WILTON 110 kv BUS RATIONALISATION. Stakeholder Information. December 2012

Size: px
Start display at page:

Download "WILTON 110 kv BUS RATIONALISATION. Stakeholder Information. December 2012"

Transcription

1 WILTON 110 kv BUS RATIONALISATION Stakeholder Information December 2012

2 1 Executive Summary This information paper provides an update to all interested parties and stakeholders as to the current status of the Wilton Bus investigation and its conclusions. The existing 110 kv bus configuration at Wilton substation means the loss of a bus section will require load to be shed at Central Park. This arrangement does not meet the Grid Reliability Standards (GRS) 1. We are required to identify places where the GRS is not met and propose investments to ensure the GRS is met.. In April 2012 we submitted a draft long list of possible options to meet GRS requirements at Wilton substation for consultation. After considering the feedback to that consultation, we finalised the long list of options. Screening criteria was applied to the long list to reduce it to a short list of options to which the Investment Test (IT) 2 was applied.. The economic analysis demonstrated that the most economic solution to address this need is to reconfigure the Wilton 110 kv bus into three bus sections at a cost of between $2 and $3 million 3. When we started this investigation, there was a possibility that the enhancement and development component of the preferred option would exceed the base capex programme threshold 4 of $5 million and thus require a major capex proposal (MCP) to be submitted to the Commerce Commission. However, given the required enhancement and development capex is well below that threshold, we will not be submitting an MCP to the Commerce Commission. 1 The GRS is Schedule 12.2 of Part 12 of the Electricity Industry Code, available at p87 2 Under the Capex IM (Schedule D), to satisfy the Investment Test a proposed investment must maximise expected net electricity market benefit 3 This cost is based on high level estimates of three very similar options, the scope and cost of which will be better defined through a solution study report. 4 The base capex programme threshold is currently $5 million, Part 1, Capex IM 2

3 Contents 1 Executive Summary The Need Description of the existing system Meeting the GRS - Grid Reliability Standards and Core Grid Determination Wilton 110 kv configuration Planned replacement and refurbishment on 110 kv bus to mitigate corrosion Assumptions Forecast electricity demand Existing generation New generation Options The Options Selecting the investment proposal Application of the Investment Test The Costs Reasons project is no longer a MCP Next Steps

4 2 The Need The existing 110 kv double bus arrangement at Wilton has two bus sections which means that one 110 kv bus section has two of the three Central Park Wilton circuits connected to it.. In the event of a fault on that 110 kv bus section, the transmission capacity into Central Park is reduced to the one circuit on the Central Park Wilton-A line. This arrangement does not meet the GRS. The GRS 5 requires that the grid remains in a satisfactory state during and following a single credible contingent event on the core grid. A Wilton 110 kv bus section outage meets the definition of a single credible contingent event on the core grid. Under this event, the transmission line ratings on the remaining Central Park-Wilton circuit are limited to 174 MVA (when Summer ratings apply), 183 MVA (Shoulder) and 191 MVA (Winter). While variable line rating (VLR) and dynamic line rating (DLR) 6 may extend the ratings during these periods, the demand at Central Park is forecast to exceed these limits. Current forecasts have the load at Central Park growing by approximately 4 MW per annum to 260 MW by Description of the existing system The Wellington regional transmission network of interest is shown in Figure 2-1. The Wilton 110 kv bus is supplied by a single 220/110 kv 250 MVA interconnecting transformer (T8) and two circuits from Takapu Road. A double-circuit 220 kv line from Bunnythorpe supplies the Wilton 220 kv bus, which in turn supplies the Wilton 110 kv bus via an interconnecting transformer, and also the Wilton 33 kv bus via two 220/33 kv 100 MVA supply transformers (T3 and T5). The Central Park and Kaiwharawhara substations, which feed the Wellington CBD, are supplied directly from Wilton. As such, Wilton is a key substation in the Wellington region. 5 The GRS is Schedule 12.2 of Part 12 of the Electricity Industry Code, available at p87 6 Transpower has been progressing trials of VLR and DLR in some parts of the grid and intends to implement these ratings methodologies sometime in the next 5-10 years grid wide as part of its Transmission Tomorrow plan. 4

5 Figure 2-1: Wellington regional transmission network detailing the 220 kv and 110 kv transmission connections at Wilton substation Takapu Road Bunnythorpe 220 kv 33 kv Wilton Kaiwharawhara 11 kv 110 kv 11 kv Central Park 220kV CIRCUIT 110kV CIRCUIT SUBSTATION BUS TRANSFORMER LOAD UNDERGROUND CABLE West Wind 33 kv There are currently three 110/33 kv transformers at Central Park (see Table 2-1). T3 and T4 are both expected to be replaced and upgraded in the near future. Table 2-1: 110/33 kv Transformer parameters at Central Park Year of manufacture Winter Shoulder Summer T MVA 109 MVA 112 MVA T MVA 108 MVA 112 MVA T MVA 146 MVA 147 MVA Each of the 110/33 kv transformers at Central Park are directly connected to one of the Central Park Wilton 110 kv circuits. This means that for a 110 kv bus section outageat Wilton, demand at Central Park will be limited to the capacity of a single transformer, and significant load reduction will be required to avoid overloading this transformer. In this regard, the present 110 kv bus arrangement at Wilton does not meet the GRS. 5

6 Figure 2-2: Central Park n-1 supply security for a Wilton 110 kv bus section fault CPK 2012 Demand Duration Curve (MW vs hours) CPK 2012 MW CPK N 1 Load at risk Figure 2-2 illustrates the amount of load at risk following a bus section fault at Wilton. The blue line represents the Central Park 33 kv and 11 kv expected forecast 2012 load duration curve and the red line shows the maximum capacity suppliable from Central Park following a bus section outage at Wilton. The distance between the blue line and red line indicates the amount of load needing to be managed for the loss of two Central Park Wilton circuits following a bus section fault at Wilton. Even under a low load growth scenario, the Wilton 110 kv bus configuration does not meet the Grid Reliability Standards (GRS). 2.2 Meeting the GRS - Grid Reliability Standards and Core Grid Determination The core grid is defined in Schedule 12.3 of the Electricity Industry Participation Code (EIPC) The 110 kv circuits into Wilton from Takapu Road and onto Central Park are all presently defined as core grid elements. So by inference, the 220/110 kv interconnecting transformer and 110 kv bus at Wilton are also core grid elements. If a single credible contingency event 8 were to occur on the core grid, which includes a bus section outage 9, the power system has to remain in a satisfactory state. Under the present configuration at Wilton, the power system will not remain in a satisfactory state following a single credible contingency event, as unacceptable overloading of...primary transmission equipment can occur for a 110 kv bus section outage at Wilton and/or there will be insufficient supply of electricity to satisfy demand. 7 Available at 8 EIPC 2010 Part 1, Schedule 12.2 clause 2 (2)(b) 9 See pg 60 of the EIPC 2010 Part 1, available at 6

