Critical Path Analysis
|
|
- Virgil Walton
- 7 years ago
- Views:
Transcription
1 Critical Path Analysis
2 There are no pre-requisites for this Achievement Standard so it can be placed in any course. No knowledge is pre-supposed.
3 Methods include a selection from those related to: precedence tables network diagrams critical events scheduling float times
4 Critical Path Analysis (CPA) A complex project must be well planned, especially if a number of people are involved. CPA is used to ensure that the complete scheme is completed in the minimum time. It is used to schedule the projects.
5 So what is a project? Any activity can be represented as a project: planning a party building a house/factory planning a conference
6 What do the projects have in common? Each project can be broken down into tasks. Each task takes time and uses resources. Tasks are structured
7 Step 1 Precedence table To identify actual tasks that make up a project To identify the order these tasks need to be in To decide how long each task will take
8 Example: Constructing a garage Task Duration (days) A prepare foundations 7 B Make and position door frame C Lay drains, floor base and screed 15 D Install services and fittings 8 E Erect walls 1 F Plaster ceiling G Erect roof 5 H Install door and windows 8 I Fit gutters and pipes J Paint outside 3
9 Some of these activities must be completed before others can start. Task Duration (days) A prepare foundations 7 B Make and position door frame C Lay drains, floor base and screed 15 D Install services and fittings 8 E Erect walls 1 F Plaster ceiling G Erect roof 5 H Install door and windows 8 I Fit gutters and pipes J Paint outside 3
10 You can t erect the roof (G) before you have erected the walls (E) Task Duration (days) A prepare foundations 7 B Make and position door frame C Lay drains, floor base and screed 15 D Install services and fittings 8 E Erect walls 1 F Plaster ceiling G Erect roof 5 H Install door and windows 8 I Fit gutters and pipes J Paint outside 3
11 Precedence
12 D must follow E Task Duration (days) A prepare foundations 7 B Make and position door frame C Lay drains, floor base and screed 15 D Install services and fittings 8 E E Erect walls 1 F Plaster ceiling G Erect roof 5 H Install door and windows 8 I Fit gutters and pipes J Paint outside 3
13 E must follow A and B Task Duration (days) A prepare foundations 7 B Make and position door frame C Lay drains, floor base and screed 15 D Install services and fittings 8 E E Erect walls 1 A, B F Plaster ceiling G Erect roof 5 H Install door and windows 8 I Fit gutters and pipes J Paint outside 3
14 F must follow D and G Task Duration (days) A prepare foundations 7 B Make and position door frame C Lay drains, floor base and screed 15 D Install services and fittings 8 E E Erect walls 1 A, B F Plaster ceiling D, G G Erect roof 5 H Install door and windows 8 I Fit gutters and pipes J Paint outside 3
15 G must follow E Task Duration (days) A prepare foundations 7 B Make and position door frame C Lay drains, floor base and screed 15 D Install services and fittings 8 E E Erect walls 1 A, B F Plaster ceiling D, G G Erect roof 5 E H Install door and windows 8 I Fit gutters and pipes J Paint outside 3
16 H must follow G Task Duration (days) A prepare foundations 7 B Make and position door frame C Lay drains, floor base and screed 15 D Install services and fittings 8 E E Erect walls 1 A, B F Plaster ceiling D, G G Erect roof 5 E H Install door and windows 8 G I Fit gutters and pipes J Paint outside 3
17 I must follow C, F Task Duration (days) A prepare foundations 7 B Make and position door frame C Lay drains, floor base and screed 15 D Install services and fittings 8 E E Erect walls 1 A, B F Plaster ceiling D, G G Erect roof 5 E H Install door and windows 8 G I Fit gutters and pipes C, F J Paint outside 3
18 J must follow H and I Task Duration (days) A prepare foundations 7 B Make and position door frame C Lay drains, floor base and screed 15 D Install services and fittings 8 E E Erect walls 1 A, B F Plaster ceiling D, G G Erect roof 5 E H Install door and windows 8 G I Fit gutters and pipes C, F J Paint outside 3 I
19 We call this a precedence table Task Duration (days) A prepare foundations 7 B Make and position door frame C Lay drains, floor base and screed 15 Precedence D Install services and fittings 8 E E Erect walls 1 A, B F Plaster ceiling D, G G Erect roof 5 E H Install door and windows 8 G I Fit gutters and pipes C, F J Paint outside 3 I
