Infection Control Risk Assessment Process

Size: px
Start display at page:

Download "Infection Control Risk Assessment Process"

Transcription

1 Direction: Planning for health care facilities shall include, in addition to space and operational needs, provisions for infection control and protection of patients during any renovations or new construction. During the programming phase of a construction project, the owner shall provide an Infection Control Risk Assessment (ICRA). Infection Control During Construction: A Guide to Prevention and JCAHO Compliance; Chapter 5, Section 5.1 Definition: An ICRA is a documented process that focuses on reduction of risk from infection, permitting the organization to anticipate potential impacts. The AIA Guidelines, Chapter 1.5, divides the ICRA elements into three process areas: 1. Design 2. Construction 3. Mitigation Design - The design area requires "long-range planning" for new or renovated buildings. Considerations include: Number, Location, and Type of Isolation Rooms Location of Special Ventilation and Filtration Systems Air Handling Needs in Surgical Areas, Isolation Rooms, Laboratories, Exhaust Hoods for Hazardous Materials, Etc Water Systems and Treatments to Limit Legionella and Other Waterborne Pathogens Finishes and Surfaces to Prevent Mold & Bacteria Growth 1

2 Construction - The areas anticipated to be affected by construction shall receive consideration of the following: Impact of Disrupting Essential Services to Patients and Employees Determination of the Specific Hazards and Associated Protection Levels for Each Location of Patients and Definition of Risks to Each Impact of Planned and Unplanned Outages or Emergencies, Traffic flow, Cleanup, and Testing Location of Known Hazards Mitigation - The mitigation recommendations in the ICRA shall address the following: Patient Placement and Relocation Standards for Barriers Standards for Negative Pressure Provisions for Modification of Mechanical, Electrical, and Plumbing Systems Protection from Demolition Training of Hospital Staff, Visitors and Construction Personnel 2

3 Copy of Hospital Infection Control Policy ICRA: REQUIRED PREPARATORY ITEMS Available From Facility Infection Preventionist or Owner Representative Plan Review Review at Site Determine Risk Level Create Project Phasing Plans Identify Project Boundaries in Various Phases Determine Project Impacts to Mechanical, Electrical, and Plumbing Systems Anticipate Underslab Activities and Other Work Areas Outside of the Construction Space Determine Project Impacts to Life Safety Systems Create Detailed Schedule Including System Shutdowns Identify Adjacent Spaces and Patient Sensitivities, Include Potentially Affected Units Above, Below, Lateral Verify Locations for Temporary Barriers Verify Above Ceiling Conditions Verify Locations of Control Valves and HVAC Dampers Verify Phasing Perimeters and Required Wall / Barrier Ratings Types of Patients Are Materials For Patient Care Stored In The Area Are Patients Boarded In The Space Are Patient Procedures Performed In The Space What Is The Sensitivity Level Of The Patients In The Space Intensity of Project What is the Anticipated Amount Of Dust / Noise / Vibration What is the Duration of the Project What is the Potential for Moisture Damage or Exposure to Hazardous Materials 3

4 Types Of Patients: Group 1 No Clinical Activities Performed in This Area, No Clinical Equipment or Supplies, Area Completely Isolated from Patients Group 2 Patients Or Patient Care Workers Pass Through This Area Group 3 Patients Are Examined / Treated - Non-Invasive Procedures In This Area Group 4 Patients Are Boarded In This Location / Food Is Prepared In This Area / Clean Utility Storage Areas Group 5 Patients Undergo Invasive Procedures In This Location / Sterile Storage Areas / Patients with Potentially Compromised Immune Systems or Compromised Skin Are Boarded In This Area Types Of Activities: Limited Non-dust and non-vapor generating activities. Inspection activities that pose little to no risk of liberating molds or bacteria. The entire is away from patient, staff and public areas Minimal The activity has a very small potential to generate dust or vapors. No reasonable anticipation for accessing potentially water damage materials or liberating mold or bacteria. Non-dust generating above ceiling activities. No demolition. Small The activity includes the potential for a minor, controllable amount of dust and vapors. Small scale sanding, minor cutting of walls, minimal storage of material or chemicals, limited demolition. Moderate The project includes a higher amount of dust and vapors, demolition of fixed components, sanding, removal of finishes and dust generating above ceiling work. Major The project includes a large amount of dust and vapor potential, major demolition or renovation. 4

5 ICRA Risk Class Matrix Group 1 Group 2 Group 3 Group 4 Group 5 Limited I I II II II Minimal I I II III III Small II II III III IV Moderate III III III III IV Major III III III IV IV CLASS I PROJECT CONTROLS 1. Appropriate signage in place 2. Vacuum work area at end of work day 3. Remove trash daily in covered / sealed containers 4. Keep Unused Doors Closed 5. Do not liberate Asbestos or Lead containing substances. CLASS II PROJECT CONTROLS 1. Appropriate signage in place. 2. Vacuum work area at end of work day. 3. Keep all doors or barriers to work area closed. 4. Remove trash daily in covered / sealed containers. 5. Non-HEPA vacuums prohibited. 6. HEPA vacuum or damp mop outside of work areas daily. 7. Prevent dust migration via shoe tracking. 8. Mist surfaces while cutting, carpet prior to removal. 9. Flush water lines prior to reuse for projects > 48hrs. 10. Maintain as dry an environment as possible. Report any water leaks that occur to walls or structure. 11. Protect HVAC from construction dust. 12. Clean / disinfect surfaces following work. 13. Do not liberate Asbestos or Lead containing substances. 5