7 2.3 Wilton 110 kv configuration The Wilton 110 kv switchyard, illustrated in Figure 2-3 consists of seven bays including a spare bay. It is fed by two circuits from Takapu Road and the 220/110 kv interconnecting transformer - T8. Wilton supplies Central Park and Kaiwharawhara substations via five 110 kv circuits. West Wind generation tees into the Central Park Wilton 2 and 3 circuits. Both the Wilton 110 kv top and bottom busbars and disconnectors are all rated at 1600 A. Figure 2-3: Wilton 110 kv switchyard configuration 2.4 Planned replacement and refurbishment on 110 kv bus to mitigate corrosion The majority of componentry in the Wilton 110 kv bus date from Condition Assessment reports have identified over half of the equipment at Wilton needs to be replaced or refurbished to maintain the Wilton 110 kv switchyard over the next 10 years. We have already had funding budgeted for this work in our base capex allowance 10 which is approved by the Commerce Commission for Transpower expenditure. 10 Clause 1.1.5(2) of Part 1 of the Capex IM 7

8 3 Assumptions 3.1 Forecast electricity demand The forecast demand of the Central Park GXP that Wilton directly supplies is based on the 2012 Annual Planning Report 11. The after diversity maximum demand (ADMD) for the Wellington region is forecast to grow on average by 1.4% annually over the next 15 years, from 756 MW in 2012 to 934 MW by This is lower than the national average demand growth of 1.7% annually. Table 3-1 is an extract from Transpower s 2012 Annual Planning Report and shows prudent forecast 12 annual peak demand (MW) for selected Wellington grid exit points to Table 3-1: Demand forecast of Wellington region GXPs Grid exit point Power Peak demand (MW) factor Next 5 years 5-15 years out Central Park 11 kv Central Park 33 kv Existing generation West Wind wind power station (installed capacity: 143 MW) is connected into the Central Park Wilton 110 kv circuits. West Wind has historically been required to be constrained-off during certain maintenance outages at the Wilton site. In addition to West Wind, there is embedded generation into Central Park. Table 3- details the predicted forecast generation capacity (directly affecting the Wilton, Central Park and Kaiwharawhara GXPs) to 2027 which may affect the Wilton 110 kv bus. 11 Available at 12 Our prudent peak forecasts can be interpreted as representing a 10% probability of exceedance (POE) forecast until 2017 and then are assumed to grow at an expected rate. In other words, in the first five years one would expect actual demand to exceed the forecast in one year out of ten. We consider this is an appropriate basis on which to conduct our planning. 8

9 Table 3-2: Forecast annual generation capacity (MW) that may affect Wilton 110 kv Grid injection point (location if embedded) Central Park (Southern Landfill) Central Park (Wellington Hospital) Next 5 years Generation capacity (MW) 5-15 years out West Wind New generation Following previous consultations, we considered it reasonable to conduct the analysis on the basis that no new generation is connected in the area. The Statement of Opportunities (SoO) predicts little generation for the Wellington region Mill Creek (60 MW) and Long Gully (12.5 MW). While new generation may affect transmission capacity and fault levels in the region, any new generation will not resolve issues associated with the loading of the Central Park transformers. 13 Available at 9

10 4 Options 4.1 Long list options A long list of possible options was developed and consulted on in April The draft long list of options included five broad development options to meet the need: Option 1: Wilton solution including a 3-section bus Option 2: Bus at Central Park, 2- section bus at Wilton Option 3: Up-Rating Kaiwharawhara and/or Wilton GXPs and load transfer from Central Park Option 4: A new Wellington GXP and load transfer from Central Park Option 5: New Transmission including new 110 kv circuit(s) between Kaiwharawara and Central Park, and cross-harbour 110 kv circuit(s) to Central Park Five submissions were received to the draft long list of options, a summary of which can be found at There was general agreement that investment is required to not only meet the GRS but also for commercial, economic and regional development reasons. Wellington City Council outlined their request for resilience and redundancy to be built into the network. They also drew attention to the importance of electricity services as demonstrated by the loss of supply during the Canterbury earthquakes. Further option variants of option 1 (1a and 1b) and option 2 (2b, 2c, 2e, and 2f) were identified through the consultation stage and were added to the long list of options. Our final Long List of options is shown in Table 4-1. We also included the screening criteria that would be used on the long list of options in the April consultation and this is shown below. This criteria has been applied to eliminate those options that are not appropriate for consideration in the short list of options to which we apply the Investment Test. The short-listing criteria applied are as follows: A. Fit for purpose The design will assist meeting future energy demand growth The extent to which the option resolves the relevant issue. B. Technically feasible Complexity of option Reliability, availability and maintainability of the option Is this proven technology (ie. used commercially, internationally and/or with available data on performance, and expected life cycle)? Does Transpower have experience with the technology?

11 Is there a low level of risk associated with implementing this technology (such as on-going maintenance requirements and availability of after sales support and spare parts)? Future flexibility - Grid Development Strategy To what extent does the option open up or foreclose future development options? Could the investment be stranded under certain conditions? C. Practicability of implementing the option It must be possible to implement the solution by the required dates (probability of proceeding) How long will it take to implement this option? Consideration includes: Property acquisition time Likelihood of gaining required environmental approvals Equipment lead time Time taken to build Implementation risks, including potential delays due to property and environmental issues Are there technical issues with access or available space for the works? Implementation risks, eg. are outage constraints on the existing system going to impact on this option? The availability of proponent for or potential counterparty to a transmission alternative D. Good electricity industry practice (GEIP) 15 Ensure safety Consistent with good international practice Minimise or mitigate environmental impacts Accounts for relative size, duty, age and technological status Manage technology risks E. System security (additional benefit resulting from an economic investment) Improved system security System Operator benefits (controllability) Does the option provide operational flexibility? F. Indicative cost Whether an option will clearly be more expensive than another option with similar or greater benefits The cost estimates, if used, are high level. Any option that does not meet one or more of the criteria was removed from further consideration. The overall assessment is indicated by a or above. 15 refer Part 1 of the Electricity Industry Participation Code 11

