AfDB Field s office in Abuja Nigeria

Size: px
Start display at page:

Download "AfDB Field s office in Abuja Nigeria"

Transcription

1 AfDB Field s office in Abuja Nigeria Lot 3: Vol 5 Commissioning Plan Prepared by: Apave Liban s.a.r.l. For : Aim Consultants Ltd.

2 Project ref : Report n : Date : 16/04/2013 Page 2/12 Table of contents Introduction 3 I Overview of the commissioning process 4 II Systems and assemblies included in the CA s scope of 4 work III Commissioning team and its responsibilities 4 IV Description of management, communication and 7 reporting of commissioning process V Commissioning Plan 8 VI List of expected work products 9 VII Testing equipment 10 VIII Commissioning process milestones and schedules 10 IX Commissioning check lists and testing procedures 11 Check lists annexes: Annex 1: T&C for Electrical Installation Annex 2: T&C for Generator Installation Annex 3: T&C for Split Unit System Annex 4: T&C for AHUs and VAVs Annex 5: T&C for Chillers and Accessories Annex 6: T&C for Cooling Pumps Annex 7: T&C for Domestic Water System Annex 8: T&C for FCU Annex 9: T&C for Fans Annex 10: T&C for BMS Annex 11: T&C for Metering Systems Annex 12: T&C for VRVs Annex 13: T&C for PV System Annex 14: T&C for Solar Heating System

3 Project ref : Report n : Date : 16/04/2013 Page 3/12 Introduction The commissioning plan is the reference document that identifies the strategies, aspects and responsibilities within the commissioning process for each phase of the project for all project team members. This document outlines the overall process, schedule, organization, responsibilities and documentation requirements of the commissioning process for all commissioning team members. The commissioning plan is developed at the start of the commissioning process, and is updated during the course of the project to reflect any changes in planning, schedule or other aspect. The required commissioning plan components as per LEED reference guide for green building design and construction are as follows: I II III IV V VI VII Required commissioning plan components: Brief overview of the commissioning process. List of all systems and assemblies included in commissioning authority s scope of work. Identification of commissioning team and its responsibilities. Description of management, communication and reporting of commissioning process. Overview of commissioning process activities for pre design, design, construction, occupancy and post occupancy phases. List of expected work products. List of commissioning process milestones.

4 Project ref : Report n : Date : 16/04/2013 Page 4/12 I Overview of the commissioning process Commissioning intent is to verify that the project s energy related systems are installed, calibrated and perform according to the owner s project requirements, basis of design and construction documents and to provide the owner with a high level of assurance that the mechanical and electrical systems have been installed in the prescribed manner, and operate within the capabilities of the documented design and specified equipment capacities. In order to comply with the LEED requirements, the commissioning plan will be divided into two levels called Fundamental Commissioning of building energy systems which is prerequisite for the system and Enhanced Commissioning with its optional credits. The prerequisite intent is to verify that the project s energy related systems are installed, calibrated and perform according to the owner s project requirements, basis of design and construction documents. The Commissioning authority will verify the installation and performance of the systems to be commissioned, and will complete a summary commissioning report as part of the Fundamental commissioning process. The commissioning authority will document all commissioning review process, submittals, system manual, verify O&M training and review building operation after 10 month of final acceptance. II Systems and assemblies included in commissioning authority s scope of work The scope of services for the commissioning authority is based on the owner s project requirements. Thus, as requested by the owner, the mission will cover the following base building systems: Ventilation systems(supply air, Return air, Exhaust air) HVAC and associated control systems Chilled water VRV system Domestic water heating Water distribution systems Domestic water treatment Electrical power generation and distribution systems Building Management System Sub meters and central electronic monitoring system Lighting and lighting controls Renewable energy systems III Commissioning team and its responsibilities Commissioning team as defined in ASHRAE s commissioning guide; it s Those people responsible for working together in carrying out the commissioning process.

5 Project ref : Report n : Date : 16/04/2013 Page 5/12 Commissioning, at every stage of a project, is a collaborative effort between all parties to the construction project; it s a team effort and requires communication, coordination and cooperation among all parties involved with the project. The commissioning authority is the leader of the team. By clearly establishing the Commissioning Team and individual responsibilities, the process execution becomes easier, more effective and more accountable. Below are the commissioning team members, along with their individual responsibilities in the commissioning process during project phases. A. Owner (The African development Bank) 1 Include a statement regarding commissioning responsibilities in request for design services. 2 Develop and commit to the Ownerʹs Program for the facility and its use. 3 Assign operations and maintenance personnel and schedule them to participate in the various meetings, training sessions, and observations/inspections. 4 Review and approve any changes made to design intent. 5 Review and approve the construction documents. 6 Provide qualified personnel for videotaping and editing of training sessions. 7 Videotape construction progress. 8 Review and comment on the commissioning authorityʹs verification report. 9 Review and accept the commissioning authorityʹs commissioning report. B. Commissioning Authority (Apave) 1 Organize and lead the commissioning team. 2 Prepare a program phase Commissioning Plan that describes in general the extent of the commissioning process to accomplish the Ownerʹs Program and the initial design intent. 3 Develop the design phase Commissioning Plan, which details the extent and activities of the commissioning process including commissioning team organization, schedule, training, and documentation requirements and all related testing, verification, and quality control procedures. 4 Execute the commissioning process through attending meetings, tests, demonstrations, training events, and performance verifications. 5 Review the plans and specifications with respect to their completeness in all areas relating to commissioned systems. This includes ensuring that the design phase Commissioning Plan has been followed and that there are adequate devices included in the design to ensure the ability to properly test, verify, and adjust the systems. Any items required but not shown shall be brought to the attention of the Owner. 6 Receive and review the operations and maintenance (O&M) manuals as submitted by the contractor. Ensure that they follow the specified outline and format. Insert systems description as provided by the design professional in the Systems Manual. 7 Witness equipment, subsystem, and system start up and testing. Ensure the results are documented, including a summary of deficiencies, and incorporated in the O&M manuals. 8 Supervise the commissioning team members in the functional performance tests. The test data will be part of the commissioning report. 9 Ensure that the O&M manuals and all other as built records have been updated to include all

6 Project ref : Report n : Date : 16/04/2013 Page 6/12 modifications made during the construction phase. 10 Prepare the final commissioning report and the systems manual. 11 Review operation after 10 month of completion. C. Design / Technical Control Consultants 1 Provide system design parameters and revisions to the initial design intent document as necessary, obtaining approval of the owner. 2 Prepare contract documents, including the commissioning specification and description of the commissioned systems. 3 Attend construction phase coordination meeting. 4 Specify and verify adequate maintenance accessibility for each piece of equipment in shop drawings and actual installation. Periodic inspections are part of the design professionalʹs construction administration duties. 5 Develop an overview of system design and operation concepts for the Systems Manual. 6 Review and accept as built records as required by contract documents and turn them over to the commissioning authority. D. Contractor/Sub contractor/supplier 1 Include costs for commissioning requirements in the contract price. 2 Include requirements for submittal data, O&M data and O&M training in each purchase order or subcontract written. 3 Ensure cooperation and participation of specialty subcontractors and controls contractors. 4 Ensure coordination, installation, and operation of interfaces between commissioning team. 5 Ensure participation of major equipment manufacturers in appropriate training and testing activities. 6 Attend construction phase coordination meeting scheduled by the commissioning authority. 7 Prepare necessary preliminary schedule for commissioned system orientation and inspections, O&M manual submission, training sessions, equipment and systems testing, for use by the commissioning authority. Update schedule as appropriate throughout the construction period. 8 Attend initial training sessions, and conduct system orientation and inspection at the equipment placement completion stage. Update drawings to record condition to date, and review with the commissioning authority. 9 Gather O&M data on all equipment and assemble in binders as required by the commissioning specification. Submit to commissioning authority prior to the completion of construction. 10 Notify the commissioning authority when equipment and system start up and testing can be witnessed. 11 Schedule equipment suppliers and contractors to participate in the O&M training sessions. 12 Conduct a system orientation and inspection with hands on training. Update drawings to record condition to date, and review with the commissioning authority prior to the orientation. 13 Provide written notification to the construction manager and commissioning authority that

7 Project ref : Report n : Date : 16/04/2013 Page 7/12 the following work has been completed in accordance with the contract documents and that the equipment, systems, and subsystems are functioning as required. 14 Demonstrate the operation of each piece of equipment to the commissioning authority. Schedule subcontractors as may apply to demonstrate the operation of the equipment and systems. 15 Provide services of an engineer to participate in verification tests. 16 Turn over a set of as built records to the commissioning authority. (Hard and soft copies) 17 Provide filled checklist data sheets to document verification tests for the commissioning authority. 18 Submit detailed verification test procedures and data sheets for review by the design team. 19 Submit detailed list of test instrumentation with appropriate calibration records to be utilized for verification. Record data as necessary. 20 Submit verification test data to the design team and the commissioning authority for review. 21 Conduct tests and verifications including opposite season tests, as required. 22 Retest if performance deficiencies are found and corrected and additional testing is requested. 23 Repeat all required testing and verification procedures after 10 months of client s occupancy. IV Description of management, communication and reporting of commissioning process Whole Building Commissioning is a process that relies upon high levels of communications and collaboration between all parties to the construction process. By its nature, the levels of communication and cooperation between the Commissioning Authority and all other parties to the construction process (Design team, Engineers, Subcontractors, Vendors, third party testing agencies, etc.) is essential to the success of the Commissioning effort. In the absence of these relationships, cooperation and support created by this communication, the Commissioning Process will likely fail to achieve its ends. With this fundamental conflict in mind, this section has been developed to recognize that, in the execution of the Commissioning Process, the Commissioning Authority must develop effective methods to communicate with every member of the construction team involved in delivering commissioned systems while simultaneously respecting the exclusive contract authority of the Contracting Officer and his/her Designated Representative. The organizational process chart below shows lines of contractual authority in this project, yet communications are encouraged between all commissioning team members, within the limit of their contracts.

