1 IGBC Green Room Diageo Brewhouse No. 4 Case Study Sean Hogan RKD Architects Thursday 21 st May 2015
2 Agenda St. James s Gate A Brewing History Diageo Drive to Sustainability Brewhouse No. 4
3 St. James s Gate A Brewing History St. James s Gate site is in excess of 50 acres in the Western part of Dublin City Site is split by James s Street in to two areas, the north and south lands Over 250 years brewing into a 9000 year lease
4 Diageo Drive to Sustainability Global Initiatives Carbon reductions Sustainable Sourcing Reduced Waste Water Efficiency
5 Diageo Drive to Sustainability
6 Diageo Drive to Sustainability
7 Diageo Drive to Sustainability
8 Brewhouse No. 4 Project Phoenix Part of Project Phoenix, a 159m capital investment at St James Gate Includes brewhouse, fermentation block and new Waste Water Neutralisation Plant (WWNP) One of the largest brewing projects worldwide Approx. 1,000 site workers at peak construction 1,000 tonnes of structural steel, 2000 tonnes of reinforcement 10,000m³ of reinforced concrete - 2,000m² stone cladding
9 Brewhouse No. 4 9,315m² on a 2.7 hectare site Brew hall Raw Materials Handling Control Room Offices, VIP Space, Welfare Facilities Laboratory and workshop Tank Farm, Trucking Staging Yard
10 Brewhouse No m hours dedicated to sustainability
11 Brewhouse No. 4 The Journey
12 Brewhouse No. 4
13 Brewhouse No. 4
14 Brewhouse No. 4
15 Brewhouse No. 4
16 Brewhouse No. 4
17 Brewhouse No. 4 Sustainable Brewing St. James s Gate 3 million pints of stout, ales and lagers per day, 35% global beer supply 600 tonnes of grain at daily peak period Brewhouse 4 Only 14% less water to make a brew 10% less CO2/GHG, 8% less electricity, 33% less thermal energy to make 1 pint
18 Brewhouse No. 4 Concept and schematic design Early design developed under EED June 2012 Feasibility study of green building certifications What is it? Why seek it? What can this project achieve? Where is the base design at? Where design uplift is required What does the project team need to do? What will it cost?
19 Brewhouse No. 4 Concept and schematic design Decision - Assemble- Make Brewhouse 4 the most energy efficient brewery in the world and seek highest possible level of certification for LEED for New Construction 2009 AND BREEAM Europe Commercial 2009 Dedicated sustainability team to supplement the existing project team and form integrated design team Sustainability Project Manager Client sustainability Champion, Contractor Sustainability Champion Energy Specialist LEEP AP, BREEAM Assessor Energy Modeller Independent Commissioning Agent Specialist consultants (ecologist, acoustician)
20 Brewhouse No. 4 Detailed Design/Construction Sustainability section added to Design Team meetings Sustainability Charrettes Roles and Responsibilities Credit Tracker Client Sustainability champion regularly updated and requests for information/decisions reviewed LEED and BREEAM requirements added to specifications Dedicated LEED BREEAM Review at site commencement Monthly Site Audits, fortnightly progress reports Steering/Principals Meetings
21 Brewhouse No. 4 Sustainable Sites Brownfield regeneration project Leverage off existing residential population, local diverse uses and public transport links No increased parking footprint, existing parking converted to preferred spaces for car pooling and low emitting fuel efficient vehicles Bikes stands, showers, changing rooms provided Heat island effect reduced through 30% GGBS in concrete for yard, painted white roof membrane Contractor implemented an ESC plan Contractor ran a considerate contractors site 5 year landscape and habitat management plan
22 Brewhouse No. 4 Water Efficiency 54% reduction over baseline water use for building services water No external irrigation Low flow fixtures, aerators on showers and sanitary supply shut off of fittings
23 Brewhouse No. 4 Energy & Atmosphere Installation of energy recovery system reducing requirement for steam heating in the brewing process, maximises the thermal energy recovered and minimises vapour losses from the brew house and atmosphere Installation of variable speed drives on the majority of process drives Installation of a hybrid refrigeration system aiming to use 0 instead of -4 Improved metering throughout the brewing process Target Air tightness of 3m 3 /(m 2 Pa, 2.7m 3 /(m 2 Pa
24 Brewhouse No. 4 Energy & Atmosphere Automatic lighting controls complete with high efficiency lighting and occupancy sensors HVAC systems condition through mechanical ventilation with specific fan power levels ensuring only a small portion of the building is air conditioned HVAC plant has been specified and procured based on low energy usage, fan speeds and high efficiency. A combined heat & power plant (CHP) provides electrical energy for the entire building HVAC and process plant and utilises 100% of the thermal energy for building services and process heating.
