West Rail Tai Lam Tunnel (Contract DB-350) Introduction

Size: px
Start display at page:

Download "West Rail Tai Lam Tunnel (Contract DB-350) Introduction"

Transcription

1 Introduction General Scope of the Contract Tai Lam Tunnel (TLT) was awarded as a Design and Build Contract on 22 September 1998 to a Nishimatsu-Dragages Joint Venture by the Kowloon Canton Railway Corporation (KCRC) as Contract DB350 for HK$1.79 billion. At 5.5 km long, TLT is the longest transportation tunnel in Hong Kong and has been constructed using the drill and blast method with computer controlled drilling jumbos and laser guidance to ensure an accurate alignment. The conforming design was to provide two single-track tube bored tunnels with interconnecting cross passage adits every 250m for escape to the non-incident tunnel in the event of an emergency. The successful JV proposed an innovative alternative tender design scheme, which was to drive a twin-track, single tube bored tunnel constructed with a center partition wall to separate the mainline up-track and down-track. Nishimatsu drove the southern half of the drill and blast tunnel. The package also included the construction of the 0.35km section of twin-cell cut-and-cover tunnel linking between the Southern Portal and the new Tsuen Wan West Station, as well as the ancillary ventilation building at Chai Wan Kok. In paralled with these works Dragage drove the northern half of the tunnel along with 0.33km of at grade site formation and slope works and the northern ancillary ventilation building.

2 Introduction Southern Portal and the Cut-and-Cover Tunnel at Chai Wan Kok, Tsuen Wan The works were complicated at the southern portal due to a number of physical factors. First of all, the tunnel alignment was directly obstructed by a group of piled foundations to a pier of the existing Chai Wan Kok Bridge at the entrance of the Tuen Mun Highway. Before any tunneling works could commence, the existing foundation needed to be underpinned, which was done by the introduction of a 27m long, 3.5m deep and 5.6m wide transfer beam. To facilitate this, two new groups of 1200mm diameter bored piles, 3 on each side, were driven to support the transfer beam, which spanned across the tunnel alignment. To account for deflection of the transfer beam and any initial settlement to the foundation under loading, the bridge was jacked up by 5mm using six 200-tonne single acting hydraulic ram jacks providing a design vertical uplift of 1000 tonnes. A secondary jacking system, consisting of two 90-tonne jacks provided horizontal restraint to the bridge deck. The vertical jacks maintained the bridge deck in a constant position throughout the whole operation to ensure the total safety of road users at all times. A simplified sequence of enabling works at the Southern Portal location is shown in the flow chart below.

3 Introduction The provision of the Southern Portal at Chai Wan Kok was a difficult job. A 250m trench, measured 40m wide x 25m deep, needed to be formed. The trench initially acted as a service shaft to provide room for the assembly of the required tunnel equipments and alter as access for the tunneling work during construction. The Southern Portal was formed in slightly to moderately decomposed medium-grained dacite with occasional localized highly decomposed bands. At this location, 1.2m thick diaphragm wall panels formed the vertical support for the sides of the trench being locally restrained by ground anchors. When reaching the formation level, a temporary ramp with up-track and down-track provision, was erected with supports onto a steel frame. This temporary access was maintained for about 15 months as the main route for spoil removal until the tunnel excavation was completed. This was followed by the dismantling of the access ramp and the construction of the approach tunnel section within the trench using a traditional cut-and-cover arrangement. The remaining 350m long cut-and-cover tunnel linking between the approach section and the Tsuen Wan West Station portion. The cut-and-cover tunnel was constructed in residual soils marine deposits, alluvium and reclamation fill. The construction of this section of tunnel was quite routine in term of tunneling work of this scale. However, the arrangement for the traffic diversion at the existing interchange at Chai Wan Kok was quite a challenge. A temporary deck supported on steel H-piles was erected in various phases in order to provide the necessary road surface for the diversion arrangement, which involved the maintenance of uninterrupted traffic to the dual 2-lane roadway in 3 directions at all time. There is a ventilation building located at both ends of the tunnel portals. The facility has a dual purpose, as well as providing ventilation to the tunnel in normal operating mode, they can also be used for smoke extraction from the tunnel in the event of a fire.

4 Introduction The Construction of the Tunnel The bored tunnel is essentially a twin-track (14m span) tunnel with the exception of the first 518m of tunnel from the Northern Portal, which is constructed as a triple-track (19m span) tunnel to accommodate a siding track. The tunnel was driven through granitic and volcanic rocks. As the tunnel advanced, the Grimstad and Barton Norwegian Method of Tunneling support methodology was used as the guide to assessing the tunnel support requirements. The face of the tunnel was advanced between 1m and 5m per blast depending on geotechnical conditions as well as the charge weights used. The anticipated monthly production for usual twin-track tunnel was 170m but for TLT the contractor managed to achieve and maintain a production rate between 200m to 210m per month. As a result, despite the additional time required for the enabling works at the tunnel portal, the tunnel breakthrough was achieved exactly on programme. For the southern section, mucking out was carried out by loading tunnel spoil into vehicles at the face of the excavation. While for the northern portal, a full-range extensible conveyor system was employed for the purpose. The tunnel has been constructed with a permanent concrete lining in order to achieve the required 120-year design life. For the southern section of the tunnel an in-situ reinforced concrete lining was only required at the portal zone, the majority of the lining being un-reinforced. All of the tunnel lining was cast in 12.5m lengths using a steel shutter and lining construction was carried out concurrently with the excavation works.

