OPEN PIT MINING PROCESS
|
|
- Emil Davis
- 7 years ago
- Views:
Transcription
1 OPEN PIT MINING PROCESS 1. Basic Open Pit Terminology 2. Pickstone Peerless Open Pit Optimisation Input Parameters 3. Pickstone Peerless Open Pit Optimisation Targets & Constraints 4. Pickstone Peerless Open Pit Optimisation Results 5. Pickstone Peerless Oxide Production Plan Summary 6. The Open Pit Optimisation Process (Net Present Value ( NPV ) Optimisation) 1. Define an Economic Model 2. Ultimate (Optimal) Pit Shell Creation 3. Practical Mining Sequence 7. Glossary of Terms 1
2 BASIC OPEN PIT TERMS The various Pit Parameters have defined through independent studies undertaken primarily by Open House Management Solutions ( OHMS ) and Minxcon Consulting. OHMS is a geotechnical group and have defined the parameters for; Overall Wall Slope Angle (Oxide) Berm Width (Oxide) Face (Batter) Angle (Oxide) Analysed Potential Slope Failure and Rock falls Potential Rock Fall Movement Minxcon are mining consultants and have defined the following design parameters; Road Width Dilution and Recovery Parameters 2
3 INPUT OPTIMISATION PARAMETERS The following input parameters were utilised for the optimisation process; Gold Price - $1,300 per ounce / $ per gram Mining Cost (Ore) - $2.50 per tonne Mining Cost (Waste)- $2.40 per tonne Mining Cut-Off Grade (g/t) : 1 12 month period : 1.25 gram per ton Mining Cut-Off Grade (g/t) : 13 end period : 1.00 gram per ton Oxide Overall Slope Angle : 35 degrees Sulphide Overall Slope Angle : 40 degrees Bench Height : 5.0 metres Batter (Face) Angle (Oxide) : 70 degrees Batter (Face) Angle (Sulphide) : 80 degrees Berm Width (Oxide) : 4.0 metres Berm Width (Sulphide) : 3.0 metres Road (Ramp) Width (Single Lane Traffic) : 8.0 metres Road (Ramp) Width (Dual Lane Traffic) : 13.0 metres Plant Operating Cost : $26.50 per ton milled Processing Recovery : 88% on Oxide ore only Note: Sulphide ore material is treated as ore in the mining cost segment and assigned a processing recovery percentage of 0%. This results in an accurate pit design and costs the drill & blast pattern correctly. Minimal sulphide is mined in the oxide mining phase. 3
4 MINING STRATEGY INITIAL 12 MONTH PERIOD A mining cut off grade of 1.25 grams per ton will be applied to the mining activities The oxide portion of the orebody will be extracted initially down to a maximum depth from surface of approximately 20 metres in the first 12 months. All oxide ore material and any incidental sulphide ore material between the grade range of 0.50 grams per ton and 1.25 grams per ton will be placed on a Low Grade Stockpile adjacent to the plant All the benches mined in the initial 12 month period will be grade control drilled before mining commences POST INITIAL 12 MONTH PERIOD UNTIL DEPLETION OF OXIDE RESOURCE A mining cut off grade of 1.00 grams per ton will be applied to the mining activities The oxide portion of the orebody will be extracted initially down to a maximum depth from surface of approximately 60 metres by the end of oxide related mining activities. All oxide ore material and any incidental sulphide ore material between the grade range of 0.50 grams per ton and 1.00 grams per ton will be placed on a Low Grade Stockpile adjacent to the plant Benches will be grade control drilled timeously to allow for planning and scheduling Test work on sulphide ore material will be ongoing in order to refine geotechnical pit design parameters 4
5 OPTIMISATION TARGETS AND CONSTRAINTS TARGETS The processing facility is capable of 10,000 tonnes per month of Oxide ore in the first 12 months of operation and thereafter will increase to 20,000 tonnes per month until oxide depletion. The Payback period for Capital Expenditure should be less than 12 months. All ore material between the grade range of 0.5 g/t 1.25 g/t will be stockpiled on a Low Grade stockpile for processing in the future. CONSTRAINTS The Burnett Shaft must stay protected to; Provide process water for the plant; Allow possible underground access in the future (can be used as a ventilation shaft). Open Pit mining cannot encroach to within 20 metres of the Mombe River in the first 12 month period to allow for a river canal diversion to be put in place; Open Pit mining cannot progress past the public road between the Mombe River and the Mining Office as the canal diversion must stay in place until oxides depleted. Once Sulphides are exploited, a pumped type river diversion will be required. A road diversion of the public road between Chegutu and Ngezi is required to; Avoid mine traffic and public traffic mingling. A bridge needs to be constructed for the new road diversion crossing the Mombe River. The area to the East of the Mombe River is predominantly Inferred Resources (drill hole line spacing s of 60m 80m) and has been excluded from optimisation. Areas under current tailings dumps have been excluded from optimisation 5
6 OPTIMISATION TARGETS AND CONSTRAINTS BURNETT SHAFT Burnett Shaft (Process Water Source) LOM Oxide Pit Limit Southwell Shaft (Impacted by Mining) Processing Plant 6
7 OPTIMISATION TARGETS AND CONSTRAINTS RIVER DIVERSION Mombe River Planned River Diversion Canal Burnett Shaft (Process Water Source) Impacted by mining without exclusion zone applied Current LOM Pit Shell Initial Pit Shell without Limitations The diversion canal was initially planned to run between the 2 pits. Investigations on the ground reveal that the road and pit would not fit and would require a complete rework of the road network in order to get ore to the plant. By placing an exclusion zone around Burnett Shaft, the area available to be mined in the eastern most pit would be minimal. 7
8 OPTIMISATION TARGETS AND CONSTRAINTS EXCLUSION ZONES Initial Pits excluded Drill hole 80 metres apart Exclusion Zone 8
