Belmont Street Bridge Rehabilitation Project

Size: px
Start display at page:

Download "Belmont Street Bridge Rehabilitation Project"

Transcription

1 Belmont Street Bridge Rehabilitation Project Christian Gospel Church Worcester 43 Belmont Street Worcester MA February 20, :00PM

2 Agenda Introductions Project site and overview Project history Construction period Question and Answer

3 Project Team A new team mix for construction Some continuity maintained MassDOT oversight moves to District 3

4 Project Team: Description The previous slide showed an image of the project team membership logo s. The project team includes MassDOT as the lead agency, Howard Stein Hudson assisting with public involvement and MIG corporation as the general contractor.

5 Project Site

6 Project Site: Description The previous slide showed an image of the project site. The Belmont Street Bridge is highlighted in orange and carries Belmont Street (Route 9) over I-290. Pedestrian improvements at the intersection of Edward Street and Belmont Street are included in the project and highlighted in orange to the west of the Belmont Street Bridge.

7 Design Project History Design work in 2012 and 2013 Significant public process: Meetings and briefings: 10/ /2012 1/2013 3/2013 6/ /2013 Direct abutter meetings: spring 2013 Coordination with CMRPC Coordination with local elected officials Database of over 120 stakeholders

8 Why all the process? Not the Kenneth F. Burns Memorial, but - Location is everything Residential and institutional abutters Major local/regional roadway Transit/school bus line Utility challenges Effective outreach is key

9 Our Goal

10 Our Goal: Description The previous slide showed an image of the existing Belmont Street Bridge. The Belmont Street Bridge carries Belmont Street (Route 9) over I-290. The bridge has been determined structurally deficient and reaching the end of it s useful life.

11 Our Goal contd.

12 Our Goal contd. Description The previous slide showed a rendering of the completed Belmont Street Bridge. While there are not significant changes to the structure itself, the major change that will occur will be an increase number of lanes on the bridge.

13 Project Timeline What s done: Tree protection Snow fencing Construction signage Installation of temporary pedestrian bridge What s coming up in March: Utility work Readying pedestrian bridge for use Removal of north sidewalk Ongoing work I-290 east and westbound lanes

14 Project Time Line: Description The previous slide showed an image of the project timeline. Notice to Proceed was issued on October 15, 2014 and ongoing work has included tree protection, snow fencing, construction signage, and the installment of the temporary pedestrian bridge. Upcoming work include utility adjustments, readying the temporary pedestrian bridge for use, removal of the north sidewalk, and ongoing work on I-290.

15 Construction Project History Notice To Proceed issued: 10/14/15 Initial construction steps 12/14 Meetings and briefings 12/11/14 Public Information Meeting 12/18/14 State Representative Briefing 1/8/15 Worcester Housing Authority Briefing 2/20/15 Catholic Gospel Church Worcester Briefing Project website updated 1/15: Ongoing coordination with local elected officials Database of over 150 stakeholders Ongoing 3-week look ahead s

16 Phase 1 - Construction

17 Phase 1 Construction: Description The previous slide showed an image of phase 1 of construction on the Belmont Street Bridge. Phase 1 of construction is anticipated to start in November of During phase 1of construction, work will take place on the southerly part of the bridge while traffic is shifted to the north.

18 Phase 1 Construction View

19 Phase 1 Construction View: Description The previous slide showed a rendering of phase 1 construction. The rendering shows a perspective looking east in front of the Worcester Housing Authority. In phase 1 of construction, work will take place on the southerly half of the Belmont Street Bridge.

20 Phase 2 - Construction

21 Phase 2 Construction: Description The previous slide showed an image of phase 2 of construction. Phase 2 of construction is anticipated to start in June of 2016 During phase 2 of construction, work will take place on the northerly part of the bridge while traffic is shifted to the south.

22 Phase 2 Construction View

23 Phase 2 Construction View: Description The previous slide showed a rendering of phase 2 construction. The rendering shows a perspective looking east in front of the Worcester Housing Authority. In phase 2 of construction, work will take place on the northerly half of the Belmont Street Bridge.

24 Detour Plan

25 Detour Plan: Description The previous slide showed an aerial of the detour plan associated with the reconstruction of the Belmont Street Bridge. The detour plan has been implemented as a result of the restricted left turn from Belmont Street onto the I-290 on-ramp. The detour route utilize Major Taylor Boulevard and Shrewsbury Street to access I-290.

26 Completion

27 Completion: Description The previous slide showed an image of the completed Belmont Street Bridge road configuration. As part of the new structure, a left-turn only lane will be provided to access the I-290 onramp as well as reduce queuing on the bridge itself.

28 Completion View

29 Completion View: Description The previous slide showed a rendering of the completed Belmont Street Bridge. The rendering shows a perspective looking east in front of the Worcester Housing Authority. The completed structure roadway configuration will include 2 eastbound and 2 westbound travel lanes with an additional designated left-turn heading west.

30 Pedestrian Improvements - RRFB

31 Pedestrian Improvements RRFB: Description The previous slide showed a photograph of rectangular rapid flashing beacons. Rectangular rapid flashing beacons improve pedestrian safety by alerting motorist that a pedestrian is crossing the street. This photograph was take in Jamaica Plain on Washington Street.

32 UMass Medical/Edward Street Crossing

33 UMass Medical/Edward Street Crossing: Description The previous slide showed an aerial of the new pedestrian crosswalk in front of the UMass Memorial Health Center. The image highlights the removal of 2 crosswalks and installment of a new crosswalk. The project scope was expanded to include this intersection after concern was voiced over pedestrian safety at this location.

34 Improved Crossing - I

35 Improved Crossing 1: Description The previous slide showed a rendering of the improvements made at the intersection of Route 9 and Edward Street. In addition to the new crosswalk the intersection will have rectangular rapid flashing beacons and a luminescent light to increase safety for pedestrian crossings.

36 Improved Crossing II

37 Improved Crossing II: Description The previous slide showed a rendering of the improvements made at the intersection of Route 9 and Edward Street. In addition to the new crosswalk the intersection will have rectangular rapid flashing beacons and a luminescent light to increase safety for pedestrian crossings.

