PRELIMINARY ENGINEERING REPORT AND UTILITY PLAN NEW WASTEWATER TREATMENT FACILITY TOWN OF MEAD FOR A FOR THE

Size: px
Start display at page:

Download "PRELIMINARY ENGINEERING REPORT AND UTILITY PLAN NEW WASTEWATER TREATMENT FACILITY TOWN OF MEAD FOR A FOR THE"

Transcription

1 PRELIMINARY ENGINEERING REPORT AND UTILITY PLAN FOR A NEW WASTEWATER TREATMENT FACILITY FOR THE TOWN OF MEAD REVISED NOVEMBER 6, 2006

2 PRELIMINARY ENGINEERING REPORT AND UTILITY PLAN FOR A NEW WASTEWATER TREATMENT FACILITY FOR THE TOWN OF MEAD, COLORADO JVA, Inc Spruce Street Boulder, CO phone: fax: JVA Project No. 1372c Revised November 6, 2006

3 TABLE OF CONTENTS Table of Contents... i Acronyms... ii List of Figures... ii List of Tables...iii Appendices...iii Section 1 - Executive Summary... 1 Section 1.1 Background... 1 Section 1.2 Project Description... 2 Section 2 - Introduction... 4 Section 3 - Analysis of Existing Facilities... 6 Section 3.1 Wastewater Treatment Facilities... 6 Section 3.2 Wastewater Effluent Limitations... 7 Section 3.3 Infrastructure Sizing and Staging... 8 Section 3.4 Infiltration and Inflow... 8 Section 3.5 Industrial Pretreatment Program... 9 Section 4 - Service Area, Population Projections, Wastewater Flow and Loads Section 4.1 Service Area Description Section 4.2 Population Projections Section 4.3 Wastewater Flow Rates: Historical and Projected Section 4.4 Wastewater Organic Loads: Historical and Projected Section 5 - Preliminary Effluent Limitations Section 6 - Water Quality Characterization Section 6.1 Water Quality of Receiving Water Section 6.2 TMDLs and/or Wasteload Allocation Section 6.3 Watershed Issues Section 7 - Site Location Analysis Section 7.1 Process for Selecting Proposed Site Location Section 7.2 Site Location Selection Section 8 - Treatment Alternative Analysis Section 8.1 Oxidation Ditch Section 8.2 Earth Basin Extended Aeration Section 8.3 Sequencing Batch Reactors Section 8.4 Treatment Alternatives Cost Summary Section 8.5 Comparison of Treatment Alternatives Section 9 - Consolidation Analysis Section 9.1 Background Section 9.2 Consolidation Analysis Section 10 - Selected Wastewater Alternative Section 10.1 Selected Wastewater Alternative Components Section 10.2 Proposed Wastewater Treatment Process Section 10.3 Staging or Phasing Town of Mead Wastewater Treatment Facility Preliminary Engineering Report and Utility Plan i

4 Section 10.4 Wastewater Reuse Section 10.5 Wetlands Section 10.6 Odor Control Considerations Section 10.7 Air Quality Permit Section 10.8 Stormwater Management Plan Section 10.9 Collection System Section Environmental Components Section 11 - Floodplain/Hazards Analysis Section 12 - Soils Report Section 13 - Legal Control Of Site Section 14 - Institutional Arrangements Section 15 - Management Capability Section 15.1 Management Structure and Agreements Section 16 - Financial Capability Section 16.1 Financial Management Plan and User Charge Summary Section 16.2 Revolving Loan Section 17 - Schedule Section 18 - Discharge Across Private Property References BOD 5 : Biochemical Oxygen Demand (5 day) CDPHE: Colorado Department of Public Health and Environment DMR: Daily Monitoring Reports gpd: Gallons per day gpm: Gallons per minute I-25: Interstate 25 ISDS: Individual sewage disposal systems NFRWQPA: North Front Range Water Quality Planning Association MGD: Million gallons per day SVSD: Saint Vrain Sanitation District TKN: Total Kjeldahl Nitrogen TSS: Total Suspended Solids WWTF: Wastewater Treatment Facility ACRONYMS Figure 1: Existing Wastewater System and 208 Boundary Figure 2: Existing Mead WWTF Treatment Schematic Figure 3: WWTF Location Alternatives Figure 4: Alternative Figure 5: Consolidation with SVSD WWTF Alternative Figure 6: Proposed Mead WWTF Process Schematic Figure 7: Conceptual Site Plan LIST OF FIGURES Preliminary Engineering Report and Utility Plan ii

5 LIST OF TABLES Table 1: Compliance Schedule Ammonia Limits Table 2: Population Projections, Wastewater Flows, and Load Table 3A: Preliminary Effluent Limit Summary Table 3B: Potential Effluent Limits based on New Total Ammonia Criteria Table 4: In-stream Standards for Stream Segment COSPSV06 Table 5: Summary of the Top 5 Wastewater Alternatives (2005 WW Study) Table 6: Wastewater Alternative 20 year Present Worth Cost Analysis Table 7: Treatment Alternatives Comparison Matrix Table 8A: Town Treatment and SVSD Consolidation - Plant Investment Fee Comparison Table 8B: Town Treatment and SVSD Consolidation Capital Cost Comparison Table 9: Summary of Management Agencies Table 10: Wastewater Rates per 1000 gallons Table 11: Projected O&M Budget Table 12: Projected Annual Revenue Based on User Fees Table 13: Historic Wastewater Tap Fee Summary Table 14: Project Capital Costs, Anticipated Loan Amounts, and EIG Impact Appendix A: CDPHE Site Application Appendix B: CDPHE and NFRWQPA report checklists Appendix C: Existing Mead WWTF Layouts Appendix D: IGA Agreement Appendix E: Preliminary Effluent Limits and Compliance Schedule Appendix F: Map of Watershed Boundary and Receiving Waters Appendix G: Property Deed Appendix H: Wastewater Treatment Alternative Itemized Costs Appendix I: Consolidation Information Appendix J: Smith Environmental Environment Assessment Report Appendix K: Environmental Assessment Agency Contact Letters Appendix L: Ground Engineering Soils Report Appendix M: Town Ordinance for Sewer User Fees and Wastewater Rate Study Appendix N: Low Density Area Map and Planning and Zoning Information Map Appendix O: Public Hearing Information Appendix P: Sewerline Map Appendix Q: East I-25 Service Plan Owner Map APPENDICES Preliminary Engineering Report and Utility Plan iii

6 SECTION 1.1 BACKGROUND SECTION 1 - EXECUTIVE SUMMARY The Town of Mead is located in Weld County approximately 35 miles north of Denver along Interstate 25 (I-25). Similar to many other Colorado communities, the Town has experienced past growth and foresees significant future development. At the present time, the majority of the proposed growth is residential, but the Town s location in the I-25 corridor indicates future business and commercial developments as well. The Town owns and operates two earthen basin aerated wastewater treatment facilities (WWTF). The main Town treatment facility, the existing Mead WWTF, is located about one-half mile east of downtown Mead. The existing Mead WWTF is permitted to discharge up to 0.14 million gallons per day (MGD) and 333 lbs per day of 5-day biochemical oxygen demand (BOD 5 ). Current flows and loads are approximately 0.10 MGD and 215 lbs BOD, respectively. The existing Mead WWTF was constructed in the mid 1950s originally as a two-basin facultative lagoon treatment system. The treatment system has undergone several modifications to improve effluent quality. However, the modifications have not been sufficient to completely eliminate discharge permit exceedances. At this time the Town is facing two significant issues associated with the existing Mead WWTF. First, the Town is under a compliance schedule issued by the Colorado Department of Public Health and Environment (CDPHE) that requires the existing Mead WWTF to meet ammonia discharge limits by 2009 with construction of a new wastewater facility. The existing aerated lagoon treatment system is not capable of complying with the anticipated ammonia discharge standards and will need to be replaced with a treatment process that is capable of consistently meeting the anticipated discharge limits. Secondly, the existing Mead WWTF does not have sufficient capacity to serve the growing population of the Town and its service area. To meet the future wastewater needs, the Town proposes installing a new mechanical WWTF to replace the existing aerated lagoon system. The engineer s opinion of probable cost for this project is $4.31 million, excluding the future lift station to serve the east side of I-25. It is anticipated that the $1.3 million lift station and force main will be constructed using funds from developers. The Town may be able to participate in a portion of this cost should adequate reserves be collected from new development. Additionally, the Town has offered developers the ability to prepurchase taps for capital improvements. The Town evaluated the possibility of sending its wastewater to the Saint Vrain Sanitation District (SVSD). Based on the monetary and non-monetary factors and in consideration of the fact that the Town is under a compliance schedule, the Town Board decided after a thorough review of the issues in several board meetings that the more cost-effective and expedient solution to providing wastewater service for its current and future customers was to construct the Town s own facilities, and that it would not be in the best interests of the Town to continue pursuing Preliminary Engineering Report and Utility Plan 1

7 consolidation with SVSD. However, the Town intends to continue to expand its IGA with SVSD to allow gravity sewer service to the SVSD along its present south 208 boundary, rather than this area being pumped into the Town s service area. It is important to note that the Town is not dependent on development of the areas east of I-25 to help pay for the proposed 0.5 MGD WWTF. However, since the Town Board revised its annexation ordinance in October 2006 to eliminate a requirement that landowners go through an election in order to receive approval from the public to be annexed, it is expected that an influx of annexation proposals will occur. The initial phase of this project will provide service to the existing and proposed or already platted areas in the Town or areas that are currently under development. Should areas on the east side of I-25 develop faster than currently anticipated, the plant can be easily expanded to include this growth. It is also important to note that the Town has adequate development on the books that is already annexed, zoned, and mostly platted that will pay fees to use the plants. It does not have to rely on future uncertain annexations. The Town can also completely finance the plant with existing development conditions, its own cash reserves, and its ability to obtain loans. The following utility plan presents a discussion of the proposed Mead WWTF to meet the documentation requirements of the CDPHE site application and NFRWQPA report and to provide master planning for the Town. The site application for this project is provided in Appendix A. SECTION 1.2 PROJECT DESCRIPTION The existing Mead WWTF site was not utilized for a proposed facility due to its proximity to the Town center and proposed residential areas. After an extensive site selection process, the Town purchased an acceptable 10-acre site for the proposed Mead WWTF, located approximately onehalf mile east of I-25 and 600 feet south of Weld County Road 34. Consolidation with the St. Vrain Sanitation District WWTF, located approximately 3 ½ miles southeast of the proposed Mead WWTF site and requiring approximately five miles of interceptors and force main, was also considered as a wastewater service alternative, but the Town Board determined that a Townowned treatment facility would be more economical for local residents and businesses. The proposed Mead WWTF will be designed for a capacity of 0.5 MGD to meet the projected 20-year development planning horizon for wastewater flow. The facility design will accommodate peak hourly flows of up to 2.0 MGD. Disinfected treated effluent will discharge to the same unnamed tributary of St. Vrain Creek as does the existing WWTF. Beyond the proposed Mead WWTF construction, the Town will also have to plan for several other wastewater infrastructure projects, including: decommissioning the existing Mead WWTF, sewerline construction, and a future wastewater lift station to serve the remaining 208 area. Influent wastewater from the Town service area west of I-25 and a portion of the area east of I- 25 will flow mostly by gravity through the existing collection system. The existing collection system will be extended to the proposed WWTF site. The existing Feather Ridge wastewater lift station will be decommissioned, since it will not be necessary due to the lower elevation of the Preliminary Engineering Report and Utility Plan 2

