1 Basis of accounting and reporting cycle in March 2015 Rome (Italy)

2 Main information sources EC Regulation 1303/2013, (CPR) e.g: Art 125(4) management declaration Art 130 interim payments up to 90% Art 134 advance payments Art 135 accounting year Art 136 decommitment Art 137 preparations of accounts EC Implementing Regulation 1010/2014, (IR): Art 2 model for transmission of financial data Art 6 model for the payment application Art 7 model for the accounts Annex II Annex VI Annex VII 2

3 Accounting year The accounting year will be as follows: (1 July N 1) to (30 June N) The first accounting year is: 1 January June 2015 However the first payment claim not before notification of designation submitted to the EC 3

4 Timing annual clearance of accounts 4

5 CA and preparation of accounts (1) CA responsible for: Preparation of accounts for 1 July N-1 to 30 June N Preparation of payment claim Accounts are prepared for each OP at the level of each priority axis, including: Total eligible expenditure by beneficiaries till 30 June Corresponding public expenditure incurred Corresponding payments made to beneficiaries Amounts withdrawn / recovered / to be recovered and irrecoverable amounts Pre-financing paid to FEI and under state aid schemes Explanations of any difference between amounts in the final payment claim for the accounting year and accounts 5

6 CA and preparation of accounts (2) Differences between accounts and final payment claim for the accounting year may results from: Further management checks / corrections by MA Further checks by CA and precautionary withdrawals to cross check the eligibility of expenditure (Art 137(2) CPR) Corrections linked to audits by the AA (system audit, audits of operations, audits on the draft accounts) Corrections linked to EU audits. 6

7 CA and preparation of accounts (3) Final payment claim reconciled with the accounts. Any correction applied since the final payment claim till the submission of the accounts (31 July 15 February N+1) to be reconciled in the accounts. If CA excludes expenditure that is subject of the assessment on regularity or legality it may include it in the future payment applications if found to be regular.

8 Accounts: tasks of other institutions MA responsible for: The management declaration The report (including annual summary of final audits and control) accompanying the accounts AA responsible for: The audit opinion An annual control report supporting the audit opinion accompanying the CA and MA set of documents Designated body (MA) responsible for: Submission of documents annually by 15 February following the accounting year 8

9 Examination and acceptance of the accounts (1) Submission to the EC by 15 February N+1 By 31 May N+1 EC informs MS (MA) whether or not it is able to accept the accounts In case of acceptance (accounts are complete, accurate and true): Calculation of the amounts chargeable to the fund for the accounting year Balance to be paid in 30 days or deducted through recovery order Without prejudice to possible subsequent financial correction decision 9

10 Examination and acceptance of the accounts (2) In case of non-acceptance of the accounts: Commission determines the amount chargeable to the fund and informs MS / MA If MS / MA within 2 months agrees, the accounts are accepted and balance is paid / recovered If absence of agreement, EC adopts a decision setting out the amount chargeable (balance to be paid / recovered) This is not a financial correction reducing contribution from the fund. 10

11 Summary of novelties - challenges New timeline: May be different many accounting / financial years in MS New 7 up-dated documents: management declaration MA report (annual summary of final audits and reports) MA Tight schedule for AA: additional task assurance of accounts two samples for audit of operation suggested by EC AA has 7 months to organise sampling, audits, preparation of reports ( it was 1 year). 11

12 Thank you for your attention Please do not hesitate to contact us for any further information or visit INTERACT Point Turku INTERACT Point Valencia INTERACT Point Viborg INTERACT Point Vienna INTERACT Programme Secretariat INTERACT is co-financed by the European Regional Development Fund (ERDF) European Territorial Cooperation

Annual Assurance and Irregularities

Annual Assurance and Irregularities Annual Assurance and Irregularities Trainer : Dermot Byrne Head of Authority ERDF Audit Authority, Ireland Brussels September 2014 This training has been organised by EIPA-Ecorys-PwC under the Framework

More information

Guidance for Member States on Audit of Accounts

Guidance for Member States on Audit of Accounts EGESIF_15_0016-02 final 05/02/2016 EUROPEAN COMMISSION European Structural and Investment Funds Guidance for Member States on Audit of Accounts DISCLAIMER: This is a document prepared by the Commission

More information

Audit authority Audits of Systems, Operations and Accounts

Audit authority Audits of Systems, Operations and Accounts Audit authority Audits of Systems, Operations and Accounts Trainer:Dermot Byrne Head of Authority ERDF Audit Authority, Ireland Brussels September 2014 This training has been organised by EIPA-Ecorys-PwC

More information

DRAFT. Guidance for Member States and Programme Authorities Designation Procedure

DRAFT. Guidance for Member States and Programme Authorities Designation Procedure 23/05/2014 EUROPEAN COMMISSION EGESIF_14-0013 DRAFT European Structural and Investment Funds Guidance for Member States and Programme Authorities Designation Procedure (under Articles 123 and 124 of Regulation

More information

Guidance on standard scales of unit costs and lump sums adopted under Article 14(1) Reg. (EU) 1304/2013

Guidance on standard scales of unit costs and lump sums adopted under Article 14(1) Reg. (EU) 1304/2013 EUROPEAN COMMISSION European Social Fund Guidance on standard scales of unit costs and lump sums adopted under Article 14(1) Reg. (EU) 1304/2013 Version of June 2015 Please consult http://ec.europa.eu/esf/sco

More information

COU CIL OF THE EUROPEA U IO. Brussels, 16 ovember /12 ADD 1 REV 1. Interinstitutional File: 2011/0276 (COD) 2011/0273 (COD)

