Construction Concerns: Connecting Cross Laminated Timber
|
|
- Thomasina Newman
- 7 years ago
- Views:
Transcription
1 Construction Concerns: Connecting Cross Laminated Timber March 14, 2016 By Gregory Havel Photos as noted The use of cross-laminated timber (CLT) was recently incorporated into the 2015 edition of the International Building Code (IBC), with an unprotected fire resistance rating of up to two hours. It is likely to be incorporated into the next edition of National Fire Protection Association (NFPA) 5000, Building Construction and Safety Code. The IBC places limits on the heights and areas of CLT structures that are similar to those of conventional Type IV (heavy timber) and Type V (wood frame) construction. As a result, the two high-rises that are proposed to be built in Oregon and New York will need variances from the building codes by state and local building officials. The IBC also permits taller buildings with larger floor areas when equipped with automatic fire sprinkler systems. CLT panels can be used as walls, floor/ceiling assemblies, and roofs. They can be connected to each other; to other manufactured wood products; to structural steel; to concrete; and to masonry. Each combination of materials has several attachment methods, as do the connections between floor and wall, wall and wall, panel to panel, and roof to wall. Some of these methods and connectors are shown with this article. As this is a relatively new material in the United States, and is not yet in use in southeastern Wisconsin, the photos and illustrations used are from manufacturer and other Web sites, as noted. These photos are for illustrative purposes only, and do not constitute an endorsement of any product or manufacturer. March 14, 2016 Page 1 of 6
2 Connections between CLT panels can use mechanical fasteners or adhesives or both. The construction adhesives used are usually a polyurethane paste applied in beads with a hand-operated or powered dispensing gun. Photo 1 (above) shows a type of ring-shank nail that can be used to fasten CLT panels together. Photo 2 shows a type of patented screw that can be used to fasten CLT panels together, or to attach plates or angles to the CLT panels. March 14, 2016 Page 2 of 6
3 Photo 3 shows an edge of a CLT panel that has been milled to receive three wood splines, which will be attached with construction adhesive and screws. Half-lap joints are milled on the edges of CLT panels at the factory, and connected in the field with adhesive and screws or nails. March 14, 2016 Page 3 of 6
4 Photo 4 shows three types of plates and angles that can be used to connect CLT panels to each other, or to concrete or masonry. These will be attached to the CLT panels with screws similar to those shown in Photo 2. These plates and angles may be exposed or concealed. Even if they are exposed after the panels are connected, they will be concealed by interior finishes and exterior cladding. Photo 5 shows a CLT wall panel being set with a crane, and which will be connected to the CLT floor with the plates and angles that are already attached to the floor. March 14, 2016 Page 4 of 6
5 Photo 6 shows how pre-assembled CLT modules can be combined together to form single-family and multi-family residential buildings. Photo 7 shows a crane setting another preassembled CLT module during construction of an apartment building. March 14, 2016 Page 5 of 6
6 Bolts, rods, dowels, and cam-locks are other types of mechanical fasteners that are used to connect CLT panels. It should be of concern to firefighters that a building of CLT construction will look like any other modern building (or older remodeled building) when it is finished. The CLT and their connections are likely to be concealed on the interior with gypsum drywall board, wood paneling, or other materials in common use in building interiors of all types. They are likely to be concealed on the exterior by insulation and exterior finishes like Exterior Insulation Foam System (EIFS), void spaces for loose-fill insulation and utilities, and noncombustible cladding (metal, cement-board). Unless the building has a preincident plan on file that was prepared either while the building was under construction or from the building plans after it was completed, firefighters will not be aware of the construction materials and methods used in the building; and will not be able to reliably predict the behavior of a fire starting in the building. For more information on cross-laminated timber, its uses, and its connection methods: Internet search for cross laminated timber or CLT ; Review manufacturer websites; Check the index of the International Building Code, 2015 edition, for cross laminated timber and