JUN-2017
From -JAN- To -JUN- -JAN- VIRP Page Period Period Period -JAN- 8 -JAN- 8 9 -JAN- 8 8 -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- -JAN- 8-JAN- 9-JAN- -JAN- -JAN- -FEB- : days
More informationGeorgian Bay General Hospital Strategic Energy Management Plan 2014
Georgian Bay General Hospital Strategic Energy Management Plan 2014 TABLE OF CONTENTS TABLE OF CONTENTS... 2 INTRODUCTION... 3 ENERGY MANAGEMENT VISION... 4 GUIDING PRINCIPLES FOR STRATEGIC ENERGY MANAGEMENT...
More informationQUALIFIED SCHOOL CONSTRUCTION BONDS (QSCB) FIRST YEAR REVIEW
QUALIFIED SCHOOL CONSTRUCTION BONDS (QSCB) FIRST YEAR REVIEW Slide 2: Quick Update Slides 3-4: Project Timeline Slides 5-19: Project Photographs Slides 20-29: Roof Photographs Slides 30-32: Budget Summary
More informationSubtropical Cities September 2006. Design for Energy Efficiency in Commercial Buildings in Queensland
Subtropical Cities September 2006 Design for Energy Efficiency in Commercial Buildings in Queensland Contents Typical Building Constraints & Requirements Understanding Energy Consumption in Buildings HVAC
More informationOff white sheetrock May 07 no asbestos found. Bralley Annex sheetrock office/room 106 May 07 removed pipe insulation mechanical room Mar 05 removed
Buildings and Building Materials Locations of Building Materials Report Date Status ACT/Admisions Building sheet rock hallways and stairwells Oct 02 removed ceiling texture 2nd and 6th floor men's restrooms,
More informationCENTERPOINT ENERGY TEXARKANA SERVICE AREA GAS SUPPLY RATE (GSR) JULY 2015. Small Commercial Service (SCS-1) GSR
JULY 2015 Area (RS-1) GSR GSR (LCS-1) Texarkana Incorporated July-15 $0.50690/Ccf $0.45450/Ccf $0.00000/Ccf $2.85090/MMBtu $17.52070/MMBtu Texarkana Unincorporated July-15 $0.56370/Ccf $0.26110/Ccf $1.66900/Ccf
More informationEarned Value Management Tutorial Module 8: Reporting. Prepared by:
Earned Value Management Tutorial Module 8: Reporting Prepared by: Module 8: Government Required Reports Welcome to Module 8. The objective of this module is to introduce you to Government required reports.
More informationRetrofit HVAC. Heating, Ventilation, and Air Conditioning Services
Retrofit HVAC Heating, Ventilation, and Air Conditioning Services Mission Reach home owners seeking low cost HVAC repair and maintenance. Provide low cost, quality HVAC services to home owners within the
More informationHome Improvement. Sarasota/Bradenton/Venice Market
Home Improvement Sarasota/Bradenton/Venice Market In Sarasota/Bradenton/Venice Per capita home center & hardware store sales are 19% above the national average. Home Center & Hardware Store Sales Per Capita
More informationComputing & Telecommunications Services Monthly Report March 2015
March 215 Monthly Report Computing & Telecommunications Services Monthly Report March 215 CaTS Help Desk (937) 775-4827 1-888-775-4827 25 Library Annex helpdesk@wright.edu www.wright.edu/cats/ Last Modified
More informationSino-Italian Environment & Energy Building S I E E B
MOST Ministry of Science and Technology Republic of China Sino-Italian Environment & Energy Building S I E E B Concept The Sino-Italy Environment & Energy Building (SIEEB) is an intelligent, ecological
More informationProposal to Reduce Opening Hours at the Revenues & Benefits Coventry Call Centre
Proposal to Reduce Opening Hours at the Revenues & Benefits Coventry Call Centre Proposal To change the opening hours of the Revenues & Benefits Call Centre to 9am until 5pm Monday to Friday with effect
More informationAshley Institute of Training Schedule of VET Tuition Fees 2015
Ashley Institute of Training Schedule of VET Fees Year of Study Group ID:DECE15G1 Total Course Fees $ 12,000 29-Aug- 17-Oct- 50 14-Sep- 0.167 blended various $2,000 CHC02 Best practice 24-Oct- 12-Dec-
More information2015-16 BCOE Payroll Calendar. Monday Tuesday Wednesday Thursday Friday Jun 29 30 Jul 1 2 3. Full Force Calc
July 2015 CM Period 1501075 July 2015 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 August 2015 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26
More informationBond Priorities. Repairs and Maintenance. School Safety. Capacity
Replace old windows, boilers, heating and air conditioning system. Improve accessibility for disabled persons. Keyless entry lock systems, redesign of school entrance, and wireless access throughout building.
