Capital budgeting - 1

Size: px
Start display at page:

Download "Capital budgeting - 1"

Transcription

1 Capital budgeting - 1 CORPORATE FINANCE - 1 UNIVERSITY OF EXETER MARK FREEMAN, 2004 Week 5 1

2 Project valuation Today, you are going to value the following project. Initial cost of the project: 2.5m to be invested immediately. The best projection for the number of items sold for the next seven years is (with nothing after this): Year Sales Next year you expect to be able to sell these items at 100 each. There is a fixed cost of production each year of 500,000 and a variable cost of production of 25 an item. You pay no corporate tax The risk-free rate currently stands at 5% and inflation is at 3%. You believe that these cashflows should be discounted at a risk premium of 8%. Week 5 2

3 Cashflows The first thing you must do is to calculate the net cashflow. Now, it is very important that you remember to include the inflation component when calculating the cashflows. If you don t do this, you will be in trouble. Year Invested ( m) (2.50) Sales T/o ( m) Fixed (0.50) (0.52) (0.53) (0.55) (0.56) (0.58) cost ( m) Variable (0.25) (0.52) (0.58) (0.66) (0.68) (0.35) cost ( m) Net Cashflow ( m) (2.50) Week 5 3

4 Payback periods The first way of evaluating this project is to calculate the payback period. How long does it take you to get back the initial 2.5m? By the end of year 1 you will have 0.25m By the end of year 2 you will have 1.27m By the end of year 3 you will have 2.49m You need 2.5m to payback the initial investment. So, a further m = 0.01m is needed. The payback period is therefore almost exactly 3 years. The advantage of using the payback period for evaluating projects is that it is simple and may be useful for companies that have serious problems with cash flow management. There are many disadvantages. It takes no account of the time value of money. It penalizes long-term projects in favour of short-term projects. Week 5 4

5 Discounting the cashflows When evaluating this project, the time value of money should be taken into account. First, we will discount the cashflows at the required rate of return. The risk-free rate is 5% and you require an 8% risk premium for this project. In other words, the required rate of return (or discount factor ) for this project is 5% + 8% = 13%. Using this to get the discounted cashflows (DCF) Year Net Cashflow ( m) (2.50) Discount factor DCF ( m) (2.50) The first thing we can do now is calculate the discounted payback period. Using the DCF numbers it is apparent that the discounted cashflows pay off the initial investment in 3 years and 8.6 months. Week 5 5

6 Net Present Value (NPV) The next way of doing the analysis is just to add up all the DCFs to get the net present value (NPV). NPV = (2.50) = 1.26m. The decision rule based on NPV analysis is: Positive NPV Negative NPV Good project Bad project Given that this is positive, this appears to be a good project. As we will see below, NPV analysis will be our chosen method of project appraisal. Before we reach this conclusion, though, we must consider some alternatives Week 5 6

7 Internal Rates of Return (IRR) Rather than discounting at 13% and then calculating the NPV, the alternative is to see what discount rate would give an NPV of zero. This is called the internal rate of return (IRR). Using the Tools/Goals Seek method in Excel that we saw in week 1 we can work out the IRR. It is 27.67%. As this is above the hurdle rate of 13%, we should undertake this project NPV % 5% 10% 15% 20% 25% 30% Discount rate Week 5 7

8 Changing the project Suppose that, we can secure a further order from a customer that will be worth 4m in revenue at the end of the third year. This will lead to additional incremental costs of 7.4m. However, we can defer these costs to 2.9m at the end of the fifth year and a further 4.5m at the end of the sixth year. Does this new order make the project more or less attractive to us? It is obvious that this is a bad deal. The effective rate of return that we are paying on this new order is: = + (1+ r ) 2 (1+ r) 3 Solving, r = 26.94%. For a project with a discount rate of 13%, this effective interest rate of 26.94% that we are paying to secure the new order is clearly too high. How does this look if we put it into our project analysis? Payback is now clearly within three years, as the cash inflow from the new order will pay off the initial investment. Week 5 8

9 Changing the project - 2 Consider the cashflows now: Year Project Cashflow (2.50) New 4.00 (2.90) (4.50) order New net (2.50) (1.42) (4.03) Cashflow Discount factor DCF ( m) (2.50) (0.74) (1.93) The NPV is now = 0.35m This NPV is lower than it was without the new order (when the NPV was 1.26m). Therefore, the decision rule that the higher the NPV the better the project works in this case. Week 5 9

10 Changing the project - 3 If we work out the IRR of the project, though, there are two problems. 1) There is an internal rate of return = 28.70%. This is higher than the IRR without the new order (which was 26.94%). So, higher IRR does not mean better project. 2) There is a second IRR of 0.142%. That is, the IRR is not unique. What does this mean? NPV % 5% 10% 15% 20% 25% 30% Discount rate Week 5 10

11 Multiple IRRs When, and why, do we have this problem of multiple IRRs? This arises when, after the initial investment, the net cashflows are sometimes positive and sometimes negative. In this example, the net cashflows start positive and end negative. As the discount rate increases this has two offsetting effects: 1) It makes the cashflows from the project less valuable in present value terms 2) Our obligations in years 5 and 6 also have a lower present value. Therefore, there are offsetting effects from increasing the discount rate. That is why the last graph is strangely nonlinear and why multiple IRRs exist. The more often the net cashflow changes between positive and negative, the more IRRs can potentially exist. Week 5 11

12 Accounting ratios Some managers like to evaluate projects on the basis of accounting ratios. For example, you could calculate a return on capital employed (ROCE) each year: ROCE = year Accounting profit after depreciation and tax Book value of capital employed at beginning of There are several reasons why this method is not favoured in finance. First, and most importantly, this number depends on somewhat subjective accounting conventions. Second, as this ratio varies year by year, it is not clear how to interpret it. The finance community prefers to use cashflows rather than accounting profits since cashflow numbers are uncontroversial. This technique is still quite commonly used in practice, however, as many senior finance directors come from an accounting background and are more confident dealing with accounting numbers than projecting cashflows. Week 5 12