CLT ; Review the CLT Handbook, US Edition, 2013 by FPInnovations and the Binational Softwood Lumber Council. It is a free download by chapter or in its entirety from Read the articles on this subject in the January 2016 issue of Fire Engineering and the July 2013 Construction Concerns Visit and Gregory Havel is a member of the Town of Burlington (WI) Fire Department; retired deputy chief and training officer; and a 35-year veteran of the fire service. He is a Wisconsin-certified fire instructor II, fire officer II, and fire inspector; an adjunct instructor in fire service programs at Gateway Technical College; and safety director for Scherrer Construction Co., Inc. Havel has a bachelor's degree from St. Norbert College; has more than 35 years of experience in facilities management and building construction; and presents classes at FDIC. March 14, 2016 Page 6 of 6
ISO Types 1-6: Construction Code Descriptions
ISO 1 Frame (combustible walls and/or roof) Class 1B Buildings where the exterior walls are wood or other combustible materials, including construction where the combustible materials are combined with
More informationNew Ontario Building Code Requirements for Mid-rise Wood Frame Buildings
New Ontario Building Code Requirements for Mid-rise Wood Frame Buildings Note: This information addresses complex issues in a summary fashion. Consideration should be given to the official version of the
More informationThe Case for Cross Laminated Timber: Part 2
Learning Objectives The Case for Cross Laminated Timber: Part 2 Opportunities and Challenges for a New Class of Timber Product 1. Review answers to common questions regarding the design and construction
More informationCHAPTER 6 CONSTRUCTION TYPES
CHAPTER 6 CONSTRUCTION TYPES SECTION 601 GENERAL 601.1 Scope. Provisions of this chapter shall govern the classification of construction type by materials and fire resistance of its elements and the use
More informationThe better way to build TM. Installation Manual. EXTERIOR WALL SIPs
The better way to build TM Installation Manual EXTERIOR WALL SIPs July 2015 EXTERIOR WALL SIPs Installation Manual Table of Contents Topics General Requirements................................... 3 Materials..............................................
More informationINSTALLATION OF A BAY WINDOW
INSTALLATION OF A BAY WINDOW Installation of a Bay Window These instructions relate to the replacement of an existing bay window or replacement of a straight window with a new bay window, in an opening
More informationBuilding Construction. Lightweight construction. Conventional Construction
Ventilation 53 Building Construction The firefighter s ability to safely and efficiently ventilate a building through its roof will depend to some degree on the firefighter s understanding of roof construction.
More informationWHI 90-Minute Rated Veneered Door Frame Installation Instructions
No. 940-03-10 INSTALLATION INSTRUCTIONS 90 MINUTE RATED VENEERED DOOR FRAME DOOR REQUIREMENTS: Consult the door manufacturer to make sure that the doors are qualified for the hardware to be installed,
More informationWisconsin Building Products Evaluation
Safety & Buildings Division 201 West Washington Avenue P.O. Box 2658 Madison, WI 53701-2658 Evaluation # 200813-O Wisconsin Building Products Evaluation Material Best Management Standards for Foundation
More informationCONSTRUCTION DETAILS & LOAD DESIGN CHARTS
Office and Production 126 New Pace Rd., PO Box 279 Newcomerstown, OH 43832 1-800-446-2188, Fax: 740-498-4184 www.buildwithsips.com CONSTRUCTION DETAILS & LOAD DESIGN CHARTS Table of Contents Description
More informationICC-ES Evaluation Report Reissued September, 2010 This report is subject to re-examination in one year.
ICC-ES Evaluation Report ESR-2270 Reissued September, 2010 This report is subject to re-examination in one year. www.icc-es.org (800) 423-6587 (562) 699-0543 A Subsidiary of the International Code Council
More informationSuperform Products Ltd.
TYPICAL CORNER REINFORCING NOTE : SEE ENGINEERED REBAR SCHEDULES SUPPLIED BY THE MANUFACTURER STEEL REINFORCEMENT WALL CORNER 90 Copyright 2012 Sept. 2012 5.1.1 Rebar Spacing 6" 12" Max. Load LB./FT. 2000
More informationInsulation R-Value Comparisons
Insulation R-Value Comparisons American Ingenuity s component panels for the 22 48 domes contains seven inch thick rigid Expanded Polystyrene (E.P.S.) insulation which has an R value of 28. American Ingenuity
More informationWood use in Type I and II (noncombustible) construction
Wood use in Type I and II (noncombustible) construction D.G. Bueche Hoover Treated Wood Products, Thomson, Georgia, USA ABSTRACT: As with many products, the building code regulates the use of wood in construction.