More informationSea Water Heat Pump Project
Sea Water Heat Pump Project Alaska SeaLife Center, Seward, AK Presenter: Andy Baker, PE, YourCleanEnergy LLC Also Present is ASLC Operations Manager: Darryl Schaefermeyer ACEP Rural Energy Conference Forum
More informationImproving comfort and energy efficiency in a nursery school design process S. Ferrari, G. Masera, D. Dell Oro
Improving comfort and energy efficiency in a nursery school design process S. Ferrari, G. Masera, D. Dell Oro Dept. Building Environment Science &Technologies Politecnico di Milano Italy Research funded
More informationInternational Telecommunication Union SERIES L: CONSTRUCTION, INSTALLATION AND PROTECTION OF TELECOMMUNICATION CABLES IN PUBLIC NETWORKS
International Telecommunication Union ITU-T TELECOMMUNICATION STANDARDIZATION SECTOR OF ITU Technical Paper (13 December 2013) SERIES L: CONSTRUCTION, INSTALLATION AND PROTECTION OF TELECOMMUNICATION CABLES
More informationMONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #5
Rendering Provided by McKissick Associates MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #5 Additions and Alterations to Williamsport Area Middle School Williamsport Area School District 17 July 2012 Geo-Thermal
More informationDallas/Fort Worth International Airport District Energy Plant Upgrades Project Making More with Less Sustainable Communities Conference Dallas, TX
Dallas/Fort Worth International Airport District Energy Plant Upgrades Project Making More with Less Sustainable Communities Conference Dallas, TX March 10, 2009 Agenda DFW Capital Development Program
More information2015 RACE TO ZERO STUDENT DESIGN COMPETITION
2015 RACE TO ZERO STUDENT DESIGN COMPETITION Team Members / Industrial Partners A. TEAM and INDUSTRY PARTNERSHIPS B C D E F G H I A. TEAM B C D E F G H I J A C D E F G H I J B. DESIGN GOALS Project Site
More informationHow To Design An Hvac Design For A Stick Built Home
LEGALETT HVAC DESIGN FEE SCHEDULE (revised April 17, 2012) Background In the past Legalett has simply supplied warm floors for comfortable living. However, 2012 Building Code changes in Ontario make it
More information2015 Settlement Calendar for ASX Cash Market Products ¹ Published by ASX Settlement Pty Limited A.B.N 49 008 504 532
2015 Calendar for ASX Cash Market Products ¹ Published by ASX Pty Limited A.B.N 49 008 504 532 Calendar for ASX Cash Market Products¹ ASX Pty Limited (ASX ) operates a trade date plus three Business (T+3)
More information2 STEPS TO CONDUCTING YOUR HVAC ASSESSMENT
Presentation Synopsis Heating, Ventilating and Air Conditioning Building Condition Assessment Vancouver, B.C. Prepared for: EPIC Prepared by: Douglas Spratt, P.Eng Douglas Spratt & Associates Ltd. www.dspratt-associates.com
More informationEnergy Efficiency: Integrated Design and HVAC Systems HEALTHCARE - TOP 5 GREEN BUILDING STRATEGIES
EPA Publication 909-F-07-001 What? Energy use in healthcare facilities is higher than nearly all other building types. With rising energy costs and climate change concerns energy efficiency is financially
More informationACCESS Nursing Programs Session 1 Center Valley Campus Only 8 Weeks Academic Calendar 8 Weeks
Session 1 Academic Calendar August 24, 2015 to October 17, 2015 Tuesday / Thursday, 5:30 pm to 8:30 pm M/W T/TH T/W TH S Saturday lab as scheduled Classes Begin 24-Aug 25-Aug 25-Aug 27-Aug 29-Aug NU205
More informationACCESS Nursing Programs Session 1 Center Valley Campus Only 8 Weeks Academic Calendar 8 Weeks
Session 1 Academic Calendar August 24, 2015 to October 17, 2015 Tuesday / Thursday, 5:30 pm to 8:30 pm M/W T/TH T/W TH S Saturday lab as scheduled Classes Begin 24-Aug 25-Aug 25-Aug 27-Aug 29-Aug NU205