25 Brewhouse No. 4 Energy & Atmosphere Energy modelled using DSM (with SEAI approval), due to building complexity % improvement over local building regulations - BER A1 rated, carbon neutral building, first non domestic A1
26 Brewhouse No. 4 Materials and Resources Zero waste to landfill for construction and operation Waste collection point for waste segregation and collection and delivery to central site waste management point 14% of total materials costs accounts for recycled materials Reinforcement, structural steel, 30% GGBS in concrete 20% of materials cost account for regional materials
27 Brewhouse No. 4 Indoor Environmental Quality Dedicated smoking shelters away from air intake CO2 monitoring of regularly occupied spaces Increased breathing zone outdoor air ventilation rates by at least 30% above the minimum required rates. Ventilation and temperature controls provided to 64% of the occupants. Potential for natural ventilation in occupied spaces Increased ventilation, CO2 monitoring of mechanical systems Contractors IAQ Plan Post Occupancy Evaluations Low VOC materials specified for paints, coatings, sealants, adhesives
28 Brewhouse No. 4 Innovation LEED AP appointed to the project Monitoring based commissioning procedures as a pilot credit HVAC noise level designed to be 5db lower than baseline acoustic modelling and no louder than 60db at nearest property line
29 Brewhouse No. 4 Results LEED Sustainable Sites 21/26 Water Efficiency 10/10 Energy & Atmosphere 32/35 Materials & Resources 5/14 Innovation 6/6 Regional Priority 4/4 Total 89/110 BREEAM Management 82 Health & Wellbeing 86 Energy 100 Transport 80 Water 78 Materials 45 Waste 100 Land Use & Ecology 70 Pollution 91 Innovation 90 Total 91%
30 Brewhouse No. 4 BREEAM
31 Brewhouse No. 4 LEED
32 Brewhouse No. 4 LEED & BREEAM Video
BAM CONSTRUCT. Dunsbury Hill Farm. BREEAM Pre-assessment Summary. BAM Sustainability department 2015
BAM CONSTRUCT Dunsbury Hill Farm BREEAM Pre-assessment Summary BAM Sustainability department 2015 1.0 Introduction This report is intended as a summary of the pre-assessment for the following BREEAM assessment:
More informationPOMONA COLLEGE Sustainability Integration Office Facilities and Campus Services
POMONA COLLEGE Sustainability Integration Office Facilities and Campus Services May 200 Table of Contents NEW CONSTRUCTION/MAJOR RENOVATION Process... Design... 3 MINOR RENOVATIONS/PROJECTS Process...
More information100% 50% 92% 99% LEED Facts PROJECT HIGHLIGHTS. Multi-occupant spaces have adjustable thermostats and lighting. Reduced water usage for landscaping
UNIVERSITY OF RICHMOND CAROLE WEINSTEIN INTERNATIONAL CENTER 28 Westhampton Way, Richmond VA 23173 LEED NC v2.2 GOLD 2015 Completed in 2010, the Carole Weinstein International Center showcases the University
More informationSiemens Gebze Location FIRST GREEN BUILDING IN TURKEY CERTIFICIED AS LEED GOLD
FIRST GREEN BUILDING IN TURKEY CERTIFICIED AS LEED GOLD Slide 1 Energy Efficiency Workshop with KFW & TSKB Sep 28th, 2010 The LEED Green Building Rating System is a voluntary standard that defines high
More informationHHHHH Outstanding 85%
Provinciehuis_Assessment_2040204_74,32%Final Score and Rating BREEAM Scheme: Europe 2009: Offices H Pass 30% Building Name: Provinciehuis Antwerpen HH Good 45% BREEAM Registration No.: BREEAM-0048-4626
More informationBREEAM Refurbishment and Fit-out 2014 Briefings. Part of the BRE Trust
BREEAM Refurbishment and Fit-out 2014 Briefings Part of the BRE Trust BREEAM for Refurbishment and Fit-out Follows 2 years of development Draft scheme published and consultation from 19 th July 2014 Launched
More informationGreen House, Hungary
Further information Skanska AB www.skanska.com Contact Noel Morrin, SVP Sustainability & Green Support noel.morrin@skanska.se Green House, Hungary Case Study 109 Aspects of Sustainability This project
More informationArchant London Environmental Awards
Archant London Environmental Awards Environmental Business of the Year Big Yellow Self Storage PLC Barking Central, Hertford Road, Barking, IG11 8BL Introduction Big Yellow is a local business that has
More informationLos Angeles Mission College Facilities Master Plan Draft Program Environmental Impact Report 3.5 ENERGY CONSERVATION AND SUSTAINABILITY.