13 In summary We have looked at four possible methods of evaluating projects. 1) NPV 2) IRR Problem with multiple IRRs 3) Payback period Undervalues long-term projects 4) ROCE Subject to accounting conventions The preferred method is NPV because: a) The decision rules are easy. You should (should not) undertake the project if the NPV is positive (negative). The higher the NPV, the better the project. It is unique. b) The technique is identical to the methods that we used to price Treasury securities and the discounted dividend model for valuing stock. The discounted cashflow method is a general method of valuing investment opportunities c) There is no subjectivity over accounting conventions. d) For those of you who like a very solid theoretical grounding for your methods, there is a fundamental theorem of asset pricing which demonstrates unambiguously that the NPV method is correct when excluding project flexibility. Week 5 13

14 What do practitioners actually use? Graham and Harvey (2001, Journal of Financial Economics) undertake a major survey of US corporations to see what corporate finance practices they actually use. They find that the following proportion of CFOs almost always use the following techniques 1 : Technique % managers using IRR 76% NPV 75% Payback period 57% Sensitivity analysis 52% Discounted payback 29% Real Options 27% ROCE 20% We will return to real options later in the course. 1 Other methods are also used by corporations, but these are much less important than NPV / IRR. Week 5 14

15 The fundamentals of NPV analysis There are three steps that must be completed before we can undertake an NPV analysis: 1) We must estimate the expected pre-tax cashflows from the project for each period between the date that the project is started and the date it terminates. 2) We must calculate the tax implications of these cashflows. 3) We must calculate the appropriate discount rate to use. For the rest of this class we shall concentrate on the fundamentals of estimating pre-tax cashflows. Week 5 15

16 Inflating the cashflows In the example given above, it was emphasized that we had to inflate the cashflows. Why? The required rate of return was calculated by adding a risk premium of 8% onto the risk-free rate of 5%. But this risk-free rate of 5% includes an inflation term of 3% and a real risk-free rate term of 1.94% (From Fisher s theorem, 1.05 = 1.03 x ). That is, the discount rate includes the inflation component already. To be consistent, therefore, we need also to include the inflation element into our cashflows. This is called nominal discounting we include inflation in both the discount rate and the cashflows. Week 5 16

17 Real vs. nominal analysis Some people do real discounting that is, they remove the inflation component from the discount rate and then do not inflate the cashflows. If done correctly this should always give the same answer. My advice, though, is to do nominal analysis. The main reason for this is that certain cashflows do not inflate whatever happens to the inflation rate. In the example given above, the cashflows to and from the venture capitalist are not inflated. Of particular importance will be tax-related cashflows. These never inflate. So, if you do real analysis, not only do you have to deflate the discount rate, you also need to deflate certain cashflows. So, while doing real analysis is completely correct if done properly, my view is that you are more likely to make mistakes this way. For this reason, all the examples in this class will be done nominally. Week 5 17

18 What cashflows do we discount? We define the relevant net pre-tax cashflows as follows: Pre-tax Cashflow = Cash received from sales - Cash paid out on operating expenses - Capital outlays as they occur - Increases in net working capital Or, comparing with profit: Pre-tax Cashflow = Earnings before interest and tax + Non-cashflow expenses (mainly depreciation) - Capital outlays - Increase in net working capital Key differences: 1) Cashflow takes the full amount of investment on the date the cost is incurred and does not depreciate them. 2) Costs and revenues are included on the date when the cash is paid/received and not on the date when they accrue. 3) Spending cash to increase inventory is considered a cashflow even though this has no effect on profit. 4) Interest payments are not taken into account. Week 5 18

19 Key issues in cashflow estimation 1) Because cashflows are considered on the date that they are paid/received, sunk costs are never included in NPV analysis. These cashflows are in the past already. 2) When evaluating a project, it is the incremental cashflows that are important. The cashflow that should be discounted is the difference between what we expect to receive if we undertake the project compared with what we would expect in the absence of the project. 3) Incremental cashflows should include the opportunity cost of cashflows lost as a consequence of starting a project. 4) NPV analysis should be undertaken from a corporate, not a divisional perspective. Whether these cashflows occur in your division or not is irrelevant. 5) For this reason, the allocation of costs is completely irrelevant to NPV analysis. Week 5 19

20 Practical cashflow estimation While the appropriate technique for estimating cashflows varies widely from industry to industry, there are certain general rules that can be used. In particular, it is often possible to estimate cashflows with some precision in the short term. It is then difficult to make predictions as to what will happen in the longer term. For this reason, we need to worry about terminal value calculations how we estimate the value of the project in the distant future. So suppose that we are able to make accurate profit forecasts for the next seven years, and that, in year 7 we will be making net operating cashflows of 1m per year. Assume that we are discounting the cashflows at 13% per year reflecting a 5% risk-free rate and an 8% risk premium. Week 5 20

21 Terminal values There are several assumptions that we could make: 1) Assume that there are no more profits to be made. In this case the NPV just comes from the first seven years. 2) Assume that the operating cashflows are going to decline say straight line to zero in say year 12. In this case, the NPV is the present value for the first seven years plus Year 8 Year 9 Year 10 Year 11 Year 12 Cashflo w 800, , , ,000 0 Discount PV 301, , ,000 52,000 0 Therefore, this gives an NPV of 671,000 more than method (1) 3) Assume that profits will decline slowly indefinitely. That is, assume that the decline in net cashflows will be, say, 5% per year on a declining balance basis. In this case, we can use the Gordon Growth Formula to get the terminal value. In terms of year 7 pounds, the terminal value will then be: ,000,000* = 5,280, ( 0.05) Week 5 21

22 Terminal values ) This, though is in terms of year seven pounds. So, in year 0 pounds, this is equivalent to 5,280,000/(1.13) 7 = 2,240,000. This gives a much higher PV than methods (1) and (2) 4) We could use the annuity formula to assume that cashflows will remain unchanged for, say, a further 5 years and then decline. 5) Any combination of these things. What I am trying to demonstrate here is that whether we get a positive NPV or not is often a factor of what terminal value assumptions we make. But, almost by definition, the terminal value is the hardest thing to estimate. This is a major problem with NPV analysis. Week 5 22

23 Manipulated NPVs Sometime managers have an incentive to fix their NPV. You should be aware of some of the tricks that they play. The easiest number to manipulate on an NPV is the terminal value. Therefore, when I am evaluating someone else s NPV this is the first number that I look at. Essentially, I am very wary when too much of the present value comes from terminal cashflows. In some cases it can be as much as 50% of the total present value. This is clearly worrying and I would be very reluctant to accept such a project without seeing a detailed analysis of why the cashflows were taking so long to come through. So, beware. Do not spend 99% of your analysis time estimating cashflows for the first few years and then 1% of your time throwing in a terminal value particularly if the terminal value accounts for a large proportion of the total present value. This is a very common mistake in practice. Week 5 23