12 Table 4-1: Long list and summary of short-listing 1a 1b 1c 1d 1e 1f 1g 2a 2b 2c 2d 2e 2f 3 Option No options presented Short- Listed? Criteria Failure Reference Non-Transmission Solutions Transmission solutions optimisation of existing assets Reason There is no economic solution which could meet the need Three section (AIS) bus at Wilton using conventional circuit breakers Three section (AIS) bus at Wilton using Hypact disconnecting circuit breakers Three section (AIS) bus at Wilton with top bus retained as maintenance bus Three section Gas Insulated Switchgear (GIS) bus at Wilton F Too costly Three section Hybrid Insulated Switchgear (HIS) bus at Wilton F / B Too costly and wrong environment Modern three section Air Insulated (AIS) Bus at Wilton F Too costly. Modern Beaker and a half Air Insulated (AIS) Bus at Wilton F Too costly and insufficient space Two section (AIS) bus at Wilton a 110kV bus and two replacement 160MVA transformers at Central Park Modern three section airinsulated (AIS) bus at Central Park substation with two large F / B Too costly and not technically feasible 270MVA transformers Modern three section GIS/HIS bus at Central Park substation F Too costly Three new 180MVA transformers at Central Park F Too costly 1x 120MVA and 2x 270MVA replacement transformers at Central Park F / B Too costly Four new 120MVA transformers at Central Park F Too costly Up Rating Kaiwharawhara and/or Wilton GXPs F Transmission solutions new assets on new land Too costly (when considering 33kV local network costs alone) 4 A New Wellington GXP F Too costly 5a 5b Transmission solutions additional transmission circuits New 110 kv circuit(s) between Kaiwharawhara and Central Park F Cross Harbour 110 kv circuit(s) to Central Park F Too costly (even when costing the minimal capacity to meet GRS) Too costly (even when costing the minimal capacity to meet GRS) NB. When an option is not progressed due to being too costly the option was significantly more expensive than the options that were short listed. 12

13 4.2 Short list development plans All options will eventually result in the need for future investment at both Wilton and Central Park to meet the GRS. This is because, even with enhancements at Wilton in the near future, additional transformer capacity is needed at Central Park so the load can be supplied with one bus section and one transformer out-of-service. To enable us to compare the investment options on a consistent whole of life basis, a 20 year development path was developed for each option considering the investment requirements at both Wilton and Central Park. The five short-listed development plan options are shown Table 4-2 below. Table 4-2: Short-listed development plan options Investments required in each development plan option Option a 1b(i) 1c 2a Wilton 3 section bus (conventional circuit breakers) Wilton 3 section bus (disconnecting circuit breakers) Hypact Wilton 3 section bus (maintenance bus) Wilton 2 section bus 2x180MVA replacement transformers at Central Park 2x180MVA replacement transformers at Central Park 2x180MVA replacement transformers at Central Park New 110kV Bus at Central park + 2x replacement 160MVA transformers at Central Park Our economic analysis determines the total cost of each development plan out to 2035, using the capital costs for each element in the plan, the resultant operating and maintenance costs and other cost differences as detailed in section 5.2. The costs are then discounted to a present value and the option with the lowest present value cost 16 satisfies the Investment Test. 16 Under the Capex IM, to satisfy the Investment Test a proposed investment must maximise expected net electricity market benefit. Our lowest cost approach is the same and is used for ease of presentation. 13

14 5 Selecting the investment proposal Under the Capex Investment Methodology (IM), to satisfy the Investment Test, a proposed investment must have a positive expected net electricity market benefit unless it is required to meet the deterministic limb of the grid reliability standards. Investment in the Wilton 110 kv bus falls into the latter category. For presentation purposes, all costs and benefits are shown here as costs. This simplifies the presentation and does not affect the result. The least-cost option passes the Investment Test. This produces exactly the same outcome as calculating expected net market benefit. 5.1 Application of the Investment Test We applied the Investment Test to the development plan for each of the five short list options. 5.2 The Costs The cost of the five short listed options are the costs incurred for the entire development plan, including: Capital costs The expected capital costs to install and commission each element of the development plan. Operating and maintenance costs The relative on-going operating and maintenance costs of the capital equipment i.e. some options will result in reduced operation and maintenance costs and this has been factored into the analysis. Cost of demand curtailment during maintenance The value of expected unserved energy taking into account the probability of fault during maintenance. Even with a reliable and resilient network there is still some chance of loss of supply. We cost this at the value of unserved energy, $24,200/MWh 17. The costs above have been combined for each development plan and a total expected cost for each option has been calculated and are shown in Table 5-1. The third column shows the expected cost of each development plan option out to 2035, expressed as a Present Value (PV) to account for phasing of the required works. The final column shows the difference in costs between the options, relative to Option 1a (the cheapest capital cost option that will meet the deterministic GRS) which has been used as a reference case. 17 $20,000/MWh in 2004 inflated to 2011 as per our April 2012 consultation 14

15 Table 5-1: Development plan net market costs (Present Value 2012 $m) Option Description Present Value Present Value Relative Expected Expected costs costs (2012 $m) (2012 $m) 1a Three section bus at Wilton conventional circuit breakers (2017) and 2x180MVA replacement transformers at Central Park (2018) 1b Three section bus at Wilton Hypact disconnecting circuit breakers (2017) and 2x180MVA replacement transformers at Central Park (2018) 1c Three section bus at Wilton with maintenance bus (2017) and 2x180MVA replacement transformers at Central Park (2018) 2a Two section bus at Wilton (2017) and 110kV bus at Central Park and 2x160MVA replacement transformers (2018) As can be seen in Table 5-1 a three section bus option at Wilton is the most economic (i.e. least cost) option for solving the deterministic GRS, and is significantly cheaper than installing a new bus at Central Park. However, the cost differences between the three section bus solutions are relatively small (within $1m). 15

16 6 Reasons project is no longer a MCP There is nearly $5 million of condition-based refurburbishment work on the Wilton 110 kv bus planned over the next few years and this is included in our base capex allowance 18. This project is for the additional enhancement work (see Table 6-1) to meet the GRS. The total enhancement cost is approximately $2 $3 million dollars. For an investment to be an major capital proposal (MCP) 19 the expected cost of the enhancement component of the investment must be more than $5 million 20. As this project is less than $5 million, Transpower will fund the project through its base capex allowance. Table 6-1: Enhancement comparison net market costs of preferred three section Wilton option Option Total Expected Costs Relative Enhancement Component ($m) ($m) Planned Wilton 2 section bus : refurbishment/replacements due to Replacements condition a Wilton 3 section bus (conventional circuit breakers) b Wilton 3 section bus (disconnecting circuit breakers) Hypact c Wilton 3 section bus (maintenance bus) Base capex means capital expenditure incurred in relation to asset replacement, asset refurbishment, business support, and information system and technology assets 19 A major capex proposal is defined as a document identifying a proposed investment for which Commission approval is sought 20 Part 1 of the Capex IM, base capex programme threshold has the [combine footnotes here, bcpt reference, currently $5million] 16

17 7 Next Steps From our investigation, having three bus sections on the 110 kv bus at Wilton is the best option to address the GRS issue of 110 kv supply to Central Park. As the high level cost estimates for the different equipment solutions are very similar we intend to scope and cost each at a higher level of detail before settling on the final detailed option. We will fund this project through our base capex allowance. 17