3.5 ENERGY CONSERVATION AND SUSTAINABILITY As a result of the analysis undertaken in the Initial Study 1 for the Los Angeles Mission College Facilities Master Plan, the LACCD determined that the proposed
More informationGREEN DEVELOPMENT PLAN Developer Name: Project Name: Address (Street/City/State) Description of Process. Goals. Design & Development Team Members Name
GREEN DEVELOPMENT PLAN Developer Name: Project Name: Address (Street/City/State) Description of Process A description of the process that was used to select the green building strategies, systems and materials
More information34% 81% 84% 19% GOLD PROJECT HIGHLIGHTS. LEED Facts. Stubbs Laboratory
HARVARD UNIVERSITY FACULTY OF ARTS AND SCIENCES LEED-CI V3.0 STUBBS LABORATORY GORDON MCKAY LABS BUILDING Gordon McKay Building, 9 Oxford Street, Cambridge, MA 02138 GOLD The Stubbs Laboratory is a 2,035
More informationTTU Green Standards. TTU Green Standards
For our rapidly expanding on-campus student residence halls, Texas Tech University felt strongly that LEED guidelines and practices would be employed. This new 457 bed, 234,500 square foot residence hall
More informationBREEAM Europe. This presentation aims to give the reader a general overview of the operational and technical aspects of BREEAM Europe.
BREEAM Europe BREEAM Europe This presentation aims to give the reader a general overview of the operational and technical aspects of BREEAM Europe. Key objectives Provide consistency and comparability
More informationEarthCents (DSM) Program Summary
EarthCents (DSM) Program Summary Renewable Energy EarthCents Programs Solar Water Heating This program is available to residential customers for the installation of a qualifying solar thermal water heater.
More informationLEED PRESENTATION OUTLINE
16902 BOLSA CHICA STREET, SUITE 101 HUNTINGTON BEACH, CA 92649 TELEPHONE (714) 840-8230 FACSIMILE (714) 840-2490 LEED PRESENTATION OUTLINE I. Overview of Green Building and Risks Involved with Sustainability
More informationSika Sarnafil World Class Roofing and Waterproofing
The following is a brief summary of the Leadership in Energy and Environmental Design program (LEED, Version 3) and the sections Sika Sarnafil s roofing systems can help contribute to obtaining LEED points.
More informationSustainable Features. High-performance HVAC. High-performance Envelope Green Roof Day-Lighting Bicycle Infrastructure
Sustainable Features High-performance HVAC High-performance Envelope Green Roof Day-Lighting Bicycle Infrastructure Sustainable Landscaping Recycled and Regional Materials Storm-water Management District
More informationALWAYS ON GLOBALSWITCH.COM
ALWAYS ON GLOBALSWITCH.COM Data Centre Design Considerations Kelvin Fong Managing Director, Hong Kong ALWAYS ON GLOBALSWITCH.COM Agenda 1. Introduction to Global Switch 2. Customer Requirements 3. Development
More informationCode for Sustainable Homes Guidelines
Canoldir Penrhos Anglesey LL65 2TS Phone: 01407 860666 Email: saps@easonline.co.uk www.easonline.co.uk Code for Sustainable Homes Guidelines A CSH rating is the responsibility of the Developer/ Architect
More informationSustainable Strategies for Rehabilitation Projects: 9th Street Office Building Adaptive Reuse Case Study
Sustainable Strategies for Rehabilitation Projects: 9th Street Office Building Adaptive Reuse Case Study Robert C. Burns, AIA, LEED AP Principal Director of Historic Architecture 804. 648. 5040, ext. 1107
More informationSouthShore HILLSBOROUGH COMMUNITY COLLEGE
SouthShore HILLSBOROUGH COMMUNITY COLLEGE The opening of Hillsborough Community College s fifth campus, the SouthShore Center, marks an exciting milestone for the college and will open an exciting new
More informationElaine Harvie & Jeremy Cruickshank Jan 10
Elaine Harvie & Jeremy Cruickshank Jan 10 3 Assembly Square, Cardiff - EXCELLENT BREEAM International Introduction Elaine Harvie Mechanical Engineer BREEAM Assessor Offices School/Education Industrial
More informationCLEAN GREEN & SUSTAINABLE NS1439215
CLEAN GREEN & SUSTAINABLE NS1439215 1 Contents 2 Introduction Strategic Alignment 1 - Energy Efficiency 2 - Water Management 3 - Fleet and Plant Management 4 - Carbon Offsets 5 - Waste Management Everything
More informationEnergy from digester gas. Optimised biogas utilisation
Energy from digester gas Optimised biogas utilisation The complete solution The complete solution Our company ENER-G designs, installs and operates biogas combined heat and power (CHP) systems for a variety
More informationBOMA BESt AND LEED EBOM COMPARISON