6 CLASS III PROJECT CONTROLS ( In Addition to Class II Controls) 1. Review procedures with Infection Prevention and Control. Documented exceptions permitted. Infection Control signature required. 2. Seal all penetrations to prevent dust migration, including openings in wall cavities and air gaps at base of existing walls. 3. Airtight barriers required. Poly barriers, > 6 mil, fire retardant permitted for projects < 5 days. Rigid barriers for projects > 5 days or in high traffic areas. Mobile containment units permitted. 4. Negatively pressurize work area. HEPA filters required for exhaust within 25 feet of patients or staff. 5. Isolate HVAC System in work area. 6. ICRA measures to remain in place until all dust generating activities are complete and work areas cleaned and disinfected. 7. Provide daily documented inspection for ICRA Compliance. CLASS IV PROJECT CONTROLS ( In Addition to Class II and III Controls) 1. All workers required to wear CLEAN protective coveralls, shoe covers and surgical caps when traversing occupied areas. 2. Utilize anteroom for donning /doffing required PPE, where feasible. 3. No exceptions to negative pressure requirement. 4. No exception to HEPA filtered exhaust. 5. Tape and seal any trash bin covers prior to transport across occupied areas. 6. Wipe with disinfectant all tools, equipment; including, trash bin exteriors, prior to transport across occupied areas. 6

Infection Control Risk Assessment Matrix of Precautions for Construction & Renovation

Infection Control Risk Assessment Matrix of Precautions for Construction & Renovation Infection Control Risk Assessment Matrix of Precautions for Construction & Renovation Step One: Using the following table, identify the Type of Construction Project Activity (Type A-D) TYPE A TYPE B TYPE

More information

Infection Control Risk Assessment Matrix of Precautions for Construction & Renovation

Infection Control Risk Assessment Matrix of Precautions for Construction & Renovation Infection Control Risk Assessment Matrix of Precautions for Construction & Renovation Step One: Using the following table, identify the Type of Construction Project Activity (Type A-D) TYPE A TYPE B TYPE

More information

Infection Control Risk Assessment : the Infection Preventionist s Role in Construction

Infection Control Risk Assessment : the Infection Preventionist s Role in Construction Infection Control Risk Assessment : the Infection Preventionist s Role in Construction Key Concepts Use of ICRA is an important element in an infection prevention program Should be an integral part of

More information

STATEMENT OF WORK (SOW) 2. Contract Title. HEPA Supply/Exhaust fans for Clean room USP 797 Compliance

STATEMENT OF WORK (SOW) 2. Contract Title. HEPA Supply/Exhaust fans for Clean room USP 797 Compliance 1. Contracting Officer s Representative (COR). STATEMENT OF WORK (SOW) Name: Oscar Garcia Section: Engineering Address: 3350 La Jolla Village Dr. 92161 Phone Number: Fax Number: E-Mail Address: Oscar.garcia2@va.gov

More information

CSA Z317-13-12 Infection Control during Construction, Renovation and Maintenance of Health Care Facilities Overview and Case Studies

CSA Z317-13-12 Infection Control during Construction, Renovation and Maintenance of Health Care Facilities Overview and Case Studies CSA Z317-13-12 Infection Control during Construction, Renovation and Maintenance of Health Care Facilities Overview and Case Studies Grant Rogers, BSc. Principal 1 North West Environmental Group Industrial

More information

ASBESTOS SCIENCE TECHNOLOGIES, INC.

ASBESTOS SCIENCE TECHNOLOGIES, INC. ASBESTOS SCIENCE TECHNOLOGIES, INC. P.O. Box 505 Bangor, CA 95914 Phone (530) 518-0934 Email - astinc17@yahoo.com Report for Lincoln Elementary School 1582 Lincoln Road Yuba City, Ca. 95993 Mold Report

More information

UAMS Representative: The person who is most directly responsible for aspects on location where renovation and construction will occur.

UAMS Representative: The person who is most directly responsible for aspects on location where renovation and construction will occur. UAMS ADMINISTRATIVE GUIDE NUMBER: 11.2.08 DATE: 5/21/2002 REVISION: 10/03/2005, 09/18/2008, 10/05/2011, 07/10/2013 PAGE: 1 of 15 SECTION: CAMPUS OPERATIONS AREA: GENERAL SUBJECT: INTERIM LIFE SAFETY MEASURES

More information

Presented by Harlan Nelson 952-237-4644 Harlan.nelson@comcast.net

Presented by Harlan Nelson 952-237-4644 Harlan.nelson@comcast.net Construction Risk Assessment Presented by Harlan Nelson 952-237-4644 Harlan.nelson@comcast.net Statistics to Consider Hospital acquired infections Over 100,000 deaths per year Majority are failure to comply

More information

How to Estimate the Cost of a. Laboratory Renovation. Candidate Number: 0714144

How to Estimate the Cost of a. Laboratory Renovation. Candidate Number: 0714144 How to Estimate the Cost of a Laboratory Renovation Candidate Number: 0714144 December 15, 2014 1 Table of Contents Cover Page Page 1 Table of Contents Page 2 Introduction Page 3 Types & Methods of Measurements

More information

Guidelines for Mold Remediation (Removal)

Guidelines for Mold Remediation (Removal) Guidelines for Mold Remediation (Removal) Indoor mold growth, water damage, or musty odors should be addressed quickly. Removing mold growth and correcting the underlying cause of water accumulation can

More information

DESERT RESEARCH INSTITUTE MOLD ASSESSMENT AND REMEDIATEION PROCEDURE

DESERT RESEARCH INSTITUTE MOLD ASSESSMENT AND REMEDIATEION PROCEDURE 1.0 Introduction DESERT RESEARCH INSTITUTE This Desert Research Institute (DRI) Mold Assessment and Remediation Procedure was established to assure that consistent and uniform information is provided to

More information

HEPA-filtered Negative Air Machines and their Role in Creating Airborne Infection Isolation Rooms with the ECU AnteRoom. Frequently Asked Questions

HEPA-filtered Negative Air Machines and their Role in Creating Airborne Infection Isolation Rooms with the ECU AnteRoom. Frequently Asked Questions HEPA-filtered Negative Air Machines and their Role in Creating Airborne Infection Isolation Rooms with the ECU AnteRoom Frequently Asked Questions What is a negative air machine and why do I need one?