16 West Coast Regional Plan

16 West Coast Regional Plan 16 West Coast Regional Plan 16.1 Regional overview 16.2 West Coast transmission system 16.3 West Coast demand 16.4 West Coast generation 16.5 West Coast significant maintenance work 16.6 Future West Coast

More information

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited

COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN. Top Energy Limited PB ASSOCIATES COMPLIANCE REVIEW OF 2006/07 ASSET MANAGEMENT PLAN Prepared for PB Associates Quality System: Document Identifier : 153162 Top Energy Final Report Revision : 2 Report Status : Final Date

More information

Cost Benefit Methodology for Optimal Design of Offshore Transmission Systems

Cost Benefit Methodology for Optimal Design of Offshore Transmission Systems Centre for Sustainable Electricity and Distributed Generation Cost Benefit Methodology for Optimal Design of Offshore Transmission Systems Predrag Djapic and Goran Strbac July 2008 FUNDED BY BERR URN 08/1144

More information

2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology

2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology 2017 19 TasNetworks Regulatory Proposal Expenditure Forecasting Methodology Version Number 1 26 June 2015 Tasmanian Networks Pty Ltd (ACN 167 357 299) Table of contents 1 Introduction... 1 2 Meeting our

More information

RCP2 Portfolio Overview Document

RCP2 Portfolio Overview Document RCP2 Portfolio Overview Document Portfolio: Expenditure Class: Base Capex Expenditure Category: Grid Replacement & Refurbishment As at date: 15 November 2013 Expenditure Forecast Real 2012/13 NZ$ (m) 2015-2016

More information

Security Policy Review: Credible Event Management. Scope and Methodology Draft for Industry 2014

Security Policy Review: Credible Event Management. Scope and Methodology Draft for Industry 2014 Security Policy Review: Credible Event Management Scope and Methodology Draft for Industry 2014 Version Date Change 1 26/03/2014 Draft for industry Position Date Prepared By: Reviewed By: Ina Ilieva, Senior

More information

NTTG Study Plan for the 2014-2015 Public Policy Consideration Scenario

NTTG Study Plan for the 2014-2015 Public Policy Consideration Scenario NTTG Study Plan for the 2014-2015 Public Policy Consideration Scenario Table of Contents NTTG Study Plan for the 2014-2015 Public Policy Consideration Scenario Table of Contents... 2 1. Executive Summary...

More information

Lifecycle Strategy DISPOSAL AND DIVESTMENT

Lifecycle Strategy DISPOSAL AND DIVESTMENT Lifecycle Strategy DISPOSAL AND DIVESTMENT Document 07/10/2013 Page 1 of 19 C O P Y R I G H T 2013 T R A N S P O W E R N E W Z E A L A N D L I M I T E D. A L L R I G H T S R E S E R V E D This document

More information

Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055

Generation Interconnection Feasibility Study Report-Web Version. PJM Generation Interconnection Request Queue Position Z1-055 Generation Interconnection Feasibility Study Report-Web Version For PJM Generation Interconnection Request Queue Position Z1-055 South Bend Generation Project March 2014 PJM Interconnection 2014. All rights

More information

QUALITY CONTROL Prepared: V. van Gastel / team TenneT Reviewed: M. Müller 23.06.2015 Approved: F. Wester 23.06.2015 1. BACKGROUND MATERIAL...

QUALITY CONTROL Prepared: V. van Gastel / team TenneT Reviewed: M. Müller 23.06.2015 Approved: F. Wester 23.06.2015 1. BACKGROUND MATERIAL... POSITION PAPER STAKE HOLDER CONSULTATION PROCESS OFFSHORE GRID NL Type: Position paper Work stream Technical Topic: T.2 Number of J-Tubes Filename ONL 15-060-T2_ J tubes_ bays_pp_v2 Version 3 - Public

More information

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD

SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD SOUTHERN MARYLAND ELECTRIC COOPERATIVE, INC. HUGHESVILLE, MD HOLLAND CLIFF HEWITT ROAD 230 KV TRANSMISSION LINE PROJECT ELECTRIC ALTERNATIVE EVALUATION STUDY BLACK & VEATCH CORPORATION B&V Project 146026(G)

More information

Understanding the Auckland electricity network

Understanding the Auckland electricity network Understanding the Auckland electricity network Introduction This presentation describes how electricity reaches homes and businesses in Auckland, with a particular focus on the distribution network run

More information

Kent Active System Management (KASM) Oct 2015 / Matthieu Michel

Kent Active System Management (KASM) Oct 2015 / Matthieu Michel Kent Active System Management (KASM) Oct 2015 / Matthieu Michel Project Background (update): D Heat Map: SPN D Connection Offers Accepted (Cumulative) 1W D Heat map (June 2015) SPN D Connection Offers

More information

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015

SHE Transmission. 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 SHE Transmission 2015_10_30 Transmission Losses Strategy Rev 2.0 October 2015 Summary This paper presents SHE Transmission s views and approach on the impact of transmission losses on the transmission

More information

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission PLC, Scottish Hydro Electric Transmission Limited TABLE OF CONTENTS 1.0 Purpose and Scope...2 1.1 Methodology Purpose...2 2.0

More information

Actual capital expenditure during the current regulatory period. Project summary

Actual capital expenditure during the current regulatory period. Project summary 1 Actual capital expenditure during the current regulatory period. Project summary This document provides a summary of the capital expenditure on large capital projects during the current regulatory period.

More information

2006 Report. of the. Optimised Deprival Valuation of Transpower s System Fixed Assets. as at 30 June 2006

2006 Report. of the. Optimised Deprival Valuation of Transpower s System Fixed Assets. as at 30 June 2006 T R A N S P O W E R N E W Z E A L A N D L I M I T E D 2006 Report of the Optimised Deprival Valuation of Transpower s System Fixed Assets as at 30 June 2006 Prepared by Transpower New Zealand Limited Reviewed

More information

TenneT. Stakeholder engagement and Consultation Process OWFs. Day 1 ONL 15-162. Michiel Müller / Rob van der Hage

TenneT. Stakeholder engagement and Consultation Process OWFs. Day 1 ONL 15-162. Michiel Müller / Rob van der Hage TenneT ONL 15-162 Stakeholder engagement and Consultation Process OWFs Day 1 Expert Meeting, 15-16.04.2015, Arnhem Michiel Müller / Rob van der Hage Stay tuned. Safety first! Voor uw en onze veiligheid

More information

Proceedings of the 38th Hawaii International Conference on System Sciences - 2005

Proceedings of the 38th Hawaii International Conference on System Sciences - 2005 The use of Multi-Attribute Trade-Off Analysis in Strategic Planning For an Electric Distribution utility: An Analysis of Abu Dhabi Distribution Company Richard D. Tabors, Ph.D. Rick Hornby Tabors Caramanis