COU CIL OF THE EUROPEA U IO. Brussels, 16 ovember /12 ADD 1 REV 1. Interinstitutional File: 2011/0276 (COD) 2011/0273 (COD) COU CIL OF THE EUROPEA U IO Brussels, 16 ovember 2012 Interinstitutional File: 2011/0276 (COD) 2011/0273 (COD) 15880/12 ADD 1 REV 1 FSTR 71 FC 46 REGIO 123 SOC 905 AGRISTR 150 PECHE 457 CADREFI 456 CODEC

More information

South East Europe (SEE) Implementation Manual

South East Europe (SEE) Implementation Manual South East Europe (SEE) Implementation Manual Version 5.0 Date of approval (v1.2): 8 th May 2009 1 st amendment (v2.1): 7th July 2009 2 nd amendment (v3.1): 21 st January 2011 3 rd amendment (v3.2): 27

More information

Declaration and co financing Statement

Declaration and co financing Statement Declaration and co financing Statement 1. Declaration and co financing statement signed and stamped by each ERDF partner (including the Lead Applicant and 20% ERDF, if any) in original! 2. Declaration

More information

TERRITORIAL COOPERATION OBJECTIVE FINANCIAL MANAGEMENT HANDBOOK

TERRITORIAL COOPERATION OBJECTIVE FINANCIAL MANAGEMENT HANDBOOK TERRITORIAL COOPERATION OBJECTIVE FINANCIAL MANAGEMENT HANDBOOK March 2007 INTERACT is financed by the European Regional Development Fund (ERDF) 2 This handbook is for information only. It is not designed

More information

SPECIFIC AGREEMENT No./.. 1 ON A GRANT FOR AN ACTION

SPECIFIC AGREEMENT No./.. 1 ON A GRANT FOR AN ACTION ANNEX II MODEL SPECIFIC GRANT AGREEMENT FOR AN ACTION SPECIFIC AGREEMENT No./.. 1 ON A GRANT FOR AN ACTION This specific agreement ("the agreement") is concluded between: The European Union ("the Union"),

More information

Official Journal of the European Union

Official Journal of the European Union L 132/32 COMMISSION IMPLEMTING REGULATION (EU) No 447/2014 of 2 May 2014 on the specific rules for implementing Regulation (EU) No 231/2014 of the European Parliament and of the Council establishing an

More information

URBACT III Programme Manual

URBACT III Programme Manual URBACT III Programme Manual Fact Sheet 2E Network Management Table of contents Fact Sheet 2E 0. Introduction... 1 1. Roles and responsibilities of Lead and Project Partners... 2 2. The legal framework...

More information

REVENUE-GENERATING PROJECTS Guidelines for Project Partners

REVENUE-GENERATING PROJECTS Guidelines for Project Partners REVENUE-GENERATING PROJECTS Guidelines for Project Partners ESTONIA - LATVIA PROGRAMME 2007-2013 CCI No 2007 CB 163 PO 050 Cross-border Co-operation Programme under European Territorial Co-operation Objective

More information

2014 2020 Programming Period

2014 2020 Programming Period 2014 2020 Programming Period Introduction Andreas von Busch f Lisbon, Portugal 14 Oktober 2014 2014 2020 Programming Period Cohesion challenge f The European Union is diverse GDP/capita 3 The European

More information

Regulation on the implementation of the Norwegian Financial Mechanism 2009-2014

Regulation on the implementation of the Norwegian Financial Mechanism 2009-2014 Regulation on the implementation of the Norwegian Financial Mechanism 2009-2014 adopted by the Norwegian Ministry of Foreign Affairs pursuant to Article 8.8 of the Agreement between the Kingdom of Norway

More information

Regulation on the implementation of the European Economic Area (EEA) Financial Mechanism 2009-2014

Regulation on the implementation of the European Economic Area (EEA) Financial Mechanism 2009-2014 the European Economic Area (EEA) Financial Mechanism 2009-2014 adopted by the EEA Financial Mechanism Committee pursuant to Article 8.8 of Protocol 38b to the EEA Agreement on 13 January 2011 and confirmed

More information

Informal Meeting of Rural Development Directors

Informal Meeting of Rural Development Directors Informal Meeting of Rural Development Directors Implementation of EIP projects within the RDPs: Managing Authorities perspective an idea put into practice with success Rome 06.11.2014 SCOPE OF THE PRESENTATION

More information

Financial instruments - opportunities offered by the 2014-2020 framework. Key novelties and Commission guidance Bratislava, 2 October 2015

Financial instruments - opportunities offered by the 2014-2020 framework. Key novelties and Commission guidance Bratislava, 2 October 2015 Financial instruments - opportunities offered by the 2014-2020 framework Key novelties and Commission guidance Bratislava, 2 October 2015 2014-2020 framework Ø Performance oriented legal framework to promote

More information

Partnership Agreement

Partnership Agreement IPA Operational Programme Slovenia Croatia 2007 2013 Partnership Agreement Based on Article 9 of the IPA Subsidy Contract No. , concluded between the Government Office for Local

More information

Rules and Procedures in the new Programme 14-20

Rules and Procedures in the new Programme 14-20 Rules and Procedures in the new Programme 14-20 OBJECTIVES Overview of main rules and procedures to be followed Main novelties compared to the 2007-2013 period Risky points Information to be completed

More information

CALL FOR SUBMISSION OF PROJECTS IN OP RDI Strengthening Research Capacities of R&D Centres

CALL FOR SUBMISSION OF PROJECTS IN OP RDI Strengthening Research Capacities of R&D Centres Ministry of Education, Youth and Sports Managing Authority OP RDI CALL FOR SUBMISSION OF PROJECTS IN OP RDI Strengthening Research Capacities of R&D Centres Call Identification Priority Axis Call Number

