CONSTRUCTION OF A SEEPAGE CUT-OFF WALL USING DEEP SOIL MIXING AND JET GROUTING

Size: px
Start display at page:

Download "CONSTRUCTION OF A SEEPAGE CUT-OFF WALL USING DEEP SOIL MIXING AND JET GROUTING"

Transcription

1 CONSTRUCTION OF A SEEPAGE CUT-OFF WALL USING DEEP SOIL MIXING AND JET GROUTING Pacific Place Soils Remediation Project Vancouver, B.C. Submitted to Consulting Engineers of British Columbia for 1993 Awards of Engineering Excellence Competition by Golder Associates Ltd., Vancouver, B.C. Sandwell Inc., Vancouver, B.C. Geo-Con Inc., Pittsburgh, PA for B.C. Environment, Lands and Parks FEBRUARY 1993

2 EXECUTIVE SUMMARY As part of the overall environmental controls required for the Pacific Place site (former EXPO 86 site), B.C. Environment Lands and Parks constructed a groundwater control system using deep cut-off walls as part of their commitment to protection of the environment and their contractual responsibility as former owners of the lands. The construction of the groundwater cut-off barrier walls through deep, highly contaminated and heterogeneous fill material in the Pacific Place site was completed using deep soil mixing and jet-grouting construction techniques. The work was completed during the summer of 1992 within the construction window to meet project commitments. The frequent inclusions of large objects and obstructions in the fill materials inhibited construction and were dealt with in a pragmatic and cost effective manner. The highly variable nature of the fill materials and their chemical composition and site constraints imposed significant challenges for the construction of the barrier wall and is believed to be a somewhat unique application in Canada. These environmental control measures have substantially reduced the discharge of dissolved contaminants in groundwater entering False Creek and fulfill the objectives of the approved remedial plan for site.

3 1.0 INTRODUCTION The former Expo 86 property in downtown Vancouver comprises 83 hectares of contagious lots bordering the north shore of False Creek, as illustrated in Figure 1. After Expo 86 this provincially owned property was tendered for sale on the international market and purchased by Concord Pacific Developments Ltd. in May 1988 for development as mixed residential and commercial land uses. The property now referred to as Pacific Place had a long history of industrial activity dating aback to the late 1800 s when Vancouver was first developed. Much of the site is reclaimed land formed by filling into False Creek. The origin and quality of the fill material was highly variable. Former industrial activities on the site included coal gasification plants, hydrocarbon-handling facilities, sawmills and wood preservative operations, and blacksmith shops/ironworks plants. These industrial operations left a variety of chemicals and refuse materials in the ground at locations now being exposed during site development. An area of particular concern, located at the east end of the Pacific Place site, is an area referred to in the development as Parcel 6, 7, 8 and 9, (shown on Figure 1). The area in the southern part of Parcel 9 included a coal gasification plant which produced coal tar and other products from the coal gasification industry. The extensive discharge of coal gasification products to the ground surface ahs resulted in extensive contamination to depths exceeding 10 meters over parts of the Parcel 9 site. It is this eastern portion of the Pacific Place site which is the subject of the remedial actions discussed in this paper. As part of the sale agreement for the property, the province accepted the responsibility to remediate the site to meet the objectives of protecting human health and the environment. Shortly after the property transfer, the British Columbia Ministry of Environment, Lands and Parks adopted standards for the clean-up of contaminated lands which are based on two approaches; a) a numerical criteria approach which sets a concentration limit for a variety of chemicals that are considered to be protective of human health, and b) a risk assessment/risk management (RA/RM) approach which involves the evaluation of the sources of contamination, pathways or the exposure of human and animal receptors and an evaluation of the toxilogical effects of these exposures on health and the environment. An evaluation of remedial alternatives for Parcel 9 led to the conclusion that inplace management of wastes using control measures was the most cost effective and suitable for the project. Thus, the RA/RM approach was applied and a baseline risk assessment was conducted to assess the control measures required. Since groundwater discharging into False Creek was a major pathway of concern, a surface liner was designed to limit infiltration into part of the site and a groundwater collection and groundwater control system using vertical cutoff walls, or barrier walls, was selected to meet the required environmental controls.

4 The results of initial groundwater modeling at the site indicated that over 90% of groundwater discharging to False Creek could be controlled by the construction of low permeability cut-off walls (< 1 x 10 6 cm/s) and with internal groundwater controls. The engineering of the barrier wall, which was completed within the year of 1992, is the subject of this paper. 2.0 SOIL CONDITIONS AND EVALUATION OF BARRIER WALL TYPES 2.1 Soil Conditions Based on subsurface investigations, the general site stratigraphy was found to comprise four layers of soil: upper random fill, marine clayey silt/silty clay, silty sand (beach deposits), and glacial till as show in the schematic cross section given in Figure 2. The glacial till was encountered at relatively shallow depths of about 3 m below the ground surface at the northern part of the site at depths of up to 17 m along the barrier wall alignment. Both the fill and the clayey silt/silty clay layer generally thicken towards the False Creek. The glacial till was found to be generally the least permeable soil layer with hydraulic conductivity ranging from 2 x 10-7 to 2 x 10-6 cm/s. The thin silty sand layer above the till has hydraulic conductivity values ranging from 7 x 10-5 to 3 x 10-4 cm/s. Overlying this layer is the marine clayey silt/silty clay layer covering almost two-thirds of the site and having hydraulic conductivity values between 3 x 10-6 and 4 x 10-5 cm/s. The uppermost fill layer is heterogeneous and its hydraulic conductivity range between 2 x 10-6 and 1 cm/s. the zones of higher hydraulic conductivity reflect fill consisting of predominantly wood waste. The ground surface at the site is generally flat and varies between Geodetic Elevation +3.0 m to +4.0 m. The average pre-development water table contours for the site is presented in Figure 3. Ground water originating form northeast flows towards the southwest through Parcel 7 and then flows directly south through Parcel 6 to False Creek. Over the normal year, the changes in the water table have been found to be small with maximum fluctuations of about 0.5m. 2.2 Evaluation of Alternative Barrier Wall Types The barrier wall design consisted of seven segments in the alignment as shown in Figure 4. Alternative barrier wall types for each segment were evaluated