20 Precedence diagrams are not that useful. A useful visual representation of a project is a network diagram.
21 Sequence the most common sequences / dependencies Task A Task B Task B depends upon Task A; B cannot start until A is finished Task A Task A Task B Task B Task C Task C Tasks B and C depend on Task A; neither can start until A is finished, but B and C are independent of each other Task C depends upon Task A and B; C cannot start until both A and B are finished
22 more unusual links and relationships so far all links have been finish-start links... Task A 3 days Task B Task B depends upon Task A, but with a 3 day delay; B cannot start until 3 days after A is finished Task A Task C The start of Task C depends on the start of Task A; this is a start-to-start link; it may also incorporate a delay Task A Task C The finish of Task C depends upon the finish of Task A
23 Drawing a NETWORK how do we get here?
24 Algorithm
25 Draw in the links Task A B C D E F G H I J Precedence E A, B D, G E G C, F I
26 Draw in A, B, C on a rough diagram
27 STEP 1- original vertices with no arcs STEP - delete all arcs incident on A, B, C and redraw as shown STEP 3 - repeat iteration
28
29 STEP 1- original vertices with no arcs STEP - delete all arcs incident on E and redraw as shown STEP 3 - repeat iteration
30
31 STEP 1- original vertices with no arcs STEP - delete all arcs incident on D, G and redraw as shown STEP 3 - repeat iteration
32
33 STEP 1- original vertices with no arcs STEP - delete all arcs incident on F and H and redraw as shown STEP 3 - repeat iteration
34
35 STEP 1- original vertices with no arcs STEP - delete all arcs incident on I and redraw as shown STEP 3 - STOP
36
37 Converting to a usable diagram
38 Proposed method Now draw the network diagram using boxes early start time duration early finish time task number and/or name late start time float late finish time slack
39 Example 15 Task C Duration Task I 7 Task A 1 Task E 8 Task D Task F 3 Task J Task B 5 Task G 8 Task H Finish
40 Critical Path Find the earliest possible start for each activity, by going forwards through the network. Secondly, the latest possible start time for each activity is found by going backwards through the network. Activities which have equal earliest and latest start time are on the critical path.
41 Practice Task Task 3 5 Task 7 3 Task 1 6 Task 4 3 Task 5 1 Task 9 Task 6 Task 8
42 Practice Task Task 3 3 Task 1 6 Task 4 3 Task 5 5 Task 7 1 Task 9 Task 6 Task 8
43 Practice Task Task 3 5 Task Task 1 6 Task 4 3 Task 5 1 Task 9 Task 6 Task 8
44 Practice Task 3 Task Task Task 4 3 Task 5 5 Task 7 1 Task 9 3 Task 6 Task 8
45 Practice Task 3 Task Task Task 4 3 Task 5 5 Task 7 1 Task Task 6 Task 8
46 Practice Task 7 3 Task Task Task Task 5 5 Task 7 1 Task Task 6 5 Task 8
47 Practice Task Task Task Task Task 5 5 Task 7 1 Task Task Task 8
48 3 4 7 Task Practice Task 3 Take the largest value 3 3 Task Task Task Task 7 1 Task Task Task 8
49 Practice Task Task Task Task Task Task 7 1 Task Task Task 8
50 3 4 7 Task Practice Task 3 Take the largest value 3 3 Task Task Task Task 7 1 Task Task Task 8
51 Forward pass complete Task Task Task Task Task Task Task 9 3 Task Task 8 Duration = 18
52 Backward pass Task Task Task Task Task Task Task Task Task 8
53 3 4 7 Task Task Task Task Task Task Task Task Task 8 Float
54 3 4 7 Task Task Task Task Task Task Task Task Task 8 17
55 3 4 7 Task Task Task Task Task Task Task Task Task
56 3 3 Task Task Task Task Task Task Task Task Task
57 Forward pass complete Take the smallest 3 3 Task Task Task Task Task Task Task Task Task
58 Critical Path float = 3 3 Task Task Task Task Task Task Task Task Task
59 Your turn 15 Task C Task I 7 Task A 1 Task E 8 Task D Task F 3 Task J Task B 5 Task G 8 Task H Finish
60 Example 1 Forward pass 15 Task C Task I 7 Task A 1 Task E 8 Task D Task F 3 Task J Task B 5 Task G 8 Task H Finish
61 Example 1 Forward pass Task C Task I 7 7 Task A 1 Task E 8 Task D Task F 3 Task J Task B 5 Task G 8 Task H Finish
62 Example 1 Take the largest value Task C? Task I 7 7 Task A 7 1 Task E 8 Task D Task F 3 Task J Task B 5 Task G 8 Task H Finish
63 Example 1 Take the largest value Task C? Task I 7 7 Task A Task E 17 8 Task D Task F 3 Task J Task B 17 5 Task G 8 Task H Finish
64 Example 1 Take the largest value Task C? Task I 7 7 Task A Task E Task D Task F 3 Task J Task B 17 5 Task G 8 Task H Finish
65 Example 1 Take the largest value Task C? Task I 7 7 Task A Task E Task D 5 Task F 3 Task J Task B 17 5 Task G 8 Task H Finish
66 Example 1 Minimum Task C 7 9 Task I 7 7 Task A Task E Task D 5 7 Task F Task J Task B 17 5 Task G 8 3 Task H 3 Finish
67 Example 1 Backward pass Task C 7 9 Task I 7 7 Task A Task E Task D 5 7 Task F Task J Task B 17 5 Task G 8 3 Task H Finish 3 3
68 Example 1 Take lowest value Task C 7 9 Task I 7 7 Task A Task E Task D 5 7 Task F Task J 9 3 Task B 17 5 Task G 8 3 Task H Finish 3