8 Project ref : Report n : Date : 16/04/2013 Page 8/12 Client AfDB Technical Control Consultants AIM Project Manager Design Consultants LEED Consultant SEEDS Main contractor To be defined Commissioning authority Apave Subcontractors / Suppliers To be defined V Commissioning Plan The commissioning plan is implemented during the construction phase. Direct interaction between the construction team and the commissioning authority and communication with the design team represents the cornerstone of successful commissioning. The commissioning authority provides leadership by communicating goals for the commissioning process, including identification of roles and responsibilities of team members, and clearly defining and documenting pass/fail criteria. Each commissioning team member shares a responsibility to support the commissioning process and achieve a quality installation. The sequence and timing of commissioning activities must be incorporated into the overall project schedule. The commissioning authority identifies the required commissioning activities. Coordination requires input from the owner, designer, and contractors. Cooperation among the parties facilitates integration of commissioning into the total construction program. At this stage, the commissioning authority obtains and reviews submittal data, and consults with the designers and contractors regarding conformance with the design intent. The designer provides final approval of all submittals. The commissioning authority should work with the general contractor to schedule commissioning meetings in conjunction with regular progress meetings, because many participants will attend both. The commissioning authority keeps meeting minutes. All commissioning team members are responsible for attending commissioning meetings and for completing assigned action items by the agreed dates. Cooperation by all parties contributes to successful commissioning. The contractor is responsible for preparing the O&M documentation and training program in accordance with specification requirements.

9 Project ref : Report n : Date : 16/04/2013 Page 9/12 The O&M training program should include: Design intent. System limitations. Start up and shut down procedures. Modes of control and operation sequences. Detailed review of the information and organization of the O&M manual. Complete listing of contractors and manufacturer contact information. Complete listing of spare parts. Detailed instructions on the control system. Routine preventative maintenance procedures as specified by the designer or recommended by the manufacturer. Provisions for safety shutdowns, emergency conditions, and interfaces with building management systems (BMS) and life safety systems (such as fire protection). Video tapes of the training sessions to allow future use. At the last phase of this stage, the commissioning authority will be responsible of preparing a summary commissioning report. This report uses the final commissioning plan as its template. The report includes all system verification and start up checklists, and all functional performance test checklists, completed with all test observations, problems encountered, corrective actions taken, and re test results dated and signed by those carrying out and witnessing the tests. Where the checklists make reference to other test reports, copies of those reports must be appended. The final commissioning report should contain an executive summary addressing design intent conformance for all commissioned equipment and systems. The report should include references to all relevant commissioned system documentation, and should be organized and tabulated to facilitate access to specific information. The commissioning authority will make a site review within 10 months after substantial completion, along with the contractor and all concerned subcontractors. Functional tests and verification will be repeated in order to get the required information. Commissioning authority will then have to make another report concerning this site review. VI List of expected work products Commissioning intent, as mentioned earlier in this report is to verify that the project s energy related systems are installed, calibrated and perform according to the owner s project requirements, basis of design and construction documents and to provide the owner with a high level of assurance that the mechanical and electrical systems have been installed in the prescribed manner, and operate within the capabilities of the documented design and specified equipment capacities. Therefore our mission will be to provide the owner, in our final commissioning report and our site review within 10 months of occupancy, with an objective point of view of the actual state of MEP equipment.

10 Project ref : Report n : Date : 16/04/2013 Page 10/12 VII Testing equipment It is be noted that all test equipment required for performing the specified tests shall be provided by contractors. Any proprietary vendor specific test equipment shall be provided by that vendor or manufacturer. Any portable or hand held setup / calibration devices required to initialize any control system shall be made available by the control vendor (at no cost) to the commissioning authority. The instrumentation shall meet the following requirements: Be of sufficient quality and accuracy to measure system performance within the tolerances required. Be calibrated with calibration tags permanently affixed to the instrument. All items needed to undertake testing and verification as described in the attached annexes should be provided by the contractor. VIII Commissioning process milestones, schedules Commissioning milestones and schedules cannot be determined exactly for the time being, but will be integrated to this report during future revisions once we receive the detailed construction planning. The startup and testing of systems may proceed prior to final completion of systems. However, the commissioning authority shall not perform checkout services that are the primary responsibility of the contractor vendor in advance of their testing and checkout, whom in return are responsible to inform the commissioning team once their systems are ready to be verified and tested. Problems observed will be addressed immediately, responsible parties will be notified. Contractor schedules and scheduling is the responsibility of the construction manager. The commissioning authority shall provide commissioning scheduling information to the construction manager for review and planning activities. The commissioning process does not relieve any contractors from their obligations to complete all portions of work in a satisfactory manner. Throughout project construction, the following table including all systems to be commissioned will be updated.

11 Project ref : Report n : Date : 16/04/2013 Page 11/12 System: Supply air Return air Exhaust air Chilled water Hot water HVAC and control Systems to be commissioned Equipment startup Pre functional checklists Functional testing Sample size Target date: Y/N Y/N Y/N % N/A Y/N Y/N Y/N % N/A Y/N Y/N Y/N % N/A Y/N Y/N Y/N % N/A Y/N Y/N Y/N % N/A Y/N Y/N Y/N % N/A VRV Y/N Y/N Y/N % N/A Domestic water heating &distribution Domestic water treatment Y/N Y/N Y/N % N/A Y/N Y/N Y/N % N/A Electric power generation and distribution Y/N Y/N Y/N % N/A BMS Y/N Y/N Y/N % N/A Sub metering & electronic monitoring Y/N Y/N Y/N % N/A Lighting and related controls Y/N Y/N Y/N % N/A IX Commissioning check lists and testing procedures Commissioning check lists and systems testing and verification procedures shall be filled by the resident consultant engineer and the concerned subcontractor. The commissioning authority will direct and witness some verification operating tests and checks. The testing contractor s technician will inspect and verify the position of each device and interlock that is identified on the checklist. Each item shall be signed off as acceptable or failed. This test will be repeated for each operating cycle that applies to the system being tested. Operating checks shall include all safety cutouts, alarms, and interlocks with smoke control and life safety systems during all modes of operation of the system. If, during a test, an operating deficiency is observed, appropriate comments shall be added to the checklist data sheet. The Interface of the monitoring and control system shall be verified. The proper response of monitoring and control system controllers and sensors shall be verified.

12 Project ref : Report n : Date : 16/04/2013 Page 12/12 Final verification: APAVE will direct and witness the field verification of the final testing report. APAVE will select at random percentage of the report data for verification. The contractor shall be given sufficient advance notice of the date of field verification. However, he shall not be informed in advance of the data points to be verified. The test engineer must use the same instruments (by model and serial number) that were used when the original data were determined. Failure of an item is defined as the following : For all readings other than sound, a deviation of more than 10%. For sound pressure readings, a deviation of 3 decibels. A failure of more than 10% of the selected items shall result in the failure of acceptance of the final testing report. All these deviations are to be followed, unless otherwise referred to or specified. Failure of the final testing and balancing report shall require contractor to complete the following work. Any system failing the verification procedure must be rechecked and corrected. New total system testing and verification reports must be provided. Field verification of the new testing and balancing report must be performed. If deficiencies are identified during verification, the construction manager will be notified and action taken to remedy the deficiency. Once verification is completed, the commissioning authority will provide a verification report to the owner. Check lists and testing procedures are found in the annexes of this report.

13 Testing & Commissioning Procedure Electrical Installation Commissioning Plan April / 32

14 Table of Contents 1 Introduction: Objective of the T & C: Scope of the T & C Works: Preliminary Steps for Testing and Commissioning: Tests & Inspections during Construction: Functional Performance Tests: Documentation and Deliverables: Testing and Commissioning (T & C) Procedure: Tests and Inspections during Construction Inspection and Test for Low Voltage Installations Inspection before Test Sequence of Tests Conductor Continuity Earth Electrode Resistance Earth Fault Loop Resistance Functional Test of System/Equipment Circuitry Check Lighting Installation Digital Multifunction Power Meter Equipment and Appliances Assessment of Any Characteristics of Equipment Likely to have Harmful Effects... 9 Appendix A Part1. Items Inspected and Tested Statutory Inspection and Test for Low Voltage (L.V.) Installation Functional Test of System /Equipment Part 2: Test Record attached to the Test Certificate Test for Low Voltage (L.V) Installation Functional Test of System /Equipment Testing Equipment Commissioning Plan April / 32

15 1 Introduction: The procedures stated in this document cover the activities in preliminary tests and inspections, functional performance tests and the commissioning of newly completed electrical installations. The Contractor shall carry out the T & C works for LEED as detailed in this document. 2 Objective of the T & C: The objectives of the T & C works are: To verify proper functioning of the equipment/system after installation. To verify that the performance of the installed equipment/systems meet with the specified design intent through a series of tests and adjustments. To capture and record performance data of the whole installation as the baseline for future operation and maintenance. 3 Scope of the T & C Works: 3.1 Preliminary Steps for Testing and Commissioning: Before carrying out T&C, the Contractor shall take the following steps: a. Review approved shop drawings and equipment schedules; b. Check manufacturer s operating instructions and statutory requirements; c. Physically inspect the installation and equipment to determine variations from designs and/or specifications. d. Check individual components, e.g. key switches, control equipment, circuit breaker status, etc. for proper position and settings for completeness of installation. e. Check inclusion of manufacturer s typical equipment testing data or factors before T&C of particular equipment. Commissioning Plan April / 32