More informationResource Management Spreadsheet Capabilities. Stuart Dixon Resource Manager
Resource Management Spreadsheet Capabilities Stuart Dixon Resource Manager Purpose Single view of resource data Shows rolling demand vs supply for 14 months, 2 months back, current month, and 11 forward
More informationClosed Crawl Spaces. Applied Building Science Team Cyrus Dastur. Presented to the NAWSRC, July 2006
Closed Crawl Spaces Applied Building Science Team Cyrus Dastur Presented to the NAWSRC, July 2006 Advanced Energy ABS Team High performance home programs Training and process consulting Failure diagnostics
More informationPurchased Services Areas of Opportunity:
Purchased Services Areas of Opportunity: How Texas Children's Hospital Achieved Significant Cost Savings For Its Contract Staffing Purchased Services Presented by Edward M. Lewis, C.P.M., CMRP Supply Chain
More informationClimatography of the United States No. 20 1971-2000
Climate Division: CA 4 NWS Call Sign: Month (1) Min (2) Month(1) Extremes Lowest (2) Temperature ( F) Lowest Month(1) Degree s (1) Base Temp 65 Heating Cooling 1 Number of s (3) Jan 59.3 41.7 5.5 79 1962
More informationEBS Building Operators Standard Operating Procedures BUILDING OPERATION & MAINTENANCE
EBS Building Operators Standard Operating Procedures BUILDING OPERATION & MAINTENANCE Maintenance Information: Routine maintenance requests are handled through the full time 24/7 Building Maintenance staff.
More information6 Units - Clearwater
6 Units - Clearwater For more information contact: Brad Carter, CCIM 727-481-6842 bdcarter@tampabay.rr.com Phone: 727-481-6842 9225 Ulmerton Rd. Suite P Largo, FL 33771 www.tip-properties.com Real Estate
More informationClimatography of the United States No. 20 1971-2000
Climate Division: CA 6 NWS Call Sign: SAN Month (1) Min (2) Month(1) Extremes Lowest (2) Temperature ( F) Lowest Month(1) Degree s (1) Base Temp 65 Heating Cooling 100 Number of s (3) Jan 65.8 49.7 57.8
More informationResidential HVAC Load Sizing Training October 14, 2015. David Kaiser Green Code Plan Reviewer
Residential HVAC Load Sizing Training October 14, 2015 David Kaiser Green Code Plan Reviewer DCRA - Green Building Division Regulations of green codes including: Green Building Act Green Construction Code
More informationFor the best ventilation performance, whole-house air distribution is key. Clean Breathing in Production Homes
For the best ventilation performance, whole-house air distribution is key. Clean Breathing in Production Homes by Armin Rudd and Joseph Lstiburek With houses today being built with tighter and tighter
More informationRequest for Proposal for Construction Management Services
Willmar Public Schools- ISD 347 611 5 th Street SW Willmar MN 56201 Dr. Jeffrey Holm, Superintendent Request for Proposal for Construction Management Services Willmar Public Schools is soliciting Construction
More informationHuman Resources Management System Pay Entry Calendar
Human Resources Management System Pay Entry Calendar http://www1.umn.edu/ohr/payroll/calendars/index.html Important Information The system is unavailable for entry, due to maintenance, during the following
More informationDirect Fresh Air Free Cooling of Data Centres
White Paper Introduction There have been many different cooling systems deployed in Data Centres in the past to maintain an acceptable environment for the equipment and for Data Centre operatives. The
More informationAcademic Calendar 2015-2018 Arkansas State University - Jonesboro
Shared Governance Proposal Any constituent (individual or group) may submit a proposal into the shared governance process. In order to be considered, each proposal must contain the following and be directed
