1 Sourcing Benefits Case & Implementation Plan January 21,
2 Contents Executive Summary Approach and Wave Plan Workshop Summary Benefits Case Implementation Plan Appendix 1
3 Executive Summary The State of North Carolina has the potential to realize as much as $30M 60M in General and Highway Fund savings in the coming biennium by strategically sourcing 20 target categories with State Agencies and Community Colleges. The Benefits Case & Implementation Plan is based on analysis of FY 08 FY 10 spending for State Agencies and Community Colleges, and incorporates feedback from the State s leadership as to the timing and categories included in the plan. The Benefits Case & Implementation Plan includes 32 in-scope categories across three groups or waves, with 11 categories targeted in wave 1 and 9 categories targeted in wave 2. Through execution of strategic sourcing, the State could save as much as $46M 96M in annualized procurement savings from all funds over the next three years, or an average of $1.4M 3.0M per month. Savings are based on anticipated spend from State Agencies and Community Colleges; savings could be expanded by extending contract usage to Universities, LEAs and/or Local Governments. Effectively executing sourcing strategies against 32 categories will require an estimated resource pool of 2-3 experienced sourcing professionals per category to support research, analytics, RFx activities, negotiations, contract implementation, and contract management. Immediate next steps would include the State finalizing the start date of sourcing activities and identifying the source of the resources needed to execute the eleven categories in wave 1 of the implementation plan. Implementation of recommend changes to statutes & policies, organization, technology, and strategy & governance will maximize and sustain benefits from strategic sourcing. Notes: 1. Annualized procurement savings assumes the current volume of purchasing remain constant with State Agencies and Community Colleges and may include funding sources outside of the General Fund 2. Actual savings realized may be impacted by factors such as the elimination of federal stimulus funds and budget reductions, and will be further dependent on governance, organizational, and statutory changes. 3. The spend data in this report includes direct payment data from NCAS and purchase order data from eprocurement, and does not necessarily represent the exact dollar amount actually paid to third party vendors. 2
4 Contents Executive Summary Approach and Wave Plan Workshop Summary Benefits Case Implementation Plan Appendix 3
5 Approach - Overview To develop the benefits case, potential annualized procurement savings are projected over time building on the findings of the Sourcing Assessment. Sourcing Assessment Benefits Case and Implementation Plan Gather Data and Refresh Analysis Refresh Final Report Select Savings Scenario Develop Business Case Develop Implementation Plan Collect FY2010 NCAS and eprocurement Data Normalize Data Add new data to spend database Validate Findings Develop survey templates Survey NC procurement stakeholders Document survey discussion findings Identify opportunities for North Carolina to generate procurement benefits and estimated the time to achieve that benefit Quantify the potential benefits associated with the identified opportunities Prioritize the opportunities based on potential benefit and ease of implementation Identified, Quantified, and Prioritized Benefits Identify key NC stakeholders for selecting an implementation approach Review category priority, wave plan, with key NC stakeholders during the Wave Plan Review Workshop Finalize wave plan and select start dates for each wave Develop benefits timeline by projecting annualized savings over time Link the benefits timeline to the State s budget cycle to estimate budget impact Conduct secondary analysis to determine portion of benefits expected to impact General and Highway Funds Estimate the number of resources required to implement the wave plan assuming use of leading practice methodologies Determine the high-level skill set of the resources required to execute leading practice methodologies The Sourcing Assessment identified strategic sourcing opportunities, quantified benefits (potential savings), and prioritized opportunities The Benefits Case and Implementation Plan utilizes the benefits (potential savings) from the Sourcing Assessment and projects them over time along with identifying the resources need to execute Strategic Sourcing 4
6 As a result of the workshop, the following adjustments were made to the Wave Plan: Freight and Freight Supplies Moved from wave 1 to wave 2 IT Services Moved from wave 2 to wave 1 Office Equipment Moved from wave 2 to wave 1 Approach - Wave Plan Workshop Summary The Wave Plan Review Workshop served as the forum to gather additional feedback from the State s leadership on the initial wave plan provided as part of the Sourcing Assessment Deliverable. The updated wave plan reflects: Potential annual savings of $46M-96M 32 in-scope categories 3 waves of strategic sourcing Wave 1: 11 Categories Wave 2: 9 Categories Wave 3: 12 Categories Notes: 1. Annualized procurement savings assumes the current volume of purchasing remain constant with State Agencies and Community Colleges and may include funding sources outside of the General Fund 2. Actual savings realized may be impacted by factors such as the elimination of federal stimulus funds and budget reductions, and will be further dependent on governance, organizational, and statutory changes. 3. The spend data in this report includes direct payment data from NCAS and purchase order data from eprocurement, and does not necessarily represent the exact dollar amount actually paid to third party vendors. 5
7 Approach Benefits Case To develop the benefits case, potential annualized procurement savings are projected over time taking into account the state s budget cycle. Sourcing Assessment Benefits Case Category Benefits Category Duration Category Sourcing Timing Estimate Budget Impact Benefits Reoccur Strategic Sourcing Opportunities are identified, quantified, and prioritized using North Carolina Data, Industry Trends, Category Benchmarks, Leading Practices, NC Observations (see Sourcing Assessment for additional details). The duration of the strategic sourcing effort expected to be needed to achieve the potential benefits are estimated (see Sourcing Assessment for additional details). The expected start date for sourcing each category is determined Based on the category duration the end date of sourcing can then be estimated The annualized benefits from sourcing can then be accounted for in the budget of the fiscal year following the completion of sourcing though a budget reduction Although not accounted for in the budget of the FY that sourcing is completed there is an immediate benefit to the state in the form of reduced cost for goods and/or services The budget reduction is continued into budgets for future years producing a Recurring benefit and lowering ongoing operating costs. Office Supplies Example Annual Addressable Spend: $18.2M Potential Savings: 10% - 20% Potential Annual Savings (Lowest %): $1.8M 6 s expected to achieve potential benefit Sourcing Start Date: March 2011 Sourcing End Date: August 2011 $1.8M in annualized reduced cost for office supplies is accounted for in the FY13 budget (additional savings would begin in FY12 as soon as a new contract is in place) One Time Budget Reduction Recurring Benefit (lower ongoing operating cost) FY'13 FY'14 FY'15 FY'16 FY'.. $1.8M 1.8M 1.8M 1.8M 1.8M Notes: 1. Annualized procurement savings assumes the current volume of purchasing remain constant with State Agencies and Community Colleges and may include funding sources outside of the General Fund 2. Actual savings realized may be impacted by factors such as the elimination of federal stimulus funds and budget reductions, and will be further dependent on governance, organizational, and statutory changes. 3. The spend data in this report includes direct payment data from NCAS and purchase order data from eprocurement, and does not necessarily represent the exact dollar amount actually paid to third party vendors. 6