BOMA BESt AND LEED EBOM COMPARISON INTERNATIONAL FACILITY MANAGEMENT ASSOCIATION James Furlong, CET, LEED AP - Senior Associate, Stantec Consulting Ltd. BOMA BESt BOMA - Building Owners and Managers Association
More informationEnergy and Sustainability-- Green IT in a holistic approach to slashing energy use, emissions and the impact to the environment
Energy and Sustainability-- Green IT in a holistic approach to slashing energy use, emissions and the impact to the environment Pieter Duijves, Director EMEA/Managing Principal Tanya Starr, LEED AP, DC
More informationThe Raleigh Convention Center Raleigh, North Carolina Green Building Education A Self Guided Walking Tour
The Raleigh Convention Center Raleigh, North Carolina Green Building Education A Self Guided Walking Tour Building Dedication Ceremony September 05, 2008 An evening view of the west facing Shimmer Wall
More informationCarbon Management Plan
E-2015-02-02 Addendum Carbon Management Plan Date: 14 May 2014 Owners: Approval: K.W.Bullimore & M.Sackett A.Burrell Executive Summary This document sets out the Carbon Management Plan (CMP) for The Open
More informationIALN11006400 /05 01 19.06.13. FAO: The Planning Department The Royal Borough of Windsor and Maidenhead Town Hall, St. Ives Road Maidenhead SL6 1RF
IALN11006400 /05 01 19.06.13 FAO: The Planning Department The Royal Borough of Windsor and Maidenhead Town Hall, St. Ives Road Maidenhead SL6 1RF Dear Sir / Madam Re: 12/02994 BCA Sports Hall Condition
More informationThe Integrated Design Process
The Integrated Design Process The Integrated Design Process (IDP) has been developed on the basis of experience gained from a small Canadian demonstration program for high-performance buildings, the C2000
More informationOur Triple Bottom Line...
Our Triple Bottom Line... A Better Approach We embrace what we consider to be our responsibility as developers to balance profits with environmental and social dividends. We believe that our long-term
More informationHow To Calculate Cost Of An Eco-Friendly Building
THE ECONOMICS OF LEED FOR EXISTING BUILDINGS FOR INDIVIDUAL BUILDINGS 2008 EDITION A WHITE PAPER BY LEONARDO ACADEMY INC. Revised February 2, 2009 APRIL 21, 2008 THIS WHITE PAPER SPONSORED BY JOHNSON CONTROLS
More informationTransportation assistance parents are encouraged to car pool when driving to schools
s Towards Carbon Neutrality The actions listed below contribute to a reduction in greenhouse gas emissions from sources for which public sector organizations are responsible under the carbon neutral government
More informationIt s not just about the environment
Supply Chain Consultancy It s not just about the environment Sustainable Supply Chains Paul Goose discusses the need to take a wider, more integrated view of operations to ensure long term growth. A great
More informationQ. Why have we set up an energy centre and heat network in Bunhill?
FAQs: Bunhill energy centre and heat network Q. Why have we set up an energy centre and heat network in Bunhill? A. We set up a heat network in the Bunhill ward to provide cheaper, greener, locallyproduced
More informationFEDERAL LEADERSHIP IN HIGH PERFORMANCE and SUSTAINABLE BUILDINGS MEMORANDUM OF UNDERSTANDING
FEDERAL LEADERSHIP IN HIGH PERFORMANCE and SUSTAINABLE BUILDINGS MEMORANDUM OF UNDERSTANDING PURPOSE: With this Memorandum of Understanding (MOU), signatory agencies commit to federal leadership in the
More information2010 LEED Application Guide for Multiple Buildings and On-Campus Building Projects (2010 AGMBC)
2010 LEED Application Guide for Multiple Buildings and On-Campus Building Projects (2010 AGMBC) For Use with 2009 LEED Rating Systems for Design and Construction and Operations and Maintenance Published
More informationThe Future of Airport Design.. Sara Beardsley, AIA, LEED AP Senior Architect
The Future of Airport Design.. Sara Beardsley, AIA, LEED AP Senior Architect Form follows PerFormance FKI Headquarters Tower Exterior Wall FKI Headquarters Tower Exterior Wall Energy Collection FKI Headquarters
More informationBOMA BESt Assessment Overview
BOMA BESt Assessment Overview BOMA Building Environmental Standards OFFICE Module August 2013 The Voice of the Commercial Real Estate Industry in Canada The Building Owners and Managers Association of
More informationBUILDING PERFORMANCE METRICS
BUILDING PERFORMANCE METRICS Hugh Crowther P. Eng. Executive Vice President, Product Management and Technology There is a steady and determined march towards designing better and better performing buildings.
