Earned Value Management

Size: px
Start display at page:

Download "Earned Value Management"

From this document you will learn the answers to the following questions:

  • What might you do late or early?

  • What does the SPI show that the Cost Performance Index reflects the difference between the amount of work that has been finished and the amount of work that was expected to be finished?

  • Depends on the relative size of what?

Transcription

1 Earned Value Management Allen D. Holliday February 27, 2008 Computer Science Department California State University, Fullerton Cost and schedule are two of the primary concerns of a project manager, who wants to know: How much money has been spent? (Will we finish within budget?) How much work has been completed? (Will we finish on time?) There s a very important characteristic of the two measures, cost and schedule they are interrelated and shouldn t be examined independently. One measure can be good while the other is bad. Being ahead of schedule or under budget isn t necessarily good news. You may have spent too much to get ahead of schedule, or you may be under budget because you don t have the staff to get enough work done, and you ll going to finish late (and may also overspend). What you need is a method of measuring spending and progress that allows you to judge their combined effect. Earned Value Management is such a method. It can be applied continually to assess a project to see if it s proceeding as expected tasks are being completed on schedule and the rate of spending is within budget. When deviations occur, you can determine how serious they are and what corrective action is required. Definitions There are three measures involved in earned value calculation: Earned Value (EV): the value of the work actually completed, in terms of the work s budgeted cost. Planned Value (PV): the value of the work expected to be completed, also in terms of the work s budgeted cost. Actual Cost (AC): the money that s been spent. We use one unit (money) for all three measures so that we can calculate unit-free ratios. There s an important point about a term used in these definitions the measure of work. This isn t just some subjective judgment of how far along a task is, such as we feel that we re 35% done. It has to be an objective measure of something physical that can be measured or counted, a milestone or a deliverable. The 35% is acceptable if it means that you ve finished 35 of 100 tasks. (Or delivered 35 of 100 products, or finished 35 of 100 parts of a system, and so forth.) In older versions of Earned Value Management, Earned Value was called Budgeted Cost of Work Performed (BCWP), Planned Value was called Budgeted Cost of Work Expected (BCWE) and Actual Cost was called Actual Cost of Work Performed (ACWP). The current terms are shorter and clearer. 1

2 Performance Indexes Two earned value performance indexes are calculated by the formulas shown below: Cost Performance Index (CPI) reflects the difference between the planned cost of the work that s been completed and the actual cost of that work, regardless of whether the work is on time, early, or late. It s calculated as follows: CPI EV AC If you re right on budget, the index will be 1.0. If you re spending less than you d planned for a given amount of work, AC will be less than EV and CPI will be greater than 1.0. If you re overspending, AC will be greater than EV and CPI will be less than 1.0. Schedule Performance Index (SPI) reflects the difference between the amount of work that s been finished and the amount of work that was expected to be finished, regardless of the cost of that work. It s calculated as follows: SPI EV PV If you re right on schedule, the index will be 1.0. If you re getting more done than you d planned, EV will be greater than PV and SPI will be greater than 1.0. If you re behind schedule, EV will be less than PV and CPI will be less than

3 There are nine possible combinations of schedule and cost indexes, some good and some bad, summarized below. Current Situation shows the meaning at a given point, Final Result shows what will happen if the current trend remains unchanged. Condition Current Situation Final Result On budget, on schedule On budget, ahead of schedule On budget, behind schedule Over budget, on schedule Over budget, ahead of schedule Over budget, behind schedule Under budget, on schedule Under budget, ahead of schedule Under budget, behind schedule Neutral. Good; you re working faster and getting more for your money. Mixed; the work is late, but you haven t spent too much so far. Mixed (some good, some bad); getting the work done on time, but spending too much. Mixed; the work is early, but you re spending faster. Bad news; the work is late, and you re spending too much. Good; getting the work done on time, and cheaper than expected. The best news; you re getting more work done at a lower cost. Mixed; the work is late, but you re also spending slower. You ll finish right on time and on budget. You ll finish early and you won t spend all of your budget. You ll finish late and overrun your budget by spending at your planned rate for too long. You ll finish on time, but overrun your budget. Depends on the relative size of the two indexes. If you re just as ahead of schedule as you are over budget, you ll finish early and you ll spend exactly what you d planned. If you re less ahead of schedule than you re over budget, you ll finish early but still overspend. If you re farther ahead of schedule than you re over budget, you ll finish early and underspend (because your over budget problem will end early). You ll finish late and overrun your budget. You ll finish on time and underspend your budget. You ll finish early with more money left over than the Ahead of schedule, on budget case. Depends on the relative size of the measures: If you re just as behind schedule as you are under budget, you ll be late but you ll spend exactly what you d planned. If you re less behind schedule than you re under budget, you ll finish late but underspend. If you re farther behind schedule than you re under budget, you ll finish late and overspend (because your slow spending rate will continue for too long and the final total will be more than you d planned). 3