5 Introduction Tunnel Interior Arrangement A 300mm thick reinforced concrete center partition wall was constructed separating the up-track and down-track tunnel. As a safety requirement to provide access to a non-incident tunnel in the event of an emergency, openings are formed every 60m along the full length of the partition wall for passenger access between the up-track and the down-track tunnel. Each opening has a sliding cross passage door with an FRP of 4 hours. A track cross-over opening in the partition wall 52m long and 8m high in the center of the tunnel (at the location of a diamond cross-over section of track) was also provided to facilitate the diversion of trains within the tunnel. This was achieved by installing a large pair of sliding doors, each leaf measuring 27m long by 6m high (162 sq m surface area) and weighing 30 tonnes which will provide 4 hour FRP separation between tracks. The cross-over door installed will be one of only two systems of its kind in the world, the other being in the Channel Tunnel, between the UK and France. The cross-over door is normally closed during usual operation hours, but in the unlikely event of an emergency or for routine maintenance, it can be remotely controlled from Tsuen Wan West Station which is located approximately 3.5km to the south of the crossover. The cross-over door operation is inter-locked with the automatic train operation systems to provide maximum safety, such that the door can only be in motion when the point device is locked and there are no trains on the track.

6 Introduction Combined services niches perpendicular to the line of the tunnel were also required. With respect to the rock mechanics for the temporary support and the permanent lining, the perpendicular niches were relatively straightforward with the niches designed with an arched roof, (typically of 7.5m span, up to 19m long). The major civil works, E & M works and tracklaying works are now substantially completed with overhead line energisation anticipated shortly. Schedule With the overcoming of all these challenges as well as the compliance of stringent requirements imposed in the job both technically and contractually, the contract is on schedule to be completed in line with KCRC's original programme of October 2003.

7 Drilling Jumpos working inside the tunnel.

8 The tunnel breaking-through in March 2001.

9 An interior view showing the completed tunnel lining and a service niches.

10 A ventilation gantry mounted with axial fans to provide fresh air supply for the tunnel interior.

11 A diamond cross-over track provided in the middle of the tunnel for emergency or routine maintenance of the train operation.

12 The 4-hour FRP (Fire Resistant Period) fire door located at the tunnel cross-over.

13 Forming the Southern Portal at Chai Wan Kok in early Note the highway flyover at the background, which was located within the alignment of the Tai Lam Tunnel where underpinning work was required.

14 Another view of the tunnel portal near the Chai Wan Kok interchange. The cut-and-cover tunnel in the background was also part of the contract packages for DB350.

15 Overview of the works at Chai Wan Kok with the portal provision and the trench for the cut-andcover tunnel in place.

16 The temporary ramp erected in the Southern Portal provided a two-way traffic for access into the tunnel during its construction.

17 Close up of the temporary access ramp leading into the portal.

18 The transfer beam that supported the pier of the highway bridge at the entrance of Tuen Mun Highway.

19 The portal arrangement at location where the tunnel cut underneath the Tuen Mun Highway.

20 A ventilation gantry being assembled inside the Southern Portal before launching into the tunnel interior.

21 Diversion and protection of the existing underground services at the Southern Portal at the early stage.

22 The ventilation building as seen in mid 2002 with the basic structure being completed.

23 An overall view of the cut-and-cover tunnel linking between the Southern Portal and the Tsuen Wan West Station.

24 An overall view of the traffic diversion arrangement for interchange at Chai Wan Kok. The road surface spanning over the cut-and-cover tunnel was a temporary deck supported on steel H-piles.

25 An aerial view of the DB350 cut-and-cover tunnel linking the Southern Portal and the Tsuen Wan West Station. On the left hand side of the photo there is another 300m section of approach tunnel (Contract CC-300 for Tsuen Wan West) to be constructed by another contractor.

26 Photo showing the work arrangement for the cut-and-cover tunnel for DB350. Far at the background of the photo was the work site for the Tsuen Wan West Station.

27 Overview of the cut-and-cover tunnel as seen from the Tsuen Wan By-pass.

28 Constructing of the tunnel cell at the formation level within the tunnel trench.

29 Detail of the formwork being used for the construction of the tunnel cell.

30 Typical cross-section of the twin-track and triple-track tunnel.

31 Flow Chart showing the underpinning operation for the pier support for Tuen Mun Highway at Chai Wan Kok

32 Animated photo showing the arrangement for the underpinning work and the layout of the transfer beam at the Southern Portal.

Member Nation Report 2010 from Denmark.

Member Nation Report 2010 from Denmark. Member Nation Report 2010 from Denmark. The has during the year 2010 arranged 6 member meetings including two technical site visits. The first technical site visit covered the 5.3 km long Leipzig City

More information

Safe & Sound Bridge Terminology

Safe & Sound Bridge Terminology Safe & Sound Bridge Terminology Abutment A retaining wall supporting the ends of a bridge, and, in general, retaining or supporting the approach embankment. Approach The part of the bridge that carries

More information

METHOD OF STATEMENT FOR STATIC LOADING TEST

METHOD OF STATEMENT FOR STATIC LOADING TEST Compression Test, METHOD OF STATEMENT FOR STATIC LOADING TEST Tension Test and Lateral Test According to the American Standards ASTM D1143 07, ASTM D3689 07, ASTM D3966 07 and Euro Codes EC7 Table of Contents

More information

53km. Deliver the New Era Network. Island Line Extension. will be added to our Hong Kong network. New Railway Projects are in progress