More informationIs Your Envelope Effective? Mark Lawton P.Eng Morrison Hershfield Limited Vancouver
Is Your Envelope Effective? Mark Lawton P.Eng Morrison Hershfield Limited Vancouver Designing an Effective Envelope Roofs Below Grade Walls and slabs Glazing & Windows Opaque portions of walls 2 3 Energy
More informationTHE DOW CHEMICAL COMPANY Issued: August 1, 2008 200 LARKIN CENTER 1605 JOSEPH DRIVE MIDLAND MICHIGAN 48674 (989) 638-8655 www.dowbuildingmaterials.
ICC EVALUATION SERVICE, INC. EvaluateP InformP Protect Los Angeles Business/Regional OfficeP 5360 Workman Mill RoadP Whittier, CA 90601 (562) 699-0543 phonep (562) 695-4694 fax DIVISION: Section: 6 WOOD
More informationBasement Window Installation Guide Hopper and Sliding
Basement Window Installation Guide Hopper and Sliding americancraftsmanwindows.com Project Requirements: Installation must comply with all applicable building codes. Existing window frame, wall and weatherresistant
More informationMarch 14, 2007. Installation of Bay, Bow and Garden Windows
March 14, 2007 Re: Installation of Bay, Bow and Garden Windows Attached are the Atrium Companies, Inc recommendation for the installation of bay, bow and garden windows. These instructions were developed
More information2.18 INTERIOR & EXTERIOR FINISHES 2.18.1 VAPOR & AIR BARRIERS
2.18 INTERIOR & EXTERIOR FINISHES 2.18.1 VAPOR & AIR BARRIERS The LOGIX wall assembly has no need for an additional vapor barrier, the solid concrete core covered with the low permeance EPS (Type II) foam
More informationThe better way to build TM. Installation Manual. FOUNDATION SIPs & FROST WALLS SIPs
The better way to build TM Installation Manual FOUNDATION SIPs & FROST WALLS SIPs February 2016 PWF FOUNDATION & FROST WALL SIPs Installation Manual Table of Contents Topics General Requirements...................................
More informationFOUNDATION INSULATING SYSTEM, INCLUDING WATERPROOFING AND DAMP PROOFING
FOUNDATION INSULATING SYSTEM, INCLUDING WATERPROOFING AND DAMP PROOFING insulation installed on foundation walls must be separated from the building interior with a code approved thermal barrier. Foam
More informationFig. 2 WALL-TO-WALL PANEL CONNECTIONS CORNER WALL CONNECTION
SIPS SCREWS WITH MINIMUM 1" PENETRATION IN WOOD MEMBER IN SIP WALL PANEL CONNECTED TO @ 24" O.C. MAXIMUM OUTSIDE SKIN EACH SIDE OF FRAMING TYP. AS RECOMMENDED BY FOAM CORE AS EACH SIDE OF FRAMING TYP.
More informationIf you are a web registered user of ArlingontPermits.com you may also request an inspection at:
TECHNICAL BULLETIN Community Development & Planning, Building Inspections TOPIC: Permits & Inspections for Roofing Replacement Effective November 1, 2011 Revised This Technical Bulletin will provide contractors
More informationInstallation Guide for Andersen Architectural Clad Outswing Commercial Doors
Installation Guide for Andersen Architectural Clad Outswing Commercial Doors Congratulations! You have just purchased one of the many fine Andersen products. Proper assembly, installation and maintenance
More informationUncovered Decks & Porches
Uncovered Decks & Porches Building Guides for Homeowners Why Do I need a Permit? D I D Y O U K N O W? As owner-builder you are the responsible party of record on such a permit. If your work is being performed
More informationAUTHORIZATION TO MARK
AUTHORIZATION TO MARK This authorizes the application of the Certification Mark(s) shown below to the models described in the Product(s) Covered section when made in accordance with the conditions set
More informationRockwool Flexi Insulation Application Guide
Pitched roof Rafters InterMediate floors INTERNAL partitions external Framed walls separating floors Separating Walls Rockwool Flexi Insulation Application Guide Ground floor The perfect fit for any framed
More informationInstallation Guide for Andersen Architectural Wood Inswing Entry Doors
Installation Guide for Andersen Architectural Wood Inswing Entry Doors Congratulations! You have just purchased one of the many fine Andersen products. Proper assembly, installation and maintenance are
More informationElectrical Wiring Technical Bulletin