More informationGUIDE TO CREATING A CAPITAL CAMPAIGN PLAN: CONTENTS
GUIDE TO CREATING A CAPITAL CAMPAIGN PLAN: CONTENTS NOTE (9-17-10): This Guide wasn t designed as a template for a capital campaign plan. It was originally created as a tool and proposal attachment for
More informationQuestion/Answer Addendum to Request for Proposals for HVAC/Maintenance Services
Question/Answer Addendum to Request for Proposals for HVAC/Maintenance Services Q1: Why is the County requesting proposals for HVAC and Maintenance services? A1: The County currently has one HVAC specialist
More informationMONTHLY REMINDERS FOR 2013
MONTHLY REMINDERS FOR 2013 Legend: Red IRS Due Dates Green Department of Revenue Due Dates Blue Parish Finance Due Dates Black Second Collections JANUARY 4 Deposit payroll tax for payments on Jan 1 if
More informationHVAC Systems: Overview
HVAC Systems: Overview Michael J. Brandemuehl, Ph.D, P.E. University of Colorado Boulder, CO, USA Overview System Description Secondary HVAC Systems Air distribution Room diffusers and air terminals Duct
More informationNational Energy Efficiency and Renewable Energy Action (NEEREA) August 2014
National Energy Efficiency and Renewable Energy Action (NEEREA) August 2014 Prepared by: Melda Jabbour, Energy Engineer, Lebanese Center for Energy Conservation (LCEC) Rana El-Guindy, Junior analyst -
More informationMay 2014 Texas School Bond Elections
May 2014 Texas School Bond Elections What are the individual districts needs? New facilities Renovations Technology Central facilities How much tax revenue can the district generate? Depends on district
More informationMequon - Thiensville School District Long Range Facilities Plan Monthly Project Schedule
Mequon - Thiensville School District Long Range Facilities Plan Monthly Project Schedule Homestead HS Sept.'15 Oct'15 Nov'15 Dec'15 Jan'16 Feb'16 Repair Asphalt @ Main Garage Replace Exterior Hollow Metal
More informationDetailed guidance for employers
April 2015 3 Detailed guidance for employers Appendix A: Pay reference periods This document accompanies: Detailed guidance no. 3 Assessing the workforce Pay reference period calendars where the definition
More informationHamilton-Wentworth Catholic District School Board Event Listing By Ascending Event Year
Hamilton-Wentworth Catholic District School Board Event Listing By Ascending Event Year Printed On: 2003/04/03 St Patrick CES, 7932 Study [03.3-050 Plumbing Piping Systems] Study condition, remaining service
More informationAccident & Emergency Department Clinical Quality Indicators
Overview This dashboard presents our performance in the new A&E clinical quality indicators. These 8 indicators will allow you to see the quality of care being delivered by our A&E department, and reflect
More informationConsumer ID Theft Total Costs
Billions Consumer and Business Identity Theft Statistics Business identity (ID) theft is a growing crime and is a growing concern for state filing offices. Similar to consumer ID theft, after initially
More informationDepartment of Public Welfare (DPW)
Department of Public Welfare (DPW) Office of Income Maintenance Electronic Benefits Transfer Card Risk Management Report Out-of-State Residency Review FISCAL YEAR 2012-2013 June 2013 (March, April and
More informationLegislative Brief: PAY OR PLAY PENALTIES LOOK BACK MEASUREMENT METHOD EXAMPLES. EmPowerHR
EmPowerHR Legislative Brief: PAY OR PLAY PENALTIES LOOK BACK MEASUREMENT METHOD EXAMPLES The Affordable Care Act (ACA) imposes a penalty on applicable large employers (ALEs) that do not offer health insurance
More informationOPTIMAL POLYGEN COOLING CONCEPT FOR ST. OLAVS HOSPITAL IN TRONDHEIM, NORWAY
