CULVERTS: Design and Construction Considerations

Size: px
Start display at page:

Download "CULVERTS: Design and Construction Considerations"

Transcription

1 CULVERTS: Design and Construction Considerations

2 Bridges and Culverts New York State DOT, by statute and following the FHWA, defines a bridge as any structure carrying a highway over an obstruction which has an opening, measured along the centerline of the highway, in excess of 20. A similar structure having a centerline span of 20 or less is defined as a culvert.

3

4 This administrative definition does have significant implications. NYSDOT maintains a complete inventory of all bridges in the state, whether State, County, or Locally owned. All bridges are rigorously inspected and rated at intervals of no more than 2 years.

5 NYSDOT is working to develop an inventory of State-owned culverts. A few Counties and Towns inventory their culverts. The great majority of culverts are not inventoried. No uniform standards exist for culvert inspection. NYSDOT inspects State-owned large culverts (span > 5 ), 5 less rigorously than bridges, with a minimum frequency of once every 4 years.

6 Using these definitions, there are 12,663 bridges over water in New York State. There are an estimated 50,000 large (>5 span) culverts. There are an estimated 1,000,000 small culverts on the State, County and Local system excluding private structures.

7 The administrative definitions, though established by statute, are necessarily arbitrary and do not reflect common usage. A perhaps better distinction might be a structural one, based on the method of support.

8 A closed conduit stream crossing is self supporting. It distributes the load of its own weight, the fill above it, and the roadway and traffic, over the bottom of the structure, which is in contact with the soil. This type of support is simple and inexpensive, and with its large area of support is often a good choice in soils having weak bearing capacity.

9

10 An open bottomed structure, by contrast, must support these loads on a much smaller area. It requires foundations capable of dealing with the more concentrated loads, either on stronger soils (or rock) or on pile foundations, which add significantly to the cost of the structure. The smaller the structure, the greater the cost of the foundations in proportion to the total cost of the structure.

11 Superstructure Deck Abutment Pier Wing wall Piles Overbank Low-flow channel Footing

12 It is the policy of New York State to use the 50- year recurrence event (Q 50 discharge) as the design flow and the 100-year (Q 100 ) as the check flow for all highway crossings. Scour is evaluated for the Q 100 event except for Interstate highways For Interstates, scour is checked for the Q 500.

13 Design policy for bridges and bridge-sized culverts is to design the proposed structure to provide a minimum of 2 2 of freeboard over the design flood whenever possible, and to pass the check flood with reduced freeboard. Hydraulically, bridges are designed as open- channel flow. Flow is purely gravity-driven, and the water surface is unconstrained, determined only by the hydraulics of the flow.

14 Culverts are generally designed and analyzed using simplified, empirical relationships. Material roughness, length and size of the barrel determine friction losses, and end geometries are assigned inlet and outlet losses. These and other minor losses make up the total energy or hydraulic head needed to push water through the culvert. Culvert hydraulics assume an elevated headwater to supply this push.

15 Culverts are said to be in either inlet or outlet control. In inlet control the barrel can carry more water than the inlet will allow in. It is hydraulically inefficient, and results in supercritical (shallow, high-velocity) flow and hydraulic jumps,, which block fish movement.

16 Outlet control occurs when the inlet does not limit the flow through the culvert. Rather, it is controlled by the slope and the characteristics of the barrel. Flow in a culvert in outlet control will be subcritical, presenting less of a barrier to fish passage. In either case, either the inlet, the outlet or both may be submerged.

17 It can be difficult to determine whether a proposed culvert design will be in inlet or outlet control. A culvert may also change from one to the other over a range of discharges. For these reasons, culvert design usually involves analysis of the proposed design for both conditions, and assuming the worst case, whichever produces the greater headwater for a given design discharge.

18 Culvert-sized structures use the same design flows as bridges. Since culverts are designed to function in pressure, there is no freeboard target. To prevent overtopping, however, the headwater at design discharge is required to be a minimum of 2 2 below the shoulder elevation of the roadway, and headwater depth cannot exceed 1.5 times the culvert rise.

19 Issues relating to closed-cell cell culverts: Material limitations corrosion, abrasion, roughness, shape and size availability Structural limitations maximum span, cover depth, excavation needs Connectivity breaks physical barriers, hydraulic barriers, habitat interruptions

20 Open-bottomed Culverts The major types of open-bottomed structures used by NYSDOT are 3-sided 3 rigid frames (e.g. Con/Span, Hy-Span Span ) ) and arches, either concrete or metal (steel or aluminum). Some counties and towns also use sheet pile and slab culverts, or block abutment structures.

21

22

23 The important thing to remember about open-bottom culverts is that structurally, they are bridges. They require the same type of separate foundation, capable of supporting concentrated loads and resisting scour, as any other bridge.

24 For State-owned installations, this means they must be founded on competent rock, or on a pile foundation designed to accommodate predicted scour, unless they span the entire 100- year floodplain.

25 Available sizes: Type Span Rise Min Max Min Max Con/Span Hy-Span PC Arches (Bebo, Kistner, etc.)

26 An additional constraint on size is the span/rise ratio. For 3-sided 3 frames, NYSDOT prefers to limit spans to no more than 4 times the rise. Greater ratios increase top slab moments and lateral foundation loads to the point where they are impractical or uneconomical to construct. Thus, an increase in desired span frequently results in an increased rise as well.

