Foundation Design and Construction for our Structural Brethren Deep Foundation Design Basic Cookbook

Size: px
Start display at page:

Download "Foundation Design and Construction for our Structural Brethren Deep Foundation Design Basic Cookbook"

Transcription

1 Foundation Design and Construction for our Structural Brethren Deep Foundation Design Basic Cookbook A Presentation on Special Foundation Topics to the Delaware Valley Association of Structural Engineers 4 February 2015

2 Today s Presenters Marc Gallagher, P.E., LEED AP Michael Fritzges, P.E. Senior Principal New York Office Project Engineer Philadelphia Office

3 Today s Topics Deep Foundations Driven Piles Types Benefits - Disadvantages Costs Equipment Drilled Piles Types Benefits - Disadvantages Costs Equipment

4 Deep Foundations Introduction When do we use deep foundations? However, we can save 700 lira by not doing borings..and I don t think we need piles anyway.

5 Deep Foundations Introduction When do we use deep foundations? Soft soils such as marsh/wetlands Poor fill in a loose condition Liquefiable soils High groundwater Contamination Very high foundation loads High loads in limited footprint Sensitive adjacent structures (subways) Reduce settlement

6 Types of Deep Foundations Driven Piles Driven into the ground with impact hammer Drilled Elements Drilled hole filled with concrete/grout/steel Other Helical piles Rammed piers

7 Driven Piles Basics Design theory Installation requirements Equipment Problems in Construction

8 Driven Piles - Basics Pile driving has been around for 1000 s of years Pile hammer imparts energy to the pile to drive into the ground Driving into harder material requires more energy More energy into the pile yields higher capacity

9

10 Driven Piles - Basics Advantages Relatively inexpensive $75-$100/ft for steel/concrete $25-$35/ft for timber Numerous contractors Material readily available Equipment fairly standard Equipment fairly low-tech

11 Driven Piles - Basics Disadvantages Practically limited to about 250 to 300 tons with the exception of very large marine applications Vibrations Noise Obstructions

12 Driven Piles - Basics Timber H-Pile Pipe Pile Taper Piles Precast Concrete

13 Driven Piles Design Theory End bearing Side friction Combination Factor of Safety

14 Driven Piles Design Theory Q ult R side R tip Q allow Q ult FS

15 Driven Piles Design Theory End bearing R q * tip tip A tip q 4* N * tip SPT (limited to 40N) L b B Bearing Capacity q tip 2 1 BN cn D c f N q

16 Driven Piles Design Theory q tip 2 1 BN cn c D f N q Sand C=0 Limited to Df = 10 to 20 * Diameter Clay Last term ~ 0 Nc = 9

17 Driven Piles Design Theory Side friction R f * s side A perimeter Sand Normal force & friction coefficient Clay Depends on the cohesion or Su (undrained shear strength) f side adhesion friction

18 Driven Piles Design Theory f s c A k ' * tan s vertical Ca = Adhesion factor relating cohesion to friction along shaft k s = coefficient of lateral earth pressure (generally 1 to 2) fs for cohesive reduces to first term fs for cohesionless reduces to second term

19 Driven Piles Design Theory Sand Q ult ( D N ) A ( *tan f q tip horizontal ) A perimeter Rule of Thumb #1 a 12 pile in dense sand will give about 1 ton allowable capacity per foot of embedment

20

21 Driven Piles Design Theory Clay Q 9* c* A c * ult tip A A perimeter Rule of Thumb #2 Call a geotech for piles in clay

22 Driven Piles Design Theory

23 Driven Piles Design Theory Load Transfer Load shed into soil along shaft and at tip Side friction starts with little displacement End bearing requires significant displacement but can be up to 50% or more of capacity, even for friction piles

24 Driven Piles Design Theory Group effects Acts more like a block than n individual piles Reduced capacity P group P single * n Both axial and lateral Increased settlement S group > S single

25 Driven Piles Design Theory Factor of Safety on a design is directly related to field verification program.

26 Driven Piles Installation Requirements Driven to a resistance Called the pile set Referenced as Blows per inch or foot

27 Driven Piles Installation ENR Formula Requirements Empirical based on 100 years of pile driving experience Input hammer energy (weight * drop) Output required resistance or set (s) Q allow 2* Weight Hammer * S 0.01 Height Drop

28 Driven Piles Installation Requirements Wave Equation Analysis WEAP Computer analysis based on elastic (spring) theories Input hammer type, pile type, soil properties Output a graph showing capacity v blow count Indicates estimated pile stresses CRITICAL FOR CONTRACTOR!

29

30 Driven Piles - Equipment Pile driving rig Base unit is usually a crane Leads hold the pile and hammer Fixed Hanging Hammer

31 Driven Piles - Equipment

32 Driven Piles - Equipment

33 Driven Piles - Equipment

34 Driven Piles - Equipment Hammer Types Gravity Steam Diesel Hydraulic Single Acting Double Acting

35 Driven Piles Installation Problems

36 Driven Piles Installation Problems Vibrations Obstructions (any) Sweep (pipe, tapered, H) Dog leg (pipe, tapered, H) Crumple (end bearing steel) Rupture (pipe, tapered) Breaks (timber, concrete) Yields (steel) Tension cracking (concrete)

37 Drilled Piles Basics Design theory Installation requirements Equipment Problems during construction

38 Drilled Piles - Basics Pile is drilled into the ground not driven Very large diameter and very high capacities possible essentially unlimited

39 Drilled Piles - Basics Advantages No vibrations Limited noise Can penetrate obstructions Small rigs, limited access/headroom Disadvantages Relatively expensive Micro-pile $200-$400/ft Auger Cast $100-$200/ft Drilled Shaft/Caissons $500-$2,500/ft Limited contractors Materials can be limited Equipment is highly specialized Equipment often high-tech Can be required to carry unskilled union contingent (operator, mechanic, etc) who are not familiar with drilling

40 Drilled Piles - Basics Micropiles Auger cast piles Drilled shafts Caissons

41 Drilled Piles - Basics Micro-piles (mini-caissons) 50 to 500 tons 5 to 14 inches Casing, grout and reinforcement Drill with fluid to flush cuttings Pressurized in soil Soil or rock socket

