A NOVEL APPROACH TO THE OUTSOURCING OF OPERATIONS AND MAINTENANCE SERVICES IN THE WATER SECTOR

Size: px
Start display at page:

Download "A NOVEL APPROACH TO THE OUTSOURCING OF OPERATIONS AND MAINTENANCE SERVICES IN THE WATER SECTOR"

Transcription

1 A NOVEL APPROACH TO THE OUTSOURCING OF OPERATIONS AND MAINTENANCE SERVICES IN THE WATER SECTOR Jeff Rigby 1, Neville Pearce 1, Mike Duell 2, Paul Collier 2, Meredith Gibbs 3, Damien O Brien 4 1. Coliban Region Water Corporation, Bendigo, VIC, Australia 2. Beca, Melbourne, VIC, Australia 3. Ashurst, Melbourne, VIC, Australia 4. Everything Infrastructure Group, Melbourne, VIC, Australia ABSTRACT Coliban Region Water Corporation (Coliban Water) has been outsourcing a variety of business functions through different contract models for over 15 years. In 2011, Coliban Water began reviewing its business functions and considering whether each function should be delivered by Coliban Water or by an external partner - insourced versus outsourced with the ultimate objective of delivering additional value to Coliban Water s customers. The review was also scheduled in preparation for the expiry of its primary frontline Operations and Maintenance (O&M) services contract in This paper reviews the methodology utilised and summarises the lessons learned. The results could benefit other water authorities considering outsourcing business functions. INTRODUCTION Coliban Water provides urban and rural water and sewerage services to the North-Central region of Victoria with a resident population of approximately 140,000 people. Coliban Water has been providing some of these services through different procurement and contracting models ranging from full outsourcing to partial outsourcing for the past 15 years. This experience includes the outsourcing of frontline O&M business functions under a ten year contract that expired in June 2013 and two Build Own Operate Transfer (BOOT) contracts that can into operation in the early 2000s. Starting in 2011, Coliban Water undertook a business model review principally to identify the best method of delivering value to its customers. The timing of the review was also key to preparing for the conclusion of three then current O&M contracts, one of which was the ten year services contract referenced above. While all business functions were reviewed through the process, the focus of this paper is the O&M business functions and the methodology utilised by Coliban Water and its advisors to undertake this review and convert it into an awarded contract with an aligned O&M service provider. Coliban Water s advisors were Beca Technical, Ashurst Legal and Everything Infrastructure Group Advisory Commercial. STRATEGIC DRIVERS The Board of Directors of Coliban Water (the Board) set the strategic drivers to be achieved through the busines model review in the following seven "Guiding Principles": 1. Promote innovation to create value and share that value created between Coliban Water, the contractor and the community; 2. Define a KPI regime that is aligned with Coliban Water s objectives and clearly drives the behaviour required from the contractor make these measureable and enforce the KPI regime; 3. Create financial flexibility consider the use of both fixed costs and variable costs to allow flexibility for variability in inflows etc; 4. Ensure the development of a contract that is easy to understand, easy to administer and clearly outlines expectations of the contract must be reflective of the spirit and intent of the agreement; 5. Ensure expectations of the contractor are clear this includes branding, performance, reporting requirements etc; 6. Consider Coliban Water s greater business objectives and make sure these are reflected in the contracts i.e. consider sustainability and financial viability etc.; and 7. Coliban Water should maintain the ownership and retention of all intellectual property capital created by its activities and functions, ie build the capability of the organisation. The Guiding Principles were applicable to both the consideration of all business functions and specific O&M business functions. To demonstrate this point, the key O&M strategic drivers are nominated alongside the corresponding Guiding Principles. Retain knowledge of the treatment and reticulation assets within Coliban Water Guiding Principle 7; Nominate maintenance standards that were representative of the fact that asset lifespans are far in excess of the contract lifespan Guiding Principle 6; and

2 Build in flexibility into the O&M contract that allows Coliban Water to remain agile to changing external conditions Guiding Principle 3. In addition to the Guiding Principles, Coliban Water's prior experience of outsourcing was also relied upon to provide guidance. This experience includes BOOT contracts, O&M contracts, Design and Construct (D&C) contracts and general labour hire contracts. Under the direction of Managing Director Jeff Rigby, Coliban Water then formulated a matrix presented in Figure 1 that encapsulated various and relevant contract models and framed them in a continuum according to their level of risk transfer, ability for Coliban Water to control the strategic direction as well as other matters. The majority of Coliban Water s experience in previous outsourcing contracts was with BOOT and regulate style contract models that provided for a high level of outsourcing and risk transfer to the service provider. However, this approach left Coliban Water with relatively low levels of control over how services would be delivered to its customers and its infrastructure assets managed. The business model review identified that one of its revised objectives was to retain strategic direction and involvement in delivery of the services and management of assets, while leveraging the skills and knowledge of an experienced service provider. This objective was particularly pertinent for services that involved customer interaction. This required an O&M services contract model that moved away from its existing contract model (fixed fee for all services) and enabled Coliban Water to have a greater degree of control over how and when services would be delivered. At the strategic level, Coliban Water identified that its ideal contract style fell within the "supervise" category. Prior to committing to an effort-intensive procurement process, a review of the existing primary O&M Contract against the Guiding Principles was also undertaken. The review demonstrated that the existing O&M contract did not align to the Guiding Principles. BUSINESS FUNCTIONS With the strategic drivers clearly articulated and with the knowledge that the primary O&M contract would not be rolled-over in its current form, the next step in the methodology was to determine whether each business function within the organisation should be outsourced or insourced. This determination was achieved, in part, by first identifying each business function within the organisation, from the provision of information technology services, customer service through to management of reservoirs. Then, each business function was assessed using a framework that was based on the Guiding Principles and in particular; customer value, risk, level of control and market appetite. The result was a recommendation for each business function to be either outsourced or insourced. Where the recommendation was to be outsourced, the level of outsourcing was also referenced in line with the matrix continuum (Figure 1). Broadly, the outcome of the assessment was to change from outsource to insource for customer-facing business functions and to continue to outsource O&M business functions, with the majority of O&M business functions to be outsourced through a supervise style model. However, some business functions such as biosolids disposal and meter reading were recommended to be outsourced through a direct approach model. The next step in the methodology was to consider various packaging options for the business functions that were to be outsourced. All business functions delivered through one contract; O&M business functions split out from the administrative business functions; or Further separation through splitting O&M business functions: o Geographic splits eg, North and South regions o Function splits eg, networks and treatment. To assess the suitability of the proposed packaging options, a number of different types of assessments were undertaken: 1. A market sounding exercise was undertaken to assess the appetite of potential contractors particularly around the financial size of the contact and the types of the business functions where delivery by the market was preferred; 2. A financial model was developed for O&M business functions in order to develop baseline costs for all O&M activities as well as for the different packaging options. The financial model was referred to as the Industry Comparator and was based on a Public Sector Comparator; and 3. Individual Best Value Assessments were undertaken for the business functions proposed to be repatriated from the contractor and returned to Coliban Water. With regards to the O&M business functions, the various assessments demonstrated that the best value would be obtained by tendering the O&M business functions as a single package under a supervise contract model see Figure 1. In summary, this step of the methodology delivered Coliban Water a clear scope and contract model.