8 proposed site. The remainder of the service area east of I-25 will be served through a wastewater lift station that will be constructed in the future when needed. The sequencing batch reactor (SBR) has been determined to be the preferred treatment option for the proposed Mead WWTF. SBRs are a proven wastewater treatment system used to reliably and effectively treat wastewater to the ammonia levels as required by the CDPHE compliance schedule. The SBR controls will be programmed as needed to handle anticipated daily and seasonal flow and load variations as required to meet treatment standards. The SBR treatment process will also have flexibility to meet anticipated future permit requirements. The schematic of the proposed Mead wastewater facility process train is illustrated in Figure 6. The raw wastewater influent will first enter a splitter box, then to the headworks facility where a mechanical bar screen will remove, wash, and compact large solids. Following the screening process the wastewater will flow to a grit removal system, and finally to an influent flow meter. After the headworks the wastewater will flow to the SBR treatment facility. The treated wastewater then flows to a flow equalization basin to normalize flows through the disinfection system and the receiving waterbody. Waste activated sludge will be treated utilizing an aerobic digester, and sludge will be hauled offsite and land applied. Figure 7 presents the proposed site plan with the preliminary process layout for the Mead WWTF. The Town has been planning for this WWTF for several years and has gradually increased tap fees from $3,000 to $7,000 for a single residential tap. A rate study was completed in 2004 and has positioned the Town to recover the necessary O&M funds for operation of the new WWTF plus establishment of a repair and replacement fund for the existing WWTF and collection system. Details of the Town s financial plan can be found in Section 16. Preliminary Engineering Report and Utility Plan 3

9 SECTION 2 - INTRODUCTION The Town of Mead is located in Weld County just north of Longmont and approximately 35 miles north of Denver, Colorado. The Town has two exits off I-25 allowing easy access. The original Town core is situated about one mile west of I-25. The Town was founded in 1906 as a rural farm-to-market center and railroad stop along the Great Western Railroad for the sugar beet industry, and up to the 1980s had gradually grown to a population of about 350. The Town s population grew by about 100 additional people during the 1980s, and then to about 2,000 residents in the 1990s, when growth factors such as easy access to I-25 increased the demand for exurban housing (as Mead was then perceived as being in such a market at the time), and population migration out of Boulder County induced the approval and rapid build-out of several subdivisions that decade. Between 2001 and 2003 there was relatively little growth, perhaps only 100 more residents, as subdivisions in the pipeline were finished. Since 2003, several new subdivisions have been started that comprise roughly 1,000 lots, and over 300 building permits within the sewer service area have been issued as of July There are several annexations that have been approved that will bring approximately 2,000 more homes into the community where construction has not yet started. In addition, the community is now receiving numerous development inquiries and proposals, and the Town expects that this trend will continue and intensify. Most proposals are for residential projects at this time, although there is potential for substantial large-scale commercial developments along the I-25 and SH 66 corridors, and smaller-scale commercial development along Town arterials and collector streets. The Town has an industrial park and a business park, both adjacent to I-25, plus an ailing traditional downtown that it desires to revitalize. At this time the Town is facing two significant issues associated with the existing Mead Fairbairn wastewater treatment facility (WWTF). First, the Town is under a compliance schedule issued by the CDPHE that requires the existing Mead WWTF to meet ammonia discharge limits by The discharge limits are discussed in Section 3.2. The existing aerated lagoon treatment system at the existing Mead WWTF is not capable of complying with the anticipated ammonia discharge standards and will need to be replaced with a treatment process that will consistently meet the anticipated discharge limits. Secondly, the existing Mead WWTF does not have sufficient capacity to serve the growing population of the Town and its service area. To meet the future wastewater needs, the Town proposes installing a new mechanical WWTF to replace the existing aerated lagoon system. This site application and engineering report was developed to provide the necessary information for the CDPHE to approve the site application for the proposed Mead WWTF. Additional information is provided to satisfy the approval criteria of the North Front Range Water Quality Planning Association (NFRWQPA). The site application form is provided in Appendix A. The CDPHE and NFRWQPA report checklists are provided at the end of this report, in Appendix B Preliminary Engineering Report and Utility Plan 4

10 with cross-references to relevant page or section numbers. Supplemental material, including preliminary effluent limits (PELs) and other referenced information are also provided in subsequent appendices as identified in this report. Upon dissolution of the Mead Sanitation District on January 1, 1993, the Town of Mead assumed ownership and control of the wastewater treatment facilities serving the Town. The Town of Mead has been designated as both a wastewater Management Agency and an Operating Agency in the NFRWQPA Areawide Water Quality Management Plan 2005 Update (WQMP). The WQMP is a planning document mandated by Section 208 of the Clean Water Act, which requires designation of wastewater treatment management agencies, and provides that such agencies may only obtain wastewater discharge permits which are not in conflict with the WQMP plan. Section 208, in conjunction with Section 201 of the Clean Water Act, also provides for designation of service areas for wastewater treatment facilities and facility operators within the adopted regional plan. Figure 1 illustrates the Town of Mead wastewater system, including the 208 Service Area, as designated in the WQMP. The Town currently owns and operates two WWTFs. The primary facility is the Town of Mead WWTF located east of downtown Mead on Fairbairn Avenue. The other facility is the Lake Thomas WWTF located east of I-25 on WCR 32. Both facilities are aerated lagoon WWTFs. The Lake Thomas WWTF treats only one small condominium complex, while the Town of Mead WWTF treats the remainder of the Town s wastewater. The existing Mead WWTF is the main focus of this plan. The Lake Thomas WWTF has potential for private developer use or could be decommissioned once the new WWTF is placed in service. Figures of the existing WWTFs can be found in Appendix C. The Town of Mead s WWTFs will be further discussed in the Analysis of Existing Facilities section. The existing Mead WWTF is an aerated lagoon treatment facility, with an advanced integrated pond system (AIPS) modification for influent BOD removal in an anaerobic cell. The WWTF is permitted for 0.14 MGD and 333 lbs of BOD 5. The existing Mead WWTF currently treats an average day flow slightly above 0.1 MGD. Unfortunately, the existing Mead WWTF has not been operating optimally and has exceeded effluent permit limits on several occasions. Between June 2002 and May 2004, the existing Mead WWTF experienced: five effluent BOD 5, four BOD 5 percent removal, two effluent BOD 5, one influent TSS, one effluent TSS, and one fecal coliform exceedances. These exceedances have been attributed, in part, to high solids content in the lagoon cells, as a result of algae formation. These recent treatment issues have raised concerns about the ability of the existing Mead WWTF to treat future flows and loads with the existing processes. In addition to the poor treatment performance of the existing Mead WWTF, the Town operations and engineering staff has indicated concern over the validity and accuracy of the influent flow metering and historic sampling that has been completed to date. Influent and effluent flow meters were replaced in 2005, but the impact of the high service lift station, which intermittently discharges up to 750 gallons per minute (gpm), is still skewing the influent flow data. Preliminary Engineering Report and Utility Plan 5

11

12 SECTION 3 - ANALYSIS OF EXISTING FACILITIES SECTION 3.1 WASTEWATER TREATMENT FACILITIES The two WWTFs owned and operated by the Town are discussed below. Figures of the existing WWTFs can be found in Appendix C. EXISTING MEAD WWTF: The existing Mead WWTF was constructed in the mid 1950s as a two-basin facultative lagoon treatment system by the former Mead Sanitation District. After the dissolution of the Mead Sanitation District in 1993, the Town took over ownership and operation of the existing Mead WWTF. The existing Mead WWTF underwent improvements in 1992 and 1993 that converted the existing two-basin facultative lagoon into an aerated lagoon system. The 1992/93 WWTF improvements included: 1) placing an earthen berm across Lagoon No. 2 thereby creating a third lagoon (Lagoon No. 3), 2) converting Lagoon Numbers 1 and 2 into aerated lagoons by installing surface aerators, 3) addition of a chlorine contact chamber and sodium hypo-chlorite feed equipment, and 4) installing flow recording devices on plant influent and effluent. In the 1990s, an engineering study determined the detention time of Lagoon No. 1 facilitated algae growth that resulted in algae-oriented effluent TSS exceedances. The study also determined that Lagoon No. 1 had excessive sludge buildup. In 1995, the existing Mead WWTF operations were modified to bypass Lagoon No. 1, thereby allowing the basin to dry for sludge removal. Concurrently, improvements to Lagoon No. 2 were made to reduce plant detention time and to allow the plant to operate more efficiently. Improvements included the installation of two curtains in Lagoon No. 2 to create three treatment cells and a bypass line of the polishing cell (Lagoon No. 3). In July 1996, Lagoon No. 1 was cleaned and 1.1 million gallons of biosolids were removed. The existing Mead WWTF has undergone several smaller system improvements since the mid s. In 1998, a new influent headwork structure was constructed. In 2000, four new 4,500- gallon chlorine contact vaults were added. The chlorine contact tanks are sized for a 30-minute detention at the peak flow rate of 180,000 gallons per day. Currently, the existing Mead WWTF provides treatment utilizing a three-cell advanced integrated pond system (AIPS) including an anaerobic fermentation cell, aeration cell, and settling cell. The existing Mead WWTF is permitted for 0.14 MGD and 333 lbs of BOD 5. All three cells are located within the old Lagoon No. 2. A schematic of the existing Mead WWTF process follows in Figure 2. LAKE THOMAS WWTF: The Lake Thomas WWTF is an aerated lagoon that was constructed in 1989 to serve the Country View Day Care Center. The Town acquired the WWTF in 2000 as Preliminary Engineering Report and Utility Plan 6

