8. Operable steel sash windows are installed at the upper south wall, adjacent to the spectator area.
|
|
- Austin McCarthy
- 7 years ago
- Views:
Transcription
1 Architectural Elements Building Envelope A. System Description 1. The main portion of the building has a standing seam/batten type roof. This is over wood sleepers which sit atop the metal decking, filled with R19 batt insulation. A vapor barrier is installed atop the metal decking at areas without the acoustic insulation. Above the pool and spectator areas, the metal roofing is also installed over the wood sleepers atop the metal decking. The decking spans over intermediate exposed wood glulam beams. The metal decking has a sprayed on acoustic finish. No vapor barrier is noted in these areas. 2. South and west sections of the roof are low slope, with modified bitumen roofing over rigid insulation over metal decking and steel bar joists. R19 batt insulation is installed below the metal deck. 3. Portions of the roof have kalwall translucent panels sloping to match metal roof slopes. These areas transition to vertical panels, both of which provide day lighting in the pool/spectator areas. 4. Exterior walls are brick veneer over concrete masonry units. At the north walls, the space between CMU and brick is filled with 1 ½ rigid insulation, leaving ½ airspace. Hollow cells of CMU are filled with vermiculite. Portions of the north wall have been rebuilt, to assure proper air space provided to allow the movement of vapor. 5. South facing non Trombe exterior walls and exterior stairwell walls are 4 brick veneer directly over the CMU. No air space or cavity insulation is provided. Hollow cells of the CMU are filled with vermiculite. 6. South facing Trombe walls have the kalwall panels installed over 4 airspace, over a 12 solid CMU mass wall. This appears to be a non-ventilated Trombe wall design. 7. Exterior walls generally have 1 rigid insulation to a depth of Operable steel sash windows are installed at the upper south wall, adjacent to the spectator area. B. System Conditions/Observations 1. The standing seam roof has been subject to problems in high wind situations. The battens have come loose. The underlying panel fasteners may have corroded over the years. Visual inspection of these is impossible, as they are concealed. Cap flashings are damaged. Several
2 sections of roof have blown off and been reinstalled and are now rippled and dented. Portions of the roof were replaced on the north side with non-matching color units. 2. The modified bitumen low slope roof areas have been reroofed and are in average condition. Vertical modified flashing is not fully adhered to the masonry. Surface mounted reglets need to be resealed. One roof drain filter basket is missing. 3. A precast wall coping element, above the Trombe wall sections is deteriorating. The protective coating is failing on the face and is cracked and allowing infiltration at the top. The metal coping atop the masonry sections is lacking screws and neoprene washers in some areas. 4. Sloping and vertical sections of the kalwall are discolored and highly deteriorated due to sun and climate exposure. The panels both leak and attract condensation on cold nights, which then drips during the days. The exterior has fiberglass bloom the exterior protective gel has worn off, exposing the underlying fiberglass. Light transparency is greatly reduced from its original form. 5. Flashing at the base of the kalwall sections allow water infiltration. 6. Water is infiltrating below the kalwall, atop the precast concrete sill, at the west exit stair. Light is visible where caulking has fallen out. The steel supporting the sloping kalwall is highly corroded. 7. Roof drainage behind the south entry and stair element, at the sloping kalwall, is non-existent and a persistent source of roof leakage. Crickets were apparently lacking in the original construction. 8. The low slope roofs above the mechanical areas are inaccessible, no roof ladder is provided for these higher roofs. 9. Glulam beams above the spectator area are showing signs of minor surface delamination. The ends of the same beams show extensive checking, where water vapor from the environment has infiltrated. 10. Some Glu-Lam columns, adjacent to the second floor operable windows, show signs of potentially major decay, where they have been exposed to repeated water infiltration. One section of kalwall has recently pulled away from the supporting column. 11. The structural lintel above the second floor foyer has a significant crack visible on the lower side. 12. At the north low roof, a gutter is coming apart at the seams. The downspouts on the north have been damage near the bottom outflow area. 13. The exterior precast element at the west stairwell is in poor condition. 14. Many areas of brick veneer are flaking off at the west and above the low slope roofs. 15. The brick veneer at the central stairwell corners and other wing wall conditions has been exposed to water infiltration and freezing conditions, causing crack and the veneer to separate from remainder of the wall.