69 Example 1 Take lowest value Task C 7 9 Task I Task A Task E Task D 5 7 Task F Task J 9 3 Task B 17 5 Task G 8 3 Task H Finish 3
70 Example 1 Take lowest value Task C 7 9 Task I Task A Task E Task D 5 7 Task F Task J 9 3 Task B 17 5 Task G 8 3 Task H Finish 3
71 Example 1 Take lowest value Task C 7 9 Task I Task A Task E Task D Task F Task J 9 3 Task B 17 5 Task G Task H Finish 3
72 Example 1 Take lowest value Task C 7 9 Task I Task A Task E Task D Task F Task J 9 3 Task B 17 5 Task G Task H Finish 3
73 Example 1 Take lowest value Task C Task I Task A Task E Task D Task F Task J 9 3 Task B Task G Task H Finish 3
74 Example 1 Critical Path zero float Task C Task I Task A Task E Task D Task F Task J 9 3 Task B Task G Task H Finish 3
75 Example 1 Critical Path A-E-D-F-I-J Task C Task I Task A Task E Task D Task F Task J 9 3 Task B Task G Task H Finish 3
76 Using the outputs Gantt Charts optimising the schedule
77 Gantt: Critical path in red
78 Gantt: Critical path in red
79 Scheduling: Move the critical path along the top
80 Now fit the other activities like a puzzle
81 Now fit the other activities like a puzzle
82 Schedule
83 Any delay on the critical path causes a delay in the entire project
84 There is a -day float on the non-critical path
85 Definitions Critical Path Those activities that can not over run without effecting the total length of the project, are those where the EST = LFT (Total float = ). Total Float LFT of the activity- the duration- EST of the activity. This shows how much slack there is on a particular route of the network. If the total float is then an activity lies on the critical path. Free Float EST of the next activity Duration EST of this activity. This shows the slack on an individual activity before it delays the start of the next activity.
86 EES = Earliest early start time LLF = latest late finish time Free float: The amount of time that a schedule activity can be delayed without delaying the early start date of any immediately following schedule activities. Free Float = EES successor EF
87 EES = Earliest early start time LLF = latest late finish time Independent float is that portion of the total float within which an activity can be delayed for start without affecting the float of the preceding activities. Independent Float = EES successor -LLF predecessor -duration
technical tips and tricks
technical tips and tricks Performing critical path analysis Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the
More information12 CRITICAL PATH ANALYSIS
1 RTL PT NLYSS hapter 1 ritical Path nalysis Objectives fter studying this chapter you should be able to construct activity networks; be able to find earliest and latest starting times; be able to identify
More informationEdExcel Decision Mathematics 1
EdExcel Decision Mathematics 1 Notes and Examples Critical Path Analysis Section 1: Activity networks These notes contain subsections on Drawing an activity network Using dummy activities Analysing the
More informationGoals of the Unit. spm - 2014 adolfo villafiorita - introduction to software project management
Project Scheduling Goals of the Unit Making the WBS into a schedule Understanding dependencies between activities Learning the Critical Path technique Learning how to level resources!2 Initiate Plan Execute
More informationLeaving Certificate Technology. Project Management. Student Workbook
Leaving Certificate Technology Project Management Student Workbook Project Management Student notes Introduction Project management is the name given to a number of techniques used in industry to manage
More informationProject Scheduling: PERT/CPM
Project Scheduling: PERT/CPM Project Scheduling with Known Activity Times (as in exercises 1, 2, 3 and 5 in the handout) and considering Time-Cost Trade-Offs (as in exercises 4 and 6 in the handout). This
More informationChapter-6. Developing a Project Plan
MGMT 4135 Project Management Chapter-6 Where we are now Developing the Project Network Why? Graphical representation of the tasks to be completed Logical sequence of activities Determines dependencies
More informationLeaving Certificate Technology. Project Management. Teacher Notes
Leaving Certificate Technology Project Management Teacher Notes 1 Project Management This is the first of three key topics that form Project and Quality Management in the Technology Syllabus core. These
More informationNetwork Planning and Analysis
46 Network Planning and Analysis 1. Objective: What can you tell me about the project? When will the project finish? How long will the project take (project total duration)? 2. Why is this topic Important
More informationGuidance on Critical Path Analysis
Guidance on Critical Path Analysis OCR GCE in Applied Business Unit F248 (Unit 9): Strategic Decision Making As part of the assessment for Unit F248 Strategic Decision-Making the examination may contain
More informationProgrammes. Unit 3: P lanning construction work processes and efficient use of resources in construction and the built environment.