8 Contents Executive Summary Approach and Wave Plan Workshop Summary Benefits Case Implementation Plan Appendix 7
9 Benefits Case - Sourcing Wave Plan Summary The wave plan prioritizes the 32 in-scope categories into three waves based on savings opportunity and ease of implementation elements. Recommended Sourcing Waves Wave 1 Wave 2 Wave 3+ Ease of Implementation Elements Category sourcing complexity Entity spend distribution Market conditions North Carolina readiness Notes: 1. Annualized procurement savings assumes the current volume of purchasing remain constant with State Agencies and Community Colleges and may include funding sources outside of the General Fund 2. Actual savings realized may be impacted by factors such as the elimination of federal stimulus funds and budget reductions, and will be further dependent on governance, organizational, and statutory changes. 3. The spend data in this report includes direct payment data from NCAS and purchase order data from eprocurement, and does not necessarily represent the exact dollar amount actually paid to third party vendors. 8
10 Benefits Case - Addressable Spend Overview The team reviewed $4.03 billion in total FY 10 spend to identify the spend most likely addressable through strategic sourcing. FY 10 Spend ($B) $4.5 $4.0 $3.5 $3.0 $2.5 $2.0 $4.0B Addressable Spend Identification Process Removed: LEAs, University, and Local Gov. $3.4B Removed: Out of Scope, Unclassified, and Misc. Categories 1 $3.1B Removed: Categories not as likely to produce significant benefits $2.4B Addressable spend across the 32 target categories Removed: Spend strategic sourcing can not likely impact 2 $1.5 $1.0 $0.8B $0.5 $ of 93 Categories Total Spend (Mapped Spend) 93 of 93 Categories State Agency and C.C. Spend 83 of 93 Categories Classified Spend Categories 32 of 93 Categories Sourceable Spend 32 of 93 Categories Addressable Spend Notes: 1. Annualized procurement savings assumes the current volume of purchasing remain constant with State Agencies and Community Colleges and may include funding sources outside of the General Fund 2. Actual savings realized may be impacted by factors such as the elimination of federal stimulus funds and budget reductions, and will be further dependent on governance, organizational, and statutory changes. 3. The spend data in this report includes direct payment data from NCAS and purchase order data from eprocurement, and does not necessarily represent the exact dollar amount actually paid to third party vendors. 9
11 Benefits Case Annualized Savings Summary The potential annualized procurement savings of $46M - $96M is divided among the 32 categories and three waves of sourcing. Category Wave Annual Addressable Spend ($M) Annual Savings Low ($M) Annual Savings High ($M) Category Wave Annual Addressable Spend ($M) Annual Savings Low ($M) Annual Savings High ($M) Category Wave Annual Addressable Spend ($M) Annual Savings Low ($M) Annual Savings High ($M) Roadway Building Materials 1 $125.2 $5.0 $10.0 Freight and Freight Supplies 2 $11.0 $0.6 $1.1 Micro Computers and Peripherals Architecture and Engineering Services 3 $28.2 $1.4 $2.5 1 $38.1 $3.8 $7.6 Industrial Equipment Rental 2 $35.6 $1.4 $2.8 Drugs and Pharmaceuticals 3 $21.7 $0.4 $1.7 IT Services 1 $44.1 $4.4 $6.6 Safety and Security Equipment and Supplies 2 $13.5 $0.7 $2.0 Radios and Communication Equipment 3 $15.0 $0.3 $1.5 Food 1 $37.8 $3.0 $5.7 Fuels 2 $43.1 $0.9 $1.7 Furniture and Fixtures 3 $11.8 $0.6 $1.2 Office Supplies 1 $18.3 $1.8 $3.7 Network Equipment 2 $10.5 $0.5 $1.6 Telecommunications 3 $13.0 $0.3 $1.3 Med/Lab Supplies and Equipment 1 $24.8 $1.2 $2.5 Advertising and Marketing 2 $25.7 $1.3 $2.6 Administrative Services 1 $9.0 $0.7 $1.3 Auto Service and Parts 2 $20.8 $0.8 $2.5 Cleaning Equipment and Supplies MRO Supplies and Equipment 1 $5.1 $0.5 $1.0 Construction and Building Management Services Mini/Mainframe Computers and Peripherals Agricultural Equipment and Supplies 3 $10.3 $0.5 $1.0 3 $7.0 $0.6 $0.8 2 $45.8 $2.3 $6.9 Rent/Real Estate 3 $12.5 $0.4 $0.9 1 $66.8 $5.3 $10.0 Health Services 2 $34.8 $1.7 $3.5 Print 3 $7.6 $0.4 $0.8 Auto 1 $73.9 $3.7 $7.4 Total (Wave 2) $240.8 $10.2 $24.7 Software 3 $10.9 $0.2 $0.9 Office Equipment 1 $8.6 $0.9 $1.7 Industrial Equipment and Service 3 $6.8 $0.3 $0.7 Total (Wave 1) $451.7 $30.5 $57.5 Legal Services 3 $1.7 $0.1 $0.2 Total (Wave 3) $146.5 $5.4 $13.5 Total (All Waves) $839.0 $46.1 $95.7 Notes: 1. Annualized procurement savings assumes the current volume of purchasing remain constant with State Agencies and Community Colleges and may include funding sources outside of the General Fund 2. Actual savings realized may be impacted by factors such as the elimination of federal stimulus funds and budget reductions, and will be further dependent on governance, organizational, and statutory changes. 3. The spend data in this report includes direct payment data from NCAS and purchase order data from eprocurement, and does not necessarily represent the exact dollar amount actually paid to third party vendors. 10
12 Benefits Case All Funds Accounting for annualized savings, resulting from strategic sourcing, in the budget process reduces ongoing operating costs. Sourcing Wave Potential Annualized Benefit Expected of Sourcing Completion FY 12 FY 13 FY 14 FY 15 FY 16 Wave 1 $30.5 Oct 11 - $30.5 $30.5 $30.5 $30.5 Wave 2 $10.2 May 12 - $10.2 $10.2 $10.2 $10.2 Wave 3 $5.4 Oct $5.4 $5.4 $5.4 Potential Budget Reduction (sum of budget reductions) N/A N/A - $40.7 $ Note: Successful procurement transformation preserves achieved benefits and should result in additional benefits beyond the three identified waves. Potential Annual Benefit (sum of budget reduction and Recurring benefit) N/A N/A - $40.7 $46.1 $46.1 $46.1 : Budget Reduction Potential Cumulative Benefits (sum of potential annual benefit for all fiscal years) *See page 21 for General and Highway Fund Benefits Case N/A N/A - $40.7 $86.8 $132.9 $179.0 *Numbers In Millions : Recurring Benefit Benefits Case Assumptions Assumes full purchasing compliance from State Agencies and Community Colleges and current purchasing volumes of sourced categories remain constant Assumes benefits from sourcing are accounted for in the budget of the fiscal year following the completion of sourcing Assumes lowest percent savings for each category and wave are achieved (see page 10 for ranges) Notes: 1. Annualized procurement savings assumes the current volume of purchasing remain constant with State Agencies and Community Colleges and may include funding sources outside of the General Fund 2. Actual savings realized may be impacted by factors such as the elimination of federal stimulus funds and budget reductions, and will be further dependent on governance, organizational, and statutory changes. 3. The spend data in this report includes direct payment data from NCAS and purchase order data from eprocurement, and does not necessarily represent the exact dollar amount actually paid to third party vendors. 11
13 Contents Executive Summary Approach and Wave Plan Workshop Summary Benefits Case Implementation Plan Appendix 12