27 Arches, too, typically come in a limited range of rises for a given span. For example, a Bebo arch having a span of 29 to 30 must have a rise between 8.5 and If the roadway embankment requires a shorter vertical rise, a shorter span must be used or the embankment raised.

28 Existing intersections, driveways, etc. may constrain raises in roadway profile. In addition, since the highway embankment must have at least a 1V:2H slope, each 1 1 rise in profile means a 4 4 widening of the road s s footprint, which can lead to ROW problems, and encroachment of fill onto surrounding areas. And it requires a 4 4 lengthening of the culvert. The additional highway work also adds greatly to project expense.

29 Depth of cover may also be a concern. Arches will support much deeper cover than will simple frames. Some structures, notably metal shapes that lack the structural strength of concrete, may require at least a certain minimum cover depth, to distribute loads and prevent crushing.

30 It is vital that designers use the appropriate specification number for 3-sided 3 structures (Sec. 562) to assure proper transport. During construction as well, care must be taken in handling the units. Open-bottomed units, until properly placed and backfilled, are inherently less stable than closed boxes. Swaying or setting them on end can result in damage.

31 Benefits of 3-sided Structures: Ecological health Recreation industry Economic output of NY freshwater fishing: $755M (American Sportfishing Association, 2006 data) Mitigation cost savings Less need for routine maintenance (debris and sediment removal) May ease permitting/regulatory concerns

32 Costs High initial cost Structure Foundation Transport / handling Labor

33 Construction Issues with 3-Sided 3 Structures Excavation often reduces this item Water management may allow simpler dewatering, diversion structures Site operability requires more room for equipment Schedule differences Takes longer than traditional box culverts Much faster (and more easily staged) than bridges

34 Cost Comparison: 3-sided 3 vs. 4-sided4 (span 24 ft x rise 7 ft, same location) Select structure fill: 19% cost reduction Concrete piles and pile driving equip: add l items Footing concrete: add l item Concrete for structures: 15% cost reduction Reinforced concrete span units: 124% cost increase Mobilization: 59% cost increase Total culvert cost increased by 59% or $227K 4-sided: $387K 3-sided: $614K

35 Stream Simulation Sediment size match range in natural channel at surface Channel cross-section section fix with larger stones Channel configuration mimic natural stream, allow room for self-adjustment

36 (Ken Bates, 2006) Stream Simulation Cross Section

37 Stream Simulation Open-bottom structures Bed is created within the assembled culvert

38 Photo Credit: Mendocino Co. DPW

39 Streambed Simulation Open-bottom structures Bed is created within the assembled culvert, or Simulated bed is created between the footings before precast units are placed

40 Photo Credit: US Forest Service

41 Streambed Simulation Open-bottom structures Bed is created within the assembled culvert, or Simulated bed is created between the footings before precast units are placed Embedded 4-sided structures Bed is created within the assembled culvert, or Bed material is allowed to naturally fill the embedded portion up to streambed grade

42 Summary Closed-cell culverts are generally economical, easily designed and installed, but require that proper care be used to assure they do not present unacceptable barriers to fish and wildlife. Open-bottomed structures avoid many of the environmental pitfalls, but are likely to be more expensive, more limited in applicability, and require greater care in handling.

43 Contact Information George Long, PE (Structures-Hydraulics) Brandon Greco (Environmental Science Bur.)

Safe & Sound Bridge Terminology

Safe & Sound Bridge Terminology Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries

More information

BRIDGES ARE relatively expensive but often are

BRIDGES ARE relatively expensive but often are Chapter 10 Bridges Chapter 10 Bridges Bridg Bridges -- usually the best, but most expensive drainage crossing structure. Protect bridges against scour. BRIDGES ARE relatively expensive but often are the

More information

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile

Chapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile Chapter 3 CULVERTS Description A culvert is a closed conduit used to convey water from one area to another, usually from one side of a road to the other side. Importance to Maintenance & Water Quality

More information

Design of Bridges. Introduction. 3 rd to 4 th July 2012. Lecture for SPIN Training at the University of Dar es Salaam

Design of Bridges. Introduction. 3 rd to 4 th July 2012. Lecture for SPIN Training at the University of Dar es Salaam Design of Bridges Introduction 3 rd to 4 th July 2012 1 FUNCTION OF A BRIDGE To connect two communities which are separated by streams, river, valley, or gorge, etc. 2 EVOLUTION OF BRIDGES 1. Log Bridge

More information

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL

June 2007 CHAPTER 7 - CULVERTS 7.0 CHAPTER 7 - CULVERTS 7.1 GENERAL 7.0 7.1 GENERAL For the purpose of this manual, culverts are defined as structures that are completely surrounded by soil and located below the surface of the roadway parallel to the general direction

More information

CITY UTILITIES DESIGN STANDARDS MANUAL

CITY UTILITIES DESIGN STANDARDS MANUAL CITY UTILITIES DESIGN STANDARDS MANUAL Book 2 (SW) SW9 June 2015 SW9.01 Purpose This Chapter provides information for the design of open channels for the conveyance of stormwater in the City of Fort Wayne.