16 3.2 Tests & Inspections during Construction: The purpose of these tests is to ensure that all components and systems are in a satisfactory and safe condition before start up. Preliminary adjustment and setting of equipment at this stage also be carried out at the same time to pave way for the functional performance tests. Before carrying out any test, The Contractor shall ensure that the installation complies with all relevant statutory requirements and regulations. The T & C works shall also comply with all site safety regulatory requirements including but not limited to: (i) (ii) IEC Electrical Installations of Buildings Electricity supply rules of the relevant power supply companies Or other approved codes and standards. 3.3 Functional Performance Tests: The purpose of functional performance tests is to demonstrate that the equipment/installation can meet the functional and performance requirements as specified in the General/Particular specifications. Functional performance test should proceed from the testing of individual components to the testing of different systems in the installation. Any performance deficiencies revealed during the functional performance tests must be evaluated to determine the cause and whether they are part of the contractual obligations. After completion of the necessary corrective measures, the Contractor shall repeat the tests. If any test cannot be completed because of circumstances that are beyond the control of the Contractor, it shall be properly documented. The contractor shall resume his testing work immediately upon the attainment of a suitable testing environment. 3.4 Documentation and Deliverables: All inspection and T & C results shall be recorded in the data record forms. A functional performance test report covering all measured data, data sheets, and a comprehensive summary describing the operation of the system at the time of the functional performance tests shall be prepared and submitted. Deviations in performance from the General/Particular Specifications or the design intent should be recorded, with a description and analysis included. Commissioning Plan April / 32

17 4 Testing and Commissioning (T & C) Procedure: 4.1 Tests and Inspections during Construction For those tests to be carried out on different systems of the installation during construction to ensure their suitability for operating at the design conditions, certificates of such tests shall be issued together with certificates of any work tests. The tests and inspection shall include, but not limited to, the followings: (a) Visual inspection; (b) Earth electrode resistance; and (c) Continuity of protective conductor. (d) Voltage measurements. (e) Lux measurements. Details of these tests shall be in accordance with relevant sections of this procedure. 4.2 Inspection and Test for Low Voltage Installations Inspection before Test A visual inspection shall be made to verify that the electrical installation /equipment as installed is correctly selected and erected and that there is no apparent damage. The visual inspection shall include a check on the following items, where appropriate: a. Adequacy of working space, access, and maintenance facilities; b. Connections of conductors; c. Identification of conductors; d. Adequacy of the sizes of conductor in relation to current carrying capacity and voltage drop; e. Correct connections of all equipment with special attention to socket outlets, lamp holders, isolators, switches, and protective conductors, f. Presence of appropriate devices for isolation and switching; g. Presence of diagrams, instructions and other similar information; Sequence of Tests The following items, where relevant, are to be tested preferably in the sequence indicated below: a. Continuity of protective conductors, including main and supplementary equipotential bonding, b. Earth electrode resistance, Commissioning Plan April / 32

18 c. Earth fault loop impedance, In the event of any test indicating failure to comply, that test and those preceding, the results of which may have been influenced by the fault indicated, shall be repeated after the fault has been rectified Conductor Continuity Continuity of Protective Conductors Every protective conductor, including all conductors and any extraneous conductive parts used for equipotential bonding should be tested for continuity. The test should be made by connecting together the neutral and protective conductors at the mains position and checking between earth and neutral at every outlet by a continuity tester, which should show a reading near zero Earth Electrode Resistance A proper earth electrode resistance tester should be used to measure earth electrode resistance. An alternating current at 50 Hz of a steady value is passed between the earth electrode T and an auxiliary earth electrode T1 placed at a separation distance recommended by the manufacturer of the tester but in any case should not be less than 20 metres away. A second auxiliary earth electrode T2, which may be a metal spike driven into the ground, is then inserted half way between T and T1, and the voltage drop between T and T2, divided by the current flowing between T and T1, gives a measured earth electrode resistance of earth electrode T. For an electrical installation having four or more earth electrodes which are installed more or less in line, following a general direction not exceeding 15 deviation and with separation between adjacent electrodes not less than the recommended distance by the manufacturer of the tester but in any case not less than 20 meters, these electrodes can be used in turn as the auxiliary electrodes for the purpose of measuring the earth electrode resistances. The following alternative method for measuring the earth electrode resistance may be used if the electricity supply is connected. A loop impedance tester should be connected between the phase conductor at the origin of the installation and the earth electrode with the test link open, and a test performed. This impedance reading could be treated as the electrode resistance Earth Fault Loop Resistance The earth fault loop impedance should be measured by a phase earth loop tester with a scale calibrated in ohms. Commissioning Plan April / 32

19 The earth fault loop impedance should not exceed the requirements of applicable code. Before the test begins, it is essential to establish, by inspection, that the earthing conductor and all relevant earth connections are in place, and that the bonding connection to electricity supplier s earthing facilities is disconnected. Measures should be taken, during the impedance tests especially when the earth leakage protective devices are effectively removed for the duration of the tests, to ensure that the installation is not being used other than by person(s) carrying out the tests. 4.4 Functional Test of System/Equipment Circuitry Check All circuits shall be verified through switching operation to ensure that the circuits are installed in accordance with the designated circuit. The tests shall include but not be limited to the following: a. On/off switching of the lighting circuit to ensure that the lighting circuit is installed corresponding to the lighting switch, protective device and labeling; b. Switching of the general power circuit to ensure that the circuit corresponds to the protective device such as RCD, RCBO and MCB, and that the protective device performs in accordance with the designated duty; c. Switching of the main switch / isolator to ensure the corresponding circuit is properly controlled by the main switch / isolator; d. Switching of all sub main and main distribution circuits, e.g. bus ducts, cable feeders, underground cables, etc. to ensure the correct isolation of the connected circuit; e. Switching of all changeover switches to ensure the changing over sequence corresponds to the design criteria; f. Ensuring all the protective devices perform properly against the designated circuit Lighting Installation Lighting installation shall be tested in terms of its light quality and control as following: a. Before carrying out the lighting measurement and test, all luminaries shall be checked against the specified color temperature, beaming angle of spot lamp and aiming angle for exterior floodlights. b. The aiming angle of external lighting or planter lighting shall be commissioned so as not to create glare or any obstructive light to external environment. Commissioning Plan April / 32

20 c. Before commissioning and /or setting of lighting control devices which including but not limited to timer switch, occupancy sensor, photocell and infra red sensor, the Contractor shall submit commissioning /setting proposal for approval. d. Illumination level of lighting installation for individual areas/rooms shall be measured to verify the light output. The Contractor shall submit the proposed locations and height levels for carrying out the measurement of illuminance level for approval before commencement of measurement. Presentation of the measurement result shall be in the form of marked up layout plan for the particular area. e. Base on the measured illuminance results for individual areas/rooms, the lighting uniformity of the respective areas /rooms shall be evaluated in terms of minimum to average illuminance ratio. f. All grouping of luminaries shall be tested by hand operation of the corresponding switches or timers. g. For lighting installation with interface connection to building management system (BMS), or central control and monitoring system (CCMS) or similar central computer control system, the Contractor shall co ordinate with other contractors responsible for such computer control system, if required, to demonstrate proper control function of the lighting installation Digital Multifunction Power Meter The digital multifunction power meter shall be tested to verify the measurement, recording and interfacing functions as required in the General Specification. Prior to the test for every digital multifunction power meter, the Contractor shall provide manufacturer s calibration certificate for each meter for checking on the accuracy. The Contractor shall provide testing kit to verify the reading accuracy of the digital multifunction power meter. For installation of digital multifunction power meter with connection to building management system (BMS), or central control and monitoring system (CCMS) or similar central computer monitoring system, the Contractor shall co ordinate with other contractor responsible for such computer monitoring system, if required, to demonstrate proper functioning and interfacing of the meter. For installation of digital multifunction power meter without external connection to building management system or CCMS, the interface functions including digital and analogue output shall be tested by means of plugging in communication module provided by the Contractor. The replacement mechanism of the meter shall be tested. The test shall demonstrate that the replacement of the meter does not require the switching off of the respective switchgear. Commissioning Plan April / 32

21 Current transformers shorting block to prevent open circuiting the current transformers shall also be tested Equipment and Appliances Testing on electrical equipment and appliances supplied within the electrical installation, e.g. meters, fans, etc. shall be carried out in accordance with the relevant sections of other Building Services Branch Testing and Commissioning Procedures for other building services installations and manufacturer s recommended testing procedures. 4.5 Assessment of Any Characteristics of Equipment Likely to have Harmful Effects Before carrying out the T&C, the Contractor shall conduct assessment for any characteristics of equipment likely to have harmful effects upon other electrical equipment or other services, or impair the supply. Those characteristics include the following: a. Overvoltages; b. Undervoltages; c. Fluctuating loads; d. Unbalanced loads; e. Power factor; f. Starting currents; g. Harmonic currents; h. Direct current (d.c.) feedback; i. High frequency oscillations; and j. Necessity for additional connection to earth. The Contractor shall, after conduct the assessment, submit an assessment report for consideration. Commissioning Plan April / 32