3 Table 1: Outsourced scope, previous and new arrangement. Note: services marked with * were continuing arrangements under separate contracts. Outsourced service Previous New arrangement arrangement Asset management Previous provider Coliban Water Urban water networks Previous provider Lend Lease Urban sewer networks Previous provider Lend Lease Water Reclamation Plant - Kyneton Previous provider Lend Lease Water Reclamation Plant Castlemaine Previous provider Lend Lease Water Reclamation Plant Echuca * WIG WIG Water Reclamation Plants All others Previous provider Lend Lease Water Treatment Plants Echuca, Castlemaine & Kyneton * Veolia Veolia Water Treatment Plants All others Previous provider Lend Lease Rural Water Networks Previous provider Coliban Water Billing, Revenue Collection, Meter Reading Previous provider Coliban Water IT Support Previous provider Coliban Water Headworks Coliban Southern Reservoir System Coliban Water Coliban Water Headworks Goldfields Super Pipe (JV with CHW) * Veolia Veolia In addition, the Industry Comparator was developed which had further benefit during tender evaluation phase. The Industry Comparator provided a baseline cost for the services using a technical assessment of the O&M requirements of each asset. The Industry Comparator also included costings for management, consumables, travel and grouping efficiency and quantified contract risk profile in line with the supervise model. It thus could be sliced and diced to match the different proposals received from the tenderers. During the contract term, the Industry Comparator could then be used as an annual maintenance plan given that it was built from Coliban Water s master asset list. CONTRACT MODEL With the scope and contract approach nominated, Coliban Water turned to its advisors to develop the contract document in line with the Guiding Principles. The methodology adopted was to conduct a series of workshops with key Coliban Water staff and management to capture lessons from the past and to articulate Coliban Water's aspirations for a successful relationship with the service provider at a practical level. The following sections reference Figure 2 which diagramatically represents the contract model. One of the key strategic drivers was that Coliban Water retained strategic direction and involvement in delivery of the services while leveraging the skills and knowledge of an experienced service provider (Guiding Principles 6 and 1 respectively). In addition, one of the key lessons identified through the workshops was that Coliban Water required a contract structure that would retain competitive tension with the service provider and avoid the pitfalls of "client capture". These dual objectives were achieved by the annual work plan process and fee structure a mixture of lump sums, schedule of rates and pass through consumables. Coliban Water retains responsibility for developing an annual work plan covering all planned maintenance services. The service provider must deliver the annual work plan within the relevant financial year to required service standards. In practice, Coliban Water retains the ability to direct the service provider regarding delivery of the work packages identified within the annual work plan. Tenderers were required to bid for a lump sum to deliver the annual work plan for the first year of the contract but also to provide costings for individual tasks within the annual work plan. Each year, the annual work plan is reset by Coliban Water after consultation with the service provider and the service provider must provide a revised lump sum for the relevant annual work plan. Coliban Water is able to refer to the individual costings for work packages provided as part of the RFT response as a basis for considering and negotiating the revised lump sum for following years of the contract. Due to the relatively high level of direction retained by Coliban Water, the contract expressly provides that Coliban Water retains all asset risk. These objectives were also achieved by making the contract non-exclusive and providing for a term of four years with two options to extend for a further five years. The initial four year term was required to achieve alignment with the future timing of the Essential Services Commission regulated price setting and Water Plan process. The options to renew would only be exercised by Coliban Water if the service provider was delivering a high level of service performance and there was a productive and effective relationship with Coliban Water. For reactive (and planned corrective) maintenance, the service provider is paid for work completed on the hourly rates negotiated at the commencement of the contract and which are adjusted for CPI increases during the contract term. However, the service provider is discouraged from gaming planned maintenance and reactive maintenance by

4 being subject to a reactive maintenance "budget". This is a pain-share, gain-share mechanism under which the service provider bid a set percentage of the planned maintenance lump sum as the "budget" for reactive maintenance. Coliban Water and the service provider share 50/50 in any overrun or underrun of the "budget". This provides an incentive for the service provider to keep up its planned maintenance schedule so that it underruns the reactive maintenance budget and therefore shares any savings. This also meets the objective of sharing benefits of any innovations between Coliban Water and the contractor (Guiding Principle 1). As per the description above, if there is an overrun on the "budget" the service provider is only paid 50% of all work in excess of the budget. This represents a significant risk to the contractor given the difficulties of predicting reactive maintenance events, and that the cost implications of a large reactive maintenance event could blow the budget. As such, only the first $25,000 of each is event is counted for the purposes of determining the budget (the service provider is still paid the full amount, subject to the pain-share gain-share mechanism). Lessons learnt workshops revealed that the previous fixed fee model had provided both benefits and disadvantages to Coliban Water. In particular, while fixed price gave budget certainty, during the drought around 2005 when water treatment throughput was low, there was a perception that that there was a windfall gain under the previous O&M contract with limited benefit to Coliban Water s customers. To account for the relatively high degree of regulation of operations services and large impact of climatic variability, the new O&M contract transfers the labour risk to the service provider (lump sum) while the risk for consumables such as chemicals and electricity is retained by Coliban Water. This model also reflects the fact that Coliban Water does not require as much strategic direction and control over these services as compared to planned maintenance services. Alternatives to this model were considered and discounted: Providing for Exceptional Events, such as Blue- Green algae outbreaks, to be at Coliban Water's risk (ie outside lump sum) was discounted to due to the complexity in defining what was, and what wasn t, an exceptional event; and Charging on a throughput rate was discounted as this would introduce a conflicting driver between Coliban Water s responsibility for asset maintenance versus the service provider s responsibility for operations. The contract model provides for the payment of a monthly Management Fee based on a percentage of all payments for planned maintenance, reactive maintenance and operations services. This is intended to cover all corporate overheads including administration, management costs and other related costs, together with profit margin. Four key result areas (KRAs) were identified for the performance incentive mechanism: safety, budget, compliance and joint outcomes. The budget incentive included the reactive maintenance painshare, gain-share "budget' mechanism described above. The three remaining KRAs operate as separate incentive pools made up of amounts withheld from the monthly Management Fee based on the percentage of the service provider's annual profit that it was required to bid for this purpose, with a minimum of 5% of profit to be put into each incentive pool. Payment of the incentive pools is made annually based on the percentage achievement of negotiated KPIs in each KRA pool. KPIs may be re-set at the end of each contract year by agreement of the parties. The KPIs align with Coliban Water's safety and key compliance measures and strategic objectives, such as building the capability of the organisation (Guiding Principle 7). In addition, the contract model also included provisions for extra services, emergency services, transition and mobilisation lump sums, default and termination, and formal instructions to the service provider from improvement notices through to major non-conformance notices. PROCUREMENT PROCESS The procurement process (see Table 2) was comprehensive and is relatively representative of the standard used throughout the water industry. Points of difference are discussed below. As previously mentioned, market sounding was undertaken by a third party without identifying Coliban Water to the potential O&M service providers. This had the benefit of gauging market interest in outsourced O&M business functions and helped inform the potential packaging options. The EoI responses confirmed that there was strong market interest and that a single contract model was preferred. Six parties were shortlisted to proceed through the procurement process. Given that two out of the six shortlised parties were incumbents it was critical that a level playing field was afforded to all shortlisted candidates. This was achieved by a number of means: Coliban Water and its advisors designed and implemented an interactive tender process so that those potential service providers less familiar with Coliban Water's business had the opportunity to learn and understand Coliban Water's fundamental business drivers, as well as the specifics of the proposed O&M services contract. This was achieved through various