3 16. The brick veneer at the north, which was replaced in a prior project is in generally good condition, though areas of this have efflorescence from the mortar staining the brick s face. 17. At the east wall, an electrical outlet is missing its cover, leaving the electrical device and cavity open to the elements. 18. The south facing lower vertical Trombe wall panels were recently replaced with a non-kalwall product (Major Industries?). These newer panel faces are already separating from their frames. Temperature extremes within the Trombe wall cavity may be causing this. 19. The operable awning windows in the spectator areas have failed insulated glass units, with condensation forming in the cavities. Hardware has also corroded. The building s main entry lacks security access control. C. Code / Life Safety Issues 1. The west, north and east building exits all have a step of 4 6 at the threshold. No transition is allowable at exits. 2. The building envelope, roof and walls, generally does not provide insulating values required by the Energy Code. D. Maintenance Issues 1. Most transitions between materials lack proper sealants or original sealants have long ago deteriorated. This is especially a problem at the sill conditions of the upper operable south facing windows. 2. Seals are missing from some of the exterior doors. 3. The southeast exit doors in the pool area have exposed wood shims at the jambs. The closer is highly corroded. E. Recommendations 1. The metal roof needs to be replaced. Additional roof insulation is needed and a new vapor retarder needs to be installed below the batt insulation, atop the exposed metal decking. 2. The low slope roof finish should be removed, with additional rigid insulation added, then a new single ply system installed. New copings and flashings need to be installed at these areas.
4 3. The kalwall day lighting system needs to be removed and replaced with new higher performing panels, or with metal roofing to replace the sloped kalwall systems, and new glazed walls to replace the vertical sections. 4. The Trombe wall should either be abandoned, with new brick veneer installed, or a new ventilated Trombe system installed, with new glass panels. 5. Photovoltaic system should be considered for the sloped metal roof areas. 6. Provide roof hatch and ladder for west roof, for safety and to improve maintenance. 7. Non insulated areas of the existing double wythe masonry walls should be furred and insulated. A water vapor should be installed at these walls, and failed exterior bricks replaced. Interior furring should water resistant. 8. Entire exterior sealants should be redone, masonry sealed and coatings replaced at precast elements. 9. The existing operable windows at the spectator areas need to be replaced.
5 Building Envelope Roofs 1 Fig. 2B.1 Loss of granular surface. Fig. 2B.2 Spalled brick at parapets. Fig. 2B.3 Roofing released from parapet. Fig. 2B.4 Roof drain missing strainer, corroded. Fig. 2B.5 Water and snow directed towards wall. Fig. 2B.6 Damaged roofing & flashings. Fig. 2B.7 Damaged battens & flashing. Fig. 2B.8 Damaged flashing & battens.
6 Building Envelope Roofs 2 Fig. 2B.9 Kalwall is discolored & deteriorating. Fig. 2B.10 Flashing is allowing for water infiltration. Fig. 2B.11 Flashings need to be replaced. Fig. 2B.12 Kalwall flashing is deteriorated. Fig. 2B.13 Flashings allow for water infiltration. Fig. 2B.14 Spalled brick and lack of seal. Fig. 2B.15 Flashings are coming apart. Fig. 2B.16 Flashing needs to be resealed.
7 Building Envelope Roofs 3 Fig. 2B.17 Window sill flashing & sealant deteriorated. Fig. 2B.18 Pipe penetratioin improperly flashed. Fig. 2B.19 Reglet improperly installed. Fig. 2B.20 Fasteners missing from coping. Fig. 2B.21 Concrete coping patch deteriorated. Fig. 2B.22 Concrete parapet cracked. Fig. 2B.23 Temporary roof panels, mismatched color. Fig. 2B.24 Gutter damaged, mortar missing at joint.
8 Building Envelope Roofs 4 Fig. 2B.25 ext.wythe of wall. Fig. 2B.26 Awkward roof gutter. Fig. 2B.27 Kalwall eave.
9 Building Envelope Exterior Walls 1 Fig. 2B.28 Roof drain leader & over flow. Fig. 2B.29 Cracks in vertical mortar joints. Fig. 2B.30 Damaged rainwater conductor. Fig. 2B.31 Weatherproof outlet cover is missing. Fig. 2B.32 Efflorescence on brick and louver. Fig. 2B.33 Irrigation controllers, exposed conduits. Fig. 2B.34 Spalled/damaged brick. Fig. 2B.35 Spalled brick faces.
10 Building Envelope Exterior Walls 2 Fig. 2B.36 Damaged brick, paint and caulk. Fig. 2B.37 Efflorescence and poor site drainage. Fig. 2B.38 Damaged brick. Fig. 2B.39 Step at exit door & leaking hose bib. Fig. 2B.40 Drainage against building. Fig. 2B.41 Spalled concrete sill. Fig. 2B.42 Water drains toward the building. Fig. 2B.43 Damaged replaced Trombe panels.
