1 PART 1 GENERAL 1.1 SUMMARY CIRCULAR GRAVITY FILTER REHABILITATION A. Section Includes: 1.2 REFERENCES 1. Furnish and install the filter equipment as specified herein and shown on the drawings. The manufacturer shall design and supply a new stainless steel pipe under-drain consisting of a manifold with perforated pipe laterals and brass nozzles. Additionally, the manufacturer shall provide new steel wash troughs with wall brackets and fasteners, surface sweeps, and filter media for four (4) circular filters. The existing tank shells shall be reused. 2. The Contractor shall blast clean each tank shell (inside and out) once each unit is drained and the internals are removed. Once blasted clean the Contractor shall replace and/or repair any tank damage, welded in trough supports, welded in tank spools and associated flanges, and replace any air/water piping as shown on the drawings or otherwise found to be corroded or otherwise defective. The ENGINEER shall be responsible for working with the CONTRACTOR to determine which parts shall be reused once each filter is cleaned and disassembled. The ENGINEER shall also be responsible for providing the CONTRACTOR with any tank shell repair plans, including the bottom plate and interface between the steel tank, the tank bottom plate and concrete foundation. The Contractor is responsible for all associated work with regard to demo, disposal, cleaning existing tank steel, disassembly, repair, replacement, coatings, etc. for and areas required by the specs or plans, which are not part of the equipment supplier s proposed scope of supply. A. American Water Works Association (AWWA): 1. AWWA B Granular Filter Material. 1.3 SUBMITTALS A. Drawings: 1. Submit necessary drawings to site contractor and/or plant for filter part replacement prior to commencing any work on the system in accordance with the requirements of Section 01330, Submittal Procedures. Page 1 of 8

2 Submittal data shall include: a. General Arrangement drawings with Materials of construction. b. Installation details and leveling requirements. B. Field Reports: 1. Submit to the ENGINEER within 2 weeks of site visit. 1.4 PRODUCT HANDLING, STORAGE, AND DELIVERY A. Place or store underdrains, troughs, and specialties only in designated staging areas as approved by the ENGINEER. B. Store underdrains and specialties off the ground, under ultravioletresistant tarps from time of delivery on-site until final installation in the filters. C. Replace underdrains and specialties damaged during storage and delivery. D. Underdrains and specialties are subject to inspection at the ENGINEER s request if visual evidence of damage is observed. 1.5 SYSTEM DESIGN A. Existing Filter Size and Construction: The filter underdrain system shall be as shown and specified. Each existing filter cell shall be of nominal dimensions as listed below: No. of Filters: 4 No. of Cells per Filter: 1 Filter Cell Radius (ft): 9.25 Filter Tank Depth (ft) 9.05 Area per Filter (ft 2 ): 269 ft 2 Total Filter Area for All Four Filters (ft 2 ): 1076 ft 2 Existing Tank material Painted carbon steel Page 2 of 8

3 B. Filter Design Conditions: The filter under-drain and backwash trough parts shall be furnished and installed to perform satisfactorily and as specified when operated under the following flow conditions: Flow Capacity per Filter (clean) 1,050 gpm max. Backwash Rate per Filter 20 gpm/ ft 2 C. General Design Requirements: 1. A single responsible MANUFACTURER shall furnish all equipment components as specified herein, and shall be experienced in the design and manufacture of gravity filters. The MANUFACTRER shall have a minimum 40 years of successful filter operation using circular gravity type filters with pipe under-drain laterals while treating lime softened clarifier water at this facility. 2. Design the filter under-drain parts to ensure long-term stability in its operating characteristics. 3. Due to the assembled size of the under-drain, the pipe laterals shall ship loose from the manifold header pipe for field assembly by the Contractor. D. Performance Requirements: 1. Design the filter under-drain parts to produce uniform water flows throughout the filter cell over the full range of normal backwash flow rates. Flow uniformity per square foot of filter area shall be as required to permit efficient and effective filtration and backwashing. E. Other Requirements: 1. Furnish such installation details and recommendations as are necessary to acceptably interface the filter parts with all surrounding structures, including requirements for leveling, grouting keys and pockets, dowels, piers, and anchorage. Prior modifications by the plant to the original tank structure, piping or associated part interfaces, which may affect the installation and/or operation of the new filter parts, shall be the responsibility of the Engineer and Contractor. 1.6 QUALITY ASSURANCE A. Certification: Provide a manufacturer s certificate of proper installation that states the filter parts have been installed in accordance with the manufacturer s requirements and has been supervised by an authorized representative of the manufacturer and that all of the specified testing has been conducted to insure proper performance. Page 3 of 8

4 B. Under-drain piping, supports, wash troughs, media, surface wash agitators, and any specialties required for installation such as special anchorage, leveling shims, etc. shall be the products of a single MANUFACTURER. PART 2 PRODUCTS 2.1 MANUFACTURERS A. Filter Parts: as originally provided by: 1. Infilco Degremont, Inc. 2.2 UNDERDRAIN MATERIALS & FABRICATION A. Underdrain 1. Each existing filter tank shall be supplied with a new under-drain consisting of a 16 manifold pipe and 2 ½ pipe laterals. The manifold pipe and pipe laterals shall be Type 304 stainless steel. Brass nozzles shall be provided for mounting to the top of the manifold pipe and shipped loose for field installation by the Contractor. Each pipe lateral shall include shop drilled, downward facing orifices, which are 1/4" in diameter. Manifold nozzles and pipe lateral orifices shall be spaced to match the existing design. The new manifold pipe shall be designed to fit inside the existing tank and the existing nozzle pipe, which is welded to the tank shell. The Contractor shall fit the pipe, provide packing to prevent leakage between the new manifold and existing tank nozzle. The Contractor shall also provide and install new grout as noted on the drawings below the under-drain piping. The ENGINEER shall direct the CONTRACTOR as to whether the old under-drain grout must be removed in order to clean and paint the tank bottom plate. Grout removal, repair and new grout shall be provided and installed by the CONTRACTOR. 2.3 WASH TROUGHS A. General: One (1) Wash trough Assembly consisting of seven individual troughs shall be provided per filter 1. All necessary wash water troughs shall be supplied and installed as shown on the plans. 2. Troughs shall have round bottoms and vertical sides. Top edges of the troughs shall be straight with no more than 1/8-inch deviation from a true plane. Longitudinal stiffening ribs shall be welded on the outside of the troughs to assure rigidity. 3. Spacer bars shall be spaced to prevent buckling, and to provide Page 4 of 8