13

14 part of an annexation and redevelopment of the day care center, which was converted to the Lake Ridge Condominium complex. At present time, the Lake Ridge Condominium complex is the only development served by the Lake Thomas WWTF. In December 2001, the Lake Thomas WWTF underwent improvements, including: 1) new inlet and outlet structures, 2) a new chlorine contact chamber, 3) rehabilitation of the lagoon banks, and 4) sludge removal. The Lake Thomas WWTF provides treatment utilizing a two-cell aerated lagoon system with an aeration cell and a settling cell. The Lake Thomas WWTF has a design capacity of 12,000 gallons per day (gpd). Currently the Lake Ridge Condominium complex only has about 4 residents. Of the total 29 units, approximately 25 units have been vacant for several years due to failed marketing of the complex. Consequently, the Lake Thomas WWTF has been receiving minimal flow and loading from the Lake Ridge Condominiums. The Lake Thomas WWTF has not discharged into Lake Thomas since the day care facility was closed in late SECTION 3.2 WASTEWATER EFFLUENT LIMITATIONS The existing Mead WWTF is discharging under the State of Colorado Discharge Permit Number CO that is effective until December 31, The permitted hydraulic and organic loading is based on an average monthly flow of 140,000 gpd and 333 pounds of BOD per day. The Lake Thomas WWTF discharges under Permit Number CO that is effective until November 30, The permitted hydraulic and organic loading is based on a maximum flow of 12,000 gpd and 24 pounds of BOD per day. In conjunction with the January 1, 2005 discharge permits, the CDPHE issued a compliance schedule to the Town. The compliance schedule requires the s to consistently meet ammonia discharge limits by late A copy of the compliance schedule is included in Appendix E. The compliance schedule limits are seen in Table 1. Preliminary effluent limits (PELs) for the lagoon system were initially provided by the CDPHE for the future ammonia limits in the compliance schedule. The preliminary effluent limits for the proposed mechanical treatment facility are discussed in Section 5 and Appendix E. Table 1: Compliance Schedule Ammonia Limits, Total Ammonia (as N), mg/l Month 30 day average Daily Maximum January February March April May June July August September October November December Preliminary Engineering Report and Utility Plan 7

15 Under current conditions, the existing Mead WWTF is operating at approximately 70% of its permitted hydraulic capacity and about 65% of its organic capacity. However, as indicated by past discharge permit limit excursions, the existing Mead WWTF may not be capable of effectively treating higher flow rates or loads. SECTION 3.3 INFRASTRUCTURE SIZING AND STAGING LIFT STATIONS: The Town of Mead currently owns and operates two wastewater lift stations located north of downtown Mead. The Feather Ridge Lift Station is located northeast of the downtown near the Great Western Railroad. The North Creek Lift Station is located north of the downtown along Weld County Road 34 ½. The Feather Ridge Lift Station has two 750 gpm pumps with the ability to add a third pump. The North Creek Lift Station has two 200 gpm pumps. The Feather Ridge lift station will be decommissioned when the new WWTF becomes operational. The North Creek Lift Station can be abandoned once a new interceptor sewer is constructed up the North Creek drainage. This would occur when a development proposal is approved by the Town for a parcel abutting the west, north, or east side of the existing North Creek subdivision. The Town has received several development inquiries about parcels in this area in the past few years, but thus far none have submitted an application. It is expected that development in this area will occur within the next 10 years. INTERCEPTORS: The Town of Mead wastewater collection system consists of force mains that range from 4 to 10 and gravity lines that range from There is one 695-foot section of 24 gravity sewerline which connects the gravity collection system to the 10 force main. See Appendix P for a Town of Mead sewerline map. The wastewater collection system consists of approximately: 6,289 ft of 4 force main 3,860 ft of 10 force main 46,774 ft of 8 sewerline 1,100 ft of 10 sewerline 9,668 ft of 12 sewerline 402 ft of 15 sewerline 1,775 ft of 18 sewerline 695 ft of 24 sewerline SECTION 3.4 INFILTRATION AND INFLOW The Town of Mead has not completed a recent infiltration and inflow study. However, though the accuracy of the historic Mead wastewater flow data is uncertain, infiltration and inflow is not believed to be an issue since flows to the WWTF appear to be low for the given population. The Town has considered exfiltration as an explanation for the low wastewater production rate per capita. However, there is no evidence of a large leak in the wastewater collection system. Most of the sewer system in the Town is fairly new, utilizing construction materials comprised of precast concrete manholes and PVC piping. The original Town subdivision was sewered in the Preliminary Engineering Report and Utility Plan 8

16 mid-1950s, making this piping system over 50 years old. The Town performed a study of this system in 1996 (Sanitary Sewer Collection System Study, October 1996, by RBD Engineering Consultants), and as part of this study a TV camera was used to perform an internal inspection of all the sewers in this area. Eleven locations were identified to have deficiencies and included holes in the pipe, offset joints, or cracked pipe. The Town has corrected all the identified deficiencies. The Town has corrected the last deficiency by replacing the Fairbairn Avenue sewer main. This sewer was originally constructed with clay and concrete sewer pipe with brick manholes. Several locations were identified to have infiltration through manhole connections and the interior of the pipe was deteriorating. Approximately 2,500 feet of the sewer was replaced with 12-inch PVC piping, and this project was completed in October SECTION 3.5 INDUSTRIAL PRETREATMENT PROGRAM According to the U.S. EPA, the National Pretreatment Program under the General Pretreatment Regulations require that any wastewater treatment facility designed to treat over five million gallons a day of wastewater, or receives significant discharges from industrial sources, must develop a local pretreatment program conforming to EPA regulations. At this time the Town does not have a pretreatment program in place, as it treats less than 5 MGD of wastewater and does not receive a significant industrial flow. The proposed growth through the year 2026 does not take the Town over 5 MGD, nor does it introduce significant industrial sources of wastewater to the WWTF. In the future, the Town plans to implement a wastewater pretreatment program to minimize oil and grease discharges to the WWTF. However, due to concerns about potential discharges by one industrial contributor, the Town did conduct a wastewater survey of the Boulder Scientific Company in December The CDPHE Industrial Pretreatment Coordinator, Rick Koplitz, participated in the wastewater inspection. This chemical manufacturer was found to have only its domestic wastewater connected to the sewer system. Preliminary Engineering Report and Utility Plan 9

17 SECTION 4 - SERVICE AREA, POPULATION PROJECTIONS, WASTEWATER FLOW AND LOADS SECTION 4.1 SERVICE AREA DESCRIPTION The Town s 208 wastewater service area, as defined by the NFRWQPA Areawide Water Quality Management Plan 2005 Update, is shown on the attached map in Figure 1. The service area incorporates two existing WWTFs and two lift stations. Currently, all of the existing collection system and sewer customers are located on the west side of I-25. The 208 service area is approximately 23 square miles and includes areas on both sides of I-25. A portion of the 208 service area is designated as very low or low density development by the 2004 Town of Mead Comprehensive Plan (See Appendix N: Planning and Zoning Information Map). These low density areas within the 208 boundary may be served by septic systems, although it is the intent of the Town to be able to provide sewer service within its 208 boundaries in the future. However, the following considerations will need to be taken into account when considering long term treatment needs: a. The Town s septic subdivisions may ultimately be required to be municipally sewered. These development are products of past land use and density decisions and are consistent with many similar subdivisions in Weld County, several of which are also in the Town s planning area and would face the same issue. b. Future regulations may require the landowners to abandon their septic systems and connect to the Town s sewer system. The landowners would be required to fund these improvements including the purchase of taps for each resident. The Town is providing additional capacity in its sewer system to accommodate possible future failures in or regulatory changes affecting these areas. c. Low land use density on the Town s Comprehensive Plan does not necessarily mean that septics would be approved. The Town has subdivisions with 1-acre lots on septic and subdivisions with average 5-acre lots that are on municipal sewer. Thus 208 boundaries should not assume that everyone inside them are on municipal sewer. Certainly the County s approval of rural subdivisions on septic inside many towns 208 boundaries indicates that this definition of urban development is not appropriate. d. Cluster subdivisions, also known as conservation subdivisions, are another way of achieving sewer service and having average low density development at the same time. Preliminary Engineering Report and Utility Plan 10

18 e. In situations where development proposals are not immediately adjacent to previously developed properties the Town may require a subdivision developer to dry-sewer a subdivision, due to timing or temporary contiguity issues. A dry-sewer subdivision would have both sewer mains and septic tanks installed. The subdivision would utilize the septic tanks only until a municipal interceptor is constructed in the vicinity. After interceptor construction, the subdivision would abandon the septic tanks and connect to the municipal wastewater system. f. Open space and large regional parks (e.g. Sandstone Ranch in Longmont) would be examples of parcels that would not be cost-effective to provide sewer service to, or which would create timing or location issues for bringing sewer service to developable properties next to them. g. There may be areas that are not currently annexed to the Town that the Town would provide sewer service to. The Town has not yet done a study to determine what tap fees and user charges should be to such properties, but is planning to do so. The Town Board revised its annexation ordinance in October 2006 to eliminate a requirement that landowners go through an election in order to receive approval from the public to be annexed, so it is expected that an influx of annexation proposals will occur. The Town of Mead has an intergovernmental agreement (IGA) with the SVSD to provide wastewater treatment to a business park near the intersection of I-25 and Highway 66 that is in the Town s 208 service area. The IGA boundaries can also be seen on Figure 1 and a copy of the IGA agreement is provided in Appendix D. In 2004, a disparate group of property owners banded together for the purpose of proposing a new Sanitation District in the area generally east of I-25 and north of SH66, directly adjacent to the corporate boundaries of Mead in numerous spots, and with a large amount of the acreage in the Mead s 208 sewer service area (See Appendix Q). This proposed project has been called the East I-25 Sanitation District (District). Because this District proposal has subsequently received a great deal of press, the Town has prepared a brief description of the situation in consultation with its legal counsel. The Town is limited in what it can submit as a part of this site application on the topic, because the situation is in litigation. Some of the origins of this proposal have been stated to be that the Town refused to annex certain properties or that it was incapable of providing sewer service in a timely manner. This is not true. In fact, the District proponents included both property owners who have either petitioned the Town for annexation at some point, and others who have never petitioned for annexation. One annexation petition is still on file with the Town because the owner has not decided which party to work with. Additionally, some property owners withdrew annexation petitions before completing negotiations, and others lost their annexation contiguity through the actions of other parties, not because the Town refused to annex them. For whatever their motivations, the District proponents prepared a service plan that was based on the assumption of being a collection system only, with treatment to be provided by the St. Vrain Sanitation District. The service plan was presented to the Weld County Board of Commissioners for approval, which the County Board did at a public hearing in February 2005 over the Preliminary Engineering Report and Utility Plan 11