EAST LYME HIGH SCHOOL
Overview: 1971 N 1966 GYM 1966 CLASSROOM WING 1966 AUD. 1971 GYM 1998 1998 POOL EAST LYME HIGH SCHOOL Original 1966 Building: The original East Lyme High School was constructed in 1966 and was composed
More informationCommercial Roof Inspection Form
Inspection Date: Inspector: Building Information Building ID: No.: Used For: Year Roof Applied: Building Description: Permanent Temporary Building Type: Retail Industrial Residential Building Name: Building
More informationSeptember 3, 2009. Ric Boyd, Public Works Director Ketchikan Gateway Borough 344 Front St. Ketchikan, AK 99901
September 3, 2009 Ric Boyd, Public Works Director Ketchikan Gateway Borough 344 Front St. Ketchikan, AK 99901 RE: Ketchikan Gateway Borough Gateway Recreation Center Roof Observations and Intrusive Inspections
More informationMarch 19, 2014. Ms. Jean McDonald CAP Management 910 16th Street, Suite 1010 Denver, Colorado 80202
Ms. Jean McDonald CAP Management 910 16th Street, Suite 1010 Denver, Colorado 80202 Re: Prospector s Point Walkway/Façade Repairs Martin/Martin, Inc Project No.: 13.0358.S.02 Ms. McDonald: Per your request
More informationTITLE: MASONRY PARAPET WALLS AND FLAT ROOF REQUIREMENTS 11/1/09
TITLE: MASONRY PARAPET WALLS AND FLAT ROOF REQUIREMENTS 11/1/09 PMT GUIDE # 10 Book of Order Section G-10.0102o: "The session is responsible for the mission and government of the particular church. It
More informationRESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000
RESIDENTIAL ROOFING & RE-ROOFING, ROOF VENTILATION AND ROOF SHEATHING REQUIREMENTS MICHIGAN RESIDENTIAL CODE 2000 SECTION R905 REQUIREMENTS FOR ROOF COVERINGS R905.1 Roof covering application. Roof coverings
More informationTotal Home Inspection Checklist
Total Home Inspection Checklist Use a checklist like this to make sure that you are looking at all parts of the house. Check off those items that are in good condition and make notes about those that are
More informationCommon Problems with Walls
Common Problems with Walls Common Problems with Walls There are problems and concerns that are shared by all walls and siding installations. In this article, we will learn about the following commonly
More informationBuilding Condition Assessment: 215-219 West Lexington Street Baltimore, Maryland
KPA The Joint Venture of EBA Engineering, Inc. and Kennedy Porter & Associates, Inc. 4813 Seton Drive, Baltimore, MD 21215 Phone: (410-358-7171) Fax: (410)358-7213 Building Condition Assessment: Baltimore,
More informationMarch 14, 2007. Installation of Bay, Bow and Garden Windows
March 14, 2007 Re: Installation of Bay, Bow and Garden Windows Attached are the Atrium Companies, Inc recommendation for the installation of bay, bow and garden windows. These instructions were developed
More informationSECTION 3 ONM & J STRUCTURAL ANALYSIS
Historic Boynton Beach High School Existing Building Assessment City of Boynton Beach February 10, 2011 SECTION 3 ONM & J STRUCTURAL ANALYSIS STRUCTURAL ENGINEERS SPECIAL INSPECTORS STRUCTURAL CONDITION
More informationwww.citiesinspection.com October 5, 2015 Dear Client,
www.citiesinspection.com October 5, 2015 Dear Client, On 9/14/2015, Cities Inspection Service, Inc. completed a building inspection of the property located at 123 Oak Street, Someplace, Minnesota for you.
More informationBuilding Foundation and Structure
Building Foundation and Structure Overview The construction of the Hall of Waters building began in 1936, and was constructed over the original site of the Siloam and Sulpho-Saline Springs. The original
More informationPELHAM MEMORIAL HIGH SCHOOL STONE FAÇADE REPORT. November 2007
PELHAM MEMORIAL HIGH SCHOOL STONE FAÇADE REPORT November 2007 PURPOSE OF INVESTIGATION Determine possible locations of moisture intrusion into and through facade. Determine cause of horizontal and vertical
More informationSODA SPRINGS JOINT SCHOOL DISTRICT NO. 150 RECOMMENDED REPAIRS, REPLACEMENT, AND ADDITIONS OPINIONS OF PROBABLE COST
SODA SPRINGS JOINT SCHOOL DISTRICT NO. 150 RECOMMENDED REPAIRS, REPLACEMENT, AND ADDITIONS OPINIONS OF PROBABLE COST SODA SPRINGS HIGH SCHOOL REPAIRS AND UPGRADES SITE Construction Estimate = $100,000
More informationRepair of Spalling and Leaking Clay Brick Building Walls
B etter buildings Repair of Spalling and Leaking Clay Brick Building Walls Overview A few years after being built in Waterloo in 1980, a condominium of three, six-storey buildings showed severe spalling
More informationCONDENSATION IN REFRIDGERATED BUILDINGS
CONDENSATION IN REFRIDGERATED BUILDINGS By: Steve Salisbury Nov. 10, 2010 (revised Nov. 14, 2013) Introduction The following discussion reviews the basic causes of condensation in refrigerated buildings
More informationInstallation Instructions Double-Hung, Single-Hung, Casement, Awning, Sliding, Picture & Shapes Non-Impact & Impact Resistant Nailing Fin Windows
Installation Instructions Double-Hung, Single-Hung, Casement, Awning, Sliding, Picture & Shapes Non-Impact & Impact Resistant Nailing Fin Windows americancraftsmanwindows.com Project Requirements: Read
More informationBuilding Condition Assessment: 109-111 North Howard Street Baltimore, Maryland
KPA The Joint Venture of EBA Engineering, Inc. and Kennedy Porter & Associates, Inc. 4813 Seton Drive, Baltimore, MD 21215 Phone: (410-358-7171) Fax: (410)358-7213 Building Condition Assessment: Baltimore,
More informationSun Windows General Information Sun New Construction Window Installation Instructions
