1 March 22, 2012 TriAusMin Announces Go Ahead for Woodlawn Retreatment Project TriAusMin Limited (ASX: TRO) (TSX: TOR) ( TriAusMin or the Company ) is pleased to announce approval for the development of the 100% owned Woodlawn Retreatment Project ( WRP or the Project ), located 250 km southwest of Sydney, New South Wales, Australia. The Project will process 11.2 Mt of tailings material to produce separate zinc, lead and copper concentrates with by-product gold and silver. An economic evaluation forecasts the Project to generate A$199 million in net cash pre-tax and provide an Internal Rate of Return (IRR) of 33% over its 7.5 year mine life based upon development capital costs of approximately A$92.8 million (US$96.5 million). Development of the Project over the next 18 to 24 months will allow TriAusMin to join the ranks of the producing mining companies and position itself for growth of its mining business in the years ahead. CEO and Managing Director Mr. Wayne Taylor commented: We are very excited about the Company s approval for the development of the Woodlawn Retreatment Project. This will see TriAusMin advance from an exploration company into a cash flowing mining enterprise over the next two years. The Project is the first step in reactivating the Woodlawn property commencing with a project that provides a short lead time to production and good cash flows. In addition, we are moving toward re-establishing the Woodlawn underground mine with the current drilling program aiming to outline additional high-grade mineralisation below the previously mined ore lenses. Discussions regarding the financing of the Project have been initiated and we look forward to commencing construction in the third quarter of this year. Project Highlights The Base Case Scenario highlights, as shown below, indicates a very attractive return on invested capital and is based upon forward curve metal prices and foreign exchange rates as at February 27, Currency is expressed in Australian dollars unless otherwise stated. Mineral Reserves: 11.2 million tonnes at 2.2% Zn, 1.3% Pb, 0.5% Cu, 31 g/t Ag, 0.3 g/t Au Mining: 4,300 tonnes per day (1.5 Mtpa) utilising hydraulic mining Mine Life: 7.5 years Processing: Conventional milling and flotation to produce Cu, Zn, and Pb concentrates containing Ag and Au Development Capital: $92.8 million including a $5.6 million contingency Site Operating Costs: $22 per tonne processed Total NSR Revenue: $586 million Pre- Tax Net Cash Flow: $199 million Pre-Tax NPV10: $81 million C1 Unit Cost: $0.12/lb payable zinc (post by-product credits) Pre-Tax Project IRR: 33% The Tailings Retreatment Project presents a low risk reserve, mining and processing project with attractive economics at metal prices significantly below current and forecast future levels. An additional key feature of the Project is the short lead time from construction to production. Page 1 of 7

2 Project Background The Woodlawn Mine operated from 1978 to 1998 during which time it processed 13.8 million tonnes (Mt) of ore grading 9.1% zinc, 3.6% lead, 1.6% copper, 74 g/t silver and 0.52 g/t gold. The tailings dams remain from processing this ore and contain economic levels of metals that warrant reprocessing using currently available technology. The WRP will retreat approximately 11 Mt of tailings contained within the three tailings dams (North, South and West) using modern fine-grinding techniques to enhance metallurgical recoveries. The planned production rate is 1.5 Mt per annum to produce zinc, copper and lead concentrates containing by-product silver and gold. An independent NI compliant Technical Report 1 on the Project was completed in 2010 by Scott Wilson Roscoe Postle Associates Inc. ( Scott Wilson ) and confirmed the existence of Proven and Probable Ore Reserves i (see Table 1) and determined that the WRP was economically attractive at forecasted long term metal prices. Table 1 Woodlawn Retreatment Project (WRP) Reserves. Dam Classification Tonnes Grade (Mt) Zn (%) Pb (%) Cu (%) Ag (g/t) Au (g/t) South Proven Probable Prov + Prob West Proven Probable Prov + Prob North Proven Probable Prov + Prob All Dams Proven Probable Prov + Prob In January 2011, the Company initiated a $1.4 million evaluation program to move the WRP toward a development decision. An Environmental Assessment (EA) study was carried out by Parsons Brinckerhoff and submitted to the regulators and is currently undergoing final review. GR Engineering Services Limited undertook the Front-End Engineering and Design ( FEED ) Study to provide the final engineering design and update the capital and operating cost estimates to a +/- 10% level of certainty. A key component of the FEED study was a series of additional metallurgical tests focusing on selection of grinding equipment and the production of separate copper, lead and zinc concentrates. The metallurgical test work and FEED study is complete and forms the basis of many of the major input assumptions for the WRP Business Case. 1 Technical Report conformed to Canadian National Instrument Standards of Disclosure for Mineral Projects (NI ). Page 2 of 7

3 Mining Method Hydraulic mining will be used to mine the tailings in a slurry form using high pressure water pumps and monitors at a rate of 4,300 tonnes per day (1.5 Mt per annum) to be transferred to the processing plant. This method is a simple, proven, low risk, low cost mining method. Mineral Processing Standard sulfide flotation processes will be used to produce separate copper, lead and zinc concentrates with by-product silver and gold. The metallurgical test work demonstrated that effective mineral liberation is at 30 microns that can be achieved through fine grinding with an IsaMill. The key features of the process plant are: Feed preparation thickener feed delivery from the mining cycle will be through an 18 m diameter thickener to increase the feed density to the level required by the grinding circuit. Primary grinding the primary grind has been set at 30 micron to ensure maximum liberation and maximum recovery. This will be achieved through the use of a 3 MW IsaMill M10000 unit. Talc flotation the highest quality final concentrates are achieved with talc pre-float and includes rougher and cleaner stages. Copper Flotation selective copper flotation will be achieved through a circuit consisting of rougher, scavenger, cleaner and re-cleaner cells. Lead flotation selective lead flotation will be achieved through a circuit similar to copper with the addition of a regrind mill with a target grind size of 15 micron. Zinc flotation a regrind mill has also been specified for the zinc circuit with a number of additional banks of cells to accommodate higher concentrate volumes. Concentrate dewatering and storage recovered concentrates will be thickened and then filtered to reduce the moisture level so that it is acceptable for transport. The concentrates will be stored separately on site for transport to port. Infrastructure and Site Logistics Considerable supporting infrastructure including power, roads and water remain in place at the Woodlawn site presenting a significant cost benefit in project development. The existing 66kV transmission line and the onsite 66/11kV sub-station have sufficient capacity to meet the power demands for the operations and no additional offsite power infrastructure is required to be built. A 300 m access road will be constructed to link the site with the existing sealed Collector Road, which provides a B-double rated route to the major service centres and ports for concentrate shipping. Process water is available on site from the existing bore field. In addition, the existing evaporation dams that serviced the former mining operations will also be utilised to manage any fluctuations in the water balance. New infrastructure aside from the processing plant will include site offices, workshops and laboratory. Local communities are expected to provide supplies, services, accommodation and labour to the Project. Page 3 of 7

