PREVENTION OF FAILURE OF BRIDGE FOUNDATION AND APPROACH EMBANKMENT ON SOFT GROUND

Size: px
Start display at page:

Download "PREVENTION OF FAILURE OF BRIDGE FOUNDATION AND APPROACH EMBANKMENT ON SOFT GROUND"

Transcription

1 PREVENTION OF FAILURE OF BRIDGE FOUNDATION AND APPROACH EMBANKMENT ON SOFT GROUND Ir. Dr. Gue See Sew & Ir. Tan Yean Chin Gue & Partners Sdn Bhd 39-5, Jalan 3/146, The Metro Centre Bandar Tasik Selatan Kuala Lumpur Tel.: + (603) Fax: + (603) gnp@gueandpartners.com.my; ABSTRACT The success of bridge construction on soft ground relies on proper planning, design, construction control and site supervision. However, this is usually easier said than done and therefore there are still repeated geotechnical failures of bridge projects on soft ground. Most of the approach embankment failures are rather similar in nature and were induced by bearing capacity and stability of the embankment. The construction methods employed at site also have significant effect on the failures of adjacent piers. This paper presents case histories of two failures on bridge projects investigated by the Authors. The causes of failure, remedial works proposed and lessons learned are discussed. 1. INTRODUCTION The success of bridge construction on soft ground relies on the following major factors :- - Planning of Subsurface Investigation - Analysis and Design. - Construction Control and Supervision. However, most of the approach embankment failures investigated by the Authors are quite similar in nature and were induced by bearing capacity and stability of the embankment. The investigations carried out also clearly showed that construction methods employed at site also have significant influence. The failures can be prevented if the design consultant had taken care in geotechnical consideration in the analysis, design and construction. Two case histories of bridge failures investigated by the Authors are presented with causes of failure, remedial works proposed and lessons learned. In order to prevent history from repeating itself, this paper presents a brief guide to ensure successful construction of bridge foundation and approach embankment on soft ground. 2. CASE HISTORY Background The project is an access road with a reinforced concrete (r.c.) bridge over a river in Selangor. The proposed heights of the approach embankments on both sides of the abutments were about 8m with side slope of 1v(vertical) to 1.5h(horizontal). These embankments were to be constructed over a layer of very soft silty clay or clayey silt of 3m to 9m thick with Standard Penetration Tests values (SPT N ) of zero. Underlying the top very soft layer is 3.5m to 5.5m thick of medium dense silty sand followed by completely weathered shale with SPT N values vary between 30 to 50 blows/300mm. The liquid limit (LL) of the clay is about 78% and average moisture content is about 106%. Fig. 1 shows the general layout of the project. Fig. 2 shows a schematic profile of the subsoil. At abutment A, the wing walls were designed on piles but Abutment B was designed with cantilever wing walls.

2 Fig. 1 Layout of the bridge in case history 1 River Fig. 2 Subsoil profile of the site

3 2.2 Slip Failures of the Approach Embankments The first slip failure occurred on the right side of the approach embankment behind Abutment B when the fill was about 3m high above ground level. The designer inspected the failure and gave instructions to build a berm and continue filling. Three days later, the second slip failure at the site occurred. This time, it was on the left side of the same embankment as shown in Fig. 3a. Despite the failure, the designer instructed the Contractor to dig a ditch of 0.5m wide by 1m deep at the toe of left side of the embankment and allowed earth filling works to continue towards Abutment B at slower rate. Piling works at Abutment B started about 6 weeks after the first slip and the construction of the whole abutment was completed in about 5 weeks. After two months and when the embankment reached a height of 7m (1m below formation level), the third slip failure occurred as shown in Fig. 3b. Fig. 3 (a) Second slip failure at the left (b) Third slip failure The third slip occurred on the same location as the first slip and together with the embankment directly behind Abutment B. There was a drop of about 2.4m at the slip interface. On further investigation, Abutment B was found to have moved forward by 0.31m and 1.12m on the left and right sides respectively of the abutment. The abutment had also tilted vertically about 2 degrees clockwise towards embankment. Fig. 4 View of exposed pile cap and piles on the right side of Abutment B

4 In the failure investigation of Abutment B, the piles immediately below the pile cap were examined by excavating a trench on the right side of the Abutment B. Fig.s 4 and 5 show the condition of the piles. Cracks on pile B appear to have propagated from left side of the pile towards the fill. This indicates that the piles had been subjected to high lateral stresses imposed by the fill. This pile also shows a slight curve which suggests that there has been some restrain at the lower end of the pile. Fig. 5: Close-up view of the three exposed piles Fig. 6 shows the crushing of Pile C, which further indicates lateral compression due to the fill. Fig. 7 shows schematically the movements of pile cap and piles. Fig. 6 Pile C showing crushing of pile near pile cap

5 Fig. 7 Movements of pile cap and piles (view from right side of Abutment B) The forth slip occurred on the left side of the embankment behind Abutment A about three months after the third slip. At the time of the failure, the height of the embankment was about 6.5m above its ground level (1.5m below proposed formation level). Fig. 8 shows the slip failure. Fig. 8 Fourth slip failure on the left side of embankment behind Abutment A 2.3 Geotechnical Investigation In order to ascertain the causes of the failures, geotechnical analyses and investigations were carried out. Independent soil investigation was carried out after the failure with the following objectives :- i) to obtain physical and strength properties of the subsoil; ii) to determine the extent of the soft materials below the fill; iii) to ascertain the depths and dry density of fill at various positions of the embankment; iv) to study the ground water table and trace the slip lines if possible; v) to check and compare the results with those obtained during previous soil investigation. The results of the independent soil investigation generally confirm the results of the previous soil investigation except that the very soft silty clay layer appeared to have gained some strength and decrease in thickness due to some consolidation.

6 Generally, the average undrained shear strength (s u ) of the very soft clay is 10kPa with a lower bound value of 7.5kPa as shown in Fig. 9. The sensitivity (St) of the clay ranges from 2 to 8. Fig. 9 Undrained shear strength (s u ) of the soft clay Bearing capacity and limit equilibrium stability analyses carried out indicate that the subsoil could not support embankment height in excess of 2.7m if there is no ground treatment or strengthening. From the analyses, it is very clear that the embankment height of 8m proposed by the designer is not safe. Further back-analyses carried out on the failed embankment indicated that the s u of the clay was 11kPa. This is in good agreement with the average s u of 10kPa obtained from the S.I.. The analyses on the foundations for Abutments A and B were also carried out. The lateral earth pressure on piles was calculated using stress distribution behind piles proposed by Tschebotarioff (1973) as shown in Fig. 10. Since the spacing of piles was about three times the width of the pile, therefore, the group of piles and soil can be assumed to act as a unit. Fig. 10 Additional forces on abutment (soil undergoing lateral movement)