19 objections of the Town. Consequently, the Town of Mead sued both the County and the District proponents to prevent the formation of the District from occurring until a court could rule on the matter. In summary, the Town alleges that the County failed to follow state statutes and its own regulations in reviewing and approving the service plan. The Town further alleges that the District proponents presented a flawed service plan that vastly understated the cost of the project, and thus its viability, and also presented misleading, incomplete, and falsely prejudicial testimony against the Town at the County s hearing that the Town was not allowed to refute. They also drew proposed District boundaries that overlapped the Town s boundaries. The matter went to trial in May 2006, and the judge in the case has yet to rule. The case is very complicated, but the fact of the matter is that the Developer proposal is still only a proposal and nothing more. The proponents have been prohibited by the court from holding an election to form the District. Accordingly, the proposed District has no standing. They have no signed agreement with SVSD for service. At this point in time, the proposed District is a hypothetical future project that is not germane to the consideration by NFRWQPA of the Town s site application, which represents a real and present need. It is possible that litigation may be elevated to a higher court by any side once a ruling is issued and could take two to three years to resolve. Furthermore, conditions have continued to change, and if any sanitation district should be proposed or come into existence within the Town s 208 service area in the future, it would need to perform its own Engineering Report and Utility Plan to prove what would be the most cost-effective treatment entity to provide them with wastewater service. The Town does not believe that it has any obligation to do this kind of analysis for them to address this issue. SECTION 4.2 POPULATION PROJECTIONS According to the 2000 U.S. Census, the total Town population was 2,017 with 641 occupied housing units, providing a residential population density equivalent of 3.15 people per household. The Town staff believes that Census population density value is not representative of the typical sewered household since the Census number also included neighborhoods that are served by septic systems. The existing downtown area and the adjacent residential neighborhoods are believed to have a lower number of residents per household. For the purposes of this report a population density of 2.67 people per home was used to establish population and flow projections connected to the sewer system. As indicated above, of the 641 occupied housing units identified in the 2000 census, less than 348 were tied into the sewer system. The remaining households were on individual sewage disposal systems (ISDS). At this time, there is no intent to tie the ISDS households or future houses in that general location to the sewer system. Since 2000, the Town has experienced an average annual growth rate of 7.7%. In 2003 and 2004 the growth rates were as high as 15.9% and 22.3%, respectively. The Town is working with several developers and has identified approximately 500 platted lots ready to be developed over the next three to five years. In light of the anticipated growth in the Town and within the 208 service area, the Town anticipates an annual growth rate of at least 5% for the 20-year planning Preliminary Engineering Report and Utility Plan 12

20 horizon. Although higher growth rates may be realized throughout portions of the 20-year planning period, an average growth rate of 5% is used for this analysis to estimate flows and loads to the proposed Mead WWTF. The 5% growth rate is also consistent with the Wastewater Rate Study the Town completed in Assuming a 5% residential growth rate, the projected 2026 Town population is approximately 7,172 people. Of the total Town population, approximately 4,581 people will be connected to the Mead wastewater system in SECTION 4.3 WASTEWATER FLOW RATES: HISTORICAL AND PROJECTED The accuracy of the historic Mead WWTF recorded flow data is highly suspect. Reviewing the historical flow data collected since 2001 indicated that the average daily flow did not increase with the addition of more taps to the sewer system. Town staff has indicated that a poorly operating recording device had likely impacted flow measurement accuracy. In addition, the upstream Feather Ridge wastewater lift station intermittently discharges up 750 gpm to the WWTF, skewing the average influent flow readings considerably. In the fall of 2005, the Town implemented updated flow measuring methods to try to rectify the flow measurement issues and to improve sampling methods. However, current flow data indicate an average day flow of MGD, resulting in an estimated flow per capita of 58.5 gpd, which is considerably lower than the industry accepted average flow per capita, which ranges between 75 gpd and 85 gpd. Due to the lack of plausible historic flow data, a per capita wastewater production rate of 75 gpd was assumed for this report. The peak hour flows were assumed to be four times greater than the average daily flow. A peaking factor of four was selected since the Town has a relatively small population and collection system and will therefore see higher peak hour flows than larger systems. The peak factor of four is also consistent with the NFRWQPA equation provided in the NFRWQPA 2000 Utility Plan Guidance. Industrial and commercial development has also been identified within the Mead service area, with development occurring over the 20-year planning period. However, at this time it is difficult to quantify the extent to which industrial/commercial development will occur. In order to address treatment needs of industrial/commercial users, the Town has elected to reserve approximately 12% of its capacity for these users. If industrial/commercial usage is higher than expected, the Town will need to address expansion earlier than anticipated. If, however, the industrial/commercial growth is slow, the excess capacity could be used for residential purposes, delaying the overall period of time to expand the facility. A summary of the population projection and resulting wastewater flows is provided in Table 2. The 20 year (2026) projected Mead residential population connected to the wastewater system would contribute approximately MGD. Assuming the 12% industrial/commercial contribution occurs during this same time frame, the plant will be at 80% of its hydraulic capacity in The proposed 0.5 MGD Mead WWTF would reach 100% capacity around 2031 under the same scenario. Preliminary Engineering Report and Utility Plan 13

21 SECTION 4.4 WASTEWATER ORGANIC LOADS: HISTORICAL AND PROJECTED The historical influent water quality data for the existing Mead WWTF is questionable due to the way in which BOD, TSS, and ammonia samples were collected. Until the fall of 2005, the influent data reported on the Daily Monitoring Reports (DMR) was developed by taking grab samples at 7 a.m., 9 a.m., 11 a.m., and 1 p.m. and combining these grabs to represent a 24-hour composite sample. The resulting information indicated a 90th percentile BOD and TSS value of 342 mg/l and 279 mg/l respectively. This data is skewed and misrepresentative of typical domestic facilities. In the fall of 2005, the Town hired a new contract operator, Ramey Environmental Compliance, Inc., (REC) to operate their WWTF and collect DMR data. Since the fall of 2005, true 24-hour composite samples using an automatic sampler have been collected at the lagoon facility, resulting in a 90th percentile BOD value of 258 mg/l and a TSS of 243 mg/l; values that are more consistent with industry standards. A BOD concentration of 258 mg/l results in a total per capita loading of 0.15 pounds per day. A typical range for BOD loading is 0.16 to 0.26 pounds per day. The recent composite flow data shows that the per capita loading rate is on the low side of normal. Given the Town's concern over the historical data collected up until the fall of 2005, and the implementation of true composite sampling in the fall of 2005, the Town's wastewater engineer and JVA have determined that it was prudent to base the design of the proposed facility on the data developed by REC. However, there are only six data points available for analysis at the time of preparation of this report. Typically, several years' worth of data is utilized to develop influent organic and solids data. For design purposes, the documented average of 258 mg/l BOD 5 will be increased 20% to obtain maximum BOD loadings giving a concentration of 310 mg/l. In 2031, at the 100% design flow rate of 0.5 MGD and a population of 5,847, the resulting BOD 5 load is 1,286 lbs/day and the per capita load is 0.22 lbs/day. In 2026, an 80% capacity flow rate of 0.4 MGD will result in a load of 1,008 lbs/day of BOD 5 based on a population of 4,581. Similarly, the average TSS concentration was increased 20% to determine a design concentration of 292 mg/l. In 2031, at the 100% design flow rate of 0.5 MGD and a population of 5,847, the resulting TSS load is 1,169 lbs/day and the per capita load is 0.2 lbs/day. In 2026, an 80% capacity flow rate of 0.4 MGD will result in a load of 916 lbs/day of TSS based on a population of 4,581. Ammonia data, since the fall of 2005, has ranged from 22.5 mg/l to 37 mg/l, and Total Kjeldahl Nitrogen (TKN) between 27 mg/l and 43 mg/l. The characterization of the Town's flow contributors includes minimal industrial or commercial usage. Future development, as identified above, includes predominantly domestic growth with some commercial growth, and minimal industrial growth. It is not anticipated that the proposed commercial/industrial growth will significantly affect the overall character of the influent to the WWTF. Based on the current and proposed growth for the service area, the influent data developed since the fall of 2005 was deemed appropriate for design purposes and has been used to develop the projected flow and load to the proposed WWTF. Utilizing the projected flows to the WWTF, and assuming the influent BOD remains at about 258 mg/l, the Town will reach 80% of its organic design capacity in Preliminary Engineering Report and Utility Plan 14

22 Table 2: Population Projections, Wastewater Flows, and Load Year Total Town Population Homes in 208 Area Home on ISDS Homes on Sewer Population on Sewer Residential WW Flow (MGD) Industrial reserved capacity (MGD) WW Flow (MGD) BOD Load (BOD lbs/d) ,703 1, , ,838 1, , ,980 1, , ,129 1, , ,285 1, , ,450 1, , ,622 1, , ,803 1, , ,994 1, , ,193 1, ,003 2, ,403 1, ,053 2, ,623 1, ,106 2, ,854 1, ,161 3, ,097 1, ,219 3, ,352 2, ,280 3, ,619 2, ,344 3, ,900 2, ,412 3, ,195 2, ,482 3, ,505 2, ,556 4, ,830 2, ,634 4, % 7,172 2, ,716 4, , ,530 2,820 1,018 1,802 4, , ,907 2,961 1,069 1,892 5, , ,302 3,109 1,122 1,986 5, , ,717 3,265 1,178 2,086 5, , % 9,153 3,428 1,237 2,190 5, ,286 Assumptions: 1. Town population growth rate of 5%. 2. Population density of 2.67 persons per household. 3. A wastewater production rate of 75 gpd per capita % of WWTF capacity reserved for Industrial / Commercial users. 5. The BOD load projects are based on a per capita loading rate of 0.22 lbs per day. Preliminary Engineering Report and Utility Plan 15

23 SECTION 5 - PRELIMINARY EFFLUENT LIMITATIONS Primary Effluent Limitations (PELs) for the proposed Mead WWTF for discharge to an unnamed tributary to St. Vrain Creek were received on July 17, A copy has been included in Appendix E. The PELs are shown in Table 3A. Table 3A: Preliminary Effluent Limit Summary Pollutants WQBEL Technology Based Limitations BOD5 (mg/l) 45 (7-day average), 30 (30-day average) BOD5 (% removal) 85 (30-day average) TSS, mechanical plant (mg/l) 45 (7-day average), 30 (30-day average) TSS, mechanical plant (% removal) 85 (30-day average) Oil and Grease (mg/l) 10 (maximum) ph (s.u.) (minimum-maximum) Other Pollutants WQBEL Fecal Coliform (#/100 ml) 400 (7-day average), 200 (30-day average) E. coli (#/100 ml) 252 (7-day average), 126 (30-day average) Total Residual Chlorine (mg/l) (daily maximum), (30-day average) Total Ammonia, January (mg/l) 12 (daily maximum), 7.1 (30-day average) Total Ammonia, February (mg/l) 11 (daily maximum), 6.6 (30-day average) Total Ammonia, March (mg/l) 9.9 (daily maximum), 4.8 (30-day average) Total Ammonia, April (mg/l) 9.8 (daily maximum), 4.5 (30-day average) Total Ammonia, May (mg/l) 9.8 (daily maximum), 4.0 (30-day average) Total Ammonia, June (mg/l) 9.7 (daily maximum), 3.4 (30-day average) Total Ammonia, July (mg/l) 14 (daily maximum), 5.2 (30-day average) Total Ammonia, August (mg/l) 23 (daily maximum), 12 (30-day average) Total Ammonia, September (mg/l) 20 (daily maximum), 9.8 (30-day average) Total Ammonia, October (mg/l) 15 (daily maximum), 7.0 (30-day average) Total Ammonia, November (mg/l) 12 (daily maximum), 6.0 (30-day average) Total Ammonia, December (mg/l) 9.9 (daily maximum), 4.9 (30-day average) The PEL issuance letter also stated that a new total ammonia criteria might be adopted in for the receiving segment, potentially effective in October of Table 3B shows the potential new ammonia water quality-based effluent limits (WQBEL) computed using the AMMTOX model. Table 3B: Potential Effluent Limits based on New Total Ammonia Criteria Month WQBEL (mg/l) January February March April May June July August September October November December 15 (daily maximum), 3.9 (30-day average) 13 (daily maximum), 3.8 (30-day average) 11 (daily maximum), 3.1 (30-day average) 11 (daily maximum), 2.9 (30-day average) 12 (daily maximum), 2.7 (30-day average) 12 (daily maximum), 2.4 (30-day average) 21 (daily maximum), 3.0 (30-day average) 35 (daily maximum), 4.1 (30-day average) 30 (daily maximum), 3.9 (30-day average) 21 (daily maximum), 3.5 (30-day average) 15 (daily maximum), 3.5 (30-day average) 11 (daily maximum), 2.3 (30-day average) Preliminary Engineering Report and Utility Plan 16