More information

Outlet stabilization structure

Outlet stabilization structure Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural

More information

DRAINAGE CRITERIA MANUAL (V. 2) CULVERTS CONTENTS

DRAINAGE CRITERIA MANUAL (V. 2) CULVERTS CONTENTS DRAINAGE CRITERIA MANUAL (V. 2) CONTENTS Section Page CU 1.0 INTRODUCTION AND OVERVIEW... 1 1.1 Required Design Information... 3 1.1.1 Discharge... 4 1.1.2 Headwater... 4 1.1.3 Tailwater... 5 1.1.4 Outlet

More information

How To Check For Scour At A Bridge

How To Check For Scour At A Bridge Case Studies Bridge Scour Inspection and Repair Edward P. Foltyn, P.E. Senior Hydraulic Engineer ODOT Bridge Unit 2013 PNW Bridge Inspectors Conference April 2013 REFERENCES Stream Stability at Highway

More information

Topic 8: Open Channel Flow

Topic 8: Open Channel Flow 3.1 Course Number: CE 365K Course Title: Hydraulic Engineering Design Course Instructor: R.J. Charbeneau Subject: Open Channel Hydraulics Topics Covered: 8. Open Channel Flow and Manning Equation 9. Energy,

More information

RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.

RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies. RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.htm#storm Definition: A permanent, erosion-resistant ground cover

More information

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1

Index. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1 6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT

More information

Objectives and Purpose...Page 1 Open Bottom Arch - Flow Model...Page 1 The Pros and Cons of Metal Arch Culverts...Page 2 Positive Features of Arch

Objectives and Purpose...Page 1 Open Bottom Arch - Flow Model...Page 1 The Pros and Cons of Metal Arch Culverts...Page 2 Positive Features of Arch Objectives and Purpose...Page 1 Open Bottom Arch - Flow Model...Page 1 The Pros and Cons of Metal Arch Culverts...Page 2 Positive Features of Arch Culverts....Page 2 Negative features of Arch Culverts...Page

More information

REINFORCED CONCRETE. Reinforced Concrete Design. A Fundamental Approach - Fifth Edition. Walls are generally used to provide lateral support for:

REINFORCED CONCRETE. Reinforced Concrete Design. A Fundamental Approach - Fifth Edition. Walls are generally used to provide lateral support for: HANDOUT REINFORCED CONCRETE Reinforced Concrete Design A Fundamental Approach - Fifth Edition RETAINING WALLS Fifth Edition A. J. Clark School of Engineering Department of Civil and Environmental Engineering

More information

CHAPTER 9 CULVERTS TABLE OF CONTENTS. CDOT Drainage Design Manual

CHAPTER 9 CULVERTS TABLE OF CONTENTS. CDOT Drainage Design Manual CHAPTER 9 CULVERTS TABLE OF CONTENTS 9.1 INTRODUCTION...4 9.1.1 Definition...4 9.1.2 Purpose of Use...5 9.1.3 Concepts and Definitions...5 9.1.4 Symbols...8 9.1.5 Classification...10 9.1.6 Geometry...10

More information

SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS

SECTION 08000 STORM DRAINAGE TABLE OF CONTENTS SECTION 08000 STORM DRAINAGE 08010 DESIGN A. Location B. Sizing TABLE OF CONTENTS 08020 MATERIALS A. Pipe Materials B. Structure Materials C. Installation D. Inlets and Outlets 08030 INSPECTIONS AND TESTING

More information

CHAPTER 9 CHANNELS APPENDIX A. Hydraulic Design Equations for Open Channel Flow

CHAPTER 9 CHANNELS APPENDIX A. Hydraulic Design Equations for Open Channel Flow CHAPTER 9 CHANNELS APPENDIX A Hydraulic Design Equations for Open Channel Flow SEPTEMBER 2009 CHAPTER 9 APPENDIX A Hydraulic Design Equations for Open Channel Flow Introduction The Equations presented

More information

IH-635 MANAGED LANES PROJECT, SEG. 3.2

IH-635 MANAGED LANES PROJECT, SEG. 3.2 IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,

More information

Bridge Type Selection

Bridge Type Selection Bridge Type Selection The major consideration for bridge type selection for bridges on the State Aid system is initial cost. Future maintenance costs, construction time, and location are considered when

More information

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS

State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary

More information

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL. STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill

More information

1. Carry water under the canal 2. Carry water over the canal 3. Carry water into the canal

1. Carry water under the canal 2. Carry water over the canal 3. Carry water into the canal Lecture 21 Culvert Design & Analysis Much of the following is based on the USBR publication: Design of Small Canal Structures (1978) I. Cross-Drainage Structures Cross-drainage is required when a canal

More information

CHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES

CHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR CHAPTER 3A Environmental Guidelines for STREAM CROSSING BY ALL-TERRAIN VEHICLES WATER RESOURCES MANAGEMENT DIVISION Water Investigations

More information

BEST PRACTICE GUIDELINES FOR CULVERT LINER SELECTION

BEST PRACTICE GUIDELINES FOR CULVERT LINER SELECTION BEST PRACTICE GUIDELINES FOR CULVERT LINER SELECTION GENERAL Rehabilitation of culverts with pipe liners is one of several methods available for extending the life of an existing culvert. It is often cost

More information

2.0 BASIC CONCEPTS OF OPEN CHANNEL FLOW MEASUREMENT

2.0 BASIC CONCEPTS OF OPEN CHANNEL FLOW MEASUREMENT 2.0 BASIC CONCEPTS OF OPEN CHANNEL FLOW MEASUREMENT Open channel flow is defined as flow in any channel where the liquid flows with a free surface. Open channel flow is not under pressure; gravity is the