38 Improved Crossing - III

39 Improved Crossing III: Description The previous slide showed a rendering of the improvements made at the intersection of Route 9 and Edward Street. In addition to a new crosswalk, the intersection will have rectangular rapid flashing beacons and a luminescent light to increase safety for pedestrian crossings.

40 Construction period outreach Ask for a targeted briefing 3-week look ahead bursts Please sign in to sign up One coming soon MassDOT social media Conversion of website for construction /social media/print media regarding phase changes College and university focus at move-in and commencement

41 Catholic Gospel Church Worcester Outreach Last met spring 2013 Overview of the job and upcoming work Evaluation of structure to determine if changes to church are project related Stakeholder membership since 25% design public hearing Compensation paid for temporary easement in 2013

42 Catholic Gospel Church Worcester Outreach Meeting with design team, spring 2013 Design Period Participation in 25% design public hearing Abutter meeting with District 3 staff Abutter meeting with right-of-way staff Construction Period Structure evaluation with MassDOT resident engineer Compensation paid for temporary easement Receipt of s Tonight s briefing

43 Temporary Pedestrian Bridge Detour Set on 2/11-2/12 Detour implemented to ensure safe installment of temporary bridge The temporary pedestrian bridge is a component of the rehabilitation of the Belmont Street Bridge Allows pedestrians to detour safely around the bridge work zone

44 Temporary Pedestrian Bridge Detour: Description The previous slide showed an image of the detour plan associated with the installment of the temporary pedestrian bridge. The detour plan was implemented to ensure a safe installment of the temporary structure. The temporary pedestrian bridge has been set and the detour plan is no longer active.

45 Temporary Pedestrian Bridge Location and support piers

46 Temporary Pedestrian Bridge: Description The previous slide showed an aerial of the temporary pedestrian bridge location. The temporary pedestrian bridge is highlighted in purple and the supporting foundations are highlighted in green. The temporary pedestrian bridge will provide a safe crossing for pedestrians over I-290 while the existing structure is under construction.

47 Temporary Pedestrian Bridge Photos I Abutting work already occurring

48 Temporary Pedestrian Bridge Photos I: Description The previous slide showed 2 photographs of the temporary pedestrian bridge. The photograph is taken looking west towards the Catholic Gospel Church Worcester. Upcoming work for the month of March includes readying the temporary pedestrian bridge for use including the installment of ADA-compliant ramps.

49 Temporary Pedestrian Bridge Photos II Abutting work already occurring

50 Temporary Pedestrian Bridge Photos II: Description The previous slide showed 2 photographs of the temporary pedestrian bridge. The photograph is taken looking west towards the Catholic Gospel Church Worcester. Upcoming work for the month of March includes readying the temporary pedestrian bridge for use including the installment of ADA-compliant ramps.

51 Temporary Pedestrian Bridge contd. Readying pedestrian bridge for use including the installation of: Utility conduits Temporary ADA-compliant ramps Fencing and construction fabric Removal of support towers used for bridge installation

52 Questions & Comments For more information, please contact: Pahola DeLeon MassDOT Public Outreach Coordinator Tel:

I-676 (Vine Expressway) Bridge Reconstruction Project 22 nd - 18 th Streets Philadelphia, PA. PSPE Presentation, December 3, 2015

I-676 (Vine Expressway) Bridge Reconstruction Project 22 nd - 18 th Streets Philadelphia, PA. PSPE Presentation, December 3, 2015 I-676 (Vine Expressway) Bridge Reconstruction Project 22 nd - 18 th Streets Philadelphia, PA PSPE Presentation, December 3, 2015 Location Map N PROJECT LOCATION 22 nd 18 th Streets PHILADELPHIA, PA General

More information

Measuring the Street:

Measuring the Street: Measuring the Street: New Metrics for 21st Century Streets 1 Measuring the Street: New Metrics for 21st Century Streets New York City s streets are constantly called on to the meet new and varied needs

More information

Alternatives Presentation Meeting Middlebury WCRS(23)

Alternatives Presentation Meeting Middlebury WCRS(23) Alternatives Presentation Meeting Middlebury WCRS(23) Main Street (VT 30/TH 2 Bridge 102) and Merchants Row (TH 8 Bridge 2) over Vermont Railway June 4, 2013 Twilight Hall Auditorium, Middlebury College

More information

FOR IMMEDIATE RELEASE September 17, 2013 Contact:

FOR IMMEDIATE RELEASE September 17, 2013 Contact: NEWS RELEASE FOR IMMEDIATE RELEASE September 17, 2013 Contact: Diana L. Klink 757.514.4104 757.359.1845 Tim Kelley 757.514.4103 757.871.3039 UPDATE (Bridge Road/Mills Godwin Bridge) The work scheduled

More information

July 2010 Met Council contributes $1 million to small business loan fund More Downtown Downtown Minneapolis St. Paul

July 2010 Met Council contributes $1 million to small business loan fund More Downtown Downtown Minneapolis St. Paul July 2010 Chair Peter Bell of the Metropolitan Council speaks about the Met Council s contribution of $1 million to a $1.5 million small business loan fund during a July 20 news conference with Mayor R.T.

More information

SEMINOLE PRATT WHITNEY ROAD & NORTHLAKE BLVD. FREQUENTLY ASKED QUESTIONS

SEMINOLE PRATT WHITNEY ROAD & NORTHLAKE BLVD. FREQUENTLY ASKED QUESTIONS UPDATED: 01/31/14 SEMINOLE PRATT WHITNEY ROAD & NORTHLAKE BLVD. FREQUENTLY ASKED QUESTIONS Q. 1. What are the County s plans for Seminole Pratt Whitney Road between SR 80 (Southern Blvd) and the Bee Line

More information

PUBLIC INFORMATIONAL MEETING THURSDAY APRIL 30, 2015

PUBLIC INFORMATIONAL MEETING THURSDAY APRIL 30, 2015 PUBLIC INFORMATIONAL MEETING THURSDAY APRIL 30, 2015 AT ACTON TOWN HALL FAULKNER ROOM 472 MAIN STREET ACTON, MASSACHUSETTS 7:00 PM FOR THE PROPOSED ASSABET RIVER RAIL TRAIL (ARRT) IN THE TOWNS OF ACTON