More information

EUROPEAN COMMISSION DIRECTORATE-GENERAL JUSTICE CALL FOR PROPOSALS JUST/2013/DAP/SAG/CAAM FOR CHILD ABDUCTION ALERT MECHANISMS SPECIFIC ACTION GRANTS

EUROPEAN COMMISSION DIRECTORATE-GENERAL JUSTICE CALL FOR PROPOSALS JUST/2013/DAP/SAG/CAAM FOR CHILD ABDUCTION ALERT MECHANISMS SPECIFIC ACTION GRANTS EUROPEAN COMMISSION DIRECTORATE-GENERAL JUSTICE Directorate A: Civil justice Unit A.4: Programme management SPECIFIC PROGRAMME "DAPHNE III (2007 2013) CALL FOR PROPOSALS JUST/2013/DAP/SAG/CAAM FOR CHILD

More information

Manual of Procedures VERSION 2.0 JULY 2012

Manual of Procedures VERSION 2.0 JULY 2012 Manual of Procedures VERSION 2.0 JULY 2012 Introduction - The current version of the MoP is an adaptation of the previous MoP which also includes information from the Cohesion Policy 2007-2013 MoP - The

More information

Annex 2: Rules and Procedures for the Swiss-Polish Cooperation Programme

Annex 2: Rules and Procedures for the Swiss-Polish Cooperation Programme Annex 2: Rules and Procedures for the Swiss-Polish Cooperation Programme Annex 2 is an integral part of the Framework Agreement between the Swiss Federal Council and the Government of the Republic of Poland

More information

Template Lead Applicant and State aid declarations

Template Lead Applicant and State aid declarations Template Lead Applicant and State aid declarations ERDF national, regional and local public bodies, bodies governed by public law, International organisations acting under national law and EGTCs 1 Project

More information

INTERACT III 2014-2020 Operational Programme version 2.4 (pre-final draft), June 2014

INTERACT III 2014-2020 Operational Programme version 2.4 (pre-final draft), June 2014 INTERACT III 2014-2020 Operational Programme version 2.4 (pre-final draft), June 2014 CCI Title INTERACT III 2014-2020 Version First year Last year Eligible from Eligible until EC decision number EC decision

More information

ENGLAND EUROPEAN REGIONAL DEVELOPMENT FUND OPERATIONAL PROGRAMME GUIDANCE ON REVENUE GENERATING PROJECTS

ENGLAND EUROPEAN REGIONAL DEVELOPMENT FUND OPERATIONAL PROGRAMME GUIDANCE ON REVENUE GENERATING PROJECTS ENGLAND EUROPEAN REGIONAL DEVELOPMENT FUND OPERATIONAL PROGRAMME 2014-20 GUIDANCE ON REVENUE GENERATING PROJECTS September 2015 Guidance on Revenue Generating Projects Contents Background Purpose of the

More information

The Terms of Reference should be completed by the Beneficiary and be agreed with the Auditor

The Terms of Reference should be completed by the Beneficiary and be agreed with the Auditor ANNEX V-A FORM - TERMS OF REFERENCE FOR THE CERTIFICATE OF FINANCIAL STATEMENTS TABLE OF CONTENTS TERMS OF REFERENCE FOR AN INDEPENDENT REPORT OF FACTUAL FINDINGS ON COSTS CLAIMED UNDER A ERC GRANT AGREEMENT

More information

PREPARATION COST REPORT

PREPARATION COST REPORT PREPARATION COST REPORT European Territorial Cooperation Objective CENTRAL EUROPE Programme Don't remove the Excel protection. You risk that the form will be damaged and become NOT RECEIVABLE Title of

More information

YOUTH EMPLOYMENT INITIATIVE Fiche no 34

YOUTH EMPLOYMENT INITIATIVE Fiche no 34 YOUTH EMPLOYMENT INITIATIVE Fiche no 34 Brussels 5 April 2013 Commission Proposal ESF Regulation [COM(2013) 145] Common Provisions Regulation [COM(2013) 146] Relevant Article Chapter III bis (Articles

More information

ANNUAL REPORT OF THE OPERATIONAL PROGRAMME TECHNICAL ASSISTANCE

ANNUAL REPORT OF THE OPERATIONAL PROGRAMME TECHNICAL ASSISTANCE ANNUAL REPORT OF THE OPERATIONAL PROGRAMME TECHNICAL ASSISTANCE FOR 2012 March 2013 Prepared for 11 th meeting of OPTA Monitoring Committee held on 4 June 2013 in Prague CONTENTS 1 IDENTIFICATION OF THE

More information

L 210/10 Official Journal of the European Union

L 210/10 Official Journal of the European Union L 210/10 Official Journal of the European Union 10.8.2007 COMMISSION REGULATION (EC) No 951/2007 of 9 August 2007 laying down implementing rules for cross-border cooperation programmes financed under Regulation

More information

Guide for Applicants. Call for Proposal:

Guide for Applicants. Call for Proposal: Guide for Applicants Call for Proposal: COSME Work Programme 2014 TABLE OF CONTENTS I. Introduction... 3 II. Preparation of the proposal... 3 II.1. Relevant documents... 3 II.2. Participants... 4 II.2.1.

More information

FP7 GRANT AGREEMENT ANNEX VII - FORM D - TERMS OF REFERENCE FOR THE CERTIFICATE OF FINANCIAL STATEMENTS

FP7 GRANT AGREEMENT ANNEX VII - FORM D - TERMS OF REFERENCE FOR THE CERTIFICATE OF FINANCIAL STATEMENTS FP7 GRANT AGREEMENT ANNEX VII - FORM D - TERMS OF REFERENCE FOR THE CERTIFICATE OF FINANCIAL STATEMENTS TABLE OF CONTENTS TERMS OF REFERENCE FOR AN INDEPENDENT REPORT OF FACTUAL FINDINGS ON COSTS CLAIMED

More information

Subsidy Contract template. The MA reserves the right to modify the text of the Draft Subsidy Contract.