More information

CHAPTER 9 CULVERTS 2005

CHAPTER 9 CULVERTS 2005 CHAPTER 9 CULVERTS 2005 Culverts 9-1 Chapter Table of Contents 9.1 - Introduction 9-5 9.2 - Policy and Practice 9-5 9.3 - Large, Medium and Small Culverts 9-8 9.4 - Sources of Information 9-8 9.5 - Culvert

More information

2011 HYDRAULICS MANUAL

2011 HYDRAULICS MANUAL STATE OF LOUISIANA DEPARTMENT OF TRANSPORTATION AND DEVELOPMENT P.O. Box 94245 Baton Rouge, Louisiana 70804-9245 http://www.dotd.la.gov/ HYDRAULICS MANUAL Hydraulics (225) 379-1306 PREFACE The following

More information

PRECAST CONCRETE BOX CULVERTS

PRECAST CONCRETE BOX CULVERTS PRECAST CONCRETE BOX CULVERTS OUTLINE Introduction Applications Manufacturing Methods Design Procedures & Joints Installation Quality Summary INTRODUCTION Four-sided culverts are typically referred to

More information

Lecture 22 Example Culvert Design Much of the following is based on the USBR technical publication Design of Small Canal Structures (1978)

Lecture 22 Example Culvert Design Much of the following is based on the USBR technical publication Design of Small Canal Structures (1978) Lecture 22 Example Culvert Design Much of the following is based on the USBR technical publication Design of Small Canal Structures (1978) I. An Example Culvert Design Design a concrete culvert using the

More information

Riprap-lined Swale (RS)

Riprap-lined Swale (RS) Riprap-lined Swale (RS) Practice Description A riprap-lined swale is a natural or constructed channel with an erosion-resistant rock lining designed to carry concentrated runoff to a stable outlet. This

More information

Travel Time. Computation of travel time and time of concentration. Factors affecting time of concentration. Surface roughness

Travel Time. Computation of travel time and time of concentration. Factors affecting time of concentration. Surface roughness 3 Chapter 3 of Concentration and Travel Time Time of Concentration and Travel Time Travel time ( T t ) is the time it takes water to travel from one location to another in a watershed. T t is a component

More information

Table 4.9 Storm Drain Inlet Protetion Applicable for

Table 4.9 Storm Drain Inlet Protetion Applicable for BMP C220: Storm Drain Inlet Protection Purpose To prevent coarse sediment from entering drainage systems prior to permanent stabilization of the disturbed area. Conditions of Use Type of Inlet Protection

More information

Nebraska Department of Roads Drainage and Erosion Control Manual December 2011 Appendix C: Pipe Material Policy Page C-1 PIPE MATERIAL POLICY

Nebraska Department of Roads Drainage and Erosion Control Manual December 2011 Appendix C: Pipe Material Policy Page C-1 PIPE MATERIAL POLICY Appendix C: Pipe Material Policy Page C-1 PIPE MATERIAL POLICY Policy: This policy will replace all previous policies regarding the selection of pipe material for cross drains, drive pipe, drop pipe, storm

More information

Muddy River Flood Risk Management & Environmental Restoration Project Phase 1 Construction Activities Next 90 Days August 2015

Muddy River Flood Risk Management & Environmental Restoration Project Phase 1 Construction Activities Next 90 Days August 2015 Muddy River Flood Risk Management & Environmental Restoration Project Phase 1 Construction Activities Next 90 Days August 2015 General: The Muddy River Flood Risk Management (FRM) & Environmental Restoration

More information

SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST

SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST For permanent structures per Delaware SCS Pond Code 378 and Delaware Sediment and Stormwater Regulations KEY PROJECT INFORMATION Item meets standard

More information

DESCRIPTION OF WORK:

DESCRIPTION OF WORK: DEPARTMENT OF PUBLIC WORKS COUNTY OF HENRICO P.O. BOX 27032 RICHMOND, VIRGINIA 23273 PERMIT NO. One (1) copy of application and four (4) copies of plans are hereby made to the Director of Public Works

More information

CHAPTER 5. Storm Sewer

CHAPTER 5. Storm Sewer CHAPTER 5 Storm Sewer A. Introduction All proposed developments shall have a properly designed and constructed storm water conveyance system. This chapter deals only with the conveyance system. Storm water

More information

STORM DRAINS CHAPTER 7

STORM DRAINS CHAPTER 7 CHAPTER 7 Chapter 7 - Storm Drains A storm drain is a drainage system that conveys water or stormwater, consisting of two or more pipes in a series connected by one or more structures. Storm drains collect

More information

Prattsville Berm Removal Project. 1.0 Project Location

Prattsville Berm Removal Project. 1.0 Project Location Prattsville Berm Removal Project 1.0 Project Location The project site is located between the New York State Route 23 Bridge over the Schoharie Creek and the Schoharie Reservoir. The restoration plan encompassed

More information

Lecture 24 Flumes & Channel Transitions. I. General Characteristics of Flumes. Flumes are often used:

Lecture 24 Flumes & Channel Transitions. I. General Characteristics of Flumes. Flumes are often used: Lecture 24 Flumes & Channel Transitions I. General Characteristics of Flumes Flumes are often used: 1. Along contours of steep slopes where minimal excavation is desired 2. On flat terrain where it is

More information

Emergency Spillways (Sediment basins)