4 Regulatory Approvals An Environmental Assessment (EA) document was lodged with the NSW Department of Planning and Infrastructure (DoPI) in August for review. Their comments were received and points of clarification have been addressed. The EA is currently with the Department for a final review prior to the formal lodgement for stakeholder comment. Development Timing Construction is expected to take approximately 58 weeks from the time of award of a construction contract. A further 15 weeks has been allowed for commissioning of the plant as well as a further 6 month ramp-up period to full plant throughput and design recoveries. The Company believes that the Project could achieve first commercial production early in 2014, subject to financing and the receipt of all regulatory approvals. Capital Costs The construction capital cost estimate is provided below. The process plant and infrastructure estimates are to an overall accuracy of +/-10% and basis Q The mining capital estimates are based on January 2012 pricing quotes. Table 2 Woodlawn Retreatment Project Construction Capital Cost Estimate. PROCESS PLANT AREA CAPITAL COST A$M Process Plant $53.5 Infrastructure $11.3 Engineering, P&G, Commissioning, First Fills $18.1 Contingency $5.6 TSF 4 Construction (non GRES) $2.6 Mining Capital + Mobilisation (non GRES) $1.7 TOTAL CONSTRUCTION CAPITAL ESTIMATE $92.8 (US$96.5) Working capital of A$5 million is required to cover pre-revenue operating costs in addition to the construction capital. Minimal sustaining capital will be required during the 7.5 year mine life. Closure costs have been estimated at A$4.5 million. Operating Costs Site costs, with the exception of mining, were estimated to an overall accuracy of +/-10% and basis Q Mining costs are based on a January 2012 pricing quote from a suitably experience mining contractor. Offsite costs include the transport of concentrates to port, storage and ship loading charges and a charge for ocean freight. These have been independently sourced from third party discussions and quotes. Page 4 of 7

5 Table 3 Woodlawn Retreatment Project Operating Costs OPERATING COST AREA A$/t TREATED Mining $1.70 Processing & Administration $19.62 Off-Site (excl. concentrate treatment charges) $5.84 TOTAL OPERATING COST ESTIMATE $27.16 (US$28.4) Treatment and refining charges have been based on current published benchmark terms for the three concentrates to be produced by the operation. Financial Analysis The Base Case economic evaluation of the Project incorporated the February 27, 2012 forward curve metal prices and exchange rates: Zn US$2,107 to 2,164 /t Pb US$2,258 to 2,375 /t Cu US$7,674 to 8,523 /t Ag US$36 to 38 /oz. Au US$1,776 to 2,005 /oz FX 1.06 to 0.8 The evaluation indicates a very attractive rate of return on the invested capital as outlined below. Mineral Reserves: 11.2 million tonnes at 2.2% Zn, 1.3% Pb, 0.5% Cu, 31 g/t Ag, 0.3 g/t Au Mining: 4,300 tonnes per day (1.5 Mtpa) utilising hydraulic mining Mine Life: 7.5 years Processing: Conventional milling and flotation to produce Cu, Zn, and Pb concentrates containing Ag and Au Development Capital: $92.8 million including a $5.6 million contingency Site Operating Costs: $22 per tonne processed Total NSR Revenue: $586 million Pre- Tax Net Cash Flow: $199 million Pre-Tax NPV10: $81 million C1 Unit Cost: $0.12/lb payable zinc (post by-product credits) Pre-Tax Project IRR: 33% Page 5 of 7

6 Sensitivities The graph below presents the impact variations in the major financial and operational parametres of the project versus the Base Case. The Project is most sensitive to changes in the metallurgical recoveries and the commodity price. The project breaks even after capital repayment at a zinc price US$1498/t, lead US$1650/t, copper US$5670/t, silver US$26/oz, and gold US$1302/oz. Project Enhancements A number of opportunities have been identified to further enhance the financial performance of the WRP including but not limited to: Metallurgical recoveries improved metallurgical recoveries are possible based on the results from the final metallurgical test work. Mining costs Mining costs could be reduced through the application of owner operated mining. Page 6 of 7

7 Company Background TriAusMin is engaged in the exploration and development of base and precious metals deposits located in the Lachlan Fold Belt in New South Wales, Australia. TriAusMin s projects include the Woodlawn Tailings Retreatment Project and Woodlawn Underground Project located 250 kilometres south west of Sydney, its Lewis Ponds Project, as well as a number of other high quality exploration projects on its properties in the Lachlan Fold Belt. For further information, please visit or contact: Australia: Mr Wayne Taylor, Managing Director and Chief Executive Officer: Tel: (Sydney) inquire@triausmin.com Canada: Tel: (Toronto) info@triausmin.com This news release contains forward-looking statements and forward-looking information, which is based on information currently available to the Company, and the Company provides no assurance that actual results will meet management s expectations. Forward-looking information includes estimates and statements that describe the Company s future plans, objectives or goals, including words to the effect that the Company or management expects a stated condition or result to occur. Forward-looking information may be identified by such terms as believes, anticipates, expects, estimates, may, could, would, will, or plan. Since forward-looking information is based on assumptions and addresses future events and conditions, by their very nature they involve inherent risks and uncertainties. Actual results relating to, among other things, the receipt of the requisite regulatory approvals, the receipt of shareholder approval for the issuance of Warrants, and the use or proceeds and future business plans of the Company, could differ materially from those currently anticipated in such information for many reasons such as: the failure to obtain the requisite approvals; changes in general economic conditions and conditions in the financial markets; changes in demand and prices for minerals; litigation, legislative, environmental and other judicial, regulatory, political and competitive developments; and other matters discussed in this news release. This list is not exhaustive of the factors that may affect any of the Company s forward-looking information. These and other factors should be considered carefully and readers should not place undue reliance on the Company s forward-looking information. The Company does not undertake to update any forward-looking information that may be made from time to time by the Company or on its behalf, except in accordance with applicable securities laws. i JORC Compliance and Declarations Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (the JORC code ), 2004 Edition, JORC (of AusIMM, AIG & MC), December The information in this release that relates to Mineral Resources or Ore Reserves associated with the Woodlawn Retreatment Project is based on information compiled by qualified person, Mr. Richard Lambert, P.E. a professional engineer and Registered Member of SME. Mr. Richard Lambert is Principal Mining Engineer and Executive Vice President of Roscoe Postle Associates, Inc. He is independent of TriAusMin applying the test set out in Section 1.4 of NI He has sufficient experience relevant to the style of mineralization and type of deposit under consideration, and to the activity which he is undertaking, to qualify as a Competent Person as defined in the 2004 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (the JORC Code) and by reason of his education, affiliation with a professional association (as defined in NI43-101) and past relevant work experience, fulfils the requirements to be a "qualified person" for the purposes of NI Page 7 of 7

For personal use only

For personal use only SEPTEMBER 2011 QUARTERLY REPORT AND STATEMENT OF CASHFLOWS About TriAusMin (ASX:TRO) (TSX:TOR) TriAusMin Limited ( TriAusMin ) is an Australian development stage base and precious metals company focused

More information

Trading Symbol: TSX: SVM February 17, 2011 NYSE: SVM

Trading Symbol: TSX: SVM February 17, 2011 NYSE: SVM PRESS RELEASE Trading Symbol: TSX: SVM February 17, 2011 NYSE: SVM SILVERCORP ANNOUNCES POSITIVE PRELIMINARY ASSESSMENT FOR THE SILVERTIP SILVER-LEAD-ZINC PROJECT, BRITISH COLUMBIA, CANADA VANCOUVER, British