4 In reality, schedule predictions aren t as simple and straightforward as the previous table shows. SPI is a summary of the amount of work completed. It doesn t account for the parallel nature of the project s tasks. Some of those tasks can be delayed without affecting the finish date of the project. SPI could be greater than 1.0 at some point and be equal (or even less than) 1.0 at the finish. Cost predictions aren t affected by this parallelism money spent can t be recovered in the same manner a schedule slip on a non-critical task can. Once CPI indicates a spending overrun, you must either increase productivity or eliminate work to finish early. Both of these are difficult to achieve. SPI and CPI are indicators showing you whether your project is performing according to your plan. You must decide how serious the problem is and what you need to do about it. Earned Value Management provides the trigger for problem investigation; you must define the solution. 4

5 Example An example will help. Imagine that you have a project with 10 tasks. To make the arithmetic simple, we ll make them all one month long and cost $100 each. The project should take ten months to complete and cost $1000. We ll be looking at the situation halfway through the project right after month five of a ten-month schedule. The budget and schedule plan calls for one half of the budget to be spent and one half of the work to be performed at this point. These linear rates aren t the typical cost or schedule curves of a real project, but they will make the example easier to follow. Also, the deviations of cost and schedule are the same in this example, while in a real project, this probably won t occur. One deviation will be larger than the other for instance, a large budget overrun and a small schedule gain. The diagrams below show a schedule bar chart and a spending graph for the ten tasks. Remember, one of these charts by itself isn t enough to show the complete picture of how you re doing. Spending Graph The spending graph also shows three conditions; whether they are good or bad depends on how they relate to the schedule chart. It might be OK to overspend if you re going to finish early and stop spending soon. Underspending might be a problem, if you re also behind schedule and will have to spend money for a longer time than planned, eventually overrunning your budget. If we view the spending rates of these three conditions, the On Budget rate is $100 per month, the Over Budget rate is $140 per month, and the Under Budget rate is $60 per month. A high rate may mean that you have a larger staff than you d originally planned, or that salaries are higher than you d expected. A low rate may mean a smaller staff than planned, or lower salaries than expected. 5

6 Schedule Bar Chart The schedule bar chart s gray boxes indicate completed tasks; the bars show three possible conditions. The Behind Schedule bar shows that we ve only finished the work that we planned to spend $300 on, but we re at a time when we should have finished $500 s worth. The On Schedule bar shows that we ve finished that $500 s worth of work. The Ahead of Schedule bar shows that we ve finished $700 s worth of work at a time when we d planned to finish only $500 s worth. If we view the task completion rates of these three conditions, the On Schedule rate is one task per month, the Behind Schedule rate is only 0.6 tasks per month, and the Ahead of Schedule rate is 1.4 tasks per month. Cost and Schedule at Completion The at completion values are calculated by: 1. Final cost Budget / CPI 2. Final duration Planned duration / SPI The final cost is a reflection of both how fast we re spending and how long we ll be spending. Remember that5 these examples are simple linear cases that illustrate a point but won t be encountered on actual projects. 6

7 Calculations of Performance Indexes Here are the calculations for the nine combinations of CPI SPI values. The labels reflect what the schedule bar chart and spending graph show individually; the calculated status values tell a more complete story when they re examined together as noted below. On Budget, On Schedule CPI AC SPI 1.0 Everything looks fine here, and it really is. You re right on plan for both cost and schedule. On Budget, Ahead Of Schedule CPI AC SPI 1.4 The cost status is better than staying even. Although you re spending at the rate you d planned, you re getting more work done for the money than you had expected. You ll finish early and spend less than you d planned, because your spending at your planned rate will end early. Note that the CPI is not 1.0, even though the AC value by itself seems to show the project being right on budget half the budget spent in half the schedule. The higher CPI is because the EV is high; more than half of the work has been performed. This is also reflected in the higher SPI. $1000 / 1.4 $ months / months 7

8 On Budget, Behind Schedule CPI AC SPI 0.6 The CPI shows that, even though you re spending at the rate you d planned, you re not getting enough work done for the money. The SPI shows that you re going to finish late. In the end, you ll spend more than you d planned. Although you won t spend faster than you d planned, you ll be spending longer than you d planned. Note that again the CPI is not 1.0, even though the AC value by itself seems to show the project being right on budget half the budget spent in half the schedule. The lower index is because the BCWP is low; less than half of the work has been performed. $1000 / 0.6 $ months / months Over Budget, On Schedule CPI AC SPI 1.0 The CPI shows that you re spending too much money, while the schedule status shows that you re going to finish on time. You ll spend more than you d planned. $1000 / 0.71 $ months / months 8

9 Over Budget, Ahead Of Schedule CPI AC SPI 1.4 The CPI shows that, even though you re spending more than you d planned, you re getting more work done for that money than you d planned. If things continue at the same pace, you ll finish early and spend exactly what you d planned. Note that the CPI is 1.0, even though the AC value by itself shows the project being over budget more than half the budget spent in half the schedule. The 1.0 value is because the EV is equally high; more than half of the work has been performed. $1000 / 1.0 $ months / months Over Budget, Behind Schedule CPI AC SPI 0.60 The CPI shows that things are pretty bad, much worse than the other two Over Budget cases. The SPI shows that you re going to finish late. You ll be seriously overspent, because you ll be spending both faster and longer than planned. $1000 / 0.43 $ months / months 9

