IBC Chapter 7. Based on the 8 th & 9 th Editions of 780 CMR: 2009 & 2015 IBC with MA Amendments For Boston Society of Architects May 18, 2016
|
|
- Madeline Pamela Anderson
- 7 years ago
- Views:
Transcription
1 IBC Chapter 7 Based on the 8 th & 9 th Editions of 780 CMR: 2009 & 2015 IBC with MA Amendments For Boston Society of Architects May 18, 2016 Presented by Doug Anderson 313 Congress Street Boston, MA fax Best Practice Commercial Construction Consulting is a Registered Provider with The American Institute of Architects Continuing Education Systems. Credit earned on completion of this program will be reported to CES Records for AIA members. Certificates of Completion for non-aia members are available upon request. This program is registered with the AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product. Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation. 1
2 Learning Objectives Learn the topics covered in Chapter 7 of the Massachusetts Building Code Understand exterior wall requirements, interior wall types, when to use them, and how they are constructed Requirements for smoke and/or fire dampers, opening protectives, and smoke and draft control doors Archaic Construction Illustrations from the 2009 IBC Commentary unless otherwise noted Chapter 7: Fire and Smoke Protection Features Primary and Secondary Frame members Exterior Walls Interior Walls Horizontal Assemblies Penetrations Fire-resistant Joint Systems Opening Protectives Duct and Air Transfer Openings Concealed Spaces Plaster Thermal and Sound Insulating Materials Prescriptive Fire Resistance Calculated Fire Resistance 2
3 Primary and Secondary Frame Members Primary Structural Frame Columns Beams and Girders connected to columns Floor and Roof construction connected to columns Bracing elements critical to vertical support Individual encasement required on all sides Secondary Structural Members Beams and girders not directly connected to the columns Floor construction not connected directly to columns Other bracing members Individual encasement on all sides, or within a membrane assembly Exterior Walls Fireresistance Rating Higher of Construction Type or Fire Separation Distance FSD 10 ft or less, rated from both sides FSD more than 10 ft, inside only Openings Limited by Fire Separation Distance 3
4 Interior Walls Wall Types: Fire Walls/ Party Walls Fire Barriers Shaft Enclosures Fire Partitions Fire Partitions (Corridors) Smoke Barriers Smoke Partitions Horizontal Assemblies None of the Above Horizontal Assemblies Floor/Ceiling and Roof/Ceiling Assemblies Slab Membrane 4
5 Penetrations Walls Floor/Ceiling Assemblies Fire-resistant Joint Systems 5
6 Opening Protectives Fire Doors 2 Hr Fire Wall or Fire Barrier: 90 Minute 1 Hr Fire Barrier, shafts: 60 minute 1 Hr Fire Barrier, others (Use Group Separation): 45 minute 1 Hr or 30 minutes Fire Partitions, Corridors: 20 minute 1 Hr Fire Partitions, Others: 45 minute 1 Hr Smoke Barriers: 20 minute 3 Hr Fire Wall: 2@ 90 minute or 1@ 3 hr Smoke and Draft Control Corridors and Smoke Barriers Duct and Air Transfer Openings Fire Walls/ Party Walls: Fire Damper Fire Barriers: Fire Damper Horizontal Exits: Fire/Smoke Shafts: Fire/Smoke Subduct Exceptions Fire Partitions: Fire or Smoke Fire not required if fully sprinklered and duct is protected as a penetration Smoke not required for separate common/dwelling systems, or for smoke control systems Smoke Barriers, Smoke Partitions: Smoke Damper Horizontal Assemblies: Fire Damper (2 or 3 stories), or shaft 6
7 Concealed Spaces Required for Combustible Construction Only Fire Blocking Draftstopping Thermal and Sound Insulating Materials Fibreboard: Chapter 23 Foam Plastic: Chapter 26 Concealed Flame Spread 25, Smoke Develop 450 Exception: In Types III, IV and V, covered backings when in substantial contact with wall or ceiling surface Exposed Flame Spread 25, Smoke Develop 450 Intumescent coatings 7
8 Prescriptive Fire Resistance Tables in 721 Archaic Construction From Principles of Tile Engineering, H.C. Plummer& E.F. Wanner, 1947 Calculated Fire Resistance 8
9 Putting It All Together General Guidelines Fire resistance rated walls must be tested in accordance with ASTM E 119 or UL 263. Testing requirements found in 780 CMR 703 If you put an opening, door, or penetrate a FRR wall, it also needs to meet certain requirements. 9
10 780 CMR 7.00: Supplemental Information Wall Types: Fire Walls/ Party Walls Fire Barriers Shaft Enclosures Fire Partitions Fire Partitions (Corridors) Smoke Barriers Smoke Partitions Horizontal Assemblies None of the Above Fire Wall Fire-resistance rated Protected openings Continuous from foundation to roof, Allows for structural collapse on either side without collapse of the fire wall Protected openings permitted EX: used to separate two buildings Party Walls A type of fire wall that separates two buildings on a party line No penetrations or openings allowed 10
11 Fire Barriers Fire resistance rated Extends slab to slab Protected openings Limited penetrations of membrane Vertical or horizontal (if horizontal, refer to horizontal assemblies) Locations: area of refuge separation, separate occupancies in a mixed use building (if required), exit enclosures, exit passageways, atrium separation Example of Continuity: Fire Barrier From top of floor/ceiling assembly to underside of deck above: 11
12 Shaft Enclosures Enclosed space extends through one or more stories connecting vertical openings Constructed as fire barriers EX: interior stairways, elevator hoistways, mechanical shafts Fire Partitions (incl Corridors) Fire-resistance rated Extends slab to slab or slab to underside of floor/ceiling membrane EX: Typically used for elevator lobby separation, tenant spaces in a covered mall, dwelling units and guestrooms Fire Partitions (Corridors) Fire-resistance rated in accordance with Not interrupted by intervening rooms Extends slab to slab or slab to underside of floor/ceiling membrane EX: Enclose an exit access corridor 12