More information

Detour Gold Provides New Life of Mine Plan for Detour Lake

Detour Gold Provides New Life of Mine Plan for Detour Lake January 25, 2016 NEWS RELEASE Detour Gold Provides New Life of Mine Plan for Detour Lake Detour Gold Corporation (TSX: DGC) ( Detour Gold or the Company ) is pleased to announce a new life of mine plan

More information

NEVADA COPPER FILES INTEGRATED FEASIBILITY STUDY ON SEDAR

NEVADA COPPER FILES INTEGRATED FEASIBILITY STUDY ON SEDAR NEWS RELEASE TSX: NCU NEVADA COPPER FILES INTEGRATED FEASIBILITY STUDY ON SEDAR July 9, 2015 - Nevada Copper Corp. (TSX: NCU) ("Nevada Copper") (the Company ) is pleased to announce that it has completed,

More information

AFRICAN GOLD GROUP, INC. DEFINITIVE FEASIBILITY STUDY FOR KOBADA GOLD PROJECT GENERATES ROBUST ECONOMIC OUTCOME

AFRICAN GOLD GROUP, INC. DEFINITIVE FEASIBILITY STUDY FOR KOBADA GOLD PROJECT GENERATES ROBUST ECONOMIC OUTCOME African Gold Group, Inc. TSX-V: AGG Yonge & Richmond Centre 151 Yonge Street, 11th Floor. Toronto Canada M5C 2W7 Tel: +1 647 775 8538 website : www.africangoldgroup.com AFRICAN GOLD GROUP, INC. DEFINITIVE

More information

Savannah North Scoping Study Looking into the future 3 February 2016

Savannah North Scoping Study Looking into the future 3 February 2016 Savannah North Scoping Study Looking into the future 3 February 2016 ASX: PAN Disclaimer Cautionary Statements This presentation includes information extracted from Panoramic Resources Limited ASX announcement

More information

SCORPIO MINING REPORTS FIRST QUARTER 2015 FINANCIAL RESULTS

SCORPIO MINING REPORTS FIRST QUARTER 2015 FINANCIAL RESULTS SCORPIO MINING REPORTS FIRST QUARTER 015 FINANCIAL RESULTS TORONTO, ONTARIO May 13, 015 Scorpio Mining Corporation (TSX: SPM)(OTCQX: SMNPF) ( Scorpio Mining or the Company ) today reported financial and

More information

Annual General Meeting. 18 November 2015 The Grace Hotel, Sydney

Annual General Meeting. 18 November 2015 The Grace Hotel, Sydney Annual General Meeting 18 November 2015 The Grace Hotel, Sydney CAUTIONARY NOTE REGARDING FORWARD-LOOKING INFORMATION This news release contains forward-looking statements and forward-looking information

More information

2015 Third Quarter Results Webcast October 29, 2015

2015 Third Quarter Results Webcast October 29, 2015 2015 Third Quarter Results Webcast October 29, 2015 Speaker Randall Oliphant Executive Chairman 2 Cautionary statements ALL AMOUNTS IN U.S. DOLLARS UNLESS OTHERWISE STATED CAUTIONARY NOTE REGARDING FORWARD-LOOKING

More information

AVINO SILVER & GOLD MINES LTD.

AVINO SILVER & GOLD MINES LTD. AVINO SILVER & GOLD MINES LTD. T 604.682.370 Suite 900, 570 Granville Street ir@avino.com F 604.682.3600 Vancouver, BC V6C 3P www.avino.com August 8, 205 NYSE - MKT: ASM TSX-V: ASM FSE: GV6 Avino Reports

More information

Funds from the placement will be used for working capital requirements, including the completion of the Productora Pre-feasibility Study (PFS).

Funds from the placement will be used for working capital requirements, including the completion of the Productora Pre-feasibility Study (PFS). ASX ANNOUNCEMENT Monday 1 st February 2016 Hot Chili to Raise A$1.6m via Placement to Strategic Shareholders Hot Chili Limited (ASX Code: HCH) is pleased to announce that it has received commitments from

More information

NEWS RELEASE LEXAM ANNOUNCES POSITIVE PRELIMINARY ECONOMIC ASSESSMENT RESULTS FOR THE OPEN PIT PROJECTS IN TIMMINS

NEWS RELEASE LEXAM ANNOUNCES POSITIVE PRELIMINARY ECONOMIC ASSESSMENT RESULTS FOR THE OPEN PIT PROJECTS IN TIMMINS NEWS RELEASE LEXAM ANNOUNCES POSITIVE PRELIMINARY ECONOMIC ASSESSMENT RESULTS FOR THE OPEN PIT PROJECTS IN TIMMINS Project Generates 32% IRR and C$33 Million NPV After-Tax; Cash Costs of US$865 per Ounce

More information

Sorby Hills Silver Lead Project

Sorby Hills Silver Lead Project ASX RELEASE Sorby Hills Silver Lead Project Major Milestone Achieved with Environmental Approval As announced on 3 April, the WA Minister for Environment has approved the development of the Sorby Hills

More information

BUILDING A COPPER COMPANY IN BRAZIL. PDAC Feb - 2014 - TORONTO

BUILDING A COPPER COMPANY IN BRAZIL. PDAC Feb - 2014 - TORONTO BUILDING A COPPER COMPANY IN BRAZIL PDAC Feb - 2014 - TORONTO CORPORATE & GOALS Shares on Issue 1.355B Significant Shareholders Share Price ~Au$0.07* Glencore 15% Market Cap ~Au$95m* BlackRock 5% Cash

More information

Supply, Logistics, Marketing and Information Technology. Executive General Manager Commercial and West Africa

Supply, Logistics, Marketing and Information Technology. Executive General Manager Commercial and West Africa Supply, Logistics, Marketing and Information Technology Lawrie Conway Executive General Manager Commercial and West Africa Disclaimer Forward Looking Statement These materials include forward looking statements.

More information

For Immediate Release Date: February 3, 2016 #01-2016. Orvana Announces New Mineral Resources at El Valle Mine, Villar Zone and at La Brueva

For Immediate Release Date: February 3, 2016 #01-2016. Orvana Announces New Mineral Resources at El Valle Mine, Villar Zone and at La Brueva For Immediate Release TSX:ORV Date: February 3, 2016 #01-2016 Orvana Announces New Mineral Resources at El Valle Mine, Villar Zone and at La Brueva New Villar Zone discovered within 50m of existing reserves

More information

Denver Gold Show September 24, 2013

Denver Gold Show September 24, 2013 Denver Gold Show September 24, 2013 Cautionary Notes CAUTIONARY NOTE REGARDING NON IFRS MEASURE CASH COSTS PER OUNCE THIS PRESENTATION PRESENTS INFORMATION ABOUT OUR CASH COSTS OF PRODUCTION OF AN OUNCE

More information

Trevali reports record Santander Mine production for Q3-2015 and increases 2015 guidance