More information

Sir Francis Drake Boulevard Rehabilitation Project Bicyclist and Pedestrian Intercept Interviews Report

Sir Francis Drake Boulevard Rehabilitation Project Bicyclist and Pedestrian Intercept Interviews Report Sir Francis Drake Boulevard Rehabilitation Project Bicyclist and Pedestrian Intercept Interviews Report Sir Francis Drake Boulevard Rehabilitation Project Bicyclist and Pedestrian Intercept Interviews

More information

3 Tappan Zee Bridge Rehabilitation Options

3 Tappan Zee Bridge Rehabilitation Options 3 Tappan Zee Bridge Rehabilitation Options 3.1 Introduction This chapter describes possible options that rehabilitate and enhance the existing Tappan Zee Bridge. Four Rehabilitation Options have been developed:

More information

BEFORE-AND-AFTER STUDY OF THE EFFECTIVENESS OF RECTANGULAR RAPID-FLASHING BEACONS USED WITH SCHOOL SIGN IN GARLAND, TEXAS

BEFORE-AND-AFTER STUDY OF THE EFFECTIVENESS OF RECTANGULAR RAPID-FLASHING BEACONS USED WITH SCHOOL SIGN IN GARLAND, TEXAS BEFORE-AND-AFTER STUDY OF THE EFFECTIVENESS OF RECTANGULAR RAPID-FLASHING BEACONS USED WITH SCHOOL SIGN IN GARLAND, TEXAS Marcus A. Brewer (corresponding author) Associate Research Engineer Texas Transportation

More information

Improving Access in Florida International University Biscayne Bay Campus Executive Summary

Improving Access in Florida International University Biscayne Bay Campus Executive Summary EXECUTIVE SUMMARY Improving Access in Florida International University Biscayne Bay Campus Executive Summary Prepared for: Miami-Dade County Metropolitan Planning Organization (Miami-Dade MPO) Prepared

More information

Purple Line Implementation Advisory Group Business Continuity During Construction July 30, 2014

Purple Line Implementation Advisory Group Business Continuity During Construction July 30, 2014 Purple Line Implementation Advisory Group Business Continuity During Construction July 30, 2014 Economic Empowerment Program Scope of Work Providing advocacy for small and disadvantaged business capacity,

More information

DESIGN PUBLIC HEARING. August 10, 2015 WEST BOYLSTON TOWN HALL, BOARD MEETING ROOM. 140 Worcester Street WEST BOYLSTON, MASSACHUSETTS 6:30 PM

DESIGN PUBLIC HEARING. August 10, 2015 WEST BOYLSTON TOWN HALL, BOARD MEETING ROOM. 140 Worcester Street WEST BOYLSTON, MASSACHUSETTS 6:30 PM DESIGN PUBLIC HEARING August 10, 2015 AT WEST BOYLSTON TOWN HALL, BOARD MEETING ROOM 140 Worcester Street WEST BOYLSTON, MASSACHUSETTS 6:30 PM FOR THE PROPOSED Rehabilitation & Stormwater Improvements

More information

Draft Transportation Management Plan for Via Verdi Repair Project

Draft Transportation Management Plan for Via Verdi Repair Project for Via Verdi Repair Project prepared for City of Richmond This report was prepared by: This report was reviewed by: Ryan McClain, P.E. Fehr & Peers TABLE OF CONTENTS 1.0 INTRODUCTION & PROJECT DESCRIPTION...

More information

Comment #1: Provide an interchange at Route 7 and Farm Market Road/White Gate Road. This was studied in the late 1990 s.

Comment #1: Provide an interchange at Route 7 and Farm Market Road/White Gate Road. This was studied in the late 1990 s. Proposed Truck Climbing Lane Route 7 Westbound Between West Market Street and Route 9 UPC# 58599, Project # 6007-053-133, P101 Date of Meeting: August 24, 2010 Time: 6:00PM to 8:00PM Location: Rust Library

More information

Public Information & Public Scoping Meeting

Public Information & Public Scoping Meeting Public Information & Public Scoping Meeting William F. Cribari Memorial Bridge Route 136 over the Saugatuck River Review of Rehabilitation Study Report Public Scoping for the gathering and analysis of

More information

Open House Public Meeting for the Thurmond Bridge Rehabilitation Project State Project: State Project S310-25/2-0.10 Federal Project: BR-0252(001)D

Open House Public Meeting for the Thurmond Bridge Rehabilitation Project State Project: State Project S310-25/2-0.10 Federal Project: BR-0252(001)D Open House Public Meeting for the State Project: State Project S310-25/2-0.10 Federal Project: BR-0252(001)D May 7, 2015 Old Glen Jean Bank Glean Jean, WV 4:00-7:00 PM www.transportation.wv.gov PROJECT

More information

North Avenue Corridor Study. Advisory Committee Meeting #5 June 11, 2014

North Avenue Corridor Study. Advisory Committee Meeting #5 June 11, 2014 North Avenue Corridor Study Advisory Committee Meeting #5 June 11, 2014 Agenda Welcome and introductions Concept refinement and evaluation: Public meeting and web survey General cross-section concepts

More information

AGENCY COORDINATION AND PUBLIC INVOLVEMENT

AGENCY COORDINATION AND PUBLIC INVOLVEMENT 5 AGENCY COORDINATION AND PUBLIC INVOLVEMENT 5.1 AGENCY COORDINATION As part of the planning process for the Oregon Avenue Final EA, DDOT conducted an agency coordination program. This coordination included

More information

ENGINEERING SOLUTIONS FOR DESIGNING YOUR SAFE ROUTES

ENGINEERING SOLUTIONS FOR DESIGNING YOUR SAFE ROUTES How to Get Started ENGINEERING SOLUTIONS FOR DESIGNING YOUR SAFE ROUTES Design Elements Selecting appropriate design treatments for school neighborhoods creates environments that address the needs of all

More information

Informational Workshop Public Meeting Kanawha Falls Bridge Project

Informational Workshop Public Meeting Kanawha Falls Bridge Project Informational Workshop Public Meeting Kanawha Falls Project WV Department of Transportation Division of Highways in Cooperation with the Federal Highway Administration State Project S310-13-0.02 00 Federal

More information

Document Name: Driving Skills. Purpose: To outline necessary driving skills required to maximize driving safety.