Subsidy Contract template. The MA reserves the right to modify the text of the Draft Subsidy Contract. Subsidy Contract template The MA reserves the right to modify the text of the Draft Subsidy Contract. Application ID: Project acronym: Project title: Subsidy Contract for the implementation of the Project

More information

ENGLAND EUROPEAN REGIONAL DEVELOPMENT FUND OPERATIONAL PROGRAMME

ENGLAND EUROPEAN REGIONAL DEVELOPMENT FUND OPERATIONAL PROGRAMME ENGLAND EUROPEAN REGIONAL DEVELOPMENT FUND OPERATIONAL PROGRAMME 2014-20 GUIDANCE ON DOCUMENT RETENTION, INCLUDING ELECTRONIC DATA EXCHANGE, FOR 2014-20 ERDF PROJECTS February 2016 DOCUMENT RETENTION,

More information

CEF Energy model grant agreement

CEF Energy model grant agreement CEF Energy model grant agreement Main features, financial and reporting conditions CEF Energy Info Day Delphine Silhol - Legal Adviser, INEA 16 March 2015 Background Single model grant agreement for the

More information

Errors in Cohesion Policy. Where are they? What is being done about them? What will the 2014-2020 legal framework improve?

Errors in Cohesion Policy. Where are they? What is being done about them? What will the 2014-2020 legal framework improve? EN Errors in Cohesion Policy Where are they? What is being done about them? What will the 2014-2020 legal framework improve? Who is responsible for the money? Cohesion policy accounts for approximately

More information

Territorial Cooperation projects : Partnership Agreement Template

Territorial Cooperation projects : Partnership Agreement Template Template DISCLAIMER: This tool was issued by INTERACT during the 2000-2006 programming period and aims at spreading good examples and lessons learnt to enable a successful implementation of the 2007-2013

More information

Financial management of the project, tools and reporting

Financial management of the project, tools and reporting Financial management of the project, tools and reporting Lead Partner Seminar 4th Call for Proposals Budapest, Hungary 11 December 2012 SEE Joint Technical Secretariat Financial management of the project,

More information

Financial Instruments supported by the European Structural and Investment (ESI) Funds in 2014-2020. MADRID, 7 November 2013

Financial Instruments supported by the European Structural and Investment (ESI) Funds in 2014-2020. MADRID, 7 November 2013 Financial Instruments supported by the European Structural and Investment (ESI) Funds in 2014-2020 MADRID, 7 November 2013 Financial instruments and IFI Relations Directorate-General for and Urban 1 Contents

More information

Annex 2: Rules and Procedures for the Swiss- Estonian Cooperation Programme

Annex 2: Rules and Procedures for the Swiss- Estonian Cooperation Programme nicht amtliche Publikation Annex 2: Rules and Procedures for the Swiss- Estonian Cooperation Programme Annex 2 is an integral part of the Framework Agreement between the Swiss Federal Council and the Government

More information

INTERREG IVA 2 Mers Seas Zeeën. Cross-border Cooperation Programme 2007-2013. Programme Manual. Guidance on Eligibility and Project Management

INTERREG IVA 2 Mers Seas Zeeën. Cross-border Cooperation Programme 2007-2013. Programme Manual. Guidance on Eligibility and Project Management INTERREG IVA 2 Mers Seas Zeeën Cross-border Cooperation Programme 2007-2013 Programme Manual Guidance on Eligibility and Project Management Version 06/02/2013 Operational programme of the European Territorial

More information

ENGLAND EUROPEAN SOCIAL FUND OPERATIONAL PROGRAMME

ENGLAND EUROPEAN SOCIAL FUND OPERATIONAL PROGRAMME ENGLAND EUROPEAN SOCIAL FUND OPERATIONAL PROGRAMME 2014-20 GUIDANCE ON DOCUMENT RETENTION, INCLUDING ELECTRONIC DATA EXCHANGE, FOR 2014-20 ESF PROJECTS April 2016 ESF Document Retention Guidance Version

More information

DG RTD COMMON AUDIT SERVICE SPECIFIC PRIVACY STATEMENT EXTERNAL AUDIT AND CONTROL

DG RTD COMMON AUDIT SERVICE SPECIFIC PRIVACY STATEMENT EXTERNAL AUDIT AND CONTROL DG RTD COMMON AUDIT SERVICE SPECIFIC PRIVACY STATEMENT EXTERNAL AUDIT AND CONTROL Version Date Description of changes Page 1.1 21 August 2014 New online location in the Participant Portal (as the file

More information

Administrative + Management Aspects. EU - Framework Programme 7. Grant Agreement: Acronym FMT-XCT Project Kick-off Meeting, 14.05.

Administrative + Management Aspects. EU - Framework Programme 7. Grant Agreement: Acronym FMT-XCT Project Kick-off Meeting, 14.05. Administrative + Management Aspects EU - Framework Programme 7 Grant Agreement: Acronym FMT-XCT Project Kick-off Meeting, 14.05.2008 Dr. Jürgen Ertel Department Program Planing and Management Head of Project

More information

Guide to Financial Issues for Cleansky GAPs

Guide to Financial Issues for Cleansky GAPs Guide to Financial Issues for Cleansky GAPs Version of 16/01/2012 adopted by the Commission and subsequently adapted for the Clean Sky Joint Undertaking on 08/05/2012 Disclaimer This guide is aimed at

More information

COMMISSION DECISION. of XXX

COMMISSION DECISION. of XXX EUROPEAN COMMISSION Brussels, XXX [ ](2014) XXX draft COMMISSION DECISION of XXX authorising the use of reimbursement on the basis of unit costs for actions requiring the conduct of clinical studies under