24 Sensitivity analysis Hopefully, by now, you are realizing that there is a great deal of subjectivity when doing NPV analysis. How are you going to estimate your cashflows? What terminal value assumption do you make? For this reason, it is strongly recommended that you do sensitivity analysis when undertaking NPV analysis. Try different scenarios. Under what conditions is the NPV positive and when is it negative? What is the worst (realistic) case? What would be the consequences in the worse case? That is, rather than accepting all projects with positive NPV and rejecting projects with negative NPV (the most naïve textbook approach), this technique should be used as a tool to help you make a management decision. Certainly, the more positive the NPV the more optimistic you should be about the project. But you should carefully consider the assumptions made in doing the analysis, consider how robust these assumptions are and what will happen if things do not go according to plan. Week 5 24

25 Questions Week 5 CORPORATE FINANCE - 1 UNIVERSITY OF EXETER MARK FREEMAN, 2004 Week 5 25

26 Question set 4 1) Work out the payback period, the NPV and IRR of the following project. Assume that there is no taxation. The nominal discount rate is 15% and the inflation rate is 3% per year into the foreseeable future. Should you undertake the project or not? The project requires immediate capital investment of 250,000. Sales in year 1 are expected to be 5,000 items. In year 2 sales will increase to 10,000 items. From years 3 to 6, sales will be at 20,000 items a year. There will be no more sales after year 6. It is expected that, in year 1, each item will sell for 75. The expected fixed cost of production in year 1 is 500,000 with a marginal cost of production of 35 per item. All costs and revenues are expected to increase in line with inflation. 2) How does the NPV that you calculated in question 1 change if the firm needs to hold 15% of annual sales (in value terms) in inventories? 3) How does the NPV that you calculated in question 2 change if you have already invested 100,000 in management consulting fees in preparation for this project? 4) How does the NPV that you calculate in question 3 change if, for each item you sell, another division within your organization loses 1 in profit (in terms of year 1 pounds) because you are cannibalizing some of their sales. 5) How does the NPV that you calculated in question 4 change if you are allocated with 100,000 of central overheads per year? 6) How does the NPV that you calculated in question 5 change if you assume that, instead of sales going to zero after year six, the net cashflows from question 1 decreases at 10% per year (after adjusting for inflation) indefinitely but that there are no cashflow implications from (2) (5) after year 6? Week 5 26

1.1 Introduction. Chapter 1: Feasibility Studies: An Overview

1.1 Introduction. Chapter 1: Feasibility Studies: An Overview Chapter 1: Introduction 1.1 Introduction Every long term decision the firm makes is a capital budgeting decision whenever it changes the company s cash flows. Consider launching a new product. This involves

More information

Why Use Net Present Value? The Payback Period Method The Discounted Payback Period Method The Average Accounting Return Method The Internal Rate of

Why Use Net Present Value? The Payback Period Method The Discounted Payback Period Method The Average Accounting Return Method The Internal Rate of 1 Why Use Net Present Value? The Payback Period Method The Discounted Payback Period Method The Average Accounting Return Method The Internal Rate of Return Problems with the IRR Approach The Profitability

More information

Chapter 9. Year Revenue COGS Depreciation S&A Taxable Income After-tax Operating Income 1 $20.60 $12.36 $1.00 $2.06 $5.18 $3.11

Chapter 9. Year Revenue COGS Depreciation S&A Taxable Income After-tax Operating Income 1 $20.60 $12.36 $1.00 $2.06 $5.18 $3.11 Chapter 9 9-1 We assume that revenues and selling & administrative expenses will increase at the rate of inflation. Year Revenue COGS Depreciation S&A Taxable Income After-tax Operating Income 1 $20.60

More information

Strategy and Analysis in Using NPV. How Positive NPV Arises

Strategy and Analysis in Using NPV. How Positive NPV Arises Strategy and Analysis in Using NPV (Text reference: Chapter 8) Topics how positive NPV arises decision trees sensitivity analysis scenario analysis break-even analysis investment options AFM 271 - Strategy

More information

Capital Investment Appraisal Techniques

Capital Investment Appraisal Techniques Capital Investment Appraisal Techniques To download this article in printable format click here A practising Bookkeeper asked me recently how and by what methods one would appraise a proposed investment

More information

CHAPTER 8 CAPITAL BUDGETING DECISIONS

CHAPTER 8 CAPITAL BUDGETING DECISIONS CHAPTER 8 CAPITAL BUDGETING DECISIONS Q1. What is capital budgeting? Why is it significant for a firm? A1 A capital budgeting decision may be defined as the firm s decision to invest its current funds

More information

Global Financial Management

Global Financial Management 1 Global Financial Management Valuation of Cash Flows Investment Decisions and Capital Budgeting Copyright 1999 by Alon Brav, Campbell R. Harvey, Stephen Gray and Ernst Maug. All rights reserved. No part

More information

ENTREPRENEURIAL FINANCE: Strategy Valuation and Deal Structure

ENTREPRENEURIAL FINANCE: Strategy Valuation and Deal Structure ENTREPRENEURIAL FINANCE: Strategy Valuation and Deal Structure Chapter 9 Valuation Questions and Problems 1. You are considering purchasing shares of DeltaCad Inc. for $40/share. Your analysis of the company

More information

CHAPTER 8 INTEREST RATES AND BOND VALUATION

CHAPTER 8 INTEREST RATES AND BOND VALUATION CHAPTER 8 INTEREST RATES AND BOND VALUATION Solutions to Questions and Problems 1. The price of a pure discount (zero coupon) bond is the present value of the par value. Remember, even though there are

More information

Chapter 8: Fundamentals of Capital Budgeting

Chapter 8: Fundamentals of Capital Budgeting Chapter 8: Fundamentals of Capital Budgeting-1 Chapter 8: Fundamentals of Capital Budgeting Big Picture: To value a project, we must first estimate its cash flows. Note: most managers estimate a project

More information

ICASL - Business School Programme

ICASL - Business School Programme ICASL - Business School Programme Quantitative Techniques for Business (Module 3) Financial Mathematics TUTORIAL 2A This chapter deals with problems related to investing money or capital in a business