Document Name: Driving Skills. Purpose: To outline necessary driving skills required to maximize driving safety. Document Name: Driving Skills Date Created: 8 October 2013 Date Reviewed: 4 February 2014 Date Approved: 29 July 2015 Purpose: To outline necessary driving skills required to maximize driving safety. Overview:

More information

Disputed Red Light Accidents: A Primer on Signal Control. Jon B. Landerville, MSME, PE Edward C. Fatzinger, MSME, PE Philip S.

Disputed Red Light Accidents: A Primer on Signal Control. Jon B. Landerville, MSME, PE Edward C. Fatzinger, MSME, PE Philip S. Disputed Red Light Accidents: A Primer on Signal Control Jon B. Landerville, MSME, PE Edward C. Fatzinger, MSME, PE Philip S. Wang, MSME Intersection Accident Statistics Intersection accidents occur on

More information

Temporary Traffic Control for Building and Maintaining Single and Multi-Lane Roundabouts

Temporary Traffic Control for Building and Maintaining Single and Multi-Lane Roundabouts Purpose and Background Temporary Traffic Control for Building and Maintaining Single and Multi-Lane Roundabouts Although roundabouts have recently gained popularity and use in the United States, minimal

More information

MassDOT s Work Zone Transportation Management Procedures. By: Neil Boudreau, MassDOT and Michael Sutton, P.E., VHB

MassDOT s Work Zone Transportation Management Procedures. By: Neil Boudreau, MassDOT and Michael Sutton, P.E., VHB MassDOT s Work Zone Transportation Management Procedures By: Neil Boudreau, MassDOT and Michael Sutton, P.E., VHB What is the Work Zone Safety and Mobility Rule? 23 CFR 630 Subpart J, effective October

More information

Section 6 Traffic Analysis

Section 6 Traffic Analysis Section 6 Traffic Analysis Traffic Operations of the Preferred Network Alternative After the Preferred Network was identified and confirmed by local policy makers and area residents, detailed traffic analysis

More information

Alternatives Evaluation Overview

Alternatives Evaluation Overview Alternatives Evaluation Overview 124 Alternatives were analyzed against the evaluation criteria Criteria and criteria weighting were set by the Community Task Force Ratings were quantitative and qualitative

More information

REHABILITATION PACKAGE 1-a

REHABILITATION PACKAGE 1-a 1-a WINONA BRIDGE (BRIDGE 5900) REHABILITATION PACKAGE 1-a Rehab option 1-a is a rehabilitation package whereby all spans of the existing structure would be rehabilitated to the degree feasible and strengthened

More information

The Corporation of the TOWN OF MILTON

The Corporation of the TOWN OF MILTON The Corporation of the TOWN OF MILTON Report to: From: Mayor G. A. Krantz & Members of Council M. Paul Cripps, P. Eng., Director, Engineering Services Date: November 11, 2013 Report No. ENG-039-13 Subject:

More information

ORDINANCE CODES FOR PARKING TICKETS

ORDINANCE CODES FOR PARKING TICKETS ORDINANCE CODES FOR PARKING TICKETS Ordinance Ordinance Fine Fine if towed Code 001 Expired Meter (Municipal Lot) - Did park a motor vehicle in a municipal lot without paying or depositing in the meter,

More information

Downtown Tampa Transportation Vision

Downtown Tampa Transportation Vision Downtown Tampa Transportation Vision Executive Summary August 1, 2006 Hillsborough County Metropolitan Planning Organization County Center, 18 th Floor Tampa, Florida 33602 813-272-5940 www.hillsboroughmpo.org

More information

11 p.m. to. Tuesday, June. will remain open. 14. closed

11 p.m. to. Tuesday, June. will remain open. 14. closed June 3, 2011 CONTACT: Marcia McAllister T: 703 572 0506 C: 571 730 9117 marcia.mcallister@dullesmetro.com Important Lane Closures June 5 11 Include Northbound Beltway Lanes, Eastbound Dulles Airport Access

More information

Road Signs Recognition Quiz

Road Signs Recognition Quiz Road Signs Recognition Quiz Place your answer for each of the signs/pavement markings on the answer sheet. Ready to Roll? Here Comes Sign # 1... #1 A No right turn B Right turn only C Warning, no turn

More information

Atlanta, Georgia Road Test

Atlanta, Georgia Road Test 1. When driving your car Into traffic from a parked position, you should: A. Sound your horn and pull Into the other lane. B. Signal and proceed when safe. C. Signal other traffic and pull directly into

More information

New Jersey SRTS Travel Plan Guide

New Jersey SRTS Travel Plan Guide New Jersey SRTS Travel Plan Guide Prepared For: Funded By: Prepared By: New Jersey Department of Transportation Federal Highway Administration Alan M. Voorhees Transportation Center Edward J. Bloustein

More information

TEST ON Driving Safely Among Bicyclists and Pedestrians

TEST ON Driving Safely Among Bicyclists and Pedestrians TEST ON Driving Safely Among Bicyclists and Pedestrians Next you will take a 16 question test about driving safely among bicyclists and pedestrians. Please take out a sheet of paper to mark down and score

More information

Transportation Management Plan Template

Transportation Management Plan Template DATE: TO: FROM: SUBJECT: Date Name Position Transportation Service Center Name Position Transportation Service Center Transportation Management Plan Job Number(s) Control Section(s) Route Details County

More information

Multi-Modal Corridor Degree of Complexity: High Cost/Benefit: High

Multi-Modal Corridor Degree of Complexity: High Cost/Benefit: High Multi-Modal Corridor Degree of Complexity: Cost/Benefit: Maintain the same level of service for Ensures continuous flow through the Might impact other transportation Consider road diet and/or different

More information

KENTUCKY TRANSPORTATION CABINET. Department of Rural and Municipal Aid. Office of Local Programs

KENTUCKY TRANSPORTATION CABINET. Department of Rural and Municipal Aid. Office of Local Programs KENTUCKY TRANSPORTATION CABINET Department of Rural and Municipal Aid Office of Local Programs Office of Local Programs Transportation Enhancements Safe Routes to School Congestion Mitigation and Air Quality

More information

S.R. 37 Pavement Rehabilitation Project. Wednesday, March 5, 2014 Orange County Community Center 6:30 p.m.