7 The ultimate lateral resistance, Ru was calculated using assumption of Poulos & Davis (1980) which assumed 4s u at the surface and increases to a constant value of 9s u at three times the width of the pile. The critical height of embankment that will induce a lateral force equivalent to the ultimate resistance was evaluated for the different thickness of soft clay. For abutment B the lateral resistance of the pile group and soil would be exceeded when the height of embankment was 5m to 5.5m. Therefore, the movements of abutment B could have happened when the height of embankment was about 5m, i.e. 3m below the proposed formation level. The calculations have also shown for Abutment A, that the lateral resistance of the pile group and soil would be exceeded when the height of embankment was 7.5m to 8.0m. However, Abutment A was only subjected to a height of 6.5m (1.5m below the proposed formation level), therefore it did not fail. Abutment A could withstand a higher embankment height than Abutment B because of its shape and dimensions. Abutment A was designed and constructed with piled wingwall. The total number of piles used was 88, and had 36 piles more than Abutment B. 2.4 Proposed Remedial Works Following many meetings with the designer, the final accepted proposals are as follows :- (a) Underpinning of Abutment B with 48 Nos. of micropiles, Abutment A with 10 Nos. of micropiles. (b) Use of reinforced soil wall behind Abutment A. (c) Piled embankment to be used for embankment fill exceeding 2.5m high. (d) Geogrid reinforced embankment for fill between 1.5m to 2.4m high. The total estimated cost of remedial works was about 3.7 million ringgit. 3. CASE HISTORY Background Similar to Case History 1, this project was under construction when failures occurred. This project is also an access road with prestressed concrete bridge over a river in Sarawak. The proposed heights of the approach embankments on both sides of the abutments were about 5m with side slopes of 1v(vertical) to 1.5h(horizontal). These embankments were constructed over 25m thick of soft coastal and riverine alluvium clay followed by dense silty Sand and very stiff silty clay. The soft alluvium generally has SPT N value of zero and average moisture content of more than 70%. Fig. 11 shows the partially completed bridge after failure and removal of failed materials. The layout is shown in Fig. 12 and the subsoil profile in shown in Fig. 13. Fig. 11 Overview of partially completed bridge.

8 Fig. 12 Layout of the Bridge in Case History 2 Fig. 13 Subsoil condition In the construction drawings, the approach embankments using local fills were supported by 200x200mm RC piles with pilecaps. In addition, 6m length wood piles were also used between the RC piles for further support of the embankment fill. More wood piles were also installed on the banks of the river trying to stabilize the lateral displacement of the soft alluvium. The abutments and piers are generally supported by 400mm diameter spun piles. 3.2 Slip Failures of the Approach Embankments

9 A deep seated slip failure occurred at the approach embankment about 25m from Abutment II. It happened when the fill reached about 3m high. Fig. 14 shows the shear drop after removal of some of the fill near the abutment. Fig. 14 Shear Drop at about 25m from Tilted Abutment Abutment II has tilted away from the river with the magnitude of about 550mm at the top of the abutment at the time of the site inspection by the Authors who were carrying out geotechnical investigation of the failure. The tilt translates into an angular distortion of 1/6. Due to the excessive angular distortion, the integrity of the spun piles driven to set into the stiffer stratum has also been affected as it exceeds the normal threshold of about 1/75. Due to the tilt of the Abutment II away from Pier II, a gap of about 300mm wide was observed between the two bridge decks at the pier s pilecap. Fig. 15 shows the photograph of the tilt at the Abutment II and the gap between two bridge decks. The failure also caused the pilecap at Pier II to tilt as shown in Fig. 16. Fig. 17 shows the schematic diagram of the possible slip plane relative to the deformed structures. Fig. 15 Tilted Abutment and Observed Gap between Bridge Decks These observations infer that the slip of the Approach Embankment near Abutment II is deep seated and is consistent with the depth of the soft alluvium. The cause of the rotational slip failure is due to the weak subsoil unable to support the weight of the approach embankment. The weight of embankment initiated the consolidation settlement of the soft subsoil and mobilised the low shear strength of the slip failure plane. The use of the 6m wood piles and RC piles offers little lateral resistance and instead, extends the

10 rotational slip deeper into the soft subsoil. At the pier, the bridge decks, being simply supported and fixed to the abutment via bearing pad, had moved along with the displacement of the abutment. Fig. 16 Titled pilecap at Pier II Fig. 17 Schematic of the slip failure At the start of the construction, the contractor observed that their personnel could not walk on the riverbanks without their feet sinking into the soft subsoil to a depth of about a foot. This observation infers that the upper subsoil undrained shear strength of the subsoil is estimated at about 10 kpa. As preliminary check using correlation of 5*s u to obtain ultimate bearing capacity of 50 to 60kPa, the estimated maximum height of fill that can be supported is about 3m which is consistent with the observed failure during embankment filling to 3m high. Therefore, if the designer and contractor had carried out simple checks, failure could have been prevented.

11 Additional subsurface investigation after the failure shows that the undrained shear strength from the vane shear tests range from 18 kpa to 51 kpa with remoulded strength of 7 kpa to 12 kpa. The higher s u obtained from the additional S.I. is due to the gain in strength during the whole period of filling. 3.3 Remedial Measures The rotational slip failure of the approach embankment is due to many factors such as inadequacy in the design, construction control, the soft subsoil and absence of adequate ground treatment. Several remedial options were explored for the embankment. The first remedial option is to remove the failed embankment fill and re-construct a new RC ramp (bridge) with ground beams for increased rigidity. This option avoids the weight of the fill bearing on the soft subsoil. The second option is to surcharge the soft subsoil in combination with prefabricated vertical drains to accelerate the consolidation process of the clayey subsoil and allow the subsoil to gain strength with time. The third option is to use piled embankment with slab to transfer the embankment load to the stiffer soil stratum instead of the soft upper clay. After much consideration by the client, the third option was chosen for the shortest construction time in order to put the bridge into service and no long term risk of further subsoil settlement. However, in this option, the soffit of the RC slab should be at or below the original ground level to avoid additional load on the soft upper subsoil stratum that can generate negative skin friction on both the abutment and embankment piles. At the tilted abutment, analyses of the pile head movement of the existing piles showed that integrity of the piles is doubtful and shall be compensated. However, there are two options of installing the compensation piles; firstly at the sides of the existing pile group and secondly, behind the abutment. The first option requires demolishing the existing abutment and enlarging the pilecap. The second option minimizes modification of the abutment but requires longer I-beams for support of the bridge deck. In addition, there is also a risk the compensation piles might be impeded by the wood and RC piles since the location of these piles might have displaced along with the slip failure. Option 1 was chosen for the minimal remedial cost by reusing the existing I-beams and minimizes risk of the new spun piles striking the existing wooden and RC piles. For the pier foundation, the existing spun piles are fully compensated by demolishing the existing pier and pilecap and installing new ones at the sides. The total estimated cost of remedial works is about 1.3 million ringgit. 4. LESSONS LEARNED AND PREVENTIVE MEASURES From the two case histories presented in this paper, it is obvious that they are very similar in nature and can be categorized to be caused by the following factors:- - Inadequacy of geotechnical design for the approach embankments or abutments. - Lack of understanding of the subsoil condition and awareness on the possible problems/failure that could happen during construction. - Lack of construction control and site supervision by the Consultant It is very obvious that the two failures are due to inadequacy of geotechnical design for the approach embankments and abutments. If proper geotechnical analyses and designs were carried out, the failures could have been prevented. The designs of approach the embankment and abutment are quite similar to normal fill embankment where key issues like stability and settlement shall be properly addressed. Although settlement calculation is equally important, they are not discussed here as it is not the main factor causing the failures but rather a long term serviceability problem that required regular maintenance. For embankment and abutment stability, both circular and non-circular (wedge) failure surfaces shall be evaluated using a limit equilibrium analysis (Tan & Gue, 2000). It is very common to wrongly assume that as long as the structural design of an abutment has considered both vertical and lateral pressures, slip failure would not occur. A good example of abutment instability is shown in Fig. 17 where a deep seated instability of the embankment fill behind the abutment seriously affect the stability of the abutment. The most critical condition that usually triggers failure is during filling where the stability of an embankment