More information

Core & Shell Construction. Rules and Regulations

Core & Shell Construction. Rules and Regulations Core & Shell Construction Rules and Regulations 1. Protection: During the construction Contractor shall endeavor to protect all areas of work from damage caused by workers, weather or equipment. 2. Permits

More information

Safety Policy Manual Policy No. 112

Safety Policy Manual Policy No. 112 Policy: Mold Prevention, Assessment and Remediation Program Page 1 of 9 APPLICATION NYU Langone Medical Center (NYULMC) POLICY SUMMARY NYULMC is committed to protecting employees, patients, and visitors

More information

Clean Water: Supply side potable water, not wastewater. Gray Water/Sewage: Wastewater originating from a drain (sink, toilet, urinal).

Clean Water: Supply side potable water, not wastewater. Gray Water/Sewage: Wastewater originating from a drain (sink, toilet, urinal). Procedures for Emergency Responses to Flooding and Building Water Intrusion PURPOSE: To establish uniform, sanitary, and systematic procedures for responding to flooding and water intrusion emergencies.

More information

Re: Addendum to Preliminary Water Damage Report, Mendocino Public Health Branch, 1120 South Dora Street, Ukiah, CA

Re: Addendum to Preliminary Water Damage Report, Mendocino Public Health Branch, 1120 South Dora Street, Ukiah, CA IAS 960 Ms. Kristin McMenomey Risk Manager County of Mendocino 841 Low Gap Road Ukiah, CA 95482 Re: Addendum to Preliminary Water Damage Report, Mendocino Public Health Branch, 1120 South Dora Street,

More information

Asbestos Work Permit Procedures

Asbestos Work Permit Procedures These procedures are to be followed by all persons required to perform the following work: Handling, installation or removal of non-friable manufactured products known to contain asbestos provided no sanding,

More information

Laboratory Biosafety Level 3 Criteria

Laboratory Biosafety Level 3 Criteria Laboratory Biosafety Level 3 Criteria Biosafety in Microbiological and Biomedical Laboratories (BMBL) 5th Edition Section IV Biosafety Level 3 (BSL-3): Biosafety Level 3 is applicable to clinical, diagnostic,

More information

Mould Mould A Basic Guide

Mould Mould A Basic Guide Mould A Basic Guide Summary Mould is a fact of life. Moulds will grow practically everywhere people live and work. Mould is recognized as an occupational hazard for indoor workers as well as outdoor workers

More information

British Columbia Institute of Technology. BCIT Safety Manual ASBESTOS MANAGEMENT

British Columbia Institute of Technology. BCIT Safety Manual ASBESTOS MANAGEMENT BCIT Safety Manual Contents 1. Purpose... 3 2. Definitions... 3 2.1 Asbestos... 3 2.2 Asbestos Containing Material (ACM)... 3 2.3 Friable Material... 3 2.4 Low Risk Work Activity... 3 2.5 Moderate Risk

More information

Procedures for Cutting and Handling of Asbestos Cement Pipe. City of Richmond Public Works Operations

Procedures for Cutting and Handling of Asbestos Cement Pipe. City of Richmond Public Works Operations Procedures for Cutting and Handling of Asbestos Cement Pipe City of Richmond Public Works Operations Version 2.0 Updates to: November 1995 Procedures Prepared by: AMEC Earth & Environmental a division

More information

UNIVERSITY OF TOLEDO

UNIVERSITY OF TOLEDO UNIVERSITY OF TOLEDO SUBJECT: INTERIM LIFE SAFETY MEASURES AND INFECTION Procedure No: LS-08-008 CONTROL PROCEDURE STATEMENT Interim life safety and infection control measures will be implemented to protect

More information

Oakland Unified San Jose Unified Stanford University Santa Ana Unified Newhall Unified Clovis Unified Merced Union High School Grossmont Union High

Oakland Unified San Jose Unified Stanford University Santa Ana Unified Newhall Unified Clovis Unified Merced Union High School Grossmont Union High Oakland Unified San Jose Unified Stanford University Santa Ana Unified Newhall Unified Clovis Unified Merced Union High School Grossmont Union High School District Industry Standards Damage Assessments

More information

Radford University. Indoor Air Quality Management Plan

Radford University. Indoor Air Quality Management Plan Radford University Indoor Air Quality Management Plan Spring 2015 Introduction Concerns with Indoor Air Quality (IAQ) have increased since energy conservation measures were instituted in office buildings

More information

PI s Name Date Bldg./Rm# CDC Biosafety Level 3 (BSL-3)

PI s Name Date Bldg./Rm# CDC Biosafety Level 3 (BSL-3) PI s Name Date Bldg./Rm# CDC Biosafety Level 3 (BSL-3) Yes No 1. Is access to the laboratory limited or restricted at the discretion of the laboratory director when experiments are in progress? Yes No

More information

Mold Remediation in Occupied Homes

Mold Remediation in Occupied Homes building science.com 2008 Building Science Press All rights of reproduction in any form reserved. Mold Remediation in Occupied Homes Research Report - 0210 January-2002 Joseph Lstiburek, Terry Brennan