13 Example of Continuity: Fire Partition From top of floor/ ceiling assembly to underside of floor assembly above: Smoke Barrier 1 hr fire-resistance rated Extends wall to wall and slab to slab EX: Usually used in Group I-2 and I-3 to evacuate occupants horizontally to another smoke compartment. Can be used in a smoke control system or part of an accessible means of egress system Firefighter lobby in new high rise buildings >120 feet (>70 feet in MA) 13
14 Smoke Partitions No fire-resistance rating Resistant to the passage of smoke Slab to slab Specific opening sealing requirements (710.5). EX: Corridor walls in a Group I-2 (Hospital, nursing home, mental hospital, detox facility) In lieu of a fire partition for elevator lobby Horizontal Assemblies Floor and roof assemblies Continuous without openings, penetrations or joints except as permitted May or may not have a FRR May also be required to be constructed as a smoke barrier 14
15 Example of Continuity: Horizontal Assembly From top of floor/ceiling assembly to underside of deck above: Construction Type Type I rated construction, limited combustibles allowed in building Type II may be unrated (Type IIB) or rated construction (Type IIA), limited combustibles allowed in building Type III typical masonry construction with rated exterior walls, rated (IIIA) or non rated floors (IIIB), combustible construction allowed in building Type IV heavy timber Type V everything s unrated (Type VB) or everything s 1 hr rated (Type VA), combustible construction allowed in building 15
16 Construction Type Req s Exterior walls Height and Area Limits Single and Mixed Use buildings Mixed Use: provide separation in order to create larger building (use table on following page) Single Use: FRR construction could be used to create a larger building (can be considered buildings on the same lot per 780 CMR 501.2) Exterior walls don t necessarily have to be FRR walls 16
17 Use Group Separation Accessory Rooms 17
18 Dwelling Unit/ Sleeping Rooms Fire partitions for vertical walls Fire rated horizontal assemblies In Types IIB, IIIB and VB, 30 minute Other types, 1 hr Corridors Rated vs. Not Rated 18
19 Corridors as egress components Can provide a 1 hour FRR corridor connecting the exit enclosures to measure travel distance in lieu of exit separation requirements ½ D for nonsprinklered buildings and 1/3 D for sprinklered buildings Exits Exit Passageways walls are fire barriers Stairways shaft walls are fire barriers 19
20 Marking and Identification Fire walls, fire barriers, fire partitions, smoke barriers and smoke partitions must be identified with signs or stenciling (Sec 703.6) Located at accessible floor, floor/ceiling or attic spaces; Repeated every 30 feet; and Min ½ lettering. Example: Smoke barrier, protect all openings Thank you for your time! Questions? This concludes The American Institute of Architects Continuing Education Systems Program Doug Anderson 313 Congress Street Boston, MA fax 20
21 C 3 Services: MEP / FP Engineering Due Diligence Construction Management Owner s Representatives Development Advisory Code Advisory Building Envelope 313 Congress Street Boston, MA fax 21
FIRE-RESISTANCE-RATED CONSTRUCTION
CHAPTER 7 FIRE-RESISTANCE-RATED CONSTRUCTION SECTION 70 GENERAL 70. Scope. The provisions of this chapter shall govern the materials and assemblies used for structural fire resistance and fire-resistance-rated
More informationFIRE-RESISTANCE-RATED CONSTRUCTION
CHAPTER 7 FIRE-RESISTANCE-RATED CONSTRUCTION SECTION 70 GENERAL 70. Scope. The provisions of this chapter shall govern the materials and assemblies used for structural fire resistance and fire-resistance-rated
More informationDesign Options (Tradeoffs) Allowed by the 2012 Building Codes for Properties with Sprinkler Systems. April 2013
Design Options (Tradeoffs) Allowed by the 2012 Building Codes for Properties with Sprinkler Systems April 2013 The National Multi Housing Council and the National Apartment Association (NMHC/NAA) have
More informationFIRE AND SMOKE PROTECTION FEATURES
CHAPTER 7 FIRE AND SMOKE PROTECTION FEATURES SECTION 70 GENERAL 70. Scope. The provisions of this chapter shall govern the materials, systems and assemblies used for structural fire resistance and fire-resistance-rated
More informationHCD DSA OSHPD 1 2 1/AC AC SS SS/CC 1 2 3 4 2013 CALIFORNIA BUILDING CODE 199
CALIFORNIA BUILDING CODE MATRIX ADOPTION TABLE CHAPTER 7 FIRE AND SMOKE PROTECTION FEATURES (Matrix Adoption Tables are non-regulatory, intended only as an aid to the user. See Chapter for state agency
More informationBuilding Codes Update: The 2009 International Fire Code and the Apartment Industry
! Building Codes Update: The 2009 International Fire Code and the Apartment Industry Apartment operators and developers should be aware of organizational changes in the 2009 edition of the International
More informationFIRE AND SMOKE PROTECTION FEATURES
CHAPTER 7 FIRE AND SMOKE PROTECTION FEATURES SECTION 70 GENERAL 70. Scope. The provisions of this chapter shall govern the materials, systems and assemblies used for structural fire resistance and fire-resistance-rated
More informationFire Barriers & Fire Stopping
Presented by: Bill Lauzon, PE Lauzon Life Safety Consulting, LLC 262-945-4567 Lauzon.lsc@gmail.com Web: Lauzon-LSC.com Environmental Part 2 Life Safety Code Chapter 8 Fire Barriers & Fire Stopping 1 Fire
More informationPage 4 of 17. Committee Input NFPA 101 Coordinate Smoke detector versus smoke alarm terminology.