12 shall be analysed based on undrained shear strength (s u ) of the subsoil. The recommended Factor of Safety (FOS) against instability is at least 1.2 for short term. Long term stability is usually less critical as the subsoil increases its strength with time. The stability of embankments and abutments in long term shall be checked using effective stress strength parameters (c and φ ) and the minimum FOS required is 1.4. A quick preliminary check on the stability of the embankment is possible using modified bearing capacity equation below : q allow = (s u. N c / FOS) where : q allow = allowable bearing pressure = (γ fill.h + 10) (kn/m 2 ) γ fill = bulk unit weight of the compacted fill (kn/m 3 ) H = allowable height of embankment (m) s u = undrained shear strength of the subsoil (kpa) N c = 5 (suggested by Authors for ease of hand calculation) FOS = Factor of Safety Note : The 10kPa allowance in the q allow is to cater for traffic load. Design consultant, consultant s site engineer(s) and contractor should have some fundamental geotechnical knowledge which include understanding of the subsoil condition and awareness on the possible problems or failures that could happen during construction. A good example is shown in Section 3.2 where the contractor were aware that their personnel could not walk on the very soft riverbank and could have used the simple bearing capacity equation to check the allowable height of the fill the subsoil can support. More often than not, failures were due to bad temporary works that were never considered for in the design. One serious problem that usually occurs for bridge project is the temporary fill placed by the contractor to form a temporary platform to facilitate their piling or other construction works. If not careful, slip failure in subsoil could be triggered by the load from the temporary fill. Therefore, it is recommended that the design consultant should consider the possible construction method to be used by the contractor and designed for it. The design consultant shall also ensure that during construction, the contractor must carry out works according to the approved method statement to prevent failure. It is also important for the design consultant to ensure the method statement including temporary works proposed by the contractor does not cause failure. Finally, the proper full-time site supervision by the consultant s representatives with adequate site experiences and knowledge are also very important to prevent failure due to temporary works and ensure permanent works are constructed according to the drawings and specifications. Another common problem caused by temporary fill over soft ground is the failure to remove the temporary fill after construction. The temporary fill will cause the compressible subsoil to settle with time (consolidation settlement). If this area has piles, then the piles will be subjected to down drag (negative skin friction) due to the settling subsoil and reduce the capacity of the piles. If the down drag is not catered for in the design, the piles will have lower allowable capacity and larger settlement causing distortion to the structures. Therefore, the design consultant shall ensure the removal of temporary fill after construction by the contractor or to design the piles to accommodate negative skin friction. 5. CONCLUSIONS The success of bridge construction on soft ground relies on proper planning, analysis, design, construction control and site supervision. However, from the two case histories presented in this paper, it is obvious that they are very similar in nature and can be categorized to be caused by the following factors:- - Inadequacy of geotechnical design for the approach embankments or abutments. - Lack of understanding of the subsoil condition and awareness on the possible problems/failure that could happen during construction. - Lack of construction control and site supervision by the Consultant To prevent embankment and abutment failure due to instability, both circular and non-circular (wedge) failure surfaces shall be checked using limit equilibrium analyses. A quick preliminary check on the stability of the embankment is possible using modified bearing capacity equation of

13 q allow = (s u. N c / FOS) It is also important for design consultant, consultant s site representatives and contractor to have some fundamental geotechnical knowledge so that any irregularities at site can be spotted and precautionary actions carried out before failure occurs. Finally, proper full-time site supervision by the consultant s representatives with adequate experiences and knowledge are also very important to prevent failure due to un-engineered temporary works. REFERENCES GUE, S.S (1988). An Investigation into Geotechnical Failures of a Bridge Project. IEM/RRIM Joint Engineering Symposium. Johor Bahru, Malaysia, pp LADD, C.C. (1991). Stability evaluation during staged construction. J. Geotech. Eng.,ASCE. 117(4) : PECK, R.B. (1969). Advantages and limitations of the observational method in applied soil mechanics. Geotechnique. 19(2): POULOS, H.G. and DAVIS, E.H. (1980). Pile Foundation Analysis and Design. John Wildy and Sons, Inc. Canada. SKEMPTON, A.W. (1951). The Bearing Capacity of Clays. Building Research Congress, London. 1 : SKEMPTON, A.W. & NORTHEY, R.D. (1953). The post-glacial clays of the Thames Estuary at Tilbury and Shellhaven. Proc. 3rd Int. Conf. Soil Mech. Found. Eng., Zurich. 1 : TAN, Y.C. & GUE, S.S. (2000), Embankment Over Soft Clay Design and Construction Control, Seminar on Geotechnical Engineering 2000, IEM (Northern Branch), Penang, 22 & 23 September, TSCHEBOTARIOFF, G.P. (1973). Foundation, Retaining and Earth Structures. 2nd Edition McGraw- Hill Inc. USA. BIOGRAPHY Ir. Dr. Gue See Sew :- After graduating with First Class (Honours) Degree from University of Strathclyde, UK in 1979, Dr. Gue joined the Public Works Department, Malaysia as a Bridge Design Engineer. In 1981, he won the prestigious Kuok Foundation Award. He completed his doctorate at University Oxford in 2½ years and joined the Public Works Department Malaysia in In 1990, he left the government service and is now the CEO/Managing Director of Gue & Partners Sdn Bhd, a geotechnical consulting firm. Dr. Gue was the President of the Institution of Engineers, Malaysia (IEM), April 2001 April He is a Board Member of The Board of Engineers, Malaysia ( , ). Dr. Gue was the Chairman for the Taskforce Committee on Policies And Procedures For Mitigating The Risk Of Landslide On Hill-Site Development. He is the Regional Chairman of the Coordinating Committee of APEC Engineer Register ( ). Dr. Gue is also the Council member of National R&D Council for 2002 to He has published 60 technical papers related to geotechnical engineering in various conferences and seminars. Ir. Tan Yean Chin :- Ir. Tan obtained his Bachelor Degree in Civil Engineering with First Class Honours from Universiti Teknologi Malaysia in He later obtained his Master Degree in Geotechnical Engineering and The Chin Fung Kee Prize for outstanding academic performance from Asian Institute of Technology, Bangkok in He is now a director of Gue & Partners Sdn Bhd; a geotechnical consultant firm. Ir. Tan is currently the Deputy Chairman of the Geotechnical Engineering Technical Division and Council member of the Institution of Engineers, Malaysia (IEM). He has published more than 30 technical papers on geotechnical engineering in local and overseas conferences and seminars. In 1998, he won The Tan Sri Raja Zainal Prize presented by IEM for an outstanding technical paper.