42 Drilled Piles - Basics

43 Drilled Piles - Basics Drilled shafts 500 to 5,000 tons+ Very large diameters, up to 12 feet have been drilled Very high capacity Can be belled at the bottom Drilled with slurry to support hole Installed with casing Temporary or Permanent Difficult in glacial and fill areas

44 Drilled Piles - Basics Drilled shafts

45

46 Drilled Piles - Basics Caissons Really a drilled shaft into rock Large diameters Extremely high capacity-10,000 tons highest to date? Casing and/or slurry for support Rock socket used for capacity

47 Drilled Piles - Basics Auger cast piles 50 tons to 300 tons Typically 12 to 30 inches Larger diameters more common now Fast installation in right environment Relatively cheap Auger is screwed into the ground, concrete injected as auger is withdrawn

48

49 Drilled Piles Design Theory Who designs drilled piles? There is no I in Team Geotechnical engineer = minimum length and diameter of the pile, axial reinforcement Structural engineer = Pile connection and verification of axial steel arrangement

50 Drilled Piles Design Theory Geotechnical - similar to driven piles End bearing Side friction Combination Structural Geotechnical capacity is typically much greater than driven piles, therefore the structural design is often a limiting factor Typical ASD design per building code factors Rebar throughout length extra in socket

51 Drilled Piles Design Theory Micropiles Ignore end bearing because small diameter Side friction only Gravity grouted Pressure grouted Typical friction values from published sources P fs * A

52 Drilled Piles Design Theory Friction Values

53 Drilled Piles Design Theory Rule of Thumb #3 The Mazzo Rule for dense sands f 0.8* N s ave

54 Drilled Piles Design Theory Drilled Shafts End bearing and Side friction Gravity grouted FHWA is the main design manual used Design is the same as for a driven pile, based on adhesion and friction Q ult R side R tip Sand Q ) A ult ( D f Nq ) Atip ( horizontal *tan perimeter Clay Q 9* c* A c * ult tip A A perimeter

55 Drilled Piles Design Theory Caissons A drilled shaft in rock End bearing and side friction Gravity grouted Unit side shear and tip resistance based on strength of intact rock samples Adjusted for quality of rock mass

56 Drilled Piles - Equipment Micropile rig External flush Duplex Reverse circulation Casing Tri-cone roller bit Down-the-hole hammer

57 Drilled Piles - Equipment Expanding bit Numa system

58 Drilled Shaft Rig Drilled Piles - Equipment Kelly Bar Rotary Table Augers Buckets Core Barrels

59 Drilled Piles - Equipment

60 Drilled Piles - Equipment

61 Caisson Rig Drilled Piles - Equipment Cluster drill Permanent or temporary casing

62

63

64

65 Drilled Piles - Equipment Standard Auger Cast Piles Continuous-flight hollow-stem auger Generates high volume of spoils

66 Drilled Piles - Equipment Drilled Displacement Specialized drill bit Compacts sidewall as tool advanced Higher capacities Fewer cuttings

67 Drilled Piles Installation Requirements Observations Drill pressure Speed of penetration Cuttings Rig reactions Grout take Grout/Concrete Properties Video Down hole inspection

68 Drilled Piles Construction Problems Collapse of hole Obstructions Filter cake on side wall Soft bottom Disturbance Seamy rock Unexpected depth increase

69 Other Miscellaneous Types Helical Piles Typically for light loads Foundation repairs for small structures Rammed Piers Drilled hole filled with aggregate that is then rammed Cheap Ground improvement

70 General Installation Requirements Controlled Inspection Record installation Count blows, estimate volumes, watch drill reactions Assess damage/problems Index Piles Confirm conditions across site Test assumptions Calibrate models Load Tests Confirm/Prove capacity

71 Pile Load Testing Load testing required if: Design compressive loads are greater than those specified by Code Design load in doubt Cast-in-place elements with enlarged base At least one load test in each area of uniform soil conditions

72 Load Tests Pile Load Testing ASTM standards (basically same as IBC) Apply a test load and hold for period of time Generally 2x the design load as a minimum (FS=2) Generally 24 to 48 hours (creep assessment) Quick test procedure acceptable in certain circumstances Static Osterberg Cell (O-cell) Statnamic

73 Pile Load Testing Static Load Test Set Up Anchor piles installed for reaction

74 Pile Load Testing Static Load Test Set Up Dead weight for reaction

75 Pile Load Testing

76 Settlement (inch) Pile Load Testing Applied Load vs. Settlement PILE No. K-10-A 0.0 Applied Load (tons) in Elastic Compression (full load transfer to pile tip) Ton Design Load Settlement Approx in in. 0.5 Measured Pile settlement due to applied load in Pile No. K-10-A Tested 2/24-2/25/00 Pile Type: 7-in OD, 0.453" wall Oil Well Casing Grout Filling: 4,000 psi Reinforcement: #20, #14 Design Load: 95 Tons Pile Length:?????? Pile Hammer: N/A - Drilled Final Driving Resistance: N/A - Drilled Avg. of Dial Gage Settlement Elastic Comp. (Full Pile Length)

77 Settlement (inch) in. Pile Load Testing Applied Load vs. Settlement PILE No. 294 Applied Load (tons) Ton Design Load Settlement Approx 0.13 in Measured Pile settlement due to first cycle of applied load in. Elastic Compression (load shed along length of pile embeded in bearing stratum) in Measured Pile settlement due to second cycle of applied load in Pile No. 294 Tested 7/12-7/19/00 Pile Type: 14" Butt Diameter, 8" Tip Diameter Monotube Concrete Filling: 4000 psi Reinforcement: None Design Load: 70 Tons Pile Length: 42' Elastic Compression (full load transfer to pile tip) Avg. of Dial Gage Settlement First Load Cycle Elastic Comp. (Full Pile Length) Ave of Dial Gage Reading for Second Load Cycle Elastic Comp (Load shed along pile within bearing stratum) in.