1st European Conference on Polygeneration OPTIMAL POLYGEN COOLING CONCEPT FOR ST. OLAVS HOSPITAL IN TRONDHEIM, NORWAY G. Eggen 1, A. Utne 2 1) COWI A/S, PB 2564 Sentrum, NO-7414 Trondheim, Norway, e-mail:
More informationP/T 2B: 2 nd Half of Term (8 weeks) Start: 25-AUG-2014 End: 19-OCT-2014 Start: 20-OCT-2014 End: 14-DEC-2014
2014-2015 SPECIAL TERM ACADEMIC CALENDAR FOR SCRANTON EDUCATION ONLINE (SEOL), MBA ONLINE, HUMAN RESOURCES ONLINE, NURSE ANESTHESIA and ERP PROGRAMS SPECIAL FALL 2014 TERM Key: P/T = Part of Term P/T Description
More informationLevel 1 Energy Audit Report. For: Gladstone Regional Council
Level 1 Energy Audit Report For: Gladstone Regional Council Gladstone Art Gallery & Museum Conducted by: Jamie Rogers - EcoXpert Barnes Electrical Service 1/54 Callemondah Drive Gladstone QLD 4680 Mob:
More informationCAFIS REPORT 2015.10
CAFIS REPORT 2015.10 INDEX Message CAFIS Inbound 03-06 07-08 CAFIS Arch 09-10 CAFIS Brain 11-12 CAFIS Global 13-14 What We Do 15-16 About CAFIS 17-18 Services for Member Stores 19-34 Services for Card
More informationP/T 2B: 2 nd Half of Term (8 weeks) Start: 26-AUG-2013 End: 20-OCT-2013 Start: 21-OCT-2013 End: 15-DEC-2013
2013-2014 SPECIAL TERM ACADEMIC CALENDAR FOR SCRANTON EDUCATION ONLINE (SEOL), MBA ONLINE, HUMAN RESOURCES ONLINE, NURSE ANESTHESIA and ERP PROGRAMS SPECIAL FALL 2013 TERM Key: P/T = Part of Term P/T Description
More informationRepair Project for April 7, 2009
Repair Project for April 7, 2009 Scope of the Project HVAC Upgrades Roof Replacement Window Replacement/Exterior Openings Science Lab Renovations New Fire Alarm/Electrical AAB (accessibility) Upgrades
More informationUNIVERSITY OF DAYTON DAYTON OHIO 2015-2016 ACADEMIC CALENDAR
UNIVERSITY OF DAYTON DAYTON OHIO 2015-2016 ACADEMIC CALENDAR FALL 2015 Mon, Aug 3 Tue, Aug 18 Thu, Aug 20 Sat, Aug 22 Sat-Tue, Aug 22-25 Sun, Aug 23 Tue, Aug 25 Tue, Aug 25 Wed, Aug 26 Tue, Sep 1 Mon,
More informationP/T 2B: 2 nd Half of Term (8 weeks) Start: 24-AUG-2015 End: 18-OCT-2015 Start: 19-OCT-2015 End: 13-DEC-2015
2015-2016 SPECIAL TERM ACADEMIC CALENDAR For Scranton Education Online (SEOL), Masters of Business Administration Online, Masters of Accountancy Online, Health Administration Online, Health Informatics
More informationUNIVERSITY OF MISSOURI 23 0000 - Heating Ventilating and Air-Conditioning (HVAC) March 2015.01
GENERAL: This section provides general standards for overall sizing and design of Heating, Ventilating, and Air Conditioning (HVAC) systems. Other sections contain specific standards for each system per
More informationNatural Gas Wholesale Prices at PG&E Citygate as of November 7, 2006
QUARTERLY GAS ISSUES UPDATE December 26 I. Supply Issues Wholesale Natural Gas Prices Above normal temperatures and a lack of hurricane activity caused market prices to decrease in October. By November,
More informationMURCH ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1929 BUILDING AREA 47,700 SF CURRENT PROGRAM CAPACITY 479 ENROLLMENT 2008 491 WARD 3 PROPOSED PROGRAM CAPACITY 500 Site Plan MURCH - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION PK-5
More information2016 Examina on dates
Please note the following informa on: The following exams are available throughout the year: Please click on the exam for which you wish to see the dates. When you have finished, you can select to return
More informationLONDON METROPOLITAN ARCHIVES LONDON METHODIST MISSION (TOOTING) CIRCUIT ACC/2707
Page 1 Reference Description Dates BALHAM HILL CHURCH /019 Microfilm Please use mircofilm Register of baptisms 30 Jan 1898-14 Mar 1920 COLLIERS WOOD METHODIST MISSION /020 Microfilm Please use mircofilm
More informationA!Team!Cymru!EIS!Report:!Growing!Exploitation!of!Small! OfCice!Routers!Creating!Serious!Risks!
