1 Reporting Exploration Results, Resources and Reserves in Context Mark Noppe SRK Consulting AIG Seminar, 21 August 2015
2 Content Reporting Resources & Reserves and project development how clear are we? Really? Introduction Context is everything Codes, standards, guidelines and industry practice Accuracy, confidence and quality Context project reporting Conclusions
3 Introduction Mining is an inherently risky business We need transparent, consistent and balanced views of technical confidence Risks and opportunities exist for advancing an exploration prospect to a viable project, and operating a mine Xstract, 2014
4 Context Why feasibility studies or mine projects fail Mined ore grade is lower than expected Processing plant under-performs Development cannot keep up with planned schedule Technical factors resulted in feasibility study failure Geology, resource and reserve estimation: 17% Geo-technical analysis: 9% Metallurgical test work, sampling, mineralogy: 15% Geo-hydrology: 4% Mine design and scheduling: 32% Mining equipment selection: 4% Process plant design: 12% Cost estimation: 7% Some 50% of causes relate to geo technical data collection and interpretation How do we convey uncertainty?
5 Context Importance of Resources & Reserves Mineral Resources and Ore Reserves underpin strategic and actual investment and valuations Valuation buckets Reserve (mine schedule) Residual resources Exploration potential Xstract, 2014
6 Codes Reporting definitions What about: Development stages Timing Level of technical- economic study Level of confidence in all relevant factors Transparent, consistent, balanced reporting JORC Code, 2012
7 Codes Project development stages VALMIN Code, 2005 Project development stage Exploration areas Advanced exploration areas Pre-development / resource Development Operating Criterion Mineralisation may or may not be defined, but where a Mineral Resource has not been identified. Considerable exploration has been undertaken and specific targets identified. Sufficient work has been completed on at least one prospect to provide a good geological understanding and encouragement that further work is likely to result in the determination of a Mineral Resource. Mineral Resources and/or Ore Reserves were identified and estimated. A positive development decision has not been made. This includes properties where a development decision has been negative and properties are either on care and maintenance or held on retention titles. Committed to production but not yet commissioned or not initially operating at design levels. Mineral properties, in particular mines and processing plants, which were fully commissioned and are in production.
8 Industry practice Timeline of development stages Xstract, 2014
9 Industry guidelines - types of study After Hatch M E White & I Harrington, Feasibility Studies Scope and Accuracy. AusIMM Monograph 30.
10 Industry practice & guidelines Technical-economic study levels Accuracy and confidence levels not provided in reporting Codes Measure / Item Scoping Study Pre-feasibility Study Final Feasibility Study Cost accuracy ±25%-50% ±15-25% ±10-15% Cost contingency 30-50% 15-30% <15% Proportion of Engineering complete Resource categories Reserve categories <5% <20% <50% Mostly Inferred Mostly Indicated Measured and Indicated None Mostly Probable Proved and Probable Mining method Assumed General Optimised Mine design Scheduling None or high-level conceptual Annual approximation Preliminary mine plan and schedule 3-monthly to annual Detailed mine plan and schedule Monthly for much of payback period Risk tolerance High Medium Low M E White & I Harrington, Feasibility Studies Scope and Accuracy. AusIMM Monograph 30.
11 Context How it all fits together Project advancement Data quantity and data quality Technical/economic assessment - Resource & Reserve reporting Final engineering / Construction Commissioning Operating Noppe, 2014
12 Codes & guidelines Mineral Resources - reasonable prospects for eventual economic extraction assessment of all matters likely to influence the prospect of economic extraction including the approximate mining parameters not an inventory of all mineralisation drilled or sampled, regardless of cut-off grade, likely mining dimensions location or continuity. Economic assessment applies equally to Inferred Resources Eventual economic extraction does not provide a license to speculate Approximate mining parameters are not necessarily the same as Modifying Factors required for defining an Ore Reserve
13 Codes & guidelines Ore Reserves timing of study & reporting The studies at Pre-Feasibility or Feasibility level demonstrate that, at the time of reporting, extraction could reasonably be justified Applicable if longer term price trends, market conditions, political, environmental, social or infrastructure issues, legislation or approvals, or funding issues that may prevent the intended project being developed in the time frame considered in the relevant technical study If re-evaluation indicates that the Ore Reserves are no longer viable, the Ore Reserves must be reclassified as Mineral Resources or removed from Mineral Resource/Ore Reserve statements