9 AVAILABLE OXIDE MINERAL RESOURCES AFTER EXCLUSION ZONES APPLIED Total available oxide ounces after Exclusion = a 1.00 g/t mining cut-off grade. LOM plan currently in place extracts 111Koz at an average mined grade of 2.72 g/t The area to the east of the Mombe River which has been excluded due to predominantly Inferred Mineral Resource Status, may potentially be scheduled for extraction once the Mineral Resource Classification is improved. This would entail additional exploration drilling on line spacing's of 40 metres or less. 1.87Mt 2.43g/t 9
10 SUMMARY OF PRODUCTION PLAN Low Grade Stockpile tonnes comprises ore material (oxide only) of between g/t in the initial 12 month period and between g/t for the remainder of the period. Factors included in the Basic Mining Equation ( BME ) are as follows; Geological Losses 2% Ore Losses 3% Ore Dilution 7% (derived from waste tons) Waste Dilution 2% Mine Call Factor 100% Processing Recovery 88% 10
11 SITE PLAN OVERVIEW OF 12 MONTH MINING PLAN Processing Plant Mine Roads (New & Existing) Pickstone Pit No.3 ROM Ore Pad Water Source (Burnett Shaft) LOM Low Grade S/pile (0.7Mt) Existing public roads not used by mine traffic Peerless Pit No. 3 Pickstone Pit No.3 Pickstone Pit No. 2 River Diversion Canal Public Road Diversion 11
12 SITE PLAN OVERVIEW OF LIFE OF MINE (OXIDE ONLY) MINING PLAN WITH 12 MONTH PIT SHELLS Peerless Pit No.1 (Life of Mine) Peerless Pit No. 3 (Life of Mine) Initial 12 month pit shell outlines River Diversion Required in Month 27 Peerless Pit No. 2 (Life of Mine) Pickstone Pit No. 1 (Life of Mine) Pickstone Pits No.2 & No.3 Combine into one pit. (Life of Mine) 12
13 THE OPEN PIT OPTIMISATION PROCESS Encodes a resource model with a value representing the cost of extraction, cost of processing and expected revenue derived from a block of ground Generates a initial pit shells for the given set of economic parameters. Does not take into account the practicality of mining non contiguous blocks. Follows the first rule of NPV Optimisation, Mine the highest value blocks first Create Mining Pushbacks in order to alter the initial mining sequence to obtain a practical and logical extraction sequence in line with any prescribed targets 13
14 DEFINE AN ECONOMIC BLOCK MODEL An Economic Model is, effectively, a geological block model containing additional supporting information relating to the 'value' of a particular block of ore. The Economic Model is defined by setting cost and price parameters for the life of the mine and then calculating an intrinsic value per processing method of each block in a geological block model as a function of its geo-metallurgical attributes. The value is usually calculated by NPV Scheduler as part of the definition of the economic model. Example of a Value Model The parameters used to calculate the block values are; the selling price of the commodity or commodities recovered from processing a unit cost of mining (ore and waste) and a unit cost of processing (ore) and any adjustment factors which apply dilution and recovery factors for the ore an additional cost for processing each unit of a commodity if required 14
15 ULTIMATE PIT DETERMINATION A series of nested pits which mines the highest value ore first Determines an Ultimate Pit shape for the given set of commodity prices, mining cost and the basic engineering constraints applied As the input economic and geotechnical parameters are varied, the Ultimate Pit shape can vary, sometimes dramatically, as various thresholds are reached and the number of economic blocks increase or decrease. In the diagram to the right, the blue area (the smallest pit), is the one that represents the best value that is possible in the early stages of mining as it is the pit that would still be valuable even under the worst economic conditions (that is, a low commodity price). The green (largest) pit represents the pit with the longest life under the best economic conditions. The difference between each pit shell and the next is considered to be a phase. Considering that realizing the best value first is a basic principle of maximizing NPV, the order of the phases represents the first high level categorization of the value and is the first stage in determining an optimal and practical Mining Schedule. 15
16 DEFINING A PRACTICAL MINING SEQUENCE WITH BEST VALUE A Pushback represents an area that can be mined in a single continuous operation as defined within the Ultimate Pit. The basic objective is to create a pushback shape which attempts to meet defined primary targets, such as ore tonnage, stripping ratios or mined grade. Multiple pushbacks can be generated, thereby catering for highly selective mining in terms of set targets. It further represents a practical mining shape as opposed to a value derived shape from the Lerch Grossman Optimal Pits Phases Eliminates or reduces the frequency of inter pit moves when compared to the Ultimate Pit mining sequence The Scheduler finds a practical schedule for mining the pushbacks. For the highest NPV it would theoretically be best to mine the pushbacks in sequence, one at a time. Unfortunately, this strategy is rarely practical because it does not satisfy targets such as ensuring a steady output of ore at manageable strip ratios, nor does it satisfy other possible requirements like ore blending or contamination control. The scheduler can be set to target mining rates, truck hours, mill throughput, stripping ratios, mining grade etc. The result is a long term mine schedule which is strategic with respect to NPV, practical with respect to mining shape and pit slope requirements and achievable with respect to the mining equipment fleet and the ore processing capability in short an optimal combination of maximum NPV within a practical, workable schedule. 16