ATeamCymruEISReport:GrowingExploitationofSmall OfCiceRoutersCreatingSeriousRisks PoweredbyTeamCymru sthreatintelligencegroup Page 1of 14www.team-cymru.com www.team-cymru.com Threat'Intelligence'Group EXECUTIVE
More informationClimatography of the United States No. 20 1971-2000
Climate Division: CA 2 NWS Call Sign: SAC Month (1) Min (2) Month(1) Extremes Lowest (2) Temperature ( F) Lowest Month(1) Degree s (1) Base Temp 65 Heating Cooling 100 Number of s (3) Jan 53.8 38.8 46.3
More informationHomewyse 2010 Home Ownership Cost Report
November 2010 Homewyse 2010 Home Ownership Cost Report Editors and Staff Homewyse Smart Home Decisions 2010 Home Ownership Cost Report 2 SUMMARY Next to mortgage expenses, home maintenance and repair costs
More informationPresentation Outline. Common Terms / Concepts HVAC Building Blocks. Links. Plant Level Building Blocks. Air Distribution Building Blocks
Presentation Outline Common Terms / Concepts HVAC Building Blocks Plant Level Building Blocks Description / Application Data Green opportunities Selection Criteria Air Distribution Building Blocks same
More informationBUILDING ASSESSMENT QUESTIONNAIRE. B. TENANTS Is there more than one tenant in the building? YES
Department of Health and Human Services, Division of Public Health Occupational and Environmental Epidemiology Branch 1912 Mail Service Center, Raleigh, North Carolina 27699-1912 BUILDING ASSESSMENT QUESTIONNAIRE
More informationContinuous Commissioning of the Dallas/Fort Worth International Airport
Continuous Commissioning of the Dallas/Fort Worth International Airport Jerry R. Dennis, CEM, CEP Rusty T., P.E., CEM, CEP, LEED AP Larry Kramer, P.E., CEM DFW International Airport Energy and Transportation
More informationUniversity of Wisconsin System Strategic Initiatives
University of Wisconsin System Strategic Initiatives April 27,2015 Sasi K. Pillay UWSA CIO 1 Principles Mission Enablement Reduction of Risk Cost-effective Operations 2 The Four Tenets A. Elevate the Professionalism
More informationPLUMMER ELEMENTARY SCHOOL
INITIAL YEAR BUILT 1959 BUILDING AREA 69,400 SF CURRENT PROGRAM CAPACITY 481 ENROLLMENT 2008 228 WARD 7 PROPOSED PROGRAM CAPACITY 325 Site Plan PLUMMER - 1 PROPOSED PROGRAM PROFILE GRADE CONFIGURATION
More informationThe principles, processes, tools and techniques of project management
Unit 34: Plan and manage a project. 341 The principles, processes, tools and techniques of project management An industrial project, big or small, must be managed effectively to ensure the project s objectives
More informationPerformance Contracting
Performance Contracting ENERGY STAR Monthly Partner Web Conference February 21, 2007 Call-in Number: 1-866-299-3188 Conference Code: 202 343 9965 About The Web Conferences Monthly Topics are structured
More informationROYAL REHAB COLLEGE AND THE ENTOURAGE EDUCATION GROUP. UPDATED SCHEDULE OF VET UNITS OF STUDY AND VET TUITION FEES Course Aug 1/2015
UPDATED SCHEDULE OF UNITS OF STUDY AND TUITION FEES Course Aug 1/2015 Course Name: Delivery Mode: BSB50215 Diploma of Business Online DBTEU01 01/08/2015 19/08/2015 31/10/2015 0.25 $4245 $3265 DBTEU02 01/11/2015
More informationExample of a diesel fuel hedge using recent historical prices
Example of a diesel fuel hedge using recent historical prices Firm A expects to consume 5,, litres of diesel fuel over the next 12 months. Fuel represents a large expense for the firm, and volatile prices
More informationHealth Insurance Exchange Finance Work Group Meeting August 22, 2012 Wakely Consulting Model Table Summaries - Updated
Table 3 Model Take up rate estimates 2014 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Revised 25.0% 25.0% 18.0% 3.6% 3.6% 3.6% 3.6% 3.6% 3.6% 3.6% 3.6% 3.6% Fast 12.0% 18.0% 20.0% 18.0% 6.0% 4.0% 4.0%
More informationEvery Student I Every Day I Every Possibility