Cambridge Wastewater Treatment Facility

Cambridge Wastewater Treatment Facility Cambridge Wastewater Treatment Facility Emergency Situations If you have a water or sewer emergency that relates to the City s utility system call the Public Works office at 763-689-1800 on normal working

More information

Wastewater Facility Plan

Wastewater Facility Plan Village of Poplar Douglas County, Wisconsin Project No. 7752000 April 2009 Village of Poplar Douglas County, Wisconsin Project No. 7752000 Prepared by: MSA Professional Services, Inc. 301 West First Street,

More information

NPDES Permit No. IL0052639. Notice No. IL0052639-12.TTL. Public Notice Beginning Date: June 15, 2012. Public Notice Ending Date: July 16, 2012

NPDES Permit No. IL0052639. Notice No. IL0052639-12.TTL. Public Notice Beginning Date: June 15, 2012. Public Notice Ending Date: July 16, 2012 NPDES Permit No. IL0052639 Notice No. IL0052639-12.TTL Public Notice/Fact Sheet Issued By: Public Notice Beginning Date: June 15, 2012 Public Notice Ending Date: July 16, 2012 National Pollutant Discharge

More information

Kansas City s Overflow Control Program

Kansas City s Overflow Control Program Kansas City s Overflow Control Program Kansas City Water Services Water Wastewater Stormwater 2 Water Services Department 1000 Positions 835 Employees 3 Utilities FY 13/14 Budget = $307 million Water Wastewater

More information

EXISTING WASTEWATER TREATMENT FACILITIES

EXISTING WASTEWATER TREATMENT FACILITIES Chapter 5 EXISTING WASTEWATER TREATMENT FACILITIES 5.1 THERESA STREET WWTF 5.1.1 Overview The Theresa Street WWTF is the larger of the two wastewater treatment facilities owned and operated by the City.

More information

EXISTING WASTEWATER TREATMENT FACILITIES

EXISTING WASTEWATER TREATMENT FACILITIES Chapter 5 EXISTING WASTEWATER TREATMENT FACILITIES 5.1 THERESA STREET WWTF 5.1.1 Overview The Theresa Street WWTF is the larger of the two wastewater treatment facilities owned and operated by the City

More information

TOWN OF LAKESHORE CLASS ENVIRONMENTAL ASSESSMENT ENVIRONMENTAL STUDY REPORT FOR LAKESHORE EASTERN COMMUNITIES SEWAGE WORKS

TOWN OF LAKESHORE CLASS ENVIRONMENTAL ASSESSMENT ENVIRONMENTAL STUDY REPORT FOR LAKESHORE EASTERN COMMUNITIES SEWAGE WORKS TOWN OF LAKESHORE CLASS ENVIRONMENTAL ASSESSMENT ENVIRONMENTAL STUDY REPORT FOR LAKESHORE EASTERN COMMUNITIES SEWAGE WORKS Prepared for The Town of Lakeshore 419 Notre Dame Street, Belle River Ontario

More information

Pursuant to Department of Environmental Protection Rules Chapter 555, effective March 9, 2009

Pursuant to Department of Environmental Protection Rules Chapter 555, effective March 9, 2009 APPLICATION FOR ADDITION OF TRANSPORTED WASTES IN WASTEWATER TREATMENT FACILITIES Pursuant to Department of Environmental Protection Rules Chapter 555, effective March 9, 2009 This application is to be

More information

DRAFT Public Outreach Document for What s an SSMP?

DRAFT Public Outreach Document for What s an SSMP? DRAFT Public Outreach Document for What s an SSMP? This easy to read document is developed and provided to interested parties to assist in educating cities, agencies, their management, elected officials

More information

THE MARSHALL STREET ADVANCED POLLUTION CONTROL FACILITY (CLEARWATER, FLORIDA) CONVERSION TO 4-STAGE BARDENPHO TO IMPROVE BIOLOGICAL NITROGEN REMOVAL

THE MARSHALL STREET ADVANCED POLLUTION CONTROL FACILITY (CLEARWATER, FLORIDA) CONVERSION TO 4-STAGE BARDENPHO TO IMPROVE BIOLOGICAL NITROGEN REMOVAL THE MARSHALL STREET ADVANCED POLLUTION CONTROL FACILITY (CLEARWATER, FLORIDA) CONVERSION TO 4-STAGE BARDENPHO TO IMPROVE BIOLOGICAL NITROGEN REMOVAL ABSTRACT Timur Deniz, Ph.D., Thomas W. Friedrich, P.E.

More information

WASTEWATER TREATMENT OBJECTIVES

WASTEWATER TREATMENT OBJECTIVES WASTEWATER TREATMENT OBJECTIVES The student will do the following: 1. Define wastewater and list components of wastewater. 2. Describe the function of a wastewater treatment plant. 3. Create a wastewater

More information

The City of Boulder 75 th Street Wastewater Treatment Facility

The City of Boulder 75 th Street Wastewater Treatment Facility The City of Boulder 75 th Street Wastewater Treatment Facility Wastewater Collection and Treatment The Foundation of Public Health Wastewater Collection Boulder s wastewater collection system, also known

More information

5. Environmental Analysis

5. Environmental Analysis 5.11 The potential for adverse impacts on utilities and service systems was evaluated based on information concerning current service levels and the ability of the service providers to accommodate the

More information

Minnesota. BMI Project No. M21.037315

Minnesota. BMI Project No. M21.037315 Wastewater Treatment Facility Plan City of Paynesville Minnesota BMI Project No. M21.037315 March 2009 TABLE OF CONTENTS EXECUTIVE SUMMARY... 1 A. GENERAL... 1 B. DESIGN PARAMETERS... 1 C. COST ESTIMATES...

More information

TEXAS: SAN ANTONIO San Antonio Protects Edwards Aquifer

TEXAS: SAN ANTONIO San Antonio Protects Edwards Aquifer TEXAS: SAN ANTONIO San Antonio Protects Edwards Aquifer Background San Antonio, the seventh largest city in the United States, covers approximately 515 square miles of Bexar County in south central Texas.

More information

A HOMEOWNERS GUIDE ON-SITE SEWAGE MANAGEMENT SYSTEMS

A HOMEOWNERS GUIDE ON-SITE SEWAGE MANAGEMENT SYSTEMS GEORGIA DEPARTMENT OF HUMAN RESOURCES ENVIRONMENTAL HEALTH SECTION A HOMEOWNERS GUIDE TO ON-SITE SEWAGE MANAGEMENT SYSTEMS March 12, 2002 WHAT IS AN ON-SITE SEWAGE MANAGEMENT SYSTEM An on-site sewage management

More information

NEVADA CITY WASTEWATER TREATMENT INQUIRY

NEVADA CITY WASTEWATER TREATMENT INQUIRY NEVADA CITY WASTEWATER TREATMENT INQUIRY REASON FOR INVESTIGATION The 2003-2004 Grand Jury investigated the status of wastewater treatment in unincorporated Nevada County. This year, the Grand Jury investigated

More information

INTRODUCTION AND BACKGROUND

INTRODUCTION AND BACKGROUND Chapter 1 INTRODUCTION AND BACKGROUND 1.1 INTRODUCTION The City of Lincoln s Sewer System Management Program (SSMP) generally describes the City s sanitary sewer system operation and maintenance procedures,

More information

Experts Review of Aerobic Treatment Unit Operation and Maintenance. Bruce Lesikar Texas AgriLife Extension Service

Experts Review of Aerobic Treatment Unit Operation and Maintenance. Bruce Lesikar Texas AgriLife Extension Service Experts Review of Aerobic Treatment Unit Operation and Maintenance Bruce Lesikar Texas AgriLife Extension Service Overview Overview of Aerobic Treatment Units Installing for accessibility to system components

More information

Guidance on applying for approval of installation of a commercial onsite wastewater system

Guidance on applying for approval of installation of a commercial onsite wastewater system Guidance on applying for approval of installation of a commercial onsite wastewater system This factsheet is designed to assist you to complete an Application to construct or install an apparatus for the

More information

Texas Commission on Environmental Quality Page 1 Chapter 217 - Design Criteria for Domestic Wastewater Systems

Texas Commission on Environmental Quality Page 1 Chapter 217 - Design Criteria for Domestic Wastewater Systems Texas Commission on Environmental Quality Page 1 217.31. Applicability. SUBCHAPTER B: TREATMENT FACILITY DESIGN REQUIREMENTS 217.31-217.39 Effective August 28, 2008 This subchapter details the design values

More information

Chapter 7: Sanitary Sewer Plan. Introduction. Metropolitan Council Coordination

Chapter 7: Sanitary Sewer Plan. Introduction. Metropolitan Council Coordination Chapter 7: Sanitary Sewer Plan Introduction The 2030 Sanitary Sewer Plan was prepared for two primary reasons. The first purpose is to provide recommendations and guidance to the City of Lino Lakes by

More information

STEAMBOAT LAKE WATER AND SANITATION DISTRICT PETITION FOR AMENDMENT TO SERVICE PLAN TABLE OF CONTENTS. SECTION DESCRIPTION Page

STEAMBOAT LAKE WATER AND SANITATION DISTRICT PETITION FOR AMENDMENT TO SERVICE PLAN TABLE OF CONTENTS. SECTION DESCRIPTION Page STEAMBOAT LAKE WATER AND SANITATION DISTRICT PETITION FOR AMENDMENT TO SERVICE PLAN TABLE OF CONTENTS SECTION DESCRIPTION Page 1 Executive Summary / Brief History 2 2 Services Provided / Administration

More information

Facilities Plan. Wastewater Treatment Facility. Detroit Lakes, Minnesota. January 23, 2015. SEH No. DLPUC 127205

Facilities Plan. Wastewater Treatment Facility. Detroit Lakes, Minnesota. January 23, 2015. SEH No. DLPUC 127205 Facilities Plan Wastewater Treatment Facility Detroit Lakes, Minnesota SEH No. DLPUC 127205 January 23, 2015 Table of Contents 1.0 Introduction... 1 2.0 Regulatory Requirements... 1 3.0 Facility Planning...