More informationSUSTAINABLE BUILDINGS
SUSTAINABLE BUILDINGS ACHIEVING A BREEAM EXCELLENT RATING GUIDANCE NOTE FOR BREEAM 2008 ASSESSMENTS Document Issued January 2009 CURRENT REQUIREMENTS: The Welsh Assembly Government has a duty to have a
More informationGoing for LEED Gold: SUSTAINABLE DESIGN IN THE RICHARD IVEY BUILDING
Going for LEED Gold: SUSTAINABLE DESIGN IN THE RICHARD IVEY BUILDING Natural lighting is an important tool in attaining sustainability. Using large windows and glass enclosures to bring in natural light
More informationGreen Globes for New Construction Pre-Assessment Checklist for Project Managers
1 Green Globes for New Construction Pre-Assessment Checklist for Project Managers What is Stage I assessment? As the design phase draws to a close, and your Green Globes questionnaire is completed through
More informationHow To Improve A Building
SUSTAINABILITY TRIFECTA Three Approaches to Campus Sustainability Mike Reca Associate VP Facilities & Auxiliary Services Rider University Frank Sherman Director of Sustainability Spiezle Architectural
More informationSustainability: Green hotels
Sustainability: Green hotels 10 October 2013 How green is your hotel? Azita Dezfouli and Adam Mactavish of Sweett Group look at the practical steps for reducing the environmental impact of hotels during
More informationenergy in education promoting energy efficiency in schools
The DART Energy Research Programme Recognising that the programme should be as much about people and changing cultures while delivering service the approach was developed initially through the four different
More informationIntegrating Landscape Irrigation Control With Building Automation Issues and Opportunities
Integrating Landscape Irrigation Control With Building Automation Issues and Opportunities Gaylen Atkinson, Chairman and Founder, Atkinson Electronics Inc. Salt Lake City, UT April 27, 2015 Agenda Benefits
More informationIndustrial Green Building Retrofit 101 Opportunities and Challenges. Light Industrial Green Building Retrofits. Why Green Retrofit?
Industrial Green Building 101 Opportunities and Challenges Joanne Sawatzky Senior Project Manager, Light House Sustainability at Work Re-visioning a Sustainable False Creek Flats Light Industrial Green
More informationAssessment Methods. 15 th November 2010 Huw Jenkins Simon Lannon
Assessment Methods 15 th November 2010 Huw Jenkins Simon Lannon Assessment Methods Program Country Year Program Country Year 1 R-2000 Canada 1982 12 LEED US 2000 2 P-mark Sweden 1989 13 ECO-Quantum Netherlands
More informationSkanska Residential UK
Skanska Residential UK Skanska Residential UK Skanska Residential UK Skanska Residential UK Local presence global strength Norway United States United Kingdom Denmark Czech Republic Finland Estonia Sweden
More informationUniversity of Melbourne Symposium on ICT Sustainability Dan Pointon 25 November 2008
University of Melbourne Symposium on ICT Sustainability Dan Pointon 25 November 2008 Contents Welcome and Introduction Chapter 1: Data centre energy recap Chapter 2: Co-generation Chapter 3: CTC case study
More informationAdvanced Energy Design Guide LEED Strategies for Schools. and High Performance Buildings
Advanced Energy Design Guide LEED Strategies for Schools and High Performance Buildings Today s Presenters Stephen Koontz, LEED AP Energy Services Leader Tampa Bay Trane Allen Irvine General Sales Manager
More informationUniversity Center Texas State Technical College Harlingen
SUSTAINABLE LEARNING ENVIRONMENTS: REGIONAL CASE STUDIES OF HIGH PERFORMANCE BUILDINGS University Center Texas State Technical College Harlingen David Gutierrez, LEED AP New Construction Case Study: University
More informationChallenges and Failures in Green Building Design Using Under-Floor Air Distribution. Ken Urbanek, PE, HBDP, LEED AP Director of Engineering
Challenges and Failures in Green Building Design Using Under-Floor Air Distribution Ken Urbanek, PE, HBDP, LEED AP Director of Engineering Agenda UFAD Overview Challenges / Failures Steps for a Successful
More informationwww.adaptcbe.co.uk Business Support
www.adaptcbe.co.uk Business Support Events and Seminars The UEA Exemplar Low Carbon Building Project was awarded 6.2m from the European Regional Development Fund in October 2011. As a condition of this