More information

GUIDE FOR APPLICANTS GRANTS PROGRAMME 2016/2017 TRAINING IN CONFERENCE INTERPRETING

GUIDE FOR APPLICANTS GRANTS PROGRAMME 2016/2017 TRAINING IN CONFERENCE INTERPRETING GUIDE FOR APPLICANTS GRANTS PROGRAMME 2016/2017 TRAINING IN CONFERENCE INTERPRETING The aim of this guide is to give a summary of the main points of the administrative and financial processes governing

More information

Guide for ERC Grant Holders Part II

Guide for ERC Grant Holders Part II EUROPEAN RESEARCH COUNCIL Guide for ERC Grant Holders Part II Reference Manual on Financial Management and Administration of the ERC Grants Starting and advanced grants Version 1-24/06/2008 Disclaimer:

More information

Project Completion Report (PCR) User Guide

Project Completion Report (PCR) User Guide Project Completion Report (PCR) User Guide FM0027-GDL-00041-EV17 8 February 2010 Page 2 of 10 1. Introduction The Project Completion Report (PCR) is a structured reporting format provided by the Financial

More information

Frequently Asked Questions (FAQs) for Recycling Fund Applicants

Frequently Asked Questions (FAQs) for Recycling Fund Applicants Frequently Asked Questions (FAQs) for Recycling Fund Applicants Industry Support Programme (ISP) 1. Eligibility 1.1 What is the Primary Objective of the Recycling Fund? The primary objective of establishing

More information

Project management in FP7. Gorgias Garofalakis ETAT S.A.

Project management in FP7. Gorgias Garofalakis ETAT S.A. Project management in FP7 Gorgias Garofalakis ETAT S.A. The whole process EU FP7 Project Project idea Proposal writing Evaluation Negotiations Project implementation Contact with partners after the evaluation

More information

FP7 Rules of Participation Funding schemes Financial issues Evaluation Criteria Implementation Submission Contractual and Financial issues

FP7 Rules of Participation Funding schemes Financial issues Evaluation Criteria Implementation Submission Contractual and Financial issues National Documentation Center (EKT/NHRF) FP7 Rules of Participation Funding schemes Financial issues Evaluation Criteria Implementation Submission Contractual and Financial issues Maria Samara, Administrative

More information

1st call for proposals: Administrative and submission procedures Infoday La Valeta, Malta, June 17th 2015

1st call for proposals: Administrative and submission procedures Infoday La Valeta, Malta, June 17th 2015 1st call for proposals: Administrative and submission procedures Infoday La Valeta, Malta, June 17th 2015 SIZE OF THE PARTNERSHIP As a minimum requirement, the partnership must involve: at least 4 financing

More information

ERDF Grant Schemes for Enterprises. Schemes part-financed by European Regional Development Funds 2007-2013

ERDF Grant Schemes for Enterprises. Schemes part-financed by European Regional Development Funds 2007-2013 ERDF Grant Schemes for Enterprises Schemes part-financed by European Regional Development Funds 2007-2013 Malta Enterprise Ministry of Finance, the Economy & Investment Operational Programme I Cohesion

More information

Questions & Answers. on e-cohesion Policy in European Territorial Cooperation Programmes. (Updated version, May 2013)

Questions & Answers. on e-cohesion Policy in European Territorial Cooperation Programmes. (Updated version, May 2013) Questions & Answers on e-cohesion Policy in European Territorial Cooperation Programmes (Updated version, May 2013) This fact sheet was drafted jointly by INTERACT and European Commission (DG Regional

More information

2 ND CALL FOR PROPOSALS 27 October 2008 30 January 2009

2 ND CALL FOR PROPOSALS 27 October 2008 30 January 2009 2 ND CALL FOR PROPOSALS 27 October 2008 30 January 2009 1. INTRODUCTION Authorities and stakeholders at local and regional level have a vital role to play in the achievement of the EU s strategies for

More information

Terms of reference first call for proposals

Terms of reference first call for proposals European Union European Regional Development Fund Sharing solutions for better regional policies Terms of reference first call for proposals 1. Introduction The European Union works to reduce disparities

More information

CERTIFICATES ISSUED BY EXTERNAL AUDITORS GUIDANCE NOTES FOR BENEFICIARIES AND AUDITORS

CERTIFICATES ISSUED BY EXTERNAL AUDITORS GUIDANCE NOTES FOR BENEFICIARIES AND AUDITORS CERTIFICATES ISSUED BY EXTERNAL AUDITORS GUIDANCE NOTES FOR BENEFICIARIES AND AUDITORS MATERIALS PREPARED BY THE WORKING GROUP ON CERTIFICATE ON THE METHODOLOGY UNDER FP7: DG RESEARCH AND INNOVATION DG

More information

Job profile for project manager in the JTS (Antenna Office) Bulgaria Turkey IPA Cross-border Programme November 2012 version JOB PROFILE

Job profile for project manager in the JTS (Antenna Office) Bulgaria Turkey IPA Cross-border Programme November 2012 version JOB PROFILE Job profile for project manager in the JTS (Antenna Office) Bulgaria Turkey IPA Cross-border Programme November 2012 version JOB PROFILE of Project Manager and Project Manager Assistant in the Joint Technical

More information

Guide for Applicants COSME calls for proposals 2015

Guide for Applicants COSME calls for proposals 2015 Guide for Applicants COSME calls for proposals 2015 CONTENTS I. Introduction... 3 II. Preparation of the proposal... 3 II.1. Relevant documents... 3 II.2. Participants... 4 Consortium coordinator... 4