78 Settlement (in) Pile Load Testing Settlement vs. Time for 200% Design Load PILE No. 294 Time (min) hr 111 hr inches Pile No. 294 Tested 7/12-7/19/00 Pile Type: 14" Butt Diameter, 8" Tip Diameter Monotube Concrete Filling: 4000 psi Reinforcement: None Design Load: 70 Tons Pile Length: 42' Pile Hammer: Vulcan 08 Final Driving Resistance: 50 blows/12" inch/48 hours allowable settlement as per NYCBC Section C (e)(2) 48 hours Ave. Incremental Settlement, in 0.10

79 Pile Load Testing O-Cell Load Test Set Up For drilled piles only

80 General Installation Requirements O-cell O-cell

81 General Installation Requirements

82 General Installation Requirements

83 Pile Load Testing Statnamic Load Test Set Up

84 Pile Load Testing Lateral Load Test Set Up

85 Questions? Marc Gallagher, PE Mike Fritzges, PE Philadelphia New York Miami Washington, DC San Francisco - Houston Doylestown Bethlehem Pittsburgh Lawrenceville New Haven Oakland Irvine Bismarck Cleveland Abu Dhabi Dubai Athens Istanbul Civil Geotechnical Environmental Planning Traffic Natural Resources

Types of foundation. Shallow foundations. Pad foundations. Shallow foundations Deep foundations

Types of foundation. Shallow foundations. Pad foundations. Shallow foundations Deep foundations Types of foundation Shallow foundations Deep foundations Shallow foundations (sometimes called 'spread footings') include pads ('isolated footings'), strip footings and rafts. Deep foundations include

More information

LRFD FOUNDATION DESIGN

LRFD FOUNDATION DESIGN LRFD FOUNDATION DESIGN Ching-Nien Tsai, P.E. LADOTD Pavement and Geotechnical Services Why Change? WHAT IS LRFD? Load and Resistance Factor Design 0.9 0.8 0.7 0.6 Load FS Reliability based design Not a

More information

Lesson 5 Test Pile Program Transcript. Welcome to the Pile Driving Inspector Course. This is Lesson 5, Test Pile Program. To begin, select the start

Lesson 5 Test Pile Program Transcript. Welcome to the Pile Driving Inspector Course. This is Lesson 5, Test Pile Program. To begin, select the start Lesson 5 Test Pile Program Transcript Welcome to the Pile Driving Inspector Course. This is Lesson 5, Test Pile Program. To begin, select the start button or press Shift+N on your keyboard. The learning

More information

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 JRHill@HaywardBaker.com

More information

Foundation Support Cost: Applications to Driven-Pile Design

Foundation Support Cost: Applications to Driven-Pile Design Foundation Support Cost: Applications to Driven-Pile Design Pile Driving Contractors Association 2015 Professor s Driven Pile Institute June 25, 2015 Van E. Komurka, P.E., D.GE, F.ASCE Wagner Komurka Geotechnical

More information

CHANCE HELICAL ANCHOR/PILE BEARING CAPACITY

CHANCE HELICAL ANCHOR/PILE BEARING CAPACITY 1 Experience has shown that in most cases the footing and stem wall foundation system that will withstand a given long term working load will withstand a pier installation force of up to 1.5 times that

More information

Auger Grouted Steel Core Displacement Piles. A vast and growing network.

Auger Grouted Steel Core Displacement Piles. A vast and growing network. A vast and growing network. IDEAL is a C.S. Stroyer & Sons company. Est. 1956 and began manufacturing in 2004. Headquarters in Greater Rochester, NY 15 acres 13,500 Sq Ft Corporate office and Training

More information

Continuous Flight Auger Pile Bridge Foundations (Phase II)

Continuous Flight Auger Pile Bridge Foundations (Phase II) Continuous Flight Auger Pile Bridge Foundations (Phase II) Project No. 5-3940-03 Implementation Report 5-3940-03-1 Texas Department of Transportation by C. Vipulanandan Ph.D., P.E. O. Guvener K. Vembu

More information

Presented By: Jeff Grieder, P.Eng. Regional Manager Alberta (North) North American Caisson Limited

Presented By: Jeff Grieder, P.Eng. Regional Manager Alberta (North) North American Caisson Limited Application and Use of Continuous Flight Auger Piles in Western Canada Presented By: Jeff Grieder, P.Eng. Regional Manager Alberta (North) North American Caisson Limited CFA Piles A Brief History Used

More information

INSTALLATION OF DRILLED PIERS

INSTALLATION OF DRILLED PIERS INSTALLATION OF DRILLED PIERS By Dawn C. Tattle, Anchor Shoring & Caissons Ltd., Toronto 1 INTRODUCTION A drilled pier is commonly referred to as a caisson or drilled shaft. Shafts typically range in diameter

More information

DEEP FOUNDATIONS. Dr. Youssef Gomaa Youssef. Dr. Youssef Gomaa Youssef 1

DEEP FOUNDATIONS. Dr. Youssef Gomaa Youssef. Dr. Youssef Gomaa Youssef 1 DEEP FOUNDATIONS Dr. Youssef Gomaa Youssef Dr. Youssef Gomaa Youssef 1 Textbook: Tomlinson, J.J., 1977. Pile Design and Construction Practice, Garden City Press Ltd., Letchworth. Canadian Foundation Engineering

More information

INTERNATIONAL PILING CONTRACTORS

INTERNATIONAL PILING CONTRACTORS Introduction SAUDI FOUNDATIONS & CONCRETE PROCESSING Co. LTD (Saudi Foundations) has been created to provide complete Ground Contracting Solutions and Geotechnical Contracting Services to the construction

More information

Design and Construction of Auger Cast Piles

Design and Construction of Auger Cast Piles Design and Construction of Auger Cast Piles 101 th Annual Road School 2015 3/11/2015 Malek Smadi, Ph.D., P.E. Principal Engineer - GEOTILL - Fishers, IN msmadi@geotill.com - www.geotill.com CONTENTS 1.