Page 1 of 17 Page 2 of 17 Committee Input NFPA 101 Coordinate Smoke detector versus smoke alarm terminology. CODE PARAGRAPH WITH SUGGESTED CHANGES: 6.4.6.1.2 Residents should be rated as response probable
More informationExcerpts from the Canadian National Building Code (NBC)
Excerpts from the Canadian National Building Code (NBC) Reproduced here with Permission of the Copyright Owner, the National Research Council of Canada, Institute for Research in Construction. For more
More informationCertification: Building Plans Examiner. Exam ID: B3
Certification: Building Plans Examiner Exam ID: B3 Scope: A Building Plans Examiner will be responsible for reviewing submitted plans to determine if they meet the requirements of the various Building
More informationHealthcare Engineering. Code Summary Report
American Society for Healthcare Engineering Code Summary Report CODE SUMMARY HEALTH CARE NEW BUILDINGS This code summary is based on the following codes: 2000 Edition NFPA 101, The Life Safety Code (LSC),
More informationCode Requirements for Existing Buildings
Code Requirements for Existing Buildings Kevin S. Hastings, P.E., LEED AP R. W. Sullivan, Inc. 529 Main St., Suite 203 Charlestown, MA (617) 523-8227 www.rwsullivan.com R.W. Sullivan Engineering (RWS)
More information2006 IBC BUILDING CODE CHECKLIST FOR COMMERCIAL PROJECTS
2006 IBC BUILDING CODE CHECKLIST FOR COMMERCIAL PROJECTS IBC CODE DESIGN CHECKLIST (EXCEPT 1 AND 2-FAMILY DWELLINGS AND TOWNHOUSES) (Transfer the resulting data on the building plans Life Safety & Building
More informationNC Rehab Code Case Study Cheerwine Building January 17, 2002; rev 4/12/02
NC Rehab Code Case Study Cheerwine Building January 17, 2002; rev 4/12/02 PART A: Project Data and Classification 1. Project name & location Renovation of the Cheerwine Building, 322 East Council St.,
More informationA ROAD MAP FOR YOUR CODE, SMOKE BARRIER & SMOKE PARTITION REQUIREMENTS
A ROAD MAP FOR YOUR CODE, SMOKE BARRIER & SMOKE PARTITION REQUIREMENTS International Code Council National Fire Protection Association Underwriters Laboratories Inc. 5203 Leesburg Pike, Suite 600 1 Batterymarch
More informationCh. 58 DIVISION D-O 34 CHAPTER 58. DIVISION D-O ORDINARY COMMERCIAL, INDUSTRIAL, OFFICE OCCUPANCY GROUP CONSTRUCTION TYPE MAXIMUM STORY HEIGHT
Ch. 58 DIVISION D-O 34 CHAPTER 58. DIVISION D-O ORDINARY COMMERCIAL, INDUSTRIAL, OFFICE Sec. 58.1. Division D-O occupancies. 58.2. Separation and mixed occupancy. OCCUPANCY GROUP CONSTRUCTION TYPE MAXIMUM
More informationPROJECT SUMMARY. Scope of work details: (If phased construction, please see plan submittal guidelines.)