More information

NYU Safety Policy Manual

NYU Safety Policy Manual NYU Safety Policy Manual Page 1 of 6 Subject: Mold Prevention, Assessment, and Remediation Program Policy No. 167 ISSUE DATE REPLACES ORIGINATOR APPLICATION NYU Washington Square Campus PURPOSE The purpose

More information

DUST AND DEBRIS MANAGEMENT PROCEDURES HPD HOUSING REHABILITATION PROGRAMS

DUST AND DEBRIS MANAGEMENT PROCEDURES HPD HOUSING REHABILITATION PROGRAMS DUST AND DEBRIS MANAGEMENT PROCEDURES HPD HOUSING REHABILITATION PROGRAMS Dust and Debris Management Procedures refers to preventive measures that shall be undertaken by the contractor to prevent exposure

More information

Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Material

Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Material Asbestos in the Workplace: A Guide to Removal of Friable Asbestos Containing Material Revised November 21, 2013 Application Code of Practice Where asbestos is present or believed to be present in a workplace

More information

ASBESTOS MANAGEMENT PROGRAM

ASBESTOS MANAGEMENT PROGRAM ASBESTOS MANAGEMENT PROGRAM Prepared By: Triumvirate Environmental Program Approval Developed: August 2011 Updated: June 2015 Associate Vice President of Public Safety & Administrative Services Date Associate

More information

Section # Medical Advisory Committee Charlton Campus West 5th Campus King Campus

Section # Medical Advisory Committee Charlton Campus West 5th Campus King Campus Hamilton Hospitals Infection Prevention & Control Effective at Hamilton Health Sciences, St. Joseph s Healthcare (This is a Hamilton Region Infection Control policy and procedure.) St. Joseph s Healthcare

More information

CONTROL METHODS. There are five ways to control the release of asbestos fibers:

CONTROL METHODS. There are five ways to control the release of asbestos fibers: Control Methods CONTROL METHODS When asbestos containing materials are found in a building, the owner must decide which method or methods will be used to deal with the asbestos. The decision will be based

More information

Controlling Condensation On CWP Insulation BY ED LIGHT, MEMBER ASHRAE; JAMES BAILEY, P.E., MEMBER ASHRAE; AND ROGER GAY

Controlling Condensation On CWP Insulation BY ED LIGHT, MEMBER ASHRAE; JAMES BAILEY, P.E., MEMBER ASHRAE; AND ROGER GAY This article was published in ASHRAE Journal, Decemeber 2014. Copyright 2014 ASHRAE. Posted at www.ashrae.org. This article may not be copied and/or distributed electronically or in paper form without

More information

Biosafety Level 2 Criteria

Biosafety Level 2 Criteria Biosafety Level 2 Criteria Biosafety in Microbiological and Biomedical Laboratories (BMBL) 5th Edition Biosafety Level 2 (BSL-2): Biosafety Level 2 builds upon BSL-1. BSL-2 is suitable for work involving

More information

Construction Drawings and Terminology for the Infection Prevention Professional. Objectives. Disclaimer

Construction Drawings and Terminology for the Infection Prevention Professional. Objectives. Disclaimer Construction Drawings and Terminology for the Infection Prevention Professional APIC Greater St. Louis Chapter 073 October 2012 Objectives Define the terms and descriptions of airborne engineering controls

More information

Gramercy Place Condo Association, Inc.

Gramercy Place Condo Association, Inc. Gramercy Place Condo Association, Inc. UNIT MODIFICATION REQUEST Date of Application: Name of Owner (s): Telephone: (Home) (Cell) E-Mail: Anticipated start date: Anticipated ending date: Permission is

More information

Specifications for Removal and Replacement of Water Damaged/Mold Impacted Materials

Specifications for Removal and Replacement of Water Damaged/Mold Impacted Materials Specifications for Removal and Replacement of Water Damaged/Mold Impacted Materials Park Potomac Place 12500 Park Potomac Avenue Potomac, Maryland 20854 KEM Project # 21703 Prepared for: Park Potomac Place

More information

Sprayed vermiculite ceiling coating management plan, Condell Park High School, Condell Park, NSW

Sprayed vermiculite ceiling coating management plan, Condell Park High School, Condell Park, NSW Sprayed vermiculite ceiling coating management plan, Condell Park High School, Condell Park, NSW August 2006 NSW Department of Commerce Parsons Brinckerhoff Australia Pty Limited ACN 078 004 798 and Parsons

More information

How To Prevent And Manage A Flood And Mold

How To Prevent And Manage A Flood And Mold Flood Response and Mold Prevention Program Prepared by the Berea College Department of Environmental Health and Safety Revised May 2010 Contents I. Introduction II. III. IV. Flood and Mold Hazards Roles

More information

Lead Exposure Management Plan

Lead Exposure Management Plan Lead Exposure Management Plan 1.0. Policy CSUF has developed the Lead Exposure Management Plan to reduce occupational and environmental exposure to lead, a potent neurotoxin and carcinogen that causes

More information

University of Nevada, Reno Facilities Services Department STANDARD OPERATING PROCEDURE. Facilities Maintenance Services

University of Nevada, Reno Facilities Services Department STANDARD OPERATING PROCEDURE. Facilities Maintenance Services University of Nevada, Reno Facilities Services Department STANDARD OPERATING PROCEDURE Facilities Maintenance Services Indoor Flood Cleanup and Mold Prevention DATE: 6/24/15 REVISED: PURPOSE This University

More information

STANDARD OPERATING PROCEDURES FOR MOLD REMEDIATION

STANDARD OPERATING PROCEDURES FOR MOLD REMEDIATION West Virginia University Environmental Health and Safety STANDARD OPERATING PROCEDURES FOR MOLD REMEDIATION Origination Date August 2013. Contents Purpose:... 2 Job Scope... 2 Definitions... 2 Roles/Responsibilities:...

