THE UNDERWATER CUT-OFF AT THE WALTER F. GEORGE DAM
|
|
- Tiffany Bennett
- 7 years ago
- Views:
Transcription
1 THE UNDERWATER CUT-OFF AT THE WALTER F. GEORGE DAM Gianfranco Di Cicco, Area Manage Special Project and Riccardo Pertocelli CEO, TREVllCOS Corporation, Boston, MA, USA Seepage problems were recorded for more then 40 years at the Walter F. George lock and dam. In 2001 the Mobile district of The U.S. Army Corps of Engineers turned to the installation of a 200 feet deep cut-off in a final attempt to remedy the situation. The advertised design-built contract requested the installation of the cutoff wall in front of the concrete structure of the dam starting from 90 feet of water, cutting through a concrete lock structure, a submerged retaining wall and extending on both sides on the earthen embankments. This paper summarize the history of the project and the installation of the first recorded cut-off wall constructed under deep water, upstream to an existing dam structures and under an existing concrete lock. The technology used combined with the project's results may be considered a milestone in the marine foundation and the marine cut-off wall construction technology. portion, the power units and two earthen wing dams extending to the Georgia and Alabama sides, respectively 5,810 feet and 6,130 feet long. As soon as the reservoir was impounded it became apparent that excessive seepage was occurring. In October 1961, during stripping operations on the final stage of construction of the Alabama dike, two sinkholes occurred. In 1962, still during construction, boils developed along the downstream toe of both Alabama and Georgia. HISTORY Project Location In order to control the seepage below the dam structure, relief wells were installed at the toe of the embankments and the foundation beneath the dikes was drilled and grouted. The Walter F. George lock and dam was constructed on the Chattahoochee River between 1955 and 1963 with the double function of improving navigation and generating power. Its 82 ft. by 450 ft. lock can accommodate large barge traffic and its four generating units with a plant capacity of 150 MW have an average energy output of 453,000 MWH. The dam consists of a 1,496 ft. long concrete structure housing the spillway, a non overflow Subsequently, after completion of the project, a large spring developed near the downstream lock guide wall and sinkhole activity increased on the Georgia side. In 1968 sinkhole activity increased and a new phase of remedial work began. Initially, the remedial work consisted of grouting a small area of the foundation under the Georgia
2 dike, filling the sinkholes with sand and grouting around each sinkhole periphery. In February 1969 a sinkhole was discovered in the reservoir near the Georgia dike and it was filled and grouted in a similar manner. A surface investigation downstream of the Georgia dike was carried out, a number of piezometers were installed and information concerning solution channels was obtained. After the evaluation of the new data, a sand filled filter trench was constructed downstream of the lock guide wall in order to intercept the water bearing solution channels which were discharging through a spring. The objective was to reduce the water velocity in order to prevent the movement of solid material. In 1970 a line of grout holes was performed downstream of the Georgia dike. During 1971, several small sinkholes were discovered at the Alabama dike toe and simultaneously pin boils were found in the relief well collector ditch in the same area. In 1978 a new design recommended the installation of a positive cut-off wall under the earth embankment to upgrade the dam to current standards. This recommendation was adopted, and a 24 inches thick concrete cut-off wall was installed to the bottom of the shell layer within the earthy limestone. In limited areas, in accordance with a previous soil investigation, the cut-off was installed deeper, generally to the bottom of the Shell Limestone. Phase I of the cut-off was installed under a portion of the Georgia dike in 1981 and Phase II was installed beneath an additional portion of the Georgia dike and the Alabama dike between 1983 and In 1982, between the two phases of construction, a boil was observed on the water surface immediately downstream of the Power House. The entrance point, called the "Hungry Hole". was plugged with a tremie pipe. The eroded channel under the Power House was filled with 175 c.y. of tremied concrete. Additional grouting was performed along the upstream face of the power house and part of the spillway. Figure 1: Aerial View of Cut-Off Wall Those efforts were only partially successful and resulted in a concentration of the seepage below the concrete structure. The seepage problems at the W. F. George dam continued to worsen. Discharges from piezometers SP-5 and from the power House drainage system increased. As the Shell Limestone material was piped from under the concrete structure, the passage ways through which the flow was occurring were being enlarged resulting in greater erosion. This situation compromised the generating potential of the dam as well as potentially jeopardized its stability. Finally, the decision was made to construct a deep cut-off primarily under the concrete portion of the dam to remedy the problem. (See Figures 1 and 2.) PROCUREMENT On July 5th, 2001, best and final offers were solicited by the Corps of Engineers (COE) for the construction of a deep cut-off to be built in front of the concrete portion of the dam from the bottom of the lake and tied into it. The cut-off had to cross an existing lock structure and an underwater retaining wall, as well as the remnants of a steel coffer cell left in place from the initial construction. The specifications required that the wall be built with a minimum thickness of 24" and that it extended from the bottom of the lake to elevation -5 into the Providence formation, an impervious layer.