APPENDIX B BUILDING CODE SUMMARY FOR ALL COMMERCIAL FIRE RESTORATION PROJECTS (EXCEPT 1 AND 2-FAMILY DWELLINGS AND TOWNHOUSES) (Reproduce the following data on the building plans sheet 1 or 2) Name of
More informationRequirements for Fire Protection of Light Weight Floor Systems **Act 1 Revisited**
PHRC Webinar Series Tuesday, September 9, 2014 1:00 pm Requirements for Fire Protection of Light Weight Floor Systems **Act 1 Revisited** Presented by: Bryan Heitzmann Credit(s) earned on completion of
More informationNew York City Department of Buildings
The New NYC Building Code Chapter 10 Means of Egress New York City Department of Buildings Technical Affairs Fatma M. Amer, P.E. Copyright Materials This presentation is protected by US and International
More informationFire Alarm Systems Requirements by Occupancy Type
WALT WHITE Fire Chief 5770 Freeport Blvd., Suite 200 Sacramento, CA 95822-3516 Ph: (916) 808-1300 Fax: (916) 808-1629 www.sacfire.org Fire Alarm Systems Requirements by Occupancy Type 2013 California Building
More informationM E M O R A N D U M. To: Partnership for Safer Buildings Date: 21 March 2003
M E M O R A N D U M To: Partnership for Safer Buildings Date: 21 March 2003 From: Codes Assessment Subcommittee Walter Smittle III, Chairman Re: Building Code Fire Safety Concerns: NFPA 5000, Building
More informationNew Ontario Building Code Requirements for Mid-rise Wood Frame Buildings
New Ontario Building Code Requirements for Mid-rise Wood Frame Buildings Note: This information addresses complex issues in a summary fashion. Consideration should be given to the official version of the
More informationREVEWED BY: Ross Rogien B.O/P.R. ADDITIONAL REVIEW(S) REQ.-FIRE DEPT Y/N
PLAN REVIEW FOR: PROJECT NAME: OWNER: ARCH/DESIGNER: ADDRESS: Ph/Fx: Plans Dated: E-mail: Sealed By: Estimated Project Cost - $ REVEWED BY: Ross Rogien B.O/P.R. ADDITIONAL REVIEW(S) REQ.-FIRE DEPT Y/N
More informationErrata has been identified as follows:
2009 IFC Performing Commercial Fire Inspections Inventory Number: 1424S09 Second Printing; July 2014 Changes HAVE been made- Third Printing: September 2014 Errata has been identified as follows: 1. Page
More informationLIFE SAFETY UPDATE. FULL SPRINKLERING OF ALL NURSING FACILITIES ADDITIONAL CLARIFICATIONS Prepared by Eric Rosenbaum, P.E. Hughes Associates, Inc.
LIFE SAFETY UPDATE FULL SPRINKLERING OF ALL NURSING FACILITIES ADDITIONAL CLARIFICATIONS Prepared by Eric Rosenbaum, P.E. Hughes Associates, Inc. The purpose of this update is as follows: Remind all state
More informationCHAPTER 6 CONSTRUCTION TYPES
CHAPTER 6 CONSTRUCTION TYPES SECTION 601 GENERAL 601.1 Scope. Provisions of this chapter shall govern the classification of construction type by materials and fire resistance of its elements and the use
More information- 5 - Table1. Maximum Compartment Volumes
- 5 - Part II - SPECIFIC REQUIREMENTS 5. Compartmentation 5.1 Every building should be divided into compartments by walls and floors to inhibit the spread of fire. 5.2 Compartment walls, compartment floors,
More information2010 FLORIDA BUILDNG CODE, FIRE AND LIFE SAFETY i
2010 FLORIDA BUILDNG CODE, FIRE AND LIFE SAFETY i Changes between the 2006 and 2009 Editions of the International Codes account for the vast majority of changes to the 2010 Florida Building Code. In many
More informationBuilding Code Clarifications - 7. Fire Resistance
Building Code Clarifications - 7. Fire Resistance 7.1 (15-12-030) Use of combustibles in Type III construction roof assemblies Code Section (15-12-030) Use of Combustibles was revised on May 17, 2000,
More informationSPECIAL RESIDENCE (ASSISTED SELF-PRESERVATION) OCCUPANCIES (Adopted by the State of Oregon)
SPECIAL RESIDENCE (ASSISTED SELF-PRESERVATION) OCCUPANCIES (Adopted by the State of Oregon) SECTION SR101 GENERAL SR101.1 General. Group SR occupancies shall comply with the provisions of this appendix
More informationFIRE PROTECTION IN THE 2008 NEW YORK CITY BUILDING CODE
FIRE PROTECTION IN THE 2008 NEW YORK CITY BUILDING CODE New York Society of Architects 24 January 2008 Presented by Joseph Razza, PE Rolf Jensen & Associates, Inc. John Lee, RA NYC Department of Buildings
More informationDesigning for Fire Protection
Architect: CUBE 3 Studio. Structural engineer: Veitas & Veitas Engineers. Photo: CUBE 3 Studio & Rixon Photography. Vox on Two in Cambridge, Massachusetts, includes four stories of wood-frame construction
More informationHOOVER TREATED WOOD PRODUCTS, INC. TECHNICAL NOTE FOR ADDITIONAL INFORMATION: 1-800-TEC-WOOD (832-9663)
HOOVER TREATED WOOD PRODUCTS, INC. TECHNICAL NOTE FOR ADDITIONAL INFORMATION: 1-800-TEC-WOOD (832-9663) Fire-Retardant-Treated Wood Framed Wall Assemblies GENERAL INFORMATION Fire-resistant construction
More informationDUCT SYSTEMS CHAPTER 6
CHAPTER 6 DUCT SYSTEMS SECTION 601 GENERAL 601.1 Scope. Duct systems used for the movement of air in air-conditioning, heating, ventilating and exhaust systems shall conform to the provisions of this chapter
More informationFire-Rated Glass and Glazing START
Fire-Rated Glass and Glazing START www.pilkington.com/fire Fire-Rated Glass and Glazing Pilkington Fire Protection Glass North America 946 Kane Street, Suite A Toledo, OH 43612 Provider Number: J200 Course
More informationWe hope these Frequently Asked Questions will be of use both to municipal officials and fire inspectors.