Electrical Wiring Technical Bulletin Overview In general, SIP construction is easier and more cost effective when things are planned and thought out before the panels are manufactured. This process will
More informationfire separating walls #2
210108 fire separating walls #2 ISSUE BSA has identified a number of instances of defective fire separating walls in duplexes, town houses and multi-residential complexes. The system of fire separating
More informationResidential Deck Safety, Construction, and Repair
Juneau Permit Center, 4 th Floor Marine View Center, (907)586-0770 This handout is designed to help you build your deck to comply with the 2006 International Residential Building code as modified by the
More informationHOOVER TREATED WOOD PRODUCTS, INC. TECHNICAL NOTE FOR ADDITIONAL INFORMATION: 1-800-TEC-WOOD (832-9663)
HOOVER TREATED WOOD PRODUCTS, INC. TECHNICAL NOTE FOR ADDITIONAL INFORMATION: 1-800-TEC-WOOD (832-9663) Fire-Retardant-Treated Wood Framed Wall Assemblies GENERAL INFORMATION Fire-resistant construction
More informationInstallation Instructions Double-Hung, Single-Hung, Casement, Awning, Sliding, Picture & Shapes Non-Impact & Impact Resistant Nailing Fin Windows
Installation Instructions Double-Hung, Single-Hung, Casement, Awning, Sliding, Picture & Shapes Non-Impact & Impact Resistant Nailing Fin Windows americancraftsmanwindows.com Project Requirements: Read
More informationSun Windows General Information Sun New Construction Window Installation Instructions
Sun Windows General Information Section 1 G F H H H A. Apply Weather Resistive Barrier B. Apply Sill Flashing Tape C. Place Waterproof Sill Shims D. Caulk Back of Nail Fin Sides & Top, Set Window, Fasten
More informationHow to secure your property after a disaster
How to secure your property after a disaster The Red Guide to Recovery HOuse secured properly Board-Up of Windows, Doors and Roof Hole. Lot secured with Perimeter Fencing. Fires, floods, tornadoes, hurricanes,
More informationGuidelines for Earthquake Bracing of Residential Water Heaters
Guidelines for Earthquake Bracing of Residential Water Heaters Department of General Services Division of the State Architect 1102 Q Street, Suite 5100 Sacramento, CA 95814 Phone: (916) 324-7099 Fax: (916)
More informationEurocode 5: Design of timber structures
Eurocode 5: Design of timber structures Arnold Page, BSc, BD, MIWSc. Structural timber engineering consultant Introduction BS EN 1995 consists of three parts: Part 1-1: General. Common rules and rules
More informationAvoiding Air Barrier Pitfalls
Avoiding Air Barrier Pitfalls Design & Durability November 2013 Air barriers, when correctly installed, help buildings achieve high levels of energy efficiency by decreasing heat loss. For example, great
More information2.9 WINDOW & DOOR BUCKS
2.9 WINDOW & DOOR BUCKS Bucks provide attachment surfaces for windows and doors while holding back concrete from these openings during concrete placement. Mark the center and edges of openings as you place
More informationClad Direct Glaze Window Installation Instructions
Clad Direct Glaze Window Installation Instructions Sill flashing and sealing: 2. An overview of the proper flashing sequence is shown in figure 1. Please read entire installation instructions carefully
More informationFire safety in timber buildings
Fire safety in timber buildings Introduction Fire spread in buildings is a risk to life safety for which the Building Regulations (for England and Wales 1,2, Scotland 3 and Northern Ireland 4 ) aims to
More informationHURRICANE MITIGATION RETROFITS FOR EXISTING SITE-BUILT SINGLE FAMILY RESIDENTIAL STRUCTURES
HURRICANE MITIGATION RETROFITS FOR EXISTING SITE-BUILT SINGLE FAMILY RESIDENTIAL STRUCTURES 101 Retrofits Required. Pursuant to Section 553.844 553.884, Florida Statutes, strengthening of existing site-built,
More informationFire 2This Technical Bulletin has been commissioned by the UK SIP Association in
REV 1-12.12.11/TB002 Technical Bulletin Fire 2This Technical Bulletin has been commissioned by the UK SIP Association in conjunction with TRADA Technology and is intended to provide the reader with introductory
More informationMark Cramer Inspection Services, Inc.