More information

Advanced Wastewater Treatment and Disposal Systems. Water and Wastewater Utility Operation and

Advanced Wastewater Treatment and Disposal Systems. Water and Wastewater Utility Operation and Advanced Wastewater Treatment and Disposal Systems Water and Wastewater Utility Operation and Management for Tribes Preliminary Treatment Primary Treatment Secondary Treatment Tertiary Treatment Disinfection

More information

Package Treatment Plant Policy and Procedure

Package Treatment Plant Policy and Procedure Package Treatment Plant Policy and Procedure PURPOSE There has been increased interest in the use of package treatment plants for new development proposals in the County. Current review procedures are

More information

San Luis Obispo County Los Osos Wastewater Project Development TECHNICAL MEMORANDUM SEPTAGE RECEIVING STATION OPTION TABLE OF CONTENTS

San Luis Obispo County Los Osos Wastewater Project Development TECHNICAL MEMORANDUM SEPTAGE RECEIVING STATION OPTION TABLE OF CONTENTS San Luis Obispo County Los Osos Wastewater Project Development TECHNICAL MEMORANDUM SEPTAGE RECEIVING STATION OPTION TABLE OF CONTENTS Page No. 1.0 BACKGROUND...1 2.0 INTRODUCTION - SEPTAGE RECEIVING STATION...1

More information

NPDES Permit No. IL0020737. Notice No. SKT:13120601.bah. Public Notice Beginning Date: April 9, 2014. Public Notice Ending Date: May 9, 2014

NPDES Permit No. IL0020737. Notice No. SKT:13120601.bah. Public Notice Beginning Date: April 9, 2014. Public Notice Ending Date: May 9, 2014 Public Notice/Fact Sheet Issued By: Notice No. SKT:13120601.bah Public Notice Beginning Date: April 9, 2014 Public Notice Ending Date: May 9, 2014 National Pollutant Discharge Elimination System (NPDES)

More information

City of Charlottetown Wastewater Treatment Expansion & Upgrading

City of Charlottetown Wastewater Treatment Expansion & Upgrading City of Charlottetown Wastewater Treatment Expansion & Upgrading Background As Canada s smallest provincial capital, the City of the Charlottetown has a population of approximately 34,000 residents and

More information

MARICOPA COUNTY ENVIRONMENTAL HEALTH CODE CHAPTER II SEWAGE AND WASTES SECTION 8

MARICOPA COUNTY ENVIRONMENTAL HEALTH CODE CHAPTER II SEWAGE AND WASTES SECTION 8 MARICOPA COUNTY ENVIRONMENTAL HEALTH CODE CHAPTER II SEWAGE AND WASTES SECTION 8 ONSITE WASTEWATER TREATMENT FACILITIES REGULATION 1. Definitions a. Aggregate means a clean graded hard rock, volcanic rock,

More information

After the Flush. Safe disposal of our wastewater is a valued and complex, not-for-profit municipal service.

After the Flush. Safe disposal of our wastewater is a valued and complex, not-for-profit municipal service. After the Flush Published: July 14, 2011 Sewage or wastewater is something we rarely think or talk about. The wastewater from our toilets, showers, washing machines and dishwashers quickly departs our

More information

NPDES Permit No. IL0021695. Notice No. JCH:12012302.bah. Public Notice Beginning Date: November 27, 2012. Public Notice Ending Date: December 27, 2012

NPDES Permit No. IL0021695. Notice No. JCH:12012302.bah. Public Notice Beginning Date: November 27, 2012. Public Notice Ending Date: December 27, 2012 Notice No. JCH:12012302.bah Public Notice/Fact Sheet Issued By: Public Notice Beginning Date: November 27, 2012 Public Notice Ending Date: December 27, 2012 National Pollutant Discharge Elimination System

More information

CHAPTER 10-2. Section 1 Inventory of Existing Sanitary Sewer Collection and Treatment Facilities

CHAPTER 10-2. Section 1 Inventory of Existing Sanitary Sewer Collection and Treatment Facilities CHAPTER 10-2 SEWAGE COLLECTION AND TREATMENT FACILITIES Section 1 Inventory of Existing Sanitary Sewer Collection and Treatment Facilities 1.1 SANITARY SEWER COLLECTION SYSTEM The City of Washougal operates

More information

William E. Dunn Water Reclamation Facility. Facility Overview & Information

William E. Dunn Water Reclamation Facility. Facility Overview & Information William E. Dunn Water Reclamation Facility Facility Overview & Information General Area Served: Plant History Facility Highlights Northern Pinellas County St. Joseph Sound to East Lake Road (E/W) Tampa

More information

Alberta Environment Standards for Advanced Waste Systems

Alberta Environment Standards for Advanced Waste Systems Alberta Environment Standards for Advanced Waste Systems + Alberta Rural Organic Waste to Resources Network + George Neurohr Regional Municipal Engineer Grande Prairie, Alberta May 1, 2012 Contents: Introduction

More information

RESIDENTIAL TREATMENT SYSTEMS

RESIDENTIAL TREATMENT SYSTEMS EFFLUENT SAMPLING FOR RESIDENTIAL TREATMENT SYSTEMS For various reasons, many wastewater treatment systems periodically require effluent sampling and characterization. Whether sampling is done to verify

More information

During the past decade, the city of

During the past decade, the city of An Advanced Pollution Control Facility s Conversion to Four-Stage Bardenpho to Improve Biological Nitrogen Removal Timur Deniz, Thomas W. Friedrich, and John Milligan During the past decade, the city of

More information

INFORMATION SHEET ORDER NO. R5-2011-XXXX TRIANGLE ROCK PRODUCTS, INC. FLORIN ROAD AGGREGATE PLANT SACRAMENTO COUNTY

INFORMATION SHEET ORDER NO. R5-2011-XXXX TRIANGLE ROCK PRODUCTS, INC. FLORIN ROAD AGGREGATE PLANT SACRAMENTO COUNTY ORDER NO. R5-2011-XXXX INFORMATION SHEET Background Triangle Rock, Inc. (Discharger) submitted a Report of Waste Discharge (RWD) on 23 August 2010. The Discharger is expanding the mining operations at

More information

ON-SITE WASTEWATER TREATMENT SYSTEMS ACT

ON-SITE WASTEWATER TREATMENT SYSTEMS ACT ON-SITE WASTEWATER TREATMENT SYSTEMS ACT Revised and reproduced by the Colorado Department of Public Health and Environment June, 2012 (PLEASE NOTE: This is an unofficial copy of this statute. The official

More information

Source Water Protection Practices Bulletin Managing Sanitary Sewer Overflows and Combined Sewer Overflows to Prevent Contamination of Drinking Water

Source Water Protection Practices Bulletin Managing Sanitary Sewer Overflows and Combined Sewer Overflows to Prevent Contamination of Drinking Water United States Office of Water EPA 916-F-01-032 Environmental Protection (4606) July 2001 Agency Source Water Protection Practices Bulletin Managing Sanitary Sewer Overflows and Combined Sewer Overflows

More information

Description of the Water Conserv II Facility

Description of the Water Conserv II Facility Description of the Water Conserv II Facility Introduction The Water Conserv II (WCII) Water Reclamation Facility provides service to a majority of the southwest section of Orlando. The WCII facility has

More information

CAPE COD. Regional Wastewater Management Plan Understanding the Cost Factors of Wastewater Treatment and Disposal

CAPE COD. Regional Wastewater Management Plan Understanding the Cost Factors of Wastewater Treatment and Disposal CAPE COD Regional Wastewater Management Plan Understanding the Cost Factors of Wastewater Treatment and Disposal MARCH 2013 Table of Contents INTRODUCTION...1 COST COMPARISON OF ON-SITE, CLUSTER, SATELLITE,

More information

SECTION 6 EXISTING WASTEWATER MANAGEMENT SYSTEMS

SECTION 6 EXISTING WASTEWATER MANAGEMENT SYSTEMS SECTION 6 EXISTING WASTEWATER MANAGEMENT SYSTEMS This section will describe the Town s existing wastewater management systems. This includes on-site disposal systems and private collection systems. The

More information

3.6.1 Existing Conditions - Police, Fire, Ambulance, Water, Sewer, & Solid Waste

3.6.1 Existing Conditions - Police, Fire, Ambulance, Water, Sewer, & Solid Waste 3.6 3.6.1 Existing Conditions - Police, Fire, Ambulance, Water, Sewer, & Solid Waste Police Protection The Clarkstown Police Department provides police protection services to properties within the 40 square

More information

Georgia Department of Public Health. Georgia Onsite Sewage Management Systems. Background and Use of Onsite Wastewater Treatment Systems in Georgia

Georgia Department of Public Health. Georgia Onsite Sewage Management Systems. Background and Use of Onsite Wastewater Treatment Systems in Georgia Georgia Department of Public Health Georgia Onsite Sewage Management Systems Background and Use of Onsite Wastewater Treatment Systems in Georgia Background On-site sewage management systems are designed

More information

City of Mebane Wastewater Collection and Treatment Facility

City of Mebane Wastewater Collection and Treatment Facility City of Mebane Wastewater Collection and Treatment Facility For the Fiscal Year July 1, 2014 - June 30, 2015 City of Mebane Wastewater Collection and Treatment Facility For the Fiscal Year July 1, 2014

More information

Town of New Castle Utility Department Introduction

Town of New Castle Utility Department Introduction Town of New Castle Utility Department Introduction Town of New Castle Utility Department Mission Statement Our commitment is to ensure that our customers receive high quality water and wastewater treatment

More information

SMALL COMMUNITY TREATMENT PLANT EXPANSION WHILE IN OPERATION USING ADVANCED TECHNOLOGY

SMALL COMMUNITY TREATMENT PLANT EXPANSION WHILE IN OPERATION USING ADVANCED TECHNOLOGY SMALL COMMUNITY TREATMENT PLANT EXPANSION WHILE IN OPERATION USING ADVANCED TECHNOLOGY Adel Bassyouni, HDR Engineering, Guillermo Garcia, HDR Engineering, Don Mc Dermott, Viejas Public Works Department

More information

TABLE OF CONTENTS EXECUTIVE SUMMARY...1 1.0 DESCRIPTION OF EXISTING CONDITIONS... 1-1. 1.1 Population... 1-1. 1.2 Wastewater Flows...