5 Table 2: Procurement process and timeline Phase Period Market sounding March 2012 April 2012 Expression of July 2012 interest Shortlisting of August 2012 service providers Request for November 2012 February Tender 2012 Contract January 2012 comments Evaluation and February 2012 March 2013 negotiation Award April 2013 Transition April 2013 June 2013 Contract Commencement 1 July 2013 information sessions (techncial, commercial and legal), a data room, site visits, a formal Q&A process and a contracts comments process. Once shortlisted, parties were required to execute a Process and Probity Deed which governed these interactions and ensured that all tenderers were afforded equal opportunity and equal information. For example, answers to questions submitted through the Q&A process were provided to all tenderers in summarised form; The procurement process was rigorously documented including throughout the contract negotations; and The process conformed to the Victorian Government s probity requirements to ensure a fair and transparent business decision process. In line with this approach, independent probity advisors and probity auditors were appointed and all processes captured in a Procurement Conduct Plan. The following arrangements were also established: o All Coliban Water and advisor employees directly involved signed confidentiality agreements at various stages of the process; o The key elements of probity were discussed and explained to project team staff to ensure that the same information was being provided to all tenderers; o A Project Manager was appointed to control the flow of key information; o A secure office was established for the storage of information and secure IT processes and electronic storage was established with access only available to the project team; o A probity auditor was appointed to review key decisions and independently report to the Board; and o A probity advisor was retained throughout the procurement process to assist with the ongoing management of probity and provide advice on probity matters identified by the project team. The interactive tender process extended to a contract comments process. The intent of this process was two-fold. To test the market's appetite for the risk allocation profile proposed by the O&M contract. Allow each tenderer to identify and demonstrate that alternative risk positions that would deliver greater value for money to Coliban Water. To enable this process, during the tender period: 1. Tenderers were requested to submit proposed contract comments marking each comment with its relative importance. Tenderers were asked to submit comments with no identifying markers so that Coliban Water and its advisors could consider the comments on a "blind' basis. The contract comments were not taken into account in the formal evaluation process of the RFT; 2. Coliban Water and its advisors then assessed these risk/contract positions to identify common themes and consider whether Coliban Water should reconsider its position. The market response was, on the whole, that the contract risk allocation was acceptable with little alteration. The result was that the contract was re-issued with minor amendments; then 3. Tenderers were requested to resubmit the final contract departures with their tenders, taking into consider Coliban Water s revised position. These formal contract departures were assessed in the final evaluation of tender responses. Tender evaluation was undertaken by separate and independent teams; Team 1: validate tender conformance on receipt and manage the tender clarification process; Team 2: financial assessment; and Team: 3: non-financial assessment. The benefit of this approach to Coliban Water was that it was only in the final stages of evaluation where moderation and compromises between financial and non-financial criteria would be drawn. The Industry Comparator was again used as part of the financial assessment. ENTERPRISE IMPACTS Given that the O&M of assets is a key function of any water authority, a change in the manner that this function is executed will lead to enterprise-wide impacts. These impacts were not just restricted to Coliban Water, but alsoextedned to the previous O&M service provider and the new service provider. These risks included:

6 The previous and new O&M contracts have different commercial structures promoting different management and operational styles. This presented a risk that Coliban Water staff would continue to interact with and manage the new O&M service provider as per the previous model. This would have resulted in Coliban Water not realising the benefits of the new contract, such as transfer of knowledge; There was a risk that fundamental understanding and/or knowledge of Coliban Water s systems and assets would be lost through the transition period leading to below standard customer outcomes during the initial transition period following contractor changeover; and There was a risk that staff in both Coliban Water and the previous O&M service provider would have uncertainty through the procurement process regarding their roles. Coliban Water proactively managed risks for which they were responsible through a number of actions including regular all staff updates, employing a dedicated transition period manager to assist with the close-out of the previous O&M contract, assigning a Coliban Water representative to act as the transition coordinator for the new O&M contract and implementing numerous transition requirements with both the outgoing and incoming O&M services contractors. APPLICATION TO OTHER WATER AUTHORITIES Both the overall process and individual aspects are directly applicable to other water authorities considering outsourcing business functions. The ultimate result of the methodology employed by Coliban Water and its advisors was the development and award of a contract that aligned to the Guiding Principles. The Board's development of the Guiding Principles early in the process meant that Coliban Water's strategic goals as reflected in the Guiding Principles could be used throughout the process as a benchmark for evaluation in quite disparate aspects of the RFT process. For example, the previous O&M contract was evaluated against the Guiding Principles to determine whether a business model review was required or not. Additionally, the business functions that changed in the outsourcing model during the business model review were evaluated to determine whether the change was warranted at a strategic, and not just organisational, level. Finally, the new O&M contract was evaluated just prior to award to confirm that it would achieve the Guiding Principles. In addition, the development of an Industry Comparator enabled a baseline cost for the contract model to be developed. This was important as the contract model differed significantly from the previous model. The baseline cost was used to evaluate tenders, inform the Essential Services Commission of the expected future service cost to Coliban Water and it will be used over the contract term to evaluate revisions in scope and price for services as a result of capital works undertaken by Coliban Water. The procurement process utilised a two-stage contract departures process so that Coliban Water could test the tenderers appetites for the risk allocation profile proposed in the O&M contract and also gave each tenderer the opportunity to demonstrate that alternative risk positions would deliver greater value for money to Coliban Water. Finally, the commercial framework financially incentivised the tenderers to adopt Coliban Water s specific O&M objectives of: retaining knowledge of the treatment and reticulation assets within the business; nominating maintenance standards that are representative of the fact that asset lifespans are far in excess of the contract lifespan; and building in flexibility into the O&M contract that allows Coliban Water to remain agile to changing external conditions and business objectives. CONCLUSION Coliban Water achieved the successful outcome of a contract for the frontline service provision of O&M activities of its network and treatment assets. The contract was awarded on time and within budget. This outcome was achieved, in part, through the novel combination of contract development processes: Defining key strategic objectives through the Guiding Principles that were used throughout the procurement process; A holistic approach through the business model review, including the contract model continuum, which identified the appropriate scope and packaging options; An Industry Comparator that provided both a baseline cost as well as maintenance strategy to be used during the contract term; and A contract comments process that both clearly conveyed Coliban Water s intended position during the tender period as well as reduced the overall procurement timeframe. ACKNOWLEDGEMENT There were many people that contributed to the success of the process. The authors would like to acknowledge the significant contribution of Coliban Water s Rick Jackel as project manager.