53km. Deliver the New Era Network. Island Line Extension. will be added to our Hong Kong network. New Railway Projects are in progress 53km will be added to our Hong Kong network Deliver the New Era Network 4 New Railway Projects are in progress Island Line Extension opened in December 2014 Executive Management s Report Hong Kong Network

More information

BRIDGES ARE relatively expensive but often are

BRIDGES ARE relatively expensive but often are Chapter 10 Bridges Chapter 10 Bridges Bridg Bridges -- usually the best, but most expensive drainage crossing structure. Protect bridges against scour. BRIDGES ARE relatively expensive but often are the

More information

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM

BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM BRIDGE RESTORATION AND LANDSLIDE CORRECTION USING STRUCTURAL PIER AND GRADE BEAM Swaminathan Srinivasan, P.E., M.ASCE H.C. Nutting/Terracon David Tomley, P.E., M.ASCE KZF Design Delivering Success for

More information

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

USE OF MICROPILES IN TEXAS BRIDGES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch USE OF MICROPILES IN TEXAS BRIDGES by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch DEFINITION OF A MICROPILE A micropile is a small diameter (typically less than 12 in.), drilled and

More information

Tunnelling & Underground. Specialists

Tunnelling & Underground. Specialists Tunnelling & Underground Specialists Mined Tunnels Excavation at Ayer Rajah Avenue, Singapore Introduction Amberg & TTI Engineering Pte Ltd (AETTI) was established in Singapore in 2002 by Amberg Engineering

More information

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL.

STRUCTURES. 1.1. Excavation and backfill for structures should conform to the topic EXCAVATION AND BACKFILL. STRUCTURES 1. General. Critical structures may impact the integrity of a flood control project in several manners such as the excavation for construction of the structure, the type of foundation, backfill

More information

Source: Port Mann Bridge Plans Unveiled Today, CBC News, February 4, 2009.

Source: Port Mann Bridge Plans Unveiled Today, CBC News, February 4, 2009. Total project cost $2.5 billion (Canadian) Financed by tolls about $3 each direction. Total project length 37 km (McGill St in Vancouver to 216 th in Langley) The new Port Mann bridge 10 lanes (existing

More information

IH-635 MANAGED LANES PROJECT, SEG. 3.2

IH-635 MANAGED LANES PROJECT, SEG. 3.2 IH-635 MANAGED LANES PROJECT, SEG. 3.2 Location: Dallas, Texas Owner: Texas Department of Transportation Client: Ferrovial Agroman Construction Cost: $1 Billion Construction Completion Date: December,

More information

Söderströmtunnel: immersion in downtown Stockholm, Sweden

Söderströmtunnel: immersion in downtown Stockholm, Sweden Söderströmtunnel: immersion in downtown Stockholm, Sweden J. Glückert Dipl.-Ing, Züblin Ground Engineering, Stuttgart, Germany N.H.J. Vink MSe, M. Reijm BSc, P.T. van Westendorp BSc Strukton Immersion

More information

REVEWED BY: Ross Rogien B.O/P.R. ADDITIONAL REVIEW(S) REQ.-FIRE DEPT Y/N

REVEWED BY: Ross Rogien B.O/P.R. ADDITIONAL REVIEW(S) REQ.-FIRE DEPT Y/N PLAN REVIEW FOR: PROJECT NAME: OWNER: ARCH/DESIGNER: ADDRESS: Ph/Fx: Plans Dated: E-mail: Sealed By: Estimated Project Cost - $ REVEWED BY: Ross Rogien B.O/P.R. ADDITIONAL REVIEW(S) REQ.-FIRE DEPT Y/N

More information

Legislative Council Panel on Transport Subcommittee on Matters Relating to Railways

Legislative Council Panel on Transport Subcommittee on Matters Relating to Railways Legislative Council Panel on Transport Subcommittee on Matters Relating to Railways CB(1)1354/13-14(01) Construction and Commissioning of the Hong Kong Section of the Guangzhou-Shenzhen-Hong Kong Express

More information

Brandangersundet Bridge A slender and light network arch

Brandangersundet Bridge A slender and light network arch Brandangersundet Bridge A slender and light network arch Rolf Magne Larssen Dr. ing./ Ph.D. Dr. ing A. Aas-Jakobsen AS Oslo, Norway rml@aaj.no Rolf Magne Larssen, born 1958, received his Ph.D. in structural

More information

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations

Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Up-Down Construction Utilizing Steel Sheet Piles and Drilled Shaft Foundations Nathan A. Ingraffea, P.E., S.E. Associate, KPFF Consulting Engineers, Portland, Oregon, USA Abstract The use of steel sheet

More information

Engineering Survey System for TBM (Tunnel Boring Machine) Tunnel Construction

Engineering Survey System for TBM (Tunnel Boring Machine) Tunnel Construction Engineering Survey System for TBM (Tunnel Boring Machine) Tunnel Construction, Hong Kong Key words: TBM, Tunnel Guidance System, Zigzag Traverse. SUMMARY For a TBM tunnel project, it is essential to establish

More information

Chaudière Crossing Bridge Rehabilitation

Chaudière Crossing Bridge Rehabilitation Chaudière Crossing Bridge Rehabilitation Douglas K. Lowry P. Eng., Armtec Infrastructure Incorporated David Delicate, P.Eng. Public Works and Government Services Canada (Retired) Prepared for presentation

More information

1,045 m length of the Deh Cho Bridge

1,045 m length of the Deh Cho Bridge Innovative Design Features: Lightweight truss: The principles of lightweight design led to a saving of 25% in the use of structural steel. State of the art deck system: Designed as a four-way slab, it

More information

4B-2. 2. The stiffness of the floor and roof diaphragms. 3. The relative flexural and shear stiffness of the shear walls and of connections.