Emergency Spillways (Sediment basins) Emergency Spillways (Sediment basins) DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short-Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]

More information

Appendix 4-C. Open Channel Theory

Appendix 4-C. Open Channel Theory 4-C-1 Appendix 4-C Open Channel Theory 4-C-2 Appendix 4.C - Table of Contents 4.C.1 Open Channel Flow Theory 4-C-3 4.C.2 Concepts 4-C-3 4.C.2.1 Specific Energy 4-C-3 4.C.2.2 Velocity Distribution Coefficient

More information

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination

National Council of Examiners for Engineering and Surveying. Principles and Practice of Engineering Structural Examination Structural Effective Beginning with the April 2011 The structural engineering exam is a breadth and exam examination offered in two components on successive days. The 8-hour Vertical Forces (Gravity/Other)

More information

HUDSON RIVER-BLACK RIVER REGULATING DISTRICT BOARD MEETING JUNE 10, 2014

HUDSON RIVER-BLACK RIVER REGULATING DISTRICT BOARD MEETING JUNE 10, 2014 HUDSON RIVER-BLACK RIVER REGULATING DISTRICT BOARD MEETING JUNE 10, 2014 PRESENTATION TOPICS Analysis Objectives Analysis Dam Removal Plan Dam Remediation Plan Effects Analysis Permit Requirements Decision

More information

TENNESSEE GAS PIPELINE COMPANY, L.L.C.

TENNESSEE GAS PIPELINE COMPANY, L.L.C. TENNESSEE GAS PIPELINE COMPANY, L.L.C. HYDROLOGIC & HYDRAULIC CALCULATIONS FOR WATERBODIES CROSSED BY CONNECTICUT PIPELINE EXPANSION PROJECT CONNECTICUT LOOP Submitted by: Tennessee Gas Pipeline Company,

More information

Coldwater Heritage Partnership Implementation Grant Final Report Morrison Run Watershed Restoration Project Western Pennsylvania Conservancy Project Summary The goal of the Morrison Run Watershed Restoration

More information

Open Channel Flow 2F-2. A. Introduction. B. Definitions. Design Manual Chapter 2 - Stormwater 2F - Open Channel Flow

Open Channel Flow 2F-2. A. Introduction. B. Definitions. Design Manual Chapter 2 - Stormwater 2F - Open Channel Flow Design Manual Chapter 2 - Stormwater 2F - Open Channel Flow 2F-2 Open Channel Flow A. Introduction The beginning of any channel design or modification is to understand the hydraulics of the stream. The

More information

Role of Underwater Substructure Inspections in Bridge Management

Role of Underwater Substructure Inspections in Bridge Management Role of Underwater Substructure Inspections in Bridge Management R. RICHARD AVENT MOHAMED ALAWADY DAVID J. MUKAI Louisiana State University INTRODUCTION In the past, the condition of underwater substructures

More information

Work Breakdown Structure Element Dictionary. Final Design

Work Breakdown Structure Element Dictionary. Final Design Initiation FD 4.1 Initiation encompasses deliverables associated with the development, implementation and control of the project s schedule, budget and scope. The lead office develops these project parameters

More information

Section 402. STORM SEWERS

Section 402. STORM SEWERS 402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide

More information

Chapter 4 SUBSURFACE INVESTIGATION GUIDELINES

Chapter 4 SUBSURFACE INVESTIGATION GUIDELINES Chapter 4 SUBSURFACE INVESTIGATION GUIDELINES Final SCDOT GEOTECHNICAL DESIGN MANUAL August 2008 Table of Contents Section Page 4.1 Introduction...4-1 4.2 Subsurface Investigation...4-2 4.2.1 Preliminary

More information

3.1 Historical Considerations

3.1 Historical Considerations 3. Recommended Scope of Bridge improvements 3.1 Historical Considerations In the fall of 2000, an outside consultant, Fraser Design, suggested that the existing 4 th St. Bridge is potentially eligible

More information

GENERAL PERMIT BWEW-GP-11 MAINTENANCE, TESTING, REPAIR, REHABILITATION, OR REPLACEMENT OF WATER OBSTRUCTIONS AND ENCROACHMENTS

GENERAL PERMIT BWEW-GP-11 MAINTENANCE, TESTING, REPAIR, REHABILITATION, OR REPLACEMENT OF WATER OBSTRUCTIONS AND ENCROACHMENTS COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION BUREAU OF WATERWAYS ENGINEERING AND WETLANDS GENERAL PERMIT BWEW-GP-11 MAINTENANCE, TESTING, REPAIR, REHABILITATION, OR REPLACEMENT OF

More information

Retaining Wall Global Stability & AASHTO LRFD Unnecessary, Unreasonable Guideline Changes Result in Huge Wastes of Money at Some Wall Locations

Retaining Wall Global Stability & AASHTO LRFD Unnecessary, Unreasonable Guideline Changes Result in Huge Wastes of Money at Some Wall Locations Retaining Wall Global Stability & AASHTO LRFD Unnecessary, Unreasonable Guideline Changes Result in Huge Wastes of Money at Some Wall Locations The implementation of the AASHTO LRFD Bridge Design Specifications

More information

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe

TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TN 5.14 February 2010 Introduction It may be at times necessary, in an aging infrastructure, to rehabilitate drainage and sanitary lines

More information

5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES

5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES 5.0 OVERVIEW OF FLOOD DAMAGE REDUCTION MEASURES Flood damage reduction consists of two basic techniques structural and non-structural. Structural methods modify the flood and take the flood away from people

More information

The unit costs are based on the trend line of the 3 low bids for the average quantity.