Sun Windows General Information Section 1 G F H H H A. Apply Weather Resistive Barrier B. Apply Sill Flashing Tape C. Place Waterproof Sill Shims D. Caulk Back of Nail Fin Sides & Top, Set Window, Fasten
More informationUNIVERSITY OF WASHINGTON Facilities Services Design Guide. Architectural. Roofing. Basis of Design
Basis of Design This section applies to roofing membranes, flashing and accessories. Design Criteria Adhere to the standards and details of the latest editions of the National Contractors Association (NRCA)
More informationStructural Assessment Report
Report Dallas Township Elementary School Dallas, Pennsylvania (JBCI Project No. 144911) 1655 Suburban Station Building 1617 John F. Kennedy Boulevard Philadelphia PA 19103 215 665 0497 5 Sandwood Drive
More informationVision Home Inspection
Vision Home Inspection 324 Rams Run Shepherdsville KY 40165-7877 Inspector: James McFadden Property Inspection Report Client(s): Property address: Inspection date: View report summary This report is the
More informationCONSERVATION MAINTENANCE WORKSHEET Universal Checklist
3.1 SITE 1 Concrete curbs Check for cracks, spalling, growth from joints X 2 Stone curbs Check for cracks, spalling, growth from joints X 3 Concrete walkways Look for uneven surfaces, ponding, growth from
More informationEnvelope INSULATION BATT (2) Avoid Using Batt Insulation With Metal Framing. Pressure or Friction Fit
R-H-DI1 INSULATION BATT NR-E-IB1 Avoid Using Batt Insulation With Metal Framing Batt insulation should not be used with metal framing systems. Although it is common to see fiberglass batt insulation installed
More informationSlavic Village Building Condition Review
Slavic Village Building Condition Review Slavic Village Development May 8, 2015 Page 1 EXECUTIVE SUMMARY City Architecture was commissioned by Slavic Village Development to review five existing facilities
More informationSelf-Home Inspection Checklist
To be used as a first home visit for note taking. Visit www.homeinspectiondirect.com for more tips and information about buying a home and hiring a home inspector. This form in no way replaces a professional
More informationRoof Inspection. Summary Report
Phone: (561) 866 9956 www.real-estate-inspections.com Roof Inspection Summary Report Subject Property File Number: 05-15-RF-002 Inspector: Craig Milliken, PE CPM Real Estate Inspections, Inc. Date of Inspection:
More informationReplacement Window Installation Guide Non-Impact & Impact Resistant Windows without Nailing Fin
Replacement Window Installation Guide Non-Impact & Impact Resistant Windows without Nailing Fin americancraftsmanwindows.com Project Requirements: Failure to follow these instructions may void product
More informationArchitectural Condition Survey
Architectural Condition Survey Santa Fe Railroad / AMTRAK Depot, Lawrence. Kansas for the City of Lawrence, 2002 Survey: (student) PI: William Carswell, Associate Dean, School of Architecture, University
More informationSTAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM
STAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM Installed in Pre-engineered Steel Buildings Provides Lowest Cost Construction Method for CORROSIVE AND WET Environments PREFERRED SOLUTIONS, INC.
More informationAvoiding Air Barrier Pitfalls
Avoiding Air Barrier Pitfalls Design & Durability November 2013 Air barriers, when correctly installed, help buildings achieve high levels of energy efficiency by decreasing heat loss. For example, great
More informationWater Damage & Repair
Water Damage & Repair Chinatown Preservation Talks 2015 James Engler, P.A Glenn Mason, AIA Mason Architects Program Outline Terminology & Waterproofing Basics Discussion of why this is important Below
More informationROOFS - Guidance for Repair, Maintenance and Replacement
ROOFS - Guidance for Repair, Maintenance and Replacement Guilford Association Architectural Committee ROOFING Slate and tile roofs are a critical design feature of Guilford homes. The homes were designed
More informationGUIDELINES FOR REHABILITATION OF TRADITIONAL COMMERCIAL BUILDINGS DESIGN GUIDELINES
GUIDELINES FOR REHABILITATION OF TRADITIONAL COMMERCIAL BUILDINGS DESIGN GUIDELINES PAGE 13 DESIGN GUIDELINES The following design guidelines have been developed to guide appropriate design in the Downtown
More informationBasement Window Installation Guide Hopper and Sliding
Basement Window Installation Guide Hopper and Sliding americancraftsmanwindows.com Project Requirements: Installation must comply with all applicable building codes. Existing window frame, wall and weatherresistant
More informationINDIAN HEAD ELEMENTARY SCHOOL
ROOF ASSESSMENT REPORT INDIAN HEAD ELEMENTARY SCHOOL NOVEMBER 08, 2010 PREPARED FOR: FACILITIES DEPARTMENT WHITMAN HANSON REGIONAL SCHOOL DISTRICT 1. Purpose This Roofing Assessment Report provides a summary
More informationDelaney-Vogel School
Wrentham Public Schools Delaney-Vogel School Schematic Design 1. INTRODUCTION Wrentham Public Schools contracted with Turowski2 Architecture, Inc. on November 11, 2015 to assess necessary roof repairs
More informationWilliamson and Associates, Inc. Report of Building Exterior Condition Evaluation, dated January 2 nd, 2013. (68 pages)
INNOVATIVE BUILDING AND ARCHITECTURE CONSULTANTS Mr. Bud Hall Senior Vice President of construction Turnberry Associates 19501 Biscayne Boulevard, Suite 400 Aventura, FL 33180 Subject: The Nashville Hilton
More informationCLIENT. Inspection Report. 271 Front St. Alert Bay, B.C. Island Building Inspections V ANCOUVER I SLAND B. C.