More information

URBACT IMPLEMENTATION NETWORKS

URBACT IMPLEMENTATION NETWORKS URBACT IMPLEMENTATION NETWORKS URBACT in a nutshell European Territorial Cooperation programme (ETC) cofinanced by ERDF All 28 Member States as well as 2 Partner States (Switzerland and Norway) are eligible

More information

FRAMEWORK AGREEMENT BETWEEN THE SWISS FEDERAL COUNCIL AND THE GOVERNMENT OF THE REPUBLIC OF ESTONIA CONCERNING

FRAMEWORK AGREEMENT BETWEEN THE SWISS FEDERAL COUNCIL AND THE GOVERNMENT OF THE REPUBLIC OF ESTONIA CONCERNING non-official publication FRAMEWORK AGREEMENT BETWEEN THE SWISS FEDERAL COUNCIL AND THE GOVERNMENT OF THE REPUBLIC OF ESTONIA CONCERNING THE IMPLEMENTATION OF THE SWISS- ESTONIAN COOPERATION PROGRAMME TO

More information

PROJECT MANAGEMENT PLAN HEKLA

PROJECT MANAGEMENT PLAN HEKLA MANAGEMENT PLAN HEKLA CONTENT 1. Introduction --------------------------------------------------------------------------- 0 2. Project organisation and management --------------------------------------------

More information

Guide to Financial Issues relating to FP7 Indirect Actions

Guide to Financial Issues relating to FP7 Indirect Actions Guide to Financial Issues relating to FP7 Indirect Actions Version 28/02/2011 Disclaimer This guide is aimed at assisting beneficiaries. It is provided for information purposes only and its contents are

More information

DRAFT AMENDING BUDGET N 2 TO THE GENERAL BUDGET 2015

DRAFT AMENDING BUDGET N 2 TO THE GENERAL BUDGET 2015 EUROPEAN COMMISSION Brussels, 20.1.2015 COM(2015) 16 final DRAFT AMENDING BUDGET N 2 TO THE GENERAL BUDGET 2015 ACCOMPANYING THE PROPOSAL FOR A COUNCIL REGULATION AMENDING COUNCIL REGULATION (EU, EURATOM)

More information

COMMISSION OF THE EUROPEAN COMMUNITIES COMMUNICATION TO THE COMMISSION FROM MS HÜBNER

COMMISSION OF THE EUROPEAN COMMUNITIES COMMUNICATION TO THE COMMISSION FROM MS HÜBNER Final version of 23/04/2008 COMMISSION OF THE EUROPEAN COMMUNITIES COCOF 08/0022/02-EN Brussels, SEC(2007) COMMUNICATION TO THE COMMISSION FROM MS HÜBNER Guidelines on the Closure of Cohesion Fund and

More information

Science and Innovation Investment Fund (SIIF) Grant Scheme, 2nd Call. Reference: EuropeAid/131920/M/ACT/HR

Science and Innovation Investment Fund (SIIF) Grant Scheme, 2nd Call. Reference: EuropeAid/131920/M/ACT/HR IPA Component IIIc - Regional Competitiveness Operational Programnme 2007-2011 for Community Assistance under the IPA Regional Development Component in Croatia Science and Innovation Investment Fund (SIIF)

More information

In2LifeSciences Implementation Guidelines Insight and Collaboration Incentives 4 th Call

In2LifeSciences Implementation Guidelines Insight and Collaboration Incentives 4 th Call In2LifeSciences Implementation Guidelines Insight and Collaboration Incentives 4 th Call IN2LifeSciences - Guidelines for insight and collaboration incentive projects 1. Project execution The insight or

More information

The Marie Curie Actions FP7 Financial Guidelines

The Marie Curie Actions FP7 Financial Guidelines The Marie Curie Actions FP7 Financial Guidelines SPECIFIC PROVISIONS RELATED TO MARIE CURIE ACTIONS FINANCED UNDER THE FP7 "PEOPLE" PROGRAMME Part 3: projects funded in the 2007-2011 Work Programmes calls

More information

GRANT AGREEMENT for a: Project with multiple beneficiaries under the ERASMUS+ Programme 1. AGREEMENT NUMBER «AgreementNumber»

GRANT AGREEMENT for a: Project with multiple beneficiaries under the ERASMUS+ Programme 1. AGREEMENT NUMBER «AgreementNumber» GRANT AGREEMENT for a: Project with multiple beneficiaries under the ERASMUS+ Programme 1 AGREEMENT NUMBER «AgreementNumber» Centre for International Mobility CIMO PL 343 00531 Helsinki, The National Agency

More information

Official Journal of the European Union

Official Journal of the European Union 31.7.2006 L 210/25 COUNCIL REGULATION (EC) No 1083/2006 of 11 July 2006 laying down general provisions on the European Regional Development Fund, the European Social Fund and the Cohesion Fund and repealing

More information

H2020 Model Grant Agreement for Lump sum grants (H2020 MGA Lump sum Multi)

H2020 Model Grant Agreement for Lump sum grants (H2020 MGA Lump sum Multi) H2020 Model Grant Agreement for Lump sum grants (H2020 MGA Lump sum Multi) Version 1.0 9 June 2015 HISTORY OF CHANGES Version Publication date Changes 1.0 09.06.2015 Initial version 1 EUROPEAN COMMISSION

More information

Report on new irregularities

Report on new irregularities Annex 5 Template for irregularities reports EEA and Norwegian Financial Mechanisms 2009-2014 Report on new irregularities 1. Report from (Beneficiary State and Designated Entity) 2. Type of reporting (tick

More information

1.2. Programme area... 7. 1.3. Financing... 7

1.2. Programme area... 7. 1.3. Financing... 7 Table of Contents 0. Introduction: How to use the Programme Manual... 5 1. General information about the Baltic Sea Region Programme 2007-2013... 6 1.1. General objectives of the Programme... 6 1.2. Programme

More information

Ministry of Infrastructure Warsaw, 28.05.2008r..