14 Sample Wave 1 Staffing Structure Successful implementation of strategic sourcing as a component of long-term procurement transformation will require participation from North Carolina resources and support from external resources. Sample Wave 1 Staffing Structure Notes: NC team resources are expected to be 80% of a single resources time not.8 FTE spread across multiple resources 13
15 Mar 11 Oct 11 May 12 MRO Supplies and Equipment Auto Office Equipment Freight and Freight Supplies Industrial Equipment Rental Safety and Security Equipment and Supplies Fuels Network Equipment Advertising and Marketing Auto Service and Parts Construction and Building Management Services Health Services Implementation Plan The Implementation Plan begins sourcing activities in March 2011, with three waves and 32 categories reaching completion by November Roadway Building Materials Micro Computers and Peripherals IT Services Food Office Supplies Med/Lab Supplies and Equipment Administrative Services Cleaning Equipment and Supplies FTE Staffing Assumptions: FTE estimates assume involvement from external experienced sourcing professionals as well as NC sourcing professionals FTE efficiency will increase as State resources build and apply leading practice sourcing skill sets Actual FTE requirements per month will be dependent on category start dates, category team support structure, and mix of North Carolina versus contracted resources Wave 1 Wave 3 Architecture and Engineering Services Drugs and Pharmaceuticals Radios and Communication Equipment Furniture and Fixtures Telecommunications Mini/Mainframe Computers and Peripherals Agricultural Equipment and Supplies Rent/Real Estate Print Software Industrial Equipment and Service Legal Wave 2 FTE Estimates Low FTE High FTE Oct 12 Notes: 1. Annualized procurement savings assumes the current volume of purchasing remain constant with State Agencies and Community Colleges and may include funding sources outside of the General Fund 2. Actual savings realized may be impacted by factors such as the elimination of federal stimulus funds and budget reductions, and will be further dependent on governance, organizational, and statutory changes. 3. The spend data in this report includes direct payment data from NCAS and purchase order data from eprocurement, and does not necessarily represent the exact dollar amount actually paid to third party vendors. 14
16 Sample Sourcing Methodology The current implementation plan requires resources that have skills in each area of a strategic sourcing methodology. Key Activities Accenture Seven-Step Strategic Sourcing Methodology Negotiate & Kickoff & Profile Develop Screen Conduct Develop Assess Internally & Category Suppliers & Competitive Sourcing Opportunity Externally Strategy Selection Exercise with Recommendation Factors Supply Mkt Develop Benefits Case Develop Category Analysis Plan High-Level Data Collection and Analysis Profile Category Develop Sourcing Build TCO Objectives Model Fast Track for Identified Quick Wins Conduct Industry Analysis Develop Sourcing Strategies & Tactics Create Supplier Selection Criteria Conduct Supplier Analysis Complete Traditional RFP Process - AND/OR - Conduct eauction(s) - AND/OR - Collaborate w/ Incumbent Supplier(s) Prepare Fact- Based Negotiation Packages Negotiate Agreements Implement Agreements Rollout Agreements and Monitor KPIs Develop Implementation Plan Potential Deliverables Spend Analysis Category Profiles Sourcing Waves Internal Profile External Profile TCO Model/CRI s Category Strategy To-Be Processes Sourcing Objectives Potential Supplier Long List Selection Decision Matrix RFI (optional) RFP / RFQ Reverse Auctions Collaborative Discussions Potential Suppler Short List Fact Based Negotiation Package Sourcing Recommendation Category Value Proposition Finalized Agreements Implementation Plan 15
17 Role Requirements In order to implement each wave of strategic sourcing, resources will need a strong procurement skill set. Kickoff and Assess Opportunities Continually evaluate category priorities based on current opportunities Leverage spend database to confirm present opportunities and evaluate future opportunities Conduct spend analysis and create spend reports Define commodity segmentation/ spend breakdown via spend analytics Understand high level spend and opportunities as identified in spend database Identify commodity stakeholders for key commodities Review categories for potential sourcing triggers such as contract renewal alerts, new demand arising from new capital projects, changes in market conditions, vendor issues, changes in operational demand forecasts, revisions to financial targets, etc. Identify commodity constraints and requirements through stakeholder engagement Profile Internally & Externally Work with key entity stakeholders/core team to gather and assess requirements and map procurement flow Evaluate category importance and measure customer values Leverage specific category knowledge from known experts in category profiling Profile current sourcing / buying practices, category characteristics, constraints Understand key drivers of Total Cost of Ownership for the category, including price, administrative / process costs, usage costs, etc. Develop TCO category baseline; allow for adjustments based on future changes in TCO elements Gather transaction-level spend details from data sources Collect existing specifications and standards Understand industry trends and competitive forces using tools like Porter s Five Forces analysis, industry cost analysis, etc. Identify potential vendors and market segments Understand current cost structure of vendor industry Develop internal and external profiles for each category Assess potential supplier capabilities, positioning and financials 16
18 Role Requirements In order to implement each wave of strategic sourcing, resources will need a strong procurement skill set. Develop Category Strategy Leverage current data and profiling analysis, working collaboratively with the stakeholder team, in order to determine appropriate sourcing objective(s), strategies and internal change tactics. Examples include: Best Price Analysis, Demand Management, Volume Leveraging, Process Improvement, and Strategic Relationship Management Evaluate strategy potential risks, business impact and opportunity sizing Determine bid mechanism, such as RFP, RFQ, eauction, collaborative discussions, direct negotiation, etc. Screen Suppliers and Selection Factors Conduct RFI (as needed) Review vendor long list and pre-quality suppliers Evaluate supplier financials Identify selection factors based on stakeholder input and industry knowledge that accurately capture business requirements and facilitate vendor differentiation. Compile selection factors into vendor scorecard to determine which vendors to include in bid process Conduct Competitive Exercise with Supply Market Determine scope/timing of competitive exercise Build competitive tender and solicit internal input / approval Develop effective qualitative questions that allow a vendor to thoroughly explain their capabilities as they apply to the stakeholders, while also soliciting the answers to allow scoring using the established selection criteria Build Bid Analysis Worksheet or Database allowing comparisons of basic price quotes across vendors Coordinate and prepare vendor communications Communicate event and distribute RFP Answer questions from vendors and clarify as needed Conduct vendor bid conferences as needed Evaluate and confirm RFP responses and supplier capabilities Identify/confirm ranges for savings potential based on RFP responses as compared to the TCO category baseline 17