22 Appendix A Commissioning Plan April / 32

23 Item tested / checked by: Contractor Item witnesses by: Part1. Items Inspected and Tested 1.1. Statutory Inspection and Test for Low Voltage (L.V.) Installation Visual Inspection Working Space and Facilities a. Adequacy working space and safe access provided for switch room and /or electrical facilities. b. Entrance /exit to switch room and/or electrical facilities are free of obstruction c. Suitable locking facilities provided for switch room and /or electrical facilities. d. Suitable lighting provision provided for switch room and /or electrical facilities. e. Suitable ventilation provision provided for switch room and /or electrical facilities. f. Suitable tools for withdrawal of fuses at fuse board provided. g. A warning notice DANGER SUBSTATION, UNAUTHORISED ENTRY PROHIBITED provided at every entrance of switch room. h. Fire barriers and other measures for protection against thermal effects are properly installed. i. Danger notices, warning notices, schematic diagrams, instructions and similar information are correctly and adequately provided. j. Warning notices for substations and switchrooms provided k. Warning notices for earthing and main bonding connections provided l. All switchgears, distribution boards and electrical equipment properly labelled. Tested / Checked by : (Name of Contractor s Representative) Witnessed by : (Name(s)) Signature: Signature Commissioning Plan April / 32

24 Switchboard, Main Switch and Circuit Breaker a. An up-to-date notice of periodic inspection and testing provided at point of supply (i.e. a switchboard, a circuit breaker or a distribution board) of the installation. b. Circuits, fuses, switches, terminals, etc. are provided with a legible and durable identification label. Item tested / checked by: Contractor Item witnesses by: c. No visible damage to impair safety. d. Work done properly recorded in logbook. e. An up-to-date schematic diagram displayed. f. All accessible live parts screened with insulating plate or earthed metal. g. All exposed conductive parts effectively earthed. h. Earthing system effectively connected. i. Warning notice displayed at main bonding connections j. All protective devices are functioned properly and correctly set. k. Suitable interlock scheme provided to prevent parallel operation of two or more sources of supply and 4-pole incoming and interconnecting circuit breakers provided for supply to be taken from more than one source and is interconnected. l. Electrically and mechanically interlocked 4-pole changeover device(s) where standby generator set(s) is installed. m. The breaking capacities of all circuit breakers / interconnection devices are able to withstand the prospective fault current. n. Protective relays have been correctly set and overcurrent protective devices suitably set for all circuits. Tested / Checked by : (Name of Contractor s Representative) Witnessed by : (Name(s)) Signature: Signature Commissioning Plan April / 32

25 Item tested / checked by: Contractor Item witnesses by: o. Protective type current transformers are used for protective relays. p. A means of isolation provided for every circuit. q. Operation of circuit breakers and main switches checked. r. Control, indication and alarm functions checked. s. No undersized conductor used between the main busbar and fuse/mcb. t. Fuses/MCB s matching the lowest rated conductor in the circuit. u. Suitable cable terminations provided. v. Cable conductors of correct phases connected. w. Single-pole devices for protection or switching connected in phase conductors only Distribution Board a. A warning notice DANGER provided on the front panel of every distribution board. b. A notice of periodic testing provided at or near the main distribution board incorporating a residual current device. c. Distribution boards securely mounted on suitable supports. d. A suitable switch provided to control each distribution board. e. Phase barriers for 3-phase distribution board provided. f. The breaking capacity of MCB is correct according to calculation g. Suitable tools for withdrawal of fuses at a fuse board provided, where necessary. h. Circuits connected to MCB or fuse in accordance with the schematic diagram. Tested / Checked by : (Name of Contractor s Representative) Witnessed by : Signature: Signature Commissioning Plan April / 32

26 Conductors, Cables and wirings Item tested / checked by: Contractor Item witnesses by: a. No visible damage to impair safety. b. All live conductors and their methods of insulation, in relation to design currents of circuits and to the operating currents of the protective devices, are properly selected and erected. c. All cables, flexible cords, switches, plugs and socket outlets, accessories and equipment are found to be in good working conditions. d. All conductors are correctly and securely connected and identified. e. Armoured cables properly terminated to metal casing or trunking by proper cable glands. f. Cables passing through smoke lobby protected by enclosures of adequate fire rating. g. Non-sheathed cables protected by conduit, trunking or ducting. h. Cables and ductings adequately supported. i. Cables at distribution board or busbar terminated with cable lugs. j. Main cables connected up with correct polarity k. Cables protected against mechanical damage and suitably supported. l. All exposed metal parts including the armour effectively earthed. Tested / Checked by : (Name of Contractor s Representative) Witnessed by : (Name(s)) Signature: Signature Commissioning Plan April / 32

27 Busbar trunking system including rising mains a. The rising mains, lateral mains and meter boards positioned at places accessible from public area. b. Fire barriers provided where the busbar trunking system passes through floor slabs or walls designated as fire barriers. c. Cables passing through smoke lobby protected by enclosures of adequate fire rating. Item tested / checked by: Contractor Item witnesses by: d. Non-sheathed cables protected by conduit, trunking or ducting. e. Busbar trunking systems, cables and ductings adequately supported. f. The bolts, nuts, screws, etc. for busbar supports, busbar connections have been checked for correct tightness in accordance with manufacturers recommendations. g. The busbar trunking system is properly and correctly installed and aligned. h. No dust, foreign particles and deleterious substances are accumulated on the busbar trunking system. i. The busbar trunking system is free from condensation. j. Armoured cables properly terminated to metal casing or trunking by proper cable glands. k. Suitable cable lugs used for terminating cables. l. Precaution against corrosion taking on aluminium conductor joined to copper conductor. m. Cutout fuses for tapping off supply fitted with insulated carriers. Tested / Checked by : (Name of Contractor s Representative) Witnessed by : (Name(s)) Signature: Signature Commissioning Plan April / 32

28 Final circuits a. All fuses and single pole switches connected to the phase conductors only with correct polarity. b. Wiring for emergency lightings and fire services installation segregated from other wirings. Item tested / checked by: Contractor Item witnesses by: c. Low voltage circuits segregated from extra low voltage circuits. d. Cables of all phases and neutral of the circuit bunched and contained in the same conduit. e. Exposed insulated non-sheathed cables protected. f. Wiring inside false ceiling protected by conduit/trunking or metallic sheath. g. Socket outlets installed below 1.5m from floor being shuttered type complying with the prescribed requirements. h. No socket outlet installed close to water tap, gas tap or cooker so as to avoid danger. i. Floor socket outlets protected with suitable cover. j. No 2-pin sockets installed. All socket outlets connected with protective conductors and live conductors terminated at correct terminals. k. Radial final circuits using socket outlets. l. Final circuits using socket outlets. m. Final circuits using industrial socket outlets. n. Circuit protective conductor is formed by the enclosure and a separate protective conductor between the earthing terminal of socket outlet and its associated metal box provided. Tested / Checked by : (Name of Contractor s Representative) Witnessed by : (Name(s)) Signature: Signature Commissioning Plan April / 32

29 o. Circuit protective conductor is not formed by the enclosure and a separate protective conductor to the earthing terminal of socket outlet provided. a. Residual current device having a rated residual operating current not exceeding 30mA provided for all socket outlets. b. Minimum sizes of protective conductors are provided for limitation of protective conductor impedance. Item Tested/ checked by: Contractor Witnessed by: c. Means of isolation provided for every fixed appliance. d. All chokes, starters and capacitors of discharge lamps enclosed in earthed metal box(es) and suitably ventilated. e. Phase conductors connected to the centre contact of the Edison-type screw lamp holders. f. No switches other than a switch fed from a safety source or operated by an insulation cord or rod or a push-button type of switch having an insulated button of a large surface area provided in bathrooms. g. Shaver supply unit complying with EN or equivalent. h. Socket outlet in bathroom installed in zone 3 (i.e. 0.6m away from shower basin or bathtub); and protected by a 30mA residual current device or protected by an isolating transformer to EN i. No fixed luminaire nor fixed heater having unguarded heating elements installed within reach of a person using the bath or shower. j. Appliances exposed to weather being splash-proof type. k. Luminaires, switches, sockets and plugs, cable couplers installed outdoor, being splashproof type. l. General/site lighting readily accessible to the public supplied from a safety source. m. General/site lighting not readily accessible to the public and not supplied from a safety source, protected by RCD having a rated residual operating current not exceeding 30mA. Tested / Checked by : (Name of Contractor s Representative) Witnessed by : Signature: Signature Commissioning Plan April / 32

30 Earthing and Bonding Item tested / checked by: Contractor Item witnesses by: a. Earth rod electrode(s) having a diameter as shown on the drawing b. Copper tape earth electrode having a cross section of not less than 25 mm x 3 mm. c. Copper plate earth electrode not less than 3mm in thickness and having a maximum dimension of 1200mm x 1200mm d. No gas/water pipe used as earth electrodes.. e. A test link provided at the main earthing terminal. f. Minimum size of protective conductor used g. Protective conductor up to and including 6mm2 with green and yellow insulation sheath used throughout its length. h. Proper bonding conductors copper or equivalent used for connection to the earthing terminal of the electricity supplier s transformer(s) or underground cable(s). i. Copper links provided at joints of metallic trunking which forms part of a protective conductor. j. Separate protective conductors provided for all flexible conduits. k. A warning notice SAFETY ELECTRICAL CONNECTION DO NOT REMOVE provided at all main earthing and bonding connections. l. Main equipotential bonding conductors effectively connected to main water pipes, main gas pipes, other services pipes/ducting and exposed metallic parts of structural framework. Tested / Checked by : (Name of Contractor s Representative) Witnessed by : (Name(s)) Signature: Signature Commissioning Plan April / 32