5 2.4 FILTER MEDIA maximum resistance to water loading on the sidewalls of the trough. 4. Troughs shall be A36 carbon steel and shop coated with NSF-61 certified epoxy coatings. 5. Trough layout, outlet, and support system shall be as shown on the approved submittal drawings. All anchors and fasteners shall be Type 304 stainless steel. Shims shall be provided to place under trough ends for leveling at each existing tank wall bracket. Stabilizers shall be provided where necessary to restrict lateral movement (oscillation). The contractor shall perform final weir plate adjustment after installation of troughs. A. General: The following media shall be supplied, shipped in Supersacks. Media provided as follows: Layer Media Type Depth Amount Per Filter 1 Anthracite cu. Ft 2 Silica Sand cu. Ft 3 Torpedo Sand 3 67 cu. Ft. 4 Gravel (1/8-1/4 ) 3 67 cu Ft. 5 Gravel (1/4-1 ½ ) cu. Ft 6 Gravel (1/2-3/4 ) cu. Ft 7 Gravel (3/4 1 ½ ) cu Ft. 1. A layer of torpedo sand, at least 3 finished depth, after backwashing, scraping, and removal of fines, shall be placed on top of gravel support layer and filter underdrain. The sand shall have an effective size of 0.8 mm to 1.2 mm, well rounded, not flat or angular, with a uniformity coefficient of A layer of torpedo sand at least 9 finished depth, after backwashing, scraping, and removal of fines, shall be placed on top of gravel support layer and filter under-drain. The sand shall have an effective size of 0.45 mm to 0.55 mm, well rounded, not flat or angular, with a uniformity coefficient of A layer of anthracite, at least 18 finished depth, after backwashing, scraping, and removal of fines, shall be placed on top of the filter media and gravel support layers. The anthracite shall have an effective size of 0.9 to 1.0 mm with a uniformity coefficient of The filter media supplier shall include sufficient media to allow for scraping of fines during media placement and cleaning. Media levels specified are considered finished depths. Page 5 of 8

6 2.5 SURFACE WASH AGITATORS A. General: Each filter cell shall be provided with one (1) 15-0 surface wash agitator assemblies. 1. The surface wash system shall provide effective cleaning of the filter. The plant shall provide water flow to each surface wash assembly as follows: a. Pressure: 85 psi minimum b. Flow: 179 gpm minimum 2. Each agitator shall include two arms supported by center bearing assembly. The arm piping and end caps shall be constructed of Brass. 3. The center bearing shall be constructed of bronze (ASTM-B ) and shall have a 2 FNPT to connect to the existing 2 ½ supply header assembly piping (by the Contractor). The Manufacturer shall provide a 2-2 ½ transition fitting with dielectric fitting where required. 4. The spray nozzles shall be connected to the agitator arms and shall be spaced and sized according to the filter underdrain manufacturer. There shall be an adequate number of nozzles to produce the flowrate at the specified pressures. The nozzles shall be threaded to the agitator arms for easy removal. The nozzles shall be constructed of Delrin. 5. Pipe, fittings and valves up to the center bearing assembly shall be by others. 2.6 FILTER CONTROL PANEL A. No filter controls are provided for this project. All filter controls are existing. 2.7 COATINGS A. All carbon steel parts shall be shop blasted to SSPC-SP 10 and painted. The troughs shall be coated with Tnemec Pota-Pox Series 20, 2 coats at MDFT each coat for a total DFT of mils or MANUFACTURER approved equal, color 39BL Delft Blue. The stainless steel under-drain piping shall be not be painted. All coatings shall be NSF- 61 certified. Brass parts shall not be painted. The tank shell and all other field applied coatings shall be by the Contractor and as directed by the Engineer. B. The Contractor shall be responsible for touch-up paint after field installation as needed. Page 6 of 8

7 PART 3 EXECUTION 3.1 INSTALLATION A. General: Install the filter under-drain parts in strict accordance with the manufacturer s installation drawings and printed recommendations and as specified. Obtain from the underdrain MANUFACTURER such written installation details, recommendations, and training required to acceptably interface the filter underdrain system with all existing structures. B. Placement and Cleaning: 1. Take all necessary precautions recommended by the underdrain manufacturer s published instructions and as specified to insure that the filter parts and piping are completely clean and free of any debris, dirt, or other foreign materials which could clog the underdrain system or interfere with flow. Before pouring of the underdrain concrete and installation of the filter media, vacuum clean the underdrain area, all cell effluent and backwash supply piping, and all surfaces that come into contact with backwash supply water. C. Installation: 1. The underdrain supplier shall retain on its permanent staff, field service staff who is experienced in the placement of the filter underdrain. Such persons shall be available on a fee-paid basis to guide the Contractor in the proper placement and testing of the underdrain. 2. Follow the filter manufacturer s specific installation instruction. 3. Following the installation, the system shall be completely cleaned and washed free of all loose materials and debris. The underdrain shall be allowed to set for three days before applying internal water pressure. The system shall be installed and tested completely in accordance with the specifications of the filter manufacturer, and under the direction of an experienced superintendent provided by the filter manufacturer. 4. Place filer media in strict accordance with the filter media supplier s recommendations, and under the direct supervision of his authorized field supervisor. Wash each layer of media by backwashing. Each media layer shall have fines scraped after backwashing. The Contractor shall be responsible for insuring the availability and connection of water for backwashing each filter to remove fines and to perform scraping of fines from each media layer. Page 7 of 8

8 3.2 MANUFACTURER S FIELD SERVICES A. The filter parts manufacturer shall provide the services of a technical representative for one (1) trip and two (2) working days per filter train (2 filters) to inspect the completed installation and witness preliminary leak tests. One (1) trip and two (2) working days shall be provided during media installation, backwashing and scraping of fines by the Contractor per filter train (2 filters). One (1) trip and two (2) working days shall be provided during start-up and for training per filter train (2 filters) A total of six (6) trips and twelve (12) days maximum shall be provided by the filter parts Manufacturer to complete onsite service of both filter trains. END OF SECTION Page 8 of 8

SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE

SECTION 15076 CEMENT-MORTAR LINED AND COATED STEEL PIPE SECTION 15076 CEMENT-MORTAR LINED AND COATED (CML&C) STEEL PIPE PART 1 GENERAL 1.01 DESCRIPTION This section designates the requirements for steel pipe fabrication, test in shop, installation of steel

More information

BLADDER SURGE CONTROL SYSTEM

BLADDER SURGE CONTROL SYSTEM PART I GENERAL 1.01 Description BLADDER SURGE CONTROL SYSTEM This specification describes the requirements for a Bladder Surge Control System. The purpose of the system is to minimize transient pressures

More information

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES

AIR RELEASE, CLEANOUT, AND SEWER MANHOLES AIR RELEASE, CLEANOUT, AND SEWER MANHOLES **From Hartford IM BLDG(10) DESCRIPTION. This work shall consist of the construction of air release, cleanout, and sanitary sewer manholes; and the furnishing

More information

SECTION 1 GENERAL REQUIREMENTS

SECTION 1 GENERAL REQUIREMENTS Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,

More information

SECTION 15410 GROUND WATER STORAGE TANKS

SECTION 15410 GROUND WATER STORAGE TANKS SECTION 15410 GROUND WATER STORAGE TANKS PART 1 GENERAL.01 SCOPE A. Section Includes Requirements for designing, fabricating, and erecting a welded steel ground storage tank..02 SYSTEM DESCRIPTION A. Design

More information

PACKAGE TERTIARY FILTER SYSTEM SPECIFICATIONS MODELS TF-2-6-C THROUGH TF-2-35-C

PACKAGE TERTIARY FILTER SYSTEM SPECIFICATIONS MODELS TF-2-6-C THROUGH TF-2-35-C PACKAGE TERTIARY FILTER SYSTEM SPECIFICATIONS MODELS TF-2-6-C THROUGH TF-2-35-C Pollution Control Systems Inc. (PCS) is pleased to provide the following equipment specifications for your consideration.

More information

Mechanical Installation

Mechanical Installation Page -1-1. INTRODUCTION AND PURPOSE 1.1. This specification covers the installation, testing and precommissioning of mechanical equipment. Work is to be performed in conjunction with the manufacturer s

More information

SECTION 33 12 19 FIRE HYDRANTS

SECTION 33 12 19 FIRE HYDRANTS SECTION 33 12 19 FIRE HYDRANTS PART 1: GENERAL 1.01 SCOPE A. Fire hydrants. B. Adjustment of fire hydrants and gate valves. 1.02 SUBMITTALS A. Conform to requirements of Section 01 33 00 - Submittals.

More information

SECTION 807 PUMP STATION REHABILITATION

SECTION 807 PUMP STATION REHABILITATION SECTION 807 PUMP STATION REHABILITATION 807-1 DESCRIPTION: Rehabilitation of pump stations shall be defined as the cleaning, removal, repair and/or replacement of any and/or all components including but

More information

Wastewater Capital Projects Management Standard Construction Specification

Wastewater Capital Projects Management Standard Construction Specification CITY AND COUNTY OF DENVER ENGINEERING DIVISION Wastewater Capital Projects Management Standard Construction Specification 10.1 Precast Concrete Pipe 10.1.1 General This section covers material requirements,

More information

Model F822 thru F834 Mulsifyre Directional Spray Nozzles, Open, High Velocity General Description

Model F822 thru F834 Mulsifyre Directional Spray Nozzles, Open, High Velocity General Description Worldwide Contacts www.tyco-fire.com Model F thru F3 Mulsifyre Directional Spray Nozzles, Open, High Velocity General Description The Mulsifyre Nozzles are open (nonautomatic) nozzles and they are designed

More information

2. Division 05 Structural Steel Framing for steel framework requirements

2. Division 05 Structural Steel Framing for steel framework requirements SECTION 131200 - CLIMBING WALLS PART 1 GENERAL 1.1 SUMMARY A. This section includes the following: 1. GFRC Rock Realistic Climbing Wall System B. Related Sections 1. Division 04 Unit Masonry 2. Division

More information

SECTION 15420 WATER STORAGE TANK PAINTING

SECTION 15420 WATER STORAGE TANK PAINTING SECTION 15420 WATER STORAGE TANK PAINTING PART 1 GENERAL.01 SCOPE A. Section Includes Surface preparation, shop priming, and field coating for interior wet, interior dry, and exterior surfaces of steel

More information

Specification Guidelines: Allan Block Modular Retaining Wall Systems

Specification Guidelines: Allan Block Modular Retaining Wall Systems Specification Guidelines: Allan Block Modular Retaining Wall Systems The following specifications provide Allan Block Corporation's typical requirements and recommendations. At the engineer of record's

More information

Calcite PH Nutralizer System

Calcite PH Nutralizer System Calcite PH Nutralizer System Installation, Operation & Maintenance Manual Facts About Calcite Ph Neutralizers Calcite is a crushed and screened white marble media which can inexpensively be used to neutralize

More information

Section 2100-Trenching and Tunneling

Section 2100-Trenching and Tunneling SECTION 5200 - STORM SEWER PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of storm sewer mains and culverts. Topics include permits and fees, trench widths, pipe laying, bedding, initial

More information

STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS

STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS STANDARD SPECIFICATIONS SECTION 02512 CLEANING AND LINING WATER MAINS PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for cleaning and lining existing cast iron and ductile iron water mains

More information

James M. Pleasants Company

James M. Pleasants Company James M. Pleasants Company SUBMITTAL DATA GAINESVILLE MECHANICAL DECEMBER 20, 2013 PROJECT: GSU: J-183 HUMANITIES LAW BLDG. QUOTE NO:12116 ENGINEER: STEVENS & WILKINSON GASKETED PLATE HEAT EXCHANGER Tag:

More information

SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION 623.10 CONCRETE BONDING COMPOUND.

SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION 623.10 CONCRETE BONDING COMPOUND. SECTION 623 CONCRETE BONDING COMPOUND, EPOXY MORTAR AND EPOXY POLYMER CONCRETE OVERLAY SECTION 623.10 CONCRETE BONDING COMPOUND. 623.10.1 Description. This work shall consist of preparing the surface,

More information

Stainless Steel Perimeter Recirculation Systems Engineered supply and return systems for swimming pools, water features and aquatic facilities.

Stainless Steel Perimeter Recirculation Systems Engineered supply and return systems for swimming pools, water features and aquatic facilities. Stainless Steel Perimeter Recirculation Systems Engineered supply and return systems for swimming pools, water features and aquatic facilities. Whether it is new construction, renovation or operation,

More information

SPECIFICATIONS. INTERLOCKING CONCRETE POROUS PAVING UNITS or Permeable Interlocking Concrete Pavers (PICP)

SPECIFICATIONS. INTERLOCKING CONCRETE POROUS PAVING UNITS or Permeable Interlocking Concrete Pavers (PICP) SPECIFICATIONS INTERLOCKING CONCRETE POROUS PAVING UNITS or Permeable Interlocking Concrete Pavers (PICP) Part 1 General 1.1 CONFORMITY Conforms to the requirements of the general conditions of the contract.

More information

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified. Section 33 0200- Page 1 of 4 PART 1 - GENERAL 1.1 DESCRIPTION OF WORK The work of this Section includes furnishing and installing Reinforced Concrete Pressure Pipe as shown on the Drawings and as specified.

More information

SECTION 02630 STORM DRAINAGE SYSTEM

SECTION 02630 STORM DRAINAGE SYSTEM SECTION 02630 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for storm drainage systems including modifications and connections to existing storm drainage systems. 1.02 REFERENCE

More information

High Strain Dynamic Load Testing of Drilled Shafts

High Strain Dynamic Load Testing of Drilled Shafts Supplemental Technical Specification for High Strain Dynamic Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 3, 2015 1.0 GENERAL This work shall consist of performing high-strain

More information

Specifications For Rehabilitation Hudson #1A Hudson #2 Foster Island Well #41

Specifications For Rehabilitation Hudson #1A Hudson #2 Foster Island Well #41 Specifications For Rehabilitation Hudson #1A Hudson #2 Foster Island Well #41 ITEM #6 1) Scope of Work The scope of this proposal is: Hudson Street Well #1A and Hudson Street Well #2 - clean and rehabilitate,

More information

Pressure Vessel Assessment Report

Pressure Vessel Assessment Report Project Information Client: Total Energy Location: Blackwell OK Date: 7/23/2013 Contact: Integrity Mgmt. Advisor: Chuck Easterbrooks - API 510 #2212 Cc: API / UT Inspector: Robert Van Pelt-API 510# 40899

More information

CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS

CCU Engineering Specifications. Section 003300 PRECAST CONCRETE PRODUCTS CCU Engineering Specifications Section 003300 Effective Date: Nov. 1st, 2011 Page 1 of 5 PRECAST CONCRETE PRODUCTS PART 1 - GENERAL The following specification is intended for use for the design, selection

More information

SWIMMING POOL, SPA, & HOT TUB GUIDELINES

SWIMMING POOL, SPA, & HOT TUB GUIDELINES SWIMMING POOL, SPA, & HOT TUB GUIDELINES Pool permit cost is based on the total value of the project. See Permit Fee Schedule Table 1A. A. Adopted construction codes and installation requirements 1. 2015

More information

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION

SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION SPECIFICATION FOR PIPE SUBSOIL DRAIN CONSTRUCTION 1. SCOPE Pipe subsoil drains shall be constructed in accordance with this specification and in conformity with the lines, grades and cross-sections shown

More information

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS

SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS Page 1 of 9 SAMPLE GUIDE SPECIFICATIONS FOR OSTERBERG CELL LOAD TESTING OF DEEP FOUNDATIONS 1. GENERAL REQUIREMENTS 1. Description of Work: This work consists of furnishing all materials, equipment and

More information

A. The CONTRACTOR shall provide pipe coating, complete and in place, in accordance with the Contract Documents.

A. The CONTRACTOR shall provide pipe coating, complete and in place, in accordance with the Contract Documents. POLYURETHANE COATING ON STEEL PIPE PART 1 -- GENERAL 1.1 THE REQUIREMENT A. The CONTRACTOR shall provide pipe coating, complete and in place, in accordance with the Contract Documents. 1.2 REFERENCE SPECIFICATIONS,

More information

SANITARY SEWER SPECIFICATIONS

SANITARY SEWER SPECIFICATIONS SANITARY SEWER SPECIFICATIONS OCTOBER 2003 HARVEST-MONROVIA WATER, SEWER, AND FIRE PROTECTION AUTHORITY SECTION 1.00 1.10 Purpose The purpose of this document is to assemble the sewer specifications, policies,

More information

Checklist for plans to Construct, Alter or Repair An Individual Subsurface Sewage Disposal System

Checklist for plans to Construct, Alter or Repair An Individual Subsurface Sewage Disposal System Checklist for plans to Construct, Alter or Repair An Individual Subsurface Sewage Disposal System An application for the construction or alteration of an individual subsurface sewage disposal system shall

More information

CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General

CITY OF BEVERLY RULES AND REGULATIONS - SEWER SYSTEM TESTING. General General All sanitary sewers, manholes and force mains shall be acceptance tested, as hereinafter specified in the presence of a City representative. Acceptance testing shall be performed after backfilling

More information

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250.

SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING UTILITIES AND UNDERGROUND STRUCTURES. 1. Trench excavation, backfill, and compaction; Section 02250. 02150-1 of 6 SECTION 02150 REMOVAL OR ABANDONMENT OF EXISTING 02150.01 GENERAL A. Description Removal or abandonment of existing utilities and underground structures shall include, but not necessarily

More information

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE

SECTION 6 SANITARY SEWER MAIN 6.01 SCOPE 6.01 SCOPE The work covered by this section of the specifications consists of the furnishing of all plant, labor, materials, equipment and supervision and performing all operations involved in the construction

More information

SECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES

SECTION 33 05 16.13 PRECAST CONCRETE UTILITY STRUCTURES SECTION 33 05 16.13 PRECAST CONCRETE PART 1 - GENERAL 1.01 SECTION INCLUDES A. This item shall consist of the construction of both sanitary and storm sewer precast concrete manholes in accordance with

More information

SECTION 11014 WINDOW WASHING SYSTEMS

SECTION 11014 WINDOW WASHING SYSTEMS SECTION 11014 WINDOW WASHING SYSTEMS PART 1 - GENERAL 1.1 SUMMARY A. Section includes, but is not limited to, design and furnishing portable davits, davit sleeves, dvit bases, four (4) removable outriggers,

More information

SECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS

SECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS SECTION 02720 SANITARY SEWER AND STORM DRAIN SYSTEMS PART 1 GENERAL 1.01 SECTION INCLUDES A. The requirements for pipe material and installation in sewer and drainage collection systems. All materials

More information

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional

More information

SECTION 15 AIR RELEASE VALVE ASSEMBLIES. 15-1 General

SECTION 15 AIR RELEASE VALVE ASSEMBLIES. 15-1 General SECTION 15 AIR RELEASE VALVE ASSEMBLIES 15-1.01 Scope 15-1 General This section describes the requirements for furnishing and installing Air Release Valve Assemblies of the size and type shown on the plans,

More information

POLYURETHANE LINING AND COATING ON PIPE RAW WATER

POLYURETHANE LINING AND COATING ON PIPE RAW WATER POLYURETHANE LINING AND COATING ON PIPE RAW WATER PART 1 -- GENERAL 1.1 THE REQUIREMENT A. The CONTRACTOR shall provide pipe coating, complete and in place, in accordance with the Contract Documents. 1.2

More information

Spray Nozzles. Spray Control. Spray Fabrication. Spray Analysis. A Guide to Optimizing In-Tank Agitation and Mixing Using Eductors

Spray Nozzles. Spray Control. Spray Fabrication. Spray Analysis. A Guide to Optimizing In-Tank Agitation and Mixing Using Eductors s Control Analysis Fabrication A Guide to Optimizing In-Tank Agitation and Mixing Using Eductors Eductors Ensure Thorough Mixing to Improve Product Quality and Reduce Maintenance Time Tank mixing eductors

More information

CLEANING, INSPECTION, AND TESTING OF SEWERS

CLEANING, INSPECTION, AND TESTING OF SEWERS CLEANING, INSPECTION, AND TESTING OF SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Cleaning, Inspecting, and Testing Sanitary Sewers B. Cleaning, Inspecting, and Testing Storm Sewers C. Cleaning and

More information

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701)

SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) SECTION 55 PIPE FOR STORM DRAINS AND CULVERTS (FAA D-701) 55-1 GENERAL The Contractor shall perform all work required by the plans for construction of pipe for storm drains, precast polymer trench drains

More information

Section 02702 SEWER PIPE INSTALLATION AND TESTING

Section 02702 SEWER PIPE INSTALLATION AND TESTING PART 1 - GENERAL Section 02702 SEWER PIPE INSTALLATION AND TESTING 1-1. SCOPE. This section covers the installation and testing of all sewer pipe furnished under the following specification sections: Concrete

More information

EXPANDED POLYSTYRENE (EPS) INSULATION BOARD SPECIFICATIONS

EXPANDED POLYSTYRENE (EPS) INSULATION BOARD SPECIFICATIONS EXPANDED POLYSTYRENE (EPS) INSULATION BOARD SPECIFICATIONS 1. SCOPE 1.1 This specification covers the type, physical properties and dimensions of Expanded Polystyrene Insulation Board intended for use

More information

LEGACY REPORT ER-5110. www.icc-es.org. ICC Evaluation Service, Inc. Reissued November 1, 2003. Legacy report on the 1997 Uniform Building Code

LEGACY REPORT ER-5110. www.icc-es.org. ICC Evaluation Service, Inc. Reissued November 1, 2003. Legacy report on the 1997 Uniform Building Code LEGACY REPORT Reissued November 1, 2003 ICC Evaluation Service, Inc. www.icc-es.org Business/Regional Office # 5360 Workman Mill Road, Whittier, California 90601 # (562) 699-0543 Regional Office # 900

More information

SECTION 14 20 10 - FREIGHT & PARKING GARAGE ELEVATORS PART I - GENERAL

SECTION 14 20 10 - FREIGHT & PARKING GARAGE ELEVATORS PART I - GENERAL SECTION 14 20 10 - FREIGHT & PARKING GARAGE PART I - GENERAL 1.1 SECTION INCLUDES [NOTE to AE: The following lists requirements that are specific to freight elevators. These requirements are in addition

More information

Pro-Lift Steel Pile Foundation Repair

Pro-Lift Steel Pile Foundation Repair Pro-Lift Steel Pile Foundation Repair Pro-Lift Steel Pile Foundation Repair System Pro-lift steel piles are designed for the stresses of Texas soils. They can have multiple steel walls, depending on the

More information

1.02 DESCRIPTION A. This Section specifies furnishing and installing Cast in Place Detectable/Tactile Warning Surface tiles where indicated.

1.02 DESCRIPTION A. This Section specifies furnishing and installing Cast in Place Detectable/Tactile Warning Surface tiles where indicated. CAST IN PLACE DETECTABLE/TACTILE WARNING SURFACE TILE PART 1 GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Special Conditions and Division 1 Specifications

More information

Sports and High Mast Lighting Poles Phone: (866) 474-7200 Fax: (817) 924-7049

Sports and High Mast Lighting Poles Phone: (866) 474-7200 Fax: (817) 924-7049 Sports and High Mast Lighting Poles 4 High Mast Lighting Poles General American LitePole offers a raising and lowering system that allows for ease of maintaining the lighting system at ground level. Ideal

More information

SECTION 08332 COILING COUNTER DOORS. Display hidden notes to specifier. (Don't know how? Click Here)