19 Role Requirements In order to implement each wave of strategic sourcing, resources will need a strong procurement skill set. Negotiate and Develop Sourcing Recommendations Develop RFP response scenarios including sourcing alternatives such as As-Is (current situation), current vendors with new prices (post RFP), $0 on the table (highest savings), and To-Be (recommendation). Define negotiation strategy, clearly documenting objectives, location, timing and participants involved in negotiations Identify and document all strategic levers and counter levers Define negotiation team, roles and responsibilities Conduct negotiations (one or multiple rounds) Document results achieved Obtain approval from management for award Sign letters of intent or contingent agreement Ensure business requirements are agreed-to by both parties, including service level agreements, key performance indicators, vendor reporting requirements, etc. Calculate final identified savings as compared to the TCO baseline, including projections for savings through the life of the contract term Implement Agreements Develop preliminary implementation plan describing the process to implement the new agreement, any process changes, or other improvements Develop communication plan incorporating the steps required to facilitate the various stages of the transition to the new sourcing environment Communicate award strategy and implementation plan internally and externally Identify vendor metrics critical to making sure your selected vendors are on track to meet expectations Refine and finalize implementation plan after integrating operations and vendor input Execute implementation plan by issuing communications both internally and externally, conducting the first vendor performance meetings, and managing any required vendor transition Track and report category performance metrics and savings; develop and review vendor scorecards/kpis Manage relationships with vendors for specified categories, resolving issues between vendors and internal customers 18
20 Contents Executive Summary Approach and Wave Plan Workshop Summary Benefits Case Implementation Plan Appendix 19
21 General and Highway Fund Analysis Process The benefits case for the General and Highway Fund is estimated by utilizing the FY09 North Carolina Budget by Function, Department, and Source of Funds. General Fund Analysis Process 1. The percentage of each entity s Total Budget Excluding Transfers from the General and Highway Fund was estimated (source: North Carolina, Post-Legislative Summary, ; Appendix Table 3B: Total North Carolina State Budget by Function, Department, and Source of Funds) (Source: Community College Budget Documents) 2. The percentage of General and Highway Funding for each entity (from step 1) was multiplied by the Total Spend for each Entity by Category as determined by the Sourcing Assessment 3. The General and Highway Fund Spending for each entity in each category was added to determine the General Fund Spending for each category 4. Addressable Spend and Estimated Savings percentages from the Sourcing Assessment are applied to determine the potential General Fund benefits 5. The General and Highway Fund benefits were projected over time using the benefits case process (see slide 6) Notes: 1. Annualized procurement savings assumes the current volume of purchasing remain constant with State Agencies and Community Colleges and may include funding sources outside of the General Fund 2. Actual savings realized may be impacted by factors such as the elimination of federal stimulus funds and budget reductions, and will be further dependent on governance, organizational, and statutory changes. 3. The spend data in this report includes direct payment data from NCAS and purchase order data from eprocurement, and does not necessarily represent the exact dollar amount actually paid to third party vendors. 20
22 Benefits Case General and Highway Funds The benefits case for the General and Highway Fund is estimated by utilizing the FY09 North Carolina Budget by Function, Department, and Source of Funds. Sourcing Wave Potential General and Highway Fund Annualized Benefit Expected of Sourcing Completion FY 12 FY 13 FY 14 FY 15 FY 16 Wave 1 $22.3 Oct 11 - $22.3 $22.3 $22.3 $22.3 Wave 2 $7.3 May 12 - $7.3 $7.3 $7.3 $7.3 Wave 3 $3.9 Oct $3.9 $3.9 $3.9 Potential Budget Reduction (sum of budget reductions) N/A N/A - $29.6 $ Note: Successful procurement transformation preserves achieved benefits and should result in additional benefits beyond the three identified waves. Potential Annual Benefit (sum of budget reduction and Recurring benefit) Potential Cumulative Benefits (sum of potential annual benefit for all fiscal years) N/A N/A - $29.6 $33.5 $33.5 $33.5 N/A N/A - $29.6 $63.1 $96.6 $130.1 : Budget Reduction : Recurring Benefit *See page 11 for all Funds Benefits Case *Number in Millions Benefits Case Assumptions Assumes full purchasing compliance from State Agencies and Community Colleges and current purchasing volumes of sourced categories remain constant Assumes benefits from sourcing are accounted for in the budget of the fiscal year following the completion of sourcing Assumes lowest percent savings for each category and wave are achieved (see page 10 for ranges) Notes: 1. Annualized procurement savings assumes the current volume of purchasing remain constant with State Agencies and Community Colleges and may include funding sources outside of the General Fund 2. Actual savings realized may be impacted by factors such as the elimination of federal stimulus funds and budget reductions, and will be further dependent on governance, organizational, and statutory changes. 3. The spend data in this report includes direct payment data from NCAS and purchase order data from eprocurement, and does not necessarily represent the exact dollar amount actually paid to third party vendors. 21
Prepared by David Willson, OCIO in consultation with Marc Buchalter, Procurement Please send comments to David Willson at dwillson@berkeley.
Technology RFX Customer Guide Introduction This guide is intended for those that have identified a need to solicit bids from suppliers but may unclear on the different types of documents, the roles various
More informationWhite paper. Reverse e-auctions. A Recipe for Success
White paper s A Recipe for Success Executive Summary Enterprises and organizations whether small, medium or large have used s with varied degrees of success in the strategic sourcing cycle. While some
More informationFinal. North Carolina Procurement Transformation. Governance Model March 11, 2011
North Carolina Procurement Transformation Governance Model March 11, 2011 Executive Summary Design Approach Process Governance Model Overview Recommended Governance Structure Recommended Governance Processes
More informationKnowledge Area Inputs, Tools, and Outputs. Knowledge area Process group/process Inputs Tools Outputs
HUMAN RESOURCE MANAGEMENT Organizational planning Staff Acquisition Project interfaces such as organizational interfaces, technical interfaces and interpersonal interfaces. Staffing requirements Staffing
More informationPROJECT MANAGEMENT PLAN CHECKLIST
PROJECT MANAGEMENT PLAN CHECKLIST The project management plan is a comprehensive document that defines each area of your project. The final document will contain all the required plans you need to manage,
More informationProject Management Professional (PMP)
Project Management Professional (PMP) Duration: 5 days Course Objectives: PMI s Project Management Professional (PMP) credential is the most important industry-recognized certification for project managers.