10 Under Budget, On Schedule CPI AC SPI 1.0 A good situation. You re not spending as fast as you d planned and you re not late. You ll finish on time and you won t spend as much as you d planned. $1000 / 1.67 $ months / months Under Budget, Ahead Of Schedule CPI AC SPI 1.4 The best of all possible cases. You won t spend as much as you d planned and you re going to finish early. $1000 / 2.33 $ months / months 10

11 Under Budget, Behind Schedule CPI AC SPI 0.6 The CPI by itself doesn t show a problem; it says that you ve spent just as much on the work performed as you d planned. The SPI shows the true reason for the underspending not enough work being done, which is a problem. In the end, you ll finish late but you won t spend more than you d planned. Even though you ll be spending longer than you d planned, you ll spend slower than you d planned, Note that the CPI is 1.0, even though the AC value by itself shows the project being under budget less than half the budget spent in half the schedule. The 1.0 value is because the EV is equally low; less than half of the work has been performed. $1000 / 1.0 $ months / months 11

Tracking Budgets and Schedules

Tracking Budgets and Schedules Tracking Budgets and Schedules David V. Tennant, PE, PMP One of the simplest questions you are likely to encounter as an engineering or project manager is: Are we on budget and schedule? While this is

More information

Estimating Cost at Completion - Judgment & EV Information

Estimating Cost at Completion - Judgment & EV Information Page 1 of 10 Estimating Cost at Completion - Judgment & EV Information Cost estimating is often called a "black art" and, too often, estimates are structured to fit some predetermined idea of a number

More information

INSE 6230 Total Quality Project Management

INSE 6230 Total Quality Project Management Lecture 5 Project Cost Management Project cost management introduction Estimating costs and budgeting Earned Value Management (EVM) 2 IT projects have a poor track record for meeting budget goals Cost

More information

Relative and Absolute Change Percentages

Relative and Absolute Change Percentages Relative and Absolute Change Percentages Ethan D. Bolker Maura M. Mast September 6, 2007 Plan Use the credit card solicitation data to address the question of measuring change. Subtraction comes naturally.

More information

SEQUENCES ARITHMETIC SEQUENCES. Examples

SEQUENCES ARITHMETIC SEQUENCES. Examples SEQUENCES ARITHMETIC SEQUENCES An ordered list of numbers such as: 4, 9, 6, 25, 36 is a sequence. Each number in the sequence is a term. Usually variables with subscripts are used to label terms. For example,

More information

technical tips and tricks

technical tips and tricks technical tips and tricks Earned Value Analysis Overview Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart

More information

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1

Earned Value. Valerie Colber, MBA, PMP, SCPM. Not for duplication nor distribution 1 Earned Value Valerie Colber, MBA, PMP, SCPM Not for duplication nor distribution 1 Where did Earned Value Management come from? In 1967 the Department of Defense (DoD) established the Cost/Schedule Control

More information

Chapter 7: Project Cost Management. Munawar moenawar@gmail.com

Chapter 7: Project Cost Management. Munawar moenawar@gmail.com Chapter 7: Project Cost Management Munawar moenawar@gmail.com Learning Objectives Understand the importance of project cost management. Explain basic project cost management principles, concepts, and terms.

More information

Terminology and Scripts: what you say will make a difference in your success

Terminology and Scripts: what you say will make a difference in your success Terminology and Scripts: what you say will make a difference in your success Terminology Matters! Here are just three simple terminology suggestions which can help you enhance your ability to make your

More information

EVM.01. Earned Value Analysis Why it Doesn't Work

EVM.01. Earned Value Analysis Why it Doesn't Work EVM.01 Earned Value Analysis Why it Doesn't Work Mr. Joseph A Lukas, PE CCE F or many companies looking to improve project performance, earned value analysis (EVA) seems a logical technique to use on projects

More information

Session 7 Bivariate Data and Analysis

Session 7 Bivariate Data and Analysis Session 7 Bivariate Data and Analysis Key Terms for This Session Previously Introduced mean standard deviation New in This Session association bivariate analysis contingency table co-variation least squares

More information

EXPRESSING LIKES, DISLIKES AND PREFERENCES DIALOGUE SCRIPT AND GLOSSARY

EXPRESSING LIKES, DISLIKES AND PREFERENCES DIALOGUE SCRIPT AND GLOSSARY EXPRESSING LIKES, DISLIKES AND PREFERENCES DIALOGUE SCRIPT AND GLOSSARY INTRODUCTION In this podcast we re going to be looking a various ways of expressing likes, dislikes and preferences. It is very easy

More information

Paying off a debt. Ethan D. Bolker Maura B. Mast. December 4, 2007

Paying off a debt. Ethan D. Bolker Maura B. Mast. December 4, 2007 Paying off a debt Ethan D. Bolker Maura B. Mast December 4, 2007 Plan Lecture notes Can you afford a mortgage? There s a $250,000 condominium you want to buy. You ve managed to scrape together $50,000

More information

Project Control. 1. Schedule Updating

Project Control. 1. Schedule Updating Project Control During the execution of a project, procedures for project control and record keeping become indispensable tools to managers and other participants in the construction process. These tools

More information

CPM -100: Principles of Project Management

CPM -100: Principles of Project Management CPM -100: Principles of Project Management Lesson B: Time and Cost Management Presented by Bruce R. Shaw, P.E., PMP starshaw@starpower.net Ph: 703-922-2772 Presented at the PMI-CPM 2002 Fall Conference

More information

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance.

Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. About the Tutorial Earned Value Management (EVM) is a technique that is used to track the progress and status of a project and forecast its likely future performance. This is a brief tutorial that acquaints

More information

Chapter 3: Project Cost Management

Chapter 3: Project Cost Management Chapter 3: Project Cost Management Learning Objectives o Understand the importance of project cost management. o Explain basic project cost management principles, concepts, and terms. o Discuss different

More information

Earned Value Formulae

Earned Value Formulae Earned Value Formulae This White Paper focuses on the basic values and formulae used in Earned Value calculations. Additional EV resources are available from http://www.mosaicprojects.com.au/techniques.html#earnedvalue

More information

Project Management: Tracking Progress and Earned Value with MS Project 2003

Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Management: Tracking Progress and Earned Value with MS Project 2003 Project Planning Suppose you have been assigned a project to construct a website in a certain time frame and given a certain

More information

Page 18. Using Software To Make More Money With Surveys. Visit us on the web at: www.takesurveysforcash.com

Page 18. Using Software To Make More Money With Surveys. Visit us on the web at: www.takesurveysforcash.com Page 18 Page 1 Using Software To Make More Money With Surveys by Jason White Page 2 Introduction So you re off and running with making money by taking surveys online, good for you! The problem, as you

More information

Using Earned Value Management for Improving Processes. By Cynthia K. West

Using Earned Value Management for Improving Processes. By Cynthia K. West Using Earned Value Management for Improving Processes By Cynthia K. West Summary: This article explains earned value management and explores how the metric can be used to improve project and business processes.

More information

IST 302 : Project Cost Management

IST 302 : Project Cost Management IST 302 : Project Cost Management Project Cost Management : Why do we care? 1 Cost and Cost Management Cost: Cost Management: Project Cost Management Processes Cost Estimating Developing an estimate of

More information

Brainstorm. What is Cost and Project Cost Management?

Brainstorm. What is Cost and Project Cost Management? Brainstorm Suppose you need to create a network from scratch in your organization's headquarter. Your project is named HQ Network. Your major deliverables includes: LAN, WAN, server room, workstations,

More information

700 Analysis and Reporting

700 Analysis and Reporting Jefferson Science Associates, LLC 700 Analysis and Reporting Project Control System Manual Revision 7-50 - 700 Analysis and Reporting This chapter of the JSA Project Control System Manual explains how

More information

Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP

Earned Value Exercise. Su-Cheng Wu. MET AD 644: Project Risk, and Cost Management. Paul B. Cook, PhD PMP Earned Value Exercise 1 Running head: Earned Value Exercise Earned Value Exercise SuCheng Wu MET AD 644: Project Risk, and Cost Management Paul B. Cook, PhD PMP Earned Value Exercise 2 Case 1: Background:

More information

Introduction to earn value management in Civil Engineering

Introduction to earn value management in Civil Engineering 3 rd World Conference on Applied Sciences, Engineering & Technology 27-29 September 2014, Kathmandu, Nepal Introduction to earn value management in Civil Engineering S. K. KAMANE, S. A. MAHADIK, A. C.

More information

Brillig Systems Making Projects Successful

Brillig Systems Making Projects Successful Metrics for Successful Automation Project Management Most automation engineers spend their days controlling manufacturing processes, but spend little or no time controlling their project schedule and budget.

More information

An introduction to Earned Value Analysis

An introduction to Earned Value Analysis An introduction to Earned Value Analysis Prepared by: Suketu Nagrecha, MBA, PMP, CNA March 16, 2002 Earned Value Analysis - 2 Abstract Earned value analysis is a method of performance measurement. Many

More information

Updates to Graphing with Excel

Updates to Graphing with Excel Updates to Graphing with Excel NCC has recently upgraded to a new version of the Microsoft Office suite of programs. As such, many of the directions in the Biology Student Handbook for how to graph with

More information

SAY IT BETTER IN ENGLISH

SAY IT BETTER IN ENGLISH PHRASE GUIDE FOR THE BOOK SAY IT BETTER IN ENGLISH Useful Phrases for Work & Everyday Life Directions for use: This guide contains all the phrases included in the book Say it Better in English. If you

More information

BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant

BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant BEYOND EARNED VALUE: A Better Practice for Monitoring Project Performance 2012 Dr. Kenneth F. Smith, PMP ; Project Management Consultant Introduction Earned Value (EV) has been around since the 1960 s

More information

PMP Exam Preparation Answer Key

PMP Exam Preparation Answer Key Chapter 2 Answers 1) d) They are all of equal importance unless otherwise stated The Triple Constraint of Project Management is that Scope, Time, and Cost are all equal unless otherwise defined as such.