September 14, 2012 Dear AMM Member: Please see the attached Fire Code Frequently Asked Questions. This document was compiled by the Office of the Fire Commissioner at the AMM s request to help clarify
More information2012 IBC & 2012 NFPA 101 Significant Means of Egress Changes. Questions. 1004.1 Design Occupant Load. 1005 - Means of Egress Capacity Determination
2012 IBC & 2012 NFPA 101 Significant Means of Egress Changes Clay Aler, P.E. Principal caler@koffel.com Andrew M. Schneider, P.E. Senior Fire Protection Engineer aschneider@koffel.com Questions Submit
More informationLearn how all this can be achieved. architecture AND save money. exceptional. with the SALT LAKE CITY, UT PERMIT # US POSTAGE PAID FIRST CLASS
The ONLY horizontal sliding fire-door with these unique features: Spans unlimited widths, heights up to 23 feet Meets fire codes without being seen Approved for egress applications Automatic closing and
More informationFire-Retardant-Treated (FRT) Plywood
T e c h n i c a l n o t e Fire-Retardant-Treated (FRT) Plywood Number K320 January 2009 Introduction Codes assure fire safety by controlling such things as size and design of the structure and flame-spread
More informationOverview of Hotel Fire Safety Requirements
Overview of Hotel Fire Safety Requirements in the Fire Code Susan Clarke, P.Eng. Office of the Fire Marshal - January 10, 2012 1 Agenda Regulation History - Hotels Fire Code Overview (Parts 1 to 8) Defined
More informationWood use in Type I and II (noncombustible) construction
Wood use in Type I and II (noncombustible) construction D.G. Bueche Hoover Treated Wood Products, Thomson, Georgia, USA ABSTRACT: As with many products, the building code regulates the use of wood in construction.
More informationMassachusetts State Building Code 8 th Edition
Massachusetts State Building Code 8 th Edition A. Vernon Woodworth, AIA, LEED AP Kevin S. Hastings, P.E., LEED AP R. W. Sullivan, Inc. 529 Main St., Suite 203 Charlestown, MA (617) 523-8227 www.rwsullivan.com
More informationHealth Care Facilities
Health Care Facilities CHAPTER 25 Joseph M. Jardin A large Illinois hospital undergoing a sprinkler retrofit quickly discovered the benefits of upgrading its system when sprinklers confined a fire caused
More informationGeneral Safety & Health Standards Published by the Division of Building Safety In Cooperation with the Idaho Industrial Commission
General Safety & Health Standards Published by the Division of Building Safety In Cooperation with the Idaho Industrial Commission Local Fire Alarm 064. FIRE ALARM SYSTEMS 01. Scope 02. Definitions 03.
More informationCHAPTER 6 DUCT SYSTEMS
CHAPTER 6 DUCT SYSTEMS SECTION MC 601 GENERAL 601.1 Scope. Duct systems used for the movement of air in air-conditioning, heating, ventilating and exhaust systems shall conform to the provisions of this
More informationThe American Institute of Architects Continuing Education Systems (AIA/CES) AIA/CES AIA/CES
AIA Austin is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES). Credit(s) earned on completion of this program will be reported to AIA/CES for AIA
More informationFIRE-RESISTANCE RATINGS WITH STEEL JOISTS
FIRE-RESISTANCE RATINGS WITH STEEL JOISTS The Underwriters Laboratories (U.L.) Fire Resistance Directory lists hundreds of assemblies their fire resistance ratings. The Specifying Professional can choose
More informationDollars & Sense of Compliance!
CRCA s 29 th Annual Trade Show Oakbrook k Terrace, IL January 19 20, 2012 Dollars & Sense of Compliance! Mark S. Graham Associate ExecutiveDirector Director, Technical Services National Roofing Contractors
More informationFIRE ALARM PLAN REVIEW. Office of the State Fire Marshal Massachusetts Department of Fire Services December 2009
FIRE ALARM PLAN REVIEW Office of the State Fire Marshal Massachusetts December 2009 SURPRISE QUIZ 1. A fire alarm system is required to be installed by the MSBC, what edition of NFPA 72 do you use? 2.