Mark Cramer Inspection Services, Inc. 492 Twentieth Avenue, Indian Rocks Beach, FL 34635-2970 (727) 595-4211 Fax (727) 596-7583 Certified Member #12085 American Society of Home Inspectors Construction
More informationRACQUETBALL, HANDBALL OR SQUASH COURTS AND GYMNASIUM WALL SURFACES
1807 Elmwood Avenue, Suite 275 Buffalo, New York 14207 (800) 543-5155 RACQUETBALL, HANDBALL OR SQUASH COURTS AND GYMNASIUM WALL SURFACES Fiberesin Wall System Provide materials and labor to complete courts
More informationfirst look at GigaCrete s revolutionary new New Construction GigaHouse GigaHouse Utilizing GigaPanel
first look at GigaCrete s revolutionary new New Construction GigaHouse GigaHouse Utilizing GigaPanel What is GigaCrete GigaCrete is a family of products based on low carbon footprint Green ceramic binders
More informationBrick Veneer Construction
Brick Veneer Construction Check list of suggested tools & support items Claw hammer Tape measure 3/4" [19 or 20] Wood chisel Wood or plastic shims Pry bar Utility knife Caulking and caulking gun Power
More informationPITCHED ROOF STRUCTURES
PITCHED ROOF STRUCTURES for framed and frameless photovoltaic modules Needed tools and materials: cordless screwdriver 10mm and 13mm spanners 5mm Allen key bolts, screws and tools for fixing the system
More informationROOFING APPLICATION STANDARD (RAS) No. 150 PRESCRIPTIVE BUR REQUIREMENTS
ROOFING APPLICATION STANDARD (RAS) No. 150 PRESCRIPTIVE BUR REQUIREMENTS 1. 2. 3. 3.0 Scope 1.1 This application standard shall be used where the authority having jurisdiction has adopted its use, and
More informationStandard from CSI Part Section Format. 06212 For Wood Framing 05160 For Metal Framing 09226 For Gypsum Sheathing
Standard from CSI Part Section Format. 06212 For Wood Framing 05160 For Metal Framing 09226 For Gypsum Sheathing Specifications for SURE-BOARD Series 200 and 200W Panel for shear PART 1.0 GENERAL 1.01
More informationWorkSafe Guidance Document FALL PROTECTION IN RESIDENTIAL CONSTRUCTION
WorkSafe Guidance Document FALL PROTECTION IN RESIDENTIAL CONSTRUCTION WorkSafe Guidance Document Fall Protection in Residential Construction Table of Contents Executive Summary... 1 Introduction... 1
More informationFire-Retardant-Treated (FRT) Plywood
T e c h n i c a l n o t e Fire-Retardant-Treated (FRT) Plywood Number K320 January 2009 Introduction Codes assure fire safety by controlling such things as size and design of the structure and flame-spread
More informationDesigning With. Designing With Structural Insulated Panels Advanced. Credit for this course is 1 AIA HSW CE Hour. Course Sponsor
SIPA 2014 An American Institute of Architects (AIA) Continuing Education Program Provider: Structural Insulated Panel Association Designing With Structural Insulated Panels Advanced Credit for this course
More informationRESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000
RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000 SECTION R905 REQUIREMENTS FOR ROOF COVERINGS R905.1 Roof covering application. Roof coverings
More informationEngineered Wood Foundations
Engineered Wood Foundations Emeraldfoundations.com 1 EWF Planning and Installation manual This manual will serve as a guide to planning and installing an Emerald Foundation system. This system is comprised
More informationPANELIZED HOME INSTALLATION GUIDELINE
PANELIZED HOME INSTALLATION GUIDELINE A typical home package will be constructed of Snap-N-Lock Insulated Panels clad with steel skins. 4" panels will be used for the walls, and 6" panels for the roof.
More informationWindow Installation Instructions
Caution The correct installation methods of windows in full frame or insert applications is critical towards achieving the tested performance of the window and longterm enjoyment and energy savings for
More informationWINDOW PANNING AND TRIMS
OCTOBER, 2010 PANNING AND TRIMS GENERAL INFORMATION 1 EXTERIOR PANNING Panning is primarily used to cover the perimeters of existing building openings prior to the installation of replacement windows.
More informationPost and Beam Construction
Post and Beam Construction A Presentation By the Canadian Wood Council Canadian Conseil Wood canadien Council du bois Early settlers introduced the concept of post and beam construction in North America
More informationContractor s Statement of Responsibility for Seismic-Force-Resisting Systems This form is to be filled out by the contractor.