5 relative to the performance requirements, subsurface conditions, site constraints, and relative cost. The types of barrier wall considered were: sheet pile walls; soil-bentonite, cement-bentonite and plastic concrete walls installed by the slurry trench method; soil-cement-bentonite walls installed by the deep soil mixing method; soil-cement-bentonite walls installed by the jet grouting method; and soil-cement-bentonite and asphaltic barrier walls installed by the vibrated beam technique. The performance requirements were a barrier wall permeability of 1 x 10-6 cm/sec or less and a design life of 50 years. In addition, several site constraints were considered. The barrier wall Segments 1, 3, and 5 were required to accommodate future adjacent excavations. In Segment 1, the adjacent excavations of up to 3m below underlying glacial drift was required. The selection of wall types for Segments 2 and 4 was influenced by the low headroom requirements of Dunsmuir and Georgia traffic viaducts, and BC Transit ALRT guideway. In addition, the required alignments of these segments crossed a significant number of active utilities such as City of Vancouver sewers, BC Hydro high voltage transmission ducts, and BC Tel communication lines. Segments 6 and 7, being parallel and in close proximity to the False Creek shoreline, demanded the installation of the wall while maintaining adequate shoreline slope stability. With the exception of the sheet pile wall, all of the above barrier wall types could be used to meet the permeability requirement. The sheet pile wall could be made to meet the permeability requirement by excavation of the wall and sealing of its joints. Slurry barrier walls, although able to meet the permeability requirement and suitable for installation through the random site fills, have the disadvantage of requiring disposal of large amounts of contaminated soil which would add considerably to use the barrier wall cost. Also along the shoreline slope conventional slurry trenches would have to be installed in short panels and a cement-bentonite or plastic concrete wall material would be required in order to limit lateral thrust due to the slurry and semi-fluid backfill and maintain shore stability. Barrier walls installed by the vibrated beam method were ruled out due to the presence of debris in the site fills which would make formation of the wall by this method difficult and unreliable at best. Deep soil mixing and jet grouting were judged to be practical and would involve less waste soil generation than slurry trench barrier walls. The jet grout barrier wall, although more expensive than the deep soil mixing wall, has the advantage of low headroom requirement for

6 installation and the ability to install barrier walls below shallow services by inclined drilling. The selection of barrier wall types for each of the above segments are given in Table 1. TABLE 1 Segment and 7 Barrier Wall Type And Length Sheet Pile 120m Jet Grouting 100m Deep Soil Mixing with Reinforcement 35m Jet Grouting 35m Deep Soil Mixing with Reinforcement 130m Deep Soil Mixing except jet grouting at west end of Segment 7 400m Reasons Rapid installation to meet tight schedule possible due to local availability of necessary equipment Ability to support adjacent excavation Later excavation would allow sealing Ability to install wall between and beneath buried services Low headroom requirement Low waste soil generation Adequate headroom Low waste soil generation Adjacent future excavation Low cost compared to jet-grouting Low headroom requirement Service crossings Low waste soil generation Adequate headroom Adjacent future excavation Low waste soil generation Low cost compared to jet-grouting Adequate headroom Low cost compared to jet-grouting Low waste soil generation Low impact on shoreline slope stability 3.0 BARRIER WALL SEGMENTS 2, 6, AND 7 The results of groundwater modeling indicated that the target cut-off levels in groundwater discharge to False Creek could be effectively achieved by the installation of barrier wall Segments 1, 2, 6, and 7 combines with a groundwater collection system and a low permeability surface cap over Parcel 9. The installation of the Segment 1 sheet pile barrier wall was completed during the latter part of The work related to the surface cap (HDPE liner) in the northern portion of Parcel 9, which began in 1991, is still ongoing. The construction of barrier wall Segments 2, 6, and 7, which was accomplished during the summer of 1992, involved the use of modern and highly specialized jet grouting and deep soil mixing techniques. The following text focuses on the

7 construction work of the above Segments 2, 6, and 7 of the barrier wall which could be considered as the most challenging construction phases of the Pacific Place soils remediation project during The design and construction inspection of the barrier wall project was carried out by Golder Associates Ltd., Vancouver, B.C. as members of the Soils Remediation Group. Sandwell Inc. of Vancouver, B.C. acted as the Construction Manage for the work and was responsible for the contract management aspects of the project. The prime contract for the construction of wall Segments 2, 6, and 7 was awarded to Geo-Con Inc., Pittsburgh, Pennsylvania, U.S.A., a specialist contractor in jet grouting and deep soil mixing. Wherever possible, work was awarded to local sub-contractors. 3.1 Construction Segment 2 of the barrier wall was completed using jet grout construction techniques; whereas, Segments 6 and 7 were constructed using Deep Soil Mixing (DSM) techniques. In zones where obstructions or services prevented DSM augering, jet grouting was used. The scope of the construction work for Segments 2, 6, and 7 consisted of the following main phases: (a) (b) (c) Grout mix design Installation of a jet grout test wall Installation of deep soil mixing test wall (d) Installation and field and laboratory performance testing of barrier wall Segment 2 (e) Installations and field and laboratory performance testing of barrier wall Segment 6 and 7 The contract specifications required that the grout-soil mix used in the barrier wall construction meet the following criteria: (a) (b) unconfined compressive strength of solidified groutsoil mix >0.35 MPa permeability of solidified grout-soil mix < 1 x 10-6 cm/s