7

8

Advisory Note - October 2005. Disclosure and management of conflict of interest for advisers

Advisory Note - October 2005. Disclosure and management of conflict of interest for advisers Advisory Note - October 2005 Disclosure and management of conflict of interest for advisers The Secretary Department of Treasury and Finance 1 Treasury Place, Melbourne Victoria 3002 Australia Telephone:

More information

Procurement Capability Standards

Procurement Capability Standards IPAA PROFESSIONAL CAPABILITIES PROJECT Procurement Capability Standards Definition Professional Role Procurement is the process of acquiring goods and/or services. It can include: identifying a procurement

More information

How to get value for money from service providers on major projects

How to get value for money from service providers on major projects How to get value for money from service providers on major projects Session Focus Contracting as a relationship Identifying win/win arrangements Procurement & Planning on major projects Understanding the

More information

Procurement of Goods, Services and Works Policy

Procurement of Goods, Services and Works Policy Procurement of Goods, Services and Works Policy Policy CP083 Prepared Reviewed Approved Date Council Minute No. Procurement Unit SMT Council April 2016 2016/0074 Trim File: 18/02/01 To be reviewed: March

More information

Mitchell Shire Council

Mitchell Shire Council ATTACHMENT Mitchell Shire Council Ordinary Council Meeting CONTRACT MANAGEMENT POLICY AND TENDERING POLICY Contract Management Policy 25 March 2013 Attachment 1 Pages 12 CORPORATE SERVICES DOCUMENT NUMBER

More information

Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education

Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education EMAIL contact@fosterinfrastructure.com WEB www.fosterinfrastructure.com Best Practice in Design of Public-Private Partnerships (PPPs) for Social Infrastructure, particularly in Health Care and Education

More information

REQUEST FOR QUOTE. RFQ Reference Number: RFQ <<INSERT e.g SWR 03-11/12>> <<Enter Course Name>>

REQUEST FOR QUOTE. RFQ Reference Number: RFQ <<INSERT e.g SWR 03-11/12>> <<Enter Course Name>> REQUEST FOR QUOTE RFQ Reference Number: RFQ Date of Issue: Name of Business Unit: Address: Contact Person: Telephone: Email:

More information

Health Purchasing Policy 2. Procurement Strategic Analysis

Health Purchasing Policy 2. Procurement Strategic Analysis Health Purchasing Policy 2. Procurement Strategic Analysis Determining the market dynamics, complexity of procurement and aligning capability 26 June 2014 1 Health Purchasing Policy 2. Procurement Strategic

More information

Part E: Contract management

Part E: Contract management Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project

More information

Part B1: Business case developing the business case

Part B1: Business case developing the business case Overview Part A: Strategic assessment Part B1: Business case developing the business case Part B2: Business case procurement options Part B3: Business case funding and financing options Part C: Project

More information

Australian National Audit Office. Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO

Australian National Audit Office. Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO Australian National Audit Office Report on Results of a Performance Audit of Contract Management Arrangements within the ANAO Commonwealth of Australia 2002 ISBN 0 642 80678 0 10 December 2002 Dear Mr

More information

UNSOLICITED PROPOSALS

UNSOLICITED PROPOSALS UNSOLICITED PROPOSALS GUIDE FOR SUBMISSION AND ASSESSMENT January 2012 CONTENTS 1 PREMIER S STATEMENT 3 2 INTRODUCTION 3 3 GUIDING PRINCIPLES 5 3.1 OPTIMISE OUTCOMES 5 3.2 ASSESSMENT CRITERIA 5 3.3 PROBITY

More information

LGRF. Procurement Probity Plan. July 2012

LGRF. Procurement Probity Plan. July 2012 LGRF July 2012 When to develop a : A probity plan is best used for any procurement of medium complexity and size and above. A probity plan can be implemented without use of a probity advisor/auditor. Description

More information

Contract and Vendor Management Guide

Contract and Vendor Management Guide Contents 1. Guidelines for managing contracts and vendors... 2 1.1. Purpose and scope... 2 1.2. Introduction... 2 2. Contract and Vendor Management 2.1. Levels of management/segmentation... 3 2.2. Supplier

More information

6.0 Procurement procedure 1 Infrastructure

6.0 Procurement procedure 1 Infrastructure Page 6-1 6.0 Procurement procedure 1 Infrastructure 6.1 Overview Introduction Procurement procedure 1 Infrastructure consists of four parts: guidelines for understanding the strategic context for the procurement

More information

Outsourcing. Knowledge Summary

Outsourcing. Knowledge Summary Knowledge Summary Outsourcing P&SM professionals should have the knowledge and skills required to manage the outsourcing process and to advise colleagues of the most appropriate solution to obtain best

More information

Procurement Strategy and Contract Selection

Procurement Strategy and Contract Selection GUIDELINE Capital Works Management Framework Procurement Strategy and Contract Selection The suite of Capital Works Management Framework documents is available online www.hpw.qld.gov.au: The Capital Works

More information

Contract management: renewal and transition. Report to Parliament 10 : 2013 14

Contract management: renewal and transition. Report to Parliament 10 : 2013 14 Contract management: renewal and transition Report to Parliament 10 : 2013 14 Queensland Audit Office Location Level 14, 53 Albert Street, Brisbane Qld 4000 PO Box 15396, City East Qld 4002 Telephone (07)

More information

IT Outsourcing. Third Time Lucky? Winter 2014/15 INSIGHTS

IT Outsourcing. Third Time Lucky? Winter 2014/15 INSIGHTS INSIGHTS IT Outsourcing Third Time Lucky? Coeus Consulting looks at whether the emerging third generation sourcing models are the end of the journey or is a fourth generation on the way? Winter 2014/15

More information

POSITION DESCRIPTION Number: PD:

POSITION DESCRIPTION Number: PD: POSITION DESCRIPTION Number: PD: The VALUES of The City of South Perth Customer Focus - To work together with our customers to achieve positive outcomes. Excellence - To develop a culture of flexibility,

More information

RDTL Procurement Best Practice Guide 7: Managing Contracts. RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS

RDTL Procurement Best Practice Guide 7: Managing Contracts. RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS RDTL MINISTRY OF FINANCE Procurement Service BEST PRACTICE GUIDE 7: MANAGING CONTRACTS 1 RDTL Procurement Guidelines The Procurement Legal Regime Decree Law sets out new procurement processes which must

More information

CONTRACTS STANDING ORDERS (CSOs) 2015 / 2016 CSO 2015-6 1

CONTRACTS STANDING ORDERS (CSOs) 2015 / 2016 CSO 2015-6 1 CONTRACTS STANDING ORDERS (CSOs) 2015 / 2016 CSO 2015-6 1 PART 3G Contracts Standing Orders 2015/16 Definitions Aggregation is the combining together of the total contract value from separate contracts

More information

NHS BLOOD AND TRANSPLANT 28 NOVEMBER 2013. Contract for the Collection and Disposal of Clinical Waste: Award Recommendation.