DOMESTIC ELECTRICAL INSTALLATION CERTIFICATE (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations)

DOMESTIC ELECTRICAL INSTALLATION CERTIFICATE (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations) DOMESTIC ELECTRICAL INSTALLATION CERTIFICATE (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations) DETAILS OF THE CLEINT Client and address ADDRESS OF THE INSTALLATION Installation

More information

TESTING AND COMMISSIONING PROCEDURE FOR ELECTRICAL INSTALLATION GOVERNMENT BUILDINGS THE HONG KONG SPECIAL ADMINISTRATIVE REGION

TESTING AND COMMISSIONING PROCEDURE FOR ELECTRICAL INSTALLATION GOVERNMENT BUILDINGS THE HONG KONG SPECIAL ADMINISTRATIVE REGION TESTING AND COMMISSIONING PROCEDURE FOR ELECTRICAL INSTALLATION IN GOVERNMENT BUILDINGS OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION 2012 EDITION ARCHITECTURAL SERVICES DEPARTMENT THE GOVERNMENT OF THE

More information

CHECKING AND TESTING ELECTRICAL INSTALLING WORK

CHECKING AND TESTING ELECTRICAL INSTALLING WORK CHECKING AND TESTING ELECTRICAL INSTALLING WORK Department of Consumer and Employment Protection Energy Safety Preface It is a requirement of the Electricity (Licensing) Regulations 1991 that all electrical

More information

TESTING AND COMMISSIONING PROCEDURE FOR ELECTRICAL INSTALLATION GOVERNMENT BUILDINGS THE HONG KONG SPECIAL ADMINISTRATIVE REGION

TESTING AND COMMISSIONING PROCEDURE FOR ELECTRICAL INSTALLATION GOVERNMENT BUILDINGS THE HONG KONG SPECIAL ADMINISTRATIVE REGION TESTING AND COMMISSIONING PROCEDURE FOR ELECTRICAL INSTALLATION IN GOVERNMENT BUILDINGS OF THE HONG KONG SPECIAL ADMINISTRATIVE REGION 2007 EDITION ARCHITECTURAL SERVICES DEPARTMENT THE GOVERNMENT OF THE

More information

Sample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES

Sample Company SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES SECTION 019113 GENERAL COMMISSIONING REQUIREMENTS PART 1 GENERAL 1.1 SUMMARY AND CONTRACT RESPONSIBILITIES A. The Owner will contract separately and directly for the majority of the commissioning work

More information

ELECTRICAL INSTALLATION CONDITION REPORT (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations)

ELECTRICAL INSTALLATION CONDITION REPORT (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations) Original Certificate DETAILS OF THE CLIENT Certificate reference: ELECTRICAL INSTALLATION CONDITION REPORT (Requirements for Electrical Installations BS 7671 IEE Wiring Regulations) Name: Address: PURPOSE

More information

Unified requirements for systems with voltages above 1 kv up to 15 kv

Unified requirements for systems with voltages above 1 kv up to 15 kv (1991) (Rev.1 May 2001) (Rev.2 July 2003) (Rev.3 Feb 2015) Unified requirements for systems with voltages above 1 kv up to 15 kv 1. General 1.1 Field of application The following requirements apply to

More information

A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project.

A. The Commissioning Authority (CxA) has been contracted or will be contracted directly with the Owner for this project. DIVISION 23 HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) SECTION 23 08 02 PART 1 GENERAL 1.01 AUTHORITY (CxA) A. The Commissioning Authority (CxA) has been contracted or will be contracted directly

More information

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV

ELECTRICAL INSULATION TESTING OF HV EQUIPMENT UP TO 33kV 1. SCOPE This document details PowerSystems requirements for electrical testing of HV Equipment up to and including 33kV. 2. ISSUE RECORD This is a Reference document. The current version of Controlled

More information

Trade of Electrician. Three-phase Distribution Boards And Socket Circuits

Trade of Electrician. Three-phase Distribution Boards And Socket Circuits Trade of Electrician Standards Based Apprenticeship Three-phase Distribution Boards And Socket Circuits Phase 2 Module No. 2.3 Unit No. 2.3.2 COURSE NOTES Created by Charlie Walsh - Athlone TC Revision

More information

FAQs-Main switchboard design criteria

FAQs-Main switchboard design criteria FAQs-Main switchboard design criteria Q: What is the Australian standard for main switchboards? Current Australian standard is AS/NZS 3439.1: 2002 originating from IEC 60439. The new series of standard

More information

Electrical Practices for Construction Work

Electrical Practices for Construction Work 1. Purpose Electrical Practices for Construction Work The purpose of this Code is to provide practical guidance and set minimum safety requirements for electrical practices on all construction sites in

More information

chapter8 Testing and commissioning Unit 2 outcome 2

chapter8 Testing and commissioning Unit 2 outcome 2 Testing and commissioning chapter8 Unit 2 outcome 2 It is important that electricians are not just able to construct; they should also be able to recognise faults and take action to help prevent them.

More information

Circuit Electrical Testing

Circuit Electrical Testing Safe Isolation Procedure Circuit Electrical Testing Site Safety Management It is essential from the outset that effective management and control of the system, apparatus and equipment used on site is achieved

More information

Building Commissioning 17900-1

Building Commissioning 17900-1 SECTION 17900 BUILDING COMMISSIONING PART 1 - GENERAL 1.01 WORK DESCRIPTION: A. General: 1. The Commissioning process is a joint team effort to ensure that all mechanical equipment, controls, and systems

More information

3.1.1 Full Type Tests & Routine Tests according to Clause 8 2 & 8 3. 4.0 Instructions For Installation, Operation & Maintenance

3.1.1 Full Type Tests & Routine Tests according to Clause 8 2 & 8 3. 4.0 Instructions For Installation, Operation & Maintenance SPECIFICATION FOR LOW VOLTAGE SWITCHBOARD SEN I N D E X Description 10 STANDARD TECHNICAL REQUIREMENTS 11 Standards 12 General Operating Conditions 13 General Description Of Switchboard 131 Structure 132

More information

Building Regulations P.4. Socket Outlets P.6. Other Considerations P.10. Training Seminars P.24

Building Regulations P.4. Socket Outlets P.6. Other Considerations P.10. Training Seminars P.24 1 Introduction For well over one hundred years the Wiring Regulations have provided the rules which must be followed to make sure that electrical installations are safe. The introduction of the 17 th Edition

More information

Regulation IO-6.0: Electrical Safety Regulations

Regulation IO-6.0: Electrical Safety Regulations Regulation IO-6.0: Electrical Safety Regulations 6.1 Workmanship & Material 6.2 Electrical Conductors 6.3 Overcurrent Protective Devices 6.4 Precautions against Earth Leakage and Earthfault Currents 6.5

More information

Energy Design Resources Commissioning Plan Outline Template

Energy Design Resources Commissioning Plan Outline Template IMPORTANT NOTICE: This sample document is provided for instructional purposes only. CCC is not rendering advice concerning any commission project or practices. This document is neither approved nor intended

More information

A B Brown. This sheet forms part of *Inspection Report Number/*Certificate Number NA/ * EC/ * PIR *Delete as applicable DB1 60898

A B Brown. This sheet forms part of *Inspection Report Number/*Certificate Number NA/ * EC/ * PIR *Delete as applicable DB1 60898 NAPIT Electrical Test Continuation Sheet Requirements for Electrical Installations BS 767 [IEE Wiring Regulations] and for Please complete all the unshaded areas. This sheet forms part of *Inspection Report

More information

12 SOLAR PHOTOVOLTAIC POWER SUPPLY SYSTEMS by John Ware. PV modules are current-limiting

12 SOLAR PHOTOVOLTAIC POWER SUPPLY SYSTEMS by John Ware. PV modules are current-limiting 12 SOLAR PHOTOVOLTAIC POWER by John Ware IT IS PLANNED for BS 7671:2008 to include a new Section 712 providing additional requirements for safety applicable to solar photovoltaic (pv) power supply systems.

More information

FIREFINDER XLS ADDRESSABLE FIRE ALARM SYSTEM SECTION 13851

FIREFINDER XLS ADDRESSABLE FIRE ALARM SYSTEM SECTION 13851 FIREFINDER XLS ADDRESSABLE FIRE ALARM SYSTEM SECTION 13851 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and

More information

SOLAR PV STANDARD ELECTRICAL PLAN Microinverter Systems for Single Family Dwellings

SOLAR PV STANDARD ELECTRICAL PLAN Microinverter Systems for Single Family Dwellings *** Provide this document to the inspector along with ALL system installation instructions *** Project Address: Scope: Standard plan for the installation of grounded microinverter solar PV systems, not

More information

Trial Exams C. Standards and Regulations. Examination No: GH-08-C- 1 hour and 5 minutes plus 10 minutes reading time

Trial Exams C. Standards and Regulations. Examination No: GH-08-C- 1 hour and 5 minutes plus 10 minutes reading time Trial Exams C Standards and Regulations Examination No: GH-08-C- This test is intended to gauge your knowledge of essential information contained within AS/CA S009:2013. To qualify for an allpication to

More information

INSTALLATION GUIDELINES for SOLAR PHOTOVOLTAIC SYSTEMS 1

INSTALLATION GUIDELINES for SOLAR PHOTOVOLTAIC SYSTEMS 1 City of Cotati Building Division 201 W. Sierra Ave. Cotati, CA 94931 707 665-3637 Fax 792-4604 INSTALLATION GUIDELINES for SOLAR PHOTOVOLTAIC SYSTEMS 1 Any PV system on a new structures should be included

More information

MISCELLANEOUS ELECTRICAL JOBS REQUIRING PERMITS

MISCELLANEOUS ELECTRICAL JOBS REQUIRING PERMITS MISCELLANEOUS ELECTRICAL JOBS REQUIRING PERMITS 01. SAFETY INSPECTION of service equipment at FPL Power Source 02. Construction GFI power outlets (Temp Pole for Construction) 03. 90 day temporary power

More information

TIG INVERTER INSTRUCTION MANUAL

TIG INVERTER INSTRUCTION MANUAL TIG INVERTER INSTRUCTION MANUAL Contents Warning General Description Block Diagram Main Parameters Circuit Diagram Installation and Operation Caution Maintenance Spare Parts List Troubleshooting 3 4 4

More information

FIRE ALARM AND DETECTION SYSTEMS SECTION 16721

FIRE ALARM AND DETECTION SYSTEMS SECTION 16721 PART 1 - GENERAL 1.01 WORK INCLUDED FIRE ALARM AND DETECTION SYSTEMS SECTION 16721 A. Provide a complete fully addressable, power limited, fire detection and evacuation system. The system shall be connected

More information

All work must conform to the National Electric Code, latest edition, and all other applicable codes and regulations.