TABLE OF CONTENTS EXECUTIVE SUMMARY...1 1.0 DESCRIPTION OF EXISTING CONDITIONS... 1-1. 1.1 Population... 1-1. 1.2 Wastewater Flows... TABLE OF CONTENTS EXECUTIVE SUMMARY...1 1.0 DESCRIPTION OF EXISTING CONDITIONS... 1-1 1.1 Population... 1-1 1.2 Wastewater Flows... 1-1 1.3 Existing Wastewater Facilities... 1-2 1.3.1 City of Celina...

More information

SECTION 1 PURPOSE AND POLICIES

SECTION 1 PURPOSE AND POLICIES SECTION 1 PURPOSE AND POLICIES These Rules and Regulations have been enacted to serve the public in securing the health, safety, and general welfare of the inhabitants of the Southwest Suburban Denver

More information

Dewatering - Time and Cost Relief by way of Trenchless Construction

Dewatering - Time and Cost Relief by way of Trenchless Construction North American Society for Trenchless Technology (NASTT) NASTT s 2015 No-Dig Show Denver, Colorado March 15-19, 2015 TA-T3-04 Dewatering - Time and Cost Relief by way of Trenchless Construction Jenn Stillman,

More information

Understanding and Living With Your Septic System

Understanding and Living With Your Septic System Chapter 9 Understanding and Living With Your Septic System Rural versus urban sewage treatment One of the big difference between rural and city life is how sewage is dealt with. Cities usually have community

More information

SANITARY SEWER MASTER PLAN

SANITARY SEWER MASTER PLAN SANITARY SEWER MASTER PLAN PREPARED FOR: VILLAGE OF GALENA, OHIO PREPARED BY: POGGEMEYER DESIGN GROUP, INC. 1168 NORTH MAIN STREET BOWLING GREEN, OHIO 43402 JOB NO. 3550-030 MARCH, 2006 TABLE OF CONTENTS

More information

APPENDIX M-2 SANITARY SEWER TECHNICAL MEMORANDUM. Stadium Reconstruction EIR

APPENDIX M-2 SANITARY SEWER TECHNICAL MEMORANDUM. Stadium Reconstruction EIR APPENDIX M-2 SANITARY SEWER TECHNICAL MEMORANDUM Stadium Reconstruction EIR Appendices \ AECOM Technical Services, Inc 401 West A Street Suite 1200 San Diego, CA 92101 www.aecom.com 619-610-7600 tel 619-610-7601

More information

TITLE 252. DEPARTMENT OF ENVIRONMENTAL QUALITY CHAPTER 656. WATER POLLUTION CONTROL FACILITY CONSTRUCTION STANDARDS

TITLE 252. DEPARTMENT OF ENVIRONMENTAL QUALITY CHAPTER 656. WATER POLLUTION CONTROL FACILITY CONSTRUCTION STANDARDS Codification through the 2015 legislative session. Subchapters 1, 3, 11, 21, 23, Appendix A Board adoption - February 20, 2015 Approved by Governor's declaration on June 8, 2015 Effective date - September

More information

GOALS, OBJECTIVES AND POLICIES

GOALS, OBJECTIVES AND POLICIES GOALS, OBJECTIVES AND POLICIES The following goal, objective and policy statements have been developed for the use of local policy makers in guiding and directing the decision making process as it relates

More information

Components of a Basement Flooding Protection Plan: Sewer System Improvements. November 2000

Components of a Basement Flooding Protection Plan: Sewer System Improvements. November 2000 Components of a Basement Flooding Protection Plan: Sewer System Improvements November 2000 Components of a Basement Flooding Protection Plan: Sewer System Improvements November 2000 SEMCOG 2000 Prepared

More information

Provided below is a description of the processes generating wastewater in a poultry plant and a typical pretreatment and full treatment system.

Provided below is a description of the processes generating wastewater in a poultry plant and a typical pretreatment and full treatment system. II. PROCESS OVERVIEW Provided below is a description of the processes generating wastewater in a poultry plant and a typical pretreatment and full treatment system. II.1. Wastewater Generation A typical

More information

ZIONSVILLE WASTEWATER DEPARTMENT 10-YEAR SEWER REHABILITATION REPORT 2013-2022

ZIONSVILLE WASTEWATER DEPARTMENT 10-YEAR SEWER REHABILITATION REPORT 2013-2022 ZIONSVILLE WASTEWATER DEPARTMENT 10-YEAR SEWER REHABILITATION REPORT 2013-2022 Town of Zionsville, Indiana December 19, 2012 PREPARED BY BEAM, LONGEST & NEFF, LLC. 8126 Castleton Road Indianapolis, Indiana

More information

SEPTIC SYSTEMS. 1. Building sewer connects the building plumbing to the septic tank.

SEPTIC SYSTEMS. 1. Building sewer connects the building plumbing to the septic tank. SEPTIC SYSTEMS Who Has A Septic System? Approximately 30 percent of Connecticut s population is served by on-site subsurface sewage disposal systems (a.k.a. septic systems). This means a large percentage

More information

SECTION 1 UTILITY OVERVIEW, INTRODUCTION, and PROJECT BACKGROUND

SECTION 1 UTILITY OVERVIEW, INTRODUCTION, and PROJECT BACKGROUND SECTION 1 UTILITY OVERVIEW, INTRODUCTION, and PROJECT BACKGROUND Wastewater Utility Overview In the late 1950 s, the Village of Old Forge began to realize the impacts of dumping sewage in the Moose River.

More information

COMBINED SEWER OVERFLOW OPERATIONAL AND MAINTENANCE PLAN SUMMARY

COMBINED SEWER OVERFLOW OPERATIONAL AND MAINTENANCE PLAN SUMMARY COMBINED SEWER OVERFLOW OPERATIONAL AND MAINTENANCE PLAN SUMMARY Revised: April 2014 Village of Wilmette, Illinois NPDES CSO Permit No. ILM580012 Chapter 1 Introduction This Operational and Maintenance

More information

COMBINED SEWER OVERFLOW LONG-TERM CONTROL PLAN Executive Summary

COMBINED SEWER OVERFLOW LONG-TERM CONTROL PLAN Executive Summary CITY OF LAKEWOOD COMBINED SEWER OVERFLOW LONG-TERM CONTROL PLAN Executive Summary MAY 2006 storage conveyance treatment performance Prepared for: City of Lakewood, Ohio Prepared by: Metcalf & Eddy of Ohio,

More information

Report prepared by: Kelly Hagan and Mark Anderson Grand River Conservation Authority 400 Clyde Road Cambridge ON N1R 5W6

Report prepared by: Kelly Hagan and Mark Anderson Grand River Conservation Authority 400 Clyde Road Cambridge ON N1R 5W6 2013 Watershed Overview of Wastewater Treatment Plant Performance Report prepared by: Kelly Hagan and Mark Anderson Grand River Conservation Authority 400 Clyde Road Cambridge ON N1R 5W6 Table of Contents

More information

Collection Systems Technology Fact Sheet Sewers, Conventional Gravity

Collection Systems Technology Fact Sheet Sewers, Conventional Gravity United States Environmental Protection Agency Collection Systems Technology Fact Sheet Sewers, Conventional Gravity DESCRIPTION Sewers are hydraulic conveyance structures that carry wastewater to a treatment

More information

M E M O R A N D U M. Among the standard conditions contained in the NPDES permit is also a Duty to

M E M O R A N D U M. Among the standard conditions contained in the NPDES permit is also a Duty to M E M O R A N D U M DATE: August 7, 2015 TO: FROM: SUBJECT: Metropolitan Wastewater Management Commission (MWMC) Matt Stouder, MWMC General Manager Capacity Management, Operations, and Maintenance (CMOM)

More information

Maine Department of Environmental Protection Program Guidance On Combined Sewer Overflow Facility Plans

Maine Department of Environmental Protection Program Guidance On Combined Sewer Overflow Facility Plans Maine Department of Environmental Protection Program Guidance On Combined Sewer Overflow Facility Plans OVERVIEW The objective of a Combined Sewer Overflow (CSO) Facility Plan is to abate CSO discharges

More information

City of Dallas Wastewater Collection System: TCEQ Sanitary Sewer Outreach Agreement City Council Briefing January 17, 2007

City of Dallas Wastewater Collection System: TCEQ Sanitary Sewer Outreach Agreement City Council Briefing January 17, 2007 City of Dallas Wastewater Collection System: TCEQ Sanitary Sewer Outreach Agreement City Council Briefing January 17, 2007 1/12/2007 1 Briefing Purpose Provide update on Wastewater Collection Activities

More information

TOWN OF SAUGEEN SHORES WATER AND SANITARY SEWER SERVICING MASTER PLAN 2014 REPORT

TOWN OF SAUGEEN SHORES WATER AND SANITARY SEWER SERVICING MASTER PLAN 2014 REPORT TOWN OF SAUGEEN SHORES WATER AND SANITARY SEWER SERVICING MASTER PLAN 2014 REPORT TOWN OF SAUGEEN SHORES WATER AND SANITARY SEWER SERVICING MASTER PLAN 2014 REPORT April 1, 2015 B. M. ROSS AND ASSOCIATES

More information

ENVIRONMENTAL AND ECONOMIC FACTORS IN SELECTING A SEWAGE TREATMENT SYSTEM

ENVIRONMENTAL AND ECONOMIC FACTORS IN SELECTING A SEWAGE TREATMENT SYSTEM 138 ENVIRONMENTAL AND ECONOMIC FACTORS IN SELECTING A SEWAGE TREATMENT SYSTEM Michael L. Brown* Department of Agricultural Economics, Oklahoma State University, Stillwater, Oklahoma Oklahoma communities

More information

CHAPTER 8 UPGRADING EXISTING TREATMENT FACILITIES

CHAPTER 8 UPGRADING EXISTING TREATMENT FACILITIES CHAPTER 8 UPGRADING EXISTING TREATMENT FACILITIES 8-1. General. Upgrading of wastewater treatment plants may be required to handle increased hydraulic and organic loadings to meet existing effluent quality

More information

Fusion Series Treatment Systems Small Scale Residential & Commercial Treatment Units

Fusion Series Treatment Systems Small Scale Residential & Commercial Treatment Units SECTION: C3.10.120 CL0052 0911 Supersedes New Fusion Series Treatment Systems Small Scale Residential & Commercial Treatment Units Clarus Environmental 3649 Cane Run Rd. Louisville, KY 40211 877-244-9340

More information

Sanitary Sewer Master Plan

Sanitary Sewer Master Plan , Illinois Sanitary Sewer Master Plan EXECUTIVE SUMMARY Prepared by September 9, 2010 1670 South Taylorville Road Decatur, Illinois 62521 www.bgmengineering.com Sanitary Sewer Master Plan A. SCOPE OF STUDY

More information

Wastewater Collection and Treatment Systems For Small Cities

Wastewater Collection and Treatment Systems For Small Cities Page 1 of 13 FISCAL SUSTAINABILITY PLAN For the, Wastewater Collection and Treatment System This plan outlines a (FSP) for the City of Small Town, County of Xxxxx, State of Kansas, as required by the Kansas

More information

DeSoto County is not a water service provider and does not operate any

DeSoto County is not a water service provider and does not operate any Water and Sewer DeSoto County is not a water service provider and does not operate any water delivery systems. There are 14 certificated, non-municipal water associations operating in the county that are

More information

CHAPTER 372-68 WAC WATER POLLUTION CONTROL AND ABATEMENT PLANS FOR SEWAGE DRAINAGE BASINS

CHAPTER 372-68 WAC WATER POLLUTION CONTROL AND ABATEMENT PLANS FOR SEWAGE DRAINAGE BASINS CHAPTER 372-68 WAC WATER POLLUTION CONTROL AND ABATEMENT PLANS FOR SEWAGE DRAINAGE BASINS Last Update: 6/8/88 WAC 372-68-010 Authority. 372-68-020 Purpose. 372-68-030 Definitions. 372-68-040 Planning guide.