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM Swaminathan Srinivasan, P.E., M.ASCE H.C. Nutting/Terracon David Tomley, P.E., M.ASCE KZF Design Delivering Success for

More information

Emergency repair of Bridge B421

Emergency repair of Bridge B421 Emergency repair of Bridge B421 over the Olifants River after fl ood damage INTRODUCTION AND BACKGROUND Bridge B421 is located on the R555 at km 5.03 on Section 01E between Witbank (now known as emalahleni)

More information

Value of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective

Value of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective Value of Instrumentation Systems and Real-Time Monitoring: An Owner s Perspective FHWA NATIONAL GEOTECHNICAL PROGRAM www.fhwa.dot.gov/engineering/geotech Why Geotechnical Instrumentation? Provide warning

More information

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

CONCRETE SEGMENTAL RETAINING WALL SYSTEM CONCRETE SEGMENTAL RETAINING WALL SYSTEM PART 1: GENERAL SPECIFICATIONS 1.01 Work Included A. Work shall consist of furnishing and constructing a Rockwood Vintage TM unit segmental retaining wall (SRW)

More information

When to Use Immediate Settlement in Settle 3D

When to Use Immediate Settlement in Settle 3D When to Use Immediate Settlement in Settle 3D Most engineers agree that settlement is made up of three components: immediate, primary consolidation and secondary consolidation (or creep). Most engineers

More information

EFFECT OF GEOGRID REINFORCEMENT ON LOAD CARRYING CAPACITY OF A COARSE SAND BED

EFFECT OF GEOGRID REINFORCEMENT ON LOAD CARRYING CAPACITY OF A COARSE SAND BED International Journal of Civil Engineering and Technology (IJCIET) Volume 7, Issue 3, May June 2016, pp. 01 06, Article ID: IJCIET_07_03_001 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=7&itype=3

More information

REINFORCED CONCRETE. Reinforced Concrete Design. A Fundamental Approach - Fifth Edition. Walls are generally used to provide lateral support for:

REINFORCED CONCRETE. Reinforced Concrete Design. A Fundamental Approach - Fifth Edition. Walls are generally used to provide lateral support for: HANDOUT REINFORCED CONCRETE Reinforced Concrete Design A Fundamental Approach - Fifth Edition RETAINING WALLS Fifth Edition A. J. Clark School of Engineering Department of Civil and Environmental Engineering

More information

Module 7 (Lecture 24 to 28) RETAINING WALLS

Module 7 (Lecture 24 to 28) RETAINING WALLS Module 7 (Lecture 24 to 28) RETAINING WALLS Topics 24.1 INTRODUCTION 24.2 GRAVITY AND CANTILEVER WALLS 24.3 PROPORTIONING RETAINING WALLS 24.4 APPLICATION OF LATERAL EARTH PRESSURE THEORIES TO DESIGN 24.5

More information

PILE FOUNDATIONS FM 5-134

PILE FOUNDATIONS FM 5-134 C H A P T E R 6 PILE FOUNDATIONS Section I. GROUP BEHAVIOR 6-1. Group action. Piles are most effective when combined in groups or clusters. Combining piles in a group complicates analysis since the characteristics

More information

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL. STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill

More information

How To Design A Foundation

How To Design A Foundation The Islamic university - Gaza Faculty of Engineering Civil Engineering Department CHAPTER (2) SITE INVESTIGATION Instructor : Dr. Jehad Hamad Definition The process of determining the layers of natural

More information

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains Doug Jenkins 1, Chris Lawson 2 1 Interactive Design Services, 2 Reinforced

More information

An Example of Using ReSSA in Complex Geometry of Reinforced Tiered Slope Introduction Background

An Example of Using ReSSA in Complex Geometry of Reinforced Tiered Slope Introduction Background An Example of Using ReSSA in Complex Geometry of Reinforced Tiered Slope By Dov Leshchinsky Copyright 2001, ADAMA Engineering, Inc. All Rights Reserved Introduction Geosynthetic reinforced soil structures

More information

BEARING CAPACITY AND SETTLEMENT RESPONSE OF RAFT FOUNDATION ON SAND USING STANDARD PENETRATION TEST METHOD

BEARING CAPACITY AND SETTLEMENT RESPONSE OF RAFT FOUNDATION ON SAND USING STANDARD PENETRATION TEST METHOD SENRA Academic Publishers, British Columbia Vol., No. 1, pp. 27-2774, February 20 Online ISSN: 0-353; Print ISSN: 17-7 BEARING CAPACITY AND SETTLEMENT RESPONSE OF RAFT FOUNDATION ON SAND USING STANDARD

More information

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13) Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised ) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular blocks

More information

CEEN 162 - Geotechnical Engineering Laboratory Session 7 - Direct Shear and Unconfined Compression Tests

CEEN 162 - Geotechnical Engineering Laboratory Session 7 - Direct Shear and Unconfined Compression Tests PURPOSE: The parameters of the shear strength relationship provide a means of evaluating the load carrying capacity of soils, stability of slopes, and pile capacity. The direct shear test is one of the

More information

Worked Example 2 (Version 1) Design of concrete cantilever retaining walls to resist earthquake loading for residential sites

Worked Example 2 (Version 1) Design of concrete cantilever retaining walls to resist earthquake loading for residential sites Worked Example 2 (Version 1) Design of concrete cantilever retaining walls to resist earthquake loading for residential sites Worked example to accompany MBIE Guidance on the seismic design of retaining

More information

STRUCTURAL DAMAGE OF A 5-STOREY BUILDING: DIFFERENTIAL SETTLEMENT DUE TO CONSTRUCTION OF AN ADJACENT BUILDING OR BECAUSE OF CONSTRUCTION DEFECTS?