4B-2. 2. The stiffness of the floor and roof diaphragms. 3. The relative flexural and shear stiffness of the shear walls and of connections. Shear Walls Buildings that use shear walls as the lateral force-resisting system can be designed to provide a safe, serviceable, and economical solution for wind and earthquake resistance. Shear walls

More information

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains

Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains Settlement of Precast Culverts Under High Fills; The Influence of Construction Sequence and Structural Effects of Longitudinal Strains Doug Jenkins 1, Chris Lawson 2 1 Interactive Design Services, 2 Reinforced

More information

Unit Price Averages Reports

Unit Price Averages Reports Unit Price Averages Reports 12/7/2015 UNIT PRICE AVERAGES REPORT Disclaimer The information provided in the following Unit Price Averages Report is only for the use of Alberta Infrastructure & Transportation

More information

The Follo Line Project

The Follo Line Project The Follo Line Project Longest. UrbAN. Complex. Faster. 2015/1 Norwegian National Rail Administration the follo line project 1 2 the follo line project The project The Follo Line Project is currently the

More information

DESIGN OF PRESTRESSED BARRIER CABLE SYSTEMS

DESIGN OF PRESTRESSED BARRIER CABLE SYSTEMS 8601 North Black Canyon Highway Suite 103 Phoenix, AZ 8501 For Professionals Engaged in Post-Tensioning Design Issue 14 December 004 DESIGN OF PRESTRESSED BARRIER CABLE SYSTEMS by James D. Rogers 1 1.0

More information

Step 11 Static Load Testing

Step 11 Static Load Testing Step 11 Static Load Testing Test loading is the most definitive method of determining load capacity of a pile. Testing a pile to failure provides valuable information to the design engineer and is recommended

More information

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation

Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Micropiles Reduce Costs and Schedule for Merchant RR Bridge Rehabilitation Jeff R. Hill, P.E. Hayward Baker Inc. 111 W. Port Plaza Drive Suite 600 St. Louis, MO 63146 314-542-3040 JRHill@HaywardBaker.com

More information

Elevating Your House. Introduction CHAPTER 5

Elevating Your House. Introduction CHAPTER 5 CHAPTER 5 Elevating Your House Introduction One of the most common retrofitting methods is elevating a house to a required or desired Flood Protection Elevation (FPE). When a house is properly elevated,

More information

There is no water, surface tension cracks, nor other environmental conditions present that reduce the stability of the excavation.

There is no water, surface tension cracks, nor other environmental conditions present that reduce the stability of the excavation. Part 1926 Subpart P Introduction The Occupational Safety and Health Administration (OSHA) issued its first Excavation and Trenching Standard in 1971 to protect workers from excavation hazards. Since then,

More information

Milan M5 metro extension the construction of Lotto station

Milan M5 metro extension the construction of Lotto station Milan M5 metro extension the construction of Lotto station Giuseppe LUNARDI, Rocksoil S.p.A., Italy giuseppe.lunardi@rocksoil.com Luca MANCINELLI, Rocksoil S.p.A., Italy, luca.mancinelli@rocksoil.com Massimiliano

More information

Reshaping the urban quality of Hong Kong Using the Mass Transit Railway Networks

Reshaping the urban quality of Hong Kong Using the Mass Transit Railway Networks Reshaping the urban quality of Hong Kong Using the Mass Transit Railway Networks Raymond wai-man, Wong Professor chi-ming, Tam City University of Hong Kong The background Before 2007, HK s railway networks

More information

EGYPTIAN CODES FOR DESIGN AND CONSTRUCTION OF BUILDINGS

EGYPTIAN CODES FOR DESIGN AND CONSTRUCTION OF BUILDINGS in the Euro-Mediterranean Area EGYPTIAN CODES FOR DESIGN AND CONSTRUCTION OF BUILDINGS By Prof. Amr Ezzat Salama Chairman of Housing, Building National Center Cairo, Egypt Former Minister of High Education

More information

Elevated Roads for Sri Lanka

Elevated Roads for Sri Lanka Elevated Roads for Sri Lanka M.T.R. Jayasinghe (Senior Professor, Structural Engineering, University of Moratuwa) Senior Professor M.T.R. Jayasinghe is a Professor of Structural Engineering, University

More information

Value Engineering vs. Alternate Designs in Bridge Bidding

Value Engineering vs. Alternate Designs in Bridge Bidding Value Engineering vs. Alternate Designs in Bridge Bidding Compares the advantages and disadvantages of alternate designs and value engineering in bidding of bridges as experienced in the State of Florida.