More information

Bridge Engineering Seminar

Bridge Engineering Seminar Bridge Engineering Seminar Micropile Foundations for Bridges Lexington, KY Dan Thome, P.E. January 10, 2012 Micropiles Overview Installation Techniques Applications/Case Histories Design Load Testing Reasons

More information

twenty six concrete construction: foundation design ELEMENTS OF ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SPRING 2014

twenty six concrete construction: foundation design ELEMENTS OF ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SPRING 2014 ELEMENTS OF ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SPRING 2014 lecture twenty six concrete construction: www.tamu.edu foundation design Foundations 1 Foundation the engineered

More information

PILE FOUNDATION. Pile

PILE FOUNDATION. Pile PILE FOUNDATION. One or more of the followings: (a)transfer load to stratum of adequate capacity (b)resist lateral loads. (c) Transfer loads through a scour zone to bearing stratum 1 (d)anchor structures

More information

SOILS AND FOUNDATIONS Lesson 09

SOILS AND FOUNDATIONS Lesson 09 SOILS AND FOUNDATIONS Lesson 09 Chapter 9 Deep Foundations Testing Theory Experience Lesson Plan g Topic 1 (Section 9.0 to 9.8) - Driven piles - Static capacity g Topic 2 (Section 9.9) - Driven Piles -

More information

ALLOWABLE LOADS ON A SINGLE PILE

ALLOWABLE LOADS ON A SINGLE PILE C H A P T E R 5 ALLOWABLE LOADS ON A SINGLE PILE Section I. BASICS 5-1. Considerations. For safe, economical pile foundations in military construction, it is necessary to determine the allowable load capacity

More information

New Trends in Auger Pressure Grouted Piles

New Trends in Auger Pressure Grouted Piles New Trends in Auger Pressure Grouted Piles Tracy Brettmann, P.E. Regional Manager, Berkel & Company Contractors, Inc., Richmond, Texas 77469 Abstract: There have been several interesting new trends developing

More information

HIGH CAPACITY HELICAL PILES A NEW DIMENSION FOR BRIDGE FOUNDATIONS

HIGH CAPACITY HELICAL PILES A NEW DIMENSION FOR BRIDGE FOUNDATIONS Proceedings of 8 th International Conference on Short and Medium Span Bridges Niagara Falls, Canada 2010 HIGH CAPACITY HELICAL PILES A NEW DIMENSION FOR BRIDGE FOUNDATIONS Mohammed Sakr Almita Manufacturing

More information

Vertical Capacity The program evaluates the uplift and compression capacity of the pile.

Vertical Capacity The program evaluates the uplift and compression capacity of the pile. AllPile Software is a Windows-based analysis program that handles virtually all types of piles, including steel pipes, H-piles, pre-cast concrete piles, auger-cast piles, drilled shafts, timber piles,

More information

Module 5 : Design of Deep Foundations Lecture 22 : Ultimate pile capacity [ Section 22.1 : Procedure for ultimate pile capacity : Static analysis ]

Module 5 : Design of Deep Foundations Lecture 22 : Ultimate pile capacity [ Section 22.1 : Procedure for ultimate pile capacity : Static analysis ] Lecture 22 : Ultimate pile capacity [ Section 22.1 : Procedure for ultimate pile capacity : Static analysis ] Objectives In this section you will learn the following Static analysis Piles in granular soils

More information

twenty seven concrete construction: foundation design ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN HÜDAVERDİ TOZAN SPRING 2013 lecture

twenty seven concrete construction: foundation design ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN HÜDAVERDİ TOZAN SPRING 2013 lecture ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN HÜDAVERDİ TOZAN SPRING 2013 lecture twenty seven concrete construction: Bright Football Complex www.tamu.edu foundation design Foundations 1 Foundation

More information

DFI Electric Power Systems Foundations Working Group

DFI Electric Power Systems Foundations Working Group DFI Electric Power Systems Foundations Working Group Utility Survey Questions First Name: Last Name: Company Name: Work Phone: Email Address: City: State/Province: Country: A. Demographics 1. Please select

More information

twenty six concrete construction: foundation design Foundation Structural vs. Foundation Design Structural vs. Foundation Design

twenty six concrete construction: foundation design Foundation Structural vs. Foundation Design Structural vs. Foundation Design ELEMENTS OF ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SRING 2014 lecture twenty six Foundation the engineered interface between the earth and the structure it supports that

More information

twenty six concrete construction: foundation design Foundation Structural vs. Foundation Design Structural vs. Foundation Design

twenty six concrete construction: foundation design Foundation Structural vs. Foundation Design Structural vs. Foundation Design ELEMENTS OF ARCHITECTURAL STRUCTURES: FORM, BEHAVIOR, AND DESIGN DR. ANNE NICHOLS SRING 2013 lecture twenty six Foundation the engineered interface between the earth and the structure it supports that

More information

PILE FOUNDATIONS FM 5-134

PILE FOUNDATIONS FM 5-134 C H A P T E R 6 PILE FOUNDATIONS Section I. GROUP BEHAVIOR 6-1. Group action. Piles are most effective when combined in groups or clusters. Combining piles in a group complicates analysis since the characteristics

More information

GEOTECHNICAL ENGINEERING II

GEOTECHNICAL ENGINEERING II GEOTECHNICAL ENGINEERING II MODULE I CHAPTER 2 Site investigation and soil exploration SYLLABUS - Module I 2. Site investigation and soil exploration: objectives - planning - reconnaissance - depth and

More information

PILE DRIVING BEST PRACTICE. TxDOT Bridge Presentations Webinar Sean Yoon, P.E.

PILE DRIVING BEST PRACTICE. TxDOT Bridge Presentations Webinar Sean Yoon, P.E. PILE DRIVING BEST PRACTICE TxDOT Bridge Presentations Webinar Sean Yoon, P.E. July 16, 2014 What is a pile? A pile is a prefabricated element, made of concrete, steel or timber. It is generally long and

More information

Factors that Determine Wall Type Selection. Proximity to existing structures / roadways. Service Life: temporary / permanent

Factors that Determine Wall Type Selection. Proximity to existing structures / roadways. Service Life: temporary / permanent EXCAVATION SUPPORT CONSTRUCTION IN URBAN ENVIRONENTS: CHALLENGES and SOLUTIONS Presented to: DELAWARE VALLE ASSOCIATION OF STRUCTURAL ENGINEERS Domenic D Argenzio, PE, Senior Associate ueser Rutledge Consulting

More information

ODOT LRFD Foundations

ODOT LRFD Foundations Ohio Department of Transportation John R. Kasich, Governor Jerry Wray, Director ODOT LRFD Foundations Alexander Dettloff, P.E. Foundation Engineer Office of Geotechnical Engineering May 07, 2013 AASHTO

More information

Lesson 5 TEST PILE PROGRAM

Lesson 5 TEST PILE PROGRAM Lesson 5 TEST PILE PROGRAM 5-1 Version 1.0-1/15 Page 5-1 Learning Outcomes Describe the Test Pile Program Process Describe the various pile testing methods Identify key elements of the Driving Criteria

More information

9.3. Factors Affecting the Selection of the Suitable Type of Piles for a Given Project: 1. Type, size and weight of the structure to be supported.