SECTION 08332 COILING COUNTER DOORS. Display hidden notes to specifier. (Don't know how? Click Here) SECTION 08332 COILING COUNTER DOORS Display hidden notes to specifier. (Don't know how? Click Here) PART 1 GENERAL 1.1 SECTION INCLUDES A. Coiling Metal Counter Doors. B. Coiling Counter Fire Doors. 1.2

More information

Fiberstars Lighted Laminar Flow Fountain Installation Manual

Fiberstars Lighted Laminar Flow Fountain Installation Manual Fiberstars Lighted Laminar Flow Fountain Installation Manual 79-15037-00 REV Xx http://www.fiberstars.com Page 1 of 8 SAVE THESE DIRECTIONS! These directions are provided to ensure the proper installation

More information

ENGINEERING SPECIFICATION FIBERGRATE MOLDED GRATING. January 24, 2014 06610-1

ENGINEERING SPECIFICATION FIBERGRATE MOLDED GRATING. January 24, 2014 06610-1 ENGINEERING SPECIFICATION FIBERGRATE MOLDED GRATING January 24, 2014 06610-1 SECTION 06610 FIBERGLASS REINFORCED PLASTICS (FRP) FABRICATIONS MOLDED GRATING PART 1 - GENERAL 1.1 SCOPE OF WORK A. The CONTRACTOR

More information

IHSS-N1 WELDED HONEYCOMB CORE SPECIFICATION. Generated: Sergiy Papyshev Engineering. Approved: Don Prysi Manufacturing. Approved: Merzuk Ramic Quality

IHSS-N1 WELDED HONEYCOMB CORE SPECIFICATION. Generated: Sergiy Papyshev Engineering. Approved: Don Prysi Manufacturing. Approved: Merzuk Ramic Quality IHSS-N1 WELDED HONEYCOMB CORE SPECIFICATION Generated: Sergiy Papyshev Engineering Approved: Don Prysi Manufacturing Approved: Merzuk Ramic Quality Approved: Steven Barnett Administrative DATE DATE DATE

More information

ROOF DRAINS TABLE OF CONTENTS

ROOF DRAINS TABLE OF CONTENTS Pictorial Index Product Recommendations Roof Drain Selection Factors Sizing Placement Material & Characteristics Pipe Connection Commonly Specified Options Typical Installations TABLE OF CONTENTS ROOF

More information

PIPING SYSTEM - ABRASIVE SLURRIES Engineering Standard Specification. 96 B. Riutta

PIPING SYSTEM - ABRASIVE SLURRIES Engineering Standard Specification. 96 B. Riutta PIPING SYSTEM - ABRASIVE SLURRIES Engineering Standard Specification Number: 3503-11.2.610 Rev. 2 Rubber Lined Steel Pipe and Fittings Mechanically Coupled Plain End Type System Issued Revised Approved

More information

PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE

PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE FORM A PTS HELICAL PIERS INSTALLATION SPECIFICATIONS NOTICE The following suggested specifications are written as a guide to assist the specifier in writing his own specifications. Specific circumstances

More information

07 21 19 Guide Specification STAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM

07 21 19 Guide Specification STAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM 07 21 19 STAYFLEX CORROSION CONTROL AND THERMAL INSULATION SYSTEM 7819 Broadview Road Cleveland, OH 44131 800-522-4522 February, 2011 SPEC NOTE: This guide specification is intended for use when specifying

More information

NAPCA BULLETIN 18-99 APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE

NAPCA BULLETIN 18-99 APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE NAPCA BULLETIN 18-99 APPLICATION PROCEDURES FOR CONCRETE WEIGHT COATING APPLIED BY THE COMPRESSION METHOD TO STEEL PIPE GENERAL a. These specifications may be used in whole or in part by any party without

More information

725-R-599 PIPE LINING. (Revised 05-01-12) SECTION 725, BEGIN LINE 1, INSERT AS FOLLOWS: SECTION 725 SLIP LINING OF EXISTING PIPE

725-R-599 PIPE LINING. (Revised 05-01-12) SECTION 725, BEGIN LINE 1, INSERT AS FOLLOWS: SECTION 725 SLIP LINING OF EXISTING PIPE PIPE LINING (Revised 05-01-12) The Standard Specifications are revised as follows: SECTION 725, DELETE LINES 1 THRU 317. SECTION 725, BEGIN LINE 1, INSERT AS FOLLOWS: SECTION 725 SLIP LINING OF EXISTING

More information

BRIDGE FIELD PAINTING, REPAINTING, 412 AND PAINT RESIDUE CONTAINMENT. A. Field Painting, Bridge Repainting and Residue Containment:

BRIDGE FIELD PAINTING, REPAINTING, 412 AND PAINT RESIDUE CONTAINMENT. A. Field Painting, Bridge Repainting and Residue Containment: 412.1 DESCRIPTION BRIDGE FIELD PAINTING, REPAINTING, 412 This specification contains the requirements for the removal, containment, and disposal of existing paint on steel surfaces, preparing the steel

More information

Float and Thermostatic Traps Series H, C and X

Float and Thermostatic Traps Series H, C and X Hoffman Specialty Installation & Maintenance Instructions HS-(E) and Thermostatic Traps Series H, C and X Series C & NPT Series C NPT Series X NPT Series C NPT Series H Ratings Maximum Max. Operating NPT

More information

Embedded Parts Introduction - Anchors

Embedded Parts Introduction - Anchors In the plant construction or process plants such as chemical, petrochemical, gas or power plants various disciplines are brought into contact and built on each other. Civil, mechanical, electro technical

More information

CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION

CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION CONCRETE FLOOR SLAB & CASTING BED CONSTRUCTION General 7 www.meadowburke.com 877-518-7665 MB1109 CONCRETE FLOOR SLAB AND CASTING BED CONSTRUCTION Quality Construction Begins at Ground Level Everything

More information

CHAPTER 6 - SANITARY SEWER

CHAPTER 6 - SANITARY SEWER CHAPTER 6 - SANITARY SEWER 6.1 GENERAL This section covers the requirements for PVC plastic sewer pipe materials and installation in sanitary sewer construction. 6.2 PIPE PVC gravity sewer pipe and fittings