More information

Part 7. Capital Budgeting

Part 7. Capital Budgeting Part 7. Capital Budgeting What is Capital Budgeting? Nancy Garcia and Digital Solutions Digital Solutions, a software development house, is considering a number of new projects, including a joint venture

More information

CHAPTER FOUR Cash Accounting, Accrual Accounting, and Discounted Cash Flow Valuation

CHAPTER FOUR Cash Accounting, Accrual Accounting, and Discounted Cash Flow Valuation CHAPTER FOUR Cash Accounting, Accrual Accounting, and Discounted Cash Flow Valuation Concept Questions C4.1. There are difficulties in comparing multiples of earnings and book values - the old techniques

More information

Net Present Value and Capital Budgeting. What to Discount

Net Present Value and Capital Budgeting. What to Discount Net Present Value and Capital Budgeting (Text reference: Chapter 7) Topics what to discount the CCA system total project cash flow vs. tax shield approach detailed CCA calculations and examples project

More information

Chapter 011 Project Analysis and Evaluation

Chapter 011 Project Analysis and Evaluation Multiple Choice Questions 1. Forecasting risk is defined as the: a. possibility that some proposed projects will be rejected. b. process of estimating future cash flows relative to a project. C. possibility

More information

Capital Structure: Informational and Agency Considerations

Capital Structure: Informational and Agency Considerations Capital Structure: Informational and Agency Considerations The Big Picture: Part I - Financing A. Identifying Funding Needs Feb 6 Feb 11 Case: Wilson Lumber 1 Case: Wilson Lumber 2 B. Optimal Capital Structure:

More information

GCSE Business Studies. Ratios. For first teaching from September 2009 For first award in Summer 2011

GCSE Business Studies. Ratios. For first teaching from September 2009 For first award in Summer 2011 GCSE Business Studies Ratios For first teaching from September 2009 For first award in Summer 2011 Ratios At the end of this unit students should be able to: Interpret and analyse final accounts and balance

More information

NPV Versus IRR. W.L. Silber -1000 0 0 +300 +600 +900. We know that if the cost of capital is 18 percent we reject the project because the NPV

NPV Versus IRR. W.L. Silber -1000 0 0 +300 +600 +900. We know that if the cost of capital is 18 percent we reject the project because the NPV NPV Versus IRR W.L. Silber I. Our favorite project A has the following cash flows: -1 + +6 +9 1 2 We know that if the cost of capital is 18 percent we reject the project because the net present value is

More information

Introduction to Discounted Cash Flow and Project Appraisal. Charles Ward

Introduction to Discounted Cash Flow and Project Appraisal. Charles Ward Introduction to Discounted Cash Flow and Project Appraisal Charles Ward Company investment decisions How firms makes investment decisions about real projects (not necessarily property) How to decide which

More information

Introduction to Real Estate Investment Appraisal

Introduction to Real Estate Investment Appraisal Introduction to Real Estate Investment Appraisal NPV and IRR Pat McAllister INVESTMENT APPRAISAL DISCOUNTED CASFLOW ANALYSIS Investment Mathematics Discounted cash flow to calculate Gross present value

More information

MBA 8230 Corporation Finance (Part II) Practice Final Exam #2

MBA 8230 Corporation Finance (Part II) Practice Final Exam #2 MBA 8230 Corporation Finance (Part II) Practice Final Exam #2 1. Which of the following input factors, if increased, would result in a decrease in the value of a call option? a. the volatility of the company's

More information

BUSINESS FINANCE (FIN 312) Spring 2009

BUSINESS FINANCE (FIN 312) Spring 2009 BUSINESS FINANCE (FIN 31) Spring 009 Assignment Instructions: please read carefully You can either do the assignment by yourself or work in a group of no more than two. You should show your work how to

More information

Paper F9. Financial Management. Fundamentals Pilot Paper Skills module. The Association of Chartered Certified Accountants

Paper F9. Financial Management. Fundamentals Pilot Paper Skills module. The Association of Chartered Certified Accountants Fundamentals Pilot Paper Skills module Financial Management Time allowed Reading and planning: Writing: 15 minutes 3 hours ALL FOUR questions are compulsory and MUST be attempted. Do NOT open this paper

More information

PRODUCTIVITY & GROWTH

PRODUCTIVITY & GROWTH Productivity Financial Tools There are a number of financial tools that can be used to measure the financial performance and potential contribution of improvement projects to the productivity of a business.

More information

WORKBOOK ON PROJECT FINANCE. Prepared by Professor William J. Kretlow University of Houston

WORKBOOK ON PROJECT FINANCE. Prepared by Professor William J. Kretlow University of Houston WORKBOOK ON PROJECT FINANCE Prepared by Professor William J. Kretlow University of Houston 2002 by Institute for Energy, Law & Enterprise, University of Houston Law Center. All rights reserved. TABLE

More information

ADVANCED INVESTMENT APPRAISAL

ADVANCED INVESTMENT APPRAISAL RELEVANT TO ACCA QUALIFICATION PAPER F9 Studying Paper F9? Performance objectives 15 and 16 are relevant to this exam Investment appraisal is one of the eight core topics within Paper F9, Financial Management

More information

Paper F9. Financial Management. Friday 6 June 2014. Fundamentals Level Skills Module. The Association of Chartered Certified Accountants.

Paper F9. Financial Management. Friday 6 June 2014. Fundamentals Level Skills Module. The Association of Chartered Certified Accountants. Fundamentals Level Skills Module Financial Management Friday 6 June 2014 Time allowed Reading and planning: Writing: 15 minutes 3 hours ALL FOUR questions are compulsory and MUST be attempted. Formulae

More information

Finance 445 Practice Exam Chapters 1, 2, 5, and part of Chapter 6. Part One. Multiple Choice Questions.