3 While the land portions of the wall were on average 208 feet deep, the marine portion started from up to 90 feet of water and continued through different rock formations for another 100 feet. Contractors were invited to propose their own method of constructing the cut-off and offers were evaluated using several criteria, including technical, economic, and organizational and experience. Three proposals were received and on August 14, 2001 an award was made to the Joint Venture (JV) of Treviicos and Rodio. GEOLOGICAL CHALLENGES AND PROPOSED TECHNOLOGIES The geological challenges to overcome during the cutoff wall construction consisted in the existence of a very hard stratum (up to PSI) overlaying a loose sand layer, the presence of voids, fractures and pathways in the rock mass and the existence of sediments and various debris at the lake bottom. Nevertheless it was not requested; the proposal contemplated a preliminary drilling and grouting campaign in order to verify ground conditions and to fill any large voids which could disrupt the orderly progress of the work. Treviicos-Rodio proposed to do the marine portion of the work with secant piles installed using reverse circulation top-pile rigs and using water as drilling fluid, while the land portion would be a slurry wall done by Hydromill, using bentonite as a stabilizing fluid. of safety, quality, environmental, technical and economical conditions and requirements. Safety was considered in employing a technology able to reduce to the minimum the diving operation and the risks involved in performing underwater work at depths of almost 100 feet and in such operation. Quality was considered in employing the secant piles technology as the most reliable to do the marine portion of the work. Environmental concerns were considered in employing a reverse circulation methodology which allowed the use of water as circulation fluid and the elimination of any type of slurry from contaminating the lake environment. Technical concerns were considered in researching and detailing each different phase and challenge of the various areas of the project. Economical concerns were reduced in evaluating and implementing all the above considerations and insuring that the project team was formed by experienced personnel. A very detailed technical proposal containing documents, drawings and method of statements were submitted with the bid. However, to insure the client that the proposal and the project challenges were studied, detailed and covered by the design and build proposal, it was decided to include in the presentation a video CD showing and describing the various phases of the marine work. CONSTRUCTION METHODS The construction methods used are summarized in the following sequence of mainly marine operations: Drilling and Grouting Campaign Figure 2: Plan View of the Cut-Off Wall The chosen method for the marine work construction was the result of detailed analysis As explained, the specifications were not requiring the performing of any extra soil investigation. However, since the bid preparation it was decided to propose to drill a series of exploratory holes along the axis of the cut-off wall. (See Figure 3.) The results expected and obtained were to reduce the uncertainties over the extent of the Karstic phenomenon. The exploratory investigation,
4 which was the first of the marine operation performed, consisted in: Localized borings to ascertain: - Depth of sediments - Presence of fill materials placed upstream of the dam during construction - Thickness of hard sandy limestone layer - Characteristic of sand layer (apparently none cemented) within the sandy limestone Grout holes to fill major cavities, possibly with high water flows Installing Casing Templates Tied to the Concrete Dam Whenever possible, guide beams and templates were installed and secured to the concrete dam structures. The main beam was mounted on the props connected to the fenders of the dam. Its position and alignment was checked using reference points previously installed on the dam during the initial survey. (See Figure 4.) Figure 4: Standard Templates Figure 3: Drilling and Grouting Cleaning of the Lake Bottom and Constructing a Working Apron The construction underwater of an apron was required to insure the correct installation and positioning of the cutoff wall at the lake bed elevation. A cleaning operation in front of the dam structure was requested before the apron installation. Obstructions and debris were found in large quantities from the dam construction and from years of operation. After all the obstructions were removed the apron was installed excavating a six foot minimum trench was and then backfilled with engineering material along the cut-off wall alignment. When it was possible to attach the template to the dam, temporary piles were driven to support the original or a modified template. The templates were used to insure the correct piles positioning and to guide the temporary casing while installing and driving them into the apron. Drilling and Concreting Piles The cutoff wall designed using 50 inch secant piles, spaced 33 inches center to center. The piles were installed in a sequence of primary and secondary, in which the secondary piles were drilled between the two adjacent primary piles. (See Figures 5 and 6.) The piles were installed to form a continuous wall of the minimum thickness of 24 inches, from the lakebed to El - 5 MSL, into the Providence formation.