More information

Why EVM Is Not Good for Schedule Performance Analyses (and how it could be )

Why EVM Is Not Good for Schedule Performance Analyses (and how it could be ) Why EVM Is Not Good for Schedule Performance Analyses (and how it could be ) By Radenko Corovic, MBA Abstract Project performance researchers are unanimous that the conventional EVM (Earned Value Management)

More information

Earned Value Analysis Exercise

Earned Value Analysis Exercise Earned Value Analysis Exercise www.spmbook.com Author: Adolfo Villafiorita Revision: 2 (205-02-06) Given the following project plan: ID Task Immediate Predecessor (*) Expected Duration (days) Budget ($)

More information

Towards a Complete Earned Value Analysis. Sam Sharp and Peter Hall. Paper # 166

Towards a Complete Earned Value Analysis. Sam Sharp and Peter Hall. Paper # 166 Towards a Complete Earned Value Analysis Sam Sharp and Peter Hall Paper # 166 Planned vs Actual A purely accounting approach to project tracking involves the monitoring of status by simply comparing actual

More information

Linear Programming Notes VII Sensitivity Analysis

Linear Programming Notes VII Sensitivity Analysis Linear Programming Notes VII Sensitivity Analysis 1 Introduction When you use a mathematical model to describe reality you must make approximations. The world is more complicated than the kinds of optimization

More information

Linear functions Increasing Linear Functions. Decreasing Linear Functions

Linear functions Increasing Linear Functions. Decreasing Linear Functions 3.5 Increasing, Decreasing, Max, and Min So far we have been describing graphs using quantitative information. That s just a fancy way to say that we ve been using numbers. Specifically, we have described

More information

technical tips and tricks

technical tips and tricks technical tips and tricks Applying Earned Value Analysis Document author: Produced by: Andy Jessop Project Learning International Limited The tips and tricks below are taken from Project Mentor, the smart

More information

Taking Payments Online Do You Care About Your Customers?

Taking Payments Online Do You Care About Your Customers? Taking Payments Online Do You Care About Your Customers? I love the freedom of being able to sell information products and services remotely, and the ease of taking payments online. I equally love the

More information

A Framework for Project Metrics

A Framework for Project Metrics A Framework for Project Metrics Deciding what to measure and how to measure it August 13, 2007 Dr. Gary J. Evans, PMP CVR/IT Consulting LLC www.cvr-it.com Welcome! Focus of this workshop: Project Metrics

More information

A Picture Really Is Worth a Thousand Words

A Picture Really Is Worth a Thousand Words 4 A Picture Really Is Worth a Thousand Words Difficulty Scale (pretty easy, but not a cinch) What you ll learn about in this chapter Why a picture is really worth a thousand words How to create a histogram

More information

Preparing a Simple Project Plan with MS Project

Preparing a Simple Project Plan with MS Project Background Preparing a Simple Project Plan with MS Project Part 1: Preliminary set-up MS-Project is the most widely used software product for project planning and control. It s both flexible and powerful,

More information

CONVERTING TO PHYSICAL % COMPLETE METHOD OF EARNED VALUE IN MICROSOFT PROJECT

CONVERTING TO PHYSICAL % COMPLETE METHOD OF EARNED VALUE IN MICROSOFT PROJECT CONVERTING TO PHYSICAL % COMPLETE METHOD OF EARNED VALUE IN MICROSOFT PROJECT PREPARED BY James E Aksel, PMP jim@projectpmo.com http://www.msprojectdblog.com http://www.projectpmo.com Page 1 of 19 Table

More information

SPECIAL REPORT: 4 BIG REASONS YOU CAN T AFFORD TO IGNORE BUSINESS CREDIT!

SPECIAL REPORT: 4 BIG REASONS YOU CAN T AFFORD TO IGNORE BUSINESS CREDIT! SPECIAL REPORT: 4 BIG REASONS YOU CAN T AFFORD TO IGNORE BUSINESS CREDIT! 4 BIG REASONS YOU CAN T AFFORD TO IGNORE BUSINESS CREDIT! Provided compliments of: FIRSTUSA DATA SERVICES, LLC 877-857-5045 SUPPORT@FIRSTUSADATA.COM

More information

Years after 2000. US Student to Teacher Ratio 0 16.048 1 15.893 2 15.900 3 15.900 4 15.800 5 15.657 6 15.540

Years after 2000. US Student to Teacher Ratio 0 16.048 1 15.893 2 15.900 3 15.900 4 15.800 5 15.657 6 15.540 To complete this technology assignment, you should already have created a scatter plot for your data on your calculator and/or in Excel. You could do this with any two columns of data, but for demonstration

More information

Earned Value and Agile Reporting

Earned Value and Agile Reporting Earned Value and Agile Reporting Anthony Cabri, Mike Griffiths Quadrus Development Inc. Abstract This paper reviews the concepts of Earned Value Management established in traditional project management,

More information

Using Earned Value, Part 2: Tracking Software Projects. Using Earned Value Part 2: Tracking Software Projects

Using Earned Value, Part 2: Tracking Software Projects. Using Earned Value Part 2: Tracking Software Projects Using Earned Value Part 2: Tracking Software Projects Abstract We ve all experienced it too often. The first 90% of the project takes 90% of the time, and the last 10% of the project takes 90% of the time

More information

A PARENT S GUIDE TO CPS and the COURTS. How it works and how you can put things back on track

A PARENT S GUIDE TO CPS and the COURTS. How it works and how you can put things back on track A PARENT S GUIDE TO CPS and the COURTS How it works and how you can put things back on track HOW YOU CAN USE THIS HANDBOOK We hope that this handbook will be easy for you to use. You can either read through