Unit : P lanning construction work processes and efficient use of resources in construction and the. Links This topic links to: HNC in Construction and the Built Environment Unit : LO; HNC Unit 15: LO.
More informationProject Planning and Scheduling
Project Planning and Scheduling MFS606 Project Planning Preliminary Coordination Detailed Task Description Objectives Budgeting Scheduling Project Status Monitoring When, What, Who Project Termination
More information5. Creating a Gantt Chart
5. Creating a Gantt Chart Whilst the network diagram is a useful way to describe how tasks are linked to each other, the Gantt chart is used to display the schedule of a project. The Gantt chart is the
More informationA. O. Odior Department of Production Engineering University of Benin, Edo State. E-mail: waddnis@yahoo.com
2012 Cenresin Publications www.cenresinpub.org APPLICATION OF PROJECT MANAGEMENT TECHNIQUES IN A CONSTRUCTION FIRM Department of Production Engineering University of Benin, Edo State. E-mail: waddnis@yahoo.com
More informationME 407 Mechanical Engineering Design Spring 2016
ME 407 Mechanical Engineering Design Spring 2016 Project Planning & Management Asst. Prof. Dr. Ulaş Yaman Acknowledgements to Dieter, Engineering Design, 4 th edition Ullman, The Mechanical Design Process,
More informationProject Time Management
Project Time Management Plan Schedule Management is the process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.
More informationProject and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi
Project and Production Management Prof. Arun Kanda Department of Mechanical Engineering Indian Institute of Technology, Delhi Lecture - 9 Basic Scheduling with A-O-A Networks Today we are going to be talking
More informationA GUIDE TO NETWORK ANALYSIS by MICHAEL C GLEN
Introduction A GUIDE TO NETWORK ANALYSIS by MICHAEL C GLEN The core technique available to Project Managers for planning and controlling their projects is Network Analysis. This short guide will provide
More informationB. 2-4-6 D. 3-4-5 E. 3-5-7 F. 5-7-9
Lesson 01 Project Management Solutions #1: The network diagram for a project is shown below, with three time estimates (optimistic, most likely, and pessimistic) for each activity. Activity times are in
More informationCRITICAL PATH METHOD (CEE 320 VDC SEMINAR)
CRITICAL PATH METHOD (CEE 320 VDC SEMINAR) 4 February 2009 Jesse Santiago & Desirae Magallon Overview Background & History CPM Defined The CPM approach Definitions Class Exercise Background & History Developed
More informationOperational Research. Project Menagement Method by CPM/ PERT
Operational Research Project Menagement Method by CPM/ PERT Project definition A project is a series of activities directed to accomplishment of a desired objective. Plan your work first..then work your
More informationCritical Path Analysis
Chapter 13 Critical Path Analysis Basic Concepts Activity An activity is any portion of a project which consumes time or resources and has a definable beginning and ending. For example, laying of pipe
More informationPrecedence Diagram Method. CSTM 462 Planning & Scheduling
Precedence Diagram Method CSTM 462 Planning & Scheduling Precedence Diagramming Method (PDM) PDM is more flexible than AON or AOA networks because PDM allows the overlapping of concurrent activities.
More informationScheduling Glossary Activity. A component of work performed during the course of a project.