CLIENT Inspection Report 271 Front St. Alert Bay, B.C. Island Building Inspections 2013 V ANCOUVER I SLAND B. C. Elevation Photos For the Property at 271 Front Street Alert Bay, BC ELEVATION PICTURES Front
More informationPreventing Ice Dams on Roofs
Preventing Ice Dams on Roofs Facility Manager November/December 2005 When a roof leaks, facility managers inevitably receive complaints from building occupants. If it is winter, ice dams are often the
More informationInspection Item COMMENTS
APPENDIX 9 AFFORDABLE HOUSING PROGRAM INSPECTION CHECKLIST Participating Jurisdiction: Homeowner Name: Assisted Property Address: Date of Physical Inspection of Property: Total Square Footage of Property:
More informationFacility Assessment Report, Montgomery Independent School District
THE LEARNING CENTER CAMPUS DATA THE LEARNING CENTER 700 Dr. Martin Luther King Jr. Drive, Montgomery TX 77356 Year Built 1958 Approx. Total Square Footage Grades Served Current Enrollment 22,050 n/a n/a
More informationSTRUCTURAL ASSESSMENT
STRUCTURAL ASSESSMENT Project: 1432-1434 East Commerce St. Job. No: 122200 Location: San Antonio, TX Date: Dec. 10, 2012 Weather: Sunny, Windy,60 deg Performed by: Jeff Haughton and Frank Lamas, Alpha
More information3. Tile used in the toilets is generally in good shape, though somewhat dated looking. The floor tile is slippery when wet.
Architectural Elements Support Facilities A. System Description 1. Architectural support facilities include the lobby, classroom, fitness room, office area, staff toilet/showers, public toilet/lockers,
More informationNCMA TEK CONCRETE MASONRY FOUNDATION WALL DETAILS. TEK 5-3A Details (2003)
NCMA TEK National Concrete Masonry Association an information series from the national authority on concrete masonry technology CONCRETE MASONRY FOUNDATION WALL DETAILS TEK 5-3A Details (2003) Keywords:
More information17,280 square feet Overview:
CENTRAL OFFICE Located at 167 Boston Post Road, East Lyme, Connecticut, the Central Office was built in 1916 as the original Flanders Elementary School and remains connected to the current school. The
More informationAssessing Curtain Walls
Assessing Curtain Walls Considerations and Best Practices Paul E Beers GCI Consultants, LLC pbeers@gciconsultants.com What is a Curtain Wall System? A curtain wall system is an outer covering of a building
More informationCITY OF WHITE BEAR LAKE BUILDING INSPECTION DEPARTMENT 4701 Highway 61 White Bear Lake, MN 55110 Fax: 651-429-8503. Re-Roofing: Asphalt Shingles
CITY OF WHITE BEAR LAKE BUILDING INSPECTION DEPARTMENT 4701 Highway 61 White Bear Lake, MN 55110 Fax: 651-429-8503 Re-Roofing: Asphalt Shingles This is a summary of the standard requirements based on the
More informationWINDOW INSTALLATION GUIDE
WINDOW INSTALLATION GUIDE is not responsible for or liable for any use or misuse of the information contained in this window installation guide. Window Installation Guide This guide provides basic information
More informationMaintenance & Inspection Guide
ADDRESSING THE NEEDS OF OUR CUSTOMERS AND THE ENVIRONMENT ONE high Performance roofing SOLUTION AT A TIME. Maintenance & Inspection Guide TABLE OF CONTENTS Topic: Page: I. Introduction 1 II. Maintenance
More informationSuperform Products Ltd.