17 GLOSSARY OF TERMS Mining Cost The unit cost in USD for the Drill and Blast based on a specified blast hole pattern and the Load, Haul and Dump of material at the plant (ore) and Waste Rock Dump (waste) Mining Cut-Off Grade (g/t) The grade of the ore in the open pit at which point the decision is made to haul the material to the processing plant, low grade stockpile or the waste rock dump Bench Elevation defining the working level of the open pit. In this case the bench elevations are in 5 metre increments Batter (Face) Angle The angle defining the maximum allowable slope between two bench elevations Berm A minimum horizontal allowable distance between the beginning and the end of two distinct benches Road (Ramp) A road defined at a specified gradient and width allowing vehicle access into the open pit Resource Model A block model representing the expected grade value, rock type, oxidation state and various other derived properties from the exploration stage NPV Net Present Value, the difference between the present value of cash inflows and the present value of cash outflows. NPV is used in capital budgeting to analyze the profitability of an investment or project. Pushback The planned progression of mining a series of nested pits. Nested Pit A pit shell defining an accumulation of ore blocks to be mined in a contiguous manner Ultimate Pit - The final pit limits define what is economically mineable from a given deposit It identifies which blocks should be mined and which ones should be left in the ground Lerch Grossman Optimal Pits An algorithm developed to design the contour of a pit so as to maximise the difference between total mine value of the ore extracted and the total extraction cost of ore and waste. Stripping Ratio - The ratio of the volume of overburden (or waste material) required to be handled in order to extract some volume of ore. Oxide Ore Ore minerals comprised of oxide compounds typically resulting in simplistic ore processing methods Sulphide Ore Ore minerals comprised predominantly of sulphidic compounds typically resulting in more complex ore processing methods when compared to oxide ores Geological Losses Ore lost due to variable geological features such as unknown faulting Ore Losses Losses of ore due to spillage, cross tramming of ore as waste and grade control Ore Dilution Dilution from waste material introduced to ore trucked to plant. Typically from poor mining practice, poor grade control procedures and cross tramming of waste to plant as ore Waste Dilution Unplanned for diluting material typically sourced from over break of pit outline, falls of ground and cross tramming Mine Call Factor The ratio between the ore contents accounted for from the grade control accounting model versus the final gold accounting from the plant Processing Recovery The ratio of the ore contents fed into the plant versus the final contents produced 17
Savannah North Scoping Study Looking into the future 3 February 2016
Savannah North Scoping Study Looking into the future 3 February 2016 ASX: PAN Disclaimer Cautionary Statements This presentation includes information extracted from Panoramic Resources Limited ASX announcement
More informationContinental Gold Announces a Positive Preliminary Economic Assessment for the Buriticá Project
Continental Gold Announces a Positive Preliminary Economic Assessment for the Buriticá Project Toronto, Ontario, November 17, 2014 - Continental Gold Limited (TSX:CNL; OTCQX:CGOOF) ("Continental" or the
More information3D Modelling & Mine Planning Software. Comprehensive tools provide a competitive advantage from exploration to rehabilitation.
3D Modelling & Mine Planning Software Comprehensive tools provide a competitive advantage from exploration to rehabilitation. Maptek Vulcan, the world s premier 3D mining software solution, allows users
More informationAFRICAN GOLD GROUP, INC. DEFINITIVE FEASIBILITY STUDY FOR KOBADA GOLD PROJECT GENERATES ROBUST ECONOMIC OUTCOME
African Gold Group, Inc. TSX-V: AGG Yonge & Richmond Centre 151 Yonge Street, 11th Floor. Toronto Canada M5C 2W7 Tel: +1 647 775 8538 website : www.africangoldgroup.com AFRICAN GOLD GROUP, INC. DEFINITIVE
More informationTURKEY CREEK PIT OPTIMISATION STUDY ADDS 2 YEARS MINE LIFE TO THE LITTLE EVA PROJECT AT CLONCURRY
10 August 2015 ASX: AOH, FSE: A2O TURKEY CREEK PIT OPTIMISATION STUDY ADDS 2 YEARS MINE LIFE TO THE LITTLE EVA PROJECT AT CLONCURRY Estimated oxide and sulphide resources within the optimum pit is 17.3
More informationEconomic Highlights (In US$ unless otherwise indicated)
TSX.V TSX Venture Exchange Symbol: AME Suite 615-800 West Pender Street Vancouver, B.C. V6C 2V6 Canada Tel: 604.682.0301 Fax: 604.682.0307 email: info@amemining.com website: www.amemining.com Abacus announces
More informationMako Project, Eastern Senegal Completion of Scoping Study
Toro Gold Ltd Trafalgar Court Admiral Park, Guernsey. GY1 3EL. News Release: 18 th April 2013, Guernsey Mako Project, Eastern Senegal Completion of Scoping Study Toro Gold Ltd ( Toro Gold or the Company
More informationArmadale Capital Plc Armadale or the Company Robust Project Demonstrated by Mpokoto Feasibility Study HIGHLIGHTS
Armadale Capital Plc / Index: AIM / Epic: ACP / Sector: Investment Company 8 February 2016 Armadale Capital Plc ( Armadale or the Company ) Robust Project Demonstrated by Mpokoto Feasibility Study Armadale,
More informationCandelaria and Ojos del Salado Chile
TSX : LUN OMX : LUMI 2016 Candelaria Key Facts Open Pit and Underground Mine Copper, gold, and silver 2016 estimate 124,000-128,000 tonnes copper Cash costs of $1.45 per lb copper after by-product credits
More informationEndeavour Management Presentation
Endeavour Management Presentation June 2014 GOLD PRODUCER WEST AFRICA CASH FLOW Disclaimer & Forward Looking Statements This presentation contains forward-looking statements including but not limited to,