The unit costs are based on the trend line of the 3 low bids for the average quantity. Page 1 of 8 COST ESTIMATE GENERAL INSTRUCTIONS The unit costs are based on the trend line of the 3 low bids for the average quantity. Apply the Unit Costs to ordinary structures. Unit Costs should generally

More information

Pipeline design. concrete for life

Pipeline design. concrete for life Pipeline design concrete for life Pipeline Design Pipeline design - hydraulic Graph showing relative velocity and discharge in a circular pipe for any depth of flow 1.0 0.9 0.8 0.7 Proportional depth of

More information

Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir. Presented By: Doug Stachler, P.E.

Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir. Presented By: Doug Stachler, P.E. Rehabilitation of the Red Bank Road Bridge over Hoover Reservoir Presented By: Doug Stachler, P.E. Project Organization Owner Delaware County Engineers Office Design Consultant CH2M HILL Contractor Double

More information

SECTION 7- STORM SEWER

SECTION 7- STORM SEWER SECTION 7- STORM SEWER 7.1. STORM SEWERS.... 7-1 7.2. SUMP DRAINS... 7-3 7.3. CATCH BASINS... 7-3 7.4. MANHOLES... 7-4 7.5. STORM SEWER CALCULATIONS... 7-4 7.6. CULVERTS AND BRIDGES... 7-5 7.7. OPEN CHANNELS...

More information

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM Swaminathan Srinivasan, P.E., M.ASCE H.C. Nutting/Terracon David Tomley, P.E., M.ASCE KZF Design Delivering Success for

More information

SE-10 STORM DRAIN INLET PROTECTION. Objectives

SE-10 STORM DRAIN INLET PROTECTION. Objectives STORM DRAIN INLET PROTECTION SE-10 Objectives Erosion Control - EC Sediment Control - SE Tracking Control - TC Wind Erosion Control - WE Non-Storm Water Management - NS Waste and Materials Management -

More information

Section 2100-Trenching and Tunneling

Section 2100-Trenching and Tunneling SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial

More information

Backwater Rise and Drag Characteristics of Bridge Piers under Subcritical

Backwater Rise and Drag Characteristics of Bridge Piers under Subcritical European Water 36: 7-35, 11. 11 E.W. Publications Backwater Rise and Drag Characteristics of Bridge Piers under Subcritical Flow Conditions C.R. Suribabu *, R.M. Sabarish, R. Narasimhan and A.R. Chandhru

More information

Storm Drainage Systems 11.9-1

Storm Drainage Systems 11.9-1 Storm Drainage Systems 11.9-1 11.9 Gutter Flow Calculations 11.9.1 Introduction Gutter flow calculations are necessary in order to relate the quantity of flow (Q) in the curbed channel to the spread of

More information

DANIELS RUN STREAM RESTORATION, FAIRFAX, VIRGINIA: FLOODPLAIN ANALYSIS REPORT

DANIELS RUN STREAM RESTORATION, FAIRFAX, VIRGINIA: FLOODPLAIN ANALYSIS REPORT DANIELS RUN STREAM RESTORATION, FAIRFAX, VIRGINIA: FLOODPLAIN ANALYSIS REPORT By: Conor C. Shea Stream Habitat Assessment and Restoration Program U.S. Fish and Wildlife Service CBFO-S07-01 Prepared in

More information

2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS

2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS 2006-2008 MHD BRIDGE SECTION WEIGHTED AVERAGE UNIT PRICES GUIDELINES FOR THE USE OF THE WEIGHTED AVERAGE UNIT PRICE TABULATION SHEETS GENERAL 10/16/2008 The listed average unit prices are based on the

More information

What is the most obvious difference between pipe flow and open channel flow????????????? (in terms of flow conditions and energy situation)

What is the most obvious difference between pipe flow and open channel flow????????????? (in terms of flow conditions and energy situation) OPEN CHANNEL FLOW 1 3 Question What is the most obvious difference between pipe flow and open channel flow????????????? (in terms of flow conditions and energy situation) Typical open channel shapes Figure

More information

Analysis of the Interstate 10 Twin Bridge s Collapse During Hurricane Katrina

Analysis of the Interstate 10 Twin Bridge s Collapse During Hurricane Katrina Analysis of the Interstate 0 Twin Bridge s Collapse During Hurricane Katrina By Genda Chen, Emitt C. Witt III, David Hoffman, Ronaldo Luna, and Adam Sevi The Interstate 0 Twin Span Bridge over Lake Pontchartrain

More information

Stream Rehabilitation Concepts, Guidelines and Examples. Objectives. Pierre Y. Julien. Three Laws of Stream Restoration

Stream Rehabilitation Concepts, Guidelines and Examples. Objectives. Pierre Y. Julien. Three Laws of Stream Restoration Stream Rehabilitation Concepts, Guidelines and Examples Pierre Y. Julien Wuhan 2005 Objectives Part I - Stream restoration and rehabilitation: 1. Present and discuss important concepts, laws, criteria

More information

CHAPTER 2 HYDRAULICS OF SEWERS

CHAPTER 2 HYDRAULICS OF SEWERS CHAPTER 2 HYDRAULICS OF SEWERS SANITARY SEWERS The hydraulic design procedure for sewers requires: 1. Determination of Sewer System Type 2. Determination of Design Flow 3. Selection of Pipe Size 4. Determination