More information

Mold Response and Remediation Plan

Mold Response and Remediation Plan 1.0 Policy Statement The University of New Haven has developed a mold response and remediation plan in accordance with best practices set forth by the Environmental Protection Agency (EPA), Occupational

More information

Case Studies. Disaster Recovery Restoration Remediation Decontamination 800.808.1553 www.rolyncompanies.com

Case Studies. Disaster Recovery Restoration Remediation Decontamination 800.808.1553 www.rolyncompanies.com Case Studies 800.808.1553 www.rolyncompanies.com Property Type: College Loss Type: Water and Flood Location: Hyattsville, Maryland Once Rolyn received clearance from the insurance adjuster, crews began

More information

MOLD RESPONSE AND REMEDIATION PLAN

MOLD RESPONSE AND REMEDIATION PLAN MOLD RESPONSE AND REMEDIATION PLAN Prepared By: Triumvirate Environmental Developed: April 2011 Last Revised: March 2015 Program Approval Associate Vice President of Public Safety & Administrative Services

More information

Construction Indoor Air Quality Management Plans for LEED. Matt Gregg, PE, LEED AP

Construction Indoor Air Quality Management Plans for LEED. Matt Gregg, PE, LEED AP Construction Indoor Air Quality Management Plans for LEED Matt Gregg, PE, LEED AP Agenda What is a Construction IAQ Management Plan? What are the LEED Requirements? What is the Mechanical Contractor s

More information

Biosafety Level 2 (BSL-2) Safety Guidelines

Biosafety Level 2 (BSL-2) Safety Guidelines BLS-4 Biosafety Level 2 (BSL-2) Safety Guidelines BSL-3 BSL-2 BSL-1 BSL-2 builds upon BSL-1. If you work in a lab that is designated a BSL-2, the microbes used pose moderate hazards to laboratory staff

More information

Nick s Inspection Services

Nick s Inspection Services Nick s Inspection Services 909 Shorthorn Grain Valley Mo. 64029 Phone: 816-355-0368 Cell: 816-225-5783 Email: nicksinspections@att.net Building Inspection Report and Protocol Inspection Date: 08-20-14

More information

The following standard practices, safety equipment, and facility requirements apply to BSL-1:

The following standard practices, safety equipment, and facility requirements apply to BSL-1: Section IV Laboratory Biosafety Level Criteria The essential elements of the four biosafety levels for activities involving infectious microorganisms and laboratory animals are summarized in Table 1 of

More information

Summary of Georgia s Lead-Based Paint (LBP) Renovation, Repair and Painting (RRP) Rules For Contractors, Property Managers, and Maintenance Personnel

Summary of Georgia s Lead-Based Paint (LBP) Renovation, Repair and Painting (RRP) Rules For Contractors, Property Managers, and Maintenance Personnel Second Edition Revised January 2014 Summary of Georgia s Lead-Based Paint (LBP) Renovation, Repair and Painting (RRP) Rules For Contractors, Property Managers, and Maintenance Personnel Summary of Requirements

More information

Preparing the Work Area

Preparing the Work Area Preparing the Work Area Work Area Preparation Objectives of Work Area Prep Sequence and Methods for Prep Engineering Controls: Negative Pressure Requirements, Equipment and Set-up Purpose of Area Prep

More information

Now that Your Building Experienced Water Damage What Must You and Your Water Damage Restoration Contractor Agree On?

Now that Your Building Experienced Water Damage What Must You and Your Water Damage Restoration Contractor Agree On? w that Your Building Experienced Water Damage What Must You and Your Water Damage Restoration Contractor Agree On? By Completing a Building and Occupant Survey Hopefully Your Questions will be Answered

More information

SMACNA s IAQ for Occupied Buildings Under Construction

SMACNA s IAQ for Occupied Buildings Under Construction 16 th Annual Technical Conference Rocky Mountain Section AIHA/ASSE September 29. 2010 SMACNA s IAQ for Occupied Buildings Under Construction Bill Mele Indoor Environmental Solutions, Inc. 303-948-0500,

More information

Water should be removed as soon as possible once the safety of the structure has been verified.

Water should be removed as soon as possible once the safety of the structure has been verified. FACT SHEET Posted October 18 2005 Check List for Infection Control Concerns when Reopening Healthcare Facilities Closed due to Extensive Water and Wind Damage Prior to opening a healthcare facility that

More information

ASBESTOS IN ROOFING SYSTEMS WORK PRACTICES AND DISPOSAL IN ASSOCIATION WITH ROOFING PROJECTS

ASBESTOS IN ROOFING SYSTEMS WORK PRACTICES AND DISPOSAL IN ASSOCIATION WITH ROOFING PROJECTS ASBESTOS IN ROOFING SYSTEMS WORK PRACTICES AND DISPOSAL IN ASSOCIATION WITH ROOFING PROJECTS 1.0 GENERAL 1.1 SUMMARY A. The following procedures apply to the project manual and drawings for asbestos in

More information

Before You Start an Energy Efficiency Retrofit The Building Envelope

Before You Start an Energy Efficiency Retrofit The Building Envelope ABOUT YOUR HOUSE Before You Start an Energy Efficiency Retrofit The Building Envelope The building envelope is the outer layer of the building that separates the indoor living space from the outdoor environment,