More informationDAMANG MINE: SWINGING BACK TO PROFITABILITY ALFRED BAKU EVP & Head of West Africa NG Mining Summit, Cape Town, June 2015
DAMANG MINE: SWINGING BACK TO PROFITABILITY ALFRED BAKU EVP & Head of West Africa NG Mining Summit, Cape Town, June 2015 CONTENT GLOBAL OPERATIONS WHERE WE VE COME FROM REVERSING THE TREND TRANSFORMATION
More informationALCYONE REPORTS JORC SILVER RESOURCES
ASX ANNOUNCEMENT & MEDIA RELEASE 29 March 2010 ALCYONE REPORTS JORC SILVER RESOURCES +15Moz RESOURCE INVENTORY UNDERPINS PROGRAM TARGETING RESUMPTION OF SILVER PRODUCTION AT TEXAS PROJECT LATER THIS YEAR
More informationDetour Gold Provides New Life of Mine Plan for Detour Lake
January 25, 2016 NEWS RELEASE Detour Gold Provides New Life of Mine Plan for Detour Lake Detour Gold Corporation (TSX: DGC) ( Detour Gold or the Company ) is pleased to announce a new life of mine plan
More informationCANADA S INTERMEDIATE GOLD PRODUCER
CANADA S INTERMEDIATE GOLD PRODUCER Third Quarter 2015 Results Conference 1 Call & Webcast October 29, 2015 Forward Looking Information This presentation contains certain forward-looking information and
More informationA new short- and medium-term production scheduling tool MineSight Schedule Optimizer (MSSO)
A new short- and medium-term production scheduling tool MineSight Schedule Optimizer (MSSO) Zhanyou Huang a, Wenlong Cai a, A. Frederick Banfield a a Mintec, Inc., Tucson, Arizona, USA The MineSight Schedule
More informationFor personal use only
Korab Resources Limited Gold Operations Update November 2012 Andrej K. Karpinski Executive Chairman Korab Projects BOBRIKOVO MELROSE 1 Korab Gold Projects Other Korab Projects Robust Undervalued Gold Portfolio
More informationCannon Big Pit Given the Green Light
ASX Release Tuesday 3 November 2015 Cannon Big Pit Given the Green Light Southern Gold maintains 50% profit share on Cannon Metals X estimate open pit recovered gold +270% to ~50koz Significant cash flow
More informationExploration. Exploration methods
Exploration Activities related to establishing a mineral deposit through geological, geophysical and geochemical methods. It is preceded by Prospecting and followed by Planning & Development. Geological
More informationThe Point Rousse Project - An Economic Analysis
ANACONDA MINING SELLS 3,956 OUNCES AND GENERATES $1.5M OF EBITDA AT THE POINT ROUSSE PROJECT FOR Q1 FISCAL 2016 TORONTO October 15, 2015 Anaconda Mining Inc. ( Anaconda or the Company ) (TSX: ANX) is pleased
More informationEstablishing the feasibility of your proposed mining venture
RUPPRECHT, S. Establishing the feasibility of your proposed mining venture. International Platinum Conference Platinum Adding Value, The South African Institute of Mining and Metallurgy, 2004. Establishing
More informationSeptember 2015 Quarterly Activities Report
ASX RELEASE 31 OCT 2015 September 2015 Quarterly Activities Report Expansion of Premier JV Gold Mine to 40,000ozpa production rate on track and future production growth plans advanced Highlights Production
More informationNEWS RELEASE LEXAM ANNOUNCES POSITIVE PRELIMINARY ECONOMIC ASSESSMENT RESULTS FOR THE OPEN PIT PROJECTS IN TIMMINS
NEWS RELEASE LEXAM ANNOUNCES POSITIVE PRELIMINARY ECONOMIC ASSESSMENT RESULTS FOR THE OPEN PIT PROJECTS IN TIMMINS Project Generates 32% IRR and C$33 Million NPV After-Tax; Cash Costs of US$865 per Ounce
More informationTypes of Mining - Expert Table
See page 6 Minerals Downunder Teacher Guide (2002) - Activity 4a Types of Mining - Expert Table How to Jigsaw Information 1. Divide the class into Home Groups of five for the five different types of mining
More informationBy Gene Kitts, Senior Vice President-Mining Services, International Coal Group, Inc.
Why Surface Mine? By Gene Kitts, Senior Vice President-Mining Services, International Coal Group, Inc. Why do we surface mine in Central Appalachia? It s certainly not because we like the public attention
More informationYAMANA GOLD ANNOUNCES SIGNIFICANT NEW DISCOVERIES AT CHAPADA AND EL PEÑÓN IMPROVE OPERATIONAL OUTLOOK
YAMANA GOLD ANNOUNCES SIGNIFICANT NEW DISCOVERIES AT CHAPADA AND EL PEÑÓN IMPROVE OPERATIONAL OUTLOOK TORONTO, ONTARIO, December 15, 2014 YAMANA GOLD INC. (TSX:YRI; NYSE:AUY) ( Yamana or the Company )
More informationTHIRD QUARTER EARNINGS NOVEMBER 12, 2015
THIRD QUARTER EARNINGS NOVEMBER 12, 2015 CAUTIONARY NOTES Qualified Person Brian Morris, is the non-independent Klondex Mines "qualified person" as defined by National Instrument 43-101 Standards of Disclosure
More informationUpdate on Heap Leach potential of the Murchison gold project
3 July 2012 Australian-based Kentor Gold Limited (ASX: KGL) is entering the ranks of operating gold mining companies in 2012. The Company is progressing a pipeline of advanced projects in Australia and
More informationTrading Symbol: TSX: SVM February 17, 2011 NYSE: SVM
PRESS RELEASE Trading Symbol: TSX: SVM February 17, 2011 NYSE: SVM SILVERCORP ANNOUNCES POSITIVE PRELIMINARY ASSESSMENT FOR THE SILVERTIP SILVER-LEAD-ZINC PROJECT, BRITISH COLUMBIA, CANADA VANCOUVER, British
More informationNEWS RELEASE. Toronto and Swiss Stock Exchanges Symbol IMZ, Frankfurt Symbol MIW
NEWS RELEASE February 11, 2008 Toronto and Swiss Stock Exchanges Symbol IMZ, Frankfurt Symbol MIW INTERNATIONAL MINERALS ANNOUNCES 6.2 MILLION OUNCES OF MEASURED AND INDICATED GOLD RESOURCES AND RESULTS
More informationThe final quarter of 2015 recorded 7,924 ounces of gold production, giving a year-end total of 32,629 ounces.
Fourth quarter update on gold operations at Palito and Sao Chico, declaration of commercial production at Sao Chico and extension of loan repayment terms Serabi Gold plc (AIM:SRB, TSX:SBI), the Brazilian
More informationSabina Gold & Silver Corp.