Trevali reports record Santander Mine production for Q3-2015 and increases 2015 guidance Trevali Mining Corporation 2300 1177 West Hastings Street Vancouver, British Columbia, CANADA V6E 2K3 Telephone: (604) 488-1661 Facsimile: (604) 408-7499 www.trevali.com NEWS RELEASE Trevali reports record

More information

BAUXITE RESOURCES LIMITED

BAUXITE RESOURCES LIMITED BAUXITE RESOURCES LIMITED POSITIVE EXPORT DSO BAUXITE SCOPING STUDY RESULTS RECEIVED FOR 100% BRL FORTUNA PROJECT Highlights Existing Mineral Resource and rail logistic chain can support a Direct Shipping

More information

Resources Rising Stars

Resources Rising Stars ASX Code: AYN Resources Rising Stars Andrew King, Managing Director September 2010 Pg 1 Disclaimer and Key Information Disclaimer This presentation has been prepared by the Directors of Alcyone Resources

More information

Positioned for Production: Exploring for Growth

Positioned for Production: Exploring for Growth ASX Code: AYN Positioned for Production: Exploring for Growth Andrew King, Managing Director May 2010 Pg 1 Disclaimer and Key Information Disclaimer This presentation has been prepared by the Directors

More information

Continental Gold Announces a Positive Preliminary Economic Assessment for the Buriticá Project

Continental Gold Announces a Positive Preliminary Economic Assessment for the Buriticá Project Continental Gold Announces a Positive Preliminary Economic Assessment for the Buriticá Project Toronto, Ontario, November 17, 2014 - Continental Gold Limited (TSX:CNL; OTCQX:CGOOF) ("Continental" or the

More information

(NYSE-MKT:XRA, TSX:XRC,

(NYSE-MKT:XRA, TSX:XRC, For Immediate Release: NR 15-08 Corporate Update Vancouver, B.C., December 17 th, 2015 Exeter Resource Corporation (NYSE-MKT:XRA, TSX:XRC, Frankfurt:EXB Exeter or the Company ) is pleased to provide the

More information

How To Know If Goldcorp Is A Successful Company

How To Know If Goldcorp Is A Successful Company Second Quarter Conference Call July 30 th, 2009 Management Participants Chuck Jeannes President and Chief Executive Officer Lindsay Hall Chief Financial Officer Steve Reid Chief Operating Officer Jeff

More information

WILLAMAX PROJECT. TSX-V: DVN Reach us at 604 818 1706. Developing B.C. mining assets to create profitable gold production.

WILLAMAX PROJECT. TSX-V: DVN Reach us at 604 818 1706. Developing B.C. mining assets to create profitable gold production. WILLAMAX PROJECT Developing B.C. mining assets to create profitable gold production May 2014 Reach us at 604 818 1706 Management Team Akash Patel, President and CEO Mr. Patel has received a bachelor in

More information

ANNUAL GENERAL MEETING. Investor Presentation 24 November 2015

ANNUAL GENERAL MEETING. Investor Presentation 24 November 2015 ANNUAL GENERAL MEETING Investor Presentation 24 November 2015 Corporate Structure ASX Code: OVR Shares on Issue 205.4 million Top 20 133.0 million (64.8%) Market Capitalisation $1.23 million (share price

More information

NEWS RELEASE ROXGOLD ANNOUNCES SECOND PROJECT FINANCE DRAWDOWN FOR THE YARAMOKO GOLD PROJECT & PROVIDES DEVELOPMENT UPDATE

NEWS RELEASE ROXGOLD ANNOUNCES SECOND PROJECT FINANCE DRAWDOWN FOR THE YARAMOKO GOLD PROJECT & PROVIDES DEVELOPMENT UPDATE NEWS RELEASE ROXGOLD ANNOUNCES SECOND PROJECT FINANCE DRAWDOWN FOR THE YARAMOKO GOLD PROJECT & PROVIDES DEVELOPMENT UPDATE Toronto, Ontario December 10, 2015 Roxgold Inc. (the "Company" or "Roxgold ")

More information

NEWS RELEASE New York - AG Toronto FR May 10, 2016 Frankfurt FMV Mexico - AG. First Majestic Reports First Quarter Financial Results

NEWS RELEASE New York - AG Toronto FR May 10, 2016 Frankfurt FMV Mexico - AG. First Majestic Reports First Quarter Financial Results FIRST MAJESTIC SILVER CORP. Suite 1805 925 West Georgia Street Vancouver, B.C., Canada V6C 3L2 Telephone: (604) 688-3033 Fax: (604) 639-8873 Toll Free: 1-866-529-2807 Web site: www.firstmajestic.com; E-mail:

More information

News release. No. 7/2015 KATANGA MINING ANNOUNCES 2015 SECOND QUARTER RESULTS

News release. No. 7/2015 KATANGA MINING ANNOUNCES 2015 SECOND QUARTER RESULTS No. 7/2015 News release KATANGA MINING ANNOUNCES 2015 SECOND QUARTER RESULTS BAAR, SWITZERLAND, August 12, 2015 Katanga Mining Limited (TSX: KAT) ("Katanga" or the "Company") today announces its financial

More information

Lalor Project Base Metal Zones and Gold Mineralization January 2009

Lalor Project Base Metal Zones and Gold Mineralization January 2009 Lalor Project Base Metal Zones and Gold Mineralization January 2009 1 Forward-Looking Statements All monetary amounts in Canadian dollars unless otherwise stated.. This presentation contains forward-looking

More information

CSE: LUX XETRA: NGO Frankfurt: NGO. Environmental Reclamation & Trading

CSE: LUX XETRA: NGO Frankfurt: NGO. Environmental Reclamation & Trading CSE: LUX XETRA: NGO Frankfurt: NGO Environmental Reclamation & Trading Cautionary Disclaimer Forward Looking Statements Certain statements contained herein regarding Newlox Gold Ventures Corp. (the Company

More information

GOLD RESOURCE CORPORATION REPORTS PRELIMINARY INDEPENDENT RESOURCE ESTIMATE; ANNOUNCES COMPANY CONFERENCE CALL

GOLD RESOURCE CORPORATION REPORTS PRELIMINARY INDEPENDENT RESOURCE ESTIMATE; ANNOUNCES COMPANY CONFERENCE CALL FOR IMMEDIATE RELEASE April 26, 2012 NEWS NYSE Amex: GORO GOLD RESOURCE CORPORATION REPORTS PRELIMINARY INDEPENDENT RESOURCE ESTIMATE; ANNOUNCES COMPANY CONFERENCE CALL COLORADO SPRINGS April 26, 2012

More information

NEWS RELEASE. Toronto and Swiss Stock Exchanges Symbol IMZ, Frankfurt Symbol MIW

NEWS RELEASE. Toronto and Swiss Stock Exchanges Symbol IMZ, Frankfurt Symbol MIW NEWS RELEASE February 11, 2008 Toronto and Swiss Stock Exchanges Symbol IMZ, Frankfurt Symbol MIW INTERNATIONAL MINERALS ANNOUNCES 6.2 MILLION OUNCES OF MEASURED AND INDICATED GOLD RESOURCES AND RESULTS