More information

Analysis of the Response Under Live Loads of Two New Cable Stayed Bridges Built in Mexico

Analysis of the Response Under Live Loads of Two New Cable Stayed Bridges Built in Mexico Analysis of the Response Under Live Loads of Two New Cable Stayed Bridges Built in Mexico Roberto Gómez, Raul Sánchez-García, J.A. Escobar and Luis M. Arenas-García Abstract In this paper we study the

More information

Types of Mining - Expert Table

Types of Mining - Expert Table See page 6 Minerals Downunder Teacher Guide (2002) - Activity 4a Types of Mining - Expert Table How to Jigsaw Information 1. Divide the class into Home Groups of five for the five different types of mining

More information

HIGH LEVEL SEISMIC UPGRADE COST ESTIMATE FOR CENTRE BLOCK, PARLIAMENT HILL

HIGH LEVEL SEISMIC UPGRADE COST ESTIMATE FOR CENTRE BLOCK, PARLIAMENT HILL HIGH LEVEL SEISMIC UPGRADE COST ESTIMATE FOR CENTRE BLOCK, PARLIAMENT HILL Prepared for: Public Works and Government Services Canada Parliamentary Precinct Branch Prepared by: Halsall Associates 210 Gladstone

More information

- 5 - Table1. Maximum Compartment Volumes

- 5 - Table1. Maximum Compartment Volumes - 5 - Part II - SPECIFIC REQUIREMENTS 5. Compartmentation 5.1 Every building should be divided into compartments by walls and floors to inhibit the spread of fire. 5.2 Compartment walls, compartment floors,

More information

WATERVIEW CONNECTION PROJECT. Ground Settlement WATERVIEW CONNECTION TEAM

WATERVIEW CONNECTION PROJECT. Ground Settlement WATERVIEW CONNECTION TEAM WATERVIEW CONNECTION PROJECT Ground Settlement WATERVIEW CONNECTION TEAM Settlement What is it? Settlement is the lowering of ground level caused by a volume change or movement within the soil Shrinking

More information

Geotechnical Building Works (GBW) Submission Requirements

Geotechnical Building Works (GBW) Submission Requirements Building Control (Amendment) Act 2012 and Regulations 2012: Geotechnical Building Works (GBW) Submission Requirements Building Engineering Group Building and Construction Authority May 2015 Content : 1.

More information

SECTION 02200 SUPPORT OF EXCAVATION

SECTION 02200 SUPPORT OF EXCAVATION SECTION 02200 PART 1 GENERAL 1.01 DESCRIPTION A. Section including specifications for design and installation of excavation support. B. Section also includes specifications for excavation support systems

More information

High Strain Dynamic Load Testing of Drilled Shafts

High Strain Dynamic Load Testing of Drilled Shafts Supplemental Technical Specification for High Strain Dynamic Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 3, 2015 1.0 GENERAL This work shall consist of performing high-strain

More information

Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC 2015 - October 27, 2015 Session 26

Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC 2015 - October 27, 2015 Session 26 2014 HDR Architecture, 2014 2014 HDR, HDR, Inc., all all rights reserved. Challenging Skew: Higgins Road Steel I-Girder Bridge over I-90 OTEC 2015 - October 27, 2015 Session 26 Brandon Chavel, PhD, P.E.,

More information

Heavy Metro Systems Light Rail Systems Automated Metros APMs Airport Link/City Shopping New & Retrofit Installations. w w w. platformscreendoors.

Heavy Metro Systems Light Rail Systems Automated Metros APMs Airport Link/City Shopping New & Retrofit Installations. w w w. platformscreendoors. R a i l V e h i c l e S y s t e m s P l a t f o r m S y s t e m s A p p l i c a t i o n s Heavy Metro Systems Light Rail Systems Automated Metros APMs Airport Link/City Shopping New & Retrofit Installations

More information

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS

SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS SHAFT CONSTRUCTION IN TORONTO USING SLURRY WALLS Vince Luongo Petrifond Foundation Co., Ltd. PROJECT DESCRIPTION The York Durham Sanitary System (YDSS) Interceptor in the Town of Richmond Hill located

More information

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona

1997 Uniform Administrative Code Amendment for Earthen Material and Straw Bale Structures Tucson/Pima County, Arizona for Earthen Material and Straw Bale Structures SECTION 70 - GENERAL "APPENDIX CHAPTER 7 - EARTHEN MATERIAL STRUCTURES 70. Purpose. The purpose of this chapter is to establish minimum standards of safety

More information

Lymon C. Reese & Associates LCR&A Consulting Services Tests of Piles Under Axial Load

Lymon C. Reese & Associates LCR&A Consulting Services Tests of Piles Under Axial Load Lymon C. Reese & Associates LCR&A Consulting Services Tests of Piles Under Axial Load Nature of Services The company has a long history of performance of tests of piles and pile groups under a variety

More information

TBM CROSSING OF STATIONS

TBM CROSSING OF STATIONS TBM CROSSING OF STATIONS Eng. Marco Barbanti Astaldi S.p.A. Eng. Tommaso Grosso Astaldi S.p.A. 18-11-2011 In the presence of groundwater the permeability of the ground is of great interest. It is important

More information

Forensic engineering of a bored pile wall

Forensic engineering of a bored pile wall NGM 2016 Reykjavik Proceedings of the 17 th Nordic Geotechnical Meeting Challenges in Nordic Geotechnic 25 th 28 th of May Forensic engineering of a bored pile wall Willem Robert de Bruin Geovita AS, Norway,

More information

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS

SUPPLEMENTAL TECHNICAL SPECIFICATIONS BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS July 14, 2015 1.0 GENERAL BI-DIRECTIONAL STATIC LOAD TESTING OF DRILLED SHAFTS This work shall consist of furnishing all materials, equipment, labor, and incidentals necessary for conducting bi-directional

More information

GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005

GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005 GUIDANCE NOTES FOR DEVELOPMENTS OR ENGINEERING WORKS IN THE VICINITY OF SPT SUBWAY INFRASTRUCTURE JULY 2005 CONTENTS 1.0 INTRODUCTION 2.0 OVERVIEW OF SPT APPROACH TO DEVEOPMENTS/WORKS IN THE VICINITY OF