9.3. Factors Affecting the Selection of the Suitable Type of Piles for a Given Project: 1. Type, size and weight of the structure to be supported. Chapter 9 Piles and Pile-Driving Equipment 9.1. Introduction: This chapter deals with the selection of load-bearing piles and the equipment required to drive the piles. Load-bearing piles, as the name

More information

Design and Construction of Driven Pile Foundations - Volume I

Design and Construction of Driven Pile Foundations - Volume I Design and Construction of Driven Pile Foundations - Volume I Table of Contents... Page 1....NEED FOR A PILE MANUAL... 1-1 1.1...Scope of Manual... 1-3 1.2...Information Sources... 1-4 2....OVERVIEW OF

More information

Static Testing. Expensive Time consuming

Static Testing. Expensive Time consuming Static Testing Expensive Time consuming Dynamic Pile Testing with the Pile Driving Analyzer Quality Assurance for Deep Foundations 2002, Pile Dynamics, Inc. DYNAMIC TESTING Research began at Case Institute

More information

Load & Resistance Factor Design

Load & Resistance Factor Design Load & Resistance Factor Design Bridge Design Manual Updates Sean Meddles, P.E. Bridge Standard Engineer Topics Covered: New Section 1000 Modifications to existing BDM sections Status of Standard Drawings

More information

CHOICE OF METHODS AND EQUIPMENT FOR EARTH RETENTION SYSTEMS

CHOICE OF METHODS AND EQUIPMENT FOR EARTH RETENTION SYSTEMS CHOICE OF METHODS AND EQUIPMENT FOR EARTH RETENTION SYSTEMS By Dawn C. Tattle, P. Eng. Anchor Shoring & Caissons Ltd., Toronto 1 INTRODUCTION This paper provides information regarding selection, installation

More information

Helical Pile Application and Design

Helical Pile Application and Design PDHonline Course C513 (1 PDH) Helical Pile Application and Design Instructor: Andrew P. Adams, PE 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone & Fax: 703-988-0088 www.pdhonline.org

More information

Province of Saskatchewan

Province of Saskatchewan Flyash Projects in Saskatchewan Collaborative Seminar Series on Responsible Use of Supplementary Cementing Materials (SCMs) in Performance Based Specifications" January 30,2006 1 Province of Saskatchewan

More information

ITEM 404 DRIVING PILING. Table 1 Size of Driving Equipment Minimum Maximum Ram Weight

ITEM 404 DRIVING PILING. Table 1 Size of Driving Equipment Minimum Maximum Ram Weight ITEM 404 DRIVING PILING 404.1. Description. Drive piling. 404.2. Equipment. A. Driving Equipment. Use power hammers for driving piling with specified bearing resistance. Use power hammers that comply with

More information

METHOD OF STATEMENT FOR STATIC LOADING TEST

METHOD OF STATEMENT FOR STATIC LOADING TEST Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents

More information

Rehabilitation of Existing River Piers for

Rehabilitation of Existing River Piers for Creating Value Delivering Solutions Rehabilitation of Existing River Piers for Dick Henderson Bridge, West Virginia i i Joe Carte, P.E. W.V. Department of Transportation Scott Zang, P.E. Michael Baker

More information

ARCH 1230 BUILDING TECHNOLOGY II. Professor Friedman FALL 2012

ARCH 1230 BUILDING TECHNOLOGY II. Professor Friedman FALL 2012 ARCH 1230 BUILDING TECHNOLOGY II Professor Friedman FALL 2012 SUBJECT DATE Building Technology II Foundations Part II FALL 2012 PROFESSOR Friedman spread the load into the earth Professor Friedman arch

More information

A SEISMIC RETROFITTING APPLICATION BY MEANS OF MULTI-HELIX MICROPILES. Shigeo Kanai 1

A SEISMIC RETROFITTING APPLICATION BY MEANS OF MULTI-HELIX MICROPILES. Shigeo Kanai 1 A SEISMIC RETROFITTING APPLICATION BY MEANS OF MULTI-HELIX MICROPILES Shigeo Kanai 1 Abstract The Multi-helix Micropile method utilizes a unique method of directly screwing a small steel pipe pile with

More information

SKIN FRICTION IN SHALE: RESULTS OF THE HWY. 81 BRIDGE, YANKTON, SD DRILLED SHAFT LOAD TEST

SKIN FRICTION IN SHALE: RESULTS OF THE HWY. 81 BRIDGE, YANKTON, SD DRILLED SHAFT LOAD TEST SKIN FRICTION IN SHALE: RESULTS OF THE HWY. 81 BRIDGE, YANKTON, SD DRILLED SHAFT LOAD TEST Scott M. Mackiewicz, PhD, PE, Kleinfelder, 7802 Barton, Lenexa, Kansas, USA Omar Qudus, PE, Nebraska Department

More information

DRILLED SHAFT CONSTRUCTION

DRILLED SHAFT CONSTRUCTION DRILLED SHAFT CONSTRUCTION West Tower Arthur Ravenel Jr. Bridge Photograph courtesy of Marvin Tallent, Palmetto Bridge Constructors Concrete Mix Design Considerations Dry Construction Method Wet Construction

More information

Chapter 18 Pile Foundations

Chapter 18 Pile Foundations Page 18 1 1. Piles are structural members made of (a) steel. (b) concrete. (c) timber. Chapter 18 Pile Foundations 2. Which of the following foundations will have the highest cost? (a) Pile foundation

More information

Prestressed Concrete Piles

Prestressed Concrete Piles FOUNDATION ALTERNATIVES TO MITIGATE EARTHQUAKE EFFECTS 13.17 FIGURE 13.11 Excavation for the grade beam that will span between the two piers. Usually this foundation system is designed by the structural

More information

Civil Engineering Construction Chapter 3

Civil Engineering Construction Chapter 3 Civil Engineering Construction Chapter 3 Deep Foundation Dr Mohamad Syazli Fathi Department of Civil Engineering UTM RAZAK School of Engineering & Advanced Technology UTM International Campus June 24,