NHS BLOOD AND TRANSPLANT 28 NOVEMBER 2013. Contract for the Collection and Disposal of Clinical Waste: Award Recommendation. 13/123 NHS BLOOD AND TRANSPLANT 28 NOVEMBER 2013 Title Contract for the Collection and Disposal of Clinical Waste: Award Recommendation Executive Summary Collection and Disposal of Clinical Waste across

More information

Quick Guide: Meeting ISO 55001 Requirements for Asset Management

Quick Guide: Meeting ISO 55001 Requirements for Asset Management Supplement to the IIMM 2011 Quick Guide: Meeting ISO 55001 Requirements for Asset Management Using the International Infrastructure Management Manual (IIMM) ISO 55001: What is required IIMM: How to get

More information

Doing business with local government

Doing business with local government Doing business with local government A guide to better understand how to successfully become a supplier for local government. 02 Doing business with local government Introduction 3 About this guide 3 What

More information

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process

Outsourcing. Definitions. Outsourcing Strategy. Potential Advantages of an Outsourced Service. Procurement Process CIPS takes the view that the outsourcing of services to specialist providers can often lead to better quality of services and increased value for money. Purchasing and supply management professionals should

More information

5 Year Strategic Asset Management Plan

5 Year Strategic Asset Management Plan Westernport Region Water Corporation 30 July 2007 Prepared for Westernport Region Water Corporation Prepared by Maunsell Australia Pty Ltd Level 9, 8 Exhibition Street, Melbourne VIC 3000, Australia T

More information

Partnerships Victoria Requirements

Partnerships Victoria Requirements Partnerships Victoria Requirements May 2013 Version Control Version Control Last Updated Updated sections Rationale 1 February 2009 Original publication 2 January 2010 Section 12 and Annexure 6 Annexure

More information

Building Capacity. Final Report. November 2013

Building Capacity. Final Report. November 2013 Building Capacity Final Report November 2013 1. Background One of the key challenges facing Personal Tax is improving the service we offer our customers against a backdrop of compressed budgets. Although

More information

FLEET MANAGEMENT TOOLKIT. RCV Regional Collaboration in Fleet Management

FLEET MANAGEMENT TOOLKIT. RCV Regional Collaboration in Fleet Management FLEET MANAGEMENT TOOLKIT RCV Regional Collaboration in Fleet Management PREFACE This Fleet Management Toolkit has been prepared for Rural Councils Victoria to document the outcomes of Project 4.4 Regional

More information

Professional Standards Capability Program

Professional Standards Capability Program Procurement Title of document Professional - Avante Garde Capability 18pt, 80% Standard black Professional Standards Capability Program VERSION 1 5 th Feb 2014 IPAA PROCUREMENT PROFESSIONAL CAPABILITY

More information

Outsourcing: key legal issues and contractual protections

Outsourcing: key legal issues and contractual protections Page 1 Outsourcing: key legal issues and contractual protections Paul Jones May 2009 Introduction As the economic climate becomes more challenging, organisations in all sectors are looking to drive efficiencies

More information

APPENDIX A (CFO/263/09) Merseyside Fire & Rescue Service ICT Outsourcing Procurement Support. Final Report

APPENDIX A (CFO/263/09) Merseyside Fire & Rescue Service ICT Outsourcing Procurement Support. Final Report Merseyside Fire & Rescue Service ICT Outsourcing Procurement Support Final Report Version 1.1 Oct 2009 Contents 1. Executive Summary...3 2. Context and Background...3 3. Deliverables and Value Added...

More information

Data Communications Company (DCC) price control guidance: process and procedures

Data Communications Company (DCC) price control guidance: process and procedures Guidance document Contact: Tricia Quinn, Senior Economist Publication date: 27 July 2015 Team: Smarter Metering Email: tricia.quinn@ofgem.gov.uk Overview: The Data and Communications Company (DCC) is required

More information

SECTION 6: RFQ Process, Terms and Conditions

SECTION 6: RFQ Process, Terms and Conditions SECTION 6: RFQ Process, Terms and Conditions Note to suppliers and Respondents In managing this procurement the Buyer will endeavour to act fairly and reasonably in all of its dealings with interested

More information

1. Evolution of infrastructure procurement in NSW. 2. Market consultation and outcomes. 3. Response and implementation. 4. Project Deed Evolution

1. Evolution of infrastructure procurement in NSW. 2. Market consultation and outcomes. 3. Response and implementation. 4. Project Deed Evolution Reducing Bid Costs for Outcome-Based Procurements in NSW Infrastructure and Structured Finance Unit: Partnering to Create Partnerships December 2015 1. Evolution of infrastructure procurement in NSW 2.

More information

Contract Management Guideline

Contract Management Guideline www.spb.sa.gov.au Contract Management Guideline Version 3.2 Date Issued January 2014 Review Date January 2014 Principal Contact State Procurement Board Telephone 8226 5001 Contents Overview... 3 Contract

More information

4 Adoption of Asset Management Policy and Strategy

4 Adoption of Asset Management Policy and Strategy 4 Adoption of Asset Management Policy and Strategy Abstract The report recommends the adoption of an updated Asset Management Policy 2014 and an Asset Management Strategy 2014-2019. Both documents are

More information

Agenda item: Environment & Community Safety Decision meeting

Agenda item: Environment & Community Safety Decision meeting Title of meeting: Agenda item: Environment & Community Safety Decision meeting Date of meeting: 14 th November 2014 Subject: Report by: Wards affected: Key decision: Full Council decision: Waste Disposal

More information

1. REPORT SUMMARY 1.1 INTRODUCTION

1. REPORT SUMMARY 1.1 INTRODUCTION 1. REPORT SUMMARY 1.1 INTRODUCTION In February 1996 tenders were called for a financing facility for the Territory s passenger and light commercial motor vehicles. At close of tenders on 29 February 1996,

More information

17 December 2014. Mr Jim Paul Senior Project Manager Research Australian Accounting Standards Board Level 7 600 Bourke Street MELBOURNE VIC 3000

17 December 2014. Mr Jim Paul Senior Project Manager Research Australian Accounting Standards Board Level 7 600 Bourke Street MELBOURNE VIC 3000 17 Mr Jim Paul Senior Project Manager Research Australian Accounting Standards Board Level 7 600 Bourke Street MELBOURNE VIC 3000 Dear Mr Paul Re: Thank you for the opportunity to respond to the discussion