More informationBCA Green Mark for Restaurants
BCA Green Mark for Restaurants Updated: 10/5/2011 1 Point Allocations - BCA Green Mark for Restaurants (I) Energy Related Requirements Part 1 : Energy Efficiency Category Point Allocations Minimum 20 points
More informationDesign Guide. Retrofitting Options For HVAC Systems In Live Performance Venues
Design Guide Retrofitting Options For HVAC Systems In Live Performance Venues Heating, ventilation and air conditioning (HVAC) systems are major energy consumers in live performance venues. For this reason,
More informationBloomsbury Colleges Environmental Policy Statement
15 December 2011 P a g e 1 Bloomsbury Colleges Environmental Policy Statement The Bloomsbury Colleges are committed to the responsible use of energy, water and other resources with the aim of minimising
More informationTOWARD A SUSTAINABLE DALLAS
TOWARD A SUSTAINABLE DALLAS An Overview of LEED, Green Building Programs and recommendations for next steps Presented to the Dallas City Council OCTOBER 17, 2007 w w w. d a l l a s c i t y h a l l. c o
More information125 Mount Auburn Second Floor Office Renovation LEED-CI Silver, September 2008
125 Mount Auburn Second Floor Office Renovation LEED-CI Silver, September 2008 The Harvard Law School s 125 Mount Auburn office renovation project team was committed to sustainable design and construction,
More informationEnergy Efficiency Opportunities Report 2010. Continuing our sustainability journey
Energy Efficiency Opportunities Report 2010 Continuing our sustainability journey Contents Our sustainability journey 2 Commonwealth Bank Place 2 Extending solar photovoltaic expertise to our customers
More informationComponents HVAC General Standards HVAC Guidelines HVAC System Selection Life Cycle Cost Analysis
Components HVAC General System Selection Life Cycle Cost Analysis Outdoor Air Design Values Indoor Air Design Values Outdoor Air Ventilation Welding Ventilation Temperature Control Systems Ductwork HVAC
More informationHOW TO CONDUCT ENERGY SAVINGS ANALYSIS IN A FACILITY VALUE ENGINEERING STUDY
HOW TO CONDUCT ENERGY SAVINGS ANALYSIS IN A FACILITY VALUE ENGINEERING STUDY Benson Kwong, CVS, PE, CEM, LEED AP, CCE envergie consulting, LLC Biography Benson Kwong is an independent consultant providing
More informationIntroduction to Waste Treatment Technologies. Contents. Household waste
Contents Introduction to waste treatment technologies 3 Section 1: The treatment of recyclable waste 4 Bulking facilities 5 Materials Reclamation Facility (MRF) 6 Reuse and recycling centres 8 Composting
More informationHeat Recovery from Data Centres Conference Designing Energy Efficient Data Centres
What factors determine the energy efficiency of a data centre? Where is the energy used? Local Climate Data Hall Temperatures Chiller / DX Energy Condenser / Dry Cooler / Cooling Tower Energy Pump Energy
More informationConstruction Indoor Air Quality Management Plans for LEED. Matt Gregg, PE, LEED AP
Construction Indoor Air Quality Management Plans for LEED Matt Gregg, PE, LEED AP Agenda What is a Construction IAQ Management Plan? What are the LEED Requirements? What is the Mechanical Contractor s
More informationENERGY EFFICIENCY EXPERTS. MCW's. Environmental Record. Green Design REDUCING OUR CLIENTS' ENVIRONMENTAL FOOTPRINT
ENERGY EFFICIENCY EXPERTS MCW's Environmental Record Green Design ENERGY EFFICIENCY EXPERTS Green Design The MCW Group of Companies have created the largest block of verified carbon emissions savings of
More informationGreen Codes & IGCC Update
City of Houston Code Enforcement Green Codes & IGCC Update CATEE Conference Dallas, TX November 9, 2011 Sheila Blake MBA, CBO, LEED AP Assistant Director, PWE Planning and Development Services 1 Houston
More informationBeyond Code Programs: Design Strategies and Best Practices. Eric Makela, Britt/Makela Group
Beyond Code Programs: Design Strategies and Best Practices Eric Makela, Britt/Makela Group Keys to an Effective Beyond Code Program Stakeholders involvement in the decision making process, Established
More informationGreen Buildings Guidelines for Harvard