S.R. 37 Pavement Rehabilitation Project. Wednesday, March 5, 2014 Orange County Community Center 6:30 p.m. S.R. 37 Pavement Rehabilitation Project Wednesday, March 5, 2014 Orange County Community Center 6:30 p.m. Welcome Purpose and explanation of public meeting Public meeting format Visit our sign-in table

More information

Corridor Goals and Objectives

Corridor Goals and Objectives Corridor Goals and Objectives This chapter presents the goals and objectives, developed by the Corridor Study Committee, that serve as the purpose and intent of the Corridor Plan. This plan covers a twenty

More information

The partnership has selected three intersections where enforcement, education, and engineering initiatives are being implemented to improve safety:

The partnership has selected three intersections where enforcement, education, and engineering initiatives are being implemented to improve safety: Hamilton-Finn Suite 310 Tel. (403) 207-6000 Road Safety 3016 5th Avenue N.E. Fax. (403) 273-3440 Consultants Ltd. Calgary, Alberta dawatt.dawatt.com www.hamiltonfinn.ca January 19, 2005 Mr. Don Szarko,

More information

Nashville Area MPO Regional Freight Study fast action projects

Nashville Area MPO Regional Freight Study fast action projects Project #1 Beechcroft road (sr 247) at csx crossing Motor carrier survey location Maury County (Spring Hill, Tn) / City of Spring Hill Current at-grade railway crossing causes traffic delays as a result

More information

The financial plan was prepared in conjunction with the Technical Working Group. Refer to Table 3-1: Funding and Implementation Plan.

The financial plan was prepared in conjunction with the Technical Working Group. Refer to Table 3-1: Funding and Implementation Plan. 3 Financial Plan The purpose of the financial plan is to identify funding options that would be likely sources of money to advance recommendations made by this study. The Capitol Region Transportation

More information

Implementation Strategy

Implementation Strategy Implementation Strategy 6 The following implementation strategy defines strategic points of intervention for complete streets programming, including visioning, goal-setting, local agency plans, coordination

More information

Comprehensive Mobility Project Development Process Capital Metro ¼-Cent Fund Analysis

Comprehensive Mobility Project Development Process Capital Metro ¼-Cent Fund Analysis Comprehensive Mobility Project Development Process Capital Metro ¼-Cent Fund Analysis Transportation & Mobility projects that meet the following criteria: enhances regional mobility; supports public transit;

More information

Veterans Memorial Bridge (Orange Avenue) PD&E Study

Veterans Memorial Bridge (Orange Avenue) PD&E Study Veterans Memorial Bridge (Orange Avenue) PD&E Study From City Island Parkway to South Peninsula Drive FDOT FPID# 242172-128-01 Volusia County Project# P-5351-1 Project Limits End Project City Island Veterans

More information

Bicycle Safety Quiz Answers Parental Responsibilities

Bicycle Safety Quiz Answers Parental Responsibilities Bicycle riding is a great way to get into shape and enjoy the outdoors. To remain safe on Illinois roads, it is important to follow the same traffic safety laws that govern vehicle drivers. No amount of

More information

City of Kamloops Notre Dame Corridor Access Plan

City of Kamloops Notre Dame Corridor Access Plan FINAL REPORT This report is prepared for the sole use of ICBC. No representations of any kind are made by Urban Systems Ltd. or its employees to any party with whom Urban Systems Ltd. does not have a contract.

More information

Appendix D. Public Information Centre Summary Report

Appendix D. Public Information Centre Summary Report Appendix D Public Information Centre Summary Report HIGHWAY 417 EXPANSION, OPERATIONAL IMPROVEMENTS AND INFRASTRUCTURE REHABILITATION From Nicholas Street to Ottawa Road 174 Detail Design G.W.P. 4091 07

More information

Mobility Management Plan Study of the Busch Boulevard Corridor

Mobility Management Plan Study of the Busch Boulevard Corridor Mobility Management Plan Study of the Busch Boulevard Corridor March 2000 Hillsborough County Metropolitan Planning Organization 601 E. Kennedy, 18th Floor Tampa, Florida 33602-5117 813/272-5940 FAX NO:

More information

Bicycle riding is a great way to get into shape

Bicycle riding is a great way to get into shape Bicycle riding is a great way to get into shape and have fun. To remain safe on Illinois roads, it is important to follow the same traffic safety laws that govern vehicle drivers. No amount of bicycle

More information

SEPTEMBER 2015 SCOPE OF WORK. MONTGOMERY COUNTY PLANNING DEPARTMENT M-NCPPC MontgomeryPlanning.org

SEPTEMBER 2015 SCOPE OF WORK. MONTGOMERY COUNTY PLANNING DEPARTMENT M-NCPPC MontgomeryPlanning.org SEPTEMBER 2015 SCOPE OF WORK MONTGOMERY COUNTY PLANNING DEPARTMENT M-NCPPC MontgomeryPlanning.org table of contents table of contents... 1 introduction... 2 planning context... 2 purpose of master plan...

More information

GOOD NEIGHBOURLY RELATIONS COMMITTEE MUHC Glen Campus: construction and road work

GOOD NEIGHBOURLY RELATIONS COMMITTEE MUHC Glen Campus: construction and road work GOOD NEIGHBOURLY RELATIONS COMMITTEE MUHC Glen Campus: construction and road work MINUTES Meeting held on Thursday, October 28, 2010 (7 p.m. to 8:45 p.m.) Committee members present Donna Allen (citizen)

More information

Street Audit Tool: Web 2.0 Tools

Street Audit Tool: Web 2.0 Tools Name: Email: Instructions: Auditor Information (1) Use all three tools for your assessment (2) If the tool can not determine the criteria, check (3) Indicate the tools used (4) Rate the effectiveness of

More information

Maryland Invests $845 Million in New Highway and Bridge Projects

Maryland Invests $845 Million in New Highway and Bridge Projects Maryland Invests $845 Million in New Highway and Bridge Projects Completing Widening of MD 404 Talbot And Caroline Counties Top Regional Priority Queen Anne s, Talbot, and Caroline Counties Widening MD