All work must conform to the National Electric Code, latest edition, and all other applicable codes and regulations. DIVISION 16 ELECTRICAL SECTION 16100 - ELECTRICAL PART 1 - GENERAL SCOPE All electrical work as shown on the drawings and as necessary to provide a complete electrical system. Include primary service,

More information

3 IN 1 BATHROOM HEATER

3 IN 1 BATHROOM HEATER 3 IN 1 BATHROOM HEATER MODEL NO.: A515 - SH MINI FUNCTION: HEATER, EXHAUST FAN AND LIGHT Dear customers, Thank you for selecting the AUPU 3 in 1 Bathroom Heater. Please read all instructions before commencing

More information

What are the basic electrical safety issues and remedies in solar photovoltaic installations?

What are the basic electrical safety issues and remedies in solar photovoltaic installations? What are the basic electrical safety issues and remedies in solar photovoltaic installations? Presented by: Behzad Eghtesady City of Los Angeles Department of Building and Safety Topics Covered Photovoltaic

More information

City of Riverside Building & Safety Division Phone: (951) 826-5697 www.riversideca.gov

City of Riverside Building & Safety Division Phone: (951) 826-5697 www.riversideca.gov City of Riverside Building & Safety Division Phone: (951) 826-5697 www.riversideca.gov PHOTOVOLTAIC PERMITTING GUIDELINES The information provided in this document is general and is intended only as a

More information

Contractor Connect Scheme Electrical Contractor and Worker Handbook

Contractor Connect Scheme Electrical Contractor and Worker Handbook Contractor Connect Scheme Electrical Contractor and Worker Handbook January 2016 Document release information Document number 13553681 Document title Revision status Contractor Connect Scheme handbook

More information

MEDIUM VOLTAGE CE-BF SWITCHBOARDS. UP TO 40.5 kv. CE - BF - C - en - REV.00 2012.4

MEDIUM VOLTAGE CE-BF SWITCHBOARDS. UP TO 40.5 kv. CE - BF - C - en - REV.00 2012.4 CE - BF - C - en - REV.00 2012.4 APPLICATION CE-BF Switchbords up to 40.5 kv are designed for use in public and industrial distribution system up to 40,5KV for the operation and protection of lines, transformers,

More information

High Voltage (HV) Electricity System Safety Rules and Associated Safety Guidance

High Voltage (HV) Electricity System Safety Rules and Associated Safety Guidance Annex I To Loughborough University (LU) Facilities Management (FM) Health and Safety Policy High Voltage (HV) Electricity System Safety Rules and Associated Safety Guidance 1. Introduction a. These Safety

More information

Wiser Panel Meter, Model Number WISERCTPM200 Installer s Guide

Wiser Panel Meter, Model Number WISERCTPM200 Installer s Guide Instruction Bulletin EAV85226 08/2014 Wiser Panel Meter, Model Number WISERCTPM200 Installer s Guide Retain for future use. Product Description Kit Contents The Wiser Panel Meter is for use in energy management

More information

Solar Panel Installations

Solar Panel Installations Solar Panel Installations Page 1 of 6 SINGLE-FAMILY RESIDENTIAL CHECKLIST City of Hayward Development Services Department Revised: 7-09-15 PERMIT REQUIREMENTS Permits are required for all solar panel installations.

More information

NZECP 14: 1995 ISSN 0114-0663 COVER PAGE

NZECP 14: 1995 ISSN 0114-0663 COVER PAGE NZECP 14: 1995 ISSN 0114-0663 COVER PAGE NZECP 14:1995 NEW ZEALAND ELECTRICAL CODE OF PRACTICE FOR CONTROL PROTECTION AND SWITCHBOARDS Issued by the Office of The Chief Electrical Engineer, Energy and

More information

Electrical Shore Connections / Cold Ironing

Electrical Shore Connections / Cold Ironing STANDARD FOR CERTIFICATION No. 2.25 Electrical Shore Connections / Cold Ironing JULY 2014 The electronic pdf version of this document found through http://www.dnv.com is the officially binding version

More information

Fire Alarm System Plans Submittal Guidelines For New and Existing Systems

Fire Alarm System Plans Submittal Guidelines For New and Existing Systems Fire Alarm System Plans Submittal Guidelines For New and Existing Systems SCOPE The Temecula Fire Prevention Bureau (TFPB) has established the following requirements for the submittal of all fire alarms,

More information

CAPACITOR BANK TESTING SWP

CAPACITOR BANK TESTING SWP 1. PURPOSE AND SCOPE The purpose of this Standard Work Practice (SWP) is to standardise and prescribe the method for testing Capacitor Banks including capacitors, tuning reactors and inrush limiting reactors.

More information

EARTHING AND BONDING AT SECONDARY SUBSTATIONS

EARTHING AND BONDING AT SECONDARY SUBSTATIONS DISTRIBUTION CONSTRUCTION MANUAL SECTION 4 - SUBSTATIONS ISSUE B SEPT 1996 4.4.4 EARTHING AND BONDING AT SECONDARY SUBSTATIONS 1 SCOPE This section of the Distribution Construction Manual lays down the

More information

GUIDELINES FOR ELECTRICAL WIRING IN RESIDENTIAL BUILDINGS

GUIDELINES FOR ELECTRICAL WIRING IN RESIDENTIAL BUILDINGS GUIDELINES FOR ELECTRICAL WIRING IN RESIDENTIAL BUILDINGS 2008 EDITION www.st.gov.my CONTENTS Chapter Title Page 1. 1.1 1.2 1.3 Introduction Purpose References 4 4 5 2. Supply System 6 2.1 Electricity

More information

TECHNICAL SPECIFICATIONS & SPECIAL CONDITIONS OF CONTRACT FOR ELECTRICAL WORKS CHAPTER 1 SPECIAL CONDITIONS OF CONTRACT

TECHNICAL SPECIFICATIONS & SPECIAL CONDITIONS OF CONTRACT FOR ELECTRICAL WORKS CHAPTER 1 SPECIAL CONDITIONS OF CONTRACT TECHNICAL SPECIFICATIONS & SPECIAL CONDITIONS OF CONTRACT FOR ELECTRICAL WORKS CHAPTER 1 SPECIAL CONDITIONS OF CONTRACT 1.1 General 1.1.1 These Special Conditions of Contract supplement the General Instructions.

More information

USER INSTRUCTIONS FOR GET PORTABLE 12k BTU AIR CONDITIONER MODEL No. GPACU12HR

USER INSTRUCTIONS FOR GET PORTABLE 12k BTU AIR CONDITIONER MODEL No. GPACU12HR USER INSTRUCTIONS FOR GET PORTABLE 12k BTU AIR CONDITIONER MODEL No. GPACU12HR CONTENTS Introduction Safety Notes Identification of parts Installation instructions Operation instructions Maintenance Troubleshooting

More information

GROWTH MANAGEMENT DEPARTMENT 201 SE 3 rd ST, (Second Floor), Ocala, FL 34471 (352) 629-8421; FAX: (352) 629-8264

GROWTH MANAGEMENT DEPARTMENT 201 SE 3 rd ST, (Second Floor), Ocala, FL 34471 (352) 629-8421; FAX: (352) 629-8264 BUILDING CODE GUIDELINES FOR ELECTRICAL INSPECTIONS Building Code compliance is the obligation of design professionals and/or contractors. Plan Review and Inspection Guidelines are intended to be used

More information

Fire Alarm Systems Certification

Fire Alarm Systems Certification Fire Alarm Systems Certification The skills and knowledge listed under each task are suggestive of those involved in that task, but are not intended to constitute an exhaustive listing. 2.1 Submittal Preparation

More information

FIRST STOP SAFETY 1 PAT-IT. Portable Appliance Tester. User Manual. Issue 1.6

FIRST STOP SAFETY 1 PAT-IT. Portable Appliance Tester. User Manual. Issue 1.6 FIRST STOP 1 PAT-IT Portable Appliance Tester User Manual Issue 1.6 First Stop Safety 11 Glaisdale Road Northminster Business Park Upper Poppleton York YO26 6QT t: 01904 791050 f: 01904 780054 e: info@firststopsafety.co.uk