STRUCTURAL DAMAGE OF A 5-STOREY BUILDING: DIFFERENTIAL SETTLEMENT DUE TO CONSTRUCTION OF AN ADJACENT BUILDING OR BECAUSE OF CONSTRUCTION DEFECTS? STRUCTURAL DAMAGE OF A 5-STOREY BUILDING: DIFFERENTIAL SETTLEMENT DUE TO CONSTRUCTION OF AN ADJACENT BUILDING OR BECAUSE OF CONSTRUCTION DEFECTS? Ioannis Anastasopoulos National Technical University of

More information

Anirudhan I.V. Geotechnical Solutions, Chennai

Anirudhan I.V. Geotechnical Solutions, Chennai Anirudhan I.V. Geotechnical Solutions, Chennai Often inadequate In some cases, excess In some cases, disoriented Bad investigation Once in a while good ones Depends on one type of investigation, often

More information

INTRODUCTION TO SOIL MODULI. Jean-Louis BRIAUD 1

INTRODUCTION TO SOIL MODULI. Jean-Louis BRIAUD 1 INTRODUCTION TO SOIL MODULI By Jean-Louis BRIAUD 1 The modulus of a soil is one of the most difficult soil parameters to estimate because it depends on so many factors. Therefore when one says for example:

More information

Geotechnical Building Works (GBW) Submission Requirements

Geotechnical Building Works (GBW) Submission Requirements Building Control (Amendment) Act 2012 and Regulations 2012: Geotechnical Building Works (GBW) Submission Requirements Building Engineering Group Building and Construction Authority May 2015 Content : 1.

More information

GEOTECHNICAL ENGINEERING FORMULAS. A handy reference for use in geotechnical analysis and design

GEOTECHNICAL ENGINEERING FORMULAS. A handy reference for use in geotechnical analysis and design GEOTECHNICAL ENGINEERING FORMULAS A handy reference for use in geotechnical analysis and design TABLE OF CONTENTS Page 1. SOIL CLASSIFICATION...3 1.1 USCS: Unified Soil Classification System...3 1.1.1

More information

Appendix A Sub surface displacements around excavations Data presented in Xdisp sample file

Appendix A Sub surface displacements around excavations Data presented in Xdisp sample file Appendix A Sub surface displacements around excavations Data presented in Xdisp sample file Notation B1 = lowest level of basement slab c = cohesion E = drained Young s Modulus Eu = undrained Young s Modulus

More information

ALLOWABLE LOADS ON A SINGLE PILE

ALLOWABLE LOADS ON A SINGLE PILE C H A P T E R 5 ALLOWABLE LOADS ON A SINGLE PILE Section I. BASICS 5-1. Considerations. For safe, economical pile foundations in military construction, it is necessary to determine the allowable load capacity

More information

Design of pile foundations following Eurocode 7-Section 7

Design of pile foundations following Eurocode 7-Section 7 Brussels, 18-20 February 2008 Dissemination of information workshop 1 Workshop Eurocodes: background and applications Brussels, 18-20 Februray 2008 Design of pile foundations following Eurocode 7-Section

More information

ENCE 4610 Foundation Analysis and Design

ENCE 4610 Foundation Analysis and Design This image cannot currently be displayed. ENCE 4610 Foundation Analysis and Design Shallow Foundations Total and Differential Settlement Schmertmann s Method This image cannot currently be displayed. Strength

More information

GUIDELINE FOR HAND HELD SHEAR VANE TEST

GUIDELINE FOR HAND HELD SHEAR VANE TEST GUIDELINE FOR HAND HELD SHEAR VANE TEST NZ GEOTECHNICAL SOCIETY INC August 2001 CONTENTS Page 1.0 Introduction 2 2.0 Background 2 3.0 Recommended Practice 3 4.0 Undrained Shear Strength 3 5.0 Particular

More information

Numerical Simulation of CPT Tip Resistance in Layered Soil

Numerical Simulation of CPT Tip Resistance in Layered Soil Numerical Simulation of CPT Tip Resistance in Layered Soil M.M. Ahmadi, Assistant Professor, mmahmadi@sharif.edu Dept. of Civil Engineering, Sharif University of Technology, Tehran, Iran Abstract The paper

More information

EN 1997-1 Eurocode 7. Section 10 Hydraulic Failure Section 11 Overall Stability Section 12 Embankments. Trevor L.L. Orr Trinity College Dublin Ireland

EN 1997-1 Eurocode 7. Section 10 Hydraulic Failure Section 11 Overall Stability Section 12 Embankments. Trevor L.L. Orr Trinity College Dublin Ireland EN 1997 1: Sections 10, 11 and 12 Your logo Brussels, 18-20 February 2008 Dissemination of information workshop 1 EN 1997-1 Eurocode 7 Section 10 Hydraulic Failure Section 11 Overall Stability Section

More information

ESTIMATION OF UNDRAINED SETTLEMENT OF SHALLOW FOUNDATIONS ON LONDON CLAY

ESTIMATION OF UNDRAINED SETTLEMENT OF SHALLOW FOUNDATIONS ON LONDON CLAY International Conference on Structural and Foundation Failures August 2-4, 2004, Singapore ESTIMATION OF UNDRAINED SETTLEMENT OF SHALLOW FOUNDATIONS ON LONDON CLAY A. S. Osman, H.C. Yeow and M.D. Bolton

More information

Comparison of Seismic Retrofitting Methods for Existing Foundations in Seismological Active Regions

Comparison of Seismic Retrofitting Methods for Existing Foundations in Seismological Active Regions Comparison of Seismic Retrofitting Methods for Existing Foundations in Seismological Active Regions Peyman Amini Motlagh, Ali Pak Abstract Seismic retrofitting of important structures is essential in seismological

More information

Module 5 (Lectures 17 to 19) MAT FOUNDATIONS

Module 5 (Lectures 17 to 19) MAT FOUNDATIONS Module 5 (Lectures 17 to 19) MAT FOUNDATIONS Topics 17.1 INTRODUCTION Rectangular Combined Footing: Trapezoidal Combined Footings: Cantilever Footing: Mat foundation: 17.2 COMMON TYPES OF MAT FOUNDATIONS

More information

DESIGN OF PILES AND PILE GROUPS CONSIDERING CAPACITY, SETTLEMENT, AND NEGATIVE SKIN FRICTION

DESIGN OF PILES AND PILE GROUPS CONSIDERING CAPACITY, SETTLEMENT, AND NEGATIVE SKIN FRICTION DESIGN OF PILES AND PILE GROUPS CONSIDERING CAPACITY, SETTLEMENT, AND NEGATIVE SKIN FRICTION Introduction Bengt H. Fellenius, Dr.Tech., P.Eng. Background Notes for Demo Example for UniPile at www.unisoftltd.com

More information

REPAIR AND RETROFIT OF BRIDGES DAMAGED BY THE 2010 CHILE MAULE EARTHQUAKE

REPAIR AND RETROFIT OF BRIDGES DAMAGED BY THE 2010 CHILE MAULE EARTHQUAKE Proceedings of the International Symposium on Engineering Lessons Learned from the 2011 Great East Japan Earthquake, March 1-4, 2012, Tokyo, Japan REPAIR AND RETROFIT OF BRIDGES DAMAGED BY THE 2010 CHILE

More information

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin PLAN SUBGRADES

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin PLAN SUBGRADES Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering Geotechnical Bulletin GB 1 PLAN SUBGRADES Geotechnical Bulletin GB1 was jointly developed by the Offices