More information

Position Description

Position Description Position Description POSITION TITLE Procurement Advisor POSITION NO 500268 DIRECTORATE DEPARTMENT Corporate Services Finance UNIT REPORTS TO Manager Finance CLASSIFICATION Band 7 LOCATION Civic Centre,

More information

The New Standard Construction Contracts: NZS3910, 3916 and 3917

The New Standard Construction Contracts: NZS3910, 3916 and 3917 The New Standard Construction Contracts: NZS3910, 3916 and 3917 Brian Clayton, Partner FEBRUARY 2014 3258689.3 Chapman Tripp Introduction Standards New Zealand has recently completed the first review of

More information

Attachment 20.27 SA Power Networks: Network Program Deliverability Strategy

Attachment 20.27 SA Power Networks: Network Program Deliverability Strategy Attachment 20.27 SA Power Networks: Network Program Deliverability Strategy Network Program Deliverability Strategy 2015-20 Regulatory Control Period SA Power Networks www.sapowernetworks.com.au Internal

More information

1.1 An initial request to enter into a contractual arrangement may be initiated by either Massey University or another party (Other Party).

1.1 An initial request to enter into a contractual arrangement may be initiated by either Massey University or another party (Other Party). CONTRACT MANAGEMENT PROCEDURE Section Risk Management Contact Risk Manager Last Review February 2013 Next Review February 2016 Approval Not required Procedures Contract Initiation Request Mandatory Guidance

More information

Fleet Management Services

Fleet Management Services Fleet Management Services Welcome to Smartfleet What is Smartfleet? Overview Managed Services Powerful Modules Reporting Overview Smartfleet is a leading Australian fleet management company, helping organisations

More information

Corporate Procurement Plan 2015/16

Corporate Procurement Plan 2015/16 Corporate Procurement Plan 2015/16 Table of Contents Responsibilities... 1 Definitions, Abbreviations And Acronyms... 1 References... 1 1. Link To Ergon Energy s Strategic Plan... 2 2. Procurement Objectives...

More information

QUALITY ASSURANCE GUIDE FOR GREEN BUILDING RATING TOOLS

QUALITY ASSURANCE GUIDE FOR GREEN BUILDING RATING TOOLS World Green Building Council Rating Tools Task Group: QUALITY ASSURANCE GUIDE FOR GREEN BUILDING RATING TOOLS Version 1.0 _ 2013 /(DRAFT_01 /Sept_13) INTRODUCTION This guide has been developed as a part

More information

Contract Management Handbook. A Guide to contract management at the University

Contract Management Handbook. A Guide to contract management at the University Contract Management Handbook A Guide to contract management at the University July 2012 CONTENTS 1. INTRODUCTION... 4 2. PURPOSE... 4 2.1 Using this Handbook... 5 3. CONTRACT MANAGEMENT FRAMEWORK... 5

More information

The Victorian Public Sector values dictate the way we interact with each other, with our the market and guide the way that we make decisions.

The Victorian Public Sector values dictate the way we interact with each other, with our the market and guide the way that we make decisions. POSITION DESCRIPTION Position Title: Procurement Officer New Position Department: Finance Compliance & Procurement Date: 22/10/2015 Reports to (position): Procurement Manager Grade: 5 Positions that report

More information

STRATEGIC ASSET MANAGER POSITION & PERSON DESCRIPTION February 2015

STRATEGIC ASSET MANAGER POSITION & PERSON DESCRIPTION February 2015 GENERAL Position & Person Descriptions form an important part of an integrated planning process to ensure that individual performance, and the required outputs and outcomes, align with the strategic and

More information

Part One: Introduction to Partnerships Victoria contract management... 1

Part One: Introduction to Partnerships Victoria contract management... 1 June 2003 The diverse nature of Partnerships Victoria projects requires a diverse range of contract management strategies to manage a wide variety of risks that differ in likelihood and severity from one

More information

Introduction. Part II: Insurance Structure Optimisation

Introduction. Part II: Insurance Structure Optimisation Introduction This book contains 12 chapters with different areas of benefit realisation; this is not an exhaustive list but provides those options that, in my experience as a consultant to fleet owners,

More information

TEC Capital Asset Management Standard January 2011

TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard January 2011 TEC Capital Asset Management Standard Tertiary Education Commission January 2011 0 Table of contents Introduction 2 Capital Asset Management 3 Defining

More information

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES

ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES ASSOCIATION OF INDEPENDENT SCHOOLS OF NSW BLOCK GRANT AUTHORITY GUIDE TO PROCUREMENT PROCESSES CAPITAL GRANTS PROGRAM / BUILDING GRANTS ASSISTANCE SCHEME Background Non government schools accepting the

More information

Slough Borough Council. Highway Asset Management Strategy

Slough Borough Council. Highway Asset Management Strategy Slough Borough Council Highway Asset Management Strategy OUR AMBITION USING RESOURCES WISELY By 2019 the Council s income and the value of its assets will be maximised 1 Key Priorities 1.1 We understand

More information

UNECE PPP Healthcare Standard

UNECE PPP Healthcare Standard INTERNATIONAL SPECIALIST CENTRE OF EXCELLENCE ON PPPs IN HEALTH MANILA, PHILIPPINES UNECE PPP Healthcare Standard Questions on lessons learned in the development of Public-Private Partnership ( PPP ) programmes

More information

The CFO insider s guide to outsourcing

The CFO insider s guide to outsourcing The CFO insider s guide to outsourcing Insider insights on running cost-effective customer contact centres and back-office processing services from the CFO at leading business process outsourcing provider,

More information

HEAD OF FINANCE AND CORPORATE SERVICES POSITION DESCRIPTION

HEAD OF FINANCE AND CORPORATE SERVICES POSITION DESCRIPTION Head of HEAD OF FINANCE AND CORPORATE SERVICES POSITION DESCRIPTION Summary of Position Organisation Context Melbourne Festival is a major arts organisation whose principal role is to conceive, develop

More information

Managing construction procurement risks

Managing construction procurement risks CONSTRUCTION PROCUREMENT BEST PRACTICE GUIDELINE #A5 Construction Industry Development Board Pretoria - Head Office Tel: 012 482 7200 Fraudline: 0800 11 24 32 Call Centre: 0860 103 353 E-mail: cidb@cidb.org.za

More information

Benchmark OHS Consulting Pty Ltd Self Assessment WHS Audit Tool

Benchmark OHS Consulting Pty Ltd Self Assessment WHS Audit Tool Benchmark OHS Consulting Pty Ltd Self Assessment WHS Audit Tool This WHS Auditing System Tool is to be used as a self-assessment of YOUR COMPANY compliance with AS 4801 and the Work Health and Safety Act

More information

Pricing Policy Statement - Excluded Retail Services. Introduction. Description of Excluded Services. Excluded Retail Services Offered in 2014/15