More information

Moisture Management. Infection Prevention and Corporate Safety. Contents. Posttest... 12

Moisture Management. Infection Prevention and Corporate Safety. Contents. Posttest... 12 Moisture Management Infection Prevention and Corporate Safety This self-directed learning module contains information you are expected to know to protect yourself, our patients, and our guests. Target

More information

Biological Safety Program

Biological Safety Program Risk Management & Safety Main Office, Wyoming Hall Phone: (307) 766-3277 Fax: (307)766-6116 Regulated Materials Management Center Phone: (307)766-3696 Fax: (307)766-3699 Web: www.uwyo.edu/ehs Email: UWEHS@uwyo.edu

More information

AORN Recommended Practices. AORN Practices. RPs Related to Environmental Services. Joan Blanchard, RN, MSS, CNOR, CIC September 10, 2008

AORN Recommended Practices. AORN Practices. RPs Related to Environmental Services. Joan Blanchard, RN, MSS, CNOR, CIC September 10, 2008 AORN Recommended Practices Joan Blanchard, RN, MSS, CNOR, CIC September 10, 2008 AORN Practices AORN Recommended Practices are AORN s official position on aseptic technique and technical practices. This

More information

BUILDING DYNAMICS, LLC

BUILDING DYNAMICS, LLC BUILDING DYNAMICS, LLC www.building-dynamics.com INDUSTRIAL HYGIENE 1216 Ashton Road Ashton, MD 20861 240.899.6926 (mobile) elight@building-dynamics.com HVAC ENGINEERING 703.963.0824 (mobile) jbailey@building-dynamics.com

More information

CERTIFIED LEAD-BASED PAINT RENOVATION CONTRACTOR. License Requirements & Work Practice Standards

CERTIFIED LEAD-BASED PAINT RENOVATION CONTRACTOR. License Requirements & Work Practice Standards CERTIFIED LEAD-BASED PAINT RENOVATION CONTRACTOR License Requirements & Work Practice Standards License Required By April 22, 2010, construction contractors that perform renovation on certain older buildings

More information

MOLD INSPECTION REPORT. UCD Anschutz Medical Campus Building 402 12474 E. 19 th Ave. Aurora, CO 80045

MOLD INSPECTION REPORT. UCD Anschutz Medical Campus Building 402 12474 E. 19 th Ave. Aurora, CO 80045 MOLD INSPECTION REPORT For the Subject Property: UCD Anschutz Medical Campus Building 402 12474 E. 19 th Ave. Aurora, CO 80045 Report Date: August 7, 2015 Inspection/Testing Date: August 1, 2015 SET Project:

More information

Questions & Answers (Q & A) Regarding Asbestos Treatment with the Fire Suppression and Renovation Project

Questions & Answers (Q & A) Regarding Asbestos Treatment with the Fire Suppression and Renovation Project Questions & Answers (Q & A) Regarding Asbestos Treatment with the Fire Suppression and Renovation Project The Watergate Community is currently in the process with the fire suppression and interior renovations

More information

EVERYONE'S RESPONSIBILITY

EVERYONE'S RESPONSIBILITY EVERYONE'S RESPONSIBILITY Guidelines for an Asbestos Operations and Maintenance Program February 2007 Guidelines for an Asbestos Operations and Maintenance Program Workplace Safety & Health Division 200

More information

Building and Grounds Maintenance Checklist

Building and Grounds Maintenance Checklist Building and Grounds Maintenance Checklist Name: School: Room or Area: Date Completed: Signature: Instructions 1. Read the IAQ Backgrounder and the Background Information for this checklist. 2. Keep the

More information

Specification. Indoor Air Quality Management

Specification. Indoor Air Quality Management GREENGUARD Environmental Institute 2211 Newmarket Parkway, Suite 110 Marietta, GA 30067 1.800.427.9681 Specification Indoor Air Quality Management This Master Specification section is intended for use

More information

MOLD REMEDIATION PROCEDURES

MOLD REMEDIATION PROCEDURES Page: 1 of 5 1.0 PROGRAM OBJECTIVE The purpose of this procedure is to define the responsibilities, methods, procedures and training required to safely and effectively remove or clean mold-contaminated

More information

Facilities Operations Customer Service Standards WORK ORDER PRIORITIES

Facilities Operations Customer Service Standards WORK ORDER PRIORITIES Facilities Operations Customer Service Standards WORK ORDER PRIORITIES In order to provide fair and consistent maintenance service to all University faculty, staff and students, a work priority system

More information

MOLD RELATED SERVICES LICENSING PROGRAM RULES WORKSHOP AGENDA

MOLD RELATED SERVICES LICENSING PROGRAM RULES WORKSHOP AGENDA Division of Professions Mold Related Services 1940 North Monroe Street Tallahassee, Florida 32399-2214 Phone: 850.717.1984 Fax: 850.922.2918 Ken Lawson, Secretary Rick Scott, Governor MOLD RELATED SERVICES

More information

Biosafety Guidelines. 5. Pipetting Mechanical pipetting devices must be available and used. Mouth pipetting is prohibited.