8 (c) bentonite content in grout-soil mix > 2% (d) (e) grout-soil mix to be compatible with ground water and contaminants grout to be workable and placeable Initially, a laboratory test program was carried out on test mixes of in-situ soils and grout compounded in different proportions to determine the most suitable construction grout mix for the Pacific Place site. The test program included the compressive strength, hydraulic conductivity, and immersion testing of solidified soil-grout mix. Based on the results of the test program, a mixture of Portland Cement, fly ash, gypsum, bentonite, in-situ soil, and water, making up 4.6, 1.6, 3.3, 2.0, 72.5, and 16 percent by weight respectively, was selected as the design mix for the construction Methods of Wall Construction Deep soil mixing (DSM) The Deep /soil Mixing (DSM) system of Geo-Con Inc. uses a set of four hydraulically driven augers with mixing paddles on crane supported set of leads. Each auger is 0.91 m in diameter and the augers are spaced horizontally at 0.69 m to provide overlap between adjacent augers. As the augers are advanced through the soil, the grout is pumped through the auger shafts. The augering breaks the soil at the auger shaft locations and lifts it to the mixing paddles which blend the soil with the grout. Each stroke of the DSM equipment produces four overlapping columns of soil-grout mix forming a 2.06 m long panel of the barrier wall between the outer augers. The DSM strokes along the wall alignment are arranged such that one full column overlap is provided between adjacent strokes in order to ensure formation of a continuous soil-grout wall. Jet Grouting Jet grouting on this project was carried out by initially drilling, using a tricone bit and water, to the required wall depth and then introducing the grout mix under high pressure (about 400 bars) at a flow rate of about 500 litres/min. through small orifices near the tip of the jet grout nozzle as the drilling rods are withdrawn. The jet grout nozzle has a total of 14 orifices arranged such that a 0.91 m length of a column is formed when grouting is carried out by rotating the nozzle while holding it at a specific depth. The nozzle was rotated at a speed of about 2 rpm as the grout jets cut and mix the native soil with the grout. In order to install one 0.91 m lift of jet grout column in areas of normal soil conditions at Pacific Place site, jet grouting was carried out over a period of 1 minute at the level of that lift.

9 3.1.2 Segment 2 Initially, a jet grout test wall along the Segment 2 wall alignment was constructed in order to verify the applicability of the jet grouting method to the Pacific Place site. laboratory strength and permeability testing on core samples obtained from the solidified wall, in-situ recovery testing, and finally, visual inspection of the test wall (after exposing by excavation) was carried out as a part of this program. It was found that the jet grout test wall generally met the specified criteria except in heavy debris zones such as tin sheet and brick zones that were encountered in the upper fills of Segment 2. It was decided that in those zones where debris is encountered or inferred by higher resistance to drilling, jet grouting over a double the normal period of time ( double-cutting ) should be carried out. Upon completion of the test wall program, the main construction work of Segment 2 jet grout wall was carried out. During installation of each jet grout columns the drilling process was closely, monitored and possible zones of minor and major zones of obstructions were identified for double-cutting. All underground services crossing the wall alignment were first exposed by careful subexcavation and the construction at these locations was completed by jet grout construction from either side of the services to the required depth. Adjacent Dunsmuir and Georgia viaduct and ALRT foundations, pile caps were periodically surveyed to monitor potential movements during jet grout construction in vicinity. In order to achieve a proper seal and continuity of the seepage cut-off between the Segment 1 sheet pile wall and the Segment 2 jet grout wall, a 1.5 m long jet grout overlap was installed at the junction of these two segment Segments 6 and7 Following a similar approach to that of Segment 2, a test section, rectangular in plan, was first installed using the deep soil mixing (DSM) method. During the initial construction stages of the DSM test wall, a larger number of obstructions than anticipated were encountered. Therefore, the test wall alignment had to be pre-excavated in order to remove potential obstructions. Obstructions including concrete pieces, steel bars, woodpiles, old foundations etc. were removed during this operation. The DSM test installation was then checked by in-situ permeability testing in a test well located within the rectangular area enclosed by the test wall. Test results indicated that the construction of the DSM test wall was not successful where the obstructions prevented the penetration of the augers. These zones were then repaired by drilling through the existing DSM columns and jet grouting the underlying ungrouted zones with a 1m overlap into the DSM columns above. In-situ tests conducted after jet grout repair indicated that test wall construction conformed to the specifications with estimated permeability values less than 1 x 10-6 cm/s. Moreover, this test program also indicated that the repair of an ungrouted zone below DSM construction could be effectively achieved by subsequent jet grouting.

10 Based on the experience during test wall construction, it was evident that there was a potential for encountering more obstructions, which would inhibit construction of a significant portion of the Segment 6 and 7 wall by the DSM method. In such occurrences, the uncompleted areas of the DSM wall in areas where obstructions were too deep for removal by excavation would have to be completed by jet grouting which is both expensive and time consuming. Therefore, it was decided that removal of obstructions prior to deep soil mixing would be desirable. After considering several alternative options, the removal of obstructions was carried out by pretrenching of the wall alignment under a bentonitic slurry using a Caterpillar 245 excavator equipped with a long stick. One of the main concerns that had to be addressed during pretrenching operations was the stability of the adjacent False Creek shoreline. Design calculations indicated that in order to maintain the factor of safety against shoreline failure at an acceptable level, the hydrostatic thrust from the slurry trench on the shoreline had to be kept within certain limiting values. This requirement warranted the careful control of the maximum depth and panel length of slurry trench during construction. In addition, due to the possible presence of highly permeable fill zones and/or unidentified buried services close to the shoreline, there was a potential for an accidental loss of slurry to the False Creek during pretrenching. Therefore, an Environmental Contingency Plan including a monitoring program and a contingency action plan was developed for rapid implementation in the event of such accidents. In most of the zones, pretrenching for obstruction removal was carried out to a depth of at least 1 m into the underlying clayey silt unit which is the design base level of the wall. the trench was then backfilled with screened excavation spoil in preparation for wall construction using deep soil mixing. Upon completion of pretrenching, the installation of barrier wall Segments 6 and 7 mainly was first carried out using the DSM method. In some areas, the wall could not be installed to its full depth by the DSM method due to obstructions and the presence of buried services. The wall within these zones was completed by jet grouting. 3.2 Budget Cost and Schedule The initial engineers budget for Segments 2-6 of the barrier wall was $3,650,000. Tenders for the work wee sought from across North America and three bids were received ranging in value from $3,151,800 to $7,599,100. The reconfiguration of the barrier wall to Segments 2, 2a, 6, 7, and 7a, produced a contract value of $2,244,630. Obstructions in Segment 2, pretrenching for obstruction removal and jet grout repair of DSM wall in Segments 6 and 7 with other extra work resulted in final cost of $2,759,601. Costs for the jet grout wall production were in the range of $400/m 2 and for Deep Soil Mixing $200/m 2. The