Finance 445 Practice Exam Chapters 1, 2, 5, and part of Chapter 6. Part One. Multiple Choice Questions. Finance 445 Practice Exam Chapters 1, 2, 5, and part of Chapter 6 Part One. Multiple Choice Questions. 1. Similar to the example given in class, assume that a corporation has $500 of cash revenue and $300

More information

Net Present Value (NPV)

Net Present Value (NPV) Investment Criteria 208 Net Present Value (NPV) What: NPV is a measure of how much value is created or added today by undertaking an investment (the difference between the investment s market value and

More information

The Concept of Present Value

The Concept of Present Value The Concept of Present Value If you could have $100 today or $100 next week which would you choose? Of course you would choose the $100 today. Why? Hopefully you said because you could invest it and make

More information

Investment Appraisal INTRODUCTION

Investment Appraisal INTRODUCTION 8 Investment Appraisal INTRODUCTION After reading the chapter, you should: understand what is meant by the time value of money; be able to carry out a discounted cash flow analysis to assess the viability

More information

Capital Budgeting Further Considerations

Capital Budgeting Further Considerations Capital Budgeting Further Considerations For 9.220, Term 1, 2002/03 02_Lecture10.ppt Lecture Outline Introduction The input for evaluating projects relevant cash flows Inflation: real vs. nominal analysis

More information

CHAPTER 7 MAKING CAPITAL INVESTMENT DECISIONS

CHAPTER 7 MAKING CAPITAL INVESTMENT DECISIONS CHAPTER 7 MAKING CAPITAL INVESTMENT DECISIONS Answers to Concepts Review and Critical Thinking Questions 1. In this context, an opportunity cost refers to the value of an asset or other input that will

More information

tutor2u tutor2u Interactive Business Simulations Finance: Cash Flow Management

tutor2u tutor2u Interactive Business Simulations Finance: Cash Flow Management Interactive Business Simulations Finance: Cash Flow Management Note: this interactive simulator is designed to be viewed using an up-to-date internet browser. Users must also have Macromedia Flash Player

More information

CHAPTER 12 RISK, COST OF CAPITAL, AND CAPITAL BUDGETING

CHAPTER 12 RISK, COST OF CAPITAL, AND CAPITAL BUDGETING CHAPTER 12 RISK, COST OF CAPITAL, AND CAPITAL BUDGETING Answers to Concepts Review and Critical Thinking Questions 1. No. The cost of capital depends on the risk of the project, not the source of the money.

More information

How To Calculate Discounted Cash Flow

How To Calculate Discounted Cash Flow Chapter 1 The Overall Process Capital Expenditures Whenever we make an expenditure that generates a cash flow benefit for more than one year, this is a capital expenditure. Examples include the purchase

More information

UNIVERSITY OF WAH Department of Management Sciences

UNIVERSITY OF WAH Department of Management Sciences BBA-330: FINANCIAL MANAGEMENT UNIVERSITY OF WAH COURSE DESCRIPTION/OBJECTIVES The module aims at building competence in corporate finance further by extending the coverage in Business Finance module to

More information

Paper P1 Performance Operations Post Exam Guide September 2010 Exam

Paper P1 Performance Operations Post Exam Guide September 2010 Exam General Comments This was the second sitting of the new P1 syllabus and candidate performance was generally better than that achieved in the May diet. There were however still core areas of the syllabus

More information

P2 Performance Management September 2014 examination

P2 Performance Management September 2014 examination Management Level Paper P2 Performance Management September 2014 examination Examiner s Answers Note: Some of the answers that follow are fuller and more comprehensive than would be expected from a well-prepared

More information

CHAPTER 11. Proposed Project. Incremental Cash Flow for a Project. Treatment of Financing Costs. Estimating cash flows:

CHAPTER 11. Proposed Project. Incremental Cash Flow for a Project. Treatment of Financing Costs. Estimating cash flows: CHAPTER 11 Cash Flow Estimation and Risk Analysis Estimating cash flows: Relevant cash flows Working capital treatment Inflation Risk Analysis: Sensitivity Analysis, Scenario Analysis, and Simulation Analysis

More information

Chapter 9 Net Present Value and Other Investment Criteria Chapter Organization

Chapter 9 Net Present Value and Other Investment Criteria Chapter Organization T9.1 Chapter Outline Chapter 9 Net Present Value and Other Investment Criteria Chapter Organization! 9.1 Net Present Value! 9.2 The Payback Rule! 9.3 The Average Accounting Return! 9.4 The Internal Rate

More information

CHAPTER 8: ESTIMATING CASH FLOWS

CHAPTER 8: ESTIMATING CASH FLOWS CHAPTER 8: ESTIMATING CASH FLOWS 8-1 a. Straight line depreciation = ($15 - $3)/10 = $1.20 Annual Tax Savings from Depreciation = $ 1.2 (0.4) = $0.48 Present Value of Tax Savings from Depreciation = $

More information

Fundamentals Level Skills Module, Paper F9. Section A. Mean growth in earnings per share = 100 x [(35 7/30 0) 1/3 1] = 5 97% or 6%

Fundamentals Level Skills Module, Paper F9. Section A. Mean growth in earnings per share = 100 x [(35 7/30 0) 1/3 1] = 5 97% or 6% Answers Fundamentals Level Skills Module, Paper F9 Financial Management June 2015 Answers Section A 1 A 2 D 3 D Mean growth in earnings per share = 100 x [(35 7/30 0) 1/3 1] = 5 97% or 6% 4 A 5 D 6 B 7

More information

Interpretation of Financial Statements

Interpretation of Financial Statements Interpretation of Financial Statements Author Noel O Brien, Formation 2 Accounting Framework Examiner. An important component of most introductory financial accounting programmes is the analysis and interpretation

More information

Choice of Discount Rate

Choice of Discount Rate Choice of Discount Rate Discussion Plan Basic Theory and Practice A common practical approach: WACC = Weighted Average Cost of Capital Look ahead: CAPM = Capital Asset Pricing Model Massachusetts Institute

More information

Understanding Options: Calls and Puts

Understanding Options: Calls and Puts 2 Understanding Options: Calls and Puts Important: in their simplest forms, options trades sound like, and are, very high risk investments. If reading about options makes you think they are too risky for

More information

Paper F9. Financial Management. Friday 7 June 2013. Fundamentals Level Skills Module. The Association of Chartered Certified Accountants.