Pricing Policy Statement - Excluded Retail Services. Introduction. Description of Excluded Services. Excluded Retail Services Offered in 2014/15 Pricing Policy Statement - Excluded Retail Services Introduction SA Water s Water and Sewerage Retail Services: 2013-14 to 2015-16 Revenue Determination (ESCOSA, 2013, Section 2.2) requires SA Water to

More information

Audit summary. 1.1 Introduction

Audit summary. 1.1 Introduction 1 Audit summary 1.1 Introduction The Integrated Courts Management System (ICMS) is a major Information Technology (IT) initiative of the Department of Justice (DOJ). The objective of the program is to

More information

Strathcona County Final Report Recommendations Summary with Comments (Version Jan 10, 2013)

Strathcona County Final Report Recommendations Summary with Comments (Version Jan 10, 2013) Strathcona County Final Report Recommendations Summary with Comments (Version Jan 10, 2013) 1 TABLE OF CONTENTS Performance Management...3 Corporate Planning...4 Human Resources...4 Assessment and Tax...5

More information

Procedures for Tenders and Contracts. October 2014. Huon Valley Council Procedures for Tenders and Contracts October 2014 Page 1 of 14

Procedures for Tenders and Contracts. October 2014. Huon Valley Council Procedures for Tenders and Contracts October 2014 Page 1 of 14 Procedures for Tenders and Contracts October 2014 Huon Valley Council Procedures for Tenders and Contracts October 2014 Page 1 of 14 Huon Valley Council Procedures for Tenders and Contracts October 2014

More information

FAQ s VRQA Guidelines for VET providers (last update 28 June 2010)

FAQ s VRQA Guidelines for VET providers (last update 28 June 2010) FAQ s VRQA Guidelines for VET providers (last update 28 June 2010) GENERAL Why has the VRQA developed these guidelines? On 12 September 2009 the then Minister for Skills, the Hon. Jacinta Allan MP, directed

More information

Australian Government Data Centre Strategy Industry Briefing - 2 December 2010

Australian Government Data Centre Strategy Industry Briefing - 2 December 2010 Australian Government Data Centre Strategy Industry Briefing 2 December 2010 Introduction The Australian Government s Data Centre Strategy (the Strategy) is a long term program of work with a primary objective

More information

Health Purchasing Victoria

Health Purchasing Victoria Clinical Advisor Health Purchasing Victoria Melbourne, VIC PO Box 83 Ocean Grove Victoria 3226 hrsa@hrsa.com.au www.hrsa.com.au Background Health Purchasing Victoria (HPV) achieves best value supply chain

More information

Procurement Guidelines for Non-Profit Housing

Procurement Guidelines for Non-Profit Housing Procurement Guidelines for Non-Profit Housing July 2013 Table of Contents PART 1 INTRODUCTION... 1 1.1 Objectives... 1 1.2 How to Use... 1 PART 2 WORKING WITH BC HOUSING... 3 2.1 Key Stakeholders... 3

More information

Smarter Resources Smarter Business Recycling

Smarter Resources Smarter Business Recycling Smarter Resources Smarter Business Recycling Best Practice Waste and Recycling Contracts for Business February 2014 Best Practice Waste and Recycling Contracts for Business A three step process There is

More information

Guidance Note: Corporate Governance - Board of Directors. March 2015. Ce document est aussi disponible en français.

Guidance Note: Corporate Governance - Board of Directors. March 2015. Ce document est aussi disponible en français. Guidance Note: Corporate Governance - Board of Directors March 2015 Ce document est aussi disponible en français. Applicability The Guidance Note: Corporate Governance - Board of Directors (the Guidance

More information

How To Get A Contract From The Taxman

How To Get A Contract From The Taxman Procuring Professional Services Buying Support www.buyingsupport.co.uk Procuring Professional Services What are they? Why are they needed? The 7 Steps to Best Value 2 What are Professional Services? Management

More information

Engineering Innovation

Engineering Innovation Engineering Innovation In the Department of Transport and Main Roads September 2014 Foreword The Department of Transport and Main Roads role is to provide safe, functional transport infrastructure that

More information

SECTION A: COMMON FLEET MANAGEMENT FRAMEWORK

SECTION A: COMMON FLEET MANAGEMENT FRAMEWORK SECTION A: COMMON FLEET MANAGEMENT FRAMEWORK Introduction This Common Fleet Management Framework is the recommended policy/methodology/procedural environment for a rural council, based largely upon the

More information

Network Rail Infrastructure Projects Joint Relationship Management Plan

Network Rail Infrastructure Projects Joint Relationship Management Plan Network Rail Infrastructure Projects Joint Relationship Management Plan Project Title Project Number [ ] [ ] Revision: Date: Description: Author [ ] Approved on behalf of Network Rail Approved on behalf

More information

The Concept of Project Success What 150 Australian project managers think D Baccarini 1, A Collins 2

The Concept of Project Success What 150 Australian project managers think D Baccarini 1, A Collins 2 The Concept of Project Success What 150 Australian project managers think D Baccarini 1, A Collins 2 1 Curtin University of Technology, Perth, Western Australia 2 Broad Construction Services, Perth, Western

More information

Ministry Of Health Registration of Interest

Ministry Of Health Registration of Interest Ministry Of Health Registration of Interest Intermediaries Social Bond Pilot(s) Part 1 Instructions and Supporting Information What s inside? Introduction to Social Bonds Purpose of the ROI Instructions

More information

Melbourne s New Bus Contracts

Melbourne s New Bus Contracts Melbourne s New Bus Contracts Melbourne s New Bus Contracts June 2009 Victorian Auditor-General s Report Telephone 61 3 8601 7000 Facsimile 61 3 8601 7010 www.audit.vic.gov.au 2008-09:30 Level 24 35 Collins

More information

New Ticketing System Tender

New Ticketing System Tender V I C T O R I A Victorian Auditor-General New Ticketing System Tender Ordered to be printed VICTORIAN GOVERNMENT PRINTER October 2007 PP No 50, Session 2006-07, tabled with Public Sector Procurement: Turning

More information

Investment Management Standard. A guide for Victorian government departments and agencies

Investment Management Standard. A guide for Victorian government departments and agencies Investment Management Standard A guide for Victorian government departments and agencies The Secretary Department of Treasury and Finance 1 Treasury Place Melbourne Victoria 3002 Australia Telephone: +61

More information

Risk Management Framework

Risk Management Framework Risk Management Framework THIS PAGE INTENTIONALLY LEFT BLANK Foreword The South Australian Government Risk Management Policy Statement 2009 advocates that consistent and systematic application of risk

More information

Customer Engagement Program. Stage 1 Report. March 2014. Understanding customer values, needs & expectations. Government of South Australia

Customer Engagement Program. Stage 1 Report. March 2014. Understanding customer values, needs & expectations. Government of South Australia Customer Engagement Program Stage 1 Report Understanding customer values, needs & expectations March 2014 Government of South Australia Welcome to SA Water s Customer Engagement Program This report summarises