Biosafety Guidelines. 5. Pipetting Mechanical pipetting devices must be available and used. Mouth pipetting is prohibited. Biosafety Guidelines Biosafety Level 1 Laboratory Biosafety Level 1 is suitable for work involving well-characterized agents not known to consistently cause disease in immunocompetent adult humans, and

More information

State of Illinois Illinois Department of Public Health OUT. Homeowner s Lead-based Paint Abatement Guide

State of Illinois Illinois Department of Public Health OUT. Homeowner s Lead-based Paint Abatement Guide State of Illinois Illinois Department of Public Health GET THE LEAD OUT Homeowner s Lead-based Paint Abatement Guide HOMEOwNER S LEAD-bASED PAINT AbATEMENT GUIDE ILLINOIS DEPARTMENT OF PUbLIC HEALTH Lead-based

More information

Stachybotrys chartarum a mold that may be found in water-damaged homes

Stachybotrys chartarum a mold that may be found in water-damaged homes Stachybotrys chartarum a mold that may be found in water-damaged homes November 2000 Environmental Health Investigations Branch California Department of Health Services Stachybotrys chartarum ecology Stachybotrys

More information

Prestige Home Inspection LLC

Prestige Home Inspection LLC Cover Page Prestige Home Inspection LLC IAC2/ESA - Mold Assessment and Water Damage Report 555 W. Brook ave., Client's town MI, 48059 Inspection prepared for: Client's name Inspection Date: 10/15/2012

More information

IWU PHYSICAL PLANT SAFETY PROGRAM. Toxic and Hazardous Substances, Title 29 Code of Federal Regulations (CFR) Part 1910.1001, Subpart Z Asbestos

IWU PHYSICAL PLANT SAFETY PROGRAM. Toxic and Hazardous Substances, Title 29 Code of Federal Regulations (CFR) Part 1910.1001, Subpart Z Asbestos STANDARDS Toxic and Hazardous Substances, Title 29 Code of Federal Regulations (CFR) Part 1910.1001, Subpart Z Asbestos 1. INTRODUCTION IWU has a responsibility to provide a safe environment for students,

More information

UNIVERSITY OF TOLEDO

UNIVERSITY OF TOLEDO UNIVERSITY OF TOLEDO SUBJECT: MOLD PREVENTION AND REMEDIATION Procedure No: HM-08-035 PROCEDURE STATEMENT All indoor areas on campus are expected to present no immediate threat to the health and well-being

More information

IUB Water Damage Restoration Guideline

IUB Water Damage Restoration Guideline IUB Water Damage Restoration Guideline Purpose The IUB Water Damage Restoration guideline was developed to ensure that all water intrusions are handled in a professional manner which includes the latest

More information

Indoor Air Quality Issues for Hotels

Indoor Air Quality Issues for Hotels Indoor Air Quality Issues for Hotels Chai chen Chao DEA 670 Spring, 2000 Thermal Control Relative Humidity Winter Temperature Summer Temperature 30% 68.5 F - 76.0 F 74.0 F - 80.0 F 40% 68.5 F - 75.5 F

More information

Guidelines for Cleaning Staff on Managing Mould Growth in State Buildings

Guidelines for Cleaning Staff on Managing Mould Growth in State Buildings Guidelines for Cleaning Staff on Managing Mould Growth in State Buildings Prepared by the State Claims Agency 2 Index 1. Background 2. What are moulds? 3. What are the possible health effects? 4. How do

More information

Environmental Asthma Triggers Kit

Environmental Asthma Triggers Kit Environmental Asthma Triggers Kit Overview This is an activity used to demonstrate environmental asthma triggers and solutions 1-on-1 or with small audiences in the home or clinical environment. Learning

More information

ASBESTOS CONTROL PLAN

ASBESTOS CONTROL PLAN ASBESTOS CONTROL PLAN POLICY It is the long term plan of Emily Carr University to have an asbestos free workplace. In the interim, The University plans to manage asbestos hazards based on prioritization

More information

WATER DAMAGE INVESTIGATION. Massachusetts Gaming Commission 101 Federal Street Boston, Massachusetts

WATER DAMAGE INVESTIGATION. Massachusetts Gaming Commission 101 Federal Street Boston, Massachusetts WATER DAMAGE INVESTIGATION Massachusetts Gaming Commission 101 Federal Street Boston, Massachusetts Prepared by: Massachusetts Department of Public Health Bureau of Environmental Health Indoor Air Quality

More information

Chemical Fume Hoods. Environmental Health and Safety 974-5084

Chemical Fume Hoods. Environmental Health and Safety 974-5084 Chemical Fume Hoods Environmental Health and Safety 974-5084 Regulatory References Prudent Practices in the Laboratory 2011 (National Research Council of The National Academies): Laboratory chemical hoods

More information

Procedures for the Effective Use of Biological Safety Cabinets

Procedures for the Effective Use of Biological Safety Cabinets Procedures for the Effective Use of Biological Safety Cabinets APPROVAL DATE BY BIOHAZARDS SUBCOMMITTEE: August 10, 2012 SUPERSEDES: March 1, 2012 This corporate guideline/procedure is intended as a minimum

More information

BUILDING ASSESSMENT QUESTIONNAIRE. B. TENANTS Is there more than one tenant in the building? YES

BUILDING ASSESSMENT QUESTIONNAIRE. B. TENANTS Is there more than one tenant in the building? YES Department of Health and Human Services, Division of Public Health Occupational and Environmental Epidemiology Branch 1912 Mail Service Center, Raleigh, North Carolina 27699-1912 BUILDING ASSESSMENT QUESTIONNAIRE

More information

INDOOR AIR QUALITY ASSESSMENT MOLD INVESTIGATION. Department Of Children and Family 810 Memorial Drive Cambridge, Massachusetts

INDOOR AIR QUALITY ASSESSMENT MOLD INVESTIGATION. Department Of Children and Family 810 Memorial Drive Cambridge, Massachusetts INDOOR AIR QUALITY ASSESSMENT MOLD INVESTIGATION Department Of Children and Family 810 Memorial Drive Cambridge, Massachusetts Prepared by: Massachusetts Department of Public Health Bureau of Environmental