More information

5 ALTERNATIVE SOLUTIONS AND EVALUATION

5 ALTERNATIVE SOLUTIONS AND EVALUATION Page 23 5 ALTERNATIVE SOLUTIONS AND EVALUATION The process used for the assessment and evaluation of the alternatives follows the procedures of the Municipal Class EA, as described below: Identify a reasonable

More information

BRIDGE SCOUR INVESTIGATION: DEVELOPING A SCREENING AND HYDRAULIC VULNERABILITY RATING SYSTEM FOR BRIDGES B.HERON 1 & C.BOWE 2

BRIDGE SCOUR INVESTIGATION: DEVELOPING A SCREENING AND HYDRAULIC VULNERABILITY RATING SYSTEM FOR BRIDGES B.HERON 1 & C.BOWE 2 BRIDGE SCOUR INVESTIGATION: DEVELOPING A SCREENING AND HYDRAULIC VULNERABILITY RATING SYSTEM FOR BRIDGES B.HERON 1 & C.BOWE 2 1 O Connor Sutton Cronin Consulting Engineers, Dublin, Ireland 2 Iarnród Éireann,

More information

SECTION 1 GENERAL REQUIREMENTS

SECTION 1 GENERAL REQUIREMENTS Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,

More information

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department

Land Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth

More information

SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02530 STORM DRAINAGE STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02530-1 of 5 SECTION 02530 STORM DRAINAGE STRUCTURES 02530.01 GENERAL A. Description Storm drainage structure construction shall include, but not necessarily be limited to, furnishing and installing or

More information

City of Shelbyville Site Inspection Checklist

City of Shelbyville Site Inspection Checklist City of Shelbyville Site Inspection Checklist General Information Project Name: KYR10 Permit Number: Date: Project Location: Contractor: Conractor Representative: Inspector's Name: Title: Signature : Weather

More information

Floodplain Hydraulics! Hydrology and Floodplain Analysis Dr. Philip Bedient

Floodplain Hydraulics! Hydrology and Floodplain Analysis Dr. Philip Bedient Floodplain Hydraulics! Hydrology and Floodplain Analysis Dr. Philip Bedient Open Channel Flow 1. Uniform flow - Manning s Eqn in a prismatic channel - Q, V, y, A, P, B, S and roughness are all constant

More information

CODE OF PRACTICE - VOLUME TWO - TRAIN SYSTEM [CP2] TRANSADELAIDE INFRASTRUCTURE SERVICES. Issue: 2 Date: 26/09/08 Page: 1 of 21

CODE OF PRACTICE - VOLUME TWO - TRAIN SYSTEM [CP2] TRANSADELAIDE INFRASTRUCTURE SERVICES. Issue: 2 Date: 26/09/08 Page: 1 of 21 Issue: 2 Date: 26/09/08 Page: 1 of 21 TRACK AND CIVIL INFRASTRUCTURE CODE OF PRACTICE VOLUME TWO - TRAIN SYSTEM [CP2] DRAINAGE 2004 No part of this document may be reproduced without prior written consent

More information

CHAPTER 4 STORM DRAINAGE SYSTEMS

CHAPTER 4 STORM DRAINAGE SYSTEMS CHAPTER 4 STORM DRAINAGE SYSTEMS 4.1 Overview... 4-1 4.1.1 Introduction... 4-1 4.1.2 Inlet Definition... 4-1 4.1.3 Criteria... 4-1 4.2 Pavement Drainage... 4-2 4.2.1 Introduction... 4-2 4.2.2 Storm Drain

More information

General Permit for Activities Promoting Waterway - Floodplain Connectivity [working title]

General Permit for Activities Promoting Waterway - Floodplain Connectivity [working title] General Permit for Activities Promoting Waterway - Floodplain Connectivity [working title] Purpose These rules set forth the conditions under which a person may, without an individual removal-fill permit

More information

Control filling, grading, dredging, and other development which may increase erosion or flood damage; and

Control filling, grading, dredging, and other development which may increase erosion or flood damage; and ARTICLE 16. FLOOD DAMAGE PREVENTION Section 16-1: Findings of Fact The flood hazard areas of the Town of Lillington are subject to periodic inundation which results in loss of life and property, health

More information

Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains

Module 7: Hydraulic Design of Sewers and Storm Water Drains. Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains 1 P age Module 7: Hydraulic Design of Sewers and Storm Water Drains Lecture 7 : Hydraulic Design of Sewers and Storm Water Drains 2 P age 7.1 General Consideration Generally, sewers are laid at steeper

More information

SUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION:

SUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION: September 22, 2009 Updated November 16, 2009 SUPPLEMENTAL SPECIFICATIONS CROSS SLOPE VERIFICATION: 1. DESCRIPTION: The cross slopes of the roadway are to be constructed as detailed in the plans and within

More information

Chapter 9. Steady Flow in Open channels

Chapter 9. Steady Flow in Open channels Chapter 9 Steady Flow in Open channels Objectives Be able to define uniform open channel flow Solve uniform open channel flow using the Manning Equation 9.1 Uniform Flow in Open Channel Open-channel flows

More information

Experiment (13): Flow channel

Experiment (13): Flow channel Introduction: An open channel is a duct in which the liquid flows with a free surface exposed to atmospheric pressure. Along the length of the duct, the pressure at the surface is therefore constant and