11 total cost of the project including design and supervision and related construction activities and their costs resulted in a composite $800/m 2 cost for the wall. The barrier wall construction contract was started on March 09, 1992 and completed on August 26, Concurrent site activities such as the Dragon Boat Festival, the adjacent construction of Carrall Street and Pacific Boulevard South, and the preparation for the Molson Indy Race had to be accommodated during the construction period. 4.0 CLOSURE The construction of a groundwater cut-of f barrier wall through deep heterogeneous fill material in the Pacific Place site using deep soil mixing and jetgrouting construction techniques was completed within the construction schedule to meet project commitments. The frequent inclusions of large objects and obstructions in the fill materials which inhibited construction were dealt with in a pragmatic and cost effective manner. The highly variable nature of the fill materials and their chemical composition and site constraints imposed new challenges for the construction of such a barrier wall and is believed to be unique in application. The completion of the seepage control barrier forms part of the overall environmental controls implemented on the Pacific Place site by B.C. Environment as part of their commitment to protection of the Environment and their contractual responsibility as former owners of the lands. The works have now been completed and the groundwater collection system ahs been installed with treatment of groundwater prior to discharge. A permanent groundwater treatment facility is currently being designed and will be construction during the 1993 fiscal year. These environmental control measures have substantially reduced the discharge of dissolved contaminants in groundwater entering False Creek and fulfill the objectives of the approved remedial plan for site. ACKNOWLEDGEMENTS The authors wish to acknowledge the support of several members of B.C. environment during the planning and implementation phases of this project, including Mr. Barry Olson, Dr. John Weins, Dr. John Ward, Dr. John O Riordon, Mr. Roger Ord and Mr. Bob Ferguson. We would also like to acknowledge Mr. Bill Mottershead, BCE Pacific Place Project Manager, for the opportunity to present this paper.

12

13

TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL

TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL SCOPE This section of the specifications includes requirements for the Slurry Trench Cutoff Wall and related work as indicated on the

More information

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS Vince Luongo Petrifond Foundation Co., Ltd. PROJECT DESCRIPTION The York Durham Sanitary System (YDSS) Interceptor in the Town of Richmond Hill located

More information

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 JRHill@HaywardBaker.com

More information

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL. STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill

More information

BUTE Department of Construction Management and Technology

BUTE Department of Construction Management and Technology BUTE Department of Construction Management and Technology 02.10.2012 Definition 1: Foundation: The structure, that transmits the load of the building to the soil Definition 2: Load bearing soil (strata):

More information

SECTION 02400 - STORM DRAIN SYSTEM

SECTION 02400 - STORM DRAIN SYSTEM SECTION 02400 - STORM DRAIN SYSTEM CONTENTS: Part 1 - General... 1 1.01 Work Included... 1 1.02 Related Requirements... 1 1.03 Reference Standards... 1 1.04 Quality Assurance... 1 1.05 Measurement And

More information

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling

Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation by Tunnelling Engineering and Construction Services Division Standard Specifications for Sewers and Watermains TS 415 April 2013 Amendment to OPSS 415 (Nov 2008) Construction Specification for Pipeline and Utility Installation

More information

CONSTANT HEAD AND FALLING HEAD PERMEABILITY TEST

CONSTANT HEAD AND FALLING HEAD PERMEABILITY TEST CONSTANT HEAD AND FALLING HEAD PERMEABILITY TEST 1 Permeability is a measure of the ease in which water can flow through a soil volume. It is one of the most important geotechnical parameters. However,

More information

California Department of Transportation Doyle Drive Test Program Contract No. 04A3362

California Department of Transportation Doyle Drive Test Program Contract No. 04A3362 California Department of Transportation Doyle Drive Test Program Deep Soil Mixing (DSM) /Cutter Soil Mixing (CSM) Testing Report By Malcolm Drilling Company, Inc. 3524 Breakwater Ave., Suite 108 Hayward,

More information

TBM CROSSING OF STATIONS

TBM CROSSING OF STATIONS TBM CROSSING OF STATIONS Eng. Marco Barbanti Astaldi S.p.A. Eng. Tommaso Grosso Astaldi S.p.A. 18-11-2011 In the presence of groundwater the permeability of the ground is of great interest. It is important

More information

CHAPTER 4 WELL COMPLETION AND MAINTENANCE

CHAPTER 4 WELL COMPLETION AND MAINTENANCE CHAPTER 4 WELL COMPLETION AND MAINTENANCE Section 1: Disinfection. (a) Each person who repairs, modifies, works on, or otherwise affects the physical components of a well shall clean and disinfect the

More information

SECTION 02200 SUPPORT OF EXCAVATION

SECTION 02200 SUPPORT OF EXCAVATION SECTION 02200 PART 1 GENERAL 1.01 DESCRIPTION A. Section including specifications for design and installation of excavation support. B. Section also includes specifications for excavation support systems

More information

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska

How To Prepare A Geotechnical Study For A Trunk Sewer Project In Lincoln, Nebraska APPENDIX B Geotechnical Engineering Report GEOTECHNICAL ENGINEERING REPORT Preliminary Geotechnical Study Upper Southeast Salt Creek Sanitary Trunk Sewer Lincoln Wastewater System Lincoln, Nebraska PREPARED

More information

CIVL451. Soil Exploration and Characterization

CIVL451. Soil Exploration and Characterization CIVL451 Soil Exploration and Characterization 1 Definition The process of determining the layers of natural soil deposits that will underlie a proposed structure and their physical properties is generally

More information

HIGH PERFORMANCE PRE-APPLIED SYSTEM FOR BLIND SIDE & BELOW GRADE WATERPROOFING APPLICATIONS

HIGH PERFORMANCE PRE-APPLIED SYSTEM FOR BLIND SIDE & BELOW GRADE WATERPROOFING APPLICATIONS BSW HIGH PERFORMANCE PRE-APPLIED SYSTEM FOR BLIND SIDE & BELOW GRADE WATERPROOFING APPLICATIONS BSW is a fully reinforced Pre-Applied system membrane designed for horizontal and vertical external blind-side

More information

DIRECTIONAL DRILLING

DIRECTIONAL DRILLING DIRECTIONAL DRILLING 1. General. Installation of pipelines through the levee embankment using directional drilling technology is prohibited. Installation of pipelines through a flood control project foundation