More information

Predicting progress on your project

Predicting progress on your project www.nonsuch.co info@nonsuch.co Predicting progress on your project - using Lego bricks to understand Earned Value September 4 PM Conference 2015 Presented by Youssef Mourra Director, Principal Consultant

More information

CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012

CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 King Saud University College of Computer & Information Sciences Department of Computer Science CSC 443: IT Project Management Midterm 1 exam - Spring semester 2011-2012 March 21 st, 2012 1- Decomposing

More information

performance management system that is based on Earned Schedule Management.

performance management system that is based on Earned Schedule Management. The aim of this presentation is to share lessons learned from using a project performance management system that is based on Earned Schedule Management. Earned Schedule Management is a new method created

More information

pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS

pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS pm4dev, 2008 management for development series Project Budget Management PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS PROJECT MANAGEMENT FOR DEVELOPMENT ORGANIZATIONS A methodology to manage development

More information

Forming a Limited Company and becoming a Director

Forming a Limited Company and becoming a Director Forming a Limited Company and becoming a Director Forming a Limited Company Regardless of whether this is your first business or you ve been doing it for years, one of the choices you are likely to face

More information

INTEGRATION SOFTWARE: BUILD OR BUY?

INTEGRATION SOFTWARE: BUILD OR BUY? INTEGRATION SOFTWARE: BUILD OR BUY? DAVID CHAPPELL MARCH 2010 SPONSORED BY MICROSOFT CORPORATION No modern organization uses only one application. A single software solution just isn t enough to address

More information

This document contains Chapter 2: Statistics, Data Analysis, and Probability strand from the 2008 California High School Exit Examination (CAHSEE):

This document contains Chapter 2: Statistics, Data Analysis, and Probability strand from the 2008 California High School Exit Examination (CAHSEE): This document contains Chapter 2:, Data Analysis, and strand from the 28 California High School Exit Examination (CAHSEE): Mathematics Study Guide published by the California Department of Education. The

More information

How to Make Sure Your Talk Doesn t Suck. David Tong

How to Make Sure Your Talk Doesn t Suck. David Tong How to Make Sure Your Talk Doesn t Suck David Tong This is an annotated version of a talk I gave at a summer school for first year graduate students. Anything sitting in a box, like this, summarizes what

More information

Project Management Glossary

Project Management Glossary Project Management Glossary THE VOCABULARY OF ACHIEVEMENT RON BLACK THE MENTOR GROUP WWW.RONBLACK.COM 800-381-8686 This glossary is an excerpt from Ron Black s book, The Complete Idiot s Guide to Project

More information

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition.

Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Earned Value Management Changes to the Glossary and Chapter 7 of the PMBOK Guide Third Edition. Errata for Chapter 7 (Replacement pages provided) Deleted up to a given point in time from the description

More information

Some Special Relativity Formulas

Some Special Relativity Formulas Some Special Relativity Formulas 1 Introduction The purpose of this handout is simple: to give you power in using special relativity! Even though you may not, at this stage, understand exactly where all

More information

Using Logistics to Grow Your Business

Using Logistics to Grow Your Business Using Logistics to Grow Your Business USING LOGISTICS TO GROW YOUR BUSINESS Y ou want your business to grow and logistics can help you achieve your objective. I ve put together this short guide for you

More information

EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS

EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS 14 EARNED VALUE MANAGEMENT SYSTEM AS A PROJECT MANAGEMENT TOOL FOR MAJOR MULTI-DISCIPLINARY PROJECTS Dr. P.B.G. Dissanayake 1 1 Department of Civil Engineering, Faculty of Engineering, University of Peradeniya

More information

Selected Homework Answers from Chapter 3

Selected Homework Answers from Chapter 3 elected Homework Answers from Chapter 3 NOTE: To save on space, I have not given specific labels to my axis, but rather stuck with just and. Ideally, you should put specific labels. For example, the vertical

More information

Could a Managed Services Agreement Save Your Company Tens of Thousands of Dollars Each Year?

Could a Managed Services Agreement Save Your Company Tens of Thousands of Dollars Each Year? MANAGED IT SERVICES Could a Managed Services Agreement Save Your Company Tens of Thousands of Dollars Each Year? A lot of business owners, executives, and managers have a love-hate relationship with managed

More information

Chapter 7: Project Cost Management. Information Technology Project Management, Fourth Edition

Chapter 7: Project Cost Management. Information Technology Project Management, Fourth Edition Chapter 7: Project Cost Management Information Technology Project Management, Fourth Edition Learning Objectives Understand the importance of project cost management. Explain basic project cost management

More information

SIMPLE FINANCIAL ANALYSIS FOR A SMALL FISH PROCESSING PLANT

SIMPLE FINANCIAL ANALYSIS FOR A SMALL FISH PROCESSING PLANT SIMPLE FINANCIAL ANALYSIS FOR A SMALL FISH PROCESSING PLANT by Gunnar Knapp Professor of Economics Institute of Social and Economic Research University of Alaska Anchorage 3211 Providence Drive Anchorage,

More information

Club Accounts. 2011 Question 6.