More information

SAN DIEGO GAS & ELECTRIC COMPANY SOUTH BAY SUBSTATION RELOCATION PROJECT TRAFFIC MANAGEMENT PLAN SEPTEMBER 2014

SAN DIEGO GAS & ELECTRIC COMPANY SOUTH BAY SUBSTATION RELOCATION PROJECT TRAFFIC MANAGEMENT PLAN SEPTEMBER 2014 SAN DIEGO GAS & ELECTRIC COMPANY SOUTH BAY SUBSTATION RELOCATION PROJECT TRAFFIC MANAGEMENT PLAN SEPTEMBER 2014 Traffic Management Plan TABLE OF CONTENTS 1 INTRODUCTION... 1 2 OBJECTIVES... 1 3 APPLICABLE

More information

PEDESTRIAN SAFETY AND LAWS IN PENNSYLVANIA

PEDESTRIAN SAFETY AND LAWS IN PENNSYLVANIA PEDESTRIAN SAFETY AND LAWS IN PENNSYLVANIA Gary N. Modi, P.E., Chief Safety Management Division Bureau of Highway Safety & Traffic Engineering & Christopher A. Drda, P.E., Chief Consultant Agreement Section

More information

LIMITED SCOPE CONCEPT DEVELOPMENT REPORT

LIMITED SCOPE CONCEPT DEVELOPMENT REPORT LIMITED SCOPE CONCEPT DEVELOPMENT REPORT Route 33 Resurfacing Project Eastbound: Milepost 24.2 to Milepost 28.9 Westbound: Milepost 24.3 to Milepost 28.9 Manalapan & Freehold Townships, Monmouth County

More information

Northwest Light Rail Extension Pre-Construction/Final Design. Public Meeting November 27 & 29, 2012

Northwest Light Rail Extension Pre-Construction/Final Design. Public Meeting November 27 & 29, 2012 Northwest Light Rail Extension Pre-Construction/Final Design Public Meeting November 27 & 29, 2012 6:00 6:30 p.m. Open House 6:30 7:00 p.m. Presentation 7:00 8:00 p.m. Open House 2 Project Overview Carla

More information

Context Sensitive Design for Urban Transportation in West Philadelphia

Context Sensitive Design for Urban Transportation in West Philadelphia Context Sensitive Design for Urban Transportation in West Philadelphia Transportation Research Board 85 th Annual Meeting 24 January 2006 Jeffrey M. Casello University of Waterloo Robert Wright City of

More information

UNEP recommendations to KURA on Improving Safety and Reducing Congestion on UN Avenue (7 October 2009; revised 23 November 2009)

UNEP recommendations to KURA on Improving Safety and Reducing Congestion on UN Avenue (7 October 2009; revised 23 November 2009) UNEP recommendations to KURA on Improving Safety and Reducing Congestion on UN Avenue (7 October 2009; revised 23 November 2009) UN Avenue extends for 2 km between Limuru Road and Ruaka Road (Runda Roundabout).

More information

Appendix J Transportation Management Plan Report. Traffic Operational Analysis Report

Appendix J Transportation Management Plan Report. Traffic Operational Analysis Report Appendix J Transportation Management Plan Report Traffic Operational Analysis Report Transportation Management Plan Report VIRGINIA AVENUE TUNNEL RECONSTRUCTION PROJECT WASHINGTON, DC PRELIMINARY TRANSPORTATION

More information

TRAFFIC MANAGEMENT PLAN (TMP) FRENCH-AMERICAN SCHOOL OF NEW YORK

TRAFFIC MANAGEMENT PLAN (TMP) FRENCH-AMERICAN SCHOOL OF NEW YORK Environmental and Planning Consultants 34 South Broadway Suite 401 White Plains, NY 10601 tel: 914 949-7336 fax: 914 949-7559 www.akrf.com TRAFFIC MANAGEMENT PLAN (TMP) *************************************************************

More information

APTS08 - Transit Traveler Information WRTA (1 of 2) WRTA Transit Dispatch

APTS08 - Transit Traveler Information WRTA (1 of 2) WRTA Transit Dispatch APTS08 - Transit Traveler Information WRTA (1 of 2) WRTA Website transit WRTA Transit transit user Travelers personal transit Remote Traveler Support Regional Fare Card/Transit WRTA Transit transit user

More information

Beginner s Permit. Survival Guide. Compliments of. (843) 263-5023 www.123drivedrivingacademy.com info@123drivedrivingacademy.com

Beginner s Permit. Survival Guide. Compliments of. (843) 263-5023 www.123drivedrivingacademy.com info@123drivedrivingacademy.com Beginner s Permit Survival Guide Compliments of (843) 263-5023 www.123drivedrivingacademy.com info@123drivedrivingacademy.com Please use this study guide to assist you in studying for your written knowledge

More information

WYDOT Quick Facts TRAFFIC SIGNALS

WYDOT Quick Facts TRAFFIC SIGNALS TRAFFIC SIGNALS WYDOT Quick Facts 2 Advantages of traffic signals WYDOT Quick Facts Traffic signals control vehicle and pedestrian traffic by assigning priorities to various traffic movements to influence

More information

Alterna ves Development & Evalua on

Alterna ves Development & Evalua on Spring 2015 Newsletter Issue III WHERE ARE WE IN THE PROCESS? Since the NLSD Phase I Study kickoff in 2013, numerous meetings have been held with the public, the existing conditions and transportation

More information

LOCATIONS OF UTILITIES IN PUBLIC RIGHTS-OF-WAY Examples from various Cities

LOCATIONS OF UTILITIES IN PUBLIC RIGHTS-OF-WAY Examples from various Cities LOCATIONS OF UTILITIES IN PUBLIC RIGHTS-OF-WAY Examples from various Cities American Public Works Association Utilities & Public Right of Way Committee February 29, 2000 Table o of Contents Index...Page

More information

Illinois Tollway and Chicago Department of Transportation Construction Networking Event. March 13, 2015

Illinois Tollway and Chicago Department of Transportation Construction Networking Event. March 13, 2015 Illinois Tollway and Chicago Department of Transportation Construction Networking Event March 13, 2015 Today s Agenda Welcome Illinois Tollway projects Chicago Department of Transportation (CDOT) projects