More information

AXIAL LOAD TEST PROCEDURES FOR PILE FOUNDATIONS

AXIAL LOAD TEST PROCEDURES FOR PILE FOUNDATIONS AXIAL LOAD TEST PROCEDURES FOR PILE FOUNDATIONS INTRODUCTION Because of the non-availability of reliable procedures for assessing the load transfer mechanisms between piles and surrounding soil, or for

More information

Micropiles Design 101

Micropiles Design 101 Micropiles Design 101 Allen Cadden, P.E. West Chester, PA Las Vegas, NV 2008 Objective Develop a background understanding of the geotechnical and structural design processes for micropiles in structural

More information

Uplift Resistance of Coated Driven Steel Piles. 1Professor, University of Massachusetts, Amherst, Ma

Uplift Resistance of Coated Driven Steel Piles. 1Professor, University of Massachusetts, Amherst, Ma Uplift Resistance of Coated Driven Steel Piles Alan J. Lutenegger 1, F. ASCE and Jahan Khalili 2 1Professor, University of Massachusetts, Amherst, Ma. 13 2 Geotechnical Engineer, GZA Geoenvironmental,

More information

minijet : A New Type of Micropile

minijet : A New Type of Micropile minijet : A New Type of Micropile Dr. Donald A. Bruce 1, Jeffrey J. Bean 2, and Timothy J. Myers 3 1.0 BACKGROUND In U.S. practice (Reference 1), it is common to classify micropiles on the basis of their

More information

Safety Factors for Pile Testing

Safety Factors for Pile Testing Safety Factors for Pile Testing By Garland Likins When designing a foundation system, engineers have many choices, including the ultimate load per pile and pile size (type, length and diameter). The ultimate

More information

AN INTRODUCTION TO BUILDING FOUNDATIONS AND SOIL IMPROVEMENT METHODS

AN INTRODUCTION TO BUILDING FOUNDATIONS AND SOIL IMPROVEMENT METHODS AN INTRODUCTION TO BUILDING FOUNDATIONS AND SOIL IMPROVEMENT METHODS SEAONC 2008 Spring Seminar San Francisco, 16 April 2008 Hadi J. Yap, PhD, PE, GE 1 General Foundation Types Shallow Foundations Spread

More information

Helical Torque Anchors Design Examples

Helical Torque Anchors Design Examples Chapter 3 Helical Torque Anchors Heavy Weight New Construction Light Weight New Construction Basement Wall Tieback Anchors Retaining Wall Tieback Anchors Foundation Restoration Motor Output Torque Ultimate

More information

GENERAL REQUIREMENTS FOR PILING

GENERAL REQUIREMENTS FOR PILING SECTION 70 GENERAL REQUIREMENTS FOR PILING Contents Page 70.001 General 2 70.002 Pile layout, design and construction 2 70.003 Information to be supplied with the Tender 3 70.004 Safety 4 70.005 Forcible

More information

Comprehensive Design Example 2: Foundations for Bulk Storage Facility

Comprehensive Design Example 2: Foundations for Bulk Storage Facility Comprehensive Design Example 2: Foundations for Bulk Storage Facility Problem The project consists of building several dry product storage silos near an existing rail siding in an open field presently

More information

Fayoum University. Faculty of Engineering Department of Civil Engineering. Retaining Structures. Lecture No. (14): Cantilever Sheet Pile Walls

Fayoum University. Faculty of Engineering Department of Civil Engineering. Retaining Structures. Lecture No. (14): Cantilever Sheet Pile Walls Fayoum University Faculty of Engineering Department of Civil Engineering CE 40: Part C Retaining Structures Lecture No. (14): Cantilever Sheet Pile Walls Dr.: Youssef Gomaa Youssef CE 406: Foundation Design

More information

SCREW ANCHOR TEST PROGRAM

SCREW ANCHOR TEST PROGRAM SCREW ANCHOR TEST PROGRAM (Part II): FIELD TEST RESULTS and DESIGN IMPLICATION D.J.Y. Zhang, R. Chalaturnyk, P.K. Robertson, D.C. Sego, and G. Cyre Department of Civil and Environmental Engineering, University

More information

Deep Foundations. Lesson 9 - Topic 2 Construction Monitoring and Quality Assurance. (Section 9.9)

Deep Foundations. Lesson 9 - Topic 2 Construction Monitoring and Quality Assurance. (Section 9.9) Deep Foundations Lesson 9 - Topic 2 Construction Monitoring and Quality Assurance (Section 9.9) Learning Outcomes At the end of this session, the participant will be able to: - Recall pile driving equipment

More information

DIVISION: EARTHWORK SECTION: BORED PILES REPORT HOLDER: GEOTECH ENTERPRISES, INC.

DIVISION: EARTHWORK SECTION: BORED PILES REPORT HOLDER: GEOTECH ENTERPRISES, INC. 0 ICC ES Report ICC ES (800) 423 6587 (562) 699 0543 www.icc es.org 000 Most Widely Accepted and Trusted ESR 3623 Reissued 04/2016 This report is subject to renewal 04/2017. DIVISION: 31 00 00 EARTHWORK

More information

International Society for Helical Foundations (ISHF)

International Society for Helical Foundations (ISHF) QUICK DESIGN GUIDE For Screw-Piles and Helical Anchors in Soils Ver. 1.0 Prepared by Dr. Alan J. Lutenegger, P.E., F. ASCE for International Society for Helical Foundations (ISHF) Copyright 2015 (ISHF)

More information

EXAMPLE. HelixPile software program (Version 2014) Version 1.0 Issued: 24-April-2014 Deep Excavation LLC DEEP EXCAVATION LLC

EXAMPLE. HelixPile software program (Version 2014) Version 1.0 Issued: 24-April-2014 Deep Excavation LLC  DEEP EXCAVATION LLC EXAMPLE HelixPile software program (Version 2014) Version 1.0 Issued: 24-April-2014 Deep Excavation LLC www.deepexcavation.com 1 A. Project description This example will present a helical pile design example

More information

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT Description: This work shall consist of furnishing all materials, equipment and labor necessary for conducting an Osterberg Cell (O-Cell) Load