5 It has a rotary drill table mounted on the top of a frame, and a working platform. The rig is fixed on the top of the casing by means of clamps. A jib positioned on the top pile rig platform facilitates handling of rods. (See Figure 7.) Figure 5: Phase I Primary Piles Installation Figure 6: Phase II Secondary Piles Installation Typically, the execution of the piles entailed the following steps: Installation of the temporary casing supported and guided for the steel template Setting the reverse circulation rig on top of the temporary casing Drilling to design depth Removal of the drilling string Setting tremie pipes and pouring concrete Withdrawal of casing and setting in a new pile position Water pumped from the lake was used as drilling fluid. The main equipment for the installation of the secant piles was the following: Pontoons and spoil barges Manitowoc 4000 Crawler service cranes positioned on the pontoons Templates for the installations of casings Wirth PBA 612 reverse circulation rig ICE hammers to install the casing ICE 160 Hydraulic pile hammers to install the casing through hard strata IR 960 high pressure compressors Vertically control device The secant pile cut-off wall was drilled to full depth using the Wirth PBA 612 reverse circulation rig mounted on top of the 50 casing. Figure 7: Reverse Circulation Rig On the top of rotary table there is a two way swivel, discharging the cuttings into a 10 hose. The compressed air for drilling is supplied by means of 4pipes and hoses, connected to a swivel below the rotary table. Specially designed stabilizers were used in order to maintain the verticality of the drilling string during drilling operations. Flanged double wall drillings rods, 10 feet long with 6 " inner cuttings conduit and air conduit and the drilling bit completed the drilling equipment All the cuttings excavated by the reverse circulation rigs passed through a 10 discharge pipe and were delivered to the hopper barge. From this barge the cuttings were deposited to the bottom of the lake. Silt curtains, installed around the hopper barge, prevented the
6 contamination of the lake water by the spoil material. while secant piles did the rest of the crossing. (See Figure 9.) Constructing the Slurry Wall Slurry wall installation was the technology chosen to install the land portion of the cut-off wall, to cut the lock concrete monolith and the underwater retaining wall. (See Figure 8.) Figure 9: Construction of the Secant Pile Wall in the Water Figure 8: Construction of Slurry Wall on Land The cut-off wall installed using the slurry wall was built by primary and secondary panels using a Soletanche HI 2000 series Hydromill. The primary panel was formed by single or multiple bites with a total excavation length of 8 to 24 feet. The secondary panels overlapping the primaries were a single 8 foot bite. The de-sanding plant was a Sotres-450 consisting of a series of vibrating screens and cyclones capable of screening all the cutting sizes with a capacity of 500 cu. yd. per hour. Constructing the Cut-Off through the Lock Structure The crossing of the lock structure was accomplished by using the Hydromill on the Georgia side to cross the eastern retaining wall, With the Hydromill equipment, vertical excavation within required tolerance is assured when both cutter wheels mill similar material in terms of hardness and consistency. (See Figure 10.) On the Georgia side, the sloping contact between the soil embankment and the monolithic wall did not allow for the wall to be built in the correct sequence of primary and secondary panels, due to the fact that no panel could be excavated through the inclined concrete surface without a vertical guide The solution was to re-create in advance a uniform condition where: The inclined surface had been removed by a preliminary reaming of the wall The adjacent soil had been replaced by concrete Under this modified conditions, the standard sequence of overlapped primary and secondary panels was correctly carried out.
7 In detail the following steps were adopted: Construction of the slurry wall up to the last panel touching the monolithic wall foundation Milling the first adjacent bite passing through the wall for a certain depth Figure 11: Lock Structure Crossing Connection to Secant Pile Wall Figure 10: Hydromill and Guide Pipes The connection between slurry wall and secant piles was located in the footprint of the eastern monolith. Note that when the Hydromill reached the inclined hard surface, it reacted against and was guided by the previously concreted panel acting as a shoulder. This did not allow any lateral deviation After entering in the entire concrete mass for several feet, the excavation was stopped and the panel was concreted The same procedure was repeated in single bites in an uphill progression until the entire inclined surface was entirely reamed and the soil replaced by concrete. The last panel in this sequence was excavated and left open. After this operation, the slurry wall was built at full depth, re-excavating the newly placed concrete as well as the remaining portions of the lock wall with the proper sequence of primary and secondary panels. (See Figure 11.) Figure 12: Hydromill on Pontoon
8 The following steps were carried out: The soil between the walls of the Lock was excavated under water from El 108 to the bottom of the walls at El 81, for a width of 15 feet. The lakebed westwards of the western monolith was dredged as well to the bottom of the wall The excavation as filled with 3000 psi concrete to elevation 108 The Hydromill then continued to remove the concrete from the center of the Eastern wall, progressing westward until the concrete has been removed to El 108. Cutter wheels on the Hydromill for this operation were 63 inches in width in order to accommodate the casings for the secant piles. The progression was aided by installing a steel casing to act as a vertical guide Construction of the wall by the secant pile method was advanced eastward using the guiding template across the lock, until it encountered the lock wall. A secondary pile overlapping the last panel and the first primary pile was the joint element between secant pile wall and slurry wall. At the completion of the secant pile portion, the cut of the retaining wall was repaired. Constructing the Permanent Concrete Cap Tying the Cut-Off to the Dam The construction of the cap beam was done upon completion of the cut-off installation. Depending on the cut-off wall's position and the apron elevation, a portion, or all, of the engineered backfilling between the cut-off wall and the dam was removed in order to install the cap beam. The surfaces of the monoliths and of the cut-off wall were cleaned to insure a proper joint before pouring the 3000 psi. concrete of the cap beam. Figure 13: Cutting East Lock Monolith with Hydromill CONCLUSIONS The construction of a deep under water cut-off had never been attempted before and its successful completion will open new possibilities to Engineers and Owners on how to deal with difficult underwater seepage problems. The result obtained were the consequence of awarding the project to qualified companies and the assembling of a team of highly qualified experts working together from the bid preparation and through the completion of all the difficult phases of the project.