More information

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified. Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

More information

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils Stephen W. Lacz 1, M. ASCE, P.E. and Richard C. Wells 2, F. ASCE, P.E. 1 Senior Professional, Trigon Kleinfelder, Inc., 313 Gallimore

More information

Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair

Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair Eric M. Klein, P. E., Rummel, Klepper & Kahl, LLP, Baltimore, Maryland Kenneth B. Andromalos, P. E., Brayman Environmental,

More information

Pro-Lift Steel Pile Foundation Repair

Pro-Lift Steel Pile Foundation Repair Pro-Lift Steel Pile Foundation Repair Pro-Lift Steel Pile Foundation Repair System Pro-lift steel piles are designed for the stresses of Texas soils. They can have multiple steel walls, depending on the

More information

SECTION 1 GENERAL REQUIREMENTS

SECTION 1 GENERAL REQUIREMENTS Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,

More information

Design and Construction of Auger Cast Piles

Design and Construction of Auger Cast Piles Design and Construction of Auger Cast Piles 101 th Annual Road School 2015 3/11/2015 Malek Smadi, Ph.D., P.E. Principal Engineer - GEOTILL - Fishers, IN msmadi@geotill.com - www.geotill.com CONTENTS 1.

More information

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Nathan A. Ingraffea, P.E., S.E. Associate, KPFF Consulting Engineers, Portland, Oregon, USA Abstract The use of steel sheet

More information

Construction Dewatering and Ground Freezing

Construction Dewatering and Ground Freezing UNIVERSITY OF WASHINGTON DEPARTMENT OF CONSTRUCTION MANAGEMENT CM 420 TEMPORARY STRUCTURES Winter Quarter 2007 Professor Kamran M. Nemati Temporary Structures Construction Dewatering and Ground Freezing

More information

Safe & Sound Bridge Terminology

Safe & Sound Bridge Terminology Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries

More information

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE 6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction

More information

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TN 5.14 February 2010 Introduction It may be at times necessary, in an aging infrastructure, to rehabilitate drainage and sanitary lines

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT

APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT APPLICATION FOR DEMOLITION & RIGHT-OF OF-WAY PERMIT City of Swartz Creek 8083 Civic Drive Swartz Creek, MI 48473 810-635-4464 Fee Received: $ Date: / / Receipt No: Demolition Permit (including Right of

More information

SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS

SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS PART 1: GENERAL 1.01 SECTION INCLUDES A. Abandonment in place, by cutting and capping, of existing sewers, junction structures, manholes, service lines, and

More information

Elevating Your House. Introduction CHAPTER 5

Elevating Your House. Introduction CHAPTER 5 CHAPTER 5 Elevating Your House Introduction One of the most common retrofitting methods is elevating a house to a required or desired Flood Protection Elevation (FPE). When a house is properly elevated,

More information

NRC INSPECTION MANUAL

NRC INSPECTION MANUAL NRC INSPECTION MANUAL INSPECTION PROCEDURE 88001 LLUR ON-SITE CONSTRUCTION PROGRAM APPLICABILITY: 2600, 2801 88001-01 INSPECTION OBJECTIVES 01.01 To determine by direct observation if on-site construction

More information

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS Page 1 of 9 SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS 1. GENERAL REQUIREMENTS 1. Description of Work: This work consists of furnishing all materials, equipment and

More information

ources of Drinking Water

ources of Drinking Water The drop on water Sources of Drinking Water Did you know that 40 per cent of Nova Scotians get their water privately from a drilled well, a dug well, or a surface water source? The other 60 per cent rely

More information

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing

Foundation Experts, LLC Specializes in Foundation Repair and Waterproofing 1 Most basements show some signs of leaking and cracking. Through the years, problems with water, poor soils, grading, drainage and possible settling affect the integrity of a basement. Being able to recognize

More information

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY

BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY MURRAY SHIRE COUNCIL BUILDING OVER OR NEAR WATER & SEWER MAINS POLICY ADOPTED: 1 May 2012 1 BUILDING OVER OR NEAR WATER AND SEWER MAINS POLICY CONTENTS 1. Objective... 2 2. Requirements for Building Near

More information

Federation of Piling Specialists

Federation of Piling Specialists Federation of Piling Specialists COMPANY NAME CONTRACT NAME TENDER REF SCHEDULE OF ATTENDANCES AND FACILITIES TO BE PROVIDED BY THE CLIENT TO A STEEL SHEET PILING SPECIALIST For the purposes of this document

More information

Site Assessment for the Proposed Coke Point Dredged Material Containment Facility at Sparrows Point

Site Assessment for the Proposed Coke Point Dredged Material Containment Facility at Sparrows Point Site Assessment for the Proposed Coke Point Dredged Material Containment Facility at Sparrows Point Prepared for Maryland Port Administration 2310 Broening Highway Baltimore, MD 21224 (410) 631-1022 Maryland

More information

PLANNING CAREFUL NORTH VANCOUVER PIPE BURST REQUIRES

PLANNING CAREFUL NORTH VANCOUVER PIPE BURST REQUIRES WATER & SEWER REHAB TECHNOLOGIES NORTH VANCOUVER PIPE BURST REQUIRES CAREFUL PLANNING Close proximity to storage silos, poor ground conditions and clogged storm sewer pipe puts trenchless contractor to

More information

SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING

SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING SAMPLE FRACTION MITIGATION CONTINGENCY PLAN FOR DIRECTIONAL DRILLING 1 TABLE OF CONTENTS 1.0 Introduction and Purpose 3 2.0 Description of Work 3 3.0 Site Supervisor/Foremen Responsibilities 4 4.0 Equipment

More information

APPENDIX F GEOTECHNICAL REPORT

APPENDIX F GEOTECHNICAL REPORT The City of Winnipeg Bid Opportunity No. 101-2016 Template Version: C420150806 - RW APPENDIX F GEOTECHNICAL REPORT AECOM 99 Commerce Drive 204 477 5381 tel Winnipeg, MB, Canada R3P 0Y7 204 284 2040 fax

More information

DESIGN-BUILD SUPPORT OF EXCAVATION FOR BLOCK 76. Rick Deschamps and Tom Hurley, Nicholson Construction, Pittsburgh, PA USA

DESIGN-BUILD SUPPORT OF EXCAVATION FOR BLOCK 76. Rick Deschamps and Tom Hurley, Nicholson Construction, Pittsburgh, PA USA DESIGN-BUILD SUPPORT OF EXCAVATION FOR BLOCK 76 Rick Deschamps and Tom Hurley, Nicholson Construction, Pittsburgh, PA USA The Block 76 project includes the demolition and redevelopment of an entire city

More information

LS 2540 SEWER LATERALS AND INSPECTION TEES

LS 2540 SEWER LATERALS AND INSPECTION TEES LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal

More information

Tremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete

Tremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete Tremie Concrete Underwater concrete plays an important role in the construction of offshore structures. It may be used to tie together various elements in composite action (i.e., to tie piling to the footing).