More information

SECOND QUARTER 2015 CONFERENCE CALL & WEBCAST

SECOND QUARTER 2015 CONFERENCE CALL & WEBCAST SECOND QUARTER 2015 CONFERENCE CALL & WEBCAST JULY 30, 2015 TSX: FM; LSE: FQM CAUTIONARY NOTE REGARDING FORWARD-LOOKING STATEMENT Certain statements and information herein, including all statements that

More information

SILVERCORP INTERCEPTS HIGH GRADE SILVER LEAD ZINC MINERALIZATION AT THE TLP MINE, YING MINING DISTRICT, HENAN PROVINCE, CHINA

SILVERCORP INTERCEPTS HIGH GRADE SILVER LEAD ZINC MINERALIZATION AT THE TLP MINE, YING MINING DISTRICT, HENAN PROVINCE, CHINA NEWS RELEASE Trading Symbol: TSX: SVM NYSE: SVM SILVERCORP INTERCEPTS HIGH GRADE SILVER LEAD ZINC MINERALIZATION AT THE TLP MINE, YING MINING DISTRICT, HENAN PROVINCE, CHINA VANCOUVER, BRITISH COLUMBIA,

More information

ALCYONE TO RAISE $5M TO UNDERPIN TRANSITION TO SILVER PRODUCTION AT TEXAS PROJECT

ALCYONE TO RAISE $5M TO UNDERPIN TRANSITION TO SILVER PRODUCTION AT TEXAS PROJECT ASX ANNOUNCEMENT & MEDIA RELEASE 25 November 2010 ALCYONE TO RAISE $5M TO UNDERPIN TRANSITION TO SILVER PRODUCTION AT TEXAS PROJECT ENTITLEMENT OFFER TO FUND FURTHER EXPLORATION, ACQUISITION OF LONG-LEAD

More information

Interim Financial Report for the half-year ended 31 December 2011

Interim Financial Report for the half-year ended 31 December 2011 Interim Financial Report for the half-year ended 31 December 2011 Note: The information contained herein should be read in conjunction with the most recent annual report. Aura Energy Limited Level 4, 66

More information

SILVERCORP INTERCEPTS 18.8 METRES TRUE WIDTH GRADING 368 G/T SILVER AND 1.78 PERCENT LEAD AT THE LM MINE WEST, YING MINING DISTRICT, CHINA

SILVERCORP INTERCEPTS 18.8 METRES TRUE WIDTH GRADING 368 G/T SILVER AND 1.78 PERCENT LEAD AT THE LM MINE WEST, YING MINING DISTRICT, CHINA NEWS RELEASE Trading Symbol: TSX: SVM NYSE: SVM SILVERCORP INTERCEPTS 18.8 METRES TRUE WIDTH GRADING 368 G/T SILVER AND 1.78 PERCENT LEAD AT THE LM MINE WEST, YING MINING DISTRICT, CHINA VANCOUVER, British

More information

MEDIA RELEASE OCEANAGOLD PROVIDES UPDATE ON DIDIPIO PROJECT AND CORPORATE RE-FINANCING INITIATIVES

MEDIA RELEASE OCEANAGOLD PROVIDES UPDATE ON DIDIPIO PROJECT AND CORPORATE RE-FINANCING INITIATIVES MEDIA RELEASE 16 July 2012 OCEANAGOLD PROVIDES UPDATE ON DIDIPIO PROJECT AND CORPORATE RE-FINANCING INITIATIVES (MELBOURNE) OceanaGold Corporation (ASX: OGC, TSX: OGC, NZX: OGC) (the Company ) is pleased

More information

EQUITY RAISING ANNOUNCEMENT

EQUITY RAISING ANNOUNCEMENT EQUITY RAISING ANNOUNCEMENT MARKET RELEASE 21 NOVEMBER 2012 KEY POINTS Entitlement Offer to Raise up to A$80 million o 3 for 10 accelerated non renounceable entitlement offer to raise up to A$80 million

More information

For personal use only

For personal use only Korab Resources Limited Gold Operations Update November 2012 Andrej K. Karpinski Executive Chairman Korab Projects BOBRIKOVO MELROSE 1 Korab Gold Projects Other Korab Projects Robust Undervalued Gold Portfolio

More information

For personal use only. MRV Metals Launch February 2016

For personal use only. MRV Metals Launch February 2016 MRV Metals Launch February 2016 Important Information This document has been prepared by Moreton Resources Limited ( Moreton or Company ) for the purpose of providing a company and technical overview to

More information

YAMANA GOLD ANNOUNCES SIGNIFICANT NEW DISCOVERIES AT CHAPADA AND EL PEÑÓN IMPROVE OPERATIONAL OUTLOOK

YAMANA GOLD ANNOUNCES SIGNIFICANT NEW DISCOVERIES AT CHAPADA AND EL PEÑÓN IMPROVE OPERATIONAL OUTLOOK YAMANA GOLD ANNOUNCES SIGNIFICANT NEW DISCOVERIES AT CHAPADA AND EL PEÑÓN IMPROVE OPERATIONAL OUTLOOK TORONTO, ONTARIO, December 15, 2014 YAMANA GOLD INC. (TSX:YRI; NYSE:AUY) ( Yamana or the Company )

More information

FIRST QUARTER CONFERENCE CALL MAY 4, 2010

FIRST QUARTER CONFERENCE CALL MAY 4, 2010 FIRST QUARTER CONFERENCE CALL MAY 4, 2010 1 Cautionary Statement CAUTIONARY NOTE REGARDING FORWARD-LOOKING STATEMENTS: This presentation contains or incorporates by reference forwardlooking statements

More information

ALCYONE REPORTS JORC SILVER RESOURCES

ALCYONE REPORTS JORC SILVER RESOURCES ASX ANNOUNCEMENT & MEDIA RELEASE 29 March 2010 ALCYONE REPORTS JORC SILVER RESOURCES +15Moz RESOURCE INVENTORY UNDERPINS PROGRAM TARGETING RESUMPTION OF SILVER PRODUCTION AT TEXAS PROJECT LATER THIS YEAR

More information

Mt Carrington Gold Silver Project Positive Scoping Study

Mt Carrington Gold Silver Project Positive Scoping Study ASX and Media Release: 31 July 2012 Mt Carrington Gold Silver Project Positive Scoping Study White Rock Minerals Ltd (ASX:WRM) has completed a robust scoping study on the Mt Carrington goldsilver project

More information

CNSX: TV www.trevali.com

CNSX: TV www.trevali.com CNSX: TV www.trevali.com March 2010 DISCLAIMER Certain statements contained in this document, including, without limitation, those concerning the economic outlook for the mining industry, expectations

More information

The significant milestones achieved by New Age Exploration Limited ( NAE or the Company ) during this period include:

The significant milestones achieved by New Age Exploration Limited ( NAE or the Company ) during this period include: Quarterly Report To 31 December 2015 New Age Exploration Limited ( NAE or "the Company") is pleased to provide shareholders the Company s Quarterly Report for the period ending 31 December 2015. Highlights

More information

Economic Highlights (In US$ unless otherwise indicated)