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation
Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 JRHill@HaywardBaker.com
More informationChapter 3 CULVERTS. Description. Importance to Maintenance & Water Quality. Culvert Profile
Chapter 3 CULVERTS Description A culvert is a closed conduit used to convey water from one area to another, usually from one side of a road to the other side. Importance to Maintenance & Water Quality
More informationSTRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.
STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill
More informationBUTE Department of Construction Management and Technology
BUTE Department of Construction Management and Technology 02.10.2012 Definition 1: Foundation: The structure, that transmits the load of the building to the soil Definition 2: Load bearing soil (strata):
More informationSafe & Sound Bridge Terminology
Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries
More informationDIRECTIONAL DRILLING
DIRECTIONAL DRILLING 1. General. Installation of pipelines through the levee embankment using directional drilling technology is prohibited. Installation of pipelines through a flood control project foundation
More informationSHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS
SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS Vince Luongo Petrifond Foundation Co., Ltd. PROJECT DESCRIPTION The York Durham Sanitary System (YDSS) Interceptor in the Town of Richmond Hill located
More informationIndex. protection. excavated drop inlet protection (Temporary) 6.50.1 6.51.1. Block and gravel inlet Protection (Temporary) 6.52.1
6 Index inlet protection excavated drop inlet protection (Temporary) 6.50.1 HARDWARE CLOTH AND GRAVEL INLET PROTECTION Block and gravel inlet Protection (Temporary) sod drop inlet protection ROCK DOUGHNUT
More informationTremie Concrete CM 420 CM 420 CM 420 CM 420. Temporary Structures. Tremie Concrete
Tremie Concrete Underwater concrete plays an important role in the construction of offshore structures. It may be used to tie together various elements in composite action (i.e., to tie piling to the footing).
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS
ITEM NO. 1103 POINT REPAIRS AND OBSTRUCTION REMOVALS 1103.1 DESCRIPTION: 1. Repair of sanitary sewer lines by replacing short lengths of failed pipe with new pipe. 2. Repair of service laterals located
More informationCHICAGO SANITARY AND SHIP CANAL AT LOCKPORT REHABILITATION CASE STUDY. Brant Jones, P.E. 1 Thomas Mack, P.E. 2 Amy Moore, P.E.
CHICAGO SANITARY AND SHIP CANAL AT LOCKPORT REHABILITATION CASE STUDY Brant Jones, P.E. 1 Thomas Mack, P.E. 2 Amy Moore, P.E. 3 ABSTRACT This paper will discuss the unique history and techniques for restoring
More informationGLOSSARY OF TERMINOLOGY
GLOSSARY OF TERMINOLOGY AUTHORIZED PILE LENGTHS - (a.k.a. Authorized Pile Lengths letter) Official letter stating Engineer's recommended length of concrete piles to be cast for construction of foundation.
More informationEmergency Spillways (Sediment basins)
Emergency Spillways (Sediment basins) DRAINAGE CONTROL TECHNIQUE Low Gradient Velocity Control Short-Term Steep Gradient Channel Lining Medium-Long Term Outlet Control Soil Treatment Permanent [1] [1]
More informationDesign and Construction of Auger Cast Piles
Design and Construction of Auger Cast Piles 101 th Annual Road School 2015 3/11/2015 Malek Smadi, Ph.D., P.E. Principal Engineer - GEOTILL - Fishers, IN msmadi@geotill.com - www.geotill.com CONTENTS 1.
More informationSUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS
July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional
More informationTECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL
TECHNICAL SPECIFICATIONS CEMENT-BENTONITE SLURRY TRENCH CUTOFF WALL SCOPE This section of the specifications includes requirements for the Slurry Trench Cutoff Wall and related work as indicated on the
More informationMoving Small Mountains Vesuvius Dam Rehab
Moving Small Mountains Vesuvius Dam Rehab Susan L. Peterson, P.E., regional dams engineer, Eastern Region, Bedford, IN Note: The following article, Moving Small Mountains Vesuvius Dam Rehab, by Sue Peterson,
More informationSECTION 02401 SHEETING, SHORING AND BRACING
SECTION 02401 SHEETING, SHORING AND BRACING This section should be edited to reflect soil conditions specific to the project site and the recommendations of a Geotechnical Engineer licensed in the State
More informationManaging Our Water Retention Systems
Managing Our Water Retention Systems 29th Annual USSD Conference Nashville, Tennessee, April 20-24, 2009 Hosted by Corps of Engineers On the Cover Wolf Creek Dam is on the Cumberland River in South Central
More informationNJ650.1404 Interception Drainage
NJ650.1404 Interception Drainage Interception drainage is used to intercept surface and subsurface water. The investigation, planning, and construction of surface interception drains follow the requirements
More informationState of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS
State of Illinois Department Of Transportation CONSTRUCTION INSPECTOR S CHECKLIST FOR STORM SEWERS While its use is not required, this checklist has been prepared to provide the field inspector a summary
More informationSECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS
SECTION 33 31 00.13 ABANDONMENT OF SEWER MAINS PART 1: GENERAL 1.01 SECTION INCLUDES A. Abandonment in place, by cutting and capping, of existing sewers, junction structures, manholes, service lines, and
More informationDRAINAGE MATS For Vertical: Flow 15-P For Horizontal: Flow 18-H
DRAINAGE MATS For Vertical: Flow 15-P For Horizontal: Flow 18-H Soil Drainage Mat with Built-In Protection Layer POLYGUARD DRAINAGE MATS are three-part prefabricated geocomposite drain consisting of a
More informationSECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.