More informationVestibule Case Study. Vestibule Requirement Intent [2003 IECC, 2006 IECC, 2003 IBC, 2006 IBC, 90.1-2001, 90.1-2004]
Vestibule Case Study [2003 IECC, 2006 IECC, 2003 IBC, 2006 IBC, 90.1-2001, 90.1-2004] Vestibule Requirement Intent Page 1 of 14 The primary intent behind the requirement for a vestibule is to reduce infiltration
More informationGENERAL FIRE SAFETY TERMS & DEFINITIONS
UCL Fire Technical Note - TN006 Fire Safety Technical Guide GENERAL FIRE SAFETY TERMS & DEFINITIONS Reference: BS4422-2005 Fire Safety Vocabulary - for further information and definitions BS EN ISO 13943-2000:
More informationGwinnett County - Building Plan Review Building Code Compliance Review Checklist
Gwinnett County - Building Plan Review Building Code Compliance Review Checklist Project Name Project Address Type of Permit Project Description E-Plan Review No. Construction Area SF Parcel No. Site Permit
More informationHow To Make A House Safe
1 RESIDENTIAL Screen Enclosures Orange County Residential Code Compliance Alternative design method for screen enclosures R301.2.1.1.3 PLAN REVIEW Engineered plans must state that the Alternative Design
More informationThis handout is a guide only and does not contain all of the requirements of the Minnesota State Building Code or city ordinances.
Basement Finishing Guide Community Development Department Building Inspections Division 5200 85 th Avenue North / Brooklyn Park, MN 55443 Phone: (763) 488-6379 / Fax: (763) 493-8171 6/15 www.brooklynpark.org
More informationDecree of the Ministry of the Environment on fire safety of ventilation systems
THE NATIONAL BUILDING CODE OF FINLAND MINISTRY OF THE ENVIRONMENT Housing and Building Department Decree of the Ministry of the Environment on fire safety of ventilation systems Adopted in Helsinki, 18
More informationIndiana Building Rehabilitation Standard
Rule 8. Indiana Building Rehabilitation Standard 675 IAC 12-8-1 Definitions Sec. 1. The following definitions apply throughout this rule: (1) "Building code" means the Indiana Building Code under 675 IAC
More informationEducational. Educational-Existing 1/28/2014. OCCUPANT LOADS [no change] Application. Application
February 2014 Code Requirements and Inspections in Educational Occupancies Presented By: Barry W. Rickert Douglas M. Schanne Fire Marshal Training Program Supervisor Office of Education & Data Management
More informationCHILD CARE CENTER INFORMATION SHEET
CHILD CARE CENTER INFORMATION SHEET SECTION 1 INTRODUCTION This fire safety information sheet is based on the 2007 Minnesota State Fire Code (MSFC) and the 2007 Minnesota State Building Code (MSBC). It
More informationFlorida Advanced Building Code Course# FLBC11
Florida Advanced Building Code Course# FLBC11 EZpdh.com All Rights Reserved CHAPTER 1 Administration: Significant Changes Chapter 1 is now split into two parts: Part 1 is Scope and Application, Part 2
More informationRequired Certification Documentation. Contractor's installation certification for range hood fire suppression systems.
OFFICE OF UNIVERSIT BUILDING OFFICIAL PROJECT/CONSTRUCTION MAGER: Sample Manager Required Aboveground only Required Certification Documentation Contractor s material and test certifications for both above
More informationNew York City Department of Buildings
The New NYC Building Code Chapter 11 Accessibility New York City Department of Buildings Technical Affairs Keith Wen, R.A. Copyright Materials This presentation is protected by US and International Copyright
More informationSOUTHERN NEVADA AMENDMENTS TO THE 2012 INTERNATIONAL BUILDING CODE
SOUTHERN NEVADA AMENDMENTS TO THE 2012 INTERNATIONAL BUILDING CODE PREFACE This document was developed by the Southern Nevada Building Officials International Building Code Committee and presents recommended
More informationKnow the Code: Using Spray Foam Insulation In Attics and Crawl Spaces
center for the polyurethanes industry October 2009 Know the Code: Using Spray Foam Insulation In Attics and Crawl Spaces One of the largest growing uses of spray polyurethane foam (SPF) insulation is in
More informationCleveland Clinic Drawing Standards. Version 2.2
Cleveland Clinic Drawing Standards Version 2.2 SECTION 1 LIFE SAFETY DRAWINGS 1.1 Layers Layers are required on all drawings to categorize components that create a drawing. Layers are to be strictly followed
More informationThe Accord on Fire and Building Safety in Bangladesh Building Standard
The Accord on Fire and Building Safety in Bangladesh Building Standard December 30, 2013 TABLE OF CONTENTS 1 Part 1 Scope and Definitions... 1 2 Part 2 Administration and Enforcement... 5 3 Part 3 General
More informationBUILDING PERMIT SPECIFICATIONS
BUILDING PERMIT SPECIFICATIONS The below noted requirements are based upon La Plata County Building Code. These specifications are not intended as a complete set of requirements, but are intended to provide
More informationDesign Development Quality Management Phase Checklist Project Phase Checklist Series
Best Practices Design Checklist Project Phase Checklist Series Contributed by Micheal J. Lough, AIA, Principal, Integral Consulting The AIA collects and disseminates Best Practices as a service to AIA
More informationCommercial Building Valuation Report
INSURED University of Houston - Victoria Effective Date: Expiration Date: Cost as of: 09/2010 BUILDING 1 217 - University Center 77901 Location Adjustments Climatic Region: High Wind Region: Seismic Zone:
More informationPreparation for 2015 Residential Code Changes Discussion with Local Builders and Designers
City of Duluth Preparation for 2015 Residential Code Changes Discussion with Local Builders and Designers Thank you for taking the time to join us today. We know you are busy and your time is valuable.