More information

BUTE Department of Construction Management and Technology

BUTE Department of Construction Management and Technology BUTE Department of Construction Management and Technology 02.10.2012 Definition 1: Foundation: The structure, that transmits the load of the building to the soil Definition 2: Load bearing soil (strata):

More information

Step 11 Static Load Testing

Step 11 Static Load Testing Step 11 Static Load Testing Test loading is the most definitive method of determining load capacity of a pile. Testing a pile to failure provides valuable information to the design engineer and is recommended

More information

E a r t h R e t e n t i o n S y s t e m s a n d S p e c i a l i z e d F o u n d a t i o n s

E a r t h R e t e n t i o n S y s t e m s a n d S p e c i a l i z e d F o u n d a t i o n s E a r t h R e t e n t i o n S y s t e m s a n d S p e c i a l i z e d F o u n d a t i o n s Equipment & Process Since 1959, Schnabel Foundation Company has been the leader in the development of earth retaining

More information

BASIC CONSIDERATIONS. Section I. DEFINITIONS AND CLASSIFICATIONS FM 5-134

BASIC CONSIDERATIONS. Section I. DEFINITIONS AND CLASSIFICATIONS FM 5-134 C H A P T E R 1 BASIC CONSIDERATIONS Section I. DEFINITIONS AND CLASSIFICATIONS 1-1. Definitions. a. Piles. A pile is a long, columnar element made of timber, steel, concrete, or a combination of these

More information

Module 6 : Design of Retaining Structures. Lecture 29 : Braced cuts [ Section 29.1 : Introduction ]

Module 6 : Design of Retaining Structures. Lecture 29 : Braced cuts [ Section 29.1 : Introduction ] Lecture 29 : Braced cuts [ Section 29.1 : Introduction ] Objectives In this section you will learn the following Introduction Lecture 29 : Braced cuts [ Section 29.1 : Introduction ] Introduction Deep

More information

Geotechnical Measurements and Explorations Prof. Nihar Ranjan Patra Department of Civil Engineering Indian Institute of Technology, Kanpur

Geotechnical Measurements and Explorations Prof. Nihar Ranjan Patra Department of Civil Engineering Indian Institute of Technology, Kanpur Geotechnical Measurements and Explorations Prof. Nihar Ranjan Patra Department of Civil Engineering Indian Institute of Technology, Kanpur Lecture No. # 13 (Refer Slide Time: 00:18) So last class, it was

More information

ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT GROUND WATER BRANCH GUIDELINES FOR WELL ABANDONMENT

ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT GROUND WATER BRANCH GUIDELINES FOR WELL ABANDONMENT ALABAMA DEPARTMENT OF ENVIRONMENTAL MANAGEMENT GENERAL GROUND WATER BRANCH GUIDELINES FOR WELL ABANDONMENT According to the U.S. E.P.A., the objectives of an abandonment procedure are to: 1) eliminate

More information

FOUNDATIONS FOR WIND TURBINES ENGR 340 Fall 2011

FOUNDATIONS FOR WIND TURBINES ENGR 340 Fall 2011 FOUNDATIONS FOR WIND TURBINES ENGR 340 Fall 2011 Jeramy C. Ashlock Assistant Professor, CCEE Vern Schaefer Professor, CCEE OUTLINE Topics Lecture # Design requirements, Foundation types 1 Overview of geotechnical

More information

CH. 6 SOILS & FOUNDATIONS

CH. 6 SOILS & FOUNDATIONS CH. 6 SOILS & FOUNDATIONS SOIL PROPERTIES Classified into four groups - Sands & gravels - Clays - Silts - Organics Subsurface Exploration Core borings: undisturbed samples of soil - Recovered bore samples

More information

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional

More information

Helical Design Theory and Applications. By Darin Willis, P.E.

Helical Design Theory and Applications. By Darin Willis, P.E. Helical Design Theory and Applications By Darin Willis, P.E. Solution Systems Ram Jack utilizes two unique underpinning & anchoring systems Hydraulically driven piles (pressed) Helical piles (torqued)

More information

BEARING AND FRICTION DESIGN CAPACITY FOR HELICAL ANCHORS AND PILES

BEARING AND FRICTION DESIGN CAPACITY FOR HELICAL ANCHORS AND PILES BEARING AND FRICTION DESIGN CAPACITY FOR HELICAL ANCHORS AND PILES Original Author: Editor: Gary L. Seider, P.E., Hubbell Power Systems, Inc./CHANCE, Centralia, MO, USA Wayne G. Thompson, PE, CTL Thompson,

More information

c. Heavy Tamping and Dynamic Consolidation (Dynamic compaction )

c. Heavy Tamping and Dynamic Consolidation (Dynamic compaction ) c. Heavy Tamping and Dynamic Consolidation (Dynamic compaction ) Dynamic compaction involves lifting and dropping a heavy weight several times in one place. The process is repeated on a grid pattern across

More information

Outline MICROPILES SUBJECT TO LATERAL LOADING. Dr. Jesús Gómez, P.E.

Outline MICROPILES SUBJECT TO LATERAL LOADING. Dr. Jesús Gómez, P.E. MICROPILES SUBJECT TO LATERAL LOADING Dr. Jesús Gómez, P.E. Micropile Design and Construction Seminar Las Vegas, NV April 3-4, 2008 Outline When are micropiles subject to lateral load? How do we analyze

More information

INSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:!

INSITU TESTS! Shear Vanes! Shear Vanes! Shear Vane Test! Sensitive Soils! Insitu testing is used for two reasons:! In-situ Testing! Insitu Testing! Insitu testing is used for two reasons:! To allow the determination of shear strength or penetration resistance or permeability of soils that would be difficult or impossible

More information

Deep Foundation Axial Load Capacity Static Load Tests Analytic Methods Dynamic methods

Deep Foundation Axial Load Capacity Static Load Tests Analytic Methods Dynamic methods Deep Foundation Axial Load Capacity Static Load Tests Analytic Methods Dynamic methods Pile Foundation vs. Shallow Foundation Soil property unknown after driving Excessive pore water pressure during driving

More information

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations from New construction foundations don t have to be a headache. The CHANCE Helical Pier Foundation System gives you the performance of concrete without the drawbacks and liabilities of driven piles and