02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily
More informationA perforated conduit such as pipe, tubing or tile installed beneath the ground to intercept and convey ground water. or structures.
BMP: SUBSURFACE DRAIN Definition A perforated conduit such as pipe, tubing or tile installed beneath the ground to intercept and convey ground water. PurRoses 1. To prevent sloping soils from becoming
More informationTable 4.9 Storm Drain Inlet Protetion Applicable for
BMP C220: Storm Drain Inlet Protection Purpose To prevent coarse sediment from entering drainage systems prior to permanent stabilization of the disturbed area. Conditions of Use Type of Inlet Protection
More informationUS Army Corps of Engineers BUILDING STRONG
Fort Worth District Public Meeting 20 August 2013 US Army Corps of Engineers Lewisville Dam - Authorization Authorized by the River and Harbor Act, approved 2 March 1945 (Public Law 14, 79th Congress,
More informationHow To Check For Scour At A Bridge
Case Studies Bridge Scour Inspection and Repair Edward P. Foltyn, P.E. Senior Hydraulic Engineer ODOT Bridge Unit 2013 PNW Bridge Inspectors Conference April 2013 REFERENCES Stream Stability at Highway
More informationSection 402. STORM SEWERS
402.02 Section 402. STORM SEWERS 402.01. Description. This work consists of constructing storm sewers of the size and class required, including excavation, bedding, and backfill. 402.02. Materials. Provide
More informationStormwater/Wetland Pond Construction Inspection Checklist
: Construction Inspection ChecklistsTools Stormwater/Wetland Pond Construction Inspection Checklist Project: Location: Site Status: Date: Time: Inspector: SATISFACTORY/ UNSATISFACTORY COMMENTS Pre-Construction/Materials
More informationBMP-7. A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet.
BMP-7 BMP: STORM DRAIN INLET PROTECTION Definition A sediment filter or an excavated impounding area around a storm drain drop inlet or curb inlet. To prevent sediment from entering storm drainage systems
More informationSECTION 411 DRILLED PIERS
Section Payment will be made under: Pay Item Foundation Excavation Foundation Excavation for Bent No. at Station Foundation Excavation for End Bent No. at Station Pay Unit Cubic Yard Lump Sum Lump Sum
More informationOutlet stabilization structure
Overview of Sedimentation and Erosion Control Practices Practice no. 6.41 Outlet stabilization structure Erosion at the outlet of channels, culverts, and other structures is common, and can cause structural
More informationSAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS
Page 1 of 9 SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS 1. GENERAL REQUIREMENTS 1. Description of Work: This work consists of furnishing all materials, equipment and
More informationSECTION 1 GENERAL REQUIREMENTS
Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,
More informationLockport Pool Chicago Sanitary & Ship Canal Illinois Waterway
Presentation to the Inland Waterways Users Board Lockport Pool Chicago Sanitary & Ship Canal Illinois Waterway by Gary Loss, P.E. Rock Island District July 13, 2006 Chicago Sanitary and Ship Canal A
More informationEmergency repair of Bridge B421
Emergency repair of Bridge B421 over the Olifants River after fl ood damage INTRODUCTION AND BACKGROUND Bridge B421 is located on the R555 at km 5.03 on Section 01E between Witbank (now known as emalahleni)
More informationBRIDGES ARE relatively expensive but often are
Chapter 10 Bridges Chapter 10 Bridges Bridg Bridges -- usually the best, but most expensive drainage crossing structure. Protect bridges against scour. BRIDGES ARE relatively expensive but often are the
More informationSECTION LS 2530 SANITARY SEWERS. A. General: Submit the following in accordance with The General Conditions.
SECTION LS 2530 SANITARY SEWERS PART 1 GENERAL 1.1 SUBMITTALS A. General: Submit the following in accordance with The General Conditions. 1. Product data for drainage piping specialties. 2. Shop drawings
More informationSection 2100-Trenching and Tunneling
SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial
More informationLand Disturbance, Erosion Control and Stormwater Management Checklist. Walworth County Land Conservation Department
Land Disturbance, Erosion Control and Stormwater Management Checklist Walworth County Land Conservation Department The following checklist is designed to assist the applicant in complying with the Walworth
More informationUse of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair
Use of a Reinforced Jet Grout Excavation Support System for a Major Sewer Line Repair Eric M. Klein, P. E., Rummel, Klepper & Kahl, LLP, Baltimore, Maryland Kenneth B. Andromalos, P. E., Brayman Environmental,
More informationCOSMOS 2012: Earthquakes in Action COSMOS 2012
COSMOS 2012 What is SFSI and why is it important? Soil issues in Earthquakes Structures where SFSI important Retaining structures (lateral earth pressure) Foundations (spread and pile footings, bearing
More informationUNDER DRAINAGE AND FILTER DESIGN
UNDER DRAINAGE AND FILTER DESIGN Tailings and HLP Workshop 28 April to 1 May 2010 INTRODUCTION The internal drainage is of crucial importance to the reliability and safety of a tailings dam throughout
More informationFlood mitigation program for Gatun lake. Programa de mitigación de inundaciones del lago Gatún
Flood mitigation program for Gatun lake Programa de mitigación de inundaciones del lago Gatún Moffatt & Nichol Engineers 10 de febrero de 2005 Contrato No. 126161 Introducción y Recomendaciones 1 INTRODUCTION
More informationSECTION 33 11 00.19 ABANDONMENT OF WATER MAINS. A. Conform to requirements of Section 01 33 00 - Submittals.