More information

Resource Manager Service for provision of ICT contractors CPO 798-11

Resource Manager Service for provision of ICT contractors CPO 798-11 Resource Manager Service for provision of ICT contractors CPO 798-11 Whole-of-government procurement arrangement Briefing for suppliers QGCPO Department of Housing and Public Works Key messages Consultation

More information

ECO-Buy Limited. Australian Packaging Covenant Action Plan (Final) September 2012 June 2015

ECO-Buy Limited. Australian Packaging Covenant Action Plan (Final) September 2012 June 2015 ECO-Buy Limited Australian Packaging Covenant Action Plan (Final) September 2012 June 2015 1 Summary This is ECO-Buy s first action plan as a new Signatory to the Australian Packaging Covenant. We are

More information

How To Host An Incompany Project For An Msc Student At Cranfield

How To Host An Incompany Project For An Msc Student At Cranfield The Cranfield Project an opportunity for your business Applying learning to real business issues At Cranfield School of Management we believe that Logistics and Supply Chain excellence is both a desirable

More information

OUTSOURCING MAINTENANCE SERVICES: AUSTRALIAN OVERVIEW AND SYDNEY WATER CASE STUDY

OUTSOURCING MAINTENANCE SERVICES: AUSTRALIAN OVERVIEW AND SYDNEY WATER CASE STUDY OUTSOURCING MAINTENANCE SERVICES: AUSTRALIAN OVERVIEW AND SYDNEY WATER CASE STUDY Colin Rymer 1, John Davis 2 1. Sydney Water, Sydney, NSW 2. Infrastructure Transaction Network, Brisbane, QLD ABSTRACT

More information

Commercial Skills and Competency Framework for. Practitioner Levels

Commercial Skills and Competency Framework for. Practitioner Levels Commercial Skills and Competency Framework for Developing and Practitioner Levels Sourcing Pre Market Document Title Author Commercial Skills and Competency Framework for Developing and Practitioner Levels

More information

LSB Procurement Framework

LSB Procurement Framework LSB Procurement Framework Introduction Procurement covers the typical purchase of services, supplies and works required to enable project delivery and to manage the infrastructure. The Services Board (LSB)

More information

Occupant: Vacant File reference: 2011/0390

Occupant: Vacant File reference: 2011/0390 ROLE DESCRIPTION SECTION A: GENERAL INFORMATION Role: Research Scientist Climate Applications Classification code: PO 3 Division: SA Research & Development Institute Type of appointment: Branch: Sustainable

More information

Value for Money Assessment Guidance: Capital Programmes and Projects

Value for Money Assessment Guidance: Capital Programmes and Projects Value for Money Assessment Guidance: Capital Programmes and Projects October 2011 Value for Money Assessment Guidance: Capital Programmes and Projects Foreword This guidance has been prepared and issued

More information

Guide to choosing a Consultant

Guide to choosing a Consultant Guide to choosing a Consultant Contents 1. Background: about this resource... 1 2. The process of selecting, engaging and managing consultants... 1 Stage 1: Do we really need a consultant or contractor

More information

Audit of UNESCO s Recruitment Process for International Staff

Audit of UNESCO s Recruitment Process for International Staff Internal Oversight Service Audit Section IOS/AUD/2015/07 Original: English Audit of UNESCO s Recruitment Process for International Staff September 2015 Auditors: Tuyet-Mai Grabiel Dawn Clemitson EXECUTIVE

More information

8.7 DRAINAGE MAINTENANCE SERVICES CONTRACT AMENITY JAMES LENIHAN, DRAINAGE MAINTENANCE ENGINEER

8.7 DRAINAGE MAINTENANCE SERVICES CONTRACT AMENITY JAMES LENIHAN, DRAINAGE MAINTENANCE ENGINEER 8.7 DRAINAGE MAINTENANCE SERVICES CONTRACT LOCATION/ADDRESS: GENERAL MANAGER: PREPARED BY: TRIM FILE NO: 14/06/1912 ATTACHMENTS: WHOLE OF MUNICIPALITY FIONA BLAIR, INFRASTRUCTURE & AMENITY JAMES LENIHAN,

More information

STANDARD CONTRACT PROVISIONS ROADS

STANDARD CONTRACT PROVISIONS ROADS STANDARD CONTRACT PROVISIONS ROADS Volume 3 MINOR WORKS CONTRACT SYSTEM (MW) MANUAL FOR MINOR WORKS CONTRACTS Standard Contract Provisions Roads Volume 3 Department of Transport and Main Roads for Minor

More information

ROADS ALLIANCE ASSET MANAGEMENT COMMUNIQUÉ AUGUST 2010 LOCAL GOVERNMENT ASSOCIATION OF QUEENSLAND LTD

ROADS ALLIANCE ASSET MANAGEMENT COMMUNIQUÉ AUGUST 2010 LOCAL GOVERNMENT ASSOCIATION OF QUEENSLAND LTD ROADS ALLIANCE ASSET MANAGEMENT COMMUNIQUÉ AUGUST 2010 LOCAL GOVERNMENT ASSOCIATION OF QUEENSLAND LTD Contents 4 Glossary 6 Background 9 Purpose of Communiqué 9 Australian and State Government Drivers

More information

Central Hosting. Case Study

Central Hosting. Case Study Central Hosting Case Study October, 2014 Central Hosting Case Study Background An Chéim was originally set up to procure, distribute and implement key MIS systems (hardware and software) for the Institutes

More information

aaca NCSA 01 The National Competency Standards in Architecture aaca Architects Accreditation Council of Australia PO Box 236 Civic Square ACT 2608

aaca NCSA 01 The National Competency Standards in Architecture aaca Architects Accreditation Council of Australia PO Box 236 Civic Square ACT 2608 aaca NCSA 01 The National Competency Standards in Architecture aaca Architects Accreditation Council of Australia PO Box 236 Civic Square ACT 2608 NCSA 01 Competency Based Assessment in Architecture THE

More information

POLICY CONTRACT MANAGEMENT POLICY POLICY STATEMENT

POLICY CONTRACT MANAGEMENT POLICY POLICY STATEMENT POLICY CONTRACT MANAGEMENT POLICY POLICY STATEMENT The intent of this policy is to establish a University-wide governance structure for managing contracts and other legally binding documents. The Policy

More information

Helping our clients win in the changing world of work:

Helping our clients win in the changing world of work: Helping our clients win in the changing world of work: Recruitment Process: Why Outsource? A Manpower Insights Paper The future of RPO looks strong despite or perhaps aided by the current global recession.

More information

1. The transfer of the service vehicle fleet and pool car fleet management to the County Council from 1 July 2013.

1. The transfer of the service vehicle fleet and pool car fleet management to the County Council from 1 July 2013. Cabinet Member for Finance and Resources and Cabinet Member for Highways and Transport Ref No. HT11(12/13) Service Vehicles Procurement Strategy November 2012 Report by Director of Business Change Key

More information