TYPICAL CORNER REINFORCING NOTE : SEE ENGINEERED REBAR SCHEDULES SUPPLIED BY THE MANUFACTURER STEEL REINFORCEMENT WALL CORNER 90 Copyright 2012 Sept. 2012 5.1.1 Rebar Spacing 6" 12" Max. Load LB./FT. 2000
More informationEXTERNAL WATERPROOFING MEMBRANES BEST PRACTICE GUIDELINES
Building and Construction Industry A joint industry initiative produced by BSA Supershow logo.indd 1 30/01/2008 9:43:29 AM EXTERNAL WATERPROOFING MEMBRANES BEST PRACTICE GUIDELINES FAILING WATERPROOFING
More informationbout your HOUSE before you start Repairing And Replacing Materials Exterior Walls
A bout your HOUSE before you start Repairing And Replacing Materials Exterior Walls CE 28 h Exterior finish materials are expected to protect the house from the elements while providing an attractive appearance.
More informationRehab Inspection Report Page 1
Rehab Inspection Report Page 1 Home Address: Construction Style: Number of bedrooms Square footage: Value of offer: Estimated rehab cost: Value of resale: Orientation of house: N S E W Note: orientation
More informationComment Form on Proposed Gut Rehabilitation Alternatives
Comment Form on Gut Rehabilitation Alternatives Name: Organization: Email: Instructions Submission: Please submit this form to energystarhomes@energystar.gov by October 10 th, 2012 with the subject line
More informationHome Inspection Report
Home Inspection Report Report Number: For The Property Located On: 27713 Prepared For Exclusive Use By: Mr. Dave Jones Report Prepared By: Bret Smith; License No.: 3414 Signature: Date of Inspection: Monday,
More informationResidential Roofing Guide
Residential Roofing Guide TABLE OF CONTENTS Building Detail and Accessories...... 1 Panel Introduction and Handling...... 2 Cutting and Trimming.... 3 Roof Preparation..... 3 Roof Slope..... 3 Re-roofing...
More informationNRDCA 400 GUIDELINE FOR FIELD APPLICATION of LIGHTWEIGHT INSULATING CONCRETE REROOFING/RECOVER SYSTEMS
NRDCA 400 GUIDELINE FOR FIELD APPLICATION of LIGHTWEIGHT INSULATING CONCRETE REROOFING/RECOVER SYSTEMS The (NRDCA) has prepared this document to provide customers and installers information that the industry
More informationPETERSONS WATERFRONT CONDOMINIUMS
CONSULT DESIGN CONSTRUCT PETERSONS WATERFRONT CONDOMINIUMS 103 Park Street Chelan, Washington Findings Summary Report Prepared for: Petersons Waterfront Condominium Association March 21, 2014 J2 Project
More informationSECTION 07 61 13 STANDING SEAM METAL ROOFING
SECTION 07 61 13 STANDING SEAM METAL ROOFING PART 1 GENERAL 1.01 SCOPE OF WORK A. The Work shall include all labor, materials, equipment and supervision required to complete the work of the above referenced
More informationPROFESSIONAL ENGINEERING INSPECTIONS, INC.
PROFESSIONAL ENGINEERING INSPECTIONS, INC. P. O. BOX 271492 HOUSTON, TEXAS 77277 Registered Engineering Firm #1503 http://www.profengineering.com (713) 664-1264 July 8, 2004 Mr. Simple Samson 2831 Octoberfest
More informationROOF INSPECTION & MAINTENANCE
Physical Plant Administration Facilities Maintenance Department ROOF INSPECTION & MAINTENANCE All roofs require periodic inspection and maintenance in order to perform as designed and to provide a long
More informationMark Cramer Inspection Services, Inc.
Mark Cramer Inspection Services, Inc. 492 Twentieth Avenue, Indian Rocks Beach, FL 34635-2970 (727) 595-4211 Fax (727) 596-7583 Certified Member #12085 American Society of Home Inspectors Construction
More informationFacility Assessment for. 11801 East Main Street, Huntley, IL
Facility Assessment for 11801 East Main Street, Huntley, IL July 12, 2012 Prepared by: Dewberry Architects Inc. 25 S. Grove Avenue, Suite 500 Elgin, IL 60120 (847) 695-5840 The Village of Huntley requested
More informationFig. 2 WALL-TO-WALL PANEL CONNECTIONS CORNER WALL CONNECTION
SIPS SCREWS WITH MINIMUM 1" PENETRATION IN WOOD MEMBER IN SIP WALL PANEL CONNECTED TO @ 24" O.C. MAXIMUM OUTSIDE SKIN EACH SIDE OF FRAMING TYP. AS RECOMMENDED BY FOAM CORE AS EACH SIDE OF FRAMING TYP.
More informationRoof Inspection. Summary Report
www.real-estate-inspections.com Roof Inspection Summary Report Subject Property Prepared for: File Number: Client in Detroit 05-15-RF-004 Inspector: Craig Milliken, PE # 32779 CPM Real Estate Inspections,
More informationInspecting to a higher standard.