More information

Buildings Construction Procurement Strategy

Buildings Construction Procurement Strategy Buildings Construction Procurement Strategy Graham Strickleton Site, Buildings and Power supplies Procurement Manager JOURNEE DEDIEE AUX INDUSTRIELS ET AUX MEMBRES DU RESEAU A.P.I Disclaimer: these slides

More information

Integrated Manhole Ladder System

Integrated Manhole Ladder System Application: This innovative product has been designed to provide safe access and egress to precast concrete manholes and inspection chambers. It can also be used within any other underground concrete

More information

Introduction to Minimal Excavation Foundations

Introduction to Minimal Excavation Foundations Introduction to Minimal Excavation Foundations What is a minimal excavation foundation? A construction technique that minimizes disturbance of the natural soil profile within the footprint of the structure

More information

Sector Design Concepts

Sector Design Concepts Section C Sector Design Concepts C7 Sector 7 Great North Road Underpass 6 6 6 C7. Existing situation Sector 7 refers to the cut and cover section of the project linking the northern end of the deep tunnels

More information

Project Portfolio. Tunnels & Shafts

Project Portfolio. Tunnels & Shafts Project Portfolio Tunnels & Shafts TUNNELS AND SHAFTS Southern Water Dover U.K. Foul water sewer interceptor tunnel, 1.6km long, turn key design and construct sub-contract using NATM technique value 1.1m

More information

A Solid Foundation Solution for Homeowners. from. Our products are made with 90% Recycled Material Down. Right. Solid. GREEN.

A Solid Foundation Solution for Homeowners. from. Our products are made with 90% Recycled Material Down. Right. Solid. GREEN. A Solid Foundation Solution for Homeowners from Our products are made with 90% Recycled Material Down. Right. Solid. GREEN. Stop the damaging effects of foundation settling... Sinking foundations, cracked

More information

Proceedings 2005 Rapid Excavation & Tunneling Conference, Seattle

Proceedings 2005 Rapid Excavation & Tunneling Conference, Seattle Proceedings 2005 Rapid Excavation & Tunneling Conference, Seattle EPB-TBM Face Support Control in the Metro do Porto Project, Portugal S. Babendererde, Babendererde Engineers LLC, Kent, WA; E. Hoek, Vancouver,

More information

Certification: Building Plans Examiner. Exam ID: B3

Certification: Building Plans Examiner. Exam ID: B3 Certification: Building Plans Examiner Exam ID: B3 Scope: A Building Plans Examiner will be responsible for reviewing submitted plans to determine if they meet the requirements of the various Building

More information

CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE

CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE CHAPTER 9 LONG TERM MONITORING AT THE ROUTE 351 BRIDGE 9.1 INTRODUCTION An important reason that composite piles have not gained wide acceptance in the civil engineering practice is the lack of a long

More information

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils

Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils Design, Testing and Automated Monitoring of ACIP Piles in Residual Soils Stephen W. Lacz 1, M. ASCE, P.E. and Richard C. Wells 2, F. ASCE, P.E. 1 Senior Professional, Trigon Kleinfelder, Inc., 313 Gallimore

More information

How To Build A Luxury Apartment Complex In London

How To Build A Luxury Apartment Complex In London Post Tensioning Awards 2009 Project Summary Type of structure Location Architects Structural Engineer Residential with leisure suites including Swimming pool, Cinema, Virtual Golf, Wine Cellars, and Parking

More information

Residential Deck Safety, Construction, and Repair

Residential Deck Safety, Construction, and Repair Juneau Permit Center, 4 th Floor Marine View Center, (907)586-0770 This handout is designed to help you build your deck to comply with the 2006 International Residential Building code as modified by the

More information

GOWANUS EXPRESSWAY TUNNEL PRIMER

GOWANUS EXPRESSWAY TUNNEL PRIMER GOWANUS EXPRESSWAY TUNNEL PRIMER T he New York State Department of Transportation is currently studying the replacement of the Gowanus Expressway with a tunnel. This investigation involves looking at a

More information

SECTION 1 GENERAL REQUIREMENTS

SECTION 1 GENERAL REQUIREMENTS Page 1 of 6 SECTION 1 GENERAL REQUIREMENTS 1. SCOPE OF WORK: The work to be performed under the provisions of these documents and the contract based thereon includes furnishing all labor, equipment, materials,

More information

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab,

DESIGN OF SLABS. 3) Based on support or boundary condition: Simply supported, Cantilever slab, DESIGN OF SLABS Dr. G. P. Chandradhara Professor of Civil Engineering S. J. College of Engineering Mysore 1. GENERAL A slab is a flat two dimensional planar structural element having thickness small compared

More information

LOAD TESTING OF SOME NEW BRIDGES IN LATVIA

LOAD TESTING OF SOME NEW BRIDGES IN LATVIA LOAD TESTING OF SOME NEW BRIDGES IN LATVIA Edmunds Akimovs, Civ.Eng., Bridge Engineer, Consulting Company Inzenierbuve, Address: Azenes st. 20, Riga, LV1048, Latvia. E-mail: eakimovs@inzenierbuve.lv Ainars

More information

Traffic Management During Construction

Traffic Management During Construction Traffic Management During Construction The construction of Dublin Port Tunnel couldn t begin until a traffic management plan had been developed and agreed to facilitate construction of the Tunnel and to

More information

STEP-BY-STEP. construction guide. Delivering better priced Conservatories, Sun Lounges and Garden Rooms via the Internet.