More information

Unauthorized Discharges and Sanitary Sewer Overflows

Unauthorized Discharges and Sanitary Sewer Overflows TCEQ REGULATORY GUIDANCE Field Operations Support Division RG-395 Revised April 2011 Unauthorized Discharges and Sanitary Sewer Overflows What does this document cover? The Texas Commission on Environmental

More information

Dry Weather Flow from Footing Drains and Service Connections

Dry Weather Flow from Footing Drains and Service Connections Wastewater Master Plan DWSD Project No. CS-1314 Dry Weather Flow from Footing Drains and Service Connections Technical Memorandum Original Date: May 2, 2002 Revision Date: September 2003 Author: CDM Table

More information

Town of Yorktown Comprehensive Plan 8. INFRASTRUCTURE

Town of Yorktown Comprehensive Plan 8. INFRASTRUCTURE Town of Yorktown Comprehensive Plan 8. INFRASTRUCTURE 8. Infrastructure 8.1 VISION STATEMENT Infrastructure is a basic building block of the community essential for the health, safety, and welfare of residents.

More information

DOCKET NO. D-2005-007 CP-2 DELAWARE RIVER BASIN COMMISSION

DOCKET NO. D-2005-007 CP-2 DELAWARE RIVER BASIN COMMISSION DOCKET NO. D-2005-007 CP-2 DELAWARE RIVER BASIN COMMISSION East Vincent Township Bartons Meadows Wastewater Treatment Plant East Vincent Township, Chester County, Pennsylvania PROCEEDINGS This docket is

More information

Ameren Callaway Energy Center-Water Treatment Plant Sedimentation Basins #5 &#6, MO-0098001, Construction Permit No. CP0001707, Callaway County

Ameren Callaway Energy Center-Water Treatment Plant Sedimentation Basins #5 &#6, MO-0098001, Construction Permit No. CP0001707, Callaway County Ms. Gail Geary Ameren Missouri 1901 Chouteau Ave. PO Box 66149, MC 602 St. Louis, MO 63166-6149 RE: Ameren Callaway Energy Center-Water Treatment Plant Sedimentation Basins #5 &#6, MO-0098001, Construction,

More information

YOUR SEPTIC SYSTEM UNCOVERED

YOUR SEPTIC SYSTEM UNCOVERED YOUR SEPTIC SYSTEM UNCOVERED By Raymond King District Director of Environmental Health It s underground where you can t see it. You don t really understand how it works. When it doesn t work your toilets

More information

City of Bakersfield Public Works Department Sewer System Management Plan December 2014

City of Bakersfield Public Works Department Sewer System Management Plan December 2014 City of Bakersfield Public Works Department Sewer System Management Plan December 2014 C:\Users\hmayberry\Desktop\SEWER SYSTEM MANAGEMENT PLAN 2014.doc 1 Sewer System Management Plan Index: Section 1 Goals

More information

GUIDANCE DOCUMENT FOR SIZING AND INSTALLATION OF GREASE TRAPS AND INTERCEPTORS

GUIDANCE DOCUMENT FOR SIZING AND INSTALLATION OF GREASE TRAPS AND INTERCEPTORS GUIDANCE DOCUMENT FOR SIZING AND INSTALLATION OF GREASE TRAPS AND INTERCEPTORS Fort Worth Water Department, Pretreatment Services Division, (817)871-8305 A. Introduction: Part I: Guidance for Grease Trap

More information

PUBLIC SEWER SERVICE, CAPACITY MANAGEMENT & MUNICIPAL PLANNING

PUBLIC SEWER SERVICE, CAPACITY MANAGEMENT & MUNICIPAL PLANNING PUBLIC SEWER SERVICE, CAPACITY MANAGEMENT & MUNICIPAL PLANNING Our shared role in protecting local water resources 1 Goals for this presentation: Water Environment Protection? Clean Water What is it worth?

More information

Proposed General Plan Update Goals, Policies, and Implementation Actions

Proposed General Plan Update Goals, Policies, and Implementation Actions Proposed General Plan Update Goals, Policies, and Implementation Actions The construction and maintenance of infrastructure is necessary to support existing and planned land uses and to achieve Environmental

More information

RESIDENTIAL ON-SITE WASTEWATER TREATMENT SYSTEM (OWTS) INSTALLATION PERMIT (New or Repair) Instructions and Application Form

RESIDENTIAL ON-SITE WASTEWATER TREATMENT SYSTEM (OWTS) INSTALLATION PERMIT (New or Repair) Instructions and Application Form DEPARTMENT OF PUBLIC HEALTH AND ENVIRONMENT 1555 North 17 th Avenue Greeley, CO 80631 Web: www.weldhealth.org Health Administration Vital Records Tele: 970.304.6410 Fax: 970.304.6412 Public Health & Clinical

More information

COURSE # 343 UNIT # 1: ADVANTEX WASTEWATER TREATMENT SYSTEM. What you will learn in this lesson. Introduction to the listing

COURSE # 343 UNIT # 1: ADVANTEX WASTEWATER TREATMENT SYSTEM. What you will learn in this lesson. Introduction to the listing What you will learn in this lesson IN THIS LESSON, YOU WILL LEARN... About the Orenco AdvanTex alternate technology listing The components that make up the AdvanTex Treatment System How the AdvanTex Treatment

More information

Rouge River Watershed, MI Region 5. Community Case Study ROU-1. Number of CSO Outfalls. Combined Sewer Service Area. Wastewater Treatment Capacity

Rouge River Watershed, MI Region 5. Community Case Study ROU-1. Number of CSO Outfalls. Combined Sewer Service Area. Wastewater Treatment Capacity Community Case Study Rouge River Watershed, MI Region 5 Number of CSO Outfalls 168 Combined Sewer Service Area 93 square miles Wastewater Treatment Capacity 1,700 mgd (primary) 930 mgd (secondary) Receiving

More information

Cost Estimating Procedures for Raw Sewage Overflow Control Program

Cost Estimating Procedures for Raw Sewage Overflow Control Program Raw Sewage Overflow Control Program April 23, 2004 Raw Sewage Overflow Control Program City of Indianapolis Department of Public Works Table of Contents Section Page 1.0 Introduction... 1 2.0 General Project

More information

4.2 Option 1 Expand Existing Lagoon System

4.2 Option 1 Expand Existing Lagoon System 4. WASTEWATER TREATMENT SYSTEM 4.1 of Existing Lagoons The of existing lagoon system is evaluated for future demand based on the following requirements. Existing Lagoons Anaerobic cells - Four Cells, of

More information

SECTION 3 SANITARY SEWER DESIGN

SECTION 3 SANITARY SEWER DESIGN SECTION 3 SANITARY SEWER DESIGN 3.1 GENERAL DESIGN CRITERIA 3.1.1 Requirement for Sanitary Sewer 3.1.2 Design Approval 3.1.3 IEPA Permit Required 3.1.4 Differentiation Between Public and Private Sanitary

More information

Terry Biederman, PE- Director of Public Works Greg Gucwa, PE- Principal Johnson and Anderson Engineering

Terry Biederman, PE- Director of Public Works Greg Gucwa, PE- Principal Johnson and Anderson Engineering DON T JUST REHAB IT, RENEW IT! WATERFORD TOWNSHIP, MICHIGAN IMPROVEMENTS TO A 3.0 MGD SEWAGE PUMPING STATION Terry Biederman, PE- Director of Public Works Greg Gucwa, PE- Principal Johnson and Anderson

More information

Floating Treatment Wetland Technology: Nutrient Removal from Wastewater

Floating Treatment Wetland Technology: Nutrient Removal from Wastewater Floating Treatment Wetland Technology: Nutrient Removal from Wastewater This case study illustrates the Floating Island International (FII) patented floating treatment wetland (FTW) technology and its

More information

Chapter 6 INFRASTRUCTURE ELEMENT 6.1 INTRODUCTION 6.2 AUTHORITY FOR THE ELEMENT 6.3 KEY THEMES AND VISION FOR GENERAL PLAN

Chapter 6 INFRASTRUCTURE ELEMENT 6.1 INTRODUCTION 6.2 AUTHORITY FOR THE ELEMENT 6.3 KEY THEMES AND VISION FOR GENERAL PLAN Chapter 6 INFRASTRUCTURE ELEMENT 6.1 INTRODUCTION Public infrastructure is an important support network for the City. Well-designed and maintained infrastructure systems are critical to the community s

More information

Small Wastewater Treatment Systems

Small Wastewater Treatment Systems Small Wastewater Treatment Systems By Michael Albanese, P.Eng. H2FLOW EQUIPMENT INC. www.h2flow.com Why do you need one? Typical Reasons Enviromental Regulations New Development Failing Septic Systems

More information

THE SANITARY SEWER SYSTEM

THE SANITARY SEWER SYSTEM THE SANITARY SEWER SYSTEM The Water Services Department is responsible for the planning and construction of sewers, pump stations, and treatment facilities serving Kansas City and certain surrounding areas.

More information

Appendix B: Water Treatment Scenarios from AMD Treat

Appendix B: Water Treatment Scenarios from AMD Treat Appendix B: Water Treatment Scenarios from AMD Treat 103 of 104 Jeddo Tunnel Abandoned Mine Drainage Passive vs. Active Treatment Cost Estimates Provided by Office of Surface Mining AMD Treat Software

More information

City of East Lansing CSO Control Facility Evaluation Demonstrative Approach to Meet WQS

City of East Lansing CSO Control Facility Evaluation Demonstrative Approach to Meet WQS City of East Lansing CSO Control Facility Evaluation Demonstrative Approach to Meet WQS Jeff Johnston, East Lansing WWTP Superintendent & Tom Maxwell, P.E., Hubbell, Roth & Clark, Inc. East Lansing CSO

More information

DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS

DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS DESCRIPTION OF STORMWATER STRUCTURAL CONTROLS IN MS4 PERMITS Phase I MS4 permits require continuous updating of the stormwater system inventory owned and operated by the MS4. They also include inspection

More information