SECTION 33 11 00.19 ABANDONMENT OF WATER MAINS PART 1: GENERAL 1.01 SCOPE A. Abandonment in place, by cutting and capping, of existing water mains, hydrants, service lines, and valves. B. Abandonment in
More information3. Contractor shall ensure that all permits are obtained prior to any construction. Contractor shall be responsible for all utility fees.
The following shall serve as the minimum requirements for contractors performing work in relation to the Authority s potable water and sanitary sewer system(s), appurtenances and service connections. General:
More informationSE-10 STORM DRAIN INLET PROTECTION. Objectives
STORM DRAIN INLET PROTECTION SE-10 Objectives Erosion Control - EC Sediment Control - SE Tracking Control - TC Wind Erosion Control - WE Non-Storm Water Management - NS Waste and Materials Management -
More informationCLIFTY CREEK PLANT MADISON, INDIANA
2015 DAM AND DIKE INSPECTION REPORT GERS-15-018 CLIFTY CREEK PLANT MADISON, INDIANA PREPARED BY GEOTECHNICAL ENGINEERING AEP SERVICE CORPORATION 1 RIVERSIDE PLAZA COLUMBUS, OHIO Annual Dam and Dike Inspection
More informationThe Manitoba Water Services Board SECTION 022180 Standard Construction Specifications PIPE EXCAVATION, BEDDING AND BACKFILL Page 1 of 11
Page 1 of 11 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the excavation of trenches (or excavation of tunnels); the supply and placing of bedding and backfill materials;
More informationCity of Shelbyville Site Inspection Checklist
City of Shelbyville Site Inspection Checklist General Information Project Name: KYR10 Permit Number: Date: Project Location: Contractor: Conractor Representative: Inspector's Name: Title: Signature : Weather
More informationRIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.
RIPRAP From Massachusetts Erosion and Sediment Control Guidelines for Urban and Suburban Areas http://www.mass.gov/dep/water/laws/policies.htm#storm Definition: A permanent, erosion-resistant ground cover
More informationSECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)
SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains
More informationA CASE-STUDY OF CUA_DAT CFRD IN VIETNAM
A CASE-STUDY OF CUA_DAT CFRD IN VIETNAM Giang Pham Hong, Michel Hotakhanh, Nga Pham Hong, Hoai Nam Nguyen, Abstract:Dams have been taken an important role in time and surface redistribution of water for
More informationSection 02415. Installation of pipe and casing for sanitary sewer by methods of augering.
ITY OF PRLN UGRING PIP OR SING FOR SWRS Section 02415 UGRING PIP OR SING FOR SWRS 1.0 G N R L 1.01 STION INLUS Installation of pipe and casing for sanitary sewer by methods of augering. References to Technical
More informationSEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST
SEDIMENT/STORMWATER MANAGEMENT BASIN CONSTRUCTION CHECKLIST For permanent structures per Delaware SCS Pond Code 378 and Delaware Sediment and Stormwater Regulations KEY PROJECT INFORMATION Item meets standard
More informationITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT
ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT Description: This work shall consist of furnishing all materials, equipment and labor necessary for conducting an Osterberg Cell (O-Cell) Load
More informationLS 2540 SEWER LATERALS AND INSPECTION TEES
LS 2540 SEWER LATERALS AND INSPECTION TEES A. Summary B. Submittals C. Site Information D. Sewer Pipe and Fittings E. Lateral Locations F. Lateral Installation G. Inspection Tee Installation H. Removal
More informationPROJECT COST ESTIMATE ASSUMPTIONS AND EXCLUSIONS
C PROJECT ESTIMATE ASSUMPTIONS AND EXCLUSIONS In support of the alternatives development process, preliminary cost estimates were prepared for each of the three Candidate Build Alternatives. The cost estimates
More informationChapter 9 Remedial Measures
[This is an annotated version of a chapter from the US Army Corps of Engineers book, Foundations in Expansive Soils. This book is in the public domain. This document is consists of an abbreviated and annotated
More informationThe work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.
More informationEngineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.