Economic Highlights (In US$ unless otherwise indicated) TSX.V TSX Venture Exchange Symbol: AME Suite 615-800 West Pender Street Vancouver, B.C. V6C 2V6 Canada Tel: 604.682.0301 Fax: 604.682.0307 email: info@amemining.com website: www.amemining.com Abacus announces

More information

For personal use only

For personal use only ASX Release 27 September 2012 OPTION TO ACQUIRE 560,000oz PEAK HILL GOLD PROJECT RESOURCE AND INVESTMENT NL (ASX: RNI) (RNI or the Company) has reached agreement with Montezuma Mining Company Limited for

More information

Highlights of selected high-grade mineralized zones exposed in drift tunnels include:

Highlights of selected high-grade mineralized zones exposed in drift tunnels include: NEWS RELEASE Trading Symbol: TSX: SVM SILVERCORP REPORTS NEWLY EXPOSED MINERALIZATION AT THE TLP MINE FROM ITS 2015 EXPLORATION TUNNELING PROGRAM - 1,414 METERS IN TOTAL LENGTH AND 0.70 METERS IN AVERAGE

More information

How To Mine And Treat Ore From Castle Hill Stage 1

How To Mine And Treat Ore From Castle Hill Stage 1 ` Dated: 5 th August 2014 NORTON TAKES UP OPTION TO MINE AND TREAT ORE FROM CASTLE HILL STAGE 1 ASX: PXG, PXGOA HIGHLIGHTS Development of Castle Hill Stage 1 with Norton Gold Fields potentially adds a

More information

MANAGEMENT DISCUSSION AND ANALYSIS FOR THE THREE MONTHS ENDED MAY 31, 2014

MANAGEMENT DISCUSSION AND ANALYSIS FOR THE THREE MONTHS ENDED MAY 31, 2014 MANAGEMENT DISCUSSION AND ANALYSIS FOR THE THREE MONTHS ENDED MAY 31, 2014 (2) INTRODUCTORY COMMENT Serengeti Resources Inc. is a junior mineral exploration company listed on the TSX Venture Exchange under

More information

Silver Mine Project Investment Opportunity in Scandinavia

Silver Mine Project Investment Opportunity in Scandinavia Silver Mine Project Investment Opportunity in Scandinavia KPMG Corporate Finance ( KPMG ) has been retained by Sotkamo Silver as exclusive Financial and Strategic adviser in connection with the Project

More information

Avion will host a conference call at 10:30 AM (EST) on Monday, April 2, 2011 to discuss the results. To participate in the call please dial:

Avion will host a conference call at 10:30 AM (EST) on Monday, April 2, 2011 to discuss the results. To participate in the call please dial: March 31, 2012 A v i o n G o l d A n n o u n c e s F o u r t h Q u a r t e r 2 0 1 1 E a r n i n g s o f $ 8. 1 M i l l i o n W i t h E a r n i n g s P e r S h a r e O f $ 0. 0 2 R e c o r d 2 0 1 1 E

More information

Endeavour Management Presentation

Endeavour Management Presentation Endeavour Management Presentation June 2014 GOLD PRODUCER WEST AFRICA CASH FLOW Disclaimer & Forward Looking Statements This presentation contains forward-looking statements including but not limited to,

More information

FOCUS MINERALS LIMITED

FOCUS MINERALS LIMITED FOCUS MINERALS LIMITED Aggressively Expanding into a Rising Gold Price Campbell Baird, Chief Executive Officer ASX: FML www.focusminerals.com.au 2 Disclaimer and Competent Person s Statement This presentation

More information

Update on Heap Leach potential of the Murchison gold project

Update on Heap Leach potential of the Murchison gold project 3 July 2012 Australian-based Kentor Gold Limited (ASX: KGL) is entering the ranks of operating gold mining companies in 2012. The Company is progressing a pipeline of advanced projects in Australia and

More information

FALCO COMPLETES HORNE 5 CONFIRMATION DRILLING PROGRAM AND ANNOUNCES FINAL RESULTS

FALCO COMPLETES HORNE 5 CONFIRMATION DRILLING PROGRAM AND ANNOUNCES FINAL RESULTS For Immediate Release TSX.V - FPC FALCO COMPLETES HORNE 5 CONFIRMATION DRILLING PROGRAM AND ANNOUNCES FINAL RESULTS (November 23, 2015) Montreal, Québec Falco Resources (FPC: TSX-V) ( Falco ) is pleased

More information

GOLD RESOURCE CORPORATION INTERCEPTS ADDITIONAL MULTIPLE HIGH-GRADE PARALLEL VEINS AT SWITCHBACK INCLUDING 6.32 METERS OF 5.

GOLD RESOURCE CORPORATION INTERCEPTS ADDITIONAL MULTIPLE HIGH-GRADE PARALLEL VEINS AT SWITCHBACK INCLUDING 6.32 METERS OF 5. FOR IMMEDIATE RELEASE JANUARY 26, 2016 NEWS NYSE MKT: GORO GOLD RESOURCE CORPORATION INTERCEPTS ADDITIONAL MULTIPLE HIGH-GRADE PARALLEL VEINS AT SWITCHBACK INCLUDING 6.32 METERS OF 5.87 G/T GOLD Colorado

More information

Ironbark Zinc Limited

Ironbark Zinc Limited Research Note Ironbark Zinc Limited Suite 5, Level 8, 99 York Street, Sydney NSW 2000 29 th August 2013 Ironbark Zinc to up the ante at Citronen Zinc Project with higher zinc prices Recommendation: Speculative

More information

Q3 2009 Conference Call - Q3 financial results - Dividend declaration - Near term growth outlook - New Royalty Acquisitions

Q3 2009 Conference Call - Q3 financial results - Dividend declaration - Near term growth outlook - New Royalty Acquisitions Q3 2009 Conference Call - Q3 financial results - Dividend declaration - Near term growth outlook - New Royalty Acquisitions November 10, 2009 David Harquail - CEO Alex Morrison - CFO Cautionary Statement

More information

LYDIAN ANNOUNCES $325 MILLION CONSTRUCTION FINANCING FOR AMULSAR GOLD PROJECT

LYDIAN ANNOUNCES $325 MILLION CONSTRUCTION FINANCING FOR AMULSAR GOLD PROJECT LYDIAN ANNOUNCES $325 MILLION CONSTRUCTION FINANCING FOR AMULSAR GOLD PROJECT Conference Call December 1, 2015 Lydianinternational.co.uk TSX:LYD Cautionary Statements Forward Looking Statements & Other

More information

Trip to Pulacayo. Pulacayo - Paca

Trip to Pulacayo. Pulacayo - Paca Disclaimer This Presentation contains forward-looking information as defined under applicable securities law in Canada. Forward-looking information can be identified by the use of words such as "anticipated",

More information

Ferrex plc ( Ferrex or the Company ) Acquisition of Gold Mining Company in Australia and Strategic Review

Ferrex plc ( Ferrex or the Company ) Acquisition of Gold Mining Company in Australia and Strategic Review Ferrex plc / Index: AIM / Epic: FRX / Sector: Mining 17 November 2015 Ferrex plc ( Ferrex or the Company ) Acquisition of Gold Mining Company in Australia and Strategic Review Ferrex plc, the AIM quoted

More information

Developing the Tanlouka Gold Project. AGM Presentation 18th November 2015

Developing the Tanlouka Gold Project. AGM Presentation 18th November 2015 Developing the Tanlouka Gold Project AGM Presentation 18th November 2015 1 Executive Summary West African Resources Ltd is an ASX and TSXV listed gold development company focussed on Burkina Faso Largest

More information

Building our Future. Investor Presentation. November 2015. Efemçukuru Gold Mine, Turkey

Building our Future. Investor Presentation. November 2015. Efemçukuru Gold Mine, Turkey Building our Future Investor Presentation November 2015 Efemçukuru Gold Mine, Turkey Forward Looking Statement Certain of the statements made in this Presentation may contain forward-looking statements

More information

Sabina Gold & Silver Corp.