More informationDevelop Project Charter. Develop Project Management Plan
Develop Charter Develop Charter is the process of developing documentation that formally authorizes a project or a phase. The documentation includes initial requirements that satisfy stakeholder needs
More informationContract Management The Mavericks Won t Like This!
Contract Management The Mavericks Won t Like This! Keith Wallis How Much Did That Project Cost? Real Life Example Original contract amount $500K Variations scope changes not visible Total variations =
More informationIntegration Mgmt / Initiating Process Group 4.1 Develop Project Charter
1 Mgmt / Initiating Process Group 4.1 Develop Project Charter Project statement of work Business case Agreements Facilitation techniques Project charter 26/02/2013 18:23:36 1 2 Mgmt / Planning Process
More informationTales from the Trenches: Evolution of Strategic Sourcing
Tales from the Trenches: Evolution of Strategic Sourcing Introduction The term strategic sourcing has been used in state government procurement for several years now. Over the past decade many states have
More informationState of North Carolina Department of Administration. Report on the North Carolina Procurement Transformation Project
State of North Carolina Department of Administration Report on the North Carolina Procurement Transformation Project August 2011 Table of Contents I. DEPARTMENT OF ADMINISTRATION: OVERVIEW Introduction
More informationVendor Relationship Management
Vendor Relationship Management Getting What You Paid For (and More) Stephen Guth VP, Vendor Management Thursday, February 26 th, 2015, 8:00 9:00 a.m. Topics Case Study Company Intro Begin with the End
More informationThe 10 Knowledge Areas & ITTOs
This document is part of a series that explain the newly released PMBOK 5th edition. These documents provide simple explanation and summary of the book. However they do not replace the necessity of reading
More informationOverview of Future Purchasing s fundamental and advanced training workshops...
Performance Learning Presented by: Anna Del Mar - Director, Performance Learning Future Purchasing Overview of Future Purchasing s fundamental and advanced training workshops... Tailored excellence.. Our
More informationIT Purchasing at Penn: Beyond the Basics
IT Purchasing at Penn: Beyond the Basics Business Services Division Purchasing Services www.purchasing.upenn.edu Brent Friedman, Sourcing Manager What we ll cover today Organizational Overview IT Purchasing
More informationFinal. North Carolina Procurement Transformation. Organizational Model March 11, 2011
North Carolina Procurement Transformation Organizational Model March 11, 2011 Table of Contents Executive Summary Approach and Collection Process Recommended Organizational Structure Full-Time Equivalent
More informationOffice for Finance and Administration Treasurer s Division Materials Management Purchasing Department http://www.fis.ncsu.
Office for Finance and Administration Treasurer s Division Materials Management Purchasing Department http://www.fis.ncsu.edu/materialsmgmt/ Campus Box 7212 2721 Sullivan Dr. Raleigh, NC 27695-7212 P:
More informationCOLORADO DEPARTMENT OF PUBLIC HEALTH AND ENVIRONMENT SOLICITATION QUESTIONS AND ANSWERS SOLICITATION #: FHLA2015000000000001
COLORADO DEPARTMENT OF PUBLIC HEALTH AND ENVIRONMENT SOLICITATION QUESTIONS AND ANSWERS SOLICITATION #: FHLA2015000000000001 SOLICITATION NAME: PREVENTION SERVICES DIVISION MARIJUANA PREVENTION AND EDUCATION
More informationQuick Reference Guide Interactive PDF Project Management Processes for a Project
Project Processes for a Project Click the Knowledge Area title (below and left in blue underline) to view the details of each Process Group. Project Process Groups and Knowledge Areas Mapping Project Process
More informationAnalytics Strategy Information Architecture Data Management Analytics Value and Governance Realization
1/22 As a part of Qlik Consulting, works with Customers to assist in shaping strategic elements related to analytics to ensure adoption and success throughout their analytics journey. Qlik Advisory 2/22
More informationModule 1: Supply Chain Design
Module 1: Supply Chain Design Module 1 Introduction Section A: Develop the Supply Chain Strategy Chapter 1: Inputs to Supply Chain Strategy o Topic 1: Business Model o Topic 2: External Inputs to Supply
More informationOptimizing the Source to Contract Process to Maximize and Lock in Savings Patrick Eckhert Cardinal Health Head of Indirect Procurement
Optimizing the Source to Contract Process to Maximize and Lock in Savings Patrick Eckhert Cardinal Health Head of Indirect Procurement Program Goals and Overview Goal Share our strategy and approach for
More informationStrategic e-sourcing Converting Costs into Profits. Ramesh Mehta CEO Moai Technologies Inc.
Strategic e-sourcing Converting Costs into Profits Ramesh Mehta CEO Moai Technologies Inc. What Attendees Will Learn How strategic sourcing can improve a company's profitability in a matter of weeks How
More informationAppendix 3: Project Management Substation Guidelines (General Process Flow Template)
365 Appendix 3: Project Management Substation Guidelines (General Process Flow Template) Checkpoint Methodology The schedule is issued prior to the go decision. It covers the duration of the project. It
More informationIT Standards & Contract Management
Appendix F IT Standards & Table of Contents Vision of Action... 2 Background... 3 Goals and Objectives... 4 Projects... 5 Metrics and Measures... 6 F IT Standards & Carol Steffanni Director, MDIT Bureau
More informationSourcing best practices. 2011 SAP AG. All rights reserved. Internal
Best Practices in Spend Analytics, Sourcing, and Contract Management Emily Rakowski, SAP SAP Procurement Summit: Newtown Square July 31-August 1, 2012 Sourcing best practices 2011 SAP AG. All rights reserved.
More informationProject Integration Management
Integration Initiating ning Executing Monitoring & Controlling Closing 4.1 Develop Charter Statement Of Work Business Case 4.2 Develop 4.3 Direct and Manage Work 4.4 Monitor and Control Work 4.5 Perform
More informationCreative Solutions to Increase Utilization of Strategic Sourcing Agreements. 91 st Annual Meeting & Exposition April 1 4, 2012 Anaheim, California
Creative Solutions to Increase Utilization of Strategic Sourcing Agreements Todd Adams Senior Manager UCSD Central Procurement Nicole Lamb Senior Manager UCSD Strategic Sourcing Increase Utilization of
More informationRequest for Expressions of Interest On a contract to perform: Renewal of Information Technology Strategic Plan 2013-2018
Request for Expressions of Interest On a contract to perform: Renewal of Information Technology Strategic Plan 2013-2018 for City of Pitt Meadows Table of Contents Table of Contents... 2 General Information...