More information

A perforated conduit such as pipe, tubing or tile installed beneath the ground to intercept and convey ground water. or structures.

A perforated conduit such as pipe, tubing or tile installed beneath the ground to intercept and convey ground water. or structures. BMP: SUBSURFACE DRAIN Definition A perforated conduit such as pipe, tubing or tile installed beneath the ground to intercept and convey ground water. PurRoses 1. To prevent sloping soils from becoming

More information

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO)

SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) SPECIFICATIONS FOR SEWER PIPE AND LINING INSERTION - TRENCHLESS; GENERAL GUIDELINES (As Provided by NASSCO) 1 Intent: The intent of trenchless sewer pipe Insertion is to rehabilitate the existing sewer

More information

CITY OF ST. CA THARINE S. cn- Olc.4 BY-LAW NO. WHEREAS the Council of the Corporation of the City of St. Catharines, is

CITY OF ST. CA THARINE S. cn- Olc.4 BY-LAW NO. WHEREAS the Council of the Corporation of the City of St. Catharines, is ~: ~,,' " CITY OF ST. CA THARINE S BY-LAW NO. cn- Olc.4 A By-law to regulate sanitary and storm drainage. WHEREAS the Council of the Corporation of the City of St. Catharines, is authorized by the provisions

More information

TYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR

TYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR TYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR If you listen to the hype, it sounds like there must be 20 or 30 different types of piers out there. Company A says they have an

More information

Building over or close to a public sewer

Building over or close to a public sewer Building over or close to a public sewer thameswater.co.uk/developerservices thameswater.co.uk/developerservices 1 Questions and answers Did you know Thames Water is legally responsible for more than 100,000

More information

TECHNICAL REVIEW OF SECONDARY CONTAINMENT SYSTEM TECHNOLOGY FOR ALASKA

TECHNICAL REVIEW OF SECONDARY CONTAINMENT SYSTEM TECHNOLOGY FOR ALASKA Final Report to STATE OF ALASKA DEPARTMENT OF ENVIRONMENTAL CONSERVATION DIVISION OF SPILL PREVENTION AND RESPONSE TECHNICAL REVIEW OF SECONDARY CONTAINMENT SYSTEM TECHNOLOGY FOR ALASKA May 1, 1998 Steven

More information

PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE

PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE FORM A PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE The following suggested specifications are written as a guide to assist the specifier in writing his own specifications. Specific circumstances

More information

The Challenge of Sustainability in the Geo-Environment Proceedings of the Geo-Congress 2008 ASCE New Orleans LA

The Challenge of Sustainability in the Geo-Environment Proceedings of the Geo-Congress 2008 ASCE New Orleans LA The Challenge of Sustainability in the Geo-Environment Proceedings of the Geo-Congress 2008 ASCE New Orleans LA Strength and Permeability of a Deep Soil Bentonite Slurry Wall Christopher R. Ryan P.E. M

More information

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS

Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS Electric Engineering Division FIBER CONDUIT RULES AND REGULATIONS TABLE OF CONTENTS I. RULES AND REGULATIONS A. TABLE OF CONTENTS... 2 B. TERMS AND DEFINITIONS... 3 C. DEVELOPER S/CONTRACTOR S RESPONSIBILITIES...

More information

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge. TM TM Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. SM The Leading Edge. 10 One Major Causes of foundation settlement or more conditions may

More information

FINAL PLAN OF REMEDIAL ACTION

FINAL PLAN OF REMEDIAL ACTION FINAL PLAN OF REMEDIAL ACTION 1000 FRENCH STREET SITE Wilmington, Delaware DE 1115 June 1999 Department of Natural Resources and Environmental Control Division of Air and Waste Management Site Investigation

More information

Moving Small Mountains Vesuvius Dam Rehab

Moving Small Mountains Vesuvius Dam Rehab Moving Small Mountains Vesuvius Dam Rehab Susan L. Peterson, P.E., regional dams engineer, Eastern Region, Bedford, IN Note: The following article, Moving Small Mountains Vesuvius Dam Rehab, by Sue Peterson,

More information

Comparison of Seismic Retrofitting Methods for Existing Foundations in Seismological Active Regions

Comparison of Seismic Retrofitting Methods for Existing Foundations in Seismological Active Regions Comparison of Seismic Retrofitting Methods for Existing Foundations in Seismological Active Regions Peyman Amini Motlagh, Ali Pak Abstract Seismic retrofitting of important structures is essential in seismological

More information

Cavity Drain R20 is manufactured from1.0mm thick black high density polyethylene with studs approximately 20mm high.