Green Buildings Guidelines for Harvard Presentation to the Administrative Deans. October 26th 2007 Leith Sharp, Director, Harvard Green Campus Initiative What is a Green Building? Average Savings of Green
More informationLEED GOLD CERTIFIED OFFICE DESIGN AND CONSTRUCTION
LEED GOLD CERTIFIED OFFICE DESIGN AND CONSTRUCTION Setting a Precedent for Sustainable Interior Commercial Design FLEXIBLE INNOVATIVE CREATIVE R E S P O N S I B L E We transformed our lower Manhattan office
More informationMTA UNIVERSAL STATION PEDESTRIAN BRIDGE Los Angeles, CA. Project Manual and Specification 100% PE SUBMITTAL TABLE OF CONTENTS
Los Angeles, CA Project Manual and Specification DIVISION 1 GENERAL CONDITIONS 01 01 10 STATEMENT OF WORK 01 11 00 SUMMARY OF THE WORK 01 14 05 METRO (OWNER) - DIRECTED STOPPAGES 01 20 00 PRICE AND PAYMENT
More informationSUSTAINABLE ENERGY ACTION PLAN AND SOLAR PILOT PROJECTS
T&E AGENDA: 03 05 07 ITEM: 6 TO: TRANSPORTATION & ENVIRONMENT COMMITTEE FROM: John Stufflebean Peter Jensen SUBJECT: SEE BELOW DATE: 02 20 07 Approved Date SUBJECT: SUSTAINABLE ENERGY ACTION PLAN AND SOLAR
More informationGreen Warehouses & Distribution Centers
Green Warehouses & Distribution Centers From Theory To Practice Serkan Emin LEED AP, CEM Emre ILICALI LEED AP, BREEAM Assessor Our Services Green Buildings - LEED Certification Management - BREEAM Certification
More informationIEQ Management Plan. Denver Museum of Nature and Science ECF Addition
IEQ Management Plan GH Phipps Construction Companies 5995 Greenwood Plaza Blvd., Suite 100 Greenwood Village, Colorado 80111-4710 303.571.5377 PHONE www.ghphipps.com Denver Museum of Nature and Science
More informationHVAC Costs. Reducing Building. Building owners are caught between two powerful forces the need to lower energy costs. By Stephen J.
Reducing Building HVAC Costs of site rec By Stephen J. Pargeter Building owners are caught between two powerful forces the need to lower energy costs and the need to meet or exceed outdoor air ventilation
More informationHow To Make A Green Building Plan
LEED v4 User Guide JUNE 2013 Table of Contents Welcome to LEED v4... 3 LEED v4 is global... 3 LEED v4: market sector improvements... 3 LEED v4: improved environmental outcomes... 4 LEED Certification Process...
More informationSECTION 15010 BASIC MECHANICAL REQUIREMENTS
SECTION 15010 BASIC MECHANICAL REQUIREMENTS A. DESIGN PARAMETERS 1. Climate Data a. For cooling design utilize the 1% Monthly Design Dry Bulb and Mean Coincident Wet Bulb Temperatures as listed in ASHRAE
More informationA closer look at the major green building rating tools in use around the world: BREEAM
A closer look at the major green building rating tools in use around the world: BREEAM Presented by: tony lee luen len, GBCM May 2010 BREEAM BRE Environmental Assessment Method is the most widely used
More informationQueen Lane Addition, Philadelphia, Pennsylvania is a building of approximately 25,000 ft². The client is Drexel University.
Page 1 of 5 INTRODUCTION Queen Lane Addition, Philadelphia, Pennsylvania is a building of approximately 25,000 ft². The client is Drexel University. Queen Lane Addition is described as follows: Medical
More informationBest Practice Guide BPGCS007
Best Practice Guide BPGCS007 ENERGY MANAGEMENT Introduction: With rising fuel costs, opening of electricity and gas markets to alternate suppliers and climate change, the requirement to monitor and reduce
More informationSOUTHERN CALIFORNIA EDISON DATA CENTER GREEN BUILDING EDUCATION: A CASE STUDY
SOUTHERN CALIFORNIA EDISON DATA CENTER GREEN BUILDING EDUCATION: A CASE STUDY SCE DATA CENTER GREEN BUILDING EDUCATION...create the most efficient and environmentally intelligent facility possible... The
More informationLead architect: Ron Arad Architects - Executive architect: Jaspers & Eyers
SOLUTIONS FOR SUSTAINABLE BUILDINGS THE GUIDE TO BREEAM Lead architect: Ron Arad Architects - Executive architect: Jaspers & Eyers Reynaers develops innovative and sustainable aluminium solutions, for
More informationCOPYRIGHT MATERIAL. Geof Syphers, PE, LEED AP BD+C Codding Enterprises 2010
COPYRIGHT MATERIAL This presentation is protected by US and International Copyright laws. Reproduction, distribution, display and use of the presentation without written permission of the author is prohibited.