More informationREQUEST FOR INFORMATION for Procurement Front-End System Modernization for The CITY OF PHILADELPHIA PROCUREMENT DEPARTMENT
REQUEST FOR INFORMATION for Procurement Front-End System Modernization for The CITY OF PHILADELPHIA PROCUREMENT DEPARTMENT Issued by: The Office of Innovation and Technology (OIT) June 25, 2014 Vendor
More informationProject Management Body of Knowledge (PMBOK) (An Overview of the Knowledge Areas)
Project Management Body of Knowledge (PMBOK) (An Overview of the Knowledge Areas) Nutek, Inc. 3829 Quarton Road, Suite 102 Bloomfield Hills, Michigan 48302, USA. Phone: 248-540-4827, Email: Support@Nutek-us.com
More informationSTATE OF NORTH CAROLINA
STATE OF NORTH CAROLINA PERFORMANCE AUDIT DEPARTMENT OF ADMINISTRATION, DIVISION OF PURCHASE AND CONTRACT STATE TERM CONTRACTING PROCESS OCTOBER 2010 OFFICE OF THE STATE AUDITOR BETH A. WOOD, CPA STATE
More informationHow Automation is Driving Strategic Sourcing Transformation at Citi
How Automation is Driving Strategic Sourcing Transformation at Citi Michael Krassos SVP Strategic Sourcing & Procurement Services Procurement Systems / Applications Management July 2012 Agenda Who We Are
More informationSourcing and Managing Marketing Agency Spend
Sourcing and Managing Marketing Agency Spend Marika Lindstrom, Director Global Business Services Global Supply Management AMD Inc. Tel. 512/9348465 marika.lindstrom@amd.com 93 rd Annual International Supply
More informationThe fact is that 90% of business strategies are not implemented through operations as intended. Overview
Overview It is important to recognize that a company s network determines its supply chain efficiency and customer satisfaction. Designing an optimal supply chain network means the network must be able
More informationIntroduction to the ITS Project Management Methodology
Introduction to the ITS Project Management Methodology In September 1999 the Joint Legislative Committee on Performance Evaluation and Expenditure Review (PEER) produced a report entitled Major Computer
More informationProcurement Outsourcing and. Shared Service Centers. SANFORD INTERNATIONAL I Global Sourcing I Supply Chain I Procurement I. www.sanfordint.com.
Procurement Outsourcing and Shared Service Centers 3rd Floor Jonsim Place 228 Queen's Road East Wan Chai Hong Kong Telephone: (852) 2861 2222 Fax: (852) 2861 2266 www.sanfordint.com.hk INTRODUCTION Procurement
More informationOversight of Information Technology Projects. Information Technology Audit
O L A OFFICE OF THE LEGISLATIVE AUDITOR STATE OF MINNESOTA FINANCIAL AUDIT DIVISION REPORT Oversight of Information Technology Projects Information Technology Audit May 29, 2009 Report 09-19 FINANCIAL
More informationPractical Cost Savings Strategies
Practical Cost Savings Strategies Eileen G. McLoughlin, Assistant Vice President of Finance and Budgeting Kelli Perry, Assistant Vice President for Finance and Controller Ron Moraski, Director of Procurement
More informationPersonal Service Contract Review Board March 2016
for Personal and Professional Services Procurement Personal Service Contract Review Board How to use this Guide This is an informational guide to be used as a resource for agencies in implementing the
More informationProject Management Plan Template
Abstract: This is the project management plan document for . This is a controlled document and should be maintained in a configuration environment. Project Management Plan Template Contents REVISION
More informationThe Fast Track Project Glossary is organized into four sections for ease of use:
The Fast Track Management Glossary provides a handy reference guide to the fast track management model, encompassing the concepts, steps and strategies used to manage successful projects even in the face
More informationMoving From a Vendor to a Partner Strategy. Chris McSwain Vice President, U.S. Benefits Walmart
Moving From a Vendor to a Partner Strategy Chris McSwain Vice President, U.S. Benefits Walmart Employer Challenges and Key Questions Employer Strategy and Use of Data Vendor / Supplier / Partner Differences
More informationDobre praktyki zarządzania zakupami technologicznymi
Dobre praktyki zarządzania zakupami technologicznymi Leszek Maśniak Executive Partner, Gartner Poland Ministerstwo Administracji i Cyfryzacji, Warszawa 12-10-2014 Gartner at a Glance 6,100 associates 14,000+
More informationTouch Points Touch Points Step 1 Spend Areas Step 2 Creating and Developing a Sourcing Team Executive Sponsorship
Strategic Sourcing: A Step-By-Step Practical Model Robert J. Engel, Vice President-Project Services The Procurement Centre 713-623-0111 Ext. 224; bengel@tpc-usa.com 89 th Annual International Supply Management
More informationDriving State Procurement Decisions Using Business Intelligence 2012 Cronin Award Submission
Driving State Procurement Decisions Using Business Intelligence 2012 Cronin Award Submission 7/3/2012 State of Arizona Jean A. Clark, State Procurement Administrator Executive Summary For years, public
More informationBest Practice Performance Measurement of the Procurement Function
Best Practice Performance Measurement of the Procurement Function How to Identify and Measure Key Performance Indicators and Reporting on the Procurement Function Agenda Importance of measuring Procurement
More informationChallenges in Developing a Small Business Tax payer Burden Model
Challenges in Developing a Small Business Tax payer Burden Model Authors: Don DeLuca Arnold Greenland Audrey Kindlon Michael Stavrianos Presented at the 2003 IRS Research Conference I. Introduction In
More informationOverview of Future Purchasing s fundamental and advanced training workshops...
Performance Learning Presented by: Anna Del Mar - Director, Performance Learning Future Purchasing Overview of Future Purchasing s fundamental and advanced training workshops... Tailored excellence.. Our
More informationEnterprise RIM: Building the Business Case. Steve Gens. Bethesda Maryland: February 25, 2014. Managing Partner Gens and Associates, Inc.