Ministry of Infrastructure Warsaw, 28.05.2008r.. Ministry of Infrastructure POLISH STATE AID SCHEMES FOR AIR TRANSPORT, INTERMODAL TRANSPORT AND ITS Ministry of Infrastructure Projects of state aid schemes according to Infrastructure & Environment Operational

More information

PART 7: OVERVIEW ON PROJECT IMPLEMENTATION PRINCIPLES

PART 7: OVERVIEW ON PROJECT IMPLEMENTATION PRINCIPLES Applicants Manual for the period 2014 2020 Version 1 PART 7: OVERVIEW ON PROJECT IMPLEMENTATION PRINCIPLES edited by the Managing Authority/Joint Secretariat Budapest, Hungary, 2015 Disclaimer This document

More information

EUROPEAN COMMISSION RESEARCH EXECUTIVE AGENCY (REA) H2020 1 MODEL GRANT AGREEMENT FOR MARIE SKŁODOWSKA-CURIE INDIVIDUAL FELLOWSHIPS 2 (MSC-IF MONO)

EUROPEAN COMMISSION RESEARCH EXECUTIVE AGENCY (REA) H2020 1 MODEL GRANT AGREEMENT FOR MARIE SKŁODOWSKA-CURIE INDIVIDUAL FELLOWSHIPS 2 (MSC-IF MONO) EUROPEAN COMMISSION RESEARCH EXECUTIVE AGENCY (REA) Director H2020 1 MODEL GRANT AGREEMENT FOR MARIE SKŁODOWSKA-CURIE INDIVIDUAL FELLOWSHIPS 2 (MSC-IF MONO) Introductory remark MSC-IF Mono deviates from

More information

FRAMEWORK PARTNERSHIP AGREEMENT ON THE EUROPEAN INVESTMENT ADVISORY HUB. between the EUROPEAN UNION. and the EUROPEAN INVESTMENT BANK

FRAMEWORK PARTNERSHIP AGREEMENT ON THE EUROPEAN INVESTMENT ADVISORY HUB. between the EUROPEAN UNION. and the EUROPEAN INVESTMENT BANK I European investment Bank ^ ^, I i FRAMEWORK PARTNERSHIP AGREEMENT ON THE EUROPEAN INVESTMENT ADVISORY HUB between the EUROPEAN UNION and the EUROPEAN INVESTMENT BANK Brussels, 22 July 2015 This Agreement

More information

COMMISSION OF THE EUROPEAN COMMUNITIES. COMMISSION REGULATION (EC) No /..

COMMISSION OF THE EUROPEAN COMMUNITIES. COMMISSION REGULATION (EC) No /.. EN EN EN COMMISSION OF THE EUROPEAN COMMUNITIES Brussels, XX/XX/2007 COM(2006) XXX COMMISSION REGULATION (EC) No /.. of [ ] implementing Council Regulation (EC) No 1085/2006 establishing an instrument

More information

Negotiations feedback for successful project preparation. ERANIS workshop, 27.11.2007, Minsk

Negotiations feedback for successful project preparation. ERANIS workshop, 27.11.2007, Minsk Negotiations feedback for successful project preparation Negotiations procedure Feedback from the Commission on the project plan issues that need to be explained in more detail Request to formulate Annex

More information

APPLICATION INSTRUCTIONS

APPLICATION INSTRUCTIONS Version 1.1 APPLICATION INSTRUCTIONS Instructions for completing the Preparatory project call application form for the Northern Periphery and Arctic Programme 2014-2020 The application instructions are

More information

Amendments to the Financial Regulations and Financial Rules

Amendments to the Financial Regulations and Financial Rules EXECUTIVE BOARD EB132/44 132nd session 11 January 2013 Provisional agenda item 12.2 Amendments to the Financial Regulations and Financial Rules Report by the Secretariat 1. The Programme, Budget and Administration

More information

RULES FOR PARTICIPATION IN THE IMI JU COLLABORATIVE PROJECTS

RULES FOR PARTICIPATION IN THE IMI JU COLLABORATIVE PROJECTS Innovative Medicines Initiative IMI-GB-DEC-2012-12 RULES FOR PARTICIPATION IN THE IMI JU COLLABORATIVE PROJECTS OUTLINE 1. Definitions 2. Participation in an IMI JU collaborative project 2.1 General provisions

More information

Silvia Grandi ADRION Managing Authority Start-up team Coordinator

Silvia Grandi ADRION Managing Authority Start-up team Coordinator Silvia Grandi ADRION Managing Authority Start-up team Coordinator Content History Geography Finance Philosophy Engineering Management EU Macro Regional Strategies 2014-2020 2007-2013 Evolutions 2007-2013

More information

D E F I N I T I O N O F Q U A L I T Y C O N T R O L P R O C E D U R E

D E F I N I T I O N O F Q U A L I T Y C O N T R O L P R O C E D U R E D E F I N I T I O N O F Q U A L I T Y C O N T R O L P R O C E D U R E D 1.1 Document identifier: V-Must.net - D1.1 Definition of quality control procedure V.1.1 Due Date of Delivery to EC End of Month

More information

FRAMEWORK AGREEMENT BETWEEN THE GOVERNMENT OF THE REPUBLIC OF HUNGARY AND THE SWISS FEDERAL COUNCIL CONCERNING

FRAMEWORK AGREEMENT BETWEEN THE GOVERNMENT OF THE REPUBLIC OF HUNGARY AND THE SWISS FEDERAL COUNCIL CONCERNING FRAMEWORK AGREEMENT BETWEEN THE GOVERNMENT OF THE REPUBLIC OF HUNGARY AND THE SWISS FEDERAL COUNCIL CONCERNING THE IMPLEMENTATION OF THE SWISS- HUNGARIAN COOPERATION PROGRAMME TO REDUCE ECONOMIC AND SOCIAL