More information

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited

NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited NETWORK OUTPUT MEASURES METHODOLOGY Authors: National Grid, SP Transmission Limited, Scottish Hydro Electric Transmission Limited TABLE OF CONTENTS 1.0 Purpose and Scope...2 1.1 Methodology Purpose...2

More information

Asset Management Plans

Asset Management Plans November 213 Introduction Table of Contents Page # ACS Buildings & Grounds 2 Purpose and Scope ACS Buildings & Seismic 3 The purpose of these ( Plans ) is to demonstrate how we intend to deliver on the

More information

Submission on the Draft Electricity Demand and Generation Scenarios

Submission on the Draft Electricity Demand and Generation Scenarios From the Electricity Networks Association Submission on the Draft Electricity Demand and Generation Scenarios Submission to the Ministry of Business, Innovation and Employment 15 May 2015 The Electricity

More information

NETWORK OUTPUT MEASURES CONSULTATION

NETWORK OUTPUT MEASURES CONSULTATION NETWORK OUTPUT MEASURES CONSULTATION Great Britain s electricity transmission network transmits high-voltage electricity from where it is produced to where it is needed throughout the country. It broadly

More information

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe

ESB Networks Response. ERGEG Consultation. Voltage Quality Regulation in Europe NETWORKS ESB Networks Response to ERGEG Consultation on Voltage Quality Regulation in Europe Date: 22 February 2007 Distribution System Operator ESB Networks Page 1 of 12 Contents 1.0 INTRODUCTION...3

More information

ICM Project Station Infrastructure and Equipment

ICM Project Station Infrastructure and Equipment EB 0 00 Schedule B. ( pages) ICM Project Station Infrastructure and Equipment (THESL) EB 0 00 Schedule B. I EXECUTIVE SUMMARY 0. Project Description Many Municipal Substations (MS) located outside of downtown

More information

CITY OF GLENDALE CALIFORNIA REPORT TO CITY COUNCIL

CITY OF GLENDALE CALIFORNIA REPORT TO CITY COUNCIL FORM CM-36 CITY OF GLENDALE CALIFORNIA REPORT TO CITY COUNCIL February 7,2012 AGENDA ITEM Request for Approval to Issue a Request for Qualification (RFQ) of Firms, and Request for Proposal (RFP) to Engineer,

More information

ABB s Disconnecting Circuit Breakers Higher substation availability and lower environmental impact

ABB s Disconnecting Circuit Breakers Higher substation availability and lower environmental impact ABB s Disconnecting Circuit Breakers Higher substation availability and lower environmental impact Authors Carl Ejnar Sölver, ABB High Voltage Products Rasmus Larsson, ABB High Voltage Products 2 ABB ABB

More information

Executive summary 2. 1 Introduction 4

Executive summary 2. 1 Introduction 4 Flexible Networks for a Low Carbon Future Future Network Monitoring Strategy September 2015 Contents Executive summary 2 Glossary 3 1 Introduction 4 2 Fundamental principles of monitoring 5 2.1 LCT monitoring

More information

ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1

ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1 ES281 COMPANY-SPECIFIC APPENDICES TO ENA ENGINEERING RECOMMENDATION G81 PART 1 Design and Planning Specification for New Low Voltage Installations for Housing Developments 1. SCOPE This appendix to ENA

More information

Non-Network Options Report

Non-Network Options Report Non-Network Options Report Kangaroo Island Submarine Cable 12 April 2016 SA Power Networks www.sapowernetworks.com.au Disclaimer This Non-Network Options Report has been prepared in accordance with Clause

More information

RELIABILITY PLANNING CRITERIA

RELIABILITY PLANNING CRITERIA RELIABILITY PLANNING CRITERIA Version 4.0 01/20/2016 Date Rev. No. Individual Making Edits REVISION HISTORY Reason / Comments 07/01/2013 1 J. Johnson Initial document 06/06/2014 2 R. Chapman Document review;

More information

Electricity Distribution Price Control Review. Network costs - August forecast business plan questionnaire rules:

Electricity Distribution Price Control Review. Network costs - August forecast business plan questionnaire rules: Electricity Distribution Price Control Review Network costs - August ecast business plan questionnaire rules: and guidance May 2008 1. Summary The purpose of these Rules is to provide a framework the collection

More information

SIEMENS Transmission and Distribution

SIEMENS Transmission and Distribution TITLE Long Term Maintenance and Care for S36A E. C. Wright 02/09/04 This document is to be used in conjunction with Installation, Operation and Maintenance Schedule IOMS 635. Its aim is to provide guidance

More information

CONNECTING YOU TO SPECIALIST ELECTRICAL SUPPORT services

CONNECTING YOU TO SPECIALIST ELECTRICAL SUPPORT services CONNECTING YOU TO SPECIALIST ELECTRICAL SUPPORT services SpecialistS IN ELECTRICAL SUPPORT SERVICES TO MINING, UTILITIES & industry Ampcontrol is committed to supporting our customers to maintain efficient

More information

Distribution Substation Manual (DSM) Section I - Introduction

Distribution Substation Manual (DSM) Section I - Introduction (DSM) Section I - Introduction March 2007 Document release information Client Project name Western Power Distribution Substation Manual Document number 3463019 Document title Revision status Introduction

More information

Attachment 20.64 SA Power Networks: Asset Management Plan 3.2.01 Substation Transformers 2014 to 2025

Attachment 20.64 SA Power Networks: Asset Management Plan 3.2.01 Substation Transformers 2014 to 2025 Attachment 20.64 SA Power Networks: Asset Management Plan 3.2.01 Substation Transformers 2014 to 2025 ASSET MANAGEMENT PLAN 3.2.01 SUBSTATION TRANSFORMERS 2014 TO 2025 Published: October 2014 SA Power

More information

Vision 2050 An Asset Management Strategy. Jaclyn Cantler Manager, Transmission Planning, PHI

Vision 2050 An Asset Management Strategy. Jaclyn Cantler Manager, Transmission Planning, PHI 1 Vision 2050 An Asset Management Strategy Jaclyn Cantler Manager, Transmission Planning, PHI 2 Agenda Case for Change About Vision 2050 Status Closing System Design Cybersecurity Interface with distributed/dispersed

More information

Asset Management Plan. A 10-year management plan for Orion s electricity network from 1 April 2015 31 March 2025

Asset Management Plan. A 10-year management plan for Orion s electricity network from 1 April 2015 31 March 2025 Asset Management Plan A 10-year management plan for Orion s electricity network from 1 April 2015 31 March 2025 Front cover: A team from Independent Line Services removing conductors prior to dismantling

More information

This document should be reviewed at least every two years.