More informationCITY PLAN REVIEW AND INSPECTION. Lisa Fleming Brown, CPM
CITY PLAN REVIEW AND INSPECTION Lisa Fleming Brown, CPM Houston Commercial Energy Conservation Code (2011) A choice of 2009 IECC or ASHRAE 90.1-2007 with amendments. Effective September 2, 2011. Complete
More informationFIRE RATED WIRING. What the FT4! Paul Latreille, C.E.T. Ottawa Branch Manager
FIRE RATED WIRING What the FT4! Paul Latreille, C.E.T. Ottawa Branch Manager INTRODUCTION OBC requirements for emergency power OBC requirements for emergency power for fire alarm systems and other building
More informationThe 60 minute Fire Rated Application Explained
The 60 minute Fire Rated Application Explained One of the most confusing aspects of the code is the 60 minute fire rated application, and its easy to see why based on the questions that come up: Is 60
More informationcontents 1. Introduction 7. Types of Construction IBC - Chapter 6 NFPA 101 - Section 8.2 2. Analysis & Recommendations
Table of Contents contents 1. Introduction 2. Analysis & Recommendations 3. Definitions IBC - Chapter 2 NFPA 101 - Chapter 3 4. Occupancy Classification IBC - Chapter 3 NFPA 101 - Chapter 6 5. Special
More informationTremco Fire Protection Systems Group Technical Bulletin
Compartmentalization products and design play a key role in protecting lives and property from fire. Understanding the tools and techniques available for firestopping is of utmost importance to designers,
More informationIFE Level 4 Certificate in Fire Science and Fire Safety (HL)
IFE Level 4 Certificate in Fire Science and Fire Safety (HL) Unit 2: Fire Safety Unit Reference Number: D/505/5932 Introduction This unit focuses on the prevention and detection of fire in premises and
More informationStandards Revisions Related to the Centers for Medicare & Medicaid Services CoPs
Standards Revisions Related to the Centers for Medicare & Medicaid Services CoPs EC.003.01 The hospital manages fire risks. 9. 10. Elements of Performance for EC.003.01 The hospital minimizes the potential
More information2011 Energy Efficiency Expo!
Welcome to the 2011 Energy Efficiency Expo! Thank you to our session sponsors! Comparison Between the 2009 and 2012 International Energy Conservation Code What s coming when the new commercial energy code
More information17,280 square feet Overview:
CENTRAL OFFICE Located at 167 Boston Post Road, East Lyme, Connecticut, the Central Office was built in 1916 as the original Flanders Elementary School and remains connected to the current school. The
More informationRequirements for Hydrogen Storage and Use
Requirements for Hydrogen Storage and Use I. INTRODUCTION Fire and Life-Safety Group (FLS) The following is a summary of the fire and building code requirements for the storage and use of hydrogen. These
More informationCITY OF FAIRFAX CODE ADMINISTRATION 703-385-7830 / FAX 703-385-9265 www.fairfaxva.gov
CITY OF FAIRFAX CODE ADMINISTRATION 703-385-7830 / FAX 703-385-9265 www.fairfaxva.gov Finishing a basement to make additional living space in a house is a popular construction project for many homeowners.