Enterprise RIM: Building the Business Case Bethesda Maryland: February 25, 2014 Steve Gens Managing Partner Gens and Associates, Inc. Disclaimer The views and opinions expressed in the following PowerPoint
More informationSeptember 2005 Report No. 06-009
An Audit Report on The Health and Human Services Commission s Consolidation of Administrative Support Functions Report No. 06-009 John Keel, CPA State Auditor An Audit Report on The Health and Human Services
More informationA Privacy Officer s Guide to Providing Enterprise De-Identification Services. Phase I
IT Management Advisory A Privacy Officer s Guide to Providing Enterprise De-Identification Services Ki Consulting has helped several large healthcare organizations to establish de-identification services
More informationLessons Learned: Ten Ideas for Effective Strategic Sourcing
Lessons Learned: Ten Ideas for Effective Strategic George L. Harris, President Calyptus Consulting Group, Inc. (781) 674-0041; gharris@calyptusgroup.com 91 st Annual International Supply Management Conference,
More informationCrosswalk Between Current and New PMP Task Classifications
Crosswalk Between Current and New PMP Task Classifications Domain 01 Initiating the Project Conduct project selection methods (e.g., cost benefit analysis, selection criteria) through meetings with the
More informationPROJECT MANAGEMENT PLAN <PROJECT NAME>
PROJECT MANAGEMENT PLAN TEMPLATE This Project Management Plan Template is free for you to copy and use on your project and within your organization. We hope that you find this template useful and welcome
More informationStrategic Procurement Services
Strategic Procurement Services Copyright 2013 by Levine, Blaszak, Block & Boothby, LLP and TechCaliber Consulting, LLC. All rights reserved. We have un-paralleled experience running strategic telecom procurements
More informationEnterprise Projects Fiscal Year 2011/2012 Third Quarter Report
Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report Enterprise Projects Fiscal Year 2011/2012 Third Quarter Report The Enterprise Program Investment Council (EPIC) is responsible for governance
More informationwww.pwc.com Next presentation starting soon Next Gen Customer Experience Enabled by PwC & Oracle s Cloud CRM & CX Applications
www.pwc.com Next presentation starting soon Next Gen Customer Experience Enabled by & Oracle s Cloud CRM & CX Applications Agenda Introductions & Customer Experience / CX Defined Why CX is Critical Today?
More informationBUILDING A STRATEGIC PROCUREMENT FUNCTION. William M. Cooper, C.P.M. University of Missouri System
BUILDING A STRATEGIC PROCUREMENT FUNCTION William M. Cooper, C.P.M. University of Missouri System Abstract "Procurement as a function, regardless of the industry, is incredibly strategic to the bottom
More informationBest practices in project and portfolio management
Business white paper Best practices in project and portfolio management Practical advice for achieving greater value and business benefits Table of contents 3 Introduction 3 The importance of best practices
More informationCPM -100: Principles of Project Management
CPM -100: Principles of Project Management Lesson E: Risk and Procurement Management Presented by Sam Lane samlane@aol.com Ph: 703-883-7149 Presented at the IPM 2002 Fall Conference Prepared by the Washington,
More informationRisk Management Primer
Risk Management Primer Purpose: To obtain strong project outcomes by implementing an appropriate risk management process Audience: Project managers, project sponsors, team members and other key stakeholders
More informationDepartment of Management and Budget
Director Debt Deputy Director and Budget FOCUS Business Support Group Budget Development & Production Revenue & Tax Analysis Customer & Information Technology Core Financial Processing Capital Projects/CIP
More informationP200 BENEFIT TRACKING SOURCING BUYERS FOR TRANSACTIONAL AND
P200 BENEFIT TRACKING FOR TRANSACTIONAL AND SOURCING BUYERS To help understand the total benefit achieved through procurement s sourcing, transactional, and other value-add activities. Benefit Tracking
More informationCASE STUDY. Barber Foods. Successful Trade Promotion Optimization Strategy Improves Retail Effectiveness. Challenge. Solution.
CASE STUDY Barber Foods Successful Trade Promotion Optimization Strategy Improves Retail Effectiveness Challenge Faced with escalating trade promotion costs and spend rates exceeding industry averages,
More informationThe Agenda. Strategic Sourcing Defined. Strategic Sourcing Its Beginnings
Strategic Sourcing: Walking the Tightrope in Developing Sourcing Strategy for The Agenda Introduction Developing Sourcing Strategy-5 Phases Thomas L. Tanel, C.P.M., CTL, CCA, CISCM, President and CEO CATTAN
More informationStep by Step Project Planning
Step by Step Project Planning Contents Introduction The Planning Process 1 Create a Project Plan...1 Create a Resource Plan...1 Create a Financial Plan...1 Create a Quality Plan...2 Create a Risk Plan...2
More informationData Integration Initiative Semi Annual Report April 2009. State of North Carolina Office of the State Controller
Data Integration Initiative Semi Annual Report April 2009 State of North Carolina Office of the State Controller David McCoy, State Controller April 1, 2009 Table of Contents I. Background... 1 II. BEACON
More informationPMP Examination Tasks Puzzle game
PMP Examination Tasks Puzzle game Here is a great game to play to test your knowledge of the tasks you will be tested on in the actual examination. What we have done is take each of the domain tasks in
More informationGartner, Inc. DIR-SDD-2042
Texas Department of Information Resources STATEMENT OF WORK (SOW) FOR DELIVERABLES-BASED INFORMATION TECHNOLOGY SERVICES Identity & Access Management Analysis IT Assessment & Planning Gartner, Inc. DIR-SDD-2042
More informationComputing Services Network Project Methodology
Computing Services Network Project Prepared By: Todd Brindley, CSN Project Version # 1.0 Updated on 09/15/2008 Version 1.0 Page 1 MANAGEMENT PLANNING Project : Version Control Version Date Author Change
More informationSound Transit Internal Audit Report - No. 2014-3
Sound Transit Internal Audit Report - No. 2014-3 IT Project Management Report Date: Dec. 26, 2014 Table of Contents Page Background 2 Audit Approach and Methodology 2 Summary of Results 4 Findings & Management
More informationSupplier Management & Procurement Strategies for Facility Managers
Supplier Management & Procurement Strategies for Facility Managers Vision Statement The FMCC is the resource and voice for Facility Management Consultants worldwide to leverage our collective expertise
More informationUC San Diego Commodity Strategy and Spend Analysis
UC San Diego Commodity Strategy and Spend Analysis October 6, 2008 Gayle Ta and Bob Neuhard Topics Commodity Strategy Commodity Analysis Strategy Development Key Performance Indicators and Metrics Executive
More informationCritical Steps to Help Small and Mid-Sized Businesses Ensure CRM Success