STEP-BY-STEP. construction guide. Delivering better priced Conservatories, Sun Lounges and Garden Rooms via the Internet. STEP-BY-STEP construction guide Delivering better priced Conservatories, Sun Lounges and Garden Rooms via the Internet. Welcome to our CONSERVATORY AND SUNROOM CONSTRUCTION GUIDE What is the specification

More information

Hanson Building Products. precast basement solutions

Hanson Building Products. precast basement solutions Hanson Building Products precast basement solutions Hanson Building Products Basement Systems Add an extra dimension and combine the inherent flexible, structural and waterproof properties of concrete

More information

Water Supplies Department Active WSD Capital Works Contracts

Water Supplies Department Active WSD Capital Works Contracts No. Title Active WSD Capital s Location of or Start 17/WSD/14 Improvement to waterworks facilities at Lantau South and Sha Tin Fuk Shing 42.600 16-Nov-15 Nov-18 Lantau South and mainlaying at Keung South

More information

Tunnelling and underground works in PPC hydro projects: Contracting practices & construction management Ioannis Thanopoulos Dr.

Tunnelling and underground works in PPC hydro projects: Contracting practices & construction management Ioannis Thanopoulos Dr. Tunnelling and underground works in PPC hydro projects: Contracting practices & construction management Ioannis Thanopoulos Dr. Civil Engineer Public Power Corporation, Greece Public Power Corporation

More information

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE

APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE APPLICATION PROCEDURES FOR PLACEMENT OF UNDERGROUND WATER AND SEWER PIPELINES IN THE VICINITY OF TRANSPORTATION FACILITIES UNDER THE JURISDICTION OF ALBERTA TRANSPORTATION 1.0 Application Procedures 2.0

More information

Emergency repair of Bridge B421

Emergency repair of Bridge B421 Emergency repair of Bridge B421 over the Olifants River after fl ood damage INTRODUCTION AND BACKGROUND Bridge B421 is located on the R555 at km 5.03 on Section 01E between Witbank (now known as emalahleni)

More information

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge.

Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. The Leading Edge. TM TM Engineered, Time-Tested Foundation Repairs for Settlement in Residential and Light Commercial Structures. SM The Leading Edge. 10 One Major Causes of foundation settlement or more conditions may

More information

Investigation of Foundation Failure. Step 1 - Data Collection. Investigation Steps

Investigation of Foundation Failure. Step 1 - Data Collection. Investigation Steps Foundations on Expansive Clay Soil Part 3 - Investigation of Failed Foundations Presented by: Eric Green, P.E. Structural Engineer Slide 1 Copyright Eric Green 2005 Investigation of Foundation Failure

More information

Scope of EN 1090-1 Clarification Document

Scope of EN 1090-1 Clarification Document Scope of EN 1090-1 Clarification Document This document has been submitted to the European Commission as the UK view on the scope of EN 1090-1. After discussions, including with the European Technical

More information

DESIGN OF SLABS. Department of Structures and Materials Engineering Faculty of Civil and Environmental Engineering University Tun Hussein Onn Malaysia

DESIGN OF SLABS. Department of Structures and Materials Engineering Faculty of Civil and Environmental Engineering University Tun Hussein Onn Malaysia DESIGN OF SLABS Department of Structures and Materials Engineering Faculty of Civil and Environmental Engineering University Tun Hussein Onn Malaysia Introduction Types of Slab Slabs are plate elements

More information

Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations

Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations Local Authority Building Control Technical Information Note 3 Driven and In-situ Piled Foundations Cambridge City Council - East Cambridgeshire District Council - Fenland District Council, Huntingdonshire

More information

PRECAST CONCRETE BOX CULVERTS

PRECAST CONCRETE BOX CULVERTS PRECAST CONCRETE BOX CULVERTS OUTLINE Introduction Applications Manufacturing Methods Design Procedures & Joints Installation Quality Summary INTRODUCTION Four-sided culverts are typically referred to

More information

CONDITION ASSESSMENT, REPAIR STRATEGY AND BUDGET ESTIMATE FOR OLP PIER 1 RMG YARD AREA

CONDITION ASSESSMENT, REPAIR STRATEGY AND BUDGET ESTIMATE FOR OLP PIER 1 RMG YARD AREA OLP Piraeus Port Authority S.A. Greece CONDITION ASSESSMENT, REPAIR STRATEGY AND BUDGET ESTIMATE FOR OLP PIER 1 RMG YARD AREA Draft Final Report December 2015 OLP Piraeus Port Authority S.A. Greece CONDITION

More information

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations

New construction Repairing failed or old foundations Retrofit foundations Permanent battered piers Machinery/equipment foundations from New construction foundations don t have to be a headache. The CHANCE Helical Pier Foundation System gives you the performance of concrete without the drawbacks and liabilities of driven piles and

More information

Optimum proportions for the design of suspension bridge

Optimum proportions for the design of suspension bridge Journal of Civil Engineering (IEB), 34 (1) (26) 1-14 Optimum proportions for the design of suspension bridge Tanvir Manzur and Alamgir Habib Department of Civil Engineering Bangladesh University of Engineering

More information

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe

TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe TECHNICAL NOTE Lining of Casings with SaniTite HP Pipe TN 5.18 October 2015 In sanitary sewer, it is often necessary to use trenchless technology methods to install a casing pipe under high volume roads,

More information

WORK SCOPE. Domains in which we work:

WORK SCOPE. Domains in which we work: WORK SCOPE Engineering consulting, technical office, assistance and supervision in industrial works. We specialize in structures, civil works and industrial equipment. Domains in which we work: Industrial