Scheduling Glossary Activity. A component of work performed during the course of a project. Activity Attributes. Multiple attributes associated with each schedule activity that can be included within the
More informationLecture 26 CPM / PERT Network Diagram
Lecture 26 CPM / PERT Network Diagram 26.1 Introduction to CPM / PERT Techniques CPM (Critical Path Method) was developed by Walker to solve project scheduling problems. PERT (Project Evaluation and Review
More informationTest Fragen + Antworten. October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003
Test Fragen + Antworten October 2004 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 1 All the following Statements about a WBS are true except that it a. Provides a framework for
More informationCambridge International AS and A Level Computer Science
Topic support guide Cambridge International AS and A Level Computer Science 9608 For examination from 2017 Topic 4.4.3 Project management PERT and GANTT charts Cambridge International Examinations retains
More informationONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS
ONLINE SUPPLEMENTAL BAPPENDIX PROJECT SCHEDULES WITH PERT/CPM CHARTS Chapter 3 of Systems Analysis and Design in a Changing World explains the techniques and steps required to build a project schedule
More informationProject Management. Week 4- Project Planning and Network Diagrams 2012-13
Project Management Week 4- Project Planning and Network Diagrams 2012-13 Last Week Project Appraisal Techniques Scoping Tools-Breakdown Structures Estimation This Week What is Planning? Purpose of Planning
More informationTest Fragen. October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003
Test Fragen October 2003 Project Management Wilhelm F. Neuhäuser IBM Corporation 2003 Question 7 Which term describes a modification of a logical relationship that delays a successor task? a. Lag b. Lead
More informationCritical Path Method (CPM)
Project Management Templates (CPM) http://spreadsheetml.com/projectmanagement/criticalpathanalysis.shtml Copyright (c) 2009-2010, ConnectCode All Rights Reserved. ConnectCode accepts no responsibility
More informationUse project management tools
Use project management tools Overview Using project management tools play a large role in all phases of a project - in planning, implementation, and evaluation. This resource will give you a basic understanding
More informationProject Scheduling: PERT/CPM
Project Scheduling: PERT/CPM CHAPTER 8 LEARNING OBJECTIVES After completing this chapter, you should be able to: 1. Describe the role and application of PERT/CPM for project scheduling. 2. Define a project
More informationNetwork Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration
Network Diagram Critical Path Method Programme Evaluation and Review Technique and Reducing Project Duration Prof. M. Rammohan Rao Former Dean Professor Emeritus Executive Director, Centre for Analytical
More informationCollaborative Scheduling using the CPM Method
MnDOT Project Management Office Presents: Collaborative Scheduling using the CPM Method Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines
More informationSWEN 256 Software Process & Project Management
SWEN 256 Software Process & Project Management Plan: Identify activities. No specific start and end dates. Estimating: Determining the size & duration of activities. Schedule: Adds specific start and end
More informationMicrosoft Project 2010
Tutorial 1: Planning a Project Microsoft Project 2010 In Tutorial Section 1.1 you will: Learn project management terminology Understand the benefits of project management Explore the Project 2010 window
More informationTime Management. Part 5 Schedule Development. Richard Boser
Time Management Part 5 Schedule Development Richard Boser 6.5 Schedule Development Inputs Organizational Process Assets Scope Statement Activity List Activity Attributes Network Diagrams Resource Req ms
More informationTable of Contents Author s Preface... 3 Table of Contents... 5 Introduction... 6 Step 1: Define Activities... 7 Identify deliverables and decompose
1 2 Author s Preface The Medialogist s Guide to Project Time Management is developed in compliance with the 9 th semester Medialogy report The Medialogist s Guide to Project Time Management Introducing
More informationProject Scheduling. Introduction
Project Scheduling Introduction In chapter, the O and ON networks were presented, also the time and cost of individual activities based were calculated. Yet, however, we do not know how long is the total
More informationEgypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014
Project Management Six Session Egypt Scholars Presented by Mohamed Khalifa Hassan Jan 2014 Mohamed Khalifa, 2014 All Rights 1 7. Scheduling 2 7. Scheduling 7.1 Scheduling techniques 7.3 Critical path method
More informationChapter 9 Computer Scheduling Projects should be scheduled one byte at a time
Chapter 9 Computer Scheduling Projects should be scheduled one byte at a time Computer Scheduling Critical path method (CPM) requires numerous computations to determine activity start and finish dates,
More informationA Computer Application for Scheduling in MS Project