SPECIAL INSPECTION PROCEDURE IBC CHAPTER 17 2012 EDITION When Required All projects that require a SC licensed Architect or Engineer per SC Architectural and Engineering registration law. Overview The
More informationFire-Rated Glass and Glazing START
Fire-Rated Glass and Glazing START www.pilkington.com/fire Fire-Rated Glass and Glazing Pilkington Fire Protection Glass North America 946 Kane Street, Suite A Toledo, OH 43612 Provider Number: J200 Course
More informationBrock Commons Phase 1 University of British Columbia, Vancouver, Canada
Construction Underway on World s Tallest Timber Tower Construction of the 18 storey Brock Commons Student Residence at the University of British Columbia in Vancouver, Canada got underway in November 2015.
More informationStructural fire design Eurocode 5-1.2 Timber structures
Background and Applications Brussels, 18-20 February 2008 Dissemination of information workshop 1 Structural fire design Eurocode 5-1.2 Timber structures Jochen Fornather Austrian Standards Institute jochen.fornather@on-norm.at
More informationRequirements for Fire Protection of Light Weight Floor Systems **Act 1 Revisited**
PHRC Webinar Series Tuesday, September 9, 2014 1:00 pm Requirements for Fire Protection of Light Weight Floor Systems **Act 1 Revisited** Presented by: Bryan Heitzmann Credit(s) earned on completion of
More informationMASTERFORMAT SPECIFICATION
Insulspan, Incorporated 9012 East US 223 Blissfield, MI, USA 49228-0026 Phone: 800.726.3510 Insulspan Division of Plasti-Fab Ltd. 600 Chester Road Deltas, BC, Canada V3M 5Y3 Phone: 866.848.8855 www.insulspan.com
More informationInstallation Details. D1 General D2 Walls D3 Ceilings D4 Reference. D Installation Details
D Installation Details D1 General D2 Walls D3 Ceilings D4 Reference D Installation Details D Contents D1 General Installation and Fastening Sequence for Steel Studs D1.1 Fastener Selection D1.3 D2 Walls
More informationChapter 6 ROOF-CEILING SYSTEMS
Chapter 6 ROOF-CEILING SYSTEMS Woodframe roof-ceiling systems are the focus of this chapter. Cold-formed steel framing for a roof-ceiling system also is permitted by the IRC but will not be discussed;
More informationH-Stud Area Separation Wall System
12 TH EDITION 09 21 16.33/NGC H-Stud Area Separation Wall System 09 21 16.33 139 H-STUD AREA SEPARATION WALL SYSTEM The fire-protection of gypsum-based Area Separation Walls is demonstrated in dramatic
More informationTimber Decks. Technical Note. March 2007
Timber Decks Technical Note. March 2007 This Technical Note contains general information for residential timber decks and floor frame structures for veranda s, patios etc which are exposed to the weather.
More informationDIVISION: 06 00 00 WOOD, PLASTICS AND COMPOSITES SECTION: 06 05 83 SHOP APPLIED WOOD COATINGS SECTION: 06 16 00 SHEATHING REPORT HOLDER:
0 ICC ES Report ICC ES (800) 423 6587 (562) 699 0543 www.icc es.org 000 Most Widely Accepted and Trusted ESR 1365 Reissued 04/2016 This report is subject to renewal 04/2017. DIVISION: 06 00 00 WOOD, PLASTICS
More informationAdditions and Alterations
Additions and Alterations Addition and alteration construction is a miscellaneous grouping of home improvement and renovation projects that are generally geared toward the enhancement of an existing principal
More informationBuilding Code Clarifications - 7. Fire Resistance
Building Code Clarifications - 7. Fire Resistance 7.1 (15-12-030) Use of combustibles in Type III construction roof assemblies Code Section (15-12-030) Use of Combustibles was revised on May 17, 2000,
More informationReplacement Window Installation Guide Non-Impact & Impact Resistant Windows without Nailing Fin
Replacement Window Installation Guide Non-Impact & Impact Resistant Windows without Nailing Fin americancraftsmanwindows.com Project Requirements: Failure to follow these instructions may void product