More information

First Transit Contra Flow Lane in Downtown San Francisco

First Transit Contra Flow Lane in Downtown San Francisco Introduction First Transit Contra Flow Lane in Downtown San Francisco Javad Mirabdal, Bond Yee Traffic congestion places a tremendous burden on transit vehicles in cities worldwide. San Francisco, located

More information

Welcome! Purpose of Tonight s Meeting. Informational Open House to discuss two City projects: Goal is to LISTEN TO YOU

Welcome! Purpose of Tonight s Meeting. Informational Open House to discuss two City projects: Goal is to LISTEN TO YOU Purpose of Tonight s Meeting Informational Open House to discuss two City projects: Fairchild Street Subway Phase I Engineering: Immediate need to replace subway Bowman Avenue Feasibility Study Future

More information

3.1 Historical Considerations

3.1 Historical Considerations 3. Recommended Scope of Bridge improvements 3.1 Historical Considerations In the fall of 2000, an outside consultant, Fraser Design, suggested that the existing 4 th St. Bridge is potentially eligible

More information

MID-HUDSON SOUTH TRANSPORTATION COORDINATING COMMITTEE APRIL 6, 2011. TIP Public Review Meeting

MID-HUDSON SOUTH TRANSPORTATION COORDINATING COMMITTEE APRIL 6, 2011. TIP Public Review Meeting MID-HUDSON SOUTH TRANSPORTATION COORDINATING COMMITTEE APRIL 6, 2011 TIP Public Review Meeting Meeting Agenda New York Metropolitan Transportation Council Major Products Transportation Improvement Program

More information

Traffic Safety Initiatives in Tampa Bay Florida Department of Transportation District Seven Tampa Bay

Traffic Safety Initiatives in Tampa Bay Florida Department of Transportation District Seven Tampa Bay Traffic Safety Initiatives in Tampa Bay Florida Department of Transportation District Seven Tampa Bay Peter Hsu, P.E. FDOT District Seven Safety Office Presentation Overview FDOT Traffic Safety Focus Areas

More information

CITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA. RSTP Funds Joint Application FOR

CITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA. RSTP Funds Joint Application FOR CITY OF ROANOKE AND TOWN OF VINTON, VIRGINIA RSTP Funds Joint Application FOR Tinker Creek Pedestrian Bridge: Tinker Creek and Glade Creek Greenways Connection Date: September 15, 2014 RSTP Project Profile

More information

California Crossing Guard Training: Online Course Part 2

California Crossing Guard Training: Online Course Part 2 California Crossing Guard Training: Online Course Part 2 Prepared by the Safe Routes to School Technical Assistance Resource Center The Safe Routes to School Technical Assistance Resource Center is a program

More information

Red Wing Bridge Project. PAC #5/TAC #8 Meeting July 18, 2013

Red Wing Bridge Project. PAC #5/TAC #8 Meeting July 18, 2013 Red Wing Bridge Project PAC #5/TAC #8 Meeting July 18, 2013 Alternatives Analysis Agenda Overview of Past Progress Progress Since April PAC Bridge 9103 Rehabilitation Study Bridge 9040 Rehab vs. Replacement

More information

AREA: 2.37 acres NUMBER OF LOTS: 1 FT. NEW STREET: 0 LF. Single-family, Non-conforming machine shop

AREA: 2.37 acres NUMBER OF LOTS: 1 FT. NEW STREET: 0 LF. Single-family, Non-conforming machine shop FILE NO.: Z-8958 NAME: Rock Structure Repair Short-form PID LOCATION: Located at 8024 Stanton Road DEVELOPER: Rock Structure Repair Attn. Rudy Gutierrez 3 Kipling Court Little Rock, AR 72209 ENGINEER:

More information

WORK ZONE SAFETY & MOBILITY GUIDANCE DOCUMENT

WORK ZONE SAFETY & MOBILITY GUIDANCE DOCUMENT WORK ZONE SAFETY & MOBILITY GUIDANCE DOCUMENT August 2007 Prepared by: Vermont Agency of Transportation The following document was drafted in response to updates made to the work zone regulations at 23

More information

APPLICATION LAFAYETTE METROPOLITAN PLANNING ORGANIZATION (MPO) SURFACE TRANSPORTATION PROGRAM (STP) FUNDS TRANSPORTATION IMPROVEMENT PROGRAM (TIP)

APPLICATION LAFAYETTE METROPOLITAN PLANNING ORGANIZATION (MPO) SURFACE TRANSPORTATION PROGRAM (STP) FUNDS TRANSPORTATION IMPROVEMENT PROGRAM (TIP) APPLICATION LAFAYETTE METROPOLITAN PLANNING ORGANIZATION (MPO) SURFACE TRANSPORTATION PROGRAM (STP) FUNDS TRANSPORTATION IMPROVEMENT PROGRAM (TIP) To be considered for STP funding, a proposed project must

More information

Project Information. New Hope - Lambertville Toll Bridge - Pavement Rehabilitation & Approach Bridges Repairs -

Project Information. New Hope - Lambertville Toll Bridge - Pavement Rehabilitation & Approach Bridges Repairs - Project Information Existing Conditions Cracked and settled pavement. Structural failure within the asphalt pavement section. Anticipated Project Elements Reconstruction of all asphalt pavement on US Route

More information

ROAD SAFETY AUDIT. Derby Street at Whiting Street (Route 53)/Gardner Street. Town of Hingham. April 2014

ROAD SAFETY AUDIT. Derby Street at Whiting Street (Route 53)/Gardner Street. Town of Hingham. April 2014 ROAD SAFETY AUDIT Derby Street at Whiting Street (Route 53)/Gardner Street Town of Hingham April 2014 Prepared for: Massachusetts Department of Transportation Prepared by: Howard/Stein-Hudson Associates

More information

Squrriel Hill Tunnel Rehabilitation Detours. The following pages are detour routes for weekend daytime/nightime traffic.