Comput. Sci. Appl. Volume 1, Number 5, 2014, pp. 309-318 Received: July 18, 2014; Published: November 25, 2014 Computer Science and Applications www.ethanpublishing.com Anabela Tereso, André Guedes and
More informationProject Scheduling & Tracking
Project Scheduling & Tracking Traditional Techniques: Work Breakdown Structure (WBS) Gantt Charts Precedence Diagrams Earned Value Planning It is the mark of an instructed mind to rest satisfied with the
More information25Project management
5Project management A Activity 5.1 (page ) 1 Verify the ESTs above by working through the diagram from left to right, taking the longest route, in days, to each node. Node 1 3 5 7 8 EST 0 0 + 8 = 8 0 +
More information8. Project Time Management
8. Project Time Management Project Time Management closely coordinated Two basic approaches -bottom-up (analytical) -top-down (expert judgement) Processes required to ensure timely completion of the project
More informationProject Scheduling by Critical Path Method (CPM)
12.1 Project Scheduling by Critical Path Method (CPM) Katta G. Murty Lecture slides CPM is application of DP to problems in Construction (project) Management. Many large construction projects going on
More informationScheduling Resources and Costs
Student Version CHAPTER EIGHT Scheduling Resources and Costs McGraw-Hill/Irwin Copyright 2011 by The McGraw-Hill Companies, Inc. All rights reserved. Gannt Chart Developed by Henry Gannt in 1916 is used
More informationModule 3: The Project Planning Stage
Overview Once you've initiated the project and gathered all relevant information, you'll then begin planning your project. The planning stage depends on the size of your project, how much information you
More informationBasic CPM Calculations
Overview Core Scheduling Papers: #7 Basic CPM Calculations Time Analysis calculations in a Precedence Diagramming Method (PDM) Critical Path Method (CPM) network can be done in a number of different ways.
More informationChapter 2: Project Time Management
Chapter 2: Project Time Management Learning Objectives o o o o Understand the importance of project schedules and good project time management. Define activities as the basis for developing project schedules.
More informationPROJECT PROPOSAL: PROJECT BLUE ZUMA
PROJECT PROPOSAL: PROJECT BLUE ZUMA To: From: CC: Dr. Edward J Glantz Alex Bok (ayb5041@psu.edu) Mark Randall Date: February 28 th, 2008 The following documents are detailed reports on our project proposal
More informationThe work breakdown structure can be illustrated in a block diagram:
1 Project Management Tools for Project Management Work Breakdown Structure A complex project is made manageable by first breaking it down into individual components in a hierarchical structure, known as
More informationImportance of Project Schedules. matter what happens on a project. projects, especially during the second half of projects
Project Time Management Chapter 6 Importance of Project Schedules Managers often cite delivering projects on time as one of their biggest challenges Time has the least amount of flexibility; it passes
More informationProject Management Glossary
Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project
More informationThe Project Planning Process Group
3 The Project Planning Process Group............................................... Terms you ll need to understand: Activity Activity attributes Activity list Activity on arrow diagram (AOA) Activity
More informationWORK PROGRAM GUIDELINES
Project Managed Change Program WORK PROGRAM GUIDELINES JABATAN KERJA RAYA MALAYSIA Cawangan Pengurusan Projek Kompleks (PROKOM) Ibu Pejabat JKR Malaysia 2 Document Ownership Section No Section Amendment
More informationTime Planning and Control
TOBIC 4 TIM SCLD NTWORK 1 June 3013 Time Planning and Control Time-Scaled Network G404 NGINRING MNGMNT 1 TOBIC 4 TIM SCLD NTWORK 1 June 3013 Processes of Time Planning and Control 1. Visualize and define
More informationNetwork Calculations
Network Calculations The concepts and graphical techniques described in this week s readings form the basis of the tools widely used today to manage large projects. There is no way of simplifying the tasks
More informationObject-Oriented Analysis. with the Unified Process. John W. Satzinger Southwest Missouri State University. Robert B. Jackson Brigham Young University
Object-Oriented Analysis and Design with the Unified Process John W. Satzinger Southwest Missouri State University Robert B. Jackson Brigham Young University Stephen D. Burd University of New Mexico ALL
More informationProject Management Chapter 3
Project Management Chapter 3 How Project Management fits the Operations Management Philosophy Operations As a Competitive Weapon Operations Strategy Project Management Process Strategy Process Analysis
More informationMS Project Tutorial. CS 587 Software Project Management Instructor: Dr. Atef Bader. Prepared by Milton Hurtado
CS 587 Software Project Management Instructor: Dr. Atef Bader MS Project Tutorial MS Project in Labs: Available in Siegal Hall Lab in Main Campus Available in Room 210 Rice Campus Prepared by Milton Hurtado
More informationProject Management SCM 352. 2011 Pearson Education, Inc. publishing as Prentice Hall