More informationExcerpts from the Canadian National Building Code (NBC)
Excerpts from the Canadian National Building Code (NBC) Reproduced here with Permission of the Copyright Owner, the National Research Council of Canada, Institute for Research in Construction. For more
More informationDesigning for Fire Protection
Architect: CUBE 3 Studio. Structural engineer: Veitas & Veitas Engineers. Photo: CUBE 3 Studio & Rixon Photography. Vox on Two in Cambridge, Massachusetts, includes four stories of wood-frame construction
More informationStudent Academic Achievement Committee (SAAC) Standardized Report Form
Student Academic Achievement Committee (SAAC) Standardized Report Form INTRODUCTION Program/Discipline Title: Construction Technology General Construction Concentration Degree Time Period: Fall term through
More informationBuilding Performance Bulletin
Building Performance Bulletin Fire is an ever-present danger for building occupants. Understanding and applying code requirements will enhance occupant safety regardless of the materials used to construct
More informationMAJOR 2015 MN RESIDENTIAL CODE CHANGES Effective Date: January 24 th, 2015
MAJOR 2015 MN RESIDENTIAL CODE CHANGES Effective Date: January 24 th, 2015 **Disclaimer: This document is to serve as informational purposes only. This is not a code book or a final interpretation of the
More informationGuidelines for Earthquake Bracing Residential Water Heaters
Guidelines for Earthquake Bracing Residential Water Heaters Department of General Services Division of the State Architect In accordance with the Health and Safety Code Section 19215, the Division of the
More informationREQUIREMENTS FOR SUBMITTING PLANS FOR NEW CONSTRUCTION
RESIDENTIAL: REQUIREMENTS FOR SUBMITTING PLANS FOR NEW CONSTRUCTION 2 COMPLETE SETS OF PRINTS WITH ENGINEERS STAMP ON FOUNDATION PLAN INCLUDING ELECTRICAL, PLUMBING, ETC. SITE PLAN SHOWING HOUSE LOCATION
More informationOSHA GUIDANCE DOCUMENT FALL PROTECTION IN RESIDENTIAL CONSTRUCTION
OSHA GUIDANCE DOCUMENT FALL PROTECTION IN RESIDENTIAL CONSTRUCTION OSHA GUIDANCE DOCUMENT FALL PROTECTION IN RESIDENTIAL CONSTRUCTION Table of Contents Executive Summary... 1 Introduction... 1 Installing
More informationPackaged Terminal Air Conditioner Wall Sleeve Installation
Installation & Maintenance Data IM 1196 Group: PTAC Part Number: 910141799 Date: October 2013 Packaged Terminal Air Conditioner Installation x 42" PGAN with Top-Mounted Hydronic Heat Note: Installation
More informationThe WANZ Guide to Window Installation
The WANZ Guide to Window Installation as described in E2/AS1 Amendment 5 Ver. 1.1 Page 2 of 74 Contents Overview Page 5 Objective Page 5 Scope Page 5 Opening Preparation Page 7 Step P1 Preliminary Check
More informationGypsum Board Systems Manual
CertainTeed Gypsum Board Systems Manual Fire Resistance and Sound Control Design Manual Division 09 GYPSUM BOARD SYSTEMS MANUAL TABLE OF CONTENTS Introduction General Fire Resistance...1 Sound Control...3
More informationPANEL CONCEPTS LLLP.
The Small Cottage Company DO-IT-YOURSELF CABINS & COTTAGES PANEL CONCEPTS INC. PANEL CONCEPTS LLLP. 2826 Gold 331 Creek N. M-33, Road Mio, Gold Michigan Creek, Montana 4864759733 (989) 826-6511 (406) 288-8585
More informationRepair of Earthquake-Damaged Masonry Fireplace Chimneys SOUTH NAPA EARTHQUAKE RECOVERY ADVISORY
Repair of Earthquake-Damaged Masonry Fireplace Chimneys SOUTH NAPA EARTHQUAKE RECOVERY ADVISORY Purpose and Intended Audience The August 24, 2014 South Napa Earthquake has again served as a reminder that
More informationChapter 36 - STRAW BALE CONSTRUCTION SECTION 3601 - PURPOSE. SECTION 3602 - SCOPE. SECTION 3603 - DEFINITIONS.