More informationGSA Green Initiatives. NEBB Annual Conference October 22, 2011
GSA Green Initiatives NEBB Annual Conference October 22, 2011 Washington, DC Kinga Porst Overview Background on GSA Energy Mandates American Recovery and Reinvestment Act What GSA is doing Resources Background
More informationZa abeel Energy City Master Plan. Dubai, United Arab Emirates
Dubai, United Arab Emirates Dubai, United Arab Emirates The Energy Master Plan is uniquely positioned as a center for both commerce and residential development. The project will embody modern, sustainable
More informationBrian Salisbury. Director, Strategic Planning Community Living British Columbia
Community Living British Columbia (CLBC) actively promoted green ideas to staff through its Go Green Committee and network of Go Green office leads located throughout the province. CLBC also maintains
More informationHVAC For Schools How to purchase an HVAC system that meets your school s unique requirements and stays within your budget
A PRIMER Educational HVAC For Schools How to purchase an HVAC system that meets your school s unique requirements and stays within your budget Contents: Introduction: The best HVAC system is durable, reliable
More informationStep 2: Define Project Objectives
Why GREEN Small-scale renovations to large-scale new construction and master planning, owners are embracing sustainable practices in order to lessen their environmental impact and to reduce their operating
More informationSub-Bid Contractor Update Statement. Tab A - Invitation for Bids. Tab B - Instructions to Bidders
INTRODUCTORY INFORMATION TABLE OF CONTENTS 00 0101 PROJECT TITLE PAGE PROCUREMENT REQUIREMENTS (PROJECT MANUAL) Tab A - Invitation for Bids Tab B - Instructions to Bidders Tab C Bid Form for General Bids
More informationCurrent Statistics Northern Tier Pennsylvania. Number of Jobs 5,700 94,600 Average Earnings Average industry earnings per worker includes benefits
Agriculture & Resource Conservation FAST FACTS Current Statistics Northern Tier Pennsylvania Number of Employers 80 2,900 Number of Jobs 5,700 94,600 Average Earnings Average industry earnings per worker
More informationLEED for Homes Rating System
LEED for Homes Rating System market rate affordable multi-family TARGET MARKET REGULATIONS typical building practices 70% The top 25% of new homes based on performance and environmental responsibility
More informationState of the Art Energy Efficient Data Centre Air Conditioning
- White Paper - State of the Art Energy Efficient Data Centre Air Conditioning - Dynamic Free Cooling - Release 2, April 2008 Contents ABSTRACT... 3 1. WHY DO I NEED AN ENERGY EFFICIENT COOLING SYSTEM...
More informationEnergy Efficiency Market Transformation Opportunities for Texas
Energy Efficiency Market Transformation Opportunities for Texas September 13, 2007 A Public Example: Investing in Energy Efficiency FRED YEBRA, P.E., MBA, DirectorofDemand of Demand Side Management Austin
More informationHOW AN ENERGY EFFICIENT HOME CAN HELP THE ENVIRONMENT
HOW AN ENERGY EFFICIENT HOME CAN HELP THE ENVIRONMENT During the last century, concern about the environment increased, as issues such as global warming and the Greenhouse Effect convinced us that the
More informationCarbon Footprint of CMC Hospital for 2013
Carbon Footprint of CMC Hospital for 2013 Carbon footprint of CMC Hospital campus was estimated for the year 2011 and 2012 and the total CO2e emission was estimated at 15271.74 CO2e tons and 15456.61 CO2e
More informationcarbon neutral update April 2008
carbon neutral update April 2008 With almost 25,000 employees and around 1,000 buildings within Australia, NAB s carbon footprint is substantial. Most of our direct environmental impacts result from the
More informationPEAK DISTRICT NATIONAL PARK AUTHORITY ENVIRONMENTAL MANAGEMENT ANNUAL PERFORMANCE REPORT 2013/2014
2009/10 2010/11 2011/12 2012/13 2013/14 2014/15 2015/16 2016/17 Carbon emissions (kgco2) Page 1 PEAK DISTRICT NATIONAL PARK AUTHORITY ENVIRONMENTAL MANAGEMENT ANNUAL PERFORMANCE REPORT 2013/2014 1. INTRODUCTION
More informationHow Do Smart Buildings Make A Building Green?
"Technology means the systematic application of scientific or other organized knowledge to practical tasks John Kenneth Galbraith, Economist, Author How Do Smart Buildings Make A Building Green? Integrating
More informationGREEN SCHOOLS CASE STUDY. West Wing Elementary
GREEN SCHOOLS CASE STUDY School School name: School Deer Valley Union School District Address: 26716 N. High Desert Drive, Peoria, Arizona Contact: Jerry Cipriano Phone number: 602-467-5131 General location:
More information