Critical Steps to Help Small and Mid-Sized Businesses Ensure CRM Success Table of Contents Abstract............................................ 3 CRM Drivers and Benefits............................. 4
More informationProgram Management Professional (PgMP) Examination Content Outline
Program Management Professional (PgMP) Examination Content Outline Project Management Institute Program Management Professional (PgMP ) Examination Content Outline April 2011 Published by: Project Management
More informationPROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE:
PROJECT MANAGEMENT PLAN Outline VERSION 0.0 STATUS: OUTLINE DATE: Project Name Project Management Plan Document Information Document Title Version Author Owner Project Management Plan Amendment History
More informationCompany A Project Plan
Company A Project Plan Project Name: Close Optimization Project Example Prepared By: David Done - Project Manager Title: John Doe -Project Manager Date: March 17, 2011 Project Plan Approval Signatures
More informationProject Start Up. Start-Up Check List. Why a Project Check List? What is a Project Check List? Initial Release 1.0 Date: January 1997
Why a Project Check List? A good way to ensure that all start-up tasks are completed prior to actually starting the project is to develop a start-up check list. The check list can be developed and then
More informationPROJECT PROCUREMENT MANAGEMENT
12 PROJECT PROCUREMENT MANAGEMENT Project Procurement Management includes the processes required to acquire goods and services from outside the performing organization. For simplicity, goods and services,
More informationChapter 3 VITA s Supply Chain Management (SCM)
Chapter 3 VITA s Supply Chain Management (SCM) Chapter highlights Purpose: This chapter outlines VITA s Supply Chain Management s (SCM s) vision, mission, core values and guiding principles. It also discusses
More informationPROJECT PLAN FOR. Project Name Here
PROJECT PLAN FOR Project Name Here Version # DatE Reviewed and Approved for submittal to Executive Sponsor , Project Manager Project Plan Approved for submittal to Executive Sponsor: , Project
More informationDescription of Program Management Processes (Initiating, Planning) 2011 PROGstudy.com. All rights reserved
Description of Program Management Processes (Initiating, Planning) Topics Covered Program Management Process Groups salient features Description of all processes in Initiating Process Group: Initiate Program
More informationManagement Principles and the RIM Program
Management Principles and the Records and Information Management (RIM) Program Management Principles and the RIM Program Principles of Management Human Resources/Staffing Methodologies Financial Considerations
More informationCertification Exam Objectives: PK0-003
Certification Exam Objectives: PK0-003 INTRODUCTION The CompTIA Project + examination is designed for business professionals involved with projects. This exam will certify that the successful candidate
More informationSeptember 17, 1:00 PM. Dean Sorensen, Founder, IBP Collaborative
BUSINESS FORECASTING AND INNOVATION FORUM 2015 September 17-18, 2015 Boston, MA September 17, 1:00 PM Track A Session: Transforming FP&A via Strategic, Financial & Operational Integration Improve forecast
More informationRFP 2013-16: Change Management Consulting for Enrollment Functionality Improvements Final Response to Questions 5/7/2014
1 Has Covered California performed any high level assessments of the changes for the upcoming open enrollment? If yes, please share the relevant details. 2 Please describe activities under post Go-live
More informationInput, Output and Tools of all Processes
1 CIS12-3 IT Project Management Input, Output and Tools of all Processes Marc Conrad D104 (Park Square Building) Marc.Conrad@luton.ac.uk 26/02/2013 18:22:06 Marc Conrad - University of Luton 1 2 Mgmt /
More informationThe Anatomy of an RFP Relocation Services. Yvonne Bosson, CRP, GMS www.ybosson.com bosson@ybosson.com 214.499.0237
The Anatomy of an RFP Relocation Services Yvonne Bosson, CRP, GMS www.ybosson.com bosson@ybosson.com 214.499.0237 Agenda Definitions Pre-Work Development Launch Supplier Evaluation Supplier Selection Award
More informationPROCUREMENT DEPARTMENT FISCAL YEAR 2016 BUDGET TESTIMONY APRIL 22, 2015 EXECUTIVE SUMMARY
PROCUREMENT DEPARTMENT FISCAL YEAR 2016 BUDGET TESTIMONY APRIL 22, 2015 EXECUTIVE SUMMARY DEPARTMENT MISSION AND FUNCTION Mission: To obtain and dispose of quality goods, services, construction, and concessions
More informationSkatteudvalget 2014-15 (2. samling) SAU Alm.del Bilag 48 Offentligt. Programme, Project & Service Management Analysis
Skatteudvalget 2014-15 (2. samling) SAU Alm.del Bilag 48 Offentligt Programme, Project & Service Management Analysis Table of Content 1 Executive Summary... 3 1.1 Scope of Work... 3 1.2 Methodology for
More informationIntroduction. Table of Contents
Introduction To stay competitive, you know how important it is to find new ways to streamline and save on your company s operations. Learning how leading companies handle commercial payments can give you
More informationUNIVERSITY HOSPITAL POLICY
UNIVERSITY HOSPITAL POLICY SUBJECT: PURCHASING SERVICES TITLE: PURCHASING PROCESS Responsible Executive: Executive Director, Supply Chain Management Responsible Office: Supply Chain Management CODING:
More informationMary Peterson, Commissioner, Department of Taxes. Annual Report on the Tax Computer System Modernization Fund
TO: FROM: The Joint Fiscal Committee Mary Peterson, Commissioner, Department of Taxes DATE: November 13, 2015 SUBJECT: Annual Report on the Tax Computer System Modernization Fund The Tax Computer System
More informationVISA COMMERCIAL SOLUTIONS BEST PRACTICES SUMMARIES. Profit from the experience of best-in-class companies.
VISA COMMERCIAL SOLUTIONS BEST PRACTICES SUMMARIES Profit from the experience of best-in-class companies. Introduction To stay competitive, you know how important it is to find new ways to streamline and
More informationBusiness Support Services Assessment Communications Plan
Business Support Services Assessment Communications Plan Background In his budget message in May of 2010 and Memorandum to employees in October 2010, County Manager Harry Jones said that the new economic
More informationConcept of Operations for Line of Business Initiatives
Concept of Operations for Line of Business Initiatives Version 1.0 Office of E-Gov and IT, OMB March 2006 Table of Contents FOREWORD...2 1 OBJECTIVES OF THE LINES OF BUSINESS CONCEPT OF OPERATIONS...3
More informationPennsylvania Act 129 Phase I Economic Impact Assessment Report
Pennsylvania Act 129 Phase I Economic Impact Assessment Report Bureau of Technical Utility Services PA Public Utility Commission August 2014 Statement of Intent On February 25, 2014 Commissioner Cawley
More informationComptroller of Public Accounts. State of Texas Cooperative Purchasing Manual
Comptroller of Public Accounts State of Texas Cooperative Purchasing Manual 1 Table of Contents I. Introduction 3 II. Membership Basics 4 Membership Code and Status Updating Contact Information and Authorized
More information