TM TM Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. SM The Leading Edge. 10 One Major Causes of foundation settlement or more conditions may
More informationWelded Mesh Gabions and Mattresses River Protection Design Guide HY-TEN GABION SOLUTIONS Dunstall Hill Trading Estate, Gorsebrook Road,
Welded Mesh Gabions and Mattresses River Protection Design Guide HY-TEN GABION SOLUTIONS Dunstall Hill Trading Estate, Gorsebrook Road, Wolverhampton, WV6 0PJ Tel 01902 712200 Fax 01902 714096 e-mail sales@hy-tengabions.com
More informationPERMEABILITY TEST. To determine the coefficient of permeability of a soil using constant head method.
PERMEABILITY TEST A. CONSTANT HEAD OBJECTIVE To determine the coefficient of permeability of a soil using constant head method. need and Scope The knowledge of this property is much useful in solving problems
More informationCONSTANT HEAD AND FALLING HEAD PERMEABILITY TEST
CONSTANT HEAD AND FALLING HEAD PERMEABILITY TEST 1 Permeability is a measure of the ease in which water can flow through a soil volume. It is one of the most important geotechnical parameters. However,
More informationSECTION 33 31 00.11 GRAVITY SANITARY SEWERS
SECTION 33 31 00.11 GRAVITY SANITARY SEWERS PART 1: GENERAL 1.01 SCOPE A. Gravity sanitary sewers and appurtenances. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 Submittals. B. Submit
More informationLighthouse Engineering, L.L.C.
Registered Engineering Firm (F: 9334) Phone: 214-577-1077 Fax: 214-224-0549 Website: www.lighthouseeng.com Email: Office@LighthouseEng.com Thursday, September 04, 2014 TO: Our Client RE: Initial Engineering
More informationHighway 23 Paynesville Richmond Soils Borings, Soils Tests, and Reporting
Highway 23 Paynesville Richmond Soils Borings, Soils Tests, and Reporting MnDOT Contract No. 1003249 General Project Overview This work is located along Trunk Highway (TH) 23, for State Project (SP) 7305-124.
More informationJackson Gulch Outlet Canal Rehabilitation Project
Jackson Gulch Outlet Canal Rehabilitation Project Preliminary Budgetary Estimate for Rehabilitation February 2004 Prepared for the Mancos Water Conservancy District Jackson Gulch Reservoir 42888 County
More informationStructures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS
Structures Construction Pre-Work Checklist PRE-WORK SHEET FOR PROJECT MANAGERS 1 Proposal & Plans Received? 2 Review Proposal, highlight important facts. Know proposal well to be able to find answers quickly.
More informationDESCRIPTION OF WORK:
DEPARTMENT OF PUBLIC WORKS COUNTY OF HENRICO P.O. BOX 27032 RICHMOND, VIRGINIA 23273 PERMIT NO. One (1) copy of application and four (4) copies of plans are hereby made to the Director of Public Works
More informationStorm Drain Inlet Protection
Objectives EC Erosion Control SE Sediment Control TR Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Objective
More informationTECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe
TECHNICAL NOTE Culvert Sliplining and Lining of Casings with HPPipe TN 5.14 February 2010 Introduction It may be at times necessary, in an aging infrastructure, to rehabilitate drainage and sanitary lines
More informationFY11 Sanitary Sewer Main Rehab and Point Repair Bid Tabulation
644-10-569 Page 1 of 9 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING
More informationHigh Strain Dynamic Load Testing of Drilled Shafts
Supplemental Technical Specification for High Strain Dynamic Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 3, 2015 1.0 GENERAL This work shall consist of performing high-strain
More informationFY08 SEWER POINT REPAIRS BID TABULATION
6-07-831 Page 1 of 12 1 FOR CLEANING AND TELEVISING EXISTING SEWERS, AS SPECIFIED, ANY REQUIRED CLEANING, ANY LOCATION, ANY LENGTH OF SEWER, COMPLETE IN PLACE, FOR VARIOUS PIPE DIAMETERS. A. EXISTING "
More informationSan Antonio Water System Standard Specifications for Construction ITEM NO. 1100 SLIP-LINING SANITARY SEWERS
ITEM NO. 1100 SLIP-LINING SANITARY SEWERS 1100.1 DESCRIPTION: This item shall consist of slip-lining sanitary sewer pipe, which is accomplished by pulling or pushing liner pipe into existing sewers by
More informationCalifornia Department of Transportation Doyle Drive Test Program Contract No. 04A3362
California Department of Transportation Doyle Drive Test Program Deep Soil Mixing (DSM) /Cutter Soil Mixing (CSM) Testing Report By Malcolm Drilling Company, Inc. 3524 Breakwater Ave., Suite 108 Hayward,
More informationHow to Design and Build a Fence/G traverse Bridge or Graffiti Project
Outline Project Location Project Description Project History Site Constraints Geotechnical Investigation & Soil Profile Foundation Design Process Photos Project Location Project Limits: The Grand River
More informationSIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes)
SIERRA LAKES COUNTY WATER DISTRICT P.O. Box 1039, Soda Springs, CA 95728-1039 (7300 Short Road, Serene Lakes) Maintenance Office Administrative Office Billing Office 530-426-7802 530-426-7800 916-332-4872
More informationMachine Foundation Design
Machine Foundation Design As the structural engineer who recently designed the machine foundation for one of the largest vertical turning and milling centers in the country, in addition to over 250 other
More informationMETHOD OF STATEMENT FOR STATIC LOADING TEST
Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents
More informationWatershed Works Manual
National Rural Employment Guarantee Act Watershed Works Manual DRAINAGE LINE TREATMENT: GABION STRUCTURE Baba Amte Centre for People s Empowerment Samaj Pragati Sahayog September 2006 Drainage Line Treatment:
More informationResidential Foundations and Basements
Residential Foundations and Basements Disclaimer All of the following information is based on the 2006 International Residential Code with Kentucky Amendments. As some information is paraphrased, article
More informationUNIFIED FACILITIES CRITERIA (UFC) DEWATERING AND GROUNDWATER CONTROL
UFC 3-220-05 16 January 2004 UNIFIED FACILITIES CRITERIA (UFC) DEWATERING AND GROUNDWATER CONTROL APPROVED FOR PUBLIC RELEASE; DISTRIBUTION UNLIMITED UFC 3-220-05 16 January 2004 UNIFIED FACILITIES CRITERIA
More informationSample Project with SlurryTBM according to Anagnostou and Kovári
1 General Sample Project with SlurryTBM according to Anagnostou and Kovári The aim of the document is to provide information about the required input parameters and the necessary steps for the calculation
More informationThe unit costs are based on the trend line of the 3 low bids for the average quantity.