Paper F9. Financial Management. Friday 7 June 2013. Fundamentals Level Skills Module. The Association of Chartered Certified Accountants. Fundamentals Level Skills Module Financial Management Friday 7 June 2013 Time allowed Reading and planning: Writing: 15 minutes 3 hours ALL FOUR questions are compulsory and MUST be attempted. Formulae

More information

Session #5 Capital Budgeting - II Damodaran - Chapter 9: 6,12,16,18 Chapter 10: 2,10,16(a&b) Chapter 11: 6,12,14

Session #5 Capital Budgeting - II Damodaran - Chapter 9: 6,12,16,18 Chapter 10: 2,10,16(a&b) Chapter 11: 6,12,14 Session #5 Capital Budgeting - II Damodaran - Chapter 9: 6,12,16,18 Chapter 10: 2,10,16(a&b) Chapter 11: 6,12,14 I. Additional Issues in Capital Budgeting. A. Capital rationing: Use profitability index

More information

Examiner s report F9 Financial Management June 2011

Examiner s report F9 Financial Management June 2011 Examiner s report F9 Financial Management June 2011 General Comments Congratulations to candidates who passed Paper F9 in June 2011! The examination paper looked at many areas of the syllabus and a consideration

More information

hp calculators HP 17bII+ Net Present Value and Internal Rate of Return Cash Flow Zero A Series of Cash Flows What Net Present Value Is

hp calculators HP 17bII+ Net Present Value and Internal Rate of Return Cash Flow Zero A Series of Cash Flows What Net Present Value Is HP 17bII+ Net Present Value and Internal Rate of Return Cash Flow Zero A Series of Cash Flows What Net Present Value Is Present Value and Net Present Value Getting the Present Value And Now For the Internal

More information

Chapter 6. 1. Your firm is considering two investment projects with the following patterns of expected future net aftertax cash flows:

Chapter 6. 1. Your firm is considering two investment projects with the following patterns of expected future net aftertax cash flows: Chapter 6 1. Your firm is considering two investment projects with the following patterns of expected future net aftertax cash flows: Year Project A Project B 1 $1 million $5 million 2 2 million 4 million

More information

STUDENT CAN HAVE ONE LETTER SIZE FORMULA SHEET PREPARED BY STUDENT HIM/HERSELF. FINANCIAL CALCULATOR/TI-83 OR THEIR EQUIVALENCES ARE ALLOWED.

STUDENT CAN HAVE ONE LETTER SIZE FORMULA SHEET PREPARED BY STUDENT HIM/HERSELF. FINANCIAL CALCULATOR/TI-83 OR THEIR EQUIVALENCES ARE ALLOWED. Test III-FINN3120-090 Fall 2009 (2.5 PTS PER QUESTION. MAX 100 PTS) Type A Name ID PRINT YOUR NAME AND ID ON THE TEST, ANSWER SHEET AND FORMULA SHEET. TURN IN THE TEST, OPSCAN ANSWER SHEET AND FORMULA

More information

CHAPTER 6 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA

CHAPTER 6 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA CHAPTER 6 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA Answers to Concepts Review and Critical Thinking Questions 1. Assuming conventional cash flows, a payback period less than the project s life means

More information

11.3 BREAK-EVEN ANALYSIS. Fixed and Variable Costs

11.3 BREAK-EVEN ANALYSIS. Fixed and Variable Costs 385 356 PART FOUR Capital Budgeting a large number of NPV estimates that we summarize by calculating the average value and some measure of how spread out the different possibilities are. For example, it

More information

CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA

CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA CHAPTER 9 NET PRESENT VALUE AND OTHER INVESTMENT CRITERIA Basic 1. To calculate the payback period, we need to find the time that the project has recovered its initial investment. After two years, the

More information

10.SHORT-TERM DECISIONS & CAPITAL INVESTMENT APPRAISAL

10.SHORT-TERM DECISIONS & CAPITAL INVESTMENT APPRAISAL INDUSTRIAL UNIVERSITY OF HO CHI MINH CITY AUDITING ACCOUNTING FACULTY 10.SHORT-TERM DECISIONS & CAPITAL INVESTMENT APPRAISAL 4 Topic List INDUSTRIAL UNIVERSITY OF HO CHI MINH CITY AUDITING ACCOUNTING FACULTY

More information

Preparing cash budgets

Preparing cash budgets 3 Preparing cash budgets this chapter covers... In this chapter we will examine in detail how a cash budget is prepared. This is an important part of your studies, and you will need to be able to prepare

More information

1. What are the three types of business organizations? Define them

1. What are the three types of business organizations? Define them Written Exam Ticket 1 1. What is Finance? What do financial managers try to maximize, and what is their second objective? 2. How do you compare cash flows at different points in time? 3. Write the formulas

More information

A Basic Introduction to the Methodology Used to Determine a Discount Rate

A Basic Introduction to the Methodology Used to Determine a Discount Rate A Basic Introduction to the Methodology Used to Determine a Discount Rate By Dubravka Tosic, Ph.D. The term discount rate is one of the most fundamental, widely used terms in finance and economics. Whether

More information

Course 3: Capital Budgeting Analysis

Course 3: Capital Budgeting Analysis Excellence in Financial Management Course 3: Capital Budgeting Analysis Prepared by: Matt H. Evans, CPA, CMA, CFM This course provides a concise overview of capital budgeting analysis. This course is recommended

More information

Measuring Investment Returns

Measuring Investment Returns Measuring Investment Returns Aswath Damodaran Stern School of Business Aswath Damodaran 156 First Principles Invest in projects that yield a return greater than the minimum acceptable hurdle rate. The

More information

Discounted Cash Flow. Alessandro Macrì. Legal Counsel, GMAC Financial Services

Discounted Cash Flow. Alessandro Macrì. Legal Counsel, GMAC Financial Services Discounted Cash Flow Alessandro Macrì Legal Counsel, GMAC Financial Services History The idea that the value of an asset is the present value of the cash flows that you expect to generate by holding it

More information

Chapter 9 Capital Budgeting Decision Models

Chapter 9 Capital Budgeting Decision Models Chapter 9 Capital Budgeting Decision Models LEARNING OBJECTIVES (Slide 9-2) 1. Explain capital budgeting and differentiate between short-term and long-term budgeting decisions. 2. Explain the payback model

More information

Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology Madras

Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology Madras Operations and Supply Chain Management Prof. G. Srinivasan Department of Management Studies Indian Institute of Technology Madras Lecture - 41 Value of Information In this lecture, we look at the Value

More information

1 (a) Calculation of net present value (NPV) Year 1 2 3 4 5 6 $000 $000 $000 $000 $000 $000 Sales revenue 1,600 1,600 1,600 1,600 1,600