Sabina Gold & Silver Corp. Creating precious metals opportunities in the Canadian North November 2011 Hackett River Camp, looking to west 1 Forward Looking Statements This presentation includes certain
More informationQ2 2015 CONFERENCE CALL. Q2 2015 Earnings Call. Thursday, August 13, 2015 10:00 am EST. www.sasgoldmines.com
Q2 2015 CONFERENCE CALL Q2 2015 Earnings Call Thursday, August 13, 2015 10:00 am EST TSX:SAS OTCQX: STADF www.sasgoldmines.com 1 WEBCAST AND Q&A INSTRUCTIONS The webcast can be accessed under the Events
More informationRFID ENABLED GRADE CONTROL MANAGEMENT SYSTEM
RFID ENABLED GRADE CONTROL MANAGEMENT SYSTEM MINE TRIAL EXECUTIVE REPORT CATEGORY A Project CONTRACT NO. 4605002077 Approval The following Signatories approve this Project Process Report: NAME ROLE SIGNATURE
More informationNEVADA COPPER FILES INTEGRATED FEASIBILITY STUDY ON SEDAR
NEWS RELEASE TSX: NCU NEVADA COPPER FILES INTEGRATED FEASIBILITY STUDY ON SEDAR July 9, 2015 - Nevada Copper Corp. (TSX: NCU) ("Nevada Copper") (the Company ) is pleased to announce that it has completed,
More informationAccounting for stripping costs in the production phase costs of waste removal and the associated benefit
IFRIC Meeting Agenda reference 2A Staff Paper Date March 2010 Project Topic xtractive Activities Accounting for stripping costs in the production phase costs of waste removal and the associated benefit
More informationQueensland Mining Corporation L I M I T E D. Maiden JORC Resources Estimate for Horseshoe Copper Deposit, Duck Creek, South Cloncurry District
ASX Release 12 October 2012 Maiden JORC Resources Estimate for Horseshoe Copper Deposit, Duck Creek, South Cloncurry District Total mineral resource at Duck Creek Project area of 960,000t @ 1.47% Cu (0.2%
More informationAvion will host a conference call at 10:30 AM (EST) on Monday, April 2, 2011 to discuss the results. To participate in the call please dial:
March 31, 2012 A v i o n G o l d A n n o u n c e s F o u r t h Q u a r t e r 2 0 1 1 E a r n i n g s o f $ 8. 1 M i l l i o n W i t h E a r n i n g s P e r S h a r e O f $ 0. 0 2 R e c o r d 2 0 1 1 E
More informationCorporate Presentation October 2015
TSX.V: GBB OTC PK: GBBFF THE GRANADA GOLD PROPERTY IN ROUYN - NORANDA QUEBEC a Corporate Presentation October 2015 GoldBullionDevelopmentCorp.com A Compelling Value Proposition High-grade rolling start
More informationDe Grey Mining Ltd. Wingina Deeps Drilling Commenced (Turner River Project) Highlights. Turner River Unlocking Shareholder Value
De Grey Mining Ltd ASX RELEASE 5 July 2016 ASX Code DEG ABN 65 094 206 292 Wingina Deeps Drilling Commenced (Turner River Project) Highlights Diamond drilling programme of approximately 1,500m has COMPANY
More informationSilver Mine Project Investment Opportunity in Scandinavia
Silver Mine Project Investment Opportunity in Scandinavia KPMG Corporate Finance ( KPMG ) has been retained by Sotkamo Silver as exclusive Financial and Strategic adviser in connection with the Project
More informationCopper and Gold at Our Core
Copper and Gold at Our Core November 2015 TSX: ETG NYSE MKT: EGI FRANKFURT: EKA Cautionary Statement This presentation contains forward-looking statements within the meaning of the United States Private
More informationANNEX D1 BASIC CONSIDERATIONS FOR REVIEWING STUDIES IN THE DETAILED RISK ASSESSMENT FOR SAFETY
ANNEX D1 BASIC CONSIDERATIONS FOR REVIEWING STUDIES IN THE DETAILED RISK ASSESSMENT FOR SAFETY ANNEX D1: BASIC CONSIDERATIONS FOR REVIEWING STUDIES IN DRA FOR SAFETY D1-1 ANNEX D1 BASIC CONSIDERATIONS
More informationEl cinturón de oro del río Narcea: el futuro de la minería de oro en España. Dr. Vern N. Rampton Presidente y CEO de Kinbauri Gold Corp.