3 Project Management 3 SCM 35 11 Pearson Education, Inc. publishing as Prentice Hall Boeing 787 Dreamliner Delays are a natural part of the airplane supply business. They promise an unreasonable delivery
More informationSYSTEMS ANALYSIS AND DESIGN DO NOT COPY
Systems Analysis and Design in a Changing World, Fourth Edition -488-6-5 Copyright 7 Thomson Course Technology. All rights reserved. FOURTH EDITION SYSTEMS ANALYSIS AND DESIGN IN A C HANGING W ORLD John
More informationCISC 322 Software Architecture. Project Scheduling (PERT/CPM) Ahmed E. Hassan
CISC 322 Software Architecture Project Scheduling (PERT/CPM) Ahmed E. Hassan Project A project is a temporary endeavour undertaken to create a "unique" product or service A project is composed of a number
More informationReview on Using Packages to Enhance the Teaching of Critical Path Networks
Review on Using Packages to Enhance the Teaching of Critical Path Networks Harry S Ku Abstract The aim of this paper is to review a published paper, Using computer software packages to enhance the teaching
More informationApplication Survey Paper
Application Survey Paper Project Planning with PERT/CPM LINDO Systems 2003 Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM) are two closely related techniques for monitoring
More informationCRITICAL PATH ANALYSIS AND GANTT CHARTS
CRITICAL PATH ANALYSIS AND GANTT CHARTS 1. An engineering project is modelled by the activity network shown in the figure above. The activities are represented by the arcs. The number in brackets on each
More informationResource Allocation and Scheduling
90 This section is about the general overview of scheduling and allocating resources. Assigning people and machines to accomplish work (work on tasks). Resource Allocation: Time-Constrained. Assigning
More informationPERT/CPM. Network Representation:
- 1 - PERT/CPM PERT Program Evaluation & Review Technique It is generally used for those projects where time required to complete various activities are not known as a priori. It is probabilistic model
More information2.3.4 Project planning
.. Project planning project consists of a set of m activities with their duration: activity i has duration d i, i =,..., m. estimate Some pairs of activities are subject to a precedence constraint: i j
More informationA Short Introduction to Project Management
2003 January April SFWR ENG 2B03 Slides 08 0 A Short Introduction to Project Management SFWR ENG 2B03 2003 Robert L. Baber 2003 January April SFWR ENG 2B03 Slides 08 1 Why Project Management? Why manage
More informationHow To Manage A Project With Project Management On M Project Software On A Pc Or Macbook 2.5 (Windows)
Project management M project tutorial Part 1: Project beginning and the Gantt chart Purpose Project management by using Microsoft Project software Introduction Project management is a process of organizing,
More informationPROGRAMMING TECHNIQUES. Chapter 5(Part 2)
PROGRAMMING TECHNIQUES Chapter 5(Part 2) LEARNING OUTCOME At the end of this lesson, students will be able to: Understand the different types of planning techniques. Understand the network analysis. Formulate
More informationMnDOT Project Management Office Presents: Schedule Float. Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc.
MnDOT Project Management Office Presents: Schedule Float Presenter: Jonathan McNatty, PSP Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar
More informationPROJECT TIME MANAGEMENT. 1 www.pmtutor.org Powered by POeT Solvers Limited
PROJECT TIME MANAGEMENT 1 www.pmtutor.org Powered by POeT Solvers Limited PROJECT TIME MANAGEMENT WHAT DOES THE TIME MANAGEMENT AREA ATTAIN? Manages the project schedule to ensure timely completion of
More informationSE351a: Software Project & Process Management
SE351a: Software Project & Process Management W8: Software Project Planning 22 Nov., 2005 SE351a, ECE UWO, (c) Hamada Ghenniwa SE351 Roadmap Introduction to Software Project Management Project Management
More informationA Generalized PERT/CPM Implementation in a Spreadsheet
A Generalized PERT/CPM Implementation in a Spreadsheet Abstract Kala C. Seal College of Business Administration Loyola Marymount University Los Angles, CA 90045, USA kseal@lmumail.lmu.edu This paper describes
More information10 Project Management with PERT/CPM
10 Project Management with PERT/CPM 468 One of the most challenging jobs that any manager can take on is the management of a large-scale project that requires coordinating numerous activities throughout
More informationProgram Evaluation and Review Technique (PERT) and Critical Path Method (CPM) Applications
Program Evaluation and Review Technique (PERT) and Critical Path Method (CPM) Applications Two simple, yet interesting and important applications of partial ordering relations are the PERT and CPM techniques
More informationAppendix A of Project Management. Appendix Table of Contents REFERENCES...761
Appendix A Glossary Terms of Project Management Appendix Table of Contents REFERENCES...761 750 Appendix A. Glossary of Project Management Terms Appendix A Glossary Terms of Project Management A Activity
More informationNotes on the Critical Path Method for project planning and management.