Inspecting to a higher standard. Rob Hopkin Silver Spring, MD 20902 Monday, June 2, 2014 ProTec Inspection Services Inc. 19736 Selby Ave Poolesville, MD 20837 301-972-8531 www.protec-inspections.com rob@protec-inspections.com
More informationRenovating Your Basement
building science.com 2006 Building Science Press All rights of reproduction in any form reserved. Renovating Your Building America Report - 0309 2003 (revised 2007) Building Science Corporation Abstract:
More informationTundra Series Windows January 2016
Tundra Series Windows January 2016 New Construction Installation Instructions Nail Fin, J-Fin and Brickmold Aplications product. ATTENTION! Read and understand all installation instructions before installing
More informationfoot skylight) is enough to knock a worker off their feet. A 10 mph wind gust on a 5 x 6 skylight develops a wind force of 270 lbs.
Skylight Installation Instructions This document provides instruction and guidelines for installation of both curb mount (CM) and self flashing (SF) unit skylights on flat, pitched (> or equal to 3/12
More informationReport for. Dick and Jane Homeowner. 1234 Lovers Lane, Houston, Texas 77000
Report for Dick and Jane Homeowner 1234 Lovers Lane, Houston, Texas 77000 March 17, 2004 I NI NP R Inspection Item I. STRUCTURAL SYSTEMS o o o A. Foundations (If all crawl space areas are not inspected,
More informationRecord of Work Experiences Trade Qualifier or Pre-Apprenticeship Credits ROOFER
Department of Advanced Education and Skills Apprenticeship and Trades Certification Division Record of Work Experiences Trade Qualifier or Pre-Apprenticeship Credits ROOFER Note to Apprenticeship Applicants
More informationInspection Report. Condo Association. Property Address: 2222 W. Water St. Swamptown, IL. William Decker, IL Lic. # 450.0002240.
Page 1 of 21 Inspection Report Condo Association Property Address: Swamptown, IL Front View William Decker, IL Lic. # 450.0002240 Page 2 of 21 Date: 10/10/2008 Time: 1:00 PM Report ID: Sample 4 Property:
More informationPackaged Terminal Air Conditioner Wall Sleeve Installation
Installation & Maintenance Data IM 1196 Group: PTAC Part Number: 910141799 Date: October 2013 Packaged Terminal Air Conditioner Installation x 42" PGAN with Top-Mounted Hydronic Heat Note: Installation
More informationIf there are any further questions with regards to the report or inspection, please call.
National Home Inspection Ltd. 1055 Woodbine Avenue Toronto, Ontario M4C 4C2 TEL: (416) 467-7809 FAX: (416) 429-5443 April 15, 2014 SUMMARY INSPECTION REPORT PROPERTY: 75 Fairlawn Avenue, Toronto, Ontario
More informationBrick Veneer Construction
Brick Veneer Construction Check list of suggested tools & support items Claw hammer Tape measure 3/4" [19 or 20] Wood chisel Wood or plastic shims Pry bar Utility knife Caulking and caulking gun Power
More informationFoundation. Foundation
Moisture Aside from structural concerns, the most important consideration for foundation design is moisture. No client wants a wet basement. No client wants a damp basement. No client wants mold in their
More information2008-2009 Cost Comparisons for Common Commercial Wall Systems
An Independent Study LA MS KY TN AL GA SC NC FL 2008-2009 Cost Comparisons for Common Commercial Systems CAPITAL BUILDING CONSULTANTS PROFESSIONAL CONSTRUCTION ESTIMATORS 2008 2009 INDEPENDENT COST COMPARISONS
More informationFoundation Experts, LLC Specializes in Foundation Repair and Waterproofing
1 Most basements show some signs of leaking and cracking. Through the years, problems with water, poor soils, grading, drainage and possible settling affect the integrity of a basement. Being able to recognize
More informationBROWNSVILLE STRUCTURES STUDY. July 2012. Prepared by. LDA ARCHITECTS 33 Terminal Way, Suite 317 Pittsburgh, Pennsylvania 15219 1208
BROWNSVILLE STRUCTURES STUDY July 2012 Prepared by LDA ARCHITECTS 33 Terminal Way, Suite 317 Pittsburgh, Pennsylvania 15219 1208 TABLE OF CONTENTS I. SUMMARY OF BUILDING ANALYSIS.. 1 II. INDIVIDUAL BUILDING
More informationWaterproofing Problems: A Simple Explanation, A Simple Solution
Waterproofing Problems: A Simple Explanation, A Simple Solution The purpose of this paper is to point out the underlying causes of waterproofing problems and simple means of preventing them. Such problems
More informationWe urge you to read and follow the attached installation instructions. Failure to do so may void the warranty of this garden window unit.