El cinturón de oro del río Narcea: el futuro de la minería de oro en España Dr. Vern N. Rampton Presidente y CEO de Kinbauri Gold Corp. CORPORATE PRESENTATION JUNE 16, 2009 TARGETED TO BECOME ONE OF WESTERN
More informationAGNICO-EAGLE MINES LIMITED
AGNICO-EAGLE MINES LIMITED Corporate Update January 2008 Agnico-Eagle Mines Limited 1 Forward Looking Statements The information in this document has been prepared as at January 15, 2007. Certain statements
More informationTHE VALUATION OF ADVANCED MINING PROJECTS & OPERATING MINES: MARKET COMPARABLE APPROACHES. Craig Roberts National Bank Financial
THE VALUATION OF ADVANCED MINING PROJECTS & OPERATING MINES: MARKET COMPARABLE APPROACHES Craig Roberts National Bank Financial ABSTRACT While various methods are available to estimate a mining project
More informationQuarterly Activities Report
ASX Release Thursday 28 January 215 Quarterly Activities Report ASX Code: SAU Issued Shares: 36.53M Directors Greg Boulton AM (Chair) Simon Mitchell (MD) Michael Billing David Turvey Head Office Southern
More informationGuidelines for the Estimation and Reporting of Australian Black Coal Resources and Reserves
Guidelines for the Estimation and Reporting of Australian Black Coal Resources and Reserves 2001 Edition (as referred to in the Joint Ore Reserves Committee Code ( The JORC Code ) 1999 edition) Prepared
More informationCondor Gold plc. (''Condor'' or "the Company") Whittle Consulting's Optimisation Study Significantly Enhances Economics
RNS Number : 7465C Condor Gold PLC 20 October 2015 7.00am on 20 October 2015 Condor Gold plc 7 th Floor 39 St. James's Street London SW1A 1JD Telephone +44 020 74081067 Fax: +44 020 74938633 Condor Gold
More informationBUILDING A COPPER COMPANY IN BRAZIL. PDAC Feb - 2014 - TORONTO
BUILDING A COPPER COMPANY IN BRAZIL PDAC Feb - 2014 - TORONTO CORPORATE & GOALS Shares on Issue 1.355B Significant Shareholders Share Price ~Au$0.07* Glencore 15% Market Cap ~Au$95m* BlackRock 5% Cash
More informationFORWARD-LOOKING STATEMENTS
FORWARD-LOOKING STATEMENTS This presentation contains forward-looking information. Forward looking information contained in this presentation includes, but is not limited to, statements with respect to:
More informationHISTORIC INTERSECTIONS INCLUDE 19.8 G/T AU OVER 8.9 METRES AND 24.4 GT AU OVER 9 METRES
65 Queen Street West Suite 825, P.O. Box 75 Toronto, Ontario M5H 2M5 Canada CROCODILE GOLD INITIATES DRILL PROGRAM AT UNION REEFS PROJECT AREA TARGETING HIGHH GRADE ZONES BELOW HISTORICAL OPEN PITS ADJACENT
More informationCondor Gold plc. (''Condor'' or "the Company") Whittle Consulting's Optimisation Study Significantly Enhances Economics
RNS Number : 6571M Condor Gold PLC 22 January 2016 22 January 2016 Condor Gold plc 7 th Floor 39 St. James's Street London SW1A 1JD Telephone +44 020 74081067 Fax: +44 020 74938633 Condor Gold plc (''Condor''
More informationAutomated Mine Scheduling: What is it and will it help me?
Automated Mine Scheduling: What is it and will it help me? Introduction This article discusses the philosophies, strategies, goals and pitfalls in automating a mine schedule. The intention is to give an
More informationThis discussion and analysis contains forward-looking statements. Please refer to the cautionary language on page 19.
This discussion and analysis of financial condition and results of operation of Thompson Creek Metals Company Inc. ( Thompson Creek or the Corporation ) is prepared as at August 7, 2008, and should be
More informationWonawinta Silver Project to be acquired; Mount Boppy development cost and risk cut back
Southern Cross Goldfields Ltd ASX Announcement 5 September 2014 Wonawinta Silver Project to be acquired; Mount Boppy development cost and risk cut back Wonawinta Silver Project (60 M oz) to be acquired
More informationFY13 was a year of transformation, including: The Company enters FY14 well positioned, with: ST BARBARA LIMITED 30 JUNE 2013
Annual Report 2013 FY13 was a year of transformation, including: The acquisition of two prospective Pacific Operations: Simberi gold operations in Papua New Guinea and Gold Ridge gold operations in the
More informationC o r p o r a t e P r e s e n t a t i o n A u g u s t 2 0 1 5
C o r p o r a t e P r e s e n t a t i o n A u g u s t 2 0 1 5 Forward Looking Statements This presentation includes certain estimates, projections and forward looking statements within the meaning of Section
More informationXtract Resources Plc (AIM:XTR) Chepica Gold Mine: Quarterly Results Presentation
Xtract Resources Plc (AIM:XTR) Chepica Gold Mine: Quarterly Results Presentation London 3 February 2016 Aerial view of Chepica Gold Mine Taken with Phantom 3 Professional Drone 2 We are xtracting significant
More informationGolpu feasibility study confirms robust investment case
Harmony Gold Mining Company Limited Registration number 1950/038232/06 Incorporated in the Republic of South Africa ISIN: ZAE000015228 JSE share code: HAR ( Harmony and/or the Company ) Golpu feasibility
More informationLydianinternational.co.uk TSX:LYD. Corporate Presentation June 2016 1
Lydianinternational.co.uk TSX:LYD Corporate Presentation June 2016 1 Cautionary Statements Certain information contained in this presentation, including any information relating to Amulsar's expected future
More informationSILVERCORP INTERCEPTS 18.8 METRES TRUE WIDTH GRADING 368 G/T SILVER AND 1.78 PERCENT LEAD AT THE LM MINE WEST, YING MINING DISTRICT, CHINA
NEWS RELEASE Trading Symbol: TSX: SVM NYSE: SVM SILVERCORP INTERCEPTS 18.8 METRES TRUE WIDTH GRADING 368 G/T SILVER AND 1.78 PERCENT LEAD AT THE LM MINE WEST, YING MINING DISTRICT, CHINA VANCOUVER, British
More informationFinancial and Operating Highlights through and subsequent to March 31, 2016: Completion of Flow-Through Share Financing
VANCOUVER, BRITISH COLUMBIA--(Marketwired - Jun 17, 2016) - Pure Gold Mining Inc. (TSX VENTURE:PGM) ("Pure Gold" or the "Company") is pleased to announce financial results and operating highlights for
More informationAVINO SILVER & GOLD MINES LTD.