Sabina Gold & Silver Corp. Sabina Gold & Silver Corp. Creating precious metals opportunities in the Canadian North November 2011 Hackett River Camp, looking to west 1 Forward Looking Statements This presentation includes certain

More information

AGNICO-EAGLE MINES LIMITED

AGNICO-EAGLE MINES LIMITED AGNICO-EAGLE MINES LIMITED Corporate Update January 2008 Agnico-Eagle Mines Limited 1 Forward Looking Statements The information in this document has been prepared as at January 15, 2007. Certain statements

More information

THIRD QUARTER EARNINGS NOVEMBER 12, 2015

THIRD QUARTER EARNINGS NOVEMBER 12, 2015 THIRD QUARTER EARNINGS NOVEMBER 12, 2015 CAUTIONARY NOTES Qualified Person Brian Morris, is the non-independent Klondex Mines "qualified person" as defined by National Instrument 43-101 Standards of Disclosure

More information

Management s Discussion and Analysis For the three and nine months ended September 30, 2015

Management s Discussion and Analysis For the three and nine months ended September 30, 2015 Management s Discussion and Analysis For the three and nine months ended September 30, 2015 This management s discussion and analysis ( MD&A ) has been prepared as of October 28, 2015 and should be read

More information

September 2015 Quarterly Activities Report

September 2015 Quarterly Activities Report ASX RELEASE 31 OCT 2015 September 2015 Quarterly Activities Report Expansion of Premier JV Gold Mine to 40,000ozpa production rate on track and future production growth plans advanced Highlights Production

More information

Abacus Mining & Exploration Corporation (an exploration stage company) Condensed Interim Financial Statements March 31, 2013.

Abacus Mining & Exploration Corporation (an exploration stage company) Condensed Interim Financial Statements March 31, 2013. Abacus Mining & Exploration Corporation (an exploration stage company) Condensed Interim Financial Statements 2013 (Unaudited) (Expressed in Canadian dollars) Index Page Notice to reader 2 Financial statements:

More information

De Grey Mining Ltd. Wingina Deeps Drilling Commenced (Turner River Project) Highlights. Turner River Unlocking Shareholder Value

De Grey Mining Ltd. Wingina Deeps Drilling Commenced (Turner River Project) Highlights. Turner River Unlocking Shareholder Value De Grey Mining Ltd ASX RELEASE 5 July 2016 ASX Code DEG ABN 65 094 206 292 Wingina Deeps Drilling Commenced (Turner River Project) Highlights Diamond drilling programme of approximately 1,500m has COMPANY

More information

Mexico s next silver mine. Corporate Presentation October 2015

Mexico s next silver mine. Corporate Presentation October 2015 Mexico s next silver mine. Corporate Presentation October 2015 San José: an Overview Large mineral resource estimate (Silver, Lead, Zinc) Potential to increase our resource base 10 year mine life based

More information

SILVERCORP REPORTS RESULTS FROM ITS 2012 EXPLORATION PROGRAM AT THE SGX MINE, YING MINING DISTRICT, CHINA

SILVERCORP REPORTS RESULTS FROM ITS 2012 EXPLORATION PROGRAM AT THE SGX MINE, YING MINING DISTRICT, CHINA NEWS RELEASE Trading Symbol: TSX: SVM NYSE: SVM SILVERCORP REPORTS RESULTS FROM ITS 2012 EXPLORATION PROGRAM AT THE SGX MINE, YING MINING DISTRICT, CHINA VANCOUVER, British Columbia June 4, 2013 Silvercorp

More information

First Quarter 2015 Investor Conference Call May 7, 2015

First Quarter 2015 Investor Conference Call May 7, 2015 NYSE:TC NYSE:TC TSX:TCM TSX:TCM First Quarter 2015 Investor Conference Call May 7, 2015 Webcast Information Webcast: This Webcast can be accessed on the Thompson Creek Metals Company website under the

More information

Cannon Big Pit Given the Green Light

Cannon Big Pit Given the Green Light ASX Release Tuesday 3 November 2015 Cannon Big Pit Given the Green Light Southern Gold maintains 50% profit share on Cannon Metals X estimate open pit recovered gold +270% to ~50koz Significant cash flow

More information

Management Discussion and Analysis for the quarter ended March 31, 2015

Management Discussion and Analysis for the quarter ended March 31, 2015 Management Discussion and Analysis for the quarter ended March 31, 2015 This Management Discussion and Analysis ( MD&A ) should be read in conjunction with Aurcana Corporation s (the Company or Aurcana

More information

FIJI GOLD LION ONE METALS

FIJI GOLD LION ONE METALS FIJI GOLD LION ONE METALS Tuvatu Gold Project January 2016 Presentation Disclaimer Forward Looking Statements and Qualified Person DISCLAIMER The information provided in this presentation is not intended

More information

Barkerville Gold Mines Investor presentation q1 2016. The last great Canadian gold mining camp controlled by a junior mining company.

Barkerville Gold Mines Investor presentation q1 2016. The last great Canadian gold mining camp controlled by a junior mining company. Barkerville Gold Mines Investor presentation q1 2016 The last great Canadian gold mining camp controlled by a junior mining company. 1 Forward Looking statement This presentation and the material contained

More information

Carpentaria Exploration Ltd Investment Update

Carpentaria Exploration Ltd Investment Update Carpentaria Exploration Ltd Investment Update June 19 th 2013 We find it. We prove it. We make it possible. Disclaimer This presentation has been prepared by the management of Carpentaria Exploration Limited

More information

Exploration and Development Activity

Exploration and Development Activity For the period ending 30 June 2008 Exploration and Development Activity Over the last year, exploration and development work at the Company s Nullagine Gold Project in Western Australia s eastern Pilbara

More information

Wonawinta Silver Project to be acquired; Mount Boppy development cost and risk cut back

Wonawinta Silver Project to be acquired; Mount Boppy development cost and risk cut back Southern Cross Goldfields Ltd ASX Announcement 5 September 2014 Wonawinta Silver Project to be acquired; Mount Boppy development cost and risk cut back Wonawinta Silver Project (60 M oz) to be acquired

More information

TD Securities Mining Conference JANUARY 26-27, 2016. Developing the third-largest copper mine