More information

SECTION 15125 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION

SECTION 15125 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION SECTION 15125 HIGH DENSITY POLYETHYLENE (HDPE) PIPE AND FITTINGS FOR WATER DISTRIBUTION AND TRANSMISSION PART 1 GENERAL.01 SECTION INCLUDES Furnishing and installing 4 inch through 16 inch high density

More information

Copper and Copper Alloy Tube, Pipe and Fittings

Copper and Copper Alloy Tube, Pipe and Fittings Copper and Copper Alloy Tube, Pipe and Fittings COPPER and COPPER ALLOY TUBE and PIPE Seamless Copper Pipe: Copper pipe is almost pure copper manufactured to the requirements of ASTM B 42 - Standard Specification

More information

Code of Standard Practice for Timber Frame Structures

Code of Standard Practice for Timber Frame Structures TFEC 2-2013 Code of Standard Practice for Timber Frame Structures August 2013 Preface This Code is intended to represent a reasonable consensus of what constitutes ordinary and acceptable practice within

More information

SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT

SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT SEPTIC SYSTEM CONSTRUCTION REQUIREMENTS ST. MARY S COUNTY HEALTH DEPARTMENT The following are minimum requirements for installation of conventional trench sewage disposal systems in St. Mary s County,

More information

DENVER MODEL 30 X 30 SPECIFICATIONS

DENVER MODEL 30 X 30 SPECIFICATIONS DENVER MODEL 30 X 30 SPECIFICATIONS Dimensions: Roof Dimensions 30-0 x 30-0 (4) Columns (Center to Center) 25-6½ x 25-6½ Minimum Clearance 8-0 Roof Height @ Peak Dependent on Col. Ht. Hip Roof 4:12 pitch

More information

TECHNICAL DATA. 2. LISTINGS AND APPROVALS See Tables 1 & 2.

TECHNICAL DATA. 2. LISTINGS AND APPROVALS See Tables 1 & 2. May 3, 2013 Foam 138a 1. DESCRIPTION Chemguard Water Powered Oscillating Monitors are designed to automatically discharge over a specific design area upon system activation. These are suitable for use

More information

STANDARD REQUIREMENTS FOR BONDING OR MECHANICAL ATTACHMENT OF INSULATION PANELS AND MECHANICAL ATTACHMENT OF ANCHOR AND/OR BASE SHEETS TO SUBSTRATES

STANDARD REQUIREMENTS FOR BONDING OR MECHANICAL ATTACHMENT OF INSULATION PANELS AND MECHANICAL ATTACHMENT OF ANCHOR AND/OR BASE SHEETS TO SUBSTRATES ROOFING APPLICATION STANDARD (RAS) No. 117 STANDARD REQUIREMENTS FOR BONDING OR MECHANICAL ATTACHMENT OF INSULATION PANELS AND MECHANICAL ATTACHMENT OF ANCHOR AND/OR BASE SHEETS TO SUBSTRATES Scope 1.1.

More information

2010 Residential Water Heater Replacement Check List

2010 Residential Water Heater Replacement Check List 2010 Residential Water Heater Replacement Check List The intent of this check list is to provide installers a general reference for the enforcement of code requirements in the Greater San Diego Area. This

More information

Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe

Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe Specification for Pipe Bursting Gravity Sewer Mains with HDPE Pipe 1. GENERAL The following supplemental sewer main specifications are intended to address the installation of high-density polyethylene

More information

60.12. Depend-O-Lok FxE Expansion Coupling. System No. Submitted By Spec Sect Para Location Date Approved Date. DEPEND-O-LOK FxE EXPANSION COUPLING

60.12. Depend-O-Lok FxE Expansion Coupling. System No. Submitted By Spec Sect Para Location Date Approved Date. DEPEND-O-LOK FxE EXPANSION COUPLING 60.1 D-O-L FxE expansion couplings are a bolted, split-sleeve design that provides for expansion and contraction at the coupled joint. These couplings are furnished with restraint rings that, when affixed

More information

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials.

A. Contractor shall furnish, to the Engineer, all materials certifications available from the manufacturer for all required materials. PART 1 GENERAL 1.1 SCOPE A. This item shall include the work necessary for the installation of storm sewer line construction. B. Reference Section 3800 Trenching and Backfill and the General Conditions,

More information

Universal Installation and Maintenance Instructions Double Wall Spill Containment Bucket (5 and 15 gal)

Universal Installation and Maintenance Instructions Double Wall Spill Containment Bucket (5 and 15 gal) Universal Installation and Maintenance Instructions Double Wall Spill Containment Bucket (5 and 15 gal) IMPORTANT: It is imperative that the user read these warnings and use of the assembly instructions

More information

CLEAR-DIVISIONS CENTERFOLD

CLEAR-DIVISIONS CENTERFOLD CLEAR-DIVISIONS CENTERFOLD Introduction: The following three (3) part specification offers the Standard and Optional features for the CLEAR-DIVISIONS CENTERFOLD moveable The yellow highlighted areas in

More information

TECHNICAL DATA 2. LISTINGS AND APPROVALS. Spray Nozzle 11. December 20, 2013

TECHNICAL DATA 2. LISTINGS AND APPROVALS. Spray Nozzle 11. December 20, 2013 Spray Nozzle 11 1. DESCRIPTION Viking Model C-1 Window Sprinklers are non-automatic, open, outside intended for protection of windows, walls, and roofs against exposure fires. The directional discharge

More information

ELECTRIC PERISTALTIC MORTAR POINTING PUMP

ELECTRIC PERISTALTIC MORTAR POINTING PUMP ELECTRIC PERISTALTIC MORTAR POINTING PUMP pointing gun & control valve ACF405 PERISTALTIC PuMP hopper feed roller & tube pump for refurbishment & repair trades heritage & conservation bridge & underground

More information

SECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE

SECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE SECTION 33 11 00.11 POLYVINYL CHLORIDE (PVC) PIPE PART 1: GENERAL 1.01 SECTION INCLUDES PVC pressure pipe and fabricated fittings in nominal sizes 4-inches through 12-inches with cast iron pipe equivalent

More information

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT

ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT ITEM #0702770 OSTERBERG CELL LOAD TESTING OF DRILLED SHAFT Description: This work shall consist of furnishing all materials, equipment and labor necessary for conducting an Osterberg Cell (O-Cell) Load