AVINO SILVER & GOLD MINES LTD. T 604.682.370 Suite 900, 570 Granville Street ir@avino.com F 604.682.3600 Vancouver, BC V6C 3P www.avino.com August 8, 205 NYSE - MKT: ASM TSX-V: ASM FSE: GV6 Avino Reports
More informationAngloGold Ashanti La Colosa Site Visit November, 2011
AngloGold Ashanti La Colosa Site Visit November, 2011 Colombia Jorge Tapia Disclaimer Certain statements made in this communication, including, without limitation, those concerning the economic outlook
More informationKeras Resources plc ( Keras or the Company ) Moving Towards First Production in Q2 2016 at Grants Patch Gold Tribute Project, Australia
Keras Resources plc / Index: AIM / Epic: KRS / Sector: Mining 14 January 2016 Keras Resources plc ( Keras or the Company ) Moving Towards First Production in Q2 2016 at Grants Patch Gold Tribute Project,
More informationQ4 & FY2015 OPERATING HIGHLIGHTS. January 29, 2016
Q4 & FY2015 OPERATING HIGHLIGHTS January 29, 2016 1 FORWARD-LOOKING STATEMENTS This presentation contains certain statements that constitute forward-looking information within the meaning of applicable
More informationRIDDARHYTTAN RESOURCES PRESS RELEASE August 11, 2003
1 RIDDARHYTTAN RESOURCES PRESS RELEASE August 11, 2003 New drill holes in the Suurikuusikko area, Finland, have further intersected high gold grades over considerable widths, increasing the depth extent
More informationUPDATE ON SRIG - ALTONA TRANSACTION AGREED WORK AND DRILLING PROGRAMME COMMENCES
6 October 2015 SX: OH, FSE: 2O UPDTE ON SRIG - LTON TRNSCTION GREED WORK ND DRILLING PROGRMME COMMENCES greed Work Programme ltona Mining Limited s ( ltona or the Company ) and Sichuan Railway Investment
More informationTHE LEADING MINE SCHEDULING SOLUTION
THE LEADING MINE SCHEDULING SOLUTION XPAC XPAC: Scheduling software that is truly life of mine. XPAC is a business focused mine scheduling application, designed specifically for reserve modelling, production
More informationMining Financial Reporting Survey 2012. kpmg.ca. For Placement Only
Mining Financial Reporting Survey 2012 kpmg.ca For Placement Only Foreword KPMG s Mining Industry practice is pleased to present the Mining Financial Reporting Survey 2012. This document publishes the
More informationQuarterly Report Newcrest Mining Limited For the three months ending 31 December 2009 (These figures are unaudited)
Quarterly Report Newcrest Mining Limited For the three months ending 31 December 2009 (These figures are unaudited) Overview Gold production of 442,333oz was 17% higher than the previous quarter. Record
More informationMining Indaba Presentation. Capetown, South Africa 8 th 10 th February 2016
Mining Indaba Presentation Capetown, South Africa 8 th 10 th February 2016 www.birimiangold.com 1 Disclaimer This presentation has been prepared by Birimian Gold Limited (BGS) for general information purposes
More informationANNUAL GENERAL MEETING 2015. 30 November 2015
ANNUAL GENERAL MEETING 2015 30 November 2015 Disclaimer Competent Person Statement This presentation may contain some references to forecasts, estimates, assumptions and other forward-looking statements.
More informationFor personal use only
27 January 2016 Savannah North Scoping Study Positive results demonstrate robust, long life, Ni-Cu-Co Project Highlights Mining Inventory of 6.07Mt @ 1.26%Ni, 0.64% Cu and 0.09% Co for 76,500t Ni, 38,600t
More informationACQUISITION OF TWO QUALITY MINES IN NEVADA
November 12 2015 ACQUISITION OF TWO QUALITY MINES IN NEVADA 1 1 CAUTIONARY STATEMENT ON FORWARD-LOOKING INFORMATION All statements, other than statements of historical fact, contained or incorporated by
More informationMINIMUM ENGINEERING STUDY REQUIREMENTS UPDATE
Issue No. 128 June 2015 MINIMUM ENGINEERING STUDY REQUIREMENTS UPDATE Issue No. 95 (March 2009) of this publication, formally known as Pincock Perspectives, has been one of our most requested and referenced
More informationBackfill for Bench Stoping Operations
Backfill for Bench Stoping Operations E. Villaescusa Professor of Mining Geomechanics, Western Australian School of Mines K. Kuganathan Senior Backfill Research Engineer, Mount Isa Mines ABSTRACT This
More informationAurvista Gold Plans Significant Exploration Program at Douay
NEWS RELEASE For Immediate Issue June 14, 2016 Aurvista Gold Plans Significant Exploration Program at Douay Ø The main gold target is the largely untested northwestern section of the Porphyry Zone; the
More informationNEWS RELEASE. Centerra Gold Reports Fourth Quarter and 2015 Year-end Results
NEWS RELEASE Centerra Gold Reports Fourth Quarter and 2015 Year-end Results This news release contains forward-looking information that is subject to the risk factors and assumptions set out on page 27
More information(NYSE-MKT:XRA, TSX:XRC,
For Immediate Release: NR 15-08 Corporate Update Vancouver, B.C., December 17 th, 2015 Exeter Resource Corporation (NYSE-MKT:XRA, TSX:XRC, Frankfurt:EXB Exeter or the Company ) is pleased to provide the
More informationInternational approaches to mining projects: Due Diligence, Scoping, Pre-Feasibility, Feasibility Studies
International approaches to mining projects: Due Diligence, Scoping, Pre-Feasibility, Feasibility Studies Sergei Sabanov, PhD, CEng MIMMM Date:10 December 2013 Location: Almaty, Kazakhstan SRK Consulting
More informationPresentation to Analysts and Investors, Leonora Operations
ASX Announcement Presentation to Analysts and Investors, Leonora Operations Attached is a copy of a presentation to analysts and investors attending a site visit to Leonora Operations on Thursday 11 March,