More information

Safe & Sound Bridge Terminology

Safe & Sound Bridge Terminology Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries

More information

Investigation of Foundation Failure. Step 1 - Data Collection. Investigation Steps

Investigation of Foundation Failure. Step 1 - Data Collection. Investigation Steps Foundations on Expansive Clay Soil Part 3 - Investigation of Failed Foundations Presented by: Eric Green, P.E. Structural Engineer Slide 1 Copyright Eric Green 2005 Investigation of Foundation Failure

More information

CHAPTER 9 FEM MODELING OF SOIL-SHEET PILE WALL INTERACTION

CHAPTER 9 FEM MODELING OF SOIL-SHEET PILE WALL INTERACTION 391 CHAPTER 9 FEM MODELING OF SOIL-SHEET PILE WALL INTERACTION 9.1 OVERVIEW OF FE SOIL-STRUCTURE INTERACTION Clough and Denby (1969) introduced Finite Element analysis into the soil-structure interaction

More information

DIRECT SHEAR TEST SOIL MECHANICS SOIL MECHANICS LABORATORY DEPARTMENT OF CIVIL ENGINEERING UNIVERSITY OF MORATUWA SRI LANKA

DIRECT SHEAR TEST SOIL MECHANICS SOIL MECHANICS LABORATORY DEPARTMENT OF CIVIL ENGINEERING UNIVERSITY OF MORATUWA SRI LANKA DIRECT SHEAR TEST SOIL MECHANICS SOIL MECHANICS LABORATORY DEPARTMENT OF CIVIL ENGINEERING UNIVERSITY OF MORATUWA SRI LANKA DIRECT SHEAR TEST OBJEVTIVES To determine the shear strength parameters for a

More information

Specification Guidelines: Allan Block Modular Retaining Wall Systems

Specification Guidelines: Allan Block Modular Retaining Wall Systems Specification Guidelines: Allan Block Modular Retaining Wall Systems The following specifications provide Allan Block Corporation's typical requirements and recommendations. At the engineer of record's

More information

Requirements for an Excavation and Lateral Support Plan Building (Administration) Regulation 8(1)(bc)

Requirements for an Excavation and Lateral Support Plan Building (Administration) Regulation 8(1)(bc) Buildings Department Practice Note for Authorized Persons, Registered Structural Engineers and Registered Geotechnical Engineers APP-57 Requirements for an Excavation and Lateral Support Plan Building

More information

Estimation of Adjacent Building Settlement During Drilling of Urban Tunnels

Estimation of Adjacent Building Settlement During Drilling of Urban Tunnels Estimation of Adjacent Building During Drilling of Urban Tunnels Shahram Pourakbar 1, Mohammad Azadi 2, Bujang B. K. Huat 1, Afshin Asadi 1 1 Department of Civil Engineering, University Putra Malaysia

More information

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT

SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT SPECIFICATION FOR DYNAMIC CONSOLIDATION / DYNAMIC REPLACEMENT 1.0 SOIL IMPROVEMENT 1.1 General Soil Investigation Information are provided in Part B1 annex as a guide to the Contractor for his consideration

More information

Chapter 2 Basis of design and materials

Chapter 2 Basis of design and materials Chapter 2 Basis of design and materials 2.1 Structural action It is necessary to start a design by deciding on the type and layout of structure to be used. Tentative sizes must be allocated to each structural

More information

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing

Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing Brussels, 18-20 February 2008 Dissemination of information workshop 1 Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing Dr.-Ing. Bernd Schuppener, Federal Waterways Engineering

More information

Tests and Analyses on Shear Strength Increment of Soft Soil under Embankment Fill

Tests and Analyses on Shear Strength Increment of Soft Soil under Embankment Fill Tests and Analyses on Shear Strength Increment of Soft Soil under Embankment Fill Guanbao Ye Professor Key Laboratory of Geotechnical and Underground Engineering,Tongji University, Ministry of Education,

More information

DESIGN AND CONSTRUCTION CONSIDERATIONS FOR DEEP EXCAVATION.

DESIGN AND CONSTRUCTION CONSIDERATIONS FOR DEEP EXCAVATION. DESIGN AND CONSTRUCTION CONSIDERATIONS FOR DEEP EXCAVATION. By: S.S. Gue & Y.C. Tan SSP Geotechnics Sdn Bhd 1.0 INTRODUCTION In Malaysia, deep basements have been extensively constructed, especially in

More information

Optimum proportions for the design of suspension bridge

Optimum proportions for the design of suspension bridge Journal of Civil Engineering (IEB), 34 (1) (26) 1-14 Optimum proportions for the design of suspension bridge Tanvir Manzur and Alamgir Habib Department of Civil Engineering Bangladesh University of Engineering

More information

ATLAS RESISTANCE Pier Foundation Systems

ATLAS RESISTANCE Pier Foundation Systems ATLAS RESISTANCE Pier Foundation Systems Foundation Repair Systems for Civil Construction Applications: Residential, Commercial, Industrial Atlas Resistance Piers have been used to restore and/or stabilize

More information

NEGATIVE SKIN FRICTION AND SETTLEMENT OF PILES. Dr. Bengt H. Fellenius, P. Eng. University of Ottawa, Canada

NEGATIVE SKIN FRICTION AND SETTLEMENT OF PILES. Dr. Bengt H. Fellenius, P. Eng. University of Ottawa, Canada Fellenius, B. H., 1984. Negative skin friction and settlement of piles. Second International Seminar, Pile Foundations, Nanyang Technological Institute, Singapore, November 28-30, 12 p. NEGATIVE SKIN FRICTION

More information

vulcanhammer.net This document downloaded from

vulcanhammer.net This document downloaded from This document downloaded from vulcanhammer.net since 1997, your source for engineering information for the deep foundation and marine construction industries, and the historical site for Vulcan Iron Works

More information

Geotechnical Characteristics of Two Different Soils and their Mixture and Relationships between Parameters

Geotechnical Characteristics of Two Different Soils and their Mixture and Relationships between Parameters Geotechnical Characteristics of Two Different Soils and their Mixture and Relationships between Parameters Arpan Laskar Post Graduate Student Civil Engineering Department, National Institute of Technology

More information

Validation of methods for assessing tunnelling-induced settlements on piles

Validation of methods for assessing tunnelling-induced settlements on piles Validation of methods for assessing tunnelling-induced settlements on piles Mike Devriendt, Arup Michael Williamson, University of Cambridge & Arup technical note Abstract For tunnelling projects, settlements

More information

APPENDIX G SETTLEMENT

APPENDIX G SETTLEMENT APPENDIX G SETTLEMENT TABLE OF CONTENTS G.1 IN T R O D U C T IO N... 1 G.2 MATERIAL PLACEMENT AND COMPACTION... 1 G.2.1 Incom pressible M aterials... 1 G.2.2 Compressible Materials... 2 G.2.3 Soil P lacem