Club Accounts. 2011 Question 6. Club Accounts. 2011 Question 6. Anyone familiar with Farm Accounts or Service Firms (notes for both topics are back on the webpage you found this on), will have no trouble with Club Accounts. Essentially

More information

Chapter 2. My Early Days Trading Forex

Chapter 2. My Early Days Trading Forex Chapter 2 My Early Days Trading Forex I want to talk about my early days as a Forex trader because I m hoping that my story will be something you can relate to. So it doesn t really matter if you are brand

More information

Research question: How does the velocity of the balloon depend on how much air is pumped into the balloon?

Research question: How does the velocity of the balloon depend on how much air is pumped into the balloon? Katie Chang 3A For this balloon rocket experiment, we learned how to plan a controlled experiment that also deepened our understanding of the concepts of acceleration and force on an object. My partner

More information

Project Control with ProTrack

Project Control with ProTrack Project Control with ProTrack 1.0 (last update: 11/11/08) 1 Project Control with ProTrack by Mario Vanhoucke Professor at Ghent University and Vlerick Leuven Gent Management School (Belgium) Partner OR-AS

More information

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques

IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques IQPC IT Project Management Conference Sydney Recent Advances in Project Prediction Techniques Kym Henderson Former Education Director, PMI Sydney Chapter March 2003 to March 2007 Kym.Henderson@froggy.com.au

More information

L10: Budgeting and Cost Control. Olivier de Weck

L10: Budgeting and Cost Control. Olivier de Weck ESD.36 System Project Management + L10: Budgeting and Cost Control Instructor(s) Olivier de Weck Lecture 10 Oct. 11, 2012 System Project Management ESD.36 Framework Project Preparation Enterprise has chosen

More information

Scheduling is a DRAG

Scheduling is a DRAG Scheduling is a DRAG Better project management does not mean making schedules longer but rather making projects shorter. By William R. Duncan and Stephen A. Devaux Most organizations have realized that

More information

A Guide to Using Excel in Physics Lab

A Guide to Using Excel in Physics Lab A Guide to Using Excel in Physics Lab Excel has the potential to be a very useful program that will save you lots of time. Excel is especially useful for making repetitious calculations on large data sets.

More information

How to Make the Most of Excel Spreadsheets

How to Make the Most of Excel Spreadsheets How to Make the Most of Excel Spreadsheets Analyzing data is often easier when it s in an Excel spreadsheet rather than a PDF for example, you can filter to view just a particular grade, sort to view which

More information

A Gentle Introduction to Earned Value Management Systems

A Gentle Introduction to Earned Value Management Systems A Gentle Introduction to Earned Value Management Systems Good metrics let us see if we are doing the right things and doing them well." Niwot Ridge Consulting 4347 Pebble Beach Niwot, Colorao www.niwotridge.com

More information

FRAMEWORK. 7 Building Blocks to Success

FRAMEWORK. 7 Building Blocks to Success The CMI Content MarketING FRAMEWORK 7 Building Blocks to Success Your company is probably already exploring the role that compelling content can play in your own marketing programs just as many other companies

More information

Chapter 5: Project Cost Management

Chapter 5: Project Cost Management Chapter 5: Project Cost Management 1 Learning Objectives Understand the importance of good project cost management Explain basic project cost management principles, concepts, and terms Describe how resource

More information

Simple Earned Value (Using MS Project 2010)

Simple Earned Value (Using MS Project 2010) Simple Earned Value (Using MS Project 2010) This document outlines a Simple Earned Value technique, a technique which sticks to a simple 0/100% Milestone approach with some Level of effort tasks maintained

More information

1.7 Graphs of Functions

1.7 Graphs of Functions 64 Relations and Functions 1.7 Graphs of Functions In Section 1.4 we defined a function as a special type of relation; one in which each x-coordinate was matched with only one y-coordinate. We spent most

More information

Graphing Parabolas With Microsoft Excel

Graphing Parabolas With Microsoft Excel Graphing Parabolas With Microsoft Excel Mr. Clausen Algebra 2 California State Standard for Algebra 2 #10.0: Students graph quadratic functions and determine the maxima, minima, and zeros of the function.

More information

T he complete guide to SaaS metrics

T he complete guide to SaaS metrics T he complete guide to SaaS metrics What are the must have metrics each SaaS company should measure? And how to calculate them? World s Simplest Analytics Tool INDEX Introduction 4-5 Acquisition Dashboard

More information

THE CMI CONTENT MARKETING FRAMEWORK. 7 Building Blocks to Success

THE CMI CONTENT MARKETING FRAMEWORK. 7 Building Blocks to Success THE CMI CONTENT MARKETING FRAMEWORK 7 Building Blocks to Success Your company is probably already exploring the role that compelling content can play in your own marketing programs just as many other companies

More information

Q: What types of businesses/industries can benefit from the SBA loan programs? A: Most small owner-operated business can benefit from SBA loans

Q: What types of businesses/industries can benefit from the SBA loan programs? A: Most small owner-operated business can benefit from SBA loans Interview with Alan Thomes, President, SBA Loan Division State Bank and Trust Company For many new start-ups and small businesses, an SBA loan may be an appropriate form of financing. In this interview