More informationRichmont Increases Mineral Reserves by 187% and Island Gold Mine Increases Mineral Reserves by 206%, With a 29% Increase in Reserve Grade
PRESS RELEASE TSX NYSE MKT: RIC Richmont Increases Mineral Reserves by 187% and Island Gold Mine Increases Mineral Reserves by 206%, With a 29% Increase in Reserve Grade TORONTO, Ontario, Canada, February
More informationGOLD RESOURCE CORPORATION REPORTS PRELIMINARY INDEPENDENT RESOURCE ESTIMATE; ANNOUNCES COMPANY CONFERENCE CALL
FOR IMMEDIATE RELEASE April 26, 2012 NEWS NYSE Amex: GORO GOLD RESOURCE CORPORATION REPORTS PRELIMINARY INDEPENDENT RESOURCE ESTIMATE; ANNOUNCES COMPANY CONFERENCE CALL COLORADO SPRINGS April 26, 2012
More informationHow To Know If Goldcorp Is A Successful Company
Second Quarter Conference Call July 30 th, 2009 Management Participants Chuck Jeannes President and Chief Executive Officer Lindsay Hall Chief Financial Officer Steve Reid Chief Operating Officer Jeff
More informationSIBANYE GOLD MINERAL RESOURCES and MINERAL RESERVES UPDATE: FURTHER INCREASE IN GOLD AND URANIUM MINERAL RESERVES
Sibanye Gold Limited Incorporated in the Republic of South Africa Registration number 2002/031431/06 Share code: SGL ISIN - ZAE000173951 Issuer code: SGL ("Sibanye Gold" or "the Company") SIBANYE GOLD
More informationNEWS RELEASE. Centerra Gold 2015 Year-End Reserve and Resource Update
NEWS RELEASE Centerra Gold 2015 Year-End Reserve and Resource Update This news release contains forward-looking information that is subject to the risk factors and assumptions set out on page 7 and in
More informationNevada Focused, Discovery Driven. TSX V. RPM OTCQX: RPMGF www.ryepatchgold.com
Nevada Focused, Discovery Driven TSX V. RPM OTCQX: RPMGF www.ryepatchgold.com Certain statements contained herein, as well as oral statements that may be made by Rye Patch Gold Corp. or by officers, directors
More informationOVERVIEW. Exploration review
Exploration review Given the Group s present constrained economic situation, exploration focus is being limited to current operations and one continuing offshore project where positive results warranted
More informationFOR IMMEDIATE RELEASE
FOR IMMEDIATE RELEASE March 19, 2014 NEWS NYSE MKT: GORO GOLD RESOURCE CORPORATION REPORTS $16.2M NET INCOME AND RECORD ANNUAL METAL PRODUCTION FOR 2014; PROVIDES 2015 PRODUCTION OUTLOOK COLORADO SPRINGS
More informationChallenges of Investing in Junior Mining Companies and. Sotkamo Silver
Challenges of Investing in Junior Mining Companies and Sotkamo Silver Life Cycle of Junior Explorer High Risk - High Potential Full value Relative Value Possible takeover Speculation Discovery Lowered
More informationTORONTO STOCK EXCHANGE COMPANY MANUAL APPENDIX B DISCLOSURE STANDARDS FOR COMPANIES ENGAGED IN MINERAL EXPLORATION, DEVELOPMENT & PRODUCTION
B-1 APPENDIX B DISCLOSURE STANDARDS FOR COMPANIES ENGAGED IN MINERAL EXPLORATION, DEVELOPMENT & PRODUCTION 1.0 INTRODUCTION The disclosure of the results of exploration and development activity on mineral
More informationManagement s Discussion and Analysis and Consolidated Financial Statements. Second Quarter 2014
Management s Discussion and Analysis and Consolidated Financial Statements Second Quarter 2014 For the six months ended June 30, 2014 TABLE OF CONTENTS Page Management s Discussion and Analysis INTRODUCTION...
More informationMt Carrington Gold Silver Project Positive Scoping Study
ASX and Media Release: 31 July 2012 Mt Carrington Gold Silver Project Positive Scoping Study White Rock Minerals Ltd (ASX:WRM) has completed a robust scoping study on the Mt Carrington goldsilver project
More informationWILLAMAX PROJECT. TSX-V: DVN Reach us at 604 818 1706. Developing B.C. mining assets to create profitable gold production.
WILLAMAX PROJECT Developing B.C. mining assets to create profitable gold production May 2014 Reach us at 604 818 1706 Management Team Akash Patel, President and CEO Mr. Patel has received a bachelor in
More informationBUSINESS PLAN FOR THE MINERAL PROJECT FOR [NAME(S) OF PERIMETER(S)] SUBMITTED TO THE MINISTRY OF NATURAL RESOURCES/RWANDA
(COVER PAGE) COMPANY NAME PHONE / Fax Physical Address P.O. Box Email Website BUSINESS PLAN FOR THE MINERAL PROJECT FOR [NAME(S) OF PERIMETER(S)] SUBMITTED TO THE MINISTRY OF NATURAL RESOURCES/RWANDA NAME
More informationFor Immediate Release Date: February 3, 2016 #01-2016. Orvana Announces New Mineral Resources at El Valle Mine, Villar Zone and at La Brueva
For Immediate Release TSX:ORV Date: February 3, 2016 #01-2016 Orvana Announces New Mineral Resources at El Valle Mine, Villar Zone and at La Brueva New Villar Zone discovered within 50m of existing reserves
More informationIn-Pit Crushing and Conveying Phil Morriss
In-Pit Crushing and Conveying Phil Morriss AGENDA 1. Introduction - what is In-Pit Crushing and Conveying (IPCC)? 2. What does a quarry need from IPCC? 3. Why and when should we consider using it? 4. How
More informationTASEKO ANNOUNCES SECOND QUARTER RESULTS FOR FISCAL 2007
1020 800 W Pender St. Vancouver BC Canada V6C 2V6 Tel 604 684 6365 Fax 604 684 8092 Toll Free 1 800 667 2114 www.tasekomines.com TASEKO ANNOUNCES SECOND QUARTER RESULTS FOR FISCAL 2007 May 14, 2007, Vancouver,
More informationHIGH GRADE DRILL RESULTS CONTINUE AT THE KYLYLAHTI MINE
22 August 2013 ASX: AOH, FSE: A2O HIGH GRADE DRILL RESULTS CONTINUE AT THE KYLYLAHTI MINE Upper part of Wombat zone returns excellent drilling intersections: - 29.0m at 4.7% copper - 37.6m at 3.2% copper
More information