More information

NUMERICAL MODELLING OF PIEZOCONE PENETRATION IN CLAY

NUMERICAL MODELLING OF PIEZOCONE PENETRATION IN CLAY NUMERICAL MODELLING OF PIEZOCONE PENETRATION IN CLAY Ilaria Giusti University of Pisa ilaria.giusti@for.unipi.it Andrew J. Whittle Massachusetts Institute of Technology ajwhittl@mit.edu Abstract This paper

More information

CIVL451. Soil Exploration and Characterization

CIVL451. Soil Exploration and Characterization CIVL451 Soil Exploration and Characterization 1 Definition The process of determining the layers of natural soil deposits that will underlie a proposed structure and their physical properties is generally

More information

Earth Pressure and Retaining Wall Basics for Non-Geotechnical Engineers

Earth Pressure and Retaining Wall Basics for Non-Geotechnical Engineers PDHonline Course C155 (2 PDH) Earth Pressure and Retaining Wall Basics for Non-Geotechnical Engineers Instructor: Richard P. Weber, P.E. 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA

More information

Figure 2.31. CPT Equipment

Figure 2.31. CPT Equipment Soil tests (1) In-situ test In order to sound the strength of the soils in Las Colinas Mountain, portable cone penetration tests (Japan Geotechnical Society, 1995) were performed at three points C1-C3

More information

METHODS FOR ACHIEVEMENT UNIFORM STRESSES DISTRIBUTION UNDER THE FOUNDATION

METHODS FOR ACHIEVEMENT UNIFORM STRESSES DISTRIBUTION UNDER THE FOUNDATION International Journal of Civil Engineering and Technology (IJCIET) Volume 7, Issue 2, March-April 2016, pp. 45-66, Article ID: IJCIET_07_02_004 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=7&itype=2

More information

Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir. Presented By: Doug Stachler, P.E.

Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir. Presented By: Doug Stachler, P.E. Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir Presented By: Doug Stachler, P.E. Project Organization Owner Delaware County Engineers Office Design Consultant CH2M HILL Contractor Double

More information

Improvement in physical properties for ground treated with rapid impact compaction

Improvement in physical properties for ground treated with rapid impact compaction International Journal of the Physical Sciences Vol. 6(22), pp. 5133-5140, 2 October 2011 Available online at http://www.academicjournals.org/ijps ISSN 1992-1950 2011 Academic Journals Full Length Research

More information

The demand for new roadway

The demand for new roadway Designing strong walls on weak soils Civil engineers have options to remedy foundation soil problems and meet project cost and schedule requirements. By Fadi Faraj, P.E.; Michael H. Garrison, P.E.; and

More information

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

CONCRETE SEGMENTAL RETAINING WALL SYSTEM CONCRETE SEGMENTAL RETAINING WALL SYSTEM PART 1: GENERAL SPECIFICATIONS 1.01 Work Included A. Work shall consist of furnishing and constructing a Rockwood Classic 8 with PCS unit segmental retaining wall

More information

BUTE Department of Construction Management and Technology

BUTE Department of Construction Management and Technology BUTE Department of Construction Management and Technology 02.10.2012 Definition 1: Foundation: The structure, that transmits the load of the building to the soil Definition 2: Load bearing soil (strata):

More information

PDHonline Course S151A (1 PDH) Steel Sheet Piling. Instructor: Matthew Stuart, PE, SE. PDH Online PDH Center

PDHonline Course S151A (1 PDH) Steel Sheet Piling. Instructor: Matthew Stuart, PE, SE. PDH Online PDH Center PDHonline Course S151A (1 PDH) Steel Sheet Piling Instructor: Matthew Stuart, PE, SE 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone & Fax: 703-988-0088 www.pdhonline.org

More information

Trench Rescue by Buddy Martinette

Trench Rescue by Buddy Martinette Trench Rescue by Buddy Martinette SOIL TYPE AND TESTING It is imperative that rescue personnel understand soil types and testing procedures if the want to be competent at trench rescue operations. Determining

More information

HOW TO DESIGN CONCRETE STRUCTURES Foundations

HOW TO DESIGN CONCRETE STRUCTURES Foundations HOW TO DESIGN CONCRETE STRUCTURES Foundations Instructions for the Members of BIBM, CEMBUREAU, EFCA and ERMCO: It is the responsibility of the Members (national associations) of BIBM, CEMBUREAU, EFCA and

More information

Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples

Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples Geotechnical Investigation Reports and Foundation Recommendations - Scope for Improvement - Examples Prof. V.S.Raju (Formerly: Director, IIT Delhi & Professor and Dean, IIT Madras) Email: rajuvs_b@yahoo.com

More information

SEISMIC UPGRADE OF OAK STREET BRIDGE WITH GFRP

SEISMIC UPGRADE OF OAK STREET BRIDGE WITH GFRP 13 th World Conference on Earthquake Engineering Vancouver, B.C., Canada August 1-6, 2004 Paper No. 3279 SEISMIC UPGRADE OF OAK STREET BRIDGE WITH GFRP Yuming DING 1, Bruce HAMERSLEY 2 SUMMARY Vancouver

More information

CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE

CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE 9.1 INTRODUCTION An important reason that composite piles have not gained wide acceptance in the civil engineering practice is the lack of a long

More information

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition. Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer

More information

Table of Contents 16.1 GENERAL... 16.1-1. 16.1.1 Overview... 16.1-1 16.1.2 Responsibilities... 16.1-1

Table of Contents 16.1 GENERAL... 16.1-1. 16.1.1 Overview... 16.1-1 16.1.2 Responsibilities... 16.1-1 Table of Contents Section Page 16.1 GENERAL... 16.1-1 16.1.1 Overview... 16.1-1 16.1.2 Responsibilities... 16.1-1 16.1.2.1 Geotechnical Section/Bridge Bureau Coordination... 16.1-1 16.1.2.2 Geotechnical

More information

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS Vince Luongo Petrifond Foundation Co., Ltd. PROJECT DESCRIPTION The York Durham Sanitary System (YDSS) Interceptor in the Town of Richmond Hill located

More information

Mechanically stabilized layers in road construction

Mechanically stabilized layers in road construction Mechanically stabilized layers in road construction Zikmund Rakowski, Jacek Kawalec Tensar International, UK, Technical University of Silesia, Poland Abstract: Effective and economical technologies are

More information

10-1 10. CONSOLIDATION

10-1 10. CONSOLIDATION 10-1 10. CONSOLIDATION 10.1 INFLUENCE OF DRAINAGE ON RATE OF SETTLEMENT When a saturated stratum of sandy soil is subjected to a stress increase, such as that caused by the erection of a building on the

More information

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 JRHill@HaywardBaker.com

More information

IH-635 MANAGED LANES PROJECT, SEG. 3.2

IH-635 MANAGED LANES PROJECT, SEG. 3.2 IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,

More information

Design and Construction of Cantilevered Reinforced Concrete Structures

Design and Construction of Cantilevered Reinforced Concrete Structures Buildings Department Practice Note for Authorized Persons, Registered Structural Engineers and Registered Geotechnical Engineers APP-68 Design and Construction of Cantilevered Reinforced Concrete Structures