E90 Engineering Design Notes on the Critical Path Method for project planning and management. CPM models any project by a network of blocks or circles called NODES that are connected by lines called ARROWS.
More informationCHAPTER 4 LINEAR SCHEDULING METHOD (LSM) AND ITS APPLICATIONS
33 CHAPTER 4 LINEAR SCHEDULING METHOD (LSM) AND ITS APPLICATIONS 4.1 BASICS OF LINEAR SCHEDULING The LSM is a graphical technique in which the locations or the length of the linear project is indicated
More informationPriori ty ... ... ...
.Maintenance Scheduling Maintenance scheduling is the process by which jobs are matched with resources (crafts) and sequenced to be executed at certain points in time. The maintenance schedule can be prepared
More informationNetwork analysis: P.E.R.T,C.P.M & Resource Allocation Some important definition:
Network analysis: P.E.R.T,C.P.M & Resource Allocation Some important definition: 1. Activity : It is a particular work of a project which consumes some resources (in ) & time. It is shown as & represented
More informationpm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS
pm4dev, 2015 management for development series Project Schedule Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development
More informationCRITICAL PATH METHOD (CPM) SCHEDULES
96 CRITICAL PATH METHOD (CPM) SCHEDULES How-to for Reading, Understanding, and Using CPM Schedules (without Direct Primavera Access.) 1 Objectives Learn to read, understand, and use CPM schedules (without
More informationCSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012
King Saud University College of Computer & Information Sciences Department of Computer Science CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 1- Decomposing
More informationScheduling. Anne Banks Pidduck Adapted from John Musser
Scheduling Anne Banks Pidduck Adapted from John Musser 1 Today Network Fundamentals Gantt Charts PERT/CPM Techniques 2 WBS Types: Process, product, hybrid Formats: Outline or graphical organization chart
More informationMSc Project Planning
MSc Project Planning Dr Paul Brunn 4 th February 2009 Project Planning and Control Intro to General Methods Some simple examples How to plan and complete an MSc Dissertation project EPS Graduate Education
More informationMastering Microsoft Project 2010
Mastering Microsoft Project 2010 Duration: 2 days Course Description This two-day instructor-led course provides students with the knowledge and skills to plan and manage projects using Microsoft Project
More informationMODEL SCHEDULING SPECIFICATION
MODEL SCHEDULING SPECIFICATION Introduction (Not part of the specification) Before implementation, we recommend that your contract and this provision be reviewed and modified to ensure compatibility with
More informationIntroduction to Project Management
L E S S O N 1 Introduction to Project Management Suggested lesson time 50-60 minutes Lesson objectives To be able to identify the steps involved in project planning, you will: a b c Plan a project. You
More informationScheduling Best Practices
In a continuing series of articles on specific aspects of critical path method (CPM) scheduling, Warner examines various facets of the process of preparing, analyzing and utilizing schedules in project
More informationSECTION 01320 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS
SECTION 01320 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division
More informationChapter 1.7 Project Management. 1. Project financing is one of the step of project management- State True or False
Chapter 1.7 Project Management Part I: Objective type questions and answers 1. Project financing is one of the step of project management- State True or False 2. Proposed new technologies, process modifications,
More informationMECH 896 Professional Development for MEng Students. Homework Discussion. Scheduling Overview. Winter 2015: Lecture #5 Project Time Management
MECH 896 Professional Development for MEng Students Mohamed Hefny and Brian Surgenor (hefny@cs.queensu.ca and surgenor@me.queensu.ca) Winter : Lecture # Project Time Management Homework Discussion Homework
More informationMnDOT Project Management Office Presents: Schedule Updates. Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc.
MnDOT Project Management Office Presents: Schedule Updates Presenter: Eric Costantino Senior Schedule Consultant DRMcNatty & Associates, Inc. Housekeeping Items Lines will be muted during the webinar Questions
More information2.3.5 Project planning
efinitions:..5 Project planning project consists of a set of m activities with their duration: activity i has duration d i, i = 1,..., m. estimate Some pairs of activities are subject to a precedence constraint:
More informationChapter 6: Project Time Management. King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072
Chapter 6: Project Time Management King Fahd University of Petroleum & Minerals SWE 417: Software Project Management Semester: 072 Learning Objectives Understand the importance of project schedules Define
More information