Important Information for New Construction Installations Attention Installer! We urge you to read and follow the attached installation instructions. Failure to do so may void the warranty of this garden
More informationMobile Home Pre-Inspection Checklist
Mobile Home Pre-Inspection Checklist TWO (2) STEP INSPECTION PROCESS STEP ONE: CALL FOR THE FIRST INSPECTION WHEN THESE ITEMS ARE COMPLETE. 1. Septic tank installed and plumbing complete. (SEE PLUMBING
More informationHOME INSPECTION CHECKLIST
CLOSING.COM LEARNING CENTER HOME INSPECTION CHECKLIST CONTENTS Attic 1 Balconies 1 Basement 1 Bathroom 2 Ceiling, Floors and Walls 2 Crawlspace 3 Decks and Porches 3 Doors and Windows 4 Drainage 4 Driveways
More informationWindow Installation Instructions
Caution The correct installation methods of windows in full frame or insert applications is critical towards achieving the tested performance of the window and longterm enjoyment and energy savings for
More informationVer. 2. Guide to. Inspecting Residential Brick Veneer
Ver. 2 Guide to Inspecting Residential Brick Veneer 1. A guide created by industry professionals. The knowledgeable staff at MASONPRO together with technical support from the Masonry Institute of Michigan
More informationLeaky Homes Financial Assistance Package (FAP) Repair plan example
LEAKY HOMES FINANCIAL ASSISTANCE PACKAGE FACT SHEET Repair Plan Example - June 2014 Page 1 Leaky Homes Financial Assistance Package (FAP) Repair plan example Introduction This repair plan example is intended
More informationINSTALLATION OF A BAY WINDOW
INSTALLATION OF A BAY WINDOW Installation of a Bay Window These instructions relate to the replacement of an existing bay window or replacement of a straight window with a new bay window, in an opening
More informationCHAPTER 7: Building Systems ROOFING SYSTEMS
ROOFING SYSTEMS Purpose Examples 1. Shingle roof system 2. Metal roof with blanket insulation 3. Metal roof with rigid insulation 4. Built-up asphalt roof system 5. Single-ply roof system 6. Modified Bitumen
More informationFacility Summary. Facility Condition Summary. Seattle School District David T. Denny International Infrastructure. Facility Components
Infrastructure Facility Condition Summary Weighted Avg Condition Score Facility Components Systems Surveyor/ Date Done Comments G Sitework.9 Site Improvements Parking Pedestrian Paving Site Development
More informationBasement & Foundation Damage
Basement & Foundation Damage Please note-this presentation is only intended to be used as a basic educational tool and is by no means all encompassing. Each property should be treated on a case by case
More informationsolutions & tips six Wise Energy Guide Building envelope solutions and simple tips AIR SEALING
Wise Energy Guide solutions & tips 32 AIR SEALING Is your house leaking money? six Building envelope solutions and simple tips If your home is like most, the greatest amount of heat loss is from air leakage;
More informationAir-Conditioning, Heating, and Refrigeration Institute. Sheet Metal and Air-Conditioning Contractors National Association
Air-Conditioning, Heating, and Refrigeration Institute Sheet Metal and Air-Conditioning Contractors National Association GUIDELINE B-1997 ACKNOWLEDGEMENT These guidelines for Roof Mounted Outdoor Air-
More informationCity of San Diego, CWP Guidelines
PART 1 -- GENERAL SECTION 08520-1.1 WORK OF THIS SECTION City of San Diego, CWP Guidelines A. The WORK of this Section includes providing aluminum windows with frames, bracing, glazing attachments, screens,
More informationLAYING BLOCK AND BRICK
LAYING BLOCK AND BRICK Products highlighted in this section: SAKRETE Type N Mortar Mix SAKRETE Type S Mortar Mix Brick And Block Laying Basics The first step in building a brick or block wall is to construct
More informationfirst look at GigaCrete s revolutionary new New Construction GigaHouse GigaHouse Utilizing GigaPanel
first look at GigaCrete s revolutionary new New Construction GigaHouse GigaHouse Utilizing GigaPanel What is GigaCrete GigaCrete is a family of products based on low carbon footprint Green ceramic binders
More informationFinegan Inspection Services, Inc.
Finegan Inspection Services, Inc. Report Prepared For: Phone 513-683-0733 Fa 513-697-0163 Owners Property Address City, State, ZIP Phone FAX Owners Realtor Realty Company Phone FAX OWNER INFORMATION PROPERTY
More informationSTRUCTURAL ASSESSMENT. Full Metal Jacket Building 0 Prince Street, Alexandria, VA
STRUCTURAL ASSESSMENT FOR Full Metal Jacket Building 0 Prince Street, Prepared by: ALPHA CORPORATION (Alpha) 1850 S. Loudoun Street, Suite 200 Winchester, VA 22601 540-723-0704 September 22, 2010 J. Michael
More informationTARRANT COUNTY DETAIL STANDARDS
TARRANT COUNTY DETAIL STANDARDS 1. Standard Coping 2. Coping at End Wall 3. Standard Sheet Metal Engagement Details 4. Gravel Guard 5. Gravel Guard Wall Termination 6. Gravel Guard, Gutter, and Downspout
More information