This document should be reviewed at least every two years. 1.0 Change Control Version Date Modification Author(s) Reviews and Approvals by Issue 1 06 August 2007 Initial Document Philip J. Tatro David Wright Issue 2 29 February Removed Confidential from Philip

More information

We appreciate your feedback

We appreciate your feedback Publishing date: 23/07/2015 Document title: We appreciate your feedback Please click on the icon to take a 5 online survey and provide your feedback about this document REPORT ON UNIT INVESTMENT COST INDICATORS

More information

SP Energy Networks 2015 2023 Business Plan

SP Energy Networks 2015 2023 Business Plan Environmental Discretionary Reward Scheme 1 SP Energy Networks 2015 2023 Business Plan Executive summary SP Distribution Ltd SP Manweb plc July 2013 RIIO ED1 Business Plan 2015 to 2023 2 A Message from

More information

PG&E Transmission Interconnection Handbook. Section L3: SUBSTATION DESIGN FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES

PG&E Transmission Interconnection Handbook. Section L3: SUBSTATION DESIGN FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES Section L3: SUBSTATION DESIGN FOR LOAD-ONLY ENTITIES AND TRANSMISSION-ONLY ENTITIES PURPOSE This section provides substation design information for Load Entities interconnected at transmission voltage

More information

Cable Consulting International

Cable Consulting International Cable Consulting International Brian Gregory BSc, CEng, MIEEE, FIEE Technical Director www.cableconsulting.net Alan Williams BSc, CEng, MIEE Senior Consultant 1 FEASIBILITY STUDY for 500 kv AC UNDERGROUND

More information

132kV network reconfiguration to accommodate wider systems works

132kV network reconfiguration to accommodate wider systems works July 2012 CONTENTS 1. Executive Summary...4 2. UK Power Networks Business Case...5 2.1 Existing network infrastructure...5 2.2 Pelham & Wymondley Group Overall assessment...6 2.3 P2/6 compliance Transfer

More information

CUSTOMER-FACING PERFORMANCE MEASURES

CUSTOMER-FACING PERFORMANCE MEASURES CUSTOMER-FACING PERFORMANCE MEASURES CUSTOMER FEEDBACK AND RESPONSE Transpower New Zealand Limited March 2013 Customer-facing performance measures Transpower New Zealand Limited 2007. All rights reserved.

More information

Superconducting and Solid-State Electronic Fault Current Limiter Technologies The shift from demonstration projects to Business-as-Usual solutions

Superconducting and Solid-State Electronic Fault Current Limiter Technologies The shift from demonstration projects to Business-as-Usual solutions Superconducting and Solid-State Electronic Fault Current Limiter Technologies The shift from demonstration projects to Business-as-Usual solutions Dr. Detlev Kirsten & Herbert Piereder Solid State SSFCL

More information

Asset Management Plan

Asset Management Plan Asset Management Plan 2010-2019 West Coast s Locally Owned Electricity Distributor Asset Management Plan A 10 Year Management Plan for Westpower s Electricity Network From 1 April 2009 to 31 March 2019

More information

Asset Management Plan. A 10-year management plan for Orion s electricity network from 1 April 2014 to 31 March 2024

Asset Management Plan. A 10-year management plan for Orion s electricity network from 1 April 2014 to 31 March 2024 Asset Management Plan A 10-year management plan for Orion s electricity network from 1 April 2014 to 31 March 2024 Front cover: A team from Connetics installs 11,000 volt and 400 volt cables into a supply

More information

Network Risk Assessment Guideline

Network Risk Assessment Guideline Network Risk Assessment Guideline Network Risk Assessment Guideline Table of Contents Revision history... ii 1. Purpose and Scope... 1 2. Definitions, Abbreviations and Acronyms... 1 3. References... 2

More information

Power products and systems. Intelligent solutions for power distribution Zone concept

Power products and systems. Intelligent solutions for power distribution Zone concept Power products and systems Intelligent solutions for power distribution Zone concept Securing continuous power supply ABB is one of the world's leading power and automation technology companies whose products,

More information

LIMITING SHORT-CIRCUIT CURRENTS IN MEDIUM-VOLTAGE APPLICATIONS

LIMITING SHORT-CIRCUIT CURRENTS IN MEDIUM-VOLTAGE APPLICATIONS LIMITING SHORT-CIRCUIT CURRENTS IN MEDIUM-VOLTAGE APPLICATIONS Terence Hazel Senior Member IEEE Schneider Electric 38050 Grenoble France Abstract The power requirements for large industrial sites is increasing.

More information

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment

Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment March 20, 2009 Joint Con Edison LIPA Offshore Wind Power Integration Project Feasibility Assessment Table of Contents:

More information

Network Consulting for Power Grid Optimization

Network Consulting for Power Grid Optimization Network Consulting for Power Grid Optimization Project experience in India Network Consulting Competences Page 1 Our worldwide representation Manchester The Hague Denver Schenectady San Diego Houston Mexico

More information

Generator Interconnection and Deliverability Study Methodology Technical Paper

Generator Interconnection and Deliverability Study Methodology Technical Paper Generator Interconnection and Deliverability Study Methodology Technical Paper July 2, 2013 Generator Interconnection and Deliverability Study Methodology Table of Contents Introduction... 1 Section One:

More information

Modeling the Financial and System Benefits of Energy Storage Applications in Distribution Systems

Modeling the Financial and System Benefits of Energy Storage Applications in Distribution Systems Modeling the Financial and System Benefits of Energy Storage Applications in Distribution Systems Patrick Balducci, Senior Economist, Pacific NW National Laboratory Hydrogen Energy Storage for Grid and

More information

Report to the Minister Responsible for the Qulliq Energy Corporation. Respecting:

Report to the Minister Responsible for the Qulliq Energy Corporation. Respecting: Report to the Minister Responsible for the Qulliq Energy Corporation Respecting: An Application by the Qulliq Energy Corporation For Approval of Major Project Permit to Upgrade the Iqaluit Distribution

More information

Introduction to Ontario's Physical Markets

Introduction to Ontario's Physical Markets Introduction to Ontario's Physical Markets Introduction to Ontario s Physical Markets AN IESO MARKETPLACE TRAINING PUBLICATION This document has been prepared to assist in the IESO training of market

More information

Integration Capacity Analysis Workshop 11/10/15 California IOU s Approach

Integration Capacity Analysis Workshop 11/10/15 California IOU s Approach Integration Capacity Analysis Workshop 11/10/15 California IOU s Approach READ AND DELETE For best results with this template, use PowerPoint 2003 10 November 2015 Background and Importance of ICA Definition:

More information

Product brochure Multi Functional Switchgear PASS M00 72.5 kv Flexible and compact switchgear solutions for windfarms

Product brochure Multi Functional Switchgear PASS M00 72.5 kv Flexible and compact switchgear solutions for windfarms Product brochure Multi Functional Switchgear PASS M00 72.5 kv Flexible and compact switchgear solutions for windfarms The future of Wind Farms As offshore wind farms move towards deploying higher capacity