1 (a) Calculation of net present value (NPV) Year 1 2 3 4 5 6 $000 $000 $000 $000 $000 $000 Sales revenue 1,600 1,600 1,600 1,600 1,600 Answers Fundamentals Level Skills Module, Paper F9 Financial Management December 2011 Answers 1 (a) Calculation of net present value (NPV) Year 1 2 3 4 5 6 $000 $000 $000 $000 $000 $000 Sales revenue 1,600

More information

6. Debt Valuation and the Cost of Capital

6. Debt Valuation and the Cost of Capital 6. Debt Valuation and the Cost of Capital Introduction Firms rarely finance capital projects by equity alone. They utilise long and short term funds from a variety of sources at a variety of costs. No

More information

Review Solutions FV = 4000*(1+.08/4) 5 = $4416.32

Review Solutions FV = 4000*(1+.08/4) 5 = $4416.32 Review Solutions 1. Planning to use the money to finish your last year in school, you deposit $4,000 into a savings account with a quoted annual interest rate (APR) of 8% and quarterly compounding. Fifteen

More information

Understanding Financial Management: A Practical Guide Guideline Answers to the Concept Check Questions

Understanding Financial Management: A Practical Guide Guideline Answers to the Concept Check Questions Understanding Financial Management: A Practical Guide Guideline Answers to the Concept Check Questions Chapter 8 Capital Budgeting Concept Check 8.1 1. What is the difference between independent and mutually

More information

ECONOMIC JUSTIFICATION

ECONOMIC JUSTIFICATION ECONOMIC JUSTIFICATION A Manufacturing Engineer s Point of View M. Kevin Nelson, P.E. President Productioneering, Inc. www.roboautotech.com Contents: I. Justification methods a. Net Present Value (NPV)

More information

Section 1 - Covered Call Writing: Basic Terms and Definitions

Section 1 - Covered Call Writing: Basic Terms and Definitions Section 1 - Covered Call Writing: Basic Terms and Definitions Covered call writing is one of the most often-used option strategies, both at the institutional and individual level. Before discussing the

More information

VALUE 11.125%. $100,000 2003 (=MATURITY

VALUE 11.125%. $100,000 2003 (=MATURITY NOTES H IX. How to Read Financial Bond Pages Understanding of the previously discussed interest rate measures will permit you to make sense out of the tables found in the financial sections of newspapers

More information

Which projects should the corporation undertake

Which projects should the corporation undertake Which projects should the corporation undertake Investment criteria 1. Investment into a new project generates a flow of cash and, therefore, a standard DPV rule should be the first choice under consideration.

More information

Article by Martin Kelly, BSc (Econ) Hons, DIP. Acc, FCA, MBA, MCMI. Examiner in Professional 2 Advanced Corporate Reporting

Article by Martin Kelly, BSc (Econ) Hons, DIP. Acc, FCA, MBA, MCMI. Examiner in Professional 2 Advanced Corporate Reporting IMPAIRMENT - IAS 36 Article by Martin Kelly, BSc (Econ) Hons, DIP. Acc, FCA, MBA, MCMI. Examiner in Professional 2 Advanced Corporate Reporting Introduction Intangible assets, particularly goodwill, have

More information

Time Value of Money. 2014 Level I Quantitative Methods. IFT Notes for the CFA exam

Time Value of Money. 2014 Level I Quantitative Methods. IFT Notes for the CFA exam Time Value of Money 2014 Level I Quantitative Methods IFT Notes for the CFA exam Contents 1. Introduction...2 2. Interest Rates: Interpretation...2 3. The Future Value of a Single Cash Flow...4 4. The

More information

Key Concepts and Skills. Net Present Value and Other Investment Rules. http://www2.gsu.edu/~fnccwh/pdf/ rwjch5v3overview.pdf.

Key Concepts and Skills. Net Present Value and Other Investment Rules. http://www2.gsu.edu/~fnccwh/pdf/ rwjch5v3overview.pdf. McGraw-Hill/Irwin Net Present Value and Other Investment Rules 9-1 http://www2.gsu.edu/~fnccwh/pdf/ rwjch5v3overview.pdf Copyright 2010 by Charles Hodges and the McGraw-Hill Companies, Inc. All rights

More information

CHAPTER 7: NPV AND CAPITAL BUDGETING

CHAPTER 7: NPV AND CAPITAL BUDGETING CHAPTER 7: NPV AND CAPITAL BUDGETING I. Introduction Assigned problems are 3, 7, 34, 36, and 41. Read Appendix A. The key to analyzing a new project is to think incrementally. We calculate the incremental

More information

CHAPTER 17. Payout Policy. Chapter Synopsis

CHAPTER 17. Payout Policy. Chapter Synopsis CHAPTER 17 Payout Policy Chapter Synopsis 17.1 Distributions to Shareholders A corporation s payout policy determines if and when it will distribute cash to its shareholders by issuing a dividend or undertaking

More information

Management Accounting 2 nd Year Examination

Management Accounting 2 nd Year Examination Management Accounting 2 nd Year Examination August 2013 Exam Paper, Solutions & Examiner s Report NOTES TO USERS ABOUT THESE SOLUTIONS The solutions in this document are published by Accounting Technicians

More information

EVA Issues as a Valuation Framework: Issues Solved By AFG s Economic Margin

EVA Issues as a Valuation Framework: Issues Solved By AFG s Economic Margin EVA Issues as a Valuation Framework: Issues Solved By AFG s Economic Margin 1 EVA as a valuation tool Firm Value = NOPAT + EVA Future * 1 * T c* c* ( 1 + c* ) Existing Assets Future Investments The basic

More information

Sources of finance (Or where can we get money from?)

Sources of finance (Or where can we get money from?) Sources of finance (Or where can we get money from?) Why do we need finance? 1. Setting up a business 2. Need to finance our day-to-day activities 3. Expansion 4. Research into new products 5. Special

More information

The Marginal Cost of Capital and the Optimal Capital Budget

The Marginal Cost of Capital and the Optimal Capital Budget WEB EXTENSION12B The Marginal Cost of Capital and the Optimal Capital Budget If the capital budget is so large that a company must issue new equity, then the cost of capital for the company increases.