TD Securities Mining Conference JANUARY 26-27, 2016. Developing the third-largest copper mine TD Securities Mining Conference JANUARY 26-27, 2016 Developing the third-largest copper mine Forward-looking statements This presentation includes certain forward-looking information within the meaning

More information

January 2014. Developing Copper, Zinc and Gold Deposits on the Asmara Project, Eritrea. November 2010

January 2014. Developing Copper, Zinc and Gold Deposits on the Asmara Project, Eritrea. November 2010 November 2010 January 2014 Underground workings at Debarwa copper-gold deposit Developing Copper, Zinc and Gold Deposits on the Asmara Project, Eritrea Eritrea and the Asmara Project Sudan Zara Bisha Mine

More information

TURKEY CREEK PIT OPTIMISATION STUDY ADDS 2 YEARS MINE LIFE TO THE LITTLE EVA PROJECT AT CLONCURRY

TURKEY CREEK PIT OPTIMISATION STUDY ADDS 2 YEARS MINE LIFE TO THE LITTLE EVA PROJECT AT CLONCURRY 10 August 2015 ASX: AOH, FSE: A2O TURKEY CREEK PIT OPTIMISATION STUDY ADDS 2 YEARS MINE LIFE TO THE LITTLE EVA PROJECT AT CLONCURRY Estimated oxide and sulphide resources within the optimum pit is 17.3

More information

KATANGA MINING ANNOUNCES 2013 YEAR END RESULTS AND COMMITMENT OF GLENCORE TO EXTEND AND INCREASE LOAN FACILITIES

KATANGA MINING ANNOUNCES 2013 YEAR END RESULTS AND COMMITMENT OF GLENCORE TO EXTEND AND INCREASE LOAN FACILITIES No. 3/2014 News release KATANGA MINING ANNOUNCES 2013 YEAR END RESULTS AND COMMITMENT OF GLENCORE TO EXTEND AND INCREASE LOAN FACILITIES ZUG, SWITZERLAND, March 3, 2014 Katanga Mining Limited (TSX: KAT)

More information

INVESTOR PRESENTATION JULY 2013

INVESTOR PRESENTATION JULY 2013 INVESTOR PRESENTATION JULY 2013 DISCLAIMER This presentation contains only a brief overview of Millennium Minerals Limited. The contents of this presentation, including matters relating to the geology

More information

2016 TD Securities Mining Conference January 2016 TSX: LUN OMX: LUMI

2016 TD Securities Mining Conference January 2016 TSX: LUN OMX: LUMI 2016 TD Securities Mining Conference January 2016 TSX: LUN OMX: LUMI Cautionary Statements Caution Regarding Forward-Looking Information This presentation contains forward-looking information, including,

More information

Walford Creek: New Generation Base Development

Walford Creek: New Generation Base Development Walford Creek: New Generation Base Development May, 2015 Sydney Resources Round-up ASX Code: AQR Disclaimer Important Information This document has been prepared by Aeon Metals Limited (Aeon) for the purpose

More information

Richmont Increases Mineral Reserves by 187% and Island Gold Mine Increases Mineral Reserves by 206%, With a 29% Increase in Reserve Grade

Richmont Increases Mineral Reserves by 187% and Island Gold Mine Increases Mineral Reserves by 206%, With a 29% Increase in Reserve Grade PRESS RELEASE TSX NYSE MKT: RIC Richmont Increases Mineral Reserves by 187% and Island Gold Mine Increases Mineral Reserves by 206%, With a 29% Increase in Reserve Grade TORONTO, Ontario, Canada, February

More information

On February 3, 2016 the Company announced the appointment of Ms. Joyce Ngo as Interim Chief Financial Officer.

On February 3, 2016 the Company announced the appointment of Ms. Joyce Ngo as Interim Chief Financial Officer. VANCOUVER, BRITISH COLUMBIA--(Marketwired - May 6, 2016) - NGEx Resources Inc. (TSX:NGQ)(OMX:NGQ) ("NGEx" or the "Company") is pleased to announce that it has filed its unaudited Consolidated Financial

More information

Native Title and Land Access Agreement (PSA) For Bauxite Hills Project

Native Title and Land Access Agreement (PSA) For Bauxite Hills Project METRO MINING LIMITE D SUPPLEMENTARY BIDDER S STATEMENT OFFER BY METRO MINING LIMITED to acquire ALL of your shares in GULF ALUMINA LIMITED THIS DOCUMENT IS IMPORTANT AND REQUIRES YOUR IMMEDIATE ATTENTION

More information

KOPY GOLDFIELDS AB. A thorny path of a public Junior Gold Exploration Company in Russia Russian & CIS Metals Summit 2014, Moscow, February, 2014

KOPY GOLDFIELDS AB. A thorny path of a public Junior Gold Exploration Company in Russia Russian & CIS Metals Summit 2014, Moscow, February, 2014 KOPY GOLDFIELDS AB A thorny path of a public Junior Gold Exploration Company in Russia Russian & CIS Metals Summit 2014, Moscow, February, 2014 Disclaimer - Forward looking statement Forward Looking Information

More information

PRESS RELEASE SEMAFO FOR IMMEDIATE RELEASE. SEMAFO Reports 2011 Cash Flow from Operations of $172 Million

PRESS RELEASE SEMAFO FOR IMMEDIATE RELEASE. SEMAFO Reports 2011 Cash Flow from Operations of $172 Million PRESS RELEASE SEMAFO FOR IMMEDIATE RELEASE SEMAFO Reports 2011 Cash Flow from Operations of 172 Million Fourth Quarter Total Cash Margin of 1,029 per Ounce Montreal, Quebec, March 14, 2012, 09:30 EDT SEMAFO

More information

FOR IMMEDIATE RELEASE

FOR IMMEDIATE RELEASE FOR IMMEDIATE RELEASE March 19, 2014 NEWS NYSE MKT: GORO GOLD RESOURCE CORPORATION REPORTS $16.2M NET INCOME AND RECORD ANNUAL METAL PRODUCTION FOR 2014; PROVIDES 2015 PRODUCTION OUTLOOK COLORADO SPRINGS

More information

Management Plan. Contractor Management

Management Plan. Contractor Management Management Plan Contractor Management Doc ID No. Version No. Owner Next Review Date Management Plan Contractor Management Risk Statement: High This document will be reviewed on a one yearly basis, unless

More information

CANADA S INTERMEDIATE GOLD PRODUCER

CANADA S INTERMEDIATE GOLD PRODUCER CANADA S INTERMEDIATE GOLD PRODUCER Third Quarter 2015 Results Conference 1 Call & Webcast October 29, 2015 Forward Looking Information This presentation contains certain forward-looking information and

More information

Yellowhead Mining Inc. (TSX-V: YMI) - Positive Feasibility Study Demonstrates Strong Economics

Yellowhead Mining Inc. (TSX-V: YMI) - Positive Feasibility Study Demonstrates Strong Economics Siddharth Rajeev, B.Tech, MBA, CFA Analyst Chris Porter, BSc Research Associate-Mining Investment Analysis for Intelligent Investors April 18, 2012 Yellowhead Mining Inc. (TSX-V: YMI) - Positive Feasibility

More information