More information

Part 2. Overview. Risk management. Workplace health and safety legislation. How should asbestos exposure be managed? Identifying asbestos hazards

Part 2. Overview. Risk management. Workplace health and safety legislation. How should asbestos exposure be managed? Identifying asbestos hazards Part 2. Overview Risk management Workplace health and safety legislation How should asbestos exposure be managed? identify hazards assess risk decide on control measures implement control measures monitor

More information

CENTER FOR ENVIRONMENTAL HEALTH Emergency Response/Indoor Air Quality Program

CENTER FOR ENVIRONMENTAL HEALTH Emergency Response/Indoor Air Quality Program CENTER FOR ENVIRONMENTAL HEALTH Emergency Response/Indoor Air Quality Program Guidance Concerning Remediation and Prevention of Mold Growth and Water Damage in Public Schools/Buildings to Maintain Air

More information

Old Dominion University Mold Management Plan

Old Dominion University Mold Management Plan OFFICE OF ENVIRONMENTAL HEALTH AND SAFETY 5255 Hampton Blvd. Spong Hall, suite 2501 Norfolk, Virginia 23529 Phone: (757) 683-4495 Fax: (757) 683-6025 Occupational Safety & Health Environmental Health Laboratory

More information

A SELF-EVALUATION CHECKLIST of BEST PRACTICES for AUTO REFINISH SHOPS and SCHOOLS

A SELF-EVALUATION CHECKLIST of BEST PRACTICES for AUTO REFINISH SHOPS and SCHOOLS A of BEST PRACTICES for AUTO REFINISH SHOPS and SCHOOLS www.epa.gov/dfe/pubs/projects/auto/ WHAT IS THE DESIGN FOR THE ENVIRONMENT (DFE) AUTO REFINISH PROJECT? The DfE Program has been working with the

More information

Asbestos. from the Home. Removing. Read this booklet for:

Asbestos. from the Home. Removing. Read this booklet for: Removing Asbestos from the Home Read this booklet for: steps and care you should take if your home has asbestos-containing material (ACM) advice about protective gear. How to get ACM removed from your

More information

How To Manage A Bsl 4 Laboratory

How To Manage A Bsl 4 Laboratory Section IV Laboratory Biosafety Level Criteria The essential elements of the four biosafety levels for activities involving infectious microorganisms and laboratory animals are summarized in Table 2 of

More information

NDSU TABLE OF CONTENTS

NDSU TABLE OF CONTENTS NDSU TABLE OF CONTENTS 1.0 INTRODUCTION 2.0 DEFINITIONS AND DESCRIPTIONS 3.0 OPERATIONS AND MAINTENANCE PROCEDURES FOR ACM 4.0 FIBER RELEASE EPISODES 5.0 DEMOLITION INFORMATION 6.0 REMARKS 1.0 INTRODUCTION

More information

Asbestos WHAT TO DO? Studies of people who were exposed to high levels of asbestos in factories and shipyards, are at increased risk of:

Asbestos WHAT TO DO? Studies of people who were exposed to high levels of asbestos in factories and shipyards, are at increased risk of: Asbestos WHAT TO DO? What Is Asbestos? Asbestos is mineral fiber. It can be positively identified only with a special type of microscope. There are several types of asbestos fibers. In the past, asbestos

More information

Foundation. Foundation

Foundation. Foundation Moisture Aside from structural concerns, the most important consideration for foundation design is moisture. No client wants a wet basement. No client wants a damp basement. No client wants mold in their

More information

UBC Plant Operations Asbestos Work Procedures April 2004

UBC Plant Operations Asbestos Work Procedures April 2004 UBC Plant Operations Asbestos Work Procedures April 2004 These Procedures are for use by UBC Plant Operations, Utilities, Housing & Conferences, and IT Services only and are not intended for use by other

More information

Appendix J IBC Biohazard Spill Management Plan

Appendix J IBC Biohazard Spill Management Plan OVERVIEW Prevention is the most important part of any spill management plan. Be sure to read and understand standard operating procedures (SOP s) and protocols for safe manipulation of biohazards before

More information

Mold Investigation Summary Report

Mold Investigation Summary Report Gold Health and Safety Consulting, Inc. 4001 Inglewood Ave., Suite 101-292, Redondo Beach, CA 90278 (310) 219-1955 (310) 219-1934 - Fax SUBJECT PROPERTY LOCATED AT: 4405 Tomorrowland Ave., Disneyland,

More information

APPENDIX B. EPA s Investigating, Evaluating, and Remediating Moisture and Mold Problems (see EPA website for complete details)

APPENDIX B. EPA s Investigating, Evaluating, and Remediating Moisture and Mold Problems (see EPA website for complete details) APPENDIX B. EPA s Investigating, Evaluating, and Remediating Moisture and Mold Problems (see EPA website for complete details) Table 1: Water Damage - Cleanup and Mold Prevention Table 1 presents strategies

More information

Quality Assurance Calendar Laundry and Housekeeping Responsible Party Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Quality Assurance Calendar Laundry and Housekeeping Responsible Party Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Laundry Cleaning agent review and approval Appropriate chemical disinfection with low temperature wash cycles Laundry water temperature Laundry chemical dispensing Wash water ph Lint trap cleaning Equipment

More information

DRYER VENTING SPECIFICATIONS DRYER SAFETY

DRYER VENTING SPECIFICATIONS DRYER SAFETY DRYER VENTING SPECIFICATIONS Table of Contents DRYER SAFETY...1 INSTALLATION REQUIREMENTS...4 Venting Requirements...5 DRYER INSPECTION AND CLEANING...7 Frequency of Exhaust System Cleaning...7 Inspecting

More information