Squrriel Hill Tunnel Rehabilitation Detours. The following pages are detour routes for weekend daytime/nightime traffic. Squrriel Hill Tunnel Rehabilitation Detours The following pages are detour routes for weekend daytime/nightime traffic. 1 P:\1555 s\21535146 - Squirrel Hill Tunnel Rehab\Cadd\Presentation\Press Release\WB_Day_Detour.dgn

More information

RESOLUTION NO. 1539 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF BONNEY LAKE, PIERCE COUNTY, WASHINGTON, APPROVING THE 192 ND CORRIDOR STUDY AND DIRECTING THE MAYOR TO PROCEED WITH PARTIAL DESIGN AND

More information

BEST PRACTICES. Smart Transportation is a key concept for the Paoli Roadway Improvement Project.

BEST PRACTICES. Smart Transportation is a key concept for the Paoli Roadway Improvement Project. Smart Transportation Smart Transportation is a key concept for the Paoli Roadway Improvement Project. PennDOT s Smart Transportation Guidebook (2008) outlines a comprehensive approach to transportation

More information

In 2005, the City of Pasadena, CA, USA, with the support of consultants,

In 2005, the City of Pasadena, CA, USA, with the support of consultants, Creating a Citywide Safe Routes to School Program: Pasadena, CA, USA s Step-by-Step Approach In 2005, the City of Pasadena, CA, USA, initiated development of a comprehensive Safe Routes to School Program.

More information

STANDARD ELEMENTS OF A CONSTRUCTION MANAGEMENT PLAN

STANDARD ELEMENTS OF A CONSTRUCTION MANAGEMENT PLAN STANDARD ELEMENTS OF A CONSTRUCTION MANAGEMENT PLAN JULY 2015 Standard Elements of a Construction Management Plan (CMP) This guidance tool was developed through partnership between the Department of Planning

More information

Project Status Update Open House West End Corridor

Project Status Update Open House West End Corridor Project Status Update Open House West End Corridor The Exposition Construction Authority cordially invites you to a Project Status Update Open House for the Exposition Light Rail Line At this meeting we

More information

Road Repaving and Street Safety Bond Quarterly Status Report presented to the Citizens General Obligation Bond Oversight Committee As of March 2016

Road Repaving and Street Safety Bond Quarterly Status Report presented to the Citizens General Obligation Bond Oversight Committee As of March 2016 Road Repaving and Street Safety Bond Quarterly Status Report presented to the Citizens General Obligation Bond Oversight Committee As of March 2016 Overview of RRSS Bond Scope and Budget (including accountability

More information

Near Westside Neighborhood and University Avenue Corridor Transportation Study. Public Workshop #2. September 12 and 23, 2013

Near Westside Neighborhood and University Avenue Corridor Transportation Study. Public Workshop #2. September 12 and 23, 2013 Near Westside Neighborhood and University Avenue Corridor Transportation Study Public Workshop #2 September 12 and 23, 2013 Presentation Outline: Brief Review of Study Scope, Background, and Current Conditions

More information

Selected Parking Regulations from the New Orleans City Code (The quotation marks have been omitted in the cited material).

Selected Parking Regulations from the New Orleans City Code (The quotation marks have been omitted in the cited material). I. Parking Violations: * Your vehicle can be towed for almost any parking offense. * Parking fines vary, and all included fines approximate the fines as of August 4, 2014. * If you neglect to pay your

More information

Appendix C Business Outreach Summary. Contents:

Appendix C Business Outreach Summary. Contents: Appendix C Business Outreach Summary Contents: 1. Business Assessment Form 2. Business Assessment Results Summary 3. Business Outreach Meetings Summary Communicating with Small Businesses About Transportation

More information

PEDESTRIAN LAWS OF NORTH CAROLINA

PEDESTRIAN LAWS OF NORTH CAROLINA PEDESTRIAN LAWS OF NORTH CAROLINA Under North Carolina law, pedestrians have the right of way at all intersections and driveways. However, pedestrians must act responsibly, using pedestrian signals where

More information

Florida Avenue Multimodal Transportation Study. June 19, 2013

Florida Avenue Multimodal Transportation Study. June 19, 2013 Florida Avenue Multimodal Transportation Study June 19, 2013 Today s Agenda Team & project introduction Project Timeline What you said Tools we use Mapped data and what clues it can provide Highlights

More information

SAFE Streets for CHICAGO

SAFE Streets for CHICAGO Overview Each day, hundreds of thousands of Chicagoans walk or drive in the city. Ensuring their safety is the City s top priority. Over the past several years, Chicago has developed many successful strategies

More information

Owner Controlled Insurance Program (OCIP) Overview

Owner Controlled Insurance Program (OCIP) Overview Owner Controlled Insurance Program (OCIP) Overview Prepared for Caltrans Oakland Touchdown Outreach Presented by: Willis One Bush Street, Suite 900 San Francisco CA 94104 (415) 981-1141 WHAT IS AN OCIP

More information

FY 2011 OHIO SMALL CITIES COMMUNITY DEVELOPMENT BLOCK GRANT COMPREHENSIVE DOWNTOWN REVITALIZATION PROGRAM

FY 2011 OHIO SMALL CITIES COMMUNITY DEVELOPMENT BLOCK GRANT COMPREHENSIVE DOWNTOWN REVITALIZATION PROGRAM CITYOFOBERLIN OHIO CITY OF OBERLIN, OHIO FY 2011 OHIO SMALL CITIES COMMUNITY DEVELOPMENT BLOCK GRANT COMPREHENSIVE DOWNTOWN REVITALIZATION PROGRAM Background In October, 2011, the City of Oberlin Planning

More information

Massachusetts Department of Transportation, Highway Division Ten Park Plaza, Boston, MA 02116-3973. A Guide on Traffic Analysis Tools

Massachusetts Department of Transportation, Highway Division Ten Park Plaza, Boston, MA 02116-3973. A Guide on Traffic Analysis Tools Massachusetts Department of Transportation, Highway Division Ten Park Plaza, Boston, MA 02116-3973 A Guide on Traffic Tools Revised October 5, 2012 1. PURPOSE The Massachusetts Department of Transportation,

More information

Evanston Main Street Station TOD Plan and Study. Appendix A.1: Station Area Existing Conditions

Evanston Main Street Station TOD Plan and Study. Appendix A.1: Station Area Existing Conditions Evanston Main Street Station TOD Plan and Study Appendix A.1: Station Area Existing Conditions EvanstonMainStreetStation TODPlanandStudy A 1 AppendixA.1: ExistingConditions Table of Contents Station Locations

More information