More information

A case study of large screw pile groups behaviour

A case study of large screw pile groups behaviour Jongerenforum Geotechniek 5 juni 2015 A case study of large screw pile groups behaviour Alice Manzotti Content of the presentation 2 Introduction General soil conditions at the site Foundation design -

More information

SECTION 31 20 00 EARTH MOVING

SECTION 31 20 00 EARTH MOVING SECTION 31 20 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for excavating, filling, and grading for earthwork at Parking Structure, new exit stair and as required to

More information

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training

Foundations 65 5 FOUNDATIONS. by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. Seismic Retrofit Training Foundations 65 5 FOUNDATIONS by Richard Chylinski, FAIA and Timothy P. McCormick, P.E. 66 Foundations Foundations 67 FOUNDATIONS Let's assume that the retrofit has been done correctly from the roofline

More information

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION 1. SCOPE Pipe subsoil drains shall be constructed in accordance with this specification and in conformity with the lines, grades and cross-sections shown

More information

Designed and Engineered to Perform

Designed and Engineered to Perform History EARTH CONTACT PRODUCTS, L.L.C., is a family owned company, based in Olathe, Kansas. This company was built upon Don May s U.S. Patented fourth-generation Steel Piering System that has led to the

More information

PDCA Driven-Pile Terms and Definitions

PDCA Driven-Pile Terms and Definitions PDCA Driven-Pile Terms and Definitions This document is available for free download at piledrivers.org. Preferred terms are descriptively defined. Potentially synonymous (but not preferred) terms are identified

More information

Embankment Consolidation

Embankment Consolidation Embankment Consolidation 36-1 Embankment Consolidation In this tutorial, RS2 is used for a coupled analysis of a road embankment subject to loading from typical daily traffic. Model Start the RS2 9.0 Model

More information

Table of Contents. July 2015 12-1

Table of Contents. July 2015 12-1 Table of Contents 12.1 General... 3 12.2 Abutment Types... 5 12.2.1 Full-Retaining... 5 12.2.2 Semi-Retaining... 6 12.2.3 Sill... 7 12.2.4 Spill-Through or Open... 7 12.2.5 Pile-Encased... 8 12.2.6 Special

More information

FOUNDATION DESIGN. Instructional Materials Complementing FEMA 451, Design Examples

FOUNDATION DESIGN. Instructional Materials Complementing FEMA 451, Design Examples FOUNDATION DESIGN Proportioning elements for: Transfer of seismic forces Strength and stiffness Shallow and deep foundations Elastic and plastic analysis Foundation Design 14-1 Load Path and Transfer to

More information

Page & Turnbull imagining change in historic environments through design, research, and technology

Page & Turnbull imagining change in historic environments through design, research, and technology DCI+SDE STRUCTURAL EVALUATIONS OFFICE BUILDING, TOOL SHED & WATER TANK, AND BLACKSMITH & MACHINE SHOP BUILDINGS SAN FRANCISCO, CALIFORNIA [14290] PRIMARY PROJECT CONTACT: H. Ruth Todd, FAIA, AICP, LEED

More information

CE 366 SETTLEMENT (Problems & Solutions)

CE 366 SETTLEMENT (Problems & Solutions) CE 366 SETTLEMENT (Problems & Solutions) P. 1) LOAD UNDER A RECTANGULAR AREA (1) Question: The footing shown in the figure below exerts a uniform pressure of 300 kn/m 2 to the soil. Determine vertical

More information

EUROCODE 7 & POLISH PRACTICE

EUROCODE 7 & POLISH PRACTICE EUROCODE 7 & POLISH PRACTICE Implementation of Eurocode 7 in Poland Beata Gajewska Road and Bridge Research Institute In Poland the designing with limit states and partial factors was introduced in 1974.

More information

Important Points: Timing: Timing Evaluation Methodology Example Immediate First announcement of building damage

Important Points: Timing: Timing Evaluation Methodology Example Immediate First announcement of building damage 3.3. Evaluation of Building Foundation Damage Basic Terminology: Damage: Destruction, deformation, inclination and settlement of a building foundation caused by an earthquake. Damage grade: Degree of danger

More information

A Solid Foundation Solution for Homeowners. from. Our products are made with 90% Recycled Material Down. Right. Solid. GREEN.

A Solid Foundation Solution for Homeowners. from. Our products are made with 90% Recycled Material Down. Right. Solid. GREEN. A Solid Foundation Solution for Homeowners from Our products are made with 90% Recycled Material Down. Right. Solid. GREEN. Stop the damaging effects of foundation settling... Sinking foundations, cracked

More information

Dynamic Load Testing of Helical Piles

Dynamic Load Testing of Helical Piles Dynamic Load Testing of Helical Piles ANNUAL KANSAS CITY SPECIALTY SEMINAR 2014 JANUARY 10, 2014 Jorge Beim JWB Consulting LLC Pile Dynamics, Inc. Main Topics Brief description of the Dynamic Load Test

More information

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils Stephen W. Lacz 1, M. ASCE, P.E. and Richard C. Wells 2, F. ASCE, P.E. 1 Senior Professional, Trigon Kleinfelder, Inc., 313 Gallimore

More information

SECTION 1 GENERAL REQUIREMENTS

SECTION 1 GENERAL REQUIREMENTS Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,

More information

Numerical modelling of shear connection between concrete slab and sheeting deck

Numerical modelling of shear connection between concrete slab and sheeting deck 7th fib International PhD Symposium in Civil Engineering 2008 September 10-13, Universität Stuttgart, Germany Numerical modelling of shear connection between concrete slab and sheeting deck Noémi Seres

More information

Lighthouse Engineering, L.L.C.

Lighthouse Engineering, L.L.C. Registered Engineering Firm (F: 9334) Phone: 214-577-1077 Fax: 214-224-0549 Website: www.lighthouseeng.com Email: Office@LighthouseEng.com Thursday, September 04, 2014 TO: Our Client RE: Initial Engineering

More information

Sisal Composite Ltd. Apparel 4 Ltd. JM Knit Ltd. Natun Para, Hemayetpur, Savar, Dhaka-1340 (23.789416N,90.266135E)

Sisal Composite Ltd. Apparel 4 Ltd. JM Knit Ltd. Natun Para, Hemayetpur, Savar, Dhaka-1340 (23.789416N,90.266135E) Revision: issue 1 Date: 11 June 2014 Sisal Composite Ltd. Apparel 4 Ltd. JM Knit Ltd. Natun Para, Hemayetpur, Savar, Dhaka-1340 (23.789416N,90.266135E) 24 th May 2014 Structural Inspection Report Observations

More information

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS FUTURE SLAB PENETRATIONS and DEMOLITION of POST-TENSIONED FLOORS 1.0 INTRODUCTION Post-tensioned floor slabs in Australia and South East Asia are now universally regarded as the most cost effective form

More information

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION PART 8000 - PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL 8-3 8101 General

More information