More information

DRILLED DEEP FOUNDATIONS

DRILLED DEEP FOUNDATIONS GROUPS: ADVANTAGES Figure 14-2. Group vs. Single Shaft (FHWA NHI-10-016). Large overturning moments are most effectively resisted using groups of shafts. Higher axial capacities. May be cost effective

More information

Dynamic testing in sensitive & difficult soil conditions

Dynamic testing in sensitive & difficult soil conditions Dynamic testing in sensitive & difficult soil conditions Morgano, C.M., White B.A. & Allin, R.C. GRL Engineers, Inc., Cleveland, Ohio, USA Keywords: dynamic testing, radiation damping, set-up, relaxation,

More information

ENGINEERING SPECIFICATION PILE LOAD TEST

ENGINEERING SPECIFICATION PILE LOAD TEST Sheet 1 of 14 ENGINEERING SPECIFICATION PILE LOAD TEST FOR CIVIL WORKS FOR HINDUSTAN PETROLEUM CORPORATION LTD. VISAKH REFINERY DHT PROJECT TEIL JOB NO. : 6261 DOCUMENT NO. : C - 001 A 29.12.2008 For Bid

More information

System. Stability. Security. Integrity. 150 Helical Anchor

System. Stability. Security. Integrity. 150 Helical Anchor Model 150 HELICAL ANCHOR System PN #MBHAT Stability. Security. Integrity. 150 Helical Anchor System About Foundation Supportworks is a network of the most experienced and knowledgeable foundation repair

More information

High Capacity Helical Piles Limited Access Projects

High Capacity Helical Piles Limited Access Projects High Capacity Helical Piles Limited Access Projects Tel 403 228-1767 Canada, USA, Russia Brendan ODonoghue 519 830-6113 Presentation Summary 1. Helical piles Background on large diameter shafts and helices

More information

Partial Factors of Safety

Partial Factors of Safety APPENDIX A Partial Factors of Safety A.I Introduction The capacity of single piles in axial compression should provide an adequate safety factor against failure due to insufficient soil-pile interface

More information

.2 Replace rejected piles to satisfaction of Contract Administrator. Causes for pile rejection are as follows:

.2 Replace rejected piles to satisfaction of Contract Administrator. Causes for pile rejection are as follows: RWPS Foundations and Concrete Structures Page 1 of 5 1. GENERAL 1.1 Work Included.1 Coordinate delivery schedule of piles with the pile supplier (Lafarge Canada Inc.) and pick up and deliver piles from

More information

Deng, N., Ma, Y. "Deep Foundations" Bridge Engineering Handbook. Ed. Wai-Fah Chen and Lian Duan Boca Raton: CRC Press, 2000

Deng, N., Ma, Y. Deep Foundations Bridge Engineering Handbook. Ed. Wai-Fah Chen and Lian Duan Boca Raton: CRC Press, 2000 Deng, N., Ma, Y. "Deep Foundations" Bridge Engineering Handbook. Ed. Wai-Fah Chen and Lian Duan Boca Raton: CRC Press, 2000 32 Deep Foundations Youzhi Ma Geomatrix Consultants, Inc. Nan Deng Bechtel Corporation

More information

DEEP SOIL MIXING SHORING SYSTEM TO CONSTRUCT A 60 MGD, 40 FOOT DEEP WASTEWATER PUMPING STATION

DEEP SOIL MIXING SHORING SYSTEM TO CONSTRUCT A 60 MGD, 40 FOOT DEEP WASTEWATER PUMPING STATION DEEP SOIL MIXING SHORING SYSTEM TO CONSTRUCT A 60 MGD, 40 FOOT DEEP WASTEWATER PUMPING STATION BY DARLA REAMS 1, JEFFREY B. GLOVER 2 AND DAVID J. REARDON 3 HDR ENGINEERING 5175 HILLSDALE CIRCLE EL DORADO

More information

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS Page 1 of 9 SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS 1. GENERAL REQUIREMENTS 1. Description of Work: This work consists of furnishing all materials, equipment and

More information

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS Bilfinger Spezialtiefbau GmbH Goldsteinstrasse 114 D-60528 Frankfurt Phone: +49 69 6688-345 Fax: +49 69 6688-277 Email: info.spezialtiefbau@bilfinger.com

More information

Communication Tower Foundation Selection Criteria

Communication Tower Foundation Selection Criteria Communication Tower Foundation Selection Criteria Introduction This foundation selection criteria document has been prepared by the Engineering Specialties Group as a resource for public and private entities,

More information

Foundation Design. p A. P D P L P u. q a. q g q net. q u. V c V u. w u

Foundation Design. p A. P D P L P u. q a. q g q net. q u. V c V u. w u Foundation Design Notation: a = name for width dimension A = name for area b = width of retaining wall stem at base = width resisting shear stress b o = perimeter length for two-way shear in concrete footing

More information

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL. STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill

More information

Dynamic Testing Methods for. Evaluation of Integrity and Capacity for Drilled Shafts

Dynamic Testing Methods for. Evaluation of Integrity and Capacity for Drilled Shafts Dynamic Testing Methods for Evaluation of Integrity and Capacity for Drilled Shafts PDA PIT CSL Deep Foundation Solutions: Driven Piles Steel, Concrete, Timber Drilled Shafts Wet or Dry, Cased or Uncased

More information

TECHNICAL SERVICES DIGEST APRIL 2014

TECHNICAL SERVICES DIGEST APRIL 2014 210 TECHNICAL SERVICES DIGEST APRIL 2014 SINGLE-WYTHE BRICK FENCES This digest contains information and suggested details on single-wythe brick fences, including details that we recommend be included.

More information

METHOD STATEMENT for INSTALLATION OF MICROPILE

METHOD STATEMENT for INSTALLATION OF MICROPILE METHOD STATEMENT for INSTALLATION OF MICROPILE A. MATERIAL TO BE USED 1. Grout Grout shall be mixed from Ordinary Portland Cement and clean water free from harmful substances. Usage of other cement which

More information

STUDY GUIDE WACEL FOUNDATION INSPECTOR LEVEL I

STUDY GUIDE WACEL FOUNDATION INSPECTOR LEVEL I STUDY GUIDE WACEL FOUNDATION INSPECTOR LEVEL I February 2016 Foundation Inspector Study Guide Scope: WACEL Foundation Inspector is an intermediate certification that builds on both WACEL Soils I and WACEL

More information