More information

Aging sewer pipes buried in the Bow River bed, from the foot of Muskrat Street to Glen Avenue must be replaced A raised crossing pipes crossing over

Aging sewer pipes buried in the Bow River bed, from the foot of Muskrat Street to Glen Avenue must be replaced A raised crossing pipes crossing over ewer utility crossing pedestrian bridge Aging sewer pipes buried in the Bow River bed, from the foot of Muskrat Street to Glen Avenue must be replaced A raised crossing pipes crossing over the river at

More information

Presentation to NYSAMPO, June 2015 Steve Wilcox, P.E., Director, Maintenance Program Planning Bureau NYSDOT

Presentation to NYSAMPO, June 2015 Steve Wilcox, P.E., Director, Maintenance Program Planning Bureau NYSDOT Presentation to NYSAMPO, June 2015 Steve Wilcox, P.E., Director, Maintenance Program Planning Bureau NYSDOT Comprehensive Asset Management Planning What Is Your Asset Management Organization? What Do You

More information

TABLE OF CONTENTS. Section / Article Page

TABLE OF CONTENTS. Section / Article Page TABLE OF CONTENTS Section / Article Page 1. INTRODUCTION 1.1 Purpose................ 6 1.2 Definitions................ 6 1.3 Guidelines and References............ 7 2. AGREEMENTS 2.1 Applicant and Contractor

More information

11 Guardrail. W-Beam Guardrail Pre-Installation Inspection During Installation Basis for Use. Modified Guardrail. End Treatments and Transitions

11 Guardrail. W-Beam Guardrail Pre-Installation Inspection During Installation Basis for Use. Modified Guardrail. End Treatments and Transitions 11 Guardrail W-Beam Guardrail Pre-Installation Inspection During Installation Basis for Use Modified Guardrail End Treatments and Transitions Footings and Anchors Impact Attenuators Measurement and Payment

More information

Engineering in the water environment: good practice guide. River crossings

Engineering in the water environment: good practice guide. River crossings Engineering in the water environment: good practice guide River crossings Second edition, November 2010 Contents 1 Introduction 3 2 Impacts of crossings 5 2.1 Construction phase impacts 5 2.2 Barrier to

More information

SECTION 31 20 00 EARTH MOVING

SECTION 31 20 00 EARTH MOVING SECTION 31 20 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for excavating, filling, and grading for earthwork at Parking Structure, new exit stair and as required to

More information

DRAINAGE MANUAL CHAPTER VII STORM DRAINAGE SYSTEMS

DRAINAGE MANUAL CHAPTER VII STORM DRAINAGE SYSTEMS TDOT DESIGN DIVISION DRAINAGE MANUAL CHAPTER VII STORM DRAINAGE SYSTEMS August 1, 2012 CHAPTER 7 STORM DRAINAGE SYSTEMS SECTION 7.01 INTRODUCTION 7.01 INTRODUCTION...7-1 SECTION 7.02 DOCUMENTATION PROCEDURES

More information

Index 20010 Series Prestressed Florida-I Beams (Rev. 07/12)

Index 20010 Series Prestressed Florida-I Beams (Rev. 07/12) Index 20010 Series Prestressed Florida-I Beams (Rev. 07/12) Design Criteria AASHTO LRFD Bridge Design Specifications, 6th Edition; Structures Detailing Manual (SDM); Structures Design Guidelines (SDG)

More information

Design Charts for Open-Channel Flow HDS 3 August 1961

Design Charts for Open-Channel Flow HDS 3 August 1961 Design Charts for Open-Channel Flow HDS 3 August 1961 Welcome to HDS 3-Design Charts for Open-Channel Flow Table of Contents Preface DISCLAIMER: During the editing of this manual for conversion to an electronic

More information

Small Dam Hazard Assessment Inventory

Small Dam Hazard Assessment Inventory Small Dam Hazard Assessment Inventory What would happen if your dam were to fail? This is a question that most dam owners hope they will never have to answer. However it is a question you, as a responsible

More information

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix. Storm Drainage 13-C-1 APPENDIX C INLETS 1.0 Introduction The application and types of storm drainage inlets are presented in detail in this Appendix. 2.0 Inlet Locations Inlets are required at locations

More information

CHAPTER 3 STORM DRAINAGE SYSTEMS

CHAPTER 3 STORM DRAINAGE SYSTEMS CHAPTER 3 STORM DRAINAGE SYSTEMS 3.7 Storm Drains 3.7.1 Introduction After the tentative locations of inlets, drain pipes, and outfalls with tail-waters have been determined and the inlets sized, the next

More information

Crossing creeks Stream crossings on farms

Crossing creeks Stream crossings on farms Crossing creeks Stream crossings on farms Looking after all our water needs Crossing creeks Stream crossings on farms Looking after all our water needs Department of Water 168 St Georges Terrace Perth

More information

Numerical Modeling and Simulation of Extreme Flood Inundation to Assess Vulnerability of Transportation Infrastructure Assets

Numerical Modeling and Simulation of Extreme Flood Inundation to Assess Vulnerability of Transportation Infrastructure Assets Numerical Modeling and Simulation of Extreme Flood Inundation to Assess Vulnerability of Transportation Infrastructure Assets 2015 University Transportation Center (UTC) Conference for the Southeastern

More information