More information

738-B-297 POLYMERIC CONCRETE BRIDGE DECK OVERLAY. (Adopted 02-20-14)

738-B-297 POLYMERIC CONCRETE BRIDGE DECK OVERLAY. (Adopted 02-20-14) POLYMERIC CONCRETE BRIDGE DECK OVERLAY (Adopted 02-20-14) Description The polymeric concrete bridge deck overlay shall consist of an epoxy polymer that acts together with special aggregate to form an overlay

More information

Select Radiators Installation Guide

Select Radiators Installation Guide Select Radiators Installation Guide Table of Contents Informational Symbols...3 Before You Begin...4 Select Rough-In... 5 Connection Installation...6 Optional Piping Arrangements...7 Conventional Wall

More information

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections

Materials. Estimating Steel. Players. Materials. Shop Drawings. Detailing Process. Standard shapes. Fabricated members, Built-up sections Materials Standard shapes W sections, C channels, Structural T, Angles, Pipes, Tubes, Rods and Plates Fabricated members, Built-up sections Adding plates to beam flanges, Stiffeners to beam webs Built

More information

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION PART 8000 - PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL 8-3 8101 General

More information

SECTION 03400 PRECAST CONCRETE STRUCTURES

SECTION 03400 PRECAST CONCRETE STRUCTURES SECTION 03400 PART 1 - GENERAL 1.01 DESCRIPTION A. Section includes specifications for precast concrete structures, including fabrication and erection. 1.02 REFERENCE STANDARDS A. American Society for

More information

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13)

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 11/5/13) Page 1 of 7 STONE STRONG SYSTEMS SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised ) PART 1: GENERAL 1.01 Description A. Work includes furnishing and installing precast modular blocks

More information

Stormwater/Wetland Pond Construction Inspection Checklist

Stormwater/Wetland Pond Construction Inspection Checklist : Construction Inspection ChecklistsTools Stormwater/Wetland Pond Construction Inspection Checklist Project: Location: Site Status: Date: Time: Inspector: SATISFACTORY/ UNSATISFACTORY COMMENTS Pre-Construction/Materials

More information

SECTION XXXXXX TECHNICAL SPECIFICATIONS FOR INSTALLATION OF PROTECTIVE COATINGS FOR MANHOLES, WETWELLS, AND OTHER SANITARY SEWER STRUCTURES

SECTION XXXXXX TECHNICAL SPECIFICATIONS FOR INSTALLATION OF PROTECTIVE COATINGS FOR MANHOLES, WETWELLS, AND OTHER SANITARY SEWER STRUCTURES 1.00 PART 1 GENERAL 1.01 SCOPE A. It is the intent of this contract to install a 100% solids epoxy monolithic coating to the walls, benches and inverts of all manholes and the specified surfaces of other

More information

UFGS-02362 (August 2004) UNIFIED FACILITIES GUIDE SPECIFICATIONS

UFGS-02362 (August 2004) UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-31 31 16.20 (April 2006) Change 2-11/14 ----------------------------- Preparing Activity: NAVFAC Replacing without change UFGS-02362 (August 2004) UNIFIED FACILITIES

More information

FLASH TANK ECONOMIZER PRODUCT GUIDE

FLASH TANK ECONOMIZER PRODUCT GUIDE FLASH TANK ECONOMIZER PRODUCT GUIDE Overview A flash tank is used to recover blowdown energy in the form of flash steam and blowdown. This can only be used with a deaerator or some other pressurized device.

More information

MS-3/2009 HDPE (High Density Polyethylene) Pipe and Fittings Specification for Buried Potable Water

MS-3/2009 HDPE (High Density Polyethylene) Pipe and Fittings Specification for Buried Potable Water MS-3/2009 HDPE (High Density Polyethylene) Pipe and Fittings Specification for Buried Potable Water 105 Decker Court, Suite 825, Irving, TX 75062 P: 469-499-1044 F: 469-499-1063 www.plasticpipe.org HDPE

More information

COLORADO MODEL. 35 x 65 SPECIFICATIONS

COLORADO MODEL. 35 x 65 SPECIFICATIONS COLORADO MODEL 35 x 65 SPECIFICATIONS Dimensions: Roof Dimensions 35-0 x 65-0 Column Dimensions (center to center) 31-0 x 30-6 Minimum Clearance 14-0 Roof Height @ Peak ±18-8 Curved Roof ±42-6 radius Square

More information

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS

SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS SECTION 36 - CAST-IN-PLACE CONCRETE PIPE (CIPCP) TABLE OF CONTENTS Section Page 36-1 GENERAL... 36.1 36-2 PIPEMAKING EQUIPMENT... 36.1 36-3 TRENCH EXCAVATION... 36.1 36-4 SPECIAL FOUNDATION TREATMENT...

More information

SECTION 10 WATER WELL SUPPLY 10.01 SCOPE OF WORK

SECTION 10 WATER WELL SUPPLY 10.01 SCOPE OF WORK 10.01 SCOPE OF WORK The work covered by this section of the specifications consists in furnishing all labor, equipment and material necessary to perform the installation of a Type I water supply well per

More information

CONTRACT SPECIFICATIONS - SEISMIC ISOLATION BEARINGS

CONTRACT SPECIFICATIONS - SEISMIC ISOLATION BEARINGS CONTRACT SPECIFICATIONS - SEISMIC ISOLATION BEARINGS 1.0 DESIGN 1.1 Scope of Work 1.1.1 This work shall consist of furnishing Isolation Bearings and installing Isolation Bearing Assemblies at the locations

More information

NRDCA 400 GUIDELINE FOR FIELD APPLICATION of LIGHTWEIGHT INSULATING CONCRETE REROOFING/RECOVER SYSTEMS

NRDCA 400 GUIDELINE FOR FIELD APPLICATION of LIGHTWEIGHT INSULATING CONCRETE REROOFING/RECOVER SYSTEMS NRDCA 400 GUIDELINE FOR FIELD APPLICATION of LIGHTWEIGHT INSULATING CONCRETE REROOFING/RECOVER SYSTEMS The (NRDCA) has prepared this document to provide customers and installers information that the industry

More information