More information

Asset Management Plan

Asset Management Plan 2013 Asset Management Plan www.topenergy.co.nz INTRODUCTION Introduction It gives me great pleasure to present Top Energy s 2013-2023 Network Asset Management Plan (AMP). The 2013 plan follows on from

More information

Minimizing Impact of Electric Utility Outages with Backup Generation

Minimizing Impact of Electric Utility Outages with Backup Generation Minimizing Impact of Electric Utility Outages with Backup Generation Introduction of the Speaker Michael Dempsey, PE Senior Electrical Engineer Carter & Burgess, Inc. Energy & Power Solutions Facility

More information

Asset Management Plan 2012

Asset Management Plan 2012 Asset Management Plan 2012 Period Covered: 1 April 2012 to 31 March 2022 Approved by: Network Waitaki Directors 27 February 2012 Table of Contents 1.0 Summary 5 1.1 Purpose of the Plan 5 1.2 Date Completed

More information

Relion. Power system protection and automation reference Fast substation busbar protection with IEC 61850 and GOOSE

Relion. Power system protection and automation reference Fast substation busbar protection with IEC 61850 and GOOSE Relion Power system protection and automation reference Fast substation busbar protection with IEC 61850 and GOOSE Fast substation busbar protection with IEC 61850 and GOOSE Falu Elnät AB applies new power

More information

ERCOT Analysis of the Impacts of the Clean Power Plan Final Rule Update

ERCOT Analysis of the Impacts of the Clean Power Plan Final Rule Update ERCOT Analysis of the Impacts of the Clean Power Plan Final Rule Update ERCOT Public October 16, 2015 ERCOT Analysis of the Impacts of the Clean Power Plan Final Rule Update In August 2015, the U.S. Environmental

More information

Asset Management Plan

Asset Management Plan 2014 Asset Management Plan www.topenergy.co.nz INTRODUCTION Introduction It gives me great pleasure to present Top Energy s 2014-2024 Network Asset Management Plan (AMP). The 2014 AMP follows on from the

More information

Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid

Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid Pakistan Study to Determine the Limit of Integrating Intermittent Renewable (wind and solar) Resources onto Pakistan's National Grid Final Report: Executive Summary - November 2015 for USAID Energy Policy

More information

Operating Security Standards

Operating Security Standards Version 1.1 Prishtina December 2009 TABLE OF CONTENTS 1 Introduction... 1 2 Definitions... 1 2.1 General...1 2.1.2 Kosovo Transmission System...1 2.1.3 Circuit...2 2.1.4 The N-1 Criterion...2 2.1.5 Normal

More information

NETWORK MANAGEMENT STRATEGY

NETWORK MANAGEMENT STRATEGY ABN 85 082 464 622 NETWORK MANAGEMENT STRATEGY DOCUMENT NUMBER: NW-#30065608-V6 DATE: 12 MAY 2011 NW-#30065608-v6-Network_Management_Strategy.DOC Page 1 of 20 This page is intentionally blank. NW-#30065608-v6-Network_Management_Strategy.DOC

More information

National Grid Electricity Transmission RIIO-T1: Initial Proposals consultation response Supplementary information Strategic Spares

National Grid Electricity Transmission RIIO-T1: Initial Proposals consultation response Supplementary information Strategic Spares National Grid Electricity Transmission RIIO-T1: Initial Proposals consultation response Supplementary information Strategic Spares Table of contents Executive summary... 2 Introduction... 4 Replenishment

More information

Electric Power Systems An Overview. Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas

Electric Power Systems An Overview. Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas Electric Power Systems An Overview Y. Baghzouz Professor of Electrical Engineering University of Nevada, Las Vegas Overview Power Generation Conventional power generation Power generation from renewables

More information

Emergency Response Solution- Keyspan

Emergency Response Solution- Keyspan Emergency Response - Keyspan Keyspan Energy needs to install four 69kV substations allowing local gas generation to be on line before the summer peak of 2002. In-house resources not available. ABB s MODULA

More information

FACT SHEET. BSES, Delhi - Distribution Network. Power Systems Consultancy from ABB

FACT SHEET. BSES, Delhi - Distribution Network. Power Systems Consultancy from ABB BSES, Delhi - Distribution Network improve power quality System design for optimal techno-economic distribution network based on current and future load forecast Analysis of existing sub-transmission and

More information

Energy and Consumer Impacts of EPA s Clean Power Plan. Prepared for the American Coalition for Clean Coal Electricity

Energy and Consumer Impacts of EPA s Clean Power Plan. Prepared for the American Coalition for Clean Coal Electricity Energy and Consumer Impacts of EPA s Clean Power Plan Prepared for the American Coalition for Clean Coal Electricity Contents Executive Summary Overview of the Clean Power Plan NERA Methodology Baseline

More information

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F

ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F ELECTRICAL ENGINEERING DESIGN CRITERIA APPENDIX F TABLE OF CONTENTS Appendix F - Electrical Engineering Design Criteria F.1 Introduction...F-1 F.2 Codes and Standards...F-1 F.3 Switchyard and Transformers...F-1

More information

Comparison of GIS and AIS systems for urban supply networks

Comparison of GIS and AIS systems for urban supply networks Comparison of GIS and AIS systems for urban supply networks Studies carried out by ABB show that for urban supply networks the combination of HV gas-insulated switchgear (GIS) and HV cable has important

More information

SUMMARY ASsET MANAGEMENT PLAN

SUMMARY ASsET MANAGEMENT PLAN SUMMARY ASsET MANAGEMENT PLAN INFORmATION DISCLOSURE FOR ELECTRICITY NETWORKS JUNE 2010 2019 ASSET MANAGEMENT PLAN ELECTRICITY NETWORKS FY2010 FY2019 1 contents CHIEF EXECUTIVE S STATEMENT... 2 POWERCO

More information

Skyrocketing Electricity Cost in Denmark

Skyrocketing Electricity Cost in Denmark 1 Skyrocketing Electricity Cost in Denmark There is a lot of evidence that electricity for households is more expensive in Denmark than anywhere else in the EU. However, most of the household price is

More information

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114.

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position X1-114. Generation Interconnection System Impact Study Report For PJM Generation Interconnection Request Queue Position X1-114 Sandyston January 2012 Preface The intent of the System Impact Study is to determine

More information

EA NETWORKS ASSET MANAGEMENT PLAN 2015-25

EA NETWORKS ASSET MANAGEMENT PLAN 2015-25 EA NETWORKS ASSET MANAGEMENT PLAN 2015-25 2 ASSET MANAGEMENT PLAN FOR EA NETWORKS' ELECTRICITY NETWORK Planning Period: 1 April 2015 to 31 March 2025 Disclosure Year: 2015-16 Disclosure Date: 31 March

More information

Underground vs. Overhead Transmission and Distribution

Underground vs. Overhead Transmission and Distribution electric power engineering Underground vs. Overhead Transmission and Distribution Your Power System Specialists June 9, 2009 1 NATIONAL TRENDS Municipalities have passed laws requiring new distribution

More information

Power System review W I L L I A M V. T O R R E A P R I L 1 0, 2 0 1 3

Power System review W I L L I A M V. T O R R E A P R I L 1 0, 2 0 1 3 Power System review W I L L I A M V. T O R R E A P R I L 1 0, 2 0 1 3 Basics of Power systems Network topology Transmission and Distribution Load and Resource Balance Economic Dispatch Steady State System

More information

Industrial IT for Substation Automation & Protection

Industrial IT for Substation Automation & Protection Industrial IT for Substation Automation & Protection Exploit the potential of ABB substation automation Improve your performance In view of the increasingly competitive arena where power providers are

More information

Permissible ambient temperature Operation Storage, transport

Permissible ambient temperature Operation Storage, transport The Sitras PRO combined DC protective unit and controller is used in the power supply for DC railways in mass transit and main-line systems up 3,000 V DC. It protects DC switch gear and contact line systems

More information

HVDC Transmission Line Project for Moving ERCOT Wind Into SERC

HVDC Transmission Line Project for Moving ERCOT Wind Into SERC HVDC Transmission Line Project for Moving ERCOT Wind Into SERC ERCOT RPG Meeting August 13, 2010 Agenda Pattern Energy Group SERC and ERCOT Market Drivers Southern Cross Project Overview Project Development

More information

Enhancing solar contribution in PV-Diesel Hybrid Power Plants with advanced Li-ion Energy Storage Systems Michael Lippert

Enhancing solar contribution in PV-Diesel Hybrid Power Plants with advanced Li-ion Energy Storage Systems Michael Lippert Enhancing solar contribution in PV-Diesel Hybrid Power Plants with advanced Li-ion Energy Storage Systems Michael Lippert Intersolar Munich, 1 June 215 Increasing numbers of microgrids Factors New facility

More information

Overload Protection in a Dual-Corded Data Center Environment

Overload Protection in a Dual-Corded Data Center Environment Overload Protection in a Dual-Corded Data Center Environment White Paper 206 Revision 0 by Neil Rasmussen Executive summary In a dual-corded environment, the loss of power on one path will cause the load

More information

ABB Power Systems. Substations References

ABB Power Systems. Substations References ABB Power Systems Substations References Jingzhou, China BA PTPS - 2 - Connection of power from the 3-Gorges-Project to Guandong province (940km away) HVDC Transmission station, Filter banks and GIS Extremely

More information

IESO Supply Deliverability Guidelines

IESO Supply Deliverability Guidelines PUBLIC IMO_GDL_0021 IESO Supply Deliverability Guidelines Issue 3.0 This document is to be used to evaluate long-term system adequacy and connection assessments Public Disclaimer The posting of documents

More information

ASSET MANAGEMENT LCNI 2014 Wednesday 22 nd October. Jennifer Woodruff Innovation & Low Carbon Networks Engineer

ASSET MANAGEMENT LCNI 2014 Wednesday 22 nd October. Jennifer Woodruff Innovation & Low Carbon Networks Engineer ASSET MANAGEMENT LCNI 2014 Wednesday 22 nd October Jennifer Woodruff Innovation & Low Carbon Networks Engineer Asset Management Efficient asset management ensures that risk is effectively managed and returns

More information

Transmission Planning Study (Year 2022) for Cherokee 4 Replacement Alternatives. Final Report

Transmission Planning Study (Year 2022) for Cherokee 4 Replacement Alternatives. Final Report Transmission Planning Study (Year 2022) for Cherokee 4 Replacement Alternatives (Required per CPUC Decision No. C10-1328) Final Report (Submitted with Public Service s 2011 ERP) Executive Summary The objective

More information

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components

Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Fundamentals of Modern Electrical Substations Part 1: Mission of Electrical Substations and their Main Components Course No: E02-010 Credit: 2 PDH Boris Shvartsberg, Ph.D., P.E., P.M.P. Continuing Education

More information

Pricing Methodology 1. 1 July 2009 to 30 June 2014. April 2010

Pricing Methodology 1. 1 July 2009 to 30 June 2014. April 2010 Pricing Methodology 1 1 July 2009 to 30 June 2014 April 2010 1 TransGrid s Pricing Methodology as approved by the Australian Energy Regulator ( AER ). This document outlines the pricing methodology that

More information

Estimation of electrical losses in Network Rail Electrification Systems

Estimation of electrical losses in Network Rail Electrification Systems Estimation of electrical losses in Network Rail Electrification Systems Page 1 of 16 Contents 1. BACKGROUND...3 2. PURPOSE...3 3. SCOPE...3 4. DEFINITIONS & ABBREVIATIONS...4 5. NETWORK RAIL INFRASTRUCTURE

More information

COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011

COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011 COMMENTS OF THE SOLAR ALLIANCE NEW JERSEY INTERCONNECTION RULES APRIL 29 TH, 2011 I. Background The Solar Alliance is a group of approximately 30 of the largest photovoltaic (PV) solar development and

More information

2012 San Francisco Colloquium

2012 San Francisco Colloquium 2012 San Francisco Colloquium http : //www.cigre.org Advances in voltage source converter (VSC) technologies B4-6 500 kv VSC Transmission System for lines and cables B. JACOBSON, B. WESTMAN, M. P. BAHRMAN*

More information

Treasure Valley Electric Plan - Community Advisory Committee

Treasure Valley Electric Plan - Community Advisory Committee Treasure Valley Electric Plan - Community Advisory Committee What is a transmission line and why are they necessary? A transmission line is used to conduct electricity between two points. Without high

More information

Deep Dive on Microgrid Technologies

Deep Dive on Microgrid Technologies March 2015 Deep Dive on Microgrid Technologies 2 3 7 7 share: In the wake of Superstorm Sandy, a microgrid kept the lights on for more than for the more than 60,000 residents of Co-Op City in the northeastern

More information

Powerlink has provided this document to the AER in support of its Revenue Proposal

Powerlink has provided this document to the AER in support of its Revenue Proposal Powerlink has provided this document to the AER in support of its Revenue Proposal Copyright Powerlink Queensland All rights reserved Powerlink Queensland owns the copyright contained in this document.

More information

Summary of Electric Transmission Assessment Report

Summary of Electric Transmission Assessment Report Summary of Electric Transmission Assessment Report January 2010 Assessment and Analysis of the State-Of-the-Art High-Voltage Electric Transmission Systems with Specific Focus on High-Voltage Direct Current

More information

How To Operate The Williston Uvls

How To Operate The Williston Uvls WND Winter Operating Guide 2012/2013 1 WND Operating Study Using EQ-890-2012WIN- FINAL.sav developed through the 890 process Got load updates from MDU, Central Power, UM G&T Made several topology updates

More information