More information

Davit Systems and Outriggers

Davit Systems and Outriggers Safety From The Top Down Davit Systems and Outriggers Suspended Access Systems and Fall Protection Davits Overview Standards in the United States and Canada require a building to provide certified anchorages

More information

THE STAR, DARLING HOTEL AND SPA PYRMONT, NSW. Associate Director, Taylor Thomson Whitting Ltd, Sydney, Australia

THE STAR, DARLING HOTEL AND SPA PYRMONT, NSW. Associate Director, Taylor Thomson Whitting Ltd, Sydney, Australia THE STAR, DARLING HOTEL AND SPA PYRMONT, NSW H Nguyen BE (Hons), CPEng MIEAUST NPER Associate Director, Taylor Thomson Whitting Ltd, Sydney, Australia ABSTRACT The redevelopment at The Star in Sydney includes

More information

SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM

SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM Shepherd University Board of Governors June 9, 2005 Agenda Item No. 9 SCHEMATIC AND PROJECT BUDGET APPROVAL EAST CAMPUS NURSING EDUCATION AND CLASSROOM In 1994 construction began on the Byrd Science and

More information

11 Guardrail. W-Beam Guardrail Pre-Installation Inspection During Installation Basis for Use. Modified Guardrail. End Treatments and Transitions

11 Guardrail. W-Beam Guardrail Pre-Installation Inspection During Installation Basis for Use. Modified Guardrail. End Treatments and Transitions 11 Guardrail W-Beam Guardrail Pre-Installation Inspection During Installation Basis for Use Modified Guardrail End Treatments and Transitions Footings and Anchors Impact Attenuators Measurement and Payment

More information

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS

FUTURE SLAB. PENETRATIONS and. DEMOLITION of POST-TENSIONED FLOORS FUTURE SLAB PENETRATIONS and DEMOLITION of POST-TENSIONED FLOORS 1.0 INTRODUCTION Post-tensioned floor slabs in Australia and South East Asia are now universally regarded as the most cost effective form

More information

THE PROVISIONAL CENTRAL PRODUCT CLASSIFICATION

THE PROVISIONAL CENTRAL PRODUCT CLASSIFICATION THE PROVISIONAL CENTRAL PRODUCT CLASSIFICATION GROUP 867 ARCHITECTURAL, ENGINEERING AND OTHER TECHNICAL SERVICES Excerpt from CPCprov-en-Publication.doc - United Nation Statistic Division Group Class Subclass

More information

Chapter 4 SUBSURFACE INVESTIGATION GUIDELINES

Chapter 4 SUBSURFACE INVESTIGATION GUIDELINES Chapter 4 SUBSURFACE INVESTIGATION GUIDELINES Final SCDOT GEOTECHNICAL DESIGN MANUAL August 2008 Table of Contents Section Page 4.1 Introduction...4-1 4.2 Subsurface Investigation...4-2 4.2.1 Preliminary

More information

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI 318-14

Draft Table of Contents. Building Code Requirements for Structural Concrete and Commentary ACI 318-14 Draft Table of Contents Building Code Requirements for Structural Concrete and Commentary ACI 318-14 BUILDING CODE REQUIREMENTS FOR STRUCTURAL CONCRETE (ACI 318 14) Chapter 1 General 1.1 Scope of ACI 318

More information

SOME EXPERIENCE FROM THE SOFT GROUND TUNNELLING IN URBAN AREA

SOME EXPERIENCE FROM THE SOFT GROUND TUNNELLING IN URBAN AREA Seminar on The State-of-the-art Technology and Experience on Geotechnical Engineering in Korea and Hong Kong - 28 Mar 2008 2008 Geotechnical Division, The Hong Kong Institution of Engineers SOME EXPERIENCE

More information

High Capacity Helical Piles Limited Access Projects

High Capacity Helical Piles Limited Access Projects High Capacity Helical Piles Limited Access Projects Tel 403 228-1767 Canada, USA, Russia Brendan ODonoghue 519 830-6113 Presentation Summary 1. Helical piles Background on large diameter shafts and helices

More information

Texas Building Pros Foundation Repair Services

Texas Building Pros Foundation Repair Services Foundation Repair Services Lets get things back on the level Life is not about the work you put into your love, It s about the Love you put into your work. -Mother Theresa Why Choose Texas Building Pros:

More information

INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE.

INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE. INCREASE OF DURABILITY AND LIFETIME OF EXISTING BRIDGES. PIARC TC 4.4 EXPERIENCE. M.Sc. Gediminas Viršilas Head of Bridge Division, Lithuanian Road Administration Working group 2 of PIARC Technical Committee

More information

Virginia Approach Spans

Virginia Approach Spans Virginia Concrete Conference 2009 Woodrow Virginia Approach Spans David Tackoor, HNTB Formerly of URS Corp for Potomac Crossing Consultants Woodrow 1 Second Severn Crossing 2 Medway Crossing (Channel Tunnel

More information

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE

TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION SERIES 8000 PRECAST CONCRETE TECHNICAL SPECIFICATION PART 8000 - PRECAST CONCRETE TABLE OF CONTENTS Item Number Page 8100 PRECAST CONCRETE CONSTRUCTION - GENERAL 8-3 8101 General

More information

The Gotthard Base Tunnel

The Gotthard Base Tunnel The Gotthard Base Tunnel The tunnel On 11 December 2016, the Gotthard Base Tunnel will come into scheduled operation. At 57 kilometres in length, it is the longest rail tunnel in the world. It has virtually

More information