More information

MCIS Aggregate Claim Editor User Guide. Core system users

MCIS Aggregate Claim Editor User Guide. Core system users MCIS Aggregate Claim Editor User Guide Core system users TABLE OF CONTENTS INTRODUCTION... 3 HOW TO USE THIS GUIDE... 3 ABOUT AGGREGATE CLAIM EDITORS... 3 AGGREGATE CLAIM EDITOR TEAM LEADERS... 3 THE CLAIMS

More information

MAXIMISING BROADBAND CONNECTIVITY ACROSS THE EU USING EUROPEAN FUNDING FOR SATELLITE BROADBAND ACCESS

MAXIMISING BROADBAND CONNECTIVITY ACROSS THE EU USING EUROPEAN FUNDING FOR SATELLITE BROADBAND ACCESS SUMMARY: MAXIMISING BROADBAND CONNECTIVITY ACROSS THE EU USING EUROPEAN FUNDING FOR SATELLITE BROADBAND ACCESS - IMPLEMENTING A VOUCHER SCHEME - DECEMBER 2013 1. The European Commission wishes to maximise

More information

Guidance on Joint Action Plans

Guidance on Joint Action Plans EGESIF_14-0038-01 Guidance on Joint Action Plans Structural and Cohesion Funds 2014-20 Social Europe EGESIF_14-0038-01 Guidance on Joint Action Plans Structural and Cohesion Funds 2014-20 European Commission

More information

GRANT AGREEMENT FOR STUDIES ERASMUS+ 2016-2017

GRANT AGREEMENT FOR STUDIES ERASMUS+ 2016-2017 GRANT AGREEMENT FOR STUDIES ERASMUS+ 2016-2017 Linköping University (S LINKOPI01), SE-581 83 LINKÖPING, SWEDEN, and the student 1 Name Address (Street and postal address) Date of birth Number of completed

More information

Admin, Legal & Financial Issues All You Need to Know about Horizon 2020 Regulations

Admin, Legal & Financial Issues All You Need to Know about Horizon 2020 Regulations Admin, Legal & Financial Issues All You Need to Know about Horizon 2020 Regulations Marlen Damjanović, PhD National Contact Point Health & ICT Euresearch Head Office marlen.damjanovic@euresearch.ch phone:

More information

Contents and timeline of the first call of CENTRAL EUROPE 2020

Contents and timeline of the first call of CENTRAL EUROPE 2020 CENTRAL EUROPE Annual Conference, Vienna, 1 July 2014 Contents and timeline of the first call of CENTRAL EUROPE 2020 Luca Ferrarese Joint Secretariat Contents 1. 2007-2013 vs 2014-2020: What s new? 2.

More information

The Financial Management of your Culture sub-programme Project

The Financial Management of your Culture sub-programme Project The Financial Management of your Culture sub-programme Project Please note that this document is based on the e-tutorial provided by the Education, Audiovisual and Culture Executive Agency (EACEA) and

More information

CALL FOR PROPOSALS MARE/2014/04. Support measures for small-scale fishing

CALL FOR PROPOSALS MARE/2014/04. Support measures for small-scale fishing Ref. Ares(2015)3122272-24/07/2015 EUROPEAN COMMISSION Budget Central Financial Service Procurements, contracts, and grants CALL FOR PROPOSALS MARE/2014/04 Support measures for small-scale fishing Contents

More information

CHAPTER 3 ERDF GRANT OFFER LETTERS CONTENTS

CHAPTER 3 ERDF GRANT OFFER LETTERS CONTENTS CHAPTER 3 ERDF GRANT OFFER LETTERS CONTENTS SECTION Page INTRODUCTION... 2 THE COVERING LETTER... 2 Pre-conditions... 4 European Commission Requirements... 4 Changes to the project... 4 Audit and monitoring

More information

ANNEX VI MODEL TERMS OF REFERENCE FOR THE CERTIFICATE ON THE FINANCIAL STATEMENTS PART ï

ANNEX VI MODEL TERMS OF REFERENCE FOR THE CERTIFICATE ON THE FINANCIAL STATEMENTS PART ï '4. J ' S., --t r - i^v. ^l- ' 1 I Version of 18.11.2013 EUROPEAN COMMISSION DIRECTORATE-GENERAL FOR EDUCATION AND CULTURE Lifelong learning: higher education and international affairs Cooperation and

More information

EVALUATION GUIDE CALL FOR PROPOSALS 22/11 SUPPORT FOR THE DEVELOPMENT OF ON AND OFF-LINE INTERACTIVE WORKS

EVALUATION GUIDE CALL FOR PROPOSALS 22/11 SUPPORT FOR THE DEVELOPMENT OF ON AND OFF-LINE INTERACTIVE WORKS EVALUATION GUIDE CALL FOR PROPOSALS 22/11 SUPPORT FOR THE DEVELOPMENT OF ON AND OFF-LINE INTERACTIVE WORKS 1 INTRODUCTION 1. Aim of the Evaluation Guide The aim of the Evaluation Guide is: - to identify

More information

Cross-border Cooperation Programme Poland-Belarus-Ukraine 2007-2013. Guidelines on Preparation and Submission of Reports

Cross-border Cooperation Programme Poland-Belarus-Ukraine 2007-2013. Guidelines on Preparation and Submission of Reports Cross-border Cooperation Programme Poland-Belarus-Ukraine 2007-2013 Guidelines on Preparation and Submission of Reports INTRODUCTION... 4 Purpose and users of this guidelines... 4 Beneficiary s obligation

More information