Austin City Code - Volume II TITLE 25 LAND DEVELOPMENT\CHAPTER 25-12 TECHNICAL CODES\ARTICLE 1: UNIFORM BUILDING CODE\25-12-3 LOCAL AMENDMENTS TO THE BUILDING CODE Chapter 36 - STRAW BALE CONSTRUCTION
More informationPatio Covers / Carports
Patio Covers / Carports Building Guides for Homeowners Why Do I need a Permit? D I D Y O U K N O W? As owner-builder you are the responsible party of record on such a permit. If your work is being performed
More informationThe University of Birmingham (Live System)
The University of Birmingham (Live System) Behaviour of Structural Insulated Panels (SIPs) under both short-term and long-term loadings Yang, Jian; Rungthonkit, Prathan Document Version Author final version
More informationEggers meticulously-crafted door frames are rivaled only by their beauty, quality and lasting performance. Turning nature s beauty into works of art
D O O R F R A M E S Eggers meticulously-crafted door frames are rivaled only by their beauty, quality and lasting performance. Turning nature s beauty into works of art D O O R F R A M E S Eggers Industries
More informationSTRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM
Chapter 9 STRUCTURAL CONCEPT FOR LIGHT GAUGE STEEL FRAME SYSTEM 9.1 BACKGROUND Steel is widely used in the construction of multi-storey buildings. However, steel construction is seldom used and is traditionally
More informationRESIDENTIAL PLUMBING ALTERATIONS PERMIT REQUIREMENTS
RESIDENTIAL PLUMBING ALTERATIONS PERMIT REQUIREMENTS The following guidelines are intended to assist with the permit acquisition process with regard to Plumbing Alterations. Not all information, or additional
More informationCF-Mesa, CF-Light Mesa, CF-Flute, CF-Metl-Plank, CF-Striated, CF-Santa Fe, CF-Architectural Flat, CF...
Building Insulations - Walls and Ceilings (FM Approval Numbers 4411, 4651, 4880, 4881, 4882) Insulating materials may occur in building construction to reduce heat or sound transmission through a wall,
More informationTriarch Products Over Various Interior Substrates
Triarch products work well over a variety of substrates, both for interior and exterior settings. This document will only discuss interior substrates and is not intended to be a technical discussion of
More informationFIRE LOSS STATISTICAL CONSIDERATIONS IN RELATING FAILURE AND BUILDING DAMAGE TO THE BUILDING CODE OBJECTIVES
FIRE LOSS STATISTICAL CONSIDERATIONS IN RELATING FAILURE AND BUILDING DAMAGE TO THE BUILDING CODE OBJECTIVES P.L. Senez*, K.D. Calder, Hsing H (Isabella) Li Sereca Fire Consulting Ltd., Canada INTRODUCTION
More informationBETONYP building boards. The modern way of living.
BETONYP building boards The modern way of living. Tough for 30 years. Healthy, debarked pine wood and cement: the raw materials used to produce one of our most successful products for more than three decades.
More informationServices Enclosures and Protected Shafts - Maintaining Compartmentation
Introduction When a fire resisting element is used to provide fire compartmentation, every opening that allows services to pass through the element must be adequately protected by sealing, or fire stopping
More informationSAMPLE INSTRUCTIONS. Best Barns USA Assembly Book. the Denver. 12'x 12' or 12'x16' Revised November 29, 2010
Best Barns USA Assembly Book Revised November 29, 2010 SAMPLE INSTRUCTIONS the Denver 12'x 12' or 12'x16' Manufactured by Reynolds Building Systems, Inc. 205 Arlington Drive Greenville, PA 16125 724-646-3775
More informationINSTALLATION INSTRUCTIONS IMPERVIA (Vent and Fixed) AWNING, CASEMENT, and LARGE AWNING WINDOW WITH FINS
2009 Pella Corporation INSTALLATION INSTRUCTIONS IMPERVIA (Vent and Fixed) AWNING, CASEMENT, and LARGE AWNING WINDOW WITH FINS Part Number: 80WH0100 Installation Instructions for Typical Wood Frame Construction.
More informationWhitley Manufacturing Co., Inc. 201 W. First Street S. Whitley, IN 46787 Phone (260) 723-5131 Sales Fax (260) 723-6396 whitley@whitleyman.
Building Type Building Code Whitley Classroom Buildings BOCA, UBC, SBCCI, NEC, ADA Structural Support Outrigger construction standard, Whitley model classrooms. Main support beams to be 12 11.8# per lineal
More information