More information

Building Services Engineering Technician

Building Services Engineering Technician Building Services Engineering Technician A competent Building Services Engineering Technician is expected to be able to demonstrate the following skills and competences: Systems design in the building

More information

Submit shop drawings for equipment provided under this section Shop drawings shall indicate:

Submit shop drawings for equipment provided under this section Shop drawings shall indicate: Section 16435 - SWITCHBOARDS Introduction Part 1 - General Reference The work under this section is subject to requirements of the Contract Documents including the General Conditions, Supplementary Conditions,

More information

COMMISSIONING OF FIRE ALARM SYSTEMS

COMMISSIONING OF FIRE ALARM SYSTEMS COMMISSIONING OF FIRE ALARM SYSTEMS OWNER FURNISHED The owner directly contracts an independent third party commissioning agent for this project. This Commissioning Plan has been included for reference

More information

Fire. The Fire Installers Mate. A guide to fire alarm systems design

Fire. The Fire Installers Mate. A guide to fire alarm systems design Fire The Fire Installers Mate A guide to fire alarm systems design BS 5839 Part 1:2002 A guide to BS 5839 Part 1:2002 Disclaimer This booklet is not intended to be a comprehensive guide to all aspects

More information

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1

ELECTRICAL CONTRACTORS THE UNIVERSITY OF TENNESSEE KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 KNOXVILLE, TENNESSEE SECTION 16050 PAGE 1 PART 1 - GENERAL 1.01 RELATED DOCUMENTS: SECTION 16050 A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division-1

More information

26 3213.13 Diesel Engine Driven Generators Page 1 of 6

26 3213.13 Diesel Engine Driven Generators Page 1 of 6 Last Update: December 8, 2014 A. Description of System Consultant s Handbook Page 1 of 6 1. Provide a diesel engine driven electric generating unit, factory assembled, tested and certified to operate at

More information

INSTALLATION & SERVICE MANUAL. Display Panel

INSTALLATION & SERVICE MANUAL. Display Panel INSTALLATION & SERVICE MANUAL Display Panel The PowerLine EMS TM is a specialized power distribution and energy management system intended to be used in recreational vehicles. The Control Module is housed

More information

SECTION 16720 - FIRE AND SMOKE ALARM SYSTEM. City of San Diego, CWP Guidelines

SECTION 16720 - FIRE AND SMOKE ALARM SYSTEM. City of San Diego, CWP Guidelines PART 1 -- GENERAL 1.1 WORK OF THIS SECTION SECTION 16720 - City of San Diego, CWP Guidelines A. The WORK of this Section includes providing manual and automatic fire alarm and smoke detection systems meeting

More information

County of Riverside Building and Safety Department

County of Riverside Building and Safety Department County of Riverside Building and Safety Department Mike Lara Director Photovoltaic Permitting Guidelines The information provided in this document is general and is intended only as a guide. Each project

More information

INFRARED QUARTZ WALL HEATER

INFRARED QUARTZ WALL HEATER INFRARED QUARTZ WALL HEATER MODEL NO: IQ2000 PART NO: 6939004 MOUNTING & OPERATION INSTRUCTIONS GC0715 INTRODUCTION Thank you for purchasing this CLARKE Infrared Wall Heater. Before attempting to use this

More information

White Paper SolarEdge Three Phase Inverter System Design and the National Electrical Code. June 2015 Revision 1.5

White Paper SolarEdge Three Phase Inverter System Design and the National Electrical Code. June 2015 Revision 1.5 White Paper SolarEdge Three Phase Inverter System Design and the National Electrical Code June 2015 Revision 1.5 Shalhevet Bar-Asher; SolarEdge Technologies, Inc. Bill Brooks, PE; Brooks Engineering LLC

More information

A. Shop Drawing submittals shall include, but not be limited to, the following:

A. Shop Drawing submittals shall include, but not be limited to, the following: SECTION 26 05 53 IDENTIFICATION FOR ELECTRICAL SYSTEMS PART 1 - GENERAL 1.1 RELATED DOCUMENTS: A. The Conditions of the Contract and applicable requirements of Divisions 0 and 1 and Section 26 00 01, Electrical

More information

Top Commercial / Residential Electrical Requirements *

Top Commercial / Residential Electrical Requirements * Department of Community Development Building Division 4800 West 92 nd Avenue Westminster, Colorado 80031 For Information call (303) 658-2075 Fax (303) 706-3922 www.westminsterpermits.com Top Commercial

More information

Control of Hazardous Energy LOCKOUT/TAGOUT 29 CFR 1910.147

Control of Hazardous Energy LOCKOUT/TAGOUT 29 CFR 1910.147 Control of Hazardous Energy LOCKOUT/TAGOUT 29 CFR 1910.147 Contents I. Introduction II. Scope and Application III. Definitions IV. Lockout/Tagout Manual V. Energy Control Procedures 1. Applying Energy

More information

Ground Resistance Clamp On Tester

Ground Resistance Clamp On Tester USER MANUAL Ground Resistance Clamp On Tester MODEL 382357 Introduction Congratulations on your purchase of Extech s 382357 Ground Resistance Tester. This Clamp on device allows the user to measure ground

More information

Sample - No Commercial Use

Sample - No Commercial Use COMPLETE REVISION October 2010 Electrical PIP ELSSG01 Design and Fabrication of Low-Voltage Metal-Enclosed AC Power Circuit Breaker Switchgear PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES In an effort

More information

D. Infrared scanning reports with pictures printed in a final report with any deficiencies and actions taken to rectify.

D. Infrared scanning reports with pictures printed in a final report with any deficiencies and actions taken to rectify. SECTION 263354 STATIC UPS TESTING AND COMMISSIONING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes 1. System start-up services. 2. Battery charging. 3. Load bank testing. 4. Battery load testing. 5.

More information

ELECTRICAL GUIDELINES FOR SINGLE-FAMILY HOME OWNERS:

ELECTRICAL GUIDELINES FOR SINGLE-FAMILY HOME OWNERS: ELECTRICAL GUIDELINES FOR SINGLE-FAMILY HOME OWNERS: Chapter 12 of the Burlington Code of ordinances allows owner occupants of single family homes to do their own wiring if they choose. If you choose to

More information

AS/NZS 3000:2007 Amendment 2

AS/NZS 3000:2007 Amendment 2 AS/NZS 3000:2007 Amendment 2 Published 14 December 2012 Under Victorian legislation the day a revised standard is published it becomes the requirement. The aim of this document is to highlight the important

More information

Design Consultant (Electrical Services) Design Deliverables and Responsibilities Allocation (Stage E+)

Design Consultant (Electrical Services) Design Deliverables and Responsibilities Allocation (Stage E+) Design Consultant (Electrical Services) Design Deliverables and Responsibilities Allocation (Stage E+) 1. In addition to the information scheduled below, the pre-tender designer is responsible for: (i)

More information

SECTION 16721 FIRE ALARM AND SMOKE DETECTION SYSTEMS

SECTION 16721 FIRE ALARM AND SMOKE DETECTION SYSTEMS SECTION 16721 PART 1 - GENERAL 1.1 SECTION INCLUDES A. Fire Alarm Control Panels B. Manual Fire Alarm Stations C. Automatic Smoke D. Fire Alarm Notification Appliances E. Auxiliary Fire Alarm Equipment

More information

FLORIDA ATLANTIC UNIVERSITY FIRE ALARM SYSTEM INSTALLATION MANUAL

FLORIDA ATLANTIC UNIVERSITY FIRE ALARM SYSTEM INSTALLATION MANUAL FLORIDA ATLANTIC UNIVERSITY FIRE ALARM SYSTEM INSTALLATION MANUAL January, 2003 Environmental Health and Safety Florida Atlantic University 777 Glades Rd. Boca Raton, FL 33431 Phone: 561-297-3129 Fax:

More information

SWIMMING POOL HEAT PUMP

SWIMMING POOL HEAT PUMP SWIMMING POOL HEAT PUMP Installation & User Manual Model HP40B HP50B HP65B Hayward Pool Products Canada, Inc. T: 1-888-238-7665 www.haywardpool.ca CONTENT I. Application 4 II. Features 4 III. Technical

More information

Significant Changes in the 2011 NEC Prepared by Bryan Holland City of North Port

Significant Changes in the 2011 NEC Prepared by Bryan Holland City of North Port Significant Changes in the 2011 NEC Prepared by Bryan Holland City of North Port Code-Wide Code Change Section 90.5(C). Fine Print Notes are now referred to as "Informational Notes." The purpose, intent,

More information

ALVERNIA UNIVERSITY OSHA REGULATION: 29 CFR 1910.147 THE CONTROL OF HAZARDOUS ENERGY (LOCKOUT / TAGOUT) SECTION: 2400

ALVERNIA UNIVERSITY OSHA REGULATION: 29 CFR 1910.147 THE CONTROL OF HAZARDOUS ENERGY (LOCKOUT / TAGOUT) SECTION: 2400 OSHA REGULATION: 29 CFR 90.7 THE CONTROL OF HAZARDOUS ENERGY (LOCKOUT / TAGOUT) DATE: 0/5/2008 DATE: /2/202 A. POLICY. This procedure follows requirements set forth in 29 CFR 90.7. 2. It is the policy

More information

PowlVac Vacuum Integrity Tester

PowlVac Vacuum Integrity Tester Instructions IB-60025B PowlVac Vacuum Integrity Tester POWELL ELECTRICAL MANUFACTURING COMPANY 8550 MOSLEY DRIVE HOUSTON, TEXAS 77075 USA PHONE (713) 944-6900 FAX (713) 947-4453 www.powellelectric.com

More information

INSTALLATION INSTRUCTIONS

INSTALLATION INSTRUCTIONS LIGHTING CONTROL PANELS 4 AND 8 RELAYS INSTALLATION INSTRUCTIONS INSTALLATION OVERVIEW The installation instructions contained in this document are provided as a guide for proper and reliable installation.