Cavity Drain R20 is manufactured from1.0mm thick black high density polyethylene with studs approximately 20mm high. CI/SfB Tn6 L6813 September 2013 RIW CAVITY DRAIN R20 R20 is manufactured from1.0mm thick black high density polyethylene with studs approximately 20mm high. Other systems are available for specific uses,

More information

Introduction. The following is an outline of the contents of this paper: Definition of Artificial Lift Page 2. How an Oil Well is Produced Page 2

Introduction. The following is an outline of the contents of this paper: Definition of Artificial Lift Page 2. How an Oil Well is Produced Page 2 Introduction Canadian Oilwell Systems Company and it s subsidiaries are suppliers of oil well Electric Submersible Pumping systems (ESPs). Such pumps are used to lift oil from oil wells so that the oil

More information

Guidelines For Sealing Groundwater Wells

Guidelines For Sealing Groundwater Wells Guidelines For Sealing Groundwater Wells Government of Newfoundland and Labrador Department of Environment and Conservation Water Resources Management Division Government of Newfoundland and Labrador Department

More information

SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE

SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel

More information

Severn Trent Water Ltd has undergone a massive investment programme in the River Tame catchment over the

Severn Trent Water Ltd has undergone a massive investment programme in the River Tame catchment over the Tame Urban Pollution Management Foxton Road & Sir Johns Road CSOs - collaborative working to deliver innovative solutions Severn Trent Water Ltd has undergone a massive investment programme in the River

More information

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily

More information

Emergency repair of Bridge B421

Emergency repair of Bridge B421 Emergency repair of Bridge B421 over the Olifants River after fl ood damage INTRODUCTION AND BACKGROUND Bridge B421 is located on the R555 at km 5.03 on Section 01E between Witbank (now known as emalahleni)

More information

Milan M5 metro extension the construction of Lotto station

Milan M5 metro extension the construction of Lotto station Milan M5 metro extension the construction of Lotto station Giuseppe LUNARDI, Rocksoil S.p.A., Italy giuseppe.lunardi@rocksoil.com Luca MANCINELLI, Rocksoil S.p.A., Italy, luca.mancinelli@rocksoil.com Massimiliano

More information

Chapter 9 Remedial Measures

Chapter 9 Remedial Measures [This is an annotated version of a chapter from the US Army Corps of Engineers book, Foundations in Expansive Soils. This book is in the public domain. This document is consists of an abbreviated and annotated

More information

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary

More information

C. Section 014510 TESTING LABORATORY SERVICE.

C. Section 014510 TESTING LABORATORY SERVICE. SECTION 014500 QUALITY CONTROL PART 1 GENERAL 1.01 RELATED REQUIREMENTS A. Drawings and General Provisions of Contract, including General and Special Conditions and other Division 1 Specification Sections,

More information

Work Type Definition and Submittal Requirements

Work Type Definition and Submittal Requirements Work Type: Highway Materials Testing Geotechnical Laboratory Testing, Geotechnical Laboratory Testing, Standard Penetration (SPT) & Rock Coring, Cone Penetration Test, Solid Stem Auger Drilling, and Materials

More information

High Strain Dynamic Load Testing of Drilled Shafts

High Strain Dynamic Load Testing of Drilled Shafts Supplemental Technical Specification for High Strain Dynamic Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 3, 2015 1.0 GENERAL This work shall consist of performing high-strain

More information

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional

More information

GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES. Materials Engineering Report No. 2009-8M (Supersedes Report No.

GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES. Materials Engineering Report No. 2009-8M (Supersedes Report No. GUIDELINES FOR GEOTECHNICAL INVESTIGATION OF BRIDGE STRUCTURES Materials Engineering Report No. 2009-8M (Supersedes Report No. 21) F CHOWDHURY GEOMECHANICS AND STRUCTURAL MATERIALS ENGINEER S REHMAN GEOTECHNICAL

More information

STATE OF THE ART IN BIO-POLYMER DRAIN CONSTRUCTION

STATE OF THE ART IN BIO-POLYMER DRAIN CONSTRUCTION STATE OF THE ART IN BIO-POLYMER DRAIN CONSTRUCTION Steven R. Day 1 and Christopher R. Ryan 1 REFERENCE: Day, S. R. and Ryan, C. R., State of the Art in Bio-Polymer Drain Construction, Slurry Walls: Design,

More information

Specifications for Residential Property Owners Connection to New Public Sewer

Specifications for Residential Property Owners Connection to New Public Sewer Specifications for Residential Property Owners Connection to New Public Sewer Spalding Tract property owners are required to connect to the community sewer system when construction is complete and the

More information

ICRC WORK SPECIFICATIONS IRAQ WATER AND HABITAT

ICRC WORK SPECIFICATIONS IRAQ WATER AND HABITAT ICRC WORK SPECIFICATIONS IRAQ WATER AND HABITAT GOVERNORATE : DISTRICT : LOCATION : DOHUK SUMEL SUMEL GO code : IRAK GEN ASSENG0 TITLE : Sharia / PHCC / Rehabilitation SO n : SO 03 WPA n : KIR16 0015 Job

More information

COST AND PERFORMANCE REPORT

COST AND PERFORMANCE REPORT COST AND PERFORMANCE REPORT Pump and Treat of Contaminated Groundwater at the United Chrome Superfund Site Corvallis, Oregon September 1998 Prepared by: SITE INFORMATION Identifying Information: United

More information

SECTION 02221 SELECTIVE DEMOLITION

SECTION 02221 SELECTIVE DEMOLITION SECTION 02221 PART 1 -GENERAL 1.01 DESCRIPTION This section includes all material, labor, machinery and supervision required to demolish and remove the following items where applicable and as noted on

More information

Evaluating the Condition of Seawalls/Bulkheads

Evaluating the Condition of Seawalls/Bulkheads Volume 2 Evaluating the Condition of Seawalls/Bulkheads By: Coastal Systems International, Inc. Typical bulkhead under construction Seawalls and bulkheads (walls) provide shoreline stabilization for many

More information

Sanitary Sewer Design, Installation and Inspection in Small Rural Community

Sanitary Sewer Design, Installation and Inspection in Small Rural Community Sanitary Sewer Design, Installation and Inspection in Small Rural Community Submitted by: First name, Last name OACETT Membership #: 000000 Submitted to: OACETT 10 Four Seasons Place, Suite 404 Toronto,

More information

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION 1. SCOPE Pipe subsoil drains shall be constructed in accordance with this specification and in conformity with the lines, grades and cross-sections shown

More information

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe TN 5.18 October 2015 In sanitary sewer, it is often necessary to use trenchless technology methods to install a casing pipe under high volume roads,

More information

Storm Sewer Trenchless Upgrade Alternatives and Recommendations

Storm Sewer Trenchless Upgrade Alternatives and Recommendations Storm Sewer Trenchless Upgrade Alternatives and Recommendations Background Approximately 1,930 feet of the 40-inch and 42-inch CMP storm sewer pipe from manhole M22 to manhole M12 will be evaluated for

More information

90 Brighton Road, Surbiton, Surrey

90 Brighton Road, Surbiton, Surrey 90 Brighton Road, Surbiton, Surrey Civil and Structural Engineering Basement Feasibility Report Mixed Use Scheme 108802-REP-002 March 2015 Contents 1. Executive Summary... 3 2. Site Description and Constraints...