More informationSUBCHAPTER 5 FIRE PROTECTION CONSTRUCTION REQUIREMENTS
SUBCHAPTER 5 FIRE PROTECTION CONSTRUCTION REQUIREMENTS TABLE OF CONTENTS [Sub-Art. Or Sec.]* Art. or Sec.** [500.0] Art.1 General [500.1] 318 Scope [500.2] 319 Standards [500.3] 320 Definitions [500.4]
More informationMINNESOTA STATE DEPARTMENT OF PUBLIC SAFETY
MINNESOTA STATE DEPARTMENT OF PUBLIC SAFETY State Fire Marshal Division 444 Cedar Street, Suite 145, St. Paul, Minnesota 55101-5145 Phone: 651/201-7200 FAX: 651/215-0525 TTY: 651/282/6555 Internet: http://www.fire.state.mn.us
More informationPLAN REVIEW SERVICES CONSTRUCTION DOCUMENTS NECESSARY FOR A THOROUGH PLAN REVIEW
CONSTRUCTION DOCUMENTS NECESSARY FOR A THOROUGH PLAN REVIEW PRELIMINARY BUILDING REVIEW two sets of the following: Architectural/engineering design development drawings indicating size of the building,
More information24.301.161 INCORPORATION BY REFERENCE OF INTERNATIONAL. (1) The Department of Labor and Industry adopts and incorporates by
24.301.161 INCORPORATION BY REFERENCE OF INTERNATIONAL ENERGY CONSERVATION CODE (1) The Department of Labor and Industry adopts and incorporates by reference the International Code Council's International
More information2012 CODES SIGNIFICANT CHANGES 2012 IBC
2012 CODES SIGNIFICANT CHANGES 2012 IBC 1. Section 303.4 added language that includes commercial kitchens which are associated with restaurants, cafeterias, and similar dining facilities to be classified
More information2007 ICC FINAL ACTION AGENDA
907.2.1.1 System initiation in Group A occupancies with an occupant load of 1,000 or more. Activation of the fire alarm in Group A occupancies with an occupant load of 1,000 or more shall initiate a signal
More informationSWAN POINT YACHT & COUNTRY CLUB
SWAN POINT YACHT & COUNTRY CLUB PROJECT INFORMATION: SCOPE OF WORK: INTERIOR ALTERATIONS ABBREVIATIONS: VICINITY MAP 33 East Charles Street PO Box 598 30-934-8078 PROPERTY MANAGER: DOTTIE HARPER BROOKFIELD
More informationMINNESOTA HEALTH CARE ENGINEERS IN ASSISTED LIVING FACILITIES
MINNESOTA HEALTH CARE ENGINEERS FIRE/LIFE SAFETY IN ASSISTED LIVING FACILITIES September 13, 2012 MINNESOTA HEALTH CARE ENGINEERS FIRE/LIFE SAFETY IN ASSISTED LIVING FACILITIES WELCOME Exits Restrooms
More informationREVIEW ON FIRE REGULATIONS FOR NEW HIGH-RISE COMMERCIAL BUILDINGS IN HONG KONG AND A BRIEF COMPARISON WITH THOSE IN OVERSEAS
, Volume 3, Number 1, p.25-51, 2001 REVIEW ON FIRE REGULATIONS FOR NEW HIGH-RISE COMMERCIAL BUILDINGS IN HONG KONG AND A BRIEF COMPARISON WITH THOSE IN OVERSEAS W.Y. Hung and W.K. Chow Department of Building
More informationSchematic Design: Quality Management Phase Checklist Project Phase Checklist Series
Best Practices : Project Phase Series Contributed by Micheal J. Lough, AIA, Principal, Integral Consulting The AIA collects and disseminates Best Practices as a service to AIA members without endorsement
More informationFrom Wired Glass to Clear Solutions: Designing with Fire Rated Glass Today
From Wired Glass to Clear Solutions: Designing with Fire Rated Glass Today Presented by SAFTI FIRST Fire Rated Glazing Solutions ABSTRACT: This white paper provides readers with a solid understanding of
More informationCOMMERCIAL PLAN SUBMISSION FOR NEW CONSTRUCTION AND/OR RENOVATIONS
COMMERCIAL PLAN SUBMISSION FOR NEW CONSTRUCTION AND/OR RENOVATIONS Permit applicants shall submit three (3) COMPLETE SETS of plans and specifications with each application for a permit. Plans and specifications
More information#506 New Multi-Family Buildings & Additions Plan Intake Submittal Checklist
#506 New Multi-Family Buildings & Additions Plan Intake Submittal Checklist Case #: Date: Project Name: Site Address: Application Submittal Building permit applications and plans can be submitted to the
More informationDevelopment Services City of Lawrence, KS
Development Services City of Lawrence, KS Building Planning Table R301.2 (1) Climatic & Geographic Design Criteria Building Planning The design criteria for wind speed increased from 90 MPH to 115 MPH.
More informationREFERENCE STANDARD RS 13 MECHANICAL VENTILATION, AIR CONDITIONING, AND REFRIGERATION SYSTEMS * LIST OF REFERENCED NATIONAL STANDARDS
REFERENCE STANDARD RS 13 MECHANICAL VENTILATION, AIR CONDITIONING, AND REFRIGERATION SYSTEMS * LIST OF REFERENCED NATIONAL STANDARDS **NFiPA 90A Standard for the Installation of Air Conditioning and Ventilating
More informationThe Case for Cross Laminated Timber: Part 2
Learning Objectives The Case for Cross Laminated Timber: Part 2 Opportunities and Challenges for a New Class of Timber Product 1. Review answers to common questions regarding the design and construction
More informationCity of Oviedo Commercial Shell Building Permit Application Guidelines
City of Oviedo Commercial Shell Building Permit Application Guidelines All permit application packages must be complete prior to acceptance. A complete application package shall include the following:
More informationFire Testing of Recycled Materials for Building Applications
Fire Testing of Recycled Materials for Building Applications Robert H. White Abstract To gain wide market acceptance of new building products made from recycled materials, fire testing may be necessary.
More information2012 Changes of the International Building Code Compared to the National Fire Protection Association- 101
2012 Changes of the International Building Code Compared to the National Fire Protection Association- 101 For the Florida Building Commission And the Fire Code Advisory Council Introduction The scope of
More information