For the Facilities Master Plan March 4, 2015 1 Introduction This has been prepared to describe a proposed process to be implemented in order to develop comprehensive Facility Master Plans for all schools
More informationBreen Elementary School
Breen Elementary School Day: Monday Time: 1:40 pm to 3:10 pm (90 minutes) Session A Sept 21, Sept28, Oct 5, Oct 19, Oct 26, Nov 2 No class on Oct 12 Session B Nov 30, Dec 7, Dec 14, Jan 4, Jan 11, Jan
More informationHow to develop a small business marketing plan
How to develop a small business marketing plan Introduction This template has been designed to assist you in the development of your marketing plan. Once you have undertaken each of the activities in this
More informationBefore You Start an Energy Efficiency Retrofit The Building Envelope
ABOUT YOUR HOUSE Before You Start an Energy Efficiency Retrofit The Building Envelope The building envelope is the outer layer of the building that separates the indoor living space from the outdoor environment,
More informationSECTION 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC INTRODUCTORY INFORMATION
SECTION 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC INTRODUCTORY INFORMATION The purpose of this guide specification is to assist the specifier in correctly specifying Mechanical System Testing
More informationPTC Creo 2.0 Hardware Support Dell
PTC Creo 2.0 Hardware Support Dell Last updated: February 2, 2016 The Desktop Virtualization Environment Support Dell table displays at the end of this document, after the standard Creo certification table.
More informationWe re Happy with Our CMMS. Should We Be?
We re Happy with Our CMMS. Should We Be? Upcoming Webinars Sept 2013: Multiple FM Software Applications: Is Consolidation or Integration the Answer? Oct 2013: Dec 2013: Jan 2014: Maintenance Outsourcing:
More informationDOE LHC Quarterly Review. Magnet Production Cable Testing Cost to Complete issues. Mike Harrison, BNL July 26, 2004
DOE LHC Quarterly Review Magnet Production Cable Testing Cost to Complete issues Mike Harrison, BNL July 26, 2004 1 BNL Production Status Magnet production complete The last series of dipoles (D3 s) is
More informationEnclosed Football Stadium Design History and Lessons Learned
Enclosed Football Stadium Design History and Lessons Learned Robert L. Towell, P.E., LEED AP, QCxP btowell@cxegroup.com CxE Group LLC St. Louis, Missouri 314-436-6543 With thanks to the St. Louis Convention
More informationHVAC Processes. Lecture 7
HVAC Processes Lecture 7 Targets of Lecture General understanding about HVAC systems: Typical HVAC processes Air handling units, fan coil units, exhaust fans Typical plumbing systems Transfer pumps, sump
More informationDCF - CJTS WC Claim Count ACCT DCF CJTS - Restraints InjuryLocation (All)
- CJTS WC Claim Count ACCT CJTS - Restraints InjuryLocation (All) Month Occur Mo Txt Loc Descr 2011 2012 2013 2014 2015 Grand Total 1 Jul CJTS Custody 8 12 5 8 11 44 2 CJTS Girls Unit 4 4 Jul Total 9 12
More informationContinuous Energy Management at UC San Diego. Anna Levitt, P.E. Assistant Energy Manager June 13, 2013
Continuous Energy Management at UC San Diego Anna Levitt, P.E. Assistant Energy Manager June 13, 2013 UC San Diego: A 42 megawatt Microgrid With a daily population of over 45,000, UC San Diego is the size
More informationIt s the right time... ... for sustainable development. Paul Westbrook. www.enerjazz.com/house
It s the right time...... for sustainable development Introduction Passive Solar - Passive Solar has a slightly different priority in Texas. We want to capture free heat from the sun in the winter, but
More informationCommittee of the Whole. January 22, 2014
Committee of the Whole January 22, 2014 Drivers for 2003 IT Outsourcing Cost savings - privatization model ($2- $3MM/year) Cost avoidance Data center lease with County expiring ($3.5MM) Disaster recovery
More information