More information

Summary of Preliminary Assessment on Structural, Fire and Electrical Safety

Summary of Preliminary Assessment on Structural, Fire and Electrical Safety Name of the Factory Address of the Factory Present Status of the Factory Structural Assessment Conducted by : Galaxy Stitch Ltd. : BSCIC Industrial Estate, Plot no. A102, Tongi Gazipur Bangladesh : Under

More information

HIGH VOLTAGE SHORE CONNECTION

HIGH VOLTAGE SHORE CONNECTION Guide for High Voltage Shore Connection GUIDE FOR HIGH VOLTAGE SHORE CONNECTION NOVEMBER 2011 American Bureau of Shipping Incorporated by Act of Legislature of the State of New York 1862 Copyright 2011

More information

Ontario Electrical Safety Code 25 th Edition/ 2012

Ontario Electrical Safety Code 25 th Edition/ 2012 Ontario Electrical Safety Code 25 th Edition/ 2012 Ted Olechna Director, Codes and Standard Chief Engineer 1 What I Will Cover ESA s role is as the regulator Highlight of 2012 Code changes The Code and

More information

270526-TC Grounding and Bonding for Telecommunications Systems

270526-TC Grounding and Bonding for Telecommunications Systems 270526-TC Grounding and Bonding for Telecommunications Systems Part 1 - General Related Documents The following related sections of the OT standards shall also be applicable to this section. OT Engineer

More information

RCD Inspection Log Book

RCD Inspection Log Book RCD Inspection Log Book This book is the property of: Commenced: / /. Completed: / /. 2 Clipsal Australia Pty Ltd Clipsal Australia Pty Ltd 3 4 Clipsal Australia Pty Ltd Clipsal Australia Pty Ltd 5 6 Clipsal

More information

SECTION 11 78 13 MORTUARY REFRIGERATORS

SECTION 11 78 13 MORTUARY REFRIGERATORS PART 1 - GENERAL 1.1 DESCRIPTION SECTION 11 78 13 MORTUARY REFRIGERATORS SPEC WRITER NOTE: Delete between //---// if not applicable to project. Also delete any other item or paragraph not applicable in

More information

PROTECTION AGAINST ELECTRIC SHOCK by John Ware

PROTECTION AGAINST ELECTRIC SHOCK by John Ware 16 become live under fault conditions. The potential of the metal enclosure is higher than that of the main earthing terminal of the installation (and that of Earth) because of a potential difference created

More information

REB 1 REB 3 REB 5 REB 6 REB 8 REB 10 REB 12 REB 16

REB 1 REB 3 REB 5 REB 6 REB 8 REB 10 REB 12 REB 16 REB 1 REB 3 REB 5 REB 6 REB 8 REB 10 REB 12 REB 16 Manually Operated Electronic Speed Controller Single Phase For all applications using suitably specified single-phase induction motor fans 1 GENERAL The

More information

INTRODUCTION. The data provided is for The Standard Products and any variation will be dealt with at the end of this manual.

INTRODUCTION. The data provided is for The Standard Products and any variation will be dealt with at the end of this manual. INTRODUCTION The information provided herein covers the range of products known as the 'Sensor 901' series. The range of equipment is designed to meet the requirements of BS 5839 parts 1 & 4 1988. The

More information

ELECTRICIAN TRADE REGULATION

ELECTRICIAN TRADE REGULATION Province of Alberta APPRENTICESHIP AND INDUSTRY TRAINING ACT ELECTRICIAN TRADE REGULATION Alberta Regulation 274/2000 With amendments up to and including Alberta Regulation 122/2014 Office Consolidation

More information

AMFA-27 AMFA-29. Operator s Manual & Installation Instructions. Rev. 2.5

AMFA-27 AMFA-29. Operator s Manual & Installation Instructions. Rev. 2.5 AMFA-27 AMFA-29 Operator s Manual & Installation Instructions Rev. 2.5 Date: 17 July, 2010 Permanently-connected, utility Interactive, single-phase, inverters Model AMFA-27 WIND TURBINE INVERTER (240 VAC

More information

Electrical Safety Tester Verification

Electrical Safety Tester Verification Ensuring Validity of Regulatory Tests Verification of electrical safety testing equipment is a procedure that is often overlooked by manufacturers. Running test verification is crucial to ensuring that

More information

SELECTION OF FINAL CIRCUIT PROTECTION

SELECTION OF FINAL CIRCUIT PROTECTION SELECTION OF FINAL CIRCUIT PROTECTION By Phil Williams, Product Marketing Manager, Power Distribution Components, Eaton Executive summary The selection of devices for final circuit protection in electrical

More information

Bold items are particular to the City of Euless

Bold items are particular to the City of Euless EULESS FIRE DEPARTMENT FIRE MARSHAL S OFFICE INFORMATION LINE: Revised 2/12 Fire Chief Wes Rhodes Fire Marshal Paul Smith EFD-FMO 3-2 2009 International Fire & Building Code as Amended NFPA Standards Adopted

More information

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Metering and Monitoring. Basis of Design

UNIVERSITY OF WASHINGTON Facilities Services Design Guide. Electrical. Metering and Monitoring. Basis of Design Basis of Design This section applies to the design, installation and integration of metering and monitoring equipment, including: hardware installed in the electrical service and distribution equipment,

More information

FIRE ALARM SYSTEM. A. Shop drawings shall be submitted as follows: 1. Manufacturer's published literature. for aspproval.

FIRE ALARM SYSTEM. A. Shop drawings shall be submitted as follows: 1. Manufacturer's published literature. for aspproval. Polk School District Specifications for the New Fire Alarm in the Existing Building Eastside Elementary School FIRE ALARM SYSTEM 1.01 SUBMITTALS A. Shop drawings shall be submitted as follows: 1. Manufacturer's

More information

TAMARAC FIRE RESCUE INSTRUCTIONS FOR FIRE ALARM PRE-SUBMITTAL CHECKLIST

TAMARAC FIRE RESCUE INSTRUCTIONS FOR FIRE ALARM PRE-SUBMITTAL CHECKLIST TAMARAC FIRE RESCUE INSTRUCTIONS FOR FIRE ALARM PRE-SUBMITTAL CHECKLIST In order to provide a comprehensive plan review in a timely manner, and to insure the design and installation of fire alarm systems

More information

DTW Works Master Specification Version 2006

DTW Works Master Specification Version 2006 Issued 2006/08/01 Section 13852 Multiplex Fire Alarm System Page 1 of 10 PART 1 GENERAL 1.1 RELATED WORK.1 Section 01330 Submittal Procedures..2 Section 01780 Closeout Procedures..3 Section 01810 Commissioning..4

More information

C. Conform to requirements of Americans with Disabilities Act (ADA).

C. Conform to requirements of Americans with Disabilities Act (ADA). SECTION 28 31 00 - FIRE ALARM AND DETECTION SYSTEMS PART 1 - GENERAL 1.1 SECTION INCLUDES A. Fire alarm and detection systems 1.2 REFERENCES A. NFPA 70 - National Electrical Code B. NFPA 72 - National

More information

A Guide to 17th Edition Testing

A Guide to 17th Edition Testing Seaward, Bracken Hill, South West Industrial Estate, Peterlee, County Durham, SR8 2SW United Kingdom Tel: +44 (0) 191 586 3511 Fax: +44 (0) 191 586 0227 Email: sales@seaward.co.uk Web: www.seaward.co.uk

More information

CalMod Design-Build Electrification Services

CalMod Design-Build Electrification Services SECTION 28 16 00 INTRUSION DETECTION SYSTEM PART 1 - GENERAL 1.1 DESCRIPTION A. This section describes the detailed technical requirements for the Intrusion Detection System (IDS), where the Contractor

More information

SECTION 26 29 23 VARIABLE FREQUENCY DRIVES

SECTION 26 29 23 VARIABLE FREQUENCY DRIVES SECTION 26 29 23 VARIABLE FREQUENCY DRIVES PART 1 GENERAL 1.01 SCOPE A. Furnish and install individual freestanding variable frequency AC drives (VFD) as shown on the Drawings and specified herein. 1.02

More information

FIRE ALARM SYSTEM TECHNICAL SPECIFICATIONS Page 1 of 10

FIRE ALARM SYSTEM TECHNICAL SPECIFICATIONS Page 1 of 10 TECHNICAL SPECIFICATIONS Page 1 of 10 FIRE DETECTION AND ALARM SYSTEM Scope Furnish a complete 24V DC conventional, electrically supervised, zone annunciated, fire detection and alarm system as specified

More information

Maintenance Report MEDIUM VOLTAGE POWER STATION 500SC / 630SC / 800SC / 900SC / 1000 1SC / 1000 2SC / 1250SC / 1600SC / 1800SC / 2000SC

Maintenance Report MEDIUM VOLTAGE POWER STATION 500SC / 630SC / 800SC / 900SC / 1000 1SC / 1000 2SC / 1250SC / 1600SC / 1800SC / 2000SC Maintenance Report MEDIUM VOLTAGE POWER STATION 500SC / 630SC / 800SC / 900SC / 1000 1SC / 1000 2SC / 1250SC / 1600SC / 1800SC / 2000SC Project name: Customer: Address, location of the system: Serial number

More information