More information

Capital Budgeting continued: Overview:(1) Estimating cash flows (2) CB examples (3) Dealing with uncertainty of cash flows

Capital Budgeting continued: Overview:(1) Estimating cash flows (2) CB examples (3) Dealing with uncertainty of cash flows Capital Budgeting continued: Overview:(1) Estimating cash flows (2) CB examples (3) Dealing with uncertainty of cash flows Chapter 7: 1,5,7,8,27,32 Chapter 8: 1,3,5,8,13 (clarification for problem 13b:

More information

Capital Budgeting Formula

Capital Budgeting Formula apital Budgeting Formula Not in the book. Wei s summary If salvage value S is less than U n : If salvage value S is greater than U n : Note: IF t : incremental cash flows (could be negative) )(NW): change

More information

A Primer on Valuing Common Stock per IRS 409A and the Impact of FAS 157

A Primer on Valuing Common Stock per IRS 409A and the Impact of FAS 157 A Primer on Valuing Common Stock per IRS 409A and the Impact of FAS 157 By Stanley Jay Feldman, Ph.D. Chairman and Chief Valuation Officer Axiom Valuation Solutions 201 Edgewater Drive, Suite 255 Wakefield,

More information

Final Examination, BUS312, D1+ E1. SFU Student number:

Final Examination, BUS312, D1+ E1. SFU Student number: Final Examination, BUS312, D1+ E1 NAME: SFU Student number: Instructions: For qualitative questions, point form is not an acceptable answer. For quantitative questions, an indication of how you arrived

More information

Chapter 8: Using DCF Analysis to Make Investment Decisions

Chapter 8: Using DCF Analysis to Make Investment Decisions FIN 301 Class Notes Chapter 8: Using DCF Analysis to Make Investment Decisions Capital Budgeting: is the process of planning for capital expenditures (long term investment). Planning process involves 1-

More information

Chapter 6. Commodity Forwards and Futures. Question 6.1. Question 6.2

Chapter 6. Commodity Forwards and Futures. Question 6.1. Question 6.2 Chapter 6 Commodity Forwards and Futures Question 6.1 The spot price of a widget is $70.00. With a continuously compounded annual risk-free rate of 5%, we can calculate the annualized lease rates according

More information

Section 1 - Overview and Option Basics

Section 1 - Overview and Option Basics 1 of 10 Section 1 - Overview and Option Basics Download this in PDF format. Welcome to the world of investing and trading with options. The purpose of this course is to show you what options are, how they

More information

Professional Level Skills Module, Paper P4

Professional Level Skills Module, Paper P4 Answers Professional Level Skills Module, Paper P4 Advanced Financial Management December 2011 Answers 1 Up to 4 professional marks are available for the presentation of the answer, which should be in

More information

Overview of Financial Management

Overview of Financial Management Overview of Financial Management Uwadiae Oduware FCA Akintola Williams Deloitte 1-1 Definition Financial Management entails planning for the future for a person or a business enterprise to ensure a positive

More information

TOPIC LEARNING OBJECTIVE

TOPIC LEARNING OBJECTIVE Topic Mapping 1 Transaction Analysis Understand the effect of various types of transactions on the accounting equation, accounting journal and accounting ledger. Concepts and Skills Accounting Equation

More information

WHAT IS CAPITAL BUDGETING?

WHAT IS CAPITAL BUDGETING? WHAT IS CAPITAL BUDGETING? Capital budgeting is a required managerial tool. One duty of a financial manager is to choose investments with satisfactory cash flows and rates of return. Therefore, a financial

More information

Investment Decision Analysis

Investment Decision Analysis Lecture: IV 1 Investment Decision Analysis The investment decision process: Generate cash flow forecasts for the projects, Determine the appropriate opportunity cost of capital, Use the cash flows and

More information

Paper F9. Financial Management. Friday 6 December 2013. Fundamentals Level Skills Module. The Association of Chartered Certified Accountants

Paper F9. Financial Management. Friday 6 December 2013. Fundamentals Level Skills Module. The Association of Chartered Certified Accountants Fundamentals Level Skills Module Financial Management Friday 6 December 2013 Time allowed Reading and planning: Writing: 15 minutes 3 hours ALL FOUR questions are compulsory and MUST be attempted. Formulae

More information

Foundations in Financial Management (FFM) September 2016 to June 2017

Foundations in Financial Management (FFM) September 2016 to June 2017 Foundations in Financial Management (FFM) September 2016 to June 2017 This syllabus and study guide is designed to help with teaching and learning and is intended to provide detailed information on what

More information

MANAGEMENT OPTIONS AND VALUE PER SHARE

MANAGEMENT OPTIONS AND VALUE PER SHARE 1 MANAGEMENT OPTIONS AND VALUE PER SHARE Once you have valued the equity in a firm, it may appear to be a relatively simple exercise to estimate the value per share. All it seems you need to do is divide

More information

Accounting Income, Residual Income and Valuation

Accounting Income, Residual Income and Valuation Accounting Income, Residual Income and Valuation Ray Donnelly PhD, MSc, BComm, ACMA Examiner in Strategic Corporate Finance 1. Introduction The residual income (RI) for a firm for any year t is its accounting

More information

The Net Present Value Rule in Comparison to the Payback and Internal Rate of Return Methods

The Net Present Value Rule in Comparison to the Payback and Internal Rate of Return Methods The Net Present Value Rule in omparison to the Payback and Internal Rate of Return Methods Sascha Rudolf, 8-- Preamble In the context of investment decisions companies have a large variety of investment

More information

CIS September 2012 Exam Diet. Examination Paper 2.2: Corporate Finance Equity Valuation and Analysis Fixed Income Valuation and Analysis

CIS September 2012 Exam Diet. Examination Paper 2.2: Corporate Finance Equity Valuation and Analysis Fixed Income Valuation and Analysis CIS September 2012 Exam Diet Examination Paper 2.2: Corporate Finance Equity Valuation and Analysis Fixed Income Valuation and Analysis Corporate Finance (1 13) 1. Assume a firm issues N1 billion in debt

More information

Chapter 09 - Using Discounted Cash-Flow Analysis to Make Investment Decisions

Chapter 09 - Using Discounted Cash-Flow Analysis to Make Investment Decisions Solutions to Chapter 9 Using Discounted Cash-Flow Analysis to Make Investment Decisions 1. Net income = ($74 $42 $10) [0.35 ($74 $42 $10)] = $22 $7.7 = $14.3 million Revenues cash expenses taxes paid =

More information