Page 1 of 8 COST ESTIMATE GENERAL INSTRUCTIONS The unit costs are based on the trend line of the 3 low bids for the average quantity. Apply the Unit Costs to ordinary structures. Unit Costs should generally
More informationARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R00060057. Lecturer: Jim Cahill
ARCHITECTURAL TECHNOLGY 4 ADVANCED CONSTRUCTION TECHNOLOGY BASEMENT CONSTRUCTION YEAR 3 SEMESTER 1 AIDAN WALSH R00060057 Lecturer: Jim Cahill 29 th November 2011 TABLE OF CONTENTS SUMMARY 1 MAIN BODY SECTION
More informationSECTION 5: SANITARY SEWER SYSTEM DESIGN
SECTION 5: SANITARY SEWER SYSTEM DESIGN 5.01 GENERAL Sanitary sewer improvements shall be designed to serve the ultimate level of City development as defined in the General Plan and the Wastewater Facilities
More informationCITY UTILITIES DESIGN STANDARDS MANUAL
CITY UTILITIES DESIGN STANDARDS MANUAL Book 2 (SW) SW9 June 2015 SW9.01 Purpose This Chapter provides information for the design of open channels for the conveyance of stormwater in the City of Fort Wayne.
More informationSPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION
SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION 1. SCOPE Pipe subsoil drains shall be constructed in accordance with this specification and in conformity with the lines, grades and cross-sections shown
More informationSeptember 1, 2003 CONCRETE MANUAL 5-694.900 CONCRETE PAVEMENT REHABILITATION 5-694.900
September 1, 2003 CONCRETE MANUAL 5-694.900 5-694.901 GENERAL CONCRETE PAVEMENT REHABILITATION 5-694.900 Concrete Pavement Rehabilitation is an extremely valuable tool of the Minnesota Department of Transportation
More informationSECTION 31 20 00 EARTH MOVING
SECTION 31 20 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for excavating, filling, and grading for earthwork at Parking Structure, new exit stair and as required to
More informationStorm Drain Inlet Protection
Categories EC Erosion Control SE Sediment Control TC Tracking Control WE Wind Erosion Control Non-Stormwater NS Management Control Waste Management and WM Materials Pollution Control Legend: Primary Category
More informationUnit Price Averages Reports
Unit Price Averages Reports 12/7/2015 UNIT PRICE AVERAGES REPORT Disclaimer The information provided in the following Unit Price Averages Report is only for the use of Alberta Infrastructure & Transportation
More informationProposed Minimum Subterranean Termite Treatment Standards
Proposed Minimum Subterranean Termite Treatment Standards Introduction This document is intended to serve as a model for states considering the adoption of standards for soil application of termiticides.
More informationTYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR
TYPES OF PIERS USED IN NORTH AND EAST TEXAS RESIDENTIAL FOUNDATION REPAIR If you listen to the hype, it sounds like there must be 20 or 30 different types of piers out there. Company A says they have an
More informationSTANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS
STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for cleaning and lining existing cast iron and ductile iron water mains
More informationEurocode 7 - Geotechnical design - Part 2 Ground investigation and testing
Brussels, 18-20 February 2008 Dissemination of information workshop 1 Eurocode 7 - Geotechnical design - Part 2 Ground investigation and testing Dr.-Ing. Bernd Schuppener, Federal Waterways Engineering
More informationGas Meter Clearances and Service Installation Requirements
March 2016 Gas Meter Clearances and Service Installation Requirements Builder/Owner/Developer Requirements Call PSE's Customer Construction Services 1 888 321 7779 or visit PSE.com/CustomerConstruction
More information