More information

ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS

ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS ENVIRONMENTAL CODE OF PRACTICE FOR CONCRETE BATCH PLANT & ROCK WASHING OPERATIONS PREPARED BY: DEPARTMENT OF ENVIRONMENT AND LANDS INDUSTRIAL ENVIRONMENTAL ENGINEERING DIVISION APRIL 16, 1992 - TABLE OF

More information

GLOSSARY OF TERMINOLOGY

GLOSSARY OF TERMINOLOGY GLOSSARY OF TERMINOLOGY AUTHORIZED PILE LENGTHS - (a.k.a. Authorized Pile Lengths letter) Official letter stating Engineer's recommended length of concrete piles to be cast for construction of foundation.

More information

UltraTech International, Inc. Canadian Secondary Containment Requirements

UltraTech International, Inc. Canadian Secondary Containment Requirements UltraTech International, Inc. 11542 Davis Creek Court Jacksonville, Florida 32256 Canadian Secondary Containment Requirements The Canadian Council of Ministers of the Environment (CCME) is the major intergovernmental

More information

Designed and Engineered to Perform

Designed and Engineered to Perform History EARTH CONTACT PRODUCTS, L.L.C., is a family owned company, based in Olathe, Kansas. This company was built upon Don May s U.S. Patented fourth-generation Steel Piering System that has led to the

More information

GOWANUS EXPRESSWAY TUNNEL PRIMER

GOWANUS EXPRESSWAY TUNNEL PRIMER GOWANUS EXPRESSWAY TUNNEL PRIMER T he New York State Department of Transportation is currently studying the replacement of the Gowanus Expressway with a tunnel. This investigation involves looking at a

More information

LOWER NORTH OUTFALL SEWER AND NORTH OUTFALL SEWER REHABILITATION USING AMERON S T HAB METHOD

LOWER NORTH OUTFALL SEWER AND NORTH OUTFALL SEWER REHABILITATION USING AMERON S T HAB METHOD www.norcalpug.com LOWER NORTH OUTFALL SEWER AND NORTH OUTFALL SEWER REHABILITATION USING AMERON S T HAB METHOD Bob Fisher and Lance Stracner Ameron Protective Lining J.R. Pipeline Co Inc. Abstract: The

More information

A Guide to Structural Waterproofing

A Guide to Structural Waterproofing A Guide to Structural Waterproofing Part One Waterproofing Protection For Below Ground Structures 1 2012 W. R. Grace & Co Benjamin J. Brooks Table of Contents Grace Around The World Reference Material

More information

BOREHOLE SEALING IN A COAXIAL HEAT EXCHANGER BY BENTONITE TREATMENT

BOREHOLE SEALING IN A COAXIAL HEAT EXCHANGER BY BENTONITE TREATMENT BOREHOLE SEALING IN A COAXIAL HEAT EXCHANGER BY BENTONITE TREATMENT Frank.B.Cruickshanks, Olof Andersson, James Bardsley Climate Change Division, Meteorological Service of Canada, 45 Alderney Drive, Dartmouth,

More information

Section 02415. Installation of pipe and casing for sanitary sewer by methods of augering.

Section 02415. Installation of pipe and casing for sanitary sewer by methods of augering. ITY OF PRLN UGRING PIP OR SING FOR SWRS Section 02415 UGRING PIP OR SING FOR SWRS 1.0 G N R L 1.01 STION INLUS Installation of pipe and casing for sanitary sewer by methods of augering. References to Technical

More information

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS

San Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located

More information

EARTHWORKS COMPLETION REPORT ELLEN STIRLING PARADE, ELLENBROOK. Ellenbrook, W.A. Georgiou Group Pty Ltd

EARTHWORKS COMPLETION REPORT ELLEN STIRLING PARADE, ELLENBROOK. Ellenbrook, W.A. Georgiou Group Pty Ltd EARTHWORKS COMPLETION REPORT ELLEN STIRLING PARADE, ELLENBROOK Ellenbrook, W.A. Georgiou Group Pty Ltd GEOTPERT08050AZ-AH 27 March 2013 EARTHWORKS COMPLETION REPORT ELLEN STIRLING PARADE, ELLENBROOK Ellenbrook,

More information

Soils, Foundations & Moisture Control

Soils, Foundations & Moisture Control Soils, Foundations & Moisture Control Soil The top loose layer mineral and/or organic material on the surface of the Earth that serves as a natural medium for the growth of plants and support for the foundations

More information

SECTION 02401 SHEETING, SHORING AND BRACING

SECTION 02401 SHEETING, SHORING AND BRACING SECTION 02401 SHEETING, SHORING AND BRACING This section should be edited to reflect soil conditions specific to the project site and the recommendations of a Geotechnical Engineer licensed in the State

More information

RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000

RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000 RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000 SECTION R905 REQUIREMENTS FOR ROOF COVERINGS R905.1 Roof covering application. Roof coverings

More information

FOUNDATION TECHNICAL CATEGORY 3 (TC3) AUGUST 2012

FOUNDATION TECHNICAL CATEGORY 3 (TC3) AUGUST 2012 FOUNDATION TECHNICAL CATEGORY 3 (TC3) AUGUST 2012 Building and Housing has published technical guidance for foundation repairs and reconstruction for residential properties in green zone Foundation Technical

More information

Well Records and Maintenance Guidelines

Well Records and Maintenance Guidelines 1 Well Records and Maintenance Guidelines If you have a home well, you alone are responsible for maintaining the safety of our drinking water supply. When your well system is suitably located, correctly

More information

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition.

Civil. 2. City of Seattle Supplement to the Specification for Road, Bridge and Municipal Construction, most current addition. Design Guide Basis of Design This section applies to the design and installation of earthwork and backfill. Design Criteria No stockpiling of excavation materials is allowed unless the Geotechnical Engineer

More information