More information

T O P I C 1 2 Techniques and tools for data analysis Preview Introduction In chapter 3 of Statistics In A Day different combinations of numbers and types of variables are presented. We go through these

More information

Schedule Compression

Schedule Compression Schedule Compression The need to reduce the time allowed for a schedule, or a part of a schedule is routine, some of the times the need arises include: When the initial schedule is too long to meet contractual

More information

When the cloud won t save you money (and why that s OK)

When the cloud won t save you money (and why that s OK) When the cloud won t save you money (and why that s OK) When the cloud won t save you money (and why that s OK) Somewhere along the line, cost savings became synonymous with cloud computing. It s true

More information

// Taming an Unruly Schedule Using the 14-Point Schedule Assessment

// Taming an Unruly Schedule Using the 14-Point Schedule Assessment // Taming an Unruly Schedule Using the 14-Point Schedule Assessment Dr. Dan Patterson, PMP CEO & President, Acumen February 2010 www.projectacumen.com Table of Contents Introduction... 3 The 14-Point Assessment...

More information

Decision Making under Uncertainty

Decision Making under Uncertainty 6.825 Techniques in Artificial Intelligence Decision Making under Uncertainty How to make one decision in the face of uncertainty Lecture 19 1 In the next two lectures, we ll look at the question of how

More information

[ INTRODUCTION ] A lot has changed since 1992, except for everything that hasn t. We come from a place you ve probably never heard of.

[ INTRODUCTION ] A lot has changed since 1992, except for everything that hasn t. We come from a place you ve probably never heard of. [ INTRODUCTION ] A businessman goes to see about a girl. They fall in love. They get married. The girl doesn t want to leave her family. He plants his roots and starts a business. Together they raise three

More information

// Benchmarking Project Schedules

// Benchmarking Project Schedules // Benchmarking Project Schedules Dr. Dan Patterson, PMP CEO & President, Acumen March 2011 www.projectacumen.com Table of Contents Introduction... 4 Benchmarking Overview... 4 Uses of Schedule Benchmarking...

More information

7 AGGREGATE SUPPLY AND AGGREGATE DEMAND* Chapter. Key Concepts

7 AGGREGATE SUPPLY AND AGGREGATE DEMAND* Chapter. Key Concepts Chapter 7 AGGREGATE SUPPLY AND AGGREGATE DEMAND* Key Concepts Aggregate Supply The aggregate production function shows that the quantity of real GDP (Y ) supplied depends on the quantity of labor (L ),

More information

The GED math test gives you a page of math formulas that

The GED math test gives you a page of math formulas that Math Smart 643 The GED Math Formulas The GED math test gives you a page of math formulas that you can use on the test, but just seeing the formulas doesn t do you any good. The important thing is understanding

More information

Wing Loading and its Effects

Wing Loading and its Effects www.performancedesigns.com I. Wing Loading Defined Wing Loading and its Effects A seminar by Performance Designs, Inc. Speaker: John LeBlanc Wing loading is a measurement of how much total weight is supported

More information

What Is Pay Per Click Advertising?

What Is Pay Per Click Advertising? PPC Management can be very confusing and daunting for newcomers to the field. Money is on the line and it s a very competitive arena where lots of people are trying to capitalize on the same keywords for

More information

Reading and Taking Notes on Scholarly Journal Articles

Reading and Taking Notes on Scholarly Journal Articles Reading and Taking Notes on Scholarly Journal Articles Set aside enough time in your schedule to read material thoroughly and repeatedly, until you understand what the author is studying, arguing, or discussing.

More information

ASVAB Study Guide. Peter Shawn White

ASVAB Study Guide. Peter Shawn White ASVAB Study Guide By Peter Shawn White Table of Contents Introduction Page 3 What Is The ASVAB? Page 4 Preparing For The ASVAB Page 5 Study Tips Page 7 Some Final Words Page 9 Introduction I m going to

More information

Use it or Lose it: Microsoft Windows Backup By Tom Dell, ntb group partner

Use it or Lose it: Microsoft Windows Backup By Tom Dell, ntb group partner Use it or Lose it: Microsoft Windows Backup By Tom Dell, ntb group partner Learning to use a backup application is one of the most important things a user of a Windows computer can do. It is so important,

More information

A lot has changed since 1992, except for everything that hasn t. We come from a place you ve probably never heard of.

A lot has changed since 1992, except for everything that hasn t. We come from a place you ve probably never heard of. THE MANIFESTO [ INTRODUCTION ] A businessman goes to see about a girl. They fall in love. They get married. The girl doesn t want to leave her family. He plants his roots and starts a business. Together

More information

Basic ESXi Networking

Basic ESXi Networking Basic ESXi Networking About vmnics, vswitches, management and virtual machine networks In the vsphere client you can see the network diagram for your ESXi host by clicking Networking on the Configuration

More information

The Mortgage Guide. Helping you find the right mortgage for you. Brought to you by. V0050713a

The Mortgage Guide. Helping you find the right mortgage for you. Brought to you by. V0050713a The Mortgage Guide Helping you find the right mortgage for you Brought to you by Hello. Contents We re the Which? Mortgage Advisers team. Buying a house is the biggest financial commitment most of us ever

More information