14 Accuracy, confidence & quality Accuracy and the nature of the deposit No two deposits are identical Essential the Competent Person s meaning of Resource or Reserve categories is provided May be possible to report the same accuracy for Measured Resources for a stratiform base metal deposit over a 3-month period a nickel sulphide deposit over a 6-month period, or A nuggetty gold deposit over 2-years of production
15 Accuracy, confidence & quality Discussing reporting confidence What do we really mean? Discuss and where possible provide a statement of the relative accuracy and confidence level of the reported Resource and Reserve categories, or The Code terminology Measured, Indicated, Inferred Proved and Probable accuracy, uncertainty, reliability, confidence, confidence level, quality of data, quality of information, quality of reported results Provide at least a qualitative discussion of the relevant uncertainties
16 Context - quantity & quality Item Reconciliation Ore Reserves Increasing Confidence in Quantity and Quality of Grade Information (JORC Code, ASX) Production Target on Measured + Indicated (ASX) Measured and Indicated Resources Production Target on Inferred (ASX) Inferred Resources Foreign / Historical Estimate (ASX) Exploration Target Exploration Results Early Exploration
17 Context - project stage Exploration Areas Project Development Stage (VALMIN, 2005) Advanced Prospect Evaluation Development Operating Exploration Resource Definition Preliminary Development Options Final Development Option
18 Context - study accuracy Exploration (pre-discovery) Mineralisation Delineation (postdiscovery) Level of Technical-Economic Accuracy Approximate Scoping Pre- Feasibility Mining Study Feasibility Study Parameters Study Final Engineering Operating
19 Context - project reporting
20 Example
21 Context project reporting example
22 Example retraction & clarification
23 Context project reporting example Still to update Resources Yet to define a Reserve; Economics not available; Development decision conditional Not a definitive Feas Study
24 Project development & reporting context
25 References Noppe, M A, Reporting and converting resources to reserves how confident are we? In AusIMM Ninth International Mining Geology Conference Proceedings, Adelaide August 2014, and In AusIMM Monograph 30, Mineral Resource and Ore Reserve Estimation, 2nd Edition. Noppe, M A, A framework for presenting and benchmarking resource projects. In preparation for the 2016 AusIMM Project Evaluation Conference. Xstract, AusIMM Monograph 30 Roadshow Presentations by Noppe, M A. Mark Noppe mnoppe@srk.com.au
Technical Due Diligence what do we look out for?
Technical Due Diligence what do we look out for? AusIMM M&A Masterclass May 2014 Mark Noppe General Manager and Principal Consultant XstractGroup.com Xstract - Excellence from the Outset GEOLOGY ENVIRONMENT
More information2015/01/04. New SAMREC Representative. Ken Lomberg. Group. Pr.Sci.Nat. Senior Principal Consultant. with Coffey. 30 years experience in South Africa
New SAMREC Representative Ken Lomberg Chairman of the SAMREC Working Group Pr.Sci.Nat. Senior Principal Consultant with Coffey 30 years experience in South Africa 1 THE SOUTH AFRICAN CODE FOR THE REPORTING
More informationALCYONE REPORTS JORC SILVER RESOURCES
ASX ANNOUNCEMENT & MEDIA RELEASE 29 March 2010 ALCYONE REPORTS JORC SILVER RESOURCES +15Moz RESOURCE INVENTORY UNDERPINS PROGRAM TARGETING RESUMPTION OF SILVER PRODUCTION AT TEXAS PROJECT LATER THIS YEAR
More informationCIM DEFINITION STANDARDS - For Mineral Resources and Mineral Reserves
CIM DEFINITION STANDARDS - For Mineral Resources and Mineral Reserves Prepared by the CIM Standing Committee on Reserve Definitions Adopted by CIM Council on November 27, 2010 FOREWORD CIM Council, on
More informationSavannah North Scoping Study Looking into the future 3 February 2016
Savannah North Scoping Study Looking into the future 3 February 2016 ASX: PAN Disclaimer Cautionary Statements This presentation includes information extracted from Panoramic Resources Limited ASX announcement
More informationGuidelines for the Estimation and Reporting of Australian Black Coal Resources and Reserves
Guidelines for the Estimation and Reporting of Australian Black Coal Resources and Reserves 2001 Edition (as referred to in the Joint Ore Reserves Committee Code ( The JORC Code ) 1999 edition) Prepared
More informationTORONTO STOCK EXCHANGE COMPANY MANUAL APPENDIX B DISCLOSURE STANDARDS FOR COMPANIES ENGAGED IN MINERAL EXPLORATION, DEVELOPMENT & PRODUCTION
B-1 APPENDIX B DISCLOSURE STANDARDS FOR COMPANIES ENGAGED IN MINERAL EXPLORATION, DEVELOPMENT & PRODUCTION 1.0 INTRODUCTION The disclosure of the results of exploration and development activity on mineral
More informationInvesting in an Underground Coal Mine in Indonesia
Coal Supplying Key Resources into expanding Asian markets Investing in an Underground Coal Mine in Indonesia Disclaimer Forward Looking Statements This presentation includes certain forward looking Statements.
More informationExploration. Exploration methods
Exploration Activities related to establishing a mineral deposit through geological, geophysical and geochemical methods. It is preceded by Prospecting and followed by Planning & Development. Geological
More informationChapter 5. Rules and Policies
Chapter 5 Rules and Policies 5.1.1 NI 43-101 Standards of Disclosure for Mineral Projects, Form 43-101F1 Technical Report and Related Consequential Amendments NATIONAL INSTRUMENT 43-101 STANDARDS OF DISCLOSURE
More informationEstablishing the feasibility of your proposed mining venture
RUPPRECHT, S. Establishing the feasibility of your proposed mining venture. International Platinum Conference Platinum Adding Value, The South African Institute of Mining and Metallurgy, 2004. Establishing
More informationFor personal use only. MRV Metals Launch February 2016
MRV Metals Launch February 2016 Important Information This document has been prepared by Moreton Resources Limited ( Moreton or Company ) for the purpose of providing a company and technical overview to
More informationPathway to Production
Charging forward with Lithium Pathway to Production 8th Lithium Supply & Markets Conference 24 26 May 2016 Las Vegas Disclaimer This presentation has been prepared by Altura Mining Limited ( Altura or
More informationRISK MANAGEMENT POLICY
RISK MANAGEMENT POLICY 1. INTRODUCTION 1.1 This Policy sets out Marindi Metals Ltd ( Marindi or the Company ) system of risk oversight, management of material business risks and internal control. 1.2 Marindi
More informationALCYONE TO RAISE $5M TO UNDERPIN TRANSITION TO SILVER PRODUCTION AT TEXAS PROJECT
ASX ANNOUNCEMENT & MEDIA RELEASE 25 November 2010 ALCYONE TO RAISE $5M TO UNDERPIN TRANSITION TO SILVER PRODUCTION AT TEXAS PROJECT ENTITLEMENT OFFER TO FUND FURTHER EXPLORATION, ACQUISITION OF LONG-LEAD
More informationReport for the Quarter Ended 30 September 2015
Report for the Quarter Ended 30 September 2015 ASX: KIS Market Capitalisation $18.2 million Shares on Issue 165.3 million 52 Week High 16.5 cents 52 Week Low 8.9 cents Share Price Board of Directors Johann
More informationANNUAL GENERAL MEETING. Investor Presentation 24 November 2015
ANNUAL GENERAL MEETING Investor Presentation 24 November 2015 Corporate Structure ASX Code: OVR Shares on Issue 205.4 million Top 20 133.0 million (64.8%) Market Capitalisation $1.23 million (share price
More informationBACANORA MINERALS ANNOUNCES SONORA LITHIUM PROJECT UPDATE, FILING OF PRE-FEASIBILITY STUDY AND AMENDED MINERAL RESOURCE ESTIMATE
TSX-V/AIM Symbol: BCN April 15, 2016 NEWS RELEASE BACANORA MINERALS ANNOUNCES SONORA LITHIUM PROJECT UPDATE, FILING OF PRE-FEASIBILITY STUDY AND AMENDED MINERAL RESOURCE ESTIMATE BACANORA MINERALS LTD.
More informationAppendix A Use of Supporting Studies in Process for NI 43-101 Documentation
Appendix A Use of Supporting Studies in Process for NI 43-101 Documentation Foreword Appendix A serves as support documentation within the Best Practice Guidelines for Mineral Processing (BPGMP). It supplements
More informationStripping Costs in the Production Phase of a Surface Mine
INTERPRETATION OF STATUTORY BOARD FINANCIAL REPORTING STANDARD INT SB-FRS 120 Stripping Costs in the Production Phase of a Surface Mine This version of INT SB-FRS 120 does not include amendments that are
More informationPositioned for Production: Exploring for Growth
ASX Code: AYN Positioned for Production: Exploring for Growth Andrew King, Managing Director May 2010 Pg 1 Disclaimer and Key Information Disclaimer This presentation has been prepared by the Directors
More informationFor personal use only
Investor Presentation August 2012 Disclaimer/Competent Person s Disclaimer: This presentation has been prepared by Buxton Resources ( Buxton ). The information contained in this presentation is a professional
More informationThe significant milestones achieved by New Age Exploration Limited ( NAE or the Company ) during this period include:
Quarterly Report To 31 December 2015 New Age Exploration Limited ( NAE or "the Company") is pleased to provide shareholders the Company s Quarterly Report for the period ending 31 December 2015. Highlights
More informationResources Rising Stars
ASX Code: AYN Resources Rising Stars Andrew King, Managing Director September 2010 Pg 1 Disclaimer and Key Information Disclaimer This presentation has been prepared by the Directors of Alcyone Resources
More informationStripping Costs in the Production Phase of a Surface Mine
IFRIC Interpretation 20 Stripping Costs in the Production Phase of a Surface Mine In October 2011 the International Accounting Standards Board issued IFRIC 20 Stripping Costs in the Production Phase of
More informationInternational approaches to mining projects: Due Diligence, Scoping, Pre-Feasibility, Feasibility Studies
International approaches to mining projects: Due Diligence, Scoping, Pre-Feasibility, Feasibility Studies Sergei Sabanov, PhD, CEng MIMMM Date:10 December 2013 Location: Almaty, Kazakhstan SRK Consulting
More informationFor personal use only
ASX Release 27 September 2012 OPTION TO ACQUIRE 560,000oz PEAK HILL GOLD PROJECT RESOURCE AND INVESTMENT NL (ASX: RNI) (RNI or the Company) has reached agreement with Montezuma Mining Company Limited for
More informationNEWS RELEASE NOT FOR DISSEMINATION IN THE UNITED STATES OR FOR DISTRIBUTION TO U.S. WIRE SERVICES
Suite 250, 1075 West Georgia Street Vancouver, BC, Canada V6E 3C9 Tel: 1.778.373.0102 Fax: 1.604.434.1487 NEWS RELEASE NOT FOR DISSEMINATION IN THE UNITED STATES OR FOR DISTRIBUTION TO U.S. WIRE SERVICES
More informationTHE SOUTH AFRICAN CODE FOR THE REPORTING OF EXPLORATION RESULTS, MINERAL RESOURCES AND MINERAL RESERVES (THE SAMREC CODE) 2007 EDITION
THE SOUTH AFRICAN CODE FOR THE REPORTING OF EXPLORATION RESULTS, MINERAL RESOURCES AND MINERAL RESERVES (THE SAMREC CODE) 2007 EDITION Prepared By The South African Mineral Resource Committee (SAMREC)
More informationQueensland Mining Corporation L I M I T E D. Maiden JORC Resources Estimate for Horseshoe Copper Deposit, Duck Creek, South Cloncurry District
ASX Release 12 October 2012 Maiden JORC Resources Estimate for Horseshoe Copper Deposit, Duck Creek, South Cloncurry District Total mineral resource at Duck Creek Project area of 960,000t @ 1.47% Cu (0.2%
More informationBUSINESS PLAN FOR THE MINERAL PROJECT FOR [NAME(S) OF PERIMETER(S)] SUBMITTED TO THE MINISTRY OF NATURAL RESOURCES/RWANDA
(COVER PAGE) COMPANY NAME PHONE / Fax Physical Address P.O. Box Email Website BUSINESS PLAN FOR THE MINERAL PROJECT FOR [NAME(S) OF PERIMETER(S)] SUBMITTED TO THE MINISTRY OF NATURAL RESOURCES/RWANDA NAME
More informationDECEMBER 2015 QUARTERLY REPORT HIGHLIGHTS
29 th January 2016 DECEMBER 2015 QUARTERLY REPORT HIGHLIGHTS Minerals Development Licence (MDL) formal application lodged with all requested associated technical documentation, awaiting Departmental approval
More informationIronbark Zinc Limited
Research Note Ironbark Zinc Limited Suite 5, Level 8, 99 York Street, Sydney NSW 2000 29 th August 2013 Ironbark Zinc to up the ante at Citronen Zinc Project with higher zinc prices Recommendation: Speculative
More informationHow To Mine And Treat Ore From Castle Hill Stage 1
` Dated: 5 th August 2014 NORTON TAKES UP OPTION TO MINE AND TREAT ORE FROM CASTLE HILL STAGE 1 ASX: PXG, PXGOA HIGHLIGHTS Development of Castle Hill Stage 1 with Norton Gold Fields potentially adds a
More informationEarth Sciences 4211/6210! Putting the Economics Back in Economic Geology!
Earth Sciences 4211/6210! Putting the Economics Back in Economic Geology! Stephen J. Piercey! Department of Earth Sciences! Memorial University! St. John s, NL, Canada! A1B 3X5! spiercey@mun.ca!!! Special
More informationCannon Big Pit Given the Green Light
ASX Release Tuesday 3 November 2015 Cannon Big Pit Given the Green Light Southern Gold maintains 50% profit share on Cannon Metals X estimate open pit recovered gold +270% to ~50koz Significant cash flow
More informationSeptember 2015 Quarterly Activities Report
ASX RELEASE 31 OCT 2015 September 2015 Quarterly Activities Report Expansion of Premier JV Gold Mine to 40,000ozpa production rate on track and future production growth plans advanced Highlights Production
More informationLalor Project Base Metal Zones and Gold Mineralization January 2009
Lalor Project Base Metal Zones and Gold Mineralization January 2009 1 Forward-Looking Statements All monetary amounts in Canadian dollars unless otherwise stated.. This presentation contains forward-looking
More informationTHE VALUATION OF ADVANCED MINING PROJECTS & OPERATING MINES: MARKET COMPARABLE APPROACHES. Craig Roberts National Bank Financial
THE VALUATION OF ADVANCED MINING PROJECTS & OPERATING MINES: MARKET COMPARABLE APPROACHES Craig Roberts National Bank Financial ABSTRACT While various methods are available to estimate a mining project
More informationFunds from the placement will be used for working capital requirements, including the completion of the Productora Pre-feasibility Study (PFS).
ASX ANNOUNCEMENT Monday 1 st February 2016 Hot Chili to Raise A$1.6m via Placement to Strategic Shareholders Hot Chili Limited (ASX Code: HCH) is pleased to announce that it has received commitments from
More informationMining Indaba Presentation. Capetown, South Africa 8 th 10 th February 2016
Mining Indaba Presentation Capetown, South Africa 8 th 10 th February 2016 www.birimiangold.com 1 Disclaimer This presentation has been prepared by Birimian Gold Limited (BGS) for general information purposes
More informationFor personal use only
SEPTEMBER 2011 QUARTERLY REPORT AND STATEMENT OF CASHFLOWS About TriAusMin (ASX:TRO) (TSX:TOR) TriAusMin Limited ( TriAusMin ) is an Australian development stage base and precious metals company focused
More informationInterim Financial Report for the half-year ended 31 December 2011
Interim Financial Report for the half-year ended 31 December 2011 Note: The information contained herein should be read in conjunction with the most recent annual report. Aura Energy Limited Level 4, 66
More informationUPDATE ON SRIG - ALTONA TRANSACTION AGREED WORK AND DRILLING PROGRAMME COMMENCES
6 October 2015 SX: OH, FSE: 2O UPDTE ON SRIG - LTON TRNSCTION GREED WORK ND DRILLING PROGRMME COMMENCES greed Work Programme ltona Mining Limited s ( ltona or the Company ) and Sichuan Railway Investment
More informationQUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 31 DECEMBER 2015
ASX RELEASE ASX:AWV 29 January 2015 QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 31 DECEMBER 2015 HIGHLIGHTS Review of updated pit optimisation undertaken Metallurgical testwork report received confirming
More informationDeveloping the Tanlouka Gold Project. AGM Presentation 18th November 2015
Developing the Tanlouka Gold Project AGM Presentation 18th November 2015 1 Executive Summary West African Resources Ltd is an ASX and TSXV listed gold development company focussed on Burkina Faso Largest
More informationRC drilling identifies high grade gold in bedrock at Pacific Dunes Corkwood Camp Scale Target
ASX Announcement 29 January 2016 Quarterly Report For the period ending 31 December 2015 ASX Code GOR ABN 13 109 289 527 Highlights Solid progress on Gruyere Pre Feasibility Study Gruyere PFS remains on
More informationCapability Statement
Capability Statement About Cube Practical & Professional Advice Cube Consulting provides consulting services and software systems to the global mining industry. We are a quality team of geologists, mining
More informationNOTE FOR MINING AND OIL & GAS COMPANIES - JU N E 2 0 0 9
NOTE FOR MINING AND OIL & GAS COMPANIES - JU N E 2 0 0 9 A G U I D E T O A I M U K TA X B E N E F I T S 2 AIM Note for Mining, Oil and Gas Companies Contents Introduction 1 Companies to which this Note
More informationRichmont Increases Mineral Reserves by 187% and Island Gold Mine Increases Mineral Reserves by 206%, With a 29% Increase in Reserve Grade
PRESS RELEASE TSX NYSE MKT: RIC Richmont Increases Mineral Reserves by 187% and Island Gold Mine Increases Mineral Reserves by 206%, With a 29% Increase in Reserve Grade TORONTO, Ontario, Canada, February
More informationCummins Range Rare Earths Project
Cummins Range Rare Earths Project December 2011 DISCLAIMER The information contained in this presentation is not financial product advice. The presentation is for information purposes and is of a general
More informationBAUXITE RESOURCES LIMITED
BAUXITE RESOURCES LIMITED POSITIVE EXPORT DSO BAUXITE SCOPING STUDY RESULTS RECEIVED FOR 100% BRL FORTUNA PROJECT Highlights Existing Mineral Resource and rail logistic chain can support a Direct Shipping
More informationCOMPANY PRESENTATION. Cape Town 2016
COMPANY PRESENTATION Cape Town 2016 DISCLAIMER The purpose of this presentation is to provide general information about OreCorp Limited (Company). It is not recommended that any person makes any investment
More informationBig Data & Coal. How big data can help Coal Geology, Exploration and Resource Evaluation in a downturn 12/07/2013
Big Data & Coal How big data can help Coal Geology, Exploration and Resource Evaluation in a downturn 12/07/2013 GEOLOGY GEOTECH MINING PROCESSING VALUATION/RISK TECHNOLOGIES ENVIRONMENT TRAINING Xstract
More informationSTANDARDS AND GUIDELINES FOR VALUATION OF MINERAL PROPERTIES
STANDARDS AND GUIDELINES FOR VALUATION OF MINERAL PROPERTIES SPECIAL COMMITTEE OF THE CANADIAN INSTITUTE OF MINING, METALLURGY AND PETROLEUM ON VALUATION OF MINERAL PROPERTIES (CIMVAL) FEBRUARY 2003 (FINAL
More informationDe Grey Mining Ltd. Wingina Deeps Drilling Commenced (Turner River Project) Highlights. Turner River Unlocking Shareholder Value
De Grey Mining Ltd ASX RELEASE 5 July 2016 ASX Code DEG ABN 65 094 206 292 Wingina Deeps Drilling Commenced (Turner River Project) Highlights Diamond drilling programme of approximately 1,500m has COMPANY
More informationKOPY GOLDFIELDS AB. A thorny path of a public Junior Gold Exploration Company in Russia Russian & CIS Metals Summit 2014, Moscow, February, 2014
KOPY GOLDFIELDS AB A thorny path of a public Junior Gold Exploration Company in Russia Russian & CIS Metals Summit 2014, Moscow, February, 2014 Disclaimer - Forward looking statement Forward Looking Information
More informationFor personal use only
dmin1138 27 January 2016 Key Points Corporate and Operational Update Savannah - decision made to preserve the value of the remaining Savannah orebody and to move the operation onto care and maintenance
More informationTechnical Presentation The Star-Orion South Diamond Project George Read P.Geo. Senior VP Exploration & Development. 16 June 2015
Technical Presentation The Star-Orion South Diamond Project George Read P.Geo. Senior VP Exploration & Development 16 June 2015 Safe Harbour Statement This presentation contains forward-looking statements
More informationFor personal use only
Mawson Iron Project PERTH 21 ST NOVEMBER 2015 Dr Gavin England General Manager DISCLAIMER AND COMPETENT PERSONS STATEMENT Slogan XXXX URBANISATION & INDUSTRIALISATION Chinese urbanisation and industrialisation
More informationAfrican Barrick Gold. BMO Global Metals & Mining Conference February 2013
African Barrick Gold BMO Global Metals & Mining Conference February 2013 Disclaimer Important Notice This presentation has been provided to you for information purposes only. It does not constitute an
More informationNovember 20, 2014. The key points included in the November 20, 2014 document are included below where necessary.
2015 CIM Guidance on Commodity Pricing used in Resource and Reserve Estimation and Reporting submitted by the Commodity Price Sub-Committee of the CIM Best Practices Committee adopted by CIM Council November
More informationIvanhoe Mines announces an accelerated infill drilling program at the Kamoa copper project s Kakula Discovery in the D.R. Congo
April 6, 2016 Ivanhoe Mines announces an accelerated infill drilling program at the Kamoa copper project s Kakula Discovery in the D.R. Congo SANTIAGO, CHILE Robert Friedland, Executive Chairman of Ivanhoe
More informationFALCO COMPLETES HORNE 5 CONFIRMATION DRILLING PROGRAM AND ANNOUNCES FINAL RESULTS
For Immediate Release TSX.V - FPC FALCO COMPLETES HORNE 5 CONFIRMATION DRILLING PROGRAM AND ANNOUNCES FINAL RESULTS (November 23, 2015) Montreal, Québec Falco Resources (FPC: TSX-V) ( Falco ) is pleased
More informationTIGER RESOURCES LTD ACN 077 110 304
TIGER RESOURCES LTD ACN 077 110 304 1st Floor, 8 Parliament Place, West Perth WA 6005 PO Box 1618, West Perth WA 6872 Tel: (08) 9481-7833 Fax: (08) 9481-7835 Email: tiger@tigerez.com Website: www.tigerez.com
More informationQUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 30 SEPTEMBER 2015
ASX RELEASE ASX:AWV 30 October 2015 QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDED 30 SEPTEMBER 2015 HIGHLIGHTS Pit optimisation and final mine design completed Metallurgical test work completed Engineering
More informationWonawinta Silver Project to be acquired; Mount Boppy development cost and risk cut back
Southern Cross Goldfields Ltd ASX Announcement 5 September 2014 Wonawinta Silver Project to be acquired; Mount Boppy development cost and risk cut back Wonawinta Silver Project (60 M oz) to be acquired
More informationCautionary Statement
Cautionary Statement This presentation contains certain "forward-looking statements", including, but not limited to, the statements regarding each of Minera Andes Inc., US Gold Corporation, Lexam Explorations
More informationFor personal use only
Investigator Resources Limited Date: 7 th February 2012 up to 2.25% Ag at the new Paris prospect in South Australia First assays received for new drilling on Paris Line 7 with all three holes assayed returning
More informationTURKEY CREEK PIT OPTIMISATION STUDY ADDS 2 YEARS MINE LIFE TO THE LITTLE EVA PROJECT AT CLONCURRY
10 August 2015 ASX: AOH, FSE: A2O TURKEY CREEK PIT OPTIMISATION STUDY ADDS 2 YEARS MINE LIFE TO THE LITTLE EVA PROJECT AT CLONCURRY Estimated oxide and sulphide resources within the optimum pit is 17.3
More informationFor personal use only
27 January 2016 Savannah North Scoping Study Positive results demonstrate robust, long life, Ni-Cu-Co Project Highlights Mining Inventory of 6.07Mt @ 1.26%Ni, 0.64% Cu and 0.09% Co for 76,500t Ni, 38,600t
More informationYAMANA GOLD ANNOUNCES SIGNIFICANT NEW DISCOVERIES AT CHAPADA AND EL PEÑÓN IMPROVE OPERATIONAL OUTLOOK
YAMANA GOLD ANNOUNCES SIGNIFICANT NEW DISCOVERIES AT CHAPADA AND EL PEÑÓN IMPROVE OPERATIONAL OUTLOOK TORONTO, ONTARIO, December 15, 2014 YAMANA GOLD INC. (TSX:YRI; NYSE:AUY) ( Yamana or the Company )
More informationDecember 2015 Quarterly Report
ANNOUNCEMENT TO THE AUSTRALIAN SECURITIES EXCHANGE December 2015 Quarterly Report The Board of OreCorp Limited (OreCorp or the Company) is pleased to present its quarterly report for the period ended 31
More informationFor personal use only
29 January 2016 ASX Announcement December 2015 Quarterly Activities Report Summary New Satimola Limited Sale and Purchase Agreement Signed Financing to Acquire Satimola Limited Secured Revised Consulting
More informationLYDIAN ANNOUNCES $325 MILLION CONSTRUCTION FINANCING FOR AMULSAR GOLD PROJECT
LYDIAN ANNOUNCES $325 MILLION CONSTRUCTION FINANCING FOR AMULSAR GOLD PROJECT Conference Call December 1, 2015 Lydianinternational.co.uk TSX:LYD Cautionary Statements Forward Looking Statements & Other
More informationOVERVIEW. Exploration review
Exploration review Given the Group s present constrained economic situation, exploration focus is being limited to current operations and one continuing offshore project where positive results warranted
More informationShaw River Manganese Ltd January 2012 Update. Vincent Algar - Managing Director
Shaw River Manganese Ltd January 2012 Update Vincent Algar - Managing Director Disclaimer This presentation has been prepared by Shaw River Manganese Limited ( Shaw River or the Company ). It should not
More information2015 Third Quarter Results Webcast October 29, 2015
2015 Third Quarter Results Webcast October 29, 2015 Speaker Randall Oliphant Executive Chairman 2 Cautionary statements ALL AMOUNTS IN U.S. DOLLARS UNLESS OTHERWISE STATED CAUTIONARY NOTE REGARDING FORWARD-LOOKING
More informationAurvista Gold Plans Significant Exploration Program at Douay
NEWS RELEASE For Immediate Issue June 14, 2016 Aurvista Gold Plans Significant Exploration Program at Douay Ø The main gold target is the largely untested northwestern section of the Porphyry Zone; the
More informationCarpentaria Exploration Ltd Investment Update
Carpentaria Exploration Ltd Investment Update June 19 th 2013 We find it. We prove it. We make it possible. Disclaimer This presentation has been prepared by the management of Carpentaria Exploration Limited
More informationChallenges of Investing in Junior Mining Companies and. Sotkamo Silver
Challenges of Investing in Junior Mining Companies and Sotkamo Silver Life Cycle of Junior Explorer High Risk - High Potential Full value Relative Value Possible takeover Speculation Discovery Lowered
More informationDumont Geometallurgical Modelling Do you know where your nickel is? AusIMM. Michelle Sciortino Johnna Muinonen John Korczak Alger St-Jean
Dumont Geometallurgical Modelling Do you know where your nickel is? AusIMM Michelle Sciortino Johnna Muinonen John Korczak Alger St-Jean Disclaimer Cautionary Statements Concerning Forward-Looking Statements
More informationMASUPARIA GOLD CORPORATION
CONDENSED CONSOLIDATED INTERIM FINANCIAL STATEMENTS THREE MONTHS ENDED DECEMBER 31, 2011 and 2010 (expressed in Canadian Dollars) NOTICE TO READERS Under National Instrument 51-102, Part 4.3 (3)(a), if
More informationFact sheet Exploration
Fact sheet 01 The Group combines Rio Tinto plc, which is listed on the London Stock Exchange, and Rio Tinto Limited, which is listed on the Australian Securities Exchange. Within Rio Tinto, the group
More informationSupply, Logistics, Marketing and Information Technology. Executive General Manager Commercial and West Africa
Supply, Logistics, Marketing and Information Technology Lawrie Conway Executive General Manager Commercial and West Africa Disclaimer Forward Looking Statement These materials include forward looking statements.
More informationSabina Gold & Silver Corp.
Sabina Gold & Silver Corp. Creating precious metals opportunities in the Canadian North November 2011 Hackett River Camp, looking to west 1 Forward Looking Statements This presentation includes certain
More informationNEWS RELEASE LEXAM ANNOUNCES POSITIVE PRELIMINARY ECONOMIC ASSESSMENT RESULTS FOR THE OPEN PIT PROJECTS IN TIMMINS
NEWS RELEASE LEXAM ANNOUNCES POSITIVE PRELIMINARY ECONOMIC ASSESSMENT RESULTS FOR THE OPEN PIT PROJECTS IN TIMMINS Project Generates 32% IRR and C$33 Million NPV After-Tax; Cash Costs of US$865 per Ounce
More informationFor personal use only
Korab Resources Limited Gold Operations Update November 2012 Andrej K. Karpinski Executive Chairman Korab Projects BOBRIKOVO MELROSE 1 Korab Gold Projects Other Korab Projects Robust Undervalued Gold Portfolio
More informationINTERNATIONAL FRAMEWORK FOR ASSURANCE ENGAGEMENTS CONTENTS
INTERNATIONAL FOR ASSURANCE ENGAGEMENTS (Effective for assurance reports issued on or after January 1, 2005) CONTENTS Paragraph Introduction... 1 6 Definition and Objective of an Assurance Engagement...
More informationA Battery Technology focused Graphite Company
February 2016 Taking Graphite to New Levels A Battery Technology focused Graphite Company ASX: MTA www.metalsofafrica.com.au Disclaimer & Competent Person Statement Statements and material contained in
More informationPress Release 30 th October 2015
Press Release 30 th October 2015 SEPTEMBER 2015 QUARTERLY ACTIVITIES REPORT Resources Limited (ASX: WAF) is pleased to report activities on its 100%-owned and 100%- earning gold and copper-gold projects
More informationFor personal use only
23 August 2013 Technical data supports copper porphyry potential Highlights: Data room initiated following unsolicited approaches from major copper resource companies Technical data supports intact high
More informationQUARTERLY REPORT FOR THE PERIOD TO 31 MAY 2012
QUARTERLY REPORT FOR THE PERIOD TO 31 MAY 2012 Metals Finance Limited (ASX: MFC) is pleased to provide its Quarterly Activities Report for the three month period ending 31 May 2012. HIGHLIGHTS Separate
More informationFIRST QUARTER CONFERENCE CALL MAY 4, 2010
FIRST QUARTER CONFERENCE CALL MAY 4, 2010 1 Cautionary Statement CAUTIONARY NOTE REGARDING FORWARD-LOOKING STATEMENTS: This presentation contains or incorporates by reference forwardlooking statements
More informationUpdate on Heap Leach potential of the Murchison gold project
3 July 2012 Australian-based Kentor Gold Limited (ASX: KGL) is entering the ranks of operating gold mining companies in 2012. The Company is progressing a pipeline of advanced projects in Australia and
More informationDiscounted Cash Flow Analysis Input Parameters and Sensitivity. Christopher R. Lattanzi, P. Eng., President, Micon International Limited
Discounted Cash Flow Analysis Input Parameters and Sensitivity Christopher R. Lattanzi, P. Eng., President, Micon International Limited Abstract Discounted cash flow analysis provides a means of relating
More informationExploration and Development Activity
For the period ending 30 June 2008 Exploration and Development Activity Over the last year, exploration and development work at the Company s Nullagine Gold Project in Western Australia s eastern Pilbara
More informationAlecto Minerals plc / EPIC: ALO / Market: AIM / Sector: Exploration & Development 8 February 2016 Alecto Minerals plc ( Alecto or the Company )
Alecto Minerals plc / EPIC: ALO / Market: AIM / Sector: Exploration & Development 8 February 2016 Alecto Minerals plc ( Alecto or the Company ) Joint Venture with Randgold Resources for the Advancement
More informationMINIMUM ENGINEERING STUDY REQUIREMENTS UPDATE
Issue No. 128 June 2015 MINIMUM ENGINEERING STUDY REQUIREMENTS UPDATE Issue No. 95 (March 2009) of this publication, formally known as Pincock Perspectives, has been one of our most requested and referenced
More informationNorth Atlantic and Rio Tinto Joint Venture Potash Project in Saskatchewan, Canada. Resource Summary
North Atlantic and Rio Tinto Joint Venture Potash Project in Saskatchewan, Canada Resource Summary The Canadian Potash Project